THE YEMEN LNG PROJECT LE PROJET GNL YEMEN

Size: px
Start display at page:

Download "THE YEMEN LNG PROJECT LE PROJET GNL YEMEN"

Transcription

1 THE YEMEN LNG PROJECT LE PROJET GNL YEMEN Jean Paul Azalbert Dr. Khaled Muhsin Frank Kern Yemen LNG Company Republic of Yemen ABSTRACT The Yemen LNG Project is on its way now for two years. The paper focuses on the technical part of the substantial efforts carried out so far by Yemen LNG Company, from Project Definition through the Call for Tenders Documents. RESUME Le projet GNL Yémen est maintenant à l étude depuis deux ans. La présentation est centrée sur la partie technique de l important travail réalisé par la Yémen LNG Company, depuis la définition du projet jusqu aux documents d appel d offre

2 THE YEMEN LNG PROJECT 1. BACKGROUND The valorization of the gas reserves of Marib fields in Yemen under the form of LNG has been envisaged now for six years. After several attempts to materialize this project, Yemen sent in 1994 a call for tender to various possible Project. On February 1, 1995, the Yemeni Council of Ministers designated TOTAL as the Lead shareholder of the Yemen LNG Project. Shortly thereafter, in early 1995, negotiations were initiated with the Marib field shareholders, for their affiliates joinder to the Project, i.e., EXXON YEMEN LNG COMPANY Ltd (EYLNG), YEMEN HUNT LNG LLC (YHLNG), and YUKONG LIMITED (YUKONG). In September 1995, the Ministry of Oil and Mineral Resources (MOMR), Yemen Gas Company (YGC) and TOTAL signed a Gas Development Agreement to be further approved by the Parliament of the Republic of Yemen. As a consequence, the YEMEN LNG COMPANY (YLNG) was incorporated in Bermuda, for the purpose of implementing the project; its initial shareholders were YGC and TOTAL YEMEN LNG COMPANY (TYLNG). The YLNG Company has been created to process, to export and to sell LNG for a period of 25 years after commencement of Commercial Production, transporting the feed gas from the Marib fields to the LNG Plant, and delivering feed gas to YGC in the North of Sana a area, through a Spur Line, and to construct all corresponding facilities. A Project Definition study was performed by the Lead Shareholder from July 1995 to March 1996: the design criteria of the facilities were defined and the selection of the LNG Plant site and of the pipeline routes were made. For that purpose, a data acquisition campaign was launched on the different potential sites, with topographical and geo-technical surveys. Out of six potential sites surveyed in June 1995, Bal-Haf was selected on the Gulf of Aden coast, approximately 160 km West of Al-Mukalla, 320 km south east of the gas producing field of Marib and 450 km east of Aden. The pipeline routes between the Marib area and the delivery points in Bal-Haf and near Sana a were also identified. The selections of both the pipeline routes and the Bal-Haf site were endorsed by MOMR. As part of the Project Definition studies, after various feasibility scenarios, a Statement of Requirement was developed with identification and selection of all governing principles of the facilities, the selection of the base processing case with Air Products and Chemicals, Inc. (APCI) and the definition of the scope of the Front End Engineering Design phase which commenced in March

3 In January 1997, MOMR, YGC and TOTAL in conjunction with EYLNG, YHLNG, and YUKONG, plus associates of some of these companies, signed 7 Agreements as applicable: The Gas Development Agreement (GDA) The Upstream Facilities and Services Agreement The Subscription & Participation Agreement The Shareholders Agreement The Upstream Operating Agreement The Upstream Joint Venture & Shareholders Agreement The Feed Gas Delivery Agreement Both the Gas Development Agreement and the Upstream Facilities and Services Agreement were ratified by the Parliament of the Republic of Yemen, prior to the issue of a Presidential Decree in March The final closing between the initial and new shareholders also took place in March As of year-end 1997, the Front End Engineering Design was complete as was the preparation of the calls for tender packages. The lists of potential tenderers have been approved by the Board and MOMR, based on completed prequalification process. 2. SHAREHOLDERS YLNG current shareholders are: % TOTAL YEMEN LNG COMPANY LTD (lead shareholder) YEMEN GAS COMPANY YEMEN HUNT LNG COMPANY LLC EXXON YEMEN LNG COMPANY LTD YUKONG LIMITED PROJECT PHASES The project will be implemented in three phases : Phase 1 : The Preliminary Phase, comprising the conceptual design work and the Front End Engineering Design and preparation of the calls for tenders 4.4 3

4 Phase 2 : Construction Phase This phase extends from the date on which YLNG notifies Ministry of its decision to proceed with Phase 2 until Commencement of Commercial Production and shall include all works related to engineering, procurement and construction. Phase 3 : The Commercial Production Phase That phase extends from the date of Commencement of Commercial Production, i.e., the date at which the first regular export of LNG occurs, and shall last at least 25 years. 4. PROJECT DESCRIPTION 4.1. The Fields / The Upstream Facilities Under a Production Sharing Agreement(PSA) with MOMR, Yemen Exploration and Production Company (YEPC) - the Upstream Operator - is currently operating the fields of Block 18, located in the Marib area, approximately 190 km East of Sana a. The gas is processed for LPG extraction and condensate C5 + recovery, prior to reinjection, at the production units located at Alif Central Processing Unit (CPU) and at Kamil Processing Unit (KPU). Out of the bpd of LPG currently produced, bpd supply the current local market, and the surplus is re-injected with the treated gas. The field reserves have been certified by the certifying independent agent DeGolyer and MacNaughton, who confirmed that the reserves were ample to support the Project. A gas analysis campaign performed during the 1996 spring has shown a gas of good quality, ideal as liquefaction plant feed: low nitrogen low carbon dioxide no hydrogen sulfide nor sulfur components no mercury A total of about MMscfd (stream day) of gas are currently produced from 15 fields in the Marib area, with the great majority (95 %) coming from major fields: Al Raja (condensate gas field), Kamil (oil field), Azal (oil field) and Alif (oil field). Some other smaller gas accumulations, already delineated but not developed yet, will be put on production at a later stage according to a Long Term Gas Delivery Plan which is being performed

5 Out of these MMscfd, approximately MMscfd are re-injected into different dedicated reservoirs, of which: 1600 MMscfd are processed through four Natural Gas Liquids (C3 + ) extraction plants: one lean oil absorption plant and one cryogenic extraction plant at the CPU and two cryogenic extraction plants at the KPU 400 MMscfd are by-passing these NGL plants. All along the project life, upstream facilities will be installed and/or modified to meet the LNG project requirement with respect to the quality and quantity of the feed gas. At the early stage of the project, the required new Upstream Facilities were identified as follows: drying of the NGL Cryogenic plant by-pass (mole sieve unit) in order to avoid any water condensation in the main line, minimization of C5+ in the LNG feed gas by processing all or a portion of currently by-passed gas. letdown stations in order to deliver the feed gas at the delivery point at sufficient pressure to enter the mainline, 2 metering stations for custody transfer, flaring facilities, all necessary ties-in, manifolding and interconnecting piping. The studies / modifications to the upstream facilities are performed by YEPC, but at YLNG costs. Currently, YEPC is performing the studies which are part of the approved YEPC 1997 Work Program The Pipelines The project will include three pipelines that will traverse widely varied topography and elevations: For the 2 liquefaction train LNG Plant, the 320 km long, 36 diameter Main Line will transport feed gas from KPU to Bal-Haf at an initial flow rate of approximately 900 MMscfd. Additional flow rate for a potential third liquefaction train at Bal-Haf can be obtained with the installation of an intermediate booster compression station located near Mikrab, 40 km North East from Ataq. Associated with the Main Line, the 26 km long, 20 diameter Transfer Line transports gas between CPU and KPU through a flat desert area of sand dunes at a flow rate corresponding to the requirements of the two train LNG plant. The 200 km long, 14 diameter Spur Line will transport, for MOMR use, gas from CPU to a delivery point North of Sana a at an initial flow rate of 100 MMscfd and with an ultimate potential flow rate of 250 MMscfd by installing future intermediate compressor stations

6 These three pipelines will be: operated dry, free of any liquid hydrocarbons and water, designed according to ASME B 31.8 code requirements, including sectionalization block valves, buried, of grade API 5L, X 70 steel, and externally protected with a polyethylene coating. The pipeline parameters and block valves will be controlled by a System Control And Data Acquisition (SCADA system); a fiber optic cable installed parallel to the pipeline will provide communication links. The electrical power needed for emergency shut down valves, SCADA system, and permanent cathodic protection by impressed current, will be supplied, for the extremity sections, respectively from CPU, KPU and the Bal-Haf plant. For each intermediate block valve station, thermo electric generator units will be installed The LNG Plant The LNG Plant will be constructed on a 120 hectare site at Bal-Haf. It will be fully self supporting, independent of any local infrastructure and will include administrative buildings, process facilities, utilities, offsites and a marine terminal. Admin Zone The administrative zone includes a group of buildings, among which are: administrative building canteen medical center training center and other infrastructure needed to support plant operations. Process Area The plant will be designed for minimum capital cost within the limits set by efficiency, reliability, safety and environmental impact. Based on 335 stream days per year, two liquefaction plants in parallel will be installed to achieve an annual guaranteed production of 5.3 million metric tonnes per year, FOB. The two train LNG Plant will have the following major process / product handling facilities, as listed here below: Feed gas reception facilities Acid gas (CO 2 ) removal 4.4 6

7 Dehydration Liquefaction system LPG Fractionation for refrigerant make-up and C5+ removal. Prior to liquefaction, the carbon dioxide content of the natural gas will be reduced to 50 ppmv in an amine type acid gas removal unit. Water content will be reduced to 1 ppmv in a molecular sieve unit to prevent any freeze out in the cryogenic sections of the plant. A mercury guard bed will be installed to ensure removal of any trace amounts of mercury, although none has been detected in the feed to date. The liquefaction process is based on Air Products and Chemicals, Inc. (APCI) Propane / Multi Component Refrigerant (MCR) process, which requires a propane refrigerant cycle multistage centrifugal compressor driven by a Frame 7 - size gas turbine and a centrifugal / axial compressor for the mixed refrigerant liquefaction cycle, also driven by a Frame 7 - size gas turbine. The overall refrigerant power required for a train of 2.65 Mtpa is approximately 115 MW, of which 66 MW are required for the liquefaction cycle. As a component of their license, APCI are also supplying the spool wound Main Cryogenic Heat Exchanger (MCHE) for gas liquefaction. Utilities Area To support the operation of the LNG Trains, the following common facilities are required: Flare systems Electrical power generation - main and emergency Cooling media Heating media Fuel systems Nitrogen generation Compressed air Fire protection systems Fresh water Telecommunications Surface drainage Direct sea water cooling will be used, with a sea water flow of m 3 per hour, for the two trains. Low pressure steam will be used as heating medium. Three Frame 6 power generation sets will be installed to supply the power required for plant operations. The fuel gas required will be supplied from the LNG trains and by the boil off gas from the storage area. Fuel gas demand represents 10 to 12 % of the total gas feed to the plant

8 Storage LNG produced will run down to two storage tanks at a temperature of degree Celsius, with a higher heating value (HHV) in the / Btu/scf range. The LNG net storage capacity, based on transportation studies, is m3. Two m3 tanks will be installed. For safety reasons, we have selected above ground full containment tanks with either a concrete outer shell and a free standing 9% Nickel alloy inner tank, or a stainless steel membrane in a concrete outer shell. Marine Facilities All the components of a self sufficient LNG marine terminal will be installed, including a turning basin, a service vessel / tug berth and a marine base. A single berth will be installed to accommodate LNG carriers in the / m3 range. The location, orientation and design of the berth have been considered with due attention to weather, sea and meteorological conditions, mooring breasting, tug assistance, access and departure in case of emergency. Marine Off-loading facilities (M.O.F.) will also be installed for unloading of equipment for the LNG plant during the construction period. Off Plot Facilities In addition to the above, an air strip for Dash 7 type planes, available take-off 950x45 m, for normal day light shift rotation, will be installed at a short distance, North West of the Plant. An access road will link the main Al Mukala / Aden road to the LNG Plant and to the Permanent Camp Pre investment for a Third Train In view of a potential 50% increase in the capacity of the liquefaction plant, the possibility of installing a third process train and a third LNG storage tank, with associated utilities and plant layout is taken into account in the current design. Permanent Camp Its location is on the Bal Haf North Rock situated to the West of the access road to the LNG Plant, at the crossing with the main AL Mukalla / Aden road, close to the Construction Camp area of the LNG Plant. The Operating Organization is not yet finalized, but for current design purposes, it is assumed that approximately 700 persons will be accommodated in the Permanent Camp, with m 2 floor space on a 58 hectare area

9 The personnel to be accommodated in this Camp is YLNG Payroll personnel for normal operation, routine maintenance and support services. 5. CONTRACTING/IMPLEMENTATION One of YLNG objective is to finance the Project through non recourse, Project financing credits and Export Credit Agencies (ECA s) General During the preparation of the call for tender for the Front End Engineering Design (F.E.E.D.) of the whole facilities (pipelines and liquefaction plant), the following contracting strategy was envisaged for the construction phase of the works: construction contracts will be lump sum, contracts will be awarded by installations, and not by disciplines, number of contracts will be kept to a minimum, some Early Contracts (LNG storage, refrigeration compressors, Main Cryogenic Heat Exchangers, ) will be prepared during the F.E.E.D. period, and ultimately assigned to the selected Main contractor, constraints of non recourse financing will have to be considered, monitoring and control will be made by the Project Task Force. YLNG Contracting Strategy aims to fulfill 3 objectives: to select EPC contractors who will provide their specific LNG experience to design, procure, supply, erect and commission fit-for-purpose facilities, to obtain cost effective implementation through competitive bidding, to maximize non recourse financing by providing to the banking community the comfort of a frozen project cost guaranteed by sound and capable contractors. In order to reach these objectives, the following actions have been / will be implemented: launching a pre-qualification exercise to ensure that the most experienced construction contractors are selected (done), providing calls for tender dossiers with an adequate level of engineering and data acquisition details to allow for all inclusive lump sum quotes. defining a minimum number of bid packages to limit to a bare minimum the potential claims and corresponding increase in investment costs, by reducing interfaces between contractors and between YLNG and the construction contractors (done). The contracting strategy was endorsed by the Board of Directors

10 5.2. Action plan Pipeline A pre-qualification questionnaire was issued, answers analyzed, recommendation endorsed by YLNG Board and approved by MOMR. In order to obtain, from the various potential EPC pipeline laying contractors, comprehensive quotes without any qualifications relating to soil conditions and to route changes, an aerial survey of the routes has been performed and precise mapping of all areas has been completed. In addition, a geo-technical survey of the entire pipeline routes has been made. This will allow the incorporation of all pertinent data into the pipeline alignment sheets. The call for tender dossier for the installation of the pipeline consists in the base case of a single package with the Main Line + Transfer Line as one sub package (to be installed first), with the Spur Line as a second sub-package to be sequentially installed. As an option, independent quotes will be solicited for the Main Line + the Transfer Line on one side, and the Spur Line on the other side. Taking into account the importance of the supply of the line pipe, a pre-qualification exercise has been implemented to identify potential steel mills. The line pipe supply could be considered as a Long Lead / Critical Item to be assigned to the EPC contractor(s), or, as the supply of the line pipe is not on the critical path of the Project, could be directly incorporated into the scope of supply of the EPC contractor(s), depending upon the best interest of the Project. LNG Plant A pre-qualification questionnaire was issued, answers assessed, recommendation endorsed by YLNG Board and approved by MOMR. Long Lead / Critical Items A few parts of the facilities have a major impact on cost, schedule and / or on the technical content of the Project; accordingly, Long Lead / critical Items have been identified. The calls for tender, evaluation and pre-award, and possibly award, will be directly performed by YLNG prior to the award of the main construction contract. LNG storage: pre-qualification questionnaire was issued, answers analyzed, recommendation endorsed, MOMR approval obtained. The issue of this call for tender will be coordinated with the issue of the LNG Plant call for tender. refrigeration compressor manufacturers have already been pre-qualified and the call for tender is in preparation; the issue of this call for tender will be coordinated with the issue of the LNG Plant call for tender. It is envisaged that separate quotes will be requested from the turbine manufacturer and from the compressor suppliers, but with a complete guarantee of the whole package from the compressor supplier

11 the call for tender for the supply of the Main Cryogenic Heat Exchanger (APCI) is under preparation. The issue of this call for tender will be coordinated with the issue of the LNG Plant call for tender. a questionnaire has also been sent to line pipe manufacturers, before issuing the corresponding call for tender. In order to minimize the interfaces between YLNG and contractors, these early contracts will be assigned to the corresponding main EPC contractor. Permanent Camp Due to the characteristics of an urban type development, the design and construction of the Permanent Camp will be done independently of the lump sum EPC contract for the LNG Plant. This will allow for taking full benefit of the existence of local resources, with an evolutive contractual strategy, depending upon the findings of the local contractor surveys still to be performed, and upon the results of the different calls for tender. Contracts will be awarded per trade or through a Main Construction Contractor. This will be assessed during the Detailed engineering / Tender period. A step like approach will be implemented for the Permanent Camp development: first, a Project Definition period for finalizing YLNG Statement of Requirements then a Building Permit Dossier / Tender Period with detailed construction engineering and subsequent calls for tender / clarifications / negotiations. and last, the construction period. These different periods will be managed and controlled by the Project Task Force, with the help of ad-hoc consultants, i.e., 2 Architects / Urban Planners and their specialized engineering associates. There will be one consultant for Design and Detailed Engineering, and another, drawing on Yemeni cultural resources, for providing architectural support, cultural and local inputs, and for assisting YLNG in construction supervision. LNG Carriers Options are being considered by the Marketing Committee for sale of LNG, F.O.B, C.I.F. and ex ship basis (refer to corresponding definitions in the narrative to be developed by the shipping group). For the C.I.F sales, it will be the responsibility of the Shipping committee to develop the corresponding implementation strategy and determine the organization, resources, schedule and budget required. E.P.C. Contract Implementation and Oversight In addition to their normal EPC activities, contractors will have to implement all the actions detailed in the Procedures which will be part of the E.P.C. contracts, in particular

12 those related to Quality Assurance (QA), Health, Safety and Environment (HSE) and Project Control. Although it is contractors responsibility to guarantee and to demonstrate that the installations they design and construct meet the specified specifications and standards, the Project Task Force will monitor all their activities through detailed engineering, construction, pre-commissioning and commissioning. In addition, and according to the Inspections and Quality Assurance Plans, the Project Task Force will perform audits relative to such activities. All commissioning activities will be performed by systems, with a specific hand-over mechanism whereby such systems, and relevant documentation, are handed over by the contractor to the Project Task Force, with YLNG Operation team as a witness. The whole facilities will be transferred to YLNG (Operations) care and custody when the last handover certificate is signed. 6. QUALITY ASSURANCE Quality Assurance (QA) addresses the implementation of a disciplined approach toward all activities affecting quality, including verification, where appropriate. It ensures that each task has been satisfactorily completed, that there is documentary evidence that the required quality has been achieved and that this level of quality has not been inadvertently undermined by subsequent change(s). The concept of quality is normally associated with fitness for purpose, as evidenced by demonstrable compliance with an approved specification. Since QA involves all activities affecting quality, very few activities are exclusive to QA personnel. But the primary responsibility for quality rests with the party responsible for the work. To avoid duplication of QA functions within the Project Task Force and with contractor organizations, and to encourage contractors to exercise fully their contractual obligations in respect of QA, the Project QA function and its degree of intervention in the main contractors QA business will be reduced to the minimum consistent with establishing and maintaining effective quality systems and effective Company auditing activities. This requires that only contractors with strong, independent and suitably staffed QA functions will be considered for the Project. All major contractors will be required to submit quality plans showing their proposed QA system, the procedures to be used, the responsibilities and authorities inherent in them and the quality activities and resources to be allocated. This includes QA/QC of all design activities and change control. Such plans must include the contractor s own schedule of internal reviews and audits, which will be monitored by the Project QA for both performance and effect

13 7. SAFETY AND ENVIRONMENTAL IMPACT It is the objective of the Project Team to execute the work in a safe manner, in accordance with the relevant Policies on Health-and-Safety-at-Work and Environmental Conservation. Relevant policy on both these subjects is not only to comply with safety (loss prevention), health and environmental impact measures required by law, but to act positively to prevent injury, ill health, damage, loss and pollution arising from its operations. At all stages of the Project, all operations, whether performed by, or on behalf of YLNG, will conform to the requirements of the relevant statutory regulations and established Company Practices and Policies on Safety and Environmental Impact. In order to ensure that the above policy is effectively implemented, the Project Task Force will develop and maintain a Safety and Environmental Impact Plan. This plan will cover all phases of the Project through design development, detailed design, construction and pre-commissioning, commissioning, start-up and hand-over to Operations; the Project Task Force will be responsible for safety until inerting and handover to Operations. The following subjects will be addressed in the Plan: safety objectives environmental quality objectives acceptance criteria legislative requirements statutory / non-statutory requirements risk assessment environmental impact assessments safety requirements management of changes The Project Team has already completed, with the help of various survey contractors and consultants (both for the Pipelines and for the LNG Plant) the Environmental Base Line Surveys and the Environmental Impact Assessments. Mitigation measures have been identified and incorporated into the design. 8. PROJECT COST & SCHEDULE Studies based on past experience, current trends and Shareholder data bases lead to an estimation of overall cost of the Project for Phase 1 and Phase 2 close to 2.5 billion US dollars (1997) A period of 40 months is planned between the launching of Phase 2 and the first shipment

14 9. CURRENT ORGANIZATION Incorporated in Bermuda in 1995, YLNG opened Company Offices in Sana a in 1997 where staffing will be greatly expanded for management of activities relating to Phase 2 (the Construction Phase) and for Phase 3. During Phase 1, certain services are being provided for YLNG through the lead shareholder with a team consisting of secondees from the various shareholders under the direction of a General Manager. 10. YEMENISATION PLAN All the policies and procedures related to the operation of the Company in Phase 2 and Phase 3 are being currently finalized. Among these, the Yemenization plan occupies a significant place. From the very beginning, Yemeni senior and junior staff have been involved within the Paris team, holding responsibility positions. This is to be further extended at quite a significant scale for the years to come

15 4.4 15

16 4.4 16

Yemen LNG Operational feedbacks

Yemen LNG Operational feedbacks Yemen LNG Operational feedbacks APCI Owners Seminar XI September 2013 1 Yemen LNG - Agenda 1. Yemen LNG general presentation 2. Feedback on Plant restarts optimization 3. Other operational feedbacks 2

More information

MLNG DUA DEBOTTLENECKING PROJECT

MLNG DUA DEBOTTLENECKING PROJECT MLNG DUA DEBOTTLENECKING PROJECT Yahya Ibrahim Senior General Manager Malaysia LNG Malaysia yahyai@petronas.com.my Tariq Shukri LNG Consultant Foster Wheeler Energy Limited Reading, U.K. Tariq_shukri@fwuk.fwc.com

More information

We deliver gas infrastructure

We deliver gas infrastructure We deliver gas infrastructure We are Uniper We are a leading international energy company with operations in more than 40 countries and around 13,000 employees. We combine a balanced portfolio of modern

More information

Brownfield Projects. Equinox Engineering

Brownfield Projects. Equinox Engineering BROWNFIELD PROJECTS Equinox Engineering Brownfield Projects Equinox Engineering Ltd. is a world class provider of EPCM services to the global oil and gas marketplace. Founded in 1997, Equinox has successfully

More information

Alaska South Central LNG (SCLNG) Project

Alaska South Central LNG (SCLNG) Project Alaska South Central LNG (SCLNG) Project Overview for Alaska Legislators February, 2013 - Overview BP, ConocoPhillips, ExxonMobil and TransCanada are working together to progress an Alaska LNG project:

More information

ENGINEERING CONSULTANCY SERVICES

ENGINEERING CONSULTANCY SERVICES Oman LNG L.L.C. Pre-Qualification of Tenderers QEN-16-825 ENGINEERING CONSULTANCY SERVICES Engineering Consultancy Services Page 1 of 7 10/05/16 GUIDELINES Response to this questionnaire shall be completed

More information

Stratus Development in Joint Venture with Middle East Petroleum Services (Offshore) SAL

Stratus Development in Joint Venture with Middle East Petroleum Services (Offshore) SAL Stratus Development in Joint Venture with Middle East Petroleum Services (Offshore) SAL Stratus Development in Joint Venture with Middle East Petroleum Services (Offshore) SAL is a service, general trading

More information

GLADSTONE LNG leads the way with its first LNG shipment in 2012

GLADSTONE LNG leads the way with its first LNG shipment in 2012 GLADSTONE LNG leads the way with its first LNG shipment in 2012 LNG Business Model Development of mid-scale LNG projects of up to 1.5 million tonne per annum (Mtpa) production capacity per LNG train, based

More information

LNG Plant Overview. Seminar with Supplier Association Murmanshelf Murmansk, 15 May 2012 Jostein Pettersen

LNG Plant Overview. Seminar with Supplier Association Murmanshelf Murmansk, 15 May 2012 Jostein Pettersen LNG Plant Overview Seminar with Supplier Association Murmanshelf Murmansk, 15 May 2012 Jostein Pettersen Table of Content Part 1 : LNG plant overview (Jostein) Part 2 : Main equipment units (Jostein) Part

More information

Appendix A: Project Characteristics

Appendix A: Project Characteristics Gorgon Fourth Train Expansion Proposal Appendix A: Project Characteristics Appendices Project Characteristics A Key Characteristics table has been prepared to describe the elements of the Foundation Project

More information

Dominion Cove Point Export Project Platts 16 th Annual Liquefied Natural Gas February 9, 2017

Dominion Cove Point Export Project Platts 16 th Annual Liquefied Natural Gas February 9, 2017 Dominion Cove Point Export Project Platts 16 th Annual Liquefied Natural Gas February 9, 2017 Note to Investors This presentation contains certain forward-looking statements, including projected future

More information

A World of Solutions Visit Product Storage Terminals for Bulk Liquids

A World of Solutions Visit  Product Storage Terminals for Bulk Liquids A World of Solutions Visit www.cbi.com Product Storage Terminals for Bulk Liquids United Arab Emirates The most global experience of any tank company CB&I has more than eight decades of experience designing

More information

Floating LNG Business A breakthrough in offshore gas monetization

Floating LNG Business A breakthrough in offshore gas monetization Floating LNG Business A breakthrough in offshore gas monetization LNG Malaysia Forum 2013 19-21 March, Kuala Lumpur Allan Magee, Ph.D. R&D Manager, Offshore Product Line and Technologies, Technip Geoproduction

More information

DSLNG Project Update. Andy Karamoy PT Donggi Senoro LNG. 4 th LNG Supply, Transport and Storage Indonesia May 2014 Bali, Indonesia

DSLNG Project Update. Andy Karamoy PT Donggi Senoro LNG. 4 th LNG Supply, Transport and Storage Indonesia May 2014 Bali, Indonesia DSLNG Project Update Andy Karamoy PT Donggi Senoro LNG 4 th LNG Supply, Transport and Storage Indonesia 19-21 May 2014 Bali, Indonesia Table of Contents 1. Introduction of Donggi Senoro LNG Project 2.

More information

Floating LNG: The Challenges of production systems and well fluids management By: Frederic MOLLARD, TECHNIP France 04/19/2013

Floating LNG: The Challenges of production systems and well fluids management By: Frederic MOLLARD, TECHNIP France 04/19/2013 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17) Floating LNG: The Challenges of production systems and well fluids management By: Frederic MOLLARD, TECHNIP France 04/19/2013

More information

ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17)

ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17) HOW TO DEVELOP AN ECONOMICAL SMALL CAPACITY FLOATING

More information

LNG Experience. Owner & Investor Project Management

LNG Experience. Owner & Investor Project Management LNG Experience Owner & Investor Project Management Project Management (Operator / Investor) Most mega projects fail to meet FID Cost & Schedule Contracting Strategies are not meeting the challenges Regulatory

More information

Teknologi Pemrosesan Gas (TKK 564) Instructor: Dr. Istadi (http://tekim.undip.ac.id/staf/istadi )

Teknologi Pemrosesan Gas (TKK 564) Instructor: Dr. Istadi (http://tekim.undip.ac.id/staf/istadi ) Teknologi Pemrosesan Gas (TKK 564) Instructor: Dr. Istadi (http://tekim.undip.ac.id/staf/istadi ) Email: istadi@undip.ac.id id Instructor s t Background BEng. (1995): Universitas Diponegoro Meng. (2000):

More information

MOLECULAR GATE TECHNOLOGY FOR (SMALLER SCALE) LNG PRETREATMENT

MOLECULAR GATE TECHNOLOGY FOR (SMALLER SCALE) LNG PRETREATMENT MOLECULAR GATE TECHNOLOGY FOR (SMALLER SCALE) LNG PRETREATMENT Presented at the 2010 Gas Processors 89 th Annual Convention Austin, TX March, 2010 Michael Mitariten, P.E. Guild Associates, Inc. Dublin,

More information

Evolution of an LNG Terminal: Senboku Terminal of Osaka Gas

Evolution of an LNG Terminal: Senboku Terminal of Osaka Gas 23 rd World Gas Conference, Amsterdam 2006 Evolution of an LNG Terminal: Senboku Terminal of Osaka Gas Main author Toshiro Otsuka Japan TABLE OF CONTENTS 1. Abstract 2. Body of Paper 3. List Tables 4.

More information

Enabling safe and reliable offshore LNG transfer operations By Vincent Lagarrigue, Marketing & Project Manager within Trelleborg Industrial Solutions

Enabling safe and reliable offshore LNG transfer operations By Vincent Lagarrigue, Marketing & Project Manager within Trelleborg Industrial Solutions Enabling safe and reliable offshore LNG transfer operations By Vincent Lagarrigue, Marketing & Project Manager within Trelleborg Industrial Solutions Executive Summary Moving liquefied natural gas (LNG)

More information

Natural Gas. and the Liquefaction Process

Natural Gas. and the Liquefaction Process Natural Gas and the Liquefaction Process Table of Contents Cameron LNG.................... 2 Liquefied Natural Gas................ 4 LNG Safety...................... 5 Environmental Safety................

More information

UNIQUE DESIGN CHALLENGES IN THE AUX SABLE NGL RECOVERY PLANT

UNIQUE DESIGN CHALLENGES IN THE AUX SABLE NGL RECOVERY PLANT UNIQUE DESIGN CHALLENGES IN THE AUX SABLE NGL RECOVERY PLANT Presented at the 81 st Annual Convention of the Gas Processors Association March 11, 2002 Dallas, Texas Joe T. Lynch, P.E. Ortloff Engineers,

More information

The Technical & Practical challenges of FLNG

The Technical & Practical challenges of FLNG SUT Evening Technical Meeting: On the Fringes of FLNG, Perth 19/08/2015 Jeff Baker Energy Compliance Technical Manager, Australasia Working together for a safer world Agenda Introduction Acknowledgement

More information

FUGRO GROUP LNG FIELD DEVELOPMENT AND FACILITIES. TACKLING your complex challenges. UNDERSTANDING your operational objectives

FUGRO GROUP LNG FIELD DEVELOPMENT AND FACILITIES. TACKLING your complex challenges. UNDERSTANDING your operational objectives LNG FIELD DEVELOPMENT AND FACILITIES FUGRO GROUP UNDERSTANDING your operational objectives TACKLING your complex challenges DELIVERING your global success stories LNG FIELD DEVELOPMENT AND FACILITIES Developing

More information

Energy East Pipeline. Project Overview. Kevin Maloney Manager, New Build Pipeline AB, NB, JV Irving and Cromer September, 2014

Energy East Pipeline. Project Overview. Kevin Maloney Manager, New Build Pipeline AB, NB, JV Irving and Cromer September, 2014 Energy East Pipeline Project Overview Kevin Maloney Manager, New Build Pipeline AB, NB, JV Irving and Cromer September, 2014 TransCanada: Leading North American Energy Infrastructure Company ENERGY EAST

More information

Natural Gas Facilities & Pipelines

Natural Gas Facilities & Pipelines Natural Gas Facilities & Pipelines Equinox Engineering Ltd. Equinox Engineering Ltd is a world class provider of EPCM services to the global oil and gas marketplace. Founded in 1997, Equinox has successfully

More information

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018 SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018 1.0 SCOPE This document establishes the quality program requirements for an organization providing engineering

More information

Petronet LNG Ltd., India. LNG Terminal Design- Major Design Considerations

Petronet LNG Ltd., India. LNG Terminal Design- Major Design Considerations Petronet LNG Ltd., India LNG Terminal Design- Major Design Considerations OVERVIEW 1. What is LNG and LNG Chain 2. Project Development & Site Selection 3. Studies Required 4. Marine Facilities 5. Storage

More information

ENERGY MANAGEMENT INITIATIVE AT PETRONAS LNG COMPLEX

ENERGY MANAGEMENT INITIATIVE AT PETRONAS LNG COMPLEX ENERGY MANAGEMENT INITIATIVE AT PETRONAS LNG COMPLEX AUTHORS: ABDUL HALIM CHE ABAS AZMI ABD RAHMAN FRANKY BUDIT OMAR TECHNICAL SERVICES DEPARTMENT MALAYSIA LNG SDN BHD Page 1 of 11 TABLE OF CONTENTS 1.0

More information

Optimising. the LNG process. The rapidly expanding global LNG industry continues. Projects

Optimising. the LNG process. The rapidly expanding global LNG industry continues. Projects Optimising the LNG process John Baguley, Liquefied Natural Gas Ltd, Australia, outlines the benefits of an innovative liquefaction process technology for mid scale LNG projects. The rapidly expanding global

More information

Transportation of Natural Gas-LPG Mixtures

Transportation of Natural Gas-LPG Mixtures 50c Transportation of Natural Gas-LPG Mixtures Shuncheng Ji and Richard G. Mallinson Institute for Gas Utilization Technologies And School of Chemical Engineering and Materials Science The University of

More information

Improving Natural Gas Liquefaction Plant Performance with Process Analyzers

Improving Natural Gas Liquefaction Plant Performance with Process Analyzers Process Analytics Improving Natural Gas Liquefaction Plant Performance with Process Analyzers LNG is natural gas in its liquid state with high energy density, which makes it useful for storage and transportation

More information

DYNAMIC SIMULATION FOR DESIGN IMPROVEMENTS, COST REDUCTION AND OPERATIONAL STABILITY IN LNG PLANT DESIGN

DYNAMIC SIMULATION FOR DESIGN IMPROVEMENTS, COST REDUCTION AND OPERATIONAL STABILITY IN LNG PLANT DESIGN DYNAMIC SIMULATION FOR DESIGN IMPROVEMENTS, COST REDUCTION AND OPERATIONAL STABILITY IN LNG PLANT DESIGN SIMULATION DYNAMIQUE POUR L AMELIORATION DU PROCEDE, REDUCTION DES COUT, ET STABILITE DE L OPERATION

More information

MITIGATION OF SEASONAL PRODUCTION LOSS FOR THREE PARALLEL 4.7MMTPA

MITIGATION OF SEASONAL PRODUCTION LOSS FOR THREE PARALLEL 4.7MMTPA 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION MITIGATION OF SEASONAL PRODUCTION LOSS FOR THREE PARALLEL 4.7MMTPA

More information

BASED ON EXPERIENCE TGE GAS ENGINEERING EVOLUTION OF SAFETY DESIGN FOR CRYOGENIC TANKS REVAMP VS. NEW BUILT

BASED ON EXPERIENCE TGE GAS ENGINEERING EVOLUTION OF SAFETY DESIGN FOR CRYOGENIC TANKS REVAMP VS. NEW BUILT BASED ON EXPERIENCE TGE GAS ENGINEERING EVOLUTION OF SAFETY DESIGN FOR CRYOGENIC TANKS REVAMP VS. NEW BUILT Page 1 CONTENT Overview on the services and experience of TGE Gas Engineering GmbH Examples of

More information

LNG UNIT (ENGINEERING DESIGN GUIDELINE)

LNG UNIT (ENGINEERING DESIGN GUIDELINE) Page : 1 of 60 Guidelines for Processing Plant www.klmtechgroup.com Rev 01 KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia (ENGINEERING DESIGN GUIDELINE)

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

LIQUEFIED NATURAL GAS LIMITED

LIQUEFIED NATURAL GAS LIMITED LIQUEFIED NATURAL GAS LIMITED ASX: LNG CNPC HQCEC: Company Making Transaction Liquefied Natural Gas Limited 5 Ord Street West Perth WA 6005 +61 8 9366 3700 www.lnglimited.com.au LNG Limited An Overview

More information

REQUEST FOR QUALIFICATIONS (RFQ) For Engineering Services Institute for Marine Mammal Studies (IMMS)

REQUEST FOR QUALIFICATIONS (RFQ) For Engineering Services Institute for Marine Mammal Studies (IMMS) REQUEST FOR QUALIFICATIONS (RFQ) For Engineering Services Institute for Marine Mammal Studies (IMMS) The IMMS is soliciting qualification statements for engineering services to assist the IMMS with the

More information

SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION

SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION The Society gratefully acknowledges those companies that support the program by allowing their professionals

More information

Technical Summary for TCC0 Global overview of the scope for TCC0 contract

Technical Summary for TCC0 Global overview of the scope for TCC0 contract IDM UID V89YJN VERSION CREATED ON / VERSION / STATUS 06 Oct 2017 / 2.0 / Signed EXTERNAL REFERENCE / VERSION Technical Specification Technical Summary for TCC0 Global overview of the scope for TCC0 contract

More information

Alaska LNG Concept Information. Alaska LNG. Overview. October

Alaska LNG Concept Information. Alaska LNG. Overview. October Overview October December 3, 2013 Project Overview Project Team BP, ConocoPhillips, ExxonMobil and TransCanada are working together to progress an project: 300+ people involved in project planning and

More information

The Pipelines Regulations, 2000

The Pipelines Regulations, 2000 PIPELINES, 2000 P-12.1 REG 1 1 The Pipelines Regulations, 2000 being Chapter P-12.1 Reg 1 (effective April 1, 2000) as amended by the Statutes of Saskatchewan, 2014, c.21; and by Saskatchewan Regulations

More information

Company Profile. Atlas Offshore Co. No.8, Negar Ave. Vali e Asr St., Tehran, Iran

Company Profile. Atlas Offshore Co. No.8, Negar Ave. Vali e Asr St., Tehran, Iran Company Profile Atlas Offshore Co. No.8, Negar Ave. Vali e Asr St., Tehran, Iran +98 21 88774544 +98 21 88790572 Table of Contents About US........ 2 Our Capabilities.. 3 Work shop / Storage... 4 EPC Services

More information

Modular Oil & Gas Equipment Onshore & Offshore

Modular Oil & Gas Equipment Onshore & Offshore Modular Oil & Gas Equipment Onshore & Offshore Separators & Desalters AI Energy Solutions onshore and offshore oil process solutions offer innovative technologies packaged with global project management

More information

INCREASING THE CAPACITY OF NGL RECOVERY TRAINS. Stéphane MESPOULHES XVI CONVENCIÓN INTERNACIONAL DE GAS Caracas de Mayo de 2004

INCREASING THE CAPACITY OF NGL RECOVERY TRAINS. Stéphane MESPOULHES XVI CONVENCIÓN INTERNACIONAL DE GAS Caracas de Mayo de 2004 INCREASING THE CAPACITY OF NGL RECOVERY TRAINS Stéphane MESPOULHES XVI CONVENCIÓN INTERNACIONAL DE GAS Caracas WHO IS TECHNIP? 2 World Class Engineering & Construction Group in Oil & Gas Public Company

More information

TCO Future Growth Project - Wellhead Pressure Management Project Construction Contractors Forum

TCO Future Growth Project - Wellhead Pressure Management Project Construction Contractors Forum TCO Future Growth Project - Wellhead Pressure Management Project Construction Contractors Forum FGP-WPMP Major Construction Scope Overview Jorge Calvo 30 January 2017 Atyrau, Kazakhstan Tengizchevroil

More information

TCO Future Growth Project Wellhead Pressure Management Project

TCO Future Growth Project Wellhead Pressure Management Project TCO Future Growth Project Wellhead Pressure Management Project Project Overview, Status & Kazakhstani Content Strategy Paul Benoit 10 April 2014 Astana, Kazakhstan FGP-WPMP Tengiz expansion consists of

More information

ELIGIBILITY CRITERIA FOR QUALIFICATION OF EPC CONTRACTORS FOR LNG TERMINAL AT GANGAVARAM, VISAKHAPATNAM, ANDHRA PRADESH (INDIA)

ELIGIBILITY CRITERIA FOR QUALIFICATION OF EPC CONTRACTORS FOR LNG TERMINAL AT GANGAVARAM, VISAKHAPATNAM, ANDHRA PRADESH (INDIA) ELIGIBILITY CRITERIA FOR QUALIFICATION OF EPC CONTRACTORS FOR LNG TERMINAL AT GANGAVARAM, VISAKHAPATNAM, ANDHRA PRADESH (INDIA) Petronet LNG Limited intends to undertake International Competitive Bidding

More information

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction 9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE 9.1.1 Introduction This chapter is the provisional Environmental Management Plan (EMP) for the Jubilee Phase 1 Development project. The elements of

More information

LIQUEFACTION STORAGE DISTRIBUTION BUNKERING SMALL-SCALE LNG SOLUTIONS

LIQUEFACTION STORAGE DISTRIBUTION BUNKERING SMALL-SCALE LNG SOLUTIONS LIQUEFACTION STORAGE DISTRIBUTION BUNKERING SMALL-SCALE LNG SOLUTIONS During the last decade, liquefied natural gas (LNG) has become the new black in the gas industry and recognising its huge market potential,

More information

AKAKUS OIL OPERATIONS- LIBYA Gas Utilization& Flare Emission Reduction Project

AKAKUS OIL OPERATIONS- LIBYA Gas Utilization& Flare Emission Reduction Project Tripoli, Libya 2010 AKAKUS OIL OPERATIONS- LIBYA Gas Utilization& Flare Emission Reduction Project Presented by: Mohamed Amari Project Location Tripoli, Libya 2010 N Tunisia Tripoli Mediterranean Sea Benghazi

More information

17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17)

17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17)

More information

Azeri, Chirag & Gunashli Full Field Development Phase 3 Environmental & Socio-economic Impact Assessment

Azeri, Chirag & Gunashli Full Field Development Phase 3 Environmental & Socio-economic Impact Assessment 5.7 Export Pipelines 5.7.1 Overview Phase 3 offshore facilities will use the existing Azeri Project marine export pipeline infrastructure to export its oil and gas to the onshore terminal at Sangachal.

More information

ITER Quality Assurance

ITER Quality Assurance US ITER Central Solenoid Vendor Meeting ITER Quality Assurance by John Mashburn USIPO QA Manager 1 QA Topics ITER s Nuclear License Graded Approach Proposal QA Items Quality Plan Specific to Contract Manufacturing

More information

Massachusetts Clean Energy Center Request for Proposals (RFP): Moon Island Engineering Design Consultant

Massachusetts Clean Energy Center Request for Proposals (RFP): Moon Island Engineering Design Consultant Massachusetts Clean Energy Center Request for Proposals (RFP): Moon Island Engineering Design Consultant RFP FY2017-BFD-01 Release Date: May 8 th, 2017 Applications Due: June 23 rd, 2017 1. PROGRAM SUMMARY

More information

GAS CONDITIONING & PROCESSING TRAINING

GAS CONDITIONING & PROCESSING TRAINING Training Title GAS CONDITIONING & PROCESSING TRAINING Training Duration 5 days Training Venue and Dates Gas Conditioning & Processing 5 07 11 April $3,750 Dubai, UAE In any of the 5 star hotels. The exact

More information

Review of Project Proposed for CSLF Recognition: Al Reyadah CCUS Project (Phase I: Emirates Steel)

Review of Project Proposed for CSLF Recognition: Al Reyadah CCUS Project (Phase I: Emirates Steel) Review of Project Proposed for CSLF Recognition: Al Reyadah CCUS Project (Phase I: Emirates Steel) Dipak Sakaria (BDM - Abu Dhabi Carbon Capture Company - Al Reyadah), United Arab Emirates 30 th April

More information

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited SCREENING SCOPING DOCUMENT For the proposed Shell Quest Carbon Capture and Storage Project Shell Canada Limited Prepared by: Canadian Environmental Assessment Agency Natural Resources Canada Fisheries

More information

TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure

TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure Additional Information Regarding The Implementation Programme

More information

Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant

Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant International Journal of Engineering and Technology Volume 3 No. 1, January, 2013 Estimation of Boil-off-Gas BOG from Refrigerated Vessels in Liquefied Natural Gas Plant Wordu, A. A, Peterside, B Department

More information

LNG LIQUEFIED NATURAL GAS TECHNOLOGIES

LNG LIQUEFIED NATURAL GAS TECHNOLOGIES LNG LIQUEFIED NATURAL GAS TECHNOLOGIES Air Liquide Group Air Liquide Engineering & Construction The world leader in gases, technologies and services for Industry and Health Air Liquide is present in 80

More information

PART 3 TERMINAL INFORMATION

PART 3 TERMINAL INFORMATION International Safety Guide Part 3 Terminal information PART 3 TERMINAL INFORMATION Edition 1-2010 CCNR/OCIMF 2010 Page 235 International Safety Guide Part 3 Terminal information Edition 1-2010 CCNR/OCIMF

More information

Engineering and technologies Gas processing

Engineering and technologies Gas processing Engineering and technologies Gas processing When the world's gas producers have a new challenge they turn to Technip, and they have been doing so for 50 years Technip profile Technip is a world leader

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,

More information

THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16 ( the Act ) and

THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16 ( the Act ) and TECHNICAL STANDARDS & SAFETY AUTHORITY 14 th Floor, Centre Tower 3300 Bloor Street West Toronto, Ontario Canada M8X 2X4 IN THE MATTER OF: THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16

More information

B.C. TOWBOAT INDUSTRY CONFERENCE

B.C. TOWBOAT INDUSTRY CONFERENCE LN G T erm inals on C ana da s W est C oast Kitimat LNG LN G T erm inals on C ana da s W est C oast Presentation to 17 th B.C. TOWBOAT INDUSTRY CONFERENCE Whistler, BC Kitimat LNG Alfred Sorensen Kitimat

More information

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate Project Overview Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate a natural gas-tomethanol production plant and storage facilities, and a new marine terminal, in the

More information

Oman LNG LLC. Pre-Qualification Questionnaire. QEN EPC to Construct Car Parking Sheds with Solar Photovoltaic Panels

Oman LNG LLC. Pre-Qualification Questionnaire. QEN EPC to Construct Car Parking Sheds with Solar Photovoltaic Panels Oman LNG LLC Pre-Qualification Questionnaire QEN-18-930 EPC to Construct Car Parking Sheds with Solar Photovoltaic Panels Pre-Qualification Questionnaire Page 1 of 6 1. GUIDELINES Response to this questionnaire

More information

SPECIFICATIONS FOR AluSystems Aluminum Composite Panels Series 20 Dry Joint 1.00 GENERAL 1.01 RANGE OF WORK Section includes: Laminated panels and attachment systems for use as exterior cladding. A. Provide

More information

Resolution MEPC.11(18) adopted on 25 March 1983 GUIDELINES FOR SURVEYS UNDER ANNEX I OF THE INTERNATIONAL CONVENTION FOR THE PREVENTION OF POLLUTION

Resolution MEPC.11(18) adopted on 25 March 1983 GUIDELINES FOR SURVEYS UNDER ANNEX I OF THE INTERNATIONAL CONVENTION FOR THE PREVENTION OF POLLUTION MEPC 18/18 Resolution MEPC.ll(18) OF ~978 RELATING THERETO THE MARINE ENVIRONMENT PROTECTION COMMITTEE, RECALLING Article 39 of the Convention of the International Maritime Organization concerning the

More information

DESIGN AND OPERATING EXPERIENCE FOR ANADARKO S LANCASTER FACILITY

DESIGN AND OPERATING EXPERIENCE FOR ANADARKO S LANCASTER FACILITY DESIGN AND OPERATING EXPERIENCE FOR ANADARKO S LANCASTER FACILITY Presented at the 95 th Annual Convention of the Processors Association April 11, 2016 New Orleans, Louisiana Joe T. Lynch, P.E. Ortloff

More information

Drive Selection for LNG FPSO

Drive Selection for LNG FPSO INTRODUCTION Recently oil and gas exploration has gone into deep drilling and oil/ gas fields have been found quite far from shore. So far oil has been monetized and gas has been either flared or re-injected.

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

Transportation and regasification infrastructures

Transportation and regasification infrastructures Transportation and regasification infrastructures Snam Rete Gas is the market leader in the Italian natural gas transportation and regasification sector and the only Italian operator that regasifies liquefied

More information

ENERGY. Responding to the Upstream Boom

ENERGY. Responding to the Upstream Boom ENERGY Responding to the Upstream Boom CURRENT OPPORTUNITIES AND CHALLENGES IN MIDSTREAM/LNG 1 GROWTH Responding to demand for new and expanded oil and gas processing, transportation and storage following

More information

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT : GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT CONTENTS 3. GENERAL DESCRIPTION OF THE PROPOSED COEGA 3-1 3.1 Overview of the Coega Integrated Power Project 3-1 3.2 Description of

More information

Contract Quality Requirements Manual SLM Issue 3

Contract Quality Requirements Manual SLM Issue 3 Contract Quality Requirements Manual SLM 4.06.02 Issue 3 20 th October 2015 Gary Rushforth Supply Chain Quality Sellafield Ltd Introduction Sellafield Ltd (SL) aims to deliver excellence in everything

More information

Qualitative Phase Behavior and Vapor Liquid Equilibrium Core

Qualitative Phase Behavior and Vapor Liquid Equilibrium Core 2/22/2017 Qualitative Phase Behavior and Qualitative Phase Behavior Introduction There are three different phases: solid, liquid, and gas (vapor) Energy must be added to melt a solid to form liquid If

More information

LARGE STORAGE TANK PROJECT

LARGE STORAGE TANK PROJECT INTRODUCTION The Fairbanks Large Storage Tank is part of the Interior Energy Project (IEP) designed to expand natural gas distribution in Fairbanks and Interior Alaska. A tank with a capacity of 0.44 Bcf

More information

APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES

APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES PECO is offering cash incentives for qualified Combined Heat and Power (CHP) technology projects 1 to encourage the development of projects that improve

More information

LNG Houston, February 6-7 th, The case for developing a Floating LNG Receiving Terminal on the US East Coast

LNG Houston, February 6-7 th, The case for developing a Floating LNG Receiving Terminal on the US East Coast LNG 2002 Houston, February 6-7 th, 2002 The case for developing a Floating LNG Receiving Terminal on the US East Coast By Sveinung J. Stohle, Executive Vice President, Golar LNG Ltd. Golar LNG s Strategy

More information

California Resources Corporation. Health, Safety & Environmental Management System

California Resources Corporation. Health, Safety & Environmental Management System California Resources Corporation Health, Safety & Environmental Management System Mission of CRC s HSE Management System The mission of California Resources Corporation s (CRC s) Health, Safety and Environmental

More information

Appendix A. Project Description

Appendix A. Project Description Appendix A Project Description I. Project Summary 1. The proposed Jordan Cove LNG export terminal ( Jordan Cove ) is a facility designed to produce and export liquefied natural gas ( LNG ). Jordan Cove

More information

Magnetically Coupled Submerged Cryogenic Pumps and Expanders for Ammonia Applications

Magnetically Coupled Submerged Cryogenic Pumps and Expanders for Ammonia Applications Paper 4d Magnetically Coupled Submerged Cryogenic Pumps and Expanders for Ammonia Applications Liquefied Ammonia, or Liquid NH3, is (like LNG or liquefied natural gas) a cryogenic fluid and production

More information

Project phases II. Tendering-constructionoperation

Project phases II. Tendering-constructionoperation Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 09.03.2016 Project phases time Inception initiation Preliminary analysis

More information

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. "Beit Hanoun Emergency Water Supply Project"

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. Beit Hanoun Emergency Water Supply Project "Beit Hanoun Emergency Water Supply Project" " Rehabilitation and Construction of Beit Hanoun Water Network " BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE Bill of Quantities PREAMBLE TO

More information

Saudi Aramco General Bid Slates (GBS)

Saudi Aramco General Bid Slates (GBS) Saudi Aramco General Bid Slates (GBS) Copyright 2015, Saudi Aramco. All rights reserved. Agenda Saudi Aramco Contracting Strategy Saudi Aramco General Bid Slate (GBS) General Bid Slate Work Types 2 Saudi

More information

By-Law Number 9 Concerning Procurement Contracts for Goods, Services and Construction

By-Law Number 9 Concerning Procurement Contracts for Goods, Services and Construction By-Law Number 9 Concerning Procurement Contracts for Goods, Services and Construction Approved by the Board of Directors June 26, 2012 Amended by resolution 93-S-2-A March 11, 2014 TABLE OF CONTENTS Article

More information

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017 Company: Prepared By: Date: Changes from previous version highlighted in yellow. Paragraph Element Objective Evidence 2.1 Objective of Quality Assurance Program 2.2 Applicability and Scope 2.3 QA Program

More information

Item Hydrogen Gas Plant

Item Hydrogen Gas Plant Item 6530. Hydrogen Gas Plant Hydro-Chem Hydrogen Generating Plant 90,000 scfh @ 200 psig. Purity 99.99% Hydrogen generating plant engineered by Hydro-Chem built in 1980. Design capacity is 90,000 scfh

More information

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 DQASIP PROCUREMENT, RECEIVING, AND STORAGE PROGRAM APPLICABILITY: 2512 35065-01 INSPECTION OBJECTIVES To determine whether equipment procurement specifications

More information

Creating Optimal LNG Storage Solutions. 40 in detail

Creating Optimal LNG Storage Solutions. 40 in detail [ MARINE / IN DETAIL ] [ MARINE / IN DETAIL ] Creating Optimal LNG Storage Solutions AUTHOR: Sören Karlsson, Business Development Manager, Wärtsilä Marine Solutions mail: soren.karlsson@wartsila.com 40

More information

MEETING TECHNICAL CHALLENGES IN DEVELOPING HIGH CO 2 GAS FIELD OFFSHORE

MEETING TECHNICAL CHALLENGES IN DEVELOPING HIGH CO 2 GAS FIELD OFFSHORE MEETING TECHNICAL CHALLENGES IN DEVELOPING HIGH CO 2 GAS FIELD OFFSHORE Author: Md Faudzi Mat Isa, and Muhammad Akkil Azhar PETRONAS CARIGALI SBN BHD Keywords: 1.Offshore, 2. High CO 2, 3. Membrane I.

More information

URGENTLY REQUIRED FOR SUDAN Oil Exploration - Operation & Maintenance (O&M) JOBS

URGENTLY REQUIRED FOR SUDAN Oil Exploration - Operation & Maintenance (O&M) JOBS URGENTLY REQUIRED FOR SUDAN Oil Exploration - Operation & Maintenance (O&M) JOBS SCOPE OF WORK. Introduction The SCOPE OF WORK as minimum will be carried out within the client oil exploration and development

More information

CONVERTING DOMINION COVE POINT LNG INTO BIDIRECTIONAL FACILITY

CONVERTING DOMINION COVE POINT LNG INTO BIDIRECTIONAL FACILITY CONVERTING DOMINION COVE POINT LNG INTO BIDIRECTIONAL FACILITY Pascal Bocherel, Jim Strohman, Juan Martinez Dominion Cove Point LNG, LP Brett Wink, Kamal Shah, John Ray IHI E & C International Corporation

More information

ENGINEERING SERVICES

ENGINEERING SERVICES ICONS... ICONS ENGINEERING SERVICES Contact us at: Ph: (+91) 9704 038 648 E-mail: contactus@iconsengg.com Web: http:// ABOUT US A group of professionals imbibed with the power of knowledge thru many years

More information