Pilot Pond Update and Harvest Trials. Large Scale Pilot Harvesting Trials March 2018

Size: px
Start display at page:

Download "Pilot Pond Update and Harvest Trials. Large Scale Pilot Harvesting Trials March 2018"

Transcription

1 ASX Release Thursday 22 March 2018 Pilot Pond Update and Harvest Trials Highlights Evaporation Pond trials continue to provide invaluable insights at a representative scale not previously undertaken in Australia. 164 million litres of brine have been pumped since pump testing began, of which 83 million litres of brine have been pumped into the trial ponds. More than 10,000 tonnes of salts have been produced so far, including 3,160 tonnes of mixed potassium salts that can be processed to generate approximately 520 tonnes of SOP. Harvesting trials are ongoing providing input into harvest equipment selection and overall full scale harvest planning. Salt harvesting can commence on the engineered,1mm HDPE-lined off lake ponds after deposition of a mm protective salt layer. This takes 3-6 months to develop, representing a significant time saving of at least 12 months to first SOP production in comparison to utilising lake or clay based pond surfaces. Brine concentration curves have performed consistently as the trials have scaled up from early pilot scale and bench top studies. Time required to achieve steady state operations is approximately six months, depending on seasonal effects (temperature and humidity). Kalium Lakes Limited (KLL) is pleased to provide an update on its Large Scale Pilot Evaporation trials at the 100% owned Beyondie Sulphate Of Potash Project (BSOPP). The pilot trials commenced construction in June 2017 with first brine entering the system in August These pilot ponds have been run continuously and form the basis of pond design for the Bankable Feasibility Study (BFS). Page 1 of 7

2 Recent harvest trials are now providing detailed data about the salts, brines and techniques required to efficiently run the future operation. Managing Director, Brett Hazelden, commented: These Large Scale Pilot Evaporation Ponds cover around five MCGs in total size and have proved invaluable in testing every facet of a fully operational potash evaporation pond process. It has enabled Kalium Lakes to assess pump and pipe requirements from bores and trenches, determine pond design parameters to achieve a fully gravity fed system, observe brine evaporation behaviour and measure salt crystallisation and growth, test harvesting techniques and identify maintenance requirements. These are the largest scale pilot pond trials in Australia, which provide government agencies, investors and prospective debt financiers with a high level of certainty on scale up parameters that are being included in the Bankable Feasibility Study, Mr Hazelden said. A short video showing some of the harvest trials can viewed on the Company s website by using this link. Large Scale Pilot Evaporation Pond Program The Large Scale Pilot Evaporation Pond program reflects KLL s development strategy, where a staged development approach is preceded by a pilot program to verify current assumptions and operational parameters along with production of bulk samples for marketing purposes. This trial program is based at the Beyondie, 10 Mile and Sunshine areas of the BSOPP. The pilot ponds have been operated on a continuous basis (not batch) as recommended by KLL s key consultants K-UTEC, DRA and DSB International. The process involves pumping brine from a bore and/or trench into a concentration pond which evaporates water prior to reaching the salting point (refer to figure 1). At this point brine is gravity fed (not pumped) to the next series of ponds where the sodium salts crystallise out of solution. The brine is again gravity fed to the series of ponds where potassium salts commence crystallising out of solution. Finally, a residual magnesium bittern remains, representing only 1-2% of the original brine volume pumped into the concentrator pond. This residual brine has been the subject of magnesium product investigations and pilot trials. Importantly all the ponds are tiered so that the brine can flow via gravity, without the need for pumping between ponds. Page 2 of 7

3 Figure 1: Indicative Evaporation Pond Profile The Large Scale Pilot Evaporation Pond program has provided a detailed understanding of the following parameters, which are being optimised as part of the Bankable Feasibility Study currently underway and due for completion in Q3 2018: Layout and number of ponds Dimensions of ponds to optimise flow path Optimum brine depth within ponds Differential evaporation rates as the brine density increases Brine concentration profile and phase chemistry over seasonal and diurnal ranges Brine entrainment in salt floors Pond floor and liner requirements Harvest equipment and plans Pond start-up procedure Time required to achieve steady state operations Operations and maintenance requirements Page 3 of 7

4 The current large scale evaporation trial has been run continuously over the last seven months and follows two previous smaller scale pilot trials, all of which were utilised to inform the BFS design parameters. The Kalium Lakes pilot program has spanned more than two years and covered all seasons providing an invaluable data set. A summary of high level observations and commentary is provided below: 164 million litres of brine have been pumped since pump testing began, of which 83 million litres of brine have been pumped into the trial ponds. More than 10,000 tonnes of salts have been produced so far, including 3,160 tonnes of mixed potassium salts that can be processed to generate approximately 520 tonnes of SOP. Salt growth in each of the ponds varies in thickness from 95mm to 305mm during the seven month trial period, which is an average of 0.52mm to 2.28mm per day salt growth. It should be noted that ponds were progressively brought online during a number of months as seen in the time series photos (below). Importantly the harvested potassium salts contain ~7.5% K2O, accordingly, to achieve 1 tonne of SOP product requires ~7 tonnes of harvested mixed potassium salts which are then treated in the purification plant to remove residual sodium, magnesium and chloride salts. Salt harvesting can commence on the engineered,1mm HDPE-lined off lake ponds after deposition of a mm protective salt layer. It will take 3-6 months to develop this layer, after which all other salts above this level will be harvestable.. This is a significant time saving when compared to other salt and potash brine operations around the world which are located on salt lakes or clay pans and require around 400mm of salt to form a trafficable surface on top of which your harvestable salts will be located. As a bench marking exercise, Dampier Salt crystallises mm of salt growth per annum which would appear to be similar to the KLL pilot scale trials on an annualised basis, when taking into account seasonal factors. Therefore to crystallise 400mm of salts would require ~18 months, with a further period to generate sufficient harvestable salt depths. Entrainment of potassium bearing brine is between 10-30% of the salt bed itself and as such needs to be treated as recovery loss or alternative recovered by drainage through harvesting of the sodium chloride salts. KLL s basis of design is to harvest sodium chloride salts to release entrained brine and also avoid costly pond wall lifts which would need to occur if the sodium chloride salt was left in the ponds. Due to Kalium Lakes low Na:K ratio, less sodium chloride salt is produced reducing harvesting requirements. All ponds require a free board design ~ 270mm for a significant 1:100 rainfall event. The brine concentration curves developed; theoretically, in the laboratory and during the initial pilot scale trials have been replicated in the large scale pilot evaporation pond trials. Differential evaporation rates occur as the brine concentration increases. This means fresh brine evaporates at a significantly faster rate compared to the last potassium mixed salt pond. This requires the evaporation pond design basis to allow for an increasing ratio of pond area to brine to achieve the targeted production rate. KLL included this in the Pre-Feasibility Study. Harvesting trials have been ongoing during March as seen in the below photos. Harvest equipment selection, pond harvest intervals and an overall full scale harvesting plan is being prepared on the back of these results for the BFS. A pond start-up procedure has been developed based on the initial start-up of the pilot ponds. Time required to achieve steady state operations is approximately six months, depending on seasonal effects (temperature and humidity). Page 4 of 7

5 Actual Large Scale Pond Brine Concentration Curves versus Previous Assumptions and Testwork Page 5 of 7

6 Large Scale Pilot Evaporation Ponds August 2017 September 2017 September 2017 October 2017 November 2017 December 2017 Large Scale Pilot Evaporation Ponds January 2018 Page 6 of 7

7 Compliance Statement The information in this document that relates to Exploration Targets, Exploration Results, Mineral Resources, Ore Reserves and Production Targets have been extracted from the report(s) listed below. 3 October 2017: Pre-Feasibility Study with Maiden Ore Reserve Confirms Low Cost, Long Life and High Margin Beyondie SOP Project. (Including the attachment, JORC (2012) and NI Technical Report, compiled by German Potash Experts and Competent Persons, K-UTEC AG Salt Technologies (K-UTEC)). The report(s) are available to be viewed on the website at: Kalium Lakes confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements and, in the case of estimates of Mineral Resources, Ore Reserve Estimates, Exploration Targets or Production Targets, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The company confirms that the form and context in which the Competent Person s findings are presented have not been materially modified from the original market announcement. Cautionary Statement Regarding Forward-Looking Information Statements regarding plans with respect to the Company s mineral properties may contain forward looking statements. Statements in relation to future matters can only be made where the Company has a reasonable basis for making those statements. This announcement has been prepared in compliance with the current JORC Code 2012 Edition and the current ASX Listing Rules. The Company believes it has a reasonable basis for making the forward-looking statements on 3 October 2017, including any production targets, based on the information contained in the announcement and in particular the JORC 2012 and NI Technical Report. All statements, trend analysis and other information contained in this document relative to markets for Kalium Lakes, trends in resources, recoveries, production and anticipated expense levels, as well as other statements about anticipated future events or results constitute forward-looking statements. Forward-looking statements are often, but not always, identified by the use of words such as seek, anticipate, believe, plan, estimate, expect and intend and statements that an event or result may, will, should, could or might occur or be achieved and other similar expressions. Forward-looking statements are subject to business and economic risks and uncertainties and other factors that could cause actual results of operations to differ materially from those contained in the forward-looking statements. Forward-looking statements are based on estimates and opinions of management at the date the statements are made. Kalium Lakes does not undertake any obligation to update forward-looking statements even if circumstances or management s estimates or opinions should change. Investors should not place undue reliance on forward-looking statements. *** ENDS *** Corporate Profile (as at 21 March 2018) Kalium Lakes Limited is an exploration and development company, focused on developing the Beyondie Sulphate Of Potash Project in Western Australia with the aim of producing Sulphate of Potash (SOP) for the domestic and international markets. The Beyondie SOP Project comprises 15 granted exploration licences and a miscellaneous licence covering an area of approximately 2,400 square kilometres. This sub-surface brine deposit will supply an evaporation and processing operation located 160 kilometres south east of Newman. The results of the Pre-Feasibility Study, announced on 3 October 2017, confirmed that the Project is technically and financially robust. The Company is also a Joint Venture partner with BCI Minerals Limited (BCI) in the Carnegie Potash Project, a potash exploration project located approximately 220 kilometres north-east of Wiluna. Carnegie comprises one granted exploration licence and two exploration licence applications covering a total area of approximately 1,700 square kilometres. Kalium Lakes Limited ABN: ASX: KLL Ordinary Shares on Issue: 169,793,465 Board of Directors: Chief Financial Officer and Joint Company Secretary: Frederick Kotzee Mal Randall Non-Executive Chairman Brett Hazelden Managing Director Rudolph van Niekerk Executive Director Joint Company Secretary: Gareth Widger Brendan O Hara Non-Executive Director Contact Details: Share Registry: Kalium Lakes Limited Computershare Investor Services Pty Ltd Unit 1, 152 Balcatta Road Level 11, 172 St Georges Terrace BALCATTA WA 6021 Perth, WA 6000 Tel: (within Australia): PO Box 610 Tel: (outside Australia): BALCATTA, WA 6914 Tel: +61 (0) info@kaliumlakes.com.au Web: Page 7 of 7

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDING 31 March 2018

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDING 31 March 2018 ASX Release Thursday 26 April 2018 Highlights QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDING 31 March 2018 Signing of the second and final Native Title Agreement, covering the eastern tenements required

More information

For personal use only

For personal use only ASX Release 13 January 2017 Agrimin Limited ABN 15 122 162 396 ASX Code: AMN Level 9, 190 St Georges Terrace Perth, Western Australia 6000 T: +61 8 6141 6304 E: admin@agrimin.com.au W: www.agrimin.com.au

More information

COMPLETION OF PROCESS TESTWORK STUDIES

COMPLETION OF PROCESS TESTWORK STUDIES ASX Release 7 February 2018 Agrimin Limited ABN 15 122 162 396 ASX Code: AMN 2C Loch Street Nedlands, Western Australia 6009 T: +61 8 9389 5363 E: admin@agrimin.com.au W: www.agrimin.com.au COMPLETION

More information

Pre-Feasibility Study Nearing Completion

Pre-Feasibility Study Nearing Completion ASX Release Thursday 23 February 2017 Highlights Pre-Feasibility Study Nearing Completion Kalium Lakes confirms work associated with the Beyondie Sulphate of Potash (SOP) Project Pre-Feasibility Study

More information

PILOT SOLAR EVAPORATION PONDS COMMISSIONED AT LAKE WELLS POTASH PROJECT, WA

PILOT SOLAR EVAPORATION PONDS COMMISSIONED AT LAKE WELLS POTASH PROJECT, WA 31 Ord Street, West Perth WA 6005 PO Box 1941, West Perth WA 6872 +61 8 9322 1003 australianpotash.com.au ABN 58 149 390 394 3 October 2017 PILOT SOLAR EVAPORATION PONDS COMMISSIONED AT LAKE WELLS POTASH

More information

Excellent Brine Test Pumping Flowrates With Consistently High Potassium Grades

Excellent Brine Test Pumping Flowrates With Consistently High Potassium Grades ASX Release Tuesday 13 June 2017 Highlights Excellent Brine Test Pumping Flowrates With Consistently High Potassium Grades Excellent ongoing Production Bore Brine Test Pumping Flowrates with pump rates

More information

POND DEVELOPMENT PROGRAM IDENTIFIES SURFACE CLAY LAYER, SUPPORTS ON-LAKE UNLINED EVAPORATION PONDS

POND DEVELOPMENT PROGRAM IDENTIFIES SURFACE CLAY LAYER, SUPPORTS ON-LAKE UNLINED EVAPORATION PONDS 31 Ord Street, West Perth WA 6005 PO Box 1941, West Perth WA 6872 +61 8 9322 1003 australianpotash.com.au ABN 58 149 390 394 27 October 2017 POND DEVELOPMENT PROGRAM IDENTIFIES SURFACE CLAY LAYER, SUPPORTS

More information

SALT LAKE POTASH PLANS SOP PILOT PLANT AT GOLDFIELDS SALT LAKES PROJECT. ONGOING DISCUSSIONS WITH PROSPECTIVE GLOBAL INDUSTRY PARTNERS.

SALT LAKE POTASH PLANS SOP PILOT PLANT AT GOLDFIELDS SALT LAKES PROJECT. ONGOING DISCUSSIONS WITH PROSPECTIVE GLOBAL INDUSTRY PARTNERS. ASX ANNOUNCEMENT 21 April 2017 SALT LAKE POTASH PLANS SOP PILOT PLANT AT GOLDFIELDS SALT LAKES PROJECT. ONGOING DISCUSSIONS WITH PROSPECTIVE GLOBAL INDUSTRY PARTNERS. The Directors of Salt Lake Potash

More information

For personal use only

For personal use only 13 October 2016 First test production bores successfully installed First two of four planned test production bores successfully installed Next two test production bores will be installed over coming weeks

More information

AUSTRALIAN POTASH COMPLETES FINAL BRINE TRANSFER

AUSTRALIAN POTASH COMPLETES FINAL BRINE TRANSFER 31 Ord Street, West Perth WA 6005 PO Box 1941, West Perth WA 6872 +61 8 9322 1003 australianpotash.com.au @OzPotash ABN 58 149 390 394 22 November 2018 AUSTRALIAN POTASH COMPLETES FINAL BRINE TRANSFER

More information

SUCCESSFUL INFILL DRILLING CAMPAIGN COMPLETED

SUCCESSFUL INFILL DRILLING CAMPAIGN COMPLETED 31 Ord Street, West Perth WA 6005 PO Box 1941, West Perth WA 6872 +61 8 9322 1003 australianpotash.com.au @OzPotash ABN 58 149 390 394 13 November 2018 SUCCESSFUL INFILL DRILLING CAMPAIGN COMPLETED DEEP

More information

For personal use only

For personal use only ASX RELEASE 1 MARCH 2017 BC IRON AND KALIUM LAKES ENTER INTO JOINT VENTURE ON CARNEGIE POTASH PROJECT Joint venture agreement with the objective of fast tracking the Carnegie Project to become one of the

More information

ABN: AUGUST

ABN: AUGUST ABN: 98 117 085 748 AUGUST 2018 1 Link to video: http://bit.ly/saltlakepotash-diggersdealers2018 Potash An essential plant nutrient Two distinct products MOP (Muriate of Potash) KCl Potassium Chloride

More information

For personal use only

For personal use only ASX RELEASE 20 April 2018 Toro Advances Next Stage of Beneficiation and Process Design Studies for the Wiluna Uranium Project Highlights Flow sheet re-design may reduce capital cost of hydrometallurgy

More information

For personal use only

For personal use only ASX RELEASE QUARTERLY REPORT FOR THE PERIOD ENDING 30 JUNE 2017 Highlights 28 July 2017 R&D Rebate of $2.6 million received. ASX CODE RWD Groundwater licence application for abstraction of 63 G/L of brine

More information

For personal use only

For personal use only ASX Release 29 April 2015 High Purity SOP Samples from Colluli Pilot Plant Delivered to Support Marketing Company Details ASX Code: STB Share Price $0.30 Market Cap $45M Shares on issue Company options

More information

GROW WITH US INVESTOR PRESENTATION MARCH 2019

GROW WITH US INVESTOR PRESENTATION MARCH 2019 GROW WITH US INVESTOR PRESENTATION MARCH 2019 - Emerging SOP Province located in WA Goldfields Very accessible infrastructure options Scaleable volume growth across multiple lakes EMERGING GLOBAL FERTILISER

More information

For personal use only

For personal use only 2 May 2018 ASX Announcement METALLURGICAL TESTWORK CONFIRMS WILUNA TRANSITIONAL RESERVES AMENABLE TO PROCESSING THROUGH THE EXISTING WILUNA CIL PLANT Highlights Expansion PFS published in Aug 17 includes

More information

FIRST GOLD ORE DISPATCHED FROM ULYSSES

FIRST GOLD ORE DISPATCHED FROM ULYSSES Genesis Minerals Limited (ASX: GMD) ASX Announcement 14 November 2016 FIRST GOLD ORE DISPATCHED FROM ULYSSES Genesis poised for first cash-flow as first parcel of ore departs for Paddington gold plant

More information

For personal use only

For personal use only ASX Announcement 19 December 2014 BOARD OF DIRECTORS Paul Murphy (Non-Executive Chairman) Bryan Dixon (Managing Director) Alan Thom (Executive Director) Greg Miles (Non-Executive Director) ASX CODE BLK

More information

For personal use only

For personal use only SUITE H4.6, LEVEL 4, 172 NORTH TERRACE ADELAIDE SA PO BOX 8242 STATION ARCADE SA 5000 Telephone 08 7325 6500 Facsimile 08 8212 6818 Quarterly Report to ASX for the period 1 April to 30 June 2014 Highlights

More information

For personal use only

For personal use only For personal use only DISCLAIMER & FORWARD LOOKING STATEMENTS This presentation has been prepared by Goldphyre Resources Ltd ( GPH ). It contains background information about GPH current at the date of

More information

DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD November 3 rd 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD Construction work at Gascoyne s 100%

More information

Maiden Ore Reserve for Camel Creek JV

Maiden Ore Reserve for Camel Creek JV 10 September 2013 Manager Company Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street SYDNEY NSW 2000 ABN 85 003 257 556 Maiden Ore Reserve for Camel

More information

For personal use only

For personal use only Metals of Africa Limited (ASX: MTA) 8 June 2016 Contact Details Cherie Leeden Managing Director cherie@metalsofafrica.com.au James Moses Media and Investor Relations Mandate Corporate +61 420 991 574 james@mandatecorporate.com.au

More information

For personal use only

For personal use only ABN 64 123 993 233 ASX Announcement 21 March ABN 2016 64 123 993 233 Leigh Creek Magnesite - Project Study Highlights The Study examines possible open pit mining and processing options and provides a strong

More information

For personal use only

For personal use only ASX Announcement Arafura Extends Nolans Mine Life To Beyond Thirty Years 2 September 217 Two-thirds of Measured and Indicated Resources inventory identified as NdPr-bearing phosphate-rich material types

More information

DISCLAIMER & FORWARD LOOKING STATEMENTS

DISCLAIMER & FORWARD LOOKING STATEMENTS DISCLAIMER & FORWARD LOOKING STATEMENTS This presentation has been prepared by Goldphyre Resources Ltd ( GPH ). It contains background information about GPH current at the date of this presentation. The

More information

Successful Production of Premium Quality Boric Acid

Successful Production of Premium Quality Boric Acid ASX: GSC Suite 203, 161 Walker Street North Sydney NSW 2060 Successful Production of Premium Quality Boric Acid Highlights Premium quality boric acid produced from Rhyolite Ridge lithium-boron mineralisation

More information

Great Western Scoping Study Update & Onsite Gold Processing

Great Western Scoping Study Update & Onsite Gold Processing ASX RELEASE 10 August 2017 ABN: 45 116 153 514 ASX: TMX Great Western Scoping Study Update & Onsite Gold Processing Terrain Minerals Limited (ASX: TMX) is pleased to provide the following update on its

More information

For personal use only

For personal use only ASX RELEASE 5 December 2016 Successful beneficiation studies highlight potential for substantial cost reduction for Wiluna Uranium Project Toro Energy Limited (ASX:TOE) announces Beneficiation and Process

More information

Bryah Secures Option over Historic Manganese Mine

Bryah Secures Option over Historic Manganese Mine ASX Announcement 7 May 2018 Bryah Secures Option over Historic Manganese Mine HIGHLIGHTS Bryah Resources secures exclusive 1 year option to purchase Mining Lease covering the historical Horseshoe South

More information

Reward Minerals Limited. AGM Presentation May 2013

Reward Minerals Limited. AGM Presentation May 2013 Reward Minerals Limited AGM Presentation May 2013 Forward Looking Statements & Disclaimer This document includes forward-looking statements. When used in this document, the words such as could, plan, estimate,

More information

DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES

DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES July 25 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES The Process

More information

Lake Wells Potash Project

Lake Wells Potash Project ASX: GPH Lake Wells Potash Project Addressing Australia s Potash Demand Disclaimer Forward-looking statements This presentation has been prepared by Goldphyre Resources Ltd ( GPH ). This document contains

More information

For personal use only

For personal use only ABN 79 106 879 690 30 August 2016 The Manager Companies ASX Limited 20 Bridge Street Sydney NSW 2000 (11 pages by email) Updated Internal Scoping Study Delivers Positive Results (ASX: AUK) The Directors

More information

CLEAN TEQ COMPLETES SUCCESSFUL PILOTING OF PROPRIETARY CIF TECHNOLOGY AT COAL SEAM GAS FIELDS IN QUEENSLAND

CLEAN TEQ COMPLETES SUCCESSFUL PILOTING OF PROPRIETARY CIF TECHNOLOGY AT COAL SEAM GAS FIELDS IN QUEENSLAND ASX / Media Announcement Melbourne, 26 August 2013 CLEAN TEQ COMPLETES SUCCESSFUL PILOTING OF PROPRIETARY CIF TECHNOLOGY AT COAL SEAM GAS FIELDS IN QUEENSLAND TECHNOLOGY DEMONSTRATES SUPERIOR WATER RECOVERIES

More information

NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE

NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE ASX RELEASE 11 December 2012 NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE Independently prepared JORC Ore Reserve for Nolans Bore to support a 22 year mine life; 95% of Measured and Indicated Resources

More information

Garden Well Gold Deposit. Reserve Increases to 1.66 Million Ounces

Garden Well Gold Deposit. Reserve Increases to 1.66 Million Ounces ABN 28 009 174 761 31 March 2011 Manager Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street Sydney NSW 2000 www.regisresources.com Level 1 1 Alvan

More information

Confidence in Carrapateena project grows

Confidence in Carrapateena project grows 7 NOVEMBER 2016 Confidence in Carrapateena project grows Carrapateena Pre-Feasibility Study released - project competitive with, or better than comparable long-life copper assets globally Project metrics

More information

DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD December 8 th 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD Construction at Gascoyne s

More information

Positive Lerokis Copper Recovery Testwork

Positive Lerokis Copper Recovery Testwork For ASX Market Release: 20 November 2017 Positive Lerokis Copper Recovery Testwork HIGHLIGHTS Positive copper recovery results have been received from diamond drill core samples from Lerokis, the next

More information

For personal use only

For personal use only ASX Release 6 February 2014 Positive results from processing review studies on Colluli Potash Project Company Details ASX Code: STB Share Price $0.20 Market Cap $26M Shares on issue Company options 128M

More information

MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES

MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES ASX Release: 9 September 2010 MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES Definitive Mining Studies confirm continuity, quality and quantum of Ore body at MARILLANA Detrital Ore Reserves

More information

Investor Presentation

Investor Presentation ASX AMN Investor Presentation September 2016 Important Notices and Disclaimers Nature of Document This presentation has been prepared as a summary only, and does not contain all information about Agrimin

More information

STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS

STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS ASX RELEASE 30th January 2014 STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS Uranium developer Toro Energy Limited (ASX: TOE) (Toro) today announced the completion of an independent Mining

More information

Australian Mines to set benchmark with largest sample of battery-grade cobalt and nickel sulphate ever exported from Australia

Australian Mines to set benchmark with largest sample of battery-grade cobalt and nickel sulphate ever exported from Australia 2 July 2018 Australian Mines to set benchmark with largest sample of battery-grade cobalt and nickel sulphate ever exported from Australia HIGHLIGHTS 40 kilograms of battery-grade nickel sulphate (NiSO4)

More information

Underground Ore Reserve growth at Prominent Hill extends mine life to 2030

Underground Ore Reserve growth at Prominent Hill extends mine life to 2030 12 NOVEMBER 2018 Underground Ore Reserve growth at Prominent Hill extends mine life to 2030 Prominent Hill underground Ore Reserve increased to 40Mt @ 1.7% copper equivalent i with a 50% increase in Proved

More information

Re : Completion of the Barnes Hill drill-out

Re : Completion of the Barnes Hill drill-out 30 March 2010 The Manager Company Announcements Office Australian Securities Exchange By e-lodgement (ASX code: MFC) Dear Sir/Madam Re : Completion of the Barnes Hill drill-out The following comprises

More information

For personal use only

For personal use only 1 SCOPING STUDY CONFIRMS PROFITABLE POTENTIAL OF HASTINGS HEAVY RARE EARTH PROJECT The Manager Company Announcements Office Australian Securities Exchange 4th Floor, 20 Bridge Street SYDNEY NSW 2000 Hastings

More information

Reward Minerals Limited

Reward Minerals Limited Reward Minerals Limited Presentation July 2013 Forward Looking Statements & Disclaimer This document includes forward-looking statements. When used in this document, the words such as could, plan, estimate,

More information

OUTSTANDING RESULTS FROM ILMENITE UPGRADE TESTWORK

OUTSTANDING RESULTS FROM ILMENITE UPGRADE TESTWORK ASX and Media Release 9 September, 2015 KEY POINTS OUTSTANDING RESULTS FROM ILMENITE UPGRADE TESTWORK Breakthrough result for Thunderbird, with testwork confirming that the primary ilmenite can be substantially

More information

HORSESHOE LIGHTS PROJECT ASX/MEDIA ANNOUNCEMENT

HORSESHOE LIGHTS PROJECT ASX/MEDIA ANNOUNCEMENT OXIDE COPPER STUDY UNDERWAY AT 8 HORSESHOE LIGHTS PROJECT ASX/MEDIA ANNOUNCEMENT 20 AUGUST 2015 ASX Code: HOR Management Mr Neil Marston Managing Director/Company Secretary Mr Michael Fotios Non-Executive

More information

ASX ANNOUNCEMENT 26 November 2015

ASX ANNOUNCEMENT 26 November 2015 ASX ANNOUNCEMENT 26 November 2015 2015 AGM PRESENTATION VDM Group Limited (VDM) today held its Annual General Meeting in Perth, Western Australia. The following presentation of the SANY VDM Joint Venture

More information

personal use only Mine Development Capital Costs revised for the Yangibana Rare Earths Project 11 th March 2019

personal use only Mine Development Capital Costs revised for the Yangibana Rare Earths Project 11 th March 2019 personal use only 11 th March 2019 Hastings Technology Metals Limited ABN 43 122 911 399 ASX Stock Code: HAS Address: Level 8 Westralia Plaza 167 St Georges Terrace Perth WA 6000 Box 6 Westralia Plaza

More information

For personal use only

For personal use only ASX/Media Announcement 6 September 2016 PILBARA COMPLETES KEY METALLURGICAL TESTWORK PROGRAM AHEAD OF PILGANGOORA DEFINITIVE FEASIBILITY STUDY Phase 2 metallurgical testwork and process design completed

More information

For personal use only

For personal use only 28 February 2013 Another Major Milestone for IOH Iron Valley Transaction with Mineral Resources Limited Highlights Mine Gate Sale Agreement executed with Mineral Resources Limited (MIN) MIN to develop

More information

121 MINING INVESTMENT CONFERENCE HONG KONG

121 MINING INVESTMENT CONFERENCE HONG KONG ASX / MEDIA RELEASE 23 April 2018 121 MINING INVESTMENT CONFERENCE HONG KONG St George Mining Limited (ASX: SGQ) ( St George or the Company ) is participating at the 121 Mining Investment Conference in

More information

For personal use only

For personal use only ASX Code: MRP MacPhersons Resources Ltd ABN 98 139 357 967 ACN 139 357 967 Contact Details PO Box 10977 109 Maritana Street Kalgoorlie WA 6430 T +61 (0) 8 9091 7515 F +61 (0) 8 9091 7610 E info@mrpresources.com.au

More information

Potash is the main source of fertiliser in the world. Potash demand is expected to be underpinned by a rapidly growing world population.

Potash is the main source of fertiliser in the world. Potash demand is expected to be underpinned by a rapidly growing world population. WHY POTASH? As the world s population increases, issues of food security are becoming more and more prominent. The amount of arable land is decreasing and what remains is being depleted of nutrients from

More information

DALGARANGA PRE-FEASIBILITY UPDATE

DALGARANGA PRE-FEASIBILITY UPDATE January 19th, 2016 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA PRE-FEASIBILITY UPDATE PFS Pit optimisations indicate a production target far larger than anticipated

More information

For personal use only

For personal use only January 19th, 2016 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA PRE-FEASIBILITY UPDATE PFS Pit optimisations indicate a production target far larger than anticipated

More information

AMMAROO PHOSPHATE PRE-FEASIBILITY STUDY AND KARINGA LAKES POTASH SCOPING STUDY UPDATES

AMMAROO PHOSPHATE PRE-FEASIBILITY STUDY AND KARINGA LAKES POTASH SCOPING STUDY UPDATES ASX Release 3 rd July 2014 Listings Officer Company Announcements ASX Limited, Melbourne ASX ANNOUNCEMENT ASX CODE: RUM ABN: 33 122 131 622 REGISTERED OFFICE 20/90 Frances Bay Drive Stuart Park NT 0820

More information

For personal use only

For personal use only 17 th August 2017 ASX via Electronic Lodgement San Jose Lithium-Tin Deposit Lithium Carbonate Processing Route and Cost Estimates Highlights Plymouth has completed an estimate of the direct processing

More information

Prieska Zinc-Copper Project Advanced-Stage Metallurgical Tests Achieve Impressive Recoveries to Saleable Product

Prieska Zinc-Copper Project Advanced-Stage Metallurgical Tests Achieve Impressive Recoveries to Saleable Product ASX/JSE RELEASE: 12 June 2018 Prieska Zinc-Copper Project Advanced-Stage Metallurgical Tests Achieve Impressive Recoveries to Saleable Product Advanced-stage metallurgical testing of Prieska Project Deep

More information

Haoma Mining NL A.B.N

Haoma Mining NL A.B.N Haoma Mining NL A.B.N 12 008 676 177 Registered Office & Head Office: Level 1, 401 Collins Street, Melbourne, Vic., 3000, GPO Box 2282U, Melbourne, Vic., 3001. Telephone (03) 9629 6888, Facsimile (03)

More information

For personal use only

For personal use only The Company Announcements Officer Australian Securities Exchange Ltd via electronic lodgement The following is an Inside Briefing interview with South Boulder Mines Chief Executive Paul Donaldson In this

More information

DEVELOPING FERTILISER PROJECTS TO MEET THE GROWING DEMAND IN BRAZIL AND THE WORLD

DEVELOPING FERTILISER PROJECTS TO MEET THE GROWING DEMAND IN BRAZIL AND THE WORLD EST MINE HARVEST MINERALS Developing Fertiliser Projects DEVELOPING FERTILISER PROJECTS TO MEET THE GROWING DEMAND IN BRAZIL AND THE WORLD Corporate advisor: Investor Presentation July 2015 ASX: HMI www.harvestminerals.net

More information

POPLAR GROVE MINE CONSTRUCTION UPDATE

POPLAR GROVE MINE CONSTRUCTION UPDATE 13 December 2017 POPLAR GROVE MINE CONSTRUCTION UPDATE HIGHLIGHTS: Started vertical construction of the preparation plant at the Poplar Grove Mine Began construction of keyhole for the slope decline to

More information

For personal use only

For personal use only Mutiny makes substantial metallurgical performance gains Forecast copper recoveries increased from 58.5% to 64% in the oxide zone and copper concentrate grade increased from 21.5% Cu to 35% Cu Forecast

More information

For personal use only

For personal use only ASX RELEASE 16 February 2017 DRILL PROGRAMME AND TIMEFRAME CONFIRMED FOR OPUWO COBALT PROJECT HIGHLIGHTS Drill programme commencement scheduled for early March. First phase of drilling aims to systematically

More information

FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET

FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET May 30 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET First Gold poured from Dalgaranga

More information

For personal use only

For personal use only ASX Release 22 December 2016 BLACK ROCK MINING TO EXPAND PFS TO 120,000 TPA IN TWO STAGES WITH INITIAL 60,000 TPA PRODUCTION Highlights PFS being upgraded to incorporate high grade Cascades Mineral Resource

More information

NEW CENTURY SELECTS PREFERRED HYDRAULIC MINING CONTRACTORS FOR CENTURY TAILINGS OPERATIONS

NEW CENTURY SELECTS PREFERRED HYDRAULIC MINING CONTRACTORS FOR CENTURY TAILINGS OPERATIONS ASX / MEDIA ANNOUNCEMENT ASX: NCZ 22 February 2018 NEW CENTURY SELECTS PREFERRED HYDRAULIC MINING CONTRACTORS FOR CENTURY TAILINGS OPERATIONS National Pump & Energy Ltd, partnered with Paragon Tailings

More information

Focused on delivery of high-value metals critical to energy revolution. Annual General Meeting 20 November 2018

Focused on delivery of high-value metals critical to energy revolution. Annual General Meeting 20 November 2018 Focused on delivery of high-value metals critical to energy revolution Annual General Meeting 20 November 2018 Important Information Forward Looking Statement This presentation may contain certain statements

More information

DRA Global confirmed as preferred EPCM contractor for Colluli

DRA Global confirmed as preferred EPCM contractor for Colluli Announcement Thursday, 27 September 2018 DRA Global confirmed as preferred EPCM contractor for Colluli CMSC has confirmed DRA as the preferred EPCM contractor for Colluli DRA is a high quality multi-disciplinary

More information

For personal use only

For personal use only ASX RELEASE Sorby Hills Silver Lead Project Major Milestone Achieved with Environmental Approval As announced on 3 April, the WA Minister for Environment has approved the development of the Sorby Hills

More information

Optimisation Success Leads to Further Significant Reductions in Leach Time and Acid Consumption

Optimisation Success Leads to Further Significant Reductions in Leach Time and Acid Consumption ASX: GSC Suite 203, 161 Walker Street North Sydney NSW 2060 Optimisation Success Leads to Further Significant Reductions in Leach Time and Acid Consumption Highlights Latest results from optimisation testwork

More information

For personal use only

For personal use only 28 November 2017 Corporate Details Ordinary Shares: 780,917,069 Market Capitalisation: ~$156 million Cash and bullion at 30 September 2017: ~$20.1 million Debt: NIL ASX Code: MOY Board of Directors Greg

More information

For personal use only

For personal use only Rum Jungle Resources Limited TRANSITIONING FROM EXPLORER TO FERTILISER MINERAL PRODUCER RBS MORGANS NOOSA MINING CONFERENCE 17-18 July 2014 Chris Tziolis Managing Director Disclaimer and competent persons

More information

PILBARA COMMENCES DRILLING AT TABBA TABBA TANTALUM PROJECT AFTER SECURING FIRST TRANCHE OF FUNDING

PILBARA COMMENCES DRILLING AT TABBA TABBA TANTALUM PROJECT AFTER SECURING FIRST TRANCHE OF FUNDING ACN 112-425-788 ASX ANNOUCEMENT 7 th NOVEMBER 2013 PILBARA COMMENCES DRILLING AT TABBA TABBA TANTALUM PROJECT AFTER SECURING FIRST TRANCHE OF FUNDING DRILLING AND MINING STUDIES UNDERWAY HARD ON THE HEELS

More information

HONEYMOON FIELD LEACH TRIAL

HONEYMOON FIELD LEACH TRIAL ASX Announcement 19 June 2017 ASX: BOE HONEYMOON FIELD LEACH TRIAL HIGHLIGHTS Positioning Honeymoon to be Australia s next uranium producer as underlying prices rise Technical validation step for the Honeymoon

More information

For personal use only

For personal use only ASX Announcement 25 February 2016 Mulga Rock Project Definitive Feasibility Study Update Vimy Resources Limited ( Vimy ASX: VMY) is pleased to provide the following operational update on the Mulga Rock

More information

For personal use only

For personal use only ASX/Media Announcement 12 May 2017 NEW METALLURGICAL TESTWORK RESULTS DELIVER PROCESS IMPROVEMENTS AND OPERATING COST SAVINGS Outstanding results from flotation testwork and pilot program demonstrates

More information

Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study

Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study Chalice Gold Mines Limited ABN 47 116 648 956 30 October 2009 Highlights Scoping Study finds Koka deposit at the Zara Project in Eritrea

More information

WA s MT THIRSTY COBALT-NICKEL PROJECT POTENTIALLY WORLD S FOURTH LARGEST COBALT PRODUCER

WA s MT THIRSTY COBALT-NICKEL PROJECT POTENTIALLY WORLD S FOURTH LARGEST COBALT PRODUCER WA s MT THIRSTY COBALT-NICKEL PROJECT POTENTIALLY WORLD S FOURTH LARGEST COBALT PRODUCER Highlights Project has potential to deliver 3,700 tonnes of cobalt, 10,300 tonnes of nickel and 27,000 tonnes of

More information

STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT

STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT ASX RELEASE 30 DECEMBER 2016 STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT HIGHLIGHTS Independent Pre-Feasibility Study (PFS) supports development of the Urquhart Bauxite

More information

Wetar Expansion Update September 2015

Wetar Expansion Update September 2015 For ASX Market Release: 15 September 2015 Wetar Expansion Update September 2015 HIGHLIGHTS Mining and earthworks associated with the 25,000 tonne per annum copper cathode expansion project are well advanced

More information

ABM Hits 3000 Ounce Target from Trial Mining

ABM Hits 3000 Ounce Target from Trial Mining ASX ANNOUNCEMENT / MEDIA RELEASE ASX:ABU 12 th December 2013 ABM Hits 3000 Ounce Target from Trial Mining ABM Resources NL ( ABM or The Company ) presents an update on the Trial Mining and Processing at

More information

CHINA MINING Conference Tianjin October 2014

CHINA MINING Conference Tianjin October 2014 CHINA MINING Conference Tianjin October 2014 Forward Looking Statements These materials include forward looking statements. Often, but not always, forward looking statements can generally be identified

More information

DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD March 19 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD Process plant construction

More information

RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT

RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT 4 JULY 2017 RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT HIGHLIGHTS Robust economics: NPV 8% of A$260M (pre-tax) and IRR of 37% 1 ; Cash operating cost of

More information

FEASIBILITY STUDY COMPLETED CONFIRMING ROBUST CASH MARGINS FOR JOGJAKARTA IRON PROJECT

FEASIBILITY STUDY COMPLETED CONFIRMING ROBUST CASH MARGINS FOR JOGJAKARTA IRON PROJECT ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE: 29 AUGUST 2011 FEASIBILITY STUDY COMPLETED CONFIRMING ROBUST CASH MARGINS FOR JOGJAKARTA IRON PROJECT Highlights: Feasibility Study completed on a 2

More information

For personal use only

For personal use only Pre-Feasibility Study Highlights World Class Potential of Mt Lindsay Tin/Tungsten Project ASX Announcement Tuesday, 1 March 2011 Ref: /VMS/606/VMS/0249 Highlights: Project generates substantial revenue

More information

Shaw River Completes Acquisition of 75.5% Interest in Namibian Manganese Project

Shaw River Completes Acquisition of 75.5% Interest in Namibian Manganese Project ` ASX ANNOUNCEMENT 11 FEBRUARY 2011 Shaw River Completes Acquisition of 75.5% Interest in Namibian Manganese Project Highlights Acquisition of a 75.5% interest in the Otjozondu Manganese Project in Namibia

More information

For personal use only. Minerals Explorer in South Korea

For personal use only. Minerals Explorer in South Korea Minerals Explorer in South Korea Forward-looking and Competent Person Statement Certain statements contained in this presentation constitute forward looking statements. Such forward-looking statements

More information

March 2015 Quarterly Report

March 2015 Quarterly Report March 2015 Quarterly Report Platina Resources 3 rd Quarterly Activities Report Platina Resources Limited (ASX: PGM) is pleased to report its activities for the March 2015 quarter on the Company s 100%-owned

More information

5 th Asian Bauxite & Alumina Conference

5 th Asian Bauxite & Alumina Conference 5 th Asian Bauxite & Alumina Conference October 2015 Bauxite Hills Project Deliberate Focus ASX : MMI CORPORATE SNAPSHOT Shareholders 0.140 0.120 MMI Share Price (A$) Other 47% NetWealth Investments 5%

More information

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum ASX ANNOUNCEMENT 29 March 2010 Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum PanAust is pleased to announce that the Board of Directors

More information