Subject: State aid N 47/2008 Austria Modification of feed-in tariffs for electricity from renewable sources under the Austrian Green Electricity Act
|
|
- Ashlie Walton
- 5 years ago
- Views:
Transcription
1 EUROPEAN COMMISSION Brussels, 10.VI.2008 C(2008)2749 PUBLIC VERSION WORKING LANGUAGE This document is made available for information purposes only. Subject: State aid N 47/2008 Austria Modification of feed-in tariffs for electricity from renewable sources under the Austrian Green Electricity Act Madam, 1. PROCEDURE The Austrian Green Electricity Act 1 entered into force on 1 January It established a system for nationwide tariff support for green electricity. On 4 July 2006 the Commission approved the measure (NN 162/A/2003 and N 317/A/2006) 2, which was amended in 2006, as it was considered as being compatible with the common market in application of Article 87(3)(c) EC. By letter of 23 January 2008 Austria notified an amendment of the Austrian Green Electricity Act concerning an increase of feed-in tariffs by simplified procedure. Article 4 2 of Regulation 794/2004 of 21 April foresees that The following alterations to existing aid shall be notified on the simplified notification form set out in Annex II: (a) increases in the budget of an authorised aid scheme exceeding 20 %; BGBl I Nr. 149/2002 Letter to Austria of 4 July 2006, C(2006) 2955 Commission Regulation (EC) No 794/2004 of 21 April 2004 implementing Council Regulation (EC)No 659/1999 laying down detailed rules for the application of Article 93 of the EC Treaty, OJ L 140, , p. 1 Seiner Exzellenz Herrn Frank-Walter STEINMEIER Bundesminister des Auswärtigen Werderscher Markt 1 D Berlin Commission européenne, B-1049 Bruxelles - Belgique -Europese Commissie, B-1049 Brussel België Telefon: (0)
2 (b) (c) prolongation of an existing authorised aid scheme by up to six years, with or without an increase in the budget; tightening of the criteria for the application of an authorised aid scheme, a reduction of aid intensity or a reduction of eligible expenses However, Austria intends to increase the aid amount to the producers of green electricity by a supplement to the feed-in tariffs. From this follows that the notification does not meet the conditions as mentioned above for applying the simplified procedure. Finally the Commission asked Austria to provide further information by letter of 20 February 2008, to which Austria replied on 25 March To a further request for information of the Commission Austria replied on 23 May DESCRIPTION OF THE AID 1. The Austrian Green Electricity Act was enacted to incorporate into national law the obligations arising to Austria from Parliament and Council Directive 2001/77/EC 4 on the promotion of electricity from renewable sources in the internal electricity market. The Directive had to be transposed into national law until 27 October The Act s implementation is being constantly watched by the regulating authority Energie-Control GmbH". The following description concerns the tariff support system for electricity produced from renewable sources (in the following green electricity ). 2.1 The Green Electricity Act in force The support mechanism for green electricity 2. The Green Electricity Act 2003 obliges the so-called eco-balance group representatives ( Ökobilanzgruppenverantwortliche ) to purchase green electricity from eligible generators at a fixed feed-in tariff ( Einspeisevergütung ). The eco-balance group representatives attribute the purchased electricity to the electricity traders, who are obliged by the law to buy the attributed electricity at a fixed transfer price ( Verrechnungspreis ). The difference between the feed-in tariff for electricity and the fixed transfer price is raised by a levy imposed on the consumption of electricity by final consumers ( Förderbeitrag ). 3. The Austrian energy regulator, Energie-Control GmbH, reports annually on the implementation of the scheme analysing to what extent the measure achieves its objectives and can make proposals for improvements or adaptations of the support mechanism. The feed-in tariffs paid to renewable electricity producers 4. The eco-balance group representatives are obliged to buy green electricity which is offered to them at prices decided by the Ministry of Economic Affairs and Labour. 5. As to the calculation of the feed-in tariffs, 11(2) and (3) of the Act stipulates as follows: a. (2) In accordance with the objectives of this Federal Law, pricing shall be such that it promotes a continuous increase in the production of electric energy from green electricity plants. Prices shall be guided by the average production costs of costefficient plants. Distinction shall be made between new and old plants whenever they differ in terms of costs or have been granted public support. Prices shall be set in accordance with the various primary energy sources used, with due regard to 4 OJ L 283 of , p.33 2
3 technical and economic efficiency. They may include other means of differentiation, such as by maximum capacity or annual electricity production. A time-based differentiation by day/night and summer/winter within the meaning of section 25 of the Electricity Act shall be admissible. In order to ensure a secure investment climate, the minimum period in which the set tariffs are applied following initial operation of the respective green electricity plant shall be ten years. b. (3) Determination of the average production costs shall be based on the costs of an efficiently managed undertaking which finances the plant under financial market conditions. Service life, investment cost, operating cost, adequate return on capital employed and the quantities of electricity produced per year shall be taken into account. ( ) 6. The tariffs were calculated in order to compensate for the difference between the market price for electricity and the long-term marginal costs of green electricity production. 7. During the negotiation process in Austria, the feed-in tariffs were in most cases set at a lower level than proposed by the experts. In addition, the implementing regulation establishing the feed-in tariffs guaranteed the tariffs only for 13 years following the start of operation of every installation. Only for new or significantly revitalised small hydro power installations the feed-in tariff was guaranteed for 15 years. The average market price for base load electricity is published every three months by Energie Control GmbH The funding of the support mechanism is based on two pillars: Fixed prices to be paid by the electricity traders on the purchase of green electricity and a levy raised from all consumers of electricity. 9. On 24 May 2006, Austria informed the Commission that it has adopted the following amendments of the Act concerning the system of feed-in tariffs of green electricity production: 10. The law maintained the former level of the feed-in tariffs for different types of installations installed/substantially modernised or for installations for which administrative approval was granted at the latest by certain cut-off dates. For other installations the law established the possibility to fix prices through an implementing regulation. The principles for setting the prices remained substantially the same as under the former law. The law newly introduced that prices must be oriented on installations of best available technique and must have in mind the support of installations at the most efficient locations. The prices were fixed for 2006, and reduced subsequently on an annual basis. 11. The duration of the guaranteed feed-in tariff also depends on the type of installation, but does not exceed 13 years from the start of the installation s operation. Almost all types of installation benefit from a purchase obligation at market price minus balancing costs for a further period of 12 years. 2.2 Notified amendments subject to this decision 12. According to information provided by Austria the demand for certain raw materials, which are the basis for producing green electricity from liquid bio mass and bio gas, has 5 The regulator uses for this calculation publicly available indices of electricity exchanges or institutions consoling indices (e.g. SWEP, Platt s Notierungen). The modified law establishes that the market price will be calculated as arithmetic average of the prices fixed by the European Energy Exchange (EEX) for the next four baseload quarter futures. 3
4 substantially increased and resulted in a strong price push of up to 100 % since the beginning of the year Therefore, installations producing this kind of green electricity could not cover their production cost and may have to close. 13. The number of installations operating with bio gas is currently estimated at 270 with a total capacity of 65 MW and an annual feed-in between 400 GWh and 500 GWh, whereas on the side of liquid bio mass 45 installations operate with a total capacity of 15 MW and a feed in of 80 GWh annually. 14. To avoid a declining production of green electricity based on bio gas and liquid bio mass Austria intends to grant additional support to the guaranteed feed-in tariffs as provided by paragraphs 11 and 30 (3) of the Green Electricity Act. Based on the assumption of a 100% price increase of renewable raw materials for installations producing electricity from bio gas and liquid bio mass, the additional costs per kwh are calculated with 5,5 Cent/kWh. With the objective to cover at least a large part of the additional production cost Austria proposes to grant a raw materials supplement of 4 Cent/kWh. 15. Excluded from the supplement are new installations, which started its operation after the introduction of the supplement, mixed installations ("Mischfeuerungsanlagen"), hybrid installations and installations, for which the "Oekostromabwicklungsstelle" (the competent authority for green electricity) has no obligation for contracting or compensating or where its obligation is limited on compensating the difference to the market price minus cost of balancing energy ("Ausgleichsenergie"). According to Austria, these installations can adequately react to increasing prices of raw materials or are not or not anymore eligible for the aid. 16. Austria will provide a budget of EUR 20 mio. for this measure that is applicable only in the year The budget which originates from not used funds for feed-in tariffs of the year 2007 (EUR 13 mio.) as approved on the basis of the Green Electricity Act and formerly approved funds for supporting bio gas and solid bio mass of the year 2008 (EUR 7 mio). Austria intends authorising the supplement of 4 Cent/kWh by introducing an additional paragraph 11 (a) into the Austrian Green Electricity Act. If the measure's budget was not sufficient to support the whole production as described above the Austrian authorities would accordingly reduce the supplement of 4 Cent. Austria undertakes not granting the supplement before the Commission approves this measure. 3. ASSESSMENT 17. The Commission has examined the proposed amendment in accordance with Article 87 et seq. EC and Article 61 et seq. EEA 6 and has decided, in the light of its policy on environmental protection, not to raise objections to its implementation Presence of State aid pursuant to Article 87(1) EC 18. Article 87(1) EC lays down four conditions. First, there must be an intervention by the State or through State resources. Second, it must confer an advantage on the recipient. Third, the intervention must be liable to affect trade between Member States. Fourth, it must distort or threaten to distort competition. 19. The amendment of the Act stipulates that the beneficiaries generate income from the guaranteed prices which they would not receive from the market. The measure therefore transfers an advantage. 6 The following assessment is based on both the EC Treaty and the EEA Agreement, but for reasons of simplification, in the following assessment it will only be referred to the EC Treaty provisions. 4
5 20. The beneficiaries constitute a selective group of undertakings in the sense of Article 87(1) EC as the measure solely favours certain green electricity producers. 21. At least some of the measure s beneficiaries are engaged in sectors where trade between Member States takes place and, therefore, the measure is liable to distort competition. 3.2 Assessment of the notified amendments 22. The Commission assessed the compliance of the supplementary support of renewable electricity producers with the Article 87(3)(c) EC and particularly on the basis of the new environmental aid guidelines 7 as applicable from the 2 April With regard to the calculation method for production costs, on which the feed-in tariffs are based, Austria has undertaken to respect the provisions of the Green Electricity Act, which includes investment cost, consumption cost (e.g. raw materials), fixed operational cost (e.g. regular maintenance), insurance and administrative cost. The production cost of the electricity is determined by the tool OekoCost developed by the Austrian Energy Agency. Austria provided detailed information on the variables and parameters of the tool. 24. Based on these methods Austria submitted several examples of cost calculation for electricity producers using bio gas which differed by size (100 kw, 500 kw, 1000 kw, 1500 kw) resulting in increases of production cost of 6,89 Cent/kWh, 6,02 Cent/kWh, 5,96 Cent/kWh and 5,31 Cent/kWh under the assumption that the price for the substrate cost have increased by 100 %. 25. Austria provided official information on the price development of the basic agricultural raw materials (among others: corn, silo corn, wheat, rape seed, palm oil), rape oil, methanol, "Rapsresskuchen" and demonstrated that until the end of the year 2007 the prices for these raw materials increased between 100% and 200 % compared to the situation in the period 2006/ The Commission verified the calculation method determining the cost of electricity production based on bio gas and liquid bio mass. It also verified whether the announced cost increases correspond with the development of market prices for the used raw materials. It appears that the method applied, appropriately determines the cost of green electricity subject to this decision. The information on the level of prices for raw materials, from which Austria concluded on the need of a supplement, appears to be in line with the market developments. 27. The proposed supplement to the feed-in tariff complies with the new Community Guidelines for Environmental Protection, first of all with chapter on operating aid for renewable energy sources. In particular, the notified amendment is in line with point 109 (a) concerning operating aid to compensate for the difference between the cost of producing energy from renewable sources and the market price of the form of electricity concerned and point 109 (c) of the guidelines providing the possibility to grant operating aid for the production of renewable energy from biomass exceeding the amount of investment where Member States can show that the aggregate costs borne by the undertakings after plant depreciation are still higher than the market prices of the energy. 28. The Commission therefore finds that the Austrian authorities have illustrated that the support granted under the measure at stake will not exceed the extra production costs of 7 OJ C 82 of , p. 1 5
6 the renewable energy sources supported by the measure. Further, it can be concluded that Austria continues to apply the support mechanism described above and in particular the methods of calculating the amount of aid as formerly approved by the Commission. These mechanisms and methods for calculating the notified aid to firms the supplement - are in line with point 109 of the new Environmental Aid Guidelines as applicable from the 2. April Therefore, the supplement of 4 Cent/kWh for certain installations, which is limited to the year 2008, is in accordance with point 109 of the new environmental aid guidelines. In the context of the Commission Decision on the cases NN 162/A/2003 and N 317/A/2006 Austria has already given the commitment to ensure the respect of the environmental aid guidelines when adapting the tariffs in the future. Austria confirmed its undertaking to exclude any over-compensation of the additional cost by the proposed supplement, which it would reduce if necessary. 30. With regard to the new environmental aid guidelines applicable from 2 April 2008 the Commission reminds Austria that it is required to amend its existing environmental aid schemes in order to bring them into line with the new rules within 18 months after the entry into force of the guidelines. Austria confirmed its intention the revise the Green Electricity Act, which new version it would notify to the Commission Further the Commission reminds the Austrian authorities that according to point 49 of the guidelines state aid may be an appropriate instrument only for those uses of renewable energy sources where the environmental benefit and sustainability is evident. The proposed Directive on the Promotion of the Use of Energy from Renewable Sources (footnote 17 of the Environmental Aid Guidelines) states in Art. 15 that bioliquids will be eligible for financial support only if they fulfil the listed sustainability criteria. 4. DECISION 31. The Commission has concluded not to raise objections to the notified modification of the feed-in tariff as described and formerly approved by the Commission Decision regarding the cases NN 162/A/2003 and N 317/A/2006 as it complies with the environmental aid guidelines (OJ C 82 of , p. 1) and is therefore considered compatible with the common market in application of Article 87(3)(c) EC. 32. The Commission requests Austria to submit an annual report on the implementation of the aid enabling the Commission to verify that all conditions stipulated above were fulfilled when implementing the measure. Any change in the conditions under which the aid is granted must be notified in advance. If this letter contains confidential information which should not be disclosed to third parties, please inform the Commission within fifteen working days of the date of receipt. If the Commission does not receive a reasoned request by that deadline, you will be deemed to agree to the disclosure to third parties and to the publication of the full text of the letter in the authentic language on the Internet site: Your request should be sent by registered letter or fax to: European Commission Directorate-General for Competition Directorate for State Aid State Aid Greffe B-1049 Brussels Fax No: (0032)
7 Please mention the name and number of the case in all the correspondence. Yours faithfully, For the Commission Neelie KROES Member of the Commission 7
State aid SA /N FI Fixed operating aid for power plants using renewable energy sources
EUROPEAN COMMISSION Brussels, 22.03.2011 C (2011) 1951 PUBLIC VERSION WORKING LANGUAGE This document is made available for information purposes only. Subject: State aid SA. 32470 2011/N FI Fixed operating
More informationCIS Photovoltaic re-cladding project, Manchester
EUROPEAN COMMISSION Brussels, 14.07.2004 C(2004)2634 fin Subject: State aid N 543/2003 United Kingdom CIS Photovoltaic re-cladding project, Manchester Sir, 1. PROCEDURE (1). By letter dated 24 th November
More informationEUROPEAN COMMISSION. Brussels, SG (...) D/ Subject: N 112/04 SE, Tax exemption for biofuels
EUROPEAN COMMISSION Brussels, SG (...) D/ Subject: N 112/04 SE, Tax exemption for biofuels Excellency, The Commission wishes to inform Sweden that, having examined the information supplied by your authorities
More information1) I am pleased to inform you that the Commission has decided to approve the above aid scheme until 31 December 2013.
EUROPEAN COMMISSION Brussels, 04/04/2011 C (2011) 2378 final PUBLIC VERSION WORKING LANGUAGE This document is made available for information purposes only. Subject: State aid SA.32119 (2011/N) Spain State
More informationEUROPEAN COMMISSION. State aid No N 327/ United Kingdom (Northern Ireland) Northern Ireland Beef Quality Initiative
EUROPEAN COMMISSION Brussels, 06.09.2002 C(2002) 3246 Subject: State aid No N 327/2002 - United Kingdom (Northern Ireland) Northern Ireland Beef Quality Initiative Sir, I have the honour to inform you
More informationEmbargo VISTA illimité(*)
EUROPEAN COMMISSION Brussels, C (2015) Embargo VISTA illimité(*) Subject: State aid/germany (Baden-Wurttemberg) Aid No SA. 39942 (2014/N) Support for pruning of fruit trees in scattered orchards Sir, The
More informationEUROPEAN COMMISSION. State Aid SA (2016/N) Austria Aid to fast broadband infrastructure in rural areas in Niederösterreich
EUROPEAN COMMISSION Brussels, 3.4.2017 C(2017) 2260 final PUBLIC VERSION This document is made available for information purposes only. Subject: State Aid SA.46731 (2016/N) Austria Aid to fast broadband
More informationNOTE FOR THK ATTE)~ITIO!V OF MR LUIS ROMERO RKQUKIIIA, DIRECTOR GENERAL OF LEI AL SERVICE
Q Re f. Ares(2011)504421-10/05/2011 EUROPEAN COMMtSS1ON QIRECTORATE-GENERAL HOME AFFAIRS Director General ) 0 NAI N11 hotne.a.3(2011}547783 NOTE FOR THK ATTE)~ITIO!V OF MR LUIS ROMERO RKQUKIIIA, DIRECTOR
More information3. The Commission asked Cyprus to provide further information by letter of 8 May 2009, to which Cyprus replied by letter of 29 May 2009.
EUROPEAN COMMISSION Brussels, 02.07.2009 C(2009)5398 Subject: State aid N 143/2009 Cyprus Aid scheme to encourage electricity generation from large commercial wind, solar, photovoltaic systems and biomass
More informationGreen Electricity in Austria - Summary 2010
Green Electricity in Austria - Summary 2010 Report by E-Control GmbH pursuant to section 25 para 1 Ökostromgesetz (Green Electricity Act) September 2010 Supported green power contributes 11.4% of public
More informationEUROPEAN COMMISSION. State aid SA (2011/N) Austria Third Prolongation of the ERP Transport Programme
EUROPEAN COMMISSION Brussels, 25.7.2012 C(2012) 5052 final PUBLIC VERSION WORKING LANGUAGE This document is made available for information purposes only. Subject: State aid SA.33669 (2011/N) Austria Third
More informationCouncil of the European Union Brussels, 22 May 2017 (OR. en)
Council of the European Union Brussels, 22 May 2017 (OR. en) Interinstitutional File: 2016/0398 (COD) 9507/17 NOTE From: To: Presidency Council COMPET 431 MI 442 ETS 43 DIGIT 146 SOC 419 EMPL 326 CONSOM
More informationEUROPEAN COMMISSION. State aid SA (2017/N) Sweden Tax reductions for pure and high-blended liquid biofuels
EUROPEAN COMMISSION Brussels, 14.9.2017 C(2017) 6169 final PUBLIC VERSION This document is made available for information purposes only. Subject: State aid SA.48069 (2017/N) Sweden Tax reductions for pure
More informationEUROPEAN COMMISSION. The Right Hon Jack STRAW MP Secretary of State for Foreign and Commonwealth Affairs Downing Street London SW1A 2AL United Kingdom
EUROPEAN COMMISSION Brussels, 05.X.2005 C(2005)3660 final Subject: State aid N 267/2005 United Kingdom Rural Broadband Access Project Sir, I. PROCEDURE 1. By letter registered on 31 May 2005, pursuant
More informationCOMP/M BP / ASSOCIATED BRITISH FOODS / JV
EN Case No COMP/M.4798 - BP / ASSOCIATED BRITISH FOODS / JV Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 30/08/2007
More informationOfficial Journal of the European Union. (Acts whose publication is obligatory)
5.11.2003 L 287/1 I (Acts whose publication is obligatory) REGULATION (EC) No 1946/2003 OF THE EUROPEAN PARLIAMT AND OF THE COUNCIL of 15 July 2003 on transboundary movements of genetically modified organisms
More informationCase AT/2009/0970: Wholesale broadband access in Austria. Opening of Phase II investigation pursuant to Article 7(4) of Directive 2002/21/EC 1
EUROPEAN COMMISSION Brussels, 5/10/2009 C(2009)7720 SG-Greffe (2009) D/6009 Rundfunk und Telekom Regulierungs-GmbH (RTR) Mariahilferstraße 77-79 A-1060 Wien Austria For the attention of: Mr Georg Serentschy
More informationEmbargo VISTA illimité(*)
EUROPEAN COMMISSION Brussels, C(2016) final Embargo VISTA illimité(*) Subject: State aid/germany SA. 42766 (2015/N) Rheinland-Pfalz: Support for the conservation of genetic resources in agriculture (Conservation
More information1 OJ No C 24, , p OJ No C 240, , p OJ No C 159, , p. 32.
Council Directive 91/533/EEC of 14 October 1991 on an employer's obligation to inform employees of the conditions applicable to the contract or employment relationship Official Journal L 288, 18/10/1991
More informationDGE 2 EUROPEAN UNION. Brussels, 21 March 2018 (OR. en) 2016/0149 (COD) PE-CONS 69/17
EUROPEAN UNION THE EUROPEAN PARLIAMT THE COUNCIL Brussels, 21 March 2018 (OR. en) 2016/0149 (COD) PE-CONS 69/17 POSTES 28 TELECOM 369 MI 974 COMPET 884 DIGIT 285 CONSOM 403 CODEC 2106 LEGISLATIVE ACTS
More informationEmbargo VISTA illimité(*)
EUROPEAN COMMISSION Brussels, C(2015) Embargo VISTA illimité(*) Subject: State aid/germany SA.41143 (2015/N) Hessen - Preservation of the diversity of genetic resources in agriculture ( animal genetic
More informationThis document is meant purely as a documentation tool and the institutions do not assume any liability for its contents
2001L0018 EN 21.03.2008 003.001 1 This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents B DIRECTIVE 2001/18/EC OF THE EUROPEAN PARLIAMENT
More informationCase No COMP/M RICOH / IKON. REGULATION (EC) No 139/2004 MERGER PROCEDURE. Article 6(1)(b) NON-OPPOSITION Date: 24/10/2008
EN Case No COMP/M.5334 - RICOH / IKON Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 24/10/2008 In electronic form on
More informationEUROPEAN COMMISSION. State aid SA (2016/N) Czech Republic Individual subprograms for ensuring interoperability in railway transport
EUROPEAN COMMISSION Brussels, 7.4.2017 C(2017) 2222 final PUBLIC VERSION This document is made available for information purposes only. Subject: State aid SA.44621 (2016/N) Czech Republic Individual subprograms
More informationCase No COMP/M ADM / PURA. REGULATION (EEC) No 4064/89 MERGER PROCEDURE. Article 6(1)(b) NON-OPPOSITION Date: 03/04/2003
EN Case No COMP/M.3044 - ADM / PURA Only the English text is available and authentic. REGULATION (EEC) No 4064/89 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 03/04/2003 Also available in the
More informationProposal for a DIRECTIVE OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL
Proposal for a DIRECTIVE OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL amending Directive 2003/88/EC concerning certain aspects of the organisation of working time (presented by the Commission) EN 1 EN
More informationCase No COMP/M SHELL / BEB. REGULATION (EEC) No 4064/89 MERGER PROCEDURE. Article 6(1)(b) NON-OPPOSITION Date: 20/11/2003
EN Case No COMP/M.3293 - SHELL / BEB Only the English text is available and authentic. REGULATION (EEC) No 4064/89 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 20/11/2003 Also available in the
More informationEuropean Parliament plenary vote, 17 January this Directive have the sole function of showing
Overview of final draft text of Renewable Energy Directive (REDII) Comparing proposals from the EU Commission, Council and Parliament as of January 17th, 2018 - Includes only text elements which comprises
More informationCase No COMP/M NTN / SNR. REGULATION (EC) No 139/2004 MERGER PROCEDURE. Article 6(1)(b) NON-OPPOSITION Date: 27/03/2007
EN Case No COMP/M.4346 - NTN / SNR Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 27/03/2007 In electronic form on the
More information(2) A submission of information by the German authorities was received on 29 September 2008.
EUROPEAN COMMISSION Brussels, C(2012) PUBLIC VERSION WORKING LANGUAGE This document is made available for information purposes only. Subject: State aid SA.25611 (2012/NN) (ex CP 96/2008) Germany Alleged
More informationEUROPEAN UNION. Brussels, 25 April 2014 (OR. en) 2013/0084 (COD) PE-CONS 63/14 STATIS 39 SOC 185 ECOFIN 237 CODEC 711
EUROPEAN UNION THE EUROPEAN PARLIAMT THE COUNCIL Brussels, 25 April 2014 (OR. en) 2013/0084 (COD) PE-CONS 63/14 STATIS 39 SOC 185 ECOFIN 237 CODEC 711 LEGISLATIVE ACTS AND OTHER INSTRUMTS Subject: REGULATION
More informationCOMMISSION OF THE EUROPEAN COMMUNITIES COMMISSION INTERPRETATIVE COMMUNICATION
EN EN EN COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 05.02.2008 C(2007)6661 COMMISSION INTERPRETATIVE COMMUNICATION on the application of Community law on Public Procurement and Concessions to Institutionalised
More informationDe-Energisation Code of Practice
De-Energisation Code of Practice NIE Power Networks Changes for SEM/IME Implementation Issued 30 th August 2007 30/08/2007 DE-ENERGISATION CODE OF PRACTICE Contents Revision History... 3 1. Introduction...
More informationCOUNCIL OF THE EUROPEAN UNION. Brussels, 19 July /12 Inte rinstitutional File: 2012/0190(COD) ENV 628 ENT 181 CODEC 1935 PROPOSAL
COUNCIL OF THE EUROPEAN UNION Brussels, 19 July 2012 12733/12 Inte rinstitutional File: 2012/0190(COD) ENV 628 ENT 181 CODEC 1935 PROPOSAL from: Commission dated: 12 July 2012 No Cion doc.: COM(2012) 393
More informationCase No COMP/M PAI / CHR. HANSEN. REGULATION (EC) No 139/2004 MERGER PROCEDURE. Article 6(1)(b) NON-OPPOSITION Date: 18/07/2005
EN Case No COMP/M.3845 - PAI / CHR. HANSEN Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 18/07/2005 In electronic form
More informationAuctions preparation, course, wins. Katarzyna Szwed Lipińska, counsellor at law Director, Department of Support Systems Energy Regulatory Office
Katarzyna Szwed Lipińska, counsellor at law Director, Department of Support Systems Energy Regulatory Office Warsaw, March 2015 Installations subject to the auction procedure: existing including modernised
More informationUNITED NATIONS COMMISSION ON INTERNATIONAL TRADE LAW (UNCITRAL)
UNITED NATIONS COMMISSION ON INTERNATIONAL TRADE LAW (UNCITRAL) UNCITRAL Model Law on Procurement of Goods, Construction and Services with Guide to Enactment CONTENTS PREAMBLE CHAPTER I. GENERAL PROVISIONS
More informationEnergie-Control Austria Interpretative Note on Transparency Requirements and Third-Party Access Services Concerning Storage Facilities
Energie-Control Austria Interpretative Note on Transparency Requirements and Third-Party Access Services Concerning Storage Facilities As of 2012-02-24 Page 1 / 12 Contents 1. Aim of the interpretative
More informationMEMORANDUM OF UNDERSTANDING BETWEEN THE SINGLE RESOLUTION BOARD AND THE EUROPEAN CENTRAL BANK IN RESPECT OF COOPERATION AND INFORMATION EXCHANGE
MEMORANDUM OF UNDERSTANDING BETWEEN THE SINGLE RESOLUTION BOARD AND THE EUROPEAN CENTRAL BANK IN RESPECT OF COOPERATION AND INFORMATION EXCHANGE MEMORANDUM OF UNDERSTANDING BETWEEN THE SINGLE RESOLUTION
More informationAuditing of Swedish Enterprises and Organisations
Auditing of Swedish Enterprises and Organisations March 1st 2018 version 2018:1 1 General Application 1.1 These General Terms govern the relationship between the auditor ( the Auditor ) and the client
More informationThe North-Atlantic Free Trade Agreement and the Trans-Pacific Partnership: Side-by-Side Comparison. NAFTA Chapter 10: Government Procurement
The North-Atlantic Free Trade Agreement and the Trans-Pacific Partnership: Side-by-Side Comparison NAFTA Chapter 10: Government Procurement Chapter Ten: Government Procurement Chapter Fifteen: Government
More informationEDPS - European Data Protection Supervisor CEPD - Contrôleur européen de la protection des données
EDPS - European Data Protection Supervisor CEPD - Contrôleur européen de la protection des données Opinion on the notification for prior checking received regarding the "Manager Desktop" file of the European
More informationCOMMISSION REGULATION (EC)
L 313/40 Official Journal of the European Union 28.11.2009 COMMISSION REGULATION (EC) No 1152/2009 of 27 November 2009 imposing special conditions governing the import of certain foodstuffs from certain
More informationOfficial Journal of the European Union DIRECTIVE 2003/54/EC OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL. of 26 June 2003
15.7.2003 L 176/37 DIRECTIVE 2003/54/EC OF THE EUROPEAN PARLIAMT AND OF THE COUNCIL of 26 June 2003 concerning common rules for the internal market in electricity and repealing Directive 96/92/EC THE EUROPEAN
More informationCase No COMP/M EDP / HIDROELECTRICA DEL CANTABRICO. REGULATION (EC) No 139/2004 MERGER PROCEDURE
EN Case No COMP/M.3448 - EDP / HIDROELECTRICA DEL CANTABRICO Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 09/09/2004
More informationEUROPEAN COMMISSION. Case AT/2014/1617: Voice call termination on individual mobile networks in Austria
EUROPEAN COMMISSION Brussels, 2.7.2014 C(2014) 4640 final Rundfunk und Telekom Regulierungs-GmbH (RTR) Mariahilferstraße 77-79 A-1060 Wien Austria For the attention of: Mr Johannes Gungl Fax: + 43 1 58
More informationCOMMUNICATION FROM THE COMMISSION CRITERIA FOR THE COMPATIBILITY ANALYSIS OF TRAINING STATE AID CASES SUBJECT TO INDIVIDUAL NOTIFICATION
EN EN EN COMMUNICATION FROM THE COMMISSION CRITERIA FOR THE COMPATIBILITY ANALYSIS OF TRAINING STATE AID CASES SUBJECT TO INDIVIDUAL NOTIFICATION 1. INTRODUCTION 1. The Lisbon European Council in March
More informationCase No COMP/M WPP / CORDIANT. REGULATION (EEC) No 4064/89 MERGER PROCEDURE. Article 6(1)(b) NON-OPPOSITION Date: 25/07/2003
EN Case No COMP/M.3209 - WPP / CORDIANT Only the English text is available and authentic. REGULATION (EEC) No 4064/89 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 25/07/2003 Also available in
More informationRULES GOVERNING THE SECONDMENT OF NATIONAL EXPERTS TO THE EUROPEAN PARLIAMENT BUREAU DECISION 4 MAY 2009
7.1.5. RULES GOVERNING THE SECONDMENT OF NATIONAL EXPERTS TO THE EUROPEAN PARLIAMENT BUREAU DECISION 4 MAY 2009 The Bureau, - having regard to Rule 22 of Parliament s Rules of Procedure, - after consulting
More informationOfficial Journal of the European Union. (Non-legislative acts) REGULATIONS
17.3.2017 L 72/1 II (Non-legislative acts) REGULATIONS COMMISSION REGULATION (EU) 2017/459 of 16 March 2017 establishing a network code on capacity allocation mechanisms in gas transmission systems and
More informationCOMMISSION OF THE EUROPEAN COMMUNITIES. Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL
COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 19.12.2007 COM(2007) 856 final 2007/0297 (COD) C6-0022/08 Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL Setting emission performance
More informationCOMMISSION OF THE EUROPEAN COMMUNITIES. Draft. COMMISSION REGULATION (EU) No /
EN EN EN COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, C Draft COMMISSION REGULATION (EU) No / of [ ] amending Commission Regulation (EC) No 1702/2003 laying down implementing rules for the airworthiness
More informationTHE EUROPEAN PARLIAMENT AND THE COUNCIL OF THE EUROPEAN UNION,
Regulation (EC) No 1071/2009 of the European Parliament and of the Council of 21 October 2009 establishing common rules concerning the conditions to be complied with to pursue the occupation of road transport
More informationANNEX XIV COMPETITION
27.10.2017 - EEA AGREEMENT - ANNEX XIV p. 1 ANNEX XIV COMPETITION TABLE OF CONTENTS A. Merger Control B. Vertical Agreements and Concerted Practices C. Technology Transfer Agreements D. Specialization
More informationCOMMISSION OPINION. of XXX
EUROPEAN COMMISSION Brussels, XXX [ ](2012) XXX draft COMMISSION OPINION of XXX pursuant to Article 3(1) of Regulation (EC) No 714/2009 and Article 10(6) of Directive 2009/72/EC - Austria - Certification
More informationI. FACTS. 1. Procedure. 2. The pr oject
Case No: 69491 Event No: 631871 Dec. No: 158/12/COL EFTA SURVEILLANCE AUTHORITY DECISION of 9 May 2012 on the aid to Akershus Energi Varme AS for the construction and expansion of district heating and
More informationEUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Customs Policy, Legislation, Tariff Customs Legislation INFORMATION DOCUMENT
Ref. Ares(2017)3064802-19/06/2017 EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Customs Policy, Legislation, Tariff Customs Legislation Brussels, 19 June 2017 TAXUD(A2)/LG/dt taxud.a.2(2017)3500081
More information(Legislative acts) DIRECTIVE 2014/55/EU OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 16 April 2014 on electronic invoicing in public procurement
6.5.2014 L 133/1 I (Legislative acts) DIRECTIVES DIRECTIVE 2014/55/EU OF THE EUROPEAN PARLIAMT AND OF THE COUNCIL of 16 April 2014 on electronic invoicing in public procurement (Text with EEA relevance)
More informationARTICLE 29 DATA PROTECTION WORKING PARTY
ARTICLE 29 DATA PROTECTION WORKING PARTY 17/EN WP 256 Working Document setting up a table with the elements and principles to be found in Binding Corporate Rules (updated) Adopted on 29 November 2017 INTRODUCTION
More informationOfficial Journal of the European Union L 96/29 DECISIONS COMMISSION
9.4.2008 Official Journal of the European Union L 96/29 II (Acts adopted under the EC Treaty/Euratom Treaty whose publication is not obligatory) DECISIONS COMMISSION COMMISSION DECISION of 3 April 2008
More informationCase No COMP/M CVC / DSI. REGULATION (EC) No 139/2004 MERGER PROCEDURE. Article 6(1)(b) NON-OPPOSITION Date: 25/09/2007
EN Case No COMP/M.4850 - CVC / DSI Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 25/09/2007 In electronic form on the
More informationIn electronic form on the EUR-Lex website under document number 32017M8640
EUROPEAN COMMISSION DG Competition Case M.8640 - CVC / BLACKSTONE / PAYSAFE Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION
More informationCOMMISSION DELEGATED REGULATION (EU) No /.. of
EUROPEAN COMMISSION Brussels, 4.3.2014 C(2014) 1332 final COMMISSION DELEGATED REGULATION (EU) No /.. of 4.3.2014 supplementing Directive 2013/36/EU of the European Parliament and of the Council with regard
More informationFRAMEWORK PARTNERSHIP AGREEMENT WITH HUMANITARIAN ORGANISATIONS
FRAMEWORK PARTNERSHIP AGREEMENT WITH HUMANITARIAN ORGANISATIONS The European Union (hereinafter referred to as the Union ), represented by the European Commission (hereinafter referred to as the Commission
More informationCOMMITTEE OF THE REGIONS
11.2.2016 EN Official Journal of the European Union C 52 A/1 V (Announcements) ADMINISTRATIVE PROCEDURES COMMITTEE OF THE REGIONS VACANCY NOTICE No CDR/AD14/6BIS/2016 concerning a post of DIRECTOR (M/F)
More informationEUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Indirect Taxation and Tax Administration Value Added Tax VEG N O 067
EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Indirect Taxation and Tax Administration Value Added Tax VAT Expert Group 18 th meeting 5 February 2018 taxud.c.1(2018)588112 EN Brussels,
More informationAct. on the Promotion of Renewable Energies in the Heat Sector. (Erneuerbare-Energien-Wärmegesetz EEWärmeG)*) of 2008
Act on the Promotion of Renewable Energies in the Heat Sector (Erneuerbare-Energien-Wärmegesetz EEWärmeG)*) of 2008 The Bundestag has adopted the following Act: Contents Part 1 General provisions Article
More informationCase SI/2009/0957: Wholesale (physical) network infrastructure access (including shared or fully unbundled access) at a fixed location
EUROPEAN COMMISSION Brussels, 11/09/2009 C(2009)7007 SG-Greffe (2009) D/5397 Agencija za pošto in elektronske komunikacije Republike Slovenije (APEK) Stegne 7, p.p. 418 1001 Ljubljana Slovenia For the
More informationEUROPEAN COMMISSION. Commission Decision concerning Case DK/2014/1665: Review of the LRAIC model on the fixed markets in Denmark for the year 2015
EUROPEAN COMMISSION Brussels, 24.11.2014 C(2014) 9090 final Danish Business Authority (DBA) Dahlerups Pakhus Langelinie Allé 17 DK-2100 Copenhagen Denmark For the attention of: Ms. Betina Hagerup Director
More informationActive Intelligent. Regulation (EC) No 450/2009 of 29 May 2009 on active and intelligent
ก : Active intelligent ก ก 2552 Active intelligent (Regulation (EC) No 450/2009 of 29 May 2009 on active and intelligent materials and articles intended to come into contact with food) : ก Active Intelligent
More informationPrior Checking Opinion
Prior Checking Opinion "Data processing for social media monitoring" at the European Central Bank (ECB) Case 2017-1052 *** The ECB intends to monitor and track mentions of ECB related topics in different
More informationDIRECTIVE 2012/34/EU OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 21 November 2012 establishing a single European railway area (recast)
02012L0034 EN 24.12.2016 001.001 1 This text is meant purely as a documentation tool and has no legal effect. The Union's institutions do not assume any liability for its contents. The authentic versions
More informationStructural Assistance Act
Issuer: Riigikogu Type: act In force from: 01.09.2015 In force until: 04.12.2015 Translation published: 10.08.2015 Amended by the following acts Passed 04.06.2014 RT I, 21.06.2014, 1 Entry into force 01.07.2014
More informationCountry profile: Austria
Country profile: Austria Last updated: 23/04/2015 1 Implementation of Tracking Systems As electricity tracking system Austria uses electricity disclosure, which provides consumers with details about the
More informationPART IV: SECTOR SPECIFIC RULES. State aid to cinematographic and other audiovisual works
Page 1 1 Introduction PART IV: SECTOR SPECIFIC RULES State aid to cinematographic and other audiovisual works (1) Audiovisual works, and cinema in particular, play an important role in shaping European
More informationCase No COMP/M BOEING / AVIALL. REGULATION (EC) No 139/2004 MERGER PROCEDURE. Article 6(1)(b) NON-OPPOSITION Date: 18/08/2006
EN Case No COMP/M.4241 - BOEING / AVIALL Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 18/08/2006 In electronic form
More informationCase No COMP/M SCHNEIDER ELECTRIC/ INVENSYS. REGULATION (EC) No 139/2004 MERGER PROCEDURE. Article 6(1)(b) NON-OPPOSITION Date: 29/11/2013
EN Case No COMP/M.7005 - SCHNEIDER ELECTRIC/ INVENSYS Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 29/11/2013 In electronic
More informationEUROPEAN COMMISSION. Comments pursuant to Article 7(3) of Directive 2002/21/EC
EUROPEAN COMMISSION Brussels, 26.11.2012 C(2012) 8828 Comisión del Mercado de las Telecomunicaciones (CMT) Carrer de la Marina 16-18 E-08005 Barcelona Spain For the attention of: Mr. Bernardo Lorenzo Presidente
More informationGreen Electricity Report Austria 2010
Green Electricity Report Austria 2010 Report by Energie-Control GmbH pursuant to section 25(1) Ökostromgesetz (Green Electricity Act) September 2010 Energie-Control GmbH Rudolfsplatz 13a, 1010 Vienna www.e-control.at
More informationCase No COMP/M LUFTHANSA CARGO / AIR FRANCE FINANCE / BRITISH AIRWAYS / GLOBAL FREIGHT EXCHANGE / JV
EN Case No COMP/M.2830 - LUFTHANSA CARGO / AIR FRANCE FINANCE / BRITISH AIRWAYS / GLOBAL FREIGHT EXCHANGE / JV Only the English text is available and authentic. REGULATION (EEC) No 4064/89 MERGER PROCEDURE
More informationREPUBLIC OF LITHUANIA LAW ON ELECTRICITY 20 July, 2000, No. VIII 1881 as amended by 26 June, 2001, No. IX-408 Vilnius CHAPTER ONE GENERAL PROVISIONS
Official translation REPUBLIC OF LITHUANIA LAW ON ELECTRICITY 20 July, 2000, No. VIII 1881 as amended by 26 June, 2001, No. IX-408 Vilnius CHAPTER ONE GENERAL PROVISIONS Article 1. Purpose of the Law This
More information5965/18 OM/vc 1 DGG 1B
Council of the European Union Brussels, 9 February 2018 (OR. en) Interinstitutional File: 2017/0350 (COD) 5965/18 EF 35 ECOFIN 90 SURE 9 CODEC 163 'I' ITEM NOTE From: To: Subject: General Secretariat of
More informationCase M ABBOTT LABORATORIES / ST JUDE MEDICAL
EUROPEAN COMMISSION DG Competition Case M.8060 - ABBOTT LABORATORIES / ST JUDE MEDICAL Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Decision on the implementation
More informationStatutory Cost Regulation relating to vaccines for veterinary use
Statutory Cost Regulation relating to vaccines for veterinary use TierImpfStKostV 2010 Date of issue: 16 December 1996 Full title: "Statutory cost regulation relating to vaccines for veterinary use of
More information2. Enterprises qualifying for mandatory audits Non-SMEs.
Guidance Note on the carrying out of mandatory energy audits by non-smes pursuant to LN 196/2014 transposing the energy efficiency Directive 2009/27/EU. 1. Introduction Regulation 10 of LN 196 makes it
More informationDECISIONS. (Text with EEA relevance) Having regard to the Treaty on the Functioning of the European Union, and in particular Article 149 thereof,
L 159/32 28.5.2014 DECISIONS DECISION No 573/2014/EU OF THE EUROPEAN PARLIAMT AND OF THE COUNCIL of 15 May 2014 on enhanced cooperation between Public Employment Services (PES) (Text with EEA relevance)
More informationCase No COMP/M BOEING / LOCKHEED MARTIN / UNITED LAUNCH ALLIANCE JV. REGULATION (EC) No 139/2004 MERGER PROCEDURE
EN Case No COMP/M.3856 - BOEING / LOCKHEED MARTIN / UNITED LAUNCH ALLIANCE JV Only the English text is available and authentic. REGULATION (EC) No 139/2004 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION
More informationGUIDELINE ON LIBERALIZATION OF ELECTRICITY MARKET IN KOSOVO
GUIDELINE ON LIBERALIZATION OF ELECTRICITY MARKET IN KOSOVO Pristina, 18 January 2017 Adresa: Rr. Dervish Rozhaja nr. 12, 10000 Prishtinë, Kosovë Tel: 038 247 615 lok.. 101, Fax: 038 247 620, E-mail: info@ero-ks.org,
More informationEUROPEAN UNION. Brussels, 11 September 2009 (OR. en) 2008/0151 (COD) PE-CONS 3663/09 ENER 191 ENV 383 CODEC 758
EUROPEAN UNION THE EUROPEAN PARLIAMT THE COUNCIL Brussels, 11 September 2009 (OR. en) 2008/0151 (COD) PE-CONS 3663/09 ER 191 V 383 CODEC 758 LEGISLATIVE ACTS AND OTHER INSTRUMTS Subject: DIRECTIVE OF THE
More informationCALL FOR EXPRESSION OF INTEREST FOR TWO POSTS OF SECONDED NATIONAL EXPERTS (SNE) AND ESTABLISHMENT OF A RESERVE LIST
CALL FOR EXPRESSION OF INTEREST FOR TWO POSTS OF SECONDED NATIONAL EXPERTS (SNE) AND ESTABLISHMENT OF A RESERVE LIST REF.: S2R.2018.01 Publication External Title of function Seconded National Experts (SNE)
More informationInformation on the focal point for the Convention. Information on the point of contact for the Convention
Questionnaire for the REPORT OF MONTENEGRO ON THE IMPLEMENTATION OF THE CONVENTION ON ENVIRONMENTAL IMPACT ASSESSMENT IN A TRANSBOUNDARY CONTEXT in the period 2006 2009 Information on the focal point for
More informationEnergie-Control Austria Executive Board Ordinance on Provisions for the Gas Market Model (Gas Market Model Ordinance 2012) Title 1 Principles
Energie-Control Austria Executive Board Ordinance on Provisions for the Gas Market Model (Gas Market Model Ordinance 2012) In exercise of section 41 Gaswirtschaftsgesetz (Natural Gas Act) 2011, BGBl. (Federal
More informationElectricity Supply Agreement
Electricity Supply Agreement 1. General 1.1 Mazoon Electricity Company SAOC (the Supplier) shall on or from the Start Date, subject to the satisfactory completion of a Supply Application Form, provide
More informationEnergy from Renewable Sources Act
Energy from Renewable Sources Act Promulgated, State Gazette No. 35/3.05.2011, effective 3.05.2011, amended and supplemented, SG No. 29/10.04.2012, effective 10.04.2012, SG No. 54/17.07.2012, effective
More informationCouncil Directive 98/59/EC of 20 July 1998 on the approximation of the laws of the Member States relating to collective redundancies
Council Directive 98/59/EC of 20 July 1998 on the approximation of the laws of the Member States relating to collective redundancies Official Journal L 225, 12/08/1998 P. 0016-0021 THE COUNCIL OF THE EUROPEAN
More informationCase No COMP/M EDF / SEEBOARD. REGULATION (EEC) No 4064/89 MERGER PROCEDURE. Article 6(1)(b) NON-OPPOSITION Date: 25/07/2002
EN Case No COMP/M.2890 - EDF / SEEBOARD Only the English text is available and authentic. REGULATION (EEC) No 4064/89 MERGER PROCEDURE Article 6(1)(b) NON-OPPOSITION Date: 25/07/2002 Also available in
More informationRULES FOR THE ISSUE OF CERTIFICATION OF SUSTAINABILITY OF BIOFUELS AND BIOLIQUIDS, FOOD AND FEED, TECHNICAL/CHEMICAL AND BIOENERGY APPLICATIONS
RULES FOR THE ISSUE OF CERTIFICATION OF SUSTAINABILITY OF BIOFUELS AND BIOLIQUIDS, FOOD AND FEED, TECHNICAL/CHEMICAL AND BIOENERGY APPLICATIONS In force as from 08/09/2015 RINA Services S.p.A. Via Corsica,
More informationTHE EEG SURCHARGE FOR 2014
THE EEG SURCHARGE FOR 2014 October 15, 2013 The EEG Surcharge for 2014 2 Contents 1. Facts versus feelings... 3 2. Overview of the 2014 EEG surcharge and its components... 3 3. Factors contributing to
More informationE R E F European Renewable Energies Federation
The new EC guidelines : what is the likely impact of making RES support mechanisms compatible with the State Aid provisions of the TFEU? Dr. Emmanuelle Raoult Presentation of EREF 2 EREF Action in the
More informationFRAMEWORK BORDER-CROSSING AGREEMENT
ANNEX 4: FRAMEWORK BORDER-CROSSING AGREEMENT Framework Agreement between the Government of the Republic of XXX and the Government of the Republic of XXX on Border Dispatching for Rail Transport The Government
More information