1 California State Water Resources Control Board New General Permit For Storm Water Discharges Associated with Industrial Activities Order NPDES No. CAS Effective July 1, 2015 How will the new changes affect Solid Waste Companies? By 1

2 Current Storm Water Requirements for Industrial Sites (Under Water Quality Order No DWQ effective since 1997) 1. Submit NOI & site map and receive a WDID (waste discharge identification) number 2. Storm Water Pollution Prevention Plan (SWPPP) & Monitoring Plan kept at site 3. Collect 2 storm water samples per year (if qualified storm event) 4. Conduct 8 monthly & 4 quarterly visual observations 5. Submit an Annual Report and conduct annual site inspection 6. Conduct Annual Training The NEW General Permit For Storm Water Discharges Associated with Industrial Activities (IGP) Order NPDES No. CAS includes significant changes... 2

3 NEW Requirements /Changes Effective July 1, 2015 HOWEVER preparation ahead of time is required! 3

4 Online Submittal Requirements All Permit Registration Documents (PRDs) & submittals are required electronically via SMARTS by a Legally Responsible Person (LRP) or their Duly Authorized Representative 4

5 Online Submittal Requirements This includes: Notice of Intent (NOI) All applicable sites must submit either an NOI by July 1, 2015 or a No Exposure Certification (NEC) by October 1, SWPPP & map - Applicable sites must submit online by July 1, Upload future revisions to the SWPPP within 30 days. SWPPPs must be revised if Discharger s status changes due to annual Numeric Action Level (NAL) exceedance. Monitoring Results submit analytical data within 30 days of receipt Exceedance Response Action (ERA) Reports For annual NAL exceedances. Annual Reports 5

6 Qualified Industrial Storm Water Practitioner (QISP) New Dischargers that discharge to a water body with a 303(d) listed impairment must submit data and/or information, prepared by a QISP, when applying for IGP coverage QISP Description of Requirements: A QISP must complete a SWRCB approved training course or be a CA licensed PE, PG, or CEG. A competency exam may be required for certification as a QISP (similar to Construction QSP/QSD). Only QISPs can prepare the following documents: The SWPPPs for Level 1 & Level 2 dischargers. Level 1 status Exceedance Response Action Evaluation and Reports Level 2 status Exceedance Response Action Technical Reports / Plans and Level 2 status Exceedance Response Action Extension. 6

7 Minimum Best Management Practices (BMPs) Sites must implement the following BMPs or document why they are inapplicable, infeasible, inappropriate, etc.: Observe outdoor industrial activity areas and clean up debris, waste, spills, tracked, or leaking materials. Implement BMPs to minimize or prevent tracking. Cover all stored industrial materials that can be readily mobilized by contact with storm water. 7

8 Minimum Best Management Practices (BMPs) Continued: Contain all stored non-solid industrial materials (e.g., liquid, powder, etc.) that can be dispersed via wind or contact with storm water. Implement BMPs to ensure that facility areas impacted by rinse/wash waters are cleaned as soon as possible. Minimize authorized (NSWDs) Non-Storm Water Discharges (e.g., potable water, fire Hydrant testing, etc.) and prevent from contacting Industrial areas of the facility. Minimize storm water discharges from non-industrial areas (e.g., employee parking areas) from contact with industrial areas of the facility. 8

9 Minimum Best Management Practices (BMPs) Continued: Prevent or minimize handling of industrial materials or wastes that can be mobilized by contact with storm water during a storm event. Cover waste disposal containers & material storage containers when not in use. <<These may need covers unless they can be stored inside Direct run-on away from stock piled materials. 9

10 Minimum Best Management Practices (BMPs) Continued: Observe and clean outdoor material/waste handling equipment or containers that can be contaminated by contact with industrial materials or wastes. Establish a maintenance schedule for outdoor equipment that may spill or leak. Establish procedures for prompt maintenance and repair of equipment when conditions exist that may result in spills or leaks. 10

11 EROSION CONTROL BMPs Provide stabilization for inactive areas, slopes, and erodible areas prior to a forecasted storm event. Implement wind erosion controls. Direct run-on away from erodible materials. Maintain effective perimeter controls to control discharges of erodible materials offsite. Design sediment basins to ensure compliance with design storm standards. Maintain sediment and erosion control BMPs to comply with the General Permit during all times. 11

12 More Detailed BMP Information Required in SWPPP The SWPPP must include a narrative describing each BMP including: The pollutant the BMP is designed to reduce/prevent in storm water discharges. The frequency, time of day, or conditions when the BMP is implemented. The BMP implementation location within each area of industrial activity or pollutant source. The individual and/or position responsible for implementing the BMP. Procedures (including maintenance) to implement the BMP effectively. Equipment and tools required to implement the BMP effectively. 12

13 Increased Monitoring Requirements Monthly Daylight Visual Observations on days without precipitation (previously was Quarterly) Each month, the Discharger shall observe each drainage area for the following: i. Prior, current, or potential unauthorized NSWDs (Non-Storm Water Discharges) and their sources; ii. Authorized NSWDs, the sources, and associated BMPs; and, iii. Outdoor industrial equipment and storage areas, outdoor industrial activities areas, BMPs, and all other potential source of industrial pollutants. The Discharger shall provide an explanation in the Annual Report for uncompleted monthly visual observations. 13

14 Qualifying Storm Event (QSE) New Definition for a Qualifying Storm Event A Qualifying Storm Event (QSE) is a precipitation event that: a. Produces a discharge for at least one drainage area; and, b. Is preceded by 48 hours with no discharge from any drainage area. 14

15 Sample Frequency Requirements Increased Sample Frequency Requirements: Dischargers shall collect storm water samples from all locations that discharge storm water associated with industrial activity for 2 QSEs within the first half of each reporting year (July 1 to December 31) and 2 QSEs within the second half of each reporting year (January 1 to June 30). No More Excuses for Not Collecting Samples: Samples from each discharge location shall be collected within 4 hours of: a. The start of the discharge; or b. The start of facility operations, if the QSE occurs within the previous 12-hour period (e.g., for storms with discharges that begin during the night for facilities with day-time operating hours). 15

16 Sampling Parameter Selection Total Suspended Solids (TSS), ph, and Oil & Grease (O&G) required for all plus... Additional Standard Industrial Classification (SIC) Code Required Parameters Additional Parameters identified in a required site-specific pollutant source assessment Additional Parameters related to nearby 303(d) listed impaired water bodies Additional Parameters required by the Regional Water Board. Additional Parameters required by Subchapter N (Dischargers subject to Effluent Limitations Guidelines (ELG)) 16

17 SIC Additional Parameters Standard Industrial Classification (SIC) Code Required Parameters for Waste Handlers: 4953 Landfills & Land Application Facilities = Iron (Fe) 4953 Hazardous Waste Facilities = Ammonia (NH3), Chemical Oxygen Demand (COD), Cyanide (Cn), Arsenic (As), Lead (Pb), Magnesium (Mg), Mercury (Hg), Selenium (Se), & Silver (Ag) Scrap & Waste Materials = COD, Aluminum (Al), Iron (Fe), Lead (Pb), and Zinc (Zn) Dismantling or Wrecking Yards = Aluminum (Al), Iron (Fe), & Lead (Pb). NOTE: Copper (Cu) is no longer required for

18 Additional Parameters for 303(d) Impaired water bodies with Total Maximum Daily Loads (TMDL) Regional Water Board adopted and/or U.S. EPA established/approved TMDLs, as of the adoption date of this General Permit, that are applicable to industrial storm water Dischargers. Subject to change in future as more are added. Example.. San Diego Regional Water Quality Control Board Water Body Pollutant Chollas Creek Diazinon, Copper, Lead, and Zinc Los Peñasquitos Lagoon Sediment Rainbow Creek Total Nitrogen and Total Phosphorus Shelter Island Yacht Basin Dissolved Copper Baby Beach in Dana Point Harbor Indicator Bacteria Shelter Island Shoreline Park in SD Bay Indicator Bacteria Twenty Beaches and Creeks Indicator Bacteria 18

19 Field Measurements Field Measurements: Specific Conductance (SC) is no longer required Due to the 15 minute holding time, measurements for ph usually are made in the field. This can be done using a wide range ph litmus paper. However, if the discharger exceeds Numeric Action Levels (NALs), then the permit requires the use of a calibrated ph meter. This device must meet minimum standards for this type of field sampling and must be calibrated in accordance with the manufacturers specifications. 19

20 Numeric Action Limits TABLE 5: Parameter NAL Values, Test Methods, Detection Limits, and Reporting Units ph* PARAMETER TEST METHOD MDL*** field test with calibrated portable instrument, or lab sample per 40CFR 136. REPORTING UNITS ph units ANNUAL NAL INSTANTANEOUS MAXIMUM NAL Total Suspended Solids (TSS)* SM 2540-D 1.0 mg/l Oil & Grease (O&G)* EPA 1664A 1.0 mg/l Zinc, Total (H) EPA mg/l 0.26** Copper, Total (H) EPA mg/l ** Cyanide, Total EPA I mg/l Lead, Total (H) EPA mg/l 0.262** Chemical Oxygen Demand (COD) SM 5220C 1.0 mg/l 120 Aluminum, Total EPA mg/l 0.75 Iron, Total EPA mg/l 1.0 Nitrate + Nitrite Nitrogen SM 4500-NO3- E 0.01 mg/l as N 0.68 Total Phosphorus SM 4500-P B+E 0.05 mg/l as P 2.0 Ammonia SM 4500-NH3 B+C or E 0.1 mg/l 2.14 Magnesium, total EPA mg/l Arsenic, Total (c) EPA mg/l 0.15 Cadmium, Total (H) EPA mg/l ** Nickel, Total (H) EPA mg/l 1.02** Mercury, Total EPA mg/l Selenium, Total EPA mg/l Silver, Total (H) EPA mg/l ** Biochemical Oxygen Demand (BOD) SM 5210B 3.0 mg/l 30 SM Standard Methods for the Examination of Water and Wastewater, 18 th edition EPA EPA test methods *Minimum parameters required by this General Permit **The NAL is the highest value used by EPA based on their hardness table in the 2008 MSGP. ***More stringent test methods with lower detection limits may be used. 20

21 Numeric Action Limits Exceedances Two Types of Numeric Action Limits (NAL) Exceedances: 1) Annual NAL Exceedance When the average of the annual sample results for a parameter are exceeded (refer to Annual NAL on Table 5). Note: Sites can take additional samples (>4 per year) if they want to try and lower the annual average for a parameter. 2) Instantaneous Maximum NAL Exceedance - when two or more results in a reporting year exceed (for TSS or O&G) or are outside the ph range per Table 5. 21

22 Exceedance Response Actions (ERAs) Baseline Status No Exceedance All Dischargers start NOI Coverage at Baseline Status. Level 1 Status - NAL Exceedance immediately triggers Level 1 status for parameters exceeded. Within 60 days discharger shall evaluate the SWPPP and pollutant sources. ASAP, or by October 1 following the reporting year, dischargers shall implement additional operational and/or source control BMPs, revise the SWPPP, and submit via SMARTS a QISP prepared Level 1 ERA evaluation. 22

23 Exceedance Response Actions (ERAs) Level 2 Status Structural/Treatment Control A Level 1 status immediately changes to Level 2 for parameters that have an NAL exceedance in any subsequent reporting year. Within 120 days discharger shall: a. Evaluate the SWPPP and pollutant sources and identify whether additional structural and/or treatment control BMPs are necessary. b. Submit via SMARTS a QISP prepared Level 2 ERA Technical Report including implementation schedule for design & construction of treatment and/or structural source control BMPs or a schedule to submit a Demonstration Technical Report. ASAP, or within one year discharger shall: implement structural and/or treatment control BMPs, revise the SWPPP, and (if applicable) submit Demonstration Technical Report. 23

24 Demonstration Technical Reports BAT/BCT Compliance Demonstration Technical Report: Evaluate cost of technology in relation to effluent reduction benefits, age of equipment & facilities involved, process employed, engineering aspects of the various types of control techniques, process changes, and non-water quality environmental impact (i.e. energy requirements) Non-Industrial Source Pollutant Demonstration Technical Report: Discharger must demonstrate that the pollutants causing the exceedances are solely attributable to storm water run-on from adjacent properties or from non-industrial portions of the Discharger s property, or from aerial deposition. Requires a quantification of the relative contributions of the pollutant from run-on, non-industrial sources, or aerial deposition. 24

25 Demonstration Technical Reports Natural Background Demonstration Technical Report includes: A summary of all data previously collected by the Discharger or others that describe the levels of natural background pollutants in the storm water discharge A summary of any research and published literature that relates the pollutants evaluated at the facility; A map showing the reference site location in relation to facility along with available land cover information; Reference site and test site elevation; Available geology and soil information for reference and test sites; Photographs showing site vegetation; Site reconnaissance survey data regarding presence of roads, outfalls, or other human-made structures; and Records from relevant state or federal agencies indicating no known mining, forestry, or other human activities upstream of the proposed reference site. 25

26 COMPLIANCE GROUPS & LEADERS Baseline/Level 1 Compliance Group (CG1) and Baseline/Level 1 Compliance Group Leader (CGL1) Requirements A group of Dischargers of the same industry type (facilities with similar types of industrial activities, pollutant sources, and pollutant characteristics) may form a CG1. The CG1 shall select a CGL1 to assist with all compliance activities in this General Permit other than Level 2 ERA compliance activities. For example SWPPP development, monitoring, visual observations and inspections. The number of samples required per year is reduced from four to two. 26

27 COMPLIANCE GROUPS & LEADERS A CGL1 must prepare a Consolidated Level 1 ERA Report, which provide a description of the common industrial pollutant sources, BMPs & ERAs, and also the industrial pollutant sources, BMPs & ERAs that are not common between the CG1 Participants. The CGL1 shall revise the Consolidated Level 1 ERA Report in accordance with any comments received from the Water Boards The CGL1 shall inspect all the facilities of the CG1 Participants at a minimum of once per reporting year (July 1 to June 30). The CGL1 shall update the Consolidated Level 1 ERA Report as needed to address additional CG1 Participants that trigger the ERA Level 1 reporting requirements 27

28 Quality Assurance & Record Keeping Records must be kept for a minimum of 5 years including: Records of BMP implementation (dates of implementation/maintenance) Training Records Spill & Clean-up related response activity records Sampling Data Inspection/Observation Records Annual Reports (due July 15 th ) ERA Demonstrations Demonstration Technical Reports 28

29 Conclusions Major changes from the current program Requires a Qualified professional to do the work More Chemical testing and Analysis of Data More Sampling & Monitoring Events are Required Field ph Measurements are required More Reporting and Electronic Submittals required Must meet Discharge Limits More Stringent Corrective Action Requirements 29

Solving Your Stormwater Compliance Challenges

Solving Your Stormwater Compliance Challenges Solving Your Stormwater Compliance Challenges Presented by: Tory R. Walker, PE, CFM, LEED GA, QISP Alex J. Smith, MS, EIT, QISP 11/03/2017 Welcome & Introductions Tory R. Walker, PE, CFM, LEED GA, QISP

More information

The California Industrial Permit and the Solid Waste Industry Laura Carpenter and Sean Porter Brown and Caldwell San Diego, CA

The California Industrial Permit and the Solid Waste Industry Laura Carpenter and Sean Porter Brown and Caldwell San Diego, CA The California Industrial Permit and the Solid Waste Industry Laura Carpenter and Sean Porter Brown and Caldwell San Diego, CA INTRODUCTION On July 1, 2015, the California State Water Resources Control

More information

LEVEL 1 STATUS 9/27/2016 OVERVIEW

LEVEL 1 STATUS 9/27/2016 OVERVIEW YOU FIND YOURSELF IN ERA LEVEL 1 WHAT SHOULD YOU DO NOW? CDIM Engineering, Inc. Environmental Science & Engineering 45 Polk Street, 3 rd Floor San Francisco, California www.cdimengineering.com 1 OVERVIEW

More information

Recycling And The New Virginia Stormwater Management Program Regulations VIRGINIA RECYCLING ASSOCIATION 2014 ANNUAL CONFERENCE

Recycling And The New Virginia Stormwater Management Program Regulations VIRGINIA RECYCLING ASSOCIATION 2014 ANNUAL CONFERENCE Recycling And The New Virginia Stormwater Management Program Regulations VIRGINIA RECYCLING ASSOCIATION 2014 ANNUAL CONFERENCE Agenda Overview of regulatory program Specific guidance on: Mulching Composting

More information

Storm Water Permitting

Storm Water Permitting Storm Water Permitting July 12, 2018 N E S g l o b a l. n e t Your Participation Join audio: You have joined using computer speakers by default Choose Telephone and dial using the information provided

More information

Stormwater Management at Municipal Solid Waste Landfills

Stormwater Management at Municipal Solid Waste Landfills Stormwater Management at Municipal Solid Waste Landfills Permit Coverage Municipal Solid Waste Landfills are covered under one of the following National Pollutant Discharge Elimination System (NPDES) types

More information

Landfills And The New Virginia Stormwater Management Program Regulations

Landfills And The New Virginia Stormwater Management Program Regulations Landfills And The New Virginia Stormwater Management Program Regulations Agenda Overview of regulatory programs Specific guidance from DEQ Quiz Questions and Answers Why Is this such a hot topic? NEW REGULATIONS

More information

Wastewater Pretreatment Plant Special Waste Generator Application

Wastewater Pretreatment Plant Special Waste Generator Application New Renewal (Permit # ) EIN number All generators of Special Waste are required to apply for and receive a Special Waste Generator Permit from Lehigh County Authority (LCA) prior to discharging waste at

More information

ATTACHMENT C RISK LEVEL 1 REQUIREMENTS

ATTACHMENT C RISK LEVEL 1 REQUIREMENTS ATTACHMENT C RISK LEVEL 1 REQUIREMENTS A. Effluent Standards [These requirements are the same as those in the General Permit order.] 1. Narrative Risk Level 1 dischargers shall comply with the narrative

More information

RECOMMENDED SCOPE OF ACCREDITATION (For Testing Laboratories) * Test Method / Standard against which tests are performed

RECOMMENDED SCOPE OF ACCREDITATION (For Testing Laboratories) * Test Method / Standard against which tests are performed Sl Product / Material of test 1 Wastewater Colour, true colour units, 2 Turbidity, NTU 3 Total dissolved solids mg/1, IS-3025 (Part 4) -1983 2005: 2120 /C IS-3025 (Part 10)-1984 2005: 2130/B IS-3025 (Part

More information

Appendix B Stormwater Pollution Prevention Plan Outline

Appendix B Stormwater Pollution Prevention Plan Outline Outline Annotated Outline of SWPPP Components to meet General Permit Requirements This appendix presents a recommended structure for a traditional construction site Stormwater Pollution Prevention Plan

More information

c. Sites subject to regulation under Subtitle D of RCRA. The following discharges are not authorized by this permit:

c. Sites subject to regulation under Subtitle D of RCRA. The following discharges are not authorized by this permit: Page 1 of 6 Permit No: MNR050000 PART VII. SECTOR-SPECIFIC REQUIREMENTS The Permittee shall comply with Part VII (sector-specific requirements) for any primary SIC code and/or narrative activity and co-located

More information

SECTION WATER POLLUTION CONTROL

SECTION WATER POLLUTION CONTROL SECTION 01 35 35 WATER POLLUTION CONTROL PART 1 GENERAL 1.01 SECTION INCLUDES A. Requirements for water pollution control during construction, including preparation of Storm Water Pollution Prevention

More information

LOS ANGELES UNIFIED SCHOOL DISTRICT REFERENCE GUIDE

LOS ANGELES UNIFIED SCHOOL DISTRICT REFERENCE GUIDE TITLE: NUMBER: ISSUER: Storm Water Discharges Associated with Construction and Land Disturbance Activities REF-6286.0 John Sterritt, Director Enrique G. Boull t, Chief Operating Officer Office of the Chief

More information

Construction Permit Timeline

Construction Permit Timeline Construction Permit Timeline Previous permit Order 99 08 08 DWQ expired in 2004 September 2, 2009: Order No. 2009 0009 0009 DWQ Adopted Effective July 1, 2010 Existing Dischargers Continue to comply with

More information

Storm Water Pollution Prevention Plan

Storm Water Pollution Prevention Plan Storm Water Pollution Prevention Plan Berryessa Union School District 945 Piedmont Road San Jose, California 95132 WDID #: 2 43I009162 Approved by Berryessa Union School District Safety Committee April

More information

SIGNIFICANT USER WASTEWATER DISCHARGE PERMIT. City of Las Cruces, at. Utilities Department Regulatory Environmental Services Section

SIGNIFICANT USER WASTEWATER DISCHARGE PERMIT. City of Las Cruces, at. Utilities Department Regulatory Environmental Services Section SIGNIFICANT USER WASTEWATER DISCHARGE PERMIT City of Las Cruces Utilities Department Regulatory Environmental Services Section Permit Number 00000 In accordance with all terms and conditions of the Las

More information

ANNUAL INDUSTRIAL STORMWATER

ANNUAL INDUSTRIAL STORMWATER MARINE CORPS BASE CAMP PENDLETON ANNUAL INDUSTRIAL STORMWATER AND BMP TRAINING 5 Dec 2017 & 19 Dec 2017 1 Stu Eyler Kevin Goodell ES Stormwater Section Introductions and Announcements. You are here for

More information

Annex 7.1 National Ambient Air Quality Standards for Nepal, 2003

Annex 7.1 National Ambient Air Quality Standards for Nepal, 2003 Annex 7.1 National Ambient Air Quality Standards for Nepal, 2003 Parameters Units Averaging Time TSP (Total Suspended Particulars) Concentration in Ambient Air, maximum Test method µg/m 3 Annual - 24-hours*

More information

September A Monthly Newsletter on the California Industrial General Permit By WGR Southwest, Inc.

September A Monthly Newsletter on the California Industrial General Permit By WGR Southwest, Inc. September 2014 A Monthly Newsletter on the California Industrial General Permit By WGR Southwest, Inc. But it doesn t discharge! There is growing alarm about the Notice of Non-Applicability (NONA) requirements

More information

NC Division of Energy, Mineral, and Land Resources FACT SHEET FOR NPDES STORMWATER PERMIT DEVELOPMENT NPDES Stormwater Permit NCS000572

NC Division of Energy, Mineral, and Land Resources FACT SHEET FOR NPDES STORMWATER PERMIT DEVELOPMENT NPDES Stormwater Permit NCS000572 NC Division of Energy, Mineral, and Land Resources FACT SHEET FOR NPDES STORMWATER PERMIT DEVELOPMENT NPDES Stormwater Permit NCS000572 Facility Information Applicant/Facility Name: Duke Energy Carolinas,

More information

TPDES INDUSTRIAL STORMWATER MULTI-SECTOR GENERAL PERMIT (TXR050000) Lindsay Garza. Stormwater and Pretreatment Team Water Quality Division

TPDES INDUSTRIAL STORMWATER MULTI-SECTOR GENERAL PERMIT (TXR050000) Lindsay Garza. Stormwater and Pretreatment Team Water Quality Division TPDES INDUSTRIAL STORMWATER MULTI-SECTOR GENERAL PERMIT (TXR050000) Lindsay Garza Stormwater and Pretreatment Team Water Quality Division INDUSTRIAL STORMWATER PERMIT APPLICABILITY If a facility discharges

More information

Maryland Department of the Environment. 12-SW Permit Update for Stormwater Discharges Associated With Industrial Activity

Maryland Department of the Environment. 12-SW Permit Update for Stormwater Discharges Associated With Industrial Activity Maryland Department of the Environment 12-SW Permit Update for Stormwater Discharges Associated With Industrial Activity Stormwater Permit Background The Clean Water Act (CWA or the Act) establishes a

More information

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions

Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR050000 Storm Water Pollution Prevention Plan Worksheet Instructions The TCEQ Small Business and Local Government Assistance

More information

Annual Stormwater Pollution Prevention Training

Annual Stormwater Pollution Prevention Training Annual Stormwater Pollution Prevention Training Columbus Airport August 2018 Agenda 1. Regulatory Background 2. Regulated Activities 3. Roles and Responsibilities 4. Best Management Practices 5. Spill

More information

Proposed Addition to ATTACHMENT E, LIST OF TOTAL MAXIMUM DAILY LOADS (TMDLs) APPLICABLE TO INDUSTRIAL STORM WATER DISCHARGERS

Proposed Addition to ATTACHMENT E, LIST OF TOTAL MAXIMUM DAILY LOADS (TMDLs) APPLICABLE TO INDUSTRIAL STORM WATER DISCHARGERS Proposed Addition to ATTACHMENT E, LIST OF TOTAL MAXIMUM DAILY LOADS (TMDLs) APPLICABLE TO INDUSTRIAL STORM WATER DISCHARGERS Oxnard Drain No. 3 Total Maximum Daily Load (TMDL) for Pesticides, PCBs, and

More information

4.0 SAN GABRIEL RIVER WATERSHED MANAGEMENT AREA

4.0 SAN GABRIEL RIVER WATERSHED MANAGEMENT AREA 4.0 SAN GABRIEL RIVER WATERSHED MANAGEMENT AREA 4.1 Watershed Description 4.1.1 Watershed Land Use, Percent Impervious, and Population Land use in the San Gabriel River Watershed Management Area is approximately

More information

DRAFT OHIO EPA INDUSTRIAL STORMWATER GENERAL PERMIT. I. Comparison with Existing General Permit (OHR000004)

DRAFT OHIO EPA INDUSTRIAL STORMWATER GENERAL PERMIT. I. Comparison with Existing General Permit (OHR000004) DRAFT OHIO EPA INDUSTRIAL STORMWATER GENERAL PERMIT I. Comparison with Existing General Permit (OHR000004) A. See attached comparison chart courtesy of Curt Spence, Spence Environmental Consulting, Inc.

More information

2018 Schedule of Rates Fees and Charges City of Glens Falls, NY Water & Sewer Department Water Rates: $37.28 per Non-meter rate

2018 Schedule of Rates Fees and Charges City of Glens Falls, NY Water & Sewer Department Water Rates: $37.28 per Non-meter rate 2018 Schedule of Rates Fees and Charges City of Glens Falls, NY Water & Sewer Department Water Rates: $37.28 per Non-meter rate billing Meter Rate: $1.381 per 100 cubic feet Minimum Meter Rates Meter Size

More information

Clean Water Act Industrial Stormwater Applicability Flowchart. July 2009

Clean Water Act Industrial Stormwater Applicability Flowchart. July 2009 Clean Water Act Industrial Stormwater Applicability Flowchart July 2009 Office of Compliance Office of Enforcement and Compliance Assurance U.S. Environmental Protection Agency 1200 Pennsylvania Avenue,

More information

Risk Level 1 Annual Report Questions GENERAL INFO

Risk Level 1 Annual Report Questions GENERAL INFO GENERAL INFO A. Site Owner Information Owner Name: Owner Address: City: State: Owner Contact: E-Mail: Phone: Zip: B. Site Information Site Business Name: Site WDID No: Physical Address: City: Site Contact:

More information

DENR/DEMLR FACT SHEET FOR NPDES STORMWATER PERMIT DEVELOPMENT. NPDES Stormwater Permit NCS000548

DENR/DEMLR FACT SHEET FOR NPDES STORMWATER PERMIT DEVELOPMENT. NPDES Stormwater Permit NCS000548 DENR/DEMLR FACT SHEET FOR NPDES STORMWATER PERMIT DEVELOPMENT Facility Information Applicant/Facility Name: Duke Energy Carolinas, LLC Marshall Steam Station Applicant Address: P.O. Box 1006, Mail Code

More information

American Public Works Association May 3, 2010 Southern California Chapter

American Public Works Association May 3, 2010 Southern California Chapter American Public Works Association New Construction General Permit Overview Presented by Jason Uhley, P.E. Riverside County Flood Control and Water Conservation District and Jeff Endicott, P.E., BCEE, CPESC

More information

DOE/PPPO/ &D1 FBP-ER-PRO-WD-RPT-0001 Revision 3 April ENVIRONMENTAL NON-RADIOLOGICAL PROGRAM INFORMATION

DOE/PPPO/ &D1 FBP-ER-PRO-WD-RPT-0001 Revision 3 April ENVIRONMENTAL NON-RADIOLOGICAL PROGRAM INFORMATION 5. ENVIRONMENTAL NON-RADIOLOGICAL PROGRAM INFORMATION 5.1 SUMMARY Non-radiological environmental monitoring at PORTS includes air, water, sediment, and fish. Monitoring of non-radiological parameters is

More information

The Solution to Pollution is Dilution

The Solution to Pollution is Dilution The Solution to Pollution is Dilution The cornerstone of surface water quality protection in the United States gave EPA the authority to implement pollution control programs and... established the basic

More information

Industrial/Commercial Inspection Workshop June 2016 Kristin Kerr, P.E. EOA, Inc.

Industrial/Commercial Inspection Workshop June 2016 Kristin Kerr, P.E. EOA, Inc. Reissued MRP: How is it Different and How is it the Same Industrial/Commercial Inspection Workshop June 2016 Kristin Kerr, P.E. EOA, Inc. Outline of Presentation Regulatory Background New Municipal Regional

More information

Georgia Power Plant Bowen NPDES Permit No. GA Ash Pond Dewatering Plan. Revised December 2017

Georgia Power Plant Bowen NPDES Permit No. GA Ash Pond Dewatering Plan. Revised December 2017 Georgia Power Plant Bowen NPDES Permit No. GA0001449 Revised December 2017 Purpose This (Plan) describes the additional procedures, safeguards and enhanced wastewater treatment measures that Georgia Power

More information

Frequently Asked Questions for Permitting

Frequently Asked Questions for Permitting Frequently Asked Questions for Permitting What is a National Pretreatment Program? The National Pretreatment Program is a cooperative effort of federal, state, and local regulatory environmental agencies

More information

Clyde Mine Discharge/Tenmile Creek Water Quality Final Report

Clyde Mine Discharge/Tenmile Creek Water Quality Final Report Clyde Mine Discharge/Tenmile Creek Water Quality Final Report November 01, 2016 Background In follow-up to the Pennsylvania Department of Environmental Protection s (DEP) December 15, 2015, Tenmile Creek

More information

WASTEWATER DISCHARGE PERMIT APPLICATION SHORT FORM

WASTEWATER DISCHARGE PERMIT APPLICATION SHORT FORM WASTEWATER DISCHARGE PERMIT APPLICATION SHORT FORM * * * * * * * * * * * RETURN TO: NARRAGANSETT BAY COMMISSION PRETREATMENT SECTION 2 ERNEST STREET PROVIDENCE, RHODE ISLAND 02905 (401) 461-8848 (401)

More information

Globeville Landing Outfall Surface Water. December 12, 2017 Andrew Ross, Jon Novick Denver Department of Public Health & Environment

Globeville Landing Outfall Surface Water. December 12, 2017 Andrew Ross, Jon Novick Denver Department of Public Health & Environment Globeville Landing Outfall Surface Water December 12, 2017 Andrew Ross, Jon Novick Denver Department of Public Health & Environment Introductions Andrew Ross Environmental Program Manager, DDPHE Jon Novick

More information

Arizona Department of Environmental Quality Industrial Stormwater Program (Multi-Sector General Permit) Spencer J. York, Project Manager

Arizona Department of Environmental Quality Industrial Stormwater Program (Multi-Sector General Permit) Spencer J. York, Project Manager Arizona Department of Environmental Quality Industrial Stormwater Program (Multi-Sector General Permit) Spencer J. York, Project Manager Arizona Department of Environmental Quality Stormwater and General

More information

Georgia Power Plant McManus NPDES Permit No. GA Ash Pond Dewatering Plan. Revised April 2018

Georgia Power Plant McManus NPDES Permit No. GA Ash Pond Dewatering Plan. Revised April 2018 Georgia Power Plant McManus NPDES Permit No. GA0003794 Revised April 2018 Purpose This (Plan) describes the procedures, safeguards and enhanced wastewater treatment measures that Georgia Power Company

More information

Concentration of Metals (Cd, Hg, Ag; mean +SD) in sediment samples collected from Pit Specific Sediment Chemistry Monitoring for CMP 1 in May 2014.

Concentration of Metals (Cd, Hg, Ag; mean +SD) in sediment samples collected from Pit Specific Sediment Chemistry Monitoring for CMP 1 in May 2014. Figure 1: Concentration of Metals (Cr, Cu, Ni, Pb, Zn, As; mean +SD) in sediment samples collected from Pit Specific Sediment Chemistry Monitoring for CMP 1 in May 2014. Figure 2: Concentration of Metals

More information

General Permit No.: OHR Page 53 of 146

General Permit No.: OHR Page 53 of 146 Page 53 of 146 Part 8 Sector-Specific Requirements for Industrial Activity Subpart J Sector J Non-Metallic Mineral Mining and Dressing. You shall comply with Part 8 sector-specific requirements associated

More information

Key Requirements of the Construction General Permit Scott Taylor, P.E. Tanya Bilezikjian, P.E.

Key Requirements of the Construction General Permit Scott Taylor, P.E. Tanya Bilezikjian, P.E. Key Requirements of the Construction General Permit Scott Taylor, P.E. Tanya Bilezikjian, P.E. Learning Objectives Course participants shall be able to: Recognize basic permit elements Recognize the need

More information

Storm Water Pollution Prevention Plan for CES Gravel #3800

Storm Water Pollution Prevention Plan for CES Gravel #3800 David Lewis Cell: (870) 310-2757 Rickey Vaughn Cell: (870) 310-9602 Buddy McAdams Cell: (870) 310-8733 Local (870) 881-8830 Fax: (870) 881-8809 LICENSED, BONDED & INSURED Howard Cupp, Jr. Cell: (870) 314-2877

More information

B. CASQA Construction Handbook / Website Portal Available as a subscription service at: https://www.casqa.org/resources.

B. CASQA Construction Handbook / Website Portal Available as a subscription service at: https://www.casqa.org/resources. SECTION 01 57 23 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

Preliminary Outline of IGP QISP TOR Training (training to be provided by IGPTT)

Preliminary Outline of IGP QISP TOR Training (training to be provided by IGPTT) Attachment A Attachment A: IGP QISP Training Content Preliminary Outline of IGP QISP TOR Training (training to be provided by IGPTT) Day 1 1. Introduction to the Qualified Industrial Practitioner (QISP)

More information

Mount Polley Mining Corporation an Imperial Metals company Box 12 Likely, BC V0L 1N0 T F

Mount Polley Mining Corporation an Imperial Metals company Box 12 Likely, BC V0L 1N0 T F Mount Polley Mining Corporation an Imperial Metals company Box 12 Likely, BC V0L 1N0 T 250.790.2215 F 250.790.2613 November 24, 2016 Ministry of Environment Mining Operations Environmental Protection 2080

More information

Part 2.0 Non-Numeric Effluent Limitations

Part 2.0 Non-Numeric Effluent Limitations 2017 NH Small MS4 General Permit Page 50 of 67 report on its findings and progress towards making the practices allowable. (Information available at: http://www.epa.gov/region1/npdes/stormwater/assets/pdfs/addressingbarrier2lid.pdf

More information

State of Georgia Department of Natural Resources Environmental Protection Division NOTICE OF INTENT. NOI - Version 2012

State of Georgia Department of Natural Resources Environmental Protection Division NOTICE OF INTENT. NOI - Version 2012 State of Georgia Department of Natural Resources Environmental Protection Division For official use only NOTICE OF INTENT NOI - Version 2012 For Coverage Under NPDES General Permit GAR050000 (2012 IGP)

More information

MECON LIMITED RANCHI , INDIA

MECON LIMITED RANCHI , INDIA ORISSA MINING CORPORATION LIMITED BANGUR CHROMITE MINING PROJECT POST CLEARANCE ENVIRONMENTAL MONITORING REPORT FOR THE MONTH OF JULY 2011 MECON LIMITED RANCHI 834 002, INDIA 11.S2.2011 SEPTEMBER, 2011

More information

Building & Grounds Maintenance

Building & Grounds Maintenance Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Stormwater runoff from building and grounds maintenance activities can be contaminated with toxic hydrocarbons in solvents,

More information

Newmont Mining Corporation Water Management Standard

Newmont Mining Corporation Water Management Standard Page No: Page 1 of 5 1 PURPOSE AND OBJECTIVES This Global Standard sets the minimum Newmont requirements to proactively plan and manage water from exploration to post-closure in accordance with Newmont

More information

Overview of the New Construction General Permit. Compliance Specialist

Overview of the New Construction General Permit. Compliance Specialist Overview of the New Construction General Permit John Teravskis John Teravskis Compliance Specialist The new Construction ti General Permit (CGP) was adopted on September 2, 2009. Goes into effect July

More information

Hamlet of Aklavik. Water Licence Number: N3L Municipal Water Licence. Annual Report for the Year Date Prepared: March 9, 2017.

Hamlet of Aklavik. Water Licence Number: N3L Municipal Water Licence. Annual Report for the Year Date Prepared: March 9, 2017. Hamlet of Aklavik Water Licence Number: N3L3-0570.. Municipal Water Licence Annual Report for the Year 2016 Date Prepared: March 9, 2017. -2- Municipal Water Licence Annual Report Hamlet of Aklavik Licence

More information

State of Nevada Department of Conservation and Natural Resources Division of Environmental Protection Laboratory Scope of Accreditation

State of Nevada Department of Conservation and Natural Resources Division of Environmental Protection Laboratory Scope of Accreditation Matrix: CWA (Non Potable Water) Discipline: Chemistry ASTM D516-07 ASTM D6888-09 ASTM D7511-09e2 EPA 160.4 EPA 1631E EPA 1664A EPA 1664A (SGT-HEM) EPA 180.1 Sulfate 8/1/2018 Cyanide, Amenable 8/1/2018

More information

STORMWATER POLLUTANT ASSESSMENT AT THE CITY OF KISSIMMEE

STORMWATER POLLUTANT ASSESSMENT AT THE CITY OF KISSIMMEE STORMWATER POLLUTANT ASSESSMENT AT THE CITY OF KISSIMMEE Eric Gurr and Fidelia Nnadi Department of Civil and Environmental Engineering University of Central Florida, Orlando, FL ABSTRACT Historically,

More information

Cranston Sewer Use Ordinance

Cranston Sewer Use Ordinance Cranston Sewer Use Ordinance Proposed Revisions to Local Discharge Limits August 27, 2012 Presented by Veolia Water Daniel Gorka Local Limits Revisions - Background The Cranston Water Pollution Control

More information

Best Management Practices (BMPs): Regulations and Case Studies

Best Management Practices (BMPs): Regulations and Case Studies Best Management Practices (BMPs): Regulations and Case Studies 800 E. Ocean Blvd, Suite 105 Long Beach, CA 90802 562-391-2925 www.stormwatersystems.net Minimum BMPs Required The Industrial General Permit

More information

QSD/QSP Training Module 9 SWPPP Preparation

QSD/QSP Training Module 9 SWPPP Preparation QSD/QSP Training Module 9 SWPPP Preparation Anna Lantin, P.E., CPESC, CPSWQ Overview and Learning Objectives Given a project Risk Level or LUP Type, you will learn to: Prepare a compliant SWPPP Determine

More information

Pebble Project Surface Water Quality Program Streams, Seeps, and Ponds

Pebble Project Surface Water Quality Program Streams, Seeps, and Ponds Day1_1445_Surface Water Quality_PLP_McCay.mp3 Pebble Project Surface Water Quality Program Streams, Seeps, and Ponds Mark Stelljes SLR International February 1, 2012 Outline Stream Program Overview Results

More information

Industrial Stormwater

Industrial Stormwater Industrial Stormwater 2017 Multi-Sector General Permit OKR05 for Stormwater Discharges from Industrial Activity Ismat Esrar, P.E. Municipal Discharge & Stormwater Permitting Water Quality Division Department

More information

UNDERSTANDING YOUR FACILITY S STORMWATER POLLUTION PREVENTION PLAN

UNDERSTANDING YOUR FACILITY S STORMWATER POLLUTION PREVENTION PLAN UNDERSTANDING YOUR FACILITY S STORMWATER POLLUTION PREVENTION PLAN This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation. Featured are: INTRODUCTION: A brief description

More information

SPECIFICATION NO.1197S Addendum No.4 Attachment D. Appendix L- Ground Water Quality Data and Revised Construction Groundwater Discharge Plan

SPECIFICATION NO.1197S Addendum No.4 Attachment D. Appendix L- Ground Water Quality Data and Revised Construction Groundwater Discharge Plan SPECIFICATION NO.1197S Addendum No.4 Attachment D Appendix L- Ground Water Quality Data and Revised Construction Groundwater Discharge Plan Page 1 of 2 Specification No. 1197S Addendum No. 4 ATTACHMENT

More information

Industrial Storm Water Permitting in Ohio. The New Multi-sector General Permit (MSGP) September 2011

Industrial Storm Water Permitting in Ohio. The New Multi-sector General Permit (MSGP) September 2011 Industrial Storm Water Permitting in Ohio The New Multi-sector General Permit (MSGP) September 2011 Background Storm water discharges associated with industrial activity and larger construction sites are

More information

As a reminder, continued participation in the Ecology Lab Accreditation Program requires the lab to:

As a reminder, continued participation in the Ecology Lab Accreditation Program requires the lab to: April 9, 2015 Ms. Elisa Nguyen Energy Northwest Environmental Services Lab 350 Hills Street Suite 107 Richland,WA 99354 Dear Ms. Nguyen: Thank you for your application for renewal in the Environmental

More information

Home Remodeling Projects

Home Remodeling Projects Should your project require a Standard Urban Stormwater Mitigation Plan (SUSMP), please see the City of Pomona s Standard Urban Stormwater Mitigation Plan (SUSMP) Pamphlet Best Management Practices For

More information

As a reminder, continued participation in the Ecology Lab Accreditation Program requires the lab to:

As a reminder, continued participation in the Ecology Lab Accreditation Program requires the lab to: April 11, 2017 Mr. Brad Barfuss 350 Hills Street Suite 107 Richland, WA 99354 Dear Mr. Barfuss: Thank you for your application for renewal in the Environmental Laboratory Accreditation Program. Enclosed

More information

Water Quality Permitting Program Monitoring Matrix 1,2,3

Water Quality Permitting Program Monitoring Matrix 1,2,3 State of Oregon Department of Environmental Quality Water Quality Permitting Program Monitoring Matrix 1,2,3 ITEM OR PARAMETER Total Flow (influent and/or effluent) 4 Flow Meter Calibration 5 (influent

More information

b. Equipment cleaning and maintenance (including vehicle and equipment rehabilitation, mechanical repairs, painting, fueling, and lubrication).

b. Equipment cleaning and maintenance (including vehicle and equipment rehabilitation, mechanical repairs, painting, fueling, and lubrication). Page 1 of 7 PART VII. SECTOR-SPECIFIC REQUIREMENTS The Permittee shall comply with Part VII (sector-specific requirements) for any primary SIC code and/or narrative activity and co-located industrial activities

More information

Industrial Storm Water Permits. Summit County Safety Council Meeting Nov 15, 2018

Industrial Storm Water Permits. Summit County Safety Council Meeting Nov 15, 2018 Industrial Storm Water Permits Summit County Safety Council Meeting Nov 15, 2018 Why regulate storm water runoff? It can wash pollutants off your site! Storm sewers drain to surface waters How Ohio EPA

More information

Appendix O Example Industrial SWPPP Template

Appendix O Example Industrial SWPPP Template Appendix O Example Industrial SWPPP Template Arizona Department of Environmental Quality Multi-Sector General Permit Stormwater Pollution Prevention Plan (SWPPP) Template Introduction To help you develop

More information

LAKE FORK OF THE GUNNISON RIVER WATERSHED: WATER QUALITY DATA ANALYSIS AND SUMMARY

LAKE FORK OF THE GUNNISON RIVER WATERSHED: WATER QUALITY DATA ANALYSIS AND SUMMARY LAKE FORK OF THE GUNNISON RIVER WATERSHED: WATER QUALITY DATA ANALYSIS AND SUMMARY By: Ashley Bembenek July 21, 2011 Lake Fork Watershed 3 sub-watersheds Upper Lake Fork (ULF) Henson Creek (HC) Lower Lake

More information

MECON LIMITED RANCHI , INDIA

MECON LIMITED RANCHI , INDIA ORISSA MINING CORPORATION LIMITED BANGUR CHROMITE MINING PROJECT POST CLEARANCE ENVIRONMENTAL MONITORING REPORT FOR THE MONTH OF SEPTEMBER 2011 MECON LIMITED RANCHI 834 002, INDIA 11.S2.2011 OCTOBER, 2011

More information

5.0 LOS ANGELES RIVER WATERSHED MANAGEMENT AREA

5.0 LOS ANGELES RIVER WATERSHED MANAGEMENT AREA 5.0 LOS ANGELES RIVER WATERSHED MANAGEMENT AREA 5.1 Watershed Description 5.1.1 Watershed Land Use, Percent Impervious, and Population The Los Angeles Watershed Management Area has more than half its area

More information

REQUEST FOR QUALIFICATIONS (RFQ) IGP QISP TRAINERS

REQUEST FOR QUALIFICATIONS (RFQ) IGP QISP TRAINERS California Industrial General Permit QISP Training REQUEST FOR QUALIFICATIONS (RFQ) IGP QISP TRAINERS March 25, 2019 Please Submit Responses to: QISP Web Page https://www.casqa.org/resources/qisp-qualification/industrial-general-permit-trainer-record

More information

Appendix M Framework Stormwater Pollution Prevention Plan Prepared by: Idaho Power Company 1221 W Idaho Street Boise, ID 83702

Appendix M Framework Stormwater Pollution Prevention Plan Prepared by: Idaho Power Company 1221 W Idaho Street Boise, ID 83702 Appendix M Framework Stormwater Pollution Prevention Plan Prepared by: Idaho Power Company 1221 W Idaho Street Boise, ID 83702 November 2011 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PURPOSE... 1 3.0

More information

Industrial Storm Water

Industrial Storm Water Industrial Storm Water Annual Group Training San Diego County Office of Education - Educational Facility Solutions Group October 17, 2018 Welcome Annika Dorman, CPSWQ, QISP ToR Lana Graves, M.S. D-MAX

More information

CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES

CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES Nova Scotia Environment and Labour CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES Approval Date: October 24, 1997 Effective Date: October 24, 1997 Approved By: Peter Underwood Version Control:

More information

Mark Kelly, PE Industrial Waste Engineer July 25, 2013

Mark Kelly, PE Industrial Waste Engineer July 25, 2013 Mark Kelly, PE Industrial Waste Engineer July 25, 2013 What is The Sewer Use and Wastewater Control Ordinance? Sets requirements for sanitary sewer users Regulates the discharge of pollutants into the

More information

Date Application Signed: Principal Executive Officer / Owner Signature FOR OFFICIAL USE ONLY

Date Application Signed: Principal Executive Officer / Owner Signature FOR OFFICIAL USE ONLY FORM A (Revision May 2010) (Rules 4, 6) THE WATER POLLUTION RULES 2001 (as amended) THE ENVIRONMENTAL MANAGEMENT ACT CHAPTER 35:05 APPLICATION FOR SOURCE REGISTRATION GENERAL INSTRUCTIONS: Three (3) copies

More information

W12A Landfill Groundwater, Leachate, Water Well, Landfill Gas and Surface Water Quality Monitoring Program

W12A Landfill Groundwater, Leachate, Water Well, Landfill Gas and Surface Water Quality Monitoring Program W12A Landfill Groundwater, Leachate, Water Well, Landfill Gas and Surface Water Quality Monitoring Program The groundwater, leachate, water well, landfill gas and surface water monitoring programs are

More information

FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES

FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES 1. COVERAGE UNDER THIS GENERAL PERMIT Area of Coverage: This permit covers all areas of the Commonwealth

More information

Public Notice. Issuance of Industrial Waste Discharge Permit

Public Notice. Issuance of Industrial Waste Discharge Permit Public Notice Issuance of Industrial Waste Discharge Permit LASA s regulations [ 60-16 (I)(1)] require public notification of the issuance of Industrial Waste Discharge Permits. LASA publishes this notice

More information

No violations were noted at the time of the inspection. Please refer to the attached inspection report for any comments.

No violations were noted at the time of the inspection. Please refer to the attached inspection report for any comments. April 25, 2016 Mary Emily Slate, Vice President Nucor Steel P.O. Box 30 Armorel, AR 72310 RE: Nucor Steel/Hickman Hill Inspection AFIN: 47-00233 Permit No.: AR0045977 Dear Ms. Slate: On March 29, 2016,

More information

Butte Highlands Joint Venture Mine Design, Operations, and Closure Conference Mine Water Treatment Short Course

Butte Highlands Joint Venture Mine Design, Operations, and Closure Conference Mine Water Treatment Short Course Butte Highlands Joint Venture Mine Design, Operations, and Closure Conference Mine Water Treatment Short Course May 3, 2015 Butte Highlands Joint Venture Highland Mining (ISR Capital) ISR Capital a private

More information

Annex 2: National Environmental Quality Standards (Extract from the Gazette of Pakistan applicable to STZ CETP)

Annex 2: National Environmental Quality Standards (Extract from the Gazette of Pakistan applicable to STZ CETP) Annex 2: National Environmental Quality Standards (Extract from the Gazette of Pakistan applicable to STZ CETP) 1290 THE GAZETTE OF PAKISTAN, EXTRA, AUGUST 10, 2000 [PART-II] (1) For Annex, I the following

More information

COMPLYING WITH YOUR INDUSTRIAL PRE-TREATMENT PERMIT INDIANA CHAMBER OF COMMERCE CONFERENCE OCTOBER 24, 2017 PERMIT AGENDA

COMPLYING WITH YOUR INDUSTRIAL PRE-TREATMENT PERMIT INDIANA CHAMBER OF COMMERCE CONFERENCE OCTOBER 24, 2017 PERMIT AGENDA COMPLYING WITH YOUR INDUSTRIAL PRE-TREATMENT PERMIT INDIANA CHAMBER OF COMMERCE CONFERENCE OCTOBER 24, 2017 Erik D. White, PE Michael Golando, Esq COMPLYING WITH YOUR INDUSTRIAL PRE-TREATMENT PERMIT AGENDA

More information

APPENDIX I. LAMPIRAN I - RKL DAN RPL KEGIATAN TERPADU PROYEK PENGEMBANGAN TANGGUH LNG i

APPENDIX I. LAMPIRAN I - RKL DAN RPL KEGIATAN TERPADU PROYEK PENGEMBANGAN TANGGUH LNG i APPENDIX I Table 1 Emission Standards from Flare, Gas Turbine, Boiler, Acid Gas Incinerator and Internal Combustion Engine... 1 Table 2 n-hazardous Waste Incinerator Standard... 3 Table 3 Hazardous Waste

More information

JEFFERSON RIVER METALS TMDL PROJECT. Public Meeting October 14, 2014 Whitehall, MT

JEFFERSON RIVER METALS TMDL PROJECT. Public Meeting October 14, 2014 Whitehall, MT JEFFERSON RIVER METALS TMDL PROJECT Public Meeting October 14, 2014 Whitehall, MT Presentation Outline Jefferson River Metals Project Area TMDL Basics Metals TMDL Development Next Steps Public Comment

More information

II. JURISDICTION AND VENUE

II. JURISDICTION AND VENUE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Requirements (WDRs) For Discharges of Storm Water Associated With Industrial Activities Excluding Construction Activities, State

More information

BMPs: Best Management Practices are water pollution control practices.

BMPs: Best Management Practices are water pollution control practices. 11.30 EROSION AND SEDIMENT CONTROL ENTIRE SPECIFICATION IS AN ADDITION BELOW The Contractor s attention is directed to Section 20, Erosion Control and Highway Planting, Section 7-1.01G, Water Pollution,

More information

Industrial Pretreatment Program Industrial User Guide

Industrial Pretreatment Program Industrial User Guide Industrial Pretreatment Program Industrial User Guide Industrial Pretreatment Program Industrial User Guide Contents Introduction... 1 Federal and Local Regulations... 1 Industrial Waste Discharge Permitting...

More information

Environmental Management System

Environmental Management System Environmental Management System Moreton Bay Research Station (MBRS) Water Management Program 1. Program Scope The Water Management Program incorporates all the water used throughout the Moreton Bay Research

More information

Treatability of Organic and Radioactive Emerging Contaminants in Stormwater Runoff

Treatability of Organic and Radioactive Emerging Contaminants in Stormwater Runoff Treatability of Organic and Radioactive Emerging Contaminants in Stormwater Runoff Robert Pitt, Ph.D., P.E., D.WRE, BCEE, University of Alabama Shirley Clark, Ph.D., P.E., D.WRE, Penn State - Harrisburg

More information

Evaluation of Pollutants in Wastewater Produced from Air Conditioning Cleaning Operations

Evaluation of Pollutants in Wastewater Produced from Air Conditioning Cleaning Operations 2017 APWA NC Stormwater Management Division Conference Greenville, NC Evaluation of Pollutants in Wastewater Produced from Air Conditioning Cleaning Operations City of Durham Public Works Department -

More information

ENVIRONMENTAL GUIDANCE NOTES: ENVIRONMENTAL STANDARDS AND LIMITS

ENVIRONMENTAL GUIDANCE NOTES: ENVIRONMENTAL STANDARDS AND LIMITS ENVIRONMENTAL GUIDANCE NOTES: ENVIRONMENTAL STANDARDS AND LIMITS Disclaimer: The information contained in this communication document is intended solely for the use of guidance cannot be considered as

More information