SWPPP Development. What are Storm Water Pollution Prevention Plans. Jerald S. Fifield, Ph.D., CISEC HydroDynamics Incorporated Parker, CO

Size: px
Start display at page:

Download "SWPPP Development. What are Storm Water Pollution Prevention Plans. Jerald S. Fifield, Ph.D., CISEC HydroDynamics Incorporated Parker, CO"

Transcription

1 What are Storm Water Pollution Prevention Plans S&EC PLANS (DRAWINGS) PROJECT SITE NARRATIVE Jerald S. Fifield, Ph.D., CISEC HydroDynamics Incorporated Parker, CO SWPPP SWPPP Development Section 7 of (Hawaii Administrative Rules) HAR-55-C Requirement Develop prior to submitting the Notice of Intent (NOI) Contents Narrative Drawings 1

2 What does the acronym NPDES mean? 1. National Pollution Discharge Environmental 2. National Pollutant Discharge Elimination 3. National Pollution Discharge Elimination 4. National Pollutant Discharge Environmental Updates will occur by December 6, 2018 based upon the 2017 Construction General Permit (CGP) disturbance 1.0-acre disturbance < 1.0-acre when part of a larger development A permit is required to discharge stormwater Updates will occur by December 6, 2018 based upon the 2017 Construction General Permit (CGP) disturbance 1.0-acre disturbance < 1.0-acre when part of a larger development A permit is required to discharge stormwater General Permit Does not Address Discharges in or to state waters classified by the department as "class 1, Inland Waters," "class AA, Marine Waters," and areas restricted in accordance with the State's "No Discharge" policy in chapter entitled "Water Quality Standards." 2

3 What is Chapter (Water Quality Standards)? Limitations on Permit Does not cover storm water discharges From construction sites Flowing into a sanitary sewer system Containing Flocculants and other treatment chemicals Entering a separate storm water drainage system unless Written approval is granted Permittee is the owner From 404 Permitted areas From clearing of agricultural lands Which the (EPA) director Has issued through another general permit Finds should be under an individual permit From new sources that cause or contribute to the departure of any applicable water quality standard Area of Disturbance The permittee is required to minimize the amount of soil exposed during construction activities. The permittee is also subject to the deadlines for temporarily and/or permanently stabilizing exposed portions of the site pursuant to section Stabilization If permanent Immediately Complete as soon as practical but no later than the end of the next day If temporary for 14 or more days Immediately Completion by 14 calendar days after initiation of soil stabilization measures 3

4 Area of Disturbance The permittee is required to minimize the amount of soil exposed during construction activities. The permittee is also subject to the deadlines for temporarily and/or permanently stabilizing exposed portions of the site pursuant to section 5.2. What is in the 2017 CGP? Cumulative earth disturbances cannot exceed 5 acres Land disturbance 5 acres If permanent or to be temporary for 14+ days, initiate immediately Complete ASAP or by 14 days Land disturbance > 5 acres If permanent or to be temporary for 14+ days, initiate immediately Complete ASAP or by 7 days Final Stabilization Criteria Uniform, perennial vegetation provides 70 percent or more of the native cover Non-vegetative stabilization measures provide effective cover Design Permittee shall account for: Identifying expected amount, frequency, intensity and duration of precipitation East side is humid/tropical West side is semi-arid Months of higher risks of being impacted by rainfall Months of lower risks of being impacted by rainfall Months of higher risks of being impacted by rainfall Design Permittee shall account for: Identifying expected amount, frequency, intensity and duration of precipitation Identifying the nature of storm water runoff and run-on Impervious surfaces, slopes and site drainage features Identify the range of site soil particles sizes Understand the type of soils that exist Discharge storm water onto vegetative areas Installation Permittee shall be responsible for Installing BMPs prior to earth-disturbance activities Installing BMPs in a correct manner Inspecting and maintaining BMPs Installing new BMPs as needed 4

5 Applicable to all Sites Provide natural buffers and sediment control Section State waters are within 50 feet of site Install perimeter controls Section Sediment control Non-Linear Project: Downstream of disturbed areas Linear Project: Where practicable and document in SWPPP Maintenance Remove sediment before 50% of barrier height Minimize sediment track-out Section Restrict vehicle traffic to designated exit points Sediment removal before exit onto paved roads Track-out removed by end of same work day or End of next work day if occurs during non-working hours Stockpiles Section Separate from storm water controls Protect from storm water flows (including run-on) Where practical, provide cover or temporary stabilization No discharge into any stormwater conveyance system Unless into a sediment containment system Minimize dust Section Apply water or use other Minimize disturbance of steep slopes Section % or steeper Preserve topsoil Section Permittee shall preserve Minimize soil compaction Section Final vegetation stabilization or infiltration Restrict vehicle and equipment use Use soil conditioning techniques Planting Protect storm drain inlets Section

6 Contaminated soil and/or stockpiles Section Prevent storm water from contacting Prevent the discharge of stormwater runoff Prevent: keep (something) from happening or arising Storm water cannot be in contact with contaminated soil or stockpile Storm water cannot discharge from the site Templet from EPA 6

7 In Summary, Development of a SWPPP Requires Documentation Permits Site conditions Other reports Assessing soils and hydrologic conditions Knowing limitations of BMPs Developing and adhering to time schedules Having and applying common sense Possessing political savvy Jerald S. Fifield, Ph.D., CISEC HydroDynamics Incorporated Parker, CO

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department

More information

Nevada Department of Transportation (NDOT)

Nevada Department of Transportation (NDOT) Nevada Department of Transportation (NDOT) Stormwater Pollution Prevention Plan (SWPPP) Template for Construction Activities NDOT STORMWATER COMPLIANCE & ENFORCEMENT Table of Contents Page # STORM WATER

More information

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS 8.1 INTRODUCTION To minimize the detrimental effects of erosion and sedimentation, Henrico County requires that those individuals responsible for

More information

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants

More information

WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR

WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR All the documents shown today are in the MN Stormwater Manual on the page titled 2018 Construction Stormwater Permit Public Notice and Public Informational

More information

Construction site inspections are conducted for all projects that receive an approved site plan and proceed to construction.

Construction site inspections are conducted for all projects that receive an approved site plan and proceed to construction. Standard Operating Procedures for implementation of the Stormwater, Erosion and Sedimentation Inspection Program for Construction Sites Discharging Stormwater to the MS4 Construction site inspections are

More information

FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES

FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES 1. COVERAGE UNDER THIS GENERAL PERMIT Area of Coverage: This permit covers all areas of the Commonwealth

More information

LOUISIANA URBAN STORMWATER COALITION. EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum

LOUISIANA URBAN STORMWATER COALITION. EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum LOUISIANA URBAN STORMWATER COALITION EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum SWPPP NOTIFICATION SIGN Post sign at entrance of site or areas where the public can easily access.

More information

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies.

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

Stormwater Construction General Permit CGP-2013

Stormwater Construction General Permit CGP-2013 Stormwater Construction General Permit CGP-2013 Stormwater Construction General Permit (CGP) Stormwater Outreach for Regional Municipalities MS4 Statewide Summit June 18, 2013 Prepared by Chris Henninger

More information

Elements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP)

Elements of the Storm Water Management Plan. Storm Water Pollution Prevention Plan (SWPPP) Elements of the Storm Water Management Plan Storm Water Pollution Prevention Plan (SWPPP) Small Construction Site Storm Water Management Rodney Hendrick Water Quality Specialist LSU Ag Center Plan Requirements

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY

STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY STATE OF COLORADO GENERAL PERMIT APPLICATION Updated 11/04 STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY This application is for use by all stormwater dischargers engaged in construction

More information

ANCHORAGE STORMWATER MANUAL

ANCHORAGE STORMWATER MANUAL ANCHORAGE STORMWATER MANUAL Volume 2 Construction Practices (Stormwater Treatment Plan Review Guidance Manual) Version 1.0 DRAFT July 2017 This page intentionally left blank July 2017 TABLE OF CONTENTS

More information

General Permit No.: OHR Page 53 of 146

General Permit No.: OHR Page 53 of 146 Page 53 of 146 Part 8 Sector-Specific Requirements for Industrial Activity Subpart J Sector J Non-Metallic Mineral Mining and Dressing. You shall comply with Part 8 sector-specific requirements associated

More information

Module 4 Regulatory requirements for Land Disturbing Activities

Module 4 Regulatory requirements for Land Disturbing Activities Module 4 Regulatory requirements for Land Disturbing Activities MODULE 4 REGULATORY REQUIREMENTS FOR A LDA Module 4a Overview MODULE 4A REGULATORY REQUIREMENTS FOR A LDA ESC Regulations Overview 1990 First

More information

SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY

SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY 1. PURPOSE: SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY The purpose of this policy is to establish procedures to facilitate compliance with federal, state and local stormwater regulations

More information

Richland County Department of Public Works Engineering (Land Development) Division

Richland County Department of Public Works Engineering (Land Development) Division Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or

More information

Module 1: Construction Site Erosion Control

Module 1: Construction Site Erosion Control Module 1: Construction Site Erosion Control Problems and Regulations Robert Pitt Department of Civil and Environmental Engineering University of Alabama Tuscaloosa, AL Problems Associated with Erosion

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Review of State and Federal Stormwater Regulations November 2007

Review of State and Federal Stormwater Regulations November 2007 Review of State and Federal Stormwater Regulations November 2007 By: James T. Spaulding, PE, CPESC Joseph M. Ducharme, Jr., PE TTG ENVIRONMENTAL CONSULTANTS, LLC 27 LOCKE ROAD, CONCORD, NH 03301-5301 TELEPHONE:

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

Small Site Stormwater Quality Permit Application

Small Site Stormwater Quality Permit Application Small Site Stormwater Quality Permit Application PUBLIC WORKS ADMINISTRATION BUILDING (PWA) STORMWATER DIVISION 2525 WEST FIRST STREET LOVELAND, CO 80537 GENERAL INFORMATION (970) 962-2772 www.cityofloveland.org/stormwater

More information

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL 901.1 DESCRIPTION Install, maintain and remove temporary erosion and pollution control devices as required during the construction of the project. BID

More information

Checklist for 2013 Draft NH Small MS4 General Permit Requirements

Checklist for 2013 Draft NH Small MS4 General Permit Requirements Checklist for 2013 Draft NH Small MS4 General Permit Requirements TASK DEADLINE (in relation to permit effective date) OVERLAPS WITH AOC REQUIREMENTS ASSISTANCE FROM WISE PROJECT 1. Submit Notice of Intent

More information

City of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017

City of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017 City of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017 Why is Water Quality Important? Water has always been important to Minnesota and is a key part of our history, culture, economy

More information

SECTION 17.1 STORMWATER MANAGEMENT AND EROSION CONTROL

SECTION 17.1 STORMWATER MANAGEMENT AND EROSION CONTROL SECTION 17.1 STORMWATER MANAGEMENT AND EROSION CONTROL Subdivision 1: Purpose Subdivision 2: Scope Subdivision 3: Definitions Subdivision 4: Permit Application and Plan Subdivision 5: Stormwater Pollution

More information

CHAPTER 9 EROSION AND SEDIMENT CONTROL DESIGN

CHAPTER 9 EROSION AND SEDIMENT CONTROL DESIGN CHAPTER 9 EROSION AND SEDIMENT CONTROL DESIGN Chapter Organization 9.1 Purpose... 9-1 9.2 Applicability... 9-1 9.2.1 Exemptions... 9-2 9.3 Design Criteria... 9-3 9.4 Erosion and Sediment Control (ESC)

More information

SACHSE EROSION CONTROL GUIDELINES

SACHSE EROSION CONTROL GUIDELINES SACHSE EROSION CONTROL GUIDELINES Section I. Definitions The following words, terms, and phrases, when used in this guideline, shall have the meanings ascribed to them in this Section, except where the

More information

National Pollutant Discharge Elimination System General Permit for Discharges from Construction Activities

National Pollutant Discharge Elimination System General Permit for Discharges from Construction Activities National Pollutant Discharge Elimination System General Permit for Discharges from Construction Activities In compliance with the provisions of the Clean Water Act, 33 U.S.C. 1251 et. seq., (hereafter

More information

Permit Section Ohio EPA Permit Change or Addition Model Ordinance Section to be Changed

Permit Section Ohio EPA Permit Change or Addition Model Ordinance Section to be Changed Permit Section Ohio EPA Permit Change or Addition Model Ordinance Section to be Changed Ordinance Controlling Construction Site Soil Erosion, Sediment, and Other Wastes and Storm Water Runoff Part III.G.2:

More information

DOCUMENT SPECIAL PROVISIONS

DOCUMENT SPECIAL PROVISIONS DOCUMENT 00813 SPECIAL PROVISIONS ADDENDUM NO. 1, DECEMBER 16, 2016 PRICE ADJUSTMENTS FOR STRUCTURAL STEEL AND REINFORCING STEEL FOR CONTRACTS BID ON OR AFTER APRIL 5, 2011 ENGLISH UNITS December 12, 2016

More information

Erosion and Sediment Pollution Control Guidelines for Residential Lots with soil disturbance of less than 1 acre (see exceptions)

Erosion and Sediment Pollution Control Guidelines for Residential Lots with soil disturbance of less than 1 acre (see exceptions) Adams Co. Conservation District 670 Old Harrisburg Road, Suite 201 Gettysburg, PA 17325 Telephone: 334-0636 Fax: 337-0730 www.adamscounty.us Erosion and Sediment Pollution Control Guidelines for Residential

More information

BMP #: Infiltration Basin

BMP #: Infiltration Basin Structural BMP Criteria BMP #: Infiltration Basin An Infiltration Basin is a shallow impoundment that stores and infiltrates runoff over a level, subtle, uncompacted, (preferably undisturbed area) with

More information

SITE DESIGN ENGINEER'S STATEMENT:

SITE DESIGN ENGINEER'S STATEMENT: SITE DESIGN ENGINEER'S STATEMENT: THESE DETAILED PLANS AND SPECIFICATIONS WERE PREPARED UNDER MY DIRECTION AND SUPERVISION. SAID PLANS AND SPECIFICATIONS HAVE BEEN PREPARED ACCORDING TO THE CRITERIA ESTABLISHED

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

GENERAL PERMIT OKR10

GENERAL PERMIT OKR10 GENERAL PERMIT OKR10 FOR STORMWATER DISCHARGES FROM CONSTRUCTION ACTIVITIES WITHIN THE STATE OF OKLAHOMA OKLAHOMA DEPARTMENT OF ENVIRONMENTAL QUALITY WATER QUALITY DIVISION September 13, 2012 DRAFT Stormwater

More information

BMP 6.4.4: Infiltration Trench

BMP 6.4.4: Infiltration Trench BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY ENVIRONMENTAL SETTING The project site is located in the Wilshire community of the City of Los Angeles and is bound by S. Wetherly Drive to

More information

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established

More information

c. Sites subject to regulation under Subtitle D of RCRA. The following discharges are not authorized by this permit:

c. Sites subject to regulation under Subtitle D of RCRA. The following discharges are not authorized by this permit: Page 1 of 6 Permit No: MNR050000 PART VII. SECTOR-SPECIFIC REQUIREMENTS The Permittee shall comply with Part VII (sector-specific requirements) for any primary SIC code and/or narrative activity and co-located

More information

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO.

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. 11-91360-001 ADVERTISED: November 5, 2010 MANDATORY PRE-BID MEETING:

More information

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with

More information

Instructions for Notice of Ground Disturbance Form:

Instructions for Notice of Ground Disturbance Form: Instructions for Notice of Ground Disturbance Form: Prior to beginning any ground disturbance activity or finalizing your storm water plan, submit a completed 2 page Notice of Ground Disturbance Form to

More information

The Good, The Bad, and The Ugly

The Good, The Bad, and The Ugly Overview The Good, The Bad, and The Ugly Stormwater Regulations for the Construction Industry Seminar March 20, 2012 Wendy Terlizzi Arizona Department of Transportation Office of Environmental Services

More information

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields 4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

Stormwater Pollution Prevention Plan (SWPPP) for Construction Activity for Small Construction Sites

Stormwater Pollution Prevention Plan (SWPPP) for Construction Activity for Small Construction Sites Stormwater Pollution Prevention Plan (SWPPP) for Construction Activity for Small Construction Sites National Pollutant Discharge Elimination System (NPDES) General Permit # Prepared for: Date: Prepared

More information

Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction Activities

Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction Activities Development Services 1775 12 th Ave. NW P.O. Box 1307 Issaquah, WA 98027 425-837-3100 issaquahwa.gov Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction

More information

STORMWATER MANAGEMENT PROGRAM. Table of Contents

STORMWATER MANAGEMENT PROGRAM. Table of Contents STORMWATER MANAGEMENT PROGRAM Yakima Valley College March 1st, 0 1 0 1 Table of Contents INTRODUCTION... PROGRAM COMPONENTS... S.D.1: PUBLIC EDUCATION AND OUTREACH... Label Storm Drain Inlets:... Public

More information

Stormwater Management at Municipal Solid Waste Landfills

Stormwater Management at Municipal Solid Waste Landfills Stormwater Management at Municipal Solid Waste Landfills Permit Coverage Municipal Solid Waste Landfills are covered under one of the following National Pollutant Discharge Elimination System (NPDES) types

More information

SECTION 903 EROSION CONTROL

SECTION 903 EROSION CONTROL SECTION 903 EROSION CONTROL Delete this Section in its entirety and replace with the following: SECTION 903 EROSION CONTROL 903-1 DESCRIPTION: This work consists of providing all; administrative, labor,

More information

South Carolina

South Carolina www.scdhec.gov/water South Carolina NPDES GENERAL PERMIT FOR STORMWATER DISCHARGES FROM SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION CONSTRUCTION ACTIVITIES In compliance with the provisions of the SC Pollution

More information

[Rev - 1] 06/

[Rev - 1] 06/ WVU DESIGN GUIDELINES & CONSTRUCTION STANDARDS DIVISION 33 UTILITIES SECTION 334100 STORMWATER MANAGEMENT PART 1 GENERAL 1.1. Any deviances from the following instructions must be approved during design

More information

Erosion Control State Standards Sampling of Material Innovations

Erosion Control State Standards Sampling of Material Innovations Erosion Control State Standards Sampling of Material Innovations Greg Halverson Brock White Company Geosynthetics Product Manager 32 nd Annual North Central Local Roads Conference Rapid City, SD - October

More information

Water Quality: 1.0 Water Quality Protection Volume and Peak Flow 2.0 Construction SWP3 Guidelines and Form

Water Quality: 1.0 Water Quality Protection Volume and Peak Flow 2.0 Construction SWP3 Guidelines and Form : 1.0 Protection Volume and Peak Flow 2.0 and Form Table of Contents 1.0 Protection Volume and Peak Flow...WQ-1 1.1 Introduction...WQ-1 1.2 Protection Volume Calculation...WQ-1 1.3 Protection Volume Reduction

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm

More information

APPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports

APPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports APPENDIX H H.1 Guidance for Preparing and Reviewing CEQA Initial Studies Step 1: Consider the Project Characteristics as Provided by the Project Applicant Review the project application and draft plan

More information

iswm TM Criteria Manual City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June Chapter 1

iswm TM Criteria Manual City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June Chapter 1 City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June 2010... Chapter 1 i CITY OF AZLE iswm CRITERIA MANUAL FOR SITE DEVELOPMENT AND CONSTRUCTION Incorporating the Regional NCTCOG Integrated

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL

More information

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines Pennsylvania Stormwater Best Management Practices Manual Chapter 3 Stormwater Management Principles and Recommended Control Guidelines 363-0300-002 / December 30, 2006 Chapter 3 Stormwater Management Principles

More information

MS4 Programs: Quality, the Other Stormwater Q. Dan Bounds, PE, D.WRE IAFSM March 9, 2017

MS4 Programs: Quality, the Other Stormwater Q. Dan Bounds, PE, D.WRE IAFSM March 9, 2017 MS4 Programs: Quality, the Other Stormwater Q Dan Bounds, PE, D.WRE IAFSM March 9, 2017 MS4 Rule and Regulations MS4 Municipal Separate Storm Sewer System A conveyance or system of conveyances (catch basins,

More information

APPENDIX G Fire BMPs

APPENDIX G Fire BMPs APPENDIX G Fire BMPs BEST MANAGEMENT PRACTICES Plan for URBAN RUNOFF MANAGEMENT PARTICIPATING RIVERSIDE COUNTY FIRE FIGHTING AGENCIES City of Corona Fire Department City of Hemet Fire Department City of

More information

NPDES/SDS Stormwater Permit Program for Construction Activity Inspection Report Corrective Actions. ( ) - ext. ( ) - ext. Owner Name Telephone Fax

NPDES/SDS Stormwater Permit Program for Construction Activity Inspection Report Corrective Actions. ( ) - ext. ( ) - ext. Owner Name Telephone Fax NPDES/SDS Stormwater Permit Program for Construction Activity Inspection Report Corrective Actions MPCA use only White-MPCA Canary-Site copy Delta record Project Name / Location MN R100001-C000 Stormwater

More information

11 Ways to Avoid Storm Water Fines. No Exceptions!

11 Ways to Avoid Storm Water Fines. No Exceptions! 11 Ways to Avoid Storm Water Fines Do not start until you have gone over this with a SWPPP Rep. No Exceptions! 1. Contact Mark Atwood at 801-319-1331 or Jake Pettersson at 801-709-4463. 2. Submit a Notice

More information

Whitewater River Region SWMP. APPENDIX L BMPs for Fire Fighting Agency Activities

Whitewater River Region SWMP. APPENDIX L BMPs for Fire Fighting Agency Activities Whitewater River Region SWMP APPENDIX L June 2009 INTENT The purpose of this plan is to identify Best Management Practices (BMPs) used by fire fighting agencies for management of Urban Runoff in the Whitewater

More information

Stormwater Management and Sediment and Erosion Control Plan Review Checklist For Design Professionals

Stormwater Management and Sediment and Erosion Control Plan Review Checklist For Design Professionals Stormwater Management and Sediment and Erosion Control Plan Review Checklist For Design Professionals This Plan Review Checklist for Design Professionals has been developed to aid those who prepare Stormwater

More information

Chapter 3 Dispersion BMPs

Chapter 3 Dispersion BMPs Chapter 3 Dispersion BMPs 3.1 BMP L611 Concentrated Flow Dispersion 3.1.1 Purpose and Definition Dispersion of concentrated flows from driveways or other pavement through a vegetated pervious area attenuates

More information

Diversion Dikes. Fe=0.95

Diversion Dikes. Fe=0.95 2.2 Diversion Dike Erosion Control Description: A diversion dike is a compacted soil mound, which redirects runoff to a desired location. The dike is typically stabilized with natural grass for low velocities

More information

QSD/QSP Training Module 9 SWPPP Preparation

QSD/QSP Training Module 9 SWPPP Preparation QSD/QSP Training Module 9 SWPPP Preparation Anna Lantin, P.E., CPESC, CPSWQ Overview and Learning Objectives Given a project Risk Level or LUP Type, you will learn to: Prepare a compliant SWPPP Determine

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

Spartanburg County. Storm Water Management Design Manual

Spartanburg County. Storm Water Management Design Manual Spartanburg County TABLE OF CONTENTS Section Title Page No. Table of Contents... i List of Tables......iii Chapter 1 Introduction... 1 1.1 Purpose of the Manual... 1 1.2 Description and Use of the Manual...

More information

STATE OF FLORIDA EROSION AND SEDIMENT CONTROL DESIGNER AND REVIEWER MANUAL

STATE OF FLORIDA EROSION AND SEDIMENT CONTROL DESIGNER AND REVIEWER MANUAL STATE OF FLORIDA EROSION AND SEDIMENT CONTROL DESIGNER AND REVIEWER MANUAL Official Release and Effective: June 2007 Latest Update: July 2013 Prepared for: FLORIDA DEPARTMENT OF TRANSPORTATION & FLORIDA

More information

Section 2: Site Restorations and PCSM s Office of Oil and Gas Management Oil and Gas Industry Training Summer 2012

Section 2: Site Restorations and PCSM s Office of Oil and Gas Management Oil and Gas Industry Training Summer 2012 Section 2: Site Restorations and PCSM s Office of Oil and Gas Management Oil and Gas Industry Training Summer 2012 Site Restoration Regulations Act 13-3216(a) The Oil and Gas Act 25 Pa. Code 78.65 Oil

More information

Section 2: Site Restorations and PCSM s Office of Oil and Gas Management Oil and Gas Industry Training Summer 2012

Section 2: Site Restorations and PCSM s Office of Oil and Gas Management Oil and Gas Industry Training Summer 2012 Site Restoration Regulations Section 2: Site Restorations and PCSM s Office of Oil and Gas Management Oil and Gas Industry Training Summer 2012 Act 13-3216(a) The Oil and Gas Act 25 Pa. Code 78.65 Oil

More information

Planning & Building Department. Requirements for Erosion and Sediment Control

Planning & Building Department. Requirements for Erosion and Sediment Control Planning & Building Department 455 County Center, 2nd Floor Redwood City, California 94063 Tel: 540/863-4161/Fax: 650/363-4849 Mail Drop PLN122 plngbldg@smcgov.org http://planning.smcgov.org Requirements

More information

FLORENCE COUNTY STORMWATER DESIGN MANUAL

FLORENCE COUNTY STORMWATER DESIGN MANUAL FLORENCE COUNTY STORMWATER DESIGN MANUAL JULY 18, 2013 Resolution No. 02-2013/14 Florence County Council TABLE OF CONTENTS TITLE PAGE NO. SECTION 1. GENERAL 1.1 INTRODUCTION--------------------------------------------------------------------------

More information

Outline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control

Outline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control Inspecting Construction Site BMPs Kristin Kerr EOA, Inc. Outline of Presentation Back to Basics Erosion and Sediment Control Good Site Non-Stormwater Run-on and Run-off Control Construction Inspection

More information

Clean Water is Everyone s Business. A commercial & industrial property owner s guide to improving Lake Tahoe s clarity

Clean Water is Everyone s Business. A commercial & industrial property owner s guide to improving Lake Tahoe s clarity Clean Water is Everyone s Business A commercial & industrial property owner s guide to improving Lake Tahoe s clarity this informational guide will help you understand the tahoe regional planning agency

More information

PART V - STORM DRAIN DESIGN CRITERIA

PART V - STORM DRAIN DESIGN CRITERIA PART V - STORM DRAIN DESIGN CRITERIA A. Hydrology Studies and Hydraulic Analyses 1. Drainage area master plans and calculations are to be submitted with all subdivision improvement plans, permit improvement

More information

ACTION PLAN FOR RETROFITTING STRUCTURAL BEST MANAGEMENT PRACTICES Storm Water Management Plan

ACTION PLAN FOR RETROFITTING STRUCTURAL BEST MANAGEMENT PRACTICES Storm Water Management Plan ACTION PLAN FOR RETROFITTING STRUCTURAL BEST MANAGEMENT PRACTICES Storm Water Management Plan Marine Corps Base Hawaii NPDES Permit No. HI 000007 Prepared by: Marine Corps Base Hawaii August 2015 Table

More information

Boise City Public Works General Drainage Plan Review Requirements Checklist

Boise City Public Works General Drainage Plan Review Requirements Checklist Boise City Public Works General Drainage Plan Review Requirements Checklist Development Name Bldg. Permit # Drainage Reviewer Site Address Initial Review Date ODI Number Designer Company Name Treated Acres

More information

KANSAS CITY, MO INDUSTRIAL FACILITY INSPECTION FOR MS4 PROGRAM

KANSAS CITY, MO INDUSTRIAL FACILITY INSPECTION FOR MS4 PROGRAM KANSAS CITY, MO INDUSTRIAL FACILITY INSPECTION FOR MS4 PROGRAM Storm Water Pollution Prevention, Control, Reduction and Minimization In Compliance with Kansas City, MO Municipal Separate Storm Sewer System

More information

CCI107 ONLINE PROGRAM. Stormwater Management. Stormwater Management for Construction Activities Alberta. Market Type: Construction Level: 1

CCI107 ONLINE PROGRAM. Stormwater Management. Stormwater Management for Construction Activities Alberta. Market Type: Construction Level: 1 ONLINE PROGRAM Market Type: Construction Level: 1 Stormwater Management 1-877-25-SWPPP 1-877-25-9777 info@stormwaterone.com + Choose Alberta Enroll Now at StormwaterONE.com StormwaterONE.com 290 Pratt

More information

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit)

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit) CHESAPEAKE BAY TMDL ACTION PLAN (2013 2018 MS4 General Permit) Piedmont Virginia Community College A Plan for Achieving a 5% Reduction of Existing Loads June 30, 2015 Main Campus This plan satisfies the

More information

STANDARD PLAN FOR MINOR EARTH DISTURBANCES

STANDARD PLAN FOR MINOR EARTH DISTURBANCES Allegany Soil Conservation District 12407 Naves Cross Road, NE Cumberland, MD 21502 Phone: 301.777.1747 Fax: 301.777.7632 Permit #: Allegany County City of Cumberland City of Frostburg Other Date: STANDARD

More information

Stormwater Management and Sediment and Erosion Control Plan Review Checklist for Design Professionals

Stormwater Management and Sediment and Erosion Control Plan Review Checklist for Design Professionals Page 1 of 7 Florence County MS4 Stormwater Management and Sediment and Erosion Control Plan Review Checklist for Design Professionals Please indicate the location and page number(s) where each item below

More information

Infiltration Trench. Image: Cahill Associates, Inc.

Infiltration Trench. Image: Cahill Associates, Inc. Infiltration Trench Image: Cahill Associates, Inc. An Infiltration Trench is a linear infiltration system, designed like an infiltration basin, yet shaped like a trench (long and thin). The Trench is topped

More information

FACT SHEET STATE OF GEORGIA DEPARTMENT OF NATURAL RESOURCES ENVIRONMENTAL PROTECTION DIVISION

FACT SHEET STATE OF GEORGIA DEPARTMENT OF NATURAL RESOURCES ENVIRONMENTAL PROTECTION DIVISION FACT SHEET STATE OF GEORGIA DEPARTMENT OF NATURAL RESOURCES ENVIRONMENTAL PROTECTION DIVISION NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM GENERAL PERMITS NO. GAR100001, NO. GAR100002 and NO. GAR100003

More information

Module 1: Construction Site Erosion Control

Module 1: Construction Site Erosion Control Module 1: Construction Site Erosion Control Problems and Regulations Robert Pitt Department of Civil, Construction, and Environmental Engineering University of Alabama Tuscaloosa, AL Problems Associated

More information

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW SUBCHAPTER 8 STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW 7:45-8.1 Purpose and scope of review Except for those projects expressly exempted by this chapter or waived by the Commission, the Commission

More information

Order of road works and servicing construction to be carried out in accordance with the staged contract construction sequence specified below.

Order of road works and servicing construction to be carried out in accordance with the staged contract construction sequence specified below. SEDIMENT CONTROL NOTES 1.0 GENERAL 1.1 The Developer and Contractor shall comply with the requirements of all regulatory authorities, federal, provincial and municipal government departments including

More information

UMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist

UMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist UMD Storm Water Program Construction Requirements Greg Archer, MBA Environmental Compliance Specialist Phase 2 Regulatory Overview Dec. 1999 EPA issues Phase 2 Federal Register Municipalities (MS4) from

More information

Parking Area Maintenance

Parking Area Maintenance Description Parking lots can contribute a number of substances, such as trash, suspended solids, hydrocarbons, oil and grease, and heavy metals that can enter receiving waters through stormwater runoff

More information

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR050000 Storm Water Pollution Prevention Plan Worksheet Instructions The TCEQ Small Business and Local Government Assistance

More information

PRESENTATION OUTLINE

PRESENTATION OUTLINE PRESENTATION OUTLINE Updates to WMO since last meeting Technical memorandum on TGM rainfall data Runoff curve number reduction methodology for Green Infrastructure Summary of material to be covered in

More information

Ordinance amending the San Francisco Public Works Code by adding Article 4.2,

Ordinance amending the San Francisco Public Works Code by adding Article 4.2, FILE NO. ORDINANCE NO. 1 [Stormwater Management.] Ordinance amending the San Francisco Public Works Code by adding Article., sections., requiring the development and maintenance of stormwater management

More information

Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative

Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative Model Poultry Burial E&S Plan (7-2-15) 1. GENERAL INFORMATION Name of project Name of person responsible Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative Address Phone number Municipality

More information

Starting Construction: Your Storm Water Permit

Starting Construction: Your Storm Water Permit Starting Construction: Your Storm Water Permit Asma Vahora Compliance Assistance Specialist Small Business and Local Government Assistance San Antonio- Region 13 210-403-4039 Asma.Vahora@tceq.texas.gov

More information