1 Florida Department of Transportation District Four KICK-OFF MEETING I-95 at Southern Boulevard (SR 80) Project Development and Environment Study Palm Beach County, Florida Financial Project ID No.: ETDM No.: November 17,

2 Meeting Purpose Introduce the Project Outline the Study Process and Schedule Share Information About the Project Receive Input from Residents and Stakeholders Questions and Concerns Comment Forms Request a Group Meeting Website: 2

3 Project Development and Environment (PD&E) Study PD&E Study Objectives: To perform the necessary social, environmental and engineering studies regarding a proposed transportation improvement to support decisions concerning if and where it should be built, and what the basic design concepts will be. 3

4 The Transportation Project Process 4

5 The PD&E Study Process Data Collection: A review of all existing conditions Engineering Analysis: Develop alternatives that meet the needs of the study area Environmental Evaluations: Potential impacts to the social, natural and physical environments Public Involvement: Continuous community outreach and stakeholder coordination Project Initiation: Data Collection Identify Transportation Issues & Develop Solutions Public Kick-off Meeting: Introduce the Study to the Public & Receive Input Environmental & Engineering Analysis Alternatives Public Meeting: Present the Alternatives to the Public & Receive Input Draft Environmental & Engineering Documents Public Hearing: Final Opportunity for the Public to Make Verbal or Written Statements about the Study Final Environmental & Engineering Documents Federal Highway Administration (FHWA) Location and Design Concept Acceptance A continuous community outreach process is integrated into every step of the project to ensure that the corridor residents, businesses, the traveling public and other interested parties have meaningful opportunities for participation throughout the PD&E Study. COMMUNITY OUTREACH 5

6 PD&E Study Components Public Involvement Engineering Environmental 6

7 Location: I-95 at Southern Boulevard (SR 80) Interchange City of West Palm Beach Palm Beach County Southern Boulevard from Australian Avenue on the west side, to Parker Avenue on the east side of the interchange Study Area 7

8 Project Purpose and Need Enhance overall traffic operations at the Southern Boulevard (SR 80) Interchange Improve capacity and meet future travel demand resulting from: Population growth Employment growth Consistent with local transportation plans 8

9 Engineering and Environment Data Collection and Analysis Some of the data gathered includes: Traffic counts Crash records Existing roadway conditions Existing drainage systems and patterns Identification of wetlands Threatened/Endangered species and habitat Existing land use property information Census Data Planned developments Contamination sites Archaeological/Historical sites 9

10 Traffic Conditions Roadway doesn t handle existing traffic Average Daily Traffic (ADT) anticipated to increase Degraded traffic operations unless improvements are made 10

11 Safety Collisions on I-95 at Southern Boulevard (SR 80) ( ) Total crashes: 1,330 Average crashes per year: 266 Predominant Rear end 27% crash types: Angle 9% Fixed object 19% Fatalities: 4 Injuries:

12 Emergency Evacuation Part of the Palm Beach County emergency evacuation route network Major east-west and north-south corridors Connects with other major arterials and highways 12

13 Alternatives Analysis Meet future travel demand Avoid or minimize impacts to the community and environment Developed with input from the the public, local governments and environmental agencies Criteria for comparison of alternatives: - Community and environmental impacts - Costs for design and construction, engineering inspection/maintenance, right-of-way acquisition, and environmental mitigation 13

14 Environmental Analysis Social and Cultural Environment Natural Environment Physical Environment Environmental Reports 14

15 Social and Cultural Environment Socio-Economic Effects Socio-Cultural Effects Archaeological and Historic Sites Visual Impacts and Aesthetics Parks and Recreational Resources 15

16 Natural Environment Endangered Species Wildlife Habitat Water Resources Wetlands 16

17 Physical Environment Pedestrian and Bicycle Facilities Contamination Sites Visual Impacts Air Quality Noise Construction 17

18 Project Schedule Study Begins Data Collection Public Kick-off Meeting Develop and Evaluate Alternatives Environmental Evaluations Alternatives Public Meeting Finalize Draft Engineering & Environmental Documents Public Hearing Submit Project Document to Federal Highway Administration (FHWA) FHWA Location Design and Concept Acceptance PD&E I-95 at Southern Boulevard (SR 80) Interchange Project Development and Environment (PD&E) Study SCHEDULE TASK Quarter 2 Quarter 3 Quarter 4 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Quarter 1 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A continuous community outreach process is integrated into every step of the project to ensure that the corridor residents, businesses, the traveling public and other interested parties have meaningful participation in the process Quarter 2 Quarter 3 Quarter 4 Quarter 1 LEGEND: Study Begins Tasks Public Meeting Public Hearing Study Complete 18

19 What s Next? Continuous Public Involvement City of West Palm Beach Palm Beach County Town of Cloud Lake Town of Glen Ridge Vedado-Hillcrest Neighborhood Association Local agencies Area stakeholders Available to give presentations upon request 19

20 What s Next? Evaluate future traffic levels and operations Review engineering data collected Develop viable alternatives Evaluate environmental impacts 20

21 Public Involvement Elected and Appointed Officials/Agencies Kick-off Meeting Public Kick-off Meeting Alternatives Public Meeting Public Hearing Project Website: Local Outreach 21

22 How Can You Get Involved? Comment Forms Place in the comment box tonight Mail to the address on the form Website: Request a Group Meeting Neighborhood association Special interest group 22

23 Contact Information FDOT Project Manager Anson Sonnett, P.E. Florida Department of Transportation, District Four 3400 West Commercial Boulevard Fort Lauderdale, Florida Phone: Toll free: ext

24 Thank you for attending this Kick-off Meeting and for sharing your thoughts and concerns! 24

25 Questions? 25

SR 9/I-95 Interchange at 45th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No.

SR 9/I-95 Interchange at 45th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No. Palm Beach County, Florida Palm Beach Metropolitan Planning Organization April 217 Project Study Area LIMITS: SR 9/I-95: from S of 45th Street to N of 45th Street 45th Street: From Village Boulevard to

More information

MARTINSVILLE SOUTHERN CONNECTOR STUDY CITIZEN INFORMATION MEETING Magna Vista High School 701 Magna Vista School Road Ridgeway, Virginia May 8,

MARTINSVILLE SOUTHERN CONNECTOR STUDY CITIZEN INFORMATION MEETING Magna Vista High School 701 Magna Vista School Road Ridgeway, Virginia May 8, MARTINSVILLE SOUTHERN CONNECTOR STUDY CITIZEN INFORMATION MEETING Magna Vista High School 701 Magna Vista School Road Ridgeway, Virginia 24148 May 8, 2018 MEETING OVERVIEW AND OBJECTIVES Introduce study

More information

MDX Contract #: RFP MDX Work Program #: ETDM #: 11501

MDX Contract #: RFP MDX Work Program #: ETDM #: 11501 SR 874/Don Shula Expressway Ramp Connector Project Development & Environment (PD&E) Study PUBLIC HEARING December 8, 2011 MDX Contract #: RFP-09-04 MDX Work Program #: 87410.011 ETDM #: 11501 1 This Public

More information

State Road (S.R.) 12 (Florida Arts Trail PD&E)

State Road (S.R.) 12 (Florida Arts Trail PD&E) State Road (S.R.) 12 (Florida Arts Trail PD&E) from North Corry Street to S.R. 63 (U.S. 27) Gadsden County, Florida FPID Number: 433380-1-32-01 CRTPA Briefing September 2015 Today s Presentation Evolution

More information

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. Welcome Public Meeting August 2, 2017 5:00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. www.glenwoodsouthbridge.net Welcome to the South Bridge Environmental Assessment Public Meeting Why Are We Here Tonight?

More information

Chapter 2 Transportation Element Goals, Objectives and Policies

Chapter 2 Transportation Element Goals, Objectives and Policies Chapter 2 Transportation Element Goals, Objectives and Policies City of Belleview Comprehensive Plan Adopted by Ord 2016-10 on July 5, 2016 GOALS, OBJECTIVES AND POLICIES Goal 2 Transportation...1 Objective

More information

ENVIRONMENTAL ADVISORY GROUP MEETING NO. 2

ENVIRONMENTAL ADVISORY GROUP MEETING NO. 2 ENVIRONMENTAL ADVISORY GROUP MEETING NO. 2 Lake / Orange County Connector (US 27 to SR 429) Feasibility/Project Development & Environment Study February 12, 2019 Title VI Compliance This meeting, project,

More information

HSM APPLICATION USING IHSDM (I-12 TO BUSH) April Renard, P.E. LADOTD Highway Safety

HSM APPLICATION USING IHSDM (I-12 TO BUSH) April Renard, P.E. LADOTD Highway Safety HSM APPLICATION USING IHSDM (I-12 TO BUSH) April Renard, P.E. LADOTD Highway Safety PROJECT OVERVIEW Alternative N-S corridor to I-12 Louisiana Revised Statute 47:820.2B(e) 4-lane arterial Limited access

More information

SR 29 Project Development & Environment Study. Presentation to SR 29 Stakeholders Advisory Committee. January 23, 2014

SR 29 Project Development & Environment Study. Presentation to SR 29 Stakeholders Advisory Committee. January 23, 2014 SR 29 Project Development & Environment Study Presentation to SR 29 Stakeholders Advisory Committee January 23, 2014 Purpose and Need Enhancing Economic Competitiveness Improving Emergency Evacuation Capabilities

More information

1.4 Analysis of Alignment Alternatives

1.4 Analysis of Alignment Alternatives Parkway is 20.94 miles, with 8.16 miles in Orange County, 7.37 miles in Lake County and 5.41 miles in Seminole County. SR 46 Reconstruction and Realignment, which would begin at the SR 46/US 441 interchange

More information

LOCATION HYDRAULIC REPORT

LOCATION HYDRAULIC REPORT Draft LOCATION HYDRAULIC REPORT Florida Department of Transportation District One US 41 at Fruitville Road (CR 780) Intersection Improvements - PD&E STUDY Sarasota County, Florida Financial Project ID

More information

Project Study Area. Presentation. July 8, 2008

Project Study Area. Presentation. July 8, 2008 Florida Department of Transportation Presentation for for the the South Side Community Plan #4 at at the the South South Shore Shore Regional Regional Library, Library, 15816 15816 Beth Beth Shields Shields

More information

2050 VISION WORKSHOP

2050 VISION WORKSHOP I-75 PD&E Studies Project Development & Environment Studies From Moccasin Wallow Road to North of Fletcher Avenue Manatee and Hillsborough Counties 2050 VISION WORKSHOP Florida Department of Transportation

More information

SR 50 PD&E Study

SR 50 PD&E Study SR50 Project Development & Environment Study Public Hearing November 1, 2011 SR 50 PD&E Study 427056-1-22-01 1 Purpose of the Public Hearing Afford persons the opportunity to express their views about

More information

Final Air Quality Report

Final Air Quality Report Florida Department of TRANSPORTATION Final Air Quality Report PD&E Study From East of Babcock Street (SR 507) to US 1 Brevard County, Florida Financial Project ID: 430136-1-22-01 ETDM Project Number: 13026

More information

Palm Beach MPO Board Meeting December 7, 2015

Palm Beach MPO Board Meeting December 7, 2015 Palm Beach MPO Board Meeting December 7, 2015 Overview 1 Background and History 3 Public and Agency Engagement Strategy 2 Overview of Scope and Schedule for the Study 4 Next Steps 2 1 Background and History

More information

Public Meeting. US Highways 18 & 281 and SD Highway 50 From Douglas County Line to SD46 Charles Mix County

Public Meeting. US Highways 18 & 281 and SD Highway 50 From Douglas County Line to SD46 Charles Mix County Public Meeting US Highways 18 & 281 and SD Highway 50 From Douglas County Line to SD46 Charles Mix County Cary Cleland Road Design Engineering Supervisor January 17, 2017 Project Limits US18/US281 US281

More information

I-4 Beyond the Ultimate Project Development & Environment (PD&E) Reevaluation Study FROM WEST OF SR 528 (BEACHLINE EXPRESSWAY)

I-4 Beyond the Ultimate Project Development & Environment (PD&E) Reevaluation Study FROM WEST OF SR 528 (BEACHLINE EXPRESSWAY) I-4 Beyond the Ultimate Project Development & Environment (PD&E) Reevaluation Study FROM WEST OF SR 528 (BEACHLINE EXPRESSWAY) TO WEST OF SR 435 (KIRKMAN ROAD) ORANGE COUNTY, FLORIDA Financial Project

More information

Northwest State Route 138 Corridor Improvement Project

Northwest State Route 138 Corridor Improvement Project Northwest State Route 138 Corridor Improvement Project Los Angeles County, CA DISTRICT 7- LA- 138 (PM 0.0/36.8); DISTRICT 7- LA- 05 (PM 79.5/83.1); DISTRICT 7- LA- 14 (PM 73.4/74.4) 265100/ 0700001816

More information

D R A F T. SECTION 4(f) EVALUATION. INTERSTATE 73 From I-95 to the Myrtle Beach Region

D R A F T. SECTION 4(f) EVALUATION. INTERSTATE 73 From I-95 to the Myrtle Beach Region D R A F T SECTION 4(f) EVALUATION INTERSTATE 73 From I-95 to the Myrtle Beach Region INTRODUCTION Section 4(f) of the Department of Transportation Act of 1966, 49 USC 303 requires that prior to the use

More information

NOISE STUDY REPORT. for the WEKIVA PARKWAY (SR 429)/SR 46 REALIGNMENT PD&E STUDY. Orange, Lake, and Seminole Counties, Florida

NOISE STUDY REPORT. for the WEKIVA PARKWAY (SR 429)/SR 46 REALIGNMENT PD&E STUDY. Orange, Lake, and Seminole Counties, Florida UPDATED FINAL REPORT NOISE STUDY REPORT for the WEKIVA PARKWAY (SR 429)/SR 46 REALIGNMENT PD&E STUDY Orange, Lake, and Seminole Counties, Florida Financial Project ID: 238275 1 22 01 and 240200 1 22 01

More information

Alternatives Evaluation Methodology

Alternatives Evaluation Methodology Alternatives Evaluation Methodology www.vision54 56.com B 1 Phase 2 Alternatives Evaluation Methodology PASCO COUNTY METROPOLITAN PLANNING ORGANIZATION 8731 Citizens Drive New Port Richey, FL 34654 Ph

More information

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK MTP VISION In order to create a framework for the 2040 Metropolitan Transportation Plan (MTP), a vision statement was drafted by the Vision/Goals Committee and

More information

CENTRAL FLORIDA EXPRESSWAY AUTHORITY. SR 408 Eastern Extension PD&E Study

CENTRAL FLORIDA EXPRESSWAY AUTHORITY. SR 408 Eastern Extension PD&E Study CENTRAL FLORIDA EXPRESSWAY AUTHORITY SR 408 Eastern Extension PD&E Study WHAT IS A PD&E? Process used to evaluate - o Engineering Alternatives o Environmental Impacts and Social, Cultural and Economic

More information

Statewide Acceleration Transformation (SWAT)

Statewide Acceleration Transformation (SWAT) Presented to: AASHTO SCOE/SCOD Presented by: Marjorie Kirby Paul Hiers, P.E. Statewide Acceleration Transformation (SWAT) July 2017 PD&E Study Comply with the National Environmental Policy Act (NEPA) and

More information

POLK COUNTY TPO Polk County 2060 Transportation Vision Plan Final Report. ADOPTED June 18, 2009

POLK COUNTY TPO Polk County 2060 Transportation Vision Plan Final Report. ADOPTED June 18, 2009 POLK COUNTY TPO Polk County 2060 Transportation Vision Plan Final Report ADOPTED June 18, 2009 TABLE OF CONTENTS CHAPTER 1 Introduction and Prior Planning Effort...Page 1-1 CHAPTER 2 Population and Employment

More information

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 4G. Intergovernmental Coordination and Review Log

TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M. To: Council Members AGENDA ITEM 4G. Intergovernmental Coordination and Review Log TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 4G From: Date: Subject: Staff May 16, 2008 Council Meeting Intergovernmental Coordination and Review Log The

More information

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida November 7, 2014 SUBMITTED BY: Dewberry Bowyer-Singleton 520 South

More information

EXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD

EXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD Scope of Services 12/08/2008 EXHIBIT A SCOPE OF SERVICES INTERCHANGE JUSTIFICATION REPORT (IJR) FOR INTERSTATE 75 AT OVERPASS ROAD TABLE OF CONTENTS Section Pace I. 0 PROJECT DESCRIPTION........................,............................................................

More information

Chester Bridge Environmental Assessment (EA) CAG Meeting #2. October 12, 2017

Chester Bridge Environmental Assessment (EA) CAG Meeting #2. October 12, 2017 Chester Bridge Environmental Assessment (EA) CAG Meeting #2 October 12, 2017 Agenda Introductions Purpose & Need review and Merger Approval Review of the Conceptual Alternatives Recap of the Public Meeting

More information

SR 417 Extension. June 2003 INTRODUCTION AND HISTORY PROJECT SCOPE AND PURPOSE STUDY OBJECTIVE STUDY PHASES

SR 417 Extension. June 2003 INTRODUCTION AND HISTORY PROJECT SCOPE AND PURPOSE STUDY OBJECTIVE STUDY PHASES Planning Feasibility Study June 2003 INTRODUCTION AND HISTORY The SR 417 Extension Study was a yearlong effort undertaken by Florida s Turnpike Enterprise to investigate the feasibility of a new toll road

More information

All Aboard Florida Project Status Update TREASURE COAST REGIONAL PLANNING COUNCIL

All Aboard Florida Project Status Update TREASURE COAST REGIONAL PLANNING COUNCIL All Aboard Florida Project Status Update TREASURE COAST REGIONAL PLANNING COUNCIL APRIL 2014 Southeast Florida Rail Network & Proposed All Aboard Florida Route To Jacksonville Tampa Orlando Everglades

More information

Stakeholder Interview Information Packet December 14-17, 2015

Stakeholder Interview Information Packet December 14-17, 2015 Stakeholder Interview Information Packet December 14-17, 2015 Overview 1 Background and History 4 Public and Agency Engagement Strategy 2 Overview of Scope and Schedule for the Study 5 Decision-making

More information

MEETING SUMMARY FOR APRIL 13, 2017

MEETING SUMMARY FOR APRIL 13, 2017 SARASOTA/MANATEE METROPOLITAN PLANNING ORGANIZATION Performance Measures/Project Prioritization Process Ad Hoc Committee 7632 15 th Street East Sarasota, Florida 34243 3:00-5:00 PM MEETING SUMMARY FOR

More information

Public Meeting. US Highway 81 From 306 th St. to 303 rd St. & 300 th St. Yankton County NH 0081(103)6 PCN 04G5. Brandon Riss, PE Road Design Engineer

Public Meeting. US Highway 81 From 306 th St. to 303 rd St. & 300 th St. Yankton County NH 0081(103)6 PCN 04G5. Brandon Riss, PE Road Design Engineer Public Meeting US Highway 81 From 306 th St. to 303 rd St. & 300 th St. Yankton County NH 0081(103)6 PCN 04G5 Brandon Riss, PE Road Design Engineer October 11, 2018 Purpose of the Meeting Involve the Public

More information

Comprehensive Transportation Study for Glencoe, MN

Comprehensive Transportation Study for Glencoe, MN Comprehensive Transportation Study for Glencoe, MN Introduction and Project Information Introduction There have been a number of planning and preliminary engineering studies completed in the Glencoe area

More information

Livability 2050 Regional Transportation Plan Update. RTPAC #4 October 16, 2018

Livability 2050 Regional Transportation Plan Update. RTPAC #4 October 16, 2018 Livability 2050 Regional Transportation Plan Update RTPAC #4 October 16, 2018 1 Meeting Agenda Timeline Financial Plan Update o Adopted Funding Scenario o Revenue Projections Prioritization Process Round

More information

Concept, Feasibility & Mobility Studies. Southport Connector Expressway

Concept, Feasibility & Mobility Studies. Southport Connector Expressway Concept, Feasibility & Mobility Studies Southport Connector Expressway Project Background FDOT Alternative Corridor Evaluation (ACE) Study Advanced Notification Package distributed September 2012 ETDM

More information

State Route 8 Bridge Replacement Project

State Route 8 Bridge Replacement Project OPEN HOUSE PUBLIC INVOLVEMENT MEETING Celebration Church 688 Dan Street, Akron, Ohio Tuesday, July 14, 2015 5:00 PM to 7:00 PM State Route 8 Bridge Replacement Project Existing Bridge Future Bridges: Steel

More information

Background Study Goals and Objectives

Background Study Goals and Objectives Professional Services CONSULTANT Contract Advertisement Number 19614 FM # 437949-1-22-01 City of Hialeah Freight Mobility Implementation Plan Scope of Services Background Florida s Freight Mobility and

More information

I-17 and Happy Valley Road Diverging Diamond Interchange (DDI)

I-17 and Happy Valley Road Diverging Diamond Interchange (DDI) I-17 and Happy Valley Road Diverging Diamond Interchange (DDI) Bharat Kandel (ADOT) and Jeremy Neuman (HDR) February 28, 2018 Project Purpose and Overview New interchange will accommodate current and future

More information

Harrison Community Center November 21, 2016

Harrison Community Center November 21, 2016 Harrison Community Center November 21, 2016 Survey Wetland Delineation Utility mapping Regulated Waste study Noise Measurements Traffic Counts Conceptual Layouts New FASTLANE grant annoucment Announced

More information

NORTH I-75 MASTER PLAN Summary Report

NORTH I-75 MASTER PLAN Summary Report NORTH I-75 MASTER PLAN Summary Report Interstate 75 (SR 93) From the Florida s Turnpike Interchange to the I-10 Interchange Alachua, Bradford, Clay, Citrus, Columbia, Duval, Levy, Marion, and Sumter Counties,

More information

Interstate 66 Tier 1 Environmental Impact Statement Public Hearing

Interstate 66 Tier 1 Environmental Impact Statement Public Hearing Interstate 66 Tier 1 Environmental Impact Statement Public Hearing 1 Project Corridor Study Process / Tiering Approach Tier 1 EIS focuses on broad issues - Purpose and need - Mode / Technology choice -

More information

I-20 East Transit Initiative

I-20 East Transit Initiative I-20 East Transit Initiative Open Houses Monday, June 24 6 7 PM: Open House 7 8 PM: Presentation & Q/A City of Atlanta Old Council Chambers Atlanta City Hall 55 Trinity Avenue Atlanta, GA 30303 Tuesday,

More information

Transportation Study related to the Redevelopment of NASB

Transportation Study related to the Redevelopment of NASB In association with RKG Associates, Gorrill-Palmer Consulting Engineers, Morris Communications, Nobis Engineering, and Techedit Public Informational Meeting # 1 Transportation Study related to the Redevelopment

More information

INTERCHANGE MODIFICATION REPORT

INTERCHANGE MODIFICATION REPORT INTERSTATE 75 AND STATE ROAD 884 (COLONIAL BOULEVARD) INTERCHANGE LEE COUNTY, FLORIDA INTERCHANGE MODIFICATION REPORT Prepared for: Florida Department of Transportation District One May 2017 Interchange

More information

AIR QUALITY TECHNICAL MEMORANDUM

AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM AIR QUALITY TECHNICAL MEMORANDUM GOLDEN GLADES INTERCHANGE PD&E STUDY Miami-Dade County, Florida Financial Management Number: 428358-1-22-01 Efficient Transportation Decision

More information

SR 60 Grade Separation over CSX Railroad Traffic Technical Memorandum

SR 60 Grade Separation over CSX Railroad Traffic Technical Memorandum To: Marlon Bizerra, PE From: Thirulokesh Krishnan Email: thirulokesh.krishnan@atkinsglobal.com Phone: 210.321.2019 Date: Nov 25, 2014 Ref: cc: Kim Warren, Doug Reed, PE Subject: SR 60 Grade Separation

More information

Land Use Vision and Transportation Strategy

Land Use Vision and Transportation Strategy Phase 1: Land Use and Transportation Strategy ing Workshop March 12, 2015 Phase 1: Land Use and Transportation Strategy Welcome Purpose & Background Consensus Building / Strategies to Implement the Next

More information

Appendix. Sample EA/EIS Scope of Work

Appendix. Sample EA/EIS Scope of Work Appendix K Sample EA/EIS Scope of Work EA/EIS Sample Scope of Work The purpose of this Scope of Work (SOW) is to prepare an EA document pursuant to the National Environmental Policy Act (NEPA) to analyze

More information

Shoulder Widening Prioritization Discussion

Shoulder Widening Prioritization Discussion Shoulder Widening Prioritization Discussion Lindsey Bruer Planning Director March 2, 2018 District 8 ATP Meeting mndot.gov District 4 Shoulder Widening Study Evaluation Criteria: 3/8/2018 2 Evaluation

More information

Reconstruction Project Update

Reconstruction Project Update I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial

More information

TYPE 2 CATEGORICAL EXCLUSION DETERMINATION FORM

TYPE 2 CATEGORICAL EXCLUSION DETERMINATION FORM 1. GENERAL INFORMATION County: Project Name: Project Limits STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION TYPE 2 CATEGORICAL EXCLUSION DETERMINATION FORM Collier I-75 at SR 951 Interchange Improvement

More information

HILLSBOROUGH COUNTY METROPOLITAN PLANNING ORGANIZATION

HILLSBOROUGH COUNTY METROPOLITAN PLANNING ORGANIZATION HILLSBOROUGH COUNTY METROPOLITAN PLANNING ORGANIZATION 2035 Long Range Transportation Plan Needs Assessment Segment Summary: Prepared for: Hillsborough County Metropolitan Planning Organization P.O. Box

More information

Barrington Road. at Jane Addams Memorial Tollway (Interstate 90) Interchange Improvement Study. Community Advisory Group Meeting #1

Barrington Road. at Jane Addams Memorial Tollway (Interstate 90) Interchange Improvement Study. Community Advisory Group Meeting #1 Barrington Road at Jane Addams Memorial Tollway (Interstate 90) Interchange Improvement Study Community Advisory Group Meeting #1 Hoffman Estates Village Hall July 25, 2012 Meeting Agenda 1. Welcome and

More information

Beckett Bridge PD& E Study Elected Officials Kick-Off Meeting

Beckett Bridge PD& E Study Elected Officials Kick-Off Meeting Beckett Bridge PD& E Study Elected Officials Kick-Off Meeting March 2012 Project Location Beckett Bridge US 19 Tarpon Ave Alt US 19 Project Limits Chesapeake Drive Begin Project Beckett Bridge End Project

More information

Joe Santos Transportation Safety Engineer Florida Department of Transportation

Joe Santos Transportation Safety Engineer Florida Department of Transportation Joe Santos Transportation Safety Engineer Florida Department of Transportation D7 Safety Summit, June 8, 2011 D7 Safety Summit Purpose & Goals: Despite significant progress, crash rates in the Tampa Bay

More information

FTP Implementation Element Worksheet

FTP Implementation Element Worksheet FTP Implementation Element Worksheet The following worksheets include draft implementation actions identified for the FTP Policy Element. The worksheets are organized by the FTP goals and objectives. Each

More information

Published by the Palm Beach Metropolitan Planning Organization (MPO) in coordination with Leftwich Consulting Engineers, Inc.

Published by the Palm Beach Metropolitan Planning Organization (MPO) in coordination with Leftwich Consulting Engineers, Inc. AMENDMENT #3 + Published by the Palm Beach Metropolitan Planning Organization (MPO) in coordination with Leftwich Consulting Engineers, Inc. Adopted October 16, 2014 by the Board of Directors Palm Beach

More information

SR 15 SECTION 088 CSVT SOUTHERN SECTION PUBLIC MEETING MAY 25, 2017

SR 15 SECTION 088 CSVT SOUTHERN SECTION PUBLIC MEETING MAY 25, 2017 PUBLIC MEETING MAY 25, 2017 AGENDA MEETING PURPOSE CSVT NORTHERN SECTION UPDATE FEBRUARY PUBLIC MEETING RECAP DESIGN CHANGES ACID ROCK ALIGNMENT SHIFT ASH BASIN AVOIDANCE ALTERNATIVES NEXT STEPS OPEN HOUSE

More information

Final Air Quality Report

Final Air Quality Report Florida Department of Transportation - District VII County Line Road (C.R. 578) Project Development and Environment Study From U.S. 19 (S.R. 55) to U.S. 41 (S.R. 45) Work Program Item Segment Number: 257298

More information

Route 7 Corridor Improvements Project Reston Avenue to Jarrett Valley Drive Public Hearing

Route 7 Corridor Improvements Project Reston Avenue to Jarrett Valley Drive Public Hearing Project Reston Avenue to Jarrett Valley Drive Public Hearing Nicholas J. Roper, P.E. District Project Development Engineer Email: nicholas.roper@vdot.virginia.gov Phone: (703)259-1953 Agenda 7:00-7:15

More information

Welcome. Elk River to Zimmerman. Highway 169 Interchange & Frontage Road Study:

Welcome. Elk River to Zimmerman. Highway 169 Interchange & Frontage Road Study: Welcome Chamber of Commerce Meeting 3:30-4:30 p.m. Public Open House 4:30-7:30 p.m. Dorothea Study Background 136th Street Livonia Township 277th Ave Future High School 273rd Ave 269th Ave Huntington Proposed

More information

AGENCY MEETING. I-10E Planning & Environmental Linkages Meeting #1 TxDOT Houston District

AGENCY MEETING. I-10E Planning & Environmental Linkages Meeting #1 TxDOT Houston District AGENCY MEETING I-10E Planning & Environmental Linkages Meeting #1 TxDOT Houston District January 25, 2018 WELCOME TxDOT Project Manager: Grant Chim, P.E. Agenda 1 Introductions / Purpose of Meeting 2 What

More information

Downtown Estes Loop Project Frequently Asked Questions

Downtown Estes Loop Project Frequently Asked Questions May 15 th, 2015 Project Status 1) Has Alternative 1 already been selected? Is it a done deal? Response: The NEPA process will proceed with environmental analysis of both the No Action and Alternative 1.

More information

Purpose of the Public Hearing

Purpose of the Public Hearing www.virginiadot.org Public Hearings Interstate 66 - Outside the Beltway Tier 1 Draft Environmental Impact Statement From U.S. Route 15 To I-495 Prince William and Fairfax Counties Wednesday, March 13,

More information

CMNAA. Central Manatee Network Alternatives Analysis Alternatives Public Meeting CMNAA STUDY PROCESS. STUDY AREA 17th St. W

CMNAA. Central Manatee Network Alternatives Analysis Alternatives Public Meeting CMNAA STUDY PROCESS. STUDY AREA 17th St. W District One CMNAA Central Manatee Network Alternatives Analysis December 12, 2017 5:00 pm - 7:00 pm First Baptist Church 1306 Manatee Ave. W, Bradenton, FL 34205 Central Manatee Network Alternatives Analysis

More information

2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM

2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM 2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM A. District: 1 2 3 4 5 6 7 TPK C.O. B. Nomination Category: (Select only one category) Outstanding Major Project Outstanding

More information

Central Manatee Network Alternatives Analysis

Central Manatee Network Alternatives Analysis District One CMNAA Central Manatee Network Alternatives Analysis Central Manatee Network Alternatives Analysis The Florida Department of Transportation (FDOT) is conducting the Central Manatee Network

More information

Work Breakdown Structure Element Dictionary Preliminary Engineering

Work Breakdown Structure Element Dictionary Preliminary Engineering Element Name Initiation PE 3.1 Initiation includes the implementation of the project s funding and notification of the consultant or in-house design staff to commence work, the Kickoff Meeting with the

More information

Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Four

Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Four DISTRICT FOUR PROJECT OVERVIEW Florida s Turnpike Enterprise continues to make significant project investments in District Four. In fiscal years 2014 and 2015, current Turnpike projects total over $127

More information

I-10 KENDALL EXTENSION. Open House

I-10 KENDALL EXTENSION. Open House I-10 KENDALL EXTENSION Open House The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT

More information

IH 820 Corridor Improvement Study Randol Mill Road To North SH 121 Interchange. Public Meeting. Thursday April 4, 2013

IH 820 Corridor Improvement Study Randol Mill Road To North SH 121 Interchange. Public Meeting. Thursday April 4, 2013 IH 820 Corridor Improvement Study Randol Mill Road To North SH 121 Interchange Public Meeting Thursday April 4, 2013 1 Project Contacts: TxDOT-Fort Worth District John R. Tillinghast, P.E. IH 820 Project

More information

I-15 South, MP 0 to MP 16 Environmental Assessment. Public Hearing. August 7, :00 PM to 7:00 PM

I-15 South, MP 0 to MP 16 Environmental Assessment. Public Hearing. August 7, :00 PM to 7:00 PM I-15 South, MP 0 to MP 16 Environmental Assessment Public Hearing August 7, 2012 5:00 PM to 7:00 PM 1 PROJECT OVERVIEW The Federal Highway Administration (FHWA) and the Utah Department of Transportation

More information

NEPA and Design Public Hearings

NEPA and Design Public Hearings NEPA and Design Public Hearings Monday, December 5, 2016 Washington-Lee High School 1301 N. Stafford Street Arlington, VA 22201 Thursday, December 8, 2016 Mary Ellen Henderson Middle School 7130 Leesburg

More information

Kentucky River Area Development District

Kentucky River Area Development District Kentucky River Area Development District Regional Transportation Planning Committee DRAFT Regional Goals & FY 2016 Approved: August 12, 2015 KYTC MISSION STATEMENT: To provide a safe, secure, and reliable

More information

CORRIDOR ALTERNATIVES EVALUATION SUMMARY REPORT

CORRIDOR ALTERNATIVES EVALUATION SUMMARY REPORT CORRIDOR ALTERNATIVES EVALUATION SUMMARY REPORT GULF COAST PARKWAY PD&E STUDY from US 98 to US 231 with a connection to US 98 in Springfield Gulf County and Bay County, Florida FINANCIAL PROJECT ID NUMBER:

More information

Regional Transportation Studies Regional Council

Regional Transportation Studies Regional Council Pima Association of Governments 1 E. Broadway, Tucson, Arizona Santa Rita Conference Room Regional Transportation Studies Regional Council September 28, 2017 I-11 Tier 1 Environmental Impact Statement

More information

VENETIAN CAUSEWAY. (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE. FM No.

VENETIAN CAUSEWAY. (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE. FM No. VENETIAN CAUSEWAY (Venetian Way) Project Development & Environment (PD&E) Study FROM NORTH BAYSHORE DRIVE TO PURDY AVENUE FM No. 422713-2-22-01 Efficient Transportation Decision Making (ETDM): 12756 Project

More information

FY 2019 Unified Planning Work Program FINAL. Regional Intergovernmental Council. June 14, Kanawha Putnam Metropolitan Planning Organization

FY 2019 Unified Planning Work Program FINAL. Regional Intergovernmental Council. June 14, Kanawha Putnam Metropolitan Planning Organization FY 2019 Unified Planning Work Program FINAL Regional Intergovernmental Council Kanawha Putnam Metropolitan Planning Organization June 14, 2018 315 D Street. South Charleston, WV. 25303 The Unified Planning

More information

US 27 MULTIMODAL CORRIDOR TREASURE COAST REGIONAL PLANNING COUNCIL SOUTH FLORIDA REGIONAL PLANNING COUNCIL

US 27 MULTIMODAL CORRIDOR TREASURE COAST REGIONAL PLANNING COUNCIL SOUTH FLORIDA REGIONAL PLANNING COUNCIL US 27 MULTIMODAL CORRIDOR TREASURE COAST REGIONAL PLANNING COUNCIL SOUTH FLORIDA REGIONAL PLANNING COUNCIL JOINT MEETING OCTOBER 12, 2018 Future Corridors Auburndale Winter Haven ILC (CSX Rwy) Tampa Airport

More information

Air Quality Analysis Technical Memorandum

Air Quality Analysis Technical Memorandum Air Quality Analysis Technical Memorandum Segment 2: State Road 400 (SR 400) / Interstate 4 (I-4) from West of SR 528 (Beachline Expressway) to West of SR 435 (Kirkman Road) Orange County (75280), Florida

More information

Environmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX

Environmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX This document is scheduled to be published in the Federal Register on 10/06/2014 and available online at http://federalregister.gov/a/2014-23711, and on FDsys.gov [4910-22] DEPARTMENT OF TRANSPORTATION

More information

5.3 Noise Impact Analysis

5.3 Noise Impact Analysis 5.3 Noise Impact Analysis Existing and future traffic noise levels for the No Build and Build Alternatives were predicted for noise sensitive receivers at 43 monitoring stations within the project study

More information

SH 35 Public Meeting

SH 35 Public Meeting SH 35 Public Meeting Major Corridor Feasibility Study Environmental Impact Statement March 27 and 28, 2007 Good evening and welcome to the State Highway 35 Public Meeting. This meeting is being conducted

More information

Torbram Road Improvements From Queen Street East to Bovaird Drive

Torbram Road Improvements From Queen Street East to Bovaird Drive Torbram Road Improvements From Queen Street East to Bovaird Drive Municipal Class EA Study Public Information Centre No. 1 November 16 2017 6:30 pm 8:30 pm Please sign in so we can keep you updated on

More information

Appendix C - Highway 400 Widening and Interchange Evaluation Summary Tables

Appendix C - Highway 400 Widening and Interchange Evaluation Summary Tables Highway 400 Improvements from 1 km South of Highway 89 to the Junction of Highway 11 Appendix C - Highway 400 Widening and Interchange Tables Prepared for: Ontario Ministry of Transportation Four General

More information

RESOLUTION NO:

RESOLUTION NO: RESOLUTION NO: 11-031 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PASO ROBLES CERTIFYING THE FINAL ENVIRONMENTAL IMPACT REPORT FOR THE 2011 CIRCULATION ELEMENT OF THE GENERAL PLAN AND ADOPTING FINDINGS,

More information

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018 What is the Carolina Crossroads Project? The South Carolina Department of Transportation (SCDOT), in cooperation with the Federal Highway Administration (FHWA), is proposing to upgrade and redesign a key

More information

Proposed SM Wright Project on I-45 / US 175 / SH 310

Proposed SM Wright Project on I-45 / US 175 / SH 310 Proposed SM Wright Project on I-45 / US 175 / SH 310 Senator Royce West Town Hall Bill Hale, P.E. TxDOT Dallas District Matt Craig, P.E. Halff Associates, Inc. May 4, 2013 1 30 45 Proposed Trinity Parkway

More information

Lee County Artesian Well Abandonment Project

Lee County Artesian Well Abandonment Project Lee County Artesian Well Abandonment Project Background Uncontrolled, improperly constructed, deteriorated or abandoned artesian (free-flowing) wells can have an adverse impact on the quantity and quality

More information

Long Range Transportation Plan

Long Range Transportation Plan Charlotte County-Punta Gorda Metropolitan Planning Organization Long Range Transportation Plan Adopted October 2015 Board Charlotte County Commissioner Christopher G. Constance (Chair) Commissioner Stephen

More information

High Desert Corridor Draft EIS/EIR Public Hearings

High Desert Corridor Draft EIS/EIR Public Hearings High Desert Corridor Draft EIS/EIR Public Hearings Agenda > Registration/Open House (6pm 6:30pm) > Draft EIS/EIR Presentation (6:30pm 7pm) > Public Comment (7pm 8:30pm) Purpose of Today s Hearing > Provide

More information

I-15/US 93 Garnet Interchange & US 93 Improvements WELCOME. Public Information Meeting October 6, 2016

I-15/US 93 Garnet Interchange & US 93 Improvements WELCOME. Public Information Meeting October 6, 2016 I-15/US 93 Garnet Interchange & US 93 Improvements WELCOME Public Information Meeting October 6, 2016 Slide 1 What to Expect Tonight Project background Project goals Alternatives considered and proposed

More information

River Valley. Intermodal Facilities. February Prepared by: Federal Highway Administration Draft Environmental Impact Statement

River Valley. Intermodal Facilities. February Prepared by: Federal Highway Administration Draft Environmental Impact Statement Prepared by: River Valley Intermodal Facilities Federal Highway Administration Draft Environmental Impact Statement River Valley Regional Intermodal Facilities Authority February 2006 and Arkansas State

More information

Public Notice. Between County Road 700 South and County Road 500 South near Francesville, Pulaski County, Indiana.

Public Notice. Between County Road 700 South and County Road 500 South near Francesville, Pulaski County, Indiana. Public Notice Public Notice No. Date: Closing Date: US Army Corps LRL-2017-660-sjk 20 Apr 2018 21 May 2018 of Engineers Louisville District Please address all comments and inquiries to: U.S. Army Corps

More information

Decision Support Systems for FDOT District 4 TSM&O

Decision Support Systems for FDOT District 4 TSM&O Decision Support Systems for FDOT District 4 TSM&O Melissa Ackert, P.E. District Transportation System Management & Operations Engineer FDOT District 4 Traffic Operations 1 Transportation Systems Management

More information

MOBILITY 2045: A FOCUS ON TRANSPORTATION CHOICE:

MOBILITY 2045: A FOCUS ON TRANSPORTATION CHOICE: Mobility 2045: The Metropolitan Transportation Plan for North Central Texas is the defining vision for the multimodal transportation system in the Dallas- Fort Worth Metropolitan Planning Area. The plan,

More information

I-20 East Transit Initiative

I-20 East Transit Initiative I-20 East Transit Initiative Technical Advisory Committee (TAC) Meeting June 11 th, 2013 Introductions Purpose of Today s Meeting Project Review Preliminary Environmental Findings Next Steps Project Status

More information