Team Member Affiliation WEDA Member Role

Size: px
Start display at page:

Download "Team Member Affiliation WEDA Member Role"

Transcription

1 Summary: Dominion Cove Point LNG, LP (DCP) owns and operates the Cove Point Liquefied Natural Gas (LNG) Terminal (terminal), an LNG import terminal in Lusby, Maryland (Figure 1). The terminal includes a pier, located 1.1 miles offshore of the terminal, where LNG vessels are docked and unloaded. DCP recently reinforced the existing off-shore pier to accept larger and deeper draft ships. The Pier Reinforcement Project provided greater flexibility for LNG shippers and the vessels that bring LNG cargo into the Mid Atlantic and rtheast region. In addition to reinforcement and expansion of the pier itself, this project required the dredging and subsequent placement of approximately 120,000 cubic yards of material from the area adjacent to the pier to deepen the berthing area (Figure 2). After screening 51 possible dredged material placement options, DCP selected and implemented the Cove Point marsh protection placement site. This site is a beneficial use project that created a tidal marsh close to the dredging area and adjacent to the Cove Point marsh, which is on DCP property (Figure 2). Cove Point Marsh is a Maryland Natural Heritage Area that historically supported over 40 rare, threatened, and endangered plant species. The marsh was a unique freshwater ecosystem along the western shore of the Chesapeake Bay until the beach was breached during a 4-day northeaster in This breach allowed brackish tidal bay water to enter the marsh and degrade the freshwater ecosystem. Salinity within the marsh increased from an average of 2.8 ppt to over 17 ppt. The shoreline north of the Cove Point peninsula has also been eroding, up to 400 feet in some areas along the marsh since 1938 (Figure 3). The retreat of this shoreline also threatened the continued viability of the marsh. The beach along Cove Point marsh historically supported the federally listed northeastern beach tiger beetle, which has not been found here since Continued erosion may result in the loss of habitat for this species. Constructing the dredged material placement facility at the Cove Point marsh site, therefore, had the added benefits of protecting the threatened, ecologically valuable, freshwater Cove Point marsh and stabilizing eroding beach habitat for the threatened northeastern beach tiger beetle. The Cove Point marsh protection placement project had three main components: (1) repair of the 2006 breach that converted the former freshwater Cove Point marsh into a brackish water system, (2) a dredged material placement site, which includes a continuous containment structure, placement of dredged material, and creation of tidal marsh, and (3) a segmented breakwater and beach nourishment to protect the beach south of the placement site from shoreline erosion and to enhance habitat for the northeastern beach tiger beetle. To address the ongoing impact to the Cove Point Marsh, DCP recommended using the dredged material from the Pier Reinforcement Project to repair the barrier beach breach and allow the marsh to return to a freshwater ecosystem. DCP worked closely with local, state and federal regulatory and resource agencies, local environmental groups and the local community to design and permit the dredged material area to maximize the environmental benefits. The dredged material placement site was established by constructing a 2,500-foot long stone revetment along the shoreline to protect the dredged material from the tidal and wave action of the Bay, and by sealing the breach with sand through the creation of a dune to separate the dredged material from the Cove Point Marsh. Dredged material was then placed behind the revetment to be planted with salt-tolerant plants creating a salt marsh. The revetment and the newly-created salt marsh protect the Cove Point Marsh, allowing it to return to a freshwater ecosystem. Additionally a series of segmented breakwaters were installed south of the revetment, and imported sand was used to nourish the beach. The segmented breakwaters and sand were designed to provide habitat for the northeastern beach tiger beetle, and to protect the area south of the revetment from potential future breaches.

2 Project Team Members and Affiliations: Team Member Affiliation WEDA Member Role Michael Frederick Randal Rogers. Paul Bastin Kaitlin McCormick Jeffrey Elseroad Rich Pfingsten Timothy Donegan, P.E. Dominion Cove Point LNG, LP Dominion Resources Services, Inc. Dominion Transmission, Inc. EA Engineering, Science, and Technology, Inc. EA Engineering, Science, and Technology, Inc. EA Engineering, Science, and Technology, Inc. Gahagan and Bryant Associates Yes Representative of Project Owner Representative of Project Owner Representative of Project Owner minating Entity; Consultant to Dominion; Placement Site Screening; Permitting and Environmental Compliance Consultant to Dominion; Permitting and Environmental Compliance Expert; EA Project Manager Consultant to Dominion; Wetland Restoration/Development of Planting Plan Consultant to Dominion; Project Manager Environmental Benefits: The project was designed to protect the Cove Point Marsh Natural Heritage Area. The unique habitat provided by the historically freshwater system within the marsh was lost by the 2006 breach to the beach. The barrier beach has breached and healed throughout its existence. However, previous breaches lasted only for weeks or months before they healed. Freshwater inflow from streams and precipitation lowered the salinity within the marsh after the breaches healed, thus minimizing any changes in freshwater marsh conditions and plant species composition. The breach created in 2006 was in existence for over three years, and the inflow of tidal water from the Bay converted the marsh from a non-tidal freshwater barrier wetland to a tidal brackish marsh. Because the marsh substrate was exposed to direct tidal action significant volumes of peat and root mat and the associated seed bank were lost through the breach resulting in more of the marsh converting to open water, thus further increasing the area of the marsh exposed to the erosive force of direct tidal action. This conversion meant the potential loss of the rare freshwater plant species from the marsh. In addition to the loss of freshwater plants, the fish community changed and the freshwater species that once resided in the marsh no longer had habitat. Continued erosion of the beach through the breach and the backside of the beach also posed a threat to historic habitat for the Federally-endangered northeastern beach tiger beetle. Continued erosion would likely prevent the recurrence of this species along the beach.

3 The project created an estimated 12.4 acres of tidal marsh. The created tidal wetland seals off the existing marsh from tidal inundation to allow it to return over time to the nontidal, freshwater marsh that it was before the breach. The dredged material placement site also created approximately 3.8 acres of upland, beach/dune habitat planted with native dune vegetation.

4 The closure of the breach stopped tidal inundation and will allow the marsh to gradually return to its previous condition. w that the breach has been repaired, the Cove Point marsh is expected to convert back to freshwater marsh. The conversion to its historical condition will most likely occur over many years while material accumulates in the marsh and the marsh is gradually flushed with freshwater. w that the habitat is restored, the plant species previously occurring in the marsh will likely begin to return. Without this conversion, there was little likelihood of the return of any of the over 40 state-listed plant species previously documented at the site. An additional approximately 0.5 acres of beach nourishment was completed adjacent to the placement site. This beach nourishment area is located behind a new segmented breakwater to protect the area from erosion. The nourished beach and associated segmented breakwaters are designed to enhance and protect a portion of the beach that has historically supported the northeastern beach tiger beetle. Sand placed as part of the beach nourishment project was of a grain size that supports preferred northeastern beach tiger beetle habitat. Innovation: DCP evaluated and permitted three potential dredged material placement options. One of these was to use an existing innovative reuse project. This existing facility would not have required any additional studies or engineering on the part of DCP, but had high costs associated with the transport of material approximately 180 miles to the site. The second placement option was a beneficial use project that included the construction of breakwaters consisting of shoreline protection and island restoration at Barren Island. The Barren Island project would have built a segmented breakwater system, previously designed by the U.S. Army Corps of Engineers. DCP would then have placed the material dredged as part of the Pier Reinforcement Project behind the breakwaters. DCP recognized a need for environmental restoration at Cove Point Marsh. Rather than implement existing, designed placement options, DCP worked to engineer a solution to meet both DCP s need for placement capacity and the Cove Point Natural Heritage Trust s goal of preserving and protecting Cove Point Marsh. Rather than implement a project that was only a wetland restoration project, DCP integrated the environmental protection goals of (1) restoring Cove Point Marsh, (2) reducing the potential for future breaches of Cove Point Marsh, and (3) restoring and protecting habitat for the northeastern beach tiger beetle, a federally listed species, into the placement site design. DCP developed a hybrid design that included multiple habitats including tidal wetland, mudflat, dune, beach, and shoreline structure. This multifaceted design represents a holistic consideration of the needs of the Cove Point Marsh ecosystem while also meeting the placement capacity needs for the Pier Reinforcement Project. Economic Benefits: Placement of material at the Cove Point Marsh protection placement site provided cost savings for DCP, by eliminating the high transportation costs associated with transporting material to other placement sites, particularly one option considered that was 180 miles from the dredging area. The use of the Cove Point Marsh protection placement site also eliminated the need to handle dredged material. Material was hydraulically dredged from the offshore pier and pumped directly into the placement site. The other placement options evaluated would have required mechanical dredging, transport, and offloading at the placement site. Without the development of Cove Point Marsh protection placement site, there would not have been funding for repair of the breach at Cove Point Marsh. This provided cost savings, associated with

5 the repair of the breach, to the Cove Point Marsh Natural Heritage Trust. Further, since the repair of the breach, storm action has threatened the beach along Cove Point Marsh, but the wetland cell has withstood wind and wave action, preventing any new breaches of the dune system within the armored shoreline area. Had the breach not been repaired, it would have continued to expand, increasing repair costs of the breach. This repair would have then been the responsibility of the Trust, if it was to be completed. Transferability: DCP s Pier Reinforcement Project should provide a case study for the preferred method to identify dredged material placement sites. The comprehensive planning and screening of potential placement sites throughout the region and consideration of non-traditional placement options is recommended for all projects. DCP first screened a wide range of placement options and considered all potential placement options, including those options not even to the conceptual phase. After a long list of potential placement options was developed, this list was narrowed based on the characteristics of the placement site needed. This screening considered the costs, geotechnical constraints, chemical characteristics, timing, environmental benefits, and regulatory requirements applicable to both the placement sites and the material to be dredged as part of the Pier Reinforcement Project. This screening resulted in a short-list of placement options that was narrowed to three viable placement options: Cove Point Marsh protection placement site, Barren Island, and agricultural reuse. This planning process was very successful and identified a site (Cove Point Marsh) that would not have traditionally been identified as placement site. Another transferable component of this project is the nature of the placement site. Wetland restoration is a beneficial use project that can be implemented as a placement project for any dredging project with uncontaminated dredged material. DCP has demonstrated its commitment to environmental stewardship, which is a goal of many industries and entities with the growing push toward sustainability and environmental responsibility. This project is a case study demonstrating that a company can complete environmental restoration projects while also developing a costeffective and environmentally beneficial solution for dredged material placement. Outreach and Education: Dominion coordinated the repair of the breach at Cove Point Marsh with the Cove Point Natural Heritage Trust (the Trust). The Trust s mission is to preserve and protect ecologically sensitive sites at Cove Point and vicinity through land conservation, scientific research, and environmental education. DCP worked with the Trust to develop an appropriate method to repair the breach while also developing the needed dredged material placement capacity.

6 Dominion partnered with the National Aquarium in Baltimore's Conservation Team for the planting of the wetland and dune system created to seal the breach at Cove Point Marsh. This program is based on partnerships with a variety of organizations in the region around the Chesapeake Bay. These partnerships create opportunities for volunteers to help restore tidal wetlands throughout the Chesapeake Bay and its tributaries. Volunteers and members of the Aquarium's Conservation Team completed a planting project along the dunes at the site in February The volunteer groups consisted of local school students, community leaders and local community volunteers. The approximate 2-acre dune was planted with American beach grass (Ammophila bevilgulata), coastal panic grass (Panicum amarum) and Virginia switchgrass (Panicum virgatum). A second planting event, to plant vegetation within the approximately 11-acre tidal wetland with salt-tolerant marsh plants, which will stabilize the dredged material, is scheduled for May 11 to 14, The Aquarium's Conservation Team generates both a volunteer and hands-on learning opportunities for the public. The partnership between Dominion and the Aquarium provided an opportunity for Aquarium and Dominion staff to work with interested participants to educate them about wetland ecology, planting methods, and the unique wetland community at Cove Point Marsh. DCP is also working with the Providence Center, a nonprofit organization that operates greenhouses and offers employment services to mentally handicapped adults to grow the marsh plants. Providence Center currently is growing the plants for the May 2011 planting. Other: This project is deserving of an environmental award from the Western Dredging Association (WEDA), because it meets both the goals of DCP, by providing a dredged material placement site, while also developing an innovative environmental restoration project that addressed multiple environmental needs. DCP worked in consultation with local, state and federal resource agencies (Calvert County Department of Planning, Maryland Department of Natural Resources, Maryland Department of the Environment, U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service, and National Marine Fisheries Service), as well as with local stakeholders (Cove Point Natural Heritage Trust) to develop a comprehensive plan that met the multiple environmental concerns and the differing habitat needs of multiple sensitive species. DCP successfully placed all their dredged material at the site, meeting their project goals. DCP sealed the breach at Cove Point Marsh, beginning the natural succession of the site to its historic condition as a freshwater marsh. DCP also constructed a segmented breakwater system, protecting potential northeastern beach tiger beetle habitat, simultaneously with the construction of the dikes for the placement facility. The linking of the placement site with the environmental project into a single and complete project, rather than a series of segmented projects, represents a holistic approach to beneficial use of dredged material. DCP also found a way to incorporate the interested public through the Aquarium s Conservation Team. The community outreach program provides an educational, environmental stewardship project for any member of the public interested in gaining a deeper understanding of environmental restoration project or the specific restoration project at Cove Point Marsh. DCP serves a role model to the dredging community, by demonstrating that there are cost-effective, ways to merge industry needs with environmental stewardship in a cost-effective and innovative manner. DCP s Cove Point Marsh protection project associated with the Pier Reinforcement Project exceeds all criteria for the WEDA Environmental Excellence Award and deserves recognition for this exemplary project.

7 Figure 1. Vicinity Map

8 Approximate Dredging Area Cove Point Marsh Protection Placement Site Figure 2. Aerial Photo with Project Area

9 Figure 3. Historical Shorelines at Cove Point Marsh

May 4, Applicant: Lake Charles Harbor and Terminal District 150 Marine Street Lake Charles, Louisiana 70602

May 4, Applicant: Lake Charles Harbor and Terminal District 150 Marine Street Lake Charles, Louisiana 70602 2011 Environmental Excellence Award Application May 4, 2011 Applicant: Lake Charles Harbor and Terminal District 150 Marine Street Lake Charles, Louisiana 70602 Contact: Mr. Channing Hayden, Jr. Director

More information

MANAGEMENT OF WATERFRONT PROPERTIES FOR HOMEOWNERS

MANAGEMENT OF WATERFRONT PROPERTIES FOR HOMEOWNERS Prince William County Watershed Management MANAGEMENT OF WATERFRONT PROPERTIES FOR HOMEOWNERS Living along the shoreline brings many rewards for the property owner: a great view, a closeness to nature

More information

U.S. Army Corps of Engineers Mobile District

U.S. Army Corps of Engineers Mobile District U.S. Army Corps of Engineers Mobile District General Permit for Living Shorelines in Alabama Sandy P. Gibson Regulatory Specialist, Coastal Alabama Regulatory Division, Mobile District US Army Corps of

More information

2014 WEDA Environmental Excellence Award Application for Navigation/Environmental Dredging Projects Submitted by the Port of Stockton, California

2014 WEDA Environmental Excellence Award Application for Navigation/Environmental Dredging Projects Submitted by the Port of Stockton, California 2014 WEDA Environmental Excellence Award Application for Navigation/Environmental Dredging Projects Submitted by the Port of Stockton, California SUMMARY: The Port of Stockton (Port) is located in the

More information

Protect, Accommodate, or Retreat? Integrating Adaptation Strategies and Ecosystem Services into the Cape Cod Coastal Planner

Protect, Accommodate, or Retreat? Integrating Adaptation Strategies and Ecosystem Services into the Cape Cod Coastal Planner Protect, Accommodate, or Retreat? Integrating Adaptation Strategies and Ecosystem Services into the Cape Cod Coastal Planner Jennifer Clinton Cape Cod Commission April Wobst Association to Preserve Cape

More information

PA-03. Honorable Mike Kelly. Pennsylvania 114th Congress. 3rd Congressional District. Miles

PA-03. Honorable Mike Kelly. Pennsylvania 114th Congress. 3rd Congressional District. Miles PA-03 Honorable Mike Kelly Pennsylvania 114th Congress 3rd Congressional District 2 3 & 1&& / 0 1, O&M, Erie Harbor 2, CG-CAP 204, Presque Isle Regional Sediment Management 3, CG, Presque Isle Shoreline

More information

SEPTEMBER 18, 2018 SUBMITTED TO: STATE OF NEW YORK DEPARTMENT OF STATE COASTAL ZONE MANAGEMENT PROGRAM

SEPTEMBER 18, 2018 SUBMITTED TO: STATE OF NEW YORK DEPARTMENT OF STATE COASTAL ZONE MANAGEMENT PROGRAM COASTAL ZONE MANAGEMENT CONSISTENCY DETERMINATION FOR THE IMPROVEMENT DREDGING OF THE NEW HAVEN HARBOR FEDERAL NAVIGATION PROJECT (NEW HAVEN, CONNECTICUT) SEPTEMBER 18, 2018 SUBMITTED TO: STATE OF NEW

More information

Estuarine Restoration in San Francisco Bay: Design and Adaptive Management. Environmental Management of Enclosed Coastal Seas

Estuarine Restoration in San Francisco Bay: Design and Adaptive Management. Environmental Management of Enclosed Coastal Seas Estuarine Restoration in San Francisco Bay: Design and Adaptive Management Environmental Management of Enclosed Coastal Seas August 31, 2011 Eric Jolliffe, Bill Brostoff, and Fari Tabatabai U. S. Army

More information

Gulf of Mexico Hydrological Restoration Criteria for Identifying and Prioritizing Projects

Gulf of Mexico Hydrological Restoration Criteria for Identifying and Prioritizing Projects Gulf of Mexico Hydrological Restoration Criteria for Identifying and Prioritizing Projects Definition of hydrological restoration for this Partnership To remove or modify anthropogenic barriers to restore

More information

2013 WEDA Environmental Excellence Award Deer Island Restoration Project U.S. Army Corps of Engineers, Mobile District

2013 WEDA Environmental Excellence Award Deer Island Restoration Project U.S. Army Corps of Engineers, Mobile District Award Category: Navigation Dredging 2013 WEDA Environmental Excellence Award Deer Island Restoration Project U.S. Army Corps of Engineers, Mobile District Project Summary: Deer Island is a 3.5-mile long

More information

Ecotourism Business Owner

Ecotourism Business Owner Local Resident You have been selected to represent your community on this issue. Your community is a beach community. Members of your community enjoy living where they do because they enjoy seeing wildlife

More information

STRATEGIC PLAN Jug Bay Wetlands Sanctuary STRATEGIC PLAN

STRATEGIC PLAN Jug Bay Wetlands Sanctuary STRATEGIC PLAN 2015-2020 Jug Bay Wetlands Sanctuary STRATEGIC PLAN 0 JUG BAY WETLANDS SANCTUARY http://www.jugbay.org/ 1 INTRODUCTION Natural habitats at local, state, national and international levels are threatened

More information

Request for a Proposal The Bolsa Chica Lowlands Restoration Project: Sustainability Alternatives Study January 2019

Request for a Proposal The Bolsa Chica Lowlands Restoration Project: Sustainability Alternatives Study January 2019 Request for a Proposal The Bolsa Chica Lowlands Restoration Project: Sustainability Alternatives Study January 2019 Introduction The Bolsa Chica Land Trust (BCLT) has applied for and been selected to receive

More information

EVALUATION OF SECTION 404(b)(1) GUIDELINES (SHORT FORM)

EVALUATION OF SECTION 404(b)(1) GUIDELINES (SHORT FORM) EVALUATION OF SECTION 404(b)(1) GUIDELINES (SHORT FORM) PROPOSED PROJECT: Matagorda Ship Channel Deficiency Study and Environmental Assessment (Nov 2017) 1. Review of Compliance (230.10(a)-(d)) A review

More information

COASTAL CONSERVANCY. Staff Recommendation June 16, 2005 PIER 94 WETLAND ENHANCEMENT. File No Project Manager: Joan Cardellino

COASTAL CONSERVANCY. Staff Recommendation June 16, 2005 PIER 94 WETLAND ENHANCEMENT. File No Project Manager: Joan Cardellino COASTAL CONSERVANCY Staff Recommendation June 16, 2005 PIER 94 WETLAND ENHANCEMENT File No. 05-38 Project Manager: Joan Cardellino RECOMMENDED ACTION: Authorization to disburse up to $132,600 to the Port

More information

Mississippi Coastal Improvements Program A Comprehensive Plan for Coastal Resilience

Mississippi Coastal Improvements Program A Comprehensive Plan for Coastal Resilience Mississippi Coastal Improvements Program A Comprehensive Plan for Coastal Resilience 200 Coastal Resilience Symposium 26 May 200 US Army Corps of Engineers BUILDING STRONG Mississippi Coastal Improvements

More information

2.00 PURPOSE AND NEED FOR ACTION Project Area

2.00 PURPOSE AND NEED FOR ACTION Project Area 2.00 PURPOSE AND NEED FOR ACTION 2.01 Project Area The project area is located in Chatham County, Georgia, and Jasper County, South Carolina. These counties lie in the Coastal Plain physiographic province

More information

CHESAPEAKE BAY COMPREHENSIVE WATER RESOURCES AND RESTORATION PLAN. Update to Chesapeake Bay Program Management Board June 14, 2018

CHESAPEAKE BAY COMPREHENSIVE WATER RESOURCES AND RESTORATION PLAN. Update to Chesapeake Bay Program Management Board June 14, 2018 CHESAPEAKE BAY COMPREHENSIVE WATER RESOURCES AND 255 255 255 237 237 237 0 0 0 217 217 217 163 163 163 200 200 200 131 132 122 239 65 53 80 119 27 RESTORATION PLAN 110 135 120 252 174.59 112 92 56 62 102

More information

NATIONAL OCEAN SERVICE

NATIONAL OCEAN SERVICE NATIONAL OCEAN SERVICE Jeff Payne, Ph.D., Office for Coastal Management Steve Thur, Ph.D., Acting Director National Centers for Coastal Ocean Science February 23, 2017 NATIONAL OCEAN SERVICE oceanservice.noaa.gov

More information

Science For Coastal Wetland Restoration

Science For Coastal Wetland Restoration Science For Coastal Wetland Restoration Dr. Alfred F. Cofrancesco Technical Director Engineer Research and Development Center; Vicksburg, MS 24 May 2010 US Army Corps of Engineers Coastal Wetlands Restoration

More information

Masonville Dredged Material Project and Mitigation

Masonville Dredged Material Project and Mitigation Masonville Dredged Material Project and Mitigation Background and Status Report Presented To: AAPA HNE Seminar, June 7 th, 2006 Presentation Overview Dredging Challenges Recommendations Masonville Proposal

More information

Atlantic Coast of NY, East Rockaway Inlet to Rockaway Inlet and Jamaica Bay APPENDIX N COASTAL ZONE MANAGEMENT

Atlantic Coast of NY, East Rockaway Inlet to Rockaway Inlet and Jamaica Bay APPENDIX N COASTAL ZONE MANAGEMENT Atlantic Coast of NY, East Rockaway Inlet to Rockaway Inlet and Jamaica Bay APPENDIX N COASTAL ZONE MANAGEMENT Hurricane Sandy General Reevaluation Report August 2016 New York (and New York City Local

More information

Comprehensive Barrier Island Restoration Plan

Comprehensive Barrier Island Restoration Plan Mississippi Coastal Improvements Program (MsCIP) Comprehensive Barrier Island Restoration Plan 202 National Conference on Beach Preservation Technology February 0, 202 Justin McDonald, P.E. Lead Project

More information

The Colley Bay Story: Successful Implementation of a Living Shoreline

The Colley Bay Story: Successful Implementation of a Living Shoreline The Colley Bay Story: Successful Implementation of a Living Shoreline Definition Living Shoreline Treatments address erosion in lower energy situations by providing long-term protection, restoration or

More information

GREAT KILLS HARBOR, STATEN ISLAND, NEW YORK FEDERAL NAVIGATION PROJECT MAINTENANCE DREDGING

GREAT KILLS HARBOR, STATEN ISLAND, NEW YORK FEDERAL NAVIGATION PROJECT MAINTENANCE DREDGING Public Notice In replying refer to: Public Notice No. GREAT KILLS HARBOR FY13 Published: April 30, 2013, Expires: May 30, 2013 New York District 26 Federal Plaza New York, N.Y. 10278 ATTN: CENAN-OP-ST

More information

Testimony of Shari T. Wilson, Secretary Maryland Department of the Environment. Before. The Senate Committee on Environment and Public Works

Testimony of Shari T. Wilson, Secretary Maryland Department of the Environment. Before. The Senate Committee on Environment and Public Works Testimony of Shari T. Wilson, Secretary Maryland Department of the Environment Before The Senate Committee on Environment and Public Works The Clean Energy Jobs and American Power Act (S. 1733) Wednesday,

More information

02 APRIL PUBLIC NOTICE U.S. Army Corps of Engineers, Savannah District

02 APRIL PUBLIC NOTICE U.S. Army Corps of Engineers, Savannah District DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS, SAVANNAH DISTRICT 100 W. OGLETHORPE AVENUE SAVANNAH, GEORGIA 31401-3604 Planning Branch TO WHOM IT MAY CONCERN: 02 APRIL 2019 PUBLIC NOTICE U.S. Army

More information

Newtown Creek. Restoration Ecology. February 6, 2014 John McLaughlin Director, Office of Ecological Services

Newtown Creek. Restoration Ecology. February 6, 2014 John McLaughlin Director, Office of Ecological Services Newtown Creek Restoration Ecology February 6, 2014 John McLaughlin Director, Office of Ecological Services Office of Ecological Services Mission Statement Statement To protect and improve the ecological

More information

ENVIRONMENTAL RESTORATION IN COASTAL MISSISSIPPI: MARSH RE-ESTABLISHMENT PROJECT HARRISON AND JACKSON COUNTIES, MISSISSIPPI

ENVIRONMENTAL RESTORATION IN COASTAL MISSISSIPPI: MARSH RE-ESTABLISHMENT PROJECT HARRISON AND JACKSON COUNTIES, MISSISSIPPI SECTION 404(b)(1) EVALUATION REPORT FOR THE SECTION 204 ECOSYSTEM RESTORATION PROJECT IN CONNECTION WITH CONSTRUCTION, OPERATION, OR MAINTENANCE DREDGING OF A FEDERALLY AUTHORIZED PROJECT ENVIRONMENTAL

More information

RESTORE Act Planning. Kyle Graham Executive Director CPRA. November 12, committed to our coast

RESTORE Act Planning. Kyle Graham Executive Director CPRA. November 12, committed to our coast RESTORE Act Planning Kyle Graham Executive Director CPRA November 12, 2014 committed to our coast committed to our coast Oil Spill Funds Allocated to Date NRDA - Early Restoration Project Name Basin Funded

More information

Debbie DeVore South Florida Coastal Program U.S. Fish and Wildlife Service Vero Beach, FL

Debbie DeVore South Florida Coastal Program U.S. Fish and Wildlife Service Vero Beach, FL Debbie DeVore South Florida Coastal Program U.S. Fish and Wildlife Service Vero Beach, FL www.cbtrust.org 30% of Mobile Bay has been armored as of 1997 using rip-rap, seawalls, and bulkheads (Douglass

More information

Tampa Port Authority

Tampa Port Authority McKay Bay Restoration (McKay Bay Mitigation Site and McKay Bay Dredge Hole Restoration) Tampa Port Authority 2014 AAPA Environmental Awards Competition June 2014 Contact: Andy Fobes, Director of Public

More information

COASTAL TX PROTECTION AND RESTORATION FEASIBILITY STUDY

COASTAL TX PROTECTION AND RESTORATION FEASIBILITY STUDY COASTAL TX PROTECTION AND RESTORATION FEASIBILITY STUDY Stakeholders Forum Dr. Kelly Burks-Copes, Project Manager Mr. Tony Williams, Coastal Resources US Army Corps of Engineers, Galveston District Texas

More information

SANDY HOOK CHANNEL, NEW YORK HARBOR FEDERAL NAVIGATION PROJECT MAINTENANCE DREDGING

SANDY HOOK CHANNEL, NEW YORK HARBOR FEDERAL NAVIGATION PROJECT MAINTENANCE DREDGING Public Notice In replying refer to: Public Notice No. Sandy Hook Channel, NY Harbor FY17 Published: 14 February 2017 Expires: 14 March 2017 New York District 26 Federal Plaza New York, N.Y. 10278 ATTN:

More information

Issues in measuring and managing changes to the ecological character of the Western Port Ramsar Site as a result of climate change

Issues in measuring and managing changes to the ecological character of the Western Port Ramsar Site as a result of climate change presenter: Shelley Heron Issues in measuring and managing changes to the ecological character of the Western Port Ramsar Site as a result of climate change Western Port Bay Where is it? Ecological character

More information

What is an ecosystem?

What is an ecosystem? What is an ecosystem? An ecosystem is generally defined as a community of organisms living in a particular environment and the physical elements in that environment with which they interact. (http://www.enviroliteracy.org/category.php/3.html)

More information

SECTION 404(b)(1) EVALUATION REPORT FOR THE FOR THE OPERATIONS AND MAINTENANCE OF THE FEDERALLY AUTHORIZED BILOXI HARBOR NAVIGATION PROJECT OTT BAYOU

SECTION 404(b)(1) EVALUATION REPORT FOR THE FOR THE OPERATIONS AND MAINTENANCE OF THE FEDERALLY AUTHORIZED BILOXI HARBOR NAVIGATION PROJECT OTT BAYOU SECTION 404(b)(1) EVALUATION REPORT FOR THE FOR THE OPERATIONS AND MAINTENANCE OF THE FEDERALLY AUTHORIZED BILOXI HARBOR NAVIGATION PROJECT OTT BAYOU HARRISON COUNTY, MISSISSIPPI I. PROJECT DESCRIPTION:

More information

Maria W. Merrill Florida Fish and Wildlife Conservation Commission Aquatic Habitat Conservation and Restoration Section April 12, 2013

Maria W. Merrill Florida Fish and Wildlife Conservation Commission Aquatic Habitat Conservation and Restoration Section April 12, 2013 Maria W. Merrill Florida Fish and Wildlife Conservation Commission Aquatic Habitat Conservation and Restoration Section April 12, 2013 Focus Region 16 Coastal counties from Perdido Key east to Anclote

More information

CIVITAS is a neighborhood non-profit organization dedicated to improving quality of life on the Upper East Side and in East Harlem.

CIVITAS is a neighborhood non-profit organization dedicated to improving quality of life on the Upper East Side and in East Harlem. CIVITAS is a neighborhood non-profit organization dedicated to improving quality of life on the Upper East Side and in East Harlem. CIVITAS focuses its efforts on planning, zoning, and environmental issues.

More information

New Haven Harbor, Connecticut Navigation Improvement Feasibility Study and Environmental Impact Statement

New Haven Harbor, Connecticut Navigation Improvement Feasibility Study and Environmental Impact Statement New Haven Harbor, Connecticut Navigation Improvement Feasibility Study and Environmental Impact Statement Public Informational Meeting NEPA Scoping 24 January 2017 Planning Division New England District

More information

Gulf of Mexico Alliance Supplemental PIT Project Funding Opportunity

Gulf of Mexico Alliance Supplemental PIT Project Funding Opportunity Gulf of Mexico Alliance Supplemental PIT Project Funding Opportunity PIT: Ecosystems Integration and Assessment Coordinator: Cristina Carollo, Harte Research Institute State Lead: Larry McKinney, Harte

More information

Advancing Nature-Based Solutions An overview of living shorelines and the U.S Army Corps of Engineers proposed permit

Advancing Nature-Based Solutions An overview of living shorelines and the U.S Army Corps of Engineers proposed permit Advancing Nature-Based Solutions An overview of living shorelines and the U.S Army Corps of Engineers proposed permit Laura Lightbody, The Pew Charitable Trusts llightbody@pewtrusts.org Charley Chesnutt,

More information

CONTINUING AUTHORITIES PROGRAM (CAP) OVERVIEW

CONTINUING AUTHORITIES PROGRAM (CAP) OVERVIEW CONTINUING AUTHORITIES PROGRAM (CAP) OVERVIEW USACE Jacksonville District Brandon Burch Project Manager Trusted Partners Delivering Value, Today and Tomorrow Trusted Partners Delivering Value, Today and

More information

Protecting and Restoring Habitat (Fact Sheet)

Protecting and Restoring Habitat (Fact Sheet) University of Southern Maine USM Digital Commons Publications Casco Bay Estuary Partnership (CBEP) 2014 Protecting and Restoring Habitat (Fact Sheet) Casco Bay Estuary Partnership Follow this and additional

More information

Maritime Forest Ridge and Marsh Recreation Project

Maritime Forest Ridge and Marsh Recreation Project Maritime Forest Ridge and Marsh Recreation Project At Port Fourchon AAPA Environmental Awards June 1, 2006 Contact: Paula Schouest, Public Information Coordinator (985) 632-6701, paulas@portfourchon.com

More information

PUBLIC NOTICE NO. FP13-AB03-05 August 30, 2013 CESAM-PD-EC JOINT PUBLIC NOTICE

PUBLIC NOTICE NO. FP13-AB03-05 August 30, 2013 CESAM-PD-EC JOINT PUBLIC NOTICE DEPARTMENT OF THE ARMY MOBILE DISTRICT, CORPS OF ENGINEERS P.O. BOX 2288 MOBILE, ALABAMA 36628-0001 REPLY TO ATTENTION OF: JOINT PUBLIC NOTICE U. S. ARMY CORPS OF ENGINEERS, MOBILE DISTRICT AND FLORIDA

More information

A Guide to Shoreline Management Planning For Virginia s Coastal Localities

A Guide to Shoreline Management Planning For Virginia s Coastal Localities A Guide to Shoreline Management Planning For Virginia s Coastal Localities Introduction People who live along Virginia s shore enjoy a natural connection to the water. When erosion threatens their property,

More information

Coastal Marsh Restoration/Living Shoreline Pilot Projects in the Mid-Atlantic Region

Coastal Marsh Restoration/Living Shoreline Pilot Projects in the Mid-Atlantic Region Coastal Marsh Restoration/Living Shoreline Pilot Projects in the Mid-Atlantic Region Rejina Sharma, Lawrence Malizzi, Robert Fiorile Delaware Estuary Science & Environmental Summit 2015 January 25-28,

More information

The release of the Final Environmental Impact Statement (FEIS) for the Bogue

The release of the Final Environmental Impact Statement (FEIS) for the Bogue This document is scheduled to be published in the Federal Register on 03/05/2018 and available online at https://federalregister.gov/d/2018-04408, and on FDsys.gov BILLING CODE: 3720-58 DEPARTMENT OF DEFENSE

More information

Port of Stockton Antioch Dunes Restoration Project

Port of Stockton Antioch Dunes Restoration Project June 1, 2017 AAPA ENVIRONMENTAL IMPROVEMENT AWARD ENTRY: ENVIRONMENTAL ENHANCEMENT CATEGORY Port of Stockton Contact: Jason Cashman, Environmental and Regulatory Affairs jcashman@stocktonport.com 209.946.0246

More information

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R September 7, 2017

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R September 7, 2017 THIS IS NOT A PAID ADVERTISEMENT Public Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. Date CENAP-OP-R-2017-00042 September 7, 2017 Application

More information

Appendix C. Clean Water Act: Section 404(b)(1) Evaluation

Appendix C. Clean Water Act: Section 404(b)(1) Evaluation Appendix C Clean Water Act: Section 404(b)(1) Evaluation CLEAN WATER ACT: SECTION 404 (b) (1) EVALUATION CLEAN WATER ACT: SECTION 404 (b) (1) EVALUATION MONTAUK POINT STORM DAMAGE REDUCTION PROJECT MONTAUK

More information

Understanding Living Shorelines:

Understanding Living Shorelines: Understanding Living Shorelines: Their use, benefits, design principles, costs, and barriers and solutions to successful implementation, VA kevin.dubois@norfolk.gov Definition Living Shoreline Treatments

More information

Long Island s. Environmental Issues. Environmental Issues. Environmental Setting. Environmental Setting. Suburbia and the Environment

Long Island s. Environmental Issues. Environmental Issues. Environmental Setting. Environmental Setting. Suburbia and the Environment Environmental Issues Long Island s Environmental Issues Copyright 2011 AFG 1 agricultural land air pollution aquifers automobile barrier islands biozones fisheries groundwater recharge invasive species

More information

Notice of Availability (NOA) of the Draft Environmental Impact Statement. (DEIS) and the Announcement of a Public Hearing for the Installation of a

Notice of Availability (NOA) of the Draft Environmental Impact Statement. (DEIS) and the Announcement of a Public Hearing for the Installation of a This document is scheduled to be published in the Federal Register on 08/28/2015 and available online at http://federalregister.gov/a/2015-21282, and on FDsys.gov BILLING CODE: 3720-58 DEPARTMENT OF DEFENSE

More information

A Vision for a Healthy, Productive, and Sustainable Galveston Bay

A Vision for a Healthy, Productive, and Sustainable Galveston Bay A Vision for a Healthy, Productive, and Sustainable Galveston Bay Bob Stokes, President Preserving, protecting, and enhancing Galveston Bay for 29 years A bit about our Bay Largest bay in Texas (660 square

More information

RECOMMENDATIONS TO THE NORTH CAROLINA LEGISLATIVE COMMISSION ON GLOBAL CLIMATE CHANGE (NC LCGCC)

RECOMMENDATIONS TO THE NORTH CAROLINA LEGISLATIVE COMMISSION ON GLOBAL CLIMATE CHANGE (NC LCGCC) RECOMMENDATIONS TO THE NORTH CAROLINA LEGISLATIVE COMMISSION ON GLOBAL CLIMATE CHANGE (NC LCGCC) INTRODUCTION Stanley R. Riggs Department of Geological Sciences East Carolina University Greenville, NC

More information

Mobile Bay National Estuary Program Project Implementation Committee Trade Center February 18, 2016

Mobile Bay National Estuary Program Project Implementation Committee Trade Center February 18, 2016 Mobile Bay National Estuary Program Project Implementation Committee Trade Center February 18, 2016 Presented by: Elizabeth S. Godsey, P.E, United States Army Corps of Engineers, Mobile District US Army

More information

U. S. Steel Duluth Works - Spirit Lake Cleanup Plan FAQs

U. S. Steel Duluth Works - Spirit Lake Cleanup Plan FAQs St. Louis River Area of Concern U. S. Steel Duluth Works - Spirit Lake Cleanup Plan FAQs Spirit Lake is a large, open area in the St. Louis River that has cultural, historical, and recreational significance

More information

Restoring Ecosystems, Strengthening Communities October 20 25, 2012 Tampa, Florida

Restoring Ecosystems, Strengthening Communities October 20 25, 2012 Tampa, Florida 6 th National Conference on Coastal and Estuarine Habitat Restoration Restoring Ecosystems, Strengthening Communities October 20 25, 2012 Tampa, Florida 1 From There to Here and Beyond The Situation Challenges

More information

Living Shorelines for Coastal Erosion Protection in a Changing World Jay Tanski New York Sea Grant

Living Shorelines for Coastal Erosion Protection in a Changing World Jay Tanski New York Sea Grant Living Shorelines for Coastal Erosion Protection in a Changing World Jay Tanski New York Sea Grant jjt3@cornell.edu New York Sea Grant Workshop May 15, 2013 Hauppauge, New York Source: Newsday Shore Armoring

More information

Habitat Conservation and Fisheries

Habitat Conservation and Fisheries Habitat Conservation and Fisheries Buck Sutter Director, Office of Habitat Conservation July 14, 2014 Habitat Mission Protect and restore coastal and marine habitat to support sustainable fisheries and

More information

North Carolina Coastal Federation

North Carolina Coastal Federation North Carolina Coastal Federation Founded in 1982 Non-Profit 501(c)(3) 10,000 Citizen Members 1,200 Student/Adult Volunteers 150 Affiliated Groups Staff of 19 27 Board Members Education Restoration & Preservation

More information

City of Ocean City Lagoon/Back Bay Dredging Town Hall Meeting

City of Ocean City Lagoon/Back Bay Dredging Town Hall Meeting City of Ocean City Lagoon/Back Bay Dredging Town Hall Meeting Total Estimated Dredge Material required for North to South of the City 500,000 Cubic Yards of Dredge Material Includes: North to South of

More information

CHESAPEAKE BAY COMPREHENSIVE WATER RESOURCES AND RESTORATION PLAN - UPDATE. Update to Chesapeake Bay Program STAR January 25, 2018

CHESAPEAKE BAY COMPREHENSIVE WATER RESOURCES AND RESTORATION PLAN - UPDATE. Update to Chesapeake Bay Program STAR January 25, 2018 CHESAPEAKE BAY COMPREHENSIVE WATER RESOURCES AND RESTORATION 255 255 255 237 237 237 0 0 0 217 217 217 163 163 163 200 200 200 PLAN - UPDATE 131 132 122 239 65 53 80 119 27 110 135 120 252 174.59 112 92

More information

Salt Bayou Beneficial Use Project on J.D. Murphree WMA

Salt Bayou Beneficial Use Project on J.D. Murphree WMA Salt Bayou Beneficial Use Project on J.D. Murphree WMA 1300-Acre Marsh Restoration Project at J.D. Murphree WMA Most people would be hard-pressed to find a use for 2 million cubic yards of silt-saturated

More information

NEW HAVEN HARBOR CONNECTICUT NAVIGATION IMPROVEMENT

NEW HAVEN HARBOR CONNECTICUT NAVIGATION IMPROVEMENT NEW HAVEN HARBOR CONNECTICUT NAVIGATION IMPROVEMENT 255 255 255 237 237 237 0 0 0 217 217 217 163 163 163 200 200 200 INTEGRATED FEASIBILITY STUDY AND ENVIRONMENTAL IMPACT STATEMENT 131 132 122 PUBLIC

More information

JACKSONVILLE HARBOR DEEPENING MAYOR S TASK FORCE

JACKSONVILLE HARBOR DEEPENING MAYOR S TASK FORCE JACKSONVILLE HARBOR DEEPENING MAYOR S TASK FORCE Presented by: Colonel Alan Dodd Jacksonville District, U.S. Army Corps of Engineers August 7, 2014 47-foot Deepening 2.7 BCR Total Federal Cost: $ 312.7

More information

Achieving the Philosophy of GOMA Through MsCIP

Achieving the Philosophy of GOMA Through MsCIP Achieving the Philosophy of GOMA Through MsCIP 4 th National Conference on Ecosystem Restoration August 3, 2011 The Spirit of Cooperation Integrating Partnerships for Sustainable Ecosystem Restoration

More information

Florida Inland Navigation District: Permitting and Construction of the M 5 Island Offloading & Crossroads Maintenance Dredging and the NA 1 Upland

Florida Inland Navigation District: Permitting and Construction of the M 5 Island Offloading & Crossroads Maintenance Dredging and the NA 1 Upland Florida Inland Navigation District: Permitting and Construction of the M 5 Island Offloading & Crossroads Maintenance Dredging and the NA 1 Upland DMMA Facility Authored by Lori Brownell, P.E. and John

More information

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT Public Notice U.S. Army Corps Permit Application No: SWG-2015-00114 Of Engineers Date Issued: 18 October 2018 Galveston District Comments Due: 19 November 2018 U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT

More information

ATTACHMENT 2 PROJECT NEED AND JUSTIFICATION

ATTACHMENT 2 PROJECT NEED AND JUSTIFICATION ATTACHMENT 2 PROJECT NEED AND JUSTIFICATION INTRODUCTION The Project includes providing erosion control and shoreline stabilization measures including beach nourishment, maintenance dredging and bypassing,

More information

APPENDIX B PROJECT DESCRIPTION AND ALTERNATIVE ANALYSIS

APPENDIX B PROJECT DESCRIPTION AND ALTERNATIVE ANALYSIS APPENDIX B PROJECT DESCRIPTION AND ALTERNATIVE ANALYSIS INTRODUCTION The Chesapeake Energy Center (Station), owned and operated by Virginia Electric and Power Company dba Dominion Virginia Power (Dominion),

More information

Adapting Living Shorelines: Siting and Design for Climate Impacts

Adapting Living Shorelines: Siting and Design for Climate Impacts Adapting Living Shorelines: Siting and Design for Climate Impacts Molly Mitchell & Donna Marie Bilkovic Monitoring and Assessing Impacts of Changes in Weather Patterns and Extreme Events on BMP Siting

More information

Appendix 1 CWA Section 404 Compliance Forms Section 404(b)(1) Guideline Short Form and Coastal Zone Consistency

Appendix 1 CWA Section 404 Compliance Forms Section 404(b)(1) Guideline Short Form and Coastal Zone Consistency Appendix 1 CWA Section 404 Compliance Forms Section 404(b)(1) Guideline Short Form and Coastal Zone Consistency HSC PDR for HSC Flare at Bayport Ship Channel Environmental Assessment This page left intentionally

More information

Restoring The Elizabeth River From The Bottom Up

Restoring The Elizabeth River From The Bottom Up Restoring The Elizabeth River From The Bottom Up Presented by: Joe Rieger Elizabeth River Project Co-author: Walter Priest, NOAA Restoration Center www.elizabethriver.org The Elizabeth River Project Mission:

More information

J O I N T P U B L I C N O T I C E

J O I N T P U B L I C N O T I C E J O I N T P U B L I C N O T I C E CHARLESTON DISTRICT, CORPS OF ENGINEERS 69A Hagood Avenue Charleston, SC 29403-5107 and THE S.C. DEPARTMENT OF HEALTH AND ENVIRONMENTAL CONTROL Office of Ocean and Coastal

More information

Deer Island Aquatic Ecosystem Restoration Project

Deer Island Aquatic Ecosystem Restoration Project ERDC TN-EWN-15-2 Deer Island Aquatic Ecosystem Restoration Project By Jennifer Gerhardt Smith, Justin McDonald, Susan Ivester Rees, and Nathan Lovelace PURPOSE: Implementation of Engineering With Nature

More information

Elkhorn Slough Researchers Link Salt Marsh Dieback to Algal Blooms Generated by Increased Nutrients

Elkhorn Slough Researchers Link Salt Marsh Dieback to Algal Blooms Generated by Increased Nutrients MEDIA RELEASE For immediate release: June 5, 2017 For more information: Lorili Toth, Director of Development & Communications Elkhorn Slough Foundation Email: Lorili@elkhornslough.org phone: 831.728.5939

More information

Living Shorelines. In this issue... What is a living shoreline?

Living Shorelines. In this issue... What is a living shoreline? In this issue... We focus on an approach to shoreline management known as living shoreline designs. These strategies for managing erosion while preserving ecological services are increasingly viewed as

More information

Where the Ocean Meets Land. Coastal Engineering

Where the Ocean Meets Land. Coastal Engineering Where the Ocean Meets Land Coastal Engineering Photo credit : Rio Tinto Alcan Our Expertise MARINAS AND HARBOURS Design and repair of breakwaters Sedimentation and dredging studies Navigation guidelines

More information

Conowingo Capacity Recovery and Innovative & Beneficial Use Pilot Project. AGENDA 6:30 6:45 Welcome and Opening Remarks. 6:45 7:15 Poster Session

Conowingo Capacity Recovery and Innovative & Beneficial Use Pilot Project. AGENDA 6:30 6:45 Welcome and Opening Remarks. 6:45 7:15 Poster Session Conowingo Capacity Recovery and Innovative & Beneficial Use Pilot Project AGENDA 6:30 6:45 Welcome and Opening Remarks 6:45 7:15 Poster Session 7:15 7:30 Questions Pilot Dredging Project Goals 1) Evaluate

More information

Alabama State Port Authority

Alabama State Port Authority Alabama State Port Authority CHOCTAW POINT TERMINALS MITIGATION PROJECT 2009 AAPA ENVIRONMENTAL AWARDS COMPETITION MITIGATION CATEGORY June 24, 2009 Contact Person: Robert C. Harris, Jr., P.E. Environmental,

More information

The Tidal Wetlands Act was passed.to preserve and prevent the despoliation and destruction

The Tidal Wetlands Act was passed.to preserve and prevent the despoliation and destruction The Tidal Wetlands Act was passed.to preserve and prevent the despoliation and destruction of wetlands while accommodating necessary economic development in a manner consistent with wetlands preservation.

More information

Norfolk District Regulatory Office

Norfolk District Regulatory Office Norfolk District Regulatory Office Stream Bank Stabilization/ Stream Restoration Regena Bronson Norfolk District, Fredericksburg Field Office November 2011 Rivers and Harbors Act of 1899, Section 10 Requires

More information

Village Creek Harbor & Estuary

Village Creek Harbor & Estuary Village Creek Harbor & Estuary A Study on the Feasibility of Restoring Degraded Saltmarsh with Dredged Material Public Presentation September 7 th and 9 th 2017 Village Creek Harbor & Estuary Salt Marsh

More information

Living Shorelines from A to D in the Florida Panhandle

Living Shorelines from A to D in the Florida Panhandle Florida Department of Environmental Protection Florida Coastal Office Living Shorelines from A to D in the Florida Panhandle Zachary Schang 1, Melody Ray-Culp 2, Beth Fugate 1 Living Shorelines Summit

More information

Town of Duck North Carolina

Town of Duck North Carolina Town of Duck North Carolina Town of Duck Shore Protection Project Photograph obtained by. (July 7, 2017). Beach Maintenance Plan August 2017 Updated September 2018 Prepared By:. 4038 Masonboro Loop Road

More information

Accommodating Mega-Ships at Existing Wharves

Accommodating Mega-Ships at Existing Wharves Accommodating Mega-Ships at Existing Wharves Presented by: Kevin P. Abt, P.E. The Virginia Port Authority and Bruce Lambert U.S. Army Corps of Engineers February 22, 2006 National Cargo Trends U.S. Cargo

More information

Perimeter protection such as seawalls and levees (or raised roadways serving as levees)

Perimeter protection such as seawalls and levees (or raised roadways serving as levees) INTRODUCTION This document discusses flood issues and some conceived strategies to alleviate such issues in the Back Bay. The Back Bay experiences frequent wind tides that push water against the surrounding

More information

Encinitas-Solana Beach Coastal Storm Damage Reduction Project. San Diego County, California. Appendix M. Mitigation Strategy

Encinitas-Solana Beach Coastal Storm Damage Reduction Project. San Diego County, California. Appendix M. Mitigation Strategy 0 Encinitas-Solana Beach Coastal Storm Damage Reduction Project San Diego County, California Appendix M Mitigation Strategy U.S. Army Corps of Engineers Los Angeles District 0 December 0 0 0 This page

More information

Sea Level Change Considerations on Federal Coastal Storm Damage Reduction Projects

Sea Level Change Considerations on Federal Coastal Storm Damage Reduction Projects Sea Level Change Considerations on Federal Coastal Storm Damage Reduction Projects Jason Engle, P.E. Matt Schrader, P.E. Presented by: Jason Engle Jacksonville District U.S. Army Corps of Engineers ENGINEERING

More information

RESTORATION OF THE NORTHERN TIP OF MON LOUIS ISLAND Mobile Bay National Estuary Program. Fowl River WMP Steering Committee May 19, 2015

RESTORATION OF THE NORTHERN TIP OF MON LOUIS ISLAND Mobile Bay National Estuary Program. Fowl River WMP Steering Committee May 19, 2015 RESTORATION OF THE NORTHERN TIP OF MON LOUIS ISLAND Mobile Bay National Estuary Program Fowl River WMP Steering Committee May 19, 2015 Project Site / Background Historical Maps (Note New Outlet ) 1889

More information

Maryland s Living Shorelines Program. Bhaskaran Subramanian February 27, 2015

Maryland s Living Shorelines Program. Bhaskaran Subramanian February 27, 2015 Maryland s Living Shorelines Program Bhaskaran Subramanian February 27, 2015 1 Erosion & traditional approaches Living shorelines- what is it? Maryland s Living Shorelines program LS Law Products Funding-

More information

Appendix D 404(b) Analysis

Appendix D 404(b) Analysis Appendix D 404(b) Analysis Appendix D - Evaluation of Section 404(b)(1) Guidelines I. Project Description A. Location: Delaware Bay and bayshore communities (Pickering Beach, Kitts Hummock, Bowers Beach,

More information

Notice No Closing Date: May 2, 2015

Notice No Closing Date: May 2, 2015 Public Notice U.S. Army Corps of Engineers Pittsburgh District In Reply Refer to Notice No. below US Army Corps of Engineers, Pittsburgh District 1000 Liberty Avenue Pittsburgh, PA 15222-4186 Application

More information

Estuary Habitat Restoration STRATEGY 2012

Estuary Habitat Restoration STRATEGY 2012 Estuary Habitat Restoration STRATEGY 2012 INTRODUCTION The Estuary Restoration Act of 2000 (ERA), as amended, (title I of Pub. L. 106 457) fosters a collaborative and comprehensive process among federal

More information

Atlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY

Atlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY Atlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY Draft Reformulation Public Information October 2016 US Army Corps of Engineers Presentation Outline Project Overview

More information

NEW JERSEY BACK BAYS COASTAL STORM RISK MANAGEMENT INTERIM FEASIBILITY STUDY AND ENVIRONMENTAL SCOPING DOCUMENT. Executive Summary 1 March 2019

NEW JERSEY BACK BAYS COASTAL STORM RISK MANAGEMENT INTERIM FEASIBILITY STUDY AND ENVIRONMENTAL SCOPING DOCUMENT. Executive Summary 1 March 2019 NEW JERSEY BACK BAYS COASTAL STORM RISK MANAGEMENT INTERIM FEASIBILITY STUDY AND ENVIRONMENTAL SCOPING DOCUMENT Executive Summary 1 March 2019 Document Overview This U.S. Army Corps of Engineers (USACE)

More information