Storm Sewer Design - Introduction
|
|
- Aubrie Perry
- 5 years ago
- Views:
Transcription
1 Class 4 [1]
2 Storm Sewer Design - Introduction As urban drainage can not be expected to accommodate all rainfall events, the first step in the design procedure is to select an appropriate design storm. Normally the design storm selected will reflect both the costs associated with failure and different levels of protection. EN makes the following recommendations: Design to prevent surcharging, then check the sewer gives adequate flood protection when surcharged. [2]
3 Storm Sewer Design The next step is to collect catchment data. The area contributing should be determined using field surveys and/or contour maps. The basic pipe network should then be produced. This should, as much as is possible, make use of gravity to move flow through the network. The next stage is then to determine PIMP via surveys, maps or aerial photographs. This can then be used to determine the runoff coefficient. [3]
4 Storm Sewer Design Time of Concentration Flow times must now be considered. When a rainfall event begins rainfall does not immediately enter the sewer. The overland flow time is known as time of entry t e. This depends on: Surface Characteristics. System Characteristics Length of flow path. Rainfall Characteristics. Times normally range between 3-6 minutes (Section 4 WP V4) The time of flow (t f ) is the time taken for flow at the point of entry to reach a point X (the design point) in a sewer. The time of concentration t c is the time taken for runoff from the most distant part (in terms of travel time) of the catchment to reach a point X. t c = t e + t f [4]
5 Storm Sewer Design Rational Method Rational Method The rational method forms the basis of sewer design [ EN 752 Part 4]. This method assumes that the catchment is a fully impervious rectangular area (A) subjected to a depth of rain (D) which falls over a given time (t) at a constant intensity (i). Assuming no losses, the volume of rain accumulating on the surface is determined using DxA. Assuming the rainfall is steady and is being drained at the same rate as it is falling, the rate of flow entering the sewer (Q) can be determined using : Q DA t ia [5]
6 Storm Sewer Design Rational Method - Losses However, we know catchments are not 100% impervious & that losses do occur. We can use the runoff coefficient C [see Class 3 notes] to represent this: Q p CiA If we use: Q p Max flow rate (l/s) i Rainfall intensity (mm/h) A Catchment area (ha) This becomes (to correct for mixing units): Q 78CiA p 2. [6]
7 Storm Sewer Design Modified Rational Method The Modified Rational Method Further research with the aim of better understanding the Rainfall-Runoff process led to a modification of the Rational Method. The modification is to divide the runoff coefficient (C) into two parts C = C v C r Where: C v Volumetric runoff coefficient (-) C R Dimensionless routing coefficient (-) [7]
8 Storm Sewer Design MRM Cv & Cr The Modified Rational Method Volumetric runoff coefficient (-) The proportion of rainfall falling on a catchment which appears as runoff. Typical values are For impervious catchments this may be determined using: C v PR PIMP Dimensionless routing coefficient (-) This reflects the rainfall characteristics, catchment shape and the magnitude of the peak runoff. For design purposes, a value of 1.3 is recommended. Q CiA C C ia C p v R V ia [8]
9 Intensity (mm/h) Storm Sewer Design Storm Duration (min) Return Period 5 yr 2 yr 1 yr Remember Shorter Duration Storms Have Higher Intensities [9]
10 Flow Rate Storm Sewer Design Time of Concentration Storm 1 : t < t c Storm 2 : t = t c Storm 3 : t > t c Time Storm 2 : t = t c Storm 3 : t > t c Storm 1 : t < t c t c Time [10]
11 Storm Sewer Design Time of Concentration Due to the IDF relationship, each individual pipe in the network is designed with a different storm duration. The design storm duration should be set to equal the time of concentration. Why? Storm 1 : t < t c A point is not reached where all the catchment is contributing to the flow in the sewer. The event ends before flow from remote parts of the catchment enter the sewer. Storm 3 : t > t c With Storm 3, all the catchment does contribute. However, as the storm duration is greater than t c, the intensity (and therefore the runoff) is reduced. [11]
12 Storm Sewer Design Steps 1 & 2 We now have enough information to formalise the design procedure: 1. Assign a design rainfall return period (T), pipe roughness (k s normally 0.6mm), time of entry (t e ) and volumetric runoff coefficient (C v ). 2. Produce a preliminary layout of sewers, including tentative inlet locations. 1.0 [12]
13 Storm Sewer Design Step 3 3. Mark pipe numbers on the plan. To do this the longest route to the point of discharge is determined. The most distant pipe is numbered 1.000, the second etc. Branches are numbered in a similar way [13]
14 Storm Sewer Design Steps 4 to 6 4. Estimate impervious areas contributing to each pipe. 5. Make a first attempt [i.e. guess] at setting gradients and diameters of each pipe. 6. Calculate pipe-full velocity (V f ) and flow-rate (Q f ). This can be done using the Colebrook-White Equation: v 2 2gS f log10 k s 3.7D 2gS Alternatively hydraulic tables/charts may be used. D 2.51 f D [14]
15 k s = 0.6mm How is this chart used? Say we want to lay a pipe at a gradient of 1:500 which will convey a flow of 600l/s. What diameter will be required and what will the flow velocity be? (~750mm & ~1.25m/s) Hydraulic Chart Pipe Diameter (m) [15]
16 Storm Sewer Design Steps 7 to Calculate the time of concentration. For downstream pipes, compare alternative contributing branches and select the branch resulting in the maximum t c. 8. Obtain a rainfall intensity from IDF curves for t = t c (for design T). 9. Estimate the cumulative contributing impervious area. 10.Calculate Q using the MRM [Slide 8]. [16]
17 Storm Sewer Design Steps 9 & Check Q < Qf and Vmax > vf > Vmin. Vmin is normally specified to avoid sedimentation. This will normally be 1.0 m/s at pipe full condition. With some sewer materials, higher velocities can be a problem (especially old brick type). Further, high velocities can also lead to noise, hydraulic jumps, cavitation and safety problems. All of these issues should be considered carefully when the velocity exceeds ~3.0m/s. 10.Adjust pipe diameter and gradient as necessary (given hydraulic and physical constraints) and return to step 5 for each successive pipe. [17]
18 Example An engineer is required to design pipework which will convey runoff from part of a catchment to a pond. Based on the pipe and rainfall details below, select suitable pipe diameters using the modified rational method. Pipe Network Pipe 1 1ha 6ha Catchment Details Total Catchment Area = 25ha Estimated Impervious Area = 10ha Soil Classification = 0.30 UCWI = 85 t e = 6 minutes Pipe 3 Pipe 2 Main Road Pipe 4 River Floodplain Pipe Slope Length Area (-) (-) (m) (ha) ? ? [18]
19 Depth of Rainfall (mm) Depth of Rainfall (mm) Duration M1 Depth M5 Depth M10 Depth M20 Depth M30 Depth M50 Depth M100 Depth M200 Depth minutes (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) M1 M5 M10 M20 M30 M50 M100 M Event Duration (minutes) M1 M5 M10 M20 M30 M50 M100 M Event Duration (minutes) Rainfall Data For Example [19]
CIE4491 Lecture. Quantifying stormwater flow Rational method
CIE4491 Lecture. Quantifying stormwater flow Rational method 27-5-2014 Marie-claire ten Veldhuis, Watermanagement Department Delft University of Technology Challenge the future Robust method stationary
More informationLearning objectives. Upon successful completion of this lecture, the participants will be able to:
Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to: Describe and perform the required step for designing sewer system networks Outline Design
More informationLearning objectives. Upon successful completion of this lecture, the participants will be able to describe:
Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to describe: The different approaches for estimating peak runoff for urban drainage network
More informationMODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1. Precipitation
Watershed MODULE 1 RUNOFF HYDROGRAPHS WORKSHEET 1 A watershed is an area of land thaaptures rainfall and other precipitation and funnels it to a lake or stream or wetland. The area within the watershed
More informationRETENTION BASIN EXAMPLE
-7 Given: Total Tributary Area = 7.5 ac o Tributary Area within Existing R/W = 5.8 ac o Tributary Area, Impervious, Outside of R/W = 0.0 ac o Tributary Area, Pervious, Outside of R/W = 1.7 ac o Tributary
More informationDRAINAGE & DESIGN OF DRAINAGE SYSTEM
Drainage on Highways DRAINAGE & DESIGN OF DRAINAGE SYSTEM P. R.D. Fernando Chartered Engineer B.Sc.(Hons), M.Eng. C.Eng., MIE(SL) Drainage Requirement of Highway Drainage System Introduction Drainage means
More informationENGN.4010 ENGINEERING CAPSTONE DESIGN Watershed Analysis. CiA
RATIONAL METHOD Q CiA Where: Q = Maximum Rate of Runoff (cfs) C = Runoff Coefficient i = Average Rainfall Intensity (in/hr) A = Drainage Area (in acres) RATIONAL METHOD Assumptions and Limitations: Watershed
More informationStormwater Management Report Bachman Terrace Residential Development
Stormwater Management Report Bachman Terrace Residential Development Project # 160401069 Prepared for: Tega Developments Prepared by: Stantec Consulting Ltd. April 14, 2014 Sign-off Sheet This document
More informationChapter 6. The Empirical version of the Rational Method
Chapter 6 The Empirical version of the Rational Method The Empirical version is named because the parameters it uses (apart from rainfall data) are arbitrary and are generally based on experience or observation
More informationStorm Sewers, Page 2
Storm Sewers storm sewer systems are dendritic systems used to collect and direct stormwater runoff storm sewer systems are integral components of any urban infrastructure curbs, gutters and storm inlets
More informationUse of IDF Curves Design of a roof drainage system
Use of IDF Curves Design of a roof drainage system Your engineering firm is currently planning the construction of a residential apartment building in Davos, Switzerland. Your task is to design the roof
More informationThe Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management
The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management Husam Al-Najar Storm water management : Collection System Design principles The Objectives
More informationSTORM WATER MANAGEMENT REPORT
Silvercreek Junction STORM WATER MANAGEMENT REPORT Howitt Creek at the Silvercreek Parkway Site Guelph, Ontario August, 2008 TSH File 22304A-04 August 19, 2008 STORMWATER MANAGEMENT REPORT Howitt Creek
More informationWASTEWATER & STORM WATER COLLECTION AND REMOVAL
CVE 471 WATER RESOURCES ENGINEERING WASTEWATER & STORM WATER COLLECTION AND REMOVAL Assist. Prof. Dr. Bertuğ Akıntuğ Civil Engineering Program Middle East Technical University Northern Cyprus Campus CVE
More informationDynamic Inundation Mapping for Emergency Planning and Disaster Response
Dynamic Inundation Mapping for Emergency Planning and Disaster Response Ross Gordon, LEED AP October 29, 2008 Presentation Overview Introduce MIKE FLOOD Rice / TMC Case Study Emergency Planning Disaster
More informationFORT COLLINS STORMWATER CRITERIA MANUAL Hydrology Standards (Ch. 5) 1.0 Overview
Chapter 5: Hydrology Standards Contents 1.0 Overview... 1 1.1 Storm Runoff Determination... 1 1.2 Design Storm Frequencies... 1 1.3 Water Quality Storm Provisions... 2 1.4 Design Storm Return Periods...
More informationIntroduction to Storm Sewer Design
A SunCam online continuing education course Introduction to Storm Sewer Design by David F. Carter Introduction Storm sewer systems are vital in collection and conveyance of stormwater from the upstream
More informationWhat is runoff? Runoff. Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream
What is runoff? Runoff Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream 1 COMPONENTS OF Runoff or STREAM FLOW 2 Cont. The types of runoff
More informationA Stormwater Management Plan and Sediment Control Plan are required for all proposed developments within the City of Richmond.
Engineering Page 3-1 3.0 STORM DRAINAGE 3.1 GENERAL Good drainage is vital to flat urban areas such as Lulu Island. It is essential that every storm sewer must be designed accurately minimizing conflicts
More informationExtended Detention Basin Design
Extended Detention Basin Design 1 Extended Detention 2 Ohio Department of Transportation 1 Extended Detention Basin L&D Vol. 2 Section 1117.3 Provides quality and quantity treatment 3 Extended Detention
More informationChapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall
6.0 Introduction This chapter summarizes methodology for determining rainfall and runoff information for the design of stormwater management facilities in the City. The methodology is based on the procedures
More informationDrainage Analysis. Appendix E
Drainage Analysis Appendix E The existing and proposed storm drainage systems have been modeled with Bentley CivilStorm V8 computer modeling software. The peak stormwater discharge was determined for
More informationTECHNICAL BULLETIN. Synthetic Turf Athletic Field Drainage Design Assistance
TECHNICAL BULLETIN Synthetic Turf Athletic Field Drainage Design Assistance The SportsEdge HQ geocomposite strip drain products are engineered specifically for use in synthetic turf athletic field base
More informationAPPENDIX F RATIONAL METHOD
7-F-1 APPENDIX F RATIONAL METHOD 1.0 Introduction One of the most commonly used procedures for calculating peak flows from small drainages less than 200 acres is the Rational Method. This method is most
More informationPre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015
Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Urban Runoff Background How we got here What Problem?? Provenance of the Problem Unified Sizing Criteria What
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment
More informationOverview of NRCS (SCS) TR-20 By Dr. R.M. Ragan
Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan TR-20 is a computer program for the simulation of runoff occurring from a single storm event. The program develops flood hydrographs from runoff and routes
More informationUNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022
[ESS29] UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022 Date: Monday 21 st May 2018 Time: 10:00 13:00 INSTRUCTIONS
More informationWastewater Collection System
WASTEWATER COLLECTION SYSTEM CE 370 1 Wastewater Collection System The function of the collection system is to collect the wastewater from residential, commercial, and industrial areas within the service
More informationAPPENDIX G HYDRAULIC GRADE LINE
Storm Drainage 13-G-1 APPENDIX G HYDRAULIC GRADE LINE 1.0 Introduction The hydraulic grade line is used to aid the designer in determining the acceptability of a proposed or evaluation of an existing storm
More informationWater Resources Management Plan
P L Y M O U T H M I N N E S O T A Appendix D: The developed a to analyze and minimize the impact of existing and future development on the City s natural resources. It is important to the City to have
More information3.3 Acceptable Downstream Conditions
iswm TM Criteria Manual - = Not typically used or able to meet design criterion. 1 = The application and performance of proprietary commercial devices and systems must be provided by the manufacturer and
More informationRunoff Calculations. Time of Concentration (T c or t c ) from one location to another within a watershed. Travel
Runoff Calculations Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Time of Concentration and Travel Time (based on Chapter 3 of TR-55) Time of Concentration (T c ): time required
More informationFlood hazard assessment in the Raval District of Barcelona using a 1D/2D coupled model
9 th International Conference on Urban Drainage Modelling Belgrade 2012 Flood hazard assessment in the Raval District of Barcelona using a 1D/2D coupled model Beniamino Russo, David Suñer, Marc Velasco,
More informationStorm Sewer Design. Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg
Storm Sewer Design Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Major floods are dramatic and water flow routes must be recognized when minor drainage systems fail. These types
More informationwhere, P i = percent imperviousness R = ratio of unconnected impervious area to the total impervious area.
5.2.6 Effect of Unconnected Imervious Area on Curve Numbers Many local drainage olicies are requiring runoff that occurs from certain tyes of imervious land cover (i.e., rooftos, driveways, atios) to be
More informationAPPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS
APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS March 18, 2003 This page left blank intentionally. March 18, 2003 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method
More information2. DEFINITIONS. American Association of State Highway and Transportation Officials.
2. DEFINITIONS 2.010 Definitions [See Amendment 2] In addition to words and terms that may be defined elsewhere in this manual, the following words and terms shall have the meanings defined below: AASHTO:
More informationPART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS
PART 3 - STANDARDS FOR SEWERAGE FACILITIES 3.3 - DESIGN OF STORM SEWERS 3.301 Design of Storm Sewers A. General Information B. Investigations and Surveys C. Special Projects 3.302 Design Criteria for Storm
More informationCVEN 339 Summer 2009 Final Exam. 120 minutes allowed. 36 Students. No curve applied to grades. Median 70.6 Mean 68.7 Std. Dev High 88 Low 24.
CVEN 339 Final Exam 120 minutes allowed 36 Students No curve applied to grades Median 70.6 Mean 68.7 Std. Dev. 13.7 High 88 Low 24.5 Name: CVEN 339 Water Resources Engineering Summer Semester 2009 Dr.
More informationReport. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI
Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,
More informationSTORM WATER REPORT ASPHALT AND CONCRETE PLANTS JINKINSON SIDE ROAD, ASHTON CITY OF OTTAWA, ONTARIO PREPARED FOR:
Civil Geotechnical Structural Environmental Industrial Health & Safety (613) 860-0923 210 Prescott Street P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT ASPHALT AND CONCRETE
More informationRAIN WATER HARVESTING FOR URBAN FLOOD PEAK REDUCTION
RAIN WATER HARVESTING FOR URBAN FLOOD PEAK REDUCTION Dr. A.K.Sarma, IIT Guwahati, India M. D. Baishya, Engineering Student, NERIST, India G. Giraud, Engineering Student, ENGEES, France 2005 INTRODUCTION
More informationAPPENDIX J-3. Orcem Stormwater Management and Treatment Facilities Design Summary
APPENDIX J-3 Orcem Stormwater Management and Treatment Facilities Design Summary Stormwater Management & Treatment Facilities Design Summary INTRODUCTION KPFF Consulting Engineers has compiled this report
More informationReport. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI
Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,
More informationNew Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario
New Retirement Home 6758 & 6766 Rocque Street Orleans, Ontario Site Servicing and Stormwater Management Report By Mohamad Salame, P.Eng. Kamco Technique Ltee. 60 Grand Avenue North Cambridge, Ontario N1S
More informationHY-12 User Manual. Aquaveo. Contents
Y-12 User Manual Aquaveo Contents Overview...2 Watershed Parameters...3 Channel Parameters...3 Storm Drain Parameters...3 Design of new systems...4 Analysis of existing systems...4 Steady flow...4 ydrographic
More informationBridge Deck Drainage
Bridge Deck Drainage Introduction The presence of bridge barriers, curbs, and raised medians impedes the ability of rainfall runoff to drain off of bridge decks into ditch systems, as it does on a typical
More informationSURFACE DRAINAGE SYSTEM FOR ROADS. Components of Surface Drainage System
Lecture Hour-49 UNIT 8 10CV755 HGD SURFACE DRAINAGE SYSTEM FOR ROADS Components of Surface Drainage System The surface water from the roadway and the adjoining land is to be collected and then disposed
More informationAPPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS
ESTIMATING RUNOFF FROM SMALL WATERSHEDS June 2011 THIS PAGE LEFT BLANK INTENTIONALLY. June 2011 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method Values June 2011
More informationBasics of Wastewater Collection System
Basics of Wastewater Collection System PDH: 3.0 Hours 1 OUTLINE Introduction Definition of Terms Types of Collections Systems Types of Sewers Shapes of Sewers Collection System Appurtenances Basic Considerations
More informationIBS Site Drainage: Senior Design Project
IBS Site Drainage: Senior Design Project Len Wright, Ph.D., PE Lecturer, CEAE Wright.Len@gmail.com September 11, 2008 mwsw204i1.ppt/1 OUTLINE Motivation for Stormwater Management Quantity (both onsite,
More informationSTORM WATER REPORT. Proposed Row House Complex Clare and Hilson 566 Hilson Ave. & 148 Clare St. Ottawa, Ontario PREPARED FOR:
Civil Geotechnical Structural Environmental 210 Prescott Street, Unit 1 (613) 860-0923 P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT Proposed Row House Complex Clare and
More informationIntroduction. Keywords: Oil Palm, hydrology, HEC-HMS, HEC-RAS. a * b*
The Effect of Land Changes Towards in Sg. Pandan Perwira Bin Khusairi Rahman 1,a* and Kamarul Azlan bin Mohd Nasir 1,b 1 Faculty of Civil Engineering, Universiti Teknologi Malaysia, Malaysia a * wirakhusairirahman@gmail.com,
More informationENGINEERING STANDARD FOR DRAIN AND SEWER SYSTEMS OUTSIDE BUILDINGS FIRST EDITION NOVEMBER 2013
ENGINEERING STANDARD FOR DRAIN AND SEWER SYSTEMS OUTSIDE BUILDINGS FIRST EDITION NOVEMBER 2013 This Standard is the property of Iranian Ministry of Petroleum. All rights are reserved to the owner. Neither
More information100-yr Design Runoff (cfs) Basin ID 103b A a B B C Totals
PROPOSED DEVELOPMENT The drainage for this site has been designed to be less than the maximum allowable runoff from each basin as stated in the Overall Rigden Farm drainage plan. Table 1 compares the actual
More informationInsights from editing the ARR Urban Book. Peter J Coombes
Insights from editing the ARR Urban Book Peter J Coombes Motivation for revision of ARR Many practices and data in ARR 1987 are outdated More rainfall and streamflow data Improved understanding of climate
More informationBMP Design Aids. w w w. t r a n s p o r t a t i o n. o h i o. g o v. Equations / Programs
BMP Design Aids 1 Equations / Programs Outlet Discharge Equations Hydrograph and Pond Routing Programs USGS StreamStats 2 Ohio Department of Transportation 1 Training Intent Introduction and overview of
More informationHow Much Runoff? Coefficients for Urban land Use in South West WA and a comparison between Rational Method and volumetric runoff coefficients
How Much Runoff? Coefficients for Urban land Use in South West WA and a comparison between Rational Method and volumetric runoff coefficients Written by: Jim Davies (PhD, FIEAust, Member IPWEA, SIA WA
More informationHYDROLOGIC & HYDRAULIC ASPECTS of the Walnut Street Bridge over the Schuylkill River Philadelphia, PA
HYDROLOGIC & HYDRAULIC ASPECTS of the Walnut Street Bridge over the Schuylkill River Philadelphia, PA J. Richard Weggel CAEE201 Lectures 30 April & 2 May 2007 HYDROLOGY (Natural Science) Study of the waters
More informationPrecipitation Surface Cover Topography Soil Properties
Precipitation Surface Cover Topography Soil Properties Intrinsic capacity of rainfall to cause erosion Influenced by Amount, intensity, terminal velocity, drop size and drop size distribution of rain.
More informationAnalysis and Simulation of Drainage Capacity of Urban Pipe Network
Research Journal of Applied Sciences, Engineering and Technology 6(3): 387-392, 2013 ISSN: 2040-7459; e-issn: 2040-7467 Maxwell Scientific Organization, 2013 Submitted: July 17, 2012 Accepted: August 28,
More informationCourse: Wastewater Management
Course: Wastewater Management Prof. M. M. Ghangrekar Questions 1 1. Describe advantages and disadvantages offered by the water carriage system. 2. What are the possible adverse effects when untreated or
More informationSTORM WATER MANAGEMENT USING REMOTE SENSING AND GIS- A CASE STUDY OF SURAT CITY
STORM WATER MANAGEMENT USING REMOTE SENSING AND GIS- A CASE STUDY OF SURAT CITY 1 Ajay Gamit, 2 P. P. Lodha, 3 Indra Prakash and 4 Khalid Mehmood 1 ME (Final), 2 HOD, Civil Department, L. E. College, Morbi
More informationTHE RATIONAL METHOD FREQUENTLY USED, OFTEN MISUSED
THE RATIONAL METHOD FREQUENTLY USED, OFTEN MISUSED Mark Pennington, Engineer, Pattle Delamore Partners Ltd, Tauranga ABSTRACT The Rational Method has been in use in some form or another at least since
More informationStudy on Drainage Capacity by using Modified Rational Method and Storm Water Management Model
Study on Drainage Capacity by using Modified Rational Method and Storm Water Management Model 1 Mi Pale Kyi, 2 Dr. Win Win Zin, 3 U Tin Maung 1 Ph.D Candidate, 2 Professor, 3 Visiting Professor 1, 2, 3
More informationPRELIMINARY DRAINAGE STUDY
PRELIMINARY DRAINAGE STUDY For 34 th & J Residences 3402 J St. San Diego, CA 92102 A.P.N 545-250-08 Prepared By: Kenneth J. Discenza, P.E. Site Design Associates, Inc. 1016 Broadway, Suite A El Cajon,
More informationChapter H. Introduction to Surface Water Hydrology and Drainage for Engineering Purposes
Chapter H. Introduction to Surface Water Hydrology and Drainage for Engineering Purposes As seen in Figure H.1, hydrology is a complex science that deals with the movement of water between various stages
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part 257.82 PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part
More informationRational Method Hydrological Calculations with Excel COURSE CONTENT
Rational Method Hydrological Calculations with Excel Harlan H. Bengtson, PhD, P.E. COURSE CONTENT 1. Introduction Calculation of peak storm water runoff rate from a drainage area is often done with the
More informationHYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR
HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR 1 INTRODUCTION 1.1 Project Description and Location Isabella Ocean Residences is a residential development to be constructed
More informationDetention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges
Detention Pond Design Considering Varying Design Storms Land Development Results in Increased Peak Flow Rates and Runoff Volumes Developed area Robert Pitt Department of Civil, Construction and Environmental
More informationCOOPER STREET, EPPING STORMWATER MANAGEMENT STRATEGY. May Cooper Street Pty Ltd
415-425 COOPER STREET, EPPING STORMWATER MANAGEMENT STRATEGY May 2017 Cooper Street Pty Ltd Disclaimer Dalton Consulting Engineers Pty Ltd This report has been prepared solely for the benefit of Cooper
More informationDrainage Servicing Report - Terms of Reference
Urban Form and Corporate Strategic Development City Planning 7th Floor, Edmonton Tower 10111 104 Avenue NW Edmonton, AB T5J 0J4 edmonton.ca July 2018 1 Introduction: Drainage Servicing Reports Drainage
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or
More informationSTORM WATER REPORT ASPHALT AND CONCRETE PLANTS 891 JINKINSON SIDE ROAD, ASHTON CITY OF OTTAWA, ONTARIO PREPARED FOR:
Civil Geotechnical Structural Environmental 210 Prescott Street, Unit 1 (613) 860-0923 P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT ASPHALT AND CONCRETE PLANTS 891 JINKINSON
More informationWater supply components
Water supply components Water sources structures (Dams, wells, reservoirs) Surface water Groundewater Pipelines from source Water treatment plant components Pumping stations Storage (elevated tanks) Distribution
More informationDunpar Developments Inc.
Dunpar Developments Inc. Proposed Townhouse Development 2158, 2168, 2180 and 2192 Trafalgar Road Oakville, Ontario Functional Servicing and Stormwater Management Report (in Support of a Re-Zoning and Site
More informationSECTION 6 STORMWATER AND LAND DRAINAGE
SECTION 6 STORMWATER AND LAND DRAINAGE Final Version, Approved September 2003 Section 6 and Land Drainage Contents 6.1 PERFORMANCE STANDARDS... 2 6.1.1 General... 2 6.2 MEANS OF COMPLIANCE... 3 6.2.1 General...
More informationLearn how to design inlet grates, detention basins, channels, and riprap using the FHWA Hydraulic Toolbox and WMS
v. 11.0 WMS 11.0 Tutorial Learn how to design inlet grates, detention basins, channels, and riprap using the FHWA Hydraulic Toolbox and WMS Objectives Learn how to use several Hydraulic Toolbox calculators
More informationLAKE COUNTY HYDROLOGY DESIGN STANDARDS
LAKE COUNTY HYDROLOGY DESIGN STANDARDS Lake County Department of Public Works Water Resources Division 255 N. Forbes Street Lakeport, CA 95453 (707)263-2341 Adopted June 22, 1999 These Standards provide
More informationDICKINSON BAYOU WATERSHED STEERING COMMITTEE FINAL MEMBER CRITERIA COMPARISON
DICKINSON BAYOU WATERSHED STEERING COMMITTEE FINAL MEMBER CRITERIA COMPARISON May 25, 2006 INTRODUCTION The Dickinson Bayou Watershed covers approximately 95.5 square miles and stretches from western Brazoria
More informationTABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SPECIFICATIONS AND SCOPE 105.1
TABLE OF CONTENTS PART III - MINIMUM DESIGN STANDARDS Section 105 DRAINAGE SYSTEM DESIGN SECTION TITLE PAGE 105.1. SPECIFICATIONS AND SCOPE 105.1 105.2. METHODS OF ANALYSIS 105.1 105.2.1. Rational Method
More informationThe SuDS Manual Frequently asked questions
The SuDS Manual Frequently asked questions 1. Is source control still a requirement of the new SuDS Manual? Yes. Source control components are fundamental elements of a SuDS scheme. The benefits of source
More informationHERPIC County Storm Drainage Manual
HERPIC County Storm Drainage Manual C h r is t o p h e r B. B u r k e Research Assistant Highway Extension and Research Project for Indiana Counties Purdue University The HERPIC (Highway Extension and
More informationRiver Channel Characteristics
River Channel Characteristics Storages and Transfers in Drainage Basins Precipitation Evapotranspiration SURFACE STORAGE INTERCEPTION STORAGE CHANNEL STORAGE Soil Moisture Storage Aeration Zone Storage
More informationPRELIMINARY MUNICIPAL SERVICING REPORT NORTHWOODS SUBDIVISION. Prepared for: North Grassie Properties Inc.
PRELIMINARY MUNICIPAL SERVICING REPORT SUBDIVISION Prepared for: North Grassie Properties Inc. Prepared by: Stantec Consulting Ltd. 905 Waverley St. Winnipeg, MB R3T 5P4 July 2012 File: 116808030 SUBDIVISION
More informationPART A4 STORM DRAINAGE SYSTEM
PART A4 STORM DRAINAGE SYSTEM DECEMBER 2015 PART A4 - STORM DRAINAGE SYSTEM Page 1 1 GENERAL... 2 2 DEFINITIONS... 2 3 SUBMISSIONS AND APPROVALS... 2 MASTER DRAINAGE PLAN... 2 SITE DRAINAGE PLAN... 3 4
More informationFLOW REGULATING SYSTEM USING WEIR AND ORIFICE IN A MANHOLE
FLOW REGULATING SYSTEM USING WEIR AND ORIFICE IN A MANHOLE Masahiro Maeda and Makoto Akiba * Metropolitan Tokyo Sewage Bureau, Chubu Construction Office Kuramae 2-1-8 Taito-ku KEYWORDS Flow Regulating
More informationPRELIMINARY DRAINAGE REPORT FOR THE EDI MASTER PLAN
PRELIMINARY DRAINAGE REPORT FOR THE EDI MASTER PLAN April 5, 2015 Wayne W. Chang, MS, PE 46548 Chang Civil Engineering Hydrology Hydraulics Sedimentation P.O. Box 9496 Rancho Santa Fe, CA 92067 (858) 692-0760
More informationProject Drainage Report
Design Manual Chapter 2 - Stormwater 2A - General Information 2A-4 Project Drainage Report A. Purpose The purpose of the project drainage report is to identify and propose specific solutions to stormwater
More informationDETENTION BASIN DESIGN USING RATIONAL HYDROGRAPHS
DETENTION BASIN DESIGN USING RATIONAL HYDROGRAPHS By Thomas F. Smith, P.E., P.L.S. Bercek and Smith Engineering, Inc. www.bercekandsmith.com tfsmith2@bercekandsmith.com 1 Topics Covered: 2 1 Attributed
More informationHydrology for Drainage Design. Design Considerations Use appropriate design tools for the job at hand:
Hydrology for Drainage Design Robert Pitt Department of Civil and Environmental Engineering University of Alabama Tuscaloosa, AL Objectives for Urban Drainage Systems are Varied Ensure personal safety
More informationChapter Introduction. 5.2 Computational Standard Methods HYDROLOGY
Chapter 5. HYDROLOGY 5.1 Introduction The definition of hydrology is the scientific study of water and its properties, distribution, and effects on the earth s surface, in the soil and the atmosphere.
More informationMIDAS CREEK PROJECT. FINAL DESIGN REPORT SKR Hydrotech 4/11/2012
2012 MIDAS CREEK PROJECT FINAL DESIGN REPORT SKR Hydrotech 4/11/2012 Executive Summary... 1 Section 1 Introduction... 1 Background Information... 1 Purpose of Study... 1 Scope of Work... 1 Section 2 Description
More informationDRAINAGE OF IRRIGATED LANDS
CVE 471 WATER RESOURCES ENGINEERING DRAINAGE OF IRRIGATED LANDS Assist. Prof. Dr. Bertuğ Akıntuğ Civil Engineering Program Middle East Technical University Northern Cyprus Campus CVE 471 Water Resources
More informationTable of Contents. Overview... 1
Chapter 3 Chapter 3 Table of Contents Overview... 1 Rainfall... 2 3-2-1 Rainfall Depths and Intensities... 2 3-2-2 Design Storm Distribution for Colorado Urban Hydrograph Procedure (CUHP)... 5 3-2-3 Temporal
More informationIntroduction to Urban Drainage. Scott Arthur. Civil Engineering at the School of the Built Environment. [Class 1 - Into+ 1]
Introduction to Urban Drainage Scott Arthur s.arthur@hw.ac.uk Civil Engineering at the School of the Built Environment [Class 1 - Into+ 1] Do we even need a drainage system? [Class 1 - Into+ 2] Greenfield
More informationFAST WATER / SLOW WATER AN EVALUATION OF ESTIMATING TIME FOR STORMWATER RUNOFF
FAST WATER / SLOW WATER AN EVALUATION OF ESTIMATING TIME FOR STORMWATER RUNOFF Factors Affecting Stormwater Runoff: Rainfall intensity % Impervious surfaces Watershed size Slope Soil type, soil compaction
More informationTechnical Memorandum
Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum To: Kathy Arnold From: Greg Hemmen, P.E. Company: Rosemont Copper Company Date:
More information