Module 3. Lecture 6: Synthetic unit hydrograph
|
|
- Bartholomew Thornton
- 5 years ago
- Views:
Transcription
1 Lecture 6: Synthetic unit hydrograph
2 Synthetic Unit Hydrograph In India, only a small number of streams are gauged (i.e., stream flows due to single and multiple storms, are measured) There are many drainage basins (catchments) for which no stream flow records are available and unit hydrographs may be required for such basins In such cases, hydrographs may be synthesized directly from other catchments, which are hydrologically and meteorologically homogeneous, or indirectly from other catchments through the application of empirical relationship Methods for synthesizing hydrographs for ungauged areas have been developed from time to time by Bernard, Clark, McCarthy and Snyder. The best known approach is due to Snyder (1938)
3 Synthetic unit hydrograph Snyder s method Snyder (1938) was the to develop a synthetic UH based on a study of watersheds in the Appalachian Highlands. In basins ranging from 10 10,000 mi. 2 Snyder relations are t p = C t (LL C ) 0.3 where t p = basin lag (hr) L= length of the main stream from the outlet to the divide (mi) L c = length along the main stream to a point nearest the watershed centroid (mi) C t = Coefficient usually ranging from 1.8 to 2.2
4 Synthetic unit hydrograph Snyder s method Q p = 640 C p A/t p where Qp = peak discharge of the UH (cfs) A = Drainage area (mi2) C p = storage coefficient ranging from 0.4 to 0.8, where larger values of cp are associated with smaller values of Ct T b = 3+t p /8 where Tb is the time base of hydrograph Note: For small watershed the above eq. should be replaced by multiplying t p by the value varies from 3-5 The above 3 equations define points for a UH produced by an excess rainfall of duration D= t p /5.5 Snyder s hydrograph parameter
5 Example Problem Use Snyder s method to develop a UH for the area of 100mi2 described below. Sketch the appropriate shape. What duration rainfall does this correspond to? C t = 1.8, C p = 0.6, L= 18mi, L c = 10mi Calculate t p t p = C t (LL C ) 0.3 = 1.8(18 10) 0.3 hr, = 8.6 hr Calculate Qp Q p = 640(c p )(A)/t p = 640(0.6)(100)/8.6 = 4465 cfs Since this is a small watershed, Tb 4tp = 4(8.6) = 34.4 hr Duration of rainfall D= t p /5.5 hr = 8.6/5.5 hr = 1.6 hr
6 Example Problem Q p W 75 = 440(Q P /A) W 50 = 770(Q P /A) (widths are distributed 1/3 before Q p and 2/3 after) Q (cfs) W 75 W 50 Area drawn to represent 1 in. of runoff over the watershed Time (hr)
7 SCS (Soil Conservation Service) Unit Hydrograph Unit = 1 inch of runoff (not rainfall) in 1 hour t p Can be scaled to other depths and times Based on unit hydrographs from many watersheds The earliest method assumed a hydrograph as a simple triangle, with rainfall duration D, time of rise T (hr), time of fall B. and peak flow Q p (cfs). T Q p B SCS triangular UH
8 SCS Unit Hydrograph The volume of direct runoff is QpT Vol = 2 where B is given by + QpB 2 or Q p vol = 2 T + B B =1. 67T Therefore runoff eq. becomes, for 1 in. of rainfall excess, Q Q p p = = 0.75vol T 484A T where A= area of basin (sq mi) T = time of rise (hr) = Q p = 0.75(640) A(1.008) T
9 SCS Unit Hydrograph Time of rise T is given by D T = + 2 t p where D= rainfall duration (hr) t p = lag time from centroid of rainfall to Q P Lag time is given by t p = 0.8 L CN y 0.7 where L= length to divide (ft) Y= average watershed slope (in present) CN= curve number for various soil/land use
10 SCS Unit Hydrograph unoff curve number for different land use (source: Woo-Sung et al.,1998)
11 Example Problem Use the SCS method to develop a UH for the area of 10 mi 2 described below. Use rainfall duration of D = 2 hr C t = 1.8, C p = 0.6, L= 5mi, L c = 2mi The watershed consist CN = 78 and the average slope in the watershed is 100 ft/mi. Sketch the resulting SCS triangular hydrograph. Solution Find t p by the eq. t p 0.8 L CN y Convert L= 5mi, or (5*5280 ft/mi) = ft. = Slope is 100 ft/mi, so y = (100ft/mi) (1mi/5280 ft)(100%) = 1.9% Substituting these values in eq. of t p, we get t p = 3.36 hr 0.7
12 Example Problem Find T using eq. D T = + 2 t p Given rainfall duration is 2 hr, T = 4.36 hr, the rise of the hydrograph Then find Q p using the eq, given A= 10 mi 2 Q p = 484A T. Hence Q p = cfs To complete the graph, it is also necessary to know the time of fall B. The volume is known to be 1 in. of direct runoff over the watershed. So, Vol. = (10mi 2 ) (5280ft/mi) 2 (ac/43560ft 2 ) (1 in.) = 6400 ac-in Hence from eq. Vol = Q T p 2 B = 7.17 hr + Q p 2 B
13 Example Problem Q (cfs) Q p = 1110 (cfs) T =4.36 (hr) Time (hr) B=7.17 (hr)
14 Exercise problems 1. The stream flows due to three successive storms of 2.9, 4.9 and 3.9 cm of 6 hours duration each on a basin are given below. The area of the basin is km 2. Assuming a constant base flow of 20 cumec, derive a 6-hour unit hydrograph for the basin. An average storm loss of 0.15 cm/hr can be assumed (Hint :- Use UH convolution method) Time (hr) Flow (cumec)
15 Exercise problems 2. The ordinates of a 4-hour unit hydrograph for a particular basin are given below. Derive the ordinates of (i) the S-curve hydrograph, and (ii) the 2-hour unit hydrograph, and plot them, area of the basin is 630 km 2 Time (hr) Discharge (cumec) Time (hr) Discharge (cumec)
16 Exercise problems 3. The following are the ordinates of the 9-hour unit hydrograph for the entire catchment of the river Damodar up to Tenughat dam site: and the catchment characteristics are, A = 4480 km 2, L = 318 km, L ca = 198 km. Derive a 3-hour unit hydrograph for the catchment area of river Damodar up to the head of Tenughat reservoir, given the catchment characteristics as, A = 3780km 2, L = 284 km, L ca = 184km. Use Snyder s approach with necessary modifications for the shape of the hydrograph. Time (hr) Flow (cumec)
17 Highlights in the Module This module presents the concept of ainfall-unoff analysis, or the conversion of precipitation to runoff or streamflow, which is a central problem of engineering hydrology. Gross rainfall must be adjusted for losses to infiltration, evaporation and depression storage to obtain rainfall excess, which equals Direct unoff (DO). The concept of the Unit hydrograph allows for the conversion of rainfall excess into a basin hydrograph, through lagging procedure called hydrograph convolution. The concept of synthetic hydrograph allows the construction of hydrograph, where no streamflow data are available for the particular catchment.
Runoff Hydrographs. The Unit Hydrograph Approach
Runoff Hydrographs The Unit Hydrograph Approach Announcements HW#6 assigned Storm Water Hydrographs Graphically represent runoff rates vs. time Peak runoff rates Volume of runoff Measured hydrographs are
More informationModule 3. Lecture 4: Introduction to unit hydrograph
Lecture 4: Introduction to unit hydrograph (UH) The unit hydrograph is the unit pulse response function of a linear hydrologic system. First proposed by Sherman (1932), the unit hydrograph (originally
More informationEngineering Hydrology. Class 16: Direct Runoff (DRO) and Unit Hydrographs
Engineering Hydrology Class 16: and s Topics and Goals: 1. Calculate volume of DRO from a hydrograph; 2. Complete all steps to develop a. Class 14: s? HG? Develop Ocean Class 14: s? HG? Develop Timing
More information1. Stream Network. The most common approach to quantitatively describing stream networks was postulated by Strahler (1952).
1. Stream Network The most common approach to quantitatively describing stream networks was postulated by Strahler (1952). First Order Streams streams with no tributaries. Second Order Streams begin at
More informationTo estimate the magnitude of a flood peak the following alternative methods available: 1. Rational method 2. Empirical method
Methods for estimating flood To estimate the magnitude of a flood peak the following alternative methods available: 1. Rational method 2. Empirical method 3. Unit-hydrograph technique 4. Flood-frequency
More information5/25/2017. Overview. Flood Risk Study Components HYDROLOGIC MODEL (HEC-HMS) CALIBRATION FOR FLOOD RISK STUDIES. Hydraulics. Outcome or Impacts
HYDROLOGIC MODEL (HEC-HMS) CALIBRATION FOR FLOOD RISK STUDIES C. Landon Erickson, P.E.,CFM Water Resources Engineer USACE, Fort Worth District April 27 th, 2017 US Army Corps of Engineers Overview Flood
More informationRainfall - runoff: Unit Hydrograph. Manuel Gómez Valentín E.T.S. Ing. Caminos, Canales y Puertos de Barcelona
Rainfall - runoff: Unit Hydrograph Manuel Gómez Valentín E.T.S. ng. Caminos, Canales y Puertos de Barcelona Options in many commercial codes,, HMS and others HMS Menu Transform method, User specified,
More informationChapter 1 Introduction
Engineering Hydrology Chapter 1 Introduction 2016-2017 Hydrologic Cycle Hydrologic Cycle Processes Processes Precipitation Atmospheric water Evaporation Infiltration Surface Runoff Land Surface Soil water
More informationIntroduction to Hydrology, Part 2. Notes, Handouts
Introduction to Hydrology, Part 2 Notes, Handouts Precipitation Much of hydrology deals with precipitation How much? How frequently/infrequently? What form? How quickly? Seasonal variation? Drought frequency?
More informationPeak discharge computation
Ia/P 4 Peak Dischage Method Graphical Peak Discharge Method This chapter presents the Graphical Peak Discharge method for computing peak discharge from rural and urban areas. The Graphical method was developed
More informationENGINEERING HYDROLOGY
ENGINEERING HYDROLOGY Prof. Rajesh Bhagat Asst. Professor Civil Engineering Department Yeshwantrao Chavan College Of Engineering Nagpur B. E. (Civil Engg.) M. Tech. (Enviro. Engg.) GCOE, Amravati VNIT,
More informationRainfall, Runoff and Peak Flows: Calibration of Hydrologic Design Methods for the Kansas City Area
Rainfall, Runoff and Peak Flows: Calibration of Hydrologic Design Methods for the Kansas City Area Bruce McEnroe, Bryan Young, Ricardo Gamarra and Ryan Pohl Department of Civil, Environmental, and Architectural
More informationIJSER. within the watershed during a specific period. It is constructed
International Journal of Scientific & Engineering Research, Volume 5, Issue 7, July-014 ISSN 9-5518 306 within the watershed during a specific period. It is constructed I. INTRODUCTION In many instances,
More informationMODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1. Precipitation
Watershed MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1 A watershed is an area of land thaaptures rainfall and other precipitation and funnels it to a lake or stream or wetland. The area within the watershed
More informationHYDROLOGY WORKSHEET 1 PRECIPITATION
HYDROLOGY WORKSHEET 1 PRECIPITATION A watershed is an area of land that captures rainfall and other precipitation and funnels it to a lake or stream or wetland. The area within the watershed where the
More informationStream hydrographs. Stream hydrographs. Baseflow. Graphs of river stage or discharge at a single location as a function of time
Stream hydrographs Graphs of river stage or discharge at a single location as a function of time Hydrologic og budget Discharge: units? How is it measured? Show fluctuating water levels in response to
More informationCHAPTER FIVE Runoff. Engineering Hydrology (ECIV 4323) Instructors: Dr. Yunes Mogheir Dr. Ramadan Al Khatib. Overland flow interflow
Engineering Hydrology (ECIV 4323) CHAPTER FIVE Runoff Instructors: Dr. Yunes Mogheir Dr. Ramadan Al Khatib Overland flow interflow Base flow Saturated overland flow ١ ٢ 5.1 Introduction To Runoff Runoff
More informationHydrologic Calibration:
Hydrologic Calibration: UPDATE OF EFFECTIVE HYDROLOGY FOR MARYS CREEK October 2010 Agenda Background Hydrologic model Calibrated rainfall Hydrologic calibration 100 year discharges, Existing Conditions
More informationWhat is runoff? Runoff. Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream
What is runoff? Runoff Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream 1 COMPONENTS OF Runoff or STREAM FLOW 2 Cont. The types of runoff
More informationUNIT HYDROGRAPH AND EFFECTIVE RAINFALL S INFLUENCE OVER THE STORM RUNOFF HYDROGRAPH
UNIT HYDROGRAPH AND EFFECTIVE RAINFALL S INFLUENCE OVER THE STORM RUNOFF HYDROGRAPH INTRODUCTION Water is a common chemical substance essential for the existence of life and exhibits many notable and unique
More informationSnyder Unit Hydrograph Parameters for Malasian Catchments
, pp.88-95 http://dx.doi.org/10.14257/astl.2017.146.17 Snyder Unit Hydrograph Parameters for Malasian Catchments Hazalizah bt Hamzah¹, Jer Lang Hong² and Kee An Hong 3 ¹ Drainage and Irrigation Department,
More informationAutumn semester of Prof. Kim, Joong Hoon
1 Autumn semester of 2010 Prof. Kim, Joong Hoon Water Resources Hydrosystems System Engineering Laboratory Laboratory 2 A. HEC (Hydrologic Engineering Center) 1 Established in the U.S. Army Corps of Engineers(USACE)
More informationDEVELOPMENT OF PEAK RUNOFF HYDROGRAPHS FOR OBA AND OTIN RIVERS IN OSUN STATE, NIGERIA
DEVELOPMENT OF PEAK RUNOFF HYDROGRAPHS FOR OBA AND OTIN RIVERS IN OSUN STATE, NIGERIA 1 Adejumo, L. A., 1 Adeniran, K. A., 2 Salami, A.W., 3 Abioye Tunde., and 4 Adebayo, K. R 1 Department of Agricultural
More informationDerivation of Unit Hydrograph (UH) Module Objectives. Unit Hydrograph. Assumptions in Unit Hydrograph theory. Derivation of Unit Hydrograph
PRINT VERSION MODULE Derivation of Unit Hydrograph (UH) Module Objectives References Unit Hydrograph Assumptions in Unit Hydrograph theory Derivation of Unit Hydrograph Unit Hydrograph from a Hydrograph
More informationFlood mitigation study on a GIS platform for an ungauged catchment: a case study
Water Resources Management VI 151 Flood mitigation study on a GIS platform for an ungauged catchment: a case study A. K. Gopinath 1 & T. Radhakrishnan 2 1 Water Resources Dept, Govt. of Kerala, India 2
More informationEngineering Hydrology Class 3
Engineering Hydrology Class 3 Topics and Goals: I.Develop s (estimate precipitation) II.Develop simple constant intensity design storm III.Develop SCS design storm Ocean s Why do we want to derive the?
More informationFAST WATER / SLOW WATER AN EVALUATION OF ESTIMATING TIME FOR STORMWATER RUNOFF
FAST WATER / SLOW WATER AN EVALUATION OF ESTIMATING TIME FOR STORMWATER RUNOFF Factors Affecting Stormwater Runoff: Rainfall intensity % Impervious surfaces Watershed size Slope Soil type, soil compaction
More informationSixth Semester B. E. (R)/ First Semester B. E. (PTDP) Civil Engineering Examination
CAB/2KTF/EET 1221/1413 Sixth Semester B. E. (R)/ First Semester B. E. (PTDP) Civil Engineering Examination Course Code : CV 312 / CV 507 Course Name : Engineering Hydrology Time : 3 Hours ] [ Max. Marks
More informationCIVE22 BASIC HYDROLOGY Jorge A. Ramírez Homework No 7
Hydrologic Science and Engineering Civil and Environmental Engineering Department Fort Collins, CO 80523-1372 (970) 491-7621 CIVE22 BASIC HYDROLOGY Jorge A. Ramírez Homework No 7 1. Obtain a Unit Hydrograph
More informationAPPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY)
APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY) Hydromodification design criteria for the North Orange County permit area are based on the 2- yr, 24-hr
More informationNorman Maclean Snowmelt Flow rate Storm flows fs (c flow m a tre S
Eventually, all things merge into one, and a river runs through it. Norman Maclean Understanding Streamflow ADEQ SW Short Course June 13, 213 Phoenix, AZ Hydrographs Discharge (Q) USGS flow data & plots
More informationHydrology and Water Resources Engineering
Hydrology and Water Resources Engineering SUB GSttingen 214 868 613 K.C. Patra 't'v Mai Narosa Publishing House New Delhi Chennai Mumbai Calcutta CONTENTS Preface vii 1. Introduction 1 1.1 General 1 1.2
More informationAlpha College of Engineering. Fifth Semester B.E. Question Bank. Hydrology and irrigation engineering
Alpha College of Engineering Fifth Semester B.E. Question Bank Hydrology and irrigation engineering UNIT 1: INTRODUCTION & PRECIPITATION 1.Explain in brief the different types of precipitation. 2.How do
More informationIntroduction, HYDROGRAPHS
HYDROGRAPHS Sequence of lecture Introduction Types of Hydrograph Components of Hydrograph Effective Rainfall Basin Lag or Time Lag Parts of Hydrograph Hydrograph Analysis Factors Affecting Hydrograph Shape
More informationCalibration of the Soil Conservation Services (SCS) Method in Peninsular Malaysia Using Sungai Tasoh Catchment, Negeri Perlis
Calibration of the Soil Conservation Services (SCS) Method in Peninsular Malaysia Using Sungai Tasoh Catchment, Negeri Perlis ROZI ABDULLAH, Lecturer, School of Civil Engineering, Universiti Sains Malaysia,
More informationRemote Sensing and GIS Applications in Determination of Geomorphological Parameters and Design Flood for a Himalyan River Basin, India
International Research Journal of Earth Sciences ISSN 2321 2527 Int. Res. Earth Sci. Remote Sensing and GIS Applications in Determination of Geomorphological Parameters and Design Flood for a Himalyan
More informationSummary of Detention Pond Calculation Canyon Estates American Canyon, California
July 15, 2015 Bellecci & Associates, Inc Summary of Detention Pond Calculation Canyon Estates American Canyon, California 1. Methodology: Method: Unit Hydrograph Software: Bentley Pond Pack Version 8i
More informationDETENTION BASIN DESIGN USING RATIONAL HYDROGRAPHS
DETENTION BASIN DESIGN USING RATIONAL HYDROGRAPHS By Thomas F. Smith, P.E., P.L.S. Bercek and Smith Engineering, Inc. www.bercekandsmith.com tfsmith2@bercekandsmith.com 1 Topics Covered: 2 1 Attributed
More informationUtah State University Department of Civil and Environmental Engineering CEE 3430 Engineering Hydrology Test 2. Date: 3/31/2014
Utah State University Department of Civil and Environmental Engineering CEE 3430 Engineering Hydrology Test 2. Date: 3/31/2014 D.G. Tarboton Time: 50 min 45 Points Open Book. Answer all questions. Please
More information1 n. Flow direction Raster DEM. Spatial analyst slope DEM (%) slope DEM / 100 (actual slope) Flow accumulation
1 v= R S n 2/3 1/2 DEM Flow direction Raster Spatial analyst slope DEM (%) Flow accumulation slope DEM / 100 (actual slope) 0 = no cell contributing 215 = 215 cell contributing towards that cell sqrt (actual
More informationDrainage Analysis. Appendix E
Drainage Analysis Appendix E The existing and proposed storm drainage systems have been modeled with Bentley CivilStorm V8 computer modeling software. The peak stormwater discharge was determined for
More information2.2.1 Statistical methods (Frequency Analysis)
2.' LITERATURE SURVEY 2.1 General Flood is considered as unusually high stage of the river. It is perhaps better described as that stage at which the stream channel gets filled and above which it overflows
More informationDevelopment of Runoff Depth Map for Alberta
Development of Runoff Depth Map for Alberta Introduction Assessment of basin runoff potential is an important component of the Hydrotechnical Design Guidelines for highway projects interacting with streams.
More informationDevelopment of Synthetic Unit Hydrograph at Kakkadavu Dam
International Journal of Mechanics and Solids. ISSN 0973-1881 Volume 12, Number 1 (2017), pp. 113-124 Research India Publications http://www.ripublication.com/ijms.htm Development of Synthetic Unit Hydrograph
More informationHydrologic Engineering Center Hydrologic Modeling System (HEC-HMS) Sunil KUMAR Director, National Water Academy
Hydrologic Engineering Center Hydrologic Modeling System (HEC-HMS) Sunil KUMAR Director, National Water Academy 22 April 2015 NWA, Pune Exercise Objective: To determine hydrological Response of the given
More informationWater Budget III: Stream Flow P = Q + ET + G + ΔS
Water Budget III: Stream Flow P = Q + ET + G + ΔS Why Measure Streamflow? Water supply planning How much water can we take out (without harming ecosystems we want to protect) Flood protection How much
More informationWater Budget III: Stream Flow P = Q + ET + G + ΔS
Water Budget III: Stream Flow P = Q + ET + G + ΔS Why Measure Streamflow? Water supply planning How much water can we take out (without harming ecosystems we want to protect) Flood protection How much
More informationCE 2031 WATER RESOURCES ENGINEERING L T P C
CE 2031 WATER RESOURCES ENGINEERING L T P C 3 0 0 3 QUESTION BANK PART - A UNIT I GENERAL 1. Write short notes on Water Resources Survey. 2. How do you calculate Average Annual Runoff depth? 3. Write short
More informationWater Budget III: Stream Flow P = Q + ET + G + ΔS
Water Budget III: Stream Flow P = Q + ET + G + ΔS Why Measure Streamflow? Water supply planning How much water can we take out (without harming ecosystems we want to protect) Flood protection How much
More informationIntroduction. Keywords: Oil Palm, hydrology, HEC-HMS, HEC-RAS. a * b*
The Effect of Land Changes Towards in Sg. Pandan Perwira Bin Khusairi Rahman 1,a* and Kamarul Azlan bin Mohd Nasir 1,b 1 Faculty of Civil Engineering, Universiti Teknologi Malaysia, Malaysia a * wirakhusairirahman@gmail.com,
More informationCumulative Precipitation
Problem 1: Hyetograph Construction (4 pts) Use the rainfall information below to construct both the cumulative (inch) and incremental (in/hr) hyetographs. Note: the incremental hyetograph must be formatted
More informationHydrologic Engineering Center. Training Course on. Hydrologic Modeling with HEC-HMS. Davis, CA. Course Description
Hydrologic Engineering Center Training Course on Hydrologic Modeling with HEC-HMS Davis, CA Course Description The course provides an introduction to HEC-HMS for new users, focusing both on using the program
More informationEstimating the 100-year Peak Flow for Ungagged Middle Creek Watershed in Northern California, USA
American Journal of Water Resources, 2014, Vol. 2, No. 4, 99-105 Available online at http://pubs.sciepub.com/ajwr/2/4/3 Science and Education Publishing DOI:10.12691/ajwr-2-4-3 Estimating the 100-year
More informationRunoff Processes. Daene C. McKinney
CE 374 K Hydrology Runoff Processes Daene C. McKinney Watershed Watershed Area draining to a stream Streamflow generated by water entering surface channels Affected by Physical, vegetative, and climatic
More information5/11/2007. WinTR-55 for Plan Reviewers Small Watershed Hydrology Hydrology Terms and Definitions
WinTR-55 for Plan Reviewers Small Watershed Hydrology Hydrology Terms and Definitions 1 Course Outline Overview Review of Hydrology Terms and Definitions Modeling Single Sub-area Watersheds Multiple Sub-area
More information2. Potential Extreme Peak Discharge in Texas
2. Potential Extreme Peak Discharge in Texas This part of the work is focused on using GIS to apply the latest USGS peak discharge equations to create a 500m grid that stores the potential peak discharge
More informationThe Drainage Basin System
The Drainage Basin System These icons indicate that teacher s notes or useful web addresses are available in the Notes Page. This icon indicates that the slide contains activities created in Flash. These
More informationHydrologic Engineering Center. Training Course on. Hydrologic Modeling with HEC-HMS April 2018 Davis, CA. Course Description
Hydrologic Engineering Center Training Course on Hydrologic Modeling with HEC-HMS 23-27 April 2018 Davis, CA Course Description The course provides an introduction to HEC-HMS for new users, focusing both
More informationComparison of Rational Formula Alternatives for Streamflow Generation for Small Ungauged Catchments
ENGINEER - Vol. XXXXIV, No. 04, pp, [29-36], 2011 The Institution of Engineers, Sri Lanka Comparison of Rational Formula Alternatives for Streamflow Generation for Small Ungauged s W.M.D.Wijesinghe and
More informationOverview of NRCS (SCS) TR-20 By Dr. R.M. Ragan
Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan TR-20 is a computer program for the simulation of runoff occurring from a single storm event. The program develops flood hydrographs from runoff and routes
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationCEE3430 Engineering Hydrology
CEE3430 Engineering Hydrology Practice Exam (There are multiple practice questions here A 110 min test will likely not have more than four questions) 1. Water Balance Write the water balance as Δ Where
More informationTECHNICAL MEMORANDUM. SUBJECT: Determination of watershed historic peak flow rates as the basis for detention basin design
TECHNICAL MEMORANDUM FROM: Ken MacKenzie and Ryan Taylor SUBJECT: Determination of watershed historic peak flow rates as the basis for detention basin design DATE: June 7, 2012 The purpose of this memorandum
More informationHERPIC County Storm Drainage Manual
HERPIC County Storm Drainage Manual C h r is t o p h e r B. B u r k e Research Assistant Highway Extension and Research Project for Indiana Counties Purdue University The HERPIC (Highway Extension and
More informationINSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad
INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad -00 0 CIVIL ENGINEERING TUTORIAL QUESTION BANK Course Name : WATER RESOURCE ENGINEERING - I Course Code : A0 Class : III B. Tech I
More informationHydrologic Study Report for Single Lot Detention Basin Analysis
Hydrologic Study Report for Single Lot Detention Basin Analysis Prepared for: City of Vista, California August 18, 2006 Tory R. Walker, R.C.E. 45005 President W.O. 116-01 01/23/2007 Table of Contents Page
More informationCVEN 339 Summer 2009 Final Exam. 120 minutes allowed. 36 Students. No curve applied to grades. Median 70.6 Mean 68.7 Std. Dev High 88 Low 24.
CVEN 339 Final Exam 120 minutes allowed 36 Students No curve applied to grades Median 70.6 Mean 68.7 Std. Dev. 13.7 High 88 Low 24.5 Name: CVEN 339 Water Resources Engineering Summer Semester 2009 Dr.
More informationSECTION IV WATERSHED TECHNICAL ANALYSIS
A. Watershed Modeling SECTION IV WATERSHED TECHNICAL ANALYSIS An initial step in the preparation of this stormwater management plan was the selection of a stormwater simulation model to be utilized. It
More informationDEVELOPMENT OF PEAK RUNOFF HYDROGRAPHS FOR SELECTED RIVERS IN SOME PARTS OF NIGERIA
1. A.W. SALAMI, 2. S.A. ADEBARA, 3. S.A. ALABI DEVELOPMENT OF PEAK RUNOFF HYDROGRAPHS FOR SELECTED RIVERS IN SOME PARTS OF NIGERIA 1. DEPARTMENT OF CIVIL ENGINEERING, UNIVERSITY OF ILORIN, P.M.B 1515,
More informationLearning objectives. Upon successful completion of this lecture, the participants will be able to describe:
Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to describe: The different approaches for estimating peak runoff for urban drainage network
More informationInternational Journal of Scientific & Engineering Research, Volume 5, Issue 7, July-2014 ISSN Sruthy Nattuvetty Manoharan
ISSN 2229-5518 210 Sruthy Nattuvetty Manoharan Department of Civil Engineering Government Engineering College, Thrissur Thrissur, 680009 sruthy.n.m@gmail.com a spatially distributed excess rainfall. It
More informationHYDROLOGIC MODELING CONSISTENCY AND SENSITIVITY TO WATERSHED SIZE
HYDROLOGIC MODELING CONSISTENCY AND SENSITIVITY TO WATERSHED SIZE by James C.Y. Guo. Professor, Civil Engineering, U. Of Colorado at Denver, James.Guo@cudenver.edu.. And Eric Hsu, Project Engineer, Parson
More informationWater Budget III: Stream Flow P = Q + ET + G + ΔS
Water Budget III: Stream Flow P = Q + ET + G + ΔS Why Measure Streamflow? Water supply planning How much water can we take out (without harming ecosystems we want to protect) Flood protection How much
More informationEngineering Hydrology
Engineering Hydrology 040454 Introduction Instructor: Dr. Zeyad Tarawneh Course Contents Introduction, watershed and flow: Definition, hydrologic cycle, water balance, watersheds, statistical methods in
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any
More informationComputation of excess stormflow at the basin scale. Prof. Pierluigi Claps. Dept. DIATI, Politecnico di Torino
Computation of excess stormflow at the basin scale Prof. Pierluigi Claps Dept. DIATI, Politecnico di Torino Pierluigi.claps@polito.it losses include: interception, evapotranspiration, storage infiltration,
More informationSection 2: Hydrology. Introduction. What is the Return Period? Intensity-Duration-Frequency Data. Generating a runoff hydrograph 85 Minutes
Section 2: Hydrology Generating a runoff hydrograph 85 Minutes Press Space, PageDown, or Click to advance. Press PageUp to reverse. Esc to exit. Right-Click for other options. Copyright 2004 HydroCAD Software
More informationCourse Title: Hydrology, Irrigation and Flood Management Course Code: CE 4163 Credit: 3
Course Title: Hydrology, Irrigation and Flood Management Course Code: CE 4163 Credit: 3 Reference Books 1. Hydrology by H.M. Raghunath 2. A Text Book of Hydrology - P. Jaya Rami Reddy 3. Engineering Hydrology
More informationSOUTHEAST TEXAS CONTINUING EDUCATION
EXAM No. 118 FLOOD - RUNOFF ANALYSIS 1. Information gained from flood - runoff analysis includes which one: A. Stage, discharge, volume. B. Measure depth, volume. C. Velocity, depth, storm occurrence.
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment
More informationChapter H. Introduction to Surface Water Hydrology and Drainage for Engineering Purposes
Chapter H. Introduction to Surface Water Hydrology and Drainage for Engineering Purposes As seen in Figure H.1, hydrology is a complex science that deals with the movement of water between various stages
More informationA NEW HYDROLOGIC RESPONSE FUNCTION PHYSICALLY DERIVED FROM DEM AND REMOTE SENSING IMAGE
Proc. of the 2nd Asia Pacific Association of Hydrology and Water Resources (APHW) Conference, July 5-8, 2004, Suntec Singapore International Convention Exhibition Centre, Singapore, vol. 2, pp. 268-275,
More informationDistributed Hydrological Model For An Ungauged Subcatchment
Distributed Hydrological Model For An Ungauged Subcatchment Dr. Krishna Mohan M Professor of Civil Engineering, Malla Reddy Engg College (Autonomous under JNTUH), Secunderabad Abstract Rainfall and runoff
More informationHYDROLOGIC & HYDRAULIC ASPECTS of the Walnut Street Bridge over the Schuylkill River Philadelphia, PA
HYDROLOGIC & HYDRAULIC ASPECTS of the Walnut Street Bridge over the Schuylkill River Philadelphia, PA J. Richard Weggel CAEE201 Lectures 30 April & 2 May 2007 HYDROLOGY (Natural Science) Study of the waters
More informationHydrology and Water Management. Dr. Mujahid Khan, UET Peshawar
Hydrology and Water Management Dr. Mujahid Khan, UET Peshawar Course Outline Hydrologic Cycle and its Processes Water Balance Approach Estimation and Analysis of Precipitation Data Infiltration and Runoff
More informationUnit 2: Geomorphologic and Hydrologic Characteristics of Watersheds. ENVS 435: Watershed Management INSTR.: Dr. R.M. Bajracharya
Unit 2: Geomorphologic and Hydrologic Characteristics of Watersheds ENVS 435: Watershed Management INSTR.: Dr. R.M. Bajracharya Watersheds are hydro-geologic units Water flow and cycling are basic and
More informationCONTINUOUS RAINFALL-RUN OFF SIMULATION USING SMA ALGORITHM
CONTINUOUS RAINFALL-RUN OFF SIMULATION USING SMA ALGORITHM INTRODUCTION Dr. R N Sankhua Director, NWA, CWC, Pune In this continuous rainfall-runoff simulation, we will perform a continuous or long-term
More informationRainfall Runoff analysis of wadis contributing to the Dead Sea
Rainfall Runoff analysis of wadis contributing to the Dead Sea Salam Abu Hantash and Anan Jayyousi Introduction: Flow simulation in ungauged catchments is presently regarded as one of the most challenging
More informationICELANDIC RIVER / WASHOW BAY CREEK INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT
ICELANDIC RIVER / WASHOW BAY CREEK INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT Disclaimer: The hydrologic conditions presented in this
More informationStormwater Review Part 2. Rainfall and Runoff. Tom Seybert, PE and Andy Bennett, PE. Pennsylvania Surveyors Conference 2019
Stormwater Review Part 2 Rainfall and Runoff Tom Seybert, PE and Andy Bennett, PE Pennsylvania Surveyors Conference 2019 1 Topics Covered 1. Rainfall characteristics and sources 2. Watershed characteristics
More informationSan Luis Obispo Creek Watershed Hydrologic Model Inputs
Jeff Werst San Luis Obispo County Department of Public Works 1050 Monterey Street San Luis Obispo CA 93408 December 14, 2007 Subject: San Luis Obispo Creek Watershed Hydrology and Hydraulic Model Dear
More informationRUNOFF CALCULATIONS RATIONAL METHOD. To estimate the magnitude of a flood peak the following alternative methods are available:
RUNOFF CALCULATIONS To estimate the magnitude of a flood peak the following alternative methods are available: 1. Unit-hydrograph technique 2. Empirical method 3. Semi-Empirical method (such rational method).
More information5/11/2007. WinTR-55 for Plan Reviews Small Watershed Hydrology Overview
WinTR-55 for Plan Reviews Small Watershed Hydrology Overview 1 Overview Course Outline Historical Background Program Description Model Capabilities and Limitations This is the Overview portion of the training.
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationDERIVATION AND CALIBRATION OF VOLUME-BASED RUNOFF COEFFICIENTS FOR DENVER AREA, COLORADO
DERIVATION AND CALIBRATION OF VOLUME-BASED RUNOFF COEFFICIENTS FOR DENVER AREA, COLORADO Prepared by Dr. James C.Y. Guo, P.E., Professor and Director, Civil Engineering, U of Colorado Denver James.Guo@UCDenver.edu
More information2
1 2 3 4 5 6 The program is designed for surface water hydrology simulation. It includes components for representing precipitation, evaporation, and snowmelt; the atmospheric conditions over a watershed.
More informationResults shown on 'Detailed Summary' tab
Fill in site's Pre Development parameters on 'Pre' tab (Site Area, Drainage Area, Impervious Area, CNpre, tc) Prior to using BSD or BMP practices, fill in site's Post Development parameters on 'Post' tab
More informationCONSISTENCY BETWEEN CUHP AND RATIONAL METHODS James C.Y. Guo, PhD, P.E., and Ben Urbonas, P.E., D.WRD 08/04/2008
CONSISTENCY BETWEEN CUHP AND RATIONAL METHODS James C.Y. Guo, PhD, P.E., and Ben Urbonas, P.E., D.WRD 08/04/2008 When estimating runoff for a storm event it is assumed that the storm runoff occurs from
More informationI(n)Kn. A Qp = (PRF) --- (8) tp Where A is the watershed area in square miles and PRF is the unit hydrograph peak rate factor.
AN ALTERNATE APPROACH FOR ESTIMATING SCS UNIT HYDROGRAPH PEAK RATE FACTORS (PRFS) IN SOUTHWEST FLORIDA Himat Solanki Southwest Florida Water Management District 115 Corporation Way, Venice, Florida 34292
More informationWATER RESOURCE ENNG.(NCE-702)
Assignment: I (Unit 1) 1. Describe the concept of hydrologic cycle with the help of a neat sketch. What are the different components ofthe hydrologic cycle? What do you mean by hydrologic system? 2. A
More information