Gorgon Gas Development and Jansz Feed Gas Pipeline
|
|
- Moses Elliott
- 5 years ago
- Views:
Transcription
1 Gorgon Gas Development and Jansz Feed Gas Pipeline Ministerial Statements 800, 965, and 769 Assessment 2017 Revision ID: 1.0 Revision Date: 25 October 2017 Next Revision Due: NA Information Sensitivity: Public
2 2017 by Chevron Australia Pty Ltd This document contains proprietary information of Chevron Australia Pty Ltd. Any use of this document without express, prior, written permission from Chevron Australia Pty Ltd and/or its affiliates is prohibited. Revision ID: 1.0 Revision Date: 25 October 2017 Page 2
3 Contents Managing Director s Statement and Endorsement... 4 Managing Director s Statement and Endorsement... 5 Executive Summary Introduction Scope of this Proponent Project Scope Project Location Approvals Status of Implementation ing Methodology ing Methodology ing Non-compliances and Corrective and Preventive Actions Status Terminology Public Availability of the Changes to the Assessment Findings for MS 800 and MS Findings for MS Acronyms and Abbreviations References Tables Table 3-1: Status Terms Table 4-1: MS 800 and MS 965 Assessment Table Table 5-1: MS 769 Assessment Table Table 6-1: Acronyms and Abbreviations Table 7-1: References Figures Figure 1-1: Location of the Greater Gorgon Area... 9 Figure 1-2: Location of the Gorgon Gas Development and Jansz Feed Gas Pipeline Revision ID: 1.0 Revision Date: 25 October 2017 Page 3
4
5
6 Executive Summary Gorgon Gas Development and Jansz Feed Gas Pipeline This Assessment (the ) was prepared to meet the requirements of Condition 4 of Ministerial Statement 800 (MS 800), Condition 2 of Ministerial Statement 965 (MS 965), and Condition 4 of Ministerial Statement 769 (MS 769). It addresses the status and compliance of the Gorgon Gas Development and Jansz Feed Gas Pipeline with the conditions referred to in MS 800, MS 965, and MS 769 for works carried out during the reporting period 10 August 2016 to 9 August During the reporting period, 11 audits were conducted. Chevron Australia Pty Ltd (Chevron Australia) conducted ten audits and the Western Australian Office of the Protection Authority (OEPA) conducted one audit against the applicable conditions of MS 800 and MS 769. Chevron Australia is compliant with the conditions referred to in MS 800, MS 965, and MS 769. findings and the associated corrective actions identified from audits during the reporting period are included in the Assessment Tables (Table 4-1 and Table 5-1) to support statements of compliance status. Chevron Australia considers all audit findings are procedural and minor in nature; all have been addressed. Revision ID: 1.0 Revision Date: 25 October 2017 Page 6
7 1.0 Introduction Gorgon Gas Development and Jansz Feed Gas Pipeline This Assessment (the ) was prepared to meet the requirements of Condition 4 of Ministerial Statement 800 (MS 800), Condition 2 of Ministerial Statement 965 (MS 965), and Condition 4 of Ministerial Statement 769 (MS 769). This addresses the compliance status of the Gorgon Gas Development with the conditions referred to in MS 800 and MS 965, and the compliance status of the Jansz Feed Gas Pipeline with the conditions referred to in MS 769 for works carried out during the reporting period 10 August 2016 to 9 August Scope of this This relates to the conditions of MS 800, MS 965, and MS 769. Condition 4.6 of MS 800 and MS 769 requires Chevron Australia Pty Ltd (Chevron Australia) (as the Proponent) to submit an annual Assessment for the previous twelve-month period, and states that the report must: be endorsed by the Proponent s Managing Director or a person, approved in writing by the (Western Australian) Department of Environment and Conservation (Parks and Wildlife), delegated to sign on the Managing Director s behalf include a statement as to whether the Proponent has complied with the conditions identify all non-compliances and describe corrective and preventive actions taken be made publicly available in accordance with the approved Assessment indicate any proposed changes to the Assessment required by Condition 4.1. Condition 4.3 of MS 800 and MS 769 requires Chevron Australia to assess compliance with conditions in accordance with the Assessment (Ref. 1) required by Condition 4.1 of MS 800 and MS 769. Condition 2.1 of MS 965 requires that compliance assessment and reporting requirements that apply to the Proposal under the implementation conditions set out in MS 800 are carried out jointly with the Gorgon Gas Development Proposal referred to in MS 800. The proposal associated with MS 1002 has not been implemented. Therefore, MS 1002 is not within the scope of this document. 1.2 Proponent Chevron Australia is the proponent for the Gorgon Gas Development on behalf of these companies (collectively known as the Gorgon Joint Venturers): Chevron Australia Pty Ltd Chevron (TAPL) Pty Ltd Shell Australia Pty Ltd Mobil Australia Resources Company Pty Limited Osaka Gas Gorgon Pty Ltd Tokyo Gas Gorgon Pty Ltd JERA Gorgon Pty Ltd pursuant to MS 800 and MS 965. Chevron Australia is the person taking the action for the Jansz Feed Gas Pipeline on behalf of the Gorgon Joint Venturers, pursuant to MS 769. Revision ID: 1.0 Revision Date: 25 October 2017 Page 7
8 1.3 Project Scope Gorgon Gas Development and Jansz Feed Gas Pipeline Chevron Australia is developing the gas reserves of the Greater Gorgon Area. The gas is processed in a Gas Treatment t (GTP) on Barrow Island, which is located off the Pilbara coast 85 km north-north-east of Onslow in Western Australia (WA) (Figure 1-1). Subsea gathering systems and pipelines deliver feed gas from the Gorgon and Jansz Io gas fields to the west coast of Barrow Island. The underground feed gas pipeline system then traverses Barrow Island to the east coast where the GTP is located. The GTP includes natural gas trains that produce liquefied natural gas (LNG) as well as condensate and domestic gas (DomGas). Carbon dioxide (CO2), which occurs naturally in the feed gas, is separated during the production process, and will be injected into deep rock formations below Barrow Island. The LNG and condensate is loaded onto tankers from a jetty and then transported to international markets. Gas for domestic use is exported by pipeline from Barrow Island to the DomGas collection and distribution network on the WA mainland (Figure 1-2). 1.4 Project Location The Gorgon gas field is located approximately 130 km and the Jansz Io gas field approximately 200 km off the north-west coast of WA. Barrow Island is located off the Pilbara coast approximately 85 km north-north-east of Onslow and approximately 140 km west of Karratha. Barrow Island is approximately 25 km long and 10 km wide and covers ha. Revision ID: 1.0 Revision Date: 25 October 2017 Page 8
9 Figure 1-1: Location of the Greater Gorgon Area Revision ID: 1.0 Revision Date: 25 October 2017 Page 9
10 Figure 1-2: Location of the Gorgon Gas Development and Jansz Feed Gas Pipeline Revision ID: 1.0 Revision Date: 25 October 2017 Page 10
11 1.5 Approvals Gorgon Gas Development and Jansz Feed Gas Pipeline The initial Gorgon Gas Development was assessed through an Impact Statement/ Review and Programme (EIS/ERMP) process. The Jansz Feed Gas Pipeline was approved by the WA State Minister for the Environment on 28 May 2008 by way of MS 769 (Ref. 2) and by the Commonwealth Minister for the Environment and Water Resources on 22 March 2006 (EPBC 2005/2184 [Ref. 3]). On 10 August 2009, the WA State Minister for the Environment issued MS 800 (Ref. 4) granting approval for the Revised and Expanded Gorgon Gas Development. MS 800 provides approval for both the initial Gorgon Gas Development and the Revised and Expanded Gorgon Gas Development, which together are known as the Gorgon Gas Development. On 26 August 2009, the Commonwealth Minister for the Environment approved the Revised and Expanded Gorgon Gas Development (EPBC 2008/4178 [Ref. 5]) and varied the conditions for the initial Gorgon Gas Development (EPBC 2003/1294 [Ref. 6]). Since the Revised and Expanded Gorgon Gas Development was approved, further changes to the Gorgon Gas Development have been made and/or approved and are now also part of the Development. These include MS 965 (Ref. 7), which applies the conditions of MS 800 for an Additional Support Area, and MS 1002 (Ref. 8), which applies the conditions of MS 800 as amended by MS 865 (Ref. 9) for the Fourth Train Expansion Proposal. On 17 July 2015, the Commonwealth Department of the Environment (DotE) approved a Variation of Approval Conditions for EPBC 2005/2184 (Jansz Io Deepwater Gas Field), which revoked Conditions 1, 2, 4, 5, 6, and 7, and amended the remaining Conditions 3 and 8 (Ref. 10). Revision ID: 1.0 Revision Date: 25 October 2017 Page 11
12 2.0 Status of Implementation Gorgon Gas Development and Jansz Feed Gas Pipeline Significant progress has been made on the Gorgon Gas Development since construction started in December 2009, with the Project currently transitioning to an operational facility. At the end of the ing Period: More than 1200 people were working on Barrow Island; most of the construction workforce had been demobilised. LNG Trains 2 and 3 had been successfully commissioned and started; the 100 th LNG export cargo was achieved in July Since production commenced in 2016, five condensate export cargoes had been delivered. The Gorgon field subsea pipelines, wellheads, and associated facilities had been successfully commissioned and started, and were operating successfully. Redundant construction infrastructure on Barrow Island had been dismantled and demobilised. The DomGas plant on Barrow Island, and associated domestic gas export to the mainland, was operating successfully. During the reporting period, these plans and reports were submitted and/or approved under MS 800 and MS 769: Marine Quality (Ref. 11) Environment Monitoring Program (Ref. 12) Long-term Marine Turtle (Ref. 13) Solid and Liquid Waste (Ref. 14) Marine Quarantine System (Ref. 15). Revision ID: 1.0 Revision Date: 25 October 2017 Page 12
13 3.0 ing Methodology 3.1 ing Methodology Gorgon Gas Development and Jansz Feed Gas Pipeline The compliance assurance program for the Gorgon Gas Development includes a multitiered environmental audit program and the capture and tracking to closure of any action items associated with the audit findings. The program provides a high level of assurance as to the status of compliance with environmental obligations and the implementation of corrective actions to address any deficiencies. During the reporting period: Chevron Australia completed ten audits between August 2016 and August 2017 to determine compliance with the conditions of MS 800, MS 965, and MS 769. These audits comprised both desktop and field assessments (Chevron Australia s Perth offices, supply bases, marine vessels, and Barrow Island), which were based on interviews, physical inspections, observations, and reviews of records and documentation, where applicable. The Western Australian Office of the Protection Authority (OEPA) completed one desktop audit in June 2017 to determine Chevron Australia s compliance with the Environment Protection (Ref. 16), Environment Monitoring Program (Ref. 12), and the implementation conditions of MS 800, MS 769, and MS 965. No noncompliances were identified. Relevant findings from the audits are referenced in this (Table 4-1 and Table 5-1) to support statements of compliance status. The audit methodology for this followed the Assessment Process as described in Section 3.0 of the Assessment (Ref. 1). 3.2 ing Non-compliances and Corrective and Preventive Actions In accordance with Condition 4.6(iii) of MS 800 and MS 769, any non-compliances with the conditions of MS 800 and MS 769 identified during the reporting period must be reported in this. Table 4-1 and Table 5-1 detail the compliance status with conditions. 3.3 Status Terminology For this, Chevron Australia has adopted the Action Implementation Status terminology from the OEPA s Post Assessment Guideline for Preparing an Table document (Ref. 17). This terminology is listed in Table 3-1 and is used for reporting compliance status in Table 4-1 and Table 5-1. Table 3-1: Status Terms Status Not Required at this Stage Potentially Non-compliant Non-compliant Description Implementation of the proposal has been carried out in accordance with the requirements of the audit element A requirement with a finite period of application has been satisfactorily completed The requirements of the audit element were not triggered during the reporting period Possible or likely failure to meet the requirements of the audit element Implementation of the proposal has not been carried out in accordance with the requirements of the audit element Revision ID: 1.0 Revision Date: 25 October 2017 Page 13
14 In Process Status Description Where an audit element requires a management, or monitoring plan be submitted to the OEPA or another government agency for approval, that submission has been made and no further information or changes have been requested by the OEPA or the other government agency and assessment by the OEPA or other government agency for approval is still pending 3.4 Public Availability of the In accordance with the Assessment (Ref. 1) and Condition 4.6(iv) in MS 800 and MS 769, this will be made available to the public once Chevron Australia has received acknowledgement from the OEPA that the has been accepted as the complete and final. A copy of the will be placed on the Chevron Australia website for at least 12 months, after which the will be made available, where appropriate, on request. 3.5 Changes to the Assessment This is consistent with Revision 3 of the Assessment (Ref. 1), which was approved by OEPA on 27 August Revision ID: 1.0 Revision Date: 25 October 2017 Page 14
15 4.0 Findings for MS 800 and MS 965 with the conditions of MS 800 and MS 965 is shown in Table 4-1 for the reporting period 10 August 2016 to 9 August Table 4-1: MS 800 and MS 965 Assessment Table Notes: Common phases of development referred to in this table include:,, Operation, Decommissioning and Closure, Overall (several or all phases). This audit table summarises the MS 800 and MS 965 conditions that apply to the Gorgon Gas Development. The Requirement column is intended to accurately reflect the content of MS 800 and MS 965; however, if there is any deviation, the contents of MS 800 and MS 965 shall take precedence. The abbreviation M in the denotes an implementation condition as per the OEPA s Post Assessment Guideline for Preparing an Table document (Ref. 17). If a condition of MS 800 or MS 965 is replaced or amended during an assessment period, this compliance audit table will record the condition as it was, the date of the amendment, and the condition in its amended form. The compliance assessment for that period will then assess compliance with whichever relevant condition applied up to, and then after, the date of the condition amendment. In subsequent assessment periods, the date of the condition amendment will be noted, but the audit table will only include the amended condition. Where the WA Department of Environment and Conservation (DEC) Chief Executive Officer (CEO) or DEC are referred to in the Requirement column, these shall be taken to mean the OEPA CEO (as a result of organisational changes made by the Western Australian Government in December 2009). Where the Commonwealth Department of Environment and Water (DEW), Commonwealth Department of Environment, Water, Heritage and the Arts (DEWHA), Commonwealth Department of Sustainability, Environment, Water, Population and Communities (SEWPaC), or Department of the Environment (DotE) is referred to, this shall be taken to mean the Commonwealth Department of the Environment and Energy (DotEE). Where the WA Department of Industry and Resources (DoIR) or Department of Mines and Petroleum (DMP) is referred to, this shall be taken to mean the Department of Mines, Industry Regulation and Safety (DMIRS). Lighter text is the historic evidence of compliance from previous Assessment s, which is included for completeness where appropriate. 800:M1.1 Proposal Implementation The Proponent shall implement the Proposal as documented and described in Schedule 1 of this Statement subject to the conditions and schedules of this Statement Proposal implemented in accordance with the conditions and schedules of this statement Assessment the Minister s determination on changes to the Proposal when required Overall For life of Project The Gorgon Gas Development was implemented in accordance with the requirements of MS 800 as detailed in this Assessment Revision ID: 1.0 Revision Date: 25 October 2017 Page 15
16 800:M1A.1 Transitional Arrangements Regarding Carbon Dioxide Seismic Baseline Surveys Notwithstanding anything in these conditions, works associated with the carbon dioxide seismic baseline survey program may be undertaken for a period of 6 months from the date of this Statement, or such longer period as determined by the Minister, in accordance with the conditions contained in Ministerial Statement No. 748 and Conditions 4, 5, 6.6, 7.7, and 35 of this Statement Carbon Dioxide Seismic Baseline Survey Program implemented in accordance with the conditions in Statement No. 748 and Conditions 4, 5, 6.6, 7.7, and 35 of Statement No. 800 Annual Assessment For six months from the date of this statement (i.e. up to 10 February 2010) Ministerial Implementation Statement No (G1-NT- REPX ) Submission letter from Chevron Australia to DEC dated 3 August 2010 (G1-CO-LTR- CVXPH-DECWH ) Submission letter from Chevron Australia to OEPA, dated 3 August 2010 (G1-CO-LTR- CVXPH-EPAPH ) Ministerial Implementation Statement No. 748 Performance 2010 (G1- NT-REPX ) Submission letter from Chevron Australia to DEC, dated 18 August 2010 (G1-CO-LTR- CVXPH-DECWH ) Submission letter from Chevron Australia to OEPA, dated 18 August 2010 (G1-CO-LTR- CVXPH-EPAPH ) The carbon dioxide seismic baseline survey program works were completed in December As such, all other Gorgon Gas Development works will be governed by MS 800 and no further annual Performance s or s will be submitted under MS :M2.1 Proponent Nomination and Contact Details The Proponent for the time being nominated by the Minister for Environment under sections 38(6) or 38(7) of the Protection Act 1986 is responsible for the implementation of the Proposal Nominate any change to Proponent from time to time of nomination of Minister s response if provided Overall For life of Project The nominated Proponent for the Proposal did not change during the reporting period. 800:M2.2 Proponent Nomination and Contact Details The Proponent shall notify the Chief Executive Officer of the DEC (CEO) of any change of the name and address of the Proponent for the serving of a notice or other correspondence within 30 days of such change Notify DEC CEO of any change to contact name and/or address Written advice to OEPA CEO of change of contact name and address Overall Within 30 days of such change There was no change to the name and/or address of the nominated Proponent during the reporting period 800:M3.1 Time Limit of Authorisation The authorisation to implement the Proposal provided for in this Statement shall lapse and be void within five years after the date of this Statement if the Proposal to which this Statement relates is not substantially commenced See 800:M3.2 See 800:M3.2 Annual Assessment Overall Within five years after the date of this statement (by 10 August 2014) See 800:M :M3.2 Time Limit of Authorisation The Proponent shall provide the CEO with written evidence which demonstrates that the Proposal has substantially commenced on or before the expiration of five years from the date of this Statement Provide written advice to CEO the the Proposal Written advice Proposal submission to OEPA CEO and receipt if provided Overall Within five years after the date of this statement (by 10 August 2014) Letter from Chevron Australia to OEPA, dated 27 November 2013 (G1-CO-LTR-CVXPH- EPAPH ), providing evidence of substantial Proposal OEPA Verification, dated 29 April 2014 (G1-NT-REPX ) indicating that Chevron Australia provided information confirming the Gorgon Gas Development (MS 800) has substantially commenced within the authorised time limit, and confirming that this condition is completed Revision ID: 1.0 Revision Date: 25 October 2017 Page 16
17 800:M4.1 ing The Proponent shall prepare and maintain a Assessment to the satisfaction of the CEO Prepare and maintain a Assessment (CAP) Assessment maintenance if required submission of CAP to OEPA CEO and record of OEPA CEO satisfaction if provided Overall Prepare within six months from the date of this statement (i.e. by 10 February 2010) Maintain throughout life of Project Assessment Revision 3 (G1- NT-PLNX ) Submission letter from Chevron Australia to OEPA submitting the Assessment for approval, dated 14 August 2014 (G1- CO-LTR-CVXPH-EPAPH ) Letter from OEPA to Chevron Australia dated 27 August 2014 (G1-CO-LTR-EPAPH-CVXPH ) accepting the Assessment 800:M4.2 ing The Proponent shall submit to the CEO, the Assessment required by Condition 4.1 within 6 months of the date of this Statement. The Assessment shall indicate: 1. the frequency of compliance reporting; 2. the approach and timing of compliance assessments; 3. the retention of compliance assessments; 4. reporting of non-compliances and corrective actions taken; 5. the table of contents of Assessment ; and 6. public availability of compliance reports Submit Assessment to the CEO that cover the items listed by Condition 4.2 Assessment submission of CAP to OEPA CEO and record of OEPA CEO satisfaction if provided Within six months of the date of this Statement (i.e. by 10 February 2010) See 800:M4.1 The Assessment covered the topics required in Condition :M4.3 ing The Proponent shall assess compliance with conditions in accordance with the Assessment required by Condition 4.1 Prepare an Annual Assessment in accordance with the CAP Annual Assessment Overall For life of Project See 800:M :M4.4 ing The Proponent shall retain reports of all compliance assessments described in the Assessment required by Condition 4.1 and shall make those reports available when requested by the CEO Annual Assessment will be retained in the Chevron Australia Document System (DMS) Annual Assessment s will be made available to the DEC CEO* when requested Annual Assessment provision to the OEPA CEO when requested Overall Throughout life of Project and when requested by the OEPA CEO See 800:M4.6 Annual Assessment s are retained in Chevron Australia s Document System (DMS) were kept in accordance with Condition 4.4. were made available during the reporting period when requested by the OEPA (e.g. during the OEPA audit) 800:M4.5 ing The Proponent shall advise the CEO of any non-compliance as soon as practicable any noncompliances as soon as practicable non-compliances having been reported and in what time frame Overall As soon as practicable In accordance with Section 5 of the Assessment (Ref. 1), all noncompliances identified during the reporting period (relating to management plan provisions) that do not affect the meeting of Revision ID: 1.0 Revision Date: 25 October 2017 Page 17
18 Annual Assessment that plan s objectives are reported annually in this No non-compliances were identified during the reporting period that affect the meeting of the plan s objectives 800:M4.6 ing The Proponent shall submit to the CEO a Assessment annually from the date of issue of this Statement addressing the previous twelve-month period or other period as agreed by the CEO. The date of the first Assessment shall be 15 months from the date of this Statement, with each subsequent report 12 months from the date of the previous. The Assessment shall: 1. be endorsed by the Proponent s Managing Director or a person, approved in writing by the Department of Environment and Conservation, delegated to sign on the Managing Director s behalf; 2. include a statement as to whether the Proponent has complied with the conditions; 3. identify all non-compliances and describe corrective and preventive actions taken; 4. be made publicly available in accordance with the approved Assessment ; and 5. indicate any proposed changes to the Assessment required by Condition 4.1 A Assessment will be submitted annually covering the items listed by Condition 4.6 Annual Assessment submission to OEPA CEO and receipt if provided Overall 15 months from the date of this Statement (i.e. by 10 November 2010), with each subsequent report 12 months from the date of the previous Gorgon Gas Development and Jansz Feed Gas Pipeline: Ministerial Statement 800, 965, and 769 Assessment 2016 (ABU ) Submission from Chevron Australia to OEPA, dated 8 November 2016 (ABU ) This is the eighth annual Assessment prepared in accordance with the Assessment (Ref. 1) and Conditions 4.1 and 4.6. It covers the period 10 August 2016 to 9 August This is to be submitted by 10 November :M5.1 Performance ing The Proponent shall submit annually to the Minister an Performance covering the topics listed in Condition 5.2, and the specific details shown in Schedule 3 (excluding item 10(iii) and 10(iv)), covering the previous 12 month period as determined by the Minister. The date of the first Performance (the ) shall be 15 months from the date this Statement with each subsequent report 12 months from the date of the previous report An Performance will be submitted to the Minister annually covering the topics listed in Condition 5.2 and the details shown in Schedule 3 excluding item 10(iii) and 10(iv) Annual Performance (EPR) submission of the to the Minister and receipt if provided Overall 15 months from the date of this Statement (i.e. by 10 November 2010) with each subsequent report 12 months from the date of the previous report Gorgon Gas Development and Jansz Feed Gas Pipeline: Performance 2016 (ABU ) Submission from Chevron Australia to OEPA, dated 4 November 2016 (ABU ) Correspondence from OEPA to Chevron Australia, dated 26 June 2017 (ABU ), advising OEPA have reviewed the information provided and consider the 2016 Performance (EPR) (August 2015 August 2016) meets the requirements of Condition 5 and Schedule 3 of MS 769 and MS 800 The eighth annual EPR is to be submitted to OEPA by 10 November :M5.2 Performance ing The shall cover the following topics: 1. subterranean environment state; 2. marine quarantine (including weed management); 3. Marine turtles (including light and noise management); 4. Short range endemics and subterranean fauna; The Performance shall cover the topics listed in Condition 5.2 Annual Performance Overall 15 months from the date of this Statement (i.e. by 10 November 2010) with each subsequent report 12 months from the date of the previous See 800:M5.1 Revision ID: 1.0 Revision Date: 25 October 2017 Page 18
19 5. Fire management; 6. Carbon Dioxide Injection System; 7. Air quality; 8. Greenhouse gas abatement; 9. Terrestrial rehabilitation; and 10. Coastal stability 800:M5.3 Performance ing Every five years from the date of the first annual Performance the Proponent shall submit to the Minister an Performance for review by the Minister, covering the previous five year period, comprising: 1. The topics listed in Condition 5.2; 2. Specific details shown in Schedule 3; 3. A five year overview of environmental performance; 4. Proposed environmental management improvements; and 5. A review of whether there are any reasonably practicable management measures, operating controls or design features that can be implemented to reduce or eliminate the alteration of the light horizon on the east coast beaches of Barrow Island as a result of the implementation of the Proposal A five-yearly Performance will be submitted to the Minister covering the topics listed in Condition 5.3 Five-yearly Performance submission of the to the Minister and receipt if provided Overall Every five years from the date of the first annual Performance (the first submission being by 10 November 2015) Gorgon Gas Development and Jansz Feed Gas Pipeline: Five Year Performance (August 2010 August 2015) (G1-NT-REPX ) submitted on 10 November 2015 covered the topics required in Condition :M5.4 Performance ing The Proponent shall, if required by the Minister, update s, Programs, Systems, or s in accordance with Condition 36 to include any reasonably practicable improvements identified as part of the Performance referred to in Condition 5.3(iv) Prepare and submit an amendment or addendum to a management plan, program, system, or report in accordance with Condition 36 if required by the Minister Amendment or addendum to a management plan, program, system, or report submission to Minister if required Overall When required by the Minister Not Required at this Stage No update was required by the Minister in relation to the EPR. 800:M6.1 Baseline State and Impact terrestrial facilities on Barrow Island, as defined in Condition 6.3, the Proponent shall submit to the Minister a Baseline State and Impact (the ) that meets the purposes set out in Condition 6.4, as determined by the Minister, unless otherwise allowed in Condition 6.3A. The shall cover the following ecological elements: i. Flora; ii. Vegetation; iii. Fauna (including subterranean fauna and short range endemics); iv. Habitat; v. Ecological communities; vi. Groundwater; Prepare and submit a which meets the purposes set out in Condition 6.4, unless otherwise allowed in Condition 6.3A, and covers the ecological elements listed in Condition 6.1. Baseline State and Impact the Minister s determination of the terrestrial facilities listed in Condition 6.3 Baseline State and Impact Revision 1 (G1-TE-H-0000-REPX027) Submission letter from Chevron Australia to DEC, dated 8 September 2009 (G1-CO-LTR- CVXPH-DECWH ) Approval letter from DEC, dated 10 September 2009 (G1-CO-LTR-DECWH- CVXPH ), states that Revision 1 of the Baseline State and Impact meets the purposes set out in Condition 6.4 and is considered to be complete Letter from Chevron Australia to DEC correcting clerical errors in the submission letter, dated 8 October 2009 (G1-CO-LTR- CVXPH-DECWH ) Revision ID: 1.0 Revision Date: 25 October 2017 Page 19
20 vii. Surface water landforms; and viii. Physical landforms 800:M6.2 Baseline State and Impact The Proponent shall consult with DEC in the preparation of the required by Condition 6.1, including the methodology to be used to survey, collect, and collate the baseline data and information for the ecological elements identified in Condition 6.1 Consult with DEC preparation Baseline State and Impact consultation terrestrial facilities listed in Condition 6.3 Baseline State and Impact Revision 1 (G1-TE-H-0000-REPX027) Submission letter from Chevron Australia to DEC, dated 8 September 2009 (G1-CO-LTR- CVXPH-DECWH ) from DEC, dated 8 September 2009 (G1-CO-EML-DECWH-CVXPH ) 800:M6.3 Baseline State and Impact The terrestrial facilities referred to in Condition 6.1 are: 1. Gas Treatment t; 2. Carbon Dioxide Injection System; 3. Associated Terrestrial Infrastructure forming part of the Proposal; 4. Areas impacted for seismic data acquisition; and 5. Onshore Feed Gas Pipeline System as defined in Schedule 1 See 800:M6.1 Baseline State and Impact Not applicable See 800:M :M6.3A Baseline State and Impact In the event that any portions of the related to specific elements or sub-elements (Condition 6.3) are not submitted as required by Condition 6.1, the Proponent shall submit the portions of the relevant to that element or sub-element to the Minister prior to the that element or sub-element. All portions of the shall meet the purposes identified in Condition 6.4 and the requirements of Condition 6.5 as determined by the Minister Prepare and submit portions of the relevant to the specific element or sub-element that meet the purposes identified in Condition 6.4 and the requirements of Condition 6.5 Baseline State and Impact the Minister's determination of the portions of the relevant to the element or sub-element If any portions of the related to specific elements or subelements (Condition 6.3) are not submitted as required by Condition 6.1 All relevant elements and sub-elements listed in Condition 6.3 are included in the Terrestrial and Baseline State and Impact Revision 3, Amendment 1 (G1-TE-H-0000-REPX027) See 800:M :M6.4 Baseline State and Impact The purposes of the are to: 1. Define and map the pre-development baseline state for the ecological elements within the areas that are expected to, or may be at risk of Material or Serious Harm due to any works associated with the terrestrial facilities listed in Condition 6.3; 2. Define and map the ecological elements within the Terrestrial Disturbance Footprint; and 3. Define and map the ecological elements of reference sites to be used as part of Condition 8, which are not at risk of Material or Serious Harm due to construction or operation of the terrestrial facilities listed in Condition 6.3 See 800:M6.1 Baseline State and Impact terrestrial facilities listed in Condition 6.3 Baseline State and Impact Revision 3, Amendment 1 (G1-TE-H-0000-REPX027) Approval letter from OEPA to Chevron Australia, dated 8 May 2014 (G1-CO-LTR- DECWH-CVXPH ), states the revised plan meets the objectives identified in MS 800 and MS 769 Approval letter from OEPA, dated 8 July 2014 (G1-CO-LTR-EPAPH-CVXPH ), accepting the Gorgon Gas Development and Jansz Feed Gas Pipeline: Baseline State and Impact, Revision 3, Amendment 1 as the current version of the plan required by Condition 6 of MS 800 and MS :M6.5 The shall include: The will cover the topics See 800:M6.4 Revision ID: 1.0 Revision Date: 25 October 2017 Page 20
21 Baseline State and Impact 1. A review of the results of the qualitative ecological risk assessments of the likelihood and consequence of Proposal impacts on the ecological elements identified in Condition 6.1; 2. Details of the methodology that was used to survey, collect, and collate the baseline data and information for all ecological elements identified in Condition 6.1; 3. A description and map of the ecological elements within the Terrestrial Disturbance Footprint; 4. A description and map of the ecological elements which are at risk of Material or Serious Harm outside the Terrestrial Disturbance Footprint due to construction and operation of the terrestrial facilities listed in Condition 6.3; 5. A review of the results to include existing areas of disturbance, including clearing, existing non-indigenous species (including weeds) and disturbed landscapes; 6. Spatially accurate (i.e. rectified and geographically referenced) maps showing the baseline data and information for the ecological elements identified in Condition 6.1; 7. Discussion of the data on the baseline biological, physical, and chemical variables including any significant relationships, for the ecological elements identified in Condition 6.1; 8. Significant ecological elements to be protected e.g. Declared Rare Flora (DRF), threatened ecological communities, Threatened Species under the EPBC Act, habitats of rare fauna; 9. An analysis of, and procedures to address data and information gaps associated with the baseline data for the areas identified in Condition 6.5(iv) for the ecological elements identified in Condition 6.1; and 10. A description and map of the ecological elements of reference sites in locations which are not at risk of Material or Serious harm due to construction and operation of the terrestrial facilities listed in Condition 6.3 listed in Condition 6.5 Baseline State and Impact terrestrial facilities as listed in Condition :M6.6 Baseline State and Impact The Proponent shall not cause or allow Material or Serious Harm outside the Terrestrial Disturbance Footprint Implement the approved Annual Assessment Performance s Overall For life of Project No Material or Serious Harm outside the Terrestrial Disturbance Footprint occurred during the reporting period as a result of the Gorgon Gas Development Revision ID: 1.0 Revision Date: 25 October 2017 Page 21
22 800:M7.1 Environment Protection any of the terrestrial facilities identified in Condition 6.3, the Proponent shall submit a Environment Protection (the ) that meets the objectives identified in Condition 7.4 and the requirements of Condition 7.5 as determined by the Minister, unless otherwise allowed in Condition 7.2 Prepare and submit a which meets the purposes set out in Condition 7.4, and covers the requirements of Condition 7.5, unless otherwise allowed in Condition 7.2 Environment Protection the Minister s determination of the any of the terrestrial facilities identified in Condition 6.3 Environment Protection Revision 1 (G1-NT- PLNX ) Submission letter from Chevron Australia to DEC, dated 8 September 2009 (G1-CO-LTR- CVXPH-DECWH ) Approval letter from DEC, dated 10 September 2009 (G1-CO-LTR-DECWH- CVXPH ), states that Revision 1 of the Environment Protection meets the objectives identified in Condition 7.4 and the requirements of Condition 7.5 are considered to be complete Letter from Chevron Australia to DEC correcting clerical errors in the submission letter, dated 8 October 2009 (G1-CO-LTR- CVXPH-DECWH ) The procedures required by Condition 7.6 were submitted and approved during the reporting period (see 800:M7.6) 800:M7.2 Environment Protection In the event that any portions of the related to specific elements or sub-elements (Schedule 1) is not submitted as required by Condition 7.1, the Proponent shall submit the portions of the relevant to that element or sub-element to the Minister prior to the that element or sub-element. All portions of the shall meet the objectives identified in Condition 7.4 and the requirements of Condition 7.5 as determined by the Minister Prepare and submit portions of the relevant to the specific element or subelement that meet the objectives identified in Condition 7.4 and the requirements of Condition 7.5 as determined by the Minister Environment Protection the Minister's determination of the portions of the relevant to the element or sub-element If any portions of the related to specific elements or sub-elements (Schedule 1) is not submitted as required by Condition 7.1 All relevant elements and sub-elements listed in Schedule 1 are included in the Terrestrial and Environment Protection Revision 3 (G1-NT-PLNX ) 800:M7.3 Environment Protection The Proponent shall consult with the DEC and DEWHA in the preparation of the Consult with the DEC and DEWHA during preparation Environment Protection consultation any of the terrestrial facilities identified in Condition 6.3 Environment Protection Revision 1 (G1-NT- PLNX ) from DEWHA, dated 4 September 2009 (G1-CO-EML-DENCH-CVXPH ) from DEC, dated 8 September 2009 (G1-CO-EML-DECWH-CVXPH ) Approval letter from DEC, dated 10 September 2009 (G1-CO-LTR-DECWH- CVXPH ) Approval letter from DEWHA, dated 22 September 2009 (G1-CO-LTR-DENCH- CVXPH ), states that Revision 1 of the is approved for the purpose of Condition 6 of EPBC 2003/1294 and 2008/4178 Revision ID: 1.0 Revision Date: 25 October 2017 Page 22
23 800:M7.4 Environment Protection The objectives of the are: 1. To reduce the adverse impacts from the construction and operation of the terrestrial facilities as far as practicable; and 2. To ensure that construction and operation of the terrestrial facilities does not cause Material or Serious Harm outside the Terrestrial Disturbance Footprint, including below the surface of the land See 800:M7.1 Environment Protection any of the terrestrial facilities identified in Condition 6.3 Environment Protection Revision 3 (G1-NT- PLNX ) Approval letter from Parks and Wildlife, dated 8 May 2014 (G1-CO-LTR-DECWH-CVXPH ), states the revised document meets the objectives identified in MS 800 and MS :M7.5 Environment Protection The shall include the following: 1. measures to reduce the adverse impacts (including from light and noise) from the construction and operation of the terrestrial facilities listed in Condition 6.3 as far as practicable; and 2. measures to ensure that construction and operation of the terrestrial facilities does not cause Material or Serious Harm outside the Terrestrial Disturbance Footprint, including below the surface of the land The prepared will cover the topics listed in Condition 7.5 Environment Protection any of the terrestrial facilities identified in Condition 6.3 See 800:M :M7.6 Environment Protection The measures required by Condition 7.5(i) and (ii) shall address but not be limited to: 1. Vegetation Clearing Procedures to determine the extent of clearing and rehabilitation on an annual basis; 2. Procedures in relation to and protocols for capturing, relocating, handling, housing, caring for, and reporting to the DEC threatened or listed fauna found within the Terrestrial Disturbance Footprint that are not required by DEC for translocation; 3. Procedures to avoid secondary impacts to fauna as a consequence of risks such as animals being trapped in construction trenches or subject to vehicle strike; 4. Measures including detailed drainage and containment designs for all works and infrastructure that control stormwater run-off outside the Terrestrial Disturbance Footprint with the aim of ensuring that run-off is consistent with the pre-development run-off regime as far as practicable, and any recharge does not cause pollution; and 5. Performance Standards against which achievement of the objectives of this condition can be determined The and Procedures prepared will cover the topics listed in Condition 7.6 Environment Protection Vegetation Clearing Common User Procedure Fauna Handling and Common User Procedure Traffic Common User Procedure Minister s determination of the Procedures any of the terrestrial facilities identified in Condition 6.3 See 800:M7.4 Vegetation Clearing and Common User Procedure Revision 3 (G1-PP-HES-PRC-0012) Approval letter from Parks and Wildlife, dated 8 May 2014 (G1-CO-LTR-DECWH-CVXPH ), states that the revised procedure meets the objectives identified in MS 800 and MS 769 Traffic Common User Procedure Revision 3 (G1-PP-HES-PRC-0010) Approval letter from Parks and Wildlife, dated 8 May 2014 (G1-CO-LTR-DECWH-CVXPH ), states that the revised procedure meets the objectives identified in MS 800 and MS 769 Fauna Handling and Common User Procedure Revision 3 (G1-PP-HES-PRC- 0009) Approval letter from Parks and Wildlife, dated 8 May 2014 (G1-CO-LTR-DECWH-CVXPH ), states that the revised procedure meets the objectives identified in MS 800 and MS :M7.7 Environment Protection The Proponent shall report any Material or Serious Harm outside the Terrestrial Disturbance Footprint to the DEC and DEWHA within 48 hours of detection any Material or Serious Harm outside the Terrestrial Disturbance Footprint within reporting to Parks and Wildlife and DotE and the time frame in which this occurred after detection Overall Within 48 hours of detecting any Material or Serious Harm outside the Terrestrial No Material or Serious Harm outside the Terrestrial Disturbance Footprint occurred during the reporting period as a result of the Gorgon Gas Development; therefore, no reports were required Revision ID: 1.0 Revision Date: 25 October 2017 Page 23
24 48 hours of detection Disturbance Footprint 800:M7.8 Environment Protection The Proponent shall implement the Implement the approved Annual Assessment Overall For life of Project The Environment Protection was implemented during the reporting period Chevron Australia completed an audit of the Environment Protection during the reporting period 800:M8.1 Environment Monitoring Program the terrestrial facilities listed in Condition 6.3 the Proponent shall prepare and submit a Environment Monitoring Program (the Program) to the Minister that meets the objective set out in Condition 8.3 and the requirements of Condition 8.4 as determined by the Minister, unless otherwise allowed in Condition 8.2 Prepare and submit a Program which meets the objectives set out in Condition 8.3 and the requirements of Condition 8.4, unless otherwise allowed in Condition 8.2 Environment Monitoring Program the Minister s determination of the Program any of the terrestrial facilities identified in Condition 6.3 Environment Monitoring Program Revision 1 (G1-NT- PLNX ) Submission letter from Chevron Australia to DEC, dated 10 September 2009 (G1-CO-LTR- CVXPH-DECWH ) Approval letter from DEC, dated 10 September 2009 (G1-CO-LTR-DECWH- CVXPH ), states that Revision 1 of the Environment Monitoring Program meets the aim set out in Condition 8.3, and the requirements of Condition 8.4 and is considered to be complete for the construction phase only Letter from Chevron Australia to DEC correcting clerical errors in the submission letter, dated 8 October 2009 (G1-CO-LTR- CVXPH-DECWH ) 800:M8.2 Environment Monitoring Program In the event that any portion of the Program related to specific elements or sub-elements (Schedule 1) is not submitted as required by Condition 8.1, the Proponent shall submit the portion of the Program relevant to that element or sub-element to the Minister prior to the that element or sub-element. All portions of the Program shall meet the objective identified in Condition 8.3 and the requirements of Condition 8.4 as determined by the Minister Prepare and submit portions of the relevant to the specific element or sub-element that meet the purposes identified in Condition 8.3 and the requirements of Condition 8.4 Environment Monitoring Program the Minister s determination of the Program relevant to the element or subelement If any portion of the Program related to specific elements or subelements (Schedule 1) is not submitted as required by Condition 8.1 See 800:M :M8.3 Environment Monitoring Program The objective of this Program is to establish a statistically valid ecological monitoring program to detect any Material or Serious Harm to the ecological elements outside the Terrestrial Disturbance Footprint See 800:M8.1 Environment Monitoring Program any of the terrestrial facilities identified in Condition 6.3 Environment Monitoring Program Revision 1.0 (GOR-COP ) was updated to reflect focus on operations/transfer from construction to operations Submission letter from Chevron Australia to OEPA, dated 30 November 2015 (G1-CO- LTR-CVXPH-EPAPH ) Approval letter from OEPA to Chevron Australia, dated 31 October 2016 (G1-CO- LTR-EPAPH-CVXPH ), accepts the revision as the current version of the plan 800:M8.4 Environment Monitoring Program The Program shall include: 1. Indicators, parameters, and criteria to be used in measuring changes on the ecological elements identified in Condition 6.1 that are at risk of Material or Serious The Program prepared will cover the topics listed in Condition 8.4 Environment Monitoring Program Revision ID: 1.0 Revision Date: 25 October 2017 Page 24 any of the terrestrial See 800:M8.3
25 Harm due to construction and operation of terrestrial facilities listed in Condition 6.3; 2. Protocols for ongoing reporting of adverse changes to the ecological elements listed in Condition 6.1; 3. Triggers; 4. Protocols for identifying additional areas not originally identified that are at risk of sustaining Material or Serious Harm from the Proposal, and for adding monitoring sites to include these additional locations, if required; 5. Establishing an ecological monitoring program with the ability to detect at a statistical power of 0.8 or greater, or an alternative statistical power as determined by the Minister, any environmental harm to the ecological elements listed in Condition 6.1; 6. Location of monitoring sites in areas that are at risk of Material or Serious Harm due to construction and operation of terrestrial facilities listed in Condition 6.3; and 7. Location of reference sites (see Condition 6.4(iii) facilities identified in Condition :M8.5 Environment Monitoring Program The Proponent shall implement the Program Implement the approved Program Annual Assessment Overall For life of Project The Environment Monitoring Program was implemented during the reporting period Chevron Australia completed an audit of the Environment Monitoring Program during the reporting period Details of monitoring undertaken during the reporting period are provided in the Gorgon Gas Development and Jansz Feed Gas Pipeline: 2017 Performance (ABU ) 800:M9.1 Establishing a Quarantine Expert Panel the terrestrial facilities listed in Condition 6.3, the Proponent shall establish and provide reasonable funding to resource a Quarantine Expert Panel (QEP) to carry out the role set out in Condition 9.2 with membership as described in Condition 9.3 Establish Expert Panel by appointing members, developing terms of reference, and provide reasonable funding Panel members appointed Terms of Reference Reasonable funding provisions documented the terrestrial facilities listed in Condition 6.3 The requirement to establish a Quarantine Expert Panel (QEP) and provision of reasonable funding was fulfilled during the 2009 reporting period under MS 748. Refer to Statement No. 748 Annual 2009 (G1-NT-REPX ) from Chevron Australia to the Appeals Convenor regarding the continuation of the Expert Panels under MS 800, dated 10 August 2009 (G1-CO-EML-CVXPH-OACPH ) Letter from the Minister for Environment to Chevron Australia confirming that the Expert Panels established under MS 748 will continue to operate under MS 800, dated 10 August 2009 (G1-CO-LTR-MEYPH-CVXPH ) Gorgon Gas Development Expert Panels, Operating Guidelines (G1-NT-GDLX ) details operation, roles, membership, Revision ID: 1.0 Revision Date: 25 October 2017 Page 25
Gorgon Project. Terrestrial and Subterranean Environment Monitoring Program
Terrestrial and Subterranean Environment Monitoring Program Revision ID: 1.0 Revision Date: 31 October 2016 Next Revision Due: Contents 1.0 Introduction... 4 1.1 Proponent... 4 1.2 Project... 4 1.3 Environmental
More informationSouthern Seawater Desalination Plant Performance and Compliance Report 14 April April 2017
Southern Seawater Desalination Plant Performance and Compliance Report 14 April 2016 13 April 2017 Contents Glossary and Definition of Terms 1 1. Introduction 3 1.1 Environmental Approvals 3 1.2 Purpose
More informationAppendix A: Project Characteristics
Gorgon Fourth Train Expansion Proposal Appendix A: Project Characteristics Appendices Project Characteristics A Key Characteristics table has been prepared to describe the elements of the Foundation Project
More informationEnvironmental Impact Assessment in Western Australia
Environmental Impact Assessment in Western Australia Fact Sheet Updated February 2011 An introduction to Environmental Impact Assessment in Western Australia Environmental impact assessment under the Environmental
More informationDBNGP Stage 5 Looping Expansion Project
DBNGP Stage 5 Looping Expansion Project 2013 Annual Environmental Compliance Report (Statement No. 735) Prepared for DBNGP (WA) Nominees Pty Ltd by Strategen March 2014 DBNGP Stage 5 Looping Expansion
More informationGorgon Gas Development and Jansz Feed Gas Pipeline:
Gorgon Gas Development and Jansz Feed Gas Pipeline: Document No: G1-NT-PLNX0000012 Copy No: IP Security: Public Chevron Australia Pty Ltd Document No: G1-NT-PLNX0000012 Gorgon Gas Development and Jansz
More informationSection 4 Environmental Impact Assessment Framework
Section 4 Environmental Impact Assessment Framework 4. ENVIRONMENTAL IMPACT ASSESSMENT FRAMEWORK 4.1 Environmental Impact Assessment in Western Australia The overall framework for EIA in WA is described
More informationThe challenges and complexities of impact assessment for a seismic survey in a remote coral reef environment
The challenges and complexities of impact assessment for a seismic survey in a remote coral reef environment J.G. Colman 1,2, C.C. Grebe 1 & R.L. Hearn 1 1 Woodside Energy Ltd (cameron.grebe@woodside.com.au,
More informationGUIDELINE. environmental management of mining. GUIDELINE 11 - Terms of Reference and Preparation of an Environmental Impact. Statement.
GUIDELINE environmental management of mining GUIDELINE 11 - Terms of Reference and Preparation of an Environmental Impact Statement Content: 1 Introduction 2 Background 3 Objectives page 1 page 1 page
More informationAppendix General Environmental Risk Analysis
Proposed Solar Power Station Near Moree, NSW (MOREE SOLAR FARM) Appendix Prepared by BP Solar & Walsh Consulting January 011 Background The body of the identifies all significant environmental risks identified
More informationCORPORATE GOVERNANCE. as at 12 September Lycopodium Limited ABN: Level 5, 1 Adelaide Terrace, East Perth Western Australia 6004
CORPORATE GOVERNANCE as at 12 September 2016 This document is the property of. It must not be copied or reproduced in any way or transmitted on to any third party without written authority from. ABN: 83
More informationInformation on the focal point for the Convention. Information on the point of contact for the Convention
Questionnaire for the REPORT OF MONTENEGRO ON THE IMPLEMENTATION OF THE CONVENTION ON ENVIRONMENTAL IMPACT ASSESSMENT IN A TRANSBOUNDARY CONTEXT in the period 2006 2009 Information on the focal point for
More informationDBNGP Stage 5 Expansionn Looping Project
DBNGP Stage 5 Expansionn Looping Project DBPL00-501-0722-01 n Environmental Management Plan CONTROLLED VERSION 2 401012-00624 17 August 2011 > Title: DBPL00-501-0722-01
More informationALBANY PORT EXPANSION PROJECT
ALBANY PORT EXPANSION PROJECT Report No.3 Ministerial Statement 846 April 2015 1 ALBANY PORT EXPANSION PROJECT COMPLIANCE ASSESSMENT REPORT No.3 FOR THE PERIOD OF 1 st MAY 2014 30 th APRIL 2015 Ministerial
More informationSouth Walker Creek Mine Mulgrave Pit Extension EPBC 2014/7272 Compliance Report 30 March March 2017
South Walker Creek Mine Mulgrave Pit Extension EPBC 2014/7272 Compliance Report 30 March 2016 30 March 2017 27 June 2017 BHP Introduction Contents Introduction 1 Description of activities 2 Compliance
More information6 Risk assessment methodology
Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management
More informationGUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08
CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Manager Environment Approved: Executive General Manager Asset Strategy DOCUMENT HISTORY Date
More informationChevron Australasia Overview
Chevron Australasia Overview Roy Krzywosinski, Managing Director June 2011 Cautionary Statement CAUTIONARY STATEMENTS RELEVANT TO FORWARD-LOOKING INFORMATION FOR THE PURPOSE OF SAFE HARBOR PROVISIONS OF
More informationSubmission September Office of the Environmental Protection Authority. Contact Kane Moyle Manager Environment & Land Access
Submission September 2014 Review of EPA Environmental Assessment Guidelines 8 (Environmental Factors and Objectives) and 9 (Application of a Significance Framework in the Environmental Impact Assessment
More informationBluewaters Power 1 Pty Ltd
Bluewaters Power 1 Pty Ltd Electricity Generation Licence (EGL 4) 2014 Performance Audit (Independent Assurance) Report June 2014 Deloitte Touche Tohmatsu ABN 74 490 121 060 Woodside Plaza Level 14 240
More informationNational Railway Museum
1 of 8 pages National Railway Museum Charter for the Board and Board committees of the Port Dock Station Railway Museum (SA) Inc., trading as National Railway Museum The purpose of this charter is to articulate
More informationPILBARA LEAF-NOSED BAT MONITORING PROGRAM
PILBARA LEAF-NOSED BAT MONITORING PROGRAM 1. Introduction Atlas Iron Limited (Atlas) has sought approval to develop their Mt Dove Direct Shipping Ore (DSO) Project (the Project) located in the Pilbara
More informationANZ Audit Committee Charter
ANZ Audit Committee Charter Contents 1. Standing Rules for ANZ Board Committees 2. Purpose 3. Powers of the Audit Committee 4. Function of Respective Parties 5. Duties of the Audit Committee 6. Eligibility
More informationThis is a working draft report provided for information purposes only, and may be modified prior to finalisation. It has been prepared on the basis
This is a working draft report provided for information purposes only, and may be modified prior to finalisation. It has been prepared on the basis of the design and engineering work as part of the feasibility
More informationPollution & Environmental Harm
Pollution & Environmental Harm Fact Sheet 27 Updated December 2010 An introduction to Pollution and Environmental Harm There are a large range of activities that can lead to pollution or cause environmental
More informationOPTUS SUPPLIER WORK HEALTH & SAFETY POLICY
OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY 1. Introduction 1.1 SCOPE & PURPOSE This policy (which includes this document and the work health and safety standards, policies, procedures and safety control
More informationGorgon Project Update: Selected Images
Gorgon Project Update: Selected Images September 25, 2012 Plant Site Construction of the liquefied natural gas (LNG) plant is progressing well. Once complete, the plant will comprise three trains capable
More informationTECHNICAL GOVERNANCE AND ADVISORY STRUCTURES FOR THE STANDARDS DEVELOPMENT PROCESS
STANDARDISATION GUIDE 005: TECHNICAL GOVERNANCE AND ADVISORY STRUCTURES FOR THE STANDARDS DEVELOPMENT PROCESS COPYRIGHT Standards Australia Limited ABN: 85 087 326690 All rights are reserved. No part of
More informationMARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT
MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT The health of the world s oceans and marine life is degrading rapidly as a result of excess human activities.
More informationSection 3.19 Indigenous Cultural Heritage
Section 3.19 Indigenous Cultural Heritage Terminal 0 Environmental Impact Statement Abbot Point Coal Terminal 0 EIS Adani 3.19 Indigenous Cultural Heritage In accordance with the Project guidelines, the
More informationEmployment of Fixed-Term Staff Policy. University-wide. Staff Only Students Only Staff and Students. Vice Chancellor
Name of Policy Description of Policy Employment of Fixed-Term Staff Policy This policy covers the arrangements for the employment for fixedterm contract staff members at the University. University-wide
More informationSection 75J of the Environmental Planning & Assessment Act 1979
Project Approval Section 75J of the Environmental Planning & Assessment Act 1979 I approve the project application referred to in schedule 1, subject to the conditions in schedule 2. These conditions are
More informationNSW Heritage Law. Planning, Development & Heritage. Overview. Last updated: August 2012
Planning, Development & Heritage NSW Heritage Law Last updated: August 2012 These Fact Sheets are a guide only and are no substitute for legal advice. To request free initial legal advice on an environmental
More informationRISK AND AUDIT COMMITTEE TERMS OF REFERENCE
RISK AND AUDIT COMMITTEE TERMS OF REFERENCE Brief description Defines the Terms of Reference for the Risk and Audit Committee. BHP Billiton Limited & BHP Billiton Plc BHP Billiton Limited & BHP Billiton
More informationWI-ENV-PER-0013 GROUND DISTURBANCE PERMIT
WI-ENV-PER-0013 GROUND DISTURBANCE PERMIT PERMIT NUMBER PERMIT NAME DATE RECEIVED PERMIT APPROVAL DATE PERMIT EXPIRY DATE GDP- (Office use only) This Ground Disturbance Permit (GDP) is to be completed
More informationChevron Australia Overview
Chevron Australia Overview Roy Krzywosinski, Managing Director Chevron Australia June 2012 Safe Harbor Language CAUTIONARY STATEMENTS RELEVANT TO FORWARD-LOOKING INFORMATION FOR THE PURPOSE OF SAFE HARBOR
More informationAudit report VET Quality Framework
The QCAA uses an exceptions-based model of reporting. This means that the QCAA will only record a comprehensive description of evidence gathered and compliance findings if noncompliance is identified at
More informationChapter 4 Planning and statutory requirements. Chapter 4 Planning and statutory requirements
Chapter 4 Planning and statutory requirements Chapter 4 Planning and statutory requirements Contents Page number 4. Planning and statutory requirements 4-1 4.1 Approval under the EPBC Act 4-1 4.1.1 Controlled
More informationABUE-450-EN-R01-C-00009
Australia Pacific LNG Project Environment Protection and Biodiversity Conservation Act 1999 Approval EPBC 2009/4977 Annual Environmental Return 21 February 2016-20 February 2017 ABUE-450-EN-R01-C-00009
More informationANNUAL ENVIRONMENTAL MANAGEMENT REPORT
ORICA KURRI KURRI ANNUAL ENVIRONMENTAL MANAGEMENT REPORT JULY 2011 Revision Date Description Author Approver 0 25/07/2011 2011 Annual Environmental Report K Millard Environmental Advisor N Davies Project
More informationLandslip remediation works at Humphery Binjour Road, Gayndah, Queensland
Landslip remediation works at Humphery Binjour Road, Gayndah, Queensland EPBC 2013/6893 Decision of Approval, Australian Government, Department of Environment WICL14184614 Clearing permit, Queensland Government,
More informationClifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary
Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until 2035 Non Technical Summary SLR Consulting Limited Project Ref: 403.00079.00474
More informationPART A INTRODUCTION TO THE AEIS 1. PURPOSE OF THE ADDITIONAL
PART A INTRODUCTION TO THE AEIS 1. PURPOSE OF THE ADDITIONAL information to the environmental impact statement 1 1.1. Consultation process since release of the EIS 1 2. ANALYSIS OF SUBMISSIONS 4 2.1. Number
More informationRelevant legislation (Administering Authority Commonwealth legislation
Commonwealth legislation Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) [Commonwealth Department of Sustainability, Environment, Water, Population and Communities (SEWPaC)] New
More informationSantos GLNG Gas Transmission Pipeline
Santos GLNG Gas Transmission Pipeline EPBC No. 2008/4096 Gas Transmission Pipeline Document Number: UNCONTROLLED IF PRINTED Table of Contents 1 INTRODUCTION... 1 2 COMPLIANCE WITH CONDITIONS CONDITION
More informationUranium mining legal and regulatory framework
South Australia s Environment Protection Authority Uranium mining legal and regulatory framework An Australian perspective Keith Baldry Director Mining Radiation and Regulatory Support IAEA Seminar on
More informationCOMMUNITY OVERVIEW MARCH Overburden Management Project Environmental Impact Statement (EIS)
COMMUNITY OVERVIEW MARCH 2017 Overburden Management Project Environmental Impact Statement (EIS) About McArthur River Mine McArthur River Mining Pty Ltd (MRM) is wholly owned by Glencore and is the operator
More informationAdvice to decision maker on coal mining project
. Advice to decision maker on coal mining project IESC 2015-063: West Muswellbrook Project New Development Requesting agency The New South Wales Mining and Petroleum Gateway Panel Date of request 27 January
More informationArrow Energy. Surat development update. December 2017
Surat development update December 2017 Why we are here today Arrow has agreed one of the largest gas supply deals on Australia s east coast: - 27-year deal between Arrow and QCLNG to commercialise the
More informationAIA Group Limited. Terms of Reference for the Audit Committee. AIA Restricted and Proprietary Information
AIA Group Limited Terms of Reference for the Audit Committee AIA Restricted and Proprietary Information Issued by : Board of AIA Group Limited Date : 27 July 2016 Version : 4.0 Definitions 1. For the purposes
More informationLooking After Our Environment
Item: 12.06 Subject: DRAFT BIODIVERSITY CERTIFICATION ASSESSMENT AND APPLICATION - PORT MACQUARIE AIRPORT AND SURROUNDING LAND Presented by: Development and Environment Services, Matt Rogers Alignment
More informationCaval Ridge Mine Change Request 8 Accommodation Village Condition Changes
Caval Ridge Mine Change Request 8 Accommodation Village Condition Changes 31 May 2013 Contents Executive Summary... 3 1 Introduction... 5 1.1 Project Background... 6 1.1.1 Bowen Basin Coal Growth Project...
More informationProtection of Ramsar Wetlands under the EPBC Act
Protection of Ramsar Wetlands under the EPBC Act 1. INTRODUCTION The Commonwealth Environmental Protection and Biodiversity Conservation Act 1999 (the EPBC Act ) commenced on 16 July 2000 and brought about
More informationEWA ENVIRONMENTAL AFFAIRS
326 National Environmental Management Act (107/1998): Amendments to the Environmental Impact Assessment Regulations, 2014 40772 STAATSKOERANT, 7 APRIL 2017 No. 40772 211 DEPARTMENT OF ENVIRONMENTAL AFFAIRS
More informationCOMMITTEE FOR PROPRIETARY MEDICINAL PRODUCTS (CPMP) POSITION PAPER ON COMPLIANCE WITH PHARMACOVIGILANCE REGULATORY OBLIGATIONS
The European Agency for the Evaluation of Medicinal Products Evaluation of Medicines for Human Use London, 15 November 2001 COMMITTEE FOR PROPRIETARY MEDICINAL PRODUCTS (CPMP) POSITION PAPER ON COMPLIANCE
More informationProtection of World Heritage Properties under the EPBC Act
Protection of World Heritage Properties under the EPBC Act 1. INTRODUCTION The Commonwealth Environmental Protection and Biodiversity Conservation Act 1999 (the EPBC Act ) commenced on 16 July 2000 and
More informationCOAL AND COAL SEAM GAS REGULATION
COAL AND COAL SEAM GAS REGULATION The Australian Government protects water resources from the impacts of coal and coal seam gas development through the water trigger provisions of the Environment Protection
More informationThe anglo american Safety way. Safety Management System Standards
The anglo american Safety way Safety Management System Standards 2 The Anglo American Safety Way CONTENTS Introduction 04 Anglo American Safety Framework 05 Safety in anglo american 06 Monitoring and review
More informationClimate Change and Renewable Energy Bill 2017*
Queensland Climate Change and Renewable Energy Bill 2017* Current DRAFT as at 24 November 2017 *Material in this draft Bill has been excerpted from the Climate Change Act 2017 (Vic) and the Climate Change
More informationWheatstone Project. Construction Onshore Facilities Waste Water Discharge Plan
Wheatstone Project Construction Onshore Facilities Waste Water Discharge Plan Document No: WS0-0000-HES-PLN-CVX-000-00096-000 Revision: 4 IP Security: Public Chevron Australia Pty Ltd Construction Onshore
More informationConsultation Regulatory Impact Statement
Consultation Regulatory Impact Statement Post Implementation Review of the Industry Levy to fund the petroleum and gas water functions of the Office of Groundwater Impact Assessment December 2016 This
More informationRECORD KEEPING RULES ON INITIAL REPORTS RELATING TO ACCOUNTING SEPARATION
RECORD KEEPING RULES ON INITIAL REPORTS RELATING TO ACCOUNTING SEPARATION OVERVIEW Accounting Separation of Telstra Record Keeping Rules On 24 September 2002 the Minister for Communications, Information
More informationPORT OF PORT HEDLAND - BULK PRODUCT MANAGEMENT PROCEDURE
TABLE OF CONTENTS 1. PURPOSE... 2 2. SCOPE... 2 3. RESPONSIBILITIES... 2 4. SPECIFICATION OF BULK MINERAL PRODUCTS... 3 4.1 PROVISION OF ONGOING INFORMATION...4 4.2 SAMPLING...5 4.3 PRODUCT DEM AND MOISTURE
More informationCorporate Governance Statement
58 PROGRAMMED 2015 ANNUAL REPORT Corporate Governance Statement Programmed is committed to ensuring that its obligations and responsibilities to its various stakeholders are fulfilled through appropriate
More informationEnvironmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores
Environmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores October 2015 Environmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores WaterNSW on behalf of the NSW Government
More informationTUV SUD BABT PRODUCTION QUALITY CERTIFICATION SCHEME
TUV SUD BABT PRODUCTION QUALITY CERTIFICATION SCHEME Copyright TUV SUD BABT 2017 A Certification Body of: Page 1 of 33 Contents AMENDMENT RECORD 3 0. INTRODUCTION 3 1. PRE-CONDITIONS TO SUPPORT PRODUCTION
More informationGUIDELINES FOR. Mine Closure. Planning. in Queensland
GUIDELINES FOR Mine Closure Planning in Queensland Preface The Queensland Mining Council (QMC) is the peak representative organisation of the Queensland minerals industry. The council's membership encompasses
More informationTechnical Guidance Document for Operational Environmental Management Plan (OEMP)
Technical Guidance Document for Operational Environmental Management Plan (OEMP) EAD-EQ-PCE-TG-06 Signature on Original Environment Quality Sector * Corporate Management Representative Secretary General
More informationChatswood to Sydenham CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK
Chatswood to Sydenham CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK Contents 1 Introduction... 1 1.1 Purpose and Scope... 1 1.2 Status... 1 1.3 Environment and Sustainability Policy... 1 1.4 Project
More informationReport for Agenda Item: 2
QLDC Council 28 September 2017 Department: Planning & Development Report for Agenda Item: 2 Stage 2 Proposed District Plan Notification Purpose The purpose of this paper is to present those parts of Stage
More informationSouthern Seawater Desalination Plant. Marine Environmental Monitoring Interim Report 19 July October 2015
Southern Seawater Desalination Plant Marine Environmental Monitoring Interim Report Executive Summary The Southern Seawater Desalination Plant (SSDP) is located on Taranto Road, Binningup. Stage 1 of the
More informationCONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK
CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK APPENDIX D Contents 1 Introduction... 1 1.1 Purpose and Scope... 1 1.2 Status... 1 1.3 Environment and Sustainability Policy... 1 1.4 Project Description...
More informationPT Mandom Indonesia Tbk GCG
REGULATION OF THE INTERNAL AUDIT DEPARTMENT Chapter I GENERAL PROVISIONS Article 1 Purpose The purpose of this regulation is to serve the function of internal control for the company s activities with
More informationCertificate of Recognition (COR ) COR Program Guidelines. Infrastructure Health & Safety Association (IHSA) 05/17 1
Certificate of Recognition (COR ) COR Program Guidelines Infrastructure Health & Safety Association (IHSA) 05/17 1 Table of Contents Contents Page 1. Program Guideline Overview... 4 1.1 Scope... 4 1.2
More informationTechnical Guidance Document for Environmental Audit Reports
Technical Guidance Document for Environmental Audit Reports EAD-EQ-PCE-TG-10 Signature on Original Environment Quality Sector * Corporate Management Representative Secretary General Originated By Reviewed
More informationTruckSafe Operator Business Rules and Code of Conduct
Operator Business Rules and Code of Conduct Contents 1.0 Business Rules and Code of Conduct 3 2.0 Decision Making Bodies 4-6 3.0 Purpose 6 4.0 How the Rules will be amended 6 5.0 Introduction 6 6.0 Entry
More informationNumber 42 of 2001 YOUTH WORK ACT 2001 REVISED. Updated to 4 June 2014
Number 42 of 2001 YOUTH WORK ACT 2001 REVISED Updated to 4 June 2014 This Revised Act is an administrative consolidation of the. It is prepared by the Law Reform Commission in accordance with its function
More informationNational Centre for First Nations Governance CONSULTATION FACT SHEET 2
National Centre for First Nations Governance CONSULTATION FACT SHEET 2 CONSULTATION PROCEDURES/STEPS DEFINITION: Consultation procedures refer to the series of steps that need to be taken to accomplish
More informationThis is a working draft report provided for information purposes only, and may be modified prior to finalisation. It has been prepared on the basis
This is a working draft report provided for information purposes only, and may be modified prior to finalisation. It has been prepared on the basis of the design and engineering work as part of the feasibility
More informationQuality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17
Quality Manual DRAFT Page 1 of 17 Document Acceptance and Release Notice This is Revision A1 of the East Coast Designer Builders Quality Manual. The Manual is a managed document. For identification of
More informationWalkaway Wind Power Pty Ltd
Final For 2008 Performance Audit and Asset Management System Review Electricity Generation Licence EGL2 Audit Period 27 th January 2006 to 31 st January 2008 Audit Plan Authorisation Name Position Date
More informationCGIAR System Management Board Audit and Risk Committee Terms of Reference
Approved (Decision SMB/M4/DP4): 17 December 2016 CGIAR System Management Board Audit and Risk Committee Terms of Reference A. Purpose 1. The purpose of the Audit and Risk Committee ( ARC ) of the System
More informationPROVINCE OF BRITISH COLUMBIA REGULATION OF THE MINISTER OF ENVIRONMENT AND CLIMATE CHANGE STRATEGY. Environmental Management Act M328
PROVINCE OF BRITISH COLUMBIA REGULATION OF THE MINISTER OF ENVIRONMENT AND CLIMATE CHANGE STRATEGY Environmental Management Act Ministerial Order No. M328 I, George Heyman, Minister of Environment and
More informationClimate Change and Renewable Energy Bill 2017*
Queensland Climate Change and Renewable Energy Bill 2017* Current DRAFT as at 22 December 2017 *Material in this draft Bill has been excerpted from the Climate Change Act 2017 (Vic) and the Climate Change
More informationPOSTNL N.V. AUDIT COMMITTEE OF THE SUPERVISORY BOARD TERMS OF REFERENCE. Adopted by the Supervisory Board on 3 November 2017
POSTNL N.V. AUDIT COMMITTEE OF THE SUPERVISORY BOARD TERMS OF REFERENCE Adopted by the Supervisory Board on 3 November 2017 Introduction These Terms of Reference are established by the Supervisory Board
More informationIntermaritime Certification Services (ICS) QUALITY MANAGEMENT SYSTEM INSTRUCTIVE FOR ISM-CODE
1.0 TITLE: 2.0 OBJECTIVES This Instructive reflect, as applicable, the IMO Resolution A.1022 (26) "Guidelines on the Implementation of the ISM-Code by Administrations" and the IMO Resolution A.741 (18)
More informationAbu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)
Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) EHS Regulatory Instrument Code of Practice EHS RI - CoP 53.0 EHS Management During Construction Work Version 2.0 February 2012 ACKNOWLEDGEMENTS With gratitude
More informationGuidance Document. Guidance for Risk Management Programme (RMP) Template for Dairy Processors. Liquid Milk, Domestic Supply.
Guidance Document Guidance for Risk Management Programme (RMP) Template for Dairy Processors Liquid Milk, Domestic Supply 30 October 2015 A guidance document issued by the Ministry for Primary Industries
More informationPORT OF THURSDAY ISLAND PORT RULES
PORT OF THURSDAY ISLAND PORT RULES Far North Queensland Ports Corporation Limited ABN: 38 657 722 043 ACN: 131 836 014 PO Box 594 CAIRNS QLD 4870 Telephone: 07 4052 3888 INTRODUCTION DEFINITIONS "Act"
More informationIAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities
DS447 Date: 20 February 2015 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: SPESS STEP 12 For submission to CSS Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle
More informationIAP the road forward // Intelligent Access Program Overview Guideline
IAP the road forward // Intelligent Access Program Overview Guideline IAP the road forward // Intelligent Access Program Overview Guideline TCA-G01-2.00 First published November 2005 Transport Certification
More informationTechnical Guidance Document for Strategic Environmental Assessment (SEA)
Technical Guidance Document for Strategic Environmental Assessment (SEA) EAD-EQ-PCE-TG-03 Signature on Original Environment Quality Sector * Corporate Management Representative Secretary General Originated
More informationE37. Genetically modified organisms [CIV : Federated Farmers of New Zealand Incorporated]
E37. Genetically modified organisms [CIV-2016-404-002299: Federated Farmers of New Zealand Incorporated] E37.1. Background The outdoor use of genetically modified organisms has the potential to cause adverse
More informationInternal Audit Charter. (Board approved 13 April 2012)
Charter (Board approved 13 April 2012) Table of Contents 1. Introduction... 3 2. Objectives... 3 3. Role... 3 4. Scope of Role... 4 5. Responsibility... 4 6. Independence... 5 7. Access and Confidentiality...
More informationQuality, Audit and Risk Committee Charter
Quality, Audit and Risk Committee (A Committee of University Council) Quality, Audit and Risk Committee Charter This Charter is established under the authority of the Council of Edith Cowan University.
More informationPart 148. CAA Consolidation. 10 March Aircraft Manufacturing Organisations - Certification
Part 148 CAA Consolidation 10 March 2017 Aircraft Manufacturing Organisations - Certification Published by the Civil Aviation Authority of New Zealand DESCRIPTION Part 148 prescribes rules governing the
More informationCOMPLAINT MANAGEMENT POLICY
COMPLAINT MANAGEMENT POLICY DISCLAIMER No part of this publication may be stored in a retrieval system, transmitted, or reproduced in any way, including but not limited to photocopy, photograph, magnetic
More informationASSESSING THE CUMULATIVE EFFECTS OF MINING ON GROUNDWATER AND CONNECTED SYSTEMS
ASSESSING THE CUMULATIVE EFFECTS OF MINING ON GROUNDWATER AND CONNECTED SYSTEMS Author/s: Chris Moran 1, Paul Howe 2, Sue Vink 1, Alana Horan 2, Greg Hoxley 2 Affiliations: 1 Sustainable Minerals Institute,
More informationTEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT
TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT Final Scoping Report - Non-Technical Summary Presentation Structure of the Presentation Introduction to the Tema LNG Project
More informationAircraft Manufacturing Organisations Certification
Civil Aviation Rules Part 148, Amendment 4 Docket 8/CAR/1 Contents Rule objective... 3 Extent of consultation... 3 Summary of submissions... 3 Examination of submissions... 4 Insertion of Amendments...
More information