1 Township of Southgate Dundalk Wastewater Treatment Plant 2014 Annual Report Jim Ellis Public Works Manager

2 Dundalk Wastewater Treatment Plant 2014 Annual Report Table of Contents Wastewater Treatment Plant Annual Overview General Wastewater Information. 4 Loading Report.. 5 Performance Report.. 6 Final Effluent Discharge Report 7 Raw Sewage Parameters and Lab Results. 8 Final Effluent Parameters and Lab Results. 9

3 Overview: The Dundalk Wastewater Treatment Plant (WWTP) provided treatment in 2014 with all effluent concentrations limits being met on an annual average. The annual average influent daily flow was 996 m³/day. Project Description: The Dundalk WWTP is a four cell waste stabilization pond facility flowing into an aeration cell pond with a chemical feed system and a flocculation tank with tertiary treatment consisting of sand filters. Plant Facts: Facilities: Design Capacity: Receiver Water: Environmental Compliance Approval: Effluent Requirements: Sampling Requirements: Waste Stabilization Ponds with Tertiary Treatment 1832 m³/day Foley Drain/Grand River D9LYE CBOD SS DO T.Phos. when temperature >5 C T.Phos. when temperature <5 C Unionized Ammonia mg/l 10 mg/l 10 mg/l 4 mg/l 0.4 mg/l 0.8 mg/l 0.1 mg/l Sampling criteria for this system is in accordance with Ministry policy and the Environmental Compliance Approval (ECA) Final Effluent: A grab sample is taken bi-weekly and tested for CBOD, Suspended Solids, Total Phosphorus, Total Ammonia Nitrogen, Ecoli, ph and temperature. On site testing is performed twice a week on final effluent for Total Ammonia to determine Unionized Ammonia through lab testing, ph, temperature and Dissolved Oxygen. Raw Sewage: A grab sample is taken monthly and tested for BOD, Suspended Solids, Total Kjeldahl Nitrogen and Total Phosphorus. Effluent Flows: The total effluent flow treated in 2014 was 494,185 m³. The annual average daily flow was 1,636 m³/day, which results in a 2.33% decrease of total effluent over

4 Raw Sewage Quality: Annual average raw sewage BOD concentration to the lagoon system was 110 mg/l. Annual average raw sewage suspended solids (TSS) concentration to the lagoon system was 152 mg/l. Annual average raw total phosphorus was 3.04 mg/l concentration to the lagoon system. Annual average Total Kjeldahl Nitrogen (TKN) concentration was 29.2 mg/l. Plant Performance and Effluent Quality: Annual average effluent CBOD concentration was 3.0 mg/l. Annual average effluent total suspended solids (TSS) concentration was 3.6 mg/l day with a removal efficiency of % with an annual monthly average loading of 5.9 kg/day. Annual average effluent total phosphorus concentration was 0.21 mg/l day with a removal efficiency of 91.56% with an annual monthly average loading of 0.3 kg/day. Annual average effluent concentration for Ammonia-nitrogen was 4.07 mg/l. Annual average Unionized Ammonia was mg/l. Annual average ph was Annual monthly average Ecoli was 736 with the low being 0 and the high being The summary for 2014 of the data for the systems plant operation performance is enclosed in this report. Maintenance and Calibration Activities: Regular monthly preventative maintenance and calibration of test equipment and flow meters are performed by municipal staff and outside certified companies. 2

5 Discussion: There were three by-pass events to report: 1. March 20, 2014 staff reported to the Spills Action Centre (SAC), Grey-Bruce Health Unit, Grand River Conservation Authority (GRCA) and MOE Wastewater Inspector Shayne Finlay a spill and by-pass at the Dundalk Sewage Works. The spill incident was discovered that morning by a Township operator when he observed water running out the north man door at the filter building. The by-pass was due to water flooding over the floor and dumping into the effluent tank. Grey-Bruce Health Unit Inspector James Reason stated no further action was required downstream users were contacted by SAC and the GRCA, with minimal impact to users because of upstream reservoirs.. A number of valves and controls were submerged and were investigated by Dewar Services. 2. On March 31, 2014 staff reported to the Spills Action Centre (SAC), Grey- Bruce Health Unit, Grand River Conservation Authority (GRCA) and MOE Wastewater Inspector Shayne Finlay an overflow and by-pass at the Dundalk Sewage Works. This incident is similar to March 20 th, The overflow incident was discovered that morning by a Township operator when he observed water running out the north man door at the filter building. The bypass was due to water flooding over the floor and dumping into the effluent tank. Downstream users were contacted by SAC and the GRCA, with minimal impact to users because of upstream reservoirs. Triton Engineering and Napier Reid were on site to modify PLC code to have pumps shut off under certain criteria. The flood alarm and pager call out mechanisms are now functioning. Triton has recommended in changing out the filter media. 3. On June 16, 2014 the wet well pumps were placed out of service for the upgrades. Sewage was bypassing cells 1 and 2 and flowing into cells 3 and 4 as per the design of the Lagoon system. On August 28, 2014 Effluent Toxicity testing was completed and sample results indicated a 0% mortality rate. There were four operator shutdowns in 2014: 1. On March 20, 2014 a shutdown was completed for the entire weekend to dry out all of the electrical components that were effected from the flooding on March 20, On March 31, 2014 a shutdown was completed for the day to dry out all of the electrical components that were effected from the flooding on March 31, On June 5, 2014 a shutdown was completed for the beginning of the wastewater facilities upgrades and resumed August 5, 2014 after the upgrades were completed. 4. On November 8, 2014 a system shut down was completed because the filters were overflowing into the waste tank, valve malfunctioning running on manual shut down for weekend. 3

6 The Influent annual flow in 2014 has decreased 54.89% over 2013 flows. On June 6, 2014 Triton Engineering Services Limited sent the Township a letter outlining the reserve capacity calculations using the Ministry of Environments calculation Procedure D-5-1 Calculating and Reporting Uncommitted Reserve Capacity at Sewage and Water Treatment Plants. Staff report was submitted to council June 18, 2014 requesting the endorsement of the report for the Dundalk Water and Sewage Treatment Reserve Capacity as prepared by Triton Engineering Services Ltd. The report also recommending the support of a 40% reduction to the 2013 influent flows for the Sewage Treatment System as calculated by Triton. The MOE accepted this with monitoring conditions that 2014 flows return to normal. In 2014 the Township had 1 major infrastructure project completed. The Wastewater department with Triton Engineering Service Limited issued a Request for Tender in the fall of 2013 for upgrades to the Wastewater Facilities. Triton Engineering endorsed the recommendation to council Wednesday, November 20, 2013 to award Finnbilt General Contracting Limited the upgrades to Dundalk Sewage Lagoon which was accepted by council. The Township had received an Amended Environmental Compliance Approval from the Ministry of Environment to proceed with the upgrades. The upgrades that have been completed are: Pumping Station: 50 kw diesel generator to provide standby power for the raw sewage pumping station. Control building to house raw sewage pump control equipment, generator automatic transfer switch and other necessary electrical equipment. The Wet Well was upgraded with a VFD control of motors. Piping replaced. Transducers. Post Aeration Cell and Blower Building Replaced blower control equipment with rotary positive displacement blowers with VFD control. Tertiary Treatment Filter Building Dissolved oxygen monitoring equipment for blower control. Air pumping and fine bubble air diffusers in the effluent channel. Replacement of Filter Media. The Township requested an extension for a by-pass relief as a precautionary measure from the MOE dated July 18 th, 2014 due to a delay on the replacement of the filter media. The Township didn t require this extension. On July 14, 2014 an MOE Inspector completed a physical inspection. The inspection report received 3 non-compliance from past practice without any actions required. The Township received an Amended Environmental Compliance Approval from the MOE December 2, 2013 indicating that the effluent monitoring is to change from BOD to CBOD effective February

7 Township of Southgate - Village of Dundalk 2014 General Wastewater Information Plant # : C of A # : GYHR7 Population: 1691 (Village of Dundalk) Flows Design Capacity: 208, Influent Average Daily: - m ,221 1,183 1,164 1,020 1,217 1,482 Annual Influent Flow: 668,600 m3 364, , , , , , ,455 Influent Maximum Daily: - m3 2,873 3,991 3,926 4,453 4,390 4,258 4,577 Effluent Average Daily: 1,832 m3 1,636 1,394 1,136 1,332 1,245 1,466 1,631 Annual Effluent Flow: - m3 494, , , , , , ,173 % Discharge vs. Total Capacity: % 75.7% 55.2% 65.2% 65.0% 80.0% 89.3% Influent Decrease 2014 over 2013: % 86.14% 2.06% 14.33% % % 35.54% Effluent Decrease 2014 over 2013: % 36.99% % 0.30% % % 62.28% 4

8 Township of Southgate Loading Report - Dundalk Wastewater Plant Municipality: Township of Southgate Year: 2014 Plant: Dundalk Wastewater Treatment Lagoons & Collection System Plant # : Works # : System Description : Faculative Lagoons & Sand Filters Loading Influent Effluent Loading Effluent Effluent Effluent BOD SS T Phos. BOD SS T Phos. Month kg/day kg/day kg/day kg/day kg/day kg/day January February March April May June July August September October November December Total Average Maximum

9 Township of Southgate Performance Report - Dundalk Wastewater Plant Municipality: Township of Southgate Plant: Dundalk Wastewater Treatment Lagoons & Collection System Year: 2014 Plant # : Receiver: Foley Drain - Grand River Works # : Design Average Day Flow (m3): 1832 System Description : Faculative Lagoons & Sand Filters Flows Discharge Bio-Chemical Oxygen Demand Suspended Solids Phosphorus E Coli Temperature Nitrogen Series Loading Raw Effluent Duration Avg. Raw Avg. Effluent Avg Effluent Percent Avg. Raw Avg. Effluent Percent Avg. Raw Avg. Effluent Percent average < 5 C. TKN Avg. Effluent Unionized Effluent Effluent Effluent Total Flow Avg. Flow Max. Flow Total Flow BOD BOD CBOD Removal SS SS Removal T. Phos T. Phos Removal Effluent or NH3 + NH4 Ammonia BOD SS T Phos. Month m3 m3 m3 m3 Days mg/l mg/l mg/l mg/l mg/l mg/l mg/l Count > 5 C. mg/l mg/l mg/l kg/day kg/day kg/day January % % % February % % % March % % % April % % % May % % % June % % % July % % % August % % % September % % % October % % % November % % % December % % % Total Average % % % Maximum

10 Township of Southgate Annual Report - Dundalk Wastewater Plant Plant: Dundalk Wastewater Treatment Lagoons & Collection System Works: Year: 2014 Location Type: Final Effluent Discharge Report Discharge Total Total Average Average Average Average Average E Coli Average Average Average Duration Effluent Coagulant Coagulant BOD SS T. Phos. NH3 + NH4 average ph Temp. D.O. Month Days m3 Used (kg) Dosage (mg/l) mg/l mg/l mg/l as N (mg/l) Count Lab Reports C mg/l January February March April May June July August September October November December Total Average Maximum

11 Township of Southgate - Village of Dundalk Annual Report - Dundalk Wastewater Plant Plant: Dundalk Wastewater Treatment Lagoons & Collection System Year: 2014 Works: Population Served: 1691 Classification: Class 1 Wastewater Collection & Class 1 Wastewater Treatment Receiver Foley Drain to Grand River Raw Sewage Parameters January February March April May June July August September October November December Summary Average BOD Minimum mg/l Maximum Suspended Average Solids Minimum mg/l Maximum Average TKN Minimum mg/l Maximum Total Average Phosphorus Minimum mg/l Maximum

12 Township of Southgate - Village of Dundalk Annual Report - Dundalk Wastewater Plant Plant: Dundalk Wastewater Treatment Lagoons & Collection System Year: 2014 Works: Population Served: 1691 Classification: Class 1 Wastewater Collection & Class 1 Wastewater Treatment Receiver Foley Drain to Grand River Final Effluent Parameters January February March April May June July August September October November December Summary Average BOD Minimum SGS mg/l Maximum SGS Average CBOD Minimum SGS mg/l Maximum SGS Suspended Average Solids Minimum SGS mg/l Maximum SGS Average NH3 + NH4 Minimum SGS mg/l Maximum SGS Average TKN Minimum SGS mg/l Maximum SGS Total Average Phosphorus Minimum SGS mg/l Maximum SGS Average Ecoli Minimum SGS Maximum SGS Average ph Minimum SGS Maximum SGS Average DO Minimum Unionized mg/l Maximum Unionized Unionized Average Ammonia Minimum Unionized mg/l Maximum Unionized 9

13 Township of Southgate Performance Report - Dundalk Wastewater Plant Municipality: Township of Southgate Plant: Dundalk Wastewater Treatment Lagoons & Collection System Year: 2014 Plant # : Receiver: Foley Drain - Grand River Works # : Design Average Day Flow (m3): 1832 Sysrem Description : Faculative Lagoons & Sand Filters Flows Discharge Bio-Chemical Oxygen Demand Suspended Solids Phosphorus E Coli Temperature Nitrogen Series Loading Loading Influent Raw (Influent) Effluent Duration Avg. Raw Avg. Effluent Avg. Effluent Percent Avg. Raw Avg. Effluent Percent Avg. Raw Avg. Effluent Percent average < 5 C. TKN Avg. Effluent Unionized Effluent Effluent Effluent Lab Local Dissolved Total Flow Avg. Flow Max. Flow Total Flow BOD BOD CBOD Removal SS SS Removal T. Phos T. Phos Removal Effluent or Raw NH3 + NH4 Ammonia CBOD SS T Phos. reason Down up CBOD SS T Phos. Tests Tests Oxygen-Eff. Month m3 m3 m3 m3 Days mg/l mg/l mg/l mg/l mg/l mg/l mg/l Count > 5 C. mg/l mg/l mg/l kg/day kg/day kg/day kg/day kg/day kg/day ph ph mg/l January % % % February % % % March % % % April % % % May % % % June % % % July % % % August % % % September % % % October % % % November % % % December % % %

Dundalk Wastewater Treatment Plant

Dundalk Wastewater Treatment Plant Township of Southgate Dundalk Wastewater Treatment Plant 2016 Annual Report Jim Ellis Public Works Manager Dundalk Wastewater Treatment Plant 2016 Annual Report Table of Contents Wastewater Treatment Plant

More information

Dundalk Wastewater Treatment Plant

Dundalk Wastewater Treatment Plant Township of Southgate Dundalk Wastewater Treatment Plant 2017 Annual Report Staff Report PW2018-010 - Dundalk Wastewater Treatment Plant 2017 Annual Report Moved by Councillor Pallister, Seconded by Councillor

More information

MUNICIPALITY OF WEST ELGIN WEST LORNE WASTEWATER TREATMENT PLANT

MUNICIPALITY OF WEST ELGIN WEST LORNE WASTEWATER TREATMENT PLANT MUNICIPALITY OF WEST ELGIN WEST LORNE WASTEWATER TREATMENT PLANT 214 ANNUAL REPORT uary 1 to ember 31, 214 Environmental Compliance Approval # 3-442-9-938 Prepared by: Table of Contents Section 1: Overview...

More information

MUNICIPALITY OF WEST ELGIN RODNEY WASTEWATER TREATMENT PLANT

MUNICIPALITY OF WEST ELGIN RODNEY WASTEWATER TREATMENT PLANT MUNICIPALITY OF WEST ELGIN RODNEY WASTEWATER TREATMENT PLANT 214 ANNUAL REPORT uary 1 to ember 31, 214 Environmental Compliance Approval # 3-871-88-949 Prepared by: Table of Contents Section 1: Overview...

More information

RE: Annual Report 2016 Wardsville Wastewater Treatment Plant and Collection System

RE: Annual Report 2016 Wardsville Wastewater Treatment Plant and Collection System 14 th, 217 Tom Clubb 3232 White Oak Road, 3 rd Floor London ON N6E 1L8 Attention: Mr. Clubb RE: Annual Report 216 Wardsville Wastewater Treatment Plant and Collection System The Ontario Clean Water Agency

More information

Feel free to contact me should you require any additional information regarding the report. I can be reached at

Feel free to contact me should you require any additional information regarding the report. I can be reached at February 28, 217 Tom Clubb 3232 White Oak Road, 3 rd Floor London ON N6E 1L8 Attention: Mr. Clubb RE: Annual Report 216 Glencoe Wastewater Treatment Plant The Ontario Clean Water Agency is the Operating

More information

BRACEBRIDGE WASTEWATER TREATMENT

BRACEBRIDGE WASTEWATER TREATMENT 2014 BRACEBRIDGE WASTEWATER TREATMENT ENVIRONMENTAL COMPLIANCE APPROVAL: #6801-7VKNAQ INTRODUCTION The Lagoon Lane Wastewater Treatment Plant is owned and operated by the District Municipality of Muskoka.

More information

BRACEBRIDGE WASTEWATER TREATMENT 2016 SUMMARY REPORT

BRACEBRIDGE WASTEWATER TREATMENT 2016 SUMMARY REPORT BRACEBRIDGE WASTEWATER TREATMENT 2016 SUMMARY REPORT ENVIRONMENTAL COMPLIANCE APPROVAL: 6801-7VKNAQ ENVIRONMENTAL COMPLIANCE APPROVAL: 6222-AFGSNY (Dec 16 2016) INTRODUCTION The Lagoon Lane Wastewater

More information

Yours very truly, Municipality of West Perth. Environmental Services

Yours very truly, Municipality of West Perth. Environmental Services January 30, 2018 Municipality of West Perth 169 St. David Street Mitchell, Ontario N0K 1N0 ATTENTION: Mr. Jeff Brick CAO REFERENCE: Municipality of West Perth Annual Wastewater Report 2017 Please find

More information

2017 Performance Report for Bobcaygeon Waste Water Treatment Facility

2017 Performance Report for Bobcaygeon Waste Water Treatment Facility 2017 Performance Report for Bobcaygeon Waste Water Treatment Facility Amended Environmental Certificate of Approval (ECA) #3028-AEUKDQ Section 11(4) requires the Performance Reports to contain the following:

More information

Bracebridge Wastewater Treatment 2017 Summary Report

Bracebridge Wastewater Treatment 2017 Summary Report Bracebridge Wastewater Treatment 2017 Summary Report Environmental Compliance Approval: 6222-AFGSNY (Dec 16 2016) INTRODUCTION The Lagoon Lane Wastewater Treatment Plant is owned and operated by the District

More information

Stonecrest Estates Sewage Treatment Plant 2017 Annual Report

Stonecrest Estates Sewage Treatment Plant 2017 Annual Report 2017 Stonecrest Estates Sewage Treatment Plant 2017 Annual Report The Corporation of the City of Quinte West 0 Contents Table of Figures... 1 Executive Summary... 3 Summary and Interpretation of Monitoring

More information

February 16, Ministry of the Environment Southwestern Region 733 Exeter Road London, Ontario N6E 1L3. Attn.: Mr. Tom Clubb

February 16, Ministry of the Environment Southwestern Region 733 Exeter Road London, Ontario N6E 1L3. Attn.: Mr. Tom Clubb February 16, 2018 Ministry of the Environment Southwestern Region 733 Exeter Road London, Ontario N6E 1L3 Attn.: Mr. Tom Clubb Re: Listowel 2017 Annual Report Please find enclosed the 2017 Annual Report

More information

2017 Annual Performance Report

2017 Annual Performance Report Newcastle Water Pollution Control Plant The Regional Municipality of Durham Newcastle Water Pollution Control Plant Environmental Compliance Approval (ECA): 3-2189-87-946 Dated July 26, 1994 Amendments:

More information

PORT SEVERN WASTEWATER TREATMENT 2016 SUMMARY REPORT

PORT SEVERN WASTEWATER TREATMENT 2016 SUMMARY REPORT PORT SEVERN WASTEWATER TREATMENT 2016 SUMMARY REPORT ENVIRONMENTAL COMPLIANCE APPROVAL: #3-0429-96-006 INTRODUCTION The Lone Pine Road Water Pollution Control Plant in Port Severn was a design / build

More information

2017 Annual Performance Report

2017 Annual Performance Report 2017 Annual Performance Report Thornbury Wastewater Treatment Plant and Associated Collection System Prepared by: Wastewater Operations Staff Reporting Period: January 1 December 31, 2017 1 P age Executive

More information

MACTIER WASTEWATER TREATMENT 2016 SUMMARY REPORT

MACTIER WASTEWATER TREATMENT 2016 SUMMARY REPORT MACTIER WASTEWATER TREATMENT 2016 SUMMARY REPORT CERTIFICATE OF APPROVAL: # 7599-7PCKPU INTRODUCTION The Conger Marsh Water Pollution Control Plant (WPCP), which services the community of MacTier, is owned

More information

2014 Annual Compliance Report Operation & Maintenance Of Tara Wastewater System

2014 Annual Compliance Report Operation & Maintenance Of Tara Wastewater System 2014 Annual Compliance Report Operation & Maintenance Of Tara Wastewater System March 2015 Prepared for: Municipality of Arran-Elderslie 1925 Bruce Road 10 Box 70 Chesley, ON N0G 1L0 Prepared by: GSS Engineering

More information

2017 Annual Compliance Report. Operation & Maintenance of Paisley Wastewater System. March

2017 Annual Compliance Report. Operation & Maintenance of Paisley Wastewater System. March 2017 Annual Compliance Report Operation & Maintenance of Paisley Wastewater System March 2018 13-028 Prepared for: Municipality of Arran-Elderslie 1925 Bruce Road 10 Box 70 Chesley, ON N0G 1L0 Prepared

More information

2017 ANNUAL WASTEWATER TREATMENT SYSTEM SUMMARY REPORT. Wastewater Treatment Plant:

2017 ANNUAL WASTEWATER TREATMENT SYSTEM SUMMARY REPORT. Wastewater Treatment Plant: 2017 ANNUAL WASTEWATER TREATMENT SYSTEM SUMMARY REPORT Drumbo Wastewater Treatment Plant 1. General Information Oxford County prepares individual annual reports summarizing each wastewater treatment plant

More information

This document can be made available in other accessible formats as soon as practicable and upon request. Staff Report. Infrastructure & Public Works

This document can be made available in other accessible formats as soon as practicable and upon request. Staff Report. Infrastructure & Public Works This document can be made available in other accessible formats as soon as practicable and upon request Staff Report Infrastructure & Public Works Report To: Committee of the Whole Meeting Date: March

More information

Bruce Mines Lagoon Annual Operating Report

Bruce Mines Lagoon Annual Operating Report Bruce Mines Lagoon Annual Operating Report January 1, 2010 to December 31, 2010 Prepared by Ontario Clean Water Agency March 04, 2011 Ministry of the Environment 289 Bay Street, 3 rd Floor Sault Ste. Marie,

More information

Assuming 100 gallons per capita per day, and 3 people per REU, design flows for the development are proposed to be:

Assuming 100 gallons per capita per day, and 3 people per REU, design flows for the development are proposed to be: Andelina Farms Wastewater Treatment Plant Preliminary Basis of Design May 2018 Andelina Farms is a proposed Planned Unit Development in Saline Township located along US-12 just west of the City of Saline.

More information

Iroquois Wastewater Treatment Plant 2016 Annual Performance Report

Iroquois Wastewater Treatment Plant 2016 Annual Performance Report Iroquois Wastewater Treatment Plant 2016 Annual Performance Report The Iroquois WWTP is a Class II wastewater treatment facility owned and operated by the Municipality of South Dundas. Raw sewage is conveyed

More information

CITY OF LONDON WASTEWATER TREATMENT OPERATIONS ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT 2013 ANNUAL REPORT ADELAIDE WASTEWATER TREATMENT PLANT

CITY OF LONDON WASTEWATER TREATMENT OPERATIONS ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT 2013 ANNUAL REPORT ADELAIDE WASTEWATER TREATMENT PLANT CITY OF LONDON WASTEWATER TREATMENT OPERATIONS ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT 2013 ANNUAL REPORT ADELAIDE WASTEWATER TREATMENT PLANT FEBRUARY 2014 Adelaide Wastewater Treatment Plant 2013

More information

Upgrading Lagoons to Remove Ammonia, Nitrogen, and Phosphorus *nutrient removal in cold-climate lagoon systems

Upgrading Lagoons to Remove Ammonia, Nitrogen, and Phosphorus *nutrient removal in cold-climate lagoon systems Upgrading Lagoons to Remove Ammonia, Nitrogen, and Phosphorus *nutrient removal in cold-climate lagoon systems October 7, 2015 3:15 4:00pm Session M Room Tamboti / Aloes-wood Treatment Processes Aerated

More information

Determination of Treatment Requirements for Municipal and Private Sewage Treatment Works Discharging to Surface Waters

Determination of Treatment Requirements for Municipal and Private Sewage Treatment Works Discharging to Surface Waters PROCEDURE F-5-1 (formerly referenced by 08-01) Determination of Treatment Requirements for Municipal and Private Sewage Treatment Works Discharging to Surface Waters PROCEDURE F-5-1 DETERMINATION OF TREATMENT

More information

The Corporation of the City of St. Thomas. Water Pollution Control Plant Annual Performance Report. Under Ontario Ministry of the Environment

The Corporation of the City of St. Thomas. Water Pollution Control Plant Annual Performance Report. Under Ontario Ministry of the Environment The Corporation of the City of St. Thomas Water Pollution Control Plant 2008 Annual Performance Report Under Ontario Ministry of the Environment Certificate of Approval 5276-5M9JW7 February 2009 John Mansell,

More information

EGANVILLE SEWAGE SYSTEM 2013 PERFORMANCE REPORT

EGANVILLE SEWAGE SYSTEM 2013 PERFORMANCE REPORT EGANVILLE SEWAGE SYSTEM 2013 PERFORMANCE REPORT Township of Bonnechere Valley Water and Sewage Department January 2014 Table of Contents Executive Summary... 3 Introduction... 4 Report Availability...

More information

CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2013 ANNUAL REPORT

CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2013 ANNUAL REPORT CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2013 ANNUAL REPORT FEBRUARY 2014 SUMMARY This annual report is in response

More information

MISSISSIPPI MILLS WASTEWATER TREATMENT FACILITY 2012 ANNUAL REPORT. Prepared by Deborah Turner Process & Compliance Technician Ottawa Valley Hub

MISSISSIPPI MILLS WASTEWATER TREATMENT FACILITY 2012 ANNUAL REPORT. Prepared by Deborah Turner Process & Compliance Technician Ottawa Valley Hub MISSISSIPPI MILLS WASTEWATER TREATMENT FACILITY 2012 ANNUAL REPORT Prepared by Deborah Turner Process & Compliance Technician Ottawa Valley Hub Mississippi Mills Wastewater Treatment Plant Annual Report

More information

History of the Plant

History of the Plant History of the Plant Discharge began May 2008 Plant capacity as built 20 mgd Expansion capacity 30 mgd Beginning discharge approximately 5.5 6.0 mgd Currently discharging 7.5 mgd Activated Sludge treatment

More information

Watershed Overview of Wastewater Treatment Plant Performance

Watershed Overview of Wastewater Treatment Plant Performance Watershed Overview of Wastewater Treatment Plant Performance Report prepared by: Grand River Conservation Authority 400 Clyde Road Cambridge ON N1R 5W6 May 2014 Table of Contents Acronyms and Abbreviations...ii

More information

Attachment N o F Control & Monitoring

Attachment N o F Control & Monitoring Attachment N o F Control & Monitoring Attachment F1: Treatment, Abatement and Control Systems Air There is no treatment or abatement systems required for the minor air emission points or the potential

More information

WASTEWATER TREATMENT. Nelson Environmental Inc. Nelson Environmental Inc.

WASTEWATER TREATMENT. Nelson Environmental Inc. Nelson Environmental Inc. The OPTAER system provides reliable nutrient removal in pond based wastewater treatment plants combining cost-effective technologies and low maintenance requirements. WASTEWATER TREATMENT PrintStudioOne.com

More information

North Side WRP Master Plan Research and Development Department 2006 Seminar Series October 27, 2006 Metropolitan Water Reclamation District of

North Side WRP Master Plan Research and Development Department 2006 Seminar Series October 27, 2006 Metropolitan Water Reclamation District of North Side WRP Master Plan Research and Development Department 2006 Seminar Series October 27, 2006 Metropolitan Water Reclamation District of Greater Chicago Today s Goals Discuss project background Provide

More information

2017 Annual Compliance Report. Operation & Maintenance Of Tara Wastewater System

2017 Annual Compliance Report. Operation & Maintenance Of Tara Wastewater System 2017 Annual Compliance Report Operation & Maintenance Of Tara Wastewater System March 2018 13-028 Prepared for: Municipality of Arran-Elderslie 1925 Bruce Road 10 Box 70 Chesley, ON N0G 1L0 Prepared by:

More information

SSO Reduction Program. WWTP Effluent Violation Corrective Actions

SSO Reduction Program. WWTP Effluent Violation Corrective Actions SSO Reduction Program WWTP Effluent Violation Corrective Actions Report to United States Environmental Protection Agency: SSO Reduction Program This page intentionally left blank i WWTP Effluent Violation

More information

WIARTON WASTEWATER TREATMENT PLANT

WIARTON WASTEWATER TREATMENT PLANT WIARTON WASTEWATER TREATMENT PLANT ANNUAL PERFORMANCE REPORT For the period of JANUARY 1, 2016 TO DECEMBER 31, 2016 Prepared by the Ontario Clean Water Agency For The Corporation of the Town of South Bruce

More information

Lagoons Operation and Management in New Brunswick

Lagoons Operation and Management in New Brunswick Lagoons Operation and Management in New Brunswick Lagoons Provide secondary treatment to domestic wastewater by the action of bacteria stabilizing the organic matter in the wastewater. Benefits of lagoons:

More information

Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility

Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility Richard W. Gullick, Ph.D. Director of Operations Timothy Castillo Wastewater Manager Presented to the Albemarle County

More information

CITY OF OXFORD WASTEWATER TREATMENT FACILITY ANNUAL PERFORMANCE REPORT FOR THE CALENDAR YEAR OF 2014

CITY OF OXFORD WASTEWATER TREATMENT FACILITY ANNUAL PERFORMANCE REPORT FOR THE CALENDAR YEAR OF 2014 CITY OF OXFORD WASTEWATER TREATMENT FACILITY ANNUAL PERFORMANCE REPORT FOR THE CALENDAR YEAR OF 2014 PREPARED: January 2015 2014 ANNUAL PERFORMANCE REPORT FOR THE CITY OF OXFORD WASTEWATER TREATMENT FICILITY

More information

Water Quality Permitting Program Monitoring Matrix 1,2,3

Water Quality Permitting Program Monitoring Matrix 1,2,3 State of Oregon Department of Environmental Quality Water Quality Permitting Program Monitoring Matrix 1,2,3 ITEM OR PARAMETER Total Flow (influent and/or effluent) 4 Flow Meter Calibration 5 (influent

More information

2014 Watershed Overview of Wastewater Treatment Plant Performance

2014 Watershed Overview of Wastewater Treatment Plant Performance 2014 Watershed Overview of Wastewater Treatment Plant Performance Photo: Dundalk Lagoon Date: February 2016 Report prepared by: Kelly Hagan and Mark Anderson Grand River Conservation Authority 400 Clyde

More information

Ailsa Craig Wastewater Treatment Plant Operations Report 2017 THIRD QUARTER

Ailsa Craig Wastewater Treatment Plant Operations Report 2017 THIRD QUARTER Ailsa Craig Wastewater Treatment Plant Operations Report 2017 THIRD QUARTER Submitted by: Ontario Clean Water Agency Date: July 1 September 30, 2017 Ailsa Craig Wastewater Treatment Plant and Collection

More information

Georgia Power Plant McDonough-Atkinson NPDES Permit No. GA Ash Pond Dewatering Plan. Revised May 2018

Georgia Power Plant McDonough-Atkinson NPDES Permit No. GA Ash Pond Dewatering Plan. Revised May 2018 Georgia Power Plant McDonough-Atkinson NPDES Permit No. GA0001431 Revised May 2018 Purpose This updated (Plan) describes the additional procedures, safeguards and enhanced wastewater treatment measures

More information

Baltimore City Department of Public Works

Baltimore City Department of Public Works Baltimore City Department of Public Works Back River WWTP Process and Construction Overview Michael F. Gallagher, Chief Wastewater Facilities Division Wastewater Treatment Chesapeake Bay Restoration Water

More information

Georgia Power Plant Bowen NPDES Permit No. GA Ash Pond Dewatering Plan. Revised December 2017

Georgia Power Plant Bowen NPDES Permit No. GA Ash Pond Dewatering Plan. Revised December 2017 Georgia Power Plant Bowen NPDES Permit No. GA0001449 Revised December 2017 Purpose This (Plan) describes the additional procedures, safeguards and enhanced wastewater treatment measures that Georgia Power

More information

MEETING COLUMBUS S TREATMENT LIMITS

MEETING COLUMBUS S TREATMENT LIMITS MEETING COLUMBUS S TREATMENT LIMITS EVEN WHEN WET WEATHER CHANGES THEM Improving Quality of Life AGENDA CEPT Background CEPT Preliminary Testing CEPT Design and Construction CEPT NPDES Permit Modification

More information

WASTEWATER TREATMENT SYSTEM

WASTEWATER TREATMENT SYSTEM WASTEWATER TREATMENT SYSTEM PrintStudioOne.com Nelson Environmental Inc. The Nelson Environmental OPTAER system is an efficient pond-based wastewater treatment solution utilized in a broad spectrum of

More information

Dealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017

Dealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017 Dealing with Unexpected Wastewater Treatment Plant Disruptions February 16, 2017 Location Map WPCP History Original WPCP constructed on this site in 1928 consisting of primary treatment and chlorination;

More information

13. High Rate Filtration Process

13. High Rate Filtration Process 13.High Rate Filtration Process N. Horie 1, M.Kabata 2, K.Sano 3, S.Kanamori 4 Director, Chief Researcher,Senior Researcher 3, Researcher 4 First Research Department Japan Institute of Wastewater Engineering

More information

PHOSPHORUS AND ALGAE REMOVED FROM WAIHI FACULTATIVE POND DISCHARGE

PHOSPHORUS AND ALGAE REMOVED FROM WAIHI FACULTATIVE POND DISCHARGE PHOSPHORUS AND ALGAE REMOVED FROM WAIHI FACULTATIVE POND DISCHARGE K.M. Holyoake 1, K.V. Kotze 1, P. Patel 2 1 Armatec Environmental Ltd, 2 Hauraki District Council Paper presented at the NZ Water and

More information

Taylor Creek Treatment Plant. Metropolitan Sewer District of Greater Cincinnati

Taylor Creek Treatment Plant. Metropolitan Sewer District of Greater Cincinnati Taylor Creek Treatment Plant Metropolitan Sewer District of Greater Cincinnati Who is this guy and what is he talking about? Brad Blankenship Taylor Creek Operator 3.5 years MSD Operator 5.5 years (total)

More information

EHS SMART-Treat Onsite Moving Media Treatment System

EHS SMART-Treat Onsite Moving Media Treatment System EHS SMART-Treat Onsite Moving Media Treatment System Sampling &Testing Protocol for SMART-Treat Wastewater Treatment System SAMPLING DURING OPERATION OF THE TREATMENT SYSTEM-IF DESIRED Sampling and analytical

More information

BIOLOGICAL WASTEWATER BASICS

BIOLOGICAL WASTEWATER BASICS BIOLOGICAL WASTEWATER BASICS PRESENTATION GOALS EXPLAIN DIFFERENT TYPES OF WASTEWATER EXPLAIN THE DIFFERENT BIOLOGICAL SYSTEMS AND HOW THEY FUNCTION. COMPARE AND CONTRAST AEROBIC AND ANAEROBIC SYSTEMS

More information

FEASIBILITY REPORT ON SEWAGE TREATMENT PLANT ARCHITECTS PHE CONSULTANTS

FEASIBILITY REPORT ON SEWAGE TREATMENT PLANT ARCHITECTS PHE CONSULTANTS Uttarahalli village, FEASIBILITY REPORT ON SEWAGE TREATMENT PLANT FOR M/s. PRESTIGE ESTATES PROJECTS LTD, BENGALURU PROJECT : DEVELOPMENT OF RESIDENTIAL APARTMENT BEARING SY. Nos. 115,116 & 117 AT UTTARAHALLI

More information

Alexandria Sewage Lagoon Treatment Facility Municipal Class C Environmental Assessment Public Information Centre #2 Welcome!

Alexandria Sewage Lagoon Treatment Facility Municipal Class C Environmental Assessment Public Information Centre #2 Welcome! Alexandria Sewage Lagoon Treatment Facility Municipal Class C Environmental Assessment Public Information Centre #2 Welcome! Municipal Class Environmental Assessment Status We are Here Study Overview The

More information

Watertown Wastewater Facility Plan. August 11, 2015

Watertown Wastewater Facility Plan. August 11, 2015 Watertown Wastewater Facility Plan August 11, 2015 Watertown Wastewater Wastewater Treatment Facility History Comprehensive Planning Wastewater Concerns Capacity Condition Permitting Requirements Watertown

More information

Cannington Water Pollution Control Plant Annual Performance Report Annual Performance Report 2015

Cannington Water Pollution Control Plant Annual Performance Report Annual Performance Report 2015 Cannington Water Pollution Control Plant Cannington Water Pollution Control Plant Cannington Water Pollution Control Plant The Regional Municipality of Durham Cannington Water Pollution Control Plant 2015

More information

2015 HDR, Inc., all rights reserved.

2015 HDR, Inc., all rights reserved. 2015 HDR, Inc., all rights reserved. Hastings Utilities Water Pollution Control Facility Improvements Brian Bakke, HDR ASCE Environmental Conference 4/6/2017 Review Existing Facilities Need for the Project

More information

CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2012 ANNUAL REPORT

CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2012 ANNUAL REPORT CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2012 ANNUAL REPORT FEBRUARY 2013 SUMMARY This annual report is in response

More information

The Wetland Biofilter System:

The Wetland Biofilter System: The Wetland Biofilter System: A vertical flow constructed wetland for treatment of manure compost pile leachate water What is the Wetland Biofilter System? Vertical flow constructed wetland Consists of

More information

Wastewater Treatment Works and Collections System Annual Report Year 2005 General Information

Wastewater Treatment Works and Collections System Annual Report Year 2005 General Information Wastewater Treatment Works and Collections System Annual Report Year 2005 General Information Facility / System: Town of Farmville Wastewater Collection System and Treatment Facilities Responsible Entity:

More information

EPA Waste Water Discharge Licence Application

EPA Waste Water Discharge Licence Application Duleek Waste Water Treatment Works EPA Waste Water Discharge Licence Application ARTICLE 16 COMPLIANCE REQUIREMENTS Meath County Council EPA Document Ref: D0133-01 Section A: Non-Technical Summary Update

More information

RE: Year-End Report Woodstock Wastewater Treatment Plant (WWTP), 2012

RE: Year-End Report Woodstock Wastewater Treatment Plant (WWTP), 2012 Public Works P. O. Box 1614, 21 Reeve St.,, Woodstock Ontario N4S 7Y3 Phone: 519-539-9800 Fax: 519-421-4711 Website: www.oxfordcounty.ca March 15, 2013 District Manager Ministry of the Environment London

More information

Wastewater Facility Plan City of Marshall, Minnesota

Wastewater Facility Plan City of Marshall, Minnesota Wastewater Facility Plan City of Marshall, Minnesota Public Hearing March 14, 2017 Bolton & Menk, Inc. Project No. T22.108560 Glossary of General Terms & Abbreviations MPCA - Minnesota Pollution Control

More information

Best practice in monitoring process, operation and maintenance of wastewater treatment plants 12 September 2011, Bucharest

Best practice in monitoring process, operation and maintenance of wastewater treatment plants 12 September 2011, Bucharest Best practice in monitoring process, operation and maintenance of wastewater treatment plants 12 September 2011, Bucharest Steve Russell WRc PLC Swindon UK Steve.russell@wrcplc.co.uk WRc plc 2011 Plan

More information

International Joint Commission Water & Wastewater Treatment Best Management Practices Forum Monday, March 26, 2012 Wayne State University, Detroit MI

International Joint Commission Water & Wastewater Treatment Best Management Practices Forum Monday, March 26, 2012 Wayne State University, Detroit MI STARTUP AND OPERATION OF A BIOLOGICAL AERATED FILTER (BAF) FOR SIMULTANEOUS BOD REMOVAL AND NITRIFICATION AT THE LOU ROMANO WATER RECLAMATION PLANT WINDSOR ONTARIO CANADA International Joint Commission

More information

Georgia Power Plant McManus NPDES Permit No. GA Ash Pond Dewatering Plan. Revised April 2018

Georgia Power Plant McManus NPDES Permit No. GA Ash Pond Dewatering Plan. Revised April 2018 Georgia Power Plant McManus NPDES Permit No. GA0003794 Revised April 2018 Purpose This (Plan) describes the procedures, safeguards and enhanced wastewater treatment measures that Georgia Power Company

More information

ANNEX C INFRASTRUCTURE & OPERATION

ANNEX C INFRASTRUCTURE & OPERATION ROSCOMMON COUNTY COUNCL MONKSLAND WASTEAWATER DSCHARGE LCENCE ANNEX C NFRASTRUCTURE & OPERATON Roscommon County Council WWD Application Attachment to Form C1.1 Design Criteria The Monksland WWTP is situated

More information

APPENDIX C EXISTING CONDITIONS

APPENDIX C EXISTING CONDITIONS Environmental Study Report APPENDICES APPENDIX C EXISTING CONDITIONS R331670101001.docx C XCG File No.: 3-3167-01-01 June 6, 2013 TECHNICAL MEMORANDUM SUMMARY OF EXISTING CONDITIONS ARTHUR WWTP Prepared

More information

2014 Annual Wastewater Report

2014 Annual Wastewater Report 214 Annual Wastewater Report Mar 6, 215 v.1. 214 Annual Wastewater Report Table of Contents REPORTS PAGE Wastewater Capital Spending Overview 1 Wastewater North - 214 1 Wastewater South 214 2 Lift Stations

More information

Collingwood Wastewater Treatment Plant Annual Compliance Report

Collingwood Wastewater Treatment Plant Annual Compliance Report Collingwood Wastewater Treatment Plant 2017 Annual Compliance Report Table of Contents Definitions... 3 Wastewater System General Information... 4 Executive Summary... 5 Section 1.0 The Facility... 6 Section

More information

Nutrient Removal Optimization at the Fairview WWTP

Nutrient Removal Optimization at the Fairview WWTP Alyssa Mayer, PE Principal Engineer Nutrient Removal Optimization at the Fairview WWTP Mark Strahota, PE Associate Presentation Overview Project Background Process Model Development BNR Design Considerations

More information

Annual Environmental Report 2017

Annual Environmental Report 2017 Annual Environmental Report 2017 Agglomeration Name: Kanturk Licence Register No. D0203-01 Contents Section 1. Executive Summary and Introduction to the 2017 AER 3 1.1 Summary Report on 2017 3 Section

More information

Advanced Control in Water and Wastewater Systems

Advanced Control in Water and Wastewater Systems Advanced Control in Water and Wastewater Systems Mandy Poole, P.E. Jason Neighbors Dave Green June 6, 2014 AGENDA What is a control loop? Control Theory Pump Control Levels of Control Case study on Wastewater

More information

TABLE OF CONTENTS 1.0 INTRODUCTION 1. Classification and Control Document Information. 2.0 CONTACT INFORMATION 2

TABLE OF CONTENTS 1.0 INTRODUCTION 1. Classification and Control Document Information. 2.0 CONTACT INFORMATION 2 TABLE OF CONTENTS Page 1.0 INTRODUCTION 1 Classification and Control Document Information. 2.0 CONTACT INFORMATION 2 Owner/Operator contact information 3.0 WASTEWATER TREATMENT PLANT & TREATMENT PROCESS

More information

Delvin Wastewater Treatment Plant

Delvin Wastewater Treatment Plant Delvin Wastewater Treatment Plant WWDL No. D0267-01 ANNUAL ENVIRONMENTAL REPORT 2011 County Buildings Mullingar Co. Westmeath Phone: 04493-32000 Fax: 04493-42330 Delvin Waste Water Discharge Licence (EPA

More information

Wastewater Treatment Plant Compliance. Strategies for Surviving an NPDES Permit Inspection (National Pollutant Discharge Elimination System)

Wastewater Treatment Plant Compliance. Strategies for Surviving an NPDES Permit Inspection (National Pollutant Discharge Elimination System) Wastewater Treatment Plant Compliance Strategies for Surviving an NPDES Permit Inspection (National Pollutant Discharge Elimination System) Plus some general info about permits & reporting Eric Dunlavey

More information

CITY OF OXFORD WASTEWATER TREATMENT FACILITY ANNUAL PERFORMANCE REPORT FOR THE CALENDAR YEAR OF 2018

CITY OF OXFORD WASTEWATER TREATMENT FACILITY ANNUAL PERFORMANCE REPORT FOR THE CALENDAR YEAR OF 2018 CITY OF OXFORD WASTEWATER TREATMENT FACILITY ANNUAL PERFORMANCE REPORT FOR THE CALENDAR YEAR OF 2018 PREPARED: January 2019 2018 ANNUAL PERFORMANCE REPORT FOR THE CITY OF OXFORD WASTEWATER TREATMENT FICILITY

More information

Aeration System Improvements with a 5-Year Payback. Scott Phipps

Aeration System Improvements with a 5-Year Payback. Scott Phipps Aeration System Improvements with a 5-Year Payback Scott Phipps Wastewater Treatment Aeration Timeline 1970 s Major infrastructure investment Quick and cheap solutions Coarse bubble diffusers & PD/MS blowers

More information

Wastewater Treatment. Where does wastewater go when it leaves your house?

Wastewater Treatment. Where does wastewater go when it leaves your house? Wastewater Treatment Where does wastewater go when it leaves your house? Let s s take a look The process includes: Collection of wastewater Primary Treatment Secondary Treatment Solids Handling Influent

More information

HIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS JUNE

HIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS JUNE City of Newark, Ohio HIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS JUNE 22, 2011 High Rate Treatment Tanks/UV Wet Weather Screen Building JC2/Wet Weather Pump Station Wet Weather Control

More information

12.0 ASSESSMENT OF LEACHATE MANAGEMENT OPTIONS 12.1 Overview

12.0 ASSESSMENT OF LEACHATE MANAGEMENT OPTIONS 12.1 Overview ENVIRONMENTAL ASSESSMENT OF THE PROPOSED CAPITAL REGION 12.0 ASSESSMENT OF LEACHATE MANAGEMENT OPTIONS 12.1 Overview Leachate treatment is required for the organics processing and disposal components of

More information

DRAFT SUBMITTED TO: TOWNSHIP OF LONG HILL PREPARED BY: KLEINFELDER

DRAFT SUBMITTED TO: TOWNSHIP OF LONG HILL PREPARED BY: KLEINFELDER LONG HILL TOWNSHIP WASTEWATER TREATMENT PLANT CAPACITY ASSURANCE REPORT UPDATE DRAFT SUBMITTED TO: TOWNSHIP OF LONG HILL PREPARED BY: KLEINFELDER FEBRUARY 2018 LONG HILL TOWNSHIP WASTEWATER TREATMENT PLANT

More information

Algae Removal from a Facultative Lagoon System Using Dissolved Air Flotation. J. Patrick Pierce, P.E. Environmental Treatment Systems, Inc.

Algae Removal from a Facultative Lagoon System Using Dissolved Air Flotation. J. Patrick Pierce, P.E. Environmental Treatment Systems, Inc. Algae Removal from a Facultative Lagoon System Using Dissolved Air Flotation J. Patrick Pierce, P.E. Environmental Treatment Systems, Inc. Facultative Lagoon System Designed for 1.5 MGD Discharging 1.15-1.35

More information

Clif Bar Pretreatment

Clif Bar Pretreatment Pacific Northwest Pretreatment Workshop September 12, 2017 Clif Bar Pretreatment Larry Rupp and Jason King Keller Associates Meridian, Idaho CITY OF LEWISTON WWTP 2020 IMPROVEMENTS 1 City of Twin Falls

More information

<1ppm Phosphorus A BNR With No Chemical Addition Case Study

<1ppm Phosphorus A BNR With No Chemical Addition Case Study WWOA 51 st Annual Conference October 2017 Arn Johnson Walker Process Equipment Div. of McNish Corp. arn.johnson@walker-process.com 1 Todd Toelle, Superintendent City of Phillips, WI WWTP Chris Kaempfer,

More information

CITY OF BROCKVILLE WATER POLLUTION CONTROL CENTRE

CITY OF BROCKVILLE WATER POLLUTION CONTROL CENTRE CITY OF BROCKVILLE WATER POLLUTION CONTROL CENTRE 2014 ANNUAL SUMMARY REPORT FOR COUNCIL Peter Raabe, P. Eng., Director of Environmental Services Ed Malcomnson, Supervisor Wastewater Systems Division DATE:

More information

Application Form and Guide for an EPEA Registration Code of Practice for Wastewater Systems Using a Wastewater Lagoon

Application Form and Guide for an EPEA Registration Code of Practice for Wastewater Systems Using a Wastewater Lagoon Code of Practice for Wastewater Systems Using a Wastewater Lagoon Introduction The attached form and guidelines outline the information required for an application for a registration for wastewater systems

More information

UPGRADING GAZA WASTEWATER TREATMENT PLANT. Gaza City is populated with 550,000 inhabitants and it forms 45% of the Gaza strip population.

UPGRADING GAZA WASTEWATER TREATMENT PLANT. Gaza City is populated with 550,000 inhabitants and it forms 45% of the Gaza strip population. Gaza City Gaza City is populated with 550,000 inhabitants and it forms 45% of the Gaza strip population. Gaza City has the oldest wastewater system in Gaza Strip; it consists of some of 280 kilometers

More information

Surviving an NPDES Permit Inspection. General info about permits, limits, & reporting

Surviving an NPDES Permit Inspection. General info about permits, limits, & reporting Wastewater Treatment Plant Compliance Surviving an NPDES Permit Inspection General info about permits, limits, & reporting Step One Know your Permit Know your facility Know what your inspector wants Know

More information

BIO-BATCH TM. Sequencing Batch Reactor (SBR) Water & Wastewater Treatment

BIO-BATCH TM. Sequencing Batch Reactor (SBR) Water & Wastewater Treatment BIO-BATCH Sequencing Batch Reactor (SBR) Napier-Reid s Bio-Batch SBR is an effective aerobic biological system to remove pollutants i.e. BOD, COD, Suspended Solids, Nitrogen and Phosphorous from municipal

More information

FURTHER EXPANDED FLOWS AND LOADS R3 INDUSTRIAL WWTP PROCESS ENGINEERING EVALUATION

FURTHER EXPANDED FLOWS AND LOADS R3 INDUSTRIAL WWTP PROCESS ENGINEERING EVALUATION FURTHER EXPANDED FLOWS AND LOADS R3 INDUSTRIAL WWTP PROCESS ENGINEERING EVALUATION Prepared For: HyLife Foods Neepawa, Manitoba, Canada Prepared By: Pharmer Engineering 1998 West Judith Lane Boise, ID

More information

City of Andover, Kansas Energy Assessment-Wastewater Treatment Plant

City of Andover, Kansas Energy Assessment-Wastewater Treatment Plant City of Andover, Kansas Energy Assessment-Wastewater Treatment Plant April 7, 2014 Prepared by Jerry Blain, P.E., Project Associate Environmental Finance Center Funding for this Energy Assessment was provided

More information

SECTION 2.0 WASTEWATER TREATMENT PLANT AND DISPOSAL SYSTEM DESCRIPTION

SECTION 2.0 WASTEWATER TREATMENT PLANT AND DISPOSAL SYSTEM DESCRIPTION SECTION 2.0 WASTEWATER TREATMENT PLANT AND DISPOSAL SYSTEM DESCRIPTION Analytical Environmental Services 2-1 Jamul Indian Village Wastewater Treatment Plant Analytical Environmental Services 2-2 Jamul

More information

Wastewater Effluent License Limits

Wastewater Effluent License Limits Wastewater Effluent License Limits 1 OUTLINE Wastewater Treatment Background Licensing Considerations Typical Effluent Parameters Manitoba Conservation Limits Design and Performance Biochemical Oxygen

More information

SUMMARY OF COMMENTS/RECOMMENDATIONS

SUMMARY OF COMMENTS/RECOMMENDATIONS SUMMARY OF COMMENTS/RECOMMENDATIONS PROPONENT: PROPOSAL NAME: Wastewater Treatment Lagoon Upgrade CLASS OF DEVELOPMENT: 2 TYPE OF DEVELOPMENT: Wastewater Treatment Lagoon CLIENT FILE NO.: 2833.20 OVERVIEW:

More information