RESOURCE CONSENT CRC174931
|
|
- Bernard Gardner
- 6 years ago
- Views:
Transcription
1 RESOURCE CONSENT CRC Pursuant to Section 104 of the Resource Management Act 1991 The Canterbury Regional Council (known as Environment Canterbury) GRANTS TO: A WATER PERMIT (S14): Gary Thomas Tomes To transfer site to site groundwater; to take and use COMMENCEMENT DATE: 06 April 2017 EXPIRY DATE: 18 September 2036 LOCATION: 179 McLeods Road, Rangiora SUBJECT TO THE FOLLOWING CONDITIONS: 1 Water may be taken only from Fox Creek at surface water abstraction point (SWAP) BW24/0370, six metres wide, ten metres long and four metres deep, at map reference NZTopo50 BW24: , as shown on Plan CRC174931, which forms part of this consent. 2 Water may be taken: a. From Fox Creek at a rate not exceeding 65 litres per second for the filling of a storage dam, b. From the storage dam at a rate not exceeding 20 litres per second, with a volume not exceeding 1,209 cubic metres per day. c. at a volume not exceeding 211,582.2 cubic metres between 1 July and the following 30 June. 3 Water shall only be used for irrigation of the area of land shown on attached plan CRC The taking of water in terms of this permit shall cease for a period of up to 48 hours on notice from the Canterbury Regional Council, to allow measurement of the flow in the Fox Creek. 5 Whenever the; a. Mean flow in Saltwater Creek for the 24 hour period ending at noon on any one day falls below 100 litres per second, the taking of water in terms of this permit shall cease.
2 Page 2 CRC b. Mean flow in Saltwater Creek for the 24 hour period ending at noon on any one day falls below 508 litres per second then the rate at which water is taken shall reduce to that shown on the attached graph CRC The flow referred to in condition 5 shall be the flow estimated by the Canterbury Regional Council in Saltwater Creek at Toppings Road recorder site at map reference Topo50 BW24: The consent holder shall, before the first exercise of this consent, install an easily accessible straight pipe(s), with no fittings or obstructions that may create turbulent flow conditions, of a length at least 15 times the diameter of the pipe, as part of the pump outlet plumbing or within the mainline distribution system. 8 The consent holder shall before the first exercise of this consent: a. i. install a water meter(s) that has an international accreditation or equivalent New Zealand calibration endorsement, and has pulse output, suitable for use with an electronic recording device, which will measure the rate and the volume of water taken to within an accuracy of plus or minus five percent as part of the pump outlet plumbing, or within the mainline distribution system, at a location(s) that will ensure the total take of water is measured; and ii. install a tamper-proof electronic recording device such as a data logger(s) that shall time stamp a pulse from the flow meter at least once every 15 minutes and have the capacity to hold at least one season s data of water taken as specified in clauses (b)(i) and (b)(ii), or which is telemetered, as specified in clause (b)(iii). b. The recording device(s) shall: i. be set to wrap the data from the measuring device(s) such that the oldest data will be automatically overwritten by the newest data (i.e. cyclic recording); and ii. store the entire season s data in each 12 month period from 1 July to 30 June in the following year, which the consent holder shall then download and store in a commonly used format and provide to the Canterbury Regional Council upon request in a form and to a standard specified in writing by the Canterbury Regional Council; and iii. shall be connected to a telemetry system which collects and stores all of the data continuously with an independent network provider who will make that data available in a commonly used format at all times to the Canterbury Regional Council and the consent holder. No data in the recording device(s) shall be deliberately changed or deleted.
3 Page 3 CRC a. The water meter and recording device(s) shall be accessible to the Canterbury Regional Council at all times for inspection and/or data retrieval. b. The water meter and recording device(s) shall be installed and maintained throughout the duration of the consent in accordance with the manufacturer s instructions. c. All practicable measures shall be taken to ensure that the water meter and recording device(s) are fully functional at all times. 9 Within one month of the installation of the measuring or recording device(s), or any subsequent replacement measuring or recording device(s), and at five-yearly intervals thereafter, and at any time when requested by the Canterbury Regional Council, the consent holder shall provide a certificate to the Canterbury Regional Council, Attention Regional Leader - Monitoring and Compliance, signed by a suitably qualified person certifying, and demonstrating by means of a clear diagram, that: a. The measuring and recording device(s) has been installed in accordance with the manufacturer s specifications; and b. Data from the recording device(s) can be readily accessed and/or retrieved in accordance with clauses (b) and (c) of condition (8). 10 The consent holder shall take all practicable steps to: a. Ensure that the volume of water used for irrigation does not exceed that required for the soil to reach field capacity; and b. Avoid leakage from pipes and structures; and c. Avoid the use of water onto non-productive land such as impermeable surfaces and river or stream riparian strips. 11 If the irrigation system is used to distribute diluted effluent, fertiliser or added contaminants the consent holder shall ensure: a. An effective backflow prevention device is installed and operated within the pump outlet plumbing or within the mainline to prevent the backflow of contaminants into the water source; and b. The backflow prevention device is tested at the time of installation and annually thereafter by a suitably qualified or certified person in accordance with Canterbury Regional Council approved test methods for the device used; and c. The test report is provided to the Canterbury Regional Council Attention Regional Leader - Monitoring and Compliance, within two weeks of each inspection.
4 Page 4 CRC Advice Note: This is not authorisation to discharge fertiliser or other contaminants to land, water or air under section 15 of the Resource Management Act. 12 The Canterbury Regional Council may, on any of the last five working days of June each year, serve notice of its intention to review the conditions of this consent for the purpose of dealing with any adverse effect on the environment which may arise from the exercise of the consent and which it is appropriate to deal with at a later stage. Issued at Christchurch on 6 April 2017 Canterbury Regional Council
5 Plan CRC BW24/0370 Area to be irrigated 21 hectares Population center and locality labels Hydrographic feature labels Parks, forests, and reserves labels Address point labels Road labels Regional Boundaries Territorial Authority Boundaries Land Parcels Land Parcel State highways outside Canterbury Aerial Imagery Boundaries (Latest Visible) Aerial Imagery Footprints (Latest) Disclaimer: Information has been derived from various sources, including Environment Canterbury Regional Council s databases. Boundary information is derived under licence from LINZ Digital Cadastral Database (Crown Copyright Reserved). Environment Canterbury Regional Council does not give and expressly disclaim any warranty as to the accuracy or completeness of the information or its fitness for any purpose. Information from this web site may not be used for the purposes of any legal disputes. The user should independently verify the accuracy of any information before taking any action in reliance upon it Kilometres Scale: Copyright Canterbury Maps Environment Canterbury Land Information New Zealand 2017 Map Created by Environment Canterbury on 30/03/ :16:04 a.m.
6 Graph CRC Maximum allowable abstraction rates when the Saltwater Creek flow as specified in condition 4 of consent CRC Maximum Rate of Take (litres per second) River Flow Litres per second at Toppings Road recorder as specified in condition 5
7 RESOURCE CONSENT VERSION NOV 2009 Flowmeter, Datalogger Installation and Commissioning FOR OFFICE USE ONLY TO: Environment Canterbury Ph: C/o Water Metering Team Tuam Street PO Box 345 Christchurch 8140 Consent Holder: Consent number: CRC Well/SWAP number(s): Installation date: Flowmeter details: Make: Meter size: (mm diameter) Model: Pulse output: Yes/ No Serial number: Volume per Pulse m³/puls (Start) Meter Reading Volume: m³ (state units if different) Datalogger details: Installed Yes/ No Make: Model: Serial number: Telemetry installed for compliance: Yes/ No Data hosted by: Installation details: Pipe internal/external diameter: mm Pipe Wall Thickness mm Pipe material: Ductile Iron, Mild Steel, PVC, Polyethelene, Aluminium, other : Distance of straight, unobstructed pipe upstream of flowmeter (distance (a) in Figure 1): Distance of straight, unobstructed pipe downstream of flowmeter (distance (b) in Figure 1): Is there a straight unobstructed accessible pipe in the system of at least 15 diameters length to verify the flow with a clamp-on flow meter? Yes/ No Location in system: Figure 1: Installation diagram - Please mark any disturbances upstream of the flowmeter e.g. pipe size reduction, gate valves, pipe bends. Refer to Figure 2 for an example of a good installation. mm mm
8 RESOURCE CONSENT Insertion meters only: Insertion depth: K-factor: Ultrasonic meters only: Transducer size: Transducer mounting: V or Z (Please circle, V = Reflect, Z = Direct) Transducer spacing: Accuracy details: Do you have a WET calibration certificate? Yes/ No (If yes, then please submit the certificate.) Has the meter been checked against a portable flowmeter? Yes/ No (If yes please fill in water meter verification form) Certification: I/we certify that the above flowmeter and datalogger have been installed in accordance with Environment Canterbury s requirements. That a wet calibration certificate from the manufacturer is attached to this form That a water meter verification form is attached to this form. That a picture of the installation is attached to this form. Installed by: Signed: (by installer) Company: Date: Figure 2: An example of an Ideal installation of a flowmeter, including obstructions in pipework.
9 RESOURCE CONSENT VERSION NOV 2009 Flowmeter/Water Measuring Device Verification Form FOR OFFICE USE ONLY TO: Environment Canterbury Ph: C/o Water Metering Team Tuam Street PO Box 345 Christchurch 8140 Well/SWAP number(s): Consent Holder: Verification date: Flowmeter/Water Measuring Device details: (if not already provided on installation and commissioning form) Make: Meter size: (mm diameter) Model: Pulse output: Yes No Serial number: Volume per Pulse m³/puls Meter Reading Volume: m³ (state units if different) Insertion meters only: Encountered K-factor in the flow meter : Correct Yes No Ultrasonic meters only: Transducer size encountered: Transducer spacing: Transducer mounting: V or Z (Please circle, V = Reflect, Z = Direct) Correct Yes No Verification details: Is a clamp-on water meter used for verification: Yes No (if no describe the method used) e.g. reservoir/time calculation, volumetric etc) Verification flow meter brand and type: Verification flow meter serial number: Last calibration date of the flow meter used for verification: (Calibration certificates needs to be send in (once) after every (yearly) calibration to ECan) Verification parameters: Used parameters for verification: Pipe diameter: mm Pipe Wall Thickness mm Pipe material: Ductile Iron, Mild Steel, PVC, Polyethelene, Aluminium, other : Location in system where the clamp-on was attached:
10 RESOURCE CONSENT Measured flows: Undertake three separate observations and record and average the results in the table below. Verification flows should be taken at or around the consented flow rate and/or the flow rate the well is usually pumped at. If flows don t verify within 5% a second clamp-on location can/should be attempted. Location 1 Location 1 Location 1 Location 2 Location 2 Location 2 Average installed meter flow: L/s verification flow meter: L/s % Difference Certification: I/we certify that the above flowmeter/water measuring device has been verified and the measured flow is within 5% of the verification meter. OR (circle one) I/we have found that the installed flowmeter/water measuring device deviates more then 5% above/below the verified flow. Recommend remedial action: Verified by: Signed: (by verifyer) Verifiers Certificate No *: Company: Date: * Each verifier will be registered by the manufacturer/supplier on having attended a verifier course for their equipment. ECan will keep a list of the approved verifiers and certificate numbers.
Notice of Resource Consent Decisions Record No: CRC CRC Name: New Zealand Transport Agency, Wellington National Office
23 February 2017 New Zealand Transport Agency, Wellington National Office Attn To: Colin Knaggs Private Bag 6995 Marion Square Wellington 6141 Dear Sir/Madam Notice of Resource Consent Decisions Record
More informationTake of water and H39: at a rate not exceeding 85 litres per second, with a volume not exceeding 7,344 cubic metres per day.
Record Number: Record Type: Permit Type: Record Holder: Record Status: File Number: Previous Record(s): Next Record(s): Location: Description: CRC011940 Renewal Water Permit (s14) Dannie William McAughtrie
More informationRequirement for the use of chemigation valves for backflow prevention in Canterbury
Requirement for the use of chemigation valves for backflow prevention in Canterbury E18/4303 1.0 CONTENTS 1.0 Contents... 2 2.0 Introduction... 3 3.0 Valve specifications... 4 4.0 Application requirements...
More informationTo construct or alter a bore
Resource Consent Application Form 9A To construct or alter a bore For office use only Consent o Job o Important notes for the applicant You must complete this application form 9A and Resource Consent Application
More informationGuidelines for water meter installation Looking after all our water needs
Guidelines for water meter installation 2009 Looking after all our water needs Department of Water Report no. 2 July 2009 Department of Water 168 St Georges Terrace Perth Western Australia 6000 Telephone
More informationThe discharge shall include stormwater generated during the construction phase of the subdivision.
Limits The discharge shall be only stormwater generated from: (a) Roofs, roads, hardstand areas, and pervious areas; and (b) Exposed areas during construction (optional); associated with the proposed [residential
More informationK.A.R Water flowmeter specifications. (a) Each water flowmeter required by the chief engineer, or required pursuant to a regulation adopted
K.A.R. 5-1-4. Water flowmeter specifications. (a) Each water flowmeter required by the chief engineer, or required pursuant to a regulation adopted by the chief engineer, on or after the effective date
More informationTaranaki Racing Club Groundwater Abstraction Monitoring Programme Report Technical Report
Taranaki Racing Club Groundwater Abstraction Monitoring Programme Report 2009-2013 Technical Report 2013-71 ISSN: 0144-8184 (Print) Taranaki Regional Council ISSN: 1178-1467 (Online) Private Bag 713 Document:
More informationThe Road to Metering the Irrigation Capital of New Zealand. Colin Bird. Michael Edmondson
The Road to Metering the Irrigation Capital of New Zealand Colin Bird Resource Management Officer Water Metering Michael Edmondson Senior Resource Management Officer RMA Monitoring & Compliance In the
More informationResource Consent: Groundwater Take
Application for Resource Consent: Groundwater Take A complete Administration Form (Form A) MUST accompany this Activity Information and Assessment Form (Form B) when lodging your application. The purpose
More informationMeter and Sub- Metering Technical Specifications
Meter and Sub- Metering Technical Specifications 24 July 2015 Table of Contents 1. Introduction... 3 2. Metering Technical Specifications... 3 2.1 Water Meter Types... 3 2.2 Water Service and Meter Sizing...
More informationRock River Water Reclamation District
Document Revised 5/25/99 Detail Revised 3/3/99 Rock River Water Reclamation District Sampling/Monitoring Manhole Installation Application for Approval - General Instructions 1) Prior to installing a sampling
More informationYW Wholesale Policy on the installation, repair and replacement of a Non-Household Water Meter 14/03/2017
YW Wholesale Policy on the installation, repair and replacement of a Non-Household Water Meter 14/03/2017 Classification (external) Contents Introduction... 4 Aim... 5 Exclusions from Market Codes... 5
More informationWater Resource (Burnett Basin) Plan 2000
Queensland Water Act 2000 Water Resource (Burnett Basin) Plan 2000 Reprinted as in force on 18 December 2009 Reprint No. 2A This reprint is prepared by the Office of the Queensland Parliamentary Counsel
More informationFlow Meter Calibration
fluid mechanics H4 A compact unit that compares and shows the accuracy, losses and use of fundamental flow meters Key Features Unique quick-change flow meter adaptors and pressure connections Four tube
More informationBackflow Prevention Containment Policy
Backflow Prevention Containment Policy This policy was established in May 2011 and revised in September 2014 and has been adopted by the following water authorities in Victoria: Page 1 of 12 Contents Operating
More informationREAL-TIME PUMP CONDITION MONITORING
REAL-TIME PUMP CONDITION MONITORING CHROMATECH TECHNOLOGIES Thermodynamic Pump Testing CHROMATECH TECHNOLOGIES How Thermodynamic Pump Testing Works Nearly all energy losses in pumps are transmitted through
More informationCity of Moss Landing, CA Sanitary Sewer Flow Monitoring SFE File #C Installation Report. Submitted To:
City of Moss Landing, CA Sanitary Sewer Flow Monitoring SFE File #C91-01 Installation Report Submitted To: MBARI Attention: Mr. Keith Raybould 7700 Sandholdt Rd Moss Landing, CA 95039-9644 Submitted By:
More informationSummary of relief sought by Dairy Holdings Limited
Summary of relief sought by Dairy Holdings Limited Evidence or legal submission paragraph reference Issue (including objective/policy /rule reference) Explanation Relief sought by DHL [5] [15] Definition
More informationto facilitate sewer mining by providing timely information, advice and responses to sewer mining enquiries and applications
Policy Sewer Mining 1. Overview Sewer mining is the process of tapping into a sewer, (either before or after the sewage treatment plant), and extracting sewage, which is then treated and used as recycled
More informationOrdinances of the Plainview Water District Town of Oyster Bay, Nassau County, New York ARTICLE VII CONTROL OF BACKFLOW AND CROSS-CONNECTIONS
ARTICLE VII CONTROL OF BACKFLOW AND CROSS-CONNECTIONS Section 7.1 STATEMENT OF POLICY It is the policy of the Water District to protect the public water system by containing potential contamination within
More informationThe Pipelines Regulations, 2000
PIPELINES, 2000 P-12.1 REG 1 1 The Pipelines Regulations, 2000 being Chapter P-12.1 Reg 1 (effective April 1, 2000) as amended by the Statutes of Saskatchewan, 2014, c.21; and by Saskatchewan Regulations
More informationImplementation of Magnetic Meters for Irrigation Volumetric Measurement. Stuart W. Styles 1 and Lynn Groundwater 2
Implementation of Magnetic Meters for Irrigation Volumetric Measurement Stuart W. Styles 1 and Lynn Groundwater 2 1 Professor, Cal Poly State University BioResource and Agricultural Engineering Dept. and
More informationSelf lay policy. Company specific addendum to Code of Practice for the self laying of Water Mains and Services England and Wales 2 nd Edition May 2009
Self lay policy and Company specific addendum to Code of Practice for the self laying of Water Mains and Services England and Wales 2 nd Edition May 2009 Issue 2 - May 2013 Contents Introduction Page 3
More informationSPECIFICATION. Category: Cold Water Meter Type: Ultrasonic Transit-Time Size: 2 12 Applicable AWWA Standard: C750. Version 2.18
SPECIFICATION Category: Cold Water Meter Type: Ultrasonic Transit-Time Size: 2 12 Applicable AWWA Standard: C750 Version 2.18 Master Meter, Inc. 101 Regency Parkway, Mansfield, TX 76063 T: 817-842-8000
More informationGeneral Accreditation Criteria Equipment assurance, in-house calibration and equipment verification
General Accreditation Criteria Equipment assurance, in-house calibration and equipment verification January 2018 Copyright National Association of Testing Authorities, Australia 2009 This publication is
More informationAppendix III EUR.1 MOVEMENT CERTIFICATE AND APPLICATION FOR AN EUR.1 MOVEMENT CERTIFICATE
29.9.2000 1063 Appendix III EUR.1 MOVEMENT CERTIFICATE AND APPLICATION FOR AN EUR.1 MOVEMENT CERTIFICATE 1. Each form shall measure 210 297 mm; a tolerance of up to minus 5 mm or plus 8 mm in the length
More informationMaterials and Qualification Procedures for Ships
Materials and Qualification Procedures for Ships Approval of a Works for the Manufacture of Non-heat treated ERW Steel Pipes Revision 2, Sept 2014 Lloyd s Register Group Limited, its subsidiaries and affiliates
More informationCONTROL OF ON-SITE WASTEWATER DISPOSAL SYSTEMS
FAR NORTH DISTRICT COUNCIL BYLAWS CONTROL OF ON-SITE WASTEWATER DISPOSAL SYSTEMS To come into force: 1 July 2010 For the purpose of: Ensuring that all On-Site Wastewater Disposal Systems in operation or
More informationNational Environmental Monitoring Standards. Water Meter Data. Acquisition of Electronic Data from Water Meters for Water Resource Management
National Environmental Monitoring Standards Water Meter Data Acquisition of Electronic Data from Water Meters for Water Resource Management Version: 1.0 Date of Issue: June 2013 NEMS Standards Documents
More informationORC MINIMUM REQUIREMENTS FOR THE MEASUREMENT AND REPORTING OF WATER TAKES
ORC MINIMUM REQUIREMENTS FOR THE MEASUREMENT AND REPORTING OF WATER TAKES Otago Regional Council Version 7 1 Version No.: 7 Latest Revision date: 1 September 2017 Prepared by: Rachel Brennan Reviewed by:
More information4. The current Civil Engineering Specification for the Water Industry (CESWI).
Bristol Water plc Addendum to the Code of Practice for the Self-Laying of Water Mains and Services - England and Wales 2 nd Edition May 2009 & Addendum to the Self Lay Code of Practice (2 nd Edition) National
More informationTest Report TR1R1
1 CLIENT DETAILS Organisation: Company Contact: Origin Energy Services Ltd Eoghain Maguire Site Address: 101-103 Miller Street, North Sydney NSW 2060 Postal Address: Level 7, 321 Exhibition Street, Melbourne
More informationLAYING NEW WATER SUPPLY PIPES
LAYING NEW WATER SUPPLY PIPES www.nwl.co.uk waterregs@nwl.co.uk @nwater_care 0191 419 6583 0191 419 6664 Water Regulations Department Northumbrian Water Leat House Pattinson Road Washington NE38 8LB LAYING
More informationCEN Keymark Scheme Rules for Thermostatic Radiator Valves. 2 nd Edition
CEN Keymark Scheme Rules for Thermostatic Radiator Valves 2 nd Edition Content Foreword... 3 Introduction... 3 1 Scope... 4 2 References... 4 3 Terms and Definitions... 4 4 Application... 5 4.1 Product
More informationMinistry of the Environment and Climate Change. MOUNT FOREST DRINKING WATER SYSTEM Inspection Report. Inspection Number:
Site Number: Inspection Number: Date of Inspection: Inspected By: 220000068 1-BZMYF Nov 25, 2015 Martha Weber Drinking Water System Mount Forest Drinking Water System DWS# 220000068 2015/16 Focused TABLE
More informationCompany specific addendum
Self lay policy and Company specific addendum to Code of Practice for the self laying of Water Mains and Services England and Wales 2 nd Edition May 2009 Issue 1.0 - April 2015 life fl ow smoothly helping
More informationMaterials and Qualification Procedures for Ships
Materials and Qualification Procedures for Ships Approval of a Works for the Manufacture of Chain Cable for ships Revision 2, April 2015 Page 1 of 19 Lloyd s Register Group Limited, its subsidiaries and
More informationPALMERSTON NORTH CITY PALMERSTON NORTH WATER SUPPLY BYLAW
PALMERSTON NORTH CITY PALMERSTON NORTH WATER SUPPLY BYLAW 2015 Contents PART ONE INTRODUCTION... 3 1. Title... 3 2. Purpose... 3 3. Commencement... 3 4. Repeals... 3 5. Application... 3 6. Definitions...
More informationCross Connection Control And Backflow Prevention Program. City of Rifle, Colorado Utility Department
Purpose The purpose of this program is to protect the public water system from contaminants or pollutants that could enter the distribution system by backflow from a customer s water supply system through
More informationNew Zealand Technical Standard Order NZTSO 2001
New Zealand Technical Standard Order NZTSO 2001 Revision 1 Time in Service Recorders 17/11/15 Published by Civil Aviation Authority PO Box 3555 WELLINGTON 6140 NEW ZEALAND Approved by Manager Aircraft
More informationApproved Code of Practice Under the Hazardous Substances and New Organisms (HSNO) Act 1996
New Zealand Timber Preservation Council P O Box 308 WELLINGTON Code of Practice for the Management of Existing Stationary Container Systems at Timber Treatment Facilities Approved Code of Practice Under
More informationARTICLE 11 - Backflow Prevention and Cross Connection Control
ARTICLE 11 - Backflow Prevention and Cross Connection Control 11.1 Purpose. The purpose of this Resolution is to adopt a Backflow Prevention and Cross-Connection Control Policy ( Policy ) in order to protect
More informationTest Report TR1R0
1 CLIENT DETAILS Organisation: Company Contact: Cogent Energy Pty Ltd Eoghain Maguire Site Address: 101-103 Miller Street, North Sydney NSW 2060 Postal Address: Suite 2, Level 9, 1 Chandos Street, St Leonards
More informationCapital Projects Group Air Terminal Units Specification
Capital Projects Group Air Terminal Units Specification Specification 23 36 00 Revision 0 Date: August 2018 Air Terminal Units Specification Specification 23 36 00 Publication Date: August 2018 COPYRIGHT
More informationMETHOD 1A - SAMPLE AND VELOCITY TRAVERSES FOR STATIONARY SOURCES WITH SMALL STACKS OR DUCTS. NOTE: This method does not include all of the
206 METHOD 1A - SAMPLE AND VELOCITY TRAVERSES FOR STATIONARY SOURCES WITH SMALL STACKS OR DUCTS NOTE: This method does not include all of the specifications (e.g., equipment and supplies) and procedures
More informationExhibit A. Scope of Services for Flow Monitoring Program 2015 Flow Monitoring City of Lawrence, Kansas
Exhibit A Scope of Services for Flow Monitoring Program 2015 Flow Monitoring City of Lawrence, Kansas Intent and Purpose The City of Lawrence has begun a Rapid Inflow and Infiltration (I/I) Reduction Program.
More informationExisting System Evaluation Report for Onsite Wastewater Systems
Existing System Evaluation Report for Onsite Wastewater Systems State of Oregon Department of Environmental Quality Onsite Program 165 East 7 th Avenue, Suite 100 Eugene, Oregon 97401 For more information,
More informationANNEX III A TO PROTOCOL B. Specimens of movement certificate EUR 1 and application for a movement Certificate EUR 1. Printing instructions
ANNEX III A TO PROTOCOL B Specimens of movement certificate EUR 1 and application for a movement Certificate EUR 1 Printing instructions 1. Each form shall measure 210 x 297 mm; a tolerance of up to minus
More informationDillon Valley District
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 Dillon Valley District Backflow Prevention and Cross-connection Policy The legal authority
More informationEmissions Testing Report 2014
Orora Limited 09-Apr-2014 Emissions Testing Report 2014 Orora Limited NATA ACCREDITATION No. 2778 (14391) Accredited for compliance with ISO/IEC 17025 This document is issued in accordance with NATA s
More informationEmissions Testing Report 2015
Orora Limited 20-Jul-2015 Emissions Testing Report 2015 Orora Limited NATA ACCREDITATION No. 2778 (14391) Accredited for compliance with ISO/IEC 17025 This document is issued in accordance with NATA s
More informationWater Measurement Programme - Bay of Plenty Region
Water Measurement Programme - Bay of Plenty Region Prepared for Environment Bay of Plenty Report No H07006/1 August 2007 Disclaimer: This report has been prepared solely for the benefit of Environment
More informationCharlottetown - Water & Sewer Utility Minimum Standard of Acceptability for Water, Sewer & Sprinkler Connections
Charlottetown - Water & Sewer Utility Minimum Standard of Acceptability for Water, Sewer & Sprinkler Connections At the time of application for water, sewer and/or sprinkler service the applicant shall
More information401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply:
SECTION 400 SANITARY SEWER SYSTEM The design of sanitary sewers shall be in conformance with the applicable sections of the State of Washington, Department of Ecology manual, Criteria for Sewage Works
More informationResource Consent Application - Removal/Remediation of Flare/Blowdown Pit at Kapuni Well site KA2 for Shell Todd Oil Services Ltd
27 March 2012 Project No. 42780930 South Taranaki District Council Private Bag 902 Hawera, 4640 Attention: Blair Sutherland Dear Blair Subject: Resource Consent Application - Removal/Remediation of Flare/Blowdown
More informationPublic Water Supply District No. 3 of Franklin County 150 Old Highway 100 PO Box 160 Villa Ridge, MO
Public Water Supply District No. 3 of Franklin County 150 Old Highway 100 PO Box 160 Villa Ridge, MO 63089 636-742-5200 Superintendent: Bob Hathcock Operations Supervisor: Terry McDaniel 2018-2019 WATER
More informationIvins City Standard Specifications for Design and Construction Part 2 Engineering and Design Standards
2.9. WATER SYSTEM DESIGN Ivins City Standard Specifications for Design and Construction All culinary water mains and appurtenances shall be designed to provide for adequate future service for all contiguous
More informationSECTION Inline ULTRASONIC FLOW METERS
SECTION 40 71 66 Inline ULTRASONIC FLOW METERS PART 1- GENERAL 1.01 SUMMARY A. Ultrasonic flow meters for permanent in line installations. The meters shall utilize a transit time ultrasonic principle of
More informationCapital Projects Group Mechanical Work Commissioning Specification
Capital Projects Group Mechanical Work Commissioning Specification Specification 20 05 40 Revision 0 Date: August 2018 Mechanical Work Commissioning Specification Specification 20 05 40 Publication Date:
More informationUltrasonic clamp-on technology Flow measurement from outside the pipe. Cost-effective flexible robust
Ultrasonic clamp-on technology Flow measurement from outside the pipe Cost-effective flexible robust Benefits of ultrasonic clamp-on No process shutdown Install quickly whenever and wherever flow measurement
More informationThe Forest Resources Management (Saskatchewan Environmental Code Adoption) Regulations
FOREST RESOURCES MANAGEMENT 1 CODE ADOPTION) F-19.1 REG 11 The Forest Resources Management (Saskatchewan Environmental Code Adoption) Regulations being Chapter F-19.1 Reg 11 (effective January 5, 2015).
More informationMAYER STAINLESS STEEL PRESS-FIT PIPING SYSTEM. Product. Scope. Building Regulations. Appraisal No [2018] Appraisal No.
MAYER STAINLESS STEEL PRESS-FIT PIPING SYSTEM BRANZ Appraisals Technical Assessments of products for building and construction. Product 1.1 The Mayer Stainless Steel Press-Fit Piping System consists of
More informationE5. On-site and small scale wastewater treatment and disposal
E5. On-site and small scale wastewater treatment and disposal E5.1. Background On-site wastewater systems are utilised for residential dwellings, commercial and industrial activities and facilities not
More informationRegarding the issuing of a building consent for the separation of surface water drainage to 39 and 39A Towai Street, Kohimarama, Auckland
Determination 2013/001 1 Regarding the issuing of a building consent for the separation of surface water drainage to 39 and 39A Towai Street, Kohimarama, Auckland 1. The matters to be determined 1.1 This
More informationPlan Change 5 to the Canterbury Land and Water Regional Plan
Plan Change 5 to the Canterbury Land and Water Regional Plan Table of contents PART 1 (HOW TO READ THIS DOCUMENT)... 1-1 Introduction... 1-2 Information for the Reader... 1-2 How amendments to the Plan
More informationPortable Ultrasonic Flow Meters Ultrasonic Flow Meters Handheld Ultrasonic Flowmeter Wallmounted Ultrasonic Flow Meter Explosion Proof Ultrasonic
1 Portable Ultrasonic Flow Meters Ultrasonic Flow Meters Handheld Ultrasonic Flowmeter Wallmounted Ultrasonic Flow Meter Explosion Proof Ultrasonic Flow Meter Pipe Type Ultrasonic Flow Meter Portable Ultrasonic
More informationMID R 800 AMR READY N E W MID R=800 ULTRIMIS W DATA APPLICATION WATER MEASUREMENT
SMART THINKING WATER ULTRIMIS W ULTRASONIC WATER METER DN15, DN20, D25 i DN32 MID R 800 AMR READY Ultrimis W a state-of-the-art ultrasonic water meter with the very latest patented design features including
More informationCRAFTSMAN EXAMINATION, NOVEMBER 2008 PLUMBING ANSWER SCHEDULE
No. 9195 CRAFTSMAN EXAMINATION, NOVEMBER 2008 PLUMBING ANSWER SCHEDULE Plumbers, Gasfitters and Drainlayers Board, 2008. All rights reserved. No part of this publication may be reproduced by any means
More informationWASTEWATER DRAINAGE BYLAW
WASTEWATER DRAINAGE BYLAW 2018 Pursuant to Section 145 of the Local Government Act 2002 and every other enabling power and authority. To come into force: 1 July 2018 For the purpose of: a) Controlling
More informationInstallation of sanitary sewers, storm sewers and water piping requires the issuance of a Building Permit prior to commencement of installation.
Development and Infrastructure Department 50 Dickson St., 3rd Floor, P.O. Box 669 Cambridge, Ontario. N1 R 5W8 519.621.0740; TTY 519.623.6691 Site Service Installation - Rational Sampling Program RE: Building
More informationON-FARM WATER CONSERVATION PROGRAM 2013 PROGRAM DESCRIPTION SOUTH SAN JOAQUIN IRRIGATION DISTRICT
ON-FARM WATER CONSERVATION PROGRAM 2013 PROGRAM DESCRIPTION SOUTH SAN JOAQUIN IRRIGATION DISTRICT Table of Contents Background and Objectives... 2 Enrollment Process... 3 Solicitation and Application Process...
More informationAWS D10.18M/D10.18:2018 An American National Standard. Guide for Welding Ferritic/Austenitic Duplex Stainless Steel Piping and Tubing
An American National Standard Guide for Welding Ferritic/Austenitic Duplex Stainless Steel Piping and Tubing An American National Standard Approved by the American National Standards Institute November
More informationSECTION ULTRASONIC TRANSIT TIME CLAMP-ON FLOW MEASURING SYSTEM
SECTION 40 71 66 ULTRASONIC TRANSIT TIME CLAMP-ON FLOW MEASURING SYSTEM PART 1-GENERAL 1.01 SUMMARY A. Ultrasonic clamp-on flow measurement system designed for non-intrusive external to pipe measurement
More informationSection 12 Hydraulics.
Design Guidelines Section 12 Hydraulics. www.canterbury.ac.nz/learningresources Standards in the Design Guidelines Suite Design Standard Guidelines Index: 01 General 02 Architecture 03 Audio Visual 04
More informationSupporting Guidance (WAT-SG-85)
Water Use Supporting Guidance (WAT-SG-85) Application of Standards to Thermal Discharges Version: v3.0 Released: Aug 2016 Copyright and Legal Information Copyright 2016 Scottish Environment Protection
More informationTechnical Bulletin. Permit to Take Water Program Monitoring and Reporting of Water Takings. November 2006
November 2006 Technical Bulletin Permit to Take Water Program Monitoring and Reporting of Water Takings This bulletin is to assist permit holders in understanding the monitoring and reporting requirements
More informationRESIN & WAX HOLDINGS LIMITED, PO BOX 5228, WELLESLEY STREET, AUCKLAND 1141
Resource Consent FILE: 39163 (01 07) New Document Date: 29.03.2018 Pursuant to the Resource Management Act 1991, the Northland Regional Council (hereinafter called the Council ) does hereby grant a Resource
More informationStandard terms and conditions
Standard terms and conditions Development Services For the provision of a water service (Water Supply, Wastewater and Drainage) Introduction Under Section 73(2)(a) of the Water Services Act 2012, landowners
More informationAPPLICATION FOR A PERMIT TO CONSTRUCT A WATER WELL IN THE LOWER PLATTE NORTH NATURAL RESOURCES DISTRICT
APPLICATION FOR A PERMIT TO CONSTRUCT A WATER WELL IN THE LOWER PLATTE NORTH NATURAL RESOURCES DISTRICT DNR & NRD USE ONLY Permit No. Date Approved/Denied NRD Representative Permit Type: New, Replacement
More informationAppendix III to Annex V SPECIMEN OF MOVEMENT CERTIFICATE EUR.1 AND APPLICATION FOR A MOVEMENT CERTIFICATE EUR.1. Printing instructions
Appendix III to Annex V SPECIMEN OF MOVEMENT CERTIFICATE EUR.1 AND APPLICATION FOR A MOVEMENT CERTIFICATE EUR.1 Printing instructions 1. Each form shall measure 210 x 297 mm; a tolerance of up to minus
More informationSECTION CROSS CONNECTION CONTROL AND BACKFLOW PREVENTION
SECTION 22 11 16.13 CROSS CONNECTION CONTROL AND BACKFLOW PREVENTION PART 1: GENERAL 1.01 SUMMARY A. This Section includes water-distribution backflow prevention products and installation specifications.
More informationUniversity of Bath Generic Metering Specification (Rev6)
University of Bath generic metering specification The University of Bath has made a major commitment to reduce energy consumption and improve the sustainability of its activities. An essential part of
More informationWhat ensures measurement to accurate standards?
What ensures measurement to accurate standards? The SITRANS FUT1010 calibrated ultrasonic flow meter tells you exactly what s flowing Answers for Industry. SITRANS FUT1010 Custody transfer accuracy with
More informationENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009
ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN Environment Protection Authority, ACT May 2009 ISBN-13: 978-0-642-60494-1 ISBN-10: 0-642-60494-0 Australian Capital Territory,
More informationUNDER THE Resource Management Act 1991 STATEMENT OF EVIDENCE OF ANNA MARY WILKES ON BEHALF OF RAVENSDOWN LIMITED
BEFORE THE CANTERBURY REGIONAL COUNCIL UNDER THE Resource Management Act 1991 AND IN THE MATTER of application CRC190445 to Canterbury Regional Council by the Christchurch City Council for a comprehensive
More informationComposite-wrapping services
Maintenance, Repair & Overhaul INVESTMENT OPPORTUNITY: Composite-wrapping services Executive summary Localize composite wrapping services in Qatar. The local capabilities should include a composite wrapping
More informationNgaruroro River Flow Naturalisation
Prepared for Hawkes Bay Regional Council 15 MARCH 2010 This document has been prepared for the benefit of Hawkes Bay Regional Council. No liability is accepted by this company or any employee or sub-consultant
More informationWASTEWATER AND STORM DRAINAGE REGULATION
Province of Alberta ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT WASTEWATER AND STORM DRAINAGE REGULATION Alberta Regulation 119/1993 With amendments up to and including Alberta Regulation 170/2012 Office
More informationBackflow explained About backflow prevention containment. Backflow explained. About backflow prevention containment. Page 1
Backflow explained About backflow prevention containment Backflow explained About backflow prevention containment Page 1 Backflow Prevention Containment Policy Sydney Water is licensed to operate water,
More informationUnderground Piping for Private Hydrants & Sprinkler Supply Line
City of Brea Brea Fire Department Fire Prevention 1 Civic Center Circle Phone: (714) 990-7655 Underground Piping for Private Hydrants & Sprinkler Supply Line PURPOSE The provision of adequate water supplies
More informationDam Safety Surveillance. Templates for very low, low consequence category dams
Dam Safety Surveillance Templates for very low, low consequence category dams The State of Victoria Department of Environment, Land, Water and Planning 2015 This work is licensed under a Creative Commons
More informationWAT-TEMP-68. Water Resource Monitoring Plan Template. Water Use. Authorisation Number : Site Address :
Water Use WAT-TEMP-68 Water Resource Monitoring Plan Template Authorisation Number : CAR/L/ Site Address : Prepared By: Name: Job Title: Contact Telephone Number: E-mail address: Date Submitted : Version:
More informationQP 02 Audit and Certification Procedure
1. AUDIT PROGRAMME [9.1.1] The audit programme shall be conducted in stages within a 3-year certification cycle as follows; Initial audit: Two stage process Surveillance audit: Conducted in the first and
More informationACCURATE MEASUREMENT OF MINIMUM NIGHT FLOWS FOR WATER LOSS ANALYSIS. Melanie Werner
ACCURATE MEASUREMENT OF MINIMUM NIGHT FLOWS FOR WATER LOSS ANALYSIS Paper Presented by: Melanie Werner Authors: Melanie Werner, Water Loss Engineer, Ian Maggs, Program Manager, Marko Petkovic, Water Loss
More informationApplication For Resource Consent to Construct or Alter a Bore
Application For Resource Consent to Construct or Alter a Bore (Including Changes to Conditions of Current Resource Consents) PART A: Contact Details Pursuant to Section 88 of the Resource Management Act
More informationEnvironment Canterbury regional council works with the people of Canterbury to manage the region s air, water and land. We are committed to the
How to apply Environment Canterbury regional council works with the people of Canterbury to manage the region s air, water and land. We are committed to the sustainable management of our environment while
More informationProducer Statement. Design: On-Site Effluent Disposal Systems (AS/NZS 1547:2000)
Updated 04/09/13 Producer Statement Design: On-Site Effluent Disposal Systems (AS/NZS 1547:2000) Issued by : To : To be supplied to: Property Location:. (approved qualified design professional) (owner)