1 PROJECT PRE-FEASIBILITY REPORT Of PROPOSED EXPANSION PROJECT For SYNTHETIC ORGANIC CHEMICALS MANUFACTURING UNIT At Plot No. 1088/B Lamdapura road, Village: Manjusar, Ta: Savli, Dist: Vadodara, Gujarat Project proponent

2 CHAPTER 1 EXECUTIVE SUMMARY The project is summarized in the below table: Table 1.1: Project Summary PARTICULARS NAME OF THE UNIT OCCUPIER PRODUCTS LOCATION NATURE OF PROJECT DETAILS M/s. Universal Ester Ltd. Mr. Vishwas R. Gole, Mr. Mukesh D.Patel, Mr. Dushyant D. Patel S. No. Name of Products Proposed Quantity of Production Quantity in MT / Month Existing Quantity After Phase-I After Phase-II Existing Products* Methyl Anithranilate* Ethyl Salicylate* Ethyl Benzoate* Amyl Salicylate* 3.0 NIL NIL Benzyl Salicylate* Menthyle Salicylate* Amyl Acetate* Or any other type of chemicals in category of organge esters* Octyl Methoxycinnamate Octyl Salicylate Octyl Hydroxystearate Proposed products Homosalate Cosmetic emmolients Ethyl methoxycinnamate Proposed products (Repacking & Reselling) 7. Octocrylene - 8. Benzophenone-3-9. Benzophenone Avobenzone - TOTAL *Note: The company has obtained consolidated consent & Authorization (CC&A) no. H valid up to 24/07/2015 for manufacturing of these products as well, but is not manufacturing them anymore. Plot No. 1088/B, lamdapura road, Village: Manjusar, Ta: Savli, Dist: Vadodara, Gujarat Proposed Expansion Project for Increase in existing production quantities and adding new products in the similar category of products i.e. synthetic organic chemicals 1

3 RESOURCES Resource type Land Building Raw-materials Water Power Fuel Man-power POLLUTION POTENTIAL & MITIGATION MEASURES Parameter Potential Existing After Phase-I Wastewater Industrial: 0.60 Industrial: 7.0 KLD KLD Domestic: 2.0KLD Domestic: 1.20 KLD Air Emissions Requirement Existing m m 2 As given in section Raw Material for finished products. Existing 4.6 KLD 125 KVA Agro waste-500 kg/day Non IBR Boiler 1 no. After Phase-I m m 2 After Phase-I 29.0 KLD 250 KVA Agro waste-800kg/day Diesel-50 LPH TFH 2 Nos. 1 of 6 lakh k.cal/hrs and 1 of 10 lakh kcal/hrs. D.G. Set 125 KVA 1 nos. After Phase-II m m 2 After Phase-II 37 KLD 250 KVA Agro waste-8000 kg/day Diesel-50 LPH 55 After Phase-II Industrial: 10.0 KLD Domestic: 2.2KLD TFH 2 Nos. 1 of 6 lakh k.cal/hrs and 1 of 10 lakh kcal/hrs. D.G. Set 125 KVA 1 nos. Source No additional land is required for expansion project. Only slight modification in the existing infrastructure will be done. The raw materials are available in Local/ Indian market and are also imported from foreign countries. Fresh water is sourced from in-house bore well and same will be the source of supply for the additional quantity. Sourced from MGVCL 1 D.G. Set 125 KVA will be installed as Standby arrangement. Local Suppliers. To be employed from local area Mitigation Measures The domestic effluent is/will be disposedd off through septic tank/ soak pit system. In existing operation Industrial wastewater is treated in ETP and treated water is used for gardning purpose. After proposed expansion wastewater will be treated in ETP. Treated effluent from ETP will be sent to CETP of EICL or will be evaporated in evoporation unit. In existing operations one non IBR Boiler is installed. Agro waste is used as fuel in non IBR Boiler For proposed expansion non IBR Boiler will be replaced by two Thermic Fluid heaters of 6 lakh kcal/hrs and 10lakh kcal/hrs capacities and one D.G. Set of 125 KVA capacities will be installed. Agro waste will be used as fuel in TFH Cyclone separator will be attached to TFH as APCD. Diesel will be used as fuel in D.G. Set. There is no process gas emission from the existing plant as well as proposed expansion project. Raw Materials& Products are/will be 2

4 Hazardous & solid waste ETP Waste (Cat. 34.3) : 0.04MT/Month Distillation Residue (Cat. 20.3): 3.36 MT/Yr Spent Carbon (Cat.35.3 ): 0.05 MT/Month Used Oil (Cat. 5.1): 1.2KL/Yr Discarded Containers (33.3): 120 Nos./Month Non Haz.Waste Fly ash: 13 MT/yr. ETP Waste (Cat. 34.3) : 5.5MT/ Month Distillation Residue (Cat. 20.3): 80MT/Yr Spent Carbon (Cat.35.3 ): 0.1 MT/ Yr Used Oil (Cat. 5.1): 2 KL/Yr Discardedd Containers /Bags (33.3): 9870 Nos./yr Inorganic process waste (28.1): 97 MT/yr Spent solvent (20.2): 210MT/yr. Non Haz.Waste Fly ash: 220 MT/yr. ETP Waste (Cat. 34.3) : 8.5 MT/ Month Distillation Residue (Cat. 20.3): 125 MT/Yr Spent Carbon ( Cat.35.3 ): 0.1 MT/Month Used Oil (Cat. 5.1): 2.5 KL/Yr Discarded Containers/Bags ( 33.3): Nos./yr Inorganic process waste (28.1): 155 MT/yr Spent solvent (20.2): 325 MT/yr. Non Haz.Waste Fly ash: 220MT/yr. stored in properly designed storage area to prevent any volatilities Good housekeeping is/will be maintained in the plant. Regular VOC monitoring will be carried out after proposed expansion. ETP waste: Collection, storage, transportation, disposal at TSDF. Distillation residue: Collection, storage, transportation and disposal by common incinerator at NECL/GEPIL. Spent carbon: Collection, storage, transportation and disposal by incinerator. Used oil: Collection, storage, transportation, disposal by selling to registered re-refiners. Discarded Containers: Collection, storage, transportation, disposal by selling to registered re-refiners. Fly ash to be sold to brick manufacturer In-organic process waste: Collection, storage, transportation, disposal at TSDF Spent solvent will be sold to the actual users. Noise Expected levels Inside the plant: <80 db(a) Expected levels Inside the plant: <80 db(a) Expected levels Inside the plant: < 80 db( (A) The major sourcess of noise generation in plant area are equipment machinary and TFH. Anti vibration pads and flexible bellows is provided wherever applicable. Acousticc Enclosure to D.G. Set will be provided. Ear plug and Ear muff are provided. Regular maintenancee lubrication shall be done. 3

5 CHAPTER 2 INTRODUCTION OF THE PROJECT 2.1 IDENTIFICATION OF THE PROJECT AND PROJECT PROPONENT IDENTIFICATION OF THE PROJECT M/s. Universal Ester Ltd. is a Limited company which was established in 1994.The company is engaged in the commercial production of Personal care ingredients, used in various types of formulations, primarily in the Cosmetics industry at its manufacturing facility located at Plot No. 1088/B, Village: Manjusar, Lamdapura road, Ta.: Savli, Dist.: Vadodara. The company is a smalll scale chemicals manufacturing unit. The unit is engaged in manufacturing of (1) Octyl Methoxycinnamate, (2) Octyl Salicylate and (3)Octyl Hydroxystearate. The company has obtained consolidated consent & Authorization (CC&A) no. H valid up to 24/07/2015 for manufacturing of 11 various products but presently the company is manufacturing only above given three products. The existing consent to operate-cca is attached as Annexure-1. Now, the company has planned to increase its existing capacity and add new products in the similar category of products. The list wise products and its production capacity are given in table below: Table 2.1: List of Products S. Name of Products N o. Existing Products* 1. Methyl Anithranilate* 2. Ethyl Salicylate* 3. Ethyl Benzoate* 4. Amyl Salicylate* 5. Benzyl Salicylate* 6 Menthyle Salicylate* 7. Amyl Acetate* 8. Or any other type of chemicals in category of organge esters* 9. Octyl Methoxycinnamate 10 Octyl Salicylate. 11 Octyl Hydroxystearate. Proposed products 4. Homosalate 5. Cosmetic emmolients 6. Ethyl methoxycinnamate Proposed Quantity of Production Quantity in MT / Month Existing Quantity After Phase-I After Phase-II NIL NIL

6 Proposed products (Repacking & Reselling) 7. Octocrylene - 8. Benzophenone-3-9. Benzophenone Avobenzone - TOTAL *Note: The company has obtained consolidated consent & Authorization (CC&A) no. H valid up to 24/07/2015 for manufacturing of these products as well, but is not manufacturing them anymore PROJECT PROPONENT The company is a Limited firm and directors of the company are well educated and professionally qualified; they take every step to ensure that all safety measure to Plant and Environment are fully complied with. Below is a brief profile of the management team. Mr.Vishwas Gole (Director) Mr.Vishwas Gole has done his graduation in Chemistry. He has around 45 years of experiencee in the Chemicals industry. He has worked for over 25 years with renowned companies in USA. Before returning to India, he was Director (R&D) with a leading US company. He mainly looks after Technical and Marketing aspects in the company. Mr. Mukesh Patel (Director) Mr. Mukesh Patel is a Chemical Engineer with over 40 years of experience in the industry. He is in a strategic advisory role in the company. Chemicals Table 2.2: Addresses of Directors Sr. No Name of Directors Mr. Vishwas R. Gole Mr. Mukesh D.Patel Dushyant D. Patel Addresses 4, Kant Flats 7, Suvanapuri Soc. Jetalpur Road, Vadodara 5. 93, Urmi Society. Productivity Road, Vadodara 7. 3& 4, Aakashwan Hsg. Complex. Gotri Sevasi Road, Vadodara 2.2 NATURE OF THE PROJECT The proposed expansion project involves the production of synthetic organic chemicals whichh falls under item no 5(f) i.e. synthetic organic chemicals as per the EIA notification, 14 September 2006 (as amended timely). Since, the project is not located within any notified industrial area/estate; it is to be treated as Category A and needs to obtain the priorr Environmental Clearance from EIAA (MoEF). 5

7 2.3 NEED OF PROJECT & DEMAND-SUPPLY GAP The products are used in various types of formulations, primarily in the Cosmetics industry. All the products are user friendly confirming with international standards. The proposed products range having a good demandd in the market& as per market survey by the company there is a less supply of the product against its demand, to overcome this shortage & to get benefit out of that the company proposed to have this project. 2.4 EXPORT POSSIBILITY As per market survey by the company, these proposed products are having a domestic as well as export market due to its application in various types of formulations, primarily in the Cosmetics industry 2.5 EMPLOYMENT GENERATIONN DUE TO PROPOSED PROJECT The proposed expansion project will provide direct employment opportunityto20 persons and indirect employment to few persons. The man-power required for the project will be employed locally from the nearby areas. 6

8 CHAPTER 3 PROJECT DESCRIPTION 3.1 TYPE & LOCATION OF PROJECT TYPE The proposed project is an expansion for increase in existing production capacity and manufacturing of new range of products falling in the similar category of products, i.e. Synthetic Organic Chemicals LOCATION M/s. Universal Esters Ltd. is located at Plot No.1088/B, Village: Manjusar, Lamdapura road, Ta: Savli, Dist: Vadodara. Savli is a village near Vadodara, Gujarat in Western India. One of the Gujarat Industrial Development Corporation centers is very near to it; the branch of Santram temple is also located in this village near the Mahisagar River. The population in Savli comprises Baniaa (Vaishnava), Patel, Brahmin and Raj puts, Muslims also are part of the village. The main crop of this village is tobacco. Savli is also becoming an educational hub with an educational campus including the K. J. Institute of Engineering and Technology. In addition to this college there are arts & commerce colleges and a homeopathic medical college. The site is approximately kms SSW from Vadodara - the third largest city in the Indiann State of Gujarat, after Ahmadabad and Surat. It is the administrative headquarters of Vadodaraa District. It is located on the banks of the Vishwamitri river, southeast of Ahmadabad, 139 km from state capital, Gandhinagar. Both the railway line and national highway connecting Delhi and Mumbai pass through Vadodara. It is also the home of the Maharaja Sayajirao University of Baroda, which is the largest university in Gujarat. Major industriess include petrochemicals, engineering, chemicals,pharmaceuticals, plastics and Forex. 7

9 Figure 3.1: Project Site 8

10 Figure 3.2: Satellite Image of the Project Site 9

11 Figure 3.3: Project Site layout Table 3.1: Area Statement S. No Description Total Plot Area Built-up area Greenbelt area Open Area Approx. Area (m 2 )

12 3.2 DETAILS OF THE ALTERNATIVE SITE The proposed expansion is to be carried out in the existing industrial plot. So no alternativee study for site selection has been conducted. The present land is adequate to cater the requirement of the proposed expansion project. Further the existing infrastructure & machinery availability is very helpful to avoid installation of many infrastructure & machinery for the proposed project. These together justify the use of existing premises for proposed project. Hence only existing site is considered for the proposed project. Some more benefits of the existing site are shown below. Site is very well connected by road. Proximity to Raw Material suppliers Availability of power from MGVCL SIZE & MAGNITUDE OF OPERATION The total magnitude of operation after proposed expansion will be 2400 MT/A. 3.4 PROJECT DESCRIPTION WITH PROCESS DETAILS It is noteworthy that the company is proposing change in process in terms of change of catalystt and raw-material for manufacturing of its existing 2 nos. of products, viz. octylmethoxycinamate and octyl salicylate. Details of both existing and proposed process are provided in subsequent sections. Moreover, some of the products (viz. Octocrylene e, Benzophenone-3, Benzophenone -4, and Avobenzone) are only to be purchased, repacked and sold out. 111

13 3.4.1 Existing Products Scenario OCTYL METHOXYCINAMATE ( EXISTING PROCESS) Chemical Reaction Manufacturing Process Into an S.S. Reactor para Anisic Aldehyde, catalyst & 2-ethyl hexyl acetatee are charged. & masss is heated to 190 C 0-200C 0 for 48 hours. Then masss is cooled to 70C 0-80C 0 & filter through filter press. Mother liquor is distilled under high vacuum to get 98% octyl methoxycinamate. Recovered 2-ethyl hexyl acetate is recycled in the next batch Material Balance 12

14 OCTYL METHOXYCINAMATE ( PROPOSED PROCESS) Chemical Reaction Manufacturing Process Into an S.S. Reactor para Anisic Aldehyde, inorganic catalyst & 2-ethyl hexyl acetate are charged. & mass is heated to 190 C 0-200C 0 for 48 hours. Then mass is cooled to 70C 0-80C 0 & filter through filter press. Mother liquor is distilled under high vacuum to get 98% octyl methoxycinamate. Recovered 2-ethyl hexyl acetate is recycled in the next batch Material Balance 13

15 OCTYL SALICYLATE (EXISTING PROCESS) Chemical Reaction Manufacturing Process Into a glass lined reactor salicylic acid (1100 kgs), catalyst (60 kgs) 2-ethyl hexanol (1140 kgs) are charged. & mass is slowly heated to 120 c & hold for 3 hours. Apply low vacuum & slowly raise temp, to 150 c for 8 hours & sample is given to check G.C. Then crude is transferred to distillation tank. Crude is distilled under high vacuum to get 99% octyl salicylate Material Balance 14

16 OCTYL SALICYLATE (PROPOSED PROCESS) Chemical Reaction Manufacturing Process Into a glass lined reactor methyl salicylate, catalyst and 2-ethyl hexanol are charged. & mass is slowly heated to 120C 0 & hold for 3 hours. Slowly raise temp, to 150 C 0 for 8 hours & sample is given to check GC. Then crude is transferred to distillation tank. Crude is distilled under highh vacuum to get 99% octyl salicylate Material Balance 15

17 OCTYL HYDROXYSTEARATE Chemical Reaction Manufacturing Process Into a glass line reactor 12HAS, catalysts& 2-ethyl hexanol are charged. & mass is heated to 180 C 0 for 24 hours & water is removed. Check the acid value. If the acid value is <1.5% stop the reaction & slowly apply vacuum & then under high vacuum remove 2-ethyl hexanol. If GC of 2-ethyl hexanol is <2.0% stop the vacuum and heat. Cool down to 80 c & filter product Material Balance 16

18 3.4.2 Proposed Products Scenario HOMOSALATE Chemical Reaction Manufacturing Process Into an S.S. Reactor methyl salicylate, catalyst & homo Menthyl alcohol are charged& mass is heated to 180 C for 24 hours & check GC. If methyl salicylate is <1.5% stop the reaction. Cool down to 80 C & transfer crude to distillation unit. Crude is distilled in Column distillation to get 99% purity & colorless product Material Balance 17

19 ETHYLE METHOXYCINNAMATE Chemical Reaction Manufacturing Process Into (200 ltr) glasss lined reactor paraanisic aldehyde (40 kgs), & ethyl acetate (120kgs) are charged. Mass is cooled to 10 C. 16 kgs catalyst is added over the period of 2 hours. Keeping temp. < 30 C. Reaction mixture is kept stirring around 30 C for 3 hours. Sample is taken to check unreacted p-anisic aldehyde which is <1.0% %. 25% acetic acid is added to neutralize the catalyst. Organic and water layer is separated. Organic layer is taken for distillation to get 98% purity of ethyl methoxycinnamate. Water layer is taken for distillation in distillation/evaporation unit Material Balance 18

20 Cosmetic Emollients Chemical Reaction Manufacturing Process Into (200 ltr) glass lined reactor carboxylic acid, alcohol & catalyst are charged. Keeping temp.< 30 C. Reaction mixture is kept stirring around 30 C for 3 hours. Aqueous layer is separated which is sent to ETP. Then it is taken into high vaccum distillation. Alcohol is separated and minor loss occurred. Sample is taken to check for GC and cooled down. Then mixture is passed from filtration unit where process waste is separated. Finally 98% pure cosmetic emollients is obtained Material Balance 19

21 3.5 RAW MATERIAL FOR FINISHED PRODUCTS The raw materials for the proposed range of products will be indigenously available and will be also imported. Table 3.2(a): List of Raw Materials Product Octyl Methoxycinnamate Octyl Salicylate Octyl HydroxyStear rate Homosalate Ethyl methoxycinnamate Name of Raw Material P-Anisic Aldehyde 2-Ethyl Hexylacetate Catalyst Salicylic acid Methyl Salicylate 2-Ethyl Hexanol Catalyst 12 H.S.A. 2-Ethyl Hexanol Catalyst Methyl Salicylate Homo Menthyl Alcohol Catalyst P-Anisic Aldehyde Ethyl Acetate Catalyst Acetic acid (25%) Requirement (MT/Month) Existing After Phase I After Phase II Or Or Or And HAZARDOUS CHEMICAL STORAGE & HANDLING Hazardous chemicals are/willl be used as raw material in the manufacturing process. Storage, handling & transport of Hazardous Chemicals are given in table 3.2(b). Table 3.2(b): Storage, Handling & Transport of Hazardous Chemicals Raw Material/ finished goods Raw Material P-Anisic Aldehyde 2-EthylHexylacetatee Methyl Salicylate 2-EthylHexanol 12 H.S.A. Source CAS No Local Local Local/Imported Local/Imported Local Means of storage Drums Drums Drums Drums Drums Means of transport Truck Truck Truck Truck Truck Max. Qty. stored MT

22 Raw Material/ finished goods Homo Menthyl Alcohol Ethyl Acetate Acetic acid Products Octyl Methoxycinnamate Octyl Salicylate Octyl HydroxyStearate Homosalate Ethyl methoxycinnamate Source CAS No Local Local Local product product product product product Means of storage Drums Drums Drums Drums Drums Drums Drums Drums Means of transport Truck Truck Truck Truck Truck Truck Truck Truck Max. Qty. stored MT RESOURCE OPTIMIZATION & AVAILABILITY The major resources for the proposed project are/will be raw-materials, water, man-power, etc LAND & BUILDING REQUIREMENT Total existing plot area is m 2 and total constructed areaa is m 2. No additional land will be required for proposed project expansion. Minor construction and fabrication work will be carried out. Land Possession Document is attached as Annexure EQUIPMENTS Some additional equipment will be needed for the proposed expansion. Table 3.3: List of Equipments Sr. No. Equipments Existing 1 Glass line Reactor (3 KL) 2 SS 316 Reactor (3 KL) 3 SS 316 Distillation Vessel (800L) 4 SS 316 Distillation Vessel (2 KL) 5 SS 316 Reactor (1.5 KL) 6 SS 316 Reactor (2 KL) 7 SS 316 (1 KL) 8 SS 316 Reactor (4 KL) 9 SS 316 Reactor (5 KL ) 10 SS 316 Reactor (6 KL) 11 Advanced Continuous Distillation Unit 12 Nutche Filter 13. Non IBR Boiler Proposed additional 1 Vacuum pumps 2 SS 316 Reactor (5 KL ) 3 SS 316 Reactor (6 KL) 4 Thermic fluid heater (6& 10lakh. k.cal/hrs.) 5 Deep Freezer Chilling Unit No

23 3.6.3 POWER AND FUEL REQUIREMENT Total power requirement for existing project is 125 kva and after proposed expansion it will be kva, sourced from Madhya Gujarat Vij Company Ltd. (MGVCL) In existing 500 kg/ /day Agro waste is used as fuel for non IBR boiler. After proposed expansionn 8000 kg/day Agro waste will be used in proposed Thermic fluid heaters. Diesel will be used as fuel in D.G. Set. Table 3.4: Details of Power & Fuel Sr. No. Power 1 Power Requirement Fuel 1 Particulars Fuel & it s consumptionn Requirement Existing Scenario 125 kva Agro 500 kg/day Phase I 250 kva Agro 8000 kg/day Diesel@ 50 LPH Phase II 250 kva Agro kg/day Diesel@ 50 LPH Source Madhya Gujarat Vij Company Ltd (MGVCL.) Local Suppliers WATER REQUIREMENT For existing project, water is required for domestic, process and utility purpose, whichh is sourced from in house, bore well. Total fresh water requirement for existing project is 4.6KLD which will be 29.0 KLD after phase l and 37.0 KLD after phase II which will be sourced from in house bore well. The category wise bifurcation of the water requirement is given in the Water Balance Data in Table 3.5 Table 3.5: Category-wise Water Requirement (in KL/D) S.No Particulars Domestic Gardening Industrial Process Boiler Cooling (Make-up) washing Sub-Total: Industrial Grand Total Requirement (KLD) Existing scenario After Phase I NIL After Phase II NIL

24 3.6.5 MAN-POWER REQUIREMENT The total number of man power for existing project is 35 persons, for proposed expansionn project additional 20 persons will be required. Hencee the total man-power will be 55 The man-power equired for the project is/ will be employed locally from the nearby areas. Skilled as well as unskilled labour will be employed for the project. Table 3.6: Man Power Requirement Phase of project Existing During operations Phase I During operations Phase II During operations Type of Labour Managerial Skilled Un-skilled Managerial Skilled Un-skilled Managerial Skilled Un-skilled General M No. of workers 1 st Shift M nd Shift M rd Shift M QUANTITY OF WASTE TO BE GENERATED WASTE WATER GENERATION & MANAGEMENT The category wise bifurcation of the waste water generation is given in Table 3.7. Table 3.7:Category-wise Wastewater Generation (in KL/D) S.No Particulars Domestic Industrial Process water Cooling (Blow down) Boiler (Blow down) Washing Sub-Total: Industrial Grand Total Waste Water Generation Existing Scenario After Phase I NIL NIL After Phase II NIL

25 Fig-3.4(a): Water Balance Diagram (in KLD) for Existing Scenario Fig-3.4(b): Water Balance Diagram (in KLD) for Phase - I 24

26 Fig-3.4(c): Water Balance Diagram (in KLD) for Phase II WASTE WATER CHARACTERISTICS The tentative wastewater characteristic of effluent is given below in Table No Table 3.8: Characteristics of Wastewater Sr. No Parameterr ph Suspended Solids (SS) Chemical Oxygen Demand (COD) Biochemical Oxygen Demand (BOD) Oil & Grease Total Dissolved Solids (TDS) Characteristics Untreated Effluent Treated Effluent < < <100 <10 < < WASTE WATER TREATMENT & DISPOSAL In existing operations, the domestic effluent is disposed through septic tank/ soakss pit system and the industrial effluent is provided primary treatment and the treated effluent is used for gardening. After proposed expansion the domestic effluent will be disposed throughh septic tank/ soak pit system. For the industrial effluent from the proposed production activities, necessary maintenance and modifications will be made in the existing ETP. 25

27 The effluent coming from the process, washing and cooling tower blow down will diverted to the collection cum neutralization tank and neutralization will be carried out. After neutralization, the effluent will be pumped out to the primary settling tank; sludge from the bottom of the primary settling tank will be diverted into the sludge drying bed. The overflow of the primary settling tank will be passed through mix bed filter and diverted into the holding tank and the effluent from this tank will either be sent to CETP of EICL or will be evaporated in evaporation unit. The salts/ residue from evaporation unit along with ETP primary sludge will be disposed throughh TSDF site. ETP Scheme: Fig-3.5 (a): Existing ETP flow diagram Fig-3.5 (b): Proposed ETP flow diagram 26

28 3.7.4 AIR EMISSIONS & CONTROL Process Emission There is/will be no process emissions fromthe manufacturing activities Utility Emission In existing scenario, the company has one non IBR boiler. Agro waste is used as fuel in the boiler. Cyclone separator is provided as air pollution control measure with the boiler. For proposed expansion IBR boiler will be replaced by two thermic fluid heaters having capacity of 6 lakh k.cal/hrs& &10 lakh k.cal/hrs. Agro waste will be used as fuel in the thermic fluid heaters. Additionally a D.G. Set of 125 KVA will be installed as standby unit and will be utilized only in case of power failure and Diesel will used as fuel in the D.G. Set. The details regarding utility emissions and control measures are mentioned in the below table no Table 3.9: Details of Utility Emission Particulars Existing scenario Non IBR boiler. Fuel Agro waste Fuel Quantity 500 Kg/day Proposed Scenario for Phase I Thermic fluid heater 2 No.- one of 6 lakh k.cal/hrs and one of 10 lakh kcal/hrs. D.G. Set 125 KVA (Stand by) Agro waste Diesel Kg/day 50 LPH Proposed Scenario for Phase II Thermic fluid heater 2 No.- one of 6 lakh k.cal/hrs and one of 10 lakh kcal/hrs. D.G. Set 125 KVA (Stand by) Agro waste Diesel Kg/day 50 LPH Fugitive Emission APCD Cyclone separator Cyclone separator Cyclone separator Emission Norms PM<150 mg/nm 3 SO 2 < 100 ppm NOx< 50 ppm PM<150 mg/nm 3 SO 2 < 100 ppm NOx< 50 ppm PM<150 mg/nm 3 SO 2 < 100 ppm NOx< 50 ppm PM<150 mg/nm 3 SO 2 < 100 ppm NOx< 50 ppm PM<150 mg/nm 3 SO 2 < 100 ppm NOx< 50 ppm Minor quantity of fugitive emissions will occur during handling of the raw materials. Fugitive emissions are also likely to occur from storage area. 27

29 Following measures will be practiced to reduce the fugitive emissions: Raw Materials & Products are/will be stored in properly designated storage area and under good storage conditions to prevent any volatilities Raw Materials & Products are/will be stored in closed containers The fugitive emissionss in terms of handling losses will get reduced by proper storage and handling. Regular monitoring is/will be done of piping and fittings for checking of any leakages. Hazardous chemicals are/will be stored as per standardd criteria. Good housekeeping will be maintained in the plant HAZARDOUS/NON-HAZARDOUS WASTE MANAGEMENT Hazardous wastess generated is in the form of ETP waste, Distillation residue, spent carbon and used oil Company has provided adequate storage area for proper storage of wastes. The details of the hazardous waste and its management is given in below table 3.10 Table 3.10: Details of Hazardous Waste Generation & Disposal Type of waste & Category ETP Waste (Cat. 34.3) Distillation residuee (Cat.36.4) Spent carbon (Cat 35.3) In organic process waste (Cat. 28.1) Used Oil (Cat. 5.1) Discarded Containers/ bags (Cat. 33.3) Spent solvent (Cat. 20.2) Source ETP Process Process Process Maintenancee Raw material 120 storage Nos/Month Process... Existing 0.04 MT/Month 3.36 MT/ /Yr 0.05 MT/Month KL/Yr After Phase l After Phase ll MT/Month MT/Month 80 MT/Yr 125 MT/Yr MT/Month MT/Month 97 MT/Yr 155 MT/Yr 2.0 KL/Yr 2.5 KL/Yr 9870 Nos./Yr Nos./Yr 210 MT/Yr 325MT/Yr Disposal Method Collection, storage, transportation and disposal to TSDF site. Collection, storage, transportation and disposal by incineration at NECL/GEPIL. Collection, storage, transportation and disposal by incineration Collection, storage, transportation and disposal to TSDF site. Collection, storage, transportation, disposal by selling to registered re- storage, refiners. Collection, transportation, disposal by selling to registered resolvent sell refiners. Spent to the actual users. 28

30 3.7.6 NOISE AND ODOUR CONTROL There is/will be no major activities due to which noise would be generated other than Air compressors, TFH & pumps. However, Noise level generation would be limited to 80 db(a) within plant. The equipments resulting in noise generation is/will be Air compressor and Diesel generator. No offensive odour is/will be generated from the process. The control measures to be taken for reduction in noise levels are as below: Ear Plugs and Ear muffs are provided to the workers in Utility Section. Anti vibration pads and flexible bellows is provided wherever applicable. Acoustic Enclosure to D.G. Set will be provided. Regular maintenance & lubrication shall be done HEALTH AND SAFETY MEASURES The following key safety measures shall be implemented in the proposed project: The industry is responsible for health and safety of the workers. The industry is doing a periodical medical examination of its employees and the health records are maintained. The industry has provided first aid box containing cotton, bandage, soframycine tubes, burnol, dettol, tincture iodine, eyes and eardrops. This is to cure the injuries from chemical burns, eye injuries and electrical shocks. Goggles, Gloves, Gum boots, Helmets, Skin Cream, Earplugs, Face Masks, and clothing are provided to the workers. The industry is taking all precautionary measures to control the hazardous associated with the industry. The industry has providedd good lighting and ventilation arrangements. Fire buckets are provided to withstand the fire or explosion condition. Emergency alarm will be installed for the communication for the emergency condition. Fire extinguishers will be installed wherever necessary. Work place monitoring will be done on regular basis ENVIRONMENTAL HEALTH & SAFETY CELL The company has an environment cell in order to keep a close watch on the performance of the pollution control equipment, emissionss from the sources and the quality of surrounding environment in accordance with the monitoring program. The cell is also entrusted with the responsibilities of regulating the safety measures inside the plant campus. The cell is also responsible for maintaining the records of all data, documents and information in line within the legislative requirement. 29

31 3.7.9 POST PROJECT MONITORING PLAN The company has developedd in-house facilities for monitoring certain components. Where it is not possible to establish such facilities, the same will be done by appointing external recognized/approved agencies. The proposed post-project monitoring plan is given below: Table 3.11: Post Project Monitoring Plan Components Parameters Frequency of in house monitoring Frequency of third party monitoring Drinking water IS-10500: Once in a month Waste water Air-ambient BOD, COD, ph, TSS, TDS SPM, SOx, NOx. VOC Daily (At all ETP) -- stages of Once in a month (treated and untreated) Quarterly Stack monitoring SPM, SO 2, NOx -- Quarterly Noise monitoring db (A) -- Once in a month 30

32 CHAPTER 4 SITE ANALYSIS 4.1 CONNECTIVITY The Industry is located at Plot No. 1088/ /B, Lamdapura road, Village: Manjusar, Ta: Savli, Dist. : Vadodara. This proposed expansion project will be accommodated in the existing site. The site is very well connected by national highway and railway. Efficient transport facilities will be available nearby the project site. 4.2 LAND FORM, LAND USE & LAND OWNERSHIP LAND FORM The proposed expansion is to be carried out in the existing industrial facility LAND USE PATTERN It is a non-agricultural land and developed industrial facility outside notified industrial area. at existing industrial unit located LAND OWNERSHIP The plot is owned by the company. Land ownership document is attached as Annexure TOPOGRAPHY The topography of Vadodaraa is divided into two distinct regions, viz. western regions and the eastern regions. The western region of the city possesses a number of educational institutions, residential complexes, railway station, shopping malls, multiplexes, business districts and modern buildings. The business districtt centers at Alkapuri, Old Padraa Road and R C Duttt Road. The eastern region houses bazaars, various shrines and various shanty buildings. The eastern region also contains some of the landmarks such as Nyay Mandir, Mandvi and Laxmi Vilas Palace and the General Post Office. The eastern bank of river Vishvamitri also houses the fortified city of Vadodara. 31

33 4.4 SALIENT FEATURES The salient features of the project site are given in the table below: Table 4.1: Salient Features of the Project Site Particulars Details Co-ordinates Center: 22 28'02.92"N, 73 12'22.43"E Village Manjusar Taluka/ Tehsil Savli Districtt Vadodara Nearest Water body Mahi River 9.37 km (NW) Nearest Highway State highway 1.16 km (W) Nearest Railway station & Railway line Samlayaa railway station (ENE) Vadodara Railway Station km SSW Nearest Airport/ Airbase Vadodara Airport km (SSE) Ahmedabad Airport km (NW) State/ National borders None within 10 kms Protected Area/ Sanctuaries No CRZ applicability No Seismicity Seismic Zone III (Moderate) Note: All the above mentioned distances are the aerial distance from the project site. 4.5 EXISTING INFRASTRUCTURE The plot is located in village: Manjusar outside notified industrial area. infrastructure is developed by the company itself. The entiree necessary 4.6 CLIMATE & METEROLOGY The climate is characterized by oppressive summer dampness in the atmosphere nearly throughout the year, heavy south west monsoon rainfall and a mild winter. The year can be divided into four seasons. The cold season from December to February is followed by the summer season from March to May. The south-west monsoon season is from June to September. The post-monsoon season constitutes the months of October and November. The Table 4.2 indicates the summary of meteorological pattern at the nearest observatory of IMD, Vadodara published by IMD. 32

34 Table 4.2: Summary of Meteorologicall Data at nearest IMD Station Vadodara Location: At the Physics Department, MS University, Vadodara Gujarat ( Lat: N , Long: E 73 o 15 ) Aerial Dist from Project Site: Approx.16 Km SSW Height of installation: 34 m above MSL, Month Temperature Relativee Cloud Cover Mean Wind Pre-dominant Rainfall (mm) ( o C) Humidity (Oktas) Speed Wind Direction (%) (km/hr) Max. Min. Mor. Eve. Mor. Eve. January February March April May June July August September October November December NE CALM CALM NW SW SW SW SW SW CALM CALM NE Seasonal Average Values Period Temperature Relative Cloud Cover Mean Wind Avg. PDW Total Rainfall (mm) ( o C) Humidity (Oktas) Speed Direction (%) (m/s) Avg. Avg. Avg. Avg. Avg. Avg. Max. Min. Mor. Eve. Mor. Eve. Summer Winter Monsoonn Post monsoonn Annual Total or Mean NW,SW NE SW CALM SW Note: Winter: December, January & February, Summer: March, April & May, Monsoon: June, July, August & September, Post monsoon: October & November (Source: Book Climatological tables of Observatories in India ( ) published by IMD) TEMPERATURE The summer season from March to May is a one of continuous increase in temperatures whichh decreases during monsoons, increasess slightly during the post-monsoon season and again decreases during the winter. The south-wesmonths are generally pleasant. May is generally the hottest month with the mean daily maximum temperature recorded at 40.9 o C and mean daily minimumm temperature recorded at 12.0 o C. January is the coldest month with the mean daily maximumm temperature as 30.3 o C and mean daily minimum temperature observed as 12.0 o monsoon from June to September brings copious rain to the area. The winter C. 333

35 HUMIDITY The climate of the region is characterized by a humid summer because of the closeness to coastline. Humidity is usually high during the monsoon months, with average relative humidity generally exceeding 85%. Humidity decreases gradually during the post-monsooaverage relative humidity ranges around months and for rest of the year i.e. the period of December to April, the 20-70% CLOUD COVER During the South-wescover decreases during the post monsoon months. In the rest of the year the skies are mostly monsoon months, the skies are usually heavily clouded or overcast. Cloud clear RAINFALLL About 95% of the annual rainfall is received during the southwest monsoon season i.e. from June to September, July being the month with highest rainfall. The average annual rainfall observed from the data is mm WIND PATTERN The annual resultant vector for wind direction shows winds blowing from SW. During summer and monsoon, the winds blow mostly from the sea i.e. the NW or SW direction. The winter season experiencee a change in direction, with the winds blowing from NE. The post-monsoonn season experiencee calm winds. The wind speed is high during monsoon and summer seasons, slightly moderate during winter and post monsoon seasons. 4.7 SOCIAL INFRASTRUCTURE The infrastructure available in the study area denotes the economic well-being of the region EDUCATIONAL FACILITIES As per census 2001, Out of 136 villages, all villages have educational facilities, details of whichh are given below. 34

36 Table 4.3: Details of Educational facilities Sr.No Particulars 1. Primary Schools 2. Middle Schools 3. Secondary School 4. Senior Secondary School 5. College (Source: Primary Census s Abstract Census of India, 2001) Observed values in Savli Taluka MEDICAL FACILITIES As per census 2001, Details of medical facilities available in the study areaa are given below. Table 4.4: Details of Medical facilities Sr.No. Particulars 1 Dispensaries 2 Primary Health Centers 3 Primary Health sub centre 4 Allopathic Hospital 5 Allopathic dispensary 6 Maternity and Child welfare Centree 7 Community Health Workers (Source: Primary Census s Abstract Census of India, 2001) Observed values in Savli Taluka

37 CHAPTER 5 PLANNING BRIEF 5.1 PLANNING CONCEPT The proposed project is located at Manjusar, Savli. The nearest city is Vadodara- the third largest city in the Indian State of Gujarat, after Ahmedabadd and Surat. Major raw materials are/will be sourced locally. RM cost as many input suppliers are located nearby which will bring reduction in transportation cost. The region is well planned with all the basic infrastructural facilities like internal roads, water supply, arrangements for power, streetlights, solid waste disposal sites etc. 5.2 POPULATION PROJECTION As per census 2001, the average household size is around 5 persons. The demographic profile of study area within Savli Taluka is presented below. Table 5.1: Distribution of population Sr. No. Particulars 1 Total Population 2 No. of Households 3 Avg. household size (person) 4 Male population 5 Male population (in %) 6 Female population 7 Female population (in %) 8 Sex ratio (Source: Primary Census s Abstract Census of India, 2001) Observed values in Savli Taluka AREA STATEMENT The total area of the plot is m 2 out of which constructed area of the plant is m ASSESMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL) This is an expansion project which is to be developed in the existing premises. No additional land or building is required for the proposed project except few installations and modifications. So there will be no demand of major change in physical infrastructure and social infrastructure. 5.5 AMENITIES/FACILITIES DRINKING WATER FACILITIES As per census 2001 following drinking facilities are available in study region. 36

38 Table 5.2: Drinking Water Facilities Sr. No. Particulars 1 Tap 2 Well water 3 Tank water 4 Tube well water 5 Hand pump 6 River water 7 Canal 8 Lakes 9 Spring 10 Other drinking water sources (Source: Primary Census s Abstract Census of India, 2001) Observed values in Savli Taluka POWER SUPPLY FACILITIES As per census 2001, all the villages have power supply facilities in the study region COMMUNICATION& BANKING FACILITIES As per census 2001, Distribution of facilities such as post office, post & telegraph office, banks, and telephone connections in the study area are illustrated in table below. Table 5.3: Communication & Banking Facilities Sr. No. Particulars 1 Post Office 2 Post and telegraph office 3 Telephone connection 4 Commercial Bank (Source: Primary Census s Abstract Census of India, 2001) Observed values in Savli Taluka TRANSPORT FACILITIES As per census 2001, Bus service is available in all the villages of the study region within Savli Taluka and most preferable mode of transport in the region. Second option for transport is railway; railway line is available in 4 villages. 136villages are connected with paved roads. Theree is 100% electrification in the area APPROACH TO VILLAGES As per census 2001, 109 villages have paved road, 98 villages mud road and 73 villages have foot path. 37

39 CHAPTER 6 PROPOSED INFRASTRUCTURE 6.1 INDUSTRIAL AREAA The total area of the plot is m 2 out of which constructed area of the plant The total production capacity will be 2580 MTA after proposed project. is 1500m RESIDENTIAL AREA In the said proposal no Residential area has been proposed for workers and/or for staff. 6.3 GREENBELT Maximum possible open land is/will be allotted for green belt development. If required, experts will also be consulted for selection of species for the development of the greenbelt. 6.4 SOCIAL INFRASTUCURE Existing infrastructure will be sufficient project which is very low. to accommodate the existing load from the proposed 6.5 CONNECTIVITY This proposed expansion project will be accommodated in the existing site. The site is very well connected by national highway and railway. Efficient transportt facilities will be available nearby the project site. 6.6 DRINKING WATER MANAGEMENT Drinking water is/will be sourced from in house bore well for the proposed project. 6.7 SEWERAGE SYSTEM Domestic waste water generated from the existing and proposed project is/will be disposed offf throughh septic tank/soak pit system, which 1.20KL/D for existing plant 2.0 KL/D after phase I and 2.2 KLD after phase II. 6.8 INDUSTRIAL WASTE MANAGEMENT Industrial effluent generated after proposed project will be treated in ETP, treated water from ETP will be will be sent to EICL/CETP or will be evaporated in evaporation unit. Details are explained in Chapter 03, Section and

40 6.9 SOLID WASTE MANAGEMENT Solid wastes generated are in the form of ETP waste, spent carbon, Distillation residue, used oil and discarded containers from storage of raw materials. Company will provide adequate storage area for proper storage of wastes. Details of solid waste generation are given in table 6.1. Table 6.1: Solid waste generation and disposal Type of waste & Category ETP Waste (Cat. 34.3) Distillation residuee (Cat.36.4) Spent carbon (Cat 35.3) In organic process waste (Cat. 28.1) Used Oil (Cat. 5.1) Discarded containers/ bags (Cat. 33.3) Spent solvent (Cat. 20.2) Source ETP Process Process Process Maintenance Raw material storage Process Existing 0.04 MT/Month 3.36 MT/Yr 0.05 MT/Month KL/Yr 120 Nos/Month... After Phase l After Phase ll 5.5 MT/ /Month 8.5 MT/Month 80 MT/Yr 125 MT/Yr MT/Month MT/Month 97 MT/Yr 155 MT/Yr 2.0 KL/Yr 2.5 KL/Yr 9870 Nos/Yr 15210Nos/Yr 210 MT/Yr 325 MT/Yr Disposal Method Collection, storage, transportation and disposal to TSDF site. Collection, storage, transportation and disposal by incineration at NECL/GEPIL. Collection, storage, transportation and disposal by incineration Collection, storage, transportation and disposal to TSDF site. Collection, storage, transportation, disposal by selling to registered re- storage, refiners. Collection, transportation, disposal by selling to registered resolvent sell refiners. Spent to the actual users POWER REQUIREMENT & SOURCE OF SUPPLY Total power requirement for existing project is 125 KVA and after proposed expansion it will be - 250KVA, sourced from Madhya Gujarat Vij Company Ltd. (MGVCL) 39

41 CHAPTER 7 REHABILITATION &RESETTLEMENT (R &R) PLAN 7.1 POLICY TO BE ADOPTED The proposed project is to be developed in the existing premises.hence, no displacement of any population is proposed for the project. Therefore, detailed Social Impact Assessment studies or R&R action study has not been proposed. 40

42 CHAPTER 8 PROJECT SCHEDULE & COST ESTIMATES 8.1 TIME SCHEDULE OF THE PROJECT At present we are not proposing any additional production at the site. getting all the statutory permission from respective authorities. It will start only after 8.2 ESTIMATED PROJECT COST The company has made budgetary provision for the recurring expenses for the environmental issues and Environment Protection has also been consideredd in planning the cost projection. Green belt development is also considered. The estimated project cost after proposed project will be approximately Rs Lakhs. Table 8.1: Total Capital Cost Projection Sr. No. Purpose Capital Cost (Rs. in Lakhs) Existing Proposed additional Land Building Plant & Machinery Electrification and Administrative set-up Environment Protection (including ETP, APCD etc.) ETP Air pollution control device Safety instruments Chartered services/ Government fees Green belt development TOTAL Total Table 8.2: Recurring cost provision for EHS Sr. No. Purpose Environment Protection (including ETP, APCD etc.) Air pollution control device Fees for Common disposal facilities Env. Monitoring expenses Safety instruments maintenancee Environment & safety training Green belt maintenance Medical surveillancee TOTAL Recurring Cost per annum Existing Proposed additional (in Lakhs) Total

43 CHAPTER 9 ANALYSISS OF PROPOSAL 9.1 FINANCIAL & SOCIAL BENEFITS M/s. Universal Esters Ltd. is located at Plot No. 1088/B, Village: Manjusar, Ta: Savli, Dist: Vadodara. Currently Universal Esters has become one of the leading manufacturers of Personal Care Ingredients in India. With stringent quality standards and good manufacturing practices, Universal has built its reputation as a preferred supplier to companies all over the world. The company focuses on providing quality products to the Personal Care industry. Finally in the days of acute Deficit of Foreign Exchange in our Country, Universal contributed to the earning of Foreign Exchange in Hard Currency. Esters has For the proposed project, the company intends to benefit as Corporate Social Responsibility. donate 2% of the capital cost for the social 42

44 Annexure 1: Existing CC&A A1

45 A2

46 A3

47 A4

48 A5

49 Annexure 2: Land Ownership Document A6

50 A7

51 A8

52 A9

53 A10

54 A11

55 A12

56 A13

57 A14

58 A15

59 A16

PROJECT FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT PROJECT FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For PROPOSED CHEMICAL MANUFACTURING UNIT From M/s. MORADIA BROTHERS CHEM PVT LTD LOCATED AT: Block No.: 45, JalBhumi Industrial Estate,

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat. Pre-Feasibility Study Report For Proposed Fly Ash Co-processing clinker grinding cement Unit of 40,000 MT/month Production capacity within our Existing Premises for M/s. SAL STEEL LTD Survey no.245/p,

More information

PRE-FEASIBILITY REPORT. for

PRE-FEASIBILITY REPORT. for PRE-FEASIBILITY REPORT for PROPOSED COMMON EFFLUENT TREATMETN PLANT (CETP) of M/s. VIKASHTEX ENVIROTECH CETP PVT. LTD. Block No. 523, Village: Hathoda, Taluka: Mangrol, Dist: Surat - 394 405 (Guj.) Prepared

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA 1.0 INTRODUCTION M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA dry type of coal washery at Village: Hindadih, Tehsil: Masturi, District: Bilaspur (C.G.) for which

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED SY. NO. 29, TUPAKULAGUDEM VILLAGE, TALLAPUDI MANDAL, WEST GODAVARI DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED Duplex No. 12,

More information

PRE FEASIBILITY REPORT. For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS. M/s. M.K. DRUGS. F-10, Industrial Area, Focal Point, Tehsil: Derabassi

PRE FEASIBILITY REPORT. For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS. M/s. M.K. DRUGS. F-10, Industrial Area, Focal Point, Tehsil: Derabassi PRE FEASIBILITY REPORT For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS Of M/s. M.K. DRUGS F-10, Industrial Area, Focal Point, Tehsil: Derabassi Dist: Mohali, Punjab INTRODUCTION M/s. M.K. Drugs is

More information

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

PART A. M/s Shree Cement Ltd, (Grinding Unit) village - Udepur, Tehsil- Suratgarh, District -Shri Ganganagar, Rajasthan

PART A. M/s Shree Cement Ltd, (Grinding Unit) village - Udepur, Tehsil- Suratgarh, District -Shri Ganganagar, Rajasthan Page 1 of 9 Environmental Statement for Clinker Grinding Unit of M/s Shree Cement Limited, situated at village - Udepur, Tehsil- Suratgarh, District -Shri Ganganagar, Rajasthan for the Period from: 10

More information

Rajasthan State Pollution Control Board

Rajasthan State Pollution Control Board M/s Raj West Power Private Limited Village- Bhadresh, Tehsil:Barmer District:Barmer Sub: Ref: Sir, Consent to Operate under section 25/26 of the Water (Prevention & Control of Pollution) Act, 1974 and

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For PRIOR ENVIRONMENTAL CLEARANCE STORAGE CAPACITY ENHANCEMENT OF HPCL, LPG BOTTLING PLANT Capacity: 3 X 500 MT At Plot No.499 Kota-Jhalawar Road (NH-12) Village- Mandana, Tehsil-

More information

LIST OF PRODUCTS (PROPOSED) Existing Quantity (MT/Month)

LIST OF PRODUCTS (PROPOSED) Existing Quantity (MT/Month) LIST OF PRODUCTS (PROPOSED) Sr.No. Name of Product Existing Total after expansion 1 Benzyl Acetate 20 50 2 Benzyl Benzoate 20 50 3 Benzyl Alcohol 20 50 4 Benzyl Cyanide 20 50 5 Phenyl Acetic Acid 20 50

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT DR. REDDY S LABORATORIES LTD. CHEMICAL TECHOPS III PLOT NO.116, 116A, 116B & 126C, S.V. CO OP. IND. ESTATE, BOLLARAM VILLAGE, JINNARAM MANDAL, MEDAK DISTRICT, TELANGANA PRE FEASIBILITY REPORT DR. REDDY

More information

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

4. The ambient air quality monitoring stations We are monitoring the ambient air quality GLOBAL CALCIUM PRIVATE LTD., 125&126, SIPCOT COMPLEX, HOSUR 635 126 Ref : No. J-11011/411/2006-IA-II(I) dated 1 st August 2007. Compliance Report for the Period ending 31.3.2015 Sl. Specific Conditions

More information

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT Annexure B Land Possession letters & N.A. permission letters Annexure C Photograph of the Site Annexure D Details of Buildings Area Calculation Annexure 1 Topo Sheet Annexure 2 Soil Analysis Report Annexure

More information

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS 1. Name of the Project: M/s MCC PTA India Corp. Private Limited Haldia ( WB) Note: Company Name was change from MCC PTA India Corp.Private

More information

Prefeasibility Report. 30,000 KLPY Anhydrous (Absolute) Alcohol Manufacturing Plant at Patalganga MIDC

Prefeasibility Report. 30,000 KLPY Anhydrous (Absolute) Alcohol Manufacturing Plant at Patalganga MIDC Prefeasibility Report For 30,000 KLPY Anhydrous (Absolute) Alcohol Manufacturing Plant at Patalganga MIDC of Alkyl Amines Chemicals Limited 401-407 Nirman Vyapar Kendra, Plot No. 10, Sector 17, Vashi,

More information

Max. building height (m)

Max. building height (m) Environmental Management Plan (EMP) for Himalaya Falaknuma by Himalaya Developers Ahmedabad No. Particulars Details 1. Proposal for New Project 2. Type of Project and Commercial Building Construction Project

More information

Consultant: M/s. SADEKAR ENVIRO ENGINEERS PVT. LTD.

Consultant: M/s. SADEKAR ENVIRO ENGINEERS PVT. LTD. Summary For Ria Organics Private Limited, D-26/2, Kurkumbh - MIDC, Taluka - Daund Dist. Pune, Maharashtra, India. Consultant: M/s. SADEKAR ENVIRO ENGINEERS PVT. LTD. Accredited by QCI NABET Lab. Recognized

More information

RED CATEGORY CONSENT & AUTHORIZATION ORDER BY REGISTERED POST WITH ACKNOWLEDGEMENT DUE

RED CATEGORY CONSENT & AUTHORIZATION ORDER BY REGISTERED POST WITH ACKNOWLEDGEMENT DUE ANDHRA PRADESH POLLUTION CONTROL BOARD Paryavarana Bhavan, A-III, Industrial Estate, Sanathnagar, Hyderabad-500 018 Phone : 040-23887500, Website : www.appcb.ap.nic.in RED CATEGORY CONSENT & AUTHORIZATION

More information

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN HALF YEARLY REPORT FOR THE PERIOD OCTOBER, 2011 to MARCH 2012 V. S. Lignite Power Pvt. Ltd. Name of the Project : 1x 135 MW Lignite

More information

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA)

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA) Proposed at: Bonda Industrial

More information

M/s. Jindal Electricity Generation (P) Limited was promoted by Sri Omprakash Agrawal & Associates having other business in the area.

M/s. Jindal Electricity Generation (P) Limited was promoted by Sri Omprakash Agrawal & Associates having other business in the area. 1. INTRODUCTION Executive Summary 1.1 Background: M/s. Jindal Electricity Generation (P) Limited was promoted by Sri Omprakash Agrawal & Associates having other business in the area. 1.2 Proposed Project:

More information

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT JAYPEE NIGRIE SUPER THERMAL POWER PROJECT (A Unit of M/s Jaiprakash Power Ventures Limited) Villages: Nigrie, Tehsil :Sarai District: Singrauli 2014 2015 SUBMITTED M.P. POLLUTION CONTROL BOARD BHOPAL (M.P.)

More information

The unit obtained NOC (CFE) of A.P. Pollution control Board in the year 1988 and started operations.

The unit obtained NOC (CFE) of A.P. Pollution control Board in the year 1988 and started operations. 1. Introduction M/s. Sri Krishna Pharmaceuticals Limited, Unit-III (Formerly Sri Krishna Drugs Limited) was established in the year 1988. It is located at Sy. No. 57, Golkonda kalan, Raikunta (V), shamshabad

More information

Torrent Pharmaceuticals Ltd. Indrad EC Compliance Report

Torrent Pharmaceuticals Ltd. Indrad EC Compliance Report Status of Compliance of stipulated conditions of the Environment Clearance J- 01 It is noted that total water consumption will increase from 1000-1200 m 3 /day to 1200-1300 m 3 /day. Fresh water requirement

More information

Environmental Impact Assessment

Environmental Impact Assessment Environmental Impact Assessment A brief discussion Presented by: Apekshit Solanki Kirti Neetu Yadav Sameera Vishakha Shankar Introduction EIA is a formal process to predict the environmental consequences

More information

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004 Name of the Project: Jaypee Rewa Plant, Unit of M/s Jaiprakash Associates Limited for expansion Of cement production from 2.5 MTPA to 3.5 MTPA at Jaypee Nagar, District Rewa, Madhya Pradesh Project Code:

More information

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A (I) FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR 2013-14 M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) Name & Address of the Owner / Occupier of the Industry Operation or Process

More information

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT EXECUTIVE SUMMARY NAGERCOIL MUNICIPALITY, KANYAKUMARI DISTRICT TWAD BOARD,SEWERAGE DIVISION,NAGERCOIL

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT Capacity enhancement of Sugar Plant at crush rate of 4500 TCD expandable to 8000 TCD For DUDHGANGA VEDHGANGA SAHAKARI SAKHAR KARKHANA LTD. At Bidri, Mouninagar, Tal. Kagal, Dist.

More information

PRE FEASIBILITY REPORT INCREASE IN THE PRODUCTION OF PENTAERYTHRITOL FROM 560 MTM TO 730 MTM & SODIUM FORMATE FROM 336 MTM TO 480 MTM

PRE FEASIBILITY REPORT INCREASE IN THE PRODUCTION OF PENTAERYTHRITOL FROM 560 MTM TO 730 MTM & SODIUM FORMATE FROM 336 MTM TO 480 MTM PRE FEASIBILITY REPORT INCREASE IN THE PRODUCTION OF PENTAERYTHRITOL FROM 560 MTM TO 730 MTM & SODIUM FORMATE FROM 336 MTM TO 480 MTM (PRODUCT IS IN POWDER & SOLUTION FORM) at SIPCOT INDUSTRIAL COMPLEX,

More information

ZZH/CLAB-KSPCB/04/ Environmental Officer,

ZZH/CLAB-KSPCB/04/ Environmental Officer, ZZH/CLAB-KSPCB/04/ 21273 08-12-2014 Environmental Officer, Regional Office, Karnataka State Pollution Control Board Parisara Bhavan, LIG II, B 217 B-1, Main Road, A-16 th Cross Near Hari Om Trust, Habbuwada

More information

Telefax : 011: Dated 1 st March, 2013

Telefax : 011: Dated 1 st March, 2013 F. No. J-11011/263/2012- IA II (I) Government of India Ministry of Environment and Forests (I.A. Division) Paryavaran Bhawan CGO Complex, Lodhi Road New Delhi 110 003 To, Shri Jigar Shah, Director M/s

More information

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD PLOT No. F-1,2,3,8,9,10, ADDL. MIDC, PHASE II, AND GUT NO. 46 & 63, VILLAGE DAREGAON, TEHSIL: JALNA DIST: JALNA, MAHARASHTRA 2014-15 1. Executive

More information

DR. SANJAY V. PATIL HEAD AND TECHNICAL ADVISER DEPARTMENT OF ALCOHOL TECHNOLOGY VASANTDADA SUGAR INSTITUTE, MANJARI, PUNE (INDIA)

DR. SANJAY V. PATIL HEAD AND TECHNICAL ADVISER DEPARTMENT OF ALCOHOL TECHNOLOGY VASANTDADA SUGAR INSTITUTE, MANJARI, PUNE (INDIA) DR. SANJAY V. PATIL HEAD AND TECHNICAL ADVISER DEPARTMENT OF ALCOHOL TECHNOLOGY VASANTDADA SUGAR INSTITUTE, MANJARI, PUNE (INDIA) Email: sv.patil@vsisugar.org.in AIDA Technical Seminar www.vsisugar.com

More information

PROPOSED TERM OF REFERENCE

PROPOSED TERM OF REFERENCE PROPOSED TERM OF REFERENCE FOR ESTABLISHMENT OF PROPOSED MOLASSES/GRAIN BASED DISTILLERY HAVING CAPACITY: 160.0 KLD (MOLASSES BASED) OR 120.0 KLD (MOLASSES BASED) + 40.0 KLD (GRAIN BASED) ALONGWITH 7.0

More information

M/s.Aarti Industries Limited (Apple Organics Division), Vapi.

M/s.Aarti Industries Limited (Apple Organics Division), Vapi. EXECUTIVE SUMMARY M/s. Aarti Industries Limited (Apple Organics Division) first obtained CCA order 3431, issued on 16/08/2004. Further it was extended by CCA order no. AWH-73091 dated 14/09/2015 for manufacturing

More information

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. 20. Karnavati Premier Living F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. Screening & scoping / appraisal Details of the proposed project as presented before the committee

More information

Waste to Energy. Biogas Production Utilizing Palm Oil Mill Effluent (POME) in Indonesia

Waste to Energy. Biogas Production Utilizing Palm Oil Mill Effluent (POME) in Indonesia Waste to Energy Biogas Production Utilizing Palm Oil Mill Effluent (POME) in Indonesia Background Sundar Bajgain Senior Advisor, SNV Palm oil mills are one of the most important agro-industries in Indonesia

More information

Molvan- Chhamuchhal Group Gram Panchayat. Taluka- Mangrol, District- Surat. Ph. No

Molvan- Chhamuchhal Group Gram Panchayat. Taluka- Mangrol, District- Surat. Ph. No Serial Number FORM 1 (Application for Environment Clearance Certificate) Item 1. Name of the project/s 2. S. No. in the schedule 3. Proposed capacity/ area/ length/ tonnage to be handled/ command area/lease

More information

INTRODUCTION. Installed Capacity: The total installed capacity of the plant for the product will be as per details given below:- PRODUCT:

INTRODUCTION. Installed Capacity: The total installed capacity of the plant for the product will be as per details given below:- PRODUCT: INTRODUCTION Himalaya Alkalies& Chemicals ltd will setup Caustic soda Plant of 400 MTPD. The Plant site is situated in Village Johron, Kala Amb, Tehsil Nahan, District Sirmaur, Himachal Pradesh. It is

More information

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area.

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area. PROJECT BRIEF PROJECT LOCATION: - Pahar Kua Marble Range Mining Project Q L No 235 is located near village Pahar Kua, Tehsil Makrana., District Nagaur Rajasthan. Project is approachable from national highway.

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT for PROPOSED EXPANSION OF DISTILLERY of M/s. SHREE GANESH KHAND UDYOG SAHKARI MANDLI LTD. Shri Harisinhji Mahida Bhavan, At & Po: Vataria, Tal: Valia, Dist: Bharuch, Gujarat-393001

More information

Form V is to be filled before 30th September annually; for the period from 1st April to 31st March PART A. Company Information

Form V is to be filled before 30th September annually; for the period from 1st April to 31st March PART A. Company Information Form V is to be filled before 30th September annually; for the period from 1st April to 31st March PART A Company Information Company Name : Facility Name : Person Name * : Designation * : Premise Name

More information

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) HINAUTI LIMESTONE MINE Mine Lease area 378.261 ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) 2012-2013 SUBMITTED TO M.P.POLLUTION CONTROL BOARD BHOPAL (M.P.) Jaypee Sidhi Cement

More information

PERFORMANCE EVALUATION OF 9 MLD SEWAGE TREATMENT PLANT AT GURGAON AND COST EFFECTIVE MEASURES IN TREATMENT PROCESS

PERFORMANCE EVALUATION OF 9 MLD SEWAGE TREATMENT PLANT AT GURGAON AND COST EFFECTIVE MEASURES IN TREATMENT PROCESS PERFORMANCE EVALUATION OF 9 MLD SEWAGE TREATMENT PLANT AT GURGAON AND COST EFFECTIVE MEASURES IN TREATMENT PROCESS Mohan Singh Negi and Vaishali Sahu Department of Civil and Environment Engineering, The

More information

A. INTRODUCTION PREFEASIBILITY REPORT

A. INTRODUCTION PREFEASIBILITY REPORT A. INTRODUCTION a. BRIEF DESCRIPTION OF PROJECT M/s Bharat Petroleum Corporation Limited has set up the Haldia Coastal Installation at HAL-733, Patikhali, Durgachak, Haldia 721602, West Bengal. The Depot

More information

Ministry of Environment and Forests Notification New Delhi, the 4 th February ( As amended up to )

Ministry of Environment and Forests Notification New Delhi, the 4 th February ( As amended up to ) Ministry of Environment and Forests Notification New Delhi, the 4 th February 2011. ( As amended up to 2.7.2011) (Amendment carried out vide notification no. S.O. 1527 (E) dated 2.07.2011 have been shown

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

ENVIRONMENTAL MONITORING PROGRAMME

ENVIRONMENTAL MONITORING PROGRAMME Stage-I (2x800 MW) Page 1 5 CHAPTER - VI ENVIRONMENTAL MONITORING PROGRAMME 6.0 OBJECTIVES Regular monitoring program the environmental parameters is essential to take into account the changes in the environment.

More information

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any;

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any; TERMS OF REFERENCE 1.0 PROPOSED SCOPE OF WORK FOR EIA STUDY The components of the EIA study include: Determination of baseline data using primary data generation and secondary data available from various

More information

Welcome To Our Exhibition

Welcome To Our Exhibition Welcome To Our Exhibition Welcome to the exhibition of our proposals for a Waste Recycling and Renewable Energy Facility Distributed Renewable Energy Networks Ltd (DRENL) propose to develop a 10MW Waste

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

The Chemical Industry and Climate Change. A Snapshot from India

The Chemical Industry and Climate Change. A Snapshot from India The Chemical Industry and Climate Change A Snapshot from India B.H. Rahill Lead Environmental Specialist South Asia Environment June 14, 2006 Presentation Outline The Indian Situation (Part of) LBNL Benchmarking

More information

MATERIAL SAFETY DATA SHEET. Polypropylene

MATERIAL SAFETY DATA SHEET. Polypropylene MATERIAL SAFETY DATA SHEET Polypropylene (PP) SECTION 1 CHEMICAL PRODUCT AND COMPANY Chemical Name & Synonyms : Polypropylene (PP) Copolymer Chemical Family : Polyolefin C.A.S. No. : 9010-79-1 Formula

More information

MIDC, Nagpur Expansion of Existing Butibori Industrial Area (BIA Phase II) - Form-1

MIDC, Nagpur Expansion of Existing Butibori Industrial Area (BIA Phase II) - Form-1 ANNEXURE I SITE LOCATION MAP Building Environment (India) Pvt. Ltd 1 ANNEXURE II LAYOUT PLAN Building Environment (India) Pvt. Ltd 2 ANNEXURE III LAND DETAILS Sr. No. LAND DETAILS (In Ha.) 1. LARGE SIZE

More information

PROJECT REPORT FOR MANUFACTURING THINQ PHARMA CRO LTD PITHAMPUR -3 BADGAON MADHYA PRADESH

PROJECT REPORT FOR MANUFACTURING THINQ PHARMA CRO LTD PITHAMPUR -3 BADGAON MADHYA PRADESH PROJECT REPORT FOR MANUFACTURING THINQ PHARMA CRO LTD PITHAMPUR -3 BADGAON MADHYA PRADESH CONTENTS 1. INTRODUCTION 2. GENERAL SECTION 3. PARTICULARS OF PROJECT 4. COST OF PROJECT AND MEANS OF FINANCING

More information

Total 127 files quick download in editable form by e delivery

Total 127 files quick download in editable form by e delivery Sr. No. A. The Total Editable Document kit has 9 main directories as below. List of Directory Document of Details 1. Environmental Manual 14 files in Ms. word 2. Environmental Procedures 07 procedures

More information

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server.

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server. Environmental Clearance Point Wise Half Yearly Compliance Report (October 2014 to March 2015) Cement Plant - EC No: F.No. J-11011/450/2007-IA II(I) Dated: 24 th March 2008 A. SPECIFIC CONDITIONS : S.NO.

More information

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The Groups cement facilities are located in

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT (Proposed Expansion of Inorganic Compounds to Inorganic Compounds & Fine Chemicals Manufacturing Unit) of M/s. Vishnu Chemicals Limited Plot No. 18-26, Industrial Estate, Nandini

More information

PRE FEASIBILITY REPORT PROPOSED CONSCTRUCTION BUILDING PROJECT

PRE FEASIBILITY REPORT PROPOSED CONSCTRUCTION BUILDING PROJECT PRE FEASIBILITY REPORT FOR PROPOSED CONSCTRUCTION BUILDING PROJECT (BUILT UP AREA: 77420.15 SQ. M) BY AMC EWS HOUSING PROJECT RESIDENTIAL BUILDING & COMMERCIAL PROJECT F. P. NO. 174, T.P. NO. 32, GOTA,

More information

LATEST GUIDELINES & DIRECTIVES OF POLLUTION BOARDS FOR DISTILLERS VIDE THEIR CIRCULAR DATED 2 nd JUNE 2017

LATEST GUIDELINES & DIRECTIVES OF POLLUTION BOARDS FOR DISTILLERS VIDE THEIR CIRCULAR DATED 2 nd JUNE 2017 By K.P.SINGH LATEST GUIDELINES & DIRECTIVES OF POLLUTION BOARDS FOR DISTILLERS VIDE THEIR CIRCULAR DATED 2 nd JUNE 2017 1. Distilleries to install Online Mass Flow Measurement with online data transfer

More information

CHAPTER 3 STUDY OF EXISTING COMMON BIO-MEDICAL WASTE TREATMENT FACILITY (CBMWTF)

CHAPTER 3 STUDY OF EXISTING COMMON BIO-MEDICAL WASTE TREATMENT FACILITY (CBMWTF) 101 CHAPTER 3 STUDY OF EXISTING COMMON BIO-MEDICAL WASTE TREATMENT FACILITY (CBMWTF) 3.1 GENERAL CBMWTF was established at Chettipalayam which is reasonably far away from the residential and sensitive

More information

Chemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu

Chemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu Chemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu Compliance Report for Environmental Clearance No.11.63/2005.1A.III dated 19.12.2005 Specific Conditions

More information

.in Dated 9th August, Sharma ;

.in Dated 9th August, Sharma  ; F. No. J-11011/151/2010-IA II (I) Government of India Ministry of Environment and Forests (I.A. Division) Paryavaran Bhawan CGO Complex, Lodhi Road New Delhi -110 003.. To, Ankleshwar E-mail: pb.rastoai@nic.in

More information

M/S. LEVIN DÉCOR LLP.

M/S. LEVIN DÉCOR LLP. M/S. LEVIN DÉCOR LLP. (New Proposed Project for RESIN Production) (Phenol Formaldehyde Resin-300 MT/month Melamine Formaldehyde Resin -150 MT/month Phenol Urea Formaldehyde Resin -100 MT/month) Survey

More information

Pre Feasibility Report

Pre Feasibility Report Pre Feasibility Report For 20 MLD Common Effluent Treatment Plant (ZLD) With Recycling of Treated Waste Water For Textile Processing Industries At TDK Green Enviro Private Limited Village Tadkeshwar, Taluka

More information

Environmental Impact Assessment for TASNEE Petrochemicals Ethylene and Polyethylene Projects

Environmental Impact Assessment for TASNEE Petrochemicals Ethylene and Polyethylene Projects Environmental Impact Assessment for TASNEE Petrochemicals Ethylene and Polyethylene Projects ATTACHMENT 3: This document contains proprietary information belonging to Fluor B.V., its parent and/or affiliated

More information

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED HALF YEARLY PROGRESS REPORT ON IMPLEMENTATION OF ENVIRONMENTAL CLEARANCE CONDITION BY MoEF (PERIOD FROM OCTOBER 13 TO MARCH 14) HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED SIX MONTHLY

More information

DETERGENT POWDER & CAKE

DETERGENT POWDER & CAKE Profile No.: 18 NIC Code: 20233 DETERGENT POWDER & CAKE 1. INTRODUCTION Washing materials are made from different types of natural and synthetic raw materials. Soaps derived from vegetable oils were used

More information

Pre-Feasibility Report. for. Proposed Construction project of Santnagari

Pre-Feasibility Report. for. Proposed Construction project of Santnagari Pre-Feasibility Report for Proposed Construction project of Santnagari at Survey No. 1439, Near Dharoi Dam, Village Mahor, Taluka Vadali, District Sabarkantha, Gujarat By Gujarat Pavitra Yatradham Vikas

More information

FEASILBLITY REPORT. CONVERSION OF PAPL Facility to produce POLYOLS

FEASILBLITY REPORT. CONVERSION OF PAPL Facility to produce POLYOLS FEASILBLITY REPORT CONVERSION OF PAPL Facility to produce POLYOLS Petro Araldite Pvt. Ltd (PAPL) was set up in the year 1996 as joint venture between Ciba India Limited (part of the Swiss Ciba Geigy group

More information

Sandipbhai Shankarbhai Patel

Sandipbhai Shankarbhai Patel Minor Mineral Ordinary Sand Mine (Existing Project) Village : Oze, Ta : Karjan, Dist : Vadodara (Gujarat) Production Capacity : 9000 TPM Area : 04-33-52 Ha. Proposal For Environmental Clearance (Category

More information

Profile No.: 40 NIC Code: CASEIN FROM MILK

Profile No.: 40 NIC Code: CASEIN FROM MILK Profile No.: 40 NIC Code: 10797 CASEIN FROM MILK 1. INTRODUCTION: Casein is the major protein in cows and buffalo milk, and comprises about 80 % of the total protein content of which the rest, some 20

More information

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited)

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited) Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited) Introduction: Jaypee Group is the 3 rd largest cement producer in the country. The groups cement facilities are located

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS 1. LAND ENVIRONMENT QUERY 1.1 Will the existing land use get significantly altered from the project that is not consistent with the surroundings? Attach Maps

More information

WASTEWATER PROBLEMS ASSOCIATED WITH SOLVENTS

WASTEWATER PROBLEMS ASSOCIATED WITH SOLVENTS WASTEWATER PROBLEMS ASSOCIATED WITH SOLVENTS James L. Walsh, Jr., P.E. Senior Research Engineer Georgia Tech Research Institute Atlanta, Georgia 30332 Introduction There a number of advantages to elimination

More information

Compliance of Environmental Clearance SEIAA/GUJ/EC/8(a)/251/2012 Dated (Period April 2016 to September 2016)

Compliance of Environmental Clearance SEIAA/GUJ/EC/8(a)/251/2012 Dated (Period April 2016 to September 2016) Compliance of Environmental Clearance SEIAA/GUJ/EC/8(a)/251/2012 Dated 06.09.2012 (Period April 2016 to September 2016) Sr. No. Conditions Compliance status A. Specific Conditions A.1 Water 1. The fresh

More information

2. A SURVEY OF EFFLUENT TREATMENT PLANTS IN TANNING INDUSTRIES AROUND TIRUCHIRAPPALLI

2. A SURVEY OF EFFLUENT TREATMENT PLANTS IN TANNING INDUSTRIES AROUND TIRUCHIRAPPALLI 2. A SURVEY OF EFFLUENT TREATMENT PLANTS IN TANNING INDUSTRIES AROUND TIRUCHIRAPPALLI 2.1. INTRODUCTION Currently, the overall share of India in the global leather trade is around 3% (ITC, 1999). There

More information

Essidev SA Trading as Organic Lens Manufacturing IPPC License P Annual Environmental Report 2008

Essidev SA Trading as Organic Lens Manufacturing IPPC License P Annual Environmental Report 2008 ESSIDEV SA T/A ORGANIC LENS MANUFACTURING IPPC Licence P-0061-03 Essidev SA Trading as Organic Lens Manufacturing IPPC License P0061-03 Annual Environmental Report 2008 2 Contents Section 1 INTRODUCTION

More information

Industrialization of Green Chemistry: Opportunities & Barriers

Industrialization of Green Chemistry: Opportunities & Barriers Industrialization of Green Chemistry: Opportunities & Barriers Awareness of Green Chemistry & Engg. for Plant & Production Managers 16 th October 14 Ankleshwar Nitesh H. Mehta Green ChemisTree Foundation

More information

Questionnaire for OSH assessment in tanneries

Questionnaire for OSH assessment in tanneries Questionnaire for OSH assessment in tanneries Date of audit: COMPANY INFORMATION General Name of Company INDIAN LEATHER INDUSTRY FOUNDATION F-2, Shreyas. No.87, Greenways Lane, Greenways Road, Chennai

More information

ENVIRONMENTAL AUDIT REPORT [STATEMENT] CONSTRUCTION WORK [ HALF YEARLY ] PERIOD OCTOBER 2012 TO MARCH 2013 FOUNDRY PARK

ENVIRONMENTAL AUDIT REPORT [STATEMENT] CONSTRUCTION WORK [ HALF YEARLY ] PERIOD OCTOBER 2012 TO MARCH 2013 FOUNDRY PARK ENVIRONMENTAL AUDIT REPORT [STATEMENT] ON CONSTRUCTION WORK [ HALF YEARLY ] PERIOD OCTOBER 2012 TO MARCH 2013 FOUNDRY PARK HOULI BAGAN, RANIHATI AMTA ROAD, HOWRAH Prepared by: FOUNDRY CLUSTER DEVELOPMENT

More information

Country Questionnaire Prior to the Senior Officials Meeting on the 3R Initiative - INDIA -

Country Questionnaire Prior to the Senior Officials Meeting on the 3R Initiative - INDIA - Country Questionnaire Prior to the Senior Officials Meeting on the 3R Initiative - INDIA - [Country Questionnaire Survey] 1. Major developments regarding the strategies, policies and activities on the

More information

Realities & Opportunities in Industrialization of Green Chemistry

Realities & Opportunities in Industrialization of Green Chemistry Realities & Opportunities in Industrialization of Green Chemistry Green Chemistry & Engineering for Pharmaceutical Industry February 05, 2013 Hyderabad Nitesh H. Mehta Newreka Green-Synth Technologies

More information

Nadeem Shakir Qatar Petroleum. The 2nd Joint Qatar Japan Environmental Symposium, QP JCCP The 21st Joint GCC Japan Environmental Symposium

Nadeem Shakir Qatar Petroleum. The 2nd Joint Qatar Japan Environmental Symposium, QP JCCP The 21st Joint GCC Japan Environmental Symposium Nadeem Shakir Qatar Petroleum Scheme of Presentation General Overview of QP Refinery, Mesaieed. Challenges in Treatment Existing Waste Water Treatment Facilities Capacity Expansion and Upgradation of WWTP

More information

Major changes proposed in the Bio- Medical Waste Management Rules, 2016 and its likely implication

Major changes proposed in the Bio- Medical Waste Management Rules, 2016 and its likely implication Major changes proposed in the Bio- Medical Waste Management Rules, 2016 and its likely implication Bio- Medical Waste (Management and Handling) Rules, 2011 Title Bio- Medical Waste (Management and Handling)

More information

CONCEPTUAL PLAN. M/s. APOLLO HOSPITALS ENTERPRISE LTD., (Construction of Oncology Block)

CONCEPTUAL PLAN. M/s. APOLLO HOSPITALS ENTERPRISE LTD., (Construction of Oncology Block) CONCEPTUAL PLAN of M/s. APOLLO HOSPITALS ENTERPRISE LTD., (Construction of Oncology Block) Sy. No. 68P & 76, Health City, Chinagadila (V), Visakhapatnam District Andhra Pradesh Prepared by SV ENVIRO LABS

More information

Total 155 files quick download in editable form by e delivery

Total 155 files quick download in editable form by e delivery Chapter-1.0 CONTENTS OF ISO 9001:2015 (MANUFACTURING) DOCUMENT KIT (More than 155 document files) 6. A. The Total Editable Document kit has 9 main directories as below. Sr. No. List of Directory Document

More information

Case Study Stabilization of Effluent Treatment Plant

Case Study Stabilization of Effluent Treatment Plant Case Study Stabilization of Effluent Treatment Plant Version 1.0: March 2014 Page 1 CASE STUDY STABILIZAION OF EFFLUENT TREATMENT PLANT Project Name: Stabilization of Effluent Treatment Plant - Brewery

More information

STANDARD OPERATING PROCEDURE

STANDARD OPERATING PROCEDURE STANDARD OPERATING PROCEDURE Consent to Established/Operate Procedural Guidelines Consent to Establish NOC Check List Consent to Operate NOC Check List Renewal to Consent to Operate Check List Time Frame

More information

Table 1 Population in MBMC

Table 1 Population in MBMC EXECUTIVE SUMMARY 1.1 Existing status of physical infrastructure Mira Bhayandar which is part of Thane district is located at the northern threshold of greater Mumbai between 18 2'N 20 20'N latitude and

More information

Ingredient CAS Number Weight % ACGIH TLV PEL STEL Trichloroisocyanuric acid

Ingredient CAS Number Weight % ACGIH TLV PEL STEL Trichloroisocyanuric acid MSDS Document Page 1 of 5 Product 1. Chemical Product and Company Identification Product Manufacturer Haviland Consumer Products, Inc. 421 Ann Street N.W. Grand Rapids, MI 49504 Phone Number (616) 361-6691

More information

A MODEL FOR EFFICIENT RESOURCE UTILIZATION: DEVELOPMENT AND VALIDATION. Abstract

A MODEL FOR EFFICIENT RESOURCE UTILIZATION: DEVELOPMENT AND VALIDATION. Abstract A MODEL FOR EFFICIENT RESOURCE UTILIZATION: DEVELOPMENT AND VALIDATION B.V. Babu 1 * and V. Ramakrishna 2 Birla Institute of Technology & Science Pilani 333031 Abstract The population growth is increasing

More information