DRAFT FOR PUBLIC REVIEW

Size: px
Start display at page:

Download "DRAFT FOR PUBLIC REVIEW"

Transcription

1 ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED COMBINED CYCLE GAS TURBINE (CCGT) POWER PLANT IN THE AMERSFOORT AREA, MPUMALANGA PROVINCE (DEAT REF 12/12/20/1074) DRAFT FOR PUBLIC REVIEW PROJECT OF ESKOM HOLDINGS LIMITED 28 FEBRUARY 2008

2 Amersfoort area, Mpumalanga Province DOCUMENT DESCRIPTION Client: Report name: Report type: Bohlweki Project number: Eskom Holdings Limited Environmental Scoping Report for the proposed Combined Cycle Gas Turbine (CCGT) power plant in the Amersfoort area, Mpumalanga Province Draft E02.JNB Compiled by: Author (s) Date / location Signature Prashika Reddy Reviewer Malcolm Roods Approval Document Control Sheet

3 EXECUTIVE SUMMARY 1. INTRODUCTION Eskom Holdings Limited (Eskom) has appointed Bohlweki Environmental (Pty) Ltd as independent environmental consultants to conduct the Environmental Impact Assessment (EIA) process for the proposed Combined Cycle Gas Turbine (CCGT) power plant in the Amersfoort area, in terms of the EIA regulations published in Government Notice R385 to R387 of 21 April read with Section 24(5) and Section 44,of the National Environmental Management Act, 1998 (Act No 107 of 1998, NEMA )(as amended). Need and Justification of the Project Eskom has a mandate to satisfy potential customer and economic needs, which implies certain responsibilities. One of the most significant responsibilities is to find and maintain the balance between satisfying the needs of society and remaining within the capabilities of the environment. In order to achieve this, Eskom must continually re-assess its present infrastructure and take into account new developments to ensure that there is a continued supply of electricity, without significantly impacting on the environment. Eskom is the primary supplier of electricity in South Africa, providing approximately 95% of the electricity consumed. The decision to expand Eskom s electricity generation capacity was based on national policy and informed by on-going strategic planning undertaken by the national Department of Minerals and Energy (DME), the National Energy Regulator of South Africa (NERSA) and Eskom. Eskom applies an Integrated Strategic Electricity Planning (ISEP) process to identify long-term options regarding both the supply and demand sides of electricity provision in South Africa. The most recently approved ISEP (October 2005) identifies the need for increased peaking supply by about 2006/7 and base load by about Based on the above planning processes, and in order to meet the projected increase in the demand for electricity, various projects are underway and are at various stages of implementation. These include base load technologies such as coal fired plants, combined cycle gas turbines and conventional nuclear as well as peaking technologies such as pumped storage schemes and open cycle gas turbines. Eskom is committed to investigating and evaluating various options for the diversification of the energy mix over time (including renewable resources) and as part of an ongoing effort to assess the viability/feasibility of all supply-side options, a number of power generation technologies, not yet implemented in South Africa on a commercial basis, are being evaluated in terms of technical, socio-economic and environmental aspects. One such type of technology is Underground Coal Gasification (UCG), which has been successfully proven to be commercially viable, and Eskom plans to implement it as a fully commercially operating operation. In this current project, it is proposed that an Underground Coal Gasification- Combined Cycle Gas Turbine (UCG-CCGT) complex is constructed and operated. The current study only focused on the CCGT plant component of the complex. Executive Summary i 29/02/2007

4 1.2. Overview of the Proposed Project It is anticipated that the CCGT power plant will have approximately 2100 MW of installed capacity. The proposed project will consist of the following components: the CCGT power plant (comprising up to 6 units of approximately 350 MW each); a compressor plant; ignition gas plant, for unit start-up (using commercial propane); weather and communication mast of up to 60 meters in height and air quality monitoring station; high voltage yard; a gas pipeline from the adjacent gas cleaning plant to the CCGT; a water supply pipeline from the Rietpoort Balancing Dam (for construction and operational water supply); electricity supply for construction; a water treatment plant as well as ancillary works such as other associated infrastructure; access roads; sewage treatment plant; storage facility for hazardous materials; storage facility for waste; and borrow pits. The CCGT plant and associated infrastructure are required to be constructed on a site that is environmentally, economically and technical feasible. A Screening Study (Site selection) encompassing a sensitivity mapping exercise was undertaken by independent consultants in order to establish the best possible sites to evaluate during the Scoping Phase of the project. The purpose of such an exercise was to identify suitable areas within the wider study area that could accommodate the CCGT plant and to pro-actively identify sensitive areas that should ideally be avoided (see Chapter 5 Site Selection Summary). 2. DESCRIPTION OF ALTERNATIVES In terms of the Environmental Impact Assessment (EIA) Regulations, feasible alternatives must be considered within the Environmental Scoping Study. All identified, feasible alternatives should be evaluated in terms of social, biophysical, economic and technical factors. Site alternatives Based upon the Screening/Site selection study, a total of ten candidate sites were identified for the possible location of the CCGT power plant and associated infrastructure. Executive Summary ii 29/02/2007

5 These farms included: Site 1 (Portions 3 and 4 of the farm Roodekopjes 67 HS) Site 2 Site 2a (Portion 7 of the farm Bergvliet 65 HS; Portion 4 of the farm Rietpoort 83 HS; Werda 116 HS) Site 2b (Portions 3 and 4 of the farm Rietpoort 83 HS and Werda 116 HS) Site 3 (Portions 3 and 4 of the farm Rietpoort 83 HS) Site 4 (Portion 1 of the farm Rietpoort 83 HS and Portions 2, 6 and 7 of the farm Welgedacht 82 HS) Site 5 (Portions 4, 5 and 8 of the farm Welgedacht 82 HS) Site 6 (Portions 1, 3 and 7 of the farm Palmietspruit 68 HS; Portion 6 of the farm Strydkraal 53 HS; Portion 1 of the farm Roodekopjes 67 HS ) Site 7 Site 7a (Portions 1, 2, 6, 10 and 11 of the farm Witkoppies 81 HS) Site 7b (Portions 1, 5 and 6 of the farm Witkoppies 81 HS) Site 7c (Portions 4, 5, 8, 9, 12, 13 and 14 of the farm Witkoppies 81 HS) With further input from the technical team, four sites were eliminated as they were located in the area earmarked for future UCG operations/expansion. Six alternative sites were then selected as being potentially the most viable of all the candidate sites investigated. The following six (6) sites will, therefore, be assessed during this Scoping Study: Site 1 (Portions 1, 3 and 7 of the farm Palmietspruit 68 HS; Portion 6 of the farm Strydkraal 53 HS; Portion 1 of the farm Roodekopjes 67 HS ) Site 2 Site 2a (Portion 7 of the farm Bergvliet 65 HS; Portion 4 of the farm Rietpoort 83 HS; Werda 116 HS) Site 2b (Portions 3 and 4 of the farm Rietpoort 83 HS and Werda 116 HS) Site 3 Site 3a (Portions 1, 2, 6, 10 and 11 of the farm Witkoppies 81 HS) Site 3b (Portions 1, 5 and 6 of the farm Witkoppies 81 HS) Site 3c (Portions 4, 5, 8, 9, 12, 13 and 14 of the farm Witkoppies HS) Other alternatives Alternatives relating to the CCGT power plant layout, technology selection, pipeline corridors as well as access roads and construction village positioning will be further assessed during the EIA phase. Executive Summary iii 29/02/2007

6 3. APPROACH TO THE ENVIRONMENTAL SCOPING STUDY (ESS) AND PUBLIC PARTICIPATION PROCESS Environmental Scoping Study The ESS aims to provide a description of how the environment may be affected by the development of the proposed project. Desktop studies making use of existing information, and ground-truthing during site visits, were used to highlight and assist in the identification of potential impacts (biophysical, social and economic) associated with the proposed project. Additional issues for consideration have been extracted from feedback obtained from the public participation process, which commenced at the beginning of the Scoping phase, and will continue throughout the duration of the project. All issues identified during this phase of the study have been documented within this issues-based Environmental Scoping Report. Thus, this Environmental Scoping Report provides a record of all issues identified, and a preliminary evaluation of the significance of the issues in order to make recommendations regarding the project and further studies required to be undertaken within the EIA phase of the proposed project. The Scoping Study aims to address the following: description of the sites selected for the proposed CCGT power plant and associated infrastructure; identification of potential positive and negative environmental (biophysical and social) impacts, and an evaluation of their significance in terms of the project; optimisation of positive impacts to the benefit of the local environment and community; and undertaking of a fully inclusive public participation process to ensure that Interested and Affected Party (I&AP) issues and concerns are recorded and form part of the scoping process. As the proposed project includes a number of listed activities from Government Notices R386 and R387 of April 2006, a full Environmental Impact Assessment process is being undertaken in a two-phased approach: Phase 1: Environmental Scoping Study (ESS) Phase 2: Environmental Impact Assessment and Environmental Management Plan (EMP) A number of specialist studies were conducted in order to comprehensively identify both potential positive and negative environmental impacts (biophysical, social and economic) associated with the project. These studies are presented in Table 1 below. Executive Summary iv 29/02/2007

7 Table 1 Specialist studies conducted in the Environmental Scoping Study Specialist Study Organisation Hydrogeology and Hydrology SRK Consulting Fauna and Flora Bathusi Environmental Consulting Air Quality Bohlweki Environmental Noise Jongens Keet Associates Social Environment MasterQ Research Heritage National Cultural History Museum Visual aspects and aesthetics MetroGIS Risk Riscom Traffic SSI Engineers and Environmental Consultants Approach to Scoping Study in terms of Site Preference The evaluation and nomination of a potential site for the CCGT power plant involves an interdisciplinary approach. The approach undertaken has involved a wide range of specialist studies (hydrogeology, hydrology, biodiversity; air quality; noise; social; visual; heritage; risk and traffic) which examined a number of different issues. In order to evaluate sites and determine a preferred site/s, the studies need to be comparative and therefore a site rating matrix was developed. The site preference rating system is applied to each discipline, and the rating of each site was conducted according to the following system: 1 = not suitable for development (impact of very high significance - negative) 2 = not preferred (impact of high significance - negative) 3 = acceptable (impact of moderate significance - negative) 4 = preferred (impact of low or negligible significance - negative) 5 = ideal site for development, or positive impact One of the outcomes of each specialist study was to have a Site Preference Rating, how they evaluated each site varied from discipline to discipline and the description of their specific approaches are outlined in each specialist report (refer Chapters 8 and 9). The site preference results for each site from each specialist study were entered into a matrix and added together. The site with the highest value is then considered the most preferable. The standard matrix as described above, gives equal importance to each variable. Therefore, a weighted matrix was also used. In a weighted matrix each variable is given a different importance weighting. Input from the project team and all specialists was utilised for the allocation of weightings to the different variables. Each member of the The project team was asked to rank each variable according to their significance: 1 low significance 2 medium significance 3 high significance Executive Summary v 29/02/2007

8 Once the average weighting for each variable was obtained, it was multiplied by the Site Preference Rating (SPR) to give a weighted SPR for each variable. Table 2 (overleaf) was obtained after the above process was completed. Executive Summary vi 29/02/2007

9 Table 2 Environmental and social criteria matrix Unweighted Weighted Weighting Site 1 Site 2a Site 2b Site 3a Site 3b Site 3c Site 1 Site 2a Site 2b Site 3a Site 3b Site 3c Biophysical Criteria Hydrogeology Hydrology Flora Fauna Social Criteria Noise Social Visual Heritage Risk Traffic Total Score Executive Summary vii 29/02/2007

10 Public Participation Process A public participation process has been undertaken as part of the Scoping process, and involved the consultation of individuals throughout the broader study area representing a range of sectors of society. To date, this consultation has included telephonic consultations, a Focus Group Meeting and documentation distributed via mail, background information documents and via the printed media. Issues and concerns raised during the Scoping process thus far have been recorded and captured within an Issues Trail (Appendix D). 4. CONCLUSIONS AND RECOMMENDATIONS Based on the specialist studies, no environmental fatal flaws have been identified as a result of the proposed project on any of the sites evaluated. However, a number of potentially significant environmental impacts have been identified that requires further in-depth study. Therefore, an EIA is to be undertaken in order to provide an assessment of these potential impacts and recommend appropriate mitigation measures, where required. In the consideration of the environmental, social and economic criteria along with the technical criteria, the nominated sites for further study within an environmental impact assessment would be: Sites 1 (Portions 1, 3 and 7 of the farm Palmietspruit 68 HS; Portion 6 of the farm Strydkraal 53 HS; Portion 1 of the farm Roodekopjes 67 HS); Site 3a (Portions 1, 2, 6, 10 and 11 of the farm Witkoppies 81 HS); and Site 3b (Portions 1, 5 and 6 of the farm Witkoppies 81 HS). Executive Summary viii

11 EXECUTIVE SUMMARY i 1. INTRODUCTION Energy Policy Framework White Paper on the Energy Policy of the Republic of South Africa Integrated Energy Plan (IEP) National Integrated Resource Plan (NIRP) 2003/ Eskom Integrated Strategic Electricity Planning (ISEP) Overview of the Proposed Project Environmental Legal Requirements The National Environmental Management Act...6 The Constitution of South Africa Legal requirements in terms of other Acts Environmental Study Requirements TECHNICAL DESCRIPTION OF THE PROJECT What is a Combined Cycle Gas Turbine (CCGT) Plant? How does a Combined Cycle Gas Turbine (CCGT) work? Water and Cooling...17 Storage Tanks Other Infrastructure Access Roads Construction Village SCOPE OF ENVIRONMENTAL INVESTIGATIONS Approach to Undertaking the Scoping Study Authority Consultation Consultation with Decision-making Authorities Consultation with other Relevant Authorities Application for Authorisation Environmental Scoping Study Specialist Studies Overview of the Public Participation Process Advertising Identification of Key Stakeholders and Interested and Affected...24 Briefing Paper Consultation and Public Involvement...25 Social Issues Trail Review of the Draft Environmental Scoping Report and Plan of Study for EIA Public Review of Draft Scoping Report and Plan of Study for EIA...27 Authority Review of Draft Environmental Scoping Report Final Environmental Scoping Report GENERAL DESCRIPTION OF THE STUDY AREA ENVIRONMENT The Biophysical Environment Locality Climate and Rainfall Topography and Landscape...30 Geology Hydrogeology...31 Hydrology Biodiversity The Social Environment Air Quality Noise Social...35 Table of Contents ix

12 Visual Heritage Risk Traffic SITE SELECTION SUMMARY Sensitivity Mapping and Selection of Sites...39 Sensitivity Indexes Sensitivity Zoning ALTERNATIVES Strategic Alternatives...51 The 'Do Nothing' Alternative Site Alternatives Layout Alternatives...52 Technologies Alternatives Cooling Technologies Air Quality Abatement Technologies Pipeline Alternatives Fuel Supply Pipeline...54 Water Supply Pipeline Alignment of Access Roads Construction Village APPROACH TO SCOPING STUDY Site Evaluation Field Studies Specialist Studies Rating Criteria Assumptions and Limitations ASSESSMENT OF THE BIOPHYSICAL ENVIRONMENT Hydrogeology Introduction Methodology Potential Impacts on Hydrology Site Preference Rating (SPR)...64 Conclusions Recommendations Hydrology Introduction Methodology...66 Potential Impacts on Hydrology Site Preference Rating (SPR) Conclusions...68 Recommendations Flora Introduction Methodology Potential Impacts on Flora...71 Site Preference Rating Conclusions and Recommendations Fauna Introduction Methodology...74 Potential Impacts on Fauna Site Preference Rating Conclusions and Recommendations...77 Table of Contents x

13 9. ASSESSMENT OF THE SOCIAL ENVIRONMENT Air Quality Introduction Methodology...78 Baseline Assessment Potential Impacts on Air Quality Conclusions and Recommendations Noise Introduction Methodology Potential Noise Impacts Site Preference Ranking...90 Conclusions Recommendations Social Impact Assessment Introduction Methodology Potential Impacts on the Social Environment Site Preference Rating Conclusions Recommendations Visual Introduction Methodology Potential Visual Impacts Site Preference Ranking Conclusions Recommendations Heritage Introduction Methodology Potential Impacts on Heritage Site Preference Rating Conclusions and Recommendations Risk Site Preference Rating Recommendations Traffic Site Preference Rating Conclusions and Recommendations CONCLUSIONS AND RECOMMENDATIONS Potential Environmental Impacts Rating Matrix Recommendations PLAN OF STUDY FOR ENVIRONMENTAL IMPACT ASSESSMENT Approach to Undertaking the Environmental Impact Assessment Phase of the Project Authority Consultation Application for Authorisation The Environmental Impact Assessment Process Aims of the Environmental Impact Assessment Phase Detailed Specialist Studies to be undertaken as part of the EIA Public Participation Process Advertising Identification of and Consultation with I&APs and Key Stakeholders Table of Contents xi

14 I&AP Database Consultation and Public Involvement Social Issues Trail Compilation of the Environmental Impact Assessment Report Review of the Environmental Impact Assessment Report Public Review of the draft Environmental Impact Assessment Report Authority Review of the Environmental Impact Assessment Report Environmental Authorisation Environmental Management Plan Environmental Study Team REFERENCES Table of Contents xii

15 LIST OF FIGURES Figure 1.1 Figure 1.2 Hierarchy of policy and planning documents...1 Project funnel...4 Figure 1.3 Locality map...12 Figure 2.1 A typical 3-in-1 CCGT power plant configuration, in model form...13 Figure 2.2 Schematic of a process of that a gas turbine undergoes in order to produce electricity Figure 2.3 Figure 2.4 Layout of UCG-CCGT plant...16 Showing a direct dry cooling system...18 Figure 2.5 Showing an indirect dry cooling system...19 Figure 4.1 Map indicating the Pixley ka Seme Local Municipality and surrounding municipalities...28 Figure 4.2 Average monthly maximum and minimum temperatures recorded in the Majuba area (Weather Services Station, 2007)...29 Figure 4.3 Monthly rainfall figures for Majuba area (Weather Services Station, 2007).29 Figure 4.4 The period wind rose and wind frequency distribution for data taken at the UCG Pilot Plant and for modelled data received from the South African Weather Services respectively Figure 5.1 Environmental sensitivity index...43 Figure 5.2 Environmental Sensitivity Zones...45 Figure 5.3 Ideal/preferred areas for development...46 Figure 5.4 Alternative sites identified in the Screening Study for the proposed CCGT power plant...48 Figure 5.5 Alternative sites identified for assessment in the Scoping Study for the proposed CCGT power plant in the Amersfoort area...50 Figure 6.1 Figure 6.2 Showing a direct dry cooling system...53 Showing a typical indirect dry cooling system...54 Figure 9.1 Map indicating 4 main noise measurement sites...85 Figure 9.2 Social waypoints...96 Figure 9.3 Potential visibility of Site Figure 9.4 Figure 9.5 Potential visibility of Site 2A (left) and Site 2A (right) Potential visibility of Site 3A (left) and Site 3B (right) Figure 9.6 Potential visibility of Site 3C Figure 9.7 Figure 9.8 Location of Site 1 (north of Majuba Power Station) Location of Site 2a and 2b (east of Majuba Power Station) Figure 9.9 Location of Site 3a; 3b and 3c (south of Majuba Power Station) Figure 10.1 Showing the six (6) candidate sites evaluated in the Scoping Study Table of Contents xiii

16 LIST OF TABLES Table 4.1 Table 5.1 Specialist studies undertaken as part of the previous Scoping process...23 Lithostratigraphy of the study area...31 Table 6.1 Description of the various categories used in the sensitivity mapping...39 Table 8.1 Specialist studies and the components investigated during the Environmental Scoping Phase...57 Table 9.1 Hydrogeology percentage relating to site preference rating class...62 Table 9.2 Table 9.3 Potential nature of impacts on groundwater regime...63 Site selection comparison...64 Table 9.4 Table 9.5 Hydrology percentage relating to site preference rating class...66 Site selection comparison...67 Table 9.6 Floral score relating to site preference rating class...70 Table 9.7 Site preference ranking according to floristic sensitivity...72 Table 9.8 Faunal score relating to site preference rating class...75 Table 9.9 Site preference ranking according to faunal sensitivity...77 Table 10.1 Main locations for noise measurements...84 Table 10.2 Site Rating Comparison...92 Table 10.3 Potential Impacts on the Social Environment...98 Table 10.4 Site comparison Table 10.5 Terms of Reference for studies to be carried out in the EIA Phase Table 10.6 Comparative table of the proposed CCGT power plant alternatives Table 10.7 Potential impact on heritage during the construction and operation phase 122 Table 10.8 Site Comparison Table 10.9 Site Comparison Table Site Comparison Table 11.1 Potentially significant issues associated with the proposed CCGT power plant, identified within the Environmental Scoping Study. The area of potential impact and recommendations for investigations to be undertaken within the EIA phase are also specified Table 11.2 Environmental and social criteria matrix Table 11.3 Technical criteria Table 11.4 Environmental, social and technical criteria matrix Table 12.1 Criteria for the classification of environmental impacts Table 12.2 Key milestones of the programme for the EIA phase of the project Table 12.3 Proposed specialist team and their areas of expertise Table of Contents xiv

17 LIST OF APPENDICES APPENDIX A: APPENDIX B: APPENDIX C: APPENDIX D: APPENDIX E: APPENDIX F: APPENDIX G: APPENDIX H: APPENDIX I: APPENDIX J: APPENDIX K: Applicable Legislation Acceptance Letter - DEAT Advertisements and Proof of Placement of Site Notices Issues Trail and I&AP Database Background Information Document and Letters to I&APs Advertisements Availability of Draft Scoping Report and Letter to I&APS Minutes of Meeting Screening Report Individual Specialist Maps Screening Study Specialist Reports Biophysical Environment Specialist Reports Social Environment Table of Contents xv

18 GLOSSARY OF TERMS Alternatives: means different means of meeting the general purpose and requirements of the activity, which may include site or location alternatives; alternatives to the type of activity being undertaken; the design or layout of the activity; the technology to be used in the activity and the operational aspects of the activity. Ambient sound level or ambient noise: means the totally encompassing sound in a given situation at a given time, and usually composed of sound from many sources, both near and far. Note that ambient noise includes the noise from the noise source under investigation. The use of the word ambient should however always be clearly defined (compare with residual noise). Combined Cycle Gas Turbine (CCGT): In a combined cycle power plant or CCGT plant, a gas turbine generator generates electricity and the waste heat is used to make steam to generate additional electricity via a steam turbine; this last step enhances the efficiency of electricity generation. Cumulative impact: means the impact of an activity that in itself may not be significant but may become significant when added to the existing and potential impacts eventuating from similar or diverse activities or undertakings in the area. Direct dry cooling: In the direct system, steam from the last stage turbine blades is channelled directly into radiator-type heat exchangers adjacent to the turbine hall of the power station (there are no cooling towers.). The heat is conducted from the steam to the metal tubes of the exchanger. Air passing through the exchanger is supplied by a number of electrically driven fans. The air removes the heat, thus condensing the steam back into water which will be used once again to produce steam in the boiler. Do-nothing alternative: The do-nothing alternative is the option of not undertaking the proposed activity. Environmental impact assessment, in relation to an application to which scoping must be applied, means the process of collecting, organising, analysing, interpreting and communicating information that is relevant to the consideration of that application as defined in NEMA. Environmental Screening Study: An exercise to identify suitable areas within the study area that could accommodate the CCGT plant and to pro-actively identify sensitive areas that should ideally be avoided. Gas turbine: The gas turbine (also called a combustion turbine) is a rotary engine that extracts energy from a flow of combustion gas and is the first stage in the process of producing electricity through the CCGT plant. Glossary of Terms xvi

19 Indirect dry cooling: Indirect dry cooling systems have a condenser and turbine exhaust system as for wet systems, with the circulating water being passed through finned tubes in a natural draught cooling tower. Interested and affected party: any person, group of persons or organisation interested in or affected by an activity; and any organ of state that may have jurisdiction over any aspect of the activity. Outflow of labourers: Locals who secure employment with the contractors might also receive training, thereby enabling them to secure more permanent employment, which in turn might cause them to move out of the area and becoming part of the migrant labour force. Phase 1 Archaeological Survey: Walk through the entire footprint of the preferred site/s and document any/all heritage resources that exist on the site/s. Plan of study for environmental impact assessment: means a document which forms part of a scoping report and sets out how an environmental impact assessment must be conducted. Public participation process: means a process in which potential interested and affected parties are given an opportunity to comment on, or raise issues relevant to, specific matters. Red Data species: Species listed in terms of the International Union for Conservation of Nature and Natural Resources (IUCN) Red List of Threatened Species, and/or in terms of the South African Red Data List. In terms of the South African Red Data List, species are categorised as being extinct, endangered, vulnerable, rare, indeterminate, insufficiently known or not threatened. Site preference ranking: The approach involved a wide range of specialist studies examining a number of different issues. In order to evaluate sites and determine a preferred site/s, the studies needed to be comparative and therefore a site rating matrix was developed. The site preference rating system is applied to each discipline, and the rating of each site was conducted according to the following system: 1 = not suitable for development (impact of very high significance - negative); 2 = not preferred (impact of high significance - negative); 3 = acceptable (impact of moderate significance - negative); 4 = preferred (impact of low or negligible significance - negative) and 5 = ideal site for development, or positive impact. Underground coal gasification: UCG is a process carried out on unminable coal seams. These are coal seams that cannot be mined by using the conventional coal mining methods e.g. open cast or underground mining. UCG involves injecting steam and air (or oxygen) into a cavity created in an underground coal seam, to form a synthetic natural gas. Unweighted matrix: Each variable is given the same importance weighting. Vadose zone: The portion of Earth between the land surface and zone of saturation. It extends from the top of the ground surface to the water table. Glossary of Terms xvii

20 Vulnerable (vegetation): Vegetation types that have lost up to 20% of their original extent, which could result in some ecosystem function being altered. Weighted matrix: Each variable is given a different importance weighting. Glossary of Terms xviii

21 ABBREVIATIONS AND ACRONYMS CCGT Combined cycle gas turbine DEAT Department of Environmental Affairs and Tourism DME Department of Minerals and Energy DWAF Department of Water Affairs and Forestry EIA Environmental Impact Assessment EMP Environmental Management Plan ESS Environmental Scoping Study FGM Focus Group Meeting HRSG Heat recovery steam generator I&AP Interested and Affected Party IEP Integrated Energy Planning IEP Integrated Energy Planning ISEP Integrated Strategic Electricity Plan KSW Key Stakeholder Workshop MDALA Mpumalanga Department of Agriculture and Land Administration NEMA National Environmental Management Act (Act No 107 of 1998) NERSA National Energy Regulator of South Africa NGO Non-Governmental Organisation NHRA National Heritage Resources Act (Act No 25 of 1999) SAHRA South African Heritage Resources Agency SANRAL South African National Roads Agency Limited UCG Underground coal gasification Glossary of Terms xix

2. TECHNICAL DESCRIPTION OF THE PROJECT

2. TECHNICAL DESCRIPTION OF THE PROJECT 2. TECHNICAL DESCRIPTION OF THE PROJECT 2.1. What is a Combined Cycle Gas Turbine (CCGT) Plant? A CCGT power plant uses a cycle configuration of gas turbines, heat recovery steam generators (HRSGs) and

More information

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA DEA Reference Number: 12/12/20/2175 BACKGROUND INFORMATION

More information

8. ASSESSMENT OF THE BIOPHYSICAL ENVIRONMENT

8. ASSESSMENT OF THE BIOPHYSICAL ENVIRONMENT 8. ASSESSMENT OF THE BIOPHYSICAL ENVIRONMENT 8.1. Hydrogeology 8.1.1. Introduction Bohlweki Environmental appointed SRK Consulting to undertake the necessary hydrogeological studies for the proposed CCGT

More information

Environmental Impact Report for the proposed establishment of a New Coal-Fired Power Station in the Lephalale Area, Limpopo Province

Environmental Impact Report for the proposed establishment of a New Coal-Fired Power Station in the Lephalale Area, Limpopo Province 3. SCOPE OF ENVIRONMENTAL INVESTIGATIONS 3.1. Approach to Undertaking the Study An Environmental Scoping Study for the proposed establishment of a new coalfired Power Station, in Lephalale, was undertaken

More information

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED CONCENTRATING SOLAR POWER (CSP) PLANT AND ASSOCIATED INFRASTRUCTURE IN THE NORTHERN CAPE AREA

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED CONCENTRATING SOLAR POWER (CSP) PLANT AND ASSOCIATED INFRASTRUCTURE IN THE NORTHERN CAPE AREA ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED CONCENTRATING SOLAR POWER (CSP) PLANT AND ASSOCIATED INFRASTRUCTURE IN THE NORTHERN CAPE AREA BRIEFING PAPER March 2006 WHAT DOES THIS DOCUMENT TELL YOU?

More information

DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3

DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3 DESCRIPTION OF THE GOURIKWA POWER STATION & TRANSMISSION INTEGRATION PROJECT CHAPTER 3 This chapter provides details regarding the scope of the proposed Gourikwa Power Station and Transmission Integration

More information

STRATEGIC CONTEXT FOR ENERGY PLANNING CHAPTER 2

STRATEGIC CONTEXT FOR ENERGY PLANNING CHAPTER 2 STRATEGIC CONTEXT FOR ENERGY PLANNING CHAPTER 2 Eskom contributes to its vision of together building the powerbase for sustainable growth and development through its core business focus on electricity

More information

ENVIRONMENTAL IMPACT ASSESSMENT EIA PHASE

ENVIRONMENTAL IMPACT ASSESSMENT EIA PHASE ENVIRONMENTAL IMPACT ASSESSMENT EIA PHASE PROPOSED ESTABLISHMENT OF THE PUMPED STORAGE SCHEME AND ASSOCIATED INFRASTRUCTURE IN THE STEELPOORT AREA, LIMPOPO AND MPUMALANGA PROVINCES FINAL MINUTES OF THE

More information

APPENDIX 5 ENVIRONMENTAL IMPACT ASSESSMENT METHODOLOGY

APPENDIX 5 ENVIRONMENTAL IMPACT ASSESSMENT METHODOLOGY APPENDIX 5 ENVIRONMENTAL IMPACT ASSESSMENT METHODOLOGY ENVIRONMENTAL IMPACT ASSESSMENT METHODOLOGY In line with the Minerals and Petroleum Resource Development Act 20 of 2002 (MPRDA), an Impact Assessment

More information

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary

TABLE OF CONTENTS. Title page Table of contents List of tables List of figures Non- technical summary TABLE OF CONTENTS Title page Table of contents List of tables List of figures Non- technical summary Page i ii vii viii ix CHAPTER 1: INTRODUCTION 1 1.1 Project Background 1 1.2 Aims and Objectives 3 1.3

More information

A proposed new gas-fired power station on the Wilton International site

A proposed new gas-fired power station on the Wilton International site TEES CCPP PROJECT A proposed new gas-fired power station on the Wilton International site Welcome This event is intended to provide you with information about the proposed Tees Combined Cycle Power Plant

More information

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017

Annesley Andalusite Mine: Section 24G Rectification Process. Consultation with community members 15 June 2017 Annesley Andalusite Mine: Section 24G Rectification Process Consultation with community members 15 June 2017 AGENDA Welcome and introduction Meeting protocol Purpose of the meeting Project background Project

More information

Struma Lot 3.2 EIA Development, Working Document

Struma Lot 3.2 EIA Development, Working Document Struma Lot 3.2 EIA Development, Working Document Revision 1, 03 February 2016 1 Introduction 1.1 Background Struma Motorway is one of the most challenging road projects in Bulgaria. The motorway is about

More information

AMDAL Procedure. Flowchart of Indonesian Environmental Clearance 1

AMDAL Procedure. Flowchart of Indonesian Environmental Clearance 1 AMDAL Procedure (This is only indicative and for reference purposes. This is not exhaustive and therefore, the Consultants are requested to familiarize themselves with all the laws, rules, regulations,

More information

RE: STAKEHOLDER INFORMATION DOCUMENT 1: RIETKOL MINING OPERATIONS

RE: STAKEHOLDER INFORMATION DOCUMENT 1: RIETKOL MINING OPERATIONS 6 October 2016 Dear Stakeholder, RE: STAKEHOLDER INFORMATION DOCUMENT 1: RIETKOL MINING OPERATIONS As indicated in our previous notification dated 12 February 2016, Consol Glass (Pty) Limited ( Consol

More information

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives: ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP 1. Objectives The aim of the study is to achieve the following objectives: Review of existing EIA and RAP reports on sections of the line which are not

More information

Majuba Underground Coal Gasification

Majuba Underground Coal Gasification Majuba Underground Coal Gasification 17 September 2010 Presenter: MJ BEESLAAR Context Coal is the predominant natural energy resource in RSA. Eskom presently generates 88% of its electricity from coal.

More information

PROPOSED VOLSPRUIT MINE, MOKOPANE DISTRICT, LIMPOPO PROVINCE. Background Information Document (BID) ESCIENCE ASSOCIATES (PTY) LTD.

PROPOSED VOLSPRUIT MINE, MOKOPANE DISTRICT, LIMPOPO PROVINCE. Background Information Document (BID) ESCIENCE ASSOCIATES (PTY) LTD. ENVIRONMENTAL IMPACT ASSESSMENT (EIA), MINING RIGHT APPLICATION AND OTHER ANCILLARY LICENSING PROCESSES: PROPOSED PLATINUM GROUP METALS MINE & ASSOCIATED INFRASTRUCTURE PROPOSED VOLSPRUIT MINE, MOKOPANE

More information

Executive Summary 1. 1 Project Background 6

Executive Summary 1. 1 Project Background 6 Contents Executive Summary 1 1 Project Background 6 Page 1.1 Project Overview 6 1.2 Hotel Concept 6 1.3 Justification of the Project 8 1.3.1 Foreign Currency Earnings 8 1.3.2 Tourism Developments in Mauritius

More information

A Report for Solafrica. 14/12/16/3/3/3/203 Parabolic Trough

A Report for Solafrica. 14/12/16/3/3/3/203 Parabolic Trough Environmental Impact Assessment Study for the proposed Concentrated Solar Power Plant (Parabolic Trough) on the farm Sand Draai 391, Northern Cape Environmental Scoping Report A Report for Solafrica 14/12/16/3/3/3/203

More information

CMPDI. 4.6 Mine Closure Plan

CMPDI. 4.6 Mine Closure Plan 4.6 Mine Closure Plan Post-mining Land Use Planning The mine closure planning with regard to for Lekhapani OCP will broadly involve the following aspects: 1. Technical Aspects 2 Environmental Aspects 2.

More information

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5 CONTENTS 2. PROJECT DESCRIPTION 2-2 2.1 NEED FOR THE PROJECT 2 2 2.2 ABOUT THE PROPONENT 2 4 2.3 SITE SELECTION 2 4 2.4 OVERVIEW OF THE PROJECT 2 5 Figure 2.1: Provisional wind profile for the Jeffrey

More information

Advances in Dry Cooling Deployed at South African Power Stations

Advances in Dry Cooling Deployed at South African Power Stations Advances in Dry Cooling Deployed at South African Power Stations Steve Lennon Divisional Executive Eskom 2011 Summer Seminar August 1, 2011 Eskom s Move to Dry-Cooling Eskom historically utilized wet-cooled

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

ESKOM S UNDERGROUND COAL GASIFICATION PROJECT. Eskom s Clean Coal Programme

ESKOM S UNDERGROUND COAL GASIFICATION PROJECT. Eskom s Clean Coal Programme ESKOM S UNDERGROUND COAL GASIFICATION PROJECT SA/EU Bilateral Meeting 5/6 May 2008 1 Eskom s Clean Coal Programme Conventional sub critical Pulverised coal Supercritical Pulverised coal Medupi & Kusile

More information

Implementing the Mitigation Hierarchy

Implementing the Mitigation Hierarchy Implementing the Mitigation Hierarchy Presented by National Biodiversity and Business Network IUCN De Beers Group of Companies 10 August 2016 Objectives for the day Provide an overview of the overall framework

More information

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and Introduction There are many tools that a reviewer of environmental impact assessment documents can use to help determine whether such documents are complete and adequate. Among the powerful tools that

More information

ENVIRONMENTAL IMPACT ASSESSMENT STATION AND ASSOCIATED INFRASTRUCTURE IN THE WITBANK AREA

ENVIRONMENTAL IMPACT ASSESSMENT STATION AND ASSOCIATED INFRASTRUCTURE IN THE WITBANK AREA Report No: [4284/40 /401281 281] Report Copy: 1 of 14 ENVIRONMENTAL IMPACT ASSESSMENT PROCESS: PROPOSED COAL-FIRED POWER STATION AND ASSOCIATED INFRASTRUCTURE IN THE WITBANK AREA FINAL ENVIRONMENTAL IMPACT

More information

Outline for. Protected Areas Management Planning

Outline for. Protected Areas Management Planning Outline for Protected Areas Management Planning Level One: Community-based protected area management organizations and Level Two: Conservation organizations / Non-governmental organizations Outline for

More information

TECHNICAL INFORMATION ABOUT UNDERGROUND STORAGE RESERVOIRS FOR NATURAL GAS

TECHNICAL INFORMATION ABOUT UNDERGROUND STORAGE RESERVOIRS FOR NATURAL GAS TECHNICAL INFORMATION ABOUT UNDERGROUND STORAGE RESERVOIRS FOR NATURAL GAS I / 14 Underground Storage Reservoirs for Natural Gas 1 Fields of Application Underground storages (UGS) for natural gas are used

More information

Ukraine Sustainable Energy Lending Facility (USELF) Strategic Environmental Review (SER) Ecoline EA Centre

Ukraine Sustainable Energy Lending Facility (USELF) Strategic Environmental Review (SER) Ecoline EA Centre Ukraine Sustainable Energy Lending Facility (USELF) Strategic Environmental Review (SER) Ecoline EA Centre Objectives of Strategic Environmental Review (SER) The European Bank for Reconstruction and Development

More information

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR Overview of Presentation 1. Objectives of the Consultancy 2. Hydropower in Myanmar 3. Draft Table of Contents 4.

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

6 Risk assessment methodology

6 Risk assessment methodology Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management

More information

Appendix General Environmental Risk Analysis

Appendix General Environmental Risk Analysis Proposed Solar Power Station Near Moree, NSW (MOREE SOLAR FARM) Appendix Prepared by BP Solar & Walsh Consulting January 011 Background The body of the identifies all significant environmental risks identified

More information

18 Cumulative Impacts and Interaction of Effects

18 Cumulative Impacts and Interaction of Effects 18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly

More information

Coire Glas Pumped Storage Scheme

Coire Glas Pumped Storage Scheme About SSE SSE is one of the UK s largest energy companies and is headquartered in Perth. Our purpose is to provide the energy people need in a reliable and sustainable way. We're involved in producing,

More information

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements JUNE 2016 RONALD REAGAN WASHINGTON NATIONAL AIRPORT Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements PREPARED BY: Ricondo & Associates, Inc. IN

More information

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the

More information

Information on the focal point for the Convention. Information on the point of contact for the Convention

Information on the focal point for the Convention. Information on the point of contact for the Convention Questionnaire for the REPORT OF MONTENEGRO ON THE IMPLEMENTATION OF THE CONVENTION ON ENVIRONMENTAL IMPACT ASSESSMENT IN A TRANSBOUNDARY CONTEXT in the period 2006 2009 Information on the focal point for

More information

Alinta Cogeneration (Wagerup) Pty Ltd Alinta Wagerup Units 1 2

Alinta Cogeneration (Wagerup) Pty Ltd Alinta Wagerup Units 1 2 Pty Ltd Alinta Wagerup Units 1 2 STACK EMISSIONS MANAGEMENT PLAN WP03100-EV-PL-0006 Rev 1 October 2006 Pty Ltd Alinta Wagerup Units 1 2 STACK EMISSIONS MANAGEMENT PLAN WP03100-EV-PL-0006 Rev 1 October

More information

Case Study : Underground Coal Gasification (UCG) Majuba Update. Mark van der Riet Corporate Consultant Eskom Holdings Ltd South Africa

Case Study : Underground Coal Gasification (UCG) Majuba Update. Mark van der Riet Corporate Consultant Eskom Holdings Ltd South Africa Case Study : Underground Coal Gasification (UCG) Majuba Update Mark van der Riet Corporate Consultant Eskom Holdings Ltd South Africa Introduction Eskom presently generates 88% of its electricity from

More information

Assessing Values in Natural Resource Decision-making

Assessing Values in Natural Resource Decision-making Assessing Values in Natural Resource Decision-making Don Morgan, Dave Daust and Andrew Fall Introduction Making decisions on behalf of the public requires an understanding of societal values and knowledge

More information

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref: Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell Volume 2 NON TECHNICAL SUMMARY December 2012 SLR Ref: 419.00034.00473 INTRODUCTION 1. This Non Technical Summary (NTS) has been produced by

More information

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME 1 Introduction and Background To meet its environmental and social obligations and commitments, the Lesotho Highlands Development

More information

Gold Standard Passport CONTENTS

Gold Standard Passport CONTENTS Gold Standard Passport CONTENTS A. Project title B. Project description C. Proof of project eligibility D. Unique Project Identification E. Outcome stakeholder consultation process F. Outcome sustainability

More information

Template for ToR for Transaction Advisory Services

Template for ToR for Transaction Advisory Services Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND STATE UNIVERSITY CONSTRUCTION FUND The following checklist show the general items required by the Agreement and the Program Directives. Unless included in the lump sum fee or the Schedule B of the Consultant

More information

Provincial Policy Statement 2014 Training Aid

Provincial Policy Statement 2014 Training Aid This job aid has been developed for education and training purposes as a high-level summary of the policy changes in the PPS 2014. It should not be relied upon as a substitute for specialized legal or

More information

2. Project Justification and Feasible Alternatives

2. Project Justification and Feasible Alternatives 2. Project Justification and Feasible Alternatives 2.1 Project Justification Energy intensive industries associated with the coal and gas sectors in the Surat region continue to drive electricity demand

More information

A. OWENS 1 and J. BURKE 2

A. OWENS 1 and J. BURKE 2 A CONSOLIDATED APPROACH TO IMPLEMENTING BEST PRACTICE GUIDELINES, WATER USE LICENCE CONDITIONS AND INTEGRATED WATER AND WASTE MANAGEMENT PLANS IN THE MINING ENVIRONMENT OPPORTUNITIES AND CHALLENGES ABSTRACT

More information

NOVEMBER 2016 REVISION 0. Prepared by: JG AFRIKA (PTY) LTD

NOVEMBER 2016 REVISION 0. Prepared by: JG AFRIKA (PTY) LTD DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT & ENVIRONMENTAL MANAGEMENT PROGRAMME REPORT: PROPOSED ESTABLISHMENT OF A STAGED MOBILE CRUSHING PLANT WITHIN THE CURRENT FOOTPRINT OF THE AMASUNDU GRAVEL CC

More information

Chartered Professional Engineer (Geotechnical) Body of Knowledge and Skills

Chartered Professional Engineer (Geotechnical) Body of Knowledge and Skills 18 October 2016 Chartered Professional Engineer (Geotechnical) 1. Introduction This document defines the core knowledge and skills that a Chartered Professional Engineer (Geotechnical) ((Geotechnical))

More information

SUSTAINABLE DEVELOPMENT, DISASTER-RISK REDUCTION AND GOVERNANACE: ASSESSING CLIMATE CHANGE ADAPTATION CHALLENGES FACING SOUTH AFRICA

SUSTAINABLE DEVELOPMENT, DISASTER-RISK REDUCTION AND GOVERNANACE: ASSESSING CLIMATE CHANGE ADAPTATION CHALLENGES FACING SOUTH AFRICA SUSTAINABLE DEVELOPMENT, DISASTER-RISK REDUCTION AND GOVERNANACE: ASSESSING CLIMATE CHANGE ADAPTATION CHALLENGES FACING SOUTH AFRICA Smangele K. Mgquba Submitted in fulfillment of the requirements for

More information

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME OPERA PHASE: ENVIRONMENTAL MANAGENT PROGRAMME 1. OBJECTIVE The overall goal for the Environmental Programme (O) is to ensure that the operation of the wind energy facility (WEF) does not have unforeseen

More information

Annex 1: Project Tropicalia Sustainable Tourism, Dominican Republic

Annex 1: Project Tropicalia Sustainable Tourism, Dominican Republic Annex 1: Project Tropicalia Sustainable Tourism, Dominican Republic and Social Action Plan (ESAP) Item PS 1: Assessment and Management of and Social Risks and Impacts 1.1 and Social Management System (ESMS)

More information

DEPARTMENT OF ENVIRONMENTAL PROTECTION Bureau of Water Quality Protection. Design Criteria - Wetlands Replacement/Monitoring

DEPARTMENT OF ENVIRONMENTAL PROTECTION Bureau of Water Quality Protection. Design Criteria - Wetlands Replacement/Monitoring DEPARTMENT OF ENVIRONMENTAL PROTECTION Bureau of Water Quality Protection DOCUMENT NUMBER: 363-0300-001 TITLE: Design Criteria - Wetlands Replacement/Monitoring EFFECTIVE DATE: February 11, 1997 AUTHORITY:

More information

SABI Code of Practice for On-farm Irrigation Design

SABI Code of Practice for On-farm Irrigation Design SABI Code of Practice for On-farm Irrigation Design This code was developed to provide guidelines for irrigators and those servicing irrigators on developing a new irrigation system or upgrading an existing

More information

ABOUT US. Earth Link & Advanced Resources Development (ELARD)

ABOUT US. Earth Link & Advanced Resources Development (ELARD) ABOUT US Earth Link & Advanced Resources Development (ELARD) As a leading regional consultancy firm, operating primarily in the Middle-East, Gulf and North Africa, ELARD has become a key service provider

More information

Provincial Policy Statement 2014

Provincial Policy Statement 2014 Natural Heritage Provincial Policy Statement 2014 NATURAL HERITAGE Nature is bountiful. It is also fragile and finite. Provincial Natural Heritage 0 Interest: Ontario s natural heritage resources are valuable

More information

A1 Australian and South Australian Government Guidelines 813. A2 South Australian Government Guidelines 871

A1 Australian and South Australian Government Guidelines 813. A2 South Australian Government Guidelines 871 Appendix A EIS Guidelines CONTENTS A1 Australian and South Australian Government Guidelines 813 A2 South Australian Government Guidelines 871 A3 Northern Territory Government Guidelines 929 Olympic Dam

More information

CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999

CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999 (No. JPBN. 1509/27 Vol. II CONSERVATION OF ENVIRONMENT ENACTMENT 1996 CONSERVATION OF ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER 1999 In exercise of the powers conferred by section 5 of the Conservation

More information

Environmental Impact Statement for the Slave Falls Tramway Conversion Project

Environmental Impact Statement for the Slave Falls Tramway Conversion Project Environmental Impact Statement for the Slave Falls Tramway Conversion Project Prepared for Submitted by 41844.101 March 2008 ENVIRONMENTAL IMPACT STATEMENT FOR THE SLAVE FALLS TRAMWAY CONVERSION PROJECT

More information

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited SCREENING SCOPING DOCUMENT For the proposed Shell Quest Carbon Capture and Storage Project Shell Canada Limited Prepared by: Canadian Environmental Assessment Agency Natural Resources Canada Fisheries

More information

GUIDELINE. environmental management of mining. GUIDELINE 11 - Terms of Reference and Preparation of an Environmental Impact. Statement.

GUIDELINE. environmental management of mining. GUIDELINE 11 - Terms of Reference and Preparation of an Environmental Impact. Statement. GUIDELINE environmental management of mining GUIDELINE 11 - Terms of Reference and Preparation of an Environmental Impact Statement Content: 1 Introduction 2 Background 3 Objectives page 1 page 1 page

More information

TERMS OF REFERENCE FOR THE STELLENBOSCH PLANNING ADVISORY COMMITTEE

TERMS OF REFERENCE FOR THE STELLENBOSCH PLANNING ADVISORY COMMITTEE TERMS OF REFERENCE FOR THE STELLENBOSCH PLANNING ADVISORY COMMITTEE The Greater Stellenbosch is a place of great character and beauty. This is not only due to its dramatic natural setting but also because

More information

Nxuba Wind Farm NERSA PUBLIC HEARINGS. 10 September 2015

Nxuba Wind Farm NERSA PUBLIC HEARINGS. 10 September 2015 Nxuba Wind Farm NERSA PUBLIC HEARINGS 10 September 2015 1 Nxuba Wind Farm has been appointed as a Preferred Bidder in the Fourth Round of the Department of Energy s (DoE) Renewable Energy IPP Procurement

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT

THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT THE EGGBOROUGH CCGT PROJECT STAGE 1 CONSULTATION: PROJECT INFORMATION DOCUMENT Welcome Eggborough Power Ltd (EPL) is proposing to develop a new gas-fired power station on the site of its existing coal-fired

More information

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act:

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act: TRCA Technical Guidelines for the Development of Environmental Management Plans for Dewatering September 2013 Rationale: The Technical Guidelines for the Development of Environmental Management Plans for

More information

Background Information Document and Invitation to Comment

Background Information Document and Invitation to Comment Background Information Document and Invitation to Comment Environmental Impact Assessment for the Proposed Drennan Photovoltaic (PV) Solar Power Plant, Cradock, Eastern Cape Province Scoping/EIA DEA Ref

More information

Chapter 17 Cumulative Impacts

Chapter 17 Cumulative Impacts Chapter 17 Cumulative Impacts CONTENTS 17. Cumulative Effects... 2 17.1 Introduction... 2 17.2 Summary of Relevant Legislation, Planning Policy and Guidance... 2 17.3 Methods... 5 17.4 Consultation...

More information

Hatch Wi-Fi Username: guest Password: qskm3123 Guest Name: NBBN Conference National Biodiversity & Business Indaba

Hatch Wi-Fi Username: guest Password: qskm3123 Guest Name: NBBN Conference National Biodiversity & Business Indaba Hatch Wi-Fi Username: guest-8614098 Password: qskm3123 Guest Name: NBBN Conference 2016 National Biodiversity & Business Indaba 1. Context 2. EWT Overview 3. EWT s history in mainstreaming biodiversity

More information

DEPARTMENT OF WATER AFFAIRS. Submitted to: Department of Water and Sanitation Chamber of Mines of South Africa

DEPARTMENT OF WATER AFFAIRS. Submitted to: Department of Water and Sanitation Chamber of Mines of South Africa REPORT July 2014 DEPARTMENT OF WATER AFFAIRS Water Conservation / Water Demand Management Implementation Guideline for the Mining Sector Submitted to: Department of Water and Sanitation Chamber of Mines

More information

No October 2012

No October 2012 196 No. 35769 GOVERNMENT GAZETTE, 10 OCTOBER 2012 No. 806 10 October 2012 NATIONAL ENVIRONMENTAL MANAGEMENT ACT, 1998 (ACT NO. 107 OF 1998) PUBLICATION OF ENVIRONMENTAL MANAGEMENT FRAMEWORK GUIDELINE FOR

More information

FINAL ENVIRONMENTAL SCOPING REPORT (DEAT APPLICATION NO. 12/12/20/806)

FINAL ENVIRONMENTAL SCOPING REPORT (DEAT APPLICATION NO. 12/12/20/806) FINAL ENVIRONMENTAL SCOPING REPORT (DEAT APPLICATION NO. 12/12/20/806) for the proposed PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA BAY, WESTERN CAPE DATE: May 2007 Contract

More information

Chapter 1 Introduction

Chapter 1 Introduction Chapter 1 Introduction TABLE OF CONTENTS 1 INTRODUCTION... 1-1 1.1 General... 1-1 1.2 Background to the WREP... 1-1 1.3 Rationale for WREP-SR Project... 1-2 1.4 WREP Operator: GPC and BP Relationship...

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3946. Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3946. Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

Recruitment and Appointment Policy Responsible Officer. Executive Director, Human Resources Approved by

Recruitment and Appointment Policy Responsible Officer. Executive Director, Human Resources Approved by Recruitment and Appointment Procedure Related Policy Recruitment and Appointment Policy Responsible Officer Executive Director, Human Resources Approved by Executive Director, Human Resources Approved

More information

GP 30/5/1/3/2/10242 MP

GP 30/5/1/3/2/10242 MP ! Before Dawn Property Developers (Pty) Ltd GP 30/5/1/3/2/10242 MP Background Information Document For the proposed mining permit On the farm Malony s Eye 169 IQ. Report Ref: 2017/BDPD0001 Prepared by:

More information

Environmental Management Plan (EMP)

Environmental Management Plan (EMP) SE DELI GS DRIFT MI E ORA GE RIVER MI ES MI I G ACTIVITIES A D PROPOSED EW I PIT SLIMES DISPOSAL Environmental Management Plan (EMP) Compiled for: Namdeb Diamond Corporation (Pty) Ltd Compiled by: Unit

More information

Performance Standard 6 V2

Performance Standard 6 V2 Introduction 1. Performance Standard 6 recognizes that protecting and conserving biodiversity, maintaining ecosystem services, and sustainably managing living natural resources are fundamental to sustainable

More information

Ottawa-Trussler Area Sewage Facility Class Environmental Assessment

Ottawa-Trussler Area Sewage Facility Class Environmental Assessment Welcome to the Ottawa-Trussler Area Sewage Facility Class Environmental Assessment Public Open House May 7, 2013 September 25, 2013 Welcome The purpose of this second Public Open House is to: Present the

More information

Hydropower Sustainability Assessment Protocol Section IV Trail ESKOM. Palmiet/Drakensberg Pumped Storage Schemes. November 2009

Hydropower Sustainability Assessment Protocol Section IV Trail ESKOM. Palmiet/Drakensberg Pumped Storage Schemes. November 2009 Hydropower Sustainability Assessment Protocol Section IV Trail ESKOM Palmiet/Drakensberg Pumped Storage Schemes November 2009 Assessor: Rob Griffin Date: 2009-11-25 Table of Contents 1 Introductory Information...

More information

Electricity Slide Index Slide 2: Generating Electricity Slide 3: SA Power Grid

Electricity Slide Index Slide 2: Generating Electricity Slide 3: SA Power Grid Electricity Slide Index 1 Introduction 2 Generating Electricity 3 SA Power Grid 4 SA Electricity Supply 5 Abundant Energy Source: Coal 6 7 Supply vs Demand: 6 Electricity Demand Pattern 7 The Energy Balance

More information

Information Delivery Manual (IDM)

Information Delivery Manual (IDM) Piping Engineering - Confluence http://idm.buildingsmart.no/confluence/display/idm/piping+engineering?decorator=printable 1 af 2 11-09-2011 19:21 Information Delivery Manual (IDM) Added by Jeffrey Wix,

More information

South African Mainstream Renewable Jeffreys Bay Pty Ltd

South African Mainstream Renewable Jeffreys Bay Pty Ltd South African Mainstream Renewable Jeffreys Bay Pty Ltd Presented to : NERSA, Pine Lodge Conference Centre, Port Elizabeth Date: 2 nd March 2012 Presentation outline 1. Background 2. Milestones 3. Project

More information

Stakeholder Engagement Plan Code Of Practice

Stakeholder Engagement Plan Code Of Practice a Stakeholder Engagement Plan Code Of Practice COP 302 Revision 00 A Revisions Paragraph Revision Change Date - 00 Created 20/02/2014 B Approval Name Signature Date Compiled by Dieter Klingenberg 20/02/2014

More information

SUNDANCE 7 January 2014

SUNDANCE 7 January 2014 Artist rendering of a combined-cycle natural gas power plant. SUNDANCE 7 January 2014 Project Information Booklet Table of Contents Introduction to Sundance 7 1 TransAlta and MidAmerican 1 Project location

More information

National Occupational Standards. for. Project Management

National Occupational Standards. for. Project Management National Occupational Standards for Project Management Version 1.01 March 2003 Page 1 Comment Observations and comment for future consideration of this document may be directed to: ECITB Blue Court 1 Church

More information

PROPOSED DEVELOPMENT OF A HOTEL AT THE CONFLUENCE OF THE TIMFENHENI AND CROCODILE RIVERS WITHIN THE KRUGER NATIONAL PARK

PROPOSED DEVELOPMENT OF A HOTEL AT THE CONFLUENCE OF THE TIMFENHENI AND CROCODILE RIVERS WITHIN THE KRUGER NATIONAL PARK PROPOSED DEVELOPMENT OF A HOTEL AT THE CONFLUENCE OF THE TIMFENHENI AND CROCODILE RIVERS WITHIN THE KRUGER NATIONAL PARK DEA REFERENCE: 12/12/20/610/69 ENVIRONMENTAL IMPACT ASSESSMENT PROCESS: DRAFT SCOPING

More information

Electricity Safety (Electric Line Clearance) Regulations 2010

Electricity Safety (Electric Line Clearance) Regulations 2010 Version No. 001 Electricity Safety (Electric Line Clearance) Regulations 2010 Version as at 29 June 2010 TABLE OF PROVISIONS Regulation Page 1 Objectives 1 2 Authorising provisions 1 3 Commencement 2 4

More information

ENVIRONMENTAL IMPACT ASSESSMENT: FINAL SCOPING REPORT

ENVIRONMENTAL IMPACT ASSESSMENT: FINAL SCOPING REPORT Report No : 3907/400850 ENVIRONMENTAL IMPACT ASSESSMENT: Proposed Open Cycle Gas Turbine Power Plant, Fuel Supply Pipeline, Substation and Transmission Lines at Mossel Bay FINAL SCOPING REPORT Prepared

More information

KANMANTOO PUMPED HYDRO STEVE McCLARE IIIII CEO & MANAGING DIRECTOR PUMPED HYDRO ENERGY STORAGE CONFERENCE SYDNEY MARCH 2018

KANMANTOO PUMPED HYDRO STEVE McCLARE IIIII CEO & MANAGING DIRECTOR PUMPED HYDRO ENERGY STORAGE CONFERENCE SYDNEY MARCH 2018 KANMANTOO PUMPED HYDRO STEVE McCLARE IIIII CEO & MANAGING DIRECTOR PUMPED HYDRO ENERGY STORAGE CONFERENCE SYDNEY MARCH 2018 STATEMENT No representation or warranty is or will be made by any person (including

More information

Summary of LAKE ONTARIO Policies. 1. Requiring SPC approval: LO SEW 3 LO FUEL 2

Summary of LAKE ONTARIO Policies. 1. Requiring SPC approval: LO SEW 3 LO FUEL 2 Summary of LAE ONTARIO 1. Requiring SPC approval: LO SEW 3 LO FUEL 2 2. Information (editorial, revised, new): LO G 1 (revised) LO NGS 1 (revised) LO G 2 (revised) LO SEW 2 (revised) LO G 6 (revised) LO

More information

LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006

LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006 LESEDI ENVIRONMENTAL MANAGEMENT FRAMEWORK (EMF) PUBLIC MEETING 25 JANUARY 2006 AGENDA Opening and Welcome Introduction of Consultants Profile of Izwelisha Consortium Explanation of the EMF process Environmental

More information

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number:

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: Comprehensive Study Scoping Document for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: 07-03-26302 Prepared pursuant to Subsection 21(1) of the Canadian Environmental Assessment

More information

DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR THE FOR BELA BELA FARMYARD ESTATE (PTY) LTD ON THE FARM NOODHULP 492 KR

DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR THE FOR BELA BELA FARMYARD ESTATE (PTY) LTD ON THE FARM NOODHULP 492 KR ENVIRONMENTAL ASSURANCE (Pty) Ltd Draft EIA Report BELA BELA Report Number PROJ-115-LIM-RW-EIA 01 Revision Number 02 Page Number Page i of 113 DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR THE PROPOSED

More information

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until 2035 Non Technical Summary SLR Consulting Limited Project Ref: 403.00079.00474

More information

IAIAsa August 2014 Betty Mdala Department of Environmental Affairs

IAIAsa August 2014 Betty Mdala Department of Environmental Affairs D R A F T S TA N D A R D F O R T H E S T O R A G E O R S T O R A G E A N D H A N D L I N G O F D A N G E R O U S G O O D S A N D I D E N T I F I C AT I O N O F A C T I V I T I E S W H I C H M AY C O M

More information