Draft Environmental and Social Action Plan (ESAP) For M6-M60 Motorway, Sections between Szekszard-Boly, and Boly-Pecs

Size: px
Start display at page:

Download "Draft Environmental and Social Action Plan (ESAP) For M6-M60 Motorway, Sections between Szekszard-Boly, and Boly-Pecs"

Transcription

1 Draft Action (ESAP) For M6-M60 Motorway, Sections between Szekszard-Boly, and Boly-Pecs No Action Risks, Project preparation, permits and licences I.1 Preparation of Organization for, including inter alia: Location of borrow pits to be Routes of traffic Volume and type of vehicles Location of camps Determinations of routes of traffic, location of borrow pits and camps. Best and partly is (in 2008) Organization is submitted to the Project Management (NIF) Responsibility of Mecsek Consortium I.2 Establishing the Management to include: and social safeguard measures (including compensation procedures) Monitoring Final Public Consultation and Disclosure I.3 Conducting a baseline survey of the built and natural environmental conditions along the selected traffic routes I.4 Obtaining licenses to the explosion works to be carried out in borrow pits I.5 Preparation and submission of EIA, in case alternative design is to be Definition of clear responsibilities to the Action. Specification of sensitive areas Baseline for compensation of damages, if occur. applicable Hungarian Law applicable Hungarian law Best. Act No.LIII/1995. and best. No. 96/2005. (XI. 4.) GKM Decree. 314/2005. (XII. 25.) Governmental Decree on Impact Assessments and Expert fees Expert fees, costs of technical assistance Expert fees and administrative charges possible ( ) 3 months before the submission of Permitting Documentation is to be obtained. and Social Management Study on the built and natural environmental conditions Permit to explode in borrow pits is obtained. Permit is obtained Incorporated into the Organization See PCDP details below If explosion is necessary Only in case of alternative design is to be Draft Action for M6-M60 Motorway, Hungary Sections between Szekszard-Boly, and Boly-Pecs. 1/6

2 I.6 Preparation and submission of new Contraction Permitting Documentation including Chapter, in case alternative design is to be I.7 Preparation and submission of new Water Management Permitting Documentation for of new hydraulic objects as per alternative design Social management II.1 Finalisation of the Public Consultation and Disclosure II.2 II.3 II.4 Communication of time schedule of the Project through different media. Communication of time and location of explosion works, and the location of traffic. Setting up and operating grievance processes and procedures. applicable Hungarian law applicable Hungarian law Tasks and responsibilities are clearly identified Local communities can prepare for nuisances Local communities can prepare for nuisances People can communicate the negative impacts of and also their complaints related to expropriation (if any) and the solutions are to be found in time. Act No. LXXVIII/1997. Before Detailed Design Best, World Bank guidelines Best Best. Best of media disclosures of media disclosures Operational costs of information offices possible ( ) possible ( ), possible, ( ) Permit is obtained Water Management Permit is obtained. Final PCDP Information channels (news, websites, local announcements, information offices) Information channels are operated, as above. Management reports on the operation of grievance procedures Only in case of alternative design is to be Only in case of alternative design is to be In accordance with PCDP In accordance with PCDP In accordance with PCDP Draft Action for M6-M60 Motorway, Hungary Sections between Szekszard-Boly, and Boly-Pecs. 2/6

3 II.5 II.6 II.7 II.8 II.9 Preparation and operation of Occupational Health and Safety for the, including: Occupational Health & Safety Policy Organizational framework, operating procedures, competence, training program and documentation OHS objectives Hazard prevention Prevention and Control measures Performance monitoring and measurements Evaluation, feed back Control of ages of workers Safety campaign in schools located in settlements nearby the motorway Refining and implementing expropriation procedures and grievance procedures, including public consultation and disclosure of the processes and procedures Communication of the results of Monitoring (primary noise and air quality) to the public. Stakeholder analysis and assessment of affected communities on the basis of demographic and economic data. Prevention of injuries, child labour. Prevention of pedestrian crossing of children on the Motorway Minimizing negative social affect due to expropriation. Avoiding negative reputation of the highway. The social benefits and impact of the highway can be determined Best. ILO requirements. Hungarian Labour Code Best Law World Bank Guidelines., cost of trainer, of, and. of operation (2010-) During and operation Best During and operation (2010-) Best, Expert fee of Stakeholder analysis. During and operation (2010-) Health and Safety. Management report on school campaigns held. Public information, and monitoring reports on the operation of grievance procedures Media publications Stakeholder analysis report, Socio-economic studies In case further expropriation is necessary Draft Action for M6-M60 Motorway, Hungary Sections between Szekszard-Boly, and Boly-Pecs. 3/6

4 III.1 and monitoring of the approved Management. III.2 III.3 III.4 III.5 Preparation, operation and communication of road maintenance plans for period Preparation and operation of Water, Wastewater, Waste management plans Preparation and operation of Groundwater/Surface water protection plan with special attention to the locations of drinking water reserves Preparation of Air Quality protection plan Maintain local community support. Ensure on-going maintenance of roads impacted by traffic Mitigation of any adverse affects for site activities, camps that could be generated by the operation of machinery and the workers presence. Ensuring the prevention of surface water, groundwater by the operations of against accidental spillages (oils, lubricants, or other hazardous substances) Ensuring the mitigation of adverse affects on air quality due to earth works, and traffic (planning the location of water sprinkles and wheel washing facilities, covering filled lorries, building material dumping site locations) Best and and expert fees. Best of, Best and partly is Preventive measures for surface and groundwater are Preventive measures for air quality pollution Management reports + reports to authorities, financing institutions and other stakeholders of, of, of Road maintenance s, Contractors reports on maintenance activities performed. Water, Wastewater, and Waste management plans. Groundwater/Surf ace Water protection plans. Air Quality Protection Draft Action for M6-M60 Motorway, Hungary Sections between Szekszard-Boly, and Boly-Pecs. 4/6

5 III.6 III.7 III.8 IV.9 Preparation of Noise and Vibration Assessment based on detailed Organization including: Surveying of any protected objects in the routes, checking whether noise limits values are met. Design of temporary noise barriers Monitoring of noise standards during measures to protect landscape as per the permit (commencing planting activity during ) Designing and communicating good s during site management in order to prevent any ecological adverse affects. Establishment and implementation of archaeological supervision plan Operation IV.1 and monitoring of the approved Management. IV.2 Performing soil, sludge, and surface water monitoring measurements as Permits. Noise protection of sensitive areas Reducing landscape impacts during. Protection of natural environment. Potential archaeological remains will be excavated before they are covered by materials. Maintain local community support. Ensuring that soil/groundwater pollution does not occur, or if occurs, adequate remediation is performed. 8//2002, (III.22) KoM- EuM Decree on noise threshold values Best and it is Based on proposals for Noise and vibration study on noises and its mitigation., and some cost of soil/flora management. of From the beginning of the. ( ) Best. From the beginning of the. ( ) It is Best and It is and expert fees. Cost of soil/sludge/water analysis. During Operation ( ) Noise and Vibration Assessment. Constructor on the Noise and Vibration Monitoring Measurements. Satisfaction of requirements of the Permit. Continuous management control of works. Minutes on archaeological supervision visits Management reports + reports to authorities, financing institutions and other stakeholders Regular performance as Permit. Operator s report on measurements result, submitted to the relevant Authority. Draft Action for M6-M60 Motorway, Hungary Sections between Szekszard-Boly, and Boly-Pecs. 5/6

6 IV. 3 IV.4 IV.5 IV.6 Set up Operational Air Monitoring Set up Operational Noise Monitoring Controlling effectiveness of noise barriers designed to mitigate noise impacts of operation through noise measurements. Set up Operational Waste Management for collection and management of waste originated from: The highway itself, Rest areas Maintenance and servicing sites EIA: PCDP: NIF: applicable Hungarian Law. applicable Hungarian Law. Ensuring that prevention tools for noise impact are working effectively. applicable Hungarian Law. 21/2001. (II. 14.) gov. decree on air quality protection 14/2001. (V. 9) KoM-EuM-FVM decree on air quality limit values 17/2001. (II.14) KoM decree on air quality monitoring 8/2002.(III.22) KoM- EuM decree on noise limit values Best. 164/2003. (X.18) Gov. decree on administration of waste generation 126/2003. (VIII.15) gov. Decree on Waste management plans 98/2001. (VI.15) Gov. decree on hazardous wastes Cost of noise measurements Impact Assessment Public Disclosure Nemzeti Infrastrukturafejlesztesi Zrt. (the Project management company representing the Hungarian State) the operation the operation After start-up period of the highway ( ) the operation (2009, the latest) Operational Air Monitoring Operational Noise Monitoring limit values as per 8/2002.(III.22) KoM-EuM decree are met. Operational Waste Management Draft Action for M6-M60 Motorway, Hungary Sections between Szekszard-Boly, and Boly-Pecs. 6/6

Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT

Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT Environmental and Social Action Plan August 2016 Project: Bosnia and Herzegovina

More information

Doc. No H1 Rev. 0 - July 2011 APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN

Doc. No H1 Rev. 0 - July 2011 APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN Taking into account the findings of the ESDD, an Environmental and Social Plan (ESAP) has been developed

More information

Project: Category A Road Project, Kazakhstan Kurty Buribaytal 62 km Road Project

Project: Category A Road Project, Kazakhstan Kurty Buribaytal 62 km Road Project Project: Category A Road Project, Kazakhstan Kurty Buribaytal 62 km Road Project Date: May 2015 Version: Final Version Appendix D: Environmental and Social Plan (ESAP) No. PR1 Assessment and Management

More information

EBRD Environmental and Social Action Plan

EBRD Environmental and Social Action Plan PR 1 Assessment and Management of Environmental and Social Impacts and Issues 1.1 to establish PIU and dedicate a responsible person (head of PIU) for coordination between the various departments so as

More information

DRAFT FOR CONSULTATION OCTOBER 7, 2014

DRAFT FOR CONSULTATION OCTOBER 7, 2014 The Board has authorized the release of this document for consultation purposes to seek feedback on its content. It has not endorsed the content of the draft, and the Committee on Development Effectiveness

More information

EXECUTIVE SUMMARY of the Environmental Impact Assessment Report

EXECUTIVE SUMMARY of the Environmental Impact Assessment Report Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Introduction Additional Financing for Third East West Highway Improvement Project EXECUTIVE

More information

Public Disclosure Authorized EXECUTIVE SUMMARY

Public Disclosure Authorized EXECUTIVE SUMMARY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized EXECUTIVE SUMMARY Introduction Georgia is an important transport corridor connecting

More information

1 Environmental and Social Action Plan

1 Environmental and Social Action Plan 1 and Social Plan The table below constitutes the ESAP. It identifies the required actions during pre-construction, construction and operation of the project. of the actions is the responsibility of Koridori

More information

CRUCEA NORTH WIND POWER PLANT

CRUCEA NORTH WIND POWER PLANT ENVIRONMENTAL AND SOCIAL ACTION PLAN CRUCEA NORTH WIND POWER PLANT Draft for public comment September 2013 ENVIRONMENTAL AND SOCIAL ACTION PLAN The European Bank for Reconstruction and Development (EBRD),

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

Environmental and Social Action Plan

Environmental and Social Action Plan APPENDIX 2 Environmental and Social Action Plan 1 6 P A G E S Phase 1 Environmental and Social Management System (ESMS) Equator Principle IFC PS1, EBRD PR1, EIB PS 1 Define and implement an Environmental,

More information

Greater Amman Municipality

Greater Amman Municipality Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ECO Consult Municipal Solid Waste Management & Carbon Finance in Amman Greater Amman

More information

Source of requirement EBRD. - Each six months during construction - Annually during operation. Best practice EBRD PR 1

Source of requirement EBRD. - Each six months during construction - Annually during operation. Best practice EBRD PR 1 0 Submit report to the Bank on environmental, social, health and safety performance, including status of each ESAP element and other agreed activities. EBRD - Each six months during construction - Annually

More information

Republic of Croatia HRVATSKE AUTOCESTE (Motorway Maintenance Department) RIJEKA GATEWAY PROJECT Rehabilitation works on the big arch of Krk Bridge

Republic of Croatia HRVATSKE AUTOCESTE (Motorway Maintenance Department) RIJEKA GATEWAY PROJECT Rehabilitation works on the big arch of Krk Bridge Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Croatia HRVATSKE AUTOCESTE (Motorway Maintenance Department) RIJEKA GATEWAY

More information

B1: THE MAIN PROVISIONS OF THE PLANNING REGIME

B1: THE MAIN PROVISIONS OF THE PLANNING REGIME HIGH SPEED TWO INFORMATION PAPER B1: THE MAIN PROVISIONS OF THE PLANNING REGIME This paper outlines the main provisions of the planning regime proposed for Phase One of the HS2 project. It will be of particular

More information

E1 687 Vol. 2 ENVIRONMENTAL ASSESSMENT FOR EXTENSITION OF RUNWAY FOR ZANZIBAR AIRPORT UNITED REPUBLIC OF TANZANIA

E1 687 Vol. 2 ENVIRONMENTAL ASSESSMENT FOR EXTENSITION OF RUNWAY FOR ZANZIBAR AIRPORT UNITED REPUBLIC OF TANZANIA Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized UNITED REPUBLIC OF TANZANIA MINISTRY OF COMMUNICATION AND TRANSPORT (ZANZIBAR) ENVIRONMENTAL

More information

DRAFT ENVIRONMENTAL AND SOCIAL ACTION PLAN (ESAP)

DRAFT ENVIRONMENTAL AND SOCIAL ACTION PLAN (ESAP) KRUMOVGRAD GOLD MINE PROJECT, BULGARIA DUNDEE PRECIOUS METALS December 2014 Wardell Armstrong International Third Floor, 46 Chancery Lane, London, WC2A 1JE, United Kingdom Telephone: +44 (0) 20 7242 3243

More information

IN THE KYRGYZ REPUBLIC

IN THE KYRGYZ REPUBLIC Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL ROAD REHABILITATION (OSH-ISFANA) PROJECT (NRRP)- WORLD BANK PPA Q 6240 CONSULTANCY

More information

Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP)

Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP) Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP) No Action Environmental Risks, Liability/ Benefits Legislative Requirement / EBRD Performance Requirement

More information

EXHIBIT LIST No Exhibit Name Page 1 P3 Control of Environment Impacts Presentation.pdf (P3) 2-34

EXHIBIT LIST No Exhibit Name Page 1 P3 Control of Environment Impacts Presentation.pdf (P3) 2-34 Reference No: HOC/10001 Petitioner: Phase 2a Teach-ins Published to Collaboration Area: Friday 23-Mar-2018 EXHIBIT LIST Page 1 of 34 No Exhibit Name Page 1 P3 Control of Environment Impacts Presentation.pdf

More information

Ankara-Nigde Motorway Project

Ankara-Nigde Motorway Project Environmental and Social Plan (ESAP) ERG Otoyol Yatırım ve Isletme A.S. April 2018 Prepared for: ERG Otoyol Yatırımve Isletme A.S. Prepared by: Aecom Turkey Danışmanlık ve Mühendislik Ltd. Şti Mustafa

More information

Europe and Central Asia Region Capacity Development Trust Fund

Europe and Central Asia Region Capacity Development Trust Fund Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Europe and Central Asia Region Capacity Development Trust Fund RP1439 Draft Terms of

More information

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives: ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP 1. Objectives The aim of the study is to achieve the following objectives: Review of existing EIA and RAP reports on sections of the line which are not

More information

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project May 2018 Third Draft GEO: East West Highway (Khevi Ubisa Section) Improvement Project Section F2 of the Khevi Ubisa Shorapani Argveta Road (E60 Highway) Part 6 Appendices A D Prepared by JV IRD Engineering

More information

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes MINISTRY OF ENVIRONMENT AND NDU ENVIRONMENTAL GUIDELINE No. 31 Asphalt Plant Set Up Temporarily For The Purposes Of A Project By A Public Department 1.0 Purpose of guideline This environmental guideline

More information

10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION

10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION 10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION 10.1 Objective The main objective is to confirm the implementation of mitigation measures recommended in

More information

Mezitli Wastewater Treatment Plant

Mezitli Wastewater Treatment Plant Mezitli Wastewater Treatment Plant Revised Environmental and Social Action Plan (ESAP) October 2017 Issued by: Mersin Water and Sewage Administration (MESKI) Table of Contents 1. Environmental and Social

More information

LNG Terminal Świnoujście, Poland. Environmental and Social Action Plan (ESAP)

LNG Terminal Świnoujście, Poland. Environmental and Social Action Plan (ESAP) LNG Terminal Świnoujście, Poland Environmental and Social Action Plan (ESAP) June, 2012 Action Item Tables The ESAP Action Items are contained in several tables as shown below. Included within these Action

More information

Roads Department of the Ministry of Regional Development and Infrastructure of Georgia GEORGIA FOURTH EAST-WEST HIGHWAY IMPROVEMENT PROJECT

Roads Department of the Ministry of Regional Development and Infrastructure of Georgia GEORGIA FOURTH EAST-WEST HIGHWAY IMPROVEMENT PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Roads Department of the Ministry of Regional Development and Infrastructure of Georgia

More information

Radstone Fields, Brackley Construction Traffic Management Plan Taylor Wimpey & Barratt Strategic

Radstone Fields, Brackley Construction Traffic Management Plan Taylor Wimpey & Barratt Strategic Radstone Fields, Brackley Construction Traffic Management Plan Taylor Wimpey & Barratt Strategic April 2011 QM Issue/revision Issue 1 Revision 1 Revision 2 Revision 3 Remarks Draft for Client Draft following

More information

TABLE OF CONTENTS. Page

TABLE OF CONTENTS. Page TABLE OF CONTENTS Page 1 PROJECT INTRODUCTION... 1-1 1.1 PROJECT BACKGROUND... 1-2 1.2 PROJECT PROPONENT... 1-2 1.3 PROJECT OVERVIEW... 1-3 1.4 PROJECT REGULATORY APPROVAL PROCESS... 1-4 1.4.1 Existing

More information

left over, or an unwanted by-product, from an industrial, commercial, domestic or other activity; or

left over, or an unwanted by-product, from an industrial, commercial, domestic or other activity; or 14. Waste Management 14.1. Waste Management Regulations The regulatory requirements governing waste management are provided within the EP Act, the EPR and associated Environmental Protection (Waste Management)

More information

TERMS OF REFERENCE FOR CONSULTING SERVICES FOR ENGINEERING AND CONSTRUCTION SUPERVISION CONSULTANT

TERMS OF REFERENCE FOR CONSULTING SERVICES FOR ENGINEERING AND CONSTRUCTION SUPERVISION CONSULTANT TERMS OF REFERENCE FOR CONSULTING SERVICES FOR ENGINEERING AND CONSTRUCTION SUPERVISION CONSULTANT 1. Background The Asian Development Bank (ADB) has assisted the Kyrgyz Republic in the rehabilitation

More information

SNTGN TRANSGAZ SA MEDIAS. ESAP BRUA Version 3 1

SNTGN TRANSGAZ SA MEDIAS. ESAP BRUA Version 3 1 SNTGN TRANSGAZ SA MEDIAS ROMANIAN SECTION OF THE BULGARIA-ROMANIA-HUNGARY-AUSTRIA NATURAL GAS TRANSMISSION CORRIDOR (BRUA PIPELINE PROJECT) DRAFT ENVIRONMENTAL AND SOCIAL ACTION PLAN No. (Liab/Benefits)

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The People s Republic of Bangladesh Project: Dhaka Mass Rapid Transit Development Project (Line 5) (E/S) Loan

More information

18 Cumulative Impacts and Interaction of Effects

18 Cumulative Impacts and Interaction of Effects 18 Cumulative Impacts and Interaction of Effects 18.1 Introduction This chapter addresses the cumulative impacts and main interactions between different aspects of the environment likely to be significantly

More information

Category Environmental Item Main Check Items Confirmation of Environmental and Social Considerations

Category Environmental Item Main Check Items Confirmation of Environmental and Social Considerations al Checklist: 5. Non-Ferrous Metals Smelting and Refining(1) (1) ESIA and al Permits 1 Have ESIA reports been officially completed? Have ESIA reports been written in the official language or a language

More information

Practice Notes For Construction Managers PNCM 5: Environmental Management - First Issue, April 2004 (Index under: Environmental Management)

Practice Notes For Construction Managers PNCM 5: Environmental Management - First Issue, April 2004 (Index under: Environmental Management) Environmental Management (1 st Issue-Apr 2004) Practice Notes For Construction Managers PNCM 5: Environmental Management - First Issue, April 2004 (Index under: Environmental Management) Contents Page

More information

Table of Contents. O Devaney Gardens. Page i. Page Number. Section. 1 Introduction

Table of Contents. O Devaney Gardens. Page i. Page Number. Section. 1 Introduction Section 1 Introduction Page Number 1.1 Introduction 2 1.2 Screening - Requirement for an EIA 5 1.3 Purpose of this EIA 6 1.4 Objectives of this EIA 6 1.5 Scoping 10 1.6 Format and Structure of this EIS

More information

CORPORATE OFFICE BUILDING, C-11, URBAN ESTATE-II CITY CENTRE SECTOR 29, GURUGRAM, HARYANA

CORPORATE OFFICE BUILDING, C-11, URBAN ESTATE-II CITY CENTRE SECTOR 29, GURUGRAM, HARYANA ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan () would consist of all mitigation measures for each component of the environment due to the activities increased during the, operation and the

More information

EXHIBIT LIST No Exhibit Name Page 1 P5 Traffic Presentation.pdf (P5) 2-20

EXHIBIT LIST No Exhibit Name Page 1 P5 Traffic Presentation.pdf (P5) 2-20 Reference No: HOC/10001 Petitioner: Phase 2a Teach-ins Published to Collaboration Area: Friday 23-Mar-2018 EXHIBIT LIST Page 1 of 20 No Exhibit Name Page 1 P5 Traffic Presentation.pdf (P5) 2-20 HOC/10001/0001

More information

Chapter 14 Overall Project Assessment

Chapter 14 Overall Project Assessment Chapter 14 Overall Project Assessment TABLE OF CONTENTS 14 OVERALL PROJECT ASSESSMENT... 14-1 14.1 Introduction... 14-1 14.2 Development of the ESIA... 14-1 14.2.1 Adopted Process... 14-1 14.2.2 Challenges

More information

Syvash Wind Farm Environmental and Social Action Plan (ESAP)

Syvash Wind Farm Environmental and Social Action Plan (ESAP) General Environmental, Social Governance (ESG) management 1. Ensure Compliance with National legislation and attain all relevant National Permits, including EIA permit for the Project and associated infrastructure

More information

SFG1822 AZERBAIJAN REPUBLIC MINISTRY OF TRANSPORT AZERROADSERVICE OPEN JOINT STOCK COMPANY. October Public Disclosure Authorized

SFG1822 AZERBAIJAN REPUBLIC MINISTRY OF TRANSPORT AZERROADSERVICE OPEN JOINT STOCK COMPANY. October Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SFG1822 AZERBAIJAN REPUBLIC MINISTRY OF TRANSPORT AZERROADSERVICE OPEN JOINT STOCK COMPANY Public Disclosure Authorized October 2015 Public Disclosure

More information

Mining Environmental Impact Assessment Guidelines. May 2018

Mining Environmental Impact Assessment Guidelines. May 2018 Mining Sector Environmental and Social Impact Assessment Guidelines Mining Environmental Impact Assessment Guidelines May 2018 Background Mining EIA Guidelines Working Group established by Minister of

More information

Lisbon Metro expansion and environmental follow-up

Lisbon Metro expansion and environmental follow-up Lisbon Metro expansion and environmental follow-up COURSE: IMPACTES AMBIENTAIS / ENVIRONMENTAL IMPACTS Ana Cerdeira Lisbon, 13 April 2015 Outline 1. Definition of Environmental Follow-up 2. Environmental

More information

ENVIRONMENTAL IMPACT ASSESSMENT

ENVIRONMENTAL IMPACT ASSESSMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Roads Department of the Ministry of Regional Development and Infrastructure of Georgia

More information

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION HIGH SPEED TWO INFORMATION PAPER E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION This paper outlines the framework for the control and management of traffic associated with the construction of the Proposed

More information

Draft Code of Construction Practice

Draft Code of Construction Practice Draft Code of Construction Practice This factsheet outlines how it is expected the nominated undertaker will manage the effects of the construction of the Proposed Scheme on communities and the environment

More information

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT

More information

Main Check Items. 1 Are wastes properly treated and disposed of in accordance with the laws and regulations of the host country?

Main Check Items. 1 Are wastes properly treated and disposed of in accordance with the laws and regulations of the host country? Checklist: 16. Power Transmission and Distribution Lines(1) Confirmation of and Social (1) ESIA and Permits 1 Have ESIA reports been officially completed? Have ESIA reports been written in the official

More information

Public Disclosure Authorized

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TERMS OF REFERENCE FOR ENGAGEMENT OF A CONSULTANT TO CONDUCT AN ENVIRONMENTAL AND SOCIAL

More information

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item Checklist: 17. Roads, Railways and Bridges(1) 1. Permits and Approvals, Explanations (1) ESIA and Permits (2) Explanations to the Public Main Check s 1 Have ESIA reports been officially completed? Have

More information

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item Checklist: 17. Roads, Railways and Bridges(1) 1. Permits and Approvals, Explanations (1) ESIA and Permits (2) Explanations to the Public Main Check s 1 Have ESIA reports been officially completed? Have

More information

Assistant Planner Associate Planner Class Specification

Assistant Planner Associate Planner Class Specification Assistant Planner Class Specification FLSA Designation: Non-Exempt Effective: 03/2004 Revised: N/A DEFINITION Under general supervision (Assistant Planner) or direction (), to perform professional level

More information

ENVIRONMENTAL AND SOCIAL ACTION PLAN

ENVIRONMENTAL AND SOCIAL ACTION PLAN ENVIRONMENTAL AND SOCIAL ACTION PLAN 0 Corporate s 0.1 Maintain a Corporate EHS management system and CSR reporting for Zorlu Enerji in line with GRI4. Need to maintain and implement best practice. Disclose

More information

Environmental and Social Action Plan. Draft Report. The business of sustainability

Environmental and Social Action Plan. Draft Report. The business of sustainability Environmental and Social Action Plan Reconstruction of the P-80 motor road Sloboda- Papernya km 0.000 km 14.770 Draft Report December 2017 www.erm.com The business of sustainability Draft Report European

More information

Environmental and Social Action Plan

Environmental and Social Action Plan Environmental and Social Plan Abbreviations AESR CESMP CWMP E&S EBRD EIA EP EPC (Contractor) ESAP ESMS EU IFC OHS OESMP PR PS RAP SEP SVO SPV O&M Contractor Annual Environmental and Social Report Beo Čista

More information

FINAL. WREP Sectional Replacement Project Environmental and Social Impact Assessment. Georgian Pipeline Company

FINAL. WREP Sectional Replacement Project Environmental and Social Impact Assessment. Georgian Pipeline Company FINAL WREP Sectional Replacement Project Georgian Pipeline Company AUGUST 2016 TABLE OF CONTENTS NON-TECHNICAL SUMMARY 1 INTRODUCTION 1-1 1.1 General 1-1 1.2 Background to the WREP 1-1 1.3 Rationale for

More information

Port Granby Project ENVIRONMENTAL ASSESSMENT STUDY REPORT EXECUTIVE SUMMARY

Port Granby Project ENVIRONMENTAL ASSESSMENT STUDY REPORT EXECUTIVE SUMMARY EXECUTIVE SUMMARY Introduction Low-level radioactive waste and associated marginally contaminated soils at Port Granby are part of historical industrial activities in the Port Hope area. Since the 1930s,

More information

Izmir Bayrakli Integrated Health Campus Turkey

Izmir Bayrakli Integrated Health Campus Turkey Izmir Bayrakli Integrated Health Campus Turkey Basic Information Project name: Izmir Bayrakli Integrated Health Campus Project. Borrower: İzmir Bayraklı Hastane Yatırım ve Sağlık Hizmetleri Anonim Şirketi

More information

Summary of Preparatory Study

Summary of Preparatory Study Summary of Preparatory Study 1. Title of the Cooperation Project, Relevant Project Report Preparatory Survey on the Project for the Establishment of Rural Water Supply System in Kambia Town in the Republic

More information

Environmental Compliance Audit Report. MFF 0054-VIE: Water Sector Investment Program Tranche 2

Environmental Compliance Audit Report. MFF 0054-VIE: Water Sector Investment Program Tranche 2 Environmental Compliance Audit Report Project Number: 41456-033 June 2012 MFF 0054-VIE: Water Sector Investment Program Tranche 2 This environmental compliance audit report is a document of the borrower.

More information

MINISTRY OF LAND HOUSING AND URBAN DEVELOPMENT ALBERTINE REGION SUSTAINABLE DEVELOPMENT PROJECT

MINISTRY OF LAND HOUSING AND URBAN DEVELOPMENT ALBERTINE REGION SUSTAINABLE DEVELOPMENT PROJECT MINISTRY OF LAND HOUSING AND URBAN DEVELOPMENT ALBERTINE REGION SUSTAINABLE DEVELOPMENT PROJECT Procurement of a Project Environmental Specialist TERMS OF REFERENCE The Ministry of Lands Housing and Urban

More information

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation Energy Resilience for Climate Adaptation Project (ERCAP) Environmental Code of Practice (ECOP) for COMPONENT 2: Demonstration Measures to Enhance Resilience of Energy Sector (Pilot for Strengthening Transmission

More information

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani DESCRIPTION OF

More information

E3072 v2. GEF Large City Congestion and Carbon Reduction Project. Environment Management Plan. Public Disclosure Authorized

E3072 v2. GEF Large City Congestion and Carbon Reduction Project. Environment Management Plan. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized E3072 v2 GEF Large City Congestion and Carbon Reduction Project Environment Management

More information

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway

12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway in association with Design 151.66 Km (Existing Road Apr. 180 km) 2 OBJECTIVE: The Government of Timor Lestewishes to Engage Consultant to carry out the Preliminary, Detailed Engineering Design and Environment

More information

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME OPERA PHASE: ENVIRONMENTAL MANAGENT PROGRAMME 1. OBJECTIVE The overall goal for the Environmental Programme (O) is to ensure that the operation of the wind energy facility (WEF) does not have unforeseen

More information

ENVIRONMENTAL & SOCIAL ACTION PLAN

ENVIRONMENTAL & SOCIAL ACTION PLAN APPENDIX A: ENVIRONMENTAL & SOCIAL ACTION PLAN No 1. PROJECT PLANNING & PROCUREMENT PHASE (some actions will carry forward into Stage) 1.1 PR1: Environmental Commitments Register: Develop a Commitments

More information

Building from the ground up in West Africa. The Hatch approach to projects in a developing country

Building from the ground up in West Africa. The Hatch approach to projects in a developing country Building from the ground up in West Africa The Hatch approach to projects in a developing country 2 Agenda 1. Hatch Contribution to West Africa Development 2. Three Recent Projects on Which We Worked 3.

More information

10.0 Environmental protection, follow-up and monitoring

10.0 Environmental protection, follow-up and monitoring 10.0 Environmental protection, follow-up and monitoring 10.1 Introduction Manitoba Hydro will implement the mitigation measures, monitoring and other follow-up actions identified in chapter 8 through an

More information

Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous

Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous chemicals may include, but not limited to the following

More information

ENVIRONMENT MANAGEMENT PLAN. For Excavation of Brick Earth (Total Mining Area Ha.) (for Manufacturing of Bricks)

ENVIRONMENT MANAGEMENT PLAN. For Excavation of Brick Earth (Total Mining Area Ha.) (for Manufacturing of Bricks) ENVIRONMENT MANAGEMENT PLAN For Excavation of Brick Earth (Total Mining Area 2.121 Ha.) (for Manufacturing of Bricks) By M/s Bhagwati Eth (bzv) Udyog Village Shokanangla, Pargana & Tehsil Bazpur, District-

More information

Czech Republic National Reporting for CSD-18/19 Thematic profile: Mining

Czech Republic National Reporting for CSD-18/19 Thematic profile: Mining Czech Republic National Reporting for CSD-18/19 Thematic profile: Mining The Czech mining industry in 2006 2008 In the Czech Republic (hereinafter referred to as the "CZ"), there are currently approximately

More information

Chapter 17 Cumulative Impacts

Chapter 17 Cumulative Impacts Chapter 17 Cumulative Impacts CONTENTS 17. Cumulative Effects... 2 17.1 Introduction... 2 17.2 Summary of Relevant Legislation, Planning Policy and Guidance... 2 17.3 Methods... 5 17.4 Consultation...

More information

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES Environmental / Social issue/ aspect/ activity Anticipated negative impact Management and mitigation

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN INTRODUCTION ENVIRONMENTAL MANAGEMENT PLAN An environmental management plan (EMP) has been prepared for the proposed construction of commercial project to minimize negative impacts and is formed on the

More information

Environmental and Social Considerations in Detailed Planning Survey (Technical Cooperation for Development Planning)

Environmental and Social Considerations in Detailed Planning Survey (Technical Cooperation for Development Planning) Environmental and Social Considerations in Detailed Planning Survey (Technical Cooperation for Development Planning) 1. Full title of the Project Project for Updating Dakar Urbanization Master Plan by

More information

Chapter 13 Management and Monitoring

Chapter 13 Management and Monitoring Chapter 13 Management and Monitoring TABLE OF CONTENTS 13 MANAGEMENT AND MONITORING... 13-1 13.1 Introduction... 13-1 13.2 Construction Phase Roles and Responsibilities... 13-1 13.2.1 BP... 13-1 13.2.2

More information

Environmental and Social Policy

Environmental and Social Policy Environmental and Social Policy Contents Foreword 2 Purpose 2 Commitments 2 Environmental and Social Assessment 3 Operations financed directly 4 Operations financed through Financial Intermediaries 4 Environmental

More information

Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006.

Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006. Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006. Thus, EIA is not applicable for proposed project. We have derived project

More information

Factor Potential Effects Mitigation Measures

Factor Potential Effects Mitigation Measures Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table

More information

Summary of Environmental and Social Consideration in Development Study (Preparatory Study)

Summary of Environmental and Social Consideration in Development Study (Preparatory Study) Summary of Environmental and Social Consideration in Development Study (Preparatory Study) 1. Full title of the Project The Study on Integrated Development Strategy for Danang City and Its Neighboring

More information

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d)

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d) Checklist:. 10.Ports and Harbors (1) 1 Permits and Explanation 2 Pollution Control (1) EIA and Permits (2) Explanation to the Local Stakeholders (3) Examination of Alternatives (1) Air Quality (2) Water

More information

Corporate Policy and Procedure

Corporate Policy and Procedure Corporate Policy and Procedure POLICY CATEGORY AUTHORITY RELATED POLICIES APPROVED BY Safety Management When Outside Contractors are Retained (Contractor Safety Management Program) (the Policy ) Health

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The People's Republic of Bangladesh Project: Dhaka Urban Transport Development Project (I) Loan Agreement: February

More information

DAHSHOUR-ATFEEH GAS PIPELINE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT. Executive Summary April 2013

DAHSHOUR-ATFEEH GAS PIPELINE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT. Executive Summary April 2013 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DAHSHOUR-ATFEEH GAS PIPELINE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT April 2013 Introduction

More information

Annex C TIME-OUT CHECKLIST INTRODUCTION

Annex C TIME-OUT CHECKLIST INTRODUCTION Annex C TIME-OUT CHECKLIST INTRODUCTION A. A Time-out is a Workplace Safety and Health (WSH) response measure that involves the temporary suspension of all or part of a company s operations so as to address

More information

Principles for environmental and social responsibility

Principles for environmental and social responsibility issued by: Principles for environmental and social responsibility Sustainable development is dependent on a balance between economic considerations, social responsibility and environmental protection.

More information

V: PROJECT SCOPING & METHODOLOGY

V: PROJECT SCOPING & METHODOLOGY V: PROJECT SCOPING & METHODOLOGY 5.0 INTRODUCTION The scoping exercise is carried out to define the focus and scope of the EIA Study. The scoping exercise is required to understand the type of activities

More information

Category Environmental Item Main Check Items Confirmation of Environmental Considerations

Category Environmental Item Main Check Items Confirmation of Environmental Considerations al Checklist: 2. Oil and Natural Gas Development 1 1 Permits and Explanation 2 Mitigation (1) EIA and al Permits (2) Explanation to the Public (1) Air Quality (2) Water Quality (3) Wastes Have EIA reports

More information

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4.1 INTRODUCTION This section describes the broad principles of the methodology adopted for the EIA of the Proposed Development. EIA is a procedure required

More information

Environmental and Social Data Sheet

Environmental and Social Data Sheet Environmental and Social Data Sheet Luxembourg, 08.09.2014 Overview Project Name: Project Number: 2013-0468 Country: Project Description: OUARZAZATE III (TOWER) Morocco Construction and operation of a

More information

Environmental and Social Action Plan 400kV Transmission Line, SS Bitola 2 Macedonian/Albanian border and SS Ohrid

Environmental and Social Action Plan 400kV Transmission Line, SS Bitola 2 Macedonian/Albanian border and SS Ohrid 400kV Transmission Line, SS Bitola 2 Macedonian/Albanian border and SS Ohrid The European Bank for Reconstruction and Development (EBRD) is considering providing financing to Macedonian Transmission System

More information

Information on the focal point for the Convention. Information on the point of contact for the Convention

Information on the focal point for the Convention. Information on the point of contact for the Convention Questionnaire for the REPORT OF MONTENEGRO ON THE IMPLEMENTATION OF THE CONVENTION ON ENVIRONMENTAL IMPACT ASSESSMENT IN A TRANSBOUNDARY CONTEXT in the period 2006 2009 Information on the focal point for

More information

Project for Elaboration of the National Strategy for Treatment of Household and Similar Waste for the Kingdom of Morocco

Project for Elaboration of the National Strategy for Treatment of Household and Similar Waste for the Kingdom of Morocco Summary of Environmental and Social Considerations in Detailed Planning Survey on the Project for Elaboration of the National Strategy for Treatment of Household and Similar Waste for the Kingdom of Morocco

More information

E4477. Environmental Assessment and Environmental Management Plan. Republic of Belarus. Water Supply and Sanitation Project.

E4477. Environmental Assessment and Environmental Management Plan. Republic of Belarus. Water Supply and Sanitation Project. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Belarus Water Supply and Sanitation Project Environmental Assessment and

More information

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN SUMMARY - EMERGENCY POWER INFRASTRUCTURE REHABILITATION PROJECT PHASE II

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN SUMMARY - EMERGENCY POWER INFRASTRUCTURE REHABILITATION PROJECT PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN SUMMARY - EMERGENCY POWER INFRASTRUCTURE REHABILITATION PROJECT PHASE II Project Title: Emergency Power Infrastructure Rehabilitation Project Phase II Project Number:

More information

Code of Construction Practice Part B: Site Specific Requirements

Code of Construction Practice Part B: Site Specific Requirements Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Code of Construction Practice Part B: Site Specific Requirements Blackfriars

More information