Review of Island & Reclamation Studies for Container Terminal Development on the Pacific Coast of Panama. Autoridad del Canal de Panamá

Size: px
Start display at page:

Download "Review of Island & Reclamation Studies for Container Terminal Development on the Pacific Coast of Panama. Autoridad del Canal de Panamá"

Transcription

1 Review of Island & Reclamation Studies for Container Terminal Development on the Pacific Coast of Panama Autoridad del Canal de Panamá March 23, 2016

2 Table of Contents 1 OBJECTIVE EARLIER STUDIES Artificial Island Preliminary Study December Objectives...1 Study Results...2 Conclusions (2001)...4 Update to Conclusion (2015) Pacific Side Excavation & Dredging Material Disposal Alternatives Evaluation Objectives...7 Study Results Artificial Island Feasibility Study May Objectives Results Conclusions (2004) Farfan/Palo Seco Island Project Feasibility Study June Objectives Results Conclusions (2015) OVERALL ASSESSMENT Summary Artificial Island Palo Seco Island Findings >> PAGE i

3 List of Figures Figure 1: Artificial Island Concept 2001 (P1 Long Breakwater)... 3 Figure 2: Short Listed Beneficial Use Sites for Excavated Material... 8 Figure 3: Short Listed Offshore Island Sites (2004) Figure 4: General Area for Palo Seco Port Options Figure 5: Proposed Rail Link from Palo Seco Terminal to Albrook (2005) List of Tables Table 1: Assessment of Current Validity of Artificial Island Preliminary Study... 7 Table 2: Base Cost of Materials Transport to Disposal Sites (2004 US$)... 9 Table 3 : Development Costs of Offshore Island Disposal Sites (2004 US$)* Table 4:Estimated Cost of Palo Seco Albrook Rail Link (2005 US$) Table 5:Assessment of Current Validity of Palo Seco Rail Link Table 6: Estimated Cost of the Palo Seco Phase 1 Terminal (2005 US$) Table 7: Estimated Cost of Equipment & Superstructure Palo Seco (2015 US$) Table 8:Assessment of Current Validity of Palo Seco Island Project >> PAGE ii

4 1 OBJECTIVE This scope of work aims to assess the validity of a series of previously developed studies performed by Moffatt & Nichol for Autoridad del Canal de Panamá (ACP) in light of current market costs for construction, maritime development revenues and materials availability. In particular, the following three studies are highlighted: Contract No Preliminary Study of Island Development at the Pacific Entrance of the Panama Canal (December 2001) Contract No Feasibility Study of Island Development at the Pacific Entrance of the Panama Canal (May 2004) Contract No Feasibility Study of Palo Seco/Farfan Land Reclamation to Develop a Port Facility (June 2005) The above mentioned studies were developed to evaluate the potential beneficial use of some 70 million cubic meters (m 3 ) of excavation material from the construction of the Third Set of Locks, including the construction of an artificial island. Based on the conclusions of the earlier studies, alternative disposal sites were recommended and used for the placement of this excavation material. Given the need for additional container terminal capacity on the Pacific Coast of Panama, this study updates and comments on the validity of the conclusions and recommendations of these earlier studies. The objective is to re examine the key considerations and construction costs of an island or near shore development at the Pacific Entrance of the Panama Canal taking into account current conditions. 2 EARLIER STUDIES 2.1 ARTIFICIAL ISLAND PRELIMINARY STUDY DECEMBER 2001 OBJECTIVES In 2001, ACP requested that Moffatt & Nichol make a preliminary evaluation of the feasibility of the construction of an artificial island on the Pacific Coast, to be developed as a container port to meet increasing demand and limited expansion capacity in the Balboa area. At that time, the Master Planning studies for the Canal expansion were well advanced, with the expectation that the New Locks Project would generate up to some 70 million m 3 of excavation material. >> PAGE 1

5 The objective of this first study was to evaluate the technical, logistical and financial viability of taking advantage of this material to construct an artificial island to provide a new container port for the Pacific Side. The first element of the study was to develop a transportation cost model to evaluate the most efficient and cost effective means of moving the excavated material from the various work fronts to the proposed island location. STUDY RESULTS Somewhat surprisingly, the cost assessment clearly favored the rail option using a purpose built rail line to transport the material from the Locks area to the island site. This option also offered the advantage of a lower environmental and socio economic impact than the most expensive truck option. However, as the study progressed, it became clear that the use of the island for commercial ship traffic required a number of key elements that went beyond the simple construction of an island using the excavation material. These included: A breakwater to protect the ships at berth Dredging to accommodate the larger vessels expected in the future A 3 km access highway from the shoreline to the island location Power and other utility connections to the new island Customs and other agency facilities services for the container operations Displacement or reduction of one of the primary Panama Canal anchorages In order to use the full excavated volume of 70 million m 3 from the P1 channel alignment and considering the expected initial bulking and later consolidation of the material, it was calculated that the island would cover some 350 ha. Within this area, it was considered that five marine terminals could be built, with at least three being for containers, as shown in Figure 1, below. >> PAGE 2

6 Figure 1: Artificial Island Concept 2001 (P1 Long Breakwater) The preliminary study concluded that an island project was technically feasible, with basic materials transport costs from the excavation work by rail to the site estimated to be a total of some US$260 million for the P1 channel alignment. The total cost to construct the 350 ha unimproved island (based on the P1 channel alignment and long breakwater option) including landside access was estimated to be some US$542 million, not including navigation access, basic infrastructure, nor the container terminal facilities. The full development cost of the island including basic infrastructure, but without container or value added installations, varied from a low of $274/m 2 to a high of $451/m 2 depending on the Locks channel alignment (P1 or P2) and the breakwater options selected (long or short). If the cost of disposal to the >> PAGE 3

7 existing ACP disposal sites was discounted from the development costs 1, the range of values fell to a low of $87/m 2 and a high of $226/m 2. The study estimated that the investment cost of a fully developed 32 ha terminal module with eight gantry cranes and an annual capacity of 950,000 TEU was on the order of $149 million at that time, using 2001 costs, including support facilities but excluding yard equipment and inventory control systems which were assumed would be provided by the terminal operator. Considering the support facilities required for the module, a 48 ha terminal would result in a unit cost of $310/m 2, over and above the improved island construction cost. A 950,000 TEU capacity container terminal module on the artificial island was expected to cost approximately $157 per TEU of annual throughput in 2001 dollars. Construction of the island and basic infrastructure to support the terminal added another $40 per TEU (based on the P1 alignment and long breakwater option), indicating a total cost, including cranes, of $197 per TEU of annual throughput, assuming that the cost of disposal to the ACP sites was discounted from the estimate. With the full cost of the island construction included, the cost per TEU of installed capacity increased to $263 per TEU of annual throughput. At that time, a typical U.S. West Coast terminal on a developed site was expected to cost on the order of $165 per TEU of throughput, with land costs varying from $30 to $95 per TEU, depending on location and demand. Asian and Far East terminal construction costs were some 15% to 20% higher than the US counterparts, with land costs varying considerably depending on location. However, revenues from the Asian terminals were generally double the rates received by operators in Latin America at that time. THIS ROUGH COMPARISON INDICATED THAT THE PANAMA ARTIFICIAL ISLAND CONTAINER TERMINAL COST WAS AT THE HIGH END OF THE RANGE, IF FULL COST RECOVERY WAS REQUIRED. CONCLUSIONS (2001) As a result of the preliminary report conclusions, the ACP Board recommended that the project should be evaluated in more detail, but the scope of work was also expanded to include other location options for marine terminal development as well as other uses. 1 In order to provide a realistic estimate of the opportunity cost for the island, it was assumed at the time of the study that the basic cost of materials disposal to the existing ACP disposal sites would be borne by the Third Locks Project and should be discounted from the island cost. >> PAGE 4

8 UPDATE TO 2015 As noted, the basic objective of the artificial island study was to examine the beneficial use of the Locks expansion excavated material in a way that would provide economic benefits to Panama. While the study showed that the concept was viable technically, the economics relied heavily on the fact that the fill material would be provided at no cost, except for transportation and placement on the island. More importantly, the fundamental concept of the island was that it would receive up to some 70 million m 3 of excavated material, which then determined the 350 ha area of the island. With each marine terminal module covering some 35 to 40 ha each, it was clear that the island would accommodate multiple terminals, which were expected to be developed over a long period of time. If a private group was to develop an offshore marine facility in the area under today s conditions, the first consideration would be the source of material, and the second would be the initial size of the reclaimed area. For container development, a typical first phase project will have on the order of 1.0 million TEU annual throughput capacity and it is common to see projects with the capability of expansion to some 3.0 to 5.0 million TEU, in order to recover the high basic infrastructure investment. Given that the Third Locks excavation material would no longer be provided for use in the construction of the artificial island, this 2015 update now assumes that fill material will be obtained and purchased from alternative sources. As a result, the initial island size would be smaller than the disposal concept. On this basis, and allowing space for support industries, government agencies, commercial development and service facilities, a new island would be expected to cover some 150 ha, with one terminal having 850 m of berth as the first phase and reclamation provided for expansion for one future phase. A detailed up to date cost estimate of the previously proposed island concepts is outside the scope of this study. However, attempts were made to generate rough approximations of current costs based on escalation averages from R.S. Means and some preliminary research into fill material sources. In order to update the costs of the artificial island concept to 2015, the island layout resulting from the P2 alignment and short breakwater was used as it closely resembled the minimum requirements identified above. The requirements for dredging, breakwater, access trestle, main utilities and power would still be similar to those indicated in the original concept, while all fill material, rock and materials transport would have to be sourced alternatively. For the purposes of updating the cost estimate, it was assumed that fill material could be obtained from offshore sand borrow areas and would be purchased, dredged and transported to the island site. It was assumed that the 31 million m 3 of sand estimated to be required to create the 153 ha island would be available from existing concessions. However, very little reliable information is available on the characteristics and extents of the sand deposits. The availability of such a >> PAGE 5

9 large volume of sand from existing nearby concessions exceeds the current authorizations and is unlikely to be approved. In addition, rock for the construction of containment dikes was assumed to be purchased from nearby quarries and trucked to the site. Assuming suitable fill material and rock were available and were purchased, the updated cost to construct the improved island including basic infrastructure was estimated to be $1,472/m 2. The updated cost for developing the container terminal excluding yard equipment and inventory control systems was estimated to be an additional $412/m 2. CLEARLY THIS UPDATE MAKES THE PROJECT LESS ATTRACTIVE THAN THE EARLIER VERSION, WHICH IN ITSELF, BASED ON M&N S RECOMMENDATION, WAS CONSIDERED BY ACP TO BE AN EXPENSIVE MEANS OF DEVELOPING ADDITIONAL PORT CAPACITY ON THE PACIFIC COAST. IT THEREFORE FOLLOWS THAT THE ARTIFICIAL ISLAND CONCEPT WOULD BE MUCH LESS FEASIBLE UNDER CURRENT CONDITIONS AND WOULD NOW BE MOST UNLIKELY TO BE DEVELOPED BY PRIVATE INTERESTS. CONCLUSION (2015) Table 1 summarizes the assessment of the current validity of the 2001 Artificial Island Preliminary Study findings and recommendations. Since the 2001 study was based on the premise of using the volume of material expected to be generated from the Third Locks Project, this predefined volume dictated the size of the island. If the island were to be constructed now using fill material imported from offshore borrow sites, the size of the island would be dictated by the minimum area required for the container terminal. Thus cost comparisons are made on a cost per square meter basis. >> PAGE 6

10 Table 1: Assessment of Current Validity of Artificial Island Preliminary Study Source of fill material Transportation of fill material million m 3 of rock fill provided by ACP from Third Locks excavation material at only the transportation cost. By rail from Third Locks excavation 31 million m 3 of sand fill would have to be purchased and dredged from offshore borrow areas. It is unknown whether sufficient volume of suitable sand is available from nearby concessions and whether its extraction would be approved. Rock would have to be purchased from local quarries. Sand fill would have to be barged in from the offshore borrow areas. Rock for containment dikes would have to be trucked in from quarries. Unit cost improved $315/m 2 (P1 Long Breakwater) 1 island $393/m 2 (P2 Short Breakwater) 1 $1,472/m 2 (P2 Short Breakwater) 3 Unit cost container terminal 2 $310/m 2 (48 ha module) $412/m 2 (153 ha, Phase 1+2) Conclusion Comparison to typical developments indicated artificial island container terminal was at the high end of the range of costs. Artificial island concept should be evaluated in more detail and other location options as well as other uses should be studied. The need to purchase and import sand and rock to create the island makes the project less attractive than the 2001 version and would now be most unlikely to be developed by private interests. Given that the rail link would no longer be needed to import the excavation material, the project would no longer include connection to the existing Trans Isthmian rail system. 1 Costs for improved island in 2001 assume full cost of island construction (i.e. cost of disposal to ACP sites not discounted from estimate) 2 Yard equipment and inventory control systems not included, assumed provided by terminal operator 3 Estimated cost for purchasing fill material (assumed available) and rock included in estimate. 2.2 PACIFIC SIDE EXCAVATION & DREDGING MATERIAL DISPOSAL ALTERNATIVES EVALUATION OBJECTIVES In order to evaluate the most cost effective and environmentally acceptable option for disposal of the excavated material from the Locks expansion project, ACP requested Moffatt & Nichol in 2003 to undertake a review of the cost and environmental implications of all disposal options for the excavated material. >> PAGE 7

11 In addition to the material from the excavation of the Locks, the scope of the study was also widened to include the evaluation of alternative sites to receive the dredged material from the Pacific Entrance widening and deepening project. This study included an assessment of all identified offshore, near shore and landside potential locations for the beneficial use of the excavated/dredged material or simple disposal. These options were identified and refined in a series of work sessions attended by ACP executive staff from several departments and initially included a total of some 59 locations. The sites also included consideration of the various Unexploded Ordnance Sites (UXOs) in the area of the Pacific Locks that were essentially abandoned by the U.S. following the handing over of the Canal, but were of great concern to the Panama Government due to increasing levels and dangers of unauthorized entry. Through a series of reports and work sessions, the preferred options were reduced to a short list of 17 locations, and then refined to six preferred sites, as shown in Figure 2. Figure 2: Short Listed Beneficial Use Sites for Excavated Material >> PAGE 8

12 STUDY RESULTS After a detailed evaluation and screening assessment, the El Arado (#2) location was eliminated due to its importance to the local agricultural and poultry industry, plus the high cost of transportation. The Panama Bay (#1) and Chorrillo/Amador (#4) locations were also eliminated due to impacts of bringing material by truck over the Bridge of the Americas and/or through the city urban areas to the dump sites. In the final analysis, only two options were considered to meet the requirement to accept the full volume of material from the Third Locks Project. The UXO area (site T6) and the artificial island (Site M5) remained as the only two locations that could receive all of the fill material. The locations were tested on a transportation cost basis against the option of open water disposal with no beneficial use, as shown in Table 2, below. As can be noted from the table, the unit cost of material transport was lowest for the UXO site. Table 2: Base Cost of Materials Transport to Disposal Sites (2004 US$) Since the combined capacity of all of the other acceptable land side sites did not meet the project needs, the final recommendation was that ACP would need to select one or both of the artificial island or UXO sites options to receive the material excavated from the Locks. 2.3 ARTIFICIAL ISLAND FEASIBILITY STUDY MAY 2004 At that time, the total volume of material to be removed from the excavation area was calculated to be approximately 70 million m 3, before the application of any coefficients for bulking and compaction at the disposal site. The option to receive the dredged material from the Pacific Entrance widening and deepening was discounted during the dredging tender process, with the selection of the dredged materials disposal site to be left to the selected contractor. >> PAGE 9

13 OBJECTIVES This major technical assessment took the earlier analyses to a feasibility level in order to generate a higher level of confidence in the cost estimate and to identify key issues related to the permitting process. In turn, these engineering feasibility studies and environmental assessment included the site investigation work required to provide a basis for future detailed engineering design for construction and provide the basis for the formal environmental permitting process. Given the aesthetic considerations and potential socio economic or environmental implications of maritime related development on the island, it was suggested that the long term development of the island and one other marine site under consideration should not necessarily be limited to port and port related uses. Consequently, the 2004 study covered a broader panorama of potential uses for an artificial island and expanded the location alternatives. Beneficial use options included: Marine terminal development for concession offerings Multi purpose development (housing, commercial, parks) Public park The assessment also included a no development option, which essentially used an island location as a dump site with no landscaping, land side access or site improvements. RESULTS OFFSHORE ISLAND LOCATIONS The location study was expanded to include all potential locations from the Pacific Entrance to the Canal to the original artificial island site, as shown in Figure 3. The selected sites also took into account the need to maintain an obstacle free approach for aircraft using the Howard runway, which was being developed at that time for private use and concession. An option to develop a near shore project at Palo Seco was also included at this time. >> PAGE 10

14 Figure 3: Short Listed Offshore Island Sites (2004) >> PAGE 11

15 COSTS Among the offshore island locations, the Palo Seco area was seen to be most cost effective, as shown in Table 3 below. However, due to the very shallow water in the project area, the Palo Seco site required over 700 ha to receive the full volume of excavated material. Table 3 : Development Costs of Offshore Island Disposal Sites (2004 US$)* Alternative Probable cost ($millions) Island Area Unit cost per marketable m2 (65% of generated area) Sensitivity Ranking Low (90%) Mean High (90%) (ha) Low (90%) Mean High (90%) Item % rank 1 Isla Venado Location $754 $826 $ $305 $334 $369 Rock Quantity 75% 2 Isla Tortolita Location $703 $763 $ $264 $286 $311 Rock Quantity 92% Spoil Ground/Explosives Anchorage Location Peninsular South of Palo Seco (berths on east face) Palo Seco area - (basin configuration) $809 $867 $ $293 $314 $336 Rock Quantity 85% $829 $896 $ $182 $197 $211 Rock Quantity 86% $1,084 $1,202 $1, $237 $262 $290 Rock Quantity 89% Note: Unimproved island costs include rail corridor, island fill, breakwater (where applicable), causeway and breaches (where applicable), dredging for four container terminals, engineering & project administration. * Assumes island fill material is provided from the Third Locks Project excavation works. CONCLUSIONS (2004) The transportation and island development cost estimates indicated that the use of an artificial island as a simple disposal site was significantly more expensive than the placement of material at the UXO area. At the same time, the cost of development of any of the offshore alternatives were seen to be much higher than land costs in Panama. Also the maritime development options were not attractive as a financial venture at that time, based on private sector financial offers for concessions that were typical of the region. There were also concerns voiced from the existing port concession holders that the donation of fill materials from the Locks Project to a new port, to then be offered in concession, represented unfair competition to the existing terminals, and legal challenges were expected if the artificial island options were to be used for port terminals. >> PAGE 12

16 GIVEN THESE CONCLUSIONS AND CONCERNS AT THE ACP BOARD LEVEL REGARDING THE MARKET RISK PLUS THE RELATIVELY HIGH ADDITIONAL COSTS REQUIRED TO DEVELOP THE BASIC PORT INFRASTRUCTURE AND M&N S RECOMMENDATION, IT WAS DETERMINED THAT THE UXO OPTION REPRESENTED THE MOST COST EFFECTIVE MEANS TO RECEIVE THE PACIFIC SIDE EXCAVATED MATERIAL. 2.4 FARFAN/PALO SECO ISLAND PROJECT FEASIBILITY STUDY JUNE 2005 OBJECTIVES Following completion of the ACP studies in 2003 and 2004, the Government of Panama, not ACP, continued to receive requests from Port operators and carriers related to the potential to build additional container terminals on the Pacific Coast, to capture the increasing demand for transshipment cargoes. The President s office then requested Moffatt & Nichol to use the earlier ACP study results to expand the technical and cost assessment of the Palo Seco project, which had earlier been identified as a lower cost option for maritime development under the island location and feasibility studies. Figure 3 shows the general location of the area of interest for this project. The original studies sponsored by ACP had focused on the beneficial use of rock and other material generated by the excavation and dredging needed for the New Pacific Side Locks. However, based on the results of the earlier work, ACP had decided to use the UXO sites and other nearby landside locations for the excavation material from the Third Locks Project. This then implied a need to import the required fill material, but also that the island size could be much smaller than originally required. >> PAGE 13

17 Figure 4: General Area for Palo Seco Port Options RESULTS MATERIALS REQUIREMENTS Since the objective of this latest study was to determine the feasibility of a new container terminal in the Palo Seco area, the requirement to contain all of the excavated material was no longer an issue. Fill requirements for the Palo Seco project were then computed on a first phase development of some 1,600 m of container berth, which in turn required some 19 million m 3 of fill. It was assumed that the fill material would be available from a sand borrow site, although it was considered that there was only a slim possibility of obtaining the necessary authorizations for this volume of material. >> PAGE 14

18 PALO SECO RAIL LINK The earlier ACP decision to use the nearby land side disposal options for the Third Locks excavation material then implied that the cost of the rail link to the proposed port site could no longer be considered as part of the Canal Expansion Project. Its viability was then totally dependent on the income from the container terminal and connection to the existing Trans Isthmian rail system. As such, the cost of the rail link was then extended to include a crossing in the area of the Miraflores area, using the existing swing bridge and a new bridge over the Third Locks entrance as shown in Figure 5. At that time, discussions with the ACP Operations and pilots group indicated that the only effective time for rail crossings would be during the Canal ship traffic reversal period offering some one to two hours per day for the bridge closings. While some concerns were expressed that a problem with the rail bridges or trains could shut down the Canal transits, it was generally accepted that this traffic window would be workable for one train transfer in each direction each day. This in turn was reasonable given the expected demand for container moves from the port to and from the Albrook intermodal yard. >> PAGE 15

19 Figure 5: Proposed Rail Link from Palo Seco Terminal to Albrook (2005) >> PAGE 16

20 A preliminary cost assessment was then developed to test the financial viability of the crossing, with the resulting cost of US$172.6 million as presented in the table below Table 4:Estimated Cost of Palo Seco Albrook Rail Link (2005 US$) Description Amount (US$) Mobilization & Demob $6,712,976 Intermodal Yard $27,856,381 Rail Line $48,180,374 Crossings $50,750,341 Sub Total Rail Corridors and Intermodal Yard $133,500,072 Contingencies $25,587,524 Admin & Engineering Costs $13,522,445 Estimated Project Cost $172,610,041 At that time, and assuming amortization of this investment over a 20 year period, with interest rates of 7.0 percent, the annual payment requirement was calculated to be $18 million. Converting this to a rate per TEU at the maximum expected traffic projections indicated a need to recover at least $72.00 per TEU to amortize the cost of the rail link alone. The cross Isthmus rail fee in 2005 was on the order of US$120 each way using the east side infrastructure. Adding the rail crossings from the west side and including the additional operations costs implied a tariff of $ per TEU for the coast to coast transfer, which was substantially above the acceptable rate for the carriers. Based on this assessment, it was determined the most cost effective and efficient transfer option from the new port to the Atlantic Coast would be to improve the highway connection to the Centenario Bridge and use the Corredor Norte and that the rail link was not feasible. RAIL COST UPDATE 2015 As seen above, the estimated cost of the rail crossing in 2005 was US$172.6 million. Inflating this cost to 2015 rates would imply an increase of 41% giving a new cost of US$243 million. However, it is understood that the old Miraflores rail bridge has now been dismantled and no provision was made in the Third Locks Project for a second low level rail crossing at the entrance to the locks. For this study update it is not possible to determine the cost of the two Locks crossings/bridges under today s requirements. In the meantime, it is understood that cross Isthmian rail charges are still in the same range at the earlier numbers. >> PAGE 17

21 AT THIS LEVEL OF COSTS, IT IS CLEAR THAT A NEW CONTAINER TERMINAL ON THE WEST SIDE OF THE CANAL COULD NOT GENERATE SUFFICIENT INCOME OR INTERCHANGE VOLUMES TO JUSTIFY THE RAIL LINK WITHOUT A CONSIDERABLE SUBSIDY FROM PUBLIC OR OTHER SOURCES. Table 5:Assessment of Current Validity of Palo Seco Rail Link New crossings required since the Rail crossings would be during the Miraflores Swing Bridge has been ship traffic reversal period, using the Assumptions dismantled and no provision has existing Miraflores Swing Bridge and been made for rail crossing at the a new bridge over the Third Locks. New Cocoli Locks. At least $243 million + cost for Cost of Rail Crossings $173 million additional 3 rd Locks crossing(s) Conclusion The most cost effective and efficient transfer option from the new port to the Atlantic Coast would be to improve the highway connection to the Centenario Bridge and use the Corredor Norte. A new container terminal on the West side of the Canal could not generate sufficient income or interchange volume to justify the rail link without a considerable subsidy from public or other sources. PALO SECO PROJECT COSTS As shown below, the cost simulation models prepared in 2005 indicated an estimated CAPEX requirement of $672 million for the Phase 1 development at Palo Seco, excluding power connections, equipment and a rail connection to the existing Panama Canal Railroad yards. These costs were predicated on the construction of a terminal with 1,600 m of berth length and 80 ha of back up/storage area. >> PAGE 18

22 Table 6: Estimated Cost of the Palo Seco Phase 1 Terminal (2005 US$) Description Amount (2005 US$) Dredging and Reclamation $300,100,641 Marginal Wharf and Access Trestle $73,308,559 Site Stabilization $47,036,175 Terminal Infrastructure $91,658,853 Construction Road and Highway Improvements $16,969,899 Entrance Gates and Buildings $7,633,491 Mitigation $680,640 Sub Total Rail Corridors and Intermodal Yard $537,388,258 Contingencies $94,042,945 Planning, Engineering and Project Management $40,253,739 Estimated Project Cost $671,684,942 Applying inflation to 2005 costs implies an increase of 41%, bringing the cost today to an expected US$947 million. The cost of equipment for a terminal with 1,600 m of berth length is seen in Table 7 below to be $ million, bring the total project cost for the Palo Seco Island project to $1,255 million in 2015 US$. Table 7: Estimated Cost of Equipment & Superstructure Palo Seco (2015 US$) Description Quantity Unit Cost Amount (US$) STS Cranes 18 $8,500,000 $153,000,000 RTGs 59 $1,300,000 $76,700,000 Yard Tractors 133 $100,000 $13,300,000 Chassis 147 $12,000 $1,764,000 Reach Stackers 4 $450,000 $1,800,000 MT Handlers 10 $500,000 $5,000,000 Yard Vehicles 5 $45,000 $225,000 Personnel Buses 4 $75,000 $300,000 Scanners 2 $3,000,000 $6,000,000 TOS 1 $4,000,000 $4,000,000 IT and Security 1 $3,500,000 $3,500,000 Maintenance Equipment 1 $1,250,000 $1,250,000 Office Equipment 1 $1,000,000 $1,000,000 Miscellaneous 1 $500,000 $500,000 $268,339,000 Contingencies 15% $40,250,850 Equipment Cost $308,589,850 >> PAGE 19

23 However, the final cost of this project is particularly sensitive to the unit costs of dredging and fill materials. It also assumes that some 19 million m 3 of hydraulic fill materials would be available from a sand borrow site west of the Taboga areas and this was considered to be highly unlikely to be approved, given the move to preserve the sand deposit areas from the Canal westwards to Chame and beyond. CONCLUSIONS (2015) On completion of the Farfan/Palo Seco Study, the Government via the President s Office invited leading Port operators and carriers to present proposals for a public private partnership to develop the Phase 1 development of the Palo Seco port option, but no definite proposals were received. The general response was that the initial investment risk was very high and the transshipment market potential was too uncertain at that time. Finally, a number of objections were voiced to the Palo Seco project during the evaluation phase, including some legal actions. Table 8:Assessment of Current Validity of Palo Seco Island Project Rail Link Description Island Terminal (including cost of fill) Equipment & Superstructure Unit cost improved island, 80 ha, no equipment Conclusion $173 million $672 million $947 million Not included At least $243 million + cost for additional 3 rd Locks crossing(s) $309 million $1,056/m 2 $1,487/m 2 Potential operators deemed the initial investment risk high and the transshipment market potential too uncertain. Objections were raised by various interest groups. Assumed that some 19 million m 3 of hydraulic fill material would be available from a sand borrow site though this was considered unlikely to be approved. Availability of sufficient suitable sand from nearby approved offshore borrow sites would still need to be confirmed. Objections voiced in 2005 would likely still stand today. >> PAGE 20

24 3 OVERALL ASSESSMENT 3.1 SUMMARY The initial studies undertaken by Moffatt & Nichol for ACP were aimed at evaluating the potential uses for some 70 million m 3 of excavation material expected to be generated by the Third Locks Project. These included the construction of an island (to be used as a port, a multi purpose development, a public park, or not developed at all) and disposal in various offshore, near shore and landside sites. Based on the studies, ACP determined that the placement of the excavation materials at selected UXO sites was the most cost effective use for the material. ARTIFICIAL ISLAND In order to construct the artificial island project at the Isla Venado location and under present conditions, approximately 31 million m 3 of sand fill would have to be purchased and obtained from offshore sand borrow areas and transported to the island site. This significantly increases the project s cost compared to the original artificial island which would have been constructed using the material generated from the excavation of the Third Locks Project. The availability of such a large volume of sand from existing nearby concessions has not been confirmed and it is considered unlikely to be approved. The original artificial island project assumed the material from the excavation works would be transported to the island site via rail as the lowest cost alternative. This rail network could then have been extended to provide rail connectivity to the Atlantic Coast terminals via the existing Trans Isthmian rail system. However, if the project were to be built now, fill for the artificial island would now be transported from offshore borrow areas and the rail link would no longer be needed for material transport and would have to be justified based on the market demand for connectivity to the Atlantic Coast. These issues make the artificial island project less attractive than the 2001 version, making it now most unlikely to be developed by private interests. PALO SECO ISLAND Although the proposed Palo Seco island development also contemplated a rail link, it was premised on the use of the old Miraflores Swing Bridge and a new bridge over the Third Locks entrance. However, the Miraflores Swing Bridge has now been dismantled and no provision was made in the Third Locks Project for a rail crossing at the entrance to the locks. Thus, two new crossings would be required to provide this rail link now. The terminal would likely not generate sufficient income or interchange volume to justify the rail link without a considerable subsidy from public or other sources. >> PAGE 21

25 The Palo Seco development would also require the purchase and transport of some 19 million m 3 of sand from offshore borrow areas to use as island fill material. The availability of suitable sources of sand from existing concessions would have to be confirmed. The objections voiced in 2005 regarding the location of the Palo Seco project and its impacts on the developments along the Amador Causeway, Playa Bonita and Veracruz would likely still stand today. FINDINGS As can be seen from the previous discussions, there have been a number of studies and initiatives to develop artificial islands and shorefront reclamation projects to provide new container terminal capacity on the Pacific Side of the Canal. Each of these projects differed in the infrastructure needs, costs, environmental impacts and size of the installations. Consequently, comparisons with other terminal proposals is somewhat complex. However, over the past ten years, Moffatt & Nichol and others have maintained records of investments in container terminals on a worldwide basis. We have also undertaken many due diligence assignments for the major multilateral lending agencies and banks, and are very familiar with the elements required to justify a private sector project financially. Using the available database on costs, it is seen that the financial viability of a container terminal investment can be generally simplified to consider the following: Investment cost (marine, civils, buildings, equipment, operating systems, etc.) Income per TEU Strength of the market (import/export or transshipment) It follows from this assessment, that a high cost terminal can be justified when income is also high, but a medium or low cost terminal may not be viable if income is low. Unfortunately for Panama, at least 90% of the container moves are for transshipment traffic, which generally generates revenues that are some 60% of those expected for import/export containers. Consequently, it is important to assess the viability of the project in light of both the income and CAPEX sides. The need to purchase and transport fill material from offshore sources as well as the requirement to provide access from mainland to the island via causeway/trestle/bridges as well as power and utility connections to the island result in these potential island transshipment terminals having relatively high investment costs. This becomes even more evident in light of the relatively lower income per TEU expected from the transshipment cargo as compared to terminals with more import/export cargo. Given the high investment costs required and the low income expected, the proposed island developments rank >> PAGE 22

26 relatively low compared to other modern container terminals that have recently been completed or are in development or construction at this time. In addition, based on the level of costs of a rail link, it is anticipated that the island port development would likely not generate sufficient income or interchange volumes to justify the rail ink without considerable subsidy from public or other sources, additionally impacting the attractiveness of this development. In summary, the following conclusions can be stated: 1. The initial studies were aimed at evaluating the potential uses for some 70 million m 3 of excavation material expected to be generated by the Third Set of Locks Project. These uses included the construction of an island (to be used as a port, a multi purpose development, a public park, or not developed at all) and disposal in various offshore, near shore and landside sites. 2. The transportation and island development cost estimates indicated that the use of an artificial island as a simple disposal site was significantly more expensive than the placement of material at the UXO area. ACP determined that the UXO option represented the most cost effective means to receive the Pacific Side excavated material. 3. The Palo Seco development would require the purchase and transport of some 19 million m 3 of sand from offshore borrow areas to use as island fill material. The availability of suitable sources of sand from existing concessions would have to be confirmed. 4. New rail crossings to the Panama Canal Railroad would be required since the Miraflores Swing Bridge has been dismantled and no provision has been made for rail crossing at the New Cocoli Locks. A new container terminal on the West side of the Canal could not generate sufficient income or interchange volume to justify the rail link without a considerable subsidy from public or other sources. 5. The need to purchase and transport fill material from offshore sources as well as the requirement to provide access from mainland to the island via causeway/trestle/bridges as well as power and utility connections to the island result in these potential island transshipment terminals having relatively high investment costs compared to relatively lower income per TEU expected from the transshipment cargo. >> PAGE 23

Process for Port Master Planning

Process for Port Master Planning Process for Port Master Planning Presented by Kerry Simpson, P.E. Vice President, Marine Terminals AAPA Port Executive Management Seminar Merida, Mexico December 2014 Moffatt & Nichol Founded in 1945 in

More information

Port Planning Texas City International Terminal. William L. Allen, PE, SE*; Christopher B. Cornell, PE, SE**; and Dr. Joseph Moseley, PE***

Port Planning Texas City International Terminal. William L. Allen, PE, SE*; Christopher B. Cornell, PE, SE**; and Dr. Joseph Moseley, PE*** Port Planning Texas City International Terminal William L. Allen, PE, SE*; Christopher B. Cornell, PE, SE**; and Dr. Joseph Moseley, PE*** *Senior Project Manager, BERGER/ABAM Engineers Inc.; 33301 Ninth

More information

Opportunity for Private Investment Mauritius Island Container Terminal

Opportunity for Private Investment Mauritius Island Container Terminal Opportunity for Private Investment Mauritius Island Container Terminal According to the 2012 AU report (AIMS 2050) Container throughput in Subsaharan Africa is expected to increase 14 fold by 2040. Existing

More information

Summary Report - Terminal 2 (T2) Trade-Off Process and Outputs Container Capacity Improvement Program

Summary Report - Terminal 2 (T2) Trade-Off Process and Outputs Container Capacity Improvement Program Summary Report - Terminal 2 (T2) Trade-Off Process and Outputs Container Capacity Improvement Program February 2012 Executive Summary Overview This summary report documents concept design and planning

More information

The Panama Canal s Third Set of Locks Project

The Panama Canal s Third Set of Locks Project The Panama Canal s Third Set of Locks Project Juan Wong H. Panama Canal Authority, Panama, Republic of Panama ABSTRACT: One of the world s greatest engineering achievements, the Panama Canal plays a vital

More information

House Appropriations Committee Overview of Virginia International Terminals (VIT) October 15, 2012

House Appropriations Committee Overview of Virginia International Terminals (VIT) October 15, 2012 House Appropriations Committee Overview of Virginia International Terminals (VIT) October 15, 2012 Ms. Charlotte P. Herndon, CPA Chairman of the Board Virginia International Terminals, Inc. 1 VIT RESULTS

More information

Public Notice October 21, 2016 U.S. Army Corps of Engineers Charleston District

Public Notice October 21, 2016 U.S. Army Corps of Engineers Charleston District Public Notice October 21, 2016 U.S. Army Corps of Engineers Charleston District Notice of Intent to Prepare a Draft Environmental Impact Statement for the Proposed Jasper Ocean Terminal in Jasper County,

More information

MRMR Hambantota Port

MRMR Hambantota Port MRMR Hambantota Port The Government of Sri Lanka chose to build a port in Hambantota given its proximity to one of the busiest sea lanes in Asia and developed it as a Services and industrial port. Total

More information

Re: Participation of the Vancouver Fraser Port Authority in Orientation Session #2 for the Roberts Bank Terminal 2 Project Environmental Assessment

Re: Participation of the Vancouver Fraser Port Authority in Orientation Session #2 for the Roberts Bank Terminal 2 Project Environmental Assessment M,;\ PORT of ~~1 vancouver Vancouver Fraser Port Authority 100 The Pointe, 999 Canada Place Vancouver, B.C. Canada V6C 3T 4 portvancouver.com September 9, 2016 Jocelyne Beaudet Chair, Review Panel Roberts

More information

PANAMA CANAL EXPANSION

PANAMA CANAL EXPANSION noun 1. a purposeful or industrious undertaking (especially one that requires effort or boldness) 2. earnest and conscientious activity intended to do or accomplish something. PANAMA CANAL EXPANSION 1

More information

AGENDA ITEM #14: PANAMA CANAL EXPANSION: VIRGINA PORT AUTHORITY

AGENDA ITEM #14: PANAMA CANAL EXPANSION: VIRGINA PORT AUTHORITY AGENDA ITEM #14: PANAMA CANAL EXPANSION: VIRGINA PORT AUTHORITY SUBJECT: The Panama Canal Expansion Third Set of Locks project BACKGROUND: The expansion of the Panama Canal (Third Set of Locks) is a project

More information

American Association of Port Authorities

American Association of Port Authorities American Association of Port Authorities U.S. Infrastructure Needs and Investment Plans Doug Wray January 29, 2015 Tampa, Florida Changing Market Dynamics Key Highlights The global container shipping industry

More information

Eric Thomas Benchmark River and Rail Terminals

Eric Thomas Benchmark River and Rail Terminals Eric Thomas Benchmark River and Rail Terminals CORBA s Mission The Central Ohio River Business Association (CORBA) is an alliance of businesses and industry engaged in river commerce on and along the Ohio

More information

Intermodal Activities planned by SPRC

Intermodal Activities planned by SPRC Intermodal Activities planned by SPRC 1)Container Volumes 2010 to 2020 2)Projected Productivities and Optimization 3)Basic data for the Hinterland 4)Hinterland Transport by River 5)Hinterland Transport

More information

PLANNING, DESIGN, and REALIZATION OF AUTOMATED TERMINALS Ashebir Jacob P.E. Senior Port Engineer / Vice President

PLANNING, DESIGN, and REALIZATION OF AUTOMATED TERMINALS Ashebir Jacob P.E. Senior Port Engineer / Vice President PLANNING, DESIGN, and REALIZATION OF AUTOMATED TERMINALS Ashebir Jacob P.E. Senior Port Engineer / Vice President 1 Moffatt & Nichol Founded in 1945 in Southern California to serve the U.S. Navy & the

More information

House Select Committee on Strategic Transportation and Long Term Funding Solutions. November 6, 2017

House Select Committee on Strategic Transportation and Long Term Funding Solutions. November 6, 2017 House Select Committee on Strategic Transportation and Long Term Funding Solutions November 6, 2017 1 Welcome to N.C. Ports Fast Facts Two locations serving the Carolinas Over 350,000 teus Over 4 million

More information

The Emergence of. Florida s Seaports and Inland Ports. Florida League of Cities - International Relations Committee November 17, 2011

The Emergence of. Florida s Seaports and Inland Ports. Florida League of Cities - International Relations Committee November 17, 2011 The Emergence of Florida s Seaports and Inland Ports Florida League of Cities - International Relations Committee November 17, 2011 History of the Global Supply Chain 2 Supply Chain, Circa 1950 Regional

More information

Breakout Session 2: Development of the Dar es Salaam Port March 17, :30 12:30

Breakout Session 2: Development of the Dar es Salaam Port March 17, :30 12:30 Breakout Session 2: Development of the Dar es Salaam Port March 17, 2015 11:30 12:30 Forum co sponsor Presentation: Moderation: Panellists: Ntandu Mathayo, Strategic Planning Director, Tanzania Port Authority

More information

Port NOLA Forward: Strategic Master Plan FAQs

Port NOLA Forward: Strategic Master Plan FAQs Port NOLA Forward: Strategic Master Plan FAQs Master Plan Overall 1. What is included in the Strategic Master Plan? The Strategic Master Plan outlines a vision and provides a broad roadmap to capture market

More information

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT : GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT CONTENTS 3. GENERAL DESCRIPTION OF THE PROPOSED COEGA 3-1 3.1 Overview of the Coega Integrated Power Project 3-1 3.2 Description of

More information

Port of Long Beach Port Master Plan Overview December 22, 2008

Port of Long Beach Port Master Plan Overview December 22, 2008 Port of Long Beach Port Master Plan Overview December 22, 2008 PORT OF LONG BEACH PORT MASTER PLAN OVERVIEW INTRODUCTION In 1978 the California Coastal Commission certified the Port of Long Beach Port

More information

Port Partnerships Strategic Opportunities for Gateway & Closer Market Ports to Work Together Presented by Rainer Lilienthal General Manager-Trade

Port Partnerships Strategic Opportunities for Gateway & Closer Market Ports to Work Together Presented by Rainer Lilienthal General Manager-Trade Port Partnerships Strategic Opportunities for Gateway & Closer Market Ports to Work Together Presented by Rainer Lilienthal General Manager-Trade Development Port of Houston Overview The Port of Houston

More information

Inland Port Cargo Complex

Inland Port Cargo Complex Inland Port Cargo Complex Regional Approach for Ports A statewide improvement Connects five plus seaports Promotes connectivity utilizing existing transportation network Improves rail efficiencies Relocates

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT. General Manager of Engineering Services in consultation with the Director of Current Planning

CITY OF VANCOUVER ADMINISTRATIVE REPORT. General Manager of Engineering Services in consultation with the Director of Current Planning CITY OF VANCOUVER ADMINISTRATIVE REPORT Date: September 1, 2005 Author: Dale Bracewell Phone No.: 604.871.6440 RTS No.: 5291 CC File No.: 8203 Meeting Date: September 20, 2005 TO: FROM: SUBJECT: Standing

More information

Select U.S. Ports Prepare For Panama Canal Expansion

Select U.S. Ports Prepare For Panama Canal Expansion Select U.S. Ports Prepare For Panama Canal Expansion Port of Jacksonville Grace Wang Associate Professor, Maritime Administration Texas A&M University at Galveston Galveston, Texas Anthony M. Pagano Director,

More information

Rail Service at Brookley Aeroplex

Rail Service at Brookley Aeroplex WHAT The Mobile Airport Authority, hopes to attain improved rail infrastructure to advance economic performance and job growth. I. Background The Mobile Airport Authority s goal for Brookley Aeroplex is

More information

MARITIME REPORTER AND ENGINEERING NEWS. Offshore Energy. Arctic Operations Finland Breaks the Ice. Markets Fishing Fleet Americas

MARITIME REPORTER AND ENGINEERING NEWS. Offshore Energy. Arctic Operations Finland Breaks the Ice. Markets Fishing Fleet Americas The World s Largest Circulation Marine Industry Publication The Information Authority for the Global Marine Industry since 1939 Number 4 Volume 78 MARITIME April 2016 REPORTER AND ENGINEERING NEWS M A

More information

ROTAWN ENERGY AND LOGISTICS DREDGING PROFILE

ROTAWN ENERGY AND LOGISTICS DREDGING PROFILE ROTAWN ENERGY AND LOGISTICS DREDGING PROFILE DREDGING PROFILE ABOUT US Rotawn Energy and Logistics Services Ltd was established in 2007 as an indigenous Nigerian company offering tailor made solutions

More information

Development of the SP-SSA International Terminal, Vietnam Christopher B. Cornell, MASCE, PE, SE; 1 Morgan McArthur, MASCE; 2 and David Michou 3

Development of the SP-SSA International Terminal, Vietnam Christopher B. Cornell, MASCE, PE, SE; 1 Morgan McArthur, MASCE; 2 and David Michou 3 Development of the SP-SSA International Terminal, Vietnam Christopher B. Cornell, MASCE, PE, SE; 1 Morgan McArthur, MASCE; 2 and David Michou 3 1 Project Manager, BergerABAM, 33301 Ninth Avenue South,

More information

Facilities Engineering Seminar

Facilities Engineering Seminar Facilities Engineering Seminar Rancho Bernardo Inn San Diego, CA November 7-9, 2007 Wednesday, November 7 7:30-8:30 a.m. Registration and Continental Breakfast 8:30-8:45 a.m. Welcome and Opening Remarks

More information

Safety of LNG-Shipping around Ports and Terminals

Safety of LNG-Shipping around Ports and Terminals Safety of LNG-Shipping around Ports and Terminals Jos T.M. van Doorn and Johan H. de Jong, MARIN Introduction The design of port lay-outs and terminals suitable for LNG-carriers has to meet exceptionally

More information

Port Everglades. is South Florida s Powerhouse Port. Presented to American Association of Port Authorities Environment Committee. September 17, 2015

Port Everglades. is South Florida s Powerhouse Port. Presented to American Association of Port Authorities Environment Committee. September 17, 2015 Port Everglades is South Florida s Powerhouse Port Presented to American Association of Port Authorities Environment Committee Port Everglades Baseline Emissions Inventory EPA Partnership Emission Modeling

More information

RESTORATION OF THE NORTHERN TIP OF MON LOUIS ISLAND Mobile Bay National Estuary Program. Fowl River WMP Steering Committee May 19, 2015

RESTORATION OF THE NORTHERN TIP OF MON LOUIS ISLAND Mobile Bay National Estuary Program. Fowl River WMP Steering Committee May 19, 2015 RESTORATION OF THE NORTHERN TIP OF MON LOUIS ISLAND Mobile Bay National Estuary Program Fowl River WMP Steering Committee May 19, 2015 Project Site / Background Historical Maps (Note New Outlet ) 1889

More information

SHORT-TERM DEVELOPMENT PLAN FOR TEMA PORT

SHORT-TERM DEVELOPMENT PLAN FOR TEMA PORT PART V SHORT-TERM DEVELOPMENT PLAN FOR TEMA PORT Chapter 24 Short-term Development Plan for Tema Port 24.1 Planning Requirement for Short-term Development Plan (1) Strategy for Development As explained

More information

Miami River Freight Improvement Plan Financial Management Number:

Miami River Freight Improvement Plan Financial Management Number: Miami River Commission January 8, 2018 Miami, FL Carlos A. Castro, District Freight Coordinator Miami River Freight Improvement Plan Financial Management Number: 437946-1-22-01 Agenda Study Background

More information

By: Bernardo González, Project Director December 5, 2011

By: Bernardo González, Project Director December 5, 2011 By: Bernardo González, Project Director December 5, 2011 EXPANSION OF THE PANAMA CANAL 0INDEX 1. THE JOINT VENTURE 2. THE PROJECT 3. THE BID AND THE CONTRACT 4. DESIGN & CONSTRUCTION 5. MAJOR QUANTITIES

More information

15.8 Multipurpose Terminal Project Preparing Alternative Terminal Plans

15.8 Multipurpose Terminal Project Preparing Alternative Terminal Plans 15.8 Multipurpose Terminal Project 15.8.1 Preparing Alternative Terminal Plans As mentioned in Section 15.4, it is required to build a multipurpose terminal with six (6) 14-meter-deep berths and spacious

More information

Port Alberni Trans-Shipment Hub (PATH) Feasibility Study

Port Alberni Trans-Shipment Hub (PATH) Feasibility Study www.cpcs.ca www.cpcs.ca Port Alberni Trans-Shipment Hub (PATH) Feasibility Study Expected Economic Impacts of PATH Project Prepared for: Prepared by: CPCS Ref: 13150 May 8, 2014 Acknowlegements and Disclaimers

More information

6. PROJECT DESCRIPTION: DREDGING

6. PROJECT DESCRIPTION: DREDGING Supplementary Report to the EIS 6. PROJECT DESCRIPTION: DREDGING Development of the Port of Gladstone and adjacent Gladstone State Development Area requires improved shipping access within, particularly

More information

PORT INLAND DISTRIBUTION NETWORK SOUTH JERSEY SITE EVALUATION AND FEASIBILITY DEVELOPMENT STUDY. EXECUTIVE SUMMARY July 2003

PORT INLAND DISTRIBUTION NETWORK SOUTH JERSEY SITE EVALUATION AND FEASIBILITY DEVELOPMENT STUDY. EXECUTIVE SUMMARY July 2003 PORT INLAND DISTRIBUTION NETWORK SOUTH JERSEY SITE EVALUATION AND FEASIBILITY DEVELOPMENT STUDY NEW JERSEY DEPARTMENT OF TRANSPORTATION AND THE DELAWARE VALLEY REGIONAL PLANNING COMMISSION EXECUTIVE SUMMARY

More information

THE DYNAMICS OF THE US CONTAINER MARKET AND IMPLICATIONS FOR THE US PORT INDUSTRY

THE DYNAMICS OF THE US CONTAINER MARKET AND IMPLICATIONS FOR THE US PORT INDUSTRY THE DYNAMICS OF THE US CONTAINER MARKET AND IMPLICATIONS FOR THE US PORT INDUSTRY A PRESENTATION TO: CHANGING TRADE PATTERNS JANUARY 24, 2013 MARTIN ASSOCIATES 941 Wheatland Avenue, Suite 203 Lancaster,

More information

Eilat Port No Containers

Eilat Port No Containers 1 Israel s Southern Gateway Israel s Container Trade is Haifa/Ashdod Dependent Haifa Port Haifa Ashdod Port Ashdod Jordan Egypt Eilat Port No Containers Eilat Today, the Southern Gate only handles bulk

More information

Presentation on Initiatives to Improve Cargo Handling at the Port of Mombasa. Muhamad A. Jezan Resident Representative

Presentation on Initiatives to Improve Cargo Handling at the Port of Mombasa. Muhamad A. Jezan Resident Representative Presentation on Initiatives to Improve Cargo Handling at the Port of Mombasa. Muhamad A. Jezan Resident Representative Outline 1. Introduction 2. Role of Ports in Economic Development 3. Mombasa Port Performance

More information

White Paper on the Terminal Capacity of Pier 300 with the Automation of the 41-acre Backland at Proposed Berth 306

White Paper on the Terminal Capacity of Pier 300 with the Automation of the 41-acre Backland at Proposed Berth 306 Appendix C2 White Paper on the Terminal Capacity of Pier 300 with the Automation of the 41-acre Backland at Proposed Berth 306 Berths 302-306 [APL] Container Terminal Project December 2011 ADP# 081203-131

More information

Container Terminal Planning & Operations Current and Coming Trends

Container Terminal Planning & Operations Current and Coming Trends Container Terminal Planning & Operations Current and Coming Trends AAPA Marine Terminal Management Training Seminar September 17-21, 2012 Baltimore, Maryland Thomas Ward, PE/SE Chief Engineer Ports America

More information

V International Seminar on Port Engineering, Concepción, Chile. Site Selection & Design of Marine Terminals

V International Seminar on Port Engineering, Concepción, Chile. Site Selection & Design of Marine Terminals V International Seminar on Port Engineering, Concepción, Chile Site Selection & Design of Marine Terminals by Dr C. Skipper 1, Captain Stephen Gyi 2 ABSTRACT This paper considers the site selection and

More information

THE ECONOMIC BENEFITS OF INVESTMENTS AT SOUTH TERMINAL AT THE PORT OF EVERETT

THE ECONOMIC BENEFITS OF INVESTMENTS AT SOUTH TERMINAL AT THE PORT OF EVERETT THE ECONOMIC BENEFITS OF INVESTMENTS AT SOUTH TERMINAL AT THE PORT OF EVERETT PREPARED FOR: Port of Everett 1205 Craftsman Way, Suite 200 Everett, WA 98201 www.portofeverett.com PREPARED BY: MARTIN ASSOCIATES

More information

Growth In Container Volumes

Growth In Container Volumes US GDP and TEU Trade: 1980-2005 600 Recession Total US TEUs 500 US GDP 400 300 200 100 0 1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002

More information

Port of Los Angeles. America s Port Harbor Transportation Club June 20, 2013 Kathryn McDermott

Port of Los Angeles. America s Port Harbor Transportation Club June 20, 2013 Kathryn McDermott Port of Los Angeles America s Port 2013 Harbor Transportation Club June 20, 2013 Kathryn McDermott Sea/Tac Battle for Discretionary Cargo Prince Rupert Eastern Canada NY/NJ OAK Norfolk LA/LB Savannah

More information

Alabama State Port Authority

Alabama State Port Authority Alabama State Port Authority Port Update IFFCBANO June 6, 2014 www.asdd.com Port of Mobile Excellent Transportation Infrastructure I-10 & I-65 5 Class 1 Railroads (BNSF, CN, CSX, KCS, NS) Rail Ferry Service

More information

Capability Statement Gas and liquid bulk terminals Delta Marine Consultants

Capability Statement Gas and liquid bulk terminals Delta Marine Consultants Capability Statement Gas and liquid bulk terminals Delta Marine Consultants Delta Marine Consultants Delta Marine Consultants provides comprehensive maritime engineering services for gas and liquid bulk

More information

Hampton Roads Bridge-Tunnel Expansion Feasibility Study. Design Considerations

Hampton Roads Bridge-Tunnel Expansion Feasibility Study. Design Considerations Hampton Roads Bridge-Tunnel Expansion Feasibility Study Tunnels Design Considerations The proposed location for the new tunnel crossing is about 250 feet away from the existing westbound tunnel. This matches

More information

NC State Ports Authority. 21 st Century Transportation Intermodal Committee February 21, 2008 NC State Ports Authority Tom Eagar, CEO

NC State Ports Authority. 21 st Century Transportation Intermodal Committee February 21, 2008 NC State Ports Authority Tom Eagar, CEO NC State Ports Authority 21 st Century Transportation Intermodal Committee February 21, 2008 NC State Ports Authority Tom Eagar, CEO NC State Ports Authority Facts at a Glance 2 Enterprise agency unique

More information

Port of Philadelphia Port Advisory Board

Port of Philadelphia Port Advisory Board Port of Philadelphia Port Advisory Board JULY 7, 2016 Meeting Overview: Natural flow of port development arising from the channel being deepened to 45 feet. Channel Deepening Project The Channel Deepening

More information

Port Everglades Master/Vision Plan Update Stakeholder Meeting. January 28, 2010

Port Everglades Master/Vision Plan Update Stakeholder Meeting. January 28, 2010 Port Everglades Master/Vision Plan Update Stakeholder Meeting January 28, 2010 1 2 Agenda Updated Market Assessments determine. Master Plan Facility/Infrastructure Needs requiring. Berth Expansion into.

More information

Measuring Supply Chain Performance A Government Perspective. APCGI Workshop Toronto June 18, 2010

Measuring Supply Chain Performance A Government Perspective. APCGI Workshop Toronto June 18, 2010 Measuring Supply Chain Performance A Government Perspective APCGI Workshop Toronto June 18, 2010 1 Agenda Why should governments measure supply chain performance? 1. Policy Context 2. Supply Chain Metrics

More information

The Impact of Mega-Ships

The Impact of Mega-Ships short report The Impact of Mega-Ships by Olaf Merk 1 Container ships have grown bigger at a rapid pace over the last decades, faster than any other ship type. In one decade, the average capacity of a container

More information

The Challenges of Container Terminal Development. Ashebir Jacob, PE September 10, 2013

The Challenges of Container Terminal Development. Ashebir Jacob, PE September 10, 2013 The Challenges of Container Terminal Development Ashebir Jacob, PE September 10, 2013 State of Containerization Since its inception, the container shipping industry has done their best to increase the

More information

2. THE CONTEXT OF PORT PRICING

2. THE CONTEXT OF PORT PRICING 2. THE CONTEXT OF PORT PRICING 2.1 Pricing objectives In formulating pricing policies and establishing tariffs, ports generally endeavour to incorporate the following pricing objectives: 1 (a) To promote

More information

Embassy of Denmark in Vietnam 2 / 10

Embassy of Denmark in Vietnam 2 / 10 Date July 2015 1. Keywords... 2 2. Abstract... 2 3. Introduction... 2 4. Sector Overview... 3 5. Government policy... 7 6. Opportunities for Danish companies... 8 7. Conclusion... 8 Transport, Logistics,

More information

Investor Presentation February 2018 Slide 1. Investor Presentation February 2018

Investor Presentation February 2018 Slide 1. Investor Presentation February 2018 Investor Presentation February 2018 Slide 1 Investor Presentation February 2018 Forward Looking Statements Statements made during this presentation that set forth expectations, predictions, projections

More information

THE PORT. REASONS CHOOSE THE PORT OF Montréal PORT FACILITIES

THE PORT. REASONS CHOOSE THE PORT OF Montréal PORT FACILITIES 1 TO REASONS CHOOSE THE PORT OF Montréal THE PORT IN NUMBERS 1 STRATEGIC LOCATION Closest international container port to Eastern Canada and the U.S. Midwest major distribution centres and consumer markets.

More information

CALL FOR PROPOSALS FOR MAKING AREAS AVAILABLE AT THE TRADING PORT OF SÈTE WITH A VIEW TO OPERATING A CONTAINER AND GENERAL CARGO YARD.

CALL FOR PROPOSALS FOR MAKING AREAS AVAILABLE AT THE TRADING PORT OF SÈTE WITH A VIEW TO OPERATING A CONTAINER AND GENERAL CARGO YARD. CALL FOR PROPOSALS FOR MAKING AREAS AVAILABLE AT THE TRADING PORT OF SÈTE WITH A VIEW TO OPERATING A CONTAINER AND GENERAL CARGO YARD Specifications Preamble Ownership of the ports of Sète and Frontignan

More information

Port Performance Thoughts to Share Why Measure Performance? How to Measure?

Port Performance Thoughts to Share Why Measure Performance? How to Measure? Port Performance Thoughts to Share Why Measure Performance? How to Measure? Mary R. Brooks, 2015 Frequency Source: Variant of Griffis et al. (2007). Aligning logistics performance measures to the information

More information

Paying For Port Security. HAL HUDGINS Vice President, Planning and Security Alabama State Port Authority

Paying For Port Security. HAL HUDGINS Vice President, Planning and Security Alabama State Port Authority Paying For Port Security HAL HUDGINS Vice President, Planning and Security Alabama State Port Authority July 28, 2005 The Alabama State Port Authority A Public Corporation Wholly-Owned By The State Created

More information

Optimization of Terminal Operations September 23, Navis, LLC. All other trademarks are the property of their respective owners.

Optimization of Terminal Operations September 23, Navis, LLC. All other trademarks are the property of their respective owners. Optimization of Terminal Operations September 23, 2016 A Quick Detour from Ports Vehicle Dispatching Systems Drivers Riders Match Technology Enablers & Mobile Devices Mapping Billing & Accountability Reporting

More information

Atlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY

Atlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY Atlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY Draft Reformulation Public Information October 2016 US Army Corps of Engineers Presentation Outline Project Overview

More information

Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101

Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101 Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101 Guidelines for environmental impacts of vessels InCom

More information

Port of Manzanillo. Port of Manzanillo: Climate Risks and Opportunities. IAIA Symposium: Sustainable Mega- Infrastructure and Impact Assessment

Port of Manzanillo. Port of Manzanillo: Climate Risks and Opportunities. IAIA Symposium: Sustainable Mega- Infrastructure and Impact Assessment Port of Manzanillo Port of Manzanillo: Climate Risks and Opportunities IAIA Symposium: Sustainable Mega- Infrastructure and Impact Assessment Panama City, December 3, 2015 Vladimir Stenek, IFC, World Bank

More information

CONSTANTA PORT (a river maritime port)

CONSTANTA PORT (a river maritime port) Location Black Sea Port, connected to the Danube via the Danube Black Sea Canal Authorities National Company Maritime Ports Administration SA Constanta General Manager: Andrei Aurelian POPA Address: Incinta

More information

Southeast Florida Freight and Goods Movement Update Treasure Coast Regional Planning Council September 16, 2011

Southeast Florida Freight and Goods Movement Update Treasure Coast Regional Planning Council September 16, 2011 Southeast Florida Freight and Goods Movement Update Treasure Coast Regional Planning Council September 16, 2011 For Questions on this Presentation, Please Contact: Jeff Weidner, Mobility Manager Florida

More information

Cross Border Rail Transportation: A Canadian Perspective. Canada-United States Cross-Border Rail Peer Exchange May 25, 2011 Burlington, Vermont

Cross Border Rail Transportation: A Canadian Perspective. Canada-United States Cross-Border Rail Peer Exchange May 25, 2011 Burlington, Vermont Cross Border Rail Transportation: A Canadian Perspective Canada-United States Cross-Border Rail Peer Exchange May 25, 2011 Burlington, Vermont 2 Purpose To discuss: National Context Current State of Cross

More information

PORT OF NEW YORK & NEW JERSEY RAIL FACILITY EXPANSION PROGRAM

PORT OF NEW YORK & NEW JERSEY RAIL FACILITY EXPANSION PROGRAM PORT OF NEW YORK & NEW JERSEY RAIL FACILITY EXPANSION PROGRAM New England Rail Forum & Expo March 28, 2006 Port of NY & NJ Marine Terminals Port Newark Vehicles Global Red Hook Port Elizabeth Vehicles

More information

The Port of New York and New Jersey. The Environment

The Port of New York and New Jersey. The Environment The Environment The An Important Environment Resource for Our Region As the premier cargo center on the eastern seaboard, the Port of New York and New Jersey connects our region to both the international

More information

Container Transfer Logistics at Multimodal Container Terminals

Container Transfer Logistics at Multimodal Container Terminals Container Transfer Logistics at Multimodal Container Terminals Erhan Kozan School of Mathematical Sciences, Queensland University of Technology Brisbane Qld 4001 Australia e.kozan@qut.edu.au Abstract:

More information

Wharf structures and Quay Deck landing areas, will be built in stages to accommodate the following transport fleet:

Wharf structures and Quay Deck landing areas, will be built in stages to accommodate the following transport fleet: 8C Noise Design Assumptions and Source Data 8C.1 Construction Predicted noise levels at the nearest noise sensitive receptors from construction activities have been modelled and presented as noise contours,

More information

Conversion of Kurnell refinery to a fuel import terminal

Conversion of Kurnell refinery to a fuel import terminal Conversion of Kurnell refinery to a fuel import terminal Dr Jos Kusters 1 May 2014 AGENDA Background Kurnell site conversion Management of environmental and community impacts Operation as a terminal 2

More information

APM Terminals Nigeria

APM Terminals Nigeria APM Terminals Nigeria Our Group ownership structure A.P. Møller Mærsk A/S Maersk Line APM Terminals Maersk Oil Maersk Drilling Maersk Supply Service Maersk Tankers Damco Svitzer Maersk Container Industry

More information

IAPH & Challenges facing World s Ports

IAPH & Challenges facing World s Ports IAPH & Challenges facing World s Ports Kaohsiung, August 2015, Susumu Naruse The International Association of Ports & Harbors s_naruse@iaphworldports.org About IAPH (1) Foundation Only international association

More information

Port Reform, Privatization, and Regulation

Port Reform, Privatization, and Regulation Port Reform, Privatization, and Regulation Paul E. Kent, Ph.D., Vice President Infrastructure Planning and Economics Nathan Associates Inc. PKent@nathaninc.com December 17, 2008 Primer on Port Terminology

More information

Caribbean Port Efficiency: Challenges and Opportunities S. Brian Samuel PPP Coordinator Caribbean Development Bank

Caribbean Port Efficiency: Challenges and Opportunities S. Brian Samuel PPP Coordinator Caribbean Development Bank Caribbean Port Efficiency: Challenges and Opportunities S. Brian Samuel PPP Coordinator Caribbean Development Bank CDB 46 th Annual General Meeting, 19 th May 2016, Montego Bay, Jamaica Contents 1. Why

More information

Policy Dialogue on PPP Infrastructure Development in South Asia

Policy Dialogue on PPP Infrastructure Development in South Asia Policy Dialogue on PPP Infrastructure Development in South Asia 22-23 Sept, 2015 in Kathmandu SRI LANKA EXPERIENCE WITH PPP PROJECTS THE NATIONAL PPP (POLICY) provides a consistent framework that enables

More information

Port of Algoma. Focal Point of the Great Lakes Region

Port of Algoma. Focal Point of the Great Lakes Region Port of Algoma Focal Point of the Great Lakes Region Overview Essar Global Fund Ltd s Investments ENERGY PORTS & INFRASTRUCTURE METALS & MINING SERVICES Oil & Gas #2 largest single location refineries

More information

Milan Malpensa Airport

Milan Malpensa Airport Milan Malpensa Airport Request for Expressions of Interest for the award of areas to be used as "Cargo Trucks Services Centre in Milan Malpensa airport. 1 BACKGROUND INFORMATION As part of the cargo development

More information

CSUN RESEARCH TEAM Dr, Alireza Kabirian, Dr. S. JimmyGandhi, Dr. Emad Al-Wakil, Dr. Abhijit Mukherjee Dr. Rais Ahmed

CSUN RESEARCH TEAM Dr, Alireza Kabirian, Dr. S. JimmyGandhi, Dr. Emad Al-Wakil, Dr. Abhijit Mukherjee Dr. Rais Ahmed CSUN RESEARCH TEAM Dr, Alireza Kabirian, Dr. S. JimmyGandhi, Dr. Emad Al-Wakil, Dr. Abhijit Mukherjee Dr. Rais Ahmed & Mr. David Alba Co-Founder President GRID Logistics Inc. PROPOSING GENUINE 21 ST CENTURY

More information

PORT QASIM AUTHORITY. Port Handling Capacity / Challenges

PORT QASIM AUTHORITY. Port Handling Capacity / Challenges PORT QASIM AUTHORITY Port Handling Capacity / Challenges 11 th January-2016 1 PQA s Overview Port Qasim functions under PQA Act, 1973 on landlord concept with an attached industrial estate (13,700 acres)

More information

CHANGE OF AN OLD NAVY BASE TO A MODERN MARINA IN BOLTENHAGEN (BALTIC SEA)

CHANGE OF AN OLD NAVY BASE TO A MODERN MARINA IN BOLTENHAGEN (BALTIC SEA) CHANGE OF AN OLD NAVY BASE TO A MODERN MARINA IN BOLTENHAGEN (BALTIC SEA) Siegmund Schlie*, Bernd Opfermann** and Torsten Retzlaff*** * Heinrich Hirdes GmbH, Rostock ** b & o - Ingenieure, Hamburg ***

More information

APM Terminals Lazaro Cardenas. Mexico s new gateway to the Pacific

APM Terminals Lazaro Cardenas. Mexico s new gateway to the Pacific APM Terminals Lazaro Cardenas Mexico s new gateway to the Pacific 2 Mexico s new gateway to the Pacific 2.2% expansion in the Mexico economy in 2016 90% of Mexico s Pacific Coast trade passes through either

More information

Services and Rates of The Moin Container Terminal 2018

Services and Rates of The Moin Container Terminal 2018 Services and Rates of The Moin Container Terminal 2018 T his document describes the services that will be provided by the Moín Container Terminal (MCT), based on the conditions stipulated in the Public

More information

Benefit Cost Analysis 2016 TIGER Grant Application Funding Opportunity #: DTOS59-16-RA-TIGER8

Benefit Cost Analysis 2016 TIGER Grant Application Funding Opportunity #: DTOS59-16-RA-TIGER8 Benefit Cost Analysis 2016 TIGER Grant Application Funding Opportunity #: DTOS59-16-RA-TIGER8 Applicant: Philadelphia Regional Port Authority Packer Avenue Marine Terminal Berth and Crane Rail Enhancement

More information

Failure to Act. Of current Investment Trends in. Airports, Inland Waterways, and Marine Ports. Infrastructure EXECUTIVE SUMMARY

Failure to Act. Of current Investment Trends in. Airports, Inland Waterways, and Marine Ports. Infrastructure EXECUTIVE SUMMARY Failure to Act The economic impact Of current Investment Trends in Airports, Inland Waterways, and Marine Ports Infrastructure EXECUTIVE SUMMARY EXECUTIVE SUMMARY Air and waterborne transportation infrastructure

More information

Waterways 1 Water Transportation History

Waterways 1 Water Transportation History Waterways 1 Water Transportation History Water Transportation Propulsion History Human (oars, poles) - - 7,000-10,000 BC Wind (sails) - - 3,000 BC Steamboat invented - - 1787 AD First diesel-powered ship

More information

Climate Risk and Adaptation Case Study Ports: Muelles el Bosque (MEB) Cartagena, Colombia

Climate Risk and Adaptation Case Study Ports: Muelles el Bosque (MEB) Cartagena, Colombia Climate Risk and Adaptation Case Study Ports: Muelles el Bosque (MEB) Cartagena, Colombia Amanda Rycerz Climate Risk Analyst, Acclimatise Group Limited Surface Transportation System Resilience to Climate

More information

ESCAP. Ports as gateways to hinterland areas. getting the cogs to work together

ESCAP. Ports as gateways to hinterland areas. getting the cogs to work together Seminar on the development of port infrastructure Bangkok, 20-21 December 2016 Ports as gateways to hinterland areas getting the cogs to work together 1. The mandate resolution 71/6 (May 2015) International

More information

Intermodal connections and networks the challenge and opportunity for Latin American A railroads

Intermodal connections and networks the challenge and opportunity for Latin American A railroads Intermodal connections and networks the challenge and opportunity for Latin American A railroads by Anthony J. S cotti, Adam K. Prokopowicz and Jan A. B erg-andreassen International Infras tructure and

More information

84 th International Propeller Club Convention Fundamental Changes to a Traditional Transportation Paradigm. October 7, 2009

84 th International Propeller Club Convention Fundamental Changes to a Traditional Transportation Paradigm. October 7, 2009 84 th International Propeller Club Convention Fundamental Changes to a Traditional Transportation Paradigm October 7, 2009 Today s Objectives Endeavor to provide a broad context for today s session by

More information

Abstract. I. Introduction

Abstract. I. Introduction Strategies for Mediterranean Port Development Harilaos N. Psaraftis Professor, National Technical University of Athens 9 Iroon Polytechneiou St., 15773 Zografou Greece and General Manager, Piraeus Port

More information

TARIFF FOR PORT SERVICES

TARIFF FOR PORT SERVICES TARIFF FOR PORT SERVICES Valid as per June 1, 2018 TABLE OF CONTENTS I. General Provisions 2 II. ISPS access fee 2 III. Storage fees / stall money 2 IV. Ferry bridge fees 3 V. Fees for cargo handling services

More information

Marine Terminals Capability statement. April 2010 LWI

Marine Terminals Capability statement. April 2010 LWI Marine Terminals Capability statement April 2010 LWI About LWI Lanier Wallingford International (LWI) is a strategic alliance between: Lanier & Associates Inc HR Wallingford Ltd. As a specialist marine

More information