Stormwater Management Permit Application LESS Than One Acre. Public Works Department st Ave East Kalispell, Montana (406)
|
|
- Shanon Cox
- 5 years ago
- Views:
Transcription
1 Public Works Department st Ave East Kalispell, Montana (406) Note: This permit is separate from any permits required by the Montana Department of Environmental Quality. A State Stormwater Construction Permit is required for all land disturbance activities equal to or greater than one (1) acre or for land disturbance activities less than one (1) acre that are part of a larger common plan of development or sale that would disturb one (1) acre or more. **No land disturbance is permitted on any project site without an approved City of Kalispell Permit** (1) Contact Information (a) Project Owner: (b) Contractor: (c) Engineer: (2) Project Information Project Address : Lot Number: Subdivision (if applicable): Project Size: (Land Disturbance) Permit Application LESS than one acre $10.00 Permit Number Date Submitted Final Stabilization Date GREATER or equal to one acre $45.00 (3) Nature of Construction Check the appropriate box(es) or provide a brief description that indicates the general nature of the construction activities. Single Family Residential Multi-Family Residential Utility Commercial/Industrial Highway / Road Other (describe): Description of proposed work: SWM Permit Application Page 1 of 5
2 (4) Site Map Checklist Applicant must provide a site map(s) that includes the following: Project boundary, North arrow, and adjacent streets Direction(s) of stormwater run-on and runoff Public and private stormwater infrastructure on or adjacent to site Receiving waters on or adjacent to site Material storage and spoil area(s) Equipment staging area(s) All best management practices (BMPs) selected in Section 5 (5) Required Stormwater Controls Permit Number Date Submitted Final Stabilization Date Inlet/Outlet protection: Inlets and outlets receiving site runoff require BMPs that filter stormwater before flowing into underground infrastructure and BMPs that prevent erosion at outlets. Check BMPs from each list that will be used and show location(s) on map. Inlet protection: Outlet protection: Pre-manufactured drop inlet protection Riprap to prevent erosion at outlets Straw wattles Stabilization and erosion control of disturbed areas: Disturbed areas require BMPs that prevent erosion of barren ground. Temporary seeding Preservation of existing vegetation Mulching/straw/compost Soil binders Embankment protector Surface Roughening Perimeter control: Project boundaries require BMPs that contain stormwater flowing from disturbed areas. Silt fence Vegetated buffer Fiber roll SWM Permit Application Page 2 of 5
3 Sediment and stockpile control: Sediment and stockpiles require containment and BMPs that prevent erosion and displacement of loose material. Check BMPs from each list that will be used and show location(s) on map. Sediment control: Sediment trap Check dams Fiber rolls De-silting basin Street sweeping - Frequency: Stockpile control: Straw wattle Silt fence Cover/tarp Watering Tracking control: Travel and exit points require BMPs that prevent tracking of debris off-site onto the right-of-way and meet the City of Kalispell's Standards for Design and Construction. Stabilized construction entrance/exit Stabilized construction roadway Waste management, spill prevention, and general pollution prevention: Construction activities create waste and pollution and require BMPs to prevent contamination of local waterways. Concrete washout area Saw cutting and grinding controls Enclosed waste collection Spill prevention and control measures Covered storage of chemicals, paint, petroleum, fertilizer, and pesticides Sanitary waste facilities - minimum of 15 feet from storm drain and water bodies Wind erosion control: Wind can erode barren land and stockpiles and requires BMPs to reduce erosion. Watering Seeding SWM Permit Application Page 3 of 5
4 Run-on protection: Sites below slopes may have issues with run on and require BMPs to prevent run on from eroding the site. Temporary slope drain Drainage swales Permanent erosion control: Disturbed land related to the project activities require BMPs before final occupancy of structures to prevent erosion. Check BMPs that will be used. Landscaping/vegetation Seeding Hydroseed Identify staff responsible for: _ (7) Water bodies and Storm Conveyance Systems (a) List water bodies within 200 of project Streams: Wetlands: Sloughs: Hydromulch Sod Site inspections and record keeping Daily cleanup of construction site to ensure all litter is contained in appropriate enclosure or container (6) Project Schedule Start Date: Completion Date: Final Stabilization Date: Lakes: Rivers: Other: (b) Are any water bodies that receive stormwater runoff from the project impaired? Yes No If yes, what are the impairments: Sediment Dissolved Oxygen Nutrients Temperature Other: (c) List storm conveyance systems within 100 of project Ditches: Swales: Detention Facilities: Storm Drain Inlets: Pipe Inlets/Outlets: Gutter: SWM Permit Application Page 4 of 5
5 (d) Flood Plain: Is the project in a flood plain? Yes If yes, is a permit: (8) Certifications Required If yes, is the site/ will the site be: Applicant agrees to: (9) Acknowledgment Certificate Permit Application Pending Initial: Install applicable BMPs prior to the start of land disturbing activities. Permit Number Date Submitted Final Stabilization Date Initial: Keep this permit posted on-site and updated to reflect current site conditions. Initial: Inspect and maintain all control measures at the end of EACH workday. Initial: Contain and dispose of all pollutants generated by local, state, and federal regulations (i.e. form oil, oils/greases, fuel, masonry wash water, concrete cutting slurry, asphalt sealant, paint, and all other pollutants hazardous to the environment). Initial: Maintain a spill kit on-site, which includes, at a minimum, absorbent material, cleanup tools, and covered waste container. I certify that I am the Owner or Owner s authorized agent. If acting as an authorized agent, I further certify that I am authorized to act as the Owners agent regarding the property at the above-referenced address for the purpose of filing applications for decisions, permits or review under the City of Kalispell Ordinance 1600 and have full power and authority to perform on behalf of the Owner all acts required to enable the City to process and review such applications I certify that the information on this application is true and correct and understand that I shall not start this project until this application is approved. I shall comply with the laws of the State of Montana and the ordinances of the City of Kalispell. Signature of Legally Responsible Person (Submission must include original signature) Name (printed) Date Title **For Official Use Only** LESS than one acre Received City By Date SMP Checklist Yes No Field Visit SMP Plan Yes No Approval SMP Map Yes No Comments: Payment-$10.00 Yes No No Issued Delineated Staked Perimeter BMPs installed SWM Permit Application Page 5 of 5
2010 California Green Building Standards Code. Residential and Non-Residential Development
2010 California Green Building Standards Code Residential and Non-Residential Development Stormwater Management (Site Development) Requirements Engineering, Surveying & Permit Services Department 2700
More informationPerformance Standards Compliance Checklist
Truckee Meadows Regional Stormwater Quality Management Program Performance Standards Compliance Checklist The checklist that follows identifies the BMPs that can be used at construction sites to meet each
More informationCity of Glendale Stormwater Management Plan Checklist
City of Glendale Stormwater Management Plan Checklist Project: Title of Plan: Date: Date of Plan: Reviewer: Most Recent Revision: Criteria Yes No Identify a SWMP Administrator and an alternate - The SWMP
More informationCITY OF CHICO. Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects. Project Address: Building Permit Number:
CITY OF CHICO Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects Project Address: Building Permit Number: What is this document for? The City s Phase II MS4 NPDES General
More informationCity of West Sacramento Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects
Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects Project Name: Page intentionally left blank. - 2 - What is this document for? The City s Phase II MS4 NPDES General Permit
More informationErosion Control Inspection Form
Project Name Address Inspection Date Time Name of Certified Erosion Sediment Lead (CESCL) or qualified inspector if less than one acre Print Name: Approximate rainfall amount since the last inspection
More informationCity of El Centro. Erosion and Sediment Control Plan Review Checklist. Reviewer: Review Date:
City of El Centro Erosion and Sediment Control Plan Review Checklist Project: Reviewer: Review Date: If an item below is marked No, the Erosion and Sediment Control Plan (Plan) either does not provide
More informationLAND DISTURBANCE PERMIT
SPRINGVILLE CITY Application Date: 110 South Main Springville, UT 84663 Permit Number: (801) 491-2780 Caselle #2208 Project Name: Project Address: LAND DISTURBANCE PERMIT Priority Site Owner s Name Phone
More informationSingle Family Residential Construction Erosion/Sediment Control Standards
Single Family Residential Construction Erosion/Sediment Control Standards Introduction: This booklet contains standard plans and procedures sufficient for typical building construction. It is not intended
More informationConstruction Site Inspections
Construction Site Inspections Keep The Mud Out of The Creek Barry Tonning, Tetra Tech Inspections help to identify and correct problems! Inspection requirements Must inspect site every 14 days (LA) Some
More informationAppendix B Construction SWPPP Short Form
Appendix B Construction SWPPP Short Form Projects falling within the thresholds listed below may use this short form instead of preparing a formal Construction Stormwater Pollution Prevention Plan (SWPPP).
More informationTown of Friday Harbor PO Box 219 / Friday Harbor / WA / (360) / fax (360) /
Town of Friday Harbor PO Box 219 / Friday Harbor / WA / 98250 (360) 378-2810 / fax (360) 378-5339 / www.fridayharbor.org LAND CLEARING, GRADING, OR FILLING PERMIT APPLICATION APPLICATION DATE GRD No. APPLICANT/FRANCHISE
More informationConstruction Site Runoff (CSR) Permit Application Permit Fee $150.00
Construction Site Runoff (CSR) Permit Application Permit Fee $150.00 Site Address or Lot and Subdivision: Applicant Name: Applicant s E-Mail: Applicant s Address: Telephone: (office) City, State, ZIP (cell)
More informationProject Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering)
Compliance Assistance Program Checklist 1 Start of Construction Stormwater Self-Certification Checklist Note: This checklist must be completed and submitted to the DEM no later than 30 days after initiating
More informationUnderstanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)
Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department
More informationErosion & Sedimentation Control Policy
Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of
More informationSECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY
1. PURPOSE: SECTION V CHAPTER 12 STORMWATER POLLUTION PREVENTION POLICY The purpose of this policy is to establish procedures to facilitate compliance with federal, state and local stormwater regulations
More informationSTORMWATER POLLUTION PREVENTION PLAN
STORMWATER POLLUTION PREVENTION PLAN PART I GENERAL PROJECT INFORMATION - To be completed by Owner or Consultant PROJECT NAME: PROPERTY OWNER S NAME: ADDRESS: CITY: STATE: ZIP: PHONE #: FAX #: MOBILE #:
More informationSTORM WATER POLLUTION PREVENTION PLAN TEMPLATE
STORM WATER POLLUTION PREVENTION PLAN TEMPLATE Cover Page Certifications Project, Owner, Operator, SWPPP Preparer, Date, Project Dates Signed by RIDOT (Owner) and CONTRACTOR (as Operator) of Contents Introduction
More informationConstruction Stormwater Best Management Practices
Marin County Stormwater Pollution Prevention Program San Rafael, California November 12, 2015 Construction Stormwater Best Management Practices The mention or image of any product or service is for illustrative
More informationConstruction Phasing Bad
Construction Entrances Construction Phasing Remove mud and dirt from the tires of construction vehicles before they enter a paved roadway. Propoerly size entrance BMP's for all anticipated vehicles. Make
More informationSTORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY
STATE OF COLORADO GENERAL PERMIT APPLICATION Updated 11/04 STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY This application is for use by all stormwater dischargers engaged in construction
More informationStormwater Pollution Prevention Plan Engineering Department Requirements
Stormwater Pollution Prevention Plan Engineering Department Requirements The following are the stormwater pollution prevention plan requirements for the above referenced project. If you have any questions
More informationShelbyville, KY Stormwater Best Management Practices
5. Detention/retention volumes in the floodplain buffer shall count as fill if applied in a manner where off site floodplain storage volume is lost. 1.7 Residential and Home Owner Pollution Control Citizens
More informationAPPENDIX I. Plan Reviewer Checklist
APPENDIX I Plan Reviewer Checklist PLAN REVIEW CHECKLIST Annual Standards and Specifications The ESC/SWM Plan clearly indicates the version of Virginia Tech Annual Standards and Specifications applicable.
More informationSACHSE EROSION CONTROL GUIDELINES
SACHSE EROSION CONTROL GUIDELINES Section I. Definitions The following words, terms, and phrases, when used in this guideline, shall have the meanings ascribed to them in this Section, except where the
More informationMINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014
MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of
More informationStorm Water Pollution Prevention Plan (SWP3) Checklist
. Summit Soil and Water Conservation District Storm Water Pollution Prevention Plan (SWP3) Checklist Modified from the Ohio EPA SWP3 Checklist (Revised January 2017) SITE NAME: REVIEWER: DATE RECEIVED:
More informationEROSION CONTROL AND GRADING PERMIT APPLICATION
EROSION CONTROL AND GRADING PERMIT APPLICATION COMMUNITY DEVELOPMENT DEPARTMENT 1735 MONTGOMERY STREET OROVILLE, CA 95965 530-538-2420 FAX (530) 5382426 www.cityoforoville.org APPLICATION DATE PERMIT FEE
More informationNEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL
NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by
More informationLAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET
Permit. ARR150000 SITE WITH AUTOMATIC COVERAGE (LESS THAN 5 ACRES) CONSTRUCTION SITE NOTICE FOR THE Arkansas Department of Environmental Quality (ADEQ) Storm Water Program NPDES GENERAL PERMIT NO. ARR150000
More informationRegulatory Requirements
7B-1 Design Manual Chapter 7 - Erosion and Sediment Control 7B - Regulatory Requirements Regulatory Requirements A. National Pollutant Discharge Elimination System (NPDES) The Clean Water Act established
More informationLAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET
Permit. ARR150000 SITE WITH AUTOMATIC COVERAGE (LESS THAN 5 ACRES) CONSTRUCTION SITE NOTICE FOR THE Arkansas Department of Environmental Quality (ADEQ) Storm Water Program NPDES GENERAL PERMIT NO. ARR150000
More informationD EROSION AND SEDIMENT CONTROL. Table of Contents
Table of Contents D1. GENERAL... 1 D2. OBJECTIVE... 1 D3. REFERENCE MATERIAL... 1 D4. REGULATORY REQUIREMENTS... 1 D5. EROSION AND SEDIMENT CONTROL (ESC) PLANS... 2 D5.1 Goals and Objectives:... 2 D5.2
More informationMiddle Tennessee State University (MTSU) Stormwater Plan Review Checklist
For Middle Tennessee State University (MTSU) projects, the Project Manager or other MTSU designee will serve as the Plan Reviewer. This checklist is to be completed by the Plan Reviewer on behalf of MTSU.
More informationCITY OF JENKS EARTH CHANGE PERMIT APPLICATION
CITY OF JENKS EARTH CHANGE PERMIT APPLICATION Any applicable State or Federal permits must be attached to this application or must be applied for with copies attached to this application if this permit
More informationTemporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction Activities
Development Services 1775 12 th Ave. NW P.O. Box 1307 Issaquah, WA 98027 425-837-3100 issaquahwa.gov Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction
More informationCORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN
CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN SITUATED IN THE SW ¼ OF SECTION 18, T.2S., R.67W., OF THE 6 TH P.M. COUNTY OF ADAMS, STATE OF COLORADO PREPARED FOR: Thornton Cornerstone
More informationSECTION 11 PART I STORMWATER QUALITY PROTECTION Definitions / Acronyms 11-3 PART 1 CONSTRUCTION PRACTICES
SECTION 11 PART I STORMWATER QUALITY PROTECTION CONTENTS Page 11-1 Definitions / Acronyms 11-3 PART 1 CONSTRUCTION PRACTICES 11-2 Stormwater Pollution Prevention Plan (SWPPP) 11-3 11-3 Erosion and Sediment
More informationADDENDUM NUMBER TWO. A. SECTION ADVERTISEMENT FOR BIDS 1. REVISE Sealed Bid Date/Time/Location paragraph to read as follows:
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS SECTION 00 91 11.02 ADDENDUM NUMBER TWO June 22, 2016 TO: PLANHOLDERS SUBJECT: PCT TRUCK STAGING PROJECT PROJECT NO. 091606 CONTRACT NO. 070287 This
More informationEROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY
31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed
More informationItems in this checklist identify the base requirements that are to be provided by the design professional.
The Project Manager or other Owner designee will serve as the Plan Reviewer. This checklist is to be completed by the Plan Reviewer on behalf of the Owner. The Plan Reviewer s role is to review the submitted
More informationMemo. To: From: cc: For further assistance please contact Ben Ruzowicz, GSWCC Technical Specialist at (706)
Memo To: From: cc: Local Issuing Authorities, Design Professionals, Plan Reviewers and Other Interested Parties The Georgia Soil and Water Conservation Commission and the Georgia Environmental Protection
More informationSchedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw
Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw 6410 2006 The Erosion and Sediment Control plan should seek (i) to protect the soil surface from erosion where possible and (ii) capture
More informationPlease print or type.
SOIL EROSION AND SEDIMENTATION CONTROL PERMIT APPLICATION 6-18-07 Ann kjjkjkff- ANN ARBOR CHARTER TOWNSHIP 3792 Pontiac Trail, Ann Arbor, Michigan 48105-9656 Phone (734) 663-3418 Website: www.aatwp.org
More informationBuilding Better Storm Water Quality
Building Better Storm Water Quality s Storm Water Pollution Prevention Guidelines for Development Construction Projects City of El Segundo 350 Main Street (310) 524-2380 El Segundo, California 90245 Introduction
More information2.1 MINIMUM WATER QUALITY PROTECTION REQUIREMENTS FOR DEVELOPMENT CONSTRUCTION PROJECTS
2. Section 2 TW O SECTIONTWO 2.1 MINIMUM WATER QUALITY PROTECTION REQUIREMENTS FOR DEVELOPMENT CONSTRUCTION PROJECTS Unless specifically exempted, all Development Construction Projects will be required
More informationTemporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction Activities
Development Services 1775 12 th Ave. NW P.O. Box 1307 Issaquah, WA 98027 425-837-3100 issaquahwa.gov Temporary Erosion and Sediment Control (TESC) Report and Stormwater Pollution Prevention Plan For Construction
More informationCITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre
Approved by: City of Camarillo Stormwater Program Manager Date: CITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre Project Name: Project #: Project Location:
More informationBest Management Practices (BMPs) for Construction Sites & Home Remodeling Projects
Best Management Practices (BMPs) for Construction Sites & Home Remodeling Projects Stormwater Program Department of Public Works City of Rancho Santa Margarita 22112 El Paseo Rancho Santa Margarita, CA
More informationAPPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER SHEET FOR SPECIAL CONDITIONS AND PERMIT NUMBERING
APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER FOR SPECIAL CONDITIONS AND PERMIT NUMBERING GENERAL NOTES: HOUSE GREEN HOUSE 1900 S. NORFOLK ST. SUITE 350 GARAGE GRADING
More informationOutline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control
Inspecting Construction Site BMPs Kristin Kerr EOA, Inc. Outline of Presentation Back to Basics Erosion and Sediment Control Good Site Non-Stormwater Run-on and Run-off Control Construction Inspection
More informationCity of Daphne Standard Operating Guidance (SOGs) For Storm Drain System Management
Standard Operating Guidance (SOGs) For Storm Drain System Management Phase II MS4 Creating a Clean Water Future. Standard Operating Guidance (SOGs) For Storm Drain System Management The City of Daphne
More informationCommon Plan SWPPP for
Stormwater Pollution Prevention Plan Template (SWPPP) (This SWPPP Template is for the Only, and does NOT address SWPPP requirements found in the CGP.) Common Plan SWPPP for Date 1. Project Information
More informationDIVISION of WATER QUALITY NDPDES PROGRAM
DIVISION of WATER QUALITY NDPDES PROGRAM THIS PAGE IS NOT PART OF ANY SWPPP CONSTRUCTION Storm Water Pollution Prevention Plan * SWPPP Template (2016-01) A SWPPP must be prepared and implemented for all
More informationRe: Erosion Control Report and Drawings Requirements Accompanying Document
Re: Erosion Control Report and Drawings Requirements Accompanying Document This document was created to help engineers and other design staff to better understand, meet and exceed the erosion control requirements
More informationES Inspection and Maintenance of MS4 Structural Controls* Document Identification Number Date: March 14, 2018
ES-301-4.08 Inspection and Maintenance of MS4 Structural Controls* Document Identification Number ES-301-4.08 Date: March 14, 2018 Document Owner: Kim Ohlson 1) Activity Description: MS4 Maintenance and
More informationSmall Site Stormwater Quality Permit Application
Small Site Stormwater Quality Permit Application PUBLIC WORKS ADMINISTRATION BUILDING (PWA) STORMWATER DIVISION 2525 WEST FIRST STREET LOVELAND, CO 80537 GENERAL INFORMATION (970) 962-2772 www.cityofloveland.org/stormwater
More informationCON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist
Con Appendix FINAL US Army Garrison, Hawaii October 2015 CON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist Storm Water Management Plan CON Appendix C U.S. Army Garrison-Hawaii
More informationDemolition Permit Application
Demolition Permit Application Location of Proposed Work or Improvement Municipality: Borough Township Site Address: Tax Parcel: City: State: Zip Code: Zoning District: Lot Size: Property Owner(s): Mailing
More informationThe Good, The Bad, and The Ugly
Overview The Good, The Bad, and The Ugly Stormwater Regulations for the Construction Industry Seminar March 20, 2012 Wendy Terlizzi Arizona Department of Transportation Office of Environmental Services
More informationDivision of Water Quality (701)
Division of Water Quality (701) 328-5210 stormwater@nd.gov March April 2018 1 Construction Permit Permit #: NDR10-0000 Reissued April 1, 2015 Expires March 31, 2020 2 Discharges Covered Stormwater Discharges
More informationRock Sock (RS) Rock Sock height.
Rock Sock (RS) SC-5 Description A rock sock is constructed of gravel that has been wrapped by wire mesh or a geotextile to form an elongated cylindrical filter. Rock socks are typically used either as
More informationSTORMWATER POLLUTION PREVENTION PLAN (SWP3)
City of Moore, Oklahoma Community Development Department 301 North Broadway Moore, Oklahoma 73160 STORMWATER POLLUTION PREVENTION PLAN (SWP3) The SWP3 is a written narrative describing the site, potential
More informationPost Construction Erosion Controls
Post Construction Erosion Controls Erosion Control Permanent Controls Native Vegetation Preservation Hydroseeding & Soil Stabilizers Soil Roughening Soil Stabilizers Geotextiles Vegetation is the Best
More informationGRADING, EROSION AND SEDIMENTATION CONTROL
SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,
More informationWater Pollution Control for Work in Sensitive Areas
Water Pollution Control for Work in Sensitive Areas 10-1. WATER POLLUTION CONTROL The Contractor is advised that failure to fully comply with the provisions of this Section, and all requirements listed
More informationWAKULLA SITE PLANNING
WAKULLA CIVIL SURVEYING SITE PLANNING TRAFFIC CONTROL PLAN WAKULLA ARRAN ROAD WIDENING & RESURFACING UTILITY CONTACT LIST NO. DATE: APPR. REVISION: DATE: CIVIL SURVEYING SITE PLANNING GENERAL NOTES WAKULLA
More informationRichland County Department of Public Works Engineering (Land Development) Division
Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or
More informationTown of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL
CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with
More informationStormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)
Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater
More informationPHASE 1 UPDATES TO DESIGN AND CONSTRUCTION STANDARDS INITIAL DRAFT FOR. Chapter 6 EROSION PREVENTION AND SEDIMENT CONTROL
PHASE 1 UPDATES TO DESIGN AND CONSTRUCTION STANDARDS INITIAL DRAFT FOR Chapter 6 EROSION PREVENTION AND SEDIMENT CONTROL Reader Notes (1/18/17 draft) CWS has drafted proposed changes to Chapter 6 to incorporate
More informationContractors, Illicit Discharges, & Best Management Practices. Chris Allen Stormwater Inspector
Contractors, Illicit Discharges, & Best Management Practices Chris Allen Stormwater Inspector What is an Illicit Discharge? Georgetown County Stormwater Ordinance defines an Illicit Discharge as: Any activity
More informationNew Administration Building
New Administration Building Stormwater Pollution Prevention Plan Hudson Valley Community College Troy, New York Prepared for: Hudson Valley Community College 80 Vandenburgh Avenue Troy, New York 12180
More informationConstruction Best Management Practices Handbook BEST MANAGEMENT PRACTICES
Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN
More informationPaving and Grinding Operations
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
More informationSTORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents. SWMP Page # or Reference Location Yes/No
STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents Site Description A description of construction activity. The proposed sequence for major activities. Estimates of the total
More informationConstruction Site Runoff Inspections and Enforcement
Construction Site Runoff Inspections and Enforcement Stormwater Program 12/01/11 Table of Contents Introduction... 1 Purpose of Document... 1 Definition of Terms... 1 Compliance and Inspections... 3 Site
More informationStorm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water
Storm Water Permitting Requirements for Construction Activities John Mathews Storm Water Program Manager Division of Surface Water Why Permit Storm Water? Impacts During Construction Not an issue until
More informationHome Remodeling Projects
Should your project require a Standard Urban Stormwater Mitigation Plan (SUSMP), please see the City of Pomona s Standard Urban Stormwater Mitigation Plan (SUSMP) Pamphlet Best Management Practices For
More informationSECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS
SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS 12.1 The subdivider shall construct and install the improvements in accordance with the County's Standards for Construction Plans and Specifications
More informationCHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS
CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS 8.1 INTRODUCTION To minimize the detrimental effects of erosion and sedimentation, Henrico County requires that those individuals responsible for
More informationBowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)
Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) SMP-11 PLANNING CONSIDERATIONS: Design Life: 1 yr Acreage
More informationGuidance Document for Storm Water Pollution Prevention Plan (SWPPP) Submittal. A2 Plat showing building lot numbers/boundaries and road layout/names:
Exhibit SW12-3 Page 1 of 10 Guidance Document for Storm Water Pollution Prevention Plan SECTION A CONSTRUCTION PLAN ELEMENTS A1 Plan Index showing locations of required items: The plan index should include
More informationNevada Department of Transportation (NDOT)
Nevada Department of Transportation (NDOT) Stormwater Pollution Prevention Plan (SWPPP) Template for Construction Activities NDOT STORMWATER COMPLIANCE & ENFORCEMENT Table of Contents Page # STORM WATER
More informationCCI107 ONLINE PROGRAM. Stormwater Management. Stormwater Management for Construction Activities Alberta. Market Type: Construction Level: 1
ONLINE PROGRAM Market Type: Construction Level: 1 Stormwater Management 1-877-25-SWPPP 1-877-25-9777 info@stormwaterone.com + Choose Alberta Enroll Now at StormwaterONE.com StormwaterONE.com 290 Pratt
More information2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1
2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 There are three ways to accomplish urban soil erosion and sedimentation control: Allow erosion to take place and then control sediment
More informationCity of Maryville Grading & Construction Site Pollution Management Policies & Procedures Manual RESIDENTIAL COMMERCIAL BUSINESS INDUSTRIAL
City of Maryville Grading & Construction Site Pollution Management Policies & Procedures Manual RESIDENTIAL COMMERCIAL BUSINESS INDUSTRIAL Welcome to the City of Maryville, a progressive city located in
More informationOctober 2016 CDRPC Workshop
The New Blue Book NYS Standards and Specifications for Erosion and Sediment Control Dated July 2016 October 2016 CDRPC Workshop Blue Book Update Overview Reorganization of standard to reflect recommended
More informationBlue Book Update Overview
The New Blue Book NYS Standards and Specifications for Erosion and Sediment Control Dated July 2016 October 2016 CDRPC Workshop Blue Book Update Overview Reorganization of standard to reflect recommended
More informationCITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL () September 2017 Page Chapter 1 Acronyms and Definitions 1.01 Purpose 1 1.02 Acronyms 1 1.03 Definitions 3 Chapter 2 Introduction 2.01 Purpose 1 2.02 Applicability
More informationErosion and Sediment Pollution Control Guidelines for Residential Lots with soil disturbance of less than 1 acre (see exceptions)
Adams Co. Conservation District 670 Old Harrisburg Road, Suite 201 Gettysburg, PA 17325 Telephone: 334-0636 Fax: 337-0730 www.adamscounty.us Erosion and Sediment Pollution Control Guidelines for Residential
More informationBMP FACT SHEET DF-1 HOA Annual Self-Certification Report
PURPOSE: Public and privately owned and maintained stormwater conveyance systems collect and transport urban runoff and storm water that may contain certain pollutants. These pollutants may accumulate
More informationCity of Centerton Grading & Erosion Control Application Package
City of Centerton Grading & Erosion Control Application Package Grading & Erosion Control Application........ 3 Residential Checklist...... 5 Commercial Checklist........ 6 Utility Checklist......... 8
More informationAppendix A: SWPPP Template Instructions
Appendix A: SWPPP Template Instructions To help you develop the narrative section of your construction site SWPPP, EPA has created this electronic SWPPP template. The template is designed to help guide
More informationSuggested Best Management Practices (BMPs)
Suggested Best Management Practices (BMPs) Preface The purpose of this Best Management Practices (BMP) Manual is to help educate and instruct on ways to reduce stormwater pollution and help prevent it
More informationNDDOT Erosion & Sediment Control Construction Course
NDDOT Erosion & Sediment Control Construction Course Module 4: Stormwater Pollution Prevention Plan (SWPPP) 1 What s covered in this module? 1. What is a SWPPP 2. Important initial considerations that
More informationUMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist
UMD Storm Water Program Construction Requirements Greg Archer, MBA Environmental Compliance Specialist Phase 2 Regulatory Overview Dec. 1999 EPA issues Phase 2 Federal Register Municipalities (MS4) from
More information