Financial Viability and Barriers for Implementing AFR Project An Industry Perspective

Size: px
Start display at page:

Download "Financial Viability and Barriers for Implementing AFR Project An Industry Perspective"

Transcription

1 Financial Viability and Barriers for Implementing AFR Project An Industry Perspective Ulhas Parlikar Dy Head, Geocycle India ACC Limited 2014 Holcim Technology 2014 Ltd

2 About Geocycle For a zero-waste future Geocycle is the waste management brand of Holcim. In Geocycle, the service of waste coprocessing in cement manufacturing process is provided. Holcim is the promoter of both ACC Limited and Ambuja Cements Limited (ACL). Brand was created in 2007 as the dedicated identity used to brand waste management solutions in the Holcim Group We apply the highest health, environment and safety standards in all our operation complying to relevant regulation

3 The Geocycle Approach Waste assessment We undertake complete survey of the various kinds of wastes and full assessment of their suitability for coprocessing. Waste analysis We have dedicated laboratory facilities to analyze the various physico-chemical characteristics of wastes that are liquid, Solid or sludges. We also undertake extensive OHS assessment so as to ensure their safe disposal. Waste transportation We provide a seamless service ensuring the waste is transported in appropriate packaging with required labelling and documentation. The waste is carried by operators with required skills, qualifications and permits. Pre-processing We set up and implement extensive facilities to blend liquids, shred solid materials and homogenise wastes into Alternative Fuels and Raw materials (AFRs) prior to their usage in kilns Co-processing AFRs are then safely co-processed in our cement kilns.

4 Waste management through cement kiln coprocessing While undertaking waste management through cement kiln coprocessing, wastes have to go through several operational stages such as assessment, storage, handling, preprocessing and coprocessing etc. Reasonable investment is required to implement the above activities in an environmentally sound and operationally safe manner. For successful management of wastes in cement kilns, these investments have to be financially viable. A lot of stake holder perceptions act as barriers in getting coprocessing implemented in a successful manner. 4

5 Financial Perceptions Cement plants benefit from the Calorific & Material Value present in waste Wastes have calorific and material value present in them but there is considerable variation from lot to lot. For gainful utilisation of this energy and material value, cement plants need to implement relevant facilities. The energy and material replacement value alone cannot provide acceptable payback for these investments. Tipping fee for the disposal of wastes is essential. Cement plants must undertake waste coprocessing as a CSR initiative For cement plants to extend waste management activities in a sustainable manner, the coprocessing initiative has to be undertaken in a business mode. 5

6 Technical Perceptions Coprocessing of wastes involves release of obnoxious gases from kiln stack Very high temperature of operation, long residence time, counter current flow of waste & hot gases, alkaline environment with highly active lime etc., ensure that there are no obnoxious emissions from the kiln stack. More than 70 coprocessing trials of different kinds of wastes, having varying concentration of different parameters, conducted in different cement plants in India have demonstrated that there is no influence on emissions due to coprocessing. Waste can be fed as it is in the kiln Wastes need to be preprocessed and feed at relevant feed points depending upon their physical and combustion characteristics. Proper quality control of the input material is essential for producing right quality cement. Cement kilns can coprocess all kinds of wastes in any proportion Cement kilns can coprocess different kinds of wastes only to the extent that their raw material chemistry and design permits. All wastes can be coprocessed in cement kilns A large number of wastes can be coprocessed in the cement kilns except those that are determined as banned wastes. 6

7 Global Experience Coprocessing is a recovery operation and hence is higher in the waste management hierarchy over landfill and incineration options of disposal. Coprocessing helps reduce the GHG emissions. It is feasible for cement plants to extend coprocessing solution to manage large quantum of wastes in a win-win manner. In almost all cases, wastes gets disposed at a cost that is cheaper than the other disposal costs such as landfill or incineration. (Advantage to the waste generator). Large amounts of fossil fuels and raw materials get replaced at reduced costs thereby reducing the production cost of cement. (Advantage to cement plants) Reduces drastically the environmental load that is likely to be caused into the environment. (Advantage to society) 7

8 Infrastructure for coprocessing For responsible and environmentally sustainable coprocessing, different infrastructure is required to be created in the cement plant. An appropriate laboratory for waste characterisation. Storage & handling facility, Properly designed AFR feeding facility at the relevant feed points such as main burner, kiln intel or calciner etc. Fire fighting facility Proper business processes & qualified manpower to deal with the hazards and vagaries of wastes. Depending upon the volume of waste / AFR handled, coprocessing facility can be a manually operated starter kit or a fully automated standard facility. 8

9 Infrastructure for Preprocessing Since there is considerable variation in the quality of wastes received for coprocessing, preprocessing of them into a uniform quality material is essential. This also requires relevant facilities to be created. Laboratory Segregated storage for different kinds of incoming wastes and outgoing AFRs Properly designed equipment and machinery for shredding, impregnation, blending, mixing, screening, segregation etc. meeting specific standards to deal with the hazards associated with the different kinds of wastes. Fire fighting facility Proper business processes & qualified manpower to deal with the hazards and vagaries of wastes. Every cement kiln has different acceptability criteria depending upon the operating chemistry and the preprocessed waste needs to be tuned to match that. Depending upon the volume of waste / AFR handled, preprocessing facility can be a manually operated or a fully automated facility. Preprocessing facility can be implemented within the cement plant or can be implemented at the waste generation location. 9

10 Financial Considerations INCOME ITEMS 1. Tipping Fees from waste generator 2. Substitution benefit derived due to the replacement of traditional raw materials and fuels by wastes. EXPENDITURE ITEMS 1. Waste identification 2. Laboratory assessment 3. Handling and storage 4. Manpower cost 5. Coprocessing cost 6. Preprocessing cost 7. Production impact 8. Fuel usage impact 9. Interest, Depreciation and other costs Coprocessing initiative will be viable when income from coprocessing of wastes in cement kiln is higher than the expenditure incurred. There can be different business models for management of Industrial and segregated MSW fractions for the consideration of the cement plants. 10

11 Industrial Wastes

12 Different models for preprocessing and coprocessing of IW Third Party Assessment QA / QC Industrial Wastes Collection Preprocessing Assessment QA / QC Collection Preprocessing Co-processing Cement Plant 12

13 MSW is garbage and cannot be directly co-processed! 13

14 Current MSW Model in India Proposed as Fuel for cement plant/wte Combustible Fraction 40% ++ 25% 10% Sorting (manual+me chanical) Recycling 25% Landfill 14 14

15 Adaptable Business Model in India (integration with existing option) Key driver in the market is the appropriate tipping fee to make the economics work - Co-Processing Pre-processing shredding and blending Combustible Fraction 40% 25% 10% INR/T Sorting (manual+me chanical) Recycling 25% Landfill 15

16 Different Models for RDF Preprocessing and Coprocessing Third Party with support from ULB s Third Party /cement Plants MSW Collection Segregation Combustible Recyclables Bio-degradable Composting Pre-processing RDF Model 1 Model 2 Model 3 Pre-processing QA / QC Co-processing Cement Plants 16

17 Regulatory framework Global scenariio Coprocessing, being a technology that leaves zero waste for future concern, is practiced on large scales in many EU and other developed countries. Holcim and GTZ through a Strategic alliance Proposed international guidelines for the co-processing of waste materials in the cement production Secured the public acceptance of these guidelines Finalized them in July 2006 From those guidelines, specific legal frames on coprocessing are under implementation in around 15 countries

18 Global regulatory framework Basal Convention Basal Convention has reviewed and approved technical guidelines on coprocessing To offer objective information about co-processing of waste in the cement industry To offer objective information about coprocessing of waste in the cement industry To offer links to organizations, institutions, and companies active in the field of co-processing and to propose ways and means for capacity building. Document Number UNEP/CHW.10/6/Add.3 Available in: For facilitating governmental authorities globally in formulating guidelines for coprocessing of wastes

19 Regulatory framework Indian Scenario The HWM rules recognized co-processing under chapter III, Rule 11. It states the following: The Utilization of Hazardous Wastes as a Supplementary Resource or for Energy Recovery, or after processing shall be carried out by the units only after obtaining approval from the Central Pollution Control Board Current Framework for Hazardous Waste Coprocessing in Cement Kilns Trial Run for new HW stream Approval from CPCB for regular coprocessing Authorization from SPCB for regular coprocessing CPCB Guidelines on Co-processing in Energy Intensive Industries was published in February 2010 On similar lines, Guidelines for Co-processing of Spent Wash generated from Distillery Units was also published

20 Barriers in the present regulatory framework Every waste has to be demonstrated as suitable for coprocessing. Highly time consuming process of permitting Landfill and Incineration are still preferred options for disposal in the HWM Rules Regulatory framework does not specify standards on infrastructure required for undertaking preprocessing or coprocessing. Emission standards for coprocessing in cement kilns are not defined. Regulatory framework does not provide clarity on application process for permitting preprocessing facilities. 20

21 What needs to be done to ensure large scale use of environmentally friendly coprocessing technology in Clean India Drive. The current regulatory framework in India provides generic permit to manage the waste through land fill and incineration process. Although coprocessing technology has superior environmental performance over incineration or landfill operations, cement plant has to obtain coprocessing permit per waste stream. That too after demonstrating the suitability of each one of them in the cement kiln through an elaborate coprocessing trial. This waste by waste permitting process is a very slow permitting process requiring about one year for each of the waste stream. There is need therefore to modify the existing waste management rules in favor of coprocessing so that cement kilns can have generic permit to coprocess all kinds of suitable wastes. Since coprocessing leaves zero waste for future concern, in the current Clean India drive in the country, cement kilns can contribute substantially in treating large amounts of hazardous and non-hazardous wastes in safe and environmentally sound manner. 21

22 How are we (geocycle) contributing to waste management Waste management is undertaken in all the clinkering plants of ACC and Ambuja Setting up seven preprocessing platform of global standards in different parts of the country. 22

23 Skilled professional with State of the art infrastructure to handle waste streams Highly competent team Dedicated lab for waste evaluation Waste transportation Waste Pre-processing platforms to bring Homogeneity from various waste streams

24 Co-processing Deliverables to customers Waste managed responsibly with no waste residue Zero Liability once the waste is accepted at Geocycle Safe, secure and environmentally sound way of waste disposal Full compliance with local environmental regulations and the setting of best practices Rigorously monitored environmental and safety standards Optimized asset utilization, eliminating unnecessary onsite waste storage Co-processing Complete documentation is, therefore, a local of waste & desired disposal route activities to manage wastes with zero Locally liability, available environmental solution impact addressing all concerns of sustainable development

25 AFR projects that we are building at several locations

26 What are we striving for? Recognition Recognition of co- processing as a preferred technology for waste management Regulatory framework Hassle free Interstate movement of wastes and clear guidelines to avoid any disputes Mandate in MSW Rules for producing RDF suitable for cement plant co-processing Generic permissions Generic Permit for Co-processing to cement plants adhering to Pre-qualification criteria Uniform permitting procedure for Hazardous and non-hazardous wastes at all SPCBs

27 Business cells from market perspective defined Geocycle has access to 14 facilities across India North North central Geocycle has made more than 60 trial burns in India with various types of waste streams East The wide spread presence across the country gives the flexibility to provide seamless solutions to our customers West Business cells with one platform each and sometimes delimited South by state Central borders due to limitations in free waste transportation. South * Depending on way forward

28 Geocycle s Global Presence Co-processing activities in over 39 countries with over 4500 customers 28 pre-processing facilities More than 10 million tons of AFR coprocessed in 2011 Treated about 20,000 waste streams

29

The Preferred option of Co-processing for greening the nations backyard

The Preferred option of Co-processing for greening the nations backyard The Preferred option of Co-processing for greening the nations backyard Sharmistha Nandi Geocycle India About Geocycle For a zero-waste future Geocycle is the waste management brand of LafargeHolcim. In

More information

Waste Co-processing in Cement Kilns

Waste Co-processing in Cement Kilns Waste Co-processing in Cement Kilns A demonstrated solution for managing wastes in an Environmentally sound and Ecologically sustaining manner Ulhas Parlikar Director Geocycle Business 2012 Holcim/Switzerland

More information

Co-processing - A preferred option for management of non-recyclable Hazardous and other wastes

Co-processing - A preferred option for management of non-recyclable Hazardous and other wastes Co-processing - A preferred option for management of non-recyclable Hazardous and other wastes Ulhas Parlikar Dy. Head, Geocycle India ulhas.parlikar@geocycle.com 2014 Holcim Technology 2014 Ltd About

More information

International Experience: MSW Solutions for Urban Centres in India Waste-to-Energy Options

International Experience: MSW Solutions for Urban Centres in India Waste-to-Energy Options 7/09/0 International Experience: MSW Solutions for Urban Centres in India Waste-to-Energy Options Hyderabad - CII September 0 DR PORST INTERNATIONAL Environmental Consulting Bangalore INDIA Urban Centre

More information

Recommended Action Plan for the Chosen AFR's

Recommended Action Plan for the Chosen AFR's Recommended Action Plan for the Chosen AFR's Sanjay Jain Senior General Manager Consulting Pvt. Ltd. Most Promising Alternate Fuels RDF from municipal solid waste [ MSW ] Used tyres Hazardous waste Industrial

More information

Waste Pre and Co-processing in Cement Kilns: Concepts and Benefits

Waste Pre and Co-processing in Cement Kilns: Concepts and Benefits Waste Pre and Co-processing in Cement Kilns: Concepts and Benefits Satendra Singh Geocycle Kymore 16.10.2014 2014 Holcim Technology 2014 Ltd Agenda 1. Geocycle 2. Waste Management Hierarchy 3. Concept

More information

Best Practices in Waste Pre-processing Facility

Best Practices in Waste Pre-processing Facility For a zero-waste future Best Practices in Waste Pre-processing Facility CII Waste Management Summit, November 2016 2015-02-09 2015 Geocycle Agenda 1. Introduction to Geocycle 2. Pre-processing Facility

More information

RDF/SRF pricing and its influence on the waste management competitive arena. Ed Verhamme Managing Partner Alternate Resource Partners

RDF/SRF pricing and its influence on the waste management competitive arena. Ed Verhamme Managing Partner Alternate Resource Partners RDF/SRF pricing and its influence on the waste management competitive arena Ed Verhamme Managing Partner Alternate Resource Partners Topics of Presentation o Introduction Alternate Resource Partners o

More information

Waste Mapping and Forecasting for Alternate Fuel Usage in Cement Plants

Waste Mapping and Forecasting for Alternate Fuel Usage in Cement Plants Promoting Alternate Fuel and Raw material (AFR) utilisation in Indian Cement Industry Waste Mapping and Forecasting for Alternate Fuel Usage in Cement Plants Confederation of Indian Industry CII Godrej

More information

Swatchh Bharat Mission Management of SCF through Cement Kiln Co-processing Issues and Way Forward

Swatchh Bharat Mission Management of SCF through Cement Kiln Co-processing Issues and Way Forward Swatchh Bharat Mission Management of SCF through Cement Kiln Co-processing Issues and Way Forward 2014 About Geocycle For a zero-waste future Geocycle is the waste management brand of LafargeHolcim. ACC

More information

SPL- Background Toxic fluoride cyanide compounds Corrosive Reactive with water

SPL- Background Toxic fluoride cyanide compounds Corrosive Reactive with water SPL- Background Spent Pot Liner (SPL) is a by-product generated when the carbon and refractory lining of an aluminium electrolytic cell, known as a pot, reaches the end of its useful life. Life of Aluminium

More information

Enhanced usage of Alternative Fuels in Cement Industry

Enhanced usage of Alternative Fuels in Cement Industry ALTERNATE FUEL --- MSW RDF BY V. P. TONDAPURKAR ROCHEM GREEN ENERGY PVT LTD MUMBAI 51 1 UNDERSTANDING OF CEMENT INDUSTRY - Cement Production India Year Capacity Mn T 2010 228.3 2014 255.6 2024 666 Plant

More information

Co-processing: a unique waste treatment solution

Co-processing: a unique waste treatment solution Co-processing: a unique waste treatment solution Geocycle For a zero-waste future Our waste treatment solutions Treating waste is a demanding, complex, costly and time consuming challenge for companies

More information

Realizing new markets, lessons learned in the cement industry Experience of the European Cement Industry

Realizing new markets, lessons learned in the cement industry Experience of the European Cement Industry Realizing new markets, lessons learned in the cement industry Experience of the European Cement Industry November 17 th, 2016 Jan Theulen, Director Alternative Resources, HeidelbergCement Contents 1. Actual

More information

WHITE PAPER INCREASING CO-PROCESSING IN INDIAN CEMENT PLANTS

WHITE PAPER INCREASING CO-PROCESSING IN INDIAN CEMENT PLANTS WHITE PAPER ON INCREASING CO-PROCESSING IN INDIAN CEMENT PLANTS 0 6/27/2012 Disclaimer This report is the result of a collaborative effort between Confederation of Indian Industry (CII) & Cement Manufacturers

More information

International Experience on Increasing Use of Alternative Fuels and Raw Materials (AFR) in the Cement Industry, and Recommendations for China

International Experience on Increasing Use of Alternative Fuels and Raw Materials (AFR) in the Cement Industry, and Recommendations for China International Experience on Increasing Use of Alternative Fuels and Raw Materials (AFR) in the Cement Industry, and Recommendations for China Coal Consumption Cap and Energy Transition International Workshop

More information

Introduction of Huaxin Environmental Business. We build sustainable development world

Introduction of Huaxin Environmental Business. We build sustainable development world Introduction of Huaxin Environmental Business We build sustainable development world Content Introduction of Huaxin Cement Ltd Environmental business in Huaxin Pre-processing platform for different waste

More information

CO-PROCESSING. Alternative Fuels & Raw Materials ULTRATECH CEMENT

CO-PROCESSING. Alternative Fuels & Raw Materials ULTRATECH CEMENT CO-PROCESSING OF Alternative Fuels & Raw Materials AT ULTRATECH CEMENT A Brief Snapshot Aditya Birla Group s Cement Business journey started in the year 1983 Currently largest manufacturer of Grey Cement,

More information

Co-processing waste in the cement industry:

Co-processing waste in the cement industry: Co-processing waste in the cement industry: A solution to natural resource preservation and total emission reduction Anne Dekeukelaere - Cementis 1 Waste an ever lasting problem Waste is produced all over

More information

Holcim Group AFR Policy Holcim Ltd

Holcim Group AFR Policy Holcim Ltd Holcim Group AFR Policy Holcim Ltd Policy Principles The cement making process is energy and material intensive. Traditionally, fossil fuels and natural raw materials have been used to make clinker, the

More information

India s First MSW Treatment Facility

India s First MSW Treatment Facility India s First MSW Treatment Facility Fully Compliant with SWM 2016 guidelines OREX powered Mechanical Biological Treatment Presentation SFC Environmental Technology Pvt. Ltd, India We all agree Urgent

More information

Co-processing waste in the cement industry: A solution to natural resource preservation and total emission reduction

Co-processing waste in the cement industry: A solution to natural resource preservation and total emission reduction Co-processing waste in the cement industry: A solution to natural resource preservation and total emission reduction Cement thus concrete plays a vital part in our daily lives. Few people are aware that

More information

Co-processing : A sustainable solution for SPL management Holcim Technology 2014 Ltd

Co-processing : A sustainable solution for SPL management Holcim Technology 2014 Ltd Co-processing : A sustainable solution for SPL management 2014 Holcim Technology 2014 Ltd Business cells from market perspective defined Geocycle has access to 14 facilities across India, co-processing

More information

From UN/SBC Technical Guidelines on Co-processing of Hazardous Waste in Cement Kilns To a Co-processing Legal Frame in India

From UN/SBC Technical Guidelines on Co-processing of Hazardous Waste in Cement Kilns To a Co-processing Legal Frame in India Cement Manufacturers Association CMA-IIP INTERNATIONAL CONFERENCE ON ENHANCED USAGE OF ALTERNATE FUELS & RAW MATERIALS (AFR) - CO-PROCESSING IN CEMENT PLANTS From UN/SBC Technical Guidelines on Co-processing

More information

FOSTERING RESOURCE EFFICIENT & ZERO WASTE SYSTEMS IN NIGERIA: THE INDISPENSABLE ROLE OF THE PRIVATE SECTOR LAFARGE GLOBAL EXPERIENCE

FOSTERING RESOURCE EFFICIENT & ZERO WASTE SYSTEMS IN NIGERIA: THE INDISPENSABLE ROLE OF THE PRIVATE SECTOR LAFARGE GLOBAL EXPERIENCE NIGERIA WAPCO Operations FOSTERING RESOURCE EFFICIENT & ZERO WASTE SYSTEMS IN NIGERIA: THE INDISPENSABLE ROLE OF THE PRIVATE SECTOR LAFARGE GLOBAL EXPERIENCE By Daniel ADEDOKUN Head of Industrial Ecology,

More information

09 April 2018 VIA (Vapi Industrial Association) Conference Hall, Vapi

09 April 2018 VIA (Vapi Industrial Association) Conference Hall, Vapi Minutes of the Discussions Made in the Half Day Workshop on Utilisation of Priority Waste Streams from Vapi Industrial Estate in Cement Kilns in Gujarat 09 April 2018 VIA (Vapi Industrial Association)

More information

The Polish National Waste Management Plan 2014

The Polish National Waste Management Plan 2014 1. Introduction... 21 2. Identification of problems in waste management... 22 3. Adopted aims in waste management... 23 4. Lines of action for waste prevention and shaping of waste management system...

More information

RDF: Alternative Fuel tailor-made from Waste

RDF: Alternative Fuel tailor-made from Waste RDF: Alternative Fuel tailor-made from Waste RECUWATT Conference: Recycling and Energy Mataró, October 4 5, 2012 Hermann Krähling on behalf of Managing Director tecpol kraehling@tecpol.de www.tecpol.de

More information

SUSTAINABLE WASTE MANAGEMENT

SUSTAINABLE WASTE MANAGEMENT SUSTAINABLE WASTE MANAGEMENT,Nemam An ISO 9001:2008, ISO 14001:2004, OHSAS 18001:2007 and FSSC 22000:2011 Certified Unit PLANT PROFILE Started with one 600 BPM CSD RGB Line in March 1997. Added one more

More information

Experiences from other international processes; Basel and Stockholm convention

Experiences from other international processes; Basel and Stockholm convention Experiences from other international processes; Basel and Stockholm convention Dr. Kåre Helge Karstensen (khk@sintef.no) Chief scientist, Foundation for Scientific and Industrial Research (SINTEF), Norway,

More information

Waste to Energy Options in Developing Countries: The GIZ Perspective

Waste to Energy Options in Developing Countries: The GIZ Perspective Waste to Energy Options in Developing Countries: The GIZ Perspective Experts meeting ADB GIZ September 28, 2016 Frankfurt/Manila Page1 Content 1. Brief introduction to GIZ 2. Presentation of the forthcoming

More information

Executive Brief for NAMA Consultation Workshop

Executive Brief for NAMA Consultation Workshop Executive Brief for NAMA Consultation Workshop Nationally Appropriate Mitigation Action (NAMA) programme in the Waste Sector: Waste to Resources for Cities in Vietnam Hanoi, Vietnam, 26 November 2013 1

More information

Issues in Municipal Waste to Energy

Issues in Municipal Waste to Energy Issues in Municipal Waste to Energy K. Kasturirangan Member, Planning Commission August 27, 2013 Trivandrum Status Generation - As per Central Pollution Control Board report of 2012, 1,30,562 TPD of MSW

More information

IRELAND S CEMENT INDUSTRY AND ALTERNATIVE FUELS

IRELAND S CEMENT INDUSTRY AND ALTERNATIVE FUELS IRELAND S CEMENT INDUSTRY AND ALTERNATIVE FUELS CEMENT MANUFACTURERS IRELAND Cement Manufacturers Ireland was established as a business association in Ibec in 2003 and has three members in the Republic

More information

No Compromise on Quality is Critical to Solid Recovered Fuel Production in Cyprus

No Compromise on Quality is Critical to Solid Recovered Fuel Production in Cyprus No Compromise on Quality is Critical to Solid Recovered Fuel Production in Cyprus Professor Stephen R Smith, Department of Civil and Environmental Engineering Dr Iakovos Skourides, Vassiliko Cement Works

More information

Application of Pre- and Co-Processing in Cement Production

Application of Pre- and Co-Processing in Cement Production A GIZ-Holcim Public Private Partnership managed by FHNW Version v3.1 Contact e-mail theo.lang@solnet.ch Date 31.01.2011 Introduction Alternative raw materials and fuels are waste-derived mineral and organic

More information

Co-processing technology

Co-processing technology Co-processing technology by Geocycle Thailand Nuchida Rungthawornwong 29 th October, 2013 Waste Management Hierarchy Resource Recovery Co-processing is ranked between recycle and incineration /landfill.

More information

ANALYSIS OF FIRST WASTE-TO-ENERGY PLANT PRODUCTION LINE AT KUNDA NORDIC CEMENT AS

ANALYSIS OF FIRST WASTE-TO-ENERGY PLANT PRODUCTION LINE AT KUNDA NORDIC CEMENT AS 7th International DAAAM Baltic Conference "INDUSTRIAL ENGINEERING 22-24 April 2010, Tallinn, Estonia ANALYSIS OF FIRST WASTE-TO-ENERGY PLANT PRODUCTION LINE AT KUNDA NORDIC CEMENT AS Jõgi, G.; Bashkite,

More information

Waste to Energy Plan. MSW, Biomass, Medical Waste, and Toxic Waste RBC Group BV Hofstede 47 Lienden Holland Tel :

Waste to Energy Plan. MSW, Biomass, Medical Waste, and Toxic Waste RBC Group BV Hofstede 47 Lienden Holland Tel : Waste to Energy Plan MSW, Biomass, Medical Waste, and Toxic Waste RBC Group BV Hofstede 47 Lienden Holland Tel : 0031344 604574 1 How would we further develop the proposition into a viable project? Via

More information

MARSS Workshop. Prof. Dr. Ing. Thomas Pretz

MARSS Workshop. Prof. Dr. Ing. Thomas Pretz MARSS Workshop Prof. Dr. Ing. 06.10.2014 RegEnt as the core of the project - is an association of municipalities in the Trier region with about 520.000 inhabitants in an area of about 5.000 km² - is always

More information

Circular Economy: Spent Pot Lining an Alternate Fuel In Cement Industries

Circular Economy: Spent Pot Lining an Alternate Fuel In Cement Industries 3 rd International Conference on ALTERNATE FUELS AND RAW MATERIALS IN CEMENT INDUSTRY Organized by Cement Manufacturers Association India 23-24 th March, 2017 Circular Economy: Spent Pot Lining an Alternate

More information

James L. Stewart Chairman, BioEnergy Producers Association Waste Conversion Technology Conference August 23, 2017

James L. Stewart Chairman, BioEnergy Producers Association Waste Conversion Technology Conference August 23, 2017 James L. Stewart Chairman, BioEnergy Producers Association Waste Conversion Technology Conference August 23, 2017 I have served the industry as Chairman of the BioEnergy Producers Association since its

More information

Submission on the Draft Regional Waste Management Plans Connacht-Ulster Region Eastern-Midlands Region Southern Region

Submission on the Draft Regional Waste Management Plans Connacht-Ulster Region Eastern-Midlands Region Southern Region Submission on the Draft Regional Waste Management Plans 2015-2021 Connacht-Ulster Region Eastern-Midlands Region Southern Region from Cement Manufacturers Ireland January 2015 1 CEMENT MANUFACTURERS IRELAND

More information

My Home Industries Pvt Ltd., (An ISO 9001:2008, ISO 14001:2004 and OHSAS Certified Company) Mellacheruvu Nalgonda District (Telangana)

My Home Industries Pvt Ltd., (An ISO 9001:2008, ISO 14001:2004 and OHSAS Certified Company) Mellacheruvu Nalgonda District (Telangana) My Home Industries Pvt Ltd., (An ISO 9001:2008, ISO 14001:2004 and OHSAS -18001 Certified Company) Mellacheruvu 508 246 Nalgonda District (Telangana) Company Profile My Home Industries Pvt Ltd (MHIPL)

More information

STATUS OF CO-PROCESSING OF WASTE IN CEMENT PLANTS AS PER HAZARDOUS AND OTHER WASTES MANAGEMENT RULES, Dr B Sengupta,

STATUS OF CO-PROCESSING OF WASTE IN CEMENT PLANTS AS PER HAZARDOUS AND OTHER WASTES MANAGEMENT RULES, Dr B Sengupta, STATUS OF CO-PROCESSING OF WASTE IN CEMENT PLANTS AS PER HAZARDOUS AND OTHER WASTES MANAGEMENT RULES, 2016 Dr B Sengupta, Former Member Secretary, Central Pollution Control board bsg161@gmail.com Presented

More information

Co-processing of AFR in Indian cement industry- NCB experiences

Co-processing of AFR in Indian cement industry- NCB experiences Co-processing of AFR in Indian cement industry- NCB experiences Rabindra Singh, A K Mishra, S K Chaturvedi, Rayees Ahmed and O P Grover National Council for Cement and Building Materials, India 1.0 Abstract

More information

The DGA MBT Mechanical Bio-Treatment System

The DGA MBT Mechanical Bio-Treatment System DGA Co Ltd present The DGA MBT Mechanical Bio-Treatment System Many systems use membranes to let water vapour out and to prevent water entering a warm compost pile. Most of the moisture is removed within

More information

Significance, Achievements & Benefits of Co-processing

Significance, Achievements & Benefits of Co-processing Significance, Achievements & Benefits of Co-processing Gujarat Pollution Control Board Hardik Shah, IAS Member Secretary Gujarat Pollution Control Board 1 Content Concept and history of co-processing Role

More information

Mechanical Biological Treatment (MBT) As A Strategy For Zero Waste To Landfills. Gershman, Brickner & Bratton Inc. 1. Outline

Mechanical Biological Treatment (MBT) As A Strategy For Zero Waste To Landfills. Gershman, Brickner & Bratton Inc. 1. Outline Mechanical Biological Treatment (MBT) As A Strategy For Zero Waste To Landfills Gershman, Brickner & Bratton, Inc. August 26, 2014 Outline GBB Overview History of the MBT in Europe Tour Pohlsche Heide,

More information

GASIFICATION THE WASTE-TO-ENERGY SOLUTION SYNGAS WASTE STEAM CONSUMER PRODUCTS TRANSPORTATION FUELS HYDROGEN FOR OIL REFINING FERTILIZERS CHEMICALS

GASIFICATION THE WASTE-TO-ENERGY SOLUTION SYNGAS WASTE STEAM CONSUMER PRODUCTS TRANSPORTATION FUELS HYDROGEN FOR OIL REFINING FERTILIZERS CHEMICALS GASIFICATION THE WASTE-TO-ENERGY SOLUTION WASTE SYNGAS STEAM CONSUMER PRODUCTS HYDROGEN FOR OIL REFINING TRANSPORTATION FUELS CHEMICALS FERTILIZERS POWER SUBSTITUTE NATURAL GAS W W W. G A S I F I C A T

More information

French Experience in waste recovery in cement kilns

French Experience in waste recovery in cement kilns French Experience in waste recovery in cement kilns Dominique Bernard SVP Industrial Ecology 1 ) Worldwide leader in Building materials N 1 in Cement and Roofing N 2 in Aggregates and Concrete N 3 in Gypsum

More information

AFR use at Dalmia Cement

AFR use at Dalmia Cement AFR use at Dalmia Cement By Sanjay Jain AED Technical Services, Dalmia Cement Dalmia Cement Ariyalur Plant Dalmia Cement - Brief introduction www.justlimateaction.org 2 Dalmia Cement (Bharat) Limited A

More information

The decisions of the Ministry as per the agenda are as follows:

The decisions of the Ministry as per the agenda are as follows: Minutes of 38 th meeting of the Technical Review Committee (TRC) under the Hazardous Waste (Management, Handling and Trans-boundary Movement) Rules, 2008 held on 23 rd July 2015 under the chairmanship

More information

THE POSSIBILITY OF ENERGY RECOVERY FROM SPECIFIC WASTE STREAMS IN CYPRUS

THE POSSIBILITY OF ENERGY RECOVERY FROM SPECIFIC WASTE STREAMS IN CYPRUS THE POSSIBILITY OF ENERGY RECOVERY FROM SPECIFIC WASTE STREAMS IN CYPRUS A. MENTZIS*, A. KARKAZI*, N. GARGOULAS*, S. SKOULAXINOU* AND N. KYTHREOTOU * EPEM SA, 141b Acharnon Str., 104 46, Athens, Greece

More information

BUSINESS PLAN CEN/TC 343 SOLID RECOVERED FUELS EXECUTIVE SUMMARY

BUSINESS PLAN CEN/TC 343 SOLID RECOVERED FUELS EXECUTIVE SUMMARY Page: 1 BUSINESS PLAN CEN/TC 343 SOLID RECOVERED FUELS EXECUTIVE SUMMARY CEN/TC 343 is established to develop the relevant European Standards for the market for solid recovered fuels. The scope is: Elaboration

More information

Municipal Solid Waste To Energy Project Overview

Municipal Solid Waste To Energy Project Overview Cleveland s s Energy Future Municipal Solid Waste To Energy Project Overview February 26, 2010 Department of Public Service Division of Waste Collection Agenda Page Introduction...... 3 1. MSW to Electric

More information

Thermal Treatment. For more information, contact us: E :

Thermal Treatment. For more information, contact us:   E : Thermal treatment is the release of energy from waste. This results in a change to the chemical structure of the waste and this change is not reversible 1. The most common thermal treatment is incineration.

More information

SGS, LLC s mission is to market, build, implement, and operate or sell waste-to-energy systems in the USA and other worldwide locations based on

SGS, LLC s mission is to market, build, implement, and operate or sell waste-to-energy systems in the USA and other worldwide locations based on Waste to Energy SGS, LLC s mission is to market, build, implement, and operate or sell waste-to-energy systems in the USA and other worldwide locations based on proven, proprietary, and efficient solid

More information

WASTE TO ENERGY (W2E) AS THE MODERN CONCEPT OF WASTE MANAGEMENT

WASTE TO ENERGY (W2E) AS THE MODERN CONCEPT OF WASTE MANAGEMENT WASTE TO ENERGY (W2E) AS THE MODERN CONCEPT OF WASTE MANAGEMENT Marta Starostka-Patyk Czestochowa University of Technology, Faculty of Management, Armii Krajowej 19B, 42-200 Czestochowa, Poland Abstract

More information

By: Hardik Shah Member Secretary J K Vyas Sr. Env. Engineer, HAZ Unit Gujarat Pollution Control Board

By: Hardik Shah Member Secretary J K Vyas Sr. Env. Engineer, HAZ Unit Gujarat Pollution Control Board By: Hardik Shah Member Secretary J K Vyas Sr. Env. Engineer, HAZ Unit Gujarat Pollution Control Board Structure of Presentation The State of Gujarat Incinerable Hazardous Waste Generation Scenario in India

More information

Dr B Sengupta Former Member Secretary Central Pollu(on Control board

Dr B Sengupta Former Member Secretary Central Pollu(on Control board Dr B Sengupta Former Member Secretary Central Pollu(on Control board & Dr K.R. Ranganathan Former Member Secretary Central Pollu(on Control board Presenta(on at Ist Interna(onal Conference on Enhanced

More information

Opportunities and Challenges Waste to Energy Industry

Opportunities and Challenges Waste to Energy Industry Opportunities and Challenges Industry IMIA Conference, Istanbul September 2009 Mike Robertson Liberty International Underwriters Opportunities and Challenges Industry Dynamics and Profile Key Process Features

More information

HOW PYROLYSIS WASTE TO ENERGY WORKS

HOW PYROLYSIS WASTE TO ENERGY WORKS HOW PYROLYSIS WASTE TO ENERGY WORKS The use of pyrolysis in the thermal processing of municipal solid waste is becoming more widespread in application due to the overall flexibility of the pyrolysis process.

More information

ACM0001 Flaring or use of landfill gas

ACM0001 Flaring or use of landfill gas ACM0001 ACM0001 Flaring or use of landfill gas Women and children Capture of landfill gas (LFG) and its flaring and/or use to produce energy and/or use to supply consumers through natural gas distribution

More information

ENVIRONMENTAL REGULATIONS AND MANAGEMENT OF SPENT POT LINING (SPL) WASTE GENERATED FROM ALUMINIUM INDUSTRY. Dr. B. Sengupta

ENVIRONMENTAL REGULATIONS AND MANAGEMENT OF SPENT POT LINING (SPL) WASTE GENERATED FROM ALUMINIUM INDUSTRY. Dr. B. Sengupta ENVIRONMENTAL REGULATIONS AND MANAGEMENT OF SPENT POT LINING (SPL) WASTE GENERATED FROM ALUMINIUM INDUSTRY Dr. B. Sengupta Former Member Secretary Central Pollution Control Board Email: bsg161@gmail.com

More information

Energy Recovery from Alternative Fuels (AF) The Swiss Experience

Energy Recovery from Alternative Fuels (AF) The Swiss Experience Energy Recovery from Alternative Fuels (AF) The Swiss Experience Content The situation in Switzerland The steps to implement AF usage The Swiss agreement for AF burning Technical aspects Quality aspects

More information

ACM0001 Flaring or use of landfill gas

ACM0001 Flaring or use of landfill gas ACM0001 ACM0001 Flaring or use of landfill gas Women and children Capture of landfill gas (LFG) and its flaring and/or use to produce energy and/or use to supply consumers through natural gas distribution

More information

City of Sydney Gasification Project

City of Sydney Gasification Project APPENDIX I City of Sydney Gasification Project Master Planning Energy from Waste Mark McKenzie Senior Policy Officer Waste Local Government NSW mark.mckenzie@lgnsw.org.au (former Manager Waste Strategy,

More information

Re: EBR Registry Number (Draft Strategy for a Waste- Free Ontario: Building the Circular Economy) and (Waste Free Ontario Act)

Re: EBR Registry Number (Draft Strategy for a Waste- Free Ontario: Building the Circular Economy) and (Waste Free Ontario Act) February 29, 2016 Shari Sookhoo Senior Policy Coordinator Ministry of the Environment and Climate Change Climate Change and Environmental Policy Division Resource Recovery Policy Branch 40 St. Clair Avenue

More information

Lagan Cement Kinnegad

Lagan Cement Kinnegad Lagan Cement Kinnegad Lagan Cement: An Introduction Lagan s experience with alternative fuels Availability of SRF Feedstock Market Demands/IE & EU Lagan Cement importing cement into Belfast N. Ireland

More information

Waste management in the Netherlands. Herman Huisman RWS Environment

Waste management in the Netherlands. Herman Huisman RWS Environment Waste management in the Netherlands Herman Huisman RWS Environment Vancouver, July 21-22 2014 The Netherlands 17 million Inhabitants 40.000 km2 7,4 million households 12 provinces 400 Municipalities 60

More information

Status of Waste Management and Future Policy Directions for Renewable Energy From Waste and Biomass in Thailand

Status of Waste Management and Future Policy Directions for Renewable Energy From Waste and Biomass in Thailand Expert Group Meeting on Sustainable Application of Waste-to-Energy in Asian Region Status of Waste Management and Future Policy Directions for Renewable Energy From Waste and Biomass in Thailand Somrat

More information

Refuse Derived Fuel (RDF) Utilization in Cement Industry by Using Analytic Network Process (ANP)

Refuse Derived Fuel (RDF) Utilization in Cement Industry by Using Analytic Network Process (ANP) CHEMICAL ENGINEERING TRANSACTIONS Volume 21, 2010 Editor J. J. Klemeš, H. L. Lam, P. S. Varbanov Copyright 2010, AIDIC Servizi S.r.l., ISBN 978-88-95608-05-1 ISSN 1974-9791 DOI: 10.3303/CET1021129 769

More information

Treatment of Distillery Spent wash. Babu Alappat Professor Department of Civil Engineering I.I.T Delhi.

Treatment of Distillery Spent wash. Babu Alappat Professor Department of Civil Engineering I.I.T Delhi. Treatment of Distillery Spent wash Babu Alappat Professor Department of Civil Engineering I.I.T Delhi bjalappat@yahoo.com Problems with Anaerobic Systems Requirement of polishing Uncertainity involved

More information

Adelaide Brighton Ltd. Wood and Waste Fired Kilns

Adelaide Brighton Ltd. Wood and Waste Fired Kilns Adelaide Brighton Ltd Wood and Waste Fired Kilns Michael Jones CMIC Conference - October 2006 1 Introducing Adelaide Brighton NORTHERN CEMENT Cement MATARANKA LIME Lime DONGARA LIME Lime COCKBURN CEMENT

More information

PRE- PROCESSING OF HAZARDOUS WASTE ADVANCES & EXPERIANCES BY: PRIYESH BHATTI GEPIL

PRE- PROCESSING OF HAZARDOUS WASTE ADVANCES & EXPERIANCES BY: PRIYESH BHATTI GEPIL PRE- PROCESSING OF HAZARDOUS WASTE ADVANCES & EXPERIANCES BY: PRIYESH BHATTI GEPIL Pre-processing Facility (PPF) is a Preparatory or Pretreatment Unit For Final Treatment called Co-Processing DIRECT CO-PROCESSING

More information

City Report. (Draft) < Shimla, India>

City Report. (Draft) < Shimla, India> Eighth Regional 3R Forum in Asia and the Pacific Achieving Clean Water, Clean Land and Clean Air through 3R and Resource Efficiency- A 21 st Century Vision for Asia-Pacific Communities Indore, Madhya Pradesh,

More information

GIZ Support to Ministry of Urban Development Training on Preparation of City Sanitation Plan Part III State of Telangana

GIZ Support to Ministry of Urban Development Training on Preparation of City Sanitation Plan Part III State of Telangana GIZ Support to Ministry of Urban Development Training on Preparation of City Sanitation Plan Part III State of Telangana Session 3B: Technical Options for CSPs Hyderabad, 20-22 April 2016 Slide 1 Technological

More information

Possibilities of the cement industry to support Serbian Waste Management Strategy

Possibilities of the cement industry to support Serbian Waste Management Strategy CEMENT DIVISION Possibilities of the cement industry to support Serbian Waste Management Strategy Christian Lampl Lafarge BFC Content What is co-processing? Lafarge experience in co-processing Potentials

More information

Preparation of City Sanitation Plan Part III. Session 2: Technical Options for CSPs

Preparation of City Sanitation Plan Part III. Session 2: Technical Options for CSPs Preparation of City Sanitation Plan Part III Session 2: Technical Options for CSPs Slide 1 Technological options for On-site Sanitation systems Septic Tank with Soak pit Twin-Pit Latrine Bio-Digester DRDO

More information

Thailand s Master Plan for MSWManagement

Thailand s Master Plan for MSWManagement Thailand s Master Plan for MSWManagement Developments of Energy, Environment and Ecosystems (3E) Nexus Initiative for Sustainable Development in Asian Countries 18-19 th January 2017 Tokyo, Japan Outline

More information

CASE STUDY 15: JOURNEY TOWARDS ZERO FUEL COST - ACC LTD., MADUKKARAI CEMENT WORKS. Company Details. Project Details. Process Description

CASE STUDY 15: JOURNEY TOWARDS ZERO FUEL COST - ACC LTD., MADUKKARAI CEMENT WORKS. Company Details. Project Details. Process Description CASE STUDY 15: JOURNEY TOWARDS ZERO FUEL COST - ACC LTD., MADUKKARAI CEMENT WORKS Project Implemented by : ACC Ltd, Madukkarai Cement works Project Implemented in : 2007 Company Details ACC Limited is

More information

Spent Pot Liner Utilization in Cement Industry Steel Industry

Spent Pot Liner Utilization in Cement Industry Steel Industry Spent Pot Liner Utilization in Cement Industry Steel Industry By: Nitin Kumar Tiwari Head Operations (Line 5 & Line 6) VAL,Jharsuguda 07 th Mar 2018 1 Author s vision towards Sustainable India Creation/amendments

More information

Samsung Requirements for WEEE Managing

Samsung Requirements for WEEE Managing Samsung Requirements for WEEE Managing 1. Purpose These requirements aim to minimize environmental impacts caused by all Electronic Waste generated by Samsung's global operations and programs, including,

More information

European and German Waste Policy

European and German Waste Policy European and German Waste Policy Alexander Neubauer Ecologic Institute Table of content Definition of Waste European Waste Legislation as Framework Waste Management (General) Waste Treatment Legislation

More information

Increasing the Quantity and Quality of Metals Recovered at Waste-to Energy Facilities

Increasing the Quantity and Quality of Metals Recovered at Waste-to Energy Facilities Increasing the Quantity and Quality of Metals Recovered at Waste-to Energy Facilities Werner Sunk Earth Engineering Center, Columbia University NAWTEC 14, Tampa, FL, May 2006 Background Waste-To-Energy

More information

Standards for SRF what comes next?

Standards for SRF what comes next? Standards for SRF what comes next? Recombio Final Conference Helsinki, 13 June 2013 1 ERFO European Recovered Fuel Organisation; a non profit association, with members from : BE, NL, DE, ES, FR, UK, IT,

More information

Analysis of Energy Contained in Domestic Solid Waste

Analysis of Energy Contained in Domestic Solid Waste Analysis of Energy Contained in Domestic Solid Waste Co-Author Harsh Gupta Assistant Professor Department of Mechanical Engineering I.T.S Engineering College, Greater Noida moveharsh@rediffmail.com Puneet

More information

CEWEP Country Report 2016

CEWEP Country Report 2016 CEWEP Country Report 206 Finland Company Report: Finnish Solid Waste Association (JLY, Jätelaitosyhdistys) for the Westenergy Ltd Wte plant and also for the country information (in cooperation with Ekokem

More information

Appraisal for options of solid recovered fuel (SRF) utilisation within. the UK

Appraisal for options of solid recovered fuel (SRF) utilisation within. the UK Appraisal for options of solid recovered fuel (SRF) utilisation within the UK D. Hill, A. Garg, R. Smith, S.J.T. Pollard, P. Longhurst Centre for Resource Management and Efficiency, Sustainable Systems

More information

Re-use of waste Recycling of waste Recovery of waste Use of waste as source of energy Incineration without energy recovery

Re-use of waste Recycling of waste Recovery of waste Use of waste as source of energy Incineration without energy recovery 2.9 THE FRAMEWORK DIRECTIVE ON WASTE Official Title: Council Directive 75/442/EEC on waste, as amended by Council Directive 91/156/EEC. 2.9.1 INTRODUCTION Page 1 The Framework Directive on Waste establishes

More information

Fuel preparation Phil White, MCIWM

Fuel preparation Phil White, MCIWM Fuel preparation Phil White, MCIWM Introduction: Fuel preparation Primary fuel for thermal WtE Untreated residual MSW and commercial waste Conventional grate WtE copes with a wide range Other WtE requires

More information

Technical Presentation on Spent Pot lining Management & Red Mud

Technical Presentation on Spent Pot lining Management & Red Mud Technical Presentation on Spent Pot lining Management & Red Mud 0 Bharat Aluminium Company Ltd, Korba & Vedanta limited, Jharsuguda & Lanjigarh OUR PRESENCE 1 Jharsuguda Smelter Capacity 3,615 MW 1.75

More information

Classification of Waste Treatment Operations

Classification of Waste Treatment Operations Classification of Waste Treatment Operations Brigitte Karigl, Environmental Agency Austria Ellen Gerlach, Environmental Protection Agency Sachsen-Anhalt Workshop, 22.06.2016 Activity M 60/1 1 Content of

More information

Waste-to-Energy : Optimum utilization of Commercial kitchen waste to generate energy

Waste-to-Energy : Optimum utilization of Commercial kitchen waste to generate energy Dissertation Topic Waste-to-Energy : Optimum utilization of Commercial kitchen waste to generate energy PRESENTED BY: SONAL KOTKAR ; Sem IV INTRODUCTION FOOD WASTE FACTS! Globally 1/3 food produced is

More information

The Nexus: Waste Management, Environment &Health

The Nexus: Waste Management, Environment &Health The Nexus: Management, Environment &Health 70 Million TPA of waste generated in urban centers is estimated to more than double by 2031 to 165 Mil.TPA. Only 10% is processed Around 25% of Particulate Matter

More information

european suppliers OF Waste-tO-eNergy technology everything you always WaNteD to KNOW about Waste-tO-eNergy

european suppliers OF Waste-tO-eNergy technology everything you always WaNteD to KNOW about Waste-tO-eNergy european suppliers OF Waste-tO-eNergy technology everything you always WaNteD to KNOW about Waste-tO-eNergy WWW.ESWET.Eu ConTEnTS 4 What is Waste-to-Energy? 6 How does it work? 8 Waste-to-Energy is clean.

More information

GORE COVER FOR RECYCLING PARKS

GORE COVER FOR RECYCLING PARKS GORE COVER FOR RECYCLING PARKS RECYCLING PARK: THE INTEGRATED APPROACH TO A COMPREHENSIVE WASTE TREATMENT PROGRAMME All waste streams collected in one plant for subsequent processing Source Separated Organics

More information

Hamm MW Pyrolysis Plant. Integrated Pyrolysis into Power Plant Plant capacity 100,000 t/a Pre-processed Waste Materials

Hamm MW Pyrolysis Plant. Integrated Pyrolysis into Power Plant Plant capacity 100,000 t/a Pre-processed Waste Materials Integrated Pyrolysis into Power Plant Plant capacity 100,000 t/a Pre-processed Waste Materials Schematic Flow sheet Integrated Pyrolysis for Power Plants Pyrolysis of high calorific solid recovered fuels