The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening;

Size: px
Start display at page:

Download "The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening;"

Transcription

1 5 TRAFFIC AND TRANSPORT 5.1 SUMMARY OF RESIDUAL IMPACTS The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening; be outside of the am and pm peaks when the road network is substantially under capacity; and only be a temporary impact. The movement of operational vehicles will be minimal and any increases over the IHT guidelines, as stated in TAN 18, are not significant as they are outside of peak times, when the roads are under capacity. Finally, mitigation measures are detailed to minimise impacts from the construction and operation of the proposed development. As such there are not considered to be any significant impacts arising from either construction or operational traffic and transport. 5.2 INTRODUCTION This section of the Environmental Statement (ES) provides an assessment of the predicted construction and operational traffic impacts of the proposed scheme. Specifically, it describes the existing traffic conditions, the access routes for the transportation of materials to the site during the construction phase, and the estimated impact of the construction workers and operational traffic. The section first describes the assessment methodology and scope of the study. This is followed by a review of current national, regional and local policies that are relevant for the proposed scheme. A baseline assessment of the current conditions is then provided followed by an analysis of the potential impacts of the construction and operation of the scheme on the existing baseline conditions. Finally, mitigation measures are described and taken into account within the assessment of residual impacts. 5.3 ASSESSMENT SCOPE AND METHODOLOGY Study Area The site is located near several high capacity roads and major routes, specifically the M4 which links Baglan Bay to Swansea, West Wales, Cardiff 5-1

2 and Bristol and runs immediately to the east and north west of the site (see Figure 5.1) Significance Criteria and Definitions The assessment methodology in this section has been carried out in accordance with the principles of Planning Policy Wales (1), TAN 18 and the Wales Spatial Plan. The following types of potential impacts were assessed for this section: changes in traffic conditions and their potential for delays and congestion; and pedestrian and cyclist conditions and their potential conflict with road traffic. The method of assessing the impacts of construction and operation of the scheme on traffic and transport involves: describing the existing transport network, existing road traffic flows and the receptors that are potentially sensitive to traffic and transport impacts; identifying the future baseline conditions based on factored survey information and the expectations of public transport; predicting the traffic impacts that are likely to arise during the construction and operation of the development using, as appropriate, Institution of Highways and Transportation (IHT) guidance and consultation guidance on Transport Assessment; and identify measures to mitigate any predicted impacts. ( 1 ) National Assembly for Wales, Planning Policy Wales, March

3 CLIENT: Construction Route Red Line Boundary 0. Metres 500 APCL SIZE: A4 ERM Llandarcy House 11A The Courtyard Llandarcy Swansea Bay, SA10 6EJ Tel: Fax: SOURCE: Reproduced from Ordnance Survey digital map data. Crown copyright, All rights reserved License number PROJECTION: British National Grid TITLE: Figure 5.1 Construction Route DATE: 29/05/2008 CHECKED: SD PROJECT: DRAWN: CO SCALE: 1:25,000 DRAWING: APPROVED: SD ConstructionRoute.mxd REV: 1 File: BaglanBayGIS\mxds\NewB oundary_es\constructionroute.mxd KEY:

4 5.3.3 Assessment Criteria The guidance from Technical Advice Notice 18 has been used to consider the need for a full Transport Assessment. As the construction period is short and there will be negligible operational traffic, a full Transport Assessment is not considered to be necessary. Where there are residential properties or other sensitive receptors near roads, guidance provided by the former Institute of Environmental Assessment (1) (now the Institute of Environmental Management and Assessment, IEMA), suggests that significant traffic-related environmental impacts, such as air quality and noise as assessed in Chapters 8 and 12 respectively, may occur if: traffic generated by the development increases baseline traffic flows by more than 30%; or site-related HGV traffic increases HGV flows by more than 30%. The Institution of Highways and Transportation (IHT) (2) suggest that significant impacts to highway capacity may occur if: peak hour traffic flow increases by more than 10%; or peak hour traffic flow increases by more than 5% (where the network is sensitive). Although the above criteria are designed for assessing the long term traffic impacts, they will also be used for the assessment of the impacts of construction traffic. In the absence of criteria specifically for the assessment of construction traffic impacts on traffic conditions, a common sense approach and professional judgement will be used to identify whether or not an impact may occur in the event of an exceedance of criteria. These criteria are not prescriptive and consideration needs to be given to local conditions, existing flows and the short-term nature of any potential impacts in determining the likely magnitude of traffic impacts Construction Construction activities for the proposal will be undertaken between summer 2011 and autumn 2013 for a maximum of 30 months for Stage 1. In addition to this, elements of Stage 2, such as the civil and building works will be executed at the same time as Stage 1. Construction activities to complete Stage 2 will be undertaken between summer 2015 and autumn 2016 for a maximum of 18 months. Construction traffic is likely to be generated by the following activities: (1) Institute of Environmental Assessment (1993) Guidelines for Environmental Assessment of Road Traffic, Guidance Notes No 1, IEA. (2) The Institution of Highways and Transportation (1994), Guidelines for Traffic Impact Assessment, IHT 5-4

5 5.3.5 Operation construction workers accessing and egressing worksites; the supply of construction materials; delivery of equipment items; the removal of waste; the mobilisation of plant; and other activities, including visitors and service vehicles. The assessment will examine the impact of the scheme in terms of the magnitude of change of both total traffic and HGV flows generated by its construction. As noted, a change in excess of 10% (5% in sensitive locations) will be considered as potentially significant (with respect to road capacity), taking into account professional judgement. Combined with this aspect is the length of time the likely disruption will be maintained. The overall objective of this assessment is to ascertain the potential impacts of the development on the existing road network. Operational traffic is likely to be generated by the following activities: Data Sources operational workers accessing and egressing the site; and any significant maintenance work. The assessment considers the effects of the operational traffic generated on the existing traffic flows. The impact of the total number of operational vehicles will be assessed throughout the working day. Two way, 24 hour traffic flow counts from 2005 (adjusted to 2007) and projected counts for 2012, were obtained from Neath Port Talbot County Borough Council. 5.4 LEGISLATION AND POLICY REVIEW Introduction Transport Policy for the area is guided by a range of policies at the national, regional and local level. The way in which the proposed scheme accords with policy is described in Chapter 3 Planning Policy Context. National, regional and local policies have been described below, with particular emphasis placed on sustainable transport and accessibility. 5-5

6 5.4.2 National Regional Technical Advice Note (TAN) 18 Planning Guidance Wales 1998 and March The technical advice notes have been produced as supplementary to Welsh Planning Policy. It is a comprehensive document and it aims to provide a technical update on previous planning policy guidance. The document identifies the need for an effective, efficient and sustainable transportation system and that this can only arise from the full integration of land use planning and the development of transport infrastructure. Wales 2040 A Vision for Transport This 2004 document summarises the pressures and opportunities that are relevant to aspects such as land use, environment, network capacity and infrastructure, focussing on the problems Wales faces in terms of increasing accessibility whilst reducing the need to travel through improved land use and technology. Additionally, the document establishes that urban areas will need to be provided with additional public transport capabilities to increase levels of service through improved use of existing and future infrastructure and systems. People, Places, Future The Wales Spatial Plan, November 2004 The Wales Spatial Plan is a comprehensive plan outlining location specific strategies for each key region. The plan describes the vision for the Swansea Bay Waterfront and Western Valleys: An area of planned sustainable growth and environmental improvement, realising its potential, supported by integrated transport within the area and externally and spreading prosperity to support the revitalisation of West Wales. (Chapter 3, Page 54) The plan outlines the objectives for the area to achieve sustainable accessibility. One such objective is to enhance the transport links between the inland communities and the coast to improve the links within the region. This is combined with improving the links within the area to make it appropriate for its needs. South West Wales Integrated Transport Consortium (SWWITCH) SWWITCH was formed in 1998 and is an alliance between four local authorities in South West Wales. SWWITCH has a vision that it will: improve transport and access within and beyond the region to facilitate economic development and the development and use of more sustainable and healthier modes of transport. (Chapter 4, Page 15, Paragraph 2) 5-6

7 5.4.4 Local SWWITCH is designed to develop an integrated transport strategy for the region and it covers all forms of transport whilst combining the role of land use planning and a range of behavioural change options. Neath Port Talbot County Borough Adopted Unitary Development Plan, March 2008 The Neath Port Talbot County Borough Unitary Development Plan (NPTCBUDP) sets out the Council s policies and proposals for development and land use. The purpose of the NPTCBUDP is to guide development, conservation and land use up to 2016, which is the estimated date for the completion of the proposed development at Baglan Bay. The central themes of the draft NPTCBUDP are the principles of sustainability and community development aimed at rejuvenating the region whilst not detracting from its future potential. The NPTCBUDP emphasises the need for development to be integrated. The Neath Port Talbot County Borough Council strategy is designed to:..achieve an integrated and comprehensive transport system. The need to reduce dependency upon the car, and encourage alternative modes of travel which have less environmental impact is a major commitment. (Chapter 12, Page 131) The policies within the NPTCBUDP emphasise the desire of Neath Port Talbot County Borough Council to develop an integrated and flexible transport strategy aimed at encouraging sustainable development. The policies encourage the improvements on diverse transportation routes as it seeks to promote a multimodal transport system that considers the needs of all sections of the community through Policy T3 in the NPTCBUDP. Neath Port Talbot Community Plan The Neath Port Talbot Community Plan was produced, as required by the Local Government Act 2000, in 2005, and identifies seven significant action areas. One of these key areas was transport and the plan proposes that the transport system should: be accessible to all, both physically and in terms of information; enable businesses to operate efficiently; be convenient and safe; and encourage sustainable forms of transport. There are a number of guiding principles of the community plan. These include sustainable development, social inclusion and equal opportunities. Integration of the underlying principles and the key action areas will make sure that the aims and objectives are complied with. 5-7

8 5.4.5 Policy Summary The policies and strategies from a range of national, regional and local sources establish that there is a significant level of support for establishing sustainable and integrated transport solutions. 5.5 BASELINE CONDITIONS Existing Road Network The site is located near several high capacity roads and major routes. The M4 which links Baglan Bay to Swansea, West Wales, Cardiff and Bristol runs immediately to the east and north west of the site. The site will be approached from Junction 41 of the M4, where it joins the A48. Traffic will run north west along the A48 to Baglan until it reaches the roundabout joining the A4241 Seaway Parade. It will then run south west along the A4241 Seaway Parade until it reaches the initial roundabout on the A4241 Seaway Parade and then turn north west into the Baglan Energy Park (see Figure 5.1) Baseline Data Collection Baseline data was obtained from Neath Port Talbot County Borough Council. Additionally, a site visit was carried out to assess the access routes to the site Baseline Traffic Flows Baseline traffic flow data was taken in 2005 and factored up to 2007 levels at the following locations: the M4 between slips; J41 West Side of Slip Roads to Sunnycroft; the A4241 Baglan Link before the Energy Park Roundabout; and the access road to the Energy Park. The baseline flows are shown in Table 5.1, the am peak being and pm peak being

9 Table Baseline Two-way Traffic Flow Hour M4 between slip roads M4 J41 west side slip road A4241 South of Sunnycroft Energy Park Link 5.6 POTENTIAL IMPACTS Construction Construction of the power plant is expected to begin in 2011 and will last for approximately 30 months for Stage 1. Stage 1 is the peak construction phase as materials required for the construction of Stage 2 will be transported to site during Stage 1. Whilst exact details of the construction methodology and programme are not known at this stage, an indication of the likely levels of HGV and personnel movements which are expected have been obtained using ERM s experience with similar projects and information gained from APCL s construction consultants. It is assumed that the construction work will take place during a five day week, with the maximum length of the working day being 12 hours between 0700 and 1900 hours Generated Construction Traffic Assumptions In undertaking the assessment of the construction traffic impacts, reasonable assumptions have been made in order to calculate the construction traffic generation and the potential impact that this will have on the existing road 5-9

10 5.6.3 HGV Traffic network. The majority of the following assumptions have been drawn from information provided by APCL. The number of HGVs used throughout the construction phase will vary. However, APCL has established that the peak construction period will be two thirds of the way through the construction period, that is, month 20. It has been assumed from previous projects that there will be approximately 90 movements per day on site during the peak construction period. At all times outside of the peak construction month the generated HGV traffic is expected to be less than Construction Personnel At the peak period of construction there will be a maximum number of 1000 construction workers on site, however, this number will be less throughout the remainder of the project. For the purpose of this assessment it is assumed that 50% of staff will travel to site via 15-seater minibuses and 50% will travel by private vehicle at an occupancy rate of 1.3 persons per vehicle. This shows that during peak construction, there will be around 420 trips (two way) per day. Additionally, it has been assumed from similar projects that there will also be approximately 20 movements in the morning and evening peaks by employees at management level. Table 5.2 Generated Construction Traffic Hour HGV Movements Vehicle Movements Total Table 5.2 establishes the predicted worst case construction traffic movements throughout a day during the peak construction month. A summary of the table is shown below. 5-10

11 Construction staff inbound; HGVs inbound; Two way flow of HGVs; Managerial staff inbound; Managerial staff outbound; HGVs outbound; and Construction staff outbound. The following tables assess the combined impacts of the HGV and vehicle movements on the 2007 baseline provided by Neath Port Talbot County Borough Council for each individual road. Table 5.3 Generated Construction Traffic M4 Between Slips Hour 2 Way Baseline Flows Predicted Construction Traffic Movement Percentage Change % % % % % % % % % % % % % % Table 5.4 Generated Construction Traffic M4 Slips to Sunnycroft Hour 2 Way Baseline Flows Predicted Construction Traffic Movement Percentage Change % % % % % % % % % % % % % % 5-11

12 Table 5.5 Generated Construction Traffic A4241 Hour 2 Way Baseline Flows Predicted Construction Traffic Movement Percentage Change % % % % % % % % % % % % % % Table 5.6 Generated Construction Traffic Energy Park Link Hour 2 Way Baseline Flows Predicted Construction Traffic Movement Percentage Change % % % % % % % % % % % % % % As shown in Table 5.3 to Table 5.6, throughout each day in the peak month of construction, the traffic generated as a result of construction will not cause a significant impact except between the hours of and The increases resulting from construction staff accessing and leaving the site exceed the IHT Guidelines. However, this is outside of the network am and pm peaks and as such it is expected there will be capacity available on the network. It should also be noted that the peak construction period is only one month and therefore will be a temporary impact. Section 5.8 outlines mitigation measures that will be implemented to reduce the impacts of construction traffic. 5-12

13 5.6.5 Cumulative Construction Impacts Neath Port Talbot is an area of significant development and as a result cumulative impacts of this development and other developments in the area have been considered. The two significant developments are the new distribution warehouse for Amazon and the Coed Darcy Urban Village. Amazon is currently operational and as a result there are no cumulative construction impacts associated with this development. Coed Darcy is a large development and will be constructed in a number of phases. However, according to the work undertaken by ARUP for Coed Darcy the majority of construction impacts will occur in Phase One which is prior to 2008 and as a result will not coincide with this development. In addition, the maximum number of construction vehicles used per day is 30 HGVs and 30 LGVs. This is for the worst case scenario at Phase One and as a result will be lower at all other times as the average per day will be 20 HGVs and 15 LGVs. Furthermore, the access routes for construction vehicles are not similar and as a result the only road used which is similar is the M4 and both developments do not use the same slip roads. Assuming a similar split of construction traffic to this development throughout the day there will not be any negative significant impacts Abnormal Loads The construction of the power plant will involve the transport of a number of large structures into the site. It is assumed from similar projects that there will be around 75 abnormal loads throughout the construction phase. These movements will be carefully planned and controlled in conjunction with the police Operational Traffic Impacts The power plant will operate 24 hours a day and will create a number of permanent jobs within the area. The site will be operated on a two shift basis throughout each 24 hours. Five groups will operate in two shifts each group will have six operational staff as specified by APCL. It is expected that there will be a maximum of 40 personnel vehicles on site throughout the day, which translates into 80 movements throughout a 24 hour period. There will be 18 operational staff throughout the day plus an additional 10 personnel. In total there will be 28 staff during the day shift which is between 0700 and There will also be 12 operational staff working the night shift from 1900 until Operational staff will access the site in the hour prior to the commencement of their shift and leave immediately following the end of their shift. 5-13

14 Throughout the operational period there will be negligible numbers of HGVs accessing the site so no HGV movements have been factored into the operational assessment. The operational impacts have been based on a projected baseline for 2012 produced by Neath Port Talbot County Borough Council. The baseline counts take into account the traffic generated by other developments in the surrounding area, such as Coed Darcy, Amazon s distribution centre and the Peripheral Distributor Road (PDR) which are all explained in Section 5.7. Table 5.7 Projected Baseline Traffic Flows 2012 Hour M4 between slip roads M4 J41 west side slip road A4241 South of Sunnycroft Energy Park Link As a worst case scenario it is expected that up to six slip roads will be closed in 2012 as work will be underway to increase the capacity of the elevated M4 by diverting local traffic along the PDR. The six closed slip roads will be: the eastside of Junction 41 ie westbound on, and eastbound off sliproads. It must be noted that the west side of Junction 41 consists of the westbound off and eastbound on, to/from the Sunnycroft Roundabout; and the westside of Junction 40 ie westbound on, and eastbound off sliproads. 5-14

15 The projected figures take into account any road and junction closures that are expected to occur during that time period. As a result of six slip roads closing traffic will be redirected along local roads and as a result local network flows will be increased whilst M4 flows should be slightly reduced. However, traffic accessing the site will have access using M4 J41 on the west side so will use a slightly less trafficked route. Each of the roads identified along the access route is analysed individually using the predicted operational traffic in accordance with the relevant guidance presented in Section The hours of 6am until 8am and 6pm until 8pm have only been assessed within the following section as these are the times when staff access and egress the site when it is operational. Both of these times are when traffic is expected to arrive at site although at some points it may be necessary for maintenance vehicles to access the site. However, these vehicles will access outside of peak hours and are not frequent so their impact will be negligible. Table 5.8 Generated Operational Traffic M4 between Slip Roads Hour Traffic Flows Predicted Operational Percentage Change Traffic Movements % % % % Table 5.9 Generated Operational Traffic M4 J41 West Side Slip Road Hour Traffic Flows Predicted Operational Percentage Change Traffic Movements % % % % Table 5.10 Generated Operational Traffic A4241 South of Sunnycroft Hour Traffic Flows Predicted Operational Percentage Change Traffic Movements % % % % 5-15

16 Table 5.11 Generated Operational Traffic Energy Park Link Hour Traffic Flows Predicted Operational Percentage Change Traffic Movements % % % % While there are some increases above the 10% threshold identified in the IHT Guidance, operational traffic will have a minimal impact on peak hour traffic as can be seen from Table 5.8 to Table The increases above the threshold are outside the network peak hours and as such there will be available capacity on the network to accommodate this short exceedance. It should also be noted that the period of exceedance is lower than the network peak. The most significant impacts will be between and However these increases above the Guidelines are outside of peak hours, as a result there is no significant operational impact. However, it should be noted that the baseline traffic flows for these roads between the specified times are low and the networks are operating with spare capacity Impacts on Pedestrians and Cyclists The increase in traffic caused by construction and operational vehicles, however minor, could potentially reduce the levels of amenity for cyclists and pedestrians using these roads. Within Neath Port Talbot there is a National Cycle Network and alongside the A4241 there is a National Cycle Network traffic free route which, according to Sustrans, includes some forested routes and paths alongside busy roads. In this case it is mainly a path alongside a busy road. During construction there may be a slight negative impact as a result of increased traffic and its impacts such as dust. However, this will be a short term impact and it will not constitute a significant impact. In addition, the mitigation measures that have been identified will help to reduce any potential impacts on the cycle network. 5.7 CUMULATIVE IMPACTS The APCL development at Baglan Bay coincides with many other developments within Neath Port Talbot. Within the region a PDR is being developed between M4 Junction 38 at Margam and Sunnycroft Roundabout. The PDR will open up large areas of land in the Docks area for development and provide a major infrastructure improvement to the Baglan Energy Park and other development areas on the M4 corridor. The PDR will also relieve congestion on the elevated section of the M4 in the area and will remove local traffic off the M4, thus providing additional capacity. 5-16

17 Two major developments will occur within the region alongside the APCL development; these are Coed Darcy and Amazon. Coed Darcy is an urban village which will be built over the next 20 years which will contain some 4,000 houses, educational facilities and community facilities and will transform the former brownfield site into a thriving location in South Wales. Additionally, Amazon has recently completed the build out of a new distribution centre in Neath Port Talbot which is approximately 800,000 sq foot. This will bring increased employment numbers in the region and significantly increase vehicular flows in the region. All three developments have been taken into consideration in the evaluation of operational traffic flows for the APCL development and with these developments there will not be a significant cumulative impact. 5.8 MITIGATION AND MONITORING The following mitigation measures will be adopted to reduce the impact of construction traffic: wherever practical, deliveries of abnormal loads will be made outside of peak hours and where appropriate during the night; construction vehicles will be required to use identified construction routes; materials and equipment will be stored securely on site to minimise unnecessary traffic movements; and wheel washing will be carried out. 5.9 CONCLUSIONS The movement of construction vehicles is predicted to give rise to some measurable increases in the early morning and evening. However, these increases appear when the road network will be substantially under capacity as they occur outside of the am or pm peak periods. Furthermore, any increases will be short term and therefore are not considered to be significant. Mitigation measures described in Section 5.8 will, in addition, be implemented to ensure that impacts on the network are minimised. The measures address requirements such as designated construction routes and restrict the movement of abnormal loads to outside of the peak times. Operational residual impacts are minimal, although there are some increases between 0600 and 0700 and 1900 and 2000 that are over the IHT guidelines, as 5-17

18 detailed in Section However, significant delays will not be caused at these times as the roads are operating under capacity. 5-18

No significant construction or operational vibration impacts are expected.

No significant construction or operational vibration impacts are expected. 8 NOISE AND VIBRATION 8.1 SUMMARY OF RESIDUAL IMPACTS impacts for the construction and operation of the proposed CCGT power plant development are expected as these will be mitigated through design and

More information

12.0 TRANSPORT AND ACCESS...

12.0 TRANSPORT AND ACCESS... CHAPTER 12 12.0 TRANSPORT AND ACCESS... 1 12.1 Introduction... 1 12.2 Methodology... 6 12.3 Baseline Conditions... 12 12.4 Assessment of Effects... 17 12.5 Mitigation... 35 12.6 Residual Effects and Conclusions...

More information

EXHIBIT LIST No Exhibit Name Page 1 P5 Traffic Presentation.pdf (P5) 2-20

EXHIBIT LIST No Exhibit Name Page 1 P5 Traffic Presentation.pdf (P5) 2-20 Reference No: HOC/10001 Petitioner: Phase 2a Teach-ins Published to Collaboration Area: Friday 23-Mar-2018 EXHIBIT LIST Page 1 of 20 No Exhibit Name Page 1 P5 Traffic Presentation.pdf (P5) 2-20 HOC/10001/0001

More information

This chapter assesses the likely impact of the proposed power plant in relation to ground conditions and potential contamination.

This chapter assesses the likely impact of the proposed power plant in relation to ground conditions and potential contamination. 10 GROUND CONDITIONS AND CONTAMINATION 10.1 SUMMARY OF RESIDUAL IMPACTS Implementation of the mitigation measures identified in this Chapter will ensure that there will be no significant impacts of an

More information

Transport Assessment Guidelines November 2015 Cambridgeshire County Council

Transport Assessment Guidelines November 2015 Cambridgeshire County Council Transport Assessment Guidelines November 2015 Cambridgeshire County Council Introduction The National Planning Policy Framework (NPPF, March 2012) states that All developments that generate significant

More information

13. Traffic and Transport

13. Traffic and Transport 13. Traffic and Transport 13.1 Executive Summary The traffic impact of the Facility has been examined for both transport of materials and staff, and with regard to the latter, accessibility of the site

More information

Radstone Fields, Brackley Construction Traffic Management Plan Taylor Wimpey & Barratt Strategic

Radstone Fields, Brackley Construction Traffic Management Plan Taylor Wimpey & Barratt Strategic Radstone Fields, Brackley Construction Traffic Management Plan Taylor Wimpey & Barratt Strategic April 2011 QM Issue/revision Issue 1 Revision 1 Revision 2 Revision 3 Remarks Draft for Client Draft following

More information

150Intr Transport and Strategic Regeneration Welsh Assembly Government New M4 Project Magor to Castleton WelTAG Appraisal Report Stage 1 DRAFT 3 WORKI

150Intr Transport and Strategic Regeneration Welsh Assembly Government New M4 Project Magor to Castleton WelTAG Appraisal Report Stage 1 DRAFT 3 WORKI 150Intr Transport and Strategic Regeneration Welsh Assembly Government WelTAG Appraisal Report Stage 1 DRAFT 3 WORKING DOCUMENT 1 Transport and Strategic Regeneration Welsh Assembly Government WelTAG Appraisal

More information

ALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS

ALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS FINAL REPORT SEPTEMBER 2010 TABLE OF CONTENTS 1.0 INTRODUCTION 1 2.0 EXISTING TRAFFIC CONDITIONS 2 3.0 FUTURE TRAFFIC CONDITIONS 3 4.0 POTENTIAL IMPACTS

More information

The following section summarises the present conditions related to transportation for the proposed development of the PSS in the Steelpoort area.

The following section summarises the present conditions related to transportation for the proposed development of the PSS in the Steelpoort area. 16. TRAFFIC AND TRANSPORT 16.1 Introduction Goba Pty Ltd was appointed by Bohlweki Environmental to undertake a traffic/transportation impact study as part of the Environmental Impact Assessment (EIA)

More information

There will be no significant impact from solid waste arising during the development of the proposed power plant.

There will be no significant impact from solid waste arising during the development of the proposed power plant. 11 SOLID WASTE 11.1 SUMMARY OF RESIDUAL IMPACTS There will be no significant impact from solid waste arising during the development of the proposed power plant. 11.2 INTRODUCTION This chapter considers

More information

Chapter 12 Traffic and Transport

Chapter 12 Traffic and Transport Chapter 12 Traffic and Transport Introduction 12.1 This chapter considers the potential access and traffic impacts associated with the construction, operation and decommissioning of the proposed Wind Farm.

More information

Viridor Energy from Waste Facility. Environmental Statement Non-Technical Summary

Viridor Energy from Waste Facility. Environmental Statement Non-Technical Summary Viridor Energy from Waste Facility Environmental Statement Non-Technical Summary September 2012 Viridor Energy from Waste Facility Environmental Statement Non-Technical Summary Introduction Viridor has

More information

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION HIGH SPEED TWO INFORMATION PAPER E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION This paper outlines the framework for the control and management of traffic associated with the construction of the Proposed

More information

Chapter 24 Route window W3 Old Oak Common Depot. Transport for London

Chapter 24 Route window W3 Old Oak Common Depot. Transport for London Chapter 24 Route window W3 Old Oak Common Depot OLD OAK COMMON DEPOT 24 Route window W3 Old Oak Common depot 24.7 24.8 24.9 The permanent works The permanent works will consist of 14 new Crossrail stabling

More information

UK Onshore Scheme. Proposed DC Cable Route Construction Traffic Management Plan VKL G

UK Onshore Scheme. Proposed DC Cable Route Construction Traffic Management Plan VKL G UK Onshore Scheme Proposed DC Cable Route Construction Traffic Management Plan VKL-08-39-G500-022 August 2017 National Grid Viking Link Limited 2017. The reproduction or transmission of all or part of

More information

University Site: Land Between Madingley Road and Huntingdon Road (Parcel A); and

University Site: Land Between Madingley Road and Huntingdon Road (Parcel A); and Technical Note Project: North West Cambridge Transport Study To: Cambridgeshire County Council Subject: Additional Development Scenarios - University From: Atkins Date: 19/02/2009 cc: Executive Summary

More information

Land to the South of Old Mill Road, Sandbach Environmental Impact Assessment Environmental Statement: Non-Technical Summary

Land to the South of Old Mill Road, Sandbach Environmental Impact Assessment Environmental Statement: Non-Technical Summary Environmental Impact Assessment Report prepared by: Ecus Ltd. Brook Holt 3 Blackburn Road Sheffield S61 2DW 0114 266 9292 September 2013 Page Left Intentionally Blank 2 INTRODUCTION This Non Technical

More information

ENVIRONMENTAL IMPACT ASSESSMENT: TRAFFIC/TRANSPORTATION STUDY FOR PROJECT LIMA. for BOHLWEKI ENVIRONMENTAL

ENVIRONMENTAL IMPACT ASSESSMENT: TRAFFIC/TRANSPORTATION STUDY FOR PROJECT LIMA. for BOHLWEKI ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT: TRAFFIC/TRANSPORTATION STUDY FOR PROJECT LIMA for BOHLWEKI ENVIRONMENTAL January 7 Prepared by: Adrian Brislin Goba Pty Ltd Belvedere Place 5 Eglin Road Sunninghill Tel.

More information

A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement. Non Technical Summary. Business and Environmental Services

A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement. Non Technical Summary. Business and Environmental Services A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement Non Technical Summary Business and Environmental Services A responsive County Council providing excellent and efficient local services

More information

DRAFT Operational Traffic Management Plan

DRAFT Operational Traffic Management Plan A Development Consent Order Application by Ashfield Land Management Limited and Gazeley GLP Northampton s.à.r.l. In respect of February 2018 DOCUMENT SIGNATURE AND REVIEW SHEET Project Details Project

More information

Local Transport Plan. Implementation Plan ( )

Local Transport Plan. Implementation Plan ( ) Local Transport Plan Implementation Plan (2011-2015) www.cheshireeast.gov.uk/travel Contents 1 Introduction 2 Initiatives to Ensure a Sustainable Future 3 Initiatives to Create Conditions for Business

More information

Traffic Impact Study Guidelines. City of Guelph

Traffic Impact Study Guidelines. City of Guelph Traffic Impact Study Guidelines City of Guelph April 2016 Engineering and Capital Infrastructure Services Infrastructure, Development & Enterprise 1 Carden Street Guelph, Ontario Canada N1H 3A1 Page 1

More information

Project Appraisal Using PRISM Simon Hubbard 28 th September 2004

Project Appraisal Using PRISM Simon Hubbard 28 th September 2004 Project Appraisal Using PRISM Simon Hubbard 28 th September 2004 Introduction : Overview of Presentation - Option Appraisal Policy Context - Potential PRISM Applications - Use of the Model / Scale of the

More information

Non-Technical Summary

Non-Technical Summary 1. Introduction and Background 1.1 Following consultation Barwood Land and Estates Limited (Barwood Land) is making a number of minor amendments to and providing related additional information for the

More information

Report to: Greater Cambridge Partnership Joint Assembly 18 January 2018

Report to: Greater Cambridge Partnership Joint Assembly 18 January 2018 Report to: Greater Cambridge Partnership Joint Assembly 18 January 2018 Lead officer: Chris Tunstall Greater Cambridge Partnership Recommendations from the Ely to Cambridge A10 Transport Study and proposed

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Proposed development at Stephenson Road, Northacre Trading Estate, Westbury, BA13 4WD Non-technical summary December 2014 Introduction Northacre Renewable Energy Ltd (a company

More information

18 Cumulative Impacts and Interaction of Effects

18 Cumulative Impacts and Interaction of Effects 18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly

More information

Proposed Residential Development Land at Baldock, Hertfordshire. Air Quality Assessment Site

Proposed Residential Development Land at Baldock, Hertfordshire. Air Quality Assessment Site Proposed Residential Development Land at Baldock, Hertfordshire Air Quality Assessment Site 2 404.2048.00001 July 2008 Hertfordshire County Council i 404.2048.00001 CONTENTS 1.0 INTRODUCTION... 1 1.1 Structure

More information

Air Quality. Executive Summary

Air Quality. Executive Summary Air Quality Executive Summary Air quality adjacent to the Scheme is currently good with low background concentrations of air pollutants. However, there are areas within Cambridge city centre which currently

More information

ARCHITECTUS FEBRUARY 2010

ARCHITECTUS FEBRUARY 2010 ARCHITECTUS PEDESTRIAN AND TRAFFIC MANAGEMENT PLAN FOR DEMOLITION, EXCAVATION AND CONSTRUCTION OF COLLEGE OF FINE ARTS CAMPUS, PADDINGTON FEBRUARY 2010 COLSTON BUDD HUNT & KAFES PTY LTD ACN 002 334 296

More information

Welsh Government M4 Corridor Enhancement Measures (CEM) Participation Report Executive Summary

Welsh Government M4 Corridor Enhancement Measures (CEM) Participation Report Executive Summary M4 Corridor Enhancement Measures (CEM) Participation Report Executive Summary Issue 5 August 2013 This report takes into account the particular instructions and requirements of our client. It is not intended

More information

Transportation and Utilities

Transportation and Utilities 4 Section 4 Transportation and Utilities 4.0 Introduction Transportation and utility systems are essential to accommodate and support development proposed in the Future Land Use Map. The following pages

More information

Chapter 17 Cumulative Impacts

Chapter 17 Cumulative Impacts Chapter 17 Cumulative Impacts CONTENTS 17. Cumulative Effects... 2 17.1 Introduction... 2 17.2 Summary of Relevant Legislation, Planning Policy and Guidance... 2 17.3 Methods... 5 17.4 Consultation...

More information

7. EIA Assessment Methodology

7. EIA Assessment Methodology 7. EIA Assessment Methodology Introduction 7.1 This Chapter of the PEIR sets out the process and methodology that has been adopted in undertaking the draft EIA. Whilst the overall approach and methodology

More information

1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT

1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT 1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT This Environmental Impact Assessment Report (EIA Report) has been prepared by Environmental Resources Management Ltd

More information

IHT SPRING CONFERENCE MARCH 2008

IHT SPRING CONFERENCE MARCH 2008 IHT SPRING CONFERENCE MARCH 2008 DYNAMIC NETWORK MANAGEMENT SMART Systems in London Jason Robinson Chief Engineer, Urban Traffic Control Directorate of Traffic Operations Transport for London Presentation

More information

Transformation of Oxford Street

Transformation of Oxford Street Transformation of Oxford Street 3 January 2018 ABOUT US Heart of London Business Alliance serves as the voice for 500 businesses and 100 property owners in the Piccadilly & St James s and Leicester Square

More information

Technical Assessment Testing. Introduction

Technical Assessment Testing. Introduction B1.6.5 Technical Assessment Testing Introduction This appendix explains the three technical assessments which were undertaken by in September 2017 to consider the implications of District wide distribution

More information

IPSWICH NORTHERN ROUTES STUDY. Stage 1 Progress

IPSWICH NORTHERN ROUTES STUDY. Stage 1 Progress IPSWICH NORTHERN ROUTES STUDY Stage 1 Progress 17 th January 2017 STUDY CONTEXT 2 The study is being funded in partnership with the Suffolk district and borough councils. Work forms part of the Suffolk

More information

Transportation Master Plan Introduction

Transportation Master Plan Introduction 1. Introduction Building a Liveable Ottawa 2031 has set out a process to guide the completion of a fiveyear update of the City s Official Plan, Transportation Master Plan, Infrastructure Master Plan, Cycling

More information

1 INTRODUCTION 1.1 OVERVIEW

1 INTRODUCTION 1.1 OVERVIEW 1 INTRODUCTION 1.1 OVERVIEW This document is the Environmental Statement (ES) produced by ERM on behalf of Abernedd Power Company Limited (APCL) a wholly owned subsidiary of BP Alternative Energy International

More information

Annex A. Consultation Responses

Annex A. Consultation Responses Annex A Consultation Responses CONTENTS A1.1 INTRODUCTION A-1 A1.2 STATUTORY STAKEHOLDERS A-1 A1.3 PUBLIC EXHIBITIONS A-1 APPENDIX 1 ENVIRONMENTAL SCOPING DOCUMENT A1.1 INTRODUCTION This Annex summarises

More information

Pre- submission Core Strategy and associated documents consultation. Submitted on behalf of Extra Motorway Services Area Group

Pre- submission Core Strategy and associated documents consultation. Submitted on behalf of Extra Motorway Services Area Group Pre- submission Core Strategy and associated documents consultation (5 th November 16 th December 2013) Submitted on behalf of Extra Motorway Services Area Group Reference: BIR.4412 Date: December 2013

More information

SWDP 4: Moving Around South Worcestershire. SWDP 4: Moving Around South Worcestershire. Managing Travel Demand

SWDP 4: Moving Around South Worcestershire. SWDP 4: Moving Around South Worcestershire. Managing Travel Demand SWDP 4: Moving Around South Worcestershire Managing Travel Demand A. Proposals must demonstrate that: the layout of development will minimise demand for travel, they offer genuinely sustainable travel

More information

North Northamptonshire Joint Core Strategy Examination

North Northamptonshire Joint Core Strategy Examination North Northamptonshire Joint Core Strategy Examination Joint Position and Delivery Statement By North Northamptonshire Joint Planning Unit, Kettering Borough Council And Persimmon Homes Midlands Policy

More information

Public Information Centre #1. March 2010

Public Information Centre #1. March 2010 Public Information Centre #1 March 2010 Purpose of Public Information Centre Halton Region is initiating a Transportation Master Plan (2031) The Road to Change The Plan will develop a sustainable, integrated

More information

TRANSPORTATION IMPACT ANALYSISGUIDELINES

TRANSPORTATION IMPACT ANALYSISGUIDELINES TRANSPORTATION IMPACT ANALYSISGUIDELINES ADOPTED OCTOBER2014 SANTACLARAVALLEYTRANSPORTATION AUTHORITY CONGESTION MANAGEMENTPROGRAM CONGESTION MANAGEMENT PROGRAM TRANSPORTATION IMPACT ANALYSIS GUIDELINES

More information

Environmental Statement Non Technical Summary. Anthony s Way Frindsbury June creative minds safe hands

Environmental Statement Non Technical Summary. Anthony s Way Frindsbury June creative minds safe hands Environmental Statement Non Technical Summary Anthony s Way Frindsbury June 2010 www.wyg.com creative minds safe hands Contents Section A Introduction Part 1 Background Part 2 Environmental Assessment

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

As one of our greatest assets there is a need to take collective action to protect, enhance and value our environment for now and for future

As one of our greatest assets there is a need to take collective action to protect, enhance and value our environment for now and for future 1 As one of our greatest assets there is a need to take collective action to protect, enhance and value our environment for now and for future generations, ensuring that the Vale of Glamorgan is globally

More information

INTERIM ADVICE NOTE 103/08. Advice Regarding the Assessment of Sites for Ramp Metering

INTERIM ADVICE NOTE 103/08. Advice Regarding the Assessment of Sites for Ramp Metering INTERIM ADVICE NOTE 103/08 Advice Regarding the Assessment of Sites for Ramp Metering Summary This document provides advice on identifying on-slip locations that are likely to be suitable for the implementation

More information

Galloper Wind Farm Project

Galloper Wind Farm Project Galloper Wind Farm Project Environmental Statement Chapter 25: Traffic and Transport October 2011 Document Reference 5.2.25 Galloper Wind Farm Limited Document title Galloper Wind Farm Project Environmental

More information

Demand Reduction Assumptions Used For Travel Demand Analysis of EIS Alternatives

Demand Reduction Assumptions Used For Travel Demand Analysis of EIS Alternatives M E M O R A N D U M Demand Reduction Assumptions Used For Travel Demand Analysis of EIS Alternatives TO: FROM: Project Management Team Steve Perone/PTV America DATE: Revised: February 6, 2009 Background

More information

Strategic Environmental Assessment Environmental Report Non Technical Summary

Strategic Environmental Assessment Environmental Report Non Technical Summary Number: WG19741 We want your views on our draft Plan which aims to address transport related problems on the M4 around Newport M4 Corridor around Newport draft Plan Consultation Document Strategic Environmental

More information

Hastings District Council. Whakatu Arterial Link Traffic Management Plan

Hastings District Council. Whakatu Arterial Link Traffic Management Plan Hastings District Council Whakatu Arterial Link Traffic Management Plan June 2014 Table of contents 1. Introduction... 2 1.1 Purpose of this report... 2 1.2 The Whakatu Arterial Link... 2 2. Traffic Management...

More information

WELCOME. Redevelopment of land at Merrylees Industrial Estate, Desford LE9 9FE. This Public Exhibition. About Flogas

WELCOME. Redevelopment of land at Merrylees Industrial Estate, Desford LE9 9FE. This Public Exhibition. About Flogas WELCOME Thank you for taking the time to come along and view our proposals for Merrylees Industrial Estate. About Flogas We re a leading LPG (Liquefied Petroleum Gas) supplier with more than 30 years experience

More information

Ferrybridge Multifuel 2 (FM2) Power Station

Ferrybridge Multifuel 2 (FM2) Power Station Welcome Multifuel Energy Ltd is proposing to build a second multifuel power station at Ferrybridge (FM2). This formal consultation is an opportunity for you to provide feedback and comment on the Proposed

More information

COG MOORS WWTW PROPOSED ADVANCED ANAEROBIC DIGESTION PLANT Construction Traffic Management Plan AUGUST 2017

COG MOORS WWTW PROPOSED ADVANCED ANAEROBIC DIGESTION PLANT Construction Traffic Management Plan AUGUST 2017 COG MOORS WWTW PROPOSED ADVANCED ANAEROBIC DIGESTION PLANT Construction Traffic Management Plan AUGUST 2017 CONTACTS MATTHEW FRY PRINCIPAL TRANSPORT PLANNER dd 02920 926 886 m 07841 861627 e matthew.fry@arcadis.com

More information

A428 / Western Corridor brief. Background

A428 / Western Corridor brief. Background A428 / Western Corridor brief Background The Transport Strategy that has been developed to support the current Local Plan review outlines major investment in public transport as a pre-requisite to support

More information

HIGH HEAVENS WASTE TRANSFER STATION, HIGH WYCOMBE

HIGH HEAVENS WASTE TRANSFER STATION, HIGH WYCOMBE 2nd September 2010 Transport Development Control Buckinghamshire County Council The Winslow Centre Park Road Winslow Buckinghamshire MK18 3RB FAO Mr D. Tester Our Ref: 404-00197-00792 Your Ref: Dear Mr

More information

1 to 3 db Slight impact. 3 to 5 db Moderate Impact. 5 to 10 db Substantial Impact. >10 db Severe Impact

1 to 3 db Slight impact. 3 to 5 db Moderate Impact. 5 to 10 db Substantial Impact. >10 db Severe Impact AECOM Wolverhampton City Centre Metro Extension Environmental Impact Assessment Scoping Report 52 Table 10.2: Classification of Magnitude of Noise Impacts at NSRs Noise Level/Change db L Aeq,18h Magnitude

More information

Transportation and Works Department The Regional Municipality of York Yonge Street Newmarket, Ontario L3Y 6Z1

Transportation and Works Department The Regional Municipality of York Yonge Street Newmarket, Ontario L3Y 6Z1 TRANSPORTATION IMPACT STUDY (TIS) GUIDELINES FOR DEVELOPMENT APPLICATIONS Transportation and Works Department The Regional Municipality of York 17250 Yonge Street Newmarket, Ontario L3Y 6Z1 August, 2007

More information

Ballinabrackey and Castlejordan function as small rural centres offering only the most basic amenities. For inspection purposes only.

Ballinabrackey and Castlejordan function as small rural centres offering only the most basic amenities. For inspection purposes only. 6.0 HUMAN BEINGS 6.1 RECEIVING ENVIRONMENT The proposed site is located at Killaskillen, Co. Meath, 3km southwest of Kinnegad. The village of Ballinabrackey is located approximately 1.5 km south of the

More information

Bristol City Council Clean Air Local Plan: Transport and Air Quality Compliance Timescales, Assumptions and Calculations

Bristol City Council Clean Air Local Plan: Transport and Air Quality Compliance Timescales, Assumptions and Calculations BRISTOL CLEAN AIR LOCAL PLAN Bristol City Council Clean Air Local Plan: Transport and Air Quality Compliance Timescales, Assumptions and Calculations PREPARED FOR: PREPARED BY: CHECKED BY Bristol City

More information

City of Berkeley. Guidelines for Development of Traffic Impact Reports

City of Berkeley. Guidelines for Development of Traffic Impact Reports Office of Transportation (OOT) City of Berkeley Guidelines for Development of Traffic Impact Reports Office of Transportation, City of Berkeley 1 1. Overview These guidelines provide a framework to help

More information

Chapter 10 Route Window NE9 Romford station and depot (east) Transport for London

Chapter 10 Route Window NE9 Romford station and depot (east) Transport for London Chapter 10 Route Window NE9 Romford station and depot (east) ROMFORD STATION AND DEPOT (EAST) 10 Route Window NE9 Romford station and depot (east) Introduction 10.1 The Romford Maintenance Depot will

More information

Fishermans Bend Integrated Transport Plan Peer Review John Kiriakidis, GTA Consultants 28/03/2018

Fishermans Bend Integrated Transport Plan Peer Review John Kiriakidis, GTA Consultants 28/03/2018 Fishermans Bend Integrated Transport Plan Peer Review John Kiriakidis, GTA Consultants 28/03/2018 GTA creating transport that works 01 Preliminaries GTA creating transport that works Review scope : Review

More information

TOWN AND COUNTRY PLANNING ACT

TOWN AND COUNTRY PLANNING ACT Environment Directorate Lancaster City Council Regeneration and Policy Team Planning Advice Team PO Box 4 Town Hall Lancaster LA1 1QR County Council Phone: (01772) 534057 Fax: Email: Neil.Stevens@lancashire.gov.uk

More information

CITY OF VALLEJO PUBLIC WORKS DEPARTMENT TRAFFIC IMPACT Analysis/Study GUIDELINES

CITY OF VALLEJO PUBLIC WORKS DEPARTMENT TRAFFIC IMPACT Analysis/Study GUIDELINES The City Engineer, under the authority of the Public Works Director and recommendations from the Traffic Engineer, will make the final decision on the need for a traffic study. The purpose of the traffic

More information

Introduction to presentation structure

Introduction to presentation structure 1 Introduction to presentation structure 2 EIA ensures that the environment is considered during decision-making by planning committee (note: EIA applications are not generally made under delegated powers

More information

That will also contribute to achievement of a number of objectives and policies in the Regional Policy Statement.

That will also contribute to achievement of a number of objectives and policies in the Regional Policy Statement. Board of Inquiry MacKays to Peka Peka Expressway Proposal Submitters Evidence Public Transport Voice 5 October 2012 Executive Summary Increasing modal share for public transport is a key outcome in the

More information

Crossrail. Environmental Statement. Volume 9c. Appendices. Westbourne Park Bus Garage Extension. Volume 2 Appendices

Crossrail. Environmental Statement. Volume 9c. Appendices. Westbourne Park Bus Garage Extension. Volume 2 Appendices Crossrail Environmental Statement Volume 9c Appendices Westbourne Park Bus Garage Extension Environmental Statement Volume 2 Appendices 9c If you would like information about Crossrail in your language,

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Revision of the layout and design of the Advanced Thermal Treatment Facility permitted under consent 14/12003/WCM at Stephenson Road, Northacre Trading Estate, Westbury, BA13

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Revision of the layout and design of the Advanced Thermal Treatment Facility permitted under consent 14/12003/WCM at Stephenson Road, Northacre Trading Estate, Westbury, BA13

More information

In-combination and Cumulative Effects Assessment

In-combination and Cumulative Effects Assessment P O R T I S H E A D B R A N C H L I N E P R E L I M I N A R Y ENV I R O N M E N T A L I N F O R M A T I O N R E P O R T V O L U M E 2 C H A P T E R 18 In-combination and Cumulative Effects Assessment Table

More information

Chapter 4. Recommendations

Chapter 4. Recommendations Chapter 4 Recommendations Project Rating Methodology 1.0 Introduction This chapter outlines the prioritization of potential investments that were identified during this MIS process. During this study there

More information

South Cambridgeshire District Council South Cambridgeshire Hall Cambourne Business Park Camborne Cambridgeshire CB23 6EA

South Cambridgeshire District Council South Cambridgeshire Hall Cambourne Business Park Camborne Cambridgeshire CB23 6EA South Cambridgeshire District Council South Cambridgeshire Hall Cambourne Business Park Camborne Cambridgeshire CB23 6EA For the attention of 20 th April 2009 Dear NORTH WEST AREA ACTION PLAN PUBLIC CONSULTATION

More information

AIR QUALITY MODELLING OF STRATEGIC TRAFFIC DEMAND MANAGEMENT STRATEGIES

AIR QUALITY MODELLING OF STRATEGIC TRAFFIC DEMAND MANAGEMENT STRATEGIES ABSTRACT AIR QUALITY MODELLING OF STRATEGIC TRAFFIC DEMAND MANAGEMENT STRATEGIES Anil Namdeo and Margaret C Bell Institute for Transport Studies University of Leeds, Leeds LS2 9JT, UK anamdeo@its.leeds.ac.uk

More information

Tours-Based LUTI Modelling

Tours-Based LUTI Modelling Tours-Based LUTI Modelling Leicester and Leicestershire Integrated Transport Model Mark Dazeley, Associate Director 16 th October 2014 Presentation Structure Introduction Team technical skills, clients

More information

Cabinet Meeting 26 April 2017

Cabinet Meeting 26 April 2017 Cabinet Meeting 26 April 2017 Report title Decision designation Cabinet member with lead responsibility Key decision In forward plan Wards affected Accountable director Originating service Accountable

More information

Guidelines for the Submission of a Transportation Study Level 2

Guidelines for the Submission of a Transportation Study Level 2 Guidelines for the Submission of a Transportation Study Level 2 For Site Development Applications in the City of North Vancouver Transportation Group, City of North Vancouver Engineering, Parks & Environment

More information

Mid Wales (Powys) Conjoined Wind Farms Public Inquiry. Summary Proof of Evidence Kevin Martin BEng, CEng, MICE

Mid Wales (Powys) Conjoined Wind Farms Public Inquiry. Summary Proof of Evidence Kevin Martin BEng, CEng, MICE Transportation RES UK &Ireland Limited September 2013 Mid Wales (Powys) Conjoined Wind Farms Public Inquiry Application by RES UK & Ireland Limited dated 27 March 2009 for consent under Section 36 of the

More information

Mountain Transportation Study

Mountain Transportation Study EXECUTIVE SUMMARY Salt Lake County and its study partners including the Utah Department of Transportation (UDOT), the Utah Transit Authority (UTA), the United States Forest Service (USFS), Salt Lake City,

More information

This report assesses the outward noise and vibration impact of the proposed development on its surrounding environment.

This report assesses the outward noise and vibration impact of the proposed development on its surrounding environment. 8. NOISE AND VIBRATION 8.1 Introduction This report has been prepared by AWN to form part of an EIAR for the proposed residential development at Wonderful Barn, Barnhall, Leixlip. The chapter assesses

More information

SEARs project justification and conclusion

SEARs project justification and conclusion 31 Project justification and conclusion This chapter presents a justification for the project and a conclusion to the environmental impact statement (EIS). The justification is based on the strategic need

More information

Information supporting the traffic chapters

Information supporting the traffic chapters Annex I Metro North EIS Information supporting the traffic chapters - Baseline traffic report Information Note Project Title: MVA Project Number: Metro North EIA C8103900 Subject: Alterations to Baseline

More information

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver

More information

A Rail Freight Interchange for Spalding

A Rail Freight Interchange for Spalding A Rail Freight Interchange for Spalding Consultation by South Holland District Council on a proposed development site option for a Rail Freight Interchange facility March 2010 About the proposals Introduction

More information

5. Environmental issues and methodology

5. Environmental issues and methodology 5. Environmental issues and methodology 5 Environmental issues and methodology Introduction 5.1 The methodology used to carry out the environmental impact assessment (EIA) is set out in this chapter. This

More information

WOKING BOROUGH COUNCIL LOCAL DEVELOPMENT FRAMEWORK. Green Belt Boundary Review Sensitivity Test. Addendum Report to Strategic Transport Assessment

WOKING BOROUGH COUNCIL LOCAL DEVELOPMENT FRAMEWORK. Green Belt Boundary Review Sensitivity Test. Addendum Report to Strategic Transport Assessment S WOKING BOROUGH COUNCIL LOCAL DEVELOPMENT FRAMEWORK Green Belt Boundary Review Sensitivity Test Addendum Report to Strategic Transport Assessment Project Title: Woking Borough Council Local Development

More information

Ibsa House, The Ridgeway, London, NW7 1RN

Ibsa House, The Ridgeway, London, NW7 1RN LOCATION: Ibsa House, The Ridgeway, London, NW7 1RN REFERENCE: H/00807/14 Received: 17 February 2014 Accepted: 27 February 2014 WARD: Mill Hill Expiry: 29 May 2014 APPLICANT: IBSA Final Revisions: PROPOSAL:

More information

Land Reclamation, Surface Coal Mining and Restoration at the Former Tower Colliery Site ENVIRONMENTAL STATEMENT. Non-Technical Summary

Land Reclamation, Surface Coal Mining and Restoration at the Former Tower Colliery Site ENVIRONMENTAL STATEMENT. Non-Technical Summary Land Reclamation, Surface Coal Mining and Restoration at the Former Tower Colliery Site ENVIRONMENTAL STATEMENT Non-Technical Summary July 2010 Introduction Tower Regeneration Limited (Tower), a joint

More information

PART 5: DEVELOPMENT FRAMEWORK Figure 54: Revise Functional Road Hierarchy

PART 5: DEVELOPMENT FRAMEWORK Figure 54: Revise Functional Road Hierarchy Figure 54: Revise Functional Road Hierarchy 93 The second step was to overlay the hierarchy with all the public transport modes planned to operate within the precinct as shown in Figure 58 below. Figure

More information

Transform 66 Multimodal Project: Prioritization Process and Evaluation Criteria Approved March 3, 2016

Transform 66 Multimodal Project: Prioritization Process and Evaluation Criteria Approved March 3, 2016 Transform 66 Multimodal Project: Prioritization Process and Evaluation Criteria Approved March 3, 2016 The Memorandum of Agreement (MOA) for the Transform 66: Inside the Beltway Project directs NVTC to

More information

Consultation response. February 2014

Consultation response. February 2014 Department for Transport National road and rail networks: draft national policy statement Consultation response pteg Support Unit Wellington House 40-50 Wellington Street Leeds LS1 2DE 0113 251 7445 info@pteg.net

More information

PORTFOLIO ORIGIN TRANSPORT CONSULTANTS LTD

PORTFOLIO ORIGIN TRANSPORT CONSULTANTS LTD CASE STUDY PORTFOLIO ORIGIN TRANSPORT CONSULTANTS LTD CASE STUDY AVONMOUTH BIO POWER LOW CARBON ENERGY FACILITY D E T A I L S Transport Statement- Modelling, assessment of trips on strategic road network.

More information

The consultation will run from Wednesday 6 September Tuesday 17 October 2017

The consultation will run from Wednesday 6 September Tuesday 17 October 2017 M2 Junction 5 improvements scheme Have your say Questionnaire Contact information Please read the consultation document before completing the questionnaire The consultation will run from Wednesday 6 September

More information

SECTION 32 TRANSPORT CHAPTER

SECTION 32 TRANSPORT CHAPTER SECTION 32 TRANSPORT CHAPTER AUGUST 2014 VERSION 1 CONTENTS 1. STRATEGIC CONTEXT...3 1.1 PURPOSE AND SCOPE OF THE TRANSPORT CHAPTER...3 1.2 PROPOSED DISTRICT PLAN: OVERVIEW AND SYNOPSIS...4 1.3 RESEARCH...5

More information

2 ENVIRONMENTAL IMPACT ASSESSMENT

2 ENVIRONMENTAL IMPACT ASSESSMENT 2 ENVIRONMENTAL IMPACT ASSESSMENT Introduction 2.1 Environmental Impact Assessment (EIA) is required for certain categories of projects and involves a process of drawing together, in a systematic way,

More information