PRE FEASIBILITY REPORT. M/s. Riddhi Dyechem Industries

Size: px
Start display at page:

Download "PRE FEASIBILITY REPORT. M/s. Riddhi Dyechem Industries"

Transcription

1 PRE FEASIBILITY REPORT FOR OBTAINING ENVIRONMENTAL CLEARANCE For the Proposed Dye Manufacturing Unit of M/s. Riddhi Dyechem Industries Block No.: 680/p, 681/p, 682/p Village: Pariej, Taluka: Matar, District: Kheda, Gujarat Contact No.: Prepared By: T. R. ASSOCIATES C 605/A, Ganesh Meridian, Opp. Kargil Petrol Pump, S. G. Highway, Ahmedabad Contact No.: adm.trassociates@gmail.com September 2017

2 1. Introduction M/s. Riddhi Dyechem Industries is a partnership firm proposing to set up a Dye Manufacturing unit at Block No.: 680/p, 681/p, 682/p, (plot area : m 2 ) Village: Pariej, Taluka: Matar, District: Kheda, Gujarat Project Proponent and their back ground Company is promoted by its partner. Detail of partners is as given below. Sr. Name of the Partner No. 1 Bharatbhai Vasudevbhai Thakkar 2 Jayeshkumar Kaniyalal Thakkar Background Logistic Business Business 3. Brief description of nature of the project: M/s. Riddhi Dyechem Industries is proposing to manufacture dyes at Block No.: 680/p, 681/p, 682/p, Village: Pariaj, Taluka: Matar, District: Kheda, Gujarat Proposed products will be used for sale purpose. Dyes manufacturing falls under Category 5(f) Synthetic Organic Chemical as stated in Environment Impact Assessment Notification Published on 14 th September, Further, the location of the proposed project is outside the notified industrial estate. Hence, the project proponent has to obtain the EC from the Ministry of Environment, Forest & Climate Change, New Delhi. M/s. T. R. Associates has been appointed to carry out EIA/EMP studies for obtaining Environmental Clearance. The total plot area of company is 11,068m 2 out of which 3654 m 2 (33 % of total land) area will be developed as greenbelt area. The estimated cost of the proposed project is 6.0 Crores. Total budget allocation towards Environmental Management Facilities will be approx. Rs. 80 Lakhs. Total 30 persons will be employed including skilled persons, unskilled persons and office staff. Need for the project and its importance to the country and or region: Reactive dyes are most commonly used in dyeing of cellulose like Cotton or Flax, and also Wool is dyeable with reactive dyes. India accounts for approximately 16 per cent of the world production of dyestuff and dye intermediates, particularly for reactive acid and direct dyes.

3 The proposed product, Reactive dyes are mainly used in dyeing operation of natural fiber. These dyes have a worldwide acceptance to the dyeing technologies for dyeing cotton. Demand Supply Gap: In 2010, India produced ~200,000 tonnes of dyes. Of this, 50% were reactive dyes due to the availability of important raw materials like Vinyl Sulphone, etc. Nearly 70% of the dyestuff was supplied to the textile industry while leather and paper industries accounted for the remaining. The overall production capacity of dyestuffs is 200,000 tonnes per annum. With the ever increasing standards of quality and reliability, Indian dyestuffs industry meets more than 95% of the domestic requirement, out of which textile industry consumes nearly 60% and the remaining is shared by paper, leather & other consumer industries. As far as pigments are concerned, the market size is 115,000 tonnes. The main consumer industries are printing inks, paints, plastics, rubber, etc., accounting for 70% of the end use. Whereas many of the plants all over the world are very large size, there are many SME units in India, which are capable of producing quality colorants. Gujarat and Maharashtra account for nearly 95% of the colorant production in the country. Imports v/s Indigenous production: Indian market is open and big that is why every kind of import is booming. During the last decade, the industry was growing at an average growth of 2 3% per annum. Today, Indian dyestuffs industry comprises about 950 units (50 in large and organized sector and 900 units under Small & Medium Enterprises (SME) Sector). These units are mainly present in the western states of Gujarat and Maharashtra, with Gujarat accounting for almost 80% of capacity. The per capita consumption of dyes in India is 50 gms as compared to 400 gms in Europe, 300 gms in Japan which shows that there is tremendous potential for the Indian market. Export Possibility: Reactive dyes are used for dyeing of natural fiber. Reactive dyes are quite expensive for export. So we have only local market for sale. Exports of dyes is progressively showing an upward trend since the last two years. Major exports of dyes are to developed countries like Germany, U.K., U.S.A., Switzerland, Spain, Turkey, Singapore and Japan. Exports of Dyes to Latin American and African Countries have also started picking up. These are new emerging markets for the Indian exporters. The industry has prepared a future strategic action plan.. The industry needs to create a

4 set up to monitor very regularly the growth in exports and take necessary corrective action along the route to achieve the target. Employment Generation (Direct and Indirect) due to the project: This project will provide direct employment to 30 persons whereas it will provide employment to many others indirectly. 4. Project Description (i) Type of project including interlinked and interdependent projects: Reactive dyes are used in dyeing of Cotton, rayon, flax,, and otherr cellulosicc fibers. So Textile industries will be interdependent on Dyes industries. (ii) Location Proposed project is to be locatedd at Block No.:680/ /p,681/p,682/p, Village: Pariej, Taluka: Matar, District: Kheda, Gujarat Geographic Coordinates Latitude: 22 31ʹ34.97ʺN Longitude: 72 37ʹ16.87ʺE Google image showing proposed project site is given below;

5 Salient features in the surroundings area of the proposed site within 10 km radius are as follows: Sr. No. Important Features Description 1 Location Block No.: 680,681,682, Village: Pariej, Taluka: Matar, District: Kheda, Gujarat GPS Coordinates Latitude: 22 31ʹ34.97ʺN Longitude: 72 37ʹ16.87ʺE 3 Temperature Range Means Maximum temperatures ranges between 28.4 C during January to about 41.8 C during May Mean minimum temperatures vary between 11.7 C during January and 27 C during June 4 Mean Sea Level 16 m 5 Annual Rain Fall mm (average) (CGWA : Kheda district) 6 Nearest Railway Station Tarapur Railway Station 8.3 km in E direction 7 Nearest Airport Ahmedabad Airport 60 km in N direction 8 Nearest Town Tarapur 4.5 km in SE direction 9 Nearest Village Periej 0.5 km in ENE direction 10 Nearest National Highway Nearest State Highway SH 16 is at 0.5 Km in E direction 11 Nearest River/Water body Sabarmati River 18 km in W direction 12 National Parks / Sanctuary None within 10 km radius. (iii) Alternative Sites considered No other sites were selected. (iv) Size or magnitude of operation List of Proposed Products Sr. Production Capacity Name of Product No. (MT / Month) 1 REACTIVE BLACK B REACTIVE YELLOW REACTIVE MEGENTA HB REACTIVE BLUE REACTIVE BLUE REACTIVE RED MEUBL 50 7 REACTIVE RED B5 50 Total 600

6 (v) Project description with process details Details of manufacturing process are given in Annexure 4 of Form 1. (vi) Raw material required along with estimated quantity Details of raw material consumption is given in Annexure 3 of Form 1. (vii) Resource optimization/ recycling and reuse envisaged in the project, if any, should be briefly outlined. Latest Process technology will be adopted as available in market with optimum resources requirement with highest yield and less waste and pollution generation. Treated industrial effluent will be reused in cooling and other possible activities. In addition to this, all the feasible cleaner production technologies will be adopted. (viii) Availability of water its source, Energy/ power requirement and source should be given. Energy/power requirement will be 150 kva which will be procured through Madhya Gujarat Vij Company Limited. The total water requirement will be 100 kl/day which will be fulfilled by own Borewell. (ix) Quantity of wastes to be generated (liquid and solid) and scheme for their Management/disposal Hazardous Waste Generation and Disposal Details of hazardous waste generation and its disposal are given in Annexure 5 of Form 1. Wastewater Generation and Disposal Facility Details of domestic as well as industrial wastewater generation and its disposal are given in Annexure 7 of Form 1.

7 (x) Schematic representations of thee feasibility drawingg which give information of EIA purpose 1. Site Analysis (i) Connectivity Nearest railway station Nearest national highway Nearest airport Sojitra/Matar NH 8 Ahmedabad 10 km /8.3 Kms 42 km 60 km (ii) Land Form, Land use and Land ownership. Proposed project site has already beenn procured by proponent andd it is an which is presently not being used for any purposes. open areaa

8 (iii) Existing Land Use Pattern

9 (iv) Topography Map Project site

10 (v) Existing Infrastructure (1) Nearest railway station: Tarapur railway station is 8.3km away from the project site (2) Nearest highway: National Highway 8 is 42 km away from the project site. (3) Nearest airport: Ahmedabad Airport is 60 km from the project site. (4) Power: 375 kva from Madhya Gujarat Vij Company Limited. (5) Water: Source of the water will be a borewell. (6) Basic amenities: Good road connectivity with state and national highway. (7) Post Office: Tarapur which is 4.5 km away from the project site (vi) Soil classification of Kheda District The soils of the district can be classified into the following Cropping main types: goradu (gravelly),black,sandy and Pattern rocky type. The principal crops grown in Kheda are the ordinary millets and pulses, rice, wheat, tobacco and a little indigo. Bajri is the principal crop and the staple grain food. Tobacco is the most valuable crop produced in the district. It is grown mostly in the charotar tract. Castor seed and sesame are the only oilseeds grown in the district. (vii) Climate data from secondary source General climate of the district is sub tropical and is characterised by three well defined seasons, i.e. summer from April to June, monsoon from July to September, and winter from October to March. Temperature Means Maximum temperatures ranges between 28.4 C during January to about 41.8 C during May and the mean minimum temperatures vary between 11.7 C during January and 27 C during June. Humidity The relative humidity in Anand as per IMD varies between 32% during March and 79% during August. (source : CGWA) Wind The wind velocity in the district varies from about 74km/d during November and 174 km/d during June. (source : CGWA)

11 Rainfall More than 90% of the rainfall occurs during the monsoon. Rainfall during the winter and summer months is negligible. The average annual rainfall(1994 to 2010) of the district is mm. (viii) Social Infrastructure available. Industrialisation/Entrepreneurship: During the decade Cement& Gypsum sector has shown maximum investments followed by Paper and its products industry to the tune of Rs. 1,372 Crore nearly 59 % of the total investments and has created next highest employment of 2,974 jobs and followed by electrical equipment sector has also create 1,748 jobs in the district. Highest employment was generated by the Textile sector with 6,002 jobs during and an investment of Rs. 186 Crore. Cement & Gypsum sector has emerged as a new sector attracting highest investment of Rs. 208 Crore contributing 47 % of the total investments in the district during Food processing industries attracted next highest investment of Rs. 86 Crore with creating as many as 301 jobs. Plastic and its Products grew tremendously attracting investment of rs. 44 Crore with nearly 50 % increase in total number of units and generating employment of 528 jobs. The nearest airport is located in Vadodara only 38 km away from the district Headquarter Nadiad. It connects the district with important cities such as Ahmedabad, Delhi, Mumbai and Pune. The nearest ports are Hajira and Dahej. Marketing Potential: The proposal for setting up an integrated Textile Park in Kheda is expected to fuel the industrial and economic growth of the district with increase in employment opportunities and investments in the textile sector. Kheda has some of the best mineral based industries which offer scope of further investments in the Mining sector.there is good infrastructure in the district for the sale of industrial goods and services manufactured and produced. 2. Planning Brief (i) Planning Concept (type of industries, facilities transportation etc) Town and Country Planning/Development authority Classification.

12 Proposed project site is located near to State Highway 16 and well connected to the internal roads and highways. The site is well connected to Kheda, Matar and Tarapur, where all the infrastructural and transportation facilities are available. In 2001 census, Kheda had a population of 2,024,216 of which males were 1,052,823 and remaining 971,393 were females. Kheda District population constituted 3.81 percent of total Maharashtra population. In 2001 census, this figure for Kheda District was at 3.99 percent of Maharashtra population. There was change of percent in the population compared to population as per In the previous census of India 2001, Kheda District recorded increase of percent to its population compared to (ii) Population Description Population No. Total :2,299,885 Person Male : 1,185,727 Person Female: 1,114,158 Person Population density Village Population Urbanised Population 582 persons per sq. km. Total: 34,694,609 Person Total: 25, 74,5083 Person Population increase rate % Male Female ratio 1000 : 919 Scheduled Caste population Scheduled Tribe population persons 8,917,174 persons (iii) Land use planning (breakup along with green belt etc). Sr. No. Particular Area (m 2 ) 1 Built Up Area Green belt area Open/ Road area 5458 Total 11068

13 (iv) Assessment of Infrastructure Demand (Physical & Social). Surrounded villages in 10 km area from the project site are having all the necessary physical and social infrastructure facilities due to agricultural activities, animal husbandry and industrial development within the area as well the nearby town. (v) Amenities/Facilities. All the basic amenities/facilities such as power connection & power back up, drinking water, internal roads, water & wastewater treatment plant etc. will be provided. 3. Proposed Infrastructure a. Industrial Area Industry has provided 1956 m 2 built up area for industrial process/manufacturing activity which provides all needed facility including proper ventilation, safe handling system, etc. b. Residential Area Industry will provide labor quarter for their labors and provide all basic facilities to them. c. Green Belt. 3,654 m 2 area will be proposed for greenbelt development. In addition to this, project proponent will participate in greenbelt development programs in nearby areas under their CSR. d. Social Infrastructure The proponent will provide social infrastructure facilities within 10 km radius of the proposed project. Education Facilities: Many Facilities for village schools like game kits, drawing kits, table chairs; school construction (classroom/toilet/school boundary), ceiling fans/ coolers or books for school library are proposed. Health Facilities: Assistance to existing health facilities in nearest Hospital, for improvement in health facilities or services.

14 e. Connectivity (Traffic and Transportation Road / Rail / Metro / Water ways Proposed project site is located adjacent to State Highway 0.5 Kms and well connected to the internal roads and highways. The site is well connected to Tarapur Town and Kheda District. f. Drinking Water Management In proposed project, out of 100 kl/day water approx. 2 kl/day water will be consumed for domestic purpose g. Sewerage System. Domestic wastewater 1.8 kl/day will be disposed off through Septic Tank/ Soak Pit System. h. Industrial Wastewater Management. Industrial wastewater will be generated from process, boiler blow down, washing & RO 1. Wastewater (washing and process) will be collected collection cum neutralization tank. Then wastewater will be given Primary secondary and teriotary treatment. High TDS water from RO reject will be sent to Spray Drier. ETP sludge along with evaporation residue from evaporator will be will be disposed of at TSDF site. Thus, unit will maintain Zero Effluent Discharge. i. Solid/Hazardous Waste Management ETP waste residue, discarded bags/barrels, used oil & edge cutting waste are the main solid hazardous waste that will be generated from the proposed unit. ETP sludge will be collected, stored into solid waste storage area and disposed to authorized TSDF site. Discarded bags and containers will be sold to approve vendor. Edge cutting waste will be disposed off to common incineration facility. j. Power Requirement & Supply / source Power requirement for the proposed project will be approx. 150 kva which will be obtained from MGVCL. 4. Rehabilitation and Resettlement (R & R) Plan Not applicable.

15 5. Project Schedule & Cost Estimates (i) Likely date of start of construction and likely date of completion (Time schedule for the project to be given) Construction work is not yet started. Construction work for laminated sheets manufacturing unit will be started from January 2017 where as construction work related to Resin manufacturing plant will be only started after obtaining EC. (ii) Estimated project cost along with analysis in terms of economic viability of the project. Total cost of the entire project is approx. 6.0 Crore. (iii) Plant Layout

16

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANIC DYES (5 f B IND II) By SHREEJI BAPA DYE CHEM PLOT NO 1319 & 1320, PHASE-III, GIDC, VATVA, AHEMADABAD-382445, GUJARAT,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT for PROPOSED PROJECT FOR DYES, PIGMENTS AND DYE INTERMEDIATES MANUFACTURING PLANT IN GIDC, DAHEJ-II Of M/s. SHREEJI INDUSTRIES Plot No. D2/CH/24, Dahej-II, GIDC Industrial Estate,

More information

Pre-Feasibility Report For

Pre-Feasibility Report For Pre-Feasibility Report For Proposed New Project for manufacturing of Intermediates of Agro Chemicals & Synthetic Organic Chemicals. By M/s. MANBRO POLYMERS LIMITED, Plot No. D-2/CH-275, INDUSTRIAL ESTATE,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For PROPOSED EXPANSION OF BAKELITE POWDER MANUFACTURING UNIT of M/S. HINDUSTAN BAKELITE COMPANY PLOT NO. J-3436, GIDC ESTATE, ANKLESHWAR, DISTRICT: BHARUCH-393002, GUJARAT 0 CONTENTS

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 0.0 EXECUTIVE SUMMARY Shri Ashok Patel Partner of M/s. Patel Polymers is planning to manufacture organic chemical Different Types of Resins, for proposed expansion project at Plot

More information

EXISTING PROJECT FOR ORDINARY SAND MINING

EXISTING PROJECT FOR ORDINARY SAND MINING (C) PROJECT REPORT OF EXISTING PROJECT FOR ORDINARY SAND MINING OF JASHUBEN CHHAGANBHAI OAD AT VILLAGE:-TIMBA, TALUKA:- KAMREJ, DIST.:- SURAT 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY M/s Arti Chemical Industries is a project located at Plot No. E-22, Vilayat G.I.D.C. Tal: Vagra area of Bharuch district in Gujarat. M/s Arti Chemical Industries

More information

PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT

PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT PRE - FEASIBILITY REPORT For PROPOSED BULK DRUG & BULK DRUG INTERMEDIATES MANUFACTURING UNIT Of M/s. SHREE RAM INDUSTRIES PLOT NO.5117, GIDC-ANKLESHWAR, PIN-393002 TAL: ANKLESHWAR, DIST: BHARUCH, GUJARAT

More information

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF (B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF Makwana Dineshbhai Khimjibhai AT VILLAGE:- Tithava, TALUKA:- Wankaner, DIST.:- Morbi 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXCUTIVE SUMMARY

More information

Pre-Feasibility Report

Pre-Feasibility Report Pre-Feasibility Report 1. Executive Summary Residential, Commercial, Retail and Hotel projects and an IT/ITES. The Project has already obtained an Environmental Clearance from Ministry of Environment &

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT (B) PREFEASIBILITY REPORT OF EXISTING SAND MINING PROJECT OF RAJESHBHAI BHAGUBHAI PATEL AT VILLAGE:- Panchlai, TALUKA:- Pardi, DIST.:-Valdad. 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE SUMMARY

More information

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad

Proposed Project of Halcyon Labs Pvt Ltd D-2/CH : 335,336,337, GIDC-Dahej-2, DIst: Bharuch, Gujarat Ramans Enviro Services Pvt Ltd Ahmedabad 1. EXECUTIVE SUMMARY OF THE PROJECT BRIEF SUMMARY OF THE PROJECT : TYPE OF PROJECT : Proposed Project for manufacturing of pharma intermediates by Halcyon Labs Pvt.Ltd. LOCATION : Proposed Project of Halcyon

More information

M/S. Ever Shine Décor P. Ltd.

M/S. Ever Shine Décor P. Ltd. PRE FEASIBILITY REPORT OF M/S. Ever Shine Décor P. Ltd. Survey No. : 40, Village Indrad, Taluka Kadi, District Mehsana, Gujarat. Mob No.: 09898186603 Email: bhupeshgopani@gmail.com Prepared By: T. R. ASSOCIATES

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For Polyurethane Foam Manufacturing Facility Of M/s. KRISHNA MARUTI LTD. At Plot No-13, SMG JV Park, Block No- 334,335 Vill- Hansalpur, Tal - Mandal Dist.: Ahmedabad, Gujarat INDEX

More information

M/S. Dain Colour Chem

M/S. Dain Colour Chem PRE FEASIBILITY REPORT For PROPOSED EXPANSION IN EXISTING MANUFACTURING PLANT Of M/S. Dain Colour Chem Plot No.: 5, Nilkanth Estate, Village: Dhanot, Ta.: Kalol, Dist.: Gandhinagar-382729, Gujarat 1 CONTENTS

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project of MANUFACTURING OF SYNTHETIC ORGANICCHEMICALS (RESINS) (5 f B IND II) By M/s M R INDUSTRIES SURVEY NO. 58/1 & 58/3 OPPOSITE WHOLESOME FOOD PVT. LTD.,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE FOR MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS OF M/s. MAYUR COLOUR AND CHEMICALS LOCATED AT Plot No. 5148, GIDC Industrial Estate, Ankleshwar

More information

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha)

STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha) Pre Feasibility Report On STONE QUARRY Survey No. : 57/5, Village : Dhadhade, Tehsil: Vikramgad, District Thane, Maharashtra Area (2.0 Ha) Submitted to MINISTRY OF ENVIRONMENT & FOREST STATE LEVEL ENVIRONMENTAL

More information

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3" N to 20 44' 20.7"N Longitude " E to 85 35'27.5 "E

EXECUTIVE SUMMARY. Kumardeipur Sand Quarry Cum ' 13.3 N to 20 44' 20.7N Longitude  E to 85 35'27.5 E EXECUTIVE SUMMARY 1.0 INTRODUCTION Sri Mahesh Prasad Mishra proposes to mine Sand Quarry from an approved Mining Lease over an area of 14.85 Ac or 6.01 hectares (Non-Forest Land) which is located in at

More information

PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR

PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR PREFEASIBILITY REPORT OF EXISTING SILICA SAND MINING PROJECT OF MANGUBEN KANTILAL THAKKAR AT VILLAGE:- BRAHMPURI, TALUKA:- Sayla, DIST.:-Surendranagar 1 CONTENTS 1.0 INTRODUCTION 1.1 PREAMBLE 2.0 EXECUTIVE

More information

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad

Shri Hari Dyes & Chemicals Plot No.: 439/1,417, Phase No. II, GIDC Estate, Vatva , Ahmedabad Annexure Prefeasibility Report (PFR) File PRE FEASIBILITY REPORT For PROPOSED EXPANSION IN EXISTING MANUFACTURING PLANT Of Shri Hari Dyes & Chemicals Work & Regd. Office: CONTENTS Sr. No. Description 1.

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT PREFEASIBILITY REPORT For ToR Application of Expansion Project For MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS (Dyes Intermediates) Proposed By: M/s. Plot No. C/1/B-145-3 Phase-II, GIDC Estate, Naroda,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For NEW PROJECT (PIGMENT MANUFACTURING PLANT) Of M/s. SHREY INDUSTRIES Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat) CONTENTS Sr.

More information

PRE-FEASIBILITY REPORT FOR ORDINARY SAND

PRE-FEASIBILITY REPORT FOR ORDINARY SAND PRE-FEASIBILITY REPORT FOR ORDINARY SAND Proponent NISANT TRADERS At- Opp. Survey No.- 3 Panam River Area-2.50.00 Hectare Village-Ramji-ni-Nal, Taluka- Shahera Dist.- Panchmahal Mob.- +91924040782 CONTENTS

More information

PROJECT FEASIBILITY REPORT

PROJECT FEASIBILITY REPORT PROJECT FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For PROPOSED CHEMICAL MANUFACTURING UNIT From M/s. MORADIA BROTHERS CHEM PVT LTD LOCATED AT: Block No.: 45, JalBhumi Industrial Estate,

More information

PRE-FEASIBILITY REPORT OF SAND QUARRY

PRE-FEASIBILITY REPORT OF SAND QUARRY PRE-FEASIBILITY REPORT OF SAND QUARRY Survey No Village Taluka District Lease area : 1 Paiki : Marigana : Anjar, : Kutch, Gujarat, : 2.00 Ha. Submitted to MINISTRY OF ENVIRONMENT & FORESTS STATE LEVEL

More information

PRE FEASIBILITY REPORT. M/s. Sayaji Laminates Pvt. Ltd. Survey No. : 213,Village-Bahutha, Ta. :Savli, Dist. : Baroda, Gujrat

PRE FEASIBILITY REPORT. M/s. Sayaji Laminates Pvt. Ltd. Survey No. : 213,Village-Bahutha, Ta. :Savli, Dist. : Baroda, Gujrat PR FASIBILITY RPORT OF M/s. Sayaji Laminates Pvt. Ltd. Survey No. : 213,Village-Bahutha, Ta. :Savli, Dist. : Baroda, Gujrat-391770 mail: sayajilaminates@gmail.com Prepared By: T. R. Associates C-605/A,

More information

M/s. Lakeland Chemicals (India) Ltd.

M/s. Lakeland Chemicals (India) Ltd. FOR THE PROPOSED EXPANSION PROJECT FOR MANUFACTURING OF SPECALITY CHEMICALS Category: 5(f) A OF Located at: Plot no 63,6A,6B, Rasayani Road, Vill. Madap, Tq. Khalapur, Dist. Raigad.( Maharashtra) 1 Project

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For EXPANSION IN EXISTING MANUFACTURING PLANT Of M/s. SHIVA DYE STUFF PVT. LTD Plot no. A2-11/6104,G.I.D.C. Industrial Estate, Ankleshwar-393002, Gujarat. 1 CONTENTS Sr. No. Description

More information

PRE FEASIBILITY REPORT FOR. Silica Sand Beneficiation Plant

PRE FEASIBILITY REPORT FOR. Silica Sand Beneficiation Plant PRE FEASIBILITY REPORT FOR Silica Sand Beneficiation Plant BY Shree Silicaam Minerals LLP VILLAGE : CHOKI TALUKA : JAGADIA DIST : BHARUCH GUJARAT (INDIA) PRE-FEASIBILITY REPORT: SILICA SAND BENIFICIATION

More information

PRE FEASIBILTY REPORT

PRE FEASIBILTY REPORT PRE FEASIBILTY REPORT FOR ENVIRONMENT CLEARANCE OF PROPOSED NEW PROJECT S. O. CHEMICALS (5 f Category) Proposed By: COREL PHARMA CHEM PVT. LTD. SURVEY NO. 473 & 481, BORISANA, KADI THOL ROAD, KADI, DIST

More information

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat. Pre-Feasibility Study Report For Proposed Fly Ash Co-processing clinker grinding cement Unit of 40,000 MT/month Production capacity within our Existing Premises for M/s. SAL STEEL LTD Survey no.245/p,

More information

PRE-FEASIBILITY REPORT. for

PRE-FEASIBILITY REPORT. for PRE-FEASIBILITY REPORT for PROPOSED COMMON EFFLUENT TREATMETN PLANT (CETP) of M/s. VIKASHTEX ENVIROTECH CETP PVT. LTD. Block No. 523, Village: Hathoda, Taluka: Mangrol, Dist: Surat - 394 405 (Guj.) Prepared

More information

MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.

MODIFIED QUARRYING PLAN FOR SHINGATALOOR SAND MINING BLOCK-2 EXTENT Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY. MODIFIED QUARRYING PLAN FOR "SHINGATALOOR SAND MINING BLOCK-2" EXTENT -12.00 Acres (4.86 Ha) IN TUNGABHADRA RIVER BED ADJ ACENT TO SY.NO - 129 & 131OF SHINGATALOOR - VILLAGE MUNDARGI - TALUK GADAG - DISTRICT

More information

1.0 EXECUTIVE SUMMARY

1.0 EXECUTIVE SUMMARY 1.0 EXECUTIVE SUMMARY M/s Merino Industries Limited has proposed for manufacturing Phenol Formaldehyde Resin, Melamine Formaldehyde Resin at Plot No D2 CH 36, Dahej Phase II, Dist. Bharuch, Gujarat. The

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT Page1 PRE FEASIBILITY REPORT KALDA FLAG STONE QUARRY AREA OF -1.55 HACTARE STRICTLY AS PER MOEF GUIDELINE DATE 30/12/2006 IN TERMS OF PROVISIONS OF EIA NOTIFICATION 2006 VILLAGE KALDA TEHSIL PAWAI DISTRICT

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT For PROPOSED EXPANSION OF CARBON BLACK (10950 TPM TO 15750 TPM ) AND CO-GENERATION POWER PLANT (22 MW TO 32 MW) IN EXISTING PREMISES of M/s. PHILLIPS CARBON BLACK LTD. Survey No.

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT M/S. VANAS INFRA PROJECTS PVT. LTD SURVEY NO. 598, CHINTALAPALLY VILLAGE, KOLLAPUR MANDAL, NAGARKURNOOL DISTRICT, TELANGANA PRE-FEASIBILITY REPORT SUBMITTED BY M/s. Sri Soma Jitendra H. No. 7-1-397/150,

More information

Pre- Feasibility RepoRt

Pre- Feasibility RepoRt Pre- Feasibility RepoRt AREA- 59.28 ACRE (24.0 HA) FOR KEN RIVER SAND/MORRUM MINING AT BLOCK NO-09 KHAND NO-03 GATA NO-337 VILLAGE- KANWARA TEHSIL-BANDA, DISTRICT- BANDA(U.P) SHRI RAVINDRA NATH SINGH JULY

More information

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others

Table 1.1: The Salient Features of the Project Proposed Quartz Mine Of M/s. Viswanadha Stone Crusher & 16 others 1. EXECUTIVE SUMMARY 1.1 Introduction The Road Metal Quarries was granted in Guntur District, Andhra Pradesh has been allotted to M/s. Viswanadha Stone Crusher & 16 others by Assistant Director of Mines

More information

ANNEXURES. 1 Google image showing proposed project site. 3 Manufacturing process details. 4 Details of hazardous waste management

ANNEXURES. 1 Google image showing proposed project site. 3 Manufacturing process details. 4 Details of hazardous waste management ANNEXURES Annexure No. Description 1 Google image showing proposed project site 2 Plant Lay-Out 3 Manufacturing process details 4 Details of hazardous waste management 5 Details of Effluent Treatment Plant

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT 0.0 EXECUTIVE SUMMARY M/s Colorant Limited (Unit II) is a proposed expansion project located at Plot No. 3225, Phase IV, GIDC Vatva, Ahmedabad in Gujarat State. M/s Colorant Limited

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT Of Shri Upendra Suryawanshi At Khasra No. 413/1, 413/3 Vill.-Ambada, Tehsil-Amla, District-Betul (M.P.) Production Capacity: Max 6,320 Cu.mt/year Area 1.00Hectare Proponent Name

More information

Environment Consultant:

Environment Consultant: MODERNIZATION CUM EXPANSION OF INDUCTION FURNACE PRODUCTION(2,05,000 TPA TO 6,00,000 TPA) AND ROLLING MILL PRODUCTION (3, 69,000 TPA TO 6,00,000 TPA) at Sy. No. 158 (part) 159 (part), 166 170, village

More information

PRE-FEASIBILITY REPORT. Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location

PRE-FEASIBILITY REPORT. Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location 1. SUMMARY PRE-FEASIBILITY REPORT Project Stone Quarry Name of Company / Mine Owner Shri Jayant Kumar Choudhary Location Village Taluka District State Rupapali Basna Mahasamund Chhattisgarh 1 Mining Lease

More information

LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH

LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH LG POLYMERS INDIA PVT. LTD. SY. NO.S 29 TO 45, 83/1 AND 83/3, RR VENKATAPURAM VILLAGE, PENDURTI MANDAL, VISAKHAPATNAM DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT LG Polymers India Pvt. Ltd. Sy. No.s

More information

Limestone Mining Project (Area: ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar (Gujarat) Pre-feasibility Report

Limestone Mining Project (Area: ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar (Gujarat) Pre-feasibility Report Limestone Mining Project (Area: 16.18 ha) at Near Village: Bhod, Taluka Ranavav, District Porbandar PRE - FEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENT CLEARANCE For MINING ACTIVITY CATEGORY B2 UNDER

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED SY. NO. 29, TUPAKULAGUDEM VILLAGE, TALLAPUDI MANDAL, WEST GODAVARI DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT VENSUB LABORATORIES PRIVATE LIMITED Duplex No. 12,

More information

M/s. NGL Fine-Chem Limited Plot no. S 18/3, Tarapur MIDC, Boisar, District Palghar, Maharashtra. PIN:

M/s. NGL Fine-Chem Limited Plot no. S 18/3, Tarapur MIDC, Boisar, District Palghar, Maharashtra. PIN: Pre-feasibility Study Report For M/s. NGL Fine-Chem Limited Plot no. S 18/3, Tarapur MIDC, Boisar, District Palghar, Maharashtra. PIN: 401506 Prepared By: M/s SADEKAR ENVIRO ENGINEERS PVT. LTD. Accredited

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT 1. Introduction 1. Identification of project and project proponent The Pahanbarri Sand Quarry area is located in the Tawa River at Village- Pahanbarri, Tehsil- Itarsi & District-

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For ToR of Proposed Project Of MANUFACTURING OF SYNTHETIC ORGANIC CHEMICALS of 850 MT/Month By PASHUPATI INDUSTRIES 169/1/A2, Phase 1, Opposite Telephone Exchange, GIDC Naroda, Ahmedabad-382330

More information

PRE-FEASIBILITY REPORT. 1. SUMMARY Kudeli Brick Earth Quarry Name of Company / Mine Owner Smt. Premawati Location 744, 760/1, 760/4, 750/1, 750/2

PRE-FEASIBILITY REPORT. 1. SUMMARY Kudeli Brick Earth Quarry Name of Company / Mine Owner Smt. Premawati Location 744, 760/1, 760/4, 750/1, 750/2 PRE-FEASIBILITY REPORT 1. SUMMARY Project Kudeli Brick Earth Quarry Name of Company / Mine Owner Smt. Premawati Location 744, 760/1, 760/4, 750/1, 750/2 Village Kudeli Taluka Baikunthpur District Koriya

More information

PRE-FEASIBILITY REPORT

PRE-FEASIBILITY REPORT PRE-FEASIBILITY REPORT For Excavation of Brick Earth (Total Mining Area 1.112Ha.) (For Manufacturing of Bricks) Submitted By M/s New Kaptan Brick Field Shri Krishna Kr. Singh S/o Shri Brahma DevSingh Pure

More information

Pre-Feasibility Study Report

Pre-Feasibility Study Report Pre-Feasibility Study Report Of to be set-up at Survey No.: 1905/1, Village: Gangad, Taluka: Bavla District: Ahmedabad - 382 240, Gujarat INDEX S.N. 1. Executive Summary 2. Introduction of Project (ii)

More information

PRE- FEASIBILITY REPORT FOR PROPOSED ORDINARY EARTH EXCAVATION PROJECT (94.59 ARES) of Shri Saji Sebastian, Madeckal House, Kizhakambalam P.

PRE- FEASIBILITY REPORT FOR PROPOSED ORDINARY EARTH EXCAVATION PROJECT (94.59 ARES) of Shri Saji Sebastian, Madeckal House, Kizhakambalam P. PRE- FEASIBILITY REPORT FOR PROPOSED ORDINARY EARTH EXCAVATION PROJECT (94.59 ARES) of Shri Saji Sebastian, Madeckal House, Kizhakambalam P.O, Ernakulam (Dist.) Survey No. 129/1-4,129/2-1, Arakuzha Village,

More information

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village:

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village: PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY In our Masonry Stone Mining Lease (M.L. No. 15/96, Area: 1.0 ha), Production capacity of masonry stone: 142920 TPA and existing Stone Crusher Unit named M/s.

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT BANDOL CRUSHER STONE QUARRY OF SHRI TULSIRAM SAHU AT Khasra No. 15/2,23/2 Village Bandol Tehsil District State Madhya Pradesh Production Capacity 45030 M3/Year Area 3.150 Hectare

More information

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH

SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH SRI K. RAVI SHANKAR SURVEY NO.100, ODULAPALLI VILLAGE, TALPULA MANDAL, ANANTHAPURAMU DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT (OPENCAST QUARTZ MINE 40.313 ha) SUBMITTED BY Sri Door No. 39/49/39,

More information

PREFEASIBILITY REPORT FOR BRICK EARTH MINE

PREFEASIBILITY REPORT FOR BRICK EARTH MINE Page 1 PREFEASIBILITY REPORT FOR BRICK EARTH MINE Developed By- Village-Chandauhan, Tehsil-Phulpur, District-Allhabaad, Uttar Pradesh. RAI ENVIROMENTAL SERVICES PVT. LTD. Website: www.raienviro.com Email

More information

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Jaypee Group is a leading Business House of the country with its presence in Core industries and Service Sectors like Cement, Infrastructure development,

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT ASTRIX LABORATORIES LIMITED SY. NO. 10 & 42, IDA, GADDAPOTHARAM VILLAGE, JINNARAM MANDAL, MEDAK DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT Sy. No. 10 & 42, IDA, Gaddapotharam (V), Jinnaram (M), Medak

More information

PRE-FEASIBILTY REPORT

PRE-FEASIBILTY REPORT Aug 2018 PRE-FEASIBILTY REPORT OF M/S. J.M.R.MINES (MINING OF FELDSPAR, QUARTZ & MICA MINE) Lease Area : 5.78 Hectares(14.29 Acres) Sy.No.941,942,943 &947 Giddalur (V), Sydapuram (M), SPSR Nellore District

More information

INSPIRE INDUSTRIES PVT. LTD.

INSPIRE INDUSTRIES PVT. LTD. For Proposed 0.999 MTPA Coal Washery At Village: Bhelai, Tehsil: Baloda, District: Janjgir-Champa, Chhattisgarh Envirotech East (P) Limited An ISO 9001:2008, 14001:2004 & OHSAS:18001:2007 Company Laboratory

More information

PRE-FEASIBILITY REPORT PROPOSED PROJECT FOR MANUFACTURING OF DYES INTERMEDIATES. OF M/s. UMIYA CHEM INTERMEDIATES

PRE-FEASIBILITY REPORT PROPOSED PROJECT FOR MANUFACTURING OF DYES INTERMEDIATES. OF M/s. UMIYA CHEM INTERMEDIATES PRE-FEASIBILITY REPORT ON PROPOSED PROJECT FOR MANUFACTURING OF DYES INTERMEDIATES OF M/s. UMIYA CHEM INTERMEDIATES AT PLOT NO: 4705/1/1, GIDC ESTATE,ANKLESHWAR, DIST:BHARUCH STATE:-GUJARAT 1 1.0 EXECUTIVE

More information

Plot No. 2-D1, Obadenahalli, 3 rd Phase KIADB Industrial Area, Doddaballapur taluk, Bangalore Rural District , Karnataka State.

Plot No. 2-D1, Obadenahalli, 3 rd Phase KIADB Industrial Area, Doddaballapur taluk, Bangalore Rural District , Karnataka State. ON Plot No. 2-D1, Obadenahalli, 3 rd Phase KIADB Industrial Area, Doddaballapur taluk, Bangalore Rural District 561 205, Karnataka State. Table of Contents 1. EXECUTIVE SUMMARY 2. INTRODUCTION OF THE PROJECT/

More information

ANNEXURE A DETAILS OF PRODUCTS

ANNEXURE A DETAILS OF PRODUCTS Annexures to Form 1 & Pre Feasibility Report Proposed Project for manufacturing of Dyes Intermediates of M/s Jay Dyechem, Narol-Vatva Road,Ta : City, District : Ahmedabad, Gujarat. ANNEXURE A DETAILS OF

More information

PRE FEASIBILTY REPORT MANUFACTURING OF ORGANIC PIGMENT M/S PRINCE CHEMICALS

PRE FEASIBILTY REPORT MANUFACTURING OF ORGANIC PIGMENT M/S PRINCE CHEMICALS PRE FEASIBILTY REPORT ON PROPOSED PROJECT FOR MANUFACTURING OF ORGANIC PIGMENT OF M/S PRINCE CHEMICALS AT PLOT NO: 9111/3,9111/2/1 GIDC ESTATE, ANKLESHWAR, DIST: BHARUCH, STATE: GUJARAT 1 Index Sr no.

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT ANVITHA LIFE CARE PLOT NO. 6, ATTIVARAM INDUSTRIAL PARK, ATTIVARAM VILLAGE, OZILI MANDAL, SPSR NELLORE DISTRICT, ANDHRA PRADESH PRE FEASIBILITY REPORT ANVITHA LIFE CARE PLOT NO. 6, ATTIVARAM INDUSTRIAL

More information

Pre-feasibility Report

Pre-feasibility Report Pre-feasibility Report for expansion of production capacity of Fluoropolymers including Poly Tetrafluoro Ethylene (PTFE), manufacturing of new age refrigerant gas Difluoromethane (HFC 32) and related products,

More information

PRE FEASIBILITY REPORT OF KUMHARI STONE MINE, LESSEE M/s VINOD KUMAR JAIN VILLAGE KUMHARI, P.O. BASIA, P.S. BASIA, DIST. - GUMLA, JHARKHAND

PRE FEASIBILITY REPORT OF KUMHARI STONE MINE, LESSEE M/s VINOD KUMAR JAIN VILLAGE KUMHARI, P.O. BASIA, P.S. BASIA, DIST. - GUMLA, JHARKHAND EXECUTIVE SUMMARY Kumhari Stone Mine is situated in Village - Kumhari, P.O. Basia, P.S. - Basia, District : Gumla, Jharkhand over an area of 2.02 Hectares or 5.00 Acres [ Plot no. 2085(P)]. Kumhari Stone

More information

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED 1. SUMMARY Kacari Silica Sand,Khanda,Geeti And Moram Project at Khasra No.-10,11,12,13,101, 102,122, 126, 127,128,129,130,131, 167,568,570,571,572,

More information

For TOR New. 1. Basic Information of the Project:

For TOR New. 1. Basic Information of the Project: SEAC, Gujarat: Page 1 of 12 For TOR New. 1. Basic Information of the Project: i Name & Address of the Project site M/s. Shreenathji Dye Chem (Complete details with plot no./survey no., Landmark etc. )

More information

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED

PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED PRE-FEASIBILITY REPORT FOR M/s FIXEM CEMENT PRIVATE LIMITED 1. SUMMARY Kacari Silica Sand,Khanda,Stone And Moram Project at Khsara No.-144,145,146,147, 148,150, 309, 310, 311,312,313,314,315,316,317,318,320,399,403,404,405,

More information

Table 1.1: The Salient Features of the Project. Proposed Quartz Mine Of Sri. Syed Masthan Basha

Table 1.1: The Salient Features of the Project. Proposed Quartz Mine Of Sri. Syed Masthan Basha 1. EXECUTIVE SUMMARY 1.1 Introduction The Eknampuram Quartz mine of 89.80 Acres/ 36.34 ha is located in Sy. No. 60, Eknampuram Village, C.S. Puram Mandal, Prakasam District, Andhra Pradesh has been allotted

More information

Mr. Ravikumar R Vansadiya Mob No.: Prepared By: T. R. Associates

Mr. Ravikumar R Vansadiya Mob No.: Prepared By: T. R. Associates PRE FEASIBILITY REPORT FOR PROPOSED NEW PROJECT OF M/s. Roman Petrochemical Survey No. 922/P, Village-Mota Dahisara, Navlakhi Highway, Ta-Maliya, Dist.-Morbi, Gujarat Mr. Ravikumar R Vansadiya Mob No.:

More information

IDA, JEEDIMETLA, QUTUBULLAPUR MANDAL, RANGAREDDY DISTRICT, TELANGANA

IDA, JEEDIMETLA, QUTUBULLAPUR MANDAL, RANGAREDDY DISTRICT, TELANGANA M/s. ARTEMIS BIO TECH LTD., (A Division of Themis Medicare Ltd.,) PLOT NO. 1 & 5, Phase I, IDA, JEEDIMETLA, QUTUBULLAPUR MANDAL, RANGAREDDY DISTRICT, TELANGANA PRE FEASIBILITY REPORT Artemis Bio tech Ltd.,

More information

10 PF Resin (liquid) PF Resin (powder) Silver refining Hexamine Hardener Hexamine Tablet

10 PF Resin (liquid) PF Resin (powder) Silver refining Hexamine Hardener Hexamine Tablet PREFEASBILITY REPORT: 1.0 INTRODUCTION : M/s.Simalin Chemicals Pvt. Ltd.. is an existing unit located at plot no. 13, GIDC, Nandesari, Dist. Vadodara which is a chemical notified zone. The unit is involved

More information

2. PRE-FEASIBILITY REPORT

2. PRE-FEASIBILITY REPORT 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary Sri D. Ujjinappa has applied for quarry lease for extracting of Building stone in Sy No. 19/2, Chatnihalli Village, Harpanahalli Taluk, Davangere District,

More information

PRE - FEASIBILITY REPORT

PRE - FEASIBILITY REPORT PRE - FEASIBILITY REPORT For PROPOSED BULK DRUGS INTERMEDIATES MANUFACTURING UNIT at SY. NO: PARTS OF 318, 319 AND 321 LOCATED AT PALLEPAHAD VILLAGE, THURKAPALLY MANDAL, YADADRI - BHONGIR DISTRICT, TELANGANA

More information

BALAJI AMINES LIMITED

BALAJI AMINES LIMITED FOR EXPANSION OF EXISTING SYNTHETIC ORGANIC CHEMICALS MANUFACTURING UNIT BALAJI AMINES LIMITED At Plot No: 4 & 5, Beside Sub-Station-II, I.D.A, Bollaram, Jinnaram (M), Medak District, Telangana State -

More information

PROJECT PRE-FEASIBILITY REPORT. For

PROJECT PRE-FEASIBILITY REPORT. For PROJECT PRE-FEASIBILITY REPORT For THE PROPOSED ORGANIC CHEMICALS MANUFACTURING IN EXISTING IN FORMULATION OF PESTICIDE, AGROCHEMICAL AND BIO FERTILIZERS MANUFACTURING UNIT AT M/S. SULPHUR MILLS LTD. PLOT

More information

Pre-Feasibility Report. for. Educational Institute Allen Career Institute-Supath

Pre-Feasibility Report. for. Educational Institute Allen Career Institute-Supath Pre-Feasibility Report for Educational Institute Allen Career Institute-Supath at Plot No. 1, Educational Scheme, Naya Nohra & Hanuwantkhera, Kota, Rajasthan-324001 By M/s. Allen Career Institute Registered

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT ASTRICA LABORATORIES PRIVATE LIMITED SY. NO. Part of 46,50,51,52,53, 54,55&56, ANANTHSAGAR VILLAGE, CHEGUNTA MANDAL, MEDAK DISTRICT, TELANGANA PRE FEASIBILITY REPORT ASTRICA LABORATORIES PRIVATE LIMITED

More information

PRE FEASIBILITY REPORT

PRE FEASIBILITY REPORT PRE FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY AND INTRODUCTION OF THE PROJECT Shivneri Sugars Ltd., A/p. - Ganesh tekadi, Nhavi (Bk.), Tal.: Koregaon, Dist.: Satara, Maharashtra State was registered vide

More information

Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.)

Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.) Pre-Feasibility Report for Girgita Limestone Mine of M/s KJS Cements Ltd.) 1) Executive Summary Project Name of Company / Mine Owner Location Village Taluka District State Girgita Limestone Mine M/s KJS

More information

INDEX. S. No. Item Page No. 1 EXECUTIVE SUMMARY 3 2 INTRODUCTION OF THE PROJECT / BACKGROUND

INDEX. S. No. Item Page No. 1 EXECUTIVE SUMMARY 3 2 INTRODUCTION OF THE PROJECT / BACKGROUND PRE-FEASIBILITY REPORT PREPARED FOR D. SESHA REDDY [Mine Lease Area 3.253 Ha.] Sy. No. 12/D Nagarur Village, Yadiki Mandal, Ananthapur District, Andhra Pradesh. PREPARED BY ISO 9001: 2008 Certified Accredited

More information

For TOR New Projects. Mo. no. : Contact no. and ID of the Applicant

For TOR New Projects. Mo. no. : Contact no. and  ID of the Applicant SEAC, Gujarat : Page 1 of 6 For TOR New Projects 1. Basic Information of the Project: i Name & Address of the Project site (Complete details with plot /Survey, Landmark etc. ) M/s. Perstorp Industries

More information

PREFEASIBILITY REPORT

PREFEASIBILITY REPORT PREFEASIBILITY REPORT 1.0 INTRODUCTION OF THE PROJECT Pannageshwar Sugar Mills Ltd. (PSML), At: Pangaon, Tal.: Renapur, Dist.: Latur, Maharashtra was registered vide registration no. 11-130803 dated 01.01.2001.

More information

Pre- FEASIBILITY REPORT

Pre- FEASIBILITY REPORT Pre- FEASIBILITY REPORT In Respect Of KATIKELA RIVER SAND BED OVER 15.00 ACRES OR 6.070 HA IN VILLAGE KATIKELA, JHARSUGUDA TAHASIL OF JHARSUGUDA DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20)

More information

PRE-FEASIBILITY REPORT GHODACH SOAPSTONE & DOLOMITE MINES (APPLICANT: M/S KASTURI MINERALS)

PRE-FEASIBILITY REPORT GHODACH SOAPSTONE & DOLOMITE MINES (APPLICANT: M/S KASTURI MINERALS) 20 PRE-FEASIBILITY REPORT OF GHODACH SOAPSTONE & DOLOMITE MINES (APPLICANT: M/S KASTURI MINERALS) 1. EXECUTIVE SUMMARY: The project is for mining of Ghodach soapstone & Dolomite Mine M.L. No. 69/2010 Near

More information

Kadam Environmental Consultants

Kadam Environmental Consultants M/s. PERSTORP INDUSTRIES INDIA PRIVATE Prefeasibility Report for Proposed Pentaerythritols Manufacturing Plant at Plot No. T 49 to T 54, Saykha Industrial Estate, Vagra Taluka, Bharuch District MARCH 2018

More information

Pre-Feasibility Report

Pre-Feasibility Report Pre-Feasibility Report Essentials Pharma 1 1. Introduction M/s. Essentials Pharma is an new unit to be located at Plot 19, Survey 10/1, Rajkot-Ahmedabad National Highway 8-B, Village: Hirasar, Tal: Rajkot,

More information

PRE- FEASIBILITY REPORT

PRE- FEASIBILITY REPORT PRE- FEASIBILITY REPORT PREPARED FOR SHIV SHANTHI CEMENT PRIVATE LIMITED Sy. Nos. 92, 93 & 94, Tatiguda Village, Garividi Mandal, Vizianagaram District, Andhra Pradesh. PREPARED BY ISO 9001: 2008 Certified

More information

1.1 SALIENT FEATURES OF THE PROJECT Pipeline extension from VVSPL Vijayawada to the proposed Dharmapuri Storage Terminal

1.1 SALIENT FEATURES OF THE PROJECT Pipeline extension from VVSPL Vijayawada to the proposed Dharmapuri Storage Terminal 1.0 EXECUTIVE SUMMARY Hindustan Petroleum Corporation Limited (HPCL) is one of the major Public Sector Navratna Oil Company engaged in refining, marketing and distribution of Petroleum Products in India.

More information

Table 1.1 : Salient features of the project. Sy. No. 379/1, Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh.

Table 1.1 : Salient features of the project. Sy. No. 379/1, Perecherla Village, Medikonduru Mandal, Guntur District, Andhra Pradesh. 1.0 EXECUTIVE SUMMARY 1.1 Introduction Road Metal of M/s. Lakshmi Stone Crusher covering an extent of 2.10 Ac is located at Sy. No. 379/1 of Perecherla Village, Medikonduru Mandal, Guntur District, Andhra

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. 0.96 MTPA Wet type Coal Washery at Birgahani Village, Baloda Tehsil Janjgir-Champa District, Chhattisgarh

More information

Pre-Feasibility Report

Pre-Feasibility Report Pre-Feasibility Report M/s. Veer Poly Chem 0 1. Introduction M/s. Veer Polychem is an existing unit located at Plot 119 & 120, Ranpur road, GIDC Dhandhuka, Dist: Ahmedabad, Gujarat. Currently, unit is

More information

S. No Parameter Details 1 Name & Address of the Applicant

S. No Parameter Details 1 Name & Address of the Applicant 1. EXECUTIVE SUMMARY S. No Parameter Details 1 Name & Address of the Applicant M/s AMULYA GRANITES Prop: Smt CH.SARALA H. No. FLAT NO.207 Roja Kishore Residency, Chenchupet, Tenali, AP-522 202 Guntur District,

More information

PRE FEASIBILITY REPORT OF KANIYAKULAM EARTH QUARRY

PRE FEASIBILITY REPORT OF KANIYAKULAM EARTH QUARRY PRE FEASIBILITY REPORT OF AZHAGAPPAPURAM EARTH FOR OVER AN EXTENT OF 0.61.0HA IN AZHAGAPPAPURAM VILLAGE, AGASTEESWARAM TALUK, KANNIYAKUMARI DISTRICT, TAMIL NADU OF, (Under the Guidelines of Ministry of

More information