Rev Reason for Revision Date Prepared Reviewed Approved. V1 Issue to Minister for Planning 29/11/17 PH/SS PL DS

Size: px
Start display at page:

Download "Rev Reason for Revision Date Prepared Reviewed Approved. V1 Issue to Minister for Planning 29/11/17 PH/SS PL DS"

Transcription

1

2 Revision History Rev Reason for Revision Date Prepared Reviewed Approved V1 Issue to Minister for Planning 29/11/17 PH/SS PL DS Circulation Rev Name (Company) Position Reason for Circulation Date Issued No. of Copies V1 Severin Staalesen, BayWa r.e. Wind Peter Lausberg, BayWa r.e. Wind Tim Doolan, DELWP Planning Issue to Minister for Planning 29/11/17 Electronic & Hard Copy Timboon West Wind Farm Environmental Management Plan i

3 Table of Contents 1 Summary Permit Compliance Summary Project Summary Training Program Reporting of Environmental Incidents Timetable for Implementation of Works... 9 Appendices Environmental Sub-Plans Timboon West Wind Farm Environmental Management Plan ii

4 1 Summary Under the provisions of the Timboon West Wind Farm Planning Permit (PA ), the project proponent, Timboon West Wind Farm Pty Ltd (TWWF), is required to prepare an Environmental Management Plan. The purpose of this document is to address this requirement by detailing procedures and measures by which the Timboon West Wind Farm will ensure that the construction and operation of the wind farm will not have undue impacts on the environmental values of the project site or its immediate surrounds. This Environmental Management Plan (EMP) is required to address a number of specific issues relating to potential environmental impact which are detailed in the planning permit. These specific issue are addressed in sub-plans that are included as appendices to this document. These sub-plans include: A Construction and Worksite Management Plan (CWMP); A Construction Noise Management Plan (CNMP) A Sediment, Erosion and Water Quality Management Plan (SEWQMP); A Hydrocarbon and Hazardous Substances Plan (HHSP); A Fire Prevention and Emergency Response Plan (FPERP); and A Biosecurity Management Plan (BMP). In addition to these sub-plans the planning permit requires that the Environmental Management Plan include general measures pertaining to training programs, reporting, review processes and timeframes. These general measures are addressed in this document. As detailed below, TWWF has appointed Consolidated Power Projects (CPP) to undertake the balance of plant works for the wind farm. CPP s scope comprises the design, supply, installation, commissioning and testing of all the electrical and civil works required. TWWF has appointed Vestas Australia to supply, install and commission the two 3.6 MW V126 Wind Turbine Generators. Additional detail concerning matters addressed in this EMP will be provided in CPP s Project Work Health Safety and Environmental Management Plan (WHSEMP), Vestas Environmental Management Plan (VEMP), and Vestas Worksite Health and Safety Management Plan (VWHSMP). At the date of issue, sub-contracts are still being negotiated by Vestas and CPP and hence some details of the WHSEMP, VEMP and VWHSMP have not been finalised. Once the WHSEMP, VEMP and VWHSMP have been finalised they will be appended to this EMP and this EMP will be reissued to the Responsible Authority. 2 Permit Compliance Summary This Environmental Management Plan details how TWWF will satisfy Permit Conditions No. 35 to 47 of Planning Permit PA The table below summarises how the plan achieves this outcome. Timboon West Wind Farm 1 Environmental Management Plan

5 Table 1: Permit Conditions No Condition How/Where Addressed a 37b 37c Before the development starts, an environmental management plan must be prepared, to the satisfaction of the responsible authority. When approved, the environmental management plan will be endorsed by the responsible authority and will then form part of this permit. Once endorsed the permit holder must publish the plan on their website. The environmental management plan: a. must be generally in accordance with the Planning Permit Application Timboon West Wind Farm, Volume 1, 2 and 3 (July 2016); b. must be prepared in consultation with the agencies specified in conditions 36 to 44 or any other agency as directed by the responsible authority; c. may be prepared in sections or stages; d. must be in accordance with all applicable EPA requirements; e. should contain all storm water runoff within the development site. f. must meet the requirements of conditions 36 to 44 below. The use and development must be carried out in accordance with the endorsed environmental management plan, to the satisfaction of the responsible authority. The environmental management plan must include a construction and work site management plan. The construction and work site management plan must include: The identification of fuels, other hazardous materials and all other potential contaminants stored or used on site during the construction phase of the wind energy facility, and appropriate storage, construction and operational methods to control any identified contamination risks; Procedures for managing potential spills and leaks and pollution incidents, including incorporation of appropriate pollution control measures outlined in EPA Publication 480 Environmental Guidelines for Major Construction Sites; Procedures to suppress dust emissions from constructionrelated activities. Appropriate measures may include water spraying of roads and stockpiles, stabilising surfaces, temporary screening and wind fences, modifying construction activities during periods of heightened winds and revegetating exposed areas as soon as practicable; EMP, CWMP, CNMP, SEWQMP, HHSP, FPERP, BMP CWMP CWMP, Section 4 CWMP, Section 4 CWMP, Section 5 Timboon West Wind Farm 2 Environmental Management Plan

6 37d 37e 37f 37g 37h 37i 37j 37k 37l 37m 38 38a 38b 38c Procedures for managing noise emissions from constructionrelated activities; Criteria for the siting of any temporary concrete batching plant associated with the development of the wind energy facility and the procedure for its removal and reinstatement of the site once its use finishes. The establishment and operation of any temporary concrete batching plant must be designed and operated in accordance with EPA Publication 628 Environmental Guidelines for the Concrete Batching Industry; Appropriate sanitary facilities to be provided for construction and maintenance staff, which must be designed and operated in accordance with EPA Publication Code of Practice Onsite wastewater management (December 2008); Procedures to capture storm water runoff within the development site Procedures to retain the identification of waste re-use, recycling and disposal procedures; A timetable, where practicable, for the construction of turbine bases, access tracks and power cabling during warmer months, to minimise impacts on ephemeral wetlands, local fauna and sediment mobilisation; Procedures to ensure that construction vehicles and equipment use designated tracks and works areas to avoid impacts on native vegetation. Procedures to provide a buffer to protect any site of Aboriginal Cultural Heritage Procedures for covering trenches and holes at night, and filling trenches as soon as practical after excavation, to protect native fauna; The removal of works, buildings and staging areas on completion of the construction phase of the project. The environmental management plan must include construction noise management plan. The construction noise management plan must include: Performance requirements for noise at nearby receptors in accordance with EPA Publication 1254; procedures for measuring compliance with performance requirements; and procedures for receiving, evaluating and responding to complaints. CWMP, Section 6 CWMP, Section 9 CWMP, Section 7 CWMP, Section 8 CWMP, Section 8 CWMP, Section 14 CWMP, Section 10 CWMP, Section 13 CWMP, Section 12 CWMP, Section 11 CNMP CNMP, Section 4 CNMP, Section 5 CNMP, Section 5 Timboon West Wind Farm 3 Environmental Management Plan

7 39 39a 39b 39c 39d 39e 39f 39g 39h 39i 39j The environmental management plan must include a sediment, erosion and water quality management plan which must be prepared in consultation with the Corangamite Catchment Management Authority. The sediment, erosion and water quality management plan must include: Identification of all construction and operational processes that could potentially lead to water contamination; Procedures to ensure that silt from batters, cut-off drains, table drains and road works is retained on the site during and after construction and replaced as soon as possible. To this end: i. all land disturbances must be confined to a minimum practical working area ii. iii. soil to be removed must be stockpiled and separate soil horizons must be retained in separate stockpiles and not mixed, and soil must be replaced as soon as possible in sequence stockpiles must be located away from drainage lines; The installation of geo-textile silt fences (with sedimentation basins where appropriate) on all drainage lines from the site which are likely to receive run-off from disturbed areas; Procedures to ensure that steep batters are treated in accordance with EPA Publication 275 Construction Techniques for Sediment Pollution Control; Procedures for waste water discharge management; A process for overland flow management to prevent the concentration and diversion of waters onto steep or erosion prone slopes; Pollution management measures for stored and stockpiled materials including waste materials, litter, contaminated run-off and any other potential source of pollution to ground or surface waters; Incorporation of appropriate pollution control measures outlined in EPA Publication 480 Environmental Guidelines for Major Construction Sites; An agreed program and appropriate capacity for annual inspection and regular maintenance of any on-site wastewater management system; Siting of any concrete batching plant and any on-site wastewater disposal treatment fields at least 100 metres from any watercourse; SEWMP, Section 3, Appendix A SEWMP, Section 4 SEWMP, Section 5 SEWMP, Section 5.3 SEWMP, Section 6 SEWMP, Section 9 SEWMP, Section 8 SEWMP, Section 9 SEWMP, Section 5, Section 8, Section 9 SEWMP, Section 7.2 SEWMP, Section 4 Timboon West Wind Farm 4 Environmental Management Plan

8 39k 39l 40 40a 40b 41 41a 41b 41c 41d A program of inspection and remediation of localised erosion within a specified response time. Assurance that best practice sedimentation and pollution control measures are undertaken at all times, in accordance with Environment Protection Authority guidelines (EPA 1991; EPA 1996; Victorian Stormwater Committee 1999) to prevent offsite impacts to waterways and wetlands. The environmental management plan must include a hydrocarbon and hazardous substances plan. The hydrocarbon and hazardous substances plan must include: Procedures for any on-site, permanent post-construction storage of fuels, lubricants, waste oil or other hazardous substances or potential contaminants to be in bunded areas; Contingency measures to ensure that any chemical or oil spills are contained on-site and cleaned up in accordance with EPA requirements. The environmental management plan must include a fire prevention and emergency response plan prepared in consultation with and to the satisfaction of the CFA. The fire prevention and emergency response plan must be generally in accordance with the Emergency Management Guidelines for Wind Energy Facilities - CFA May 2015 and must include: Criteria for the provision of static water supply tanks solely for fire-fighting purposes, including minimum capacities, appropriate connections and signage; Procedures for vegetation management, fuel control and the provision of fire-fighting equipment during declared fire danger periods; Minimum standards for access roads and tracks to allow access for fire fighting vehicles, including criteria for access to static water supply tanks for fire-fighting vehicles; A requirement that, within one month after the commencement of the operation of the wind energy facility, the operator of the wind energy facility facilitates a familiarisation visit to the site and explanation of emergency services procedures for: SEWMP, Section 11 SEWMP, Section 12 HHSP HHSP, Section 4 HHSP, Section 5 FPERP, Section 3, Appendix A FPERP, Section 7 FPERP, Section 9 FPERP, Section 6, Section 7 FPERP, Section 12 Timboon West Wind Farm 5 Environmental Management Plan

9 41e 41f 41g 42 42a 42b 42c the CFA (including headquarters level, the CFA Regional Office and local volunteer brigades as specified by the CFA Regional Office); i. Rural Ambulance Victoria; ii. iii. Corangamite Shire Council's Municipal Emergency Management Committee; and Victoria Police; Subsequent familiarisation sessions for new personnel of the organisations referred to in condition 41(f) on a periodic basis as required; If requested, training of personnel of the organisations referred to in condition 41(f) in relation to suppression of wind energy facility fires. The environmental management plan must include a biosecurity management plan to be prepared in consultation with DEDJTR and to the satisfaction of the responsible authority. The biosecurity management plan must include: Procedures to prevent biosecurity risks, which may include (but are not limited to): I. the cleaning of all plant and equipment before transport onto and off the site; and II. the use of material/products on site which are free of invasive plants and animals; A protocol for effective identification of biosecurity risks, early intervention to manage biosecurity risks, ongoing monitoring of biosecurity risks, trace-backs, and integrated control measures when entry, establishment or spread of specific risk targets is identified; A requirement to comply with approved government or industry standards and procedures for the identification, prevention and management of biosecurity risks that apply from time to time, which include (but are not necessarily limited to): i. the DEDJTR s Invasive Plant and Animal Management Policy Framework (undated); ii. iii. the DEDJTR s Biosecurity Guidelines for Movement of Equipment Contractors Between Farms (Note Number: AG1171 published in January 2005 and updated in July 2009); and the DEDJTR s recommended standards and practices for managing viticulture biosecurity and plant biosecurity risks. FPERP, Section 12 FPERP, Section 12 FPERP, Section 12 BMP, Section 3 BMP, Section 5 BMP, Section 6 BMP, Section 5.1, Section 6, Section 7 Timboon West Wind Farm 6 Environmental Management Plan

10 a 44b The environmental management plan must include a training program for construction workers and permanent employees or contractors at the wind energy facility site, including a site induction program relating to the range of issues addressed by the environmental management plan. The environmental management plan must include a program for reporting environmental incidents, including: A register of environmental incidents, non-conformances and complaints, together with corrective actions taken in response to such incidents, non-conformances or complaints Identification of the person to whom reports of environmental incidents, non-conformances and complaints should be made. The environmental management plan must include a timetable for implementation of all programs and works referred to in conditions 35 to 44 above. The environmental management plan must be reviewed and if necessary amended in consultation with the responsible authority and other authorities as directed by the responsible authority every five years, to reflect operational experience and changes in environmental management standards and techniques. The amended environmental management plan must be submitted to the responsible authority for re-endorsement. Once re-endorsed, the amended environmental management plan will take the place of the earlier environmental management plan and will form part of this permit. EMP, Section 4 EMP, Section 5 EMP, Section 5 EMP, Section 5 EMP, Section 6 3 Project Summary The Timboon West Wind Farm will consist of two 3.6 MW wind turbines located on East and West Rd, Timboon West, Victoria. These two turbines will be connected to an overhead 22 kv line that runs along Boundary Rd externally to the site. As all cabling will be run underground the wind farm will not result in additional overhead power lines. Due to the relatively small size of the project a switchyard will not be required. Instead a small control building will house the electrical equipment required to connect the wind farm to the grid. Construction of the wind farm will take approximately 6 8 months. There are three main stages to the construction process, starting with construction of the access tracks, hardstands, foundations and underground cabling. Stage two sees the turbines delivered and installed using specialised cranes and highly skilled operators. The final stage involves commissioning and testing the wind farm, and connecting it the electricity grid so that the export of energy can begin. Timboon West Wind Farm 7 Environmental Management Plan

11 TWWF has appointed Consolidated Power Projects (CPP) to undertake the balance of plant work for the wind farm. CPP s scope comprises the design, supply, installation, commissioning and testing of all the electrical and civil works required. TWWF has appointed Vestas Australia to supply, install and commission the two 3.6 MW V126 Wind Turbine Generators. Powercor Australia will carry out the necessary works at the site and the local sub-station to connect the wind farm to the local electricity grid. During the operational period of the wind farm there will be very little activity on the site. The operation of the wind farm will not require anyone to be in attendance. Wind turbines automatically commence producing energy as the wind reaches a cut-in speed, and they likewise cease operating as soon as high wind speeds are reached. Energy produced is automatically fed into the local grid where it is utilised in the local area. Like all modern wind farms, the Timboon West Wind Farm will be remotely monitored 24 hours a day by the chosen maintenance provider. Under a long term maintenance agreement, routine scheduled maintenance will be undertaken on each turbine every six months. The maintenance function will be carried out by representatives of the turbine supply company, Vestas Australia. This maintenance will take approximately one day per turbine. 4 Training Program Prior to starting work on the site, all personnel will be made aware of the range of issues addressed in this EMP through a site specific induction program. The site induction program will cover the following: As outlined in the Construction and Worksite Management Plan: o Identification of fuels and other hazardous materials to be stored or used on site during the construction period; o Procedures for managing spills and leaks and pollution incidents in accordance with EPA requirements; o Procedures for managing dust emissions; o Procedures for managing noise emissions; o Procedures for waste re-use, recycling and disposal; o Procedures relating to construction vehicles and personnel use of designated tracks and works areas; As outlined in the Sediment, Erosion and Water Quality Management Plan: o Procedures for minimising soil disturbance; o Procedures for stockpiling; o Procedures for treatment of steep batters in accordance with EPA requirements; o Procedures for waste water discharge; o Procedures for management of overland flows; o Procedures for pollution control in accordance with EPA requirements; As outlined in the Hydrocarbon and Hazardous Substances Plan: o Procedures for managing spills in accordance with EPA requirements; As outlined in the Fire Prevention and Emergency Response Plan: Timboon West Wind Farm 8 Environmental Management Plan

12 o o Procedures for vegetation management in the vicinity of works; Emergency response procedures; As outlined in the Biosecurity Plan: o Procedures pertaining to cleaning of footwear, vehicles and machinery prior to entry and exit; o Procedures pertaining to the use of materials that are free of invasive species; and o The requirement to comply with approved government or industry standards and procedures for the identification, prevention and management of biosecurity risks. 5 Reporting of Environmental Incidents Environmental non-conformances, incidents and complaints will be reported to the TWWF Project Manager. The TWWF Project Manager will record all environmental non-conformances, incidents and complaints in an Environmental Incidents Register which will include the following information: Time, date and location of incident; Nature of incident; Personnel and machinery involved in incident; and Corrective measures taken in response to incident. The TWWF Project Manager will make available the Environmental Incidents Register to the Responsible Authority upon request. 6 Timetable for Implementation of Works The table below shows the current work plan for TWWF with construction work on site commencing in January Table 2: Schedule of Works Works Timing 2018 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Civil works Substation Construction 22 kv Grid Works Turbine Construction Demobilisation Timboon West Wind Farm 9 Environmental Management Plan

13 Commissioning & Testing Turbines Operational As detailed later in this EMP, a range of environmental and management programs will be scheduled throughout the construction period and at regular intervals once the wind farm is operational. Table 3 shows the programs and their approximate timing. Table 3: Schedule of Programs Works Timing Jan Feb Mar Apr May Jun Jul Aug Sept Oct Q4 H2 H1 H2 Training Program Monitoring & Reporting Develop Emergency Response Plan Emergency Services Familiarisation Visit/s Installation of Water Tank Erosion Monitoring Assessments Cordoning of Environmental Values Timboon West Wind Farm 10 Environmental Management Plan

14 Appendices Environmental Sub-Plans Timboon West Wind Farm 11 Environmental Management Plan

15 APPROVED FOR THE MINISTER FOR PLANNING SHEET 15 OF 71 Timboon West Wind Farm Construction and Worksite Management Plan Prepared by: Timboon West Wind Farm Pty Ltd March 2018 Document Reference: TWF Construction and Worksite Management Plan V2.docx

16 APPROVED FOR THE MINISTER FOR PLANNING SHEET 16 OF 71 Revision History Rev Reason for Revision Date Prepared Reviewed Approved V1 Issue to Minister for Planning 29/11/17 PH/SS PL DS V2 Issue to Minister for Planning 27/03/18 PH/SS PL DS Circulation Rev Name (Company) Position Reason for Circulation Date Issued No. of Copies V1 Severin Staalesen, BayWa r.e. Wind Peter Lausberg, BayWa r.e. Wind Tim Doolan, DELWP Planning Issue to Minister for Planning 29/11/17 Electronic & Hard Copy V2 Severin Staalesen, BayWa r.e. Wind Peter Lausberg, BayWa r.e. Wind Tim Doolan, DELWP Planning Issue to Minister for Planning 27/03/18 Electronic Timboon West Wind Farm Construction and Worksite Management Plan i

17 Table of Contents APPROVED FOR THE MINISTER FOR PLANNING SHEET 17 OF 71 1 Summary Permit Compliance Summary Overview of the Project and the Construction Process Fuels, Hazardous Materials and Potential Contaminants Storage of Hydrocarbons and Hazardous Substances Procedures for Managing Potential Spills and Pollution Incidents Procedures for Suppressing Dust Procedures for Managing Construction Noise Sanitary Facilities Procedures for Waste Re-use, Recycling and Disposal Temporary Concrete Batching Plant Procedures for Construction Vehicles Procedures for Removal of Works, Buildings and Staging Areas on Completion of Construction Procedures for Covering Trenches and Holes Procedures Relating to Aboriginal Cultural Heritage A Timetable for the Construction of Turbine Bases, Access Tracks and Power Cabling... 7 Timboon West Wind Farm Construction and Worksite Management Plan ii

18 APPROVED FOR THE MINISTER FOR PLANNING SHEET 18 OF 71 1 Summary Under the provisions of the Timboon West Wind Farm Planning Permit (PA ), the project proponent, Timboon West Wind Farm Pty Ltd (TWWF), is required to prepare a Construction and Worksite Management Plan. The purpose of this document is to address this requirement by detailing procedures and measures by which TWWF will ensure potential risks and impacts associated with the construction of the proposed wind farm are managed in accordance with the requirements of the Planning Permit. 2 Permit Compliance Summary This Construction and Worksite Management Plan details how TWWF will satisfy Permit Condition No. 37 of Planning Permit PA The table below summarises how the plan achieves this outcome. Table 1: Permit Conditions No Condition 37 The environmental management plan must include a construction and work site management plan. How/Where Addressed The construction and work site management plan must include: 37a 37b 37c 37d 37e The identification of fuels, other hazardous materials and all other potential contaminants stored or used on site during the construction phase of the wind energy facility, and appropriate storage, construction and operational methods to control any identified contamination risks; Procedures for managing potential spills and leaks and pollution incidents, including incorporation of appropriate pollution control measures outlined in EPA Publication 480 Environmental Guidelines for Major Construction Sites; Procedures to suppress dust emissions from constructionrelated activities. Appropriate measures may include water spraying of roads and stockpiles, stabilising surfaces, temporary screening and wind fences, modifying construction activities during periods of heightened winds and revegetating exposed areas as soon as practicable; Procedures for managing noise emissions from constructionrelated activities; Criteria for the siting of any temporary concrete batching plant associated with the development of the wind energy facility and the procedure for its removal and reinstatement of the site once its use finishes. The establishment and operation of any temporary concrete batching plant must be designed and operated in accordance with EPA Publication 628 Environmental Guidelines for the Concrete Batching Industry; Timboon West Wind Farm Construction and Worksite Management Plan Section 4 Section 4 Section 5 Section 6 Section 9 1

19 APPROVED FOR THE MINISTER FOR PLANNING 37f Section 7 SHEET 19 OF 71 37g Procedures to capture storm water runoff within the development site Section 8 37h Procedures to retain the identification of waste re-use, recycling and disposal procedures; Section 8 37i 37j 37k 37l 37m 3 Appropriate sanitary facilities to be provided for construction and maintenance staff, which must be designed and operated in accordance with EPA Publication Code of Practice Onsite wastewater management (December 2008); A timetable, where practicable, for the construction of turbine bases, access tracks and power cabling during warmer months, to minimise impacts on ephemeral wetlands, local fauna and sediment mobilisation; Procedures to ensure that construction vehicles and equipment use designated tracks and works areas to avoid impacts on native vegetation. Procedures to provide a buffer to protect any site of Aboriginal Cultural Heritage Procedures for covering trenches and holes at night, and filling trenches as soon as practical after excavation, to protect native fauna; The removal of works, buildings and staging areas on completion of the construction phase of the project. Section 14 Section 10 Section 13 Section 12 Section 11 Overview of the Project and the Construction Process The Timboon West Wind Farm will consist of two 3.6 MW wind turbines located on East and West Rd, Timboon West, Victoria. These two turbines will be connected to an overhead 22 kv line that runs along Boundary Rd externally to the site. As all cabling will be run underground the wind farm will not result in additional overhead power lines. Due to the relatively small size of the project a switchyard will not be required. Instead a small control building will house the electrical equipment required to connect the wind farm to the grid. Construction of the wind farm will take approximately 6 8 months. There are three main stages to the construction process, starting with construction of the access tracks, hardstands, foundations and underground cabling. Stage two sees the turbines delivered and installed using specialised cranes and highly skilled operators. The final stage involves commissioning and testing the wind farm, and connecting it the electricity grid so that the export of energy can begin. 4 Fuels, Hazardous Materials and Potential Contaminants During construction a range of hydrocarbons and hazardous substances will be used. The following have been identified as potential hazardous substances likely to be on the site during construction: Liquid fuels; Timboon West Wind Farm Construction and Worksite Management Plan 2

20 Lubricants and hydraulic oils (new and used); Compressed gases; Liquid concrete; and Adhesives. APPROVED FOR THE MINISTER FOR PLANNING SHEET 20 OF 71 Following completion of construction there will be no on-site, permanent post-construction storage of any fuels, lubricants, waste oil, or any other hazardous substances or potential contaminants. 4.1 Storage of Hydrocarbons and Hazardous Substances Appropriate storage for hydrocarbon and hazardous materials will be provided in accordance with the EPA Victorian Publication 347 Bunding Guidelines. Storage quantities will be kept to a minimum. All storage areas will be clearly identified with appropriate signage and labelled in accordance with Safe Work Australia Work Health and Safety (WHS) Regulations. Any material or substances that are or may be considered hazardous or dangerous to personnel or the environment shall be handled, stored, transported, used or applied according to the manufacturer's recommendations and all statutory requirements. Compressed gases will be stored in accordance with AS A register of hazardous materials used on site will be maintained and will be accompanied by the Safety Data Sheet (SDS) information and risk assessment of the substance. 4.2 Procedures for Managing Potential Spills and Pollution Incidents Spill kits will be present at all times in close proximity to works areas. The location of the spill kits will be included in the site induction and nominated persons will be trained in spill clean up. Oil and grease spills will be cleaned immediately in accordance with EPA and local government requirements. Spills will be reported to the EPA if deemed necessary. Reportable examples include; The spill enters the water or watercourse; and The spill exceeds the EPA permissible level of discharge and deposit to the environment. Contaminated spoil will be disposed of at an approved waste disposal facility and evidence of the disposal documented. 5 Procedures for Suppressing Dust Dust suppression measures will be implemented as required and will include the following where appropriate: Wetting of access roads, stockpiles and/or hard stand areas; Erection of temporary screening and/or wind fences around disturbed areas and stockpiles; Modifying construction activities during periods of high wind; and Timboon West Wind Farm Construction and Worksite Management Plan 3

21 Revegetating exposed areas as soon as practicable. APPROVED FOR THE MINISTER FOR PLANNING SHEET 21 OF 71 6 Procedures for Managing Construction Noise Noise will be managed in accordance with the EPA Environmental Guidelines for Major Construction Sites (Bulletin 480) and the EPA Noise Control Guidelines TG Work on site will be conducted during daytime hours between 7 am 6 pm Monday to Saturday except where significant operational requirements make it necessary to extend these hours. Wherever practical, no construction work is to be undertaken on Sundays or Public Holidays, however if absolutely essential, work hours will be restricted to between 8 am 6 pm following prior notification of local residents. Prior to the commencement of construction local residents will be notified of the proposed construction schedule. Wherever possible, noisier works will be scheduled to minimise the disturbance to nearby residents, and mechanical plant will have appropriate noise abatement or noise suppression. 7 Sanitary Facilities Sanitary amenities will be provided for construction staff working on site. These facilities will be located in portable buildings that will be installed on the site for the duration of construction, and removed following commissioning. These buildings will be fitted with storage tanks that capture all waste water. Licensed waste disposal companies will be contracted to remove this waste water in accordance with local council requirements and EPA regulations. All amenities provided will comply with the requirements of EPA Publication Code of Practice Onsite wastewater management (February 2013). 8 Procedures for Waste Re-use, Recycling and Disposal Sources of general waste and recyclable material at the project site will be: Containers, packaging and wrappings materials; Construction wastes such as scrap timber, metal and concrete; Topsoil, spoil and rock from excavations; and Domestic waste. The overriding waste strategy (in order of priority) will be avoidance where possible, followed by resource recovery, and disposal as last resort. Where waste is disposed recyclable material will be separated from general waste. The following procedures will be followed for general waste management at the project site: All waste will be removed from the site; Recycling bins and skips will be available on site; and Licensed waste disposal companies will be contracted to remove waste materials in accordance with local council requirements and EPA regulations. Timboon West Wind Farm Construction and Worksite Management Plan 4

22 APPROVED FOR THE MINISTER FOR PLANNING SHEET 22 OF 71 During operation the wind farm will not produce waste water, and all rainwater runoff will be captured by a swale drain system designed to collect and discharge runoff from engineered surfaces without impacting local waterways. For a more detailed discussion of procedures relating to stormwater runoff and water quality management see the Sediment, Erosion and Water Quality Management Plan. 9 Temporary Concrete Batching Plant There will be no temporary concrete batching plant and all plant and equipment associated with concrete delivery will be cleaned off site at an accredited concrete batching plant. 10 Procedures for Construction Vehicles The following procedures will be put in place to ensure that construction vehicles and equipment use designated tracks and works areas and avoid impacts on native vegetation: Prior to the commencement of construction native vegetation and scattered trees located in the vicinity of works areas will be cordoned with highly visible bunting; The areas formed by cordoning will be marked on a site plan as Environmental Exclusion Zones, and the site plan will be placed in a conspicuous position in the site office at A3 size at the first available opportunity and will remain in place for the duration of construction; Prior to formally entering the site, all construction personnel will be required to undergo a site induction which includes information about the environmental values of the site and the measures implemented in order to protect them. During the site induction construction personnel will be provided with copies of the site plan and informed that the following constraints will apply to these areas at all times during the construction process; o No construction machinery or personnel are to enter the environmental exclusion zones; o No waste material, water, soil, stone, or any other product of the construction process is to be placed in the environmental exclusion zones; o Construction machinery and personnel are to stay on access tracks and hardstand areas at all times, except when/where it is absolutely necessary to leave such areas; o Where construction machinery or personnel have entered an environmental exclusion zone, the TWWF project manager is to be notified that an environmental exclusion zone has been entered and will be provided with details concerning the action including its location, time and nature; Where an intrusion into an environmental exclusion zone has had a material effect on an environmental value TWWF will engage a suitably qualified specialist to determine the extent of the damage caused and to develop remedial measures; and If it is deemed by the suitably qualified specialist that remedial measures are necessary, a report concerning the intrusion, including damage caused and proposed remedial measures, will be provided to the Department of Environment, Land, Water, Planning Environment Portfolio. Timboon West Wind Farm Construction and Worksite Management Plan 5

23 APPROVED FOR THE 11 Procedures for Removal of Works, Buildings and Staging Areas onminister Completion of FOR PLANNING Construction SHEET 23 OF 71 Following completion of construction access tracks will remain for the life of the wind farm. Rehabilitation of the access tracks will occur on completion of decommissioning, the process for which will be detailed in the Decommissioning Plan to be prepared within six months after completion of construction as per the requirements of the planning permit. Aside from access tracks, the following components of the construction process will require removal or rehabilitation: Two turbine hardstand areas, one located at the base of each turbine; The cable trench; and The site office area. Following completion of construction the turbine hardstands and cable trench will be reinstated in their entirety. Rehabilitation of these areas will consist of: Removal of all temporary buildings; Surface re-levelling; Weed control if required; Revegetation; and Ongoing weed control for at least 2 years. Following completion of construction part of the site office area will be reused for the purposes of providing static water supply as detailed in the Wildfire and Emergency Response Plan. Being located at the entrance to the site and consisting of an engineered gravel surface in excess of 20 m x 20 m, the site office area is the ideal location for the water tank required by the CFA Emergency Management Guidelines for Wind Energy Facilities. Accordingly, a portion of the site office area will remain intact following construction for the purpose of providing a static water supply. This portion will be no larger than that which is required to meet the requirements of the CFA. That part of the site office area which is not required for the purpose of providing static water supply will be rehabilitated as per the turbine hardstands and cable trench. 12 Procedures for Covering Trenches and Holes TWWF will cover any open trenches and holes at night, and fill trenches and holes as soon as practical after excavation, to protect native fauna. The trench and hole covering procedure will consist of: Maintaining only the minimum number of necessary open trench lengths and hole numbers during daytime activities to ensure covering is practicable at the end of each day Backfilling any trenches as soon as the work is completed during daily construction Backfilling any holes as soon as the work is completed during daily construction Use of hard capping covers and/or physical barriers to prevent the ingress of fauna into any trench or hole that cannot be practicably covered overnight and poses a risk of entrapment to fauna Timboon West Wind Farm Construction and Worksite Management Plan 6

24 APPROVED FOR THE MINISTER FOR PLANNING SHEET 24 OF Procedures Relating to Aboriginal Cultural Heritage A Cultural Heritage Management Plan has been prepared and endorsed for the proposed wind farm (CHMP No ). As such the wind farm will be constructed in accordance with the requirements of the endorsed CHMP. 14 A Timetable for the Construction of Turbine Bases, Access Tracks and Power Cabling It is anticipated the construction of the Timboon West Wind Farm will commence in January 2018, with civil works scheduled to be completed by April 2018, meaning all earthworks should be completed before the commencement of winter Timboon West Wind Farm Construction and Worksite Management Plan 7

25 APPROVED FOR THE MINISTER FOR PLANNING SHEET 25 OF 71 Timboon West Wind Farm Construction Noise Management Plan Prepared by: Timboon West Wind Farm Pty Ltd March 2018 Document Reference: TWF Construction Noise Management Plan V2.docx

26 APPROVED FOR THE MINISTER FOR PLANNING SHEET 26 OF 71 Revision History Rev Reason for Revision Date Prepared Reviewed Approved V1 Issue to Minister for Planning 29/11/17 PH/SS PL DS V2 Issue to Minister for Planning 27/03/18 PH/SS PL DS Circulation Rev Name (Company) Position Reason for Circulation Date Issued No. of Copies V1 Severin Staalesen, BayWa r.e. Wind Peter Lausberg, BayWa r.e. Wind Tim Doolan, DELWP Planning Issue to Minister for Planning 29/11/17 Electronic & Hard Copy V2 Severin Staalesen, BayWa r.e. Wind Peter Lausberg, BayWa r.e. Wind Tim Doolan, DELWP Planning Issue to Minister for Planning 27/03/18 Electronic Timboon West Wind Farm Construction Noise Management Plan i

27 APPROVED FOR THE MINISTER FOR PLANNING Table of Contents SHEET 27 OF 71 1 Summary Permit Compliance Summary Overview of the Project and the Construction Process EPA Recommendations Regarding Construction Noise Procedures for Receiving and Responding to Complaints Receipt of Complaints by TWWF Complaints Receival via Third Parties Complaint Documentation Procedure Complaint Investigation, Evaluation and Response Procedures... 3 Timboon West Wind Farm Construction Noise Management Plan ii

28 APPROVED FOR THE MINISTER FOR PLANNING 1 SHEET 28 OF 71 Summary Under the provisions of the Timboon West Wind Farm Planning Permit (PA ), the project proponent, Timboon West Wind Farm Pty Ltd (TWWF), is required to prepare a Construction Noise Management Plan. The purpose of this document is to address this requirement by detailing procedures and measures by which the Timboon West Wind Farm will ensure potential noise impacts associated with the construction of the proposed wind farm are managed in accordance with the requirements of the Planning Permit. 2 Permit Compliance Summary This Construction Noise Management Plan details how TWWF will satisfy Permit Condition No. 38 of Planning Permit PA The table below summarises how the plan achieves this outcome. Table 1: Permit Conditions 3 No Condition How/Where Addressed 38 The environmental management plan must include construction noise management plan. The construction noise management plan must include: 38a Performance requirements for noise at nearby receptors in accordance with EPA Publication 1254; Section 4 38b Procedures for measuring compliance with performance requirements; and Section 5 38c Procedures for receiving, evaluating and responding to complaints. Section 5 Overview of the Project and the Construction Process The Timboon West Wind Farm will consist of two 3.6 MW wind turbines located on East and West Rd, Timboon West, Victoria. These turbines will be connected to an overhead 22 kv line that runs along Boundary Rd externally to the site. As all cabling will be run underground the wind farm will not result in additional overhead power lines. Due to the relatively small size of the project a switchyard will not be required. Instead a small control building will house the electrical equipment required to connect the wind farm to the grid. Construction of the wind farm will take approximately 6 8 months. There are three main stages to the construction process, starting with construction of the access tracks, hardstands, foundations and underground cabling. Stage two sees the turbines delivered and installed using specialised cranes and highly skilled operators. The final stage involves commissioning and testing the wind farm, and connecting it the electricity grid so that the export of energy can begin. For the majority of the construction period the wind farm site will only produce low level noise. High noise works, such as earthmoving and rock breaking, will only take place during the first phase of the Timboon West Wind Farm Construction Noise Management Plan 1

29 APPROVED FOR THE MINISTER FOR PLANNING SHEET 29 OF 71 construction process. This component of the works is scheduled to take three months, beginning in January 2018 and finishing in April The remainder of the works will consist of the delivery, erection and commissioning of the wind turbine generators and control building, all of which takes place without the need for high noise works. 4 EPA Recommendations Regarding Construction Noise Noise will be managed in accordance with the EPA Environmental Guidelines for Major Construction Sites and the EPA Noise Control Guidelines. The following procedures have been adopted from EPA Publication 1254: Prior to the commencement of construction TWWF will contact nearby residents by mail to inform them about the construction process and the process for making a complaint; TWWF will appoint a principal contact person for community queries, namely the project manager; TWWF will provide contact details through the project website, newsletters and site signage; TWWF will record complaints in accordance with the complaint response procedure outlined in in this document; TWWF will restrict high noise works (rock breaking etc.) to normal working hours, namely 7 am 6 pm Monday to Friday, and 7 am-1 pm Saturday, and by consultation with nearby residents outside these hours; and TWWF will allow low noise works to be conducted during all daytime hours, namely between 7 am 6 pm Monday to Sunday. 5 Procedures for Receiving and Responding to Complaints TWWF will investigate enquiries and complaints and determine an appropriate response within 10 working days of receiving the complaint. Outcomes of complaint investigations will be communicated to the complainant within 15 working days of receiving the original complaint, except where further investigations are required, in which case the outcomes will be communicated to the complainant when those investigations are complete. At any time during this process, a stakeholder may obtain feedback on the status of their complaint, by contacting TWWF and quoting the receipt number issued. TWWF will maintain communication with the complainant (and third parties where applicable) during the further investigations, particularly where progress may have been delayed. 5.1 Receipt of Complaints by TWWF Any complaint regarding TWWF construction noise will be directed to TWWF through the following channels: Toll free telephone number: ; Project address: feedback@timboonwestwindfarm.com.au; and Project mailing address: 5-73A Rupert St, Collingwood. Timboon West Wind Farm Construction Noise Management Plan 2

30 APPROVED FOR THE MINISTER FOR PLANNING SHEET 30 OF 71 These contact details will be included in pre-construction correspondence with nearby residents, displayed on signage located at the site entrance on East and West Rd, and will be shown on the TWWF website. Complaints received during the construction phase will be directed to the TWWF Project Manager. 5.2 Complaints Receival via Third Parties If a complaint is received by Council, DEWLP or the EPA, details of that complaint may be forwarded to TWWF. TWWF will consult with the third party and with the complainant in order to determine if the complaint will be assessed in accordance with the Complaints Procedure outlined in this document. If it is agreed that the complaint received by a third party is related to the construction and the complainant consents for TWWF to investigate, then the complaint will be assessed in accordance with the Complaints Procedure outlined in this document. If the complaint received by a third party is not deemed to be related to TWWF, the third party will retain responsibility for investigating that complaint. 5.3 Complaint Documentation Procedure The following complainant information will be used to document each complaint received: The complainant s name; Any applicable property reference number if connected to a noise background testing location; The complainant s address; A receipt number for each complaint which is to be communicated to the complainant; The time, prevailing conditions and description of the complainant s concerns including the potential incidence of special audible characteristics (for a noise complaint); and Any other details regarding the specific nature of the complaint to enable it to be clearly recorded, and to enable subsequent investigation and assessment by TWWF. These details will be recorded in a single database by TWWF which will be made available to the Responsible Authority upon request. 5.4 Complaint Investigation, Evaluation and Response Procedures For the purposes of TWWF construction noise complaint evaluation, the following evaluation procedure will apply: Details of complainant and complaint will be recorded and forwarded to the TWWF Project Manager; The TWWF Project Manager (or their appointed intermediary) will make contact with the complainant within 10 business days of the date of the complaint; In consultation with the complainant, the TWWF Project Manager (or their appointed intermediary) will attempt to resolve the complaint; If following this the complaint remains unresolved the TWWF Project Manager (or their appointed intermediary) will engage an experienced independent acoustic engineer to investigate the complaint and develop a remediation plan; and If following this the complaint remains unresolved the TWWF Project Manager (or their appointed intermediary) will forward information pertaining to the complaint, together with the investigation Timboon West Wind Farm Construction Noise Management Plan 3

b) Sediment, Erosion and Water Quality Management Plan ( SEWQ Plan );

b) Sediment, Erosion and Water Quality Management Plan ( SEWQ Plan ); Naroghid Wind Farm Environmental Management Plan Naroghid Wind Farm Environmental Management Plan The Environmental Management Plan ( EMP ) is listed as a requirement in the Victorian Planning Provisions

More information

Murra Warra Wind Farm Project Environmental Management Plan

Murra Warra Wind Farm Project Environmental Management Plan 1. Introduction This (EMP) covers the pre-construction, construction, operation and decommissioning phases for the Murra Warra Wind Farm Project. RES Australia recognises the importance of reducing human

More information

Construction Management Plan (CMP) 227 Princess Highway, Dandenong

Construction Management Plan (CMP) 227 Princess Highway, Dandenong Construction Management Plan (CMP) 227 Princess Highway, Dandenong - Construction Management Plan (CMP) June 2017 S2966 CMP.D2 PREPARED BY: Sustainable Development Consultants 2nd Floor, 555 Riversdale

More information

AM-PR-003 Construction Environmental Management Plan (C-EMP)

AM-PR-003 Construction Environmental Management Plan (C-EMP) OMS Procedure AM-PR-003 Construction Environmental Management Plan (C-EMP) Revision: 1 Prepared by: Shannon Holroyd Authorised by: Marcus Manning Authorisation Date: 18th May 2015 This document has been

More information

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN JSP Construction Ltd 11-13 City Road Cardiff CF24 3BJ Revisions Issue Description Approved By Signed Date 19/10/16 1st issue AN JP 19.10/16 Rev A Updated with

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) Established 1907 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) DATE: JULY 2018 Version Date Section Modified 1 July 2018 All Reason for Modification Original Management Plan Review Team MCC Environmental,

More information

PLANNING PERMIT GRANTED BY THE MINISTER UNDER SECTION 97F OF THE PLANNING AND ENVIRONMENT ACT

PLANNING PERMIT GRANTED BY THE MINISTER UNDER SECTION 97F OF THE PLANNING AND ENVIRONMENT ACT Planning and Environment Regulations 2015 Form 11 Section 97F PLANNING PERMIT GRANTED BY THE MINISTER UNDER SECTION 97F OF THE PLANNING AND ENVIRONMENT ACT 1987 PLANNING PERMIT Permit No.: 2015/23858/A

More information

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol 1/11 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP EM EPA ERAP OEH PAH OOHWP EIS MCoA Distribution

More information

Date of Inspection 10 August 2017 Location of Inspection Manildra Solar Farm. ER Demelza Scott Proponent Representative Bjorn Schultz

Date of Inspection 10 August 2017 Location of Inspection Manildra Solar Farm. ER Demelza Scott Proponent Representative Bjorn Schultz Manildra Solar Farm ER Site Inspection Report Manildra Solar Farm Construction Environmental Representative (ER) Inspection Report For internal project use only. Document not for external release or use.

More information

Environmental Control Plan

Environmental Control Plan Environmental Control Plan Environmental Control Plan In accordance with Watts & Hughes Construction Waikato Bay of Plenty Limited. corporate strategies the Company has an Environment Control Plan which

More information

Alberta Transportation The City of Edmonton The City of Calgary

Alberta Transportation The City of Edmonton The City of Calgary Alberta Transportation The City of Edmonton The City of Calgary PUBLISHING INFORMATION TITLE: PREPARED BY: DOCUMENT HOLDER: Environmental Construction Operations (ECO) Plan Framework Instructions for

More information

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Manager Environment Approved: Executive General Manager Asset Strategy DOCUMENT HISTORY Date

More information

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI Traffic Management Plan Environmental Management and Monitoring Program Appendix VI Gunlake Quarries December 2009 Olsen Consulting Group Pty Ltd 6/25 Victoria Street WOLLONGONG 2500 PO Box 353 FIGTREE

More information

Performance Standards Compliance Checklist

Performance Standards Compliance Checklist Truckee Meadows Regional Stormwater Quality Management Program Performance Standards Compliance Checklist The checklist that follows identifies the BMPs that can be used at construction sites to meet each

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan EMP for the Stage 1 Construction and Operation of the Trainers Allotment Area at the Pakenham Racecourse located at Nar Nar Goon / Longwarry Road, Tynong Pty Ltd abn: 44 706

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

Construction Environment Management Plan

Construction Environment Management Plan Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated

More information

Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 21 ENVIRONMENTAL MANAGEMENT AND MITIGATION

Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 21 ENVIRONMENTAL MANAGEMENT AND MITIGATION Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 21 ENVIRONMENTAL MANAGEMENT AND MITIGATION October 2005 Measures Contents 21. 21-1 21.1 Introduction 21-1 21.2 Construction 21-1

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan Gunnedah Quarry Products Pty Ltd Prepared by Tim MacKellar, Gunnedah Quarry Products Document created 13.10.13 Reviewed 10.10.14 Reviewed 12.10.15 Reviewed 02.02.18

More information

Manningham Works Code of Practice

Manningham Works Code of Practice Manningham Works Code of Practice June 2017 Manningham City Council 699 Doncaster Road (PO Box 1) Doncaster Vic 3108 t 9840 9333 f 9848 3110 e manningham@manningham.vic.gov.au www.manningham.vic.gov.au

More information

DOORNVALLEI EXT 5 & 6

DOORNVALLEI EXT 5 & 6 DOORNVALLEI EXT 5 & 6 Proposed township establishment on portion 107 the farm Doornkloof 391 JR Sewer Pipe Crossings - Sesmylspruit Construction Method Statement April 2016 Revision 3 PREPARED FOR: PREPARED

More information

Environmental Management Programme (EMP)

Environmental Management Programme (EMP) Appendix D Environmental Management Programme (EMP) Please note that although Construction and Operational Phase measures are included in this EMP they are relevant to the issued Waste Management Licence

More information

APRIL 2015 CONTINGENCY PLANS

APRIL 2015 CONTINGENCY PLANS APRIL 2015 CONTINGENCY PLANS Prepared by: TERRATEST (PTY) LTD PO Box 794 HILTON Postal code 3245 Telephone:0333436789 Email:terratest@terratest.co.za Project director: Simon Johnson TABLE OF CONTENTS 1

More information

Environmental Guidelines for Construction Sites

Environmental Guidelines for Construction Sites Inspection Items Guidelines Remarks 1) Air Pollution Control 1a) Notification to EPD before Work Commencement If the work is classified as notifiable work such as site formation, reclamation, building

More information

GENERAL NOTES ENGINEERS OVERSIGHT 1. ALL ELEVATIONS, DIMENSIONS, ALIGNMENTS AND ORIENTATION OF ALL ELEMENTS SHOWN IN THE PLANS MUST BE APPROVED BY THE ENGINEER OR ENGINEER'S REPRESENTATIVE ( REP ENGINEER

More information

Annex L. Project Risk Analysis Matrix

Annex L. Project Risk Analysis Matrix Annex L Project Risk Analysis Matrix L1 Table L1 Project Environmental Risk Analysis Local Road upgrades: Loss/damage cultural heritage values Low Acceptable Loss/damage of biodiversity value, EEC Construction

More information

Management Plan: Hazardous Materials Removal & Demolition

Management Plan: Hazardous Materials Removal & Demolition Management Plan: Hazardous Materials Removal & Demolition Kingswood School (Upper Site), Corby 1.0 Introduction 1.1 Background Lambert Smith Hampton has been instructed by Northamptonshire County Council

More information

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES Environmental / Social issue/ aspect/ activity Anticipated negative impact Management and mitigation

More information

Council Roadside Reserves Project. Site Management Checklists and Safeguards

Council Roadside Reserves Project. Site Management Checklists and Safeguards Council Roadside Reserves Project Site Management Checklists and Safeguards Introduction These slides cover An introduction to checklists and safeguards Example pre-construction checklist Practical safeguards

More information

PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES

PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENERGY AND MINES SAND AND GRAVEL PERMIT APPROVING WORK SYSTEM AND RECLAMATION PROGRAM (Issued pursuant to Section 10 of the Mines Act R.S.B.C. 1996, C.293) Permit:

More information

Site EMP Kit- Guidance Notes

Site EMP Kit- Guidance Notes Site EMP Kit- Guidance Notes Introduction This Guide has been designed to assist applicants to understand council s requirements for Site Environmental Management Plans (Site EMP s) for subdivisions. The

More information

CON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist

CON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist Con Appendix FINAL US Army Garrison, Hawaii October 2015 CON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist Storm Water Management Plan CON Appendix C U.S. Army Garrison-Hawaii

More information

DEMOLITION TRADE SPECIFICATION

DEMOLITION TRADE SPECIFICATION DEMOLITION TRADE SPECIFICATION GENERAL a) BDW Trading Limited Barratt Homes and David Wilson Homes are all trading names of BDW Trading Limited the Company. b) Site Condition The Contractor is to examine

More information

ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009

ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN Environment Protection Authority, ACT May 2009 ISBN-13: 978-0-642-60494-1 ISBN-10: 0-642-60494-0 Australian Capital Territory,

More information

Environmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review

Environmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review Environmental Management Plan Introduction This Environmental Management Plan (EMP) has been prepared for SEF Energy Co. Ltd. for the purpose of providing a stand-alone plan for managing the potential

More information

STORM WATER POLLUTION PREVENTION PLAN TEMPLATE

STORM WATER POLLUTION PREVENTION PLAN TEMPLATE STORM WATER POLLUTION PREVENTION PLAN TEMPLATE Cover Page Certifications Project, Owner, Operator, SWPPP Preparer, Date, Project Dates Signed by RIDOT (Owner) and CONTRACTOR (as Operator) of Contents Introduction

More information

IN THE KYRGYZ REPUBLIC

IN THE KYRGYZ REPUBLIC Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL ROAD REHABILITATION (OSH-ISFANA) PROJECT (NRRP)- WORLD BANK PPA Q 6240 CONSULTANCY

More information

Date of Inspection 14/06/2018 Location of Inspection Manildra Solar Farm. ER Demelza Scott Proponent Representative Bjorn Schultz

Date of Inspection 14/06/2018 Location of Inspection Manildra Solar Farm. ER Demelza Scott Proponent Representative Bjorn Schultz Manildra Solar Farm ER Site Inspection Report Manildra Solar Farm Construction Environmental Representative (ER) Inspection Report For internal project use only. Document not for external release or use.

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5B Access Tracks, Hardstanding Areas, Electrical Compounds, Borrow Pit And Cable Laying Construction Method Statement Copyright ESB International

More information

APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER SHEET FOR SPECIAL CONDITIONS AND PERMIT NUMBERING

APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER SHEET FOR SPECIAL CONDITIONS AND PERMIT NUMBERING APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER FOR SPECIAL CONDITIONS AND PERMIT NUMBERING GENERAL NOTES: HOUSE GREEN HOUSE 1900 S. NORFOLK ST. SUITE 350 GARAGE GRADING

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 21149 09-October Licensee SAMSUNG C&T CORPORATION BOUYGUES CONSTRUCTION AUSTRALIA PTY LTD LENDLEASE ENGINEERING PTY LIMITED LVL 14 TWR3, INT TWRS, EXCHANGE PL

More information

H28. Special Purpose Quarry Zone

H28. Special Purpose Quarry Zone H28. Special Purpose Quarry Zone H28.1. Zone description Mineral resources are important to Auckland s economy and development. The Special Purpose Quarry Zone provides for significant mineral extraction

More information

Traffic Management Plan

Traffic Management Plan Parkes PV power plant Traffic Management Plan Doc ID: PL-HS-02 Rev No.: 1 Rev Date: 10/02/2017 Prepared By: Benoit Arsac Construction Manager BYCA Reviewed by: Philippe Nguyen Senior Project Manager BYCA

More information

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014 MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of

More information

Operation Soil and Water Management Plan for Ammonium Nitrate Emulsion Production Facility

Operation Soil and Water Management Plan for Ammonium Nitrate Emulsion Production Facility Orica Australia Pty Limited 14-Nov-2017 Operation Soil and Water Management Plan for Ammonium Nitrate Emulsion Production Facility Orica, Richmond Vale Production Facility Operation Soil and Water Management

More information

Section 75J of the Environmental Planning & Assessment Act 1979

Section 75J of the Environmental Planning & Assessment Act 1979 Project Approval Section 75J of the Environmental Planning & Assessment Act 1979 I approve the project application referred to in schedule 1, subject to the conditions in schedule 2. These conditions are

More information

Borrow Pit and Quarry Management Procedure Environmental

Borrow Pit and Quarry Management Procedure Environmental 1 Purpose and Scope This procedure specifies the operational environmental requirements relating to borrow pit (BP) and quarry management at the Roy Hill Project. This procedure applies to all personnel

More information

Big Thunder Wind Park

Big Thunder Wind Park Construction Plan Report DRAFT Prepared by: M.K. Ince and Associates Ltd. May 18, 2010 TABLE OF CONTENTS BIG THUNDER WIND PARK... 1 1 PROJECT OVERVIEW... 1 1.1 PROJECT SCHEDULE... 2 2 CONSTRUCTION ACTIVITIES...

More information

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV Esso Highlands Limited Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 11: PGGP-EH-SPENV-000018-013 LNG Project Page 2 of 13 CONTENTS 1.0 Objectives... 3 2.0 Legal and Other

More information

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP)

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP) Tararua District Council Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP) NOTE: This is a draft ESCP in current preparation. Additional and updated information will

More information

CHAPTER 6 - How to Prepare a SWPPP

CHAPTER 6 - How to Prepare a SWPPP All construction sites which disturb an area of 1 acre or more, currently need a UPDES permit from the State of Utah. As a condition of the permit, a Stormwater Pollution Prevention Plan (SWPPP) must be

More information

Final Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Heat Treatment Furnace at Scaw Metals High Chrome

Final Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Heat Treatment Furnace at Scaw Metals High Chrome Final Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Heat Treatment Furnace at Scaw Metals High Chrome Ball Plant in Germiston A Report For: Scaw South Africa

More information

WI-ENV-PER-0013 GROUND DISTURBANCE PERMIT

WI-ENV-PER-0013 GROUND DISTURBANCE PERMIT WI-ENV-PER-0013 GROUND DISTURBANCE PERMIT PERMIT NUMBER PERMIT NAME DATE RECEIVED PERMIT APPROVAL DATE PERMIT EXPIRY DATE GDP- (Office use only) This Ground Disturbance Permit (GDP) is to be completed

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Environmental Specialist Responsible Manager: Head of Environment Responsible Executive:

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Contamination Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site

More information

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME OPERA PHASE: ENVIRONMENTAL MANAGENT PROGRAMME 1. OBJECTIVE The overall goal for the Environmental Programme (O) is to ensure that the operation of the wind energy facility (WEF) does not have unforeseen

More information

UNDERGROUND OPERATION

UNDERGROUND OPERATION UNDERGROUND OPERATION Approved Mine Manager Date: Environmental Adviser Date: Integra Coal Underground ENVIRONMENTAL MANAGEMENT STRATEGY TABLE OF CONTENTS 1 GENERAL 5 C:\Users\oshan\AppData\Local\Microsoft\Windows\Temporary

More information

Section 75J of the Environmental Planning and Assessment Act 1979

Section 75J of the Environmental Planning and Assessment Act 1979 Project Approval Section 75J of the Environmental Planning and Assessment Act 1979 I approve the project application referred to in Schedule 1, subject to the conditions in Schedules 2 to 4. These conditions

More information

DIVISION of WATER QUALITY NDPDES PROGRAM

DIVISION of WATER QUALITY NDPDES PROGRAM DIVISION of WATER QUALITY NDPDES PROGRAM THIS PAGE IS NOT PART OF ANY SWPPP CONSTRUCTION Storm Water Pollution Prevention Plan * SWPPP Template (2016-01) A SWPPP must be prepared and implemented for all

More information

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL This manual applies to all development projects within Pitkin County. Contact the Planning Department at 970-429-2799 with any questions. November 2017

More information

ULDA Decision Notice

ULDA Decision Notice ULDA Decision Notice Site Address Bowen St, Roma Real property description Lot 142 SP250497 Type of approval UDA development approval subject to conditions Aspects of development Reconfiguring a Lot with

More information

STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY

STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY STATE OF COLORADO GENERAL PERMIT APPLICATION Updated 11/04 STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY This application is for use by all stormwater dischargers engaged in construction

More information

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw 6410 2006 The Erosion and Sediment Control plan should seek (i) to protect the soil surface from erosion where possible and (ii) capture

More information

Clyde Street Remediation Project The Project Location

Clyde Street Remediation Project The Project Location The Project Location The Project Site Who is Jemena? Jemena is an Australian infrastructure company that builds, owns and manages a combination of major electricity, gas and water assets in Australia.

More information

Construction Noise Management Plan

Construction Noise Management Plan Construction Noise Management Plan Victoria Park Viaduct Side Protection Upgrade Project 27 November 2014 Final Page 2 Record of amendment Revision Description of change Effective date Updated by Incomplete

More information

Environmental Assessment Approval

Environmental Assessment Approval Environmental Assessment Approval Approval Date: Original Dated October 1, 2010 Hants County Aggregate Quarry Extension Project Municipal Enterprises Ltd., Proponent Hants County, Nova Scotia The Hants

More information

SERVICE BOREHOLES MANAGEMENT PLAN

SERVICE BOREHOLES MANAGEMENT PLAN Add CSG specific graphic to suit project SERVICE BOREHOLES MANAGEMENT PLAN BULLI SEAM OPERATIONS PROJECT APPLICATION NO. 08_0150 October 2012 Revision No: 0 SERVICE BOREHOLES MANAGEMENT PLAN Table of Contents

More information

PS BIODIVERSITY PURPOSE AND SCOPE FAUNA CRITICAL CONTROLS FLORA CRITICAL CONTROLS

PS BIODIVERSITY PURPOSE AND SCOPE FAUNA CRITICAL CONTROLS FLORA CRITICAL CONTROLS PS BIODIVERSITY PURPOSE AND SCOPE The intent of this primary standard is to reduce and eliminate significant environmental impacts to biodiversity including native fauna and flora as a result of construction

More information

GRADING, EROSION AND SEDIMENTATION CONTROL

GRADING, EROSION AND SEDIMENTATION CONTROL SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,

More information

Temporary Watercourse Crossing: Fords

Temporary Watercourse Crossing: Fords Temporary Watercourse Crossing: Fords DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

Outline Construction and Environmental Management Plan

Outline Construction and Environmental Management Plan 1.1.1 Gwent Farmers Community Solar Scheme January 2018 Outline Construction and Environmental Management Plan www.savills.co.uk Project: Client: Gwent Levels Community Solar Scheme Partnership Ltd Job

More information

Environmental Assessment Approval

Environmental Assessment Approval Environmental Assessment Approval Approval Date: Original Dated April 20, 2012 Trimper Sand and Gravel Pit Expansion Ivan H. Trimper Construction Ltd., Proponent Annapolis County, Nova Scotia The Trimper

More information

ENVIRONMENTAL GUIDANCE NOTES: CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP)

ENVIRONMENTAL GUIDANCE NOTES: CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP) ENVIRONMENTAL GUIDANCE NOTES: CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP) Disclaimer: The information contained in this communication document is intended solely for the use of guidance cannot be

More information

STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents. SWMP Page # or Reference Location Yes/No

STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents. SWMP Page # or Reference Location Yes/No STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents Site Description A description of construction activity. The proposed sequence for major activities. Estimates of the total

More information

Emergency Management Guidelines For Wind Energy Facilities. Emergency Management Guidelines for Wind Energy Facilities

Emergency Management Guidelines For Wind Energy Facilities. Emergency Management Guidelines for Wind Energy Facilities Emergency Management Guidelines For Wind Energy Facilities Emergency Management Guidelines for Wind Energy Facilities MAY 2015 Emergency Management Guidelines For Wind Energy Facilities 1 Emergency Management

More information

For controlled copies of this EMS the copy number is shown below and initialled in Red by the Light Horse Business Centre Project Manager.

For controlled copies of this EMS the copy number is shown below and initialled in Red by the Light Horse Business Centre Project Manager. LHBC Old Wallgrove Road, Eastern Creek Environmental Management Strategy (EMS) Aboriginal Heritage Plan June 2011 ENVIRONMENTAL MANAGEMENT STRATEGY (EMS) ABORIGINAL HERITAGE MANAGEMENT PLAN Former QUARRY

More information

Division 15 Earthworks Code (including Lot Filling)

Division 15 Earthworks Code (including Lot Filling) Division 15 Earthworks Code (including Lot Filling) 12.15.1 Earthworks Code (1) The provisions in this division comprise the (2) They are compliance with the Earthworks Code (Section 12.15.2); overall

More information

Surface Water Management Procedure Environment

Surface Water Management Procedure Environment 1 Purpose and Scope This procedure specifies the operational environmental requirements that relate to surface water management at the Roy Hill Project. This procedure applies to all personnel involved

More information

Environment Protection Licence

Environment Protection Licence Licence Details Number: Anniversary Date: 21149 09-October Licensee SAMSUNG C&T CORPORATION BOUYGUES CONSTRUCTION AUSTRALIA PTY LTD LENDLEASE ENGINEERING PTY LIMITED EXCHANGE PLACE, 300 BARANGAROO AVENUE

More information

LOSTOCK SUSTAINABLE ENERGY PLANT VARIATION OF CONSENT UNDER SECTION 36C OF THE ELECTRICITY ACT 1989

LOSTOCK SUSTAINABLE ENERGY PLANT VARIATION OF CONSENT UNDER SECTION 36C OF THE ELECTRICITY ACT 1989 DOCUMENT 8b LOSTOCK SUSTAINABLE ENERGY PLANT VARIATION OF CONSENT UNDER SECTION 36C OF THE ELECTRICITY ACT 1989 DIRECTION UNDER SECTION 90(2ZA) OF THE TOWN AND COUNTRY PLANNING ACT 1990 TO VARY THE CONDITIONS

More information

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants

More information

Victorian Desalination Project

Victorian Desalination Project Victorian Desalination Project D&C PGA Attachment C - Environmental Register TDV 0 EV RG 0011.C 03 # D&C EMP ATTACHMENT C ENVIRONMENTAL RISK REGISTER - PLANT AND GENERAL AREA Construction Method Criteria

More information

Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash

Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash Specifications Request for Quotation (RFQ) RFQ Title RFQ Number Level 1 Essential Energy Works for the Warialda Truck Wash GWY_1819_Q03 Issue Date 21st December 2018 This document contains the specification

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Air Quality Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan Site:.. Section 1 - Risk Assessment 1. Identify the environmental aspects relevant to your site. 2. Under notes, document the items that influence the assignment of the level

More information

WASTE MANAGEMENT PLAN

WASTE MANAGEMENT PLAN DEA REF: 14/12/16/3/3/2/1049 WASTE MANAGEMENT PLAN THE PROPOSED CONSTRUCTION OF A 90MW PV SOLAR PARK PROJECT, AND 66KV TRANSMISSION LINE TO CONNECT TO EXISTING SUBSTATION OVER PORTIONS 3, 4, 6 AND THE

More information

Gold Coast Airport Tenant Environment Management Guideline

Gold Coast Airport Tenant Environment Management Guideline Gold Coast Airport Tenant Environment Management Guideline July 2012 Introduction Implementation of sound environment management practices is critical in meeting legislative requirements and business objectives.

More information

Photomontages SECTION 10

Photomontages SECTION 10 Photomontages SECTION 10 10.1 Photomontages Photomontages have been prepared by Truescape Visual Communication to illustrate the likely location of the Collector Wind Farm turbines following construction.

More information

Construction Environment Management Plan (CEMP) Requirements

Construction Environment Management Plan (CEMP) Requirements Australia Pacific Airports (Melbourne) Issue No: 3 Issue Date: 19 December 2016 Construction Environment Management Plan (CEMP) Requirements DOCUMENT No. PP002 DOCUMENT CONTROLLER: APPROVED: NAME: Jesse

More information

MINING OPERATION SERVICES

MINING OPERATION SERVICES METROMIX PTY LIMITED Lower Level Management Plan Prepared in conjunction with: MINING OPERATION SERVICES SEPTEMBER 2016 CONTENTS Page COMMONLY USED ACRONYMS... 4 1 INTRODUCTION... 5 2 APPROVED ACTIVITIES...

More information

Draft Dust Management Plan

Draft Dust Management Plan Draft Dust Management Plan December 2017 Mt Messenger Alliance MMA-ENV-AIR-RPT-1032 Quality Assurance Statement Prepared by: Dylan Vernall, Sharon Atkins Tonkin and Taylor Ltd Reviewed by: Jenny Simpson

More information

Fact Sheet: Anglesea Power Station and Mine Rehabilitation Overview

Fact Sheet: Anglesea Power Station and Mine Rehabilitation Overview Fact Sheet: Anglesea Power Station and Mine Rehabilitation Overview After 46 years of operation Alcoa s Anglesea Power Station and Coal Mine was permanently shut down on 31 August 2015. The planning for

More information

FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES

FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES 1. COVERAGE UNDER THIS GENERAL PERMIT Area of Coverage: This permit covers all areas of the Commonwealth

More information

Chapter 750 WIND POWER GENERATION FACILITIES

Chapter 750 WIND POWER GENERATION FACILITIES Chapter 750 WIND POWER GENERATION FACILITIES 750.01 Purpose 750.02 Definitions 750.03 Designated Areas 750.04 Permitted Uses 750.05 Conditional Uses 750.06 Construction Standards 750.07 Application Requirements

More information

Engineering Compliance East London Regional Waste Disposal Site A Case Study

Engineering Compliance East London Regional Waste Disposal Site A Case Study Engineering Compliance East London Regional Waste Disposal Site A Case Study A.S Dookhi, Envitech Solutions (Pty) Ltd, South Africa, nash@envitech.co.za ABSTRACT The East London Regional Waste Disposal

More information

City of Glendale Stormwater Management Plan Checklist

City of Glendale Stormwater Management Plan Checklist City of Glendale Stormwater Management Plan Checklist Project: Title of Plan: Date: Date of Plan: Reviewer: Most Recent Revision: Criteria Yes No Identify a SWMP Administrator and an alternate - The SWMP

More information

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water Storm Water Permitting Requirements for Construction Activities John Mathews Storm Water Program Manager Division of Surface Water Why Permit Storm Water? Impacts During Construction Not an issue until

More information

Field Instruction. All Horizon Power workers who work in and around excavations.

Field Instruction. All Horizon Power workers who work in and around excavations. 6.4 Excavation work and directional drilling Purpose This instruction provides the minimum requirements for: All Horizon Power workers who work in and around excavations. All Horizon Power workers who

More information

Emergency Contact Numbers: Police, Fire, Ambulance 000 SES Vic Roads EPA Vic 1300 EPA VIC ( ) Safe Work Method Statement

Emergency Contact Numbers: Police, Fire, Ambulance 000 SES Vic Roads EPA Vic 1300 EPA VIC ( ) Safe Work Method Statement Safe Work Method Statement Emergency Contact Numbers: Police, Fire, Ambulance 000 SES 132 500 Vic Roads 13 11 70 EPA Vic 1300 EPA VIC (1300 372 842) WMS No: Task/Activity Grader Operation SPH Job No: Date

More information