Table of Contents. Green Line Extension Project. Draft Environmental Impact Report/Environmental Assessment and Draft Section 4(f) Evaluation

Size: px
Start display at page:

Download "Table of Contents. Green Line Extension Project. Draft Environmental Impact Report/Environmental Assessment and Draft Section 4(f) Evaluation"

Transcription

1 Table of Contents Acronyms and Abbreviations Secretary s Certificate on the EENF Executive Summary 1 Introduction and Background Introduction Project Summary Permits and Approvals Consistency with Federal, State, and Local Planning Public Involvement and Agency Coordination Requirements of Secretary's Certificate Purpose and Need Overview Project Purpose Need for Transit Improvements Goals and Objectives Alternatives Introduction No-Build Alternative Project Elements Ridership Methodology Baseline Alternative Build Alternatives Project Description Preferred Alternative Community Paths Coordination with Regional Projects Summary Affected Environment Introduction Land Use Socioeconomic Conditions Environmental Justice Existing Transportation Systems Traffic Table of Contents i Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009

2 4.7 Air Quality Noise Vibration Stormwater Wetlands Fish, Wildlife and Plants Parks and Recreation Visual Environment Historic and Archaeological Resources Hazardous Materials Environmental Consequences Introduction Land Use Socioeconomic Impacts Environmental Justice Traffic Air Quality Noise Vibration Stormwater Fish, Wildlife, and Plants Parks and Recreation Areas Visual Environment Historic and Archaeological Resources Hazardous Materials Indirect and Cumulative Effects Draft Section 61 Findings and Mitigation Commitments Introduction Project Benefits Project Mitigation Construction Period Mitigation Proposed Section 61 Findings Distribution List Federal Agencies and Elected Officials State and Regional Agencies and Elected Officials Municipalities Libraries Advisory Group Members Additional EENF Commenters and Other Interested Parties Figures... VOLUME 2 Table of Contents ii Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009

3 Appendix A: Responses to Comments on the EENF... VOLUME 3 Appendix B Appendix J... on CD Appendix B: Station and Alignment Selection Analysis Appendix C: Green Line Support Facility Alternatives Analysis Appendix D: Travel Demand Modeling Methodology Appendix E: Plans and Feasibility Analysis for Proposed Community Paths Appendix F: Traffic Analysis Appendix G: Transit Access for Environmental Justice and Disability Populations Appendix H: Air Quality Analysis Appendix I: Draft Section 4(f) Evaluation Appendix J: Draft Memorandum of Agreement Table of Contents iii Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009

4 List of Tables Table No. Description Page 1-1 Comparison of DEIR/EA Build Alternatives Meeting Summary (as of August 5, 2009) Requirements of the Secretary s Certificate Estimated Enhanced Route 80 Travel Time Alternative 1: Medford Branch Travel Times Alternative 2: Medford Branch Travel Times Alternative 3: Medford Branch Travel Times Alternative 4: Medford Branch Travel Times Alternative 5: Medford Branch Travel Times Build Alternative Evaluation Land Acquisition Summary Travel Times for the Preferred Alternative Pinch Points for Somerville Community Path Population, Housing and Employment within ½-Mile Radius of the Relocated Lechmere Station Site Population, Housing and Employment within ½-Mile Radius of the Brickbottom Station Site Population, Housing and Employment within ½-Mile Radius of the Gilman Square Station Site Population, Housing and Employment within ½-Mile Radius of the Lowell Street Station Site Population, Housing and Employment within ½-Mile Radius of the Ball Square Station Site Population, Housing and Employment within ½-Mile Radius of the College Avenue Station Site Population, Housing and Employment within ½-Mile Radius of the Mystic Valley Parkway/Route 16 Station Site Population, Housing and Employment within ½-Mile Radius of the Union Square Station Site Social and Economic Statistics for Cambridge, Somerville, and Medford State-Listed Environmental Justice Areas in Cambridge, Somerville, and Medford State-Listed Environmental Justice Populations in Cambridge, Somerville, and Medford Minority Populations in Cambridge, Somerville, Medford, and Middlesex County Span of Service Standards Minimum Frequency of Service Standards Bus Service Frequency and Ridership Table of Contents iv Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009

5 Table No. Description Page MBTA Bus Loading Standards Summary of Bus Schedule Adherence Standards Bus Cost-Effectiveness Service Standard MBTA Lowell Line Daily Weekday Boardings by Station MBTA Fitchburg Line Daily Weekday Boardings by Station Existing Daily Traffic Volumes on Study Area Roadways Vehicular Level of Service Thresholds Existing Condition Signalized Intersection Traffic Operations Existing Condition Unsignalized Intersection Traffic Operations Pedestrian Level of Service Thresholds Existing Condition Pedestrian Level-of-Service Parking Inventory Restricted Parking Allocation Existing Noise Measurement Results Existing Park and Recreation Areas within the Study Area Land Acquisitions for Extension to Medford Hillside Land Acquisitions for Extension to Union Square (via commuter rail right-of-way) Land Acquisitions for Extension to Mystic Valley Parkway/Route Land Acquisitions for Extension to Union Square (via McGrath Highway/Route 28 and Somerville Avenue) Summary of Land Acquisitions by Alternative Property Tax Effects for Alternative Property Tax Effects for Alternative Property Tax Effects for Alternative Property Tax Effects for Alternative Property Tax Effects for Alternative Property Tax Effects for Alternative Property Taxes of Real Estate Acquired For Each Alternative Property Tax Decreases by City Estimated Job Decreases or Relocations Changes in Transit Access for Disability and Environmental Justice Populations under the Baseline Alternative Changes in Transit Access for Disability and Environmental Justice Populations under a Light Rail Extension to Mystic Valley Parkway/Route 16 and Union Square Building Acquisitions and Local Demographics for Extension to Medford Hillside Building Acquisitions and Local Demographics for Extension to Union Square (via commuter rail right-of-way) Building Acquisitions and Local Demographics for Extension to Mystic Valley Parkway/Route Building Acquisitions and Local Demographics for Extension to Union Square via McGrath Highway and Somerville Avenue Summary of Project Impacts in Environmental Justice Areas No-Build Alternative Signalized Intersection Traffic Operations Results No-Build Alternative Unsignalized Intersection Traffic Operations Results Table of Contents v Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009

6 Table No. Description Page Baseline Alternative Signalized Intersection Traffic Operations Results Baseline Alternative Unsignalized Intersection Traffic Operations Results Alternative 1 Peak Hour Trip Summary by Station Alternative 1 Signalized LOS Summary Comparison Alternative 1 Unsignalized LOS Summary Comparison Alternative 2 Peak Hour Trip Summary by Station Alternative 2A (with parking) Signalized LOS Summary Comparison Alternative 2A (with parking) Unsignalized Intersection Traffic Operations Results Alternative 3 Peak Hour Trip Summary by Station Alternative 3 Signalized Intersection Traffic Operations Results Alternative 4 Peak Hour Trip Summary by Station Alternative 4 Signalized Intersection Traffic Operations Results Alternative 5 Peak Hour Trip Summary by Station Alternative 5 Signalized Intersection Traffic Operations Results Alternative 6 Peak Hour Trip Summary by Station Alternative 6 Signalized Intersection Traffic Operations Results Proposed Pedestrian Mitigation Measures Summary of Traffic Impacts and Mitigation National Ambient Air Quality Standards Predicted Maximum 1-Hour CO Concentrations (Parts Per Million) Predicted Maximum 8-Hour CO Concentrations (Parts Per Million) Predicted Maximum 24-Hour PM10 Concentrations (Parts Per Million) Predicted Maximum 24-Hour PM2.5 Concentrations (Parts Per Million) Predicted Maximum Annual PM2.5 Concentrations (Parts Per Million) Projected PM2.5 Emissions for Proposed Commuter Rail Track Relocation (ug/m 3 ) Mesoscale 2030 Mobile Source Analysis Results (kilograms per day) Greenhouse Gas (CO2) Analysis Results (kilograms per day) EOT Air Quality Analysis Comparison of Project Packages Benefits in the Year Comparison of Air Quality Benefits Potential Noise Impacts Without Mitigation for Alternatives 1, 2, 3, and Potential Noise Impacts Without Mitigation for Alternatives 5 and Summary of Potential Noise Impacts Summary of Proposed Noise Barrier Mitigation FTA Ground-Borne Noise and Vibration Impact Criteria FTA Ground-Borne Noise and Vibration Impact Criteria for Special Buildings Vibration Criteria for Detailed Analysis Potential Vibration Impacts at Sensitive Receptors Without Mitigation Summary of Potential Vibration Impact Summary of Proposed Vibration Mitigation Potential Vibration Mitigation Measures for Crossovers and Turnouts Impervious Surface Changes by Station Summary of Impervious Surface Changes by Alternative Table of Contents vi Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009

7 Table No. Description Page Direct Vegetated Habitat Impacts by Alternative Potential Impacts to Archaeologically Sensitive Areas RECs and Potential Impacts for Alternatives 1 and 3 - Extension to Medford Hillside RECs and Potential Impacts for Alternatives 1, 2, and 6 - Extension to Union Square (via commuter rail right-of-way) RECs and Potential Impacts for Alternatives 2, 4, and 5 - Extension to Route 16/Mystic Valley Parkway RECs and Potential Impacts for Alternatives 3 and 4 Extension to Union Square via McGrath Highway/Route 28 and Somerville Avenue RECs and Potential Impacts for Alternative 6 Yard 8 Maintenance Facility Summary of RECs and their Impacts by Alternative Cambridge, Somerville, Medford, and Station Area Populations (2000 and 2030) TOD Potential at Proposed Station Sites TOD Potential by Alternative Rail System Benefits on Real Estate Values Populations of Cambridge, Somerville and Medford (2000 and 2006) Projected Population and Employment Within ½- Mile of Proposed Station Sites (2010 and 2030) Proposed and Reasonably Foreseeable Projects in the Project Corridor Project Mitigation Commitments Summary of Construction Mitigation Measures Possible Permits or Approvals Table of Contents vii Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009

8 List of Figures All figures are provided in Volume 2 except as indicated otherwise below. Figure Description Page 1-1 Study Area Station Locus Map (Sheet 1 of 2) Station Locus Map (Sheet 2 of 2) Maintenance Facility Initial Site Alternatives Preferred Maintenance Facility Site Baseline Alternative Alternative Alternative Alternative Alternative Alternative Alternative Proposed Project Relocated Lechmere Station Station Layout Relocated Lechmere Station Station Plan Relocated Lechmere Station Circulation Relocated Lechmere Station Elevation Brickbottom Station Station Layout Brickbottom Station Station Plan Brickbottom Station Circulation Brickbottom Station Elevation Gilman Square Station Station Layout Gilman Square Station Station Plan Gilman Square Station Circulation Gilman Square Station Elevation Lowell Street Station Station Layout Lowell Street Station Station Plan Lowell Street Station Circulation Lowell Street Station Elevation Ball Square Station Station Layout Ball Square Station Station Plan Ball Square Station Circulation Ball Square Station Elevation College Avenue Station Medford Hillside Terminus (Alt 1, 3) Station Layout College Avenue Station (Alt 2, 4, 5) Station Layout College Avenue Station Station Plan College Avenue Station Circulation College Avenue Station Elevation Table of Contents viii Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009

9 Figure Description Page Mystic Valley Parkway/Route 16 Station Station Layout Mystic Valley Parkway/Route 16 Station Station Plan Mystic Valley Parkway/Route 16 Station Circulation Mystic Valley Parkway/Route 16 Station Elevation Union Square Station Station Layout Union Square Station Station Plan Union Square Station Circulation Union Square Station Elevation Existing Section Looking North (in text) Proposed Section Looking North (in text) Typical Construction Staging (Sheet 1 of 2) Typical Construction Staging (Sheet 2 of 2) Typical Section of Somerville Community Path (in text) Existing Conditions (Sheet 1 of 10) Existing Conditions (Sheet 2 of 10) Existing Conditions (Sheet 3 of 10) Existing Conditions (Sheet 4 of 10) Existing Conditions (Sheet 5 of 10) Existing Conditions (Sheet 6 of 10) Existing Conditions (Sheet 7 of 10) Existing Conditions (Sheet 8 of 10) Existing Conditions (Sheet 9 of 10) Existing Conditions (Sheet 10 of 10) Existing Land Use Index Existing Land Use Existing Lechmere Station Existing Land Use Brickbottom Station Existing Land Use Gilman Square Station Existing Land Use Lowell Street Station Existing Land Use Ball Square Station Existing Land Use College Avenue Station Existing Land Use Mystic Valley Parkway/Route 16 Station Existing Land Use Union Square Station Primary Use Zoning Cities of Somerville, Medford, and Cambridge State-Defined Environmental Justice Populations Existing and Proposed MBTA Bus and Transit System Existing MBTA Commuter Rail Routes Existing Freight Rail Routes Traffic Study Intersections Microscale Air Quality Study Intersections Typical A-Weighted Sound Levels (in text) Examples of Typical Outdoor Noise Exposure (in text) Noise and Vibration Measurement Sites Typical Ground-Borne Vibration Levels and Criteria (in text) Existing Vibration Measurement Results (in text) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 1 of 10) Table of Contents ix Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009

10 Figure Description Page Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 2 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 3 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 4 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 5 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 6 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 7 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 8 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 9 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 10 of 10) Proposed Property Acquisitions Lechmere Station Proposed Property Acquisitions Brickbottom Station Proposed Property Acquisitions Gilman Square Station Proposed Property Acquisitions Lowell Street Station Proposed Property Acquisitions Ball Square Station Proposed Property Acquisitions College Avenue Station Proposed Property Acquisitions Mystic Valley Parkway/ Route 16 Station Proposed Property Acquisitions Union Square Station (Fitchburg Corridor Alternative) Proposed Property Acquisitions Union Square Station (In-Street Running Alternative) Mesoscale 2030 Mobile Source Analysis Results (kilograms per day) (in text) Mobile Source Air Toxics Emissions (in text) Increase in Cumulative Noise Allowed by FTA Criteria (in text) Noise Impacts and Mitigation Measures (Sheet 1 of 5) Noise Impacts and Mitigation Measures (Sheet 2 of 5) Noise Impacts and Mitigation Measures (Sheet 3 of 5) Noise Impacts and Mitigation Measures (Sheet 4 of 5) Noise Impacts and Mitigation Measures (Sheet 5 of 5) Examples of Noise Barrier Materials (in text) Criteria for Detailed Vibration Analysis (in text) Vibration Impacts and Mitigation Measures (Sheet 1 of 5) Vibration Impacts and Mitigation Measures (Sheet 2 of 5) Vibration Impacts and Mitigation Measures (Sheet 3 of 5) Vibration Impacts and Mitigation Measures (Sheet 4 of 5) Vibration Impacts and Mitigation Measures (Sheet 5 of 5) Proposed Stormwater Drainage Proposed and Reasonably Foreseeable Projects Table of Contents x Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009

Green Line extension Project Fall 2009

Green Line extension Project Fall 2009 Introduction The Massachusetts Department of Transportation (MassDOT) is proposing to extend the Green Line to improve transit service, mobility, and regional access for residents and visitors of Cambridge,

More information

6 Draft Section 61 Findings and Mitigation Commitments

6 Draft Section 61 Findings and Mitigation Commitments 6 Draft Section 61 Findings and Mitigation Commitments 6.1 Introduction This chapter presents the proposed mitigation program of the Executive Office of Transportation (EOT) to address adverse environmental

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM. DATE January 21, 2010

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM. DATE January 21, 2010 BOSTON REGION METROPOLITAN PLANNING ORGANIZATION State Transportation Building Ten Park Plaza, Suite 2150 Boston, MA 02116-3968 Tel. (617) 973-7100 Fax (617) 973-8855 TTY (617) 973-7089 www.bostonmpo.org

More information

Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY. November 20, 2017 Public Information Meeting

Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY. November 20, 2017 Public Information Meeting Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY Purpose of tonight s meeting A Notice of Project Change (NPC) has been published for a possible extension of the Green Line from College Avenue to Mystic

More information

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session Green Line Extension Environmental Impact Report Public Scoping Session Somerville High School October 16, 2006 Project Location Green Line Extension Project Purpose Implement enhancements to transit services

More information

Katherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116

Katherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116 Comments on this Environmental Assessment (EA) and may be submitted in writing to: Katherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116 Comments must

More information

Identification and Evaluation of Alternatives Tier 1

Identification and Evaluation of Alternatives Tier 1 Vanasse Hangen Brustlin, Inc. DRAFT 4 Identification and Evaluation of Alternatives Tier This chapter describes the initial set of alternatives that were identified to address the Purpose and Need of the

More information

Vanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices

Vanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices DRFT ppendices MIS 8-05 - ppendices ppendices ugust 005 [THIS PGE INTENTIONLLY LEFT BLNK] DRFT ppendix Tier Detailed Evaluation Tables MIS 8-05 - ppendix ppendix ugust 005 [THIS PGE INTENTIONLLY LEFT BLNK]

More information

Wyandanch Intermodal Transit Facility

Wyandanch Intermodal Transit Facility Wyandanch Intermodal Transit Facility Environmental Assessment July 2010 Prepared by: The United States Department of Transportation Federal Transit Administration in cooperation with The Town of Babylon

More information

GREEN LINE EXTENSION PROJECT

GREEN LINE EXTENSION PROJECT GREEN LINE EXTENSION PROJECT RETAINING WALLS & NOISE BARRIERS AGENDA Upcoming Meeting Schedule Wall Aesthetics/ Design FTA Guidelines for Assessing & Mitigating Noise Impact Plans & Cross Sections Typical

More information

LONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

LONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION LONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Volume I September 22, 2011 The Boston Region Metropolitan Planning Organization (MPO) is composed of: Massachusetts

More information

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT Project Name: Project Location: Lead Agency & Contact Person: SEQRA Classification: Project Sponsors:

More information

12 Evaluation of Alternatives

12 Evaluation of Alternatives 12 Evaluation of Alternatives This chapter evaluates the effectiveness of the No-Build Alternative and the proposed METRO Blue Line Light Rail Transit (BLRT) Extension project based on the information

More information

River Valley. Intermodal Facilities. February Prepared by: Federal Highway Administration Draft Environmental Impact Statement

River Valley. Intermodal Facilities. February Prepared by: Federal Highway Administration Draft Environmental Impact Statement Prepared by: River Valley Intermodal Facilities Federal Highway Administration Draft Environmental Impact Statement River Valley Regional Intermodal Facilities Authority February 2006 and Arkansas State

More information

Hamilton Green. Draft Environmental Impact Statement (DEIS)

Hamilton Green. Draft Environmental Impact Statement (DEIS) Hamilton Green Draft Environmental Impact Statement (DEIS) June 2017 HAMILTON GREEN DRAFT ENVIRONMENTAL IMPACT STATEMENT (DEIS) June 14, 2017 Lead Agency: SEQRA Classification: City of White Plains Common

More information

Contents. S. Executive Summary... ES Overview of Purpose & Need

Contents. S. Executive Summary... ES Overview of Purpose & Need Contents S. Executive Summary... ES-1 S.1 Introduction... ES-1 S.2 Purpose of this Study... ES-3 S.3 Background... ES-6 S.4 Purpose and Need for Transit Investment... ES-10 S.5 Community Input Process...

More information

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014 Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend

More information

Evaluation of Alternatives

Evaluation of Alternatives Chapter 9.0 Evaluation of Alternatives Chapter 9.0 provides a summary evaluation of the No Build Alternative and the Preferred Alternative. The evaluation contained within this chapter is an assessment

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Lynnwood Link Extension 2013 Draft EIS Comments and Responses Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,

More information

Revised Final Environmental Impact Report/ Environmental Assessment for the Wilshire Bus Rapid Transit Project

Revised Final Environmental Impact Report/ Environmental Assessment for the Wilshire Bus Rapid Transit Project Revised Final Environmental Impact Report/ Environmental Assessment for the Wilshire Bus Rapid Transit Project State Clearinghouse No. 2009091094 Los Angeles County Metropolitan Transportation Authority

More information

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements

Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements JUNE 2016 RONALD REAGAN WASHINGTON NATIONAL AIRPORT Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements PREPARED BY: Ricondo & Associates, Inc. IN

More information

PROJECT DESCRIPTION...

PROJECT DESCRIPTION... TABLE OF CONTENTS Volume I Chapter Page 1. INTRODUCTION... 1-1 1.1 Introduction... 1-1 1.2 Project Description... 1-1 1.3 Purpose of the EIR... 1-2 1.4 EIR Process... 1-3 1.5 Scope of the Draft EIR...

More information

Chapter 5 Transportation Draft

Chapter 5 Transportation Draft Chapter 5 Transportation Draft Discussion Similar to the other elements in the Comprehensive Plan, the transportation element impacts the quality of life, economic development and public safety of the

More information

Pacific Wind Energy Project Draft Environmental Impact Report

Pacific Wind Energy Project Draft Environmental Impact Report Pacific Wind Energy Project Table of Contents VOLUME 1 1 Executive Summary... 1-1 1.1 Introduction... 1-1 1.2 Project Summary... 1-1 1.3 Purpose and Use of the Draft EIR... 1-4 1.4 Project Overview...

More information

BENNING ROAD & BRIDGES

BENNING ROAD & BRIDGES BENNING ROAD & BRIDGES DRAFT JUNE 2015 TRANSPORTATION IMPROVEMENTS ENVIRONMENTAL ASSESSMENT DRAFT MAY 2016 EXECUTIVE SUMMARY ES-1 This page left intentionally blank This page left intentionally blank

More information

Northern Branch Corridor CLC Meeting. June 30, 2008

Northern Branch Corridor CLC Meeting. June 30, 2008 Northern Branch Corridor CLC Meeting June 30, 2008 Agenda Introductions Project Status Environmental Process Technical Findings Capital Costs Next Steps Break Out Areas Introductions Project Status Preliminary

More information

Impact Assessment Methodology for the. Somerville Public Library August 4, 2008 Jason Ross, P.E. Harris Miller Miller & Hanson Inc.

Impact Assessment Methodology for the. Somerville Public Library August 4, 2008 Jason Ross, P.E. Harris Miller Miller & Hanson Inc. Noise and Vibration Impact Assessment Methodology for the MBTA Green Line Extension P j t Project Presentation to the Advisory Group Meeting Meeting Somerville Public Library August 4, 2008 Jason Ross,

More information

Sounder Extension to DuPont

Sounder Extension to DuPont Subarea Pierce Primary Mode Commuter Rail Facility Type Station Length 7.8 miles Version Draft ST3 Plan Date Last Modified March 28, 2016 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION

More information

Draft Supplemental Environmental Impact Statement

Draft Supplemental Environmental Impact Statement Draft Supplemental Environmental Impact Statement December 2013 City of Seattle Department of Transportation 700 Fifth Avenue, Suite 3900 Seattle, WA 98124 TABLE OF CONTENTS Elliott Bay Seawall Project

More information

VOLUME 1 Foreword...F-1 Executive Summary... S-1

VOLUME 1 Foreword...F-1 Executive Summary... S-1 Table of Contents VOLUME 1 Foreword...F-1 Executive Summary... S-1 1. Project Description... 1-1 1.1 Introduction...1-1 1.2 Background and Context...1-3 1.2.1 World Trade Center...1-3 1.2.2 Adjacent Sites...1-4

More information

INFORMATION REQUIRED FOR PROBABLE CATEGORICAL EXCLUSION (SECTION (d))

INFORMATION REQUIRED FOR PROBABLE CATEGORICAL EXCLUSION (SECTION (d)) Grant Applicant: Proposed Project: Date: August 03, 2010 Northern Virginia Transportation Commission, Arlington County Government, and Washington Metropolitan Area Transit Authority Crystal City/Potomac

More information

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE FINAL ENVIRONMENTAL IMPACT STATEMENT

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE FINAL ENVIRONMENTAL IMPACT STATEMENT LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE FINAL ENVIRONMENTAL IMPACT STATEMENT Project Name: Project Location: Lead Agency & Contact Person: SEQRA Classification: Project Sponsors:

More information

Capitol Expressway Light Rail Project Supplemental Environmental Impact Statement ANNOTATED OUTLINE

Capitol Expressway Light Rail Project Supplemental Environmental Impact Statement ANNOTATED OUTLINE Capitol Expressway Light Rail Project Supplemental Environmental Impact Statement ANNOTATED OUTLINE The purpose of this annotated outline is to focus the content of the Environmental Impact Statement (EIS)

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 275

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 275 C-034-001 Thank you for your comments describing the cultural importance of the Latvian Evangelical Lutheran Church. See Section 2.5.1 for a description of the refined Segment A alternatives that avoid

More information

Corridor Study and Feasibility Analysis

Corridor Study and Feasibility Analysis Executive Summary November 2013 Corridor Study and Feasibility Analysis Rourke Bridge, Wood Street, Westford Street, and Drum Hill Road Prepared for Northern Middlesex Council of Governments Prepared by

More information

City of Malibu. Whole Foods and the Park Shopping Center Draft Environmental Impact Report Volume I. Prepared For: Prepared by:

City of Malibu. Whole Foods and the Park Shopping Center Draft Environmental Impact Report Volume I. Prepared For: Prepared by: City of Malibu Whole Foods and the Park Shopping Center Draft Environmental Impact Report Volume I Prepared For: Prepared by: I M PA C T S C I E N C E S, I N C. 638 East Colorado Blvd, Suite 301 Pasadena,

More information

New Transportation Performance Measures for Transportation Analysis and Thresholds for CEQA

New Transportation Performance Measures for Transportation Analysis and Thresholds for CEQA New Transportation Performance Measures for Transportation Analysis and Thresholds for CEQA Transportation Advisory Commission September 11, 2014 Transportation Performance Measures Overview of OPR s Draft

More information

Appendix. Sample EA/EIS Scope of Work

Appendix. Sample EA/EIS Scope of Work Appendix K Sample EA/EIS Scope of Work EA/EIS Sample Scope of Work The purpose of this Scope of Work (SOW) is to prepare an EA document pursuant to the National Environmental Policy Act (NEPA) to analyze

More information

South Bay Metro Green Line Extension

South Bay Metro Green Line Extension Meeting Agenda Project overview and update Recap of the Scoping Meetings Progress on the project alternative and proposed station locations Meeting Schedule 6:00 Open House 6:30 Presentation 7:15 Public

More information

Chapter 5 - Transportation

Chapter 5 - Transportation Chapter 5 - Transportation Discussion Similar to the other elements in the Comprehensive Plan, the transportation element impacts the quality of life, economic development and public safety of the residents

More information

14-Dec-2016 Public Meeting Medford City Hall

14-Dec-2016 Public Meeting Medford City Hall 1 Agenda December 14, 2016 1. Update on GLX Status a. New Program Manager, John Dalton b. Work of the Interim Program Management Team 2. Design Build (DB) contractor selection process and timeline 3. Latest

More information

Table of Contents. City of Redlands - Redlands Crossing Center

Table of Contents. City of Redlands - Redlands Crossing Center City of Redlands - Redlands Crossing Center Executive Summary... ES-1 Section 1: Introduction...1-1 1.1 - Overview of the CEQA Process...1-1 1.2 - Scope of the EIR...1-5 1.3 - Organization of the EIR...1-8

More information

TABLE OF CONTENTS ES EXECUTIVE SUMMARY 1.0 INTRODUCTION 2.0 PROJECT DESCRIPTION 3.0 ENVIRONMENTAL ANALYSIS

TABLE OF CONTENTS ES EXECUTIVE SUMMARY 1.0 INTRODUCTION 2.0 PROJECT DESCRIPTION 3.0 ENVIRONMENTAL ANALYSIS ES EXECUTIVE SUMMARY ES1 ES2 ES3 ES4 ES5 Purpose and Scope of the Environmental Impact Report... ES-1 Project Summary... ES-1 Project Alternatives Summary... ES-1 Areas of Controversy/Issues to be Resolved...

More information

South Sounder Capital Improvements Program

South Sounder Capital Improvements Program Subarea South King/Pierce Primary Mode Commuter Rail Facility Type Infrastructure Improvement Length Date Last Modified July 1, 2016 PROJECT AREA AND REP RESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION

More information

Rail & Transit Alternatives Analysis. NH Capitol Corridor. Public Scoping Meeting. March 5, 2014

Rail & Transit Alternatives Analysis. NH Capitol Corridor. Public Scoping Meeting. March 5, 2014 NH Capitol Corridor Rail & Transit Alternatives Analysis Public Scoping Meeting March 5, 2014 Agenda Study overview National Environmental Policy Act Preliminary alternatives: rail, bus, stations, layover

More information

6 CHARTING PERFORMANCE

6 CHARTING PERFORMANCE DRAFT 6 CHARTING PERFORMANCE OVERVIEW OF PERFORMANCE BASED PLANNING Background of Performance Based Planning Increasingly, over the past two decades, transportation agencies have been utilizing performance

More information

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11 Contents i Contents 1 A New Transportation Plan... 1 Why develop a new plan?... 1 What area does the LRTP focus on?... 2 Why is this LRTP important?... 3 Meeting Requirements for Transportation Planning...

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 945

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 945 I-441-001 Thank you for your comments about the importance of the Latvian Center to the Latvian community. Following the Draft EIS, the Sound Transit Board directed Sound Transit to develop a Preferred

More information

S-16: Sounder Rail Extension from Puyallup to Orting

S-16: Sounder Rail Extension from Puyallup to Orting Project Number S-16 Subarea Pierce Primary Mode Commuter Rail Facility Type Corridor Length 5.7 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT

More information

Green Line Extension Project. March 28, 2018 Public Information Meeting

Green Line Extension Project. March 28, 2018 Public Information Meeting Green Line Extension Project 1 Agenda GLX Project-Wide Public Meeting March 7, 2018; 6:30 PM 8:00 PM 1. Welcome/Introductions Martin Nee (MBTA Stakeholder Support) 2. Project Update John Dalton (MBTA Program

More information

Somerville Public Meeting, October 23, Somerville High School October 23, 2017

Somerville Public Meeting, October 23, Somerville High School October 23, 2017 Somerville Public Meeting, 1 Agenda Somerville GLX Public Meeting ; 6:30 PM 8:00 PM 1. Welcome/Introductions Martin Nee 2. Project Update MBTA Program Manager John Dalton 3. Early Works Construction Overview

More information

CHAPTER 2 DESIGN REFINEMENTS

CHAPTER 2 DESIGN REFINEMENTS CHAPTER 2 DESIGN REFINEMENTS 2.1 INTRODUCTION Since publication of the Draft 2 nd Supplemental Environmental Impact Report (SEIR-2), additional design refinements have been identified. Some of these refinements

More information

San Ramon City Center Draft Subsequent EIR

San Ramon City Center Draft Subsequent EIR San Ramon City Center State Clearinghouse Number 2007042022 Prepared for: City of San Ramon Planning/Community Development Department Planning Services Division 2222 Camino Ramon San Ramon, CA 94583 Prepared

More information

MBTA Green Line Extension Noise and Vibration Technical Report

MBTA Green Line Extension Noise and Vibration Technical Report MBTA Green Line Extension Noise and Vibration Technical Report Environmental Assessment HMMH Report No. 302580.000 January, 2011 Prepared for: Vanasse Hangen & Brustlin, Inc. 99 High Street Boston, MA

More information

Final Supplemental Environmental Impact Statement

Final Supplemental Environmental Impact Statement Final Supplemental Environmental Impact Statement April 2014 City of Seattle Department of Transportation 700 Fifth Avenue, Suite 3900 Seattle, WA 98124 TABLE OF CONTENTS Elliott Bay Seawall Project TABLE

More information

TABLE OF CONTENTS Watson Ranch Specific Plan Draft Environmental Impact Report

TABLE OF CONTENTS Watson Ranch Specific Plan Draft Environmental Impact Report TABLE OF CONTENTS Watson Ranch Specific Plan Draft Environmental Impact Report 1. Introduction 1-1 1.1 Project Overview 1-1 1.2 Purpose of Environmental Impact Report 1-1 1.3 Lead Agency and Responsible

More information

DRAFT ENVIRONMENTAL IMPACT STATEMENT AND DRAFT SECTION

DRAFT ENVIRONMENTAL IMPACT STATEMENT AND DRAFT SECTION DRAFT ENVIRONMENTAL IMPACT STATEMENT AND DRAFT SECTION 4(f) EVALUATION APPENDIX 4 Analysis Framework 4-1: CEQR Technical Area Guide DRAFT ENVIRONMENTAL IMPACT STATEMENT AND DRAFT SECTION 4(f) EVALUATION

More information

A. INTRODUCTION B. NOISE ANALYSIS METHODOLOGY

A. INTRODUCTION B. NOISE ANALYSIS METHODOLOGY Chapter 8: and Vibration A. INTRODUCTION This chapter assesses the potential noise impacts resulting from operation of the proposed Wyandanch Intermodal Transit Facility by comparing existing noise levels

More information

Environmental Setting

Environmental Setting Section 5.2 Environmental Justice This section describes the potential of the proposed changes to the approved project to result in disproportionately high and adverse health or environmental effects on

More information

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report Notice of Preparation For Link Union Station (Link US) Project Joint Environmental Impact Statement and Environmental Impact Report Date: May 27, 2016 To: Subject: Project Title: From: All Interested Agencies,

More information

Taylorsville-Murray Transit

Taylorsville-Murray Transit Taylorsville-Murray Transit Environmental Study Report April 2013 Prepared for Table of Contents Acronyms & Abbreviations... iv Executive Summary... ES 1 Chapter 1: Purpose and Need 1.1 Project Description...

More information

South Sounder Capital Improvements Program

South Sounder Capital Improvements Program South Sounder Capital Improvements Program Subarea South King/Pierce Primary Mode Commuter Rail Facility Type Infrastructure Improvement Length Version Draft ST3 Plan Date Last Modified March 28, 2016

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 216

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 216 C-013-001 Thank you for your comments describing the cultural importance of the Latvian Evangelical Lutheran Church to the Latvian community in western Canada. See Section 2.5.1 for a description of the

More information

GLX Project AUGUST 2 4 FMCB MEETING

GLX Project AUGUST 2 4 FMCB MEETING GLX Project Green Line Extension Project AUGUST 2 4 FMCB MEETING Presentation Overview 1) Project Essentials 2) Funding the Green Line Extension Project 3) The Construction Manager/General Contractor Procurement

More information

Environmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS).

Environmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS). This document is scheduled to be published in the Federal Register on 11/18/2015 and available online at http://federalregister.gov/a/2015-29418, and on FDsys.gov DEPARTMENT OF TRANSPORTATION Federal Transit

More information

Appendix G Analysis of Project Impacts Compared to Existing Conditions

Appendix G Analysis of Project Impacts Compared to Existing Conditions Appendix G Analysis of Project Impacts Compared to Existing Conditions This page intentionally left blank. Analysis of Project Impacts Compared to Existing Conditions Introduction The analysis scenarios

More information

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK

CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK MTP VISION In order to create a framework for the 2040 Metropolitan Transportation Plan (MTP), a vision statement was drafted by the Vision/Goals Committee and

More information

6.0 Indirect Effects and Cumulative Impacts

6.0 Indirect Effects and Cumulative Impacts 6.0 Effects and Impacts 6.1 Introduction This chapter of the Draft EIS addresses potential indirect and cumulative impacts of the Bottineau Transitway project. effects are those that are caused by the

More information

Willmar Wye Public Open House #4 and Public Hearing

Willmar Wye Public Open House #4 and Public Hearing Willmar Wye Public Open House #4 and Public Hearing February 23, 2017 www.dot.state.mn.us/d8/willmarwye Agenda Time Topic 5:00 pm Open House Opportunity for the public to ask questions of project staff

More information

Facebook Campus Project. City Council Study Session January 31, 2012

Facebook Campus Project. City Council Study Session January 31, 2012 Facebook Campus Project City Council Study Session January 31, 2012 Meeting Purpose Opportunity for the City Council to become familiar with project and reports released to date Opportunity for the City

More information

9 Before and After Study Plan

9 Before and After Study Plan 9 Before and After Study Plan A Before and After Study Plan has been prepared, describing how the Massachusetts Bay Transportation Authority (MBTA), in cooperation with the Massachusetts Department of

More information

Inglewood Oil Field Specific Plan Project Draft Environmental Impact Report

Inglewood Oil Field Specific Plan Project Draft Environmental Impact Report Draft Environmental Impact Report SCH No. 2015101030 Prepared for: City of Culver City Planning Division 9770 Culver Boulevard Culver City, California 90232 Prepared by: Psomas 225 South Lake Avenue Suite

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM BOSTON REGION METROPOLITAN PLANNING ORGANIZATION State Transportation Building Ten Park Plaza, Suite 2150 Boston, MA 02116-3968 Tel. (617) 973-7100 Fax (617) 973-8855 TTY (617) 973-7089 www.bostonmpo.org

More information

Federal Way Transit Center to Tacoma Dome Light Rail

Federal Way Transit Center to Tacoma Dome Light Rail Subarea South King/Pierce Primary Mode Light Rail Facility Type Corridor Length 9.7 miles Date Last Modified July 1, 2016 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION This project

More information

CHAPTER 7. Illustrative Scenarios

CHAPTER 7. Illustrative Scenarios CHAPTER Illustrative Scenarios As mentioned in Chapter, this PMT presents and evaluates three scenarios state-of-good-repair (SGR), enhancement, and expansion that illustrate possible capital investment

More information

Federal Transit Administration s New Starts Process. Red Line Extension Alternatives Analysis Study

Federal Transit Administration s New Starts Process. Red Line Extension Alternatives Analysis Study Federal Transit Administration s New Starts Process Red Line Extension Alternatives Analysis Study DRAFT Schedule for Tonight s Meeting Structure of the meeting Questions and answers process Submit your

More information

LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17

LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17 LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17 1 PROJECT TEAM & COLLABORATORS 2 OPEN HOUSE SERIES Tuesday, May 16, 2017 6-8:00 pm La Verne City Council Chambers 3660 D Street La

More information

EVALUATION OF ALTERNATIVES CARRIED FORWARD

EVALUATION OF ALTERNATIVES CARRIED FORWARD 1 EVALUATION OF ALTERNATIVES CARRIED FORWARD This chapter presents a comparative evaluation of the alternatives carried forward in this Final Environmental Impact Statement (EIS). The intent of this evaluation

More information

ALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS

ALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS FINAL REPORT SEPTEMBER 2010 TABLE OF CONTENTS 1.0 INTRODUCTION 1 2.0 EXISTING TRAFFIC CONDITIONS 2 3.0 FUTURE TRAFFIC CONDITIONS 3 4.0 POTENTIAL IMPACTS

More information

C-01c: Downtown Seattle to Ballard (Market Street vicinity) LRT, primarily elevated/tunnel options

C-01c: Downtown Seattle to Ballard (Market Street vicinity) LRT, primarily elevated/tunnel options Project Number C-01c Subarea North King Primary Mode Light Rail Facility Type Corridor Length 7.5 miles Version Number ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT

More information

Appendix H Mitigation Plan

Appendix H Mitigation Plan Appendix H Appendix H The mitigation plan for Federal Way Link Extension (FWLE) describes Sound Transit s mitigation commitments that will be implemented to avoid or minimize the impacts of the Preferred

More information

WAL-MART EXPANSION STORE NO , WARSAW, NY

WAL-MART EXPANSION STORE NO , WARSAW, NY DRAFT ENVIRONMENTAL IMPACT STATEMENT WAL-MART EXPANSION STORE NO. 2043-04, WARSAW, NY 2348 NYS Route 19 Town of Warsaw Wyoming County, New York Project Sponsor / Applicant: Wal-Mart Stores, Inc. 2001 S.E.

More information

Corridor Advisory Group and Task Force Meeting #2

Corridor Advisory Group and Task Force Meeting #2 January 19, 2010 www.eisenhowerexpressway.com 1 Corridor Advisory Group and Task Force Meeting #2 January 19, 2010 January 19, 2010 www.eisenhowerexpressway.com 2 Introductions Where We Are Now? Process

More information

High Desert Corridor Draft EIS/EIR Public Hearings

High Desert Corridor Draft EIS/EIR Public Hearings High Desert Corridor Draft EIS/EIR Public Hearings Agenda > Registration/Open House (6pm 6:30pm) > Draft EIS/EIR Presentation (6:30pm 7pm) > Public Comment (7pm 8:30pm) Purpose of Today s Hearing > Provide

More information

Final Environmental Impact Report San Marcos General Plan

Final Environmental Impact Report San Marcos General Plan Final Environmental Impact Report San Marcos General Plan State Clearinghouse # 2011071028 February 2012 Lead Agency: City of San Marcos 1 Civic Center Drive San Marcos, CA 92069 V A L L E Y O F D I S

More information

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1

More information

2017 Countywide Comprehensive Transportation Plan. Transportation Plan. Draft Environmental Impact Report. Volume

2017 Countywide Comprehensive Transportation Plan. Transportation Plan. Draft Environmental Impact Report. Volume 2017 Countywide Comprehensive Transportation Plan Draft Environmental Impact Report 2017 Countywide Comprehensive Transportation Plan State Clearinghouse #2017022054 ic l b ew u P vi t Rer a f D Volume

More information

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT Date: September 18, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS H201 Sacramento,

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION PLANNING ORGANIZATIO BOSTON REGION MPO NMETROPOLITAN BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,

More information

11 Joint Development Regulatory Context and Methodology

11 Joint Development Regulatory Context and Methodology 11 Joint Development This chapter describes the long-term direct and potential indirect impacts, and short-term direct and potential indirect impacts, of the proposed METRO Blue Line Light Rail Transit

More information

Ashland. Environmental Assessment Bus Rapid Transit. November Prepared for: The Federal Transit Administration 79th. Prepared by.

Ashland. Environmental Assessment Bus Rapid Transit. November Prepared for: The Federal Transit Administration 79th. Prepared by. Irving Park Addison Roscoe Belmont in partnership with Diversey Fullerton Cortland North Chicago Grand Lake Madison Jackson Harrison Polk Roosevelt 18th Blue Island 31st 35th Environmental Assessment Bus

More information

Cumulative and Secondary Impacts

Cumulative and Secondary Impacts Chapter 14: Cumulative and Secondary Impacts A. INTRODUCTION SEQRA regulations require the consideration of the Proposed Project s potential to result in cumulative impacts (6 NYCRR 617.9(b)(5)(a)) and

More information

DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CONTENTS CENTINELA SOLAR ENERGY PROJECT

DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CONTENTS CENTINELA SOLAR ENERGY PROJECT CONTENTS DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CENTINELA SOLAR ENERGY PROJECT CHAPTER 1.0 INTRODUCTION 1.1 PURPOSE OF THE DOCUMENT... 1.0 1 1.2 PROJECT BACKGROUND... 1.0 1 1.3 Project

More information

Northwest State Route 138 Corridor Improvement Project

Northwest State Route 138 Corridor Improvement Project Northwest State Route 138 Corridor Improvement Project Los Angeles County, CA DISTRICT 7- LA- 138 (PM 0.0/36.8); DISTRICT 7- LA- 05 (PM 79.5/83.1); DISTRICT 7- LA- 14 (PM 73.4/74.4) 265100/ 0700001816

More information

Going Forward The Plan to Maintain & Improve Mobility Frequently Asked Questions (FAQs)

Going Forward The Plan to Maintain & Improve Mobility Frequently Asked Questions (FAQs) Going Forward The Plan to Maintain & Improve Mobility Frequently Asked Questions (FAQs) What is Going Forward The Plan to Maintain & Improve Mobility (Plan) and why does the region need a Long Range Transportation

More information

County of El Dorado. El Dorado Hills Apartments Project Draft Environmental Impact Report. SCH No Prepared For: Prepared by:

County of El Dorado. El Dorado Hills Apartments Project Draft Environmental Impact Report. SCH No Prepared For: Prepared by: County of El Dorado El Dorado Hills Apartments Project Draft Environmental Impact Report SCH No. 2017042017 Prepared by: 505 14th Street, Suite 1230 Oakland, California 94612 Prepared For: County of El

More information

Environmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX

Environmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX This document is scheduled to be published in the Federal Register on 10/06/2014 and available online at http://federalregister.gov/a/2014-23711, and on FDsys.gov [4910-22] DEPARTMENT OF TRANSPORTATION

More information

Environmental Assessment May 2007

Environmental Assessment May 2007 jurisdictional waters. It is assumed that, at a minimum, a USACE Section 404 Nationwide Permit would be necessary to construct these features. The impacts of the fill into the floodplain cannot be fully

More information

Future Build Alternative Traffic Forecasts and Level of Service Analysis

Future Build Alternative Traffic Forecasts and Level of Service Analysis 4.2.10 Future Build Alternative Traffic Forecasts and Level of Service Analysis For the five Build Alternatives, study intersections within one mile of potential station locations were analyzed, as it

More information