1 ORDINANCE APPENDIX C RUNOFF COEFFICIENTS AND CURVE NUMBERS TABLE C-1. RUNOFF CURVE NUMBERS Source: Table 2-2a, Table 2-2b, and Table 2-2c from U. S. Department of Agriculture, Natural Resources Conservation Service, June 1986, Urban Hydrology for Small Watersheds, Technical Release No. 55 (TR-55), Second Edition. TABLE C-2. RATIONAL RUNOFF COEFFICIENTS Source: Table F.2 from Delaware County Planning Department, December 2011, Crum Creek Watershed Act 167 Stormwater Management Plan. TABLE C-3. MANNING S n VALUES Source: Table 3-1 from United States Army Corps of Engineers, January 2010, HEC-RAS River Analysis System, Hydraulic Reference Manual, Version 4.1.

2 TABLE C-1. RUNOFF CURVE NUMBERS (3 pages) Source: Table 2-2a, Table 2-2b, and Table 2-2c from U. S. Department of Agriculture, Natural Resources Conservation Service, June 1986, Urban Hydrology for Small Watersheds, Technical Release No. 55 (TR-55), Second Edition.

3 Chapter 2 Estimating Runoff Technical Release 55 Urban Hydrology for Small Watersheds Table 2-2a Runoff curve numbers for urban areas 1/ Curve numbers for Cover description hydrologic soil group Average percent Cover type and hydrologic condition impervious area 2/ A B C D Fully developed urban areas (vegetation established) Open space (lawns, parks, golf courses, cemeteries, etc.) 3/ : Poor condition (grass cover < 50%) Fair condition (grass cover 50% to 75%) Good condition (grass cover > 75%) Impervious areas: Paved parking lots, roofs, driveways, etc. (excluding right-of-way) Streets and roads: Paved; curbs and storm sewers (excluding right-of-way) Paved; open ditches (including right-of-way) Gravel (including right-of-way) Dirt (including right-of-way) Western desert urban areas: Natural desert landscaping (pervious areas only) 4/ Artificial desert landscaping (impervious weed barrier, desert shrub with 1- to 2-inch sand or gravel mulch and basin borders) Urban districts: Commercial and business Industrial Residential districts by average lot size: 1/8 acre or less (town houses) /4 acre /3 acre /2 acre acre acres Developing urban areas Newly graded areas (pervious areas only, no vegetation) 5/ Idle lands (CN s are determined using cover types similar to those in table 2-2c). 1 Average runoff condition, and I a = 0.2S. 2 The average percent impervious area shown was used to develop the composite CN s. Other assumptions are as follows: impervious areas are directly connected to the drainage system, impervious areas have a CN of 98, and pervious areas are considered equivalent to open space in good hydrologic condition. CN s for other combinations of conditions may be computed using figure 2-3 or CN s shown are equivalent to those of pasture. Composite CN s may be computed for other combinations of open space cover type. 4 Composite CN s for natural desert landscaping should be computed using figures 2-3 or 2-4 based on the impervious area percentage (CN = 98) and the pervious area CN. The pervious area CN s are assumed equivalent to desert shrub in poor hydrologic condition. 5 Composite CN s to use for the design of temporary measures during grading and construction should be computed using figure 2-3 or 2-4 based on the degree of development (impervious area percentage) and the CN s for the newly graded pervious areas. (210-VI-TR-55, Second Ed., June 1986) 2 5

4 Chapter 2 Estimating Runoff Technical Release 55 Urban Hydrology for Small Watersheds Table 2-2b Runoff curve numbers for cultivated agricultural lands 1/ Curve numbers for Cover description hydrologic soil group Hydrologic Cover type Treatment 2/ condition 3/ A B C D Fallow Bare soil Crop residue cover (CR) Poor Good Row crops Straight row (SR) Poor Good SR + CR Poor Good Contoured (C) Poor Good C + CR Poor Good Contoured & terraced (C&T) Poor Good C&T+ CR Poor Good Small grain SR Poor Good SR + CR Poor Good C Poor Good C + CR Poor Good C&T Poor Good C&T+ CR Poor Good Close-seeded SR Poor or broadcast Good legumes or C Poor rotation Good meadow C&T Poor Good Average runoff condition, and I a =0.2S 2 Crop residue cover applies only if residue is on at least 5% of the surface throughout the year. 3 Hydraulic condition is based on combination factors that affect infiltration and runoff, including (a) density and canopy of vegetative areas, (b) amount of year-round cover, (c) amount of grass or close-seeded legumes, (d) percent of residue cover on the land surface (good 20%), and (e) degree of surface roughness. Poor: Factors impair infiltration and tend to increase runoff. Good: Factors encourage average and better than average infiltration and tend to decrease runoff. 2 6 (210-VI-TR-55, Second Ed., June 1986)

5 Chapter 2 Estimating Runoff Technical Release 55 Urban Hydrology for Small Watersheds Table 2-2c Runoff curve numbers for other agricultural lands 1/ Curve numbers for Cover description hydrologic soil group Hydrologic Cover type condition A B C D Pasture, grassland, or range continuous Poor forage for grazing. 2/ Fair Good Meadow continuous grass, protected from grazing and generally mowed for hay. Brush brush-weed-grass mixture with brush Poor the major element. 3/ Fair Good 30 4/ Woods grass combination (orchard Poor or tree farm). 5/ Fair Good Woods. 6/ Poor Fair Good 30 4/ Farmsteads buildings, lanes, driveways, and surrounding lots. 1 Average runoff condition, and I a = 0.2S. 2 Poor: <50%) ground cover or heavily grazed with no mulch. Fair: 50 to 75% ground cover and not heavily grazed. Good: > 75% ground cover and lightly or only occasionally grazed. 3 Poor: <50% ground cover. Fair: 50 to 75% ground cover. Good: >75% ground cover. 4 Actual curve number is less than 30; use CN = 30 for runoff computations. 5 CN s shown were computed for areas with 50% woods and 50% grass (pasture) cover. Other combinations of conditions may be computed from the CN s for woods and pasture. 6 Poor: Forest litter, small trees, and brush are destroyed by heavy grazing or regular burning. Fair: Woods are grazed but not burned, and some forest litter covers the soil. Good: Woods are protected from grazing, and litter and brush adequately cover the soil. (210-VI-TR-55, Second Ed., June 1986) 2 7

6 TABLE C-2. RATIONAL RUNOFF COEFFICIENTS (1 page) Source: Table F.2 from Delaware County Planning Department, December 2011, Crum Creek Watershed Act 167 Stormwater Management Plan.

7 TABLE F-2 RATIONAL RUNOFF COEFFICIENTS HYDROLOGIC SOIL GROUP LAND USE DESCRIPTION A B C D Cultivated land : without conservation treatment : with conservation treatment Pasture or range land: poor condition : good condition ---* Meadow: good condition ---* ---* Woods: thin stand, poor cover, no mulch ---* : good cover ---* ---* Open spaces, lawns, parks, golf courses, cemeteries Good condition: grass cover on 75% or more of ---* the area Fair condition: grass cover on 50% to 75% of ---* the area Commercial and business areas (85% impervious) Industrial districts (72% impervious) Residential: Average lot size Average % impervious 1/8 acre or less /4 acre /3 acre * /2 acre * acre * Paved parking lots, roofs, driveways, etc Streets and roads: Paved with curbs and storm sewers Gravel Dirt Notes: Values are based on SCS definitions and are average values. Values indicated by ---* should be determined by the design engineer based on site characteristics. Source : New Jersey Department of Environmental Protection, Technical Manual for Stream Encroachment, August 1984 F-3

8 TABLE C-3. MANNING S n VALUES (3 pages) Source: Table 3-1 from United States Army Corps of Engineers, January 2010, HEC-RAS River Analysis System, Hydraulic Reference Manual, Version 4.1.

9

10

11

0.0. Pervious CN = 40. (Unconnected impervious) (Total impervious) Total impervious area (percent) Composite CN

0.0. Pervious CN = 40. (Unconnected impervious) (Total impervious) Total impervious area (percent) Composite CN Figure 2-3 Composite CN with connected impervious area. 100 Composite CN 90 80 70 60 Pervious CN = 90 80 70 60 50 40 50 40 0 10 20 30 40 50 60 70 80 90 100 Connected impervious area (percent) Figure 2-4

More information

Ponds Planning, Design, Construction

Ponds Planning, Design, Construction United States Department of Agriculture Natural Resources Conservation Service Ponds Planning, Design, Construction Agriculture Handbook Number 590 Estimating storm runoff The amount of precipitation,

More information

ORDINANCE APPENDIX F STORMWATER MANAGEMENT DESIGN CRITERIA

ORDINANCE APPENDIX F STORMWATER MANAGEMENT DESIGN CRITERIA ORDINANCE APPENDIX F STORMWATER MANAGEMENT DESIGN CRITERIA TABLE F-1 DESIGN STORM RAINFALL AMOUNT FIGURE F-1 ALTERNATING BLOCK METHOD FOR RAINFALL DISTRIBUTION FIGURE F-2 PENNDOT DELINEATED REGIONS FIGURE

More information

Stormwater Drainage Criteria Manual. City Of Clearwater Engineering Department Effective July 1, 2015

Stormwater Drainage Criteria Manual. City Of Clearwater Engineering Department Effective July 1, 2015 Stormwater Drainage Criteria Manual City Of Clearwater Engineering Department Effective July 1, 2015 Engineering Department STORMWATER DRAINAGE CRITERIA MANUAL Table of Contents STORMWATER DRAINAGE CRITERIA

More information

Chapter Introduction. 5.2 Computational Standard Methods HYDROLOGY

Chapter Introduction. 5.2 Computational Standard Methods HYDROLOGY Chapter 5. HYDROLOGY 5.1 Introduction The definition of hydrology is the scientific study of water and its properties, distribution, and effects on the earth s surface, in the soil and the atmosphere.

More information

Basic Hydrology Runoff Curve Numbers

Basic Hydrology Runoff Curve Numbers Basic Hydrology Runoff Curve Numbers By: Paul Schiariti, P.E., CPESC Mercer County Soil Conservation District The SCS Runoff Curve Number The RCN (Runoff Curve Number) method was originally established

More information

LAKE COUNTY HYDROLOGY DESIGN STANDARDS

LAKE COUNTY HYDROLOGY DESIGN STANDARDS LAKE COUNTY HYDROLOGY DESIGN STANDARDS Lake County Department of Public Works Water Resources Division 255 N. Forbes Street Lakeport, CA 95453 (707)263-2341 Adopted June 22, 1999 These Standards provide

More information

Appendix C Little Calumet River Watershed Curve Number Calculation

Appendix C Little Calumet River Watershed Curve Number Calculation Little Calumet River Watershed Curve Number Calculation Introduction SCS hydrology uses the empirical curve number (CN) parameter as a part of calculating runoff volumes based on landscape characteristics

More information

Runoff Calculations. Time of Concentration (T c or t c ) from one location to another within a watershed. Travel

Runoff Calculations. Time of Concentration (T c or t c ) from one location to another within a watershed. Travel Runoff Calculations Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Time of Concentration and Travel Time (based on Chapter 3 of TR-55) Time of Concentration (T c ): time required

More information

What is runoff? Runoff. Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream

What is runoff? Runoff. Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream What is runoff? Runoff Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream 1 COMPONENTS OF Runoff or STREAM FLOW 2 Cont. The types of runoff

More information

Names: ESS 315. Lab #6, Floods and Runoff Part I Flood frequency

Names: ESS 315. Lab #6, Floods and Runoff Part I Flood frequency Names: ESS 315 Lab #6, Floods and Runoff Part I Flood frequency A flood is any relatively high flow of water over land that is not normally under water. Floods occur at streams and rivers but can also

More information

A Comprehensive Review of Runoff Estimation by the Curve Number Method

A Comprehensive Review of Runoff Estimation by the Curve Number Method A Comprehensive Review of Runoff Estimation by the Curve Number Method Ankit Balvanshi 1, H.L. Tiwari 2 P.G. Student, Department of Civil Engineering, Maulana Azad National Institute of Technology, Bhopal,

More information

Appendix I OFFICE OF THE MORGAN COUNTY SURVEYOR STORMWATER DESIGN MANUAL 7/1/2008

Appendix I OFFICE OF THE MORGAN COUNTY SURVEYOR STORMWATER DESIGN MANUAL 7/1/2008 Appendix I OFFICE OF THE MORGAN COUNTY SURVEYOR This Page Left Intentionally Blank OFFICE OF THE MORGAN COUNTY SURVEYOR APPENDIX I PAGE 1 Appendix II OFFICE OF THE MORGAN COUNTY SURVEYOR This Page Left

More information

APPENDIX F RATIONAL METHOD

APPENDIX F RATIONAL METHOD 7-F-1 APPENDIX F RATIONAL METHOD 1.0 Introduction One of the most commonly used procedures for calculating peak flows from small drainages less than 200 acres is the Rational Method. This method is most

More information

Faculty of Applied Science and Engineering. Department of Civil Engineering. Hydrology and Hydraulics. Final Exam, April 21, 2017

Faculty of Applied Science and Engineering. Department of Civil Engineering. Hydrology and Hydraulics. Final Exam, April 21, 2017 F Name: Student #: University of Toronto Faculty of Applied Science and Engineering Department of Civil Engineering C1V250 - Hydrology and Hydraulics Final Exam, April 21, 2017 Duration: 2 and V2 hrs The

More information

Appendix D Tables and Figures

Appendix D Tables and Figures Appendix D Tables and Figures PC-HYDRO User Guide V5 Figure D-1. Hydrologic Soil-Cover Complexes and their Associated SCS Curve Numbers D-1 Figure D-2. Aerial Reduction for Watersheds Larger Than Ten Square

More information

6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff

6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff October 2003, Revised February 2005 Chapter 6.0, Runoff Page 1 6.1 Introduction 6.0 Runoff The timing, peak rates of discharge, and volume of stormwater runoff are the primary considerations in the design

More information

WinTR-55 Small Watershed Hydrology

WinTR-55 Small Watershed Hydrology WinTR-55 Small Watershed Hydrology Modeling Single Sub-area Watersheds (Part 2) We ve looked at the minimum data entry requirements and how we can enter curve numbers and times of concentration directly

More information

HYDROLOGIC CONSIDERATIONS. 22 nd Annual Nonpoint Source Pollution Conference Saratoga Springs, NY

HYDROLOGIC CONSIDERATIONS. 22 nd Annual Nonpoint Source Pollution Conference Saratoga Springs, NY LOW IMPACT DEVELOPMENT HYDROLOGIC CONSIDERATIONS 22 nd Annual Nonpoint Source Pollution Conference Saratoga Springs, NY May 18, 2011 PRESENTATION AGENDA Introduction Definitions Discuss Impacts to Hydrologic

More information

PRELIMINARY DRAINAGE STUDY

PRELIMINARY DRAINAGE STUDY PRELIMINARY DRAINAGE STUDY For 34 th & J Residences 3402 J St. San Diego, CA 92102 A.P.N 545-250-08 Prepared By: Kenneth J. Discenza, P.E. Site Design Associates, Inc. 1016 Broadway, Suite A El Cajon,

More information

APPENDIX A: STORMWATER HYDROLOGY

APPENDIX A: STORMWATER HYDROLOGY APPENDIX A: STORMWATER HYDROLOGY In low impact development (LID), the objective of stormwater control measures (SCMs) is to mimic or replicate the hydrologic function of a natural system. This approach

More information

Decatur, Georgia Stormwater Management Policy Guidelines. DRAFT November 5, 2014

Decatur, Georgia Stormwater Management Policy Guidelines. DRAFT November 5, 2014 Decatur, Georgia Stormwater Management Policy Guidelines Stormwater Management Policy Guidelines Decatur, Georgia STORMWATER MANAGEMENT POLICY GUIDELINES 1.0 Introduction... 3 2.0 Determining Predevelopment

More information

Appendix A Stormwater Site Plan Report Short Form

Appendix A Stormwater Site Plan Report Short Form Appendix A Stormwater Site Plan Report Short Form The Stormwater Site Plan Report Short Form may be used for projects that trigger only Minimum Requirements #1-#5. These projects typically fall within

More information

CHELTENHAM TOWNSHIP Chapter 290: WATERSHED STORMWATER MANAGEMENT Article IV: Stormwater Management

CHELTENHAM TOWNSHIP Chapter 290: WATERSHED STORMWATER MANAGEMENT Article IV: Stormwater Management CHELTENHAM TOWNSHIP Chapter 290: WATERSHED STORMWATER MANAGEMENT Article IV: Stormwater Management Online ECode Available on Cheltenham Township Website at: http://ecode360.com/14477578 For all regulated

More information

The Big Picture SOILS, WETLANDS AND DEVELOPMENT SOILS OVERVIEW BRUCE BARBER. PWS, Soil Scientist Certified Ecologist CORNERSTONE ASSOCIATES

The Big Picture SOILS, WETLANDS AND DEVELOPMENT SOILS OVERVIEW BRUCE BARBER. PWS, Soil Scientist Certified Ecologist CORNERSTONE ASSOCIATES SOILS, WETLANDS AND DEVELOPMENT BRUCE BARBER PWS, Soil Scientist Certified Ecologist CORNERSTONE ASSOCIATES 1770 CENTRAL STREET YORKTOWN HEIGHTS NY 10598 PHONE: (914) 962-7733 FAX: (914) 962-0330 EMAIL:

More information

STORMWATER HYDROLOGY

STORMWATER HYDROLOGY ..CHAPTER.. STORMWATER HYDROLOGY 3.1 Introduction to Hydrologic Methods Hydrology is the science dealing with the characteristics, distribution, and movement of water on and below the earth's surface and

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose STANDARD FOR GRASSED WATERWAYS Definition A natural or constructed watercourse shaped or graded in earth materials and stabilized with suitable vegetation for the safe conveyance of runoff water. Purpose

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall 6.0 Introduction This chapter summarizes methodology for determining rainfall and runoff information for the design of stormwater management facilities in the City. The methodology is based on the procedures

More information

APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY)

APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY) APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY) Hydromodification design criteria for the North Orange County permit area are based on the 2- yr, 24-hr

More information

Effect of Land Surface on Runoff Generation

Effect of Land Surface on Runoff Generation Effect of Land Surface on Runoff Generation Context: Hydrologic Cycle Runoff vs Infiltration Infiltration: Process by which water on the ground surface enters the soil Runoff: Water (from rain, snowmelt,

More information

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS March 18, 2003 This page left blank intentionally. March 18, 2003 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method

More information

Table of Contents CHAPTER. Chapter 2 Hydrologic Analysis. 2.1 Estimating Runoff

Table of Contents CHAPTER. Chapter 2 Hydrologic Analysis. 2.1 Estimating Runoff CHAPTER Table of Contents 2 Chapter 2 Hydrologic Analysis 2.1 Estimating Runoff 2.1.1 Introduction to Hydrologic Methods...2.1-1 2.1.2 Symbols and Definitions...2.1-4 2.1.3 Rainfall Estimation...2.1-5

More information

Continuing Education Course #209 Green Irrigation Fundamentals Balancing Aquifer Recharge and Withdrawal

Continuing Education Course #209 Green Irrigation Fundamentals Balancing Aquifer Recharge and Withdrawal 1 of 7 Continuing Education Course #209 Green Irrigation Fundamentals Balancing Aquifer Recharge and Withdrawal 1. The balanced irrigation water demand is based mainly on (hint: water created by the improvements):

More information

Modeling Infiltration BMPs

Modeling Infiltration BMPs Modeling Infiltration BMPs CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) 696-4150 www.thcahill.com Design Goals for Calculations 1. Mitigate Peak Rates 2-Year to 100-Year 2. No Volume

More information

Appendix 1 - Updated Isohyet Based Calculation of Design Peakflows UPDATED ISOHYET BASED CALCULATION OF DESIGN PEAKFLOWS

Appendix 1 - Updated Isohyet Based Calculation of Design Peakflows UPDATED ISOHYET BASED CALCULATION OF DESIGN PEAKFLOWS Appendix 1 - Updated Isohyet Based Calculation of Design Peakflows UPDATED ISOHYET BASED CALCULATION OF DESIGN PEAKFLOWS Final 1) 11 October 2011 Updated Isohyet Based Calculation of Design Peakflows UPDATED

More information

Erosion, Sediment and Storm Water Control Ordinance Peoria County, Illinois

Erosion, Sediment and Storm Water Control Ordinance Peoria County, Illinois Erosion, Sediment and Storm Water Control Ordinance Peoria County, Illinois EROSION, SEDIMENT, AND STORM WATER CONTROL ORDINANCE FOR PEORIA COUNTY Including Amendments through April 9, 1996 PEORIA COUNTY,

More information

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines Pennsylvania Stormwater Best Management Practices Manual Chapter 3 Stormwater Management Principles and Recommended Control Guidelines 363-0300-002 / December 30, 2006 Chapter 3 Stormwater Management Principles

More information

TECHNICAL NOTES U.S. DEPARTMENT OF AGRICULTURE NATURAL RESOURCES CONSERVATION SERVICE. TEXAS Revised December, 2012

TECHNICAL NOTES U.S. DEPARTMENT OF AGRICULTURE NATURAL RESOURCES CONSERVATION SERVICE. TEXAS Revised December, 2012 TECHNICAL NOTES U.S. DEPARTMENT OF AGRICULTURE NATURAL RESOURCES CONSERVATION SERVICE TEXAS Revised December, 2012 AGRONOMY TECHNICAL NOTE NUMBER 15 PHOSPHORUS ASSESSMENT TOOL For Texas BACKGROUND AND

More information

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS ESTIMATING RUNOFF FROM SMALL WATERSHEDS June 2011 THIS PAGE LEFT BLANK INTENTIONALLY. June 2011 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method Values June 2011

More information

Volume 1, Chapter 5 - Runoff:

Volume 1, Chapter 5 - Runoff: Volume 1, Chapter 5 - Runoff: Users Guidance: If a UDFCD Section number in this chapter is skipped: It was adopted as is; please refer to that Section in the corresponding UDFCD Manual, Volume, Chapter

More information

Chapter 6. The Empirical version of the Rational Method

Chapter 6. The Empirical version of the Rational Method Chapter 6 The Empirical version of the Rational Method The Empirical version is named because the parameters it uses (apart from rainfall data) are arbitrary and are generally based on experience or observation

More information

TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1

TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1 TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SECTION TITLE PAGE 105.1. SPECIFICATIONS AND SCOPE 105.1 105.2. METHODS OF ANALYSIS 105.1 105.2.1. Rational Method

More information

FORT COLLINS STORMWATER CRITERIA MANUAL Hydrology Standards (Ch. 5) 1.0 Overview

FORT COLLINS STORMWATER CRITERIA MANUAL Hydrology Standards (Ch. 5) 1.0 Overview Chapter 5: Hydrology Standards Contents 1.0 Overview... 1 1.1 Storm Runoff Determination... 1 1.2 Design Storm Frequencies... 1 1.3 Water Quality Storm Provisions... 2 1.4 Design Storm Return Periods...

More information

FAST WATER / SLOW WATER AN EVALUATION OF ESTIMATING TIME FOR STORMWATER RUNOFF

FAST WATER / SLOW WATER AN EVALUATION OF ESTIMATING TIME FOR STORMWATER RUNOFF FAST WATER / SLOW WATER AN EVALUATION OF ESTIMATING TIME FOR STORMWATER RUNOFF Factors Affecting Stormwater Runoff: Rainfall intensity % Impervious surfaces Watershed size Slope Soil type, soil compaction

More information

Section 600 Runoff Table of Contents

Section 600 Runoff Table of Contents Section 600 Runoff Table of Contents 601 INTRODUCTION...600-1 602 RATIONAL METHOD...600-1 602.1 Rational Method Formula...600-2 602.2 Time of Concentration...600-2 602.3 Intensity...600-4 602.4 Runoff

More information

iswm TM Technical Manual Hydrology:

iswm TM Technical Manual Hydrology: : 1.0 2.0 Downstream Assessment 3.0 Streambank Protection 4.0 Water Balance 5.0 Rainfall Tables 6.0 Hydrologic Soils Data Table of Contents 1.0... HO-1 1.1 Estimating Runoff... HO-1 1.1.1 Introduction

More information

STORMWATER MANAGEMENT: Emerging Planning Approaches and Control Technologies

STORMWATER MANAGEMENT: Emerging Planning Approaches and Control Technologies STORMWATER MANAGEMENT: Emerging Planning Approaches and Control Technologies Chapter 5 " HYDROLOGIC SYSTEMS " CHAPTER 5 5.1 INTRODUCTION 5.1.1 Training Objectives The objectives of this module are:! to

More information

CHAPTER 3 STORMWATER HYDROLOGY. Table of Contents SECTION 3.1 METHODS FOR ESTIMATING STORMWATER RUNOFF

CHAPTER 3 STORMWATER HYDROLOGY. Table of Contents SECTION 3.1 METHODS FOR ESTIMATING STORMWATER RUNOFF CHAPTER 3 STORMWATER HYDROLOGY Table of Contents SECTION 3.1 METHODS FOR ESTIMATING STORMWATER RUNOFF 3.1.1 Introduction to Hydrologic Methods...3.1-1 3.1.2 Symbols and Definitions...3.1-3 3.1.3 Rainfall

More information

Center for Urban Rural Interface Studies. Pearl River County, Mississippi Land Cover Analysis

Center for Urban Rural Interface Studies. Pearl River County, Mississippi Land Cover Analysis Center for Urban Rural Interface Studies Pearl River County, Mississippi Land Cover Analysis Introduction The Center for Urban Rural Interface Studies (CURIS) created land cover maps for its focus area

More information

Activity Calculating Property Drainage

Activity Calculating Property Drainage Page 1 of 5 Activity 2.3.11 Calculating Property Drainage Introduction When a property is developed, it is important to understand that changes to watershed characteristics (i.e., land use, slope, soil

More information

Simple Method for Estimating Phosphorus Export

Simple Method for Estimating Phosphorus Export Appendix L Simple Method for Estimating Phosphorus Export 1. The Simple Method The Simple Method is a technique used for estimating storm pollutant export delivered from urban development sites. The method

More information

Estimating Stormwater Runoff from the 3D-model of an Urban Area in Istanbul

Estimating Stormwater Runoff from the 3D-model of an Urban Area in Istanbul 198 Estimating Stormwater Runoff from the 3D-model of an Urban Area in Istanbul Muhammed Ali Örnek 1, Melike Ersoy 2, Yasin Çağatay Seçkin 3 1 Istanbul Technical University, Istanbul/Turkey maornek@itu.edu.tr

More information

Stormwater Manual. City of Mason, Ohio. May 2010

Stormwater Manual. City of Mason, Ohio. May 2010 City of Mason, Ohio May 2010 Contents City of Mason, Ohio Section 1 - Introduction... 1 1.1 Stormwater Policy Goals...1 1.2 Construction Plan Submittal Requirements...2 1.3 Symbols & Abbreviations...3

More information

Streamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators

Streamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators Page 1 of 5 STREAMLINES A Newsletter for North Carolina Water Supply Watershed Administrators Volume 2, Number 2 May 1997 Non-Point Source (NPS) Pollution This issue of Streamlines provides basic information

More information

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater

More information

Chapter 3 Dispersion BMPs

Chapter 3 Dispersion BMPs Chapter 3 Dispersion BMPs 3.1 BMP L611 Concentrated Flow Dispersion 3.1.1 Purpose and Definition Dispersion of concentrated flows from driveways or other pavement through a vegetated pervious area attenuates

More information

Stormwater Analysis Report

Stormwater Analysis Report Stormwater Analysis Report Solar Panel Array Temple Street (Rt. 14) West Boylston, MA February 24, 216 SITE Prepared for: West Boylston Municipal Lighting Plant 4 Crescent Street West Boylston, MA 1583

More information

DESIGN HYDROLOGY MANUAL

DESIGN HYDROLOGY MANUAL DESIGN HYDROLOGY MANUAL 2010 ERRATA PAGES VENTURA COUNTY WATERSHED PROTECTION DISTRICT VENTURA COUNTY, CALIFORNIA JUNE, 2011 DISTRICT CONTACTS: Design Hydrologist: VCRat Programmer Reviewer: District Director:

More information

Hydrologic Study Report for Single Lot Detention Basin Analysis

Hydrologic Study Report for Single Lot Detention Basin Analysis Hydrologic Study Report for Single Lot Detention Basin Analysis Prepared for: City of Vista, California August 18, 2006 Tory R. Walker, R.C.E. 45005 President W.O. 116-01 01/23/2007 Table of Contents Page

More information

DRAFT Great Bay Nitrogen Non-Point Source Study

DRAFT Great Bay Nitrogen Non-Point Source Study DRAFT Great Bay Nitrogen Non-Point Source Study by Philip Trowbridge, P.E. & Matthew A. Wood Ted Diers, Administrator Watershed Management Bureau Open up the black box Source: PREP (2013) Non-Point Sources

More information

MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1. Precipitation

MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1. Precipitation Watershed MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1 A watershed is an area of land thaaptures rainfall and other precipitation and funnels it to a lake or stream or wetland. The area within the watershed

More information

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.)

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.) Module 2: Selection of Controls and Site Planning for Construction Site Erosion Prevention Robert Pitt Department of Civil, Construction, and Environmental Engineering University of Alabama Tuscaloosa,

More information

Module 3 and Module 4 Watershed Analysis and RUSLE Calculation. Noboru Togawa. Presented to: Dr. Pitt Construction Site Erosion Control

Module 3 and Module 4 Watershed Analysis and RUSLE Calculation. Noboru Togawa. Presented to: Dr. Pitt Construction Site Erosion Control Module 3 and Module 4 Watershed Analysis and RUSLE Calculation by Presented to: Dr. Pitt Construction Site Erosion Control Department of Civil, Construction, and Environmental Engineering The University

More information

How is Water Quality Affected by Land Use?

How is Water Quality Affected by Land Use? Watershed Connections Lesson Les4 3 How is Water Quality Affected by Land Use? Overview What are the benefits of a healthy watershed? What are examples of land uses? What types of pollution can come from

More information

c h a p t e r 4 d e s i g n e x a m p l e s f o r s a n m a t e o c o u n t y Options for New Development

c h a p t e r 4 d e s i g n e x a m p l e s f o r s a n m a t e o c o u n t y Options for New Development LOW-DENSITY RESIDENTIAL STREETS: Vegetated Swales Options for New Development In San Mateo County, retrofitting vegetated swales within existing neighborhood streets may be difficult because there are

More information

EVALUATION OF VOLUME IN TWO BIOSWALE. Judy Horwatich US Geological Survey

EVALUATION OF VOLUME IN TWO BIOSWALE. Judy Horwatich US Geological Survey EVALUATION OF VOLUME IN TWO BIOSWALE Judy Horwatich US Geological Survey COOPERATORS Wisconsin Department of Transportation Wisconsin Department of Natural Resources Support Changes to State Technical

More information

Center for Urban Rural Interface Studies. St. John the Baptist Parish, Louisiana Land Cover Analysis

Center for Urban Rural Interface Studies. St. John the Baptist Parish, Louisiana Land Cover Analysis Center for Urban Rural Interface Studies St. John the Baptist Parish, Louisiana Land Cover Analysis Introduction The Center for Urban Rural Interface Studies (CURIS) created land cover maps for its focus

More information

PUNTA GORDA AIRPORT CONSTRUCT TAXIWAY A EXTENSION DRAINAGE REPORT

PUNTA GORDA AIRPORT CONSTRUCT TAXIWAY A EXTENSION DRAINAGE REPORT PUNTA GORDA AIRPORT CONSTRUCT TAIWAY A ETENSION DRAINAGE REPORT Prepared for the Charlotte County Airport Authority Prepared By: 7650 West Courtney Campbell Causeway Tampa, Florida 33607-1462 May 2015

More information

Subject: Civil Site Development Plans for Mark Black Wedding Venue

Subject: Civil Site Development Plans for Mark Black Wedding Venue 1405 Hillmont Street Austin, Texas 78704 Phone: 512-326-8880 e-mail: lauren@ Mr. Chad Gilpin City of Dripping Springs, City Engineer PO Box 384 Dripping Springs, Texas 78620 Via email: cgilpin@cityofdrippingsprings.com

More information

Role of Soils in Water Quality. Mike Marshall Extension Associate Texas A&M-Institute of Renewable Natural Resources

Role of Soils in Water Quality. Mike Marshall Extension Associate Texas A&M-Institute of Renewable Natural Resources Role of Soils in Water Quality Mike Marshall Extension Associate Texas A&M-Institute of Renewable Natural Resources Water Quality in Texas Water is a finite resource that can be impaired by pollution from

More information

Chapter 4 Population and Land Cover

Chapter 4 Population and Land Cover Chapter 4 Population and Land Cover Population in the French Broad Basin The population of the entire basin for the year 2000 was estimated at about 427,000, or about 151 people per square mile (Figure

More information

Project: Developer/Designer: Reviewer:

Project: Developer/Designer: Reviewer: City of Charlottesville, Virginia Engineering Plan Review Checklist (Site Plans, Site Plan Amendments, and Major Subdivisions) 610 East Market Street, Charlottesville, VA 22902 Telephone 434-970-3182;

More information

Low Impact Development in Western WA Municipal Stormwater Permits

Low Impact Development in Western WA Municipal Stormwater Permits Low Impact Development in Western WA Municipal Stormwater Permits USGS Tacoma Office September 19, 2012 E-mail: eobr461@ecy.wa.gov ttp://www.ecy.wa.gov/programs/wq/stormwater/municipal/index.html Municipal

More information

SECTION IV WATERSHED TECHNICAL ANALYSIS

SECTION IV WATERSHED TECHNICAL ANALYSIS A. Watershed Modeling SECTION IV WATERSHED TECHNICAL ANALYSIS An initial step in the preparation of this stormwater management plan was the selection of a stormwater simulation model to be utilized. It

More information

WinSLAMM v 10 Theory and Practice

WinSLAMM v 10 Theory and Practice WinSLAMM v 10 Theory and Practice Using WinSLAMM v10 to Meet Urban Stormwater Management Goals 1 We will cover... WinSLAMM Purpose, History and Unique Features Model Applications Small Storm Hydrology

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm

More information

Stormwater Management Impacts Resulting from the Volumetric Abstraction of Runoff from Frequent Storms per PADEP CG-1. Geoffrey A. Cerrelli 1, P.E.

Stormwater Management Impacts Resulting from the Volumetric Abstraction of Runoff from Frequent Storms per PADEP CG-1. Geoffrey A. Cerrelli 1, P.E. Stormwater Management Impacts Resulting from the Volumetric Abstraction of Runoff from Frequent Storms per PADEP CG-1 Geoffrey A. Cerrelli 1, P.E. 1 Hydraulic Engineer USDA/NRCS, One Credit Union Place,

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

MVP 17.3 WATER BAR END TREATMENT SIZING AND DETAILS 1/22/18

MVP 17.3 WATER BAR END TREATMENT SIZING AND DETAILS 1/22/18 MVP 17.3 WATER BAR END TREATMENT SIZING AND DETAILS 1/22/18 The purpose of this detail is to document the methodology developed to size the length of the water bar end treatments to ensure flow leaving

More information

Written by: Lindsay O Leary Date: 11 /08 /26 Reviewed by: Brandon Klenzendorf Date: 11 /08 /26 YY MM DD YY MM DD

Written by: Lindsay O Leary Date: 11 /08 /26 Reviewed by: Brandon Klenzendorf Date: 11 /08 /26 YY MM DD YY MM DD Page 2 of 21 Written by: Lindsay O Leary Date: 11 /08 /26 Reviewed by: Brandon Klenzendorf Date: 11 /08 /26 YY MM DD YY MM DD Client: Malcolm Pirnie, Inc. Project: ASARCO El Paso Site Project/Proposal

More information

STORM DRAINAGE DESIGN CRITERIA

STORM DRAINAGE DESIGN CRITERIA BWM Orig. 01/01/05 Revised 01/01/10 LUCAS COUNTY ENGINEERS OFFICE STORM DRAINAGE DESIGN CRITERIA Drainage The design of storm sewer systems will be based upon the Rational Method using the equation Q=CiA

More information

Cherokee County Future Conditions Floodplain Development

Cherokee County Future Conditions Floodplain Development TECHNICAL MEMORANDUM Cherokee County Future Conditions Floodplain Development Prepared for: Prepared by: Geoff Morton, P.E., County Engineer Cherokee County Richard Greuel, P.E.,, Inc. Richard Taylor,

More information

Stormwater Design Manual

Stormwater Design Manual Stormwater Design Manual Page i Stormwater Design Manual TABLE OF CONTENTS Section 1 INTRODUCTION & GENERAL GUIDELINES... 1 1.1 INTRODUCTION AND PURPOSE... 1 1.2 DISCLAIMER... 2 1.3 COMPLIANCE... 2 1.4

More information

Stormwater Design Manual Last Revised

Stormwater Design Manual Last Revised Stormwater Design Manual Page i Stormwater Design Manual Last Revised 5.25.16 TABLE OF CONTENTS Section 1 INTRODUCTION & GENERAL GUIDELINES... 1 1.1 INTRODUCTION AND PURPOSE... 1 1.2 DISCLAIMER... 2 1.3

More information

Unit E: Basic Principles of Soil Science. Lesson 7: Understanding Soil Erosion and Management Practices

Unit E: Basic Principles of Soil Science. Lesson 7: Understanding Soil Erosion and Management Practices Unit E: Basic Principles of Soil Science Lesson 7: Understanding Soil Erosion and Management Practices 1 Important Terms Accelerated erosion Conservation tillage Cover crops Diversion ditches Geologic

More information

Sustainable Water Resource Practices

Sustainable Water Resource Practices Sustainable Water Resource Practices This section is related to and shoudl be read in conjunction with the Land Use Element, and Conservation Element. Implementing sustainable water resource practices

More information

GLASI GLASI. Priority Subwatershed Project. Great Lakes Agricultural Stewardship Initiative

GLASI GLASI. Priority Subwatershed Project. Great Lakes Agricultural Stewardship Initiative GLASI GLASI Great Lakes Agricultural Stewardship Initiative Priority Subwatershed Project Wigle Creek Priority Subwatershed Project Essex Region Conservation Authority Up to $75,000 per eligible farm business

More information

Sediment and Erosion Control Plan (SECP) Template

Sediment and Erosion Control Plan (SECP) Template Sediment and Erosion Control Plan (SECP) Template Member Name: 1. General Information: Provide the required information where indicated. Parcel (APN) Field ID(s) General Information Comments: Name of Person

More information

Chapter 2: Conditions in the Spring Lake Watershed related to Stormwater Pollution

Chapter 2: Conditions in the Spring Lake Watershed related to Stormwater Pollution Chapter 2: Conditions in the Spring Lake Watershed related to Stormwater Pollution To identify the primary causes and consequences of stormwater discharges to Spring Lake and its adjoining waterbodies,

More information

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established

More information

RAINFALL RUNOFF MODELING FOR A SMALL URBANIZING SUB-WATERSHED IN THE UPPER DELAWARE RIVER BASIN

RAINFALL RUNOFF MODELING FOR A SMALL URBANIZING SUB-WATERSHED IN THE UPPER DELAWARE RIVER BASIN RAINFALL RUNOFF MODELING FOR A SMALL URBANIZING SUB-WATERSHED IN THE UPPER DELAWARE RIVER BASIN Practical Exam APRIL 2, 2014 ALYSSA LYND Shippensburg University TABLE OF CONTENTS List of tables and figures

More information

Chapter 5. Precipitation Losses. Introduction

Chapter 5. Precipitation Losses. Introduction Chapter 5 Precipitation Losses Introduction Effective Precipitation The Sacramento method derives the direct runoff from the effective precipitation. Effective precipitation is the total precipitation

More information

Community LID Workgroup Issue Paper #3

Community LID Workgroup Issue Paper #3 Topic: Clearing, Grading & Healthy Soils Community LID Workgroup Issue Paper #3 Objectives: Limit clearing, grading, and soil disturbance outside of the building footprint on newly developed residential

More information

Degradation of the resource Fertility loss Organic matter Tilth degradation. Water quality Sediment Nutrients

Degradation of the resource Fertility loss Organic matter Tilth degradation. Water quality Sediment Nutrients Near Blue River ca. 1980 Degradation of the resource Fertility loss Organic matter Tilth degradation Water quality Sediment Nutrients Program cost Cheaper to prevent Still expensive Long-term productivity

More information

Waackaack Creek Preliminary Hydrologic Model Report

Waackaack Creek Preliminary Hydrologic Model Report Waackaack Creek Preliminary Hydrologic Model Report Developed by the Rutgers Cooperative Extension Water Resources Program Prepared for Holmdel Township, Monmouth County, New Jersey March 8, 2019 1 Table

More information

Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates VNH File No.

Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates VNH File No. Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates 2005 VNH File No. 35317-210-21 Table of Contents Introduction... 3 Goals... 3 Storm water Discussion...

More information

Land Development Characteristics in the Southeastern United States

Land Development Characteristics in the Southeastern United States Background February 21: BS in Geography from Romania Minor in Meteorology-Hydrology May 27: MSE (Environmental) at UA December 28: Ph.D. in Civil Engineering at UA Concentration: Water Resources / Environmental

More information

Site Design Checklist and LID Calculations Worksheet. Draft Revision December 2004