1 ATLANTA, GEORGIA 1

2 ATLANTA, GEORGIA NEPA Session 2 When to Start NEPA Emily Underhill, PE Division Director Development SW Florida International emunderhill@flylcpa.com Bill Willkie Principal Project Manager, CH2M HILL Bill.Willkie@ch2m.com

3 Topics Overview NEPA starts with a plan The planning & environmental process Transitions Durations Uncertainty What to do? Case Study: SW Florida International Airport 3

4 Overview NEPA Starts with a Plan NEPA applies only to federal actions: For most airport development, the federal action is approval of changes to an Airport Layout Plan (ALP), approval to spend Passenger Facility Charge (PFC) revenues, or issuance of Airport Improvement Program (AIP) grants. Airport sponsors define the project: Definition of physical development Identification of benefits Identification of operational characteristics Foundation for proposed action, purpose and need 4

5 Overview NEPA Starts with a Plan But what if it s not airport development? For non-aviation development the federal action is often the release of airport property acquired with Federal funds. FAA is required to consider the direct and indirect consequences of land releases. FAA requirements include: Sponsor retains sufficient control to protect aviation uses Environmental assessment of intended and reasonably foreseeable uses (zoning and land use regulations may establish what is reasonably foreseeable) NEPA document type will depend on foreseeable uses Difficulties arise when land would be made available for speculative development 5

6 6 The Planning & Environmental Process Transitions Typically, NEPA starts immediately after completion of planning process CatEx Airport Planning Process EA Outreach & Draft EA l Final EA FONSI EIS Scoping l Draft EIS l Final EIS ROD Note: Sponsor Lead FAA Lead

7 Immediate, Sequential Scenario typical approach Sponsor provides planning information and FAA decides if it is sufficient for completing NEPA Occurs when project need is solid and data supporting the need are rational and well-developed at the end of the planning process Allows a smooth, almost seamless transition from planning to the NEPA process Project funding and/or unconditional ALP approval typically linked to the NEPA process, helps develop an accurate planning grant (planning grants can t be amended) 7

8 8 The Planning & Environmental Process Transitions Sometimes demand for improvement lags behind planning Pre-NEPA Project Definition Master Planning Project Definition EIS NOI/Scoping l Draft EIS l Final EIS ROD Project Definition in NEPA Process Master Planning EIS Project Definition NOI/Scoping l Draft EIS l Final EIS ROD Note: Sponsor Lead FAA Lead

9 Delayed Project Implementation Scenario Some Time Approach Sponsor seeks FAA approval some time after planning completed Typically occurs when the sponsor identifies a need, but justification depends on traffic growth NEPA requires FAA to look at projects that are ripe for decision, consider: 3-year NEPA document shelf life 5-year planning horizon for short-term purposes Focus on facilities justified in the short-term 9

10 Delayed Project Implementation Scenario Some Time Approach May require updated data needed to develop an accurate planning grant (critical because planning grants can t be amended) Data considerations in this scenario include: Age of forecasts - does the sponsor s forecast meet the 10% / 15% TAF rule? Does the documentation still reflect the characteristics of the No Action alternative? Funding is normally linked to NEPA process, through project planning grants 10

11 11 The Planning & Environmental Process Transitions In rare occasions, demand is so immediate that NEPA starts during the planning process Airport Planning Process EA EIS Outreach & Draft EA l Final EA FONSI Scoping l Draft EIS l Final EIS ROD Note: Sponsor Lead FAA Lead

12 12 Concurrent Scenario the Rare Approach Sponsor and FAA agree to start the NEPA process before the sponsor completes its planning process Occurs when the project is urgently needed and justified when planning begins Planning issues not well developed = delays in NEPA or re-doing costly, complex analyses because planning principles change during NEPA process Can occur, but requires intensive amount of labor as planning and NEPA are coordinated, almost simultaneously More easily accomplished in an EA than in an EIS

13 13 The Planning & Environmental Process Typical Durations Master Plan EIS Master Plan: 2-3 years EIS: 3-6 years 1 year = 6-10 years Master Plan EA Master Plan: 2-3 years EA: 1-3 years = 3-6 years Focused Planning Study CatEx Planning CatEx < 1 year Note: Sponsor Lead FAA Lead

14 The Planning & Environmental Process Uncertainty 14

15 The Planning & Environmental Process Uncertainty 15

16 The Planning & Environmental Process Uncertainty 16

17 The Planning & Environmental Process Uncertainty 17

18 The Planning & Environmental Process What to Do? The following options apply primarily to capacity projects: Update forecast at the start of the NEPA process Conduct an optimum time to invest analysis Maintain dialogue with airlines or other relevant stakeholders Start the NEPA process earlier (the concurrent scenario) Start the NEPA process later (risks higher levels of delay in near term but reduces uncertainty about need) 18

19 19 Case Study: 30 Years of Planning and NEPA at RSW EIS approved for original RSW airport site Airport opened ALP - Draft EA Short Term FONSI Long Term EA/FONSI proposed actions ,000 acre mitigation park Master Plan/ALP ALP

20 Where are We? 20

21 I977 Site Selection-EIS 21

22 RSW ALP and Draft EA 1990 planning for midfield terminal starts Submitted EA/Master Plan for all new facilities Document was too immense for agency Took back document and split into a short-term EA (runway expansion) and a long-term EA (balance) 1992: Master Plan/Short-term EA/FONSI issued for 6/24 extension.

23 23 RSW Long Term EA FDOT State Land Acquisition Grant Voluntary Purchase of 7,400 Acres Unconditional ALP Approval FAA FONSI Issuance Decrease Project Scope/Impacts Increase Mitigation Establish Mitigation Park EPA, USFWS, USACOE Written Endorsements

24 24 RSW 1994 ALP Revisions Reduce Parallel RW Length from 12,000 to 9,100 Reduce Parallel RW Separation from 5,875 to 5,385 Decrease Estimated Wetland Impacts from 1,010 acres to 547 acres Reduce Land Required for airfield Development from 6,300 acres to 4,130 acres Reduce Project Cost Estimate by $88,500,000 (in 1994 Dollars) Established a 7,000 acre offsite mitigation park EA/FONSI APPROVED MARCH 10, 1994 ALP APPROVED!

25 25 Mitigation Park: A Visionary New Approach 1994 EA/FONSI approved mitigation for the new midfield terminal &future parallel runway. Located 5 miles from airport AOA to reduce wildlife hazards. Largest single mitigation area for one project site within SW Florida. LCPA responsible for maintenance of land in perpetuity. Regionally significant conservation project - provides connectivity between other conservation lands.

26 Mitigation Park: Flow-way Restoration 26

27 Mitigation Park: Farm Field Restoration 27

28 28 Mitigation Park: Created Marsh

29 29 Mitigation Park Awards 2004 Airport Council International (ACI) Environmental Excellence award for Mitigation Park 2008 Florida Airports Council Environmental Excellence Award for Mitigation Park 2009 Florida Native Plant Society Mitigation Award of Honor

30 Sticking to the Vision: It Works!!! 2004 ALP/Master Plan Update Updated the terminal building configuration Changed taxiway/ramp configuration No significant changes or additional impacts in relation to 1994 ALP 30

31 Sticking to the Vision: It Works!!! 2011 ALP/ Master Plan Update Updated the configuration of: ATCT location ARFF location Changes in taxiway/apron layout Parallel runway shift No significant changes and actually reduced impacts in relation to 2004 ALP 31

32 Questions?? 32

Updates on FAA Order F. Agenda. Communicate FAA Order Updates. Educate attendees on the changes to FAA Order

Updates on FAA Order F. Agenda. Communicate FAA Order Updates. Educate attendees on the changes to FAA Order Updates on FAA Order 1050.1F Rhonda Solomon March 3, 2015 Airports Conference 2015 Agenda Communicate FAA Order 1050.1 Updates Educate attendees on the changes to FAA Order 1050.1 1 1 Overview of NEPA

More information

NextGen Implementation Plan An Update

NextGen Implementation Plan An Update NextGen Implementation Plan An Update Presented to: Illuminating Engineering Society Aviation Lighting Committee Government Contacts Subcommittee By: Pamela Whitley, Acting Director for NextGen Integration

More information

ARP SOP No SOP for CATEX Determinations Effective Date: Oct. 01, Federal Aviation Administration

ARP SOP No SOP for CATEX Determinations Effective Date: Oct. 01, Federal Aviation Administration ARP SOP No. 5.00 SOP for CATEX Determinations Effective Date: Oct. 01, 2014 February 2016 Important Points to Note: FAA recently established Standard Operating Procedures (SOP) for CatEx Determinations

More information

October 19, 2017 Community Engagement Panel Meeting #4 Overview of Environmental Effects

October 19, 2017 Community Engagement Panel Meeting #4 Overview of Environmental Effects Lake Elmo Airport Environmental Assessment (EA)/ Environmental Assessment (EAW) Worksheet October 19, 2017 Community Engagement Panel Meeting #4 Overview of Environmental Effects Agenda Public Event #2

More information

How to Prepare Your Categorical Exclusion (CATEX) Information and Prepare a Brief Environmental Assessment

How to Prepare Your Categorical Exclusion (CATEX) Information and Prepare a Brief Environmental Assessment How to Prepare Your Categorical Exclusion (CATEX) Information and Prepare a Brief Environmental Assessment Presented to: By: Peter F. Ciesla, Environmental Protection Specialist Date: CATEX Presentation

More information

EXECUTIVE SUMMARY ES.1 BACKGROUND ES.2 PURPOSE AND NEED FOR THE PROPOSED PROJECT

EXECUTIVE SUMMARY ES.1 BACKGROUND ES.2 PURPOSE AND NEED FOR THE PROPOSED PROJECT EXECUTIVE SUMMARY ES.1 BACKGROUND The purpose of this Draft Environmental Report (DEIR) is the implementation of improvement projects at Charles M. Schulz Sonoma County Airport (the Airport). The improvement

More information

Runway Protection Zones: Incompatible Land Use Alternatives Analysis & Risk Assessment

Runway Protection Zones: Incompatible Land Use Alternatives Analysis & Risk Assessment March 3rd, 2015 Runway Protection Zones: Incompatible Land Use Alternatives Analysis & Risk Assessment Matt Lee Vice President Landrum & Brown Cincinnati, OH Cody Meyer Consultant Landrum & Brown Cincinnati,

More information

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements JUNE 2016 RONALD REAGAN WASHINGTON NATIONAL AIRPORT Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements PREPARED BY: Ricondo & Associates, Inc. IN

More information

agenda ACI-NA/ACC Airport Planning & NEPA Workshop December 9-11, 2013 Washington Marriott Washington, D.C. Thank you to our conference sponsor:

agenda ACI-NA/ACC Airport Planning & NEPA Workshop December 9-11, 2013 Washington Marriott Washington, D.C. Thank you to our conference sponsor: agenda ACI-NA/ACC Airport Planning & NEPA Workshop December 9-11, 2013 Washington Marriott Washington, D.C. Thank you to our conference sponsor: 12:00 PM 5:00 PM Registration Open MONDAY, DECEMBER 9 1:15

More information

August 8, 2017 Community Engagement Panel Meeting #3 Alternatives Evaluation Process & Identification of Preferred Alternatives

August 8, 2017 Community Engagement Panel Meeting #3 Alternatives Evaluation Process & Identification of Preferred Alternatives Lake Elmo Airport Environmental Assessment (EA)/ Environmental Assessment (EAW) Worksheet August 8, 2017 Community Engagement Panel Meeting #3 Alternatives Evaluation Process & Identification of Preferred

More information

FEDERAL AVIATION ADMINISTRATION (FAA) REAUTHORIZATION

FEDERAL AVIATION ADMINISTRATION (FAA) REAUTHORIZATION BACKGROUND STATUS FEDERAL AVIATION ADMINISTRATION (FAA) REAUTHORIZATION Airports are one of the nation s most important hubs for transportation, shipping, and economic development. To ensure safe and efficient

More information

Eric Engstrom, Principal Planner; Steve Kountz, Senior Planner. Incorporating Airport Futures into Portland s 2035 Comprehensive Plan

Eric Engstrom, Principal Planner; Steve Kountz, Senior Planner. Incorporating Airport Futures into Portland s 2035 Comprehensive Plan DATE: January 8, 2015 TO: FROM: CC: SUBJECT: PDX Community Advisory Committee Deborah Stein, Principal Planner and PDX CAC Member Eric Engstrom, Principal Planner; Steve Kountz, Senior Planner Incorporating

More information

Port of Portland Hillsboro Airport Wildlife Hazard Management Plan. Portland, Oregon.

Port of Portland Hillsboro Airport Wildlife Hazard Management Plan. Portland, Oregon. 9. References Executive Summary Oregon Natural Heritage Information Center (ORNHIC). 2008. Data system search for rare, threatened and endangered plants and animals in T1NR2W Sec 20, 28, 29, 32, and 33,

More information

Lindbergh Field Alternatives Considered

Lindbergh Field Alternatives Considered Presented To: San Diego County Regional Airport Authority Strategic Planning Committee Lindbergh Field Alternatives Considered May 22, 2006 1 Alternatives Considered - Outline Lindbergh Field Site Constraints

More information

Airports 101. (or, 10 Things You Need to Know about Airports) MARY ASHBURN PEARSON, AICP ROY G. LEWIS, AICP DELTA AIRPORT CONSULTANTS, INC.

Airports 101. (or, 10 Things You Need to Know about Airports) MARY ASHBURN PEARSON, AICP ROY G. LEWIS, AICP DELTA AIRPORT CONSULTANTS, INC. Airports 101 (or, 10 Things You Need to Know about Airports) MARY ASHBURN PEARSON, AICP ROY G. LEWIS, AICP DELTA AIRPORT CONSULTANTS, INC. 4/10/2015 1 Delta Airport Consultants, Inc. oyes, it s ALL we

More information

Development of a Prototype Air Passenger Survey Database

Development of a Prototype Air Passenger Survey Database ACRP Problem No. 12-03-08 Development of a Prototype Air Passenger Survey Database ACRP Staff Comments: The proposed research should consider ACRP Project 01-13, Developing a Database-Driven Web Application

More information

Master Plan Study Public Workshop #3. June 1-2, 2016

Master Plan Study Public Workshop #3. June 1-2, 2016 Master Plan Study Public Workshop #3 June 1-2, 2016 Agenda Master Plan Status Alternatives Process Development Screening Vision2040 Next Steps Alternatives (Boards) Master Plan Study Progress COMPLETED

More information

CHAPTER 4 IDENTIFICATION AND EVALUATION OF ALTERNATIVES

CHAPTER 4 IDENTIFICATION AND EVALUATION OF ALTERNATIVES CHAPTER 4 IDENTIFICATION AND EVALUATION OF ALTERNATIVES Chapter 4, Identification and Evaluation of Alternatives presents the various alternatives considered to address the facility requirements presented

More information

National Environmental Policy Act (NEPA) Process and Federal Agency Compliance

National Environmental Policy Act (NEPA) Process and Federal Agency Compliance National Environmental Policy Act (NEPA) Process and Federal Agency Compliance Prepared for Northwest/Tribal Transportation Program Training/Conference April 1, 2014 4/2/2014 1 Course Objectives Provide

More information

Airport of the Future. Air Cargo Conference June 2017

Airport of the Future. Air Cargo Conference June 2017 Airport of the Future Air Cargo Conference June 2017 How CVG landed its biggest deal in history. The deal at $1.49 billion is the largest ever one-time capital investment by a company in Northern Kentucky,

More information

Airport Asset Management

Airport Asset Management Airport Investment Assessment Page Airport Asset Management M2P PRODUCT OFFERING GmbH Bockenheimer Landstrasse 94-96 60323 Frankfurt am Main Germany Airport Asset Management M2P Product Offering First

More information

BAGGAGE HANDLING SYSTEM RECAPITALIZATION & OPTIMIZATION

BAGGAGE HANDLING SYSTEM RECAPITALIZATION & OPTIMIZATION BAGGAGE HANDLING SYSTEM RECAPITALIZATION & OPTIMIZATION ACI North America Technical & Operations Committee Vancouver, British Columbia March 24, 2015 Emily Underhill, P.E., A.A.E. Division Director Development

More information

FINAL ENVIRONMENTAL IMPACT REPORT. CHAPTER ONE: EXECUTIVE SUMMARY with RESPONSES TO COMMENTS

FINAL ENVIRONMENTAL IMPACT REPORT. CHAPTER ONE: EXECUTIVE SUMMARY with RESPONSES TO COMMENTS FINAL ENVIRONMENTAL IMPACT REPORT SDCRAA # EIR-06-01 State Clearinghouse No. 2005091105 CHAPTER ONE: EXECUTIVE SUMMARY with RESPONSES TO COMMENTS Lead Agency: SAN DIEGO COUNTY REGIONAL AIRPORT AUTHORITY

More information

Safety Management System (SMS)

Safety Management System (SMS) 14 th Annual Risk Management Conference Concurrent Session 2a Safety Management System (SMS) A Comprehensive Approach Cynthia Schultz PE, AAE Vice President, Airports cschultz@jdasolutions.aero 406-788-7667

More information

SCOPE OF SERVICES FINAL. Airport Master Plan Update. Lehigh Valley International Airport. for the. Lehigh-Northampton Airport Authority

SCOPE OF SERVICES FINAL. Airport Master Plan Update. Lehigh Valley International Airport. for the. Lehigh-Northampton Airport Authority SCOPE OF SERVICES FINAL Airport Master Plan Update at Lehigh Valley International Airport for the Lehigh-Northampton Airport Authority July 1, 2016 FINAL 1 PROJECT UNDERSTANDING AND BACKGROUND The Airport

More information

AIRPORT CARBON FOOTPRINTS: FINDING BENCHMARKS TO GUIDE EMISSION REDUCTIONS

AIRPORT CARBON FOOTPRINTS: FINDING BENCHMARKS TO GUIDE EMISSION REDUCTIONS AIRPORT CARBON FOOTPRINTS: FINDING BENCHMARKS TO GUIDE EMISSION REDUCTIONS Willam Faas, Divya Vasudeva This White Paper presents the main findings of the "Refort" project conducted by Envisa in 2014. The

More information

Pullman-Moscow Regional Airport

Pullman-Moscow Regional Airport FINAL ENVIRONMENTAL ASSESSMENT Environmental Assessment to Comply with FAA Design Standards, Meet Runway Length Requirements, Improve All-Weather Reliability, and Terminal Improvements Pullman-Moscow Regional

More information

Master Development Plans (MDPs) / Geographic Area Plans (GAPS)

Master Development Plans (MDPs) / Geographic Area Plans (GAPS) Master Development Plans (MDPs) / Geographic Area Plans (GAPS) COMPREHENSIVE PLANNING TOOLS FOR OIL AND GAS PROJECTS BUREAU OF LAND MANAGEMENT COLORADO RIVER VALLEY FIELD OFFICE (CRVFO) SILT, COLORADO

More information

Appendix H Support Facilities Preliminary and Intermediate Alternatives Analysis

Appendix H Support Facilities Preliminary and Intermediate Alternatives Analysis Appendix H SUPPORT FACILITIES PRELIMINARY AND INTERMEDIATE ALTERNATIVES ANALYSIS H TABLE OF CONTENTS EXHIBITS TABLES H.1 Evaluation Criteria... 1 H.1.1 Meeting the Base Constrained Demand Level... 1 H.1.2

More information

FINDING OF NO SIGNIFICANT IMPACT AND RECORD of DECISION

FINDING OF NO SIGNIFICANT IMPACT AND RECORD of DECISION DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION ORLANDO AIRPORTS DISTRICT OFFICE SOUTHERN REGION AIRPORTS DIVISION FINDING OF NO SIGNIFICANT IMPACT AND RECORD of DECISION AIRGLADES AIRPORT

More information

Columbia Regional Airport (COU) Columbia, Missouri. Draft Environmental Assessment Airside, Landside, and Surface Transportation Developments

Columbia Regional Airport (COU) Columbia, Missouri. Draft Environmental Assessment Airside, Landside, and Surface Transportation Developments (COU) Columbia, Missouri Draft Environmental Assessment Airside, Landside, and Surface Transportation Developments RS&H No. 226-1077-000 Prepared for the: City of Columbia and U.S. Department of Transportation

More information

Public Review Draft Part III Guidelines for the Application of Criteria for Financial Assistance for Local Projects.

Public Review Draft Part III Guidelines for the Application of Criteria for Financial Assistance for Local Projects. Bureau of Reclamation 800 Cottage Way, MP-170 Sacramento, Calif. 9585-1898 Public Review Draft for the Application of Criteria for March 9, 010 To: All Interested Parties and Organizations The U.S. Department

More information

Pavement Update Track: Engineering

Pavement Update Track: Engineering Pavement Update Track: Engineering 2017 ACC Airports Technical Workshop June 21-22, 2017 Arlington, VA Gregory D. Cline, P.E. FAA Airport Engineering AAS-100 gregory.cline@faa.gov (202) 267-8814 Pavement

More information

Airport Master Plan Update June 14, 2017

Airport Master Plan Update June 14, 2017 Airport Master Plan Update June 14, 2017 www.harveyfield.com The Master Plan is a 20-year plan to understand the needs of current and future users of the Airport. This is important to ensure that safe

More information

Draft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2

Draft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2 Draft Environmental Assessment for Phoenix Sky Harbor International Airport Sky Train Stage 2 Prepared for: City of Phoenix Aviation Department and U.S. Department of Transportation Federal Aviation Administration

More information

PRACTITIONER S HANDBOOK

PRACTITIONER S HANDBOOK AASHTO PRACTITIONER S HANDBOOK 03 August 2016 MANAGING THE NEPA PROCESS FOR TOLL LANES AND TOLL ROADS This Handbook provides recommendations for conducting National Environmental Policy Act (NEPA) studies

More information

Pipelines, Offshore Drilling, and LNG Export Facilities:

Pipelines, Offshore Drilling, and LNG Export Facilities: Pipelines, Offshore Drilling, and LNG Export Facilities: Legal Strategies to Promote More Responsible Decision-Making Jessica Wentz Associate Director, Sabin Center for Climate Change Law November 13,

More information

actions and approvals by the Federal Aviation Administration ( FAA) and the Federal

actions and approvals by the Federal Aviation Administration ( FAA) and the Federal METROPOLITAN AIRPORTS COMMISSION In re MSP 2020 Improvements Final Environmental Assessment/Environmental Assessment Worksheet, Adequacy Determination, and Negative Declaration on the Need for an Environmental

More information

Airport Master Plan Update (AMPU) Phase 2. Scope of Work

Airport Master Plan Update (AMPU) Phase 2. Scope of Work BST AMPU Phase 2 Scope of Work Page 1 of 19 Belfast Municipal Airport Belfast, Maine Airport Master Plan Update (AMPU) Phase 2 Scope of Work The intent of this project is to update the 1999 Belfast Municipal

More information

Downtown Estes Loop Project Frequently Asked Questions

Downtown Estes Loop Project Frequently Asked Questions May 15 th, 2015 Project Status 1) Has Alternative 1 already been selected? Is it a done deal? Response: The NEPA process will proceed with environmental analysis of both the No Action and Alternative 1.

More information

CMPA Campus Wide Solar Array Installation 2 of 4

CMPA Campus Wide Solar Array Installation 2 of 4 Reference 27 This Campus Master Plan Amendment was adopted by the Board of Regents Facilities and Land Management Committee at the June 2013 Board of Regents meeting and placed on the consent agenda for

More information

Overview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations

Overview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations Overview of the Project Development Process Brian Blanchard, PE Assistant Secretary for Engineering and Operations Overall Project Development Process The time it takes to produce a project varies significantly

More information

Building an Enterprise GIS for SFO Then and Now

Building an Enterprise GIS for SFO Then and Now Building an Enterprise GIS for SFO Then and Now Introduction Overhead View Humble Beginnings Organization Overhaul Technical Transformation Stakeholder Engagement Enterprise Implementation Next Destination

More information

M2P Airport Investment Assessment. Airport Asset Management M2P PRODUCT OFFERING

M2P Airport Investment Assessment. Airport Asset Management M2P PRODUCT OFFERING M2P Airport Investment Assessment Airport Asset Management M2P PRODUCT OFFERING 1 M2P Airport Asset Management 2/7 SUCCESSFULLY MANAGING AIRPORT ASSETS The aviation industry is faced with changing requirements

More information

GENERAL INFORMATION ABOUT THIS DOCUMENT

GENERAL INFORMATION ABOUT THIS DOCUMENT GENERAL INFORMATION ABOUT THIS DOCUMENT WHAT IS IN THIS DOCUMENT? This document is a Final Environmental Assessment (EA) for a new Airport Traffic Control Tower (ATCT) for the Phoenix-Mesa Gateway Airport

More information

CRATER LAKE KLAMATH REGIONAL AIRPORT

CRATER LAKE KLAMATH REGIONAL AIRPORT DRAFT ENVIRONMENTAL ASSESSMENT FOR THE CONSTRUCTION OF TAXIWAY J, CONNECTING TAXIWAYS, AND ASSOCIATED DRAINAGE IMPROVEMENTS CRATER LAKE KLAMATH REGIONAL AIRPORT Prepared for City of Klamath Falls, Oregon

More information

Boston Overflight Noise Study. Phase 1 PROJECT CONSULTANT SCOPE OF SERVICES

Boston Overflight Noise Study. Phase 1 PROJECT CONSULTANT SCOPE OF SERVICES Phase 1 PROJECT CONSULTANT SCOPE OF SERVICES March 8, 2004 Project Consultant Phase 1 Scope of Services 3/8/2004 TABLE OF CONTENTS INTRODUCTION... 2 1 STUDY DESIGN... 3 2 PROJECT MANAGEMENT... 4 2.1 Project

More information

Dallas/Fort Worth International Airport ASCE Presentation. Terminal Development Program. November, 2009

Dallas/Fort Worth International Airport ASCE Presentation. Terminal Development Program. November, 2009 Dallas/Fort Worth International Airport ASCE Presentation Terminal Development Program November, 2009 ASCE PRESENTATION, NOVEMBER 2009 Background Objective The objective of today s presentation 1. Review

More information

Distribution Restriction Statement

Distribution Restriction Statement CECW-A Engineer Regulation 1165-2-501 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 ER 1165-2-501 30 September 1999 Water Resources Policies and Authorities CIVIL WORKS

More information

Intelligent Transportation Systems Master Plan

Intelligent Transportation Systems Master Plan Space Coast Transportation Planning Organization Intelligent Transportation Systems Master Plan April 15, 2014 Version 1.0 Prepared for: Space Coast Transportation Planning Organization 2725 Judge Fran

More information

THE KBRA S UNWARRANTED AND COSTLY SUBSIDIES

THE KBRA S UNWARRANTED AND COSTLY SUBSIDIES THE KBRA S UNWARRANTED AND COSTLY SUBSIDIES Background: On January 7, 2010, the final draft of the Klamath Hydroelectric Settlement Agreement (KHSA) and the final draft of the Klamath River Basin Restoration

More information

18 June 2017 PRACTITIONER S HANDBOOK AASHTO ADDRESSING AIR QUALITY ISSUES IN THE NEPA PROCESS FOR HIGHWAY PROJECTS

18 June 2017 PRACTITIONER S HANDBOOK AASHTO ADDRESSING AIR QUALITY ISSUES IN THE NEPA PROCESS FOR HIGHWAY PROJECTS AASHTO PRACTITIONER S HANDBOOK 18 June 2017 ADDRESSING AIR QUALITY ISSUES IN THE NEPA PROCESS FOR HIGHWAY PROJECTS This handbook is intended to assist practitioners in addressing air quality issues, including

More information

3.0 CUMULATIVE PROJECTS SCENARIO

3.0 CUMULATIVE PROJECTS SCENARIO 3.0 CUMULATIVE PROJECTS SCENARIO The CEQA Guidelines define cumulative impacts as two or more individual effects that, when considered together, are considerable or which compound or increase other environmental

More information

Emissions from international air transport and related policies

Emissions from international air transport and related policies Ad hoc Working Group on further Commitments for Annex I Parties under the Kyoto Protocol Emissions from international air transport and related policies ICAO - International Civil Aviation Organization

More information

a g e n d a ACI-NA/ACC Airport NEPA & Planning Workshop November 29-December 1, 2017 RITZ CARLTON Pentagon City Arlington, Virginia

a g e n d a ACI-NA/ACC Airport NEPA & Planning Workshop November 29-December 1, 2017 RITZ CARLTON Pentagon City Arlington, Virginia a g e n d a ACI-NA/ACC Airport NEPA & Planning Workshop November 29-December 1, 2017 RITZ CARLTON Pentagon City Arlington, Virginia 12:00 PM 5:00 PM Registration (Salon 3 Foyer) WEDNESDAY, NOVEMBER 29

More information

Collaborative Decision Making in Aviation

Collaborative Decision Making in Aviation the way we do it Collaborative Decision Making in Aviation In an uncertain world there is reasonable certainty in stating that air travel will increase in the future. How airlines and airports will work

More information

Phoenix Sky Harbor People Mover. ❸ Financial Considerations

Phoenix Sky Harbor People Mover. ❸ Financial Considerations Phoenix Sky Harbor People Mover ❸ Financial Considerations Phoenix Sky Harbor People Mover ❸ Financial Considerations Key Elements: A people mover that accesses the terminals and parking structures at

More information

LA 23 NOGC Railway Relocation PE/NEPA Project

LA 23 NOGC Railway Relocation PE/NEPA Project LA 23 NOGC Railway Relocation PE/NEPA Project LA 23/New Orleans & Gulf Coast Railway Relocation Preliminary Engineering (PE) / National Environmental Policy Act (NEPA) Project Kevin Keller, PE HDR Engineering,

More information

Sunrise Project South I-205 Corridor Improvement Project

Sunrise Project South I-205 Corridor Improvement Project Sunrise Project South I-205 Corridor Improvement Project January 24, 2007 Sunrise and I-205 Project Summary Conclusions Sunrise Scoping Study Key Results South I-205 Scoping Study Key Results South I-205

More information

Policy for Vegetation Management Offsets 30 July 2008

Policy for Vegetation Management Offsets 30 July 2008 Policy for Vegetation Management Offsets 30 July 2008 Offset History During development of the current vegetation management framework, the Minister gave a commitment to industry stakeholders that a policy

More information

ABSTRACT INTRODUCTION

ABSTRACT INTRODUCTION ` D2 EXPANSION PROGRAM AT WASHINGTON DULLES INTERNATIONAL AIRPORT BY FELIX C. BARTHOLOMEW ABSTRACT Lessons Learned: An examination of the Program Management policies and procedures that contributed to

More information

MIA Cargo Facilities and Needs Workshop June 29 th, 2011

MIA Cargo Facilities and Needs Workshop June 29 th, 2011 MIA Cargo Facilities and Needs Workshop June 29 th, 2011 SMP Overview 1. Prior Studies 2. Current MIA Capital Improvement Program (CIP) 3. SMP Goals and Objectives 4. SMP Study Approach 2 SMP Background

More information

PUBLIC DISCLOSURE AUTHORISED

PUBLIC DISCLOSURE AUTHORISED PUBLIC DISCLOSURE AUTHORISED CARIBBEAN DEVELOPMENT BANK EXECUTIVE SUMMARY WITH MANAGEMENT RESPONSE PROJECT COMPLETION VALIDATION REPORT EXPANSION OF THE GRANTLEY ADAMS INTERNATIONAL AIRPORT - BARBADOS

More information

Transportation Project Delivery Process & Mitigation

Transportation Project Delivery Process & Mitigation Florida Department of TRANSPORTATION Transportation Project Delivery Process & Mitigation Marjorie Kirby State Environmental Program Administrator State Environmental Management Office July 2015 Florida

More information

National Environmental Policy Act (NEPA)

National Environmental Policy Act (NEPA) National Environmental Policy Act (NEPA) Jeff Wade Center for Governmental Responsibility University of Florida Levin College of Law The National Environmental Policy Act of 1969 (NEPA) first significant,

More information

Project Delivery. Rodger Rochelle, PE Technical Services Administrator. Mike Holder, PE Chief Engineer

Project Delivery. Rodger Rochelle, PE Technical Services Administrator. Mike Holder, PE Chief Engineer Project Delivery Rodger Rochelle, PE Technical Services Administrator Mike Holder, PE Chief Engineer NC : Project Delivery - Preconstruction Overview of Project Delivery Process Review of Other States

More information

TRAFFIC STUDY GUIDELINES

TRAFFIC STUDY GUIDELINES TRAFFIC STUDY GUIDELINES December 2013 The scope of the traffic impact analysis (TIA) should follow these guidelines and the requirements of VMC 11.80.130 and VMC 11.70, transportation concurrency (attached

More information

ECONOMIC IMPACT FORECAST SYSTEM (EIFS) MODEL CONTENTS

ECONOMIC IMPACT FORECAST SYSTEM (EIFS) MODEL CONTENTS Appendix H Table of Contents APPENDIX H. ECONOMIC IMPACT FORECAST SYSTEM (EIFS) MODEL CONTENTS Economic Impact Forecast System (EIFS) Model... H-1 Economic Impact Forecast System (EIFS) Report... H-4 Final

More information

Alternatives Analysis, New Starts

Alternatives Analysis, New Starts Alternatives Analysis, New Starts E. Beimborn, University of Wisconsin-Milwaukee 1 Outline Overview The process at the local level FTA new starts process Project justification Financial rating Forecasting

More information

5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES

5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES 5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES Section 106 of the National Historic Preservation Act (NHPA) of 1966, as amended (16 U.S.C. Section 470(f)) protects properties that

More information

The Business of Operating a HSR System. May 3rd Denis DOUTÉ CEO, SNCF America, Inc.

The Business of Operating a HSR System. May 3rd Denis DOUTÉ CEO, SNCF America, Inc. The Business of Operating a HSR System May 3rd 2011 Denis DOUTÉ CEO, SNCF America, Inc. 1 Why do public subsidies to HSR make sense? Net Present Value Example : TGV East (investment costs) Total created

More information

Project Planning area. King County Department of Transportation Road Services Division

Project Planning area. King County Department of Transportation Road Services Division NE Novelty Hill Road Transportation Improvement Citizen Advisory Group Presentation Project Planning area King County Department of Transportation Road Services Division i i February 25, 2009 Why are we

More information

Transportation Decision-making Principles of Project Evaluation and Programming. Chapter 1. Introductory Concepts in Transportation Decision Making

Transportation Decision-making Principles of Project Evaluation and Programming. Chapter 1. Introductory Concepts in Transportation Decision Making Transportation Decision-making Principles of Project Evaluation and Programming Chapter 1 Introductory Concepts in Transportation Decision Making K. C. Sinha and S. Labi Purdue University School of Civil

More information

CenterPlace. SW Florida International Airport Cemex Mine. Meridian Center IHub. Gulf Coast Town Center. Miromar Lakes. Youngquist Mine FGCU

CenterPlace. SW Florida International Airport Cemex Mine. Meridian Center IHub. Gulf Coast Town Center. Miromar Lakes. Youngquist Mine FGCU SW Florida International Airport Cemex Mine Meridian Center IHub Gulf Coast Town Center CenterPlace Miromar Lakes FGCU Youngquist Mine University Highlands Grandezza Corkscrew Woods Preserve at Corkscrew

More information

American Society of Military Engineers

American Society of Military Engineers Presentation to American Society of Military Engineers Runway 9-27 Rehabilitation Project POHNPEI INTERNATIONAL AIRPORT, FSM Presented by Wadgy A. Guirguis, P.E. President August 14, 2012 PROJECT SCOPE

More information

South Florida East Coast Corridor (SFECC) Study

South Florida East Coast Corridor (SFECC) Study South Florida East Coast Corridor (SFECC) Study P r o j e c t U p d a t e J u l y 2 7, 2 0 11 FM Number: 417031-3-22-01 Re-introduce Passenger Rail Service on FEC Corridor (85 miles) Improve Freight Capacity

More information

Chapter 7 ENVIRONMENTAL OVERVIEW

Chapter 7 ENVIRONMENTAL OVERVIEW Chapter 7 ENVIRONMENTAL OVERVIEW 7.1 INTRODUCTION This Environmental Overview conceptually evaluates the potential environmental impacts associated with each of the projects recommended in the Master Plan

More information

Opportunities for Accelerating FTA Project Development Post MAP-21

Opportunities for Accelerating FTA Project Development Post MAP-21 Opportunities for Accelerating FTA Project Development Post MAP-21 October 20, 2013 Diana C. Mendes, AICP AECOM Overview Framework for FTA approach to environmental review during project development Provisions

More information

Air Quality, General Conformity & Class Exercise

Air Quality, General Conformity & Class Exercise Air Quality, General Conformity & Class Exercise Thurs., Dec. 10 th, 2009 (8:00 12:00) Ed Melisky Environmental Specialist, Federal Aviation Administration, Airports Planning and Environmental Division,

More information

POLICY AND PROCEDURES MEMORANDUM - AIRPORTS DIVISION. General Processing of Modifications to Agency Airport Design and Construction Standards

POLICY AND PROCEDURES MEMORANDUM - AIRPORTS DIVISION. General Processing of Modifications to Agency Airport Design and Construction Standards U. S. Department of Transportation Federal Aviation Administration Great Lakes Region Illinois, Indiana, Michigan Minnesota, North Dakota, Ohio, South Dakota, Wisconsin 2300 East Devon Avenue Des Plaines,

More information

Pangborn Memorial Airport I One Pangborn Drive I East Wenatchee, WA 98802

Pangborn Memorial Airport I One Pangborn Drive I East Wenatchee, WA 98802 TO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Kickoff Meeting #1 DATE: August 22, 2016 On behalf of the Pangborn Memorial Airport, I would like to invite you to serve

More information

Is Renewable Energy Development Bad for the Environment? Do Environmental Laws Hinder Development of Renewable Energy?

Is Renewable Energy Development Bad for the Environment? Do Environmental Laws Hinder Development of Renewable Energy? Is Renewable Energy Development Bad for the Environment? Do Environmental Laws Hinder Development of Renewable Energy? Altamont Pass Wind Farm East of San Francisco 1981; one of oldest ~7,000 turbines

More information

The 3 M s of ATM. Professor John-Paul Clarke Air Transportation Laboratory Georgia Institute of Technology

The 3 M s of ATM. Professor John-Paul Clarke Air Transportation Laboratory Georgia Institute of Technology The 3 M s of ATM Professor John-Paul Clarke Air Transportation Laboratory Georgia Institute of Technology Outline 2 What was the NextGendream? What is the NextGenreality? What were some of the issues?

More information

WILMINGTON DISTRICT US ARMY CORPS OF ENGINEERS REGULATORY DIVISION. US Army Corps of Engineers BUILDING STRONG

WILMINGTON DISTRICT US ARMY CORPS OF ENGINEERS REGULATORY DIVISION. US Army Corps of Engineers BUILDING STRONG WILMINGTON DISTRICT US ARMY CORPS OF ENGINEERS REGULATORY DIVISION US Army Corps of Engineers Organization The Wilmington District Regulatory Division consists of 4 field offices in Wilmington, Washington,

More information

Railway-Related Cement Consumption Outlook

Railway-Related Cement Consumption Outlook Contact: Ed Sullivan, Senior VP & Chief Economist, (847) 972.9006, esullivan@cement.org Trevor Storck, Economist, (847) 972.9044, tstorck@cement.org May 2018 Railway-Related Cement Consumption Outlook

More information

CHAPTER 21: COMMITMENT OF RESOURCES

CHAPTER 21: COMMITMENT OF RESOURCES CHAPTER 21: COMMITMENT OF RESOURCES 21.1 INTRODUCTION In accordance with the National Environmental Policy Act (NEPA) and the Council on Environmental Quality s implementing procedures under Title 40,

More information

Chapter 5.0 Alternatives Analysis

Chapter 5.0 Alternatives Analysis Chapter 5.0 Alternatives Analysis The Master Plan process thus far has accumulated the baseline of existing airport data, presented the outlook for the future in terms of operational activity, and defined

More information

TEXAS TRANSPORTATION PLAN

TEXAS TRANSPORTATION PLAN TEXAS TRANSPORTATION PLAN TxDOT Planning Conference June 5, 2014 Michelle Maggiore, P.E., CH2M HILL Agenda 1 Performance-based planning what is it? 3 2 How is performance-based planning addressed in the

More information

CHAPTER 9 DISCUSSIONS, CONCLUSIONS, AND RECOMMENDATIONS

CHAPTER 9 DISCUSSIONS, CONCLUSIONS, AND RECOMMENDATIONS CHAPTER 9 DISCUSSIONS, CONCLUSIONS, AND RECOMMENDATIONS This chapter summarizes the results of feasibility level investigations undertaken to identify solutions to the water and related land resource problems

More information

Chapter 9 Wetlands Park Study Team

Chapter 9 Wetlands Park Study Team Chapter 9 Wetlands Park Study Team Objective How can we help Clark County facilitate implementation of the Clark County Wetlands Park Master Plan, and provide for the management of various ecosystems within

More information

WATERSHED MANAGEMENT INITIATIVE: GOALS & IMPLEMENTATION OBJECTIVES, JULY 26, 1999

WATERSHED MANAGEMENT INITIATIVE: GOALS & IMPLEMENTATION OBJECTIVES, JULY 26, 1999 WATERSHED MANAGEMENT INITIATIVE: GOALS & IMPLEMENTATION OBJECTIVES, JULY 26, 1999 The following table indicates the draft goals and objectives for the Santa Clara Basin WMI process. The overall objectives

More information

2.1 Summary of Existing and Future Population Estimates

2.1 Summary of Existing and Future Population Estimates SECTION 2 Demographics This technical memorandum identifies the uncertainties and describes potential future demographics that might affect wastewater facilities in the City of McCall, Idaho (the City).

More information

US 70 Corridor James City Project Update. Craig Young, Three Oaks Engineering US 70 Corridor Commission May 21, 2015

US 70 Corridor James City Project Update. Craig Young, Three Oaks Engineering US 70 Corridor Commission May 21, 2015 US 70 Corridor James City Project Update Craig Young, Three Oaks Engineering US 70 Corridor Commission May 21, 2015 Presentation Overview Improving the US 70 Corridor The Project Team Where Are We Today?

More information

Northwest State Route 138 Corridor Improvement Project

Northwest State Route 138 Corridor Improvement Project Northwest State Route 138 Corridor Improvement Project Los Angeles County, CA DISTRICT 7- LA- 138 (PM 0.0/36.8); DISTRICT 7- LA- 05 (PM 79.5/83.1); DISTRICT 7- LA- 14 (PM 73.4/74.4) 265100/ 0700001816

More information

WETLANDS AND OPEN WATERS Compensatory Mitigation Definitions of Factors

WETLANDS AND OPEN WATERS Compensatory Mitigation Definitions of Factors Adverse effects as used in this section of the SOP means any adverse ecological effect on wetlands or areas of open water. Those effects, or impacts, include filling, excavating, flooding, draining, clearing,

More information

Looking After Our Environment

Looking After Our Environment Item: 12.06 Subject: DRAFT BIODIVERSITY CERTIFICATION ASSESSMENT AND APPLICATION - PORT MACQUARIE AIRPORT AND SURROUNDING LAND Presented by: Development and Environment Services, Matt Rogers Alignment

More information

ADDENDUM #1. The following sheets have been revised and are being reissued as part of this addendum:

ADDENDUM #1. The following sheets have been revised and are being reissued as part of this addendum: ADDENDUM #1 AIRFIELD IMPROVEMENTS EXTEND, MARK, AND LIGHT RUNWAY 6-24 AND TAXIWAY ALPHA REHABILITATE RUNWAY 6-24 at the LAKE WALES MUNICIPAL AIRPORT FAA AIP NO: TBD FDOT FM NO: TBD BID NO: 16-412 5/11/16

More information

Florida Department of TRANSPORTATION Florida Transportation Plan (FTP) and Strategic Intermodal System (SIS) Strategic Plan Updates

Florida Department of TRANSPORTATION Florida Transportation Plan (FTP) and Strategic Intermodal System (SIS) Strategic Plan Updates Florida Department of TRANSPORTATION Florida Transportation Plan (FTP) and Strategic Intermodal System (SIS) Strategic Plan Updates Jim Wood Director, Office of Policy Planning Overview The FTP and the

More information

Commission hearing on the preparation for RP3

Commission hearing on the preparation for RP3 Commission hearing on the preparation for RP3 14th December 2016 Brussels Discussion document Introduction The performance scheme is at the heart of Single European Sky (SES) policy and is a major driver

More information

Special Publication SJ2004-SP27. Affordability Analysis of Alternative Water Supply

Special Publication SJ2004-SP27. Affordability Analysis of Alternative Water Supply Special Publication SJ2004-SP27 of Alternative Water Supply of Alternative Water Supply Technical Memorandum February 9, 2004 TABLE OF CONTENTS Section Page EXECUTIVE SUMMARY i A. Background and Scope

More information