CHAPTER 7 STAKEHOLDER ENGAGEMENT

Size: px
Start display at page:

Download "CHAPTER 7 STAKEHOLDER ENGAGEMENT"

Transcription

1 CHAPTER 7 STAKEHOLDER ENGAGEMENT

2 TABLE OF CONTENTS 7 STAKEHOLDER ENGAGEMENT PROCESS INTRODUCTION STAKEHOLDERS IDENTIFIED STAKEHOLDER ENGAGEMENT PROCESS Stakeholder Engagement Activities Outcomes of the Stakeholder Engagement Activities NEXT STEPS IN THE STAKEHOLDER ENGAGEMENT PROCESS FEEDBACK MECHANISM MONITORING AND REPORTING CONCLUSION LIST OF TABLES Table 7-1: Phases of Engagement Table 7-2: Summary of Stakeholder Issues and Concerns LIST OF FIGURES Figure 7-1: Location of Local Stakeholder Groups Quantum Power Ghana Gas Limited 7-i Knight Piésold Consulting

3 7 STAKEHOLDER ENGAGEMENT PROCESS 7.1 INTRODUCTION This chapter presents a summary of the engagement activities undertaken as well as future engagement activities planned as part of the ESIA process for the Tema LNG Project. It serves as a summary of the more detailed Public Consultation and Disclosure Plan (PCDP) contained in Volume Two - Annexure B. The PCDP has been compiled to present on the engagement approaches adopted, the stakeholders included in the engagement activities, and the methods through which they were engaged. The PCDP also provides a means to document all future stakeholder engagement process yet to be undertaken. The complete PCDP, a list of identified stakeholders and key issues and responses to date, are contained in the PCDP of Volume Two- Annexure B. The engagement process was designed to meet Ghanaian legal requirements for public participation and also to align as far as practically possible with good international industry best practice (GIIP), based on the project timing and budget. The key objectives of stakeholder engagement for the ESIA process included: Ensuring understanding: An open, inclusive and transparent process of culturally appropriate engagement and communication was undertaken to ensure that stakeholders are well informed about the proposed development. Information throughout the ESIA process was disclosed early, and as comprehensively as possible for stakeholder groups. Involving stakeholders in the assessment: Stakeholders were included in the scoping of issues, the assessment of impacts, the generation of mitigation and management measures and the finalisation of the ESIA report. They also played an important role in providing local knowledge and information for the baseline to inform the impact assessment. Building relationships: Through supporting open dialogue, engagements helped establish and maintain a productive relationship between the ESIA team and stakeholders. This supported not only an effective ESIA, but will also strengthen the existing relationships between Quantum Power and identified stakeholders. Engaging vulnerable people: An open and inclusive approach to consultation increases the opportunity of stakeholders to provide comment on the proposed Project and to voice their concerns. Some stakeholders, however, need special attention in such a process due to their vulnerability. Where vulnerable groups were identified, differentiated measures were used to ensure effective participation of vulnerable stakeholders. Managing expectations: It was important to ensure that the proposed Project does not create or allow unrealistic expectations to develop amongst stakeholders about Project benefits. The engagement process was designed to serve as one of the mechanisms for understanding and then managing stakeholder and community expectations, where the latter will be achieved by disseminating accurate information in an accessible way. Ensuring compliance: The process was designed to ensure compliance with Ghanaian regulatory requirements and align with good international industry best practice. Quantum Power Ghana Gas Limited 7-1 Knight Piésold Consulting

4 7.2 STAKEHOLDERS IDENTIFIED A stakeholder to the Project refers to any individual or group which is potentially affected directly or indirectly by the proposed Project or who has an interest in the proposed Project and its potential impacts. A complete stakeholder database has been compiled and is appended to the PCDP. The database has been periodically updated throughout the ESIA scoping engagement process. Figure 7-1 illustrates the location of different stakeholder groups that were identified and engaged with through the process. This figure also shows the location of directly affected communities in and near the Project area that are likely to be affected by the proposed Project. This includes key areas related to the fishing industry and other livelihoods. Quantum Power Ghana Gas Limited 7-2 Knight Piésold Consulting

5 Figure 7-1: Location of Local Stakeholder Groups Quantum Power Ghana Gas Limited 7-3 Knight Piésold Consulting

6 7.3 STAKEHOLDER ENGAGEMENT PROCESS Stakeholder Engagement Activities The engagement process was designed to align to the stages of the ESIA process, which involved: Scoping Baseline Data Gathering Draft ESIA Preparation Final ESIA Preparation and Disclosure A summary of the objectives and activities undertaken is listed in Table 7-1. Further information regarding the engagement activities undertaken during each of these phases, as well as the outcomes of these visits are described in detailed in the PCDP. Quantum Power Ghana Gas Limited 7-4 Knight Piésold Consulting

7 Table 7-1: Phases of Engagement Phase Objective Key Activities Key Outputs Scoping Engagement To gain a preliminary understanding of the scope of the Project, it s likely impacts and relevant stakeholders; To meet key stakeholders and introduce them to the proposed Project and ESIA; To generate feedback on the Draft Scoping Report, including the scope, approach and key issues to be investigated further for the ESIA; and To consult key stakeholders on the next steps in the ESIA process. Notification and communication on the proposed Project and associated ESIA through: - Media (BIDs, Adverts, Posters etc) - Meetings with key stakeholders including: Government Ministries, Departments and Agencies Local Public Organisations Updated PCDP detailing engagement and issues and concerns Engagement tools and proof of their dissemination. Non-technical Summary summarising the Scoping Report including list of preliminary identified impacts. Final Scoping Report with record of stakeholder issues available to key stakeholders. Other Companies Fence line communities - Distribution of Scoping Report to key stakeholders directly and via project website; and - Dissemination of a nontechnical summary of the Scoping Report. Baseline Data Gathering Engagement To collect baseline data through detailed surveys using participatory appraisal methods. Fence line community survey with a random selection of households; Focus Group Discussions (FGD) with select stakeholders; and Updated PCDP; Engagement tools; and Socio-economic baseline. Key Informant Interviews (KII) with key stakeholders. Quantum Power Ghana Gas Limited 7-5 Knight Piésold Consulting

8 Phase Objective Key Activities Key Outputs Draft ESIA Engagement To generate feedback on the Draft ESIA and preliminary impact assessment. Dissemination of the draft ESIA to key stakeholders directly and via project website; Dissemination of a non-technical summary of the draft ESIA report; and Draft ESIA report; Non-technical summary of identified impacts and mitigation measures; and Draft Stakeholder Engagement Strategy (SES). Meetings and workshops at the national, regional/ District and local level. ESIA Disclosure Engagement Obtain stakeholder/ community agreement on a position on the proposed Project and associated process; and To notify stakeholders of the submission of the final report to regulators. Dissemination of the final ESIA to key stakeholders via project website; Disclosure of the final ESIA report with stakeholders; Meetings at local, regional/district and national levels to gain stakeholder sign-off on a position about the proposed Project and endorsement of the process. Final ESIA report; Endorsement letter from local authorities verifying: - the outcomes of the stakeholder process reflect the true and unbiased opinions of local stakeholders; - Stakeholders have been provided the opportunity to voice their opinions; and - Have agreed and are satisfied with the mitigation measures set out in the preliminary Environmental and Social Management Pan (ESMP). Final SES. Quantum Power Ghana Gas Limited 7-6 Knight Piésold Consulting

9 7.3.2 Outcomes of the Stakeholder Engagement Activities The key issues there were identified during scoping disclosure and baseline data gathering are summarised in Table 7-2, below. The findings of the stakeholder consultation activities were also used in the compilation of Chapter 13 (Assessment of Socio-economic Impacts and Mitigation). Quantum Power Ghana Gas Limited 7-7 Knight Piésold Consulting

10 Table 7-2: Summary of Stakeholder Issues and Concerns Issue Category Issue Details on the Issue Stakeholder (s) Project duration Potential short term disruption in fishing activities during construction Fisheries Scientific and Survey Division (FSSD) Anufa Anufa Fishing Association Project development ESIA Process and report review ESIA needs to make provision for post mitigation monitoring especially on locally affected receptors Discussions regarding timeframes for ESIA review and public disclosure Fisheries Scientific and Survey Division (FSSD) Environmental Protection Agency Environmental Protection Agency Project affected administrative boundaries Alternative pipeline routes to only one administrative district to reduce revenue generation cost LNG Plant Technology proposed, liquefaction process Cooling system for plant Impacts on local and artisanal fishery Energy Commission Noise and aerial emissions from plant Potential collision of fishing boats and LNG vessels Potential for fishing nets to be caught within the FSRU and associated infrastructure Anufa Anufa Fishing Association Anticipated Impacts The construction and operation of Project related infrastructure Potential for fish gathering under FSRU/LNG vessel Disturbance of shrines within close proximity to the Gao Lagoon Disturbance of Goa Lagoon and mangroves in the project area Kpone Traditional Council Kpone Katamanso District Assembly Quantum Power Ghana Gas Limited 7-8 Knight Piésold Consulting

11 Issue Category Issue Details on the Issue Stakeholder (s) Subsea pipeline survey trench construction impact on fishery resource Fisheries Scientific and Survey Division (FSSD) Offsets for ecosystems Environmental Protection Agency (EPA) Pipeline corridors Cumulative impacts on fishery resource from existing WAGP pipeline and Tema LNG pipelines National Fisheries Association of Ghana (NAFAG) Restriction in fishing and landing areas Projects fixed linear infrastructure and pipelines crossing main Tema-Aflao road Tema Development Corporation Increased traffic during road crossing Population influx in communities Social, Health and Wellbeing Influx of social vices and stress on social amenities Impacts on health and education systems How will the project impact on health of coastal ecosystems Tema Traditional Council Chief and Elders of Bankuman Life span of construction camps Ghana Ports and Harbours Authority (GHAPOHA) Safety and Emergency Services Tema Traditional Council Safety and security during construction stage Chief and Elders of Bankuman Impact of fishing and exclusion zone Ghana Ports and Harbours Authority (GHAPOHA) Shipping turn around and safety Ghana Ports and Harbours Authority (GHAPOHA) Pipelines leaks and safety Ghana Ports and Harbours Authority (GHAPOHA) Emergency response and impact on health system Quantum Power Ghana Gas Limited 7-9 Knight Piésold Consulting

12 Issue Category Issue Details on the Issue Stakeholder (s) Offshore pipeline corridors Potential increased restriction in fishing activities National Fisheries Association of Ghana (NAFAG) FSRU water discharge and temperature changes and impact on fishery resource Fisheries Scientific and Survey Division (FSSD) Tema Traditional Council Design of FSRU and storage FSRU water discharge must meet requirements of marine water balance code Ghana Ports and Harbours Authority Ghana Maritime Authority FSRU location and fish migration Fisheries Scientific and Survey Division (FSSD) FSRU Operation(s) FSRU position is potential breeding and spawning area for anchovies. National Fisheries Association of Ghana (NAFAG) Process Related Increased restrictions and exclusion zone around FSRU Impact of re-gasification on fishery resource Size of workforce on FSRU Energy Commission Aerial and noise emissions from FSRU to fishermen at sea Anufa Anufa Fishing Association Wastewater discharge into ocean and impact on fishery resource National Fisheries Association of Ghana (NAFAG) Flaring System Aerial emissions and impact on local residents. Health risk from heat plume Energy Commission Metering Station Potential noise emission from pressure valve testing Energy Commission Stakeholder Corporate Social Incorporation of local content into project design Fisheries Scientific and Survey Division(FSSD) Quantum Power Ghana Gas Limited 7-10 Knight Piésold Consulting

13 Issue Category Issue Details on the Issue Stakeholder (s) Expectations Responsibilities Implementation of community development/support programs Community support programs must to tied to activities of NGOs Chief and Elders of Bankuman Kpone Traditional Council Anufa Anufa Fishing Association Energy Commission How will grievances and compensation issues be addressed Anufa Anufa Fishing Association Fisheries Scientific and Survey Division(FSSD) Physical displacement of land assets and Land acquisition and Physical Displacement subsistence farms Potential resettlement of residential homes Kpone District Assembly within RoW Social Investments and corporate citizenship Fishermen and fishing association perception that Tema LNG project is set to Anufa Anufa Fishing Association make a large profit with no tangible benefits to local fishermen and residents National Fisheries Association of Ghana (NAFAG) Employment, business and procurement Potential short term employment opportunities during construction. Limited short term employment, what will be available is mainly aimed at skilled workers Local employers versus import/foreign employers Job creation and local employment and procurement policy Chief and Elders of Bankuman Kpone Traditional Council Tema Traditional Council Potential neglect/abandoning of fishing activities for better prospects in LNG jobs. Quantum Power Ghana Gas Limited 7-11 Knight Piésold Consulting

14 7.4 NEXT STEPS IN THE STAKEHOLDER ENGAGEMENT PROCESS As indicated in this report, consultation for the Tema LNG project is an ongoing process and will see another round of information sessions and displays as well as other activities undertaken during the public exhibition of the ESIA. These activities will include: public notices, one-on-one meetings and responses to s, telephone and written enquires. Following disclosure engagement on the draft ESIA, the records of engagement will be appended to the Final ESIA report. This will be reviewed by the Environmental Protection Authority (EPA) and a final consultation forum will be held organised by the EPA with Quantum Power as host. The consultation durbar will involve EPA officials disclosing the outcomes of the ESIA to all identified stakeholders by Quantum Power. Once stakeholders have agreed with the mitigation measures addressing significant impacts identified in the ESIA, the EPA will inform Quantum Power of their Record of Decision (RoD). Following receipt of the RoD, Quantum Power through Knight Piésold s engagement team will conduct final round of consultation and make this available to stakeholders as well as providing information on the appeals process. 7.5 FEEDBACK MECHANISM Following completion of disclosure engagement, Knight Piésold s stakeholder engagement team will arrange for a handover to Quantum Power of key project information including the stakeholder database and issues table completed to date. Knight Piésold has set up a Grievance Management Framework (refer to Annexure B) with tools and approaches which Quantum Power can adopt to resolve all project conflicting issues. Knight Piésold will provide input on a broader approach towards engagement for the Project through a Stakeholder Engagement Strategy (SES) which will be generated as one of the outcomes of the ESIA process. 7.6 MONITORING AND REPORTING It is important to monitor and report on the on-going stakeholder engagement efforts to ensure that the desired outcomes are being achieved, and to maintain a comprehensive record of engagement activities and issues raised. This has been done through the PCDP, where the following have been recorded: Updates to the stakeholder database; Recording of all consultations held; and Updates to the issues and responses table. These records and outputs have been regularly updated and appended to each iteration of the ESIA. In other words, the PCDP has served as a tool not only to plan future engagements but to also record previous phases of the process. Further details on monitoring and reporting stakeholder engagement across the project lifecycle are included in the SES. Quantum Power Ghana Gas Limited 7-12 Knight Piésold Consulting

15 7.7 CONCLUSION Due to the time constraint for the Tema LNG ESIA consultation, it presented a unique challenge in that the community had been consulted to the point of saturation. The reality could have been accepted and little or no effort made to motivate the community to participate in the consultation process. This was not the case, however and an enormous amount of energy and resources was devoted to ensuring that the community and stakeholders were not only given the opportunity to become engaged and involved but also that their knowledge on local resources and how the project will affect them were incorporated exponentially. Feedback from and evaluation of the consultation activities helped both to guide the direction of the consultation and inform the project team of the significance and importance of specific issues to stakeholders and communities. In particular, the consultation assisted with understanding the social impacts of the fishing industry and how the LNG project will impact the sector. All issues raised during the scoping disclosure consultation process have been incorporated into this draft ESIA and plans are that they will subsequently have an impact on the project design, construction and operation. Quantum Power Ghana Gas Limited 7-13 Knight Piésold Consulting

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT Final Scoping Report - Non-Technical Summary Presentation Structure of the Presentation Introduction to the Tema LNG Project

More information

1 PROJECT OVERVIEW. Quantum Power Ghana Gas Limited 1 Knight Piésold Consulting GMF

1 PROJECT OVERVIEW. Quantum Power Ghana Gas Limited 1 Knight Piésold Consulting GMF 1 PROJECT OVERVIEW Quantum Power Ghana Gas Limited (hereinafter referred to as Quantum Power) is a developer, owner and operator of electricity generation assets and power-related infrastructure throughout

More information

CHAPTER 13 ASSESSMENT OF SOCIO-ECONOMIC IMPACTS AND MITIGATION

CHAPTER 13 ASSESSMENT OF SOCIO-ECONOMIC IMPACTS AND MITIGATION CHAPTER 13 ASSESSMENT OF SOCIO-ECONOMIC IMPACTS AND MITIGATION TABLE OF CONTENTS 13 ASSESSMENT OF SOCIO-ECONOMIC IMPACTS AND MITIGATION... 13-1 13.1 SOCIO-ECONOMICS AND LIVELIHOODS... 13-1 13.1.1 Increased

More information

Annex A. Stakeholder Engagement Plan

Annex A. Stakeholder Engagement Plan Annex A Stakeholder Engagement Plan Draft Stakeholder Engagement Plan Environmental &Social Impact Assessment Proposed Yara Dallol Potash Project, Dallol, Ethiopia Version 3 April 2014 www.erm.com The

More information

EBRD Performance Requirement 10

EBRD Performance Requirement 10 EBRD Performance Requirement 10 Information Disclosure and Stakeholder Engagement Introduction 1. This Performance Requirement (PR) recognises the importance of an open and transparent engagement between

More information

Guide to Respecting Human Rights

Guide to Respecting Human Rights Guide to Respecting Human Rights APRIL 2017 Overview We recognize our activities throughout the mine lifecycle have the potential to impact people s rights, and that increasingly the risks and impacts

More information

Stakeholder Engagement Plan

Stakeholder Engagement Plan Stakeholder Engagement Plan South Stream Offshore Pipeline Bulgarian Sector, July 2014 Abbreviations Abbreviation EEZ EIA ESIA ESMP ESMS IFC IFC PSs MoEW NGO PAC NTS SCD SEP ToR Description Exclusive

More information

February 2012 Tweneboa, Enyenra, Ntomme T.E.N. Development Project Environmental Impact Assessment Scoping Report and Terms of Reference (ToR)

February 2012 Tweneboa, Enyenra, Ntomme T.E.N. Development Project Environmental Impact Assessment Scoping Report and Terms of Reference (ToR) February 2012 Tweneboa, Enyenra, Ntomme T.E.N. Development Project Environmental Impact Assessment Scoping Report and Terms of Reference (ToR) Project Overview: Background Exploration and appraisal drilling

More information

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR Overview of Presentation 1. Objectives of the Consultancy 2. Hydropower in Myanmar 3. Draft Table of Contents 4.

More information

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction 9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE 9.1.1 Introduction This chapter is the provisional Environmental Management Plan (EMP) for the Jubilee Phase 1 Development project. The elements of

More information

5 PUBLIC PARTICIPATION PROCESS 5.1 INTRODUCTION

5 PUBLIC PARTICIPATION PROCESS 5.1 INTRODUCTION 5 PUBLIC PARTICIPATION PROCESS 5.1 INTRODUCTION This Chapter presents a summary of the stakeholder engagement activities planned as part of the EIA process. It serves as a summary of a more detailed Stakeholder

More information

DRAFT FOR PUBLIC COMMENT Guidance Note for ESS10 Stakeholder Engagement and Information Disclosure

DRAFT FOR PUBLIC COMMENT Guidance Note for ESS10 Stakeholder Engagement and Information Disclosure The Guidance Notes provide guidance for the Borrower on the application of the Environmental and Social Standards (ESSs), which form part of the World Bank s 2016 Environmental and Social Framework. The

More information

SUMMARY 2013 EDITION

SUMMARY 2013 EDITION SUMMARY 2013 EDITION RSAT Joint Initiative on Rapid Basin-wide Hydropower Sustainability Assessment Tool PART 1: OVERVIEW OF THE RSAT The RSAT is designed as an integrative tool to assess hydropower development

More information

a) Status and trends b) Challenges and opportunities

a) Status and trends b) Challenges and opportunities Joint Regional Input of the General Fisheries Commission for the Mediterranean (GFCM) and UN Environment/MAP-Barcelona Convention Secretariats into the Concept Paper of the Secretary-General of the Conference

More information

Mining & Communities

Mining & Communities Mining & Communities Supporting human rights-based development in the context of industrial mining in Guinea Abridged version of the Practical guide for civil society organizations and local authorities

More information

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives: ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP 1. Objectives The aim of the study is to achieve the following objectives: Review of existing EIA and RAP reports on sections of the line which are not

More information

Stakeholder Engagement Plan Code Of Practice

Stakeholder Engagement Plan Code Of Practice a Stakeholder Engagement Plan Code Of Practice COP 302 Revision 00 A Revisions Paragraph Revision Change Date - 00 Created 20/02/2014 B Approval Name Signature Date Compiled by Dieter Klingenberg 20/02/2014

More information

Annex A. Stakeholder Engagement Plan

Annex A. Stakeholder Engagement Plan Annex A Stakeholder Engagement Plan A1 LIST OF ACRONYMS Table 1-A Acronyms Abbreviation BID CBO CLO EIA ESIA ERM EP ESMP FGDs IA&Ps IFC KII NGOs NTS SEP Full Definition Background Information Document

More information

7. Community Consultation

7. Community Consultation 7. Community Consultation This section provides a summary of the public consultation process implemented for the Project, incorporating the Mine and Rail aspects. The consultation process has been undertaken

More information

SCOPING STUDY TO DEVELOP STRATEGIC APPROACH FOR ENTERPRISE DEVELOPMENT IN COASTAL FISHING COMMUNITIES IN KENYA

SCOPING STUDY TO DEVELOP STRATEGIC APPROACH FOR ENTERPRISE DEVELOPMENT IN COASTAL FISHING COMMUNITIES IN KENYA Republic of Kenya MINISTRY OF AGRICULTURE, LIVESTOCK & FISHERIES STATE DEPARTMENT OF FISHERIES AND BLUE ECONOMY KENYA MARINE FISHERIES AND SOCIO-ECONOMIC DEVELOPMENT PROJECT (KEMFSED) TERMS OF REFERENCE

More information

IN FOCUS. MATERIAL ISSUES continued ISSUES. Engaging with stakeholders for mutual benefit and building trust

IN FOCUS. MATERIAL ISSUES continued ISSUES. Engaging with stakeholders for mutual benefit and building trust Engagement is an opportunity for us to listen to our stakeholders, and to initiate proactive and meaningful dialogue that captures the voices of all concerned. We continuously seek to be inclusive and

More information

THE ENERGY DEVELOPMENT CYCLE

THE ENERGY DEVELOPMENT CYCLE THE ENERGY DEVELOPMENT CYCLE PRE-PROJECT EXPLORATION APPRAISAL & DEVELOPMENT OPERATION CLOSURE USE Risks & Opportunities Across the Development Cycle Activities prior to the start of the individual project

More information

Environmental Impact Assessment (EIA) for Oil & Gas and Power Projects

Environmental Impact Assessment (EIA) for Oil & Gas and Power Projects Environmental Impact Assessment (EIA) for Oil & Gas and Power Projects Insert then choose Picture select your picture. Right click your picture and Send to back. August 6-8 th, 2014 Craig A. Reid Partner,

More information

Chapter 1 Introduction

Chapter 1 Introduction Chapter 1 Introduction TABLE OF CONTENTS 1 INTRODUCTION... 1-1 1.1 General... 1-1 1.2 Background to the WREP... 1-1 1.3 Rationale for WREP-SR Project... 1-2 1.4 WREP Operator: GPC and BP Relationship...

More information

Deliverable 2: Procedural guidelines as a recommendation to the national competent authorities

Deliverable 2: Procedural guidelines as a recommendation to the national competent authorities Deliverable 2: Procedural guidelines as a recommendation to the national competent authorities Content Introduction... 2 Procedural Guidelines... 2 1. Scope of recommended procedural guidelines... 3 2.

More information

Greece Stakeholder Engagement Plan

Greece Stakeholder Engagement Plan Greece Stakeholder Engagement Plan Table of contents List of Acronyms and Abbreviations 4 1. Introduction 5 1.1 Purpose and Objectives of the SEP 5 1.2 TAP Engagement Commitments 5 2. Project Stakeholders

More information

URS- EIA- REP Date of Issue 19th November 2012

URS- EIA- REP Date of Issue 19th November 2012 DocID: External DocID: URS-EIA-REP-201040 46369085_Doc020_REP_Rev03 Date of Issue 19th November 2012 This report has been prepared by URS Infrastructure & Environment UK Limited on behalf of South Stream

More information

Gender impact assessment and hydropower. Assessment understanding - empowerment

Gender impact assessment and hydropower. Assessment understanding - empowerment Gender impact assessment and hydropower Assessment understanding - empowerment Michael Simon 13 September 2013 Overview 1. Why gender impact assessment? Basic principles and approach 1. Dam project: Simple

More information

Developing a Feedback and Grievance Redress Mechanism (FGRM) for the Fiji National REDD+ Programme TERMS OF REFERENCE

Developing a Feedback and Grievance Redress Mechanism (FGRM) for the Fiji National REDD+ Programme TERMS OF REFERENCE FIJI REDD+ Readiness Program supported by FCPF/World Bank Developing a Feedback and Grievance Redress Mechanism (FGRM) for the Fiji National REDD+ Programme TERMS OF REFERENCE 1. INTRODUCTION Fiji has

More information

Social and Environmental Investment Overview

Social and Environmental Investment Overview Table of contents 1. Introduction 3 2. SEI Governance Hierarchy 3 3. SEI Programme 4 3.1 Goal and Objectives 4 3.2 SEI Programme Framework 5 3.3 Project Funding Types 6 4. SEI Management System 7 4.1 SEI

More information

Social Investment. Child Rights and Mining Toolkit. Tool

Social Investment. Child Rights and Mining Toolkit. Tool 10 Child Rights and Mining kit Investing in children s safety, education and health leads to more resilient and peaceful societies in the long term, and is therefore the best foundation for a sustainable

More information

6 Risk assessment methodology

6 Risk assessment methodology Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management

More information

Terms of Reference (TORs)

Terms of Reference (TORs) Terms of Reference (TORs) Assessment of alternative livelihoods and development of a new value chain Organization Pakistan Fisher Folk (PFF) Project Title Strengthening of Resilience through DRR and Livelihood

More information

Scoping Document for the Environmental Assessment. BP Exploration (Canada) Ltd. Tangier 3D Seismic Survey

Scoping Document for the Environmental Assessment. BP Exploration (Canada) Ltd. Tangier 3D Seismic Survey Scoping Document for the Environmental Assessment BP Exploration (Canada) Ltd. Tangier 3D Seismic Survey Exploration Licenses 2431, 2432, 2433, and 2434 August 2013 Contents 1.0 Purpose... 2 2.0 Regulatory

More information

EBRD and Wind Energy

EBRD and Wind Energy EBRD and Wind Energy Climate Investment Funds Managing the Impact of Wind Energy Development on Birds and Bats September 2012 Jack Mozingo and Robert Adamczyk Environmental and Sustainability Department

More information

FRAMEWORK FOR AQUACULTURE DEVELOPMENT ON THE VOLTA LAKE. Implementation Guidelines Document

FRAMEWORK FOR AQUACULTURE DEVELOPMENT ON THE VOLTA LAKE. Implementation Guidelines Document FRAMEWORK FOR AQUACULTURE DEVELOPMENT ON THE VOLTA LAKE Implementation Guidelines Document APRIL 2017 INTERPRETATIONS: In these Guidelines, unless the context otherwise requires: Applicant: Company or

More information

The Ocean Pathway. A Strategy for the Ocean into COP23 Towards an Ocean Inclusive UNFCCC Process

The Ocean Pathway. A Strategy for the Ocean into COP23 Towards an Ocean Inclusive UNFCCC Process The Ocean Pathway A Strategy for the Ocean into COP23 Towards an Ocean Inclusive UNFCCC Process Note: this is an evolving document compiled from consultations by the COP23 Fiji Presidency with interested

More information

Key Components and Best Practices for Environmental Impact Assessments

Key Components and Best Practices for Environmental Impact Assessments Key Components and Best Practices for Environmental Impact Assessments Introduction 1 The immense technological advances since the adoption of UN Convention on the Law of the Sea (UNCLOS) have exponentially

More information

9 Socio-Economic Impact Assessment, Mitigation and Management

9 Socio-Economic Impact Assessment, Mitigation and Management 9 Mitigation and Management Table of Contents 9.1 Introduction... 9-2 9.2 Scoping... 9-3 9.3 Socio Economic Impacts... 9-9 9.3.1 Onshore Impacts Associated with Physical Presence of Seismic Vehicles and

More information

Stakeholder Engagement Plan. Doc. No: PLN Rev. B Page 1 of 19 Date: August 2017

Stakeholder Engagement Plan. Doc. No: PLN Rev. B Page 1 of 19 Date: August 2017 Rev. B Page 1 of 19 Stakeholder Engagement Plan Rev. B Page 2 of 19 1 Introduction... 3 2 Policy & legislative requirements... 4 2.1 Corporate Objectives... 4 2.2 Omani Legislative Requirements... 4 2.3

More information

Chapter 14 Overall Project Assessment

Chapter 14 Overall Project Assessment Chapter 14 Overall Project Assessment TABLE OF CONTENTS 14 OVERALL PROJECT ASSESSMENT... 14-1 14.1 Introduction... 14-1 14.2 Development of the ESIA... 14-1 14.2.1 Adopted Process... 14-1 14.2.2 Challenges

More information

Principles for environmental and social responsibility

Principles for environmental and social responsibility issued by: Principles for environmental and social responsibility Sustainable development is dependent on a balance between economic considerations, social responsibility and environmental protection.

More information

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT The health of the world s oceans and marine life is degrading rapidly as a result of excess human activities.

More information

Environmental and Social Policy

Environmental and Social Policy Environmental and Social Policy Contents Foreword 2 Purpose 2 Commitments 2 Environmental and Social Assessment 3 Operations financed directly 4 Operations financed through Financial Intermediaries 4 Environmental

More information

GHANA NATIONAL PETROLEUM CORPORATION (GNPC) NATURAL GAS TRANSPORTATION AND PROCESSING PROJECT (NGTPP) RESETTLEMENT POLICY FRAMEWORK (RPF)

GHANA NATIONAL PETROLEUM CORPORATION (GNPC) NATURAL GAS TRANSPORTATION AND PROCESSING PROJECT (NGTPP) RESETTLEMENT POLICY FRAMEWORK (RPF) GHANA NATIONAL PETROLEUM CORPORATION (GNPC) NATURAL GAS TRANSPORTATION AND PROCESSING PROJECT (NGTPP) RESETTLEMENT POLICY FRAMEWORK (RPF) TERMS OF REFERENCE 1.0 Introduction and Background The Government

More information

EBRD Performance Requirement 1

EBRD Performance Requirement 1 EBRD Performance Requirement 1 Assessment and Management of Environmental and Social Impacts and Issues Introduction 1. This Performance Requirement (PR) establishes the importance of integrated assessment

More information

Performance Requirements

Performance Requirements Environmental and Social Policy 15 Performance Requirements PR 1: Environmental and Social Appraisal and Management Introduction 1. The EBRD considers it important that all companies receiving EBRD financing

More information

Developing, Appraising and Approving an Activity Design

Developing, Appraising and Approving an Activity Design Developing, Appraising and Approving an Activity Design Guideline Last updated: 22 September 2016 Approver: PDLT Contents Overview... 2 Drafting Terms of Reference... 3 Terms of Reference drafted by MFAT...

More information

CCAMLR Secretariat Strategic Plan

CCAMLR Secretariat Strategic Plan CCAMLR Secretariat Strategic Plan 2015 2018 Introduction The CAMLR Convention entered into force on 7 April 1982. It establishes the Commission for the Conservation of Antarctic Marine Living Resources

More information

EARTHQUAKE- PRONE BUILDINGS POLICY

EARTHQUAKE- PRONE BUILDINGS POLICY EARTHQUAKE- PRONE BUILDINGS POLICY 2009 1. Introduction CONTENTS 2. Policy Objectives and Principles 3. Key Policy Components - Assessing earthquake-prone buildings - Standard of strengthening required

More information

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d)

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d) Checklist:. 10.Ports and Harbors (1) 1 Permits and Explanation 2 Pollution Control (1) EIA and Permits (2) Explanation to the Local Stakeholders (3) Examination of Alternatives (1) Air Quality (2) Water

More information

ESIA for the proposed Baynes Hydropower Project:

ESIA for the proposed Baynes Hydropower Project: ESIA for the proposed Baynes Hydropower Project: Public Scoping Meeting: Windhoek Special Arrangements Visitors from Kunene Region Liaison Officer will translate for them. Meeting filmed. Microphones to

More information

Operations OPERATIONS

Operations OPERATIONS 143 T. Pollett Operations OPERATIONS GOOD PRACTICE POINTERS Manage the transition from construction to operations. Periodically review and update your stakeholder information. Consider ways to assess stakeholder

More information

Chapter 13 Management and Implementation

Chapter 13 Management and Implementation Chapter 13 Management and Implementation TABLE OF CONTENTS 13 MANAGEMENT AND MONITORING... 13-1 13.1 Introduction... 13-1 13.2 Overview of AGT Region Operating Management System... 13-1 13.3 Construction

More information

Working with Care along the Trans Adriatic Pipeline Route

Working with Care along the Trans Adriatic Pipeline Route Working with Care along the Trans Adriatic Pipeline Route Ulrike Andres, TAP Commercial and Public Affairs Director Clara Risso, TAP Senior Permit Manager Italy TAP linepipe transported in Greece 2 TAP

More information

Initiative of the European Union, European Civil Protection and Humanitarian Aid Operations department (ECHO)

Initiative of the European Union, European Civil Protection and Humanitarian Aid Operations department (ECHO) Alliance 2015 EU Aid Volunteers Deployment Agriculture EU Aid Project Volunteer, ACTED LEBANON Junior 1 position Middle East Western Asia Lebanon Closing date: 04/08/2017 ACTED are looking for talented

More information

Stakeholder Engagement Strategy

Stakeholder Engagement Strategy Stakeholder Engagement Strategy Contents List of Acronyms and Abbreviations 4 1. Introduction 5 1.1 Purpose and Objectives 5 1.2 Applicable Standards and Guidelines 6 1.3 Articulation with TAP Management

More information

A Partnership for Saving West Africa s Coastal Assets

A Partnership for Saving West Africa s Coastal Assets A Partnership for Saving West Africa s Coastal Assets 2015 West Africa Coastal Areas Management Program (WACA) 1 Africa s development and climate agendas are inextricably linked: If unaddressed, climate

More information

Processing unit (fish products)

Processing unit (fish products) EXECUTIVE SUMMARY E1. INTRODUCTION The Proponent, Ferme Marine de Mahebourg Ltd (FMM), is involved in the Fish Farming sector in Mauritius since 2000. To date, FMM manages two declared Fish Farm Zones

More information

Social, Cultural and Economic Indicators Project Final Report. April NCR# v1

Social, Cultural and Economic Indicators Project Final Report. April NCR# v1 Social, Cultural and Economic Indicators Project Final Report April 2015 Beaufort Regional Environmental Assessment Final Report Social, Cultural and Economic Indicators Project (Inuvialuit Indicators

More information

Voluntary Guidelines for Securing Sustainable Small-Scale Fisheries in the Context of Food Security and Poverty Eradication

Voluntary Guidelines for Securing Sustainable Small-Scale Fisheries in the Context of Food Security and Poverty Eradication Voluntary Guidelines for Securing Sustainable Small-Scale Fisheries in the Context of Food Security and Poverty Eradication At a glance 2 What are the SSF Guidelines? The Voluntary Guidelines for Securing

More information

Armenia: ENA-Modernisation of Distribution Network Stakeholder Engagement Plan: Draft Final Report

Armenia: ENA-Modernisation of Distribution Network Stakeholder Engagement Plan: Draft Final Report Armenia: ENA-Modernisation of Distribution Network Stakeholder Engagement Plan: Draft Final Report Prepared by June 2017 EBRD Armenia: ENA - Modernisation of Distribution Network Stakeholder Engagement

More information

Stakeholder Engagement paper

Stakeholder Engagement paper R-PP Finalization Project Climate Compatible Development Agency 17 September 01 Stakeholder Engagement paper Introduction REDD+ readiness in the context of the Forest Carbon Partnership Facility (FCPF)

More information

This document sets out how AIB complies with these Regulations. 1. Governance

This document sets out how AIB complies with these Regulations. 1. Governance Compliance with the European Union (Capital Requirements) Regulations 2014 The legal basis for implementing Basel III is the European Union ( EU ) adopted legislative package, known as CRD IV, which came

More information

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3)

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) 3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) Emagine IT s approach to Independent Verification and Validation (IV&V) has been shaped over the years by hands-on experience and contributions

More information

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify)

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify) PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION Interested Organization Name: Project Location: Projected amount of required project funding ($ /USD): TOTAL: Project Sector or Similar:

More information

11 Socio-economic Impact Assessment

11 Socio-economic Impact Assessment 11 Socio-economic Impact Assessment 11.1 Introduction Chapter 3 discusses the approach and methodology developed and applied for this impact assessment process. The adopted definition of a socio-economic

More information

TEXAS MEXICO TRANSPORTATION BORDER MASTER PLAN UPDATE

TEXAS MEXICO TRANSPORTATION BORDER MASTER PLAN UPDATE TEXAS MEXICO TRANSPORTATION BORDER MASTER PLAN UPDATE Border Trade Advisory Committee Footer Text Date Background Information: May 31, 2017 Previous border master plans (2013 / 2014) Primarily focused

More information

Independent Study of Marine Environmental Conditions and Influence of Oil and Gas Activities in Ghana

Independent Study of Marine Environmental Conditions and Influence of Oil and Gas Activities in Ghana Independent Study of Marine Environmental Conditions and Influence of Oil and Gas Activities in Ghana Launch of Final Report and Next Steps February 25, 2015 Accra Performed in collaboration with: Acorn

More information

UNEP Principles 1. Integration of Tourism into Overall Policy for Sustainable Development

UNEP Principles 1. Integration of Tourism into Overall Policy for Sustainable Development UNEP Principles The principles cover: 1. Integration of Tourism into Overall Policy for Sustainable Development 2. Development of Sustainable Tourism 3. Management of Tourism 4. Conditions for Success

More information

IFAD S PARTICIPATION IN THE HARMONIZATION INITIATIVE

IFAD S PARTICIPATION IN THE HARMONIZATION INITIATIVE Distribution: Restricted EB 2005/84/INF.8 19 April 2005 Original: English English a IFAD Executive Board Eighty-Fourth Session Rome, 18-20 April 2005 IFAD S PARTICIPATION IN THE HARMONIZATION INITIATIVE

More information

Environment Statistics and System of Environment-Economic Accounting (SEEA) - National Assessment Report 1

Environment Statistics and System of Environment-Economic Accounting (SEEA) - National Assessment Report 1 Environment Statistics and System of Environment-Economic Accounting (SEEA) - National Assessment Report 1 1 Version dated and released on 24 July 2017. Table of Contents Contents Page Objective... 3 Country

More information

In March 2014, the WGII report on Impacts, Adaptation and Vulnerability, which forms part of the IPCC 5th assessment, will be published.

In March 2014, the WGII report on Impacts, Adaptation and Vulnerability, which forms part of the IPCC 5th assessment, will be published. MCCIP Marine Climate Smart Working Examples of adaptation for marine and coastal stakeholders Introduction The aim of this document is to provide a regularly updated overview of key pieces of adaptation

More information

An Oceans Supplement to the Natural Capital Protocol

An Oceans Supplement to the Natural Capital Protocol An Oceans Supplement to the Natural Capital Protocol Technical Briefing Note What is the need? Oceans support millions of jobs, and contribute an estimated US $2.5 trillion per year into the global economy,

More information

DRAFT GUIDELINE ON PUBLIC PARTICIPATION IN MYANMAR S EIA PROCESSES CONSULTATION DRAFT

DRAFT GUIDELINE ON PUBLIC PARTICIPATION IN MYANMAR S EIA PROCESSES CONSULTATION DRAFT DRAFT GUIDELINE ON PUBLIC PARTICIPATION IN MYANMAR S EIA PROCESSES CONSULTATION DRAFT 5 April 2017 This Draft Guideline is made possible by the generous support of the American people through the United

More information

Participatory rural planning processes

Participatory rural planning processes Rural Transport Training Materials Module 2: Planning, Design, Appraisal and Implementation Participatory rural planning processes Session 2.1 Part 1 Presentation 2.1a The Training Modules Module1. Policies

More information

6. Cross-Cutting Issues Indicators

6. Cross-Cutting Issues Indicators 6. Cross-Cutting Issues Indicators This thematic area evaluates in more detail several key topics that transcend each of the first four thematic areas. As such, the indicators in this section can be applied

More information

TITLE OF CONSULTANT: Individual Consultant (IC) to Develop a Strategic Plan and Implementation Program for Business Botswana

TITLE OF CONSULTANT: Individual Consultant (IC) to Develop a Strategic Plan and Implementation Program for Business Botswana INDIVIDUAL CONSULTANT PROCUREMENT NOTICE 19 th December 2017 TITLE OF CONSULTANT: Individual Consultant (IC) to Develop a Strategic Plan and Implementation Program for Business Botswana COUNTRY: BOTSWANA

More information

CANADA TRANSPORTATION ACT REVIEW INITIAL SUBMISSION FOCUSED ON THE GRAIN INDUSTRY. Infrastructure, Efficiency, Transparency

CANADA TRANSPORTATION ACT REVIEW INITIAL SUBMISSION FOCUSED ON THE GRAIN INDUSTRY. Infrastructure, Efficiency, Transparency CANADA TRANSPORTATION ACT REVIEW INITIAL SUBMISSION FOCUSED ON THE GRAIN INDUSTRY Infrastructure, Efficiency, Transparency December 31, 2014 Table of Contents Introduction and context... 2 Executive summary...

More information

KING III COMPLIANCE ANALYSIS

KING III COMPLIANCE ANALYSIS Principle element No Application method or explanation This document has been prepared in terms of the JSE Listings Requirements and sets out the application of the 75 Principles of the King III Report

More information

Transport Domain Plan. Draft list of Enduring Questions

Transport Domain Plan. Draft list of Enduring Questions Transport Domain Plan Draft list of Engagement Draft v1.0 August 2014 Introduction The Transport Domain Plan is jointly led by Statistics NZ and the Ministry of Transport. It is a project that will identify

More information

High Seas. The High Seas are open-access common areas. As such, a growing number of VULNERABLE HABITATS AND BIOLOGICAL COMMUNITIES OF THE HIGH SEAS

High Seas. The High Seas are open-access common areas. As such, a growing number of VULNERABLE HABITATS AND BIOLOGICAL COMMUNITIES OF THE HIGH SEAS High Seas Ocean territory under threat An estimated 64% of the oceans lie beyond the 200-nautical-mile limit of the Exclusive Economic Zones (EEZs) of coastal states. These areas, known as the High Seas,

More information

Information Disclosure

Information Disclosure Information Disclosure What s in this section? 28 28 30 31 Be transparent Apply good practice principles Weigh the risks and benefits Manage information on sensitive and controversial issues Adopting a

More information

The challenges and complexities of impact assessment for a seismic survey in a remote coral reef environment

The challenges and complexities of impact assessment for a seismic survey in a remote coral reef environment The challenges and complexities of impact assessment for a seismic survey in a remote coral reef environment J.G. Colman 1,2, C.C. Grebe 1 & R.L. Hearn 1 1 Woodside Energy Ltd (cameron.grebe@woodside.com.au,

More information

FAQs on ESIA of CASA-1000

FAQs on ESIA of CASA-1000 FAQs on ESIA of CASA-1000 I. Technical Questions A. When will the project start in my (province/municipality/region)? The project implementation schedule will be finalized after selection of the contractor

More information

GLOSSARY. Quantum Power Ghana Gas Limited ix Knight Piésold Consulting Environmental and Social Impact Assessment

GLOSSARY. Quantum Power Ghana Gas Limited ix Knight Piésold Consulting Environmental and Social Impact Assessment GLOSSARY Alternative Alternatives can refer to any of the following, but are not limited to: alternative sites for development, alternative projects for a particular site, alternative site layouts, alternative

More information

Audit & Risk Committee Charter

Audit & Risk Committee Charter Audit & Risk Committee Charter Status: Approved Custodian: Executive Office Date approved: 2014-03-14 Implementation date: 2014-03-17 Decision number: SAQA 04103/14 Due for review: 2015-03-13 File Number:

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

Rio Ocean Declaration

Rio Ocean Declaration Rio Ocean Declaration Calling for strong and immediate action to meet the sustainable development goals for oceans, coasts, and small island developing States (SIDS) at Rio+20 and beyond Co-Chairs Statement

More information

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and Introduction There are many tools that a reviewer of environmental impact assessment documents can use to help determine whether such documents are complete and adequate. Among the powerful tools that

More information

Chapter 17 Cumulative Impacts

Chapter 17 Cumulative Impacts Chapter 17 Cumulative Impacts CONTENTS 17. Cumulative Effects... 2 17.1 Introduction... 2 17.2 Summary of Relevant Legislation, Planning Policy and Guidance... 2 17.3 Methods... 5 17.4 Consultation...

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

RENEWABLE ENERGY AND MIGRATORY SPECIES

RENEWABLE ENERGY AND MIGRATORY SPECIES CMS CONVENTION ON MIGRATORY SPECIES Distribution: General UNEP/CMS/Resolution 11.27 (Rev.COP12) Original: English RENEWABLE ENERGY AND MIGRATORY SPECIES Adopted by the Conference of the Parties at its

More information

Building from the ground up in West Africa. The Hatch approach to projects in a developing country

Building from the ground up in West Africa. The Hatch approach to projects in a developing country Building from the ground up in West Africa The Hatch approach to projects in a developing country 2 Agenda 1. Hatch Contribution to West Africa Development 2. Three Recent Projects on Which We Worked 3.

More information

Baseline Study on Newly Fairtrade Certified Cocoa Producer Organizations in Côte d Ivoire and Ghana. Terms of Reference - May 2013

Baseline Study on Newly Fairtrade Certified Cocoa Producer Organizations in Côte d Ivoire and Ghana. Terms of Reference - May 2013 Baseline Study on Newly Fairtrade Certified Cocoa Producer Organizations in Côte d Ivoire and Ghana Terms of Reference - May 2013 Fairtrade Africa and Fairtrade International are currently seeking a research

More information

Environmental and Social Data Sheet

Environmental and Social Data Sheet Environmental and Social Data Sheet Overview Project Name: Project Number: 2013-0342 OUARZAZATE II (PARABOLIC) Country: MOROCCO Project Description: Construction and operation of a 200 MW CSP Parabolic

More information

Summary of the Pacific Community s 2015 work programme in. Samoa. (November 2015 update)

Summary of the Pacific Community s 2015 work programme in. Samoa. (November 2015 update) Summary of the Pacific Community s 2015 work programme in Samoa (November 2015 update) The following table lists key work areas that SPC is undertaking in 2015 in cooperation with Samoa. The country-specific

More information

SA Water Strategic Plan Delivering water and wastewater services in efficient, responsive, sustainable and accountable ways

SA Water Strategic Plan Delivering water and wastewater services in efficient, responsive, sustainable and accountable ways SA Water Strategic Plan 2012-16 Delivering water and wastewater services in efficient, responsive, sustainable and accountable ways Contents 3 From the Chairman and Chief Executive 4 Our Business Context

More information

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS Agricultural Expansion on Portion 2 of Farm 92, Tregaron, known as Sylvania, Sundays River Valley Municipality BACKGROUND INFORMATION DOCUMENT,

More information

King lll Principle Comments on application in 2016 Reference Chapter 1: Ethical leadership and corporate citizenship Principle 1.

King lll Principle Comments on application in 2016 Reference Chapter 1: Ethical leadership and corporate citizenship Principle 1. Clicks Group Application of King III Principles 2016 APPLICATION OF King III PrincipleS 2016 This document has been prepared in terms of the JSE Listings Requirements and sets out the application of King

More information