Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS

Size: px
Start display at page:

Download "Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS"

Transcription

1 Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Lagan Cement Ltd. IPPC Licence Application

2 Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Air Contents F.2.0 Air Emissions.3 Water F.2.1 Introduction... 4 F.2.2 Major emission point (SW1) OS E, N... 4 F.2.3 Minor emission point (SW2) OS E, N... 7 Attachment N o F.2 Page 2 of 7

3 AIR F.2.0 Air Emissions All sampling points will remain as currently in place and as specified in Schedule B(1) of IPPC Licence Register No P There will be no additional emission points as a result of this proposal. The main potential impacts on air quality associated with the existing activities at the site relate to emissions of dust and combustion gases such as SO 2 (sulphur dioxide), NO 2 (nitrogen dioxide) and CO (carbon monoxide). These emissions are currently being monitored as part of the ongoing monitoring programme at the site. In addition, HCl, HF, Heavy Metals and Dioxins and Furans are also measured in the emission stream from the main stack as part of the monitoring requirements. The operation of the plant using the proposed alternative fuels will not lead to the discharge of any additional emissions from the main stack into the atmosphere. All current emissions monitoring will remain in place as required by IPPC Licence Register No P and as discussed in detail in Section 9 of the Planning and Environmental Report. Attachment N o F.2 Page 3 of 7

4 WATER F.2.1 Introduction The main surface water resources in the vicinity of the site are the Kinnegad and Castlejordan Rivers. The Lagan Cement Ltd site lies entirely within the catchment of the Kinnegad River, which forms the northern boundary of part of the site, just north of the shale quarry. The source of the Kinnegad River is located west of the site and the surface water divide between the catchments of the Kinnegad and Castlejordan Rivers lies to the south of the site. The existing cement works and quarry facility is licenced by the EPA and a number of conditions in the IPPC Licence define monitoring requirements for the Operational Phase of the development. The existing ongoing monitoring programme was implemented for the duration of the construction phase of the project and is continuing since cement production commenced. The proposed addition of two new alternative fuels to the fuel list at the facility will also be regulated under the terms of the IPPC Licence. There will be no impacts on the surface water and groundwater at the site as a result of this proposal and there are no proposed changes to the surface water and groundwater management regime at the site. This section outlines the existing operational drainage system and control systems to handle the water discharge at the emission points SW1 and SW2. F.2.2 Major emission point (SW1) OS E, N The major emission point at SW1 comprises all pumped groundwater from the limestone and shale quarry and surface run-off, including treated effluent from the works pond and runoff from the surrounding areas. The water is discharged in the Kinnegad River via an oil trap and the settlement lagoons. The details of abatement/treatments systems, quarry sumps and ongoing monitoring programme are presented below. Surface Water Collection and Handling There are three main sumps used for water management at the site. The terrace sump, which manages surface water run-off in the plant area, the shale quarry sump and the limestone quarry sump which manage groundwater pumped from the two quarries. A flow chart for the storm water and groundwater management at the facility is presented in Appendix I of this report. The terrace sump is located at the northern end of the raw materials reception and handling compound and has a maximum discharge rate of 200m 3 /hr which is controlled by means of a float switch. The 35 x 40 x 3m sump is formed at a low level to avoid two-stage pumping and water from here is pumped via two 160mm pipes to an inlet chamber from where it is gravity fed into the balancing pond. Water is pumped on an as-required basis using a level controlled submersible pump capable of handling inflows in excess of Attachment N o F.2 Page 4 of 7

5 700l/sec. The sole function of the terrace sump is to pump stormwater from the surface water drains in the main plant yard area and therefore this sump only functions during rainfall. Waters from the balancing pond are gravity fed into the pre-settlement lagoon from where they are fed onto the main settlement lagoon again under gravity. The limestone quarry sump has a maximum discharge rate of 138m 3 /hr, which is controlled by means of a float switch. Water is pumped from the limestone quarry sump on an intermittent basis as required. The limestone quarry sump discharge is pumped to the inlet chamber from where it is gravity fed to the balancing pond. From here it is directed to the pre-settlement lagoon and then onto the settlement lagoon. The shale quarry sump has a maximum discharge rate of 45m 3 /hr and is controlled by means of a float switch. Water is pumped from the shale quarry into a purpose built drain and then flows by gravity into the pre-settlement lagoon and on into the settlement lagoon. Water may be directed to the balancing pond from the shale quarry sump if flow rates from the balancing pond to the settlement lagoons would exceed those which can permit settlement of suspended solids in the settlement lagoons. Surface Water Treatment The balancing pond and the settlement lagoons are the main features of the surface water management system at the site. Balancing Pond The balancing pond receives all water pumped from the terrace sump and the limestone quarry sump and can receive water from the shale quarry sump if and when required. The balancing pond measures 170 x 110 x 4m deep and is designed to accept excess run-off from storm conditions up to a 20 year return storm. The volume of the balancing pond is approximately 35,000m 3 and the top water level is 85.5mAOD and the invert of the discharge pipe is at 82.25mAOD. To be able to function at times of high rainfall, it is necessary for the pond water level generally to be low. The discharge from the balancing pond is regulated by a 52mm diameter throttle plate attached to the outflow pipe. Oil traps are installed to intercept any potential on-site spillage of hydrocarbons. The water from the balancing pond flows under gravity to the pre settlement lagoon in a 225mm drainpipe. Water from the balancing pond flows at a rate not exceeding 109m³/hr (for the 20 year storm) and at a mean discharge rate of 75m³/hr (for the same storm). This ensures that excess water during storms can be regulated in discharge to the settlement lagoons whilst these lagoons are still receiving some pumped ground water. Settlement Lagoons Attachment N o F.2 Page 5 of 7

6 The settlement lagoons are located just north of the shale quarry and discharge into the Kinnegad River at the emission point SW1. The volume of the presettlement lagoon and the settlement lagoon is 35,000m 3 and 70,000m 3 respectively. The settlement lagoons receive water pumped directly from the sumps of the two quarries and from the balancing pond. The maximum permitted discharge rate from the settlement lagoons to the Kinnegad River is 260m³/hr or 6150m³/d (71 l/s). The design residence time in the settlement lagoons is 28 hrs. The final discharge to SW1 is via a pipe from the overflow weir. An oil interceptor is installed to remove oils and hydrocarbons from all inflow. The minimum daily discharge to the Kinnegad River will be solely that from groundwater pumping during periods of drought viz 3,520m 3 /d (after 38 years). The routings of surface water run-off either via the works sumps, balancing pond and settlement lagoons or via the quarry sumps and the settlement lagoons are such that it is most unlikely that significant increases in discharge will arrive at SW1 until 48 hours after a heavy end-of-drought rainfall. After prolonged drought it is likely that the quarry sumps receiving surface water run-off would be low having been used to provide water for dust suppression. Hence, increased discharges into the Kinnegad River, following heavy rainfall, should correspond to a parallel increase in river flow. The maximum controlled rate of discharge of both surface water and pumped groundwater is 6150m³/d. The mean surface water and pumped groundwater flow will be 5,040m3/d (after 38 years). Mean discharges will normally occur during normal periods of rainfall and not during droughts. Flow from the settlement lagoons to the Kinnegad River (emission point SW1) are continuously monitored and when this exceeds 256m³/hr water from one or both of the quarries, is switched automatically to feed into the balancing pond. For storms beyond the 20 year return period water would be allowed to rise in one or both of the quarries. Therefore, the outlet from the settlement lagoon acts as a hydrobrake, designed to flood at the balancing pond and the settlement lagoons in the event that storm flow and pump rates from the quarries exceed the discharge limit. Surface Water Monitoring The water at the emission point SW1 is sampled with a flow proportional sampler with 24-hour composite samples being collected. An automatic ph sensor is also installed at the emission point. The ph of the discharge water should always lie in the range 6 to 9. Daily samples are also tested for suspended solids. Discharge BOD is recorded weekly. Mineral Oil presence is checked visually on a daily basis and oils, fats and greases are recorded monthly as required by the terms and conditions of the IPPC Licence. If (as is considered unlikely) dirty water discharges above the limit of 35mg/l, an automatic diversion system for flow through the attenuation pond will be installed. This will be triggered by means of a calibrated photocell control. Attachment N o F.2 Page 6 of 7

7 F.2.3 Minor emission point (SW2) OS E, N The minor emission point at SW2 comprises surface water runoff from fields and permanent seeded/planted screening banks from the southwestern part of the site. Runoff from the screening banks is collected in perimeter ditches and routed to a combined silt/oil trap facility. A controlled flow of 7l/s discharges into the westerly flowing ditch via the minor emission SW2. Storm attenuation area The area lying east of the silt and oil interceptor is allowed to flood to a maximum depth of 0.8m over a maximum area of 88 x 176m in order to attenuate storm flow. Bunding was installed around the perimeter of the plant area as a flood prevention measure. The discharge at SW2 will not exceed 600m³/d and will be c 100m³/d for mean surface water run-off. Operational and monitoring arrangements The surface water emitted at SW2 does not comprise any process effluent or runoff from working or quarry areas. The emitted water only comprises runoff generated from greenfield and woodland. No abatement /control systems is therefore required for this emission point. However, as a matter of precaution a silt/oil trap was installed upstream from the emission point. The discharge at this emission point is usually at a very slow rate with a near static water at many of the ditches connected to the outflow for the site. Attachment N o F.2 Page 7 of 7

Attachment N o F Control & Monitoring

Attachment N o F Control & Monitoring Attachment N o F Control & Monitoring Attachment F1: Treatment, Abatement and Control Systems Air There is no treatment or abatement systems required for the minor air emission points or the potential

More information

Inflow pipe. Drain. Drain

Inflow pipe. Drain. Drain Inflow pipe Screened overflow Drain Foul flush diverter Screened intake Manhole cover Maximum water level Seal Inspection cover Possible local drainage through screen Drain Bottom sloped Screened outlet

More information

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description. 7. WATER: HYDROGEOLOGY & HYDROLOGY 7.1 Introduction This chapter of the EIAR comprises of an assessment of the likely impact of the proposed development on the surrounding surface water and hydrogeological

More information

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022 [ESS29] UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2017/2018 URBAN DRAINAGE SYSTEMS MODULE NO: BLT4022 Date: Monday 21 st May 2018 Time: 10:00 13:00 INSTRUCTIONS

More information

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT THE GOVERNMENT OF MALAYSIA PRIME MINISTER S DEPARTMENT ECONOMIC PLANNING UNIT THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT VOL. 5: TECHNICAL

More information

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information

INFRASTRUCTURE & OPERATION

INFRASTRUCTURE & OPERATION SECTION C: INFRASTRUCTURE & OPERATION Advice on completing this section is provided in the accompanying Guidance Note. C.1 Operational Information Requirements Provide a description of the plant, process

More information

CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY

CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY Project #08223 CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY PREPARED FOR: City of Crystal Lake 100 West Woodstock Street Crystal Lake, Illinois 60014 FEBRUARY 11, 2009 26575 W. COMMERCE DRIVE, SUITE 601,

More information

Separators. A Range of Fuel/Oil Separators for Peace of Mind.

Separators. A Range of Fuel/Oil Separators for Peace of Mind. s A Range of Fuel/Oil s for Peace of Mind www.klargester.com Introduction Surface water drains normally discharge to a watercourse or indirectly into underground waters (groundwater) via a soakaway. Contamination

More information

ATTACHMENT E.2 EMISSIONS TO SURFACE WATERS SITE SERVICES LAYOUT SHEET 1 OF 2 (IE DR-0021)

ATTACHMENT E.2 EMISSIONS TO SURFACE WATERS SITE SERVICES LAYOUT SHEET 1 OF 2 (IE DR-0021) ATTACHMENT E.2 EMISSIONS TO SURFACE WATERS SITE SERVICES LAYOUT SHEET 1 OF 2 (IE0310818-30-DR-0021) SITE SERVICES LAYOUT SHEET 2 OF 2 (IE0310818-30-DR-0022) LOCATION OF EMISSION TO SURFACE WATER (IE0310818-22-DR-

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

CONSTRUCTION SPECIFICATION FOR DEWATERING

CONSTRUCTION SPECIFICATION FOR DEWATERING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 517 NOVEMBER 2016 CONSTRUCTION SPECIFICATION FOR DEWATERING TABLE OF CONTENTS 517.01 SCOPE 517.02 REFERENCES 517.03 DEFINITIONS 517.04 DESIGN

More information

Attachment 12 Stage 1 Flood Risk Assessment (IE RP-0001)

Attachment 12 Stage 1 Flood Risk Assessment (IE RP-0001) IE0311133-22-RP-0001, Issue A 17/10/2013 Attachment 12 Stage 1 Flood Risk Assessment (IE0311133-30-RP-0001) IE0311133-22-RP-0001_A_02.DOC Flood Risk Assessment Celebrating 40 Years in Business Jazz Pharmaceuticals

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

ATTACHMENT N o A1: NON-TECHNICAL SUMMARY

ATTACHMENT N o A1: NON-TECHNICAL SUMMARY ATTACHMENT N o A1: NON-TECHNICAL SUMMARY A1 INTRODUCTION Dairygold AgriBusiness Ltd is making an application to the Environmental Protection Agency for an Industrial Emissions Licence which relates to

More information

13. High Rate Filtration Process

13. High Rate Filtration Process 13.High Rate Filtration Process N. Horie 1, M.Kabata 2, K.Sano 3, S.Kanamori 4 Director, Chief Researcher,Senior Researcher 3, Researcher 4 First Research Department Japan Institute of Wastewater Engineering

More information

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications Environmental Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications Sustainable, Reliable, Affordable Stormwater Attenuation Systems Sustainable Drainage

More information

EPA Waste Water Discharge Licence Application

EPA Waste Water Discharge Licence Application Duleek Waste Water Treatment Works EPA Waste Water Discharge Licence Application ARTICLE 16 COMPLIANCE REQUIREMENTS Meath County Council EPA Document Ref: D0133-01 Section A: Non-Technical Summary Update

More information

Community SHEC Report. Kooragang Island March 2015

Community SHEC Report. Kooragang Island March 2015 Community SHEC Report Kooragang Island March 2015 TABLE OF CONTENTS 1 Introduction 2 2 Safety and Environmental Reporting 2 2.1 February 2015 Environmental Performance 2 3 Environmental Improvements 5

More information

Georgia Power Plant Bowen NPDES Permit No. GA Ash Pond Dewatering Plan. Revised December 2017

Georgia Power Plant Bowen NPDES Permit No. GA Ash Pond Dewatering Plan. Revised December 2017 Georgia Power Plant Bowen NPDES Permit No. GA0001449 Revised December 2017 Purpose This (Plan) describes the additional procedures, safeguards and enhanced wastewater treatment measures that Georgia Power

More information

TechNews. Part 2: Creative Solutions to Secondary Containment at Electrical Substations December 2018

TechNews. Part 2: Creative Solutions to Secondary Containment at Electrical Substations December 2018 TechNews Part 2: Creative Solutions to Secondary Containment at Electrical Substations December 2018 Wastewater storage tanks and oil/water separators may be used as part of an electric power facility

More information

Flood Risk Assessment. for. Proposed Residential Development at Bentletts Scrap Yard Claygate Road Collier Street Kent

Flood Risk Assessment. for. Proposed Residential Development at Bentletts Scrap Yard Claygate Road Collier Street Kent Flood Risk Assessment for Proposed Residential Development at Bentletts Scrap Yard Claygate Road Collier Street Kent 1129-1008 February 2016 RCD Consultants Ltd Proposed Residential Development Bentletts

More information

2.0 SITE LOCATION AND CONTEXT

2.0 SITE LOCATION AND CONTEXT 2.0 SITE LOCATION AND CONTEXT 2.1 SITE LOCATION The Lagan Cement Plant is located in the south-western corner of County Meath adjacent to the County Westmeath border (see Figure 2.1). The cement plant

More information

Notes on Monitoring Data

Notes on Monitoring Data Incitec Pivot Limited Environment Protection Licence: 1181 39 Heron Road, Kooragang Island, NSW Date Data Published: 22 January 215. Date Sampled: December 214 Date Sample Results Obtained: 19 January

More information

Notes on Monitoring Data

Notes on Monitoring Data Incitec Pivot Limited Environment Protection Licence: 11781 Heron Road, Kooragang Island, NSW Date Data Published: October 2014. Date Sampled: August 2014 Date Sample Results Obtained: 24 September 2014.

More information

Oversized quarry sumps can be used to store run-off during

Oversized quarry sumps can be used to store run-off during Oversized quarry sumps can be used to store run-off during large events Paved quarry yard with channels routing run-off to attenuation 3 The Hydrogeology of Quarry Dewatering Extraction below the water

More information

Lombard s Storm, Sanitary & Combined Sewers. Unseen Networks at Work

Lombard s Storm, Sanitary & Combined Sewers. Unseen Networks at Work Lombard s Storm, Sanitary & Combined Sewers Unseen Networks at Work Three Types of Sewers As an older community dating back to 1869, Lombard still has some sewers that carry sanitary effluent, as well

More information

TOTAL SUSPENDED SOLIDS REMOVAL TEST OF A HIGH DENSITY POLYETHYLENE WATER QUALITY UNIT. By James T. Mailloux Dean K. White

TOTAL SUSPENDED SOLIDS REMOVAL TEST OF A HIGH DENSITY POLYETHYLENE WATER QUALITY UNIT. By James T. Mailloux Dean K. White TOTAL SUSPENDED SOLIDS REMOVAL TEST OF A HIGH DENSITY POLYETHYLENE WATER QUALITY UNIT By James T. Mailloux Dean K. White Submitted to ADVANCED DRAINAGE SYSTEMS 250-04/H1098F September 2004 TOTAL SUSPENDED

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

PLANNING REPORT. For inspection purposes only. MOUNTMELLICK WASTEWATER TREATMENT PLANT PART 8 PROCEDURE

PLANNING REPORT. For inspection purposes only. MOUNTMELLICK WASTEWATER TREATMENT PLANT PART 8 PROCEDURE PLANNING REPORT MOUNTMELLICK WASTEWATER TREATMENT PLANT PART 8 PROCEDURE Donal Kiely Senior Executive Planner John Daly Director of Services Pursuant to Part VIII of the Planning & Development Regulations

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part 257.82 PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R. Part

More information

1 Construction The sewage treatment plant (STP) is to be an Icon-Septech Pty Ltd Turbojet 5000 as described below and as shown on the drawings.

1 Construction The sewage treatment plant (STP) is to be an Icon-Septech Pty Ltd Turbojet 5000 as described below and as shown on the drawings. 1 Construction The sewage treatment plant (STP) is to be an Icon-Septech Pty Ltd Turbojet 5000 as described below and as shown on the drawings. 2 Design Parameters Domestic sewage will be collected from

More information

1 Construction The sewage treatment plant (STP) is to be an Icon-Septech Pty Ltd Turbojet 4000 as described below and as shown on the drawings.

1 Construction The sewage treatment plant (STP) is to be an Icon-Septech Pty Ltd Turbojet 4000 as described below and as shown on the drawings. 1 Construction The sewage treatment plant (STP) is to be an Icon-Septech Pty Ltd Turbojet 4000 as described below and as shown on the drawings. 2 Design Parameters Domestic sewage will be collected from

More information

Chapter 1 Introduction

Chapter 1 Introduction Engineering Hydrology Chapter 1 Introduction 2016-2017 Hydrologic Cycle Hydrologic Cycle Processes Processes Precipitation Atmospheric water Evaporation Infiltration Surface Runoff Land Surface Soil water

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 HUFFAKER ROAD (PLANT HAMMOND) PRIVATE INDUSTRIAL LANDFILL (HUFFAKER ROAD LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion

More information

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1 To: From: The City of Virginia Beach Lewis White and Rachael Johnson on behalf of WSP Date: June 6, 2017 Subject: s Drainage Alternatives Analysis This memorandum represents the summary of findings from

More information

Orica Kooragang Island Community Reference Group Monthly Briefing Paper #15 January 2013

Orica Kooragang Island Community Reference Group Monthly Briefing Paper #15 January 2013 Orica Kooragang Island Community Reference Group Monthly Briefing Paper #15 January 2013 1. Introduction This Briefing Paper focuses on activities and events during the month of December 2012 (with the

More information

San Francisco State University Site 1 Vegetated Infiltration Basin Monitoring Report: Rainy Seasons and

San Francisco State University Site 1 Vegetated Infiltration Basin Monitoring Report: Rainy Seasons and San Francisco State University Site 1 Vegetated Infiltration Basin Monitoring Report: Rainy Seasons 2011-12 and 2012-13 Project Overview San Francisco State University (SFSU) has implemented several green

More information

Controlling runon and runoff:

Controlling runon and runoff: Chapter 8. Surface Water Management This chapter explores: runon and runoff what they are, and the risks associated with them. various management options runon reductions, runoff catchbasins, vegetated

More information

1 Construction The sewage treatment plant (STP) is to be an Icon-Septech Pty Ltd Turbojet 2000 as described below and as shown on the drawings.

1 Construction The sewage treatment plant (STP) is to be an Icon-Septech Pty Ltd Turbojet 2000 as described below and as shown on the drawings. 1 Construction The sewage treatment plant (STP) is to be an Icon-Septech Pty Ltd Turbojet 2000 as described below and as shown on the drawings. 2 Design Parameters Domestic sewage will be collected from

More information

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257 INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 PLANT BOWEN PRIVATE INDUSTRY SOLID WASTE DISPOSAL FACILITY (ASH LANDFILL) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals

More information

TABLE B.3 - STORMWATER BMP POLLUTANT REMOVAL EFFICIENCIES

TABLE B.3 - STORMWATER BMP POLLUTANT REMOVAL EFFICIENCIES BMPS DESCRIPTION p p p p TSS TP Sol P TN Stormwater Ponds**, 8 Stormwater Wetland** and extended detention, and some elements of a shallow marsh equivalent capable of treating the full water quality volume.

More information

VERIFICATION STATEMENT

VERIFICATION STATEMENT Verification Statement Verification Statement Verification Statement VERIFICATION STATEMENT Verifies the performance of Jellyfish Filter JF4-2-1 Developed by Imbrium Systems, Inc., Whitby, Ontario, Canada

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Storm water Catchment Analysis

Storm water Catchment Analysis Storm water Catchment Analysis Analysis index 1. Storm water attenuation tank sizing method 2. Consent notices for storm water attenuation tanks 3. Summary of sub catchments 4. Hydrological Analysis for

More information

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) SMP-11 PLANNING CONSIDERATIONS: Design Life: 1 yr Acreage

More information

Appendix 8.4. Site-wide Drainage Strategy

Appendix 8.4. Site-wide Drainage Strategy Appendix 8.4 Site-wide Drainage Strategy Noble House, Capital Drive, Linford Wood, Milton Keynes MK14 6QP T +44 (0)1908 669898 F +44 (0)1908 669899 E harrisjt@rpsgroup.com W www.rpsgroup.com/design THE

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or

More information

GRADING, EROSION AND SEDIMENTATION CONTROL

GRADING, EROSION AND SEDIMENTATION CONTROL SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,

More information

Stormwater Management Report Bachman Terrace Residential Development

Stormwater Management Report Bachman Terrace Residential Development Stormwater Management Report Bachman Terrace Residential Development Project # 160401069 Prepared for: Tega Developments Prepared by: Stantec Consulting Ltd. April 14, 2014 Sign-off Sheet This document

More information

VERIFICATION STATEMENT

VERIFICATION STATEMENT Verification Statement Verification Statement Verification Statement VERIFICATION STATEMENT GLOBE Performance Solutions Verifies the performance of Stormceptor EF4 and EFO4 Oil-Grit Separators Developed

More information

STORM DRAINAGE CHAPTER 11

STORM DRAINAGE CHAPTER 11 CHAPTER 11 STORM DRAINAGE SECTION 11 GENERAL 11.1 Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. 11.2 Where required. All roofs,

More information

D.G.S.W. Pitakumbura Manager (Groundwater Studies) Groundwater Section NWS&DB. Groundwater recharge or deep drainage or

D.G.S.W. Pitakumbura Manager (Groundwater Studies) Groundwater Section NWS&DB. Groundwater recharge or deep drainage or Groundwater Recharge and Extraction Techniques D.G.S.W. Pitakumbura Manager (Groundwater Studies) Groundwater Section NWS&DB What is Groundwater Recharge Groundwater recharge or deep drainage or deep percolation

More information

Georgia Power Plant McDonough-Atkinson NPDES Permit No. GA Ash Pond Dewatering Plan. Revised May 2018

Georgia Power Plant McDonough-Atkinson NPDES Permit No. GA Ash Pond Dewatering Plan. Revised May 2018 Georgia Power Plant McDonough-Atkinson NPDES Permit No. GA0001431 Revised May 2018 Purpose This updated (Plan) describes the additional procedures, safeguards and enhanced wastewater treatment measures

More information

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS March 18, 2003 This page left blank intentionally. March 18, 2003 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method

More information

Orica Kooragang Island. Community Reference Group. Monthly Briefing Paper #3 January 2012 ISSUED FOR CRG MEETING ON 30 JANUARY 2012

Orica Kooragang Island. Community Reference Group. Monthly Briefing Paper #3 January 2012 ISSUED FOR CRG MEETING ON 30 JANUARY 2012 Orica Kooragang Island Community Reference Group Monthly Briefing Paper #3 January 2012 ISSUED FOR CRG MEETING ON 30 JANUARY 2012 1. Introduction This Briefing Paper focuses on activity and events during

More information

STATE OF NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY DIVISION OF WATER RESOURCES PERMIT TO DISCHARGE WASTEWATER UNDER THE

STATE OF NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY DIVISION OF WATER RESOURCES PERMIT TO DISCHARGE WASTEWATER UNDER THE STATE OF NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY DIVISION OF WATER RESOURCES PERMIT TO DISCHARGE WASTEWATER UNDER THE NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM In compliance with the provision

More information

Water Resources Management Plan

Water Resources Management Plan P L Y M O U T H M I N N E S O T A Appendix D: The developed a to analyze and minimize the impact of existing and future development on the City s natural resources. It is important to the City to have

More information

Learning objectives. Upon successful completion of this lecture, the participants will be able to:

Learning objectives. Upon successful completion of this lecture, the participants will be able to: Solomon Seyoum Learning objectives Upon successful completion of this lecture, the participants will be able to: Describe and perform the required step for designing sewer system networks Outline Design

More information

Ayrburn Farm Development Infrastructure Assessment Report

Ayrburn Farm Development Infrastructure Assessment Report Ayrburn Farm Development Infrastructure Assessment Report 1 EXECUTIVE SUMMARY Further to Clark Fortune McDonald & Associates correspondence dated 12 February 2015 please find below the assessment of foul

More information

Appendix 11. Erosion and Sediment Control Management Plan. Appendix 11

Appendix 11. Erosion and Sediment Control Management Plan. Appendix 11 Appendix 11 Erosion and Sediment Control Management Plan Appendix 11 OTAIKA QUARRY - PROPOSED OVERBURDEN DISPOSAL AREA Application for Land Use Consent and Assessment of Environmental Effects Otaika Quarry

More information

ASH FILTER PONDS INFLOW DESIGN FLOOD CONTROL SYSTEM INITIAL PLAN

ASH FILTER PONDS INFLOW DESIGN FLOOD CONTROL SYSTEM INITIAL PLAN CCR RULE COMPLIANCE ASH FILTER PONDS INFLOW DESIGN FLOOD CONTROL SYSTEM INITIAL PLAN Prepared for: GenOn Northeast Management Company Keystone Generating Station Shelocta, Pennsylvania Prepared by: CB&I

More information

PRESSURE SEWER SYSTEMS: NEW DESIGN INNOVATIONS CAN IMPROVE SYSTEM PERFORMANCE

PRESSURE SEWER SYSTEMS: NEW DESIGN INNOVATIONS CAN IMPROVE SYSTEM PERFORMANCE PRESSURE SEWER SYSTEMS: NEW DESIGN INNOVATIONS CAN IMPROVE SYSTEM PERFORMANCE Graeme Salmon GHD Ltd, New Zealand ABSTRACT An innovative approach to dynamic modelling of pressure sewer systems is outlined.

More information

Action plans for hotspot locations

Action plans for hotspot locations Action plans for hotspot locations Ash Vale North 1. Local evidence indicates the culvert could not discharge during December 2013 because the outlet was blocked on the western side of the railway. Guildford

More information

Table 4.7.2(II) BREF Document on Best Available Techniques on Emissions from Storage, July 2006

Table 4.7.2(II) BREF Document on Best Available Techniques on Emissions from Storage, July 2006 Table 4.7.2(II) BREF Document on Best Available Techniques on Emissions from Storage, July 2006 With respect to the Conclusions on BAT for this horizontal BREF, the details of applicability and status

More information

ROOF AND PROPERTY DRAINAGE

ROOF AND PROPERTY DRAINAGE CHAPTER 4 ROOF AND PROPERTY DRAINAGE 4.1 INTRODUCTION... 4-1 4.2 ROOF DRAINAGE SYSTEM... 4-1 4.3 ROOF DRAINAGE DESIGN PROCEDURE... 4-2 4.3.1 Catchment Area... 4-2 4.3.2 Design Average Recurrence Intervals...

More information

New England Quarry Resource Recovery Centre Landfill Nr Ivybridge, Devon Environmental Permit (EP) Application Surface Water Management Plan

New England Quarry Resource Recovery Centre Landfill Nr Ivybridge, Devon Environmental Permit (EP) Application Surface Water Management Plan New England Quarry Resource Recovery Centre Landfill Nr Ivybridge, Devon Environmental Permit (EP) Application Surface Water Management Plan February 2011 Ref: 402.0036.00463/SWMP Viridor i Ref: 407-0036-00463/SWMP

More information

STORM WATER MANAGEMENT REPORT

STORM WATER MANAGEMENT REPORT Silvercreek Junction STORM WATER MANAGEMENT REPORT Howitt Creek at the Silvercreek Parkway Site Guelph, Ontario August, 2008 TSH File 22304A-04 August 19, 2008 STORMWATER MANAGEMENT REPORT Howitt Creek

More information

Chapter 2: Selecting Best Management Practices (BMPs)

Chapter 2: Selecting Best Management Practices (BMPs) Chapter 2: Selecting Best Management Practices (BMPs) 2.1 - Temporary versus Permanent BMPs The same level of care should be taken to select both temporary BMPs and permanent BMPs. The same level of care

More information

Drainage Servicing Report - Terms of Reference

Drainage Servicing Report - Terms of Reference Urban Form and Corporate Strategic Development City Planning 7th Floor, Edmonton Tower 10111 104 Avenue NW Edmonton, AB T5J 0J4 edmonton.ca July 2018 1 Introduction: Drainage Servicing Reports Drainage

More information

Wastewater Discharge Reduction Plan June 2016

Wastewater Discharge Reduction Plan June 2016 Wastewater Discharge Reduction Plan June 2016 Version 3 1 TABLE OF CONTENTS Our Plan on a Page 3 Section 1 Plan Framework 4 1.1 Background 5 1.2 What s the problem? 6 What causes the problem? 6 What s

More information

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY 405 TWEEDSMUIR AVENUE

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY 405 TWEEDSMUIR AVENUE FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY FOR CITY OF OTTAWA PROJECT NO.: 11-532 FOR TABLE OF CONTENTS 1.0 INTRODUCTION... 1 1.1 Existing Conditions... 2 1.2 Required Permits / Approvals...

More information

Globeville Landing Outfall Surface Water. December 12, 2017 Andrew Ross, Jon Novick Denver Department of Public Health & Environment

Globeville Landing Outfall Surface Water. December 12, 2017 Andrew Ross, Jon Novick Denver Department of Public Health & Environment Globeville Landing Outfall Surface Water December 12, 2017 Andrew Ross, Jon Novick Denver Department of Public Health & Environment Introductions Andrew Ross Environmental Program Manager, DDPHE Jon Novick

More information

ESK TM. Oil/Water Separator with Automatic Shutoff Valve. Our waterways. Our future.

ESK TM. Oil/Water Separator with Automatic Shutoff Valve. Our waterways. Our future. ESK TM Oil/Water Separator with Automatic Shutoff Valve Our waterways. Our future. ESK TM Industrial Site Solution The ESK is a passive high efficiency coalescing separator that removes free oil from contaminated

More information

Elsham Water Treatment Works (WTW) is located approximately 10km east of Scunthorpe in North Lincolnshire

Elsham Water Treatment Works (WTW) is located approximately 10km east of Scunthorpe in North Lincolnshire Elsham WTW upgrade to increase output and improve performance of non-potable WTW to meet forecast industrial growth on the south Humber Bank by Stewart Bell Elsham Water Treatment Works (WTW) is located

More information

D. B. G R A Y E N G I N E E R I N G I N C.

D. B. G R A Y E N G I N E E R I N G I N C. STORMWATER MANAGEMENT REPORT 22 Perkins Street Ottawa, Ontario Report No. 13030-SWM February 6, 2015 D. B. G R A Y E N G I N E E R I N G I N. Stormwater Management - Grading & Drainage - Storm & Sanitary

More information

BAT Guidance Note on Best Available Techniques for the Production of Cement and for the Production of Lime in a Kiln

BAT Guidance Note on Best Available Techniques for the Production of Cement and for the Production of Lime in a Kiln BAT Guidance Note on Best Available Techniques for the Production of Cement and for the Production of Lime in a Kiln (1 st Edition) ENVIRONMENTAL PROTECTION AGENCY An Ghníomhaireacht um Chaomhnú Comhshaoil

More information

14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring

14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring 14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring An effective monitoring program provides results to: indicate whether the facility is working as expected and that the assumptions used in the assessment

More information

MUNICIPALITY OF WEST ELGIN WEST LORNE WASTEWATER TREATMENT PLANT

MUNICIPALITY OF WEST ELGIN WEST LORNE WASTEWATER TREATMENT PLANT MUNICIPALITY OF WEST ELGIN WEST LORNE WASTEWATER TREATMENT PLANT 214 ANNUAL REPORT uary 1 to ember 31, 214 Environmental Compliance Approval # 3-442-9-938 Prepared by: Table of Contents Section 1: Overview...

More information

Date: 12/07/99. FINAL REPORT Micco E Exfiltration Pipe Project Demonstration Project DEP Contract # WM603. Prepared by:

Date: 12/07/99. FINAL REPORT Micco E Exfiltration Pipe Project Demonstration Project DEP Contract # WM603. Prepared by: FINAL REPORT Micco E Exfiltration Pipe Project Demonstration Project DEP Contract # WM603 Prepared by: John C. Royal and Gordon England, P.E. Brevard County Surface Water Improvement Program Building A,

More information

Environmental Assessment Chapter 8 Surface Water

Environmental Assessment Chapter 8 Surface Water Environmental Assessment Chapter 8 Surface Water 8.2.7 Rainfall and Evaporation Based on recorded data for the area of interest, the mean annual rainfall is about 700mm, with maximum monthly rainfalls

More information

STORM WATER REPORT ASPHALT AND CONCRETE PLANTS JINKINSON SIDE ROAD, ASHTON CITY OF OTTAWA, ONTARIO PREPARED FOR:

STORM WATER REPORT ASPHALT AND CONCRETE PLANTS JINKINSON SIDE ROAD, ASHTON CITY OF OTTAWA, ONTARIO PREPARED FOR: Civil Geotechnical Structural Environmental Industrial Health & Safety (613) 860-0923 210 Prescott Street P.O. Box 189 Kemptville, Ontario K0G 1J0 FAX: (613) 258-0475 STORM WATER REPORT ASPHALT AND CONCRETE

More information

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257.81 PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40

More information

STORM DRAINAGE CHAPTER 11

STORM DRAINAGE CHAPTER 11 CHAPTER STORM DRAINAGE SECTION 0 GENERAL 0. Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage, except in one- and two-family dwellings.

More information

Georgia Power Plant McManus NPDES Permit No. GA Ash Pond Dewatering Plan. Revised April 2018

Georgia Power Plant McManus NPDES Permit No. GA Ash Pond Dewatering Plan. Revised April 2018 Georgia Power Plant McManus NPDES Permit No. GA0003794 Revised April 2018 Purpose This (Plan) describes the procedures, safeguards and enhanced wastewater treatment measures that Georgia Power Company

More information

VERIFICATION STATEMENT

VERIFICATION STATEMENT Verification Statement Verification Statement Verification Statement VERIFICATION STATEMENT GLOBE Performance Solutions Verifies the performance of Filterra Bioretention System Distributed and marketed

More information

WESTPORT, CO. MAYO, IRELAND.

WESTPORT, CO. MAYO, IRELAND. - c. ALLERCAN GEE PHARMACEUTICALS IRELAND TELEPHONE: +353-98-25222 TELEFAX: +353-98-25791 WEB SITE: www.allergan.com WESTPORT, CO. MAYO, IRELAND. Office of Climate, Licensing & Resource Use, EPA Headquarters,

More information

City of Gardiner, Maine Wastewater Committee Meeting. CSO Storage Tank & Screening Evaluation

City of Gardiner, Maine Wastewater Committee Meeting. CSO Storage Tank & Screening Evaluation City of Gardiner, Maine Wastewater Committee Meeting CSO Storage Tank & Screening Evaluation December 11, 2013 Introduction - Update on field work - Flow monitoring - Survey - GIS - Borings - Assessment

More information

Preliminary Rainfall Runoff Management for Developments EA/Defra Report Procedure W5-074/A Summary Guidance for Developers and Engineers

Preliminary Rainfall Runoff Management for Developments EA/Defra Report Procedure W5-074/A Summary Guidance for Developers and Engineers Preliminary Rainfall Runoff Management for Developments EA/Defra Report Procedure W5-074/A Summary Guidance for Developers and Engineers 1. Objective of this guidance and Procedure W5-074/A is to assist

More information

1. Overview 2 2. Definitions 2 3. Laboratory Testing Criteria 2. A. Laboratory Qualifications 2. B. Analysis of TSS Samples 2. C.

1. Overview 2 2. Definitions 2 3. Laboratory Testing Criteria 2. A. Laboratory Qualifications 2. B. Analysis of TSS Samples 2. C. New Jersey Department of Environmental Protection Laboratory Protocol to Assess Total Suspended Solids Removal by a Hydrodynamic Sedimentation Manufactured Treatment Device January 25, 2013 Contents 1.

More information

Environmental Control Plan

Environmental Control Plan Environmental Control Plan Environmental Control Plan In accordance with Watts & Hughes Construction Waikato Bay of Plenty Limited. corporate strategies the Company has an Environment Control Plan which

More information

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1 CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm

More information

A signed statement from the manufacturer listing the protocol requirements and indicating that all of the requirements were met or exceeded.

A signed statement from the manufacturer listing the protocol requirements and indicating that all of the requirements were met or exceeded. Protocol for Manufactured Hydrodynamic Sedimentation Devices for Total Suspended Solids Based on Laboratory Analysis Dated August 5, 2009, Revised December 15, 2009 The New Jersey Stormwater Management

More information

APPENDIX F: DRAINAGE AND STORMWATER MANAGEMENT

APPENDIX F: DRAINAGE AND STORMWATER MANAGEMENT APPENDIX F: DRAINAGE AND STORMWATER MANAGEMENT Downtown Ottawa Transit Tunnel: Tunney s Pasture to Blair Station via a Downtown LRT Tunnel Prepared for: City of Ottawa 110 Laurier Avenue West Ottawa, ON

More information

INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS IAPMO GUIDE CRITERIA FOR

INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS IAPMO GUIDE CRITERIA FOR INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS IAPMO GUIDE CRITERIA FOR WASTEWATER INTERCEPTOR SYSTEM (WIS) FOR AN INTERACTIVE MECHANICAL WASTEWATER INTERCEPTOR IGC 245-2007a 1. PURPOSE

More information

HUBER Sewerage Program

HUBER Sewerage Program WASTE WATER Solutions HUBER Sewerage Program Machines and system solutions for stormwater treatment and sewer system management Combined and Storm Water Treatment Innovative technology and solutions for

More information

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E Ambassador Bridge Enhancement Project CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT Replacement Span and Plaza Expansion APPENDIX E DRAFT EROSION AND SEDIMENT

More information

Appendix A9.1: Private Water Supply Supplementary Environmental Information

Appendix A9.1: Private Water Supply Supplementary Environmental Information Appendix A9.1: Private Water Supply Supplementary Environmental Information 1.1 Introduction SEPA objected to the planning application for the Project in their consultation response dated 19 October 2013

More information