Table of Contents. Green Line Extension Project. Draft Environmental Impact Report/Environmental Assessment and Draft Section 4(f) Evaluation
|
|
- Giles Baldwin
- 5 years ago
- Views:
Transcription
1 Table of Contents Acronyms and Abbreviations Secretary s Certificate on the EENF Executive Summary 1 Introduction and Background Introduction Project Summary Permits and Approvals Consistency with Federal, State, and Local Planning Public Involvement and Agency Coordination Requirements of Secretary's Certificate Purpose and Need Overview Project Purpose Need for Transit Improvements Goals and Objectives Alternatives Introduction No-Build Alternative Project Elements Ridership Methodology Baseline Alternative Build Alternatives Project Description Preferred Alternative Community Paths Coordination with Regional Projects Summary Affected Environment Introduction Land Use Socioeconomic Conditions Environmental Justice Existing Transportation Systems Traffic Table of Contents i Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009
2 4.7 Air Quality Noise Vibration Stormwater Wetlands Fish, Wildlife and Plants Parks and Recreation Visual Environment Historic and Archaeological Resources Hazardous Materials Environmental Consequences Introduction Land Use Socioeconomic Impacts Environmental Justice Traffic Air Quality Noise Vibration Stormwater Fish, Wildlife, and Plants Parks and Recreation Areas Visual Environment Historic and Archaeological Resources Hazardous Materials Indirect and Cumulative Effects Draft Section 61 Findings and Mitigation Commitments Introduction Project Benefits Project Mitigation Construction Period Mitigation Proposed Section 61 Findings Distribution List Federal Agencies and Elected Officials State and Regional Agencies and Elected Officials Municipalities Libraries Advisory Group Members Additional EENF Commenters and Other Interested Parties Figures... VOLUME 2 Table of Contents ii Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009
3 Appendix A: Responses to Comments on the EENF... VOLUME 3 Appendix B Appendix J... on CD Appendix B: Station and Alignment Selection Analysis Appendix C: Green Line Support Facility Alternatives Analysis Appendix D: Travel Demand Modeling Methodology Appendix E: Plans and Feasibility Analysis for Proposed Community Paths Appendix F: Traffic Analysis Appendix G: Transit Access for Environmental Justice and Disability Populations Appendix H: Air Quality Analysis Appendix I: Draft Section 4(f) Evaluation Appendix J: Draft Memorandum of Agreement Table of Contents iii Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009
4 List of Tables Table No. Description Page 1-1 Comparison of DEIR/EA Build Alternatives Meeting Summary (as of August 5, 2009) Requirements of the Secretary s Certificate Estimated Enhanced Route 80 Travel Time Alternative 1: Medford Branch Travel Times Alternative 2: Medford Branch Travel Times Alternative 3: Medford Branch Travel Times Alternative 4: Medford Branch Travel Times Alternative 5: Medford Branch Travel Times Build Alternative Evaluation Land Acquisition Summary Travel Times for the Preferred Alternative Pinch Points for Somerville Community Path Population, Housing and Employment within ½-Mile Radius of the Relocated Lechmere Station Site Population, Housing and Employment within ½-Mile Radius of the Brickbottom Station Site Population, Housing and Employment within ½-Mile Radius of the Gilman Square Station Site Population, Housing and Employment within ½-Mile Radius of the Lowell Street Station Site Population, Housing and Employment within ½-Mile Radius of the Ball Square Station Site Population, Housing and Employment within ½-Mile Radius of the College Avenue Station Site Population, Housing and Employment within ½-Mile Radius of the Mystic Valley Parkway/Route 16 Station Site Population, Housing and Employment within ½-Mile Radius of the Union Square Station Site Social and Economic Statistics for Cambridge, Somerville, and Medford State-Listed Environmental Justice Areas in Cambridge, Somerville, and Medford State-Listed Environmental Justice Populations in Cambridge, Somerville, and Medford Minority Populations in Cambridge, Somerville, Medford, and Middlesex County Span of Service Standards Minimum Frequency of Service Standards Bus Service Frequency and Ridership Table of Contents iv Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009
5 Table No. Description Page MBTA Bus Loading Standards Summary of Bus Schedule Adherence Standards Bus Cost-Effectiveness Service Standard MBTA Lowell Line Daily Weekday Boardings by Station MBTA Fitchburg Line Daily Weekday Boardings by Station Existing Daily Traffic Volumes on Study Area Roadways Vehicular Level of Service Thresholds Existing Condition Signalized Intersection Traffic Operations Existing Condition Unsignalized Intersection Traffic Operations Pedestrian Level of Service Thresholds Existing Condition Pedestrian Level-of-Service Parking Inventory Restricted Parking Allocation Existing Noise Measurement Results Existing Park and Recreation Areas within the Study Area Land Acquisitions for Extension to Medford Hillside Land Acquisitions for Extension to Union Square (via commuter rail right-of-way) Land Acquisitions for Extension to Mystic Valley Parkway/Route Land Acquisitions for Extension to Union Square (via McGrath Highway/Route 28 and Somerville Avenue) Summary of Land Acquisitions by Alternative Property Tax Effects for Alternative Property Tax Effects for Alternative Property Tax Effects for Alternative Property Tax Effects for Alternative Property Tax Effects for Alternative Property Tax Effects for Alternative Property Taxes of Real Estate Acquired For Each Alternative Property Tax Decreases by City Estimated Job Decreases or Relocations Changes in Transit Access for Disability and Environmental Justice Populations under the Baseline Alternative Changes in Transit Access for Disability and Environmental Justice Populations under a Light Rail Extension to Mystic Valley Parkway/Route 16 and Union Square Building Acquisitions and Local Demographics for Extension to Medford Hillside Building Acquisitions and Local Demographics for Extension to Union Square (via commuter rail right-of-way) Building Acquisitions and Local Demographics for Extension to Mystic Valley Parkway/Route Building Acquisitions and Local Demographics for Extension to Union Square via McGrath Highway and Somerville Avenue Summary of Project Impacts in Environmental Justice Areas No-Build Alternative Signalized Intersection Traffic Operations Results No-Build Alternative Unsignalized Intersection Traffic Operations Results Table of Contents v Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009
6 Table No. Description Page Baseline Alternative Signalized Intersection Traffic Operations Results Baseline Alternative Unsignalized Intersection Traffic Operations Results Alternative 1 Peak Hour Trip Summary by Station Alternative 1 Signalized LOS Summary Comparison Alternative 1 Unsignalized LOS Summary Comparison Alternative 2 Peak Hour Trip Summary by Station Alternative 2A (with parking) Signalized LOS Summary Comparison Alternative 2A (with parking) Unsignalized Intersection Traffic Operations Results Alternative 3 Peak Hour Trip Summary by Station Alternative 3 Signalized Intersection Traffic Operations Results Alternative 4 Peak Hour Trip Summary by Station Alternative 4 Signalized Intersection Traffic Operations Results Alternative 5 Peak Hour Trip Summary by Station Alternative 5 Signalized Intersection Traffic Operations Results Alternative 6 Peak Hour Trip Summary by Station Alternative 6 Signalized Intersection Traffic Operations Results Proposed Pedestrian Mitigation Measures Summary of Traffic Impacts and Mitigation National Ambient Air Quality Standards Predicted Maximum 1-Hour CO Concentrations (Parts Per Million) Predicted Maximum 8-Hour CO Concentrations (Parts Per Million) Predicted Maximum 24-Hour PM10 Concentrations (Parts Per Million) Predicted Maximum 24-Hour PM2.5 Concentrations (Parts Per Million) Predicted Maximum Annual PM2.5 Concentrations (Parts Per Million) Projected PM2.5 Emissions for Proposed Commuter Rail Track Relocation (ug/m 3 ) Mesoscale 2030 Mobile Source Analysis Results (kilograms per day) Greenhouse Gas (CO2) Analysis Results (kilograms per day) EOT Air Quality Analysis Comparison of Project Packages Benefits in the Year Comparison of Air Quality Benefits Potential Noise Impacts Without Mitigation for Alternatives 1, 2, 3, and Potential Noise Impacts Without Mitigation for Alternatives 5 and Summary of Potential Noise Impacts Summary of Proposed Noise Barrier Mitigation FTA Ground-Borne Noise and Vibration Impact Criteria FTA Ground-Borne Noise and Vibration Impact Criteria for Special Buildings Vibration Criteria for Detailed Analysis Potential Vibration Impacts at Sensitive Receptors Without Mitigation Summary of Potential Vibration Impact Summary of Proposed Vibration Mitigation Potential Vibration Mitigation Measures for Crossovers and Turnouts Impervious Surface Changes by Station Summary of Impervious Surface Changes by Alternative Table of Contents vi Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009
7 Table No. Description Page Direct Vegetated Habitat Impacts by Alternative Potential Impacts to Archaeologically Sensitive Areas RECs and Potential Impacts for Alternatives 1 and 3 - Extension to Medford Hillside RECs and Potential Impacts for Alternatives 1, 2, and 6 - Extension to Union Square (via commuter rail right-of-way) RECs and Potential Impacts for Alternatives 2, 4, and 5 - Extension to Route 16/Mystic Valley Parkway RECs and Potential Impacts for Alternatives 3 and 4 Extension to Union Square via McGrath Highway/Route 28 and Somerville Avenue RECs and Potential Impacts for Alternative 6 Yard 8 Maintenance Facility Summary of RECs and their Impacts by Alternative Cambridge, Somerville, Medford, and Station Area Populations (2000 and 2030) TOD Potential at Proposed Station Sites TOD Potential by Alternative Rail System Benefits on Real Estate Values Populations of Cambridge, Somerville and Medford (2000 and 2006) Projected Population and Employment Within ½- Mile of Proposed Station Sites (2010 and 2030) Proposed and Reasonably Foreseeable Projects in the Project Corridor Project Mitigation Commitments Summary of Construction Mitigation Measures Possible Permits or Approvals Table of Contents vii Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009
8 List of Figures All figures are provided in Volume 2 except as indicated otherwise below. Figure Description Page 1-1 Study Area Station Locus Map (Sheet 1 of 2) Station Locus Map (Sheet 2 of 2) Maintenance Facility Initial Site Alternatives Preferred Maintenance Facility Site Baseline Alternative Alternative Alternative Alternative Alternative Alternative Alternative Proposed Project Relocated Lechmere Station Station Layout Relocated Lechmere Station Station Plan Relocated Lechmere Station Circulation Relocated Lechmere Station Elevation Brickbottom Station Station Layout Brickbottom Station Station Plan Brickbottom Station Circulation Brickbottom Station Elevation Gilman Square Station Station Layout Gilman Square Station Station Plan Gilman Square Station Circulation Gilman Square Station Elevation Lowell Street Station Station Layout Lowell Street Station Station Plan Lowell Street Station Circulation Lowell Street Station Elevation Ball Square Station Station Layout Ball Square Station Station Plan Ball Square Station Circulation Ball Square Station Elevation College Avenue Station Medford Hillside Terminus (Alt 1, 3) Station Layout College Avenue Station (Alt 2, 4, 5) Station Layout College Avenue Station Station Plan College Avenue Station Circulation College Avenue Station Elevation Table of Contents viii Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009
9 Figure Description Page Mystic Valley Parkway/Route 16 Station Station Layout Mystic Valley Parkway/Route 16 Station Station Plan Mystic Valley Parkway/Route 16 Station Circulation Mystic Valley Parkway/Route 16 Station Elevation Union Square Station Station Layout Union Square Station Station Plan Union Square Station Circulation Union Square Station Elevation Existing Section Looking North (in text) Proposed Section Looking North (in text) Typical Construction Staging (Sheet 1 of 2) Typical Construction Staging (Sheet 2 of 2) Typical Section of Somerville Community Path (in text) Existing Conditions (Sheet 1 of 10) Existing Conditions (Sheet 2 of 10) Existing Conditions (Sheet 3 of 10) Existing Conditions (Sheet 4 of 10) Existing Conditions (Sheet 5 of 10) Existing Conditions (Sheet 6 of 10) Existing Conditions (Sheet 7 of 10) Existing Conditions (Sheet 8 of 10) Existing Conditions (Sheet 9 of 10) Existing Conditions (Sheet 10 of 10) Existing Land Use Index Existing Land Use Existing Lechmere Station Existing Land Use Brickbottom Station Existing Land Use Gilman Square Station Existing Land Use Lowell Street Station Existing Land Use Ball Square Station Existing Land Use College Avenue Station Existing Land Use Mystic Valley Parkway/Route 16 Station Existing Land Use Union Square Station Primary Use Zoning Cities of Somerville, Medford, and Cambridge State-Defined Environmental Justice Populations Existing and Proposed MBTA Bus and Transit System Existing MBTA Commuter Rail Routes Existing Freight Rail Routes Traffic Study Intersections Microscale Air Quality Study Intersections Typical A-Weighted Sound Levels (in text) Examples of Typical Outdoor Noise Exposure (in text) Noise and Vibration Measurement Sites Typical Ground-Borne Vibration Levels and Criteria (in text) Existing Vibration Measurement Results (in text) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 1 of 10) Table of Contents ix Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009
10 Figure Description Page Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 2 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 3 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 4 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 5 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 6 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 7 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 8 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 9 of 10) Location of Historic Resources Identified within the Green Line Extension Project APE (Sheet 10 of 10) Proposed Property Acquisitions Lechmere Station Proposed Property Acquisitions Brickbottom Station Proposed Property Acquisitions Gilman Square Station Proposed Property Acquisitions Lowell Street Station Proposed Property Acquisitions Ball Square Station Proposed Property Acquisitions College Avenue Station Proposed Property Acquisitions Mystic Valley Parkway/ Route 16 Station Proposed Property Acquisitions Union Square Station (Fitchburg Corridor Alternative) Proposed Property Acquisitions Union Square Station (In-Street Running Alternative) Mesoscale 2030 Mobile Source Analysis Results (kilograms per day) (in text) Mobile Source Air Toxics Emissions (in text) Increase in Cumulative Noise Allowed by FTA Criteria (in text) Noise Impacts and Mitigation Measures (Sheet 1 of 5) Noise Impacts and Mitigation Measures (Sheet 2 of 5) Noise Impacts and Mitigation Measures (Sheet 3 of 5) Noise Impacts and Mitigation Measures (Sheet 4 of 5) Noise Impacts and Mitigation Measures (Sheet 5 of 5) Examples of Noise Barrier Materials (in text) Criteria for Detailed Vibration Analysis (in text) Vibration Impacts and Mitigation Measures (Sheet 1 of 5) Vibration Impacts and Mitigation Measures (Sheet 2 of 5) Vibration Impacts and Mitigation Measures (Sheet 3 of 5) Vibration Impacts and Mitigation Measures (Sheet 4 of 5) Vibration Impacts and Mitigation Measures (Sheet 5 of 5) Proposed Stormwater Drainage Proposed and Reasonably Foreseeable Projects Table of Contents x Prepared by Vanasse Hangen Brustlin, Inc. 10/15/2009
Green Line extension Project Fall 2009
Introduction The Massachusetts Department of Transportation (MassDOT) is proposing to extend the Green Line to improve transit service, mobility, and regional access for residents and visitors of Cambridge,
More information6 Draft Section 61 Findings and Mitigation Commitments
6 Draft Section 61 Findings and Mitigation Commitments 6.1 Introduction This chapter presents the proposed mitigation program of the Executive Office of Transportation (EOT) to address adverse environmental
More informationBOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM. DATE January 21, 2010
BOSTON REGION METROPOLITAN PLANNING ORGANIZATION State Transportation Building Ten Park Plaza, Suite 2150 Boston, MA 02116-3968 Tel. (617) 973-7100 Fax (617) 973-8855 TTY (617) 973-7089 www.bostonmpo.org
More informationGreen Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY. November 20, 2017 Public Information Meeting
Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY Purpose of tonight s meeting A Notice of Project Change (NPC) has been published for a possible extension of the Green Line from College Avenue to Mystic
More informationGreen Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session
Green Line Extension Environmental Impact Report Public Scoping Session Somerville High School October 16, 2006 Project Location Green Line Extension Project Purpose Implement enhancements to transit services
More informationKatherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116
Comments on this Environmental Assessment (EA) and may be submitted in writing to: Katherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116 Comments must
More informationIdentification and Evaluation of Alternatives Tier 1
Vanasse Hangen Brustlin, Inc. DRAFT 4 Identification and Evaluation of Alternatives Tier This chapter describes the initial set of alternatives that were identified to address the Purpose and Need of the
More informationVanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices
DRFT ppendices MIS 8-05 - ppendices ppendices ugust 005 [THIS PGE INTENTIONLLY LEFT BLNK] DRFT ppendix Tier Detailed Evaluation Tables MIS 8-05 - ppendix ppendix ugust 005 [THIS PGE INTENTIONLLY LEFT BLNK]
More informationWyandanch Intermodal Transit Facility
Wyandanch Intermodal Transit Facility Environmental Assessment July 2010 Prepared by: The United States Department of Transportation Federal Transit Administration in cooperation with The Town of Babylon
More informationGREEN LINE EXTENSION PROJECT
GREEN LINE EXTENSION PROJECT RETAINING WALLS & NOISE BARRIERS AGENDA Upcoming Meeting Schedule Wall Aesthetics/ Design FTA Guidelines for Assessing & Mitigating Noise Impact Plans & Cross Sections Typical
More informationLONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION
LONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Volume I September 22, 2011 The Boston Region Metropolitan Planning Organization (MPO) is composed of: Massachusetts
More informationLONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT
LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT Project Name: Project Location: Lead Agency & Contact Person: SEQRA Classification: Project Sponsors:
More information12 Evaluation of Alternatives
12 Evaluation of Alternatives This chapter evaluates the effectiveness of the No-Build Alternative and the proposed METRO Blue Line Light Rail Transit (BLRT) Extension project based on the information
More informationRiver Valley. Intermodal Facilities. February Prepared by: Federal Highway Administration Draft Environmental Impact Statement
Prepared by: River Valley Intermodal Facilities Federal Highway Administration Draft Environmental Impact Statement River Valley Regional Intermodal Facilities Authority February 2006 and Arkansas State
More informationHamilton Green. Draft Environmental Impact Statement (DEIS)
Hamilton Green Draft Environmental Impact Statement (DEIS) June 2017 HAMILTON GREEN DRAFT ENVIRONMENTAL IMPACT STATEMENT (DEIS) June 14, 2017 Lead Agency: SEQRA Classification: City of White Plains Common
More informationContents. S. Executive Summary... ES Overview of Purpose & Need
Contents S. Executive Summary... ES-1 S.1 Introduction... ES-1 S.2 Purpose of this Study... ES-3 S.3 Background... ES-6 S.4 Purpose and Need for Transit Investment... ES-10 S.5 Community Input Process...
More informationAgenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014
Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend
More informationEvaluation of Alternatives
Chapter 9.0 Evaluation of Alternatives Chapter 9.0 provides a summary evaluation of the No Build Alternative and the Preferred Alternative. The evaluation contained within this chapter is an assessment
More informationLynnwood Link Extension 2013 Draft EIS Comments and Responses
Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,
More informationRevised Final Environmental Impact Report/ Environmental Assessment for the Wilshire Bus Rapid Transit Project
Revised Final Environmental Impact Report/ Environmental Assessment for the Wilshire Bus Rapid Transit Project State Clearinghouse No. 2009091094 Los Angeles County Metropolitan Transportation Authority
More informationDraft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements
JUNE 2016 RONALD REAGAN WASHINGTON NATIONAL AIRPORT Draft Environmental Assessment Terminal B/C Redevelopment, Secure National Hall, and Related Improvements PREPARED BY: Ricondo & Associates, Inc. IN
More informationPROJECT DESCRIPTION...
TABLE OF CONTENTS Volume I Chapter Page 1. INTRODUCTION... 1-1 1.1 Introduction... 1-1 1.2 Project Description... 1-1 1.3 Purpose of the EIR... 1-2 1.4 EIR Process... 1-3 1.5 Scope of the Draft EIR...
More informationChapter 5 Transportation Draft
Chapter 5 Transportation Draft Discussion Similar to the other elements in the Comprehensive Plan, the transportation element impacts the quality of life, economic development and public safety of the
More informationPacific Wind Energy Project Draft Environmental Impact Report
Pacific Wind Energy Project Table of Contents VOLUME 1 1 Executive Summary... 1-1 1.1 Introduction... 1-1 1.2 Project Summary... 1-1 1.3 Purpose and Use of the Draft EIR... 1-4 1.4 Project Overview...
More informationBENNING ROAD & BRIDGES
BENNING ROAD & BRIDGES DRAFT JUNE 2015 TRANSPORTATION IMPROVEMENTS ENVIRONMENTAL ASSESSMENT DRAFT MAY 2016 EXECUTIVE SUMMARY ES-1 This page left intentionally blank This page left intentionally blank
More informationNorthern Branch Corridor CLC Meeting. June 30, 2008
Northern Branch Corridor CLC Meeting June 30, 2008 Agenda Introductions Project Status Environmental Process Technical Findings Capital Costs Next Steps Break Out Areas Introductions Project Status Preliminary
More informationImpact Assessment Methodology for the. Somerville Public Library August 4, 2008 Jason Ross, P.E. Harris Miller Miller & Hanson Inc.
Noise and Vibration Impact Assessment Methodology for the MBTA Green Line Extension P j t Project Presentation to the Advisory Group Meeting Meeting Somerville Public Library August 4, 2008 Jason Ross,
More informationSounder Extension to DuPont
Subarea Pierce Primary Mode Commuter Rail Facility Type Station Length 7.8 miles Version Draft ST3 Plan Date Last Modified March 28, 2016 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION
More informationDraft Supplemental Environmental Impact Statement
Draft Supplemental Environmental Impact Statement December 2013 City of Seattle Department of Transportation 700 Fifth Avenue, Suite 3900 Seattle, WA 98124 TABLE OF CONTENTS Elliott Bay Seawall Project
More informationVOLUME 1 Foreword...F-1 Executive Summary... S-1
Table of Contents VOLUME 1 Foreword...F-1 Executive Summary... S-1 1. Project Description... 1-1 1.1 Introduction...1-1 1.2 Background and Context...1-3 1.2.1 World Trade Center...1-3 1.2.2 Adjacent Sites...1-4
More informationINFORMATION REQUIRED FOR PROBABLE CATEGORICAL EXCLUSION (SECTION (d))
Grant Applicant: Proposed Project: Date: August 03, 2010 Northern Virginia Transportation Commission, Arlington County Government, and Washington Metropolitan Area Transit Authority Crystal City/Potomac
More informationLONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE FINAL ENVIRONMENTAL IMPACT STATEMENT
LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE FINAL ENVIRONMENTAL IMPACT STATEMENT Project Name: Project Location: Lead Agency & Contact Person: SEQRA Classification: Project Sponsors:
More informationCapitol Expressway Light Rail Project Supplemental Environmental Impact Statement ANNOTATED OUTLINE
Capitol Expressway Light Rail Project Supplemental Environmental Impact Statement ANNOTATED OUTLINE The purpose of this annotated outline is to focus the content of the Environmental Impact Statement (EIS)
More informationLynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 275
C-034-001 Thank you for your comments describing the cultural importance of the Latvian Evangelical Lutheran Church. See Section 2.5.1 for a description of the refined Segment A alternatives that avoid
More informationCorridor Study and Feasibility Analysis
Executive Summary November 2013 Corridor Study and Feasibility Analysis Rourke Bridge, Wood Street, Westford Street, and Drum Hill Road Prepared for Northern Middlesex Council of Governments Prepared by
More informationCity of Malibu. Whole Foods and the Park Shopping Center Draft Environmental Impact Report Volume I. Prepared For: Prepared by:
City of Malibu Whole Foods and the Park Shopping Center Draft Environmental Impact Report Volume I Prepared For: Prepared by: I M PA C T S C I E N C E S, I N C. 638 East Colorado Blvd, Suite 301 Pasadena,
More informationNew Transportation Performance Measures for Transportation Analysis and Thresholds for CEQA
New Transportation Performance Measures for Transportation Analysis and Thresholds for CEQA Transportation Advisory Commission September 11, 2014 Transportation Performance Measures Overview of OPR s Draft
More informationAppendix. Sample EA/EIS Scope of Work
Appendix K Sample EA/EIS Scope of Work EA/EIS Sample Scope of Work The purpose of this Scope of Work (SOW) is to prepare an EA document pursuant to the National Environmental Policy Act (NEPA) to analyze
More informationSouth Bay Metro Green Line Extension
Meeting Agenda Project overview and update Recap of the Scoping Meetings Progress on the project alternative and proposed station locations Meeting Schedule 6:00 Open House 6:30 Presentation 7:15 Public
More informationChapter 5 - Transportation
Chapter 5 - Transportation Discussion Similar to the other elements in the Comprehensive Plan, the transportation element impacts the quality of life, economic development and public safety of the residents
More information14-Dec-2016 Public Meeting Medford City Hall
1 Agenda December 14, 2016 1. Update on GLX Status a. New Program Manager, John Dalton b. Work of the Interim Program Management Team 2. Design Build (DB) contractor selection process and timeline 3. Latest
More informationTable of Contents. City of Redlands - Redlands Crossing Center
City of Redlands - Redlands Crossing Center Executive Summary... ES-1 Section 1: Introduction...1-1 1.1 - Overview of the CEQA Process...1-1 1.2 - Scope of the EIR...1-5 1.3 - Organization of the EIR...1-8
More informationTABLE OF CONTENTS ES EXECUTIVE SUMMARY 1.0 INTRODUCTION 2.0 PROJECT DESCRIPTION 3.0 ENVIRONMENTAL ANALYSIS
ES EXECUTIVE SUMMARY ES1 ES2 ES3 ES4 ES5 Purpose and Scope of the Environmental Impact Report... ES-1 Project Summary... ES-1 Project Alternatives Summary... ES-1 Areas of Controversy/Issues to be Resolved...
More informationSouth Sounder Capital Improvements Program
Subarea South King/Pierce Primary Mode Commuter Rail Facility Type Infrastructure Improvement Length Date Last Modified July 1, 2016 PROJECT AREA AND REP RESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION
More informationRail & Transit Alternatives Analysis. NH Capitol Corridor. Public Scoping Meeting. March 5, 2014
NH Capitol Corridor Rail & Transit Alternatives Analysis Public Scoping Meeting March 5, 2014 Agenda Study overview National Environmental Policy Act Preliminary alternatives: rail, bus, stations, layover
More information6 CHARTING PERFORMANCE
DRAFT 6 CHARTING PERFORMANCE OVERVIEW OF PERFORMANCE BASED PLANNING Background of Performance Based Planning Increasingly, over the past two decades, transportation agencies have been utilizing performance
More informationContents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11
Contents i Contents 1 A New Transportation Plan... 1 Why develop a new plan?... 1 What area does the LRTP focus on?... 2 Why is this LRTP important?... 3 Meeting Requirements for Transportation Planning...
More informationLynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 945
I-441-001 Thank you for your comments about the importance of the Latvian Center to the Latvian community. Following the Draft EIS, the Sound Transit Board directed Sound Transit to develop a Preferred
More informationS-16: Sounder Rail Extension from Puyallup to Orting
Project Number S-16 Subarea Pierce Primary Mode Commuter Rail Facility Type Corridor Length 5.7 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT
More informationGreen Line Extension Project. March 28, 2018 Public Information Meeting
Green Line Extension Project 1 Agenda GLX Project-Wide Public Meeting March 7, 2018; 6:30 PM 8:00 PM 1. Welcome/Introductions Martin Nee (MBTA Stakeholder Support) 2. Project Update John Dalton (MBTA Program
More informationSomerville Public Meeting, October 23, Somerville High School October 23, 2017
Somerville Public Meeting, 1 Agenda Somerville GLX Public Meeting ; 6:30 PM 8:00 PM 1. Welcome/Introductions Martin Nee 2. Project Update MBTA Program Manager John Dalton 3. Early Works Construction Overview
More informationCHAPTER 2 DESIGN REFINEMENTS
CHAPTER 2 DESIGN REFINEMENTS 2.1 INTRODUCTION Since publication of the Draft 2 nd Supplemental Environmental Impact Report (SEIR-2), additional design refinements have been identified. Some of these refinements
More informationSan Ramon City Center Draft Subsequent EIR
San Ramon City Center State Clearinghouse Number 2007042022 Prepared for: City of San Ramon Planning/Community Development Department Planning Services Division 2222 Camino Ramon San Ramon, CA 94583 Prepared
More informationMBTA Green Line Extension Noise and Vibration Technical Report
MBTA Green Line Extension Noise and Vibration Technical Report Environmental Assessment HMMH Report No. 302580.000 January, 2011 Prepared for: Vanasse Hangen & Brustlin, Inc. 99 High Street Boston, MA
More informationFinal Supplemental Environmental Impact Statement
Final Supplemental Environmental Impact Statement April 2014 City of Seattle Department of Transportation 700 Fifth Avenue, Suite 3900 Seattle, WA 98124 TABLE OF CONTENTS Elliott Bay Seawall Project TABLE
More informationTABLE OF CONTENTS Watson Ranch Specific Plan Draft Environmental Impact Report
TABLE OF CONTENTS Watson Ranch Specific Plan Draft Environmental Impact Report 1. Introduction 1-1 1.1 Project Overview 1-1 1.2 Purpose of Environmental Impact Report 1-1 1.3 Lead Agency and Responsible
More informationDRAFT ENVIRONMENTAL IMPACT STATEMENT AND DRAFT SECTION
DRAFT ENVIRONMENTAL IMPACT STATEMENT AND DRAFT SECTION 4(f) EVALUATION APPENDIX 4 Analysis Framework 4-1: CEQR Technical Area Guide DRAFT ENVIRONMENTAL IMPACT STATEMENT AND DRAFT SECTION 4(f) EVALUATION
More informationA. INTRODUCTION B. NOISE ANALYSIS METHODOLOGY
Chapter 8: and Vibration A. INTRODUCTION This chapter assesses the potential noise impacts resulting from operation of the proposed Wyandanch Intermodal Transit Facility by comparing existing noise levels
More informationEnvironmental Setting
Section 5.2 Environmental Justice This section describes the potential of the proposed changes to the approved project to result in disproportionately high and adverse health or environmental effects on
More informationNotice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report
Notice of Preparation For Link Union Station (Link US) Project Joint Environmental Impact Statement and Environmental Impact Report Date: May 27, 2016 To: Subject: Project Title: From: All Interested Agencies,
More informationTaylorsville-Murray Transit
Taylorsville-Murray Transit Environmental Study Report April 2013 Prepared for Table of Contents Acronyms & Abbreviations... iv Executive Summary... ES 1 Chapter 1: Purpose and Need 1.1 Project Description...
More informationSouth Sounder Capital Improvements Program
South Sounder Capital Improvements Program Subarea South King/Pierce Primary Mode Commuter Rail Facility Type Infrastructure Improvement Length Version Draft ST3 Plan Date Last Modified March 28, 2016
More informationLynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 216
C-013-001 Thank you for your comments describing the cultural importance of the Latvian Evangelical Lutheran Church to the Latvian community in western Canada. See Section 2.5.1 for a description of the
More informationGLX Project AUGUST 2 4 FMCB MEETING
GLX Project Green Line Extension Project AUGUST 2 4 FMCB MEETING Presentation Overview 1) Project Essentials 2) Funding the Green Line Extension Project 3) The Construction Manager/General Contractor Procurement
More informationEnvironmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS).
This document is scheduled to be published in the Federal Register on 11/18/2015 and available online at http://federalregister.gov/a/2015-29418, and on FDsys.gov DEPARTMENT OF TRANSPORTATION Federal Transit
More informationAppendix G Analysis of Project Impacts Compared to Existing Conditions
Appendix G Analysis of Project Impacts Compared to Existing Conditions This page intentionally left blank. Analysis of Project Impacts Compared to Existing Conditions Introduction The analysis scenarios
More informationCHAPTER 2. VISION, GOALS AND MTP FRAMEWORK
CHAPTER 2. VISION, GOALS AND MTP FRAMEWORK MTP VISION In order to create a framework for the 2040 Metropolitan Transportation Plan (MTP), a vision statement was drafted by the Vision/Goals Committee and
More information6.0 Indirect Effects and Cumulative Impacts
6.0 Effects and Impacts 6.1 Introduction This chapter of the Draft EIS addresses potential indirect and cumulative impacts of the Bottineau Transitway project. effects are those that are caused by the
More informationWillmar Wye Public Open House #4 and Public Hearing
Willmar Wye Public Open House #4 and Public Hearing February 23, 2017 www.dot.state.mn.us/d8/willmarwye Agenda Time Topic 5:00 pm Open House Opportunity for the public to ask questions of project staff
More informationFacebook Campus Project. City Council Study Session January 31, 2012
Facebook Campus Project City Council Study Session January 31, 2012 Meeting Purpose Opportunity for the City Council to become familiar with project and reports released to date Opportunity for the City
More information9 Before and After Study Plan
9 Before and After Study Plan A Before and After Study Plan has been prepared, describing how the Massachusetts Bay Transportation Authority (MBTA), in cooperation with the Massachusetts Department of
More informationInglewood Oil Field Specific Plan Project Draft Environmental Impact Report
Draft Environmental Impact Report SCH No. 2015101030 Prepared for: City of Culver City Planning Division 9770 Culver Boulevard Culver City, California 90232 Prepared by: Psomas 225 South Lake Avenue Suite
More informationBOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM
BOSTON REGION METROPOLITAN PLANNING ORGANIZATION State Transportation Building Ten Park Plaza, Suite 2150 Boston, MA 02116-3968 Tel. (617) 973-7100 Fax (617) 973-8855 TTY (617) 973-7089 www.bostonmpo.org
More informationFederal Way Transit Center to Tacoma Dome Light Rail
Subarea South King/Pierce Primary Mode Light Rail Facility Type Corridor Length 9.7 miles Date Last Modified July 1, 2016 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION This project
More informationCHAPTER 7. Illustrative Scenarios
CHAPTER Illustrative Scenarios As mentioned in Chapter, this PMT presents and evaluates three scenarios state-of-good-repair (SGR), enhancement, and expansion that illustrate possible capital investment
More informationFederal Transit Administration s New Starts Process. Red Line Extension Alternatives Analysis Study
Federal Transit Administration s New Starts Process Red Line Extension Alternatives Analysis Study DRAFT Schedule for Tonight s Meeting Structure of the meeting Questions and answers process Submit your
More informationLONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17
LONE HILL TO WHITE DOUBLE TRACK STUDY Community Open Houses May 16 & 17 1 PROJECT TEAM & COLLABORATORS 2 OPEN HOUSE SERIES Tuesday, May 16, 2017 6-8:00 pm La Verne City Council Chambers 3660 D Street La
More informationEVALUATION OF ALTERNATIVES CARRIED FORWARD
1 EVALUATION OF ALTERNATIVES CARRIED FORWARD This chapter presents a comparative evaluation of the alternatives carried forward in this Final Environmental Impact Statement (EIS). The intent of this evaluation
More informationALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS
EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS FINAL REPORT SEPTEMBER 2010 TABLE OF CONTENTS 1.0 INTRODUCTION 1 2.0 EXISTING TRAFFIC CONDITIONS 2 3.0 FUTURE TRAFFIC CONDITIONS 3 4.0 POTENTIAL IMPACTS
More informationC-01c: Downtown Seattle to Ballard (Market Street vicinity) LRT, primarily elevated/tunnel options
Project Number C-01c Subarea North King Primary Mode Light Rail Facility Type Corridor Length 7.5 miles Version Number ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT
More informationAppendix H Mitigation Plan
Appendix H Appendix H The mitigation plan for Federal Way Link Extension (FWLE) describes Sound Transit s mitigation commitments that will be implemented to avoid or minimize the impacts of the Preferred
More informationWAL-MART EXPANSION STORE NO , WARSAW, NY
DRAFT ENVIRONMENTAL IMPACT STATEMENT WAL-MART EXPANSION STORE NO. 2043-04, WARSAW, NY 2348 NYS Route 19 Town of Warsaw Wyoming County, New York Project Sponsor / Applicant: Wal-Mart Stores, Inc. 2001 S.E.
More informationCorridor Advisory Group and Task Force Meeting #2
January 19, 2010 www.eisenhowerexpressway.com 1 Corridor Advisory Group and Task Force Meeting #2 January 19, 2010 January 19, 2010 www.eisenhowerexpressway.com 2 Introductions Where We Are Now? Process
More informationHigh Desert Corridor Draft EIS/EIR Public Hearings
High Desert Corridor Draft EIS/EIR Public Hearings Agenda > Registration/Open House (6pm 6:30pm) > Draft EIS/EIR Presentation (6:30pm 7pm) > Public Comment (7pm 8:30pm) Purpose of Today s Hearing > Provide
More informationFinal Environmental Impact Report San Marcos General Plan
Final Environmental Impact Report San Marcos General Plan State Clearinghouse # 2011071028 February 2012 Lead Agency: City of San Marcos 1 Civic Center Drive San Marcos, CA 92069 V A L L E Y O F D I S
More informationFEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION
FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1
More information2017 Countywide Comprehensive Transportation Plan. Transportation Plan. Draft Environmental Impact Report. Volume
2017 Countywide Comprehensive Transportation Plan Draft Environmental Impact Report 2017 Countywide Comprehensive Transportation Plan State Clearinghouse #2017022054 ic l b ew u P vi t Rer a f D Volume
More informationNOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT
Date: September 18, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS H201 Sacramento,
More informationBOSTON REGION METROPOLITAN PLANNING ORGANIZATION
PLANNING ORGANIZATIO BOSTON REGION MPO NMETROPOLITAN BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,
More information11 Joint Development Regulatory Context and Methodology
11 Joint Development This chapter describes the long-term direct and potential indirect impacts, and short-term direct and potential indirect impacts, of the proposed METRO Blue Line Light Rail Transit
More informationAshland. Environmental Assessment Bus Rapid Transit. November Prepared for: The Federal Transit Administration 79th. Prepared by.
Irving Park Addison Roscoe Belmont in partnership with Diversey Fullerton Cortland North Chicago Grand Lake Madison Jackson Harrison Polk Roosevelt 18th Blue Island 31st 35th Environmental Assessment Bus
More informationCumulative and Secondary Impacts
Chapter 14: Cumulative and Secondary Impacts A. INTRODUCTION SEQRA regulations require the consideration of the Proposed Project s potential to result in cumulative impacts (6 NYCRR 617.9(b)(5)(a)) and
More informationDRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CONTENTS CENTINELA SOLAR ENERGY PROJECT
CONTENTS DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CENTINELA SOLAR ENERGY PROJECT CHAPTER 1.0 INTRODUCTION 1.1 PURPOSE OF THE DOCUMENT... 1.0 1 1.2 PROJECT BACKGROUND... 1.0 1 1.3 Project
More informationNorthwest State Route 138 Corridor Improvement Project
Northwest State Route 138 Corridor Improvement Project Los Angeles County, CA DISTRICT 7- LA- 138 (PM 0.0/36.8); DISTRICT 7- LA- 05 (PM 79.5/83.1); DISTRICT 7- LA- 14 (PM 73.4/74.4) 265100/ 0700001816
More informationGoing Forward The Plan to Maintain & Improve Mobility Frequently Asked Questions (FAQs)
Going Forward The Plan to Maintain & Improve Mobility Frequently Asked Questions (FAQs) What is Going Forward The Plan to Maintain & Improve Mobility (Plan) and why does the region need a Long Range Transportation
More informationCounty of El Dorado. El Dorado Hills Apartments Project Draft Environmental Impact Report. SCH No Prepared For: Prepared by:
County of El Dorado El Dorado Hills Apartments Project Draft Environmental Impact Report SCH No. 2017042017 Prepared by: 505 14th Street, Suite 1230 Oakland, California 94612 Prepared For: County of El
More informationEnvironmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX
This document is scheduled to be published in the Federal Register on 10/06/2014 and available online at http://federalregister.gov/a/2014-23711, and on FDsys.gov [4910-22] DEPARTMENT OF TRANSPORTATION
More informationEnvironmental Assessment May 2007
jurisdictional waters. It is assumed that, at a minimum, a USACE Section 404 Nationwide Permit would be necessary to construct these features. The impacts of the fill into the floodplain cannot be fully
More informationFuture Build Alternative Traffic Forecasts and Level of Service Analysis
4.2.10 Future Build Alternative Traffic Forecasts and Level of Service Analysis For the five Build Alternatives, study intersections within one mile of potential station locations were analyzed, as it
More information