Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document

Size: px
Start display at page:

Download "Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document"

Transcription

1 Decision 3476-D Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document ATCO Electric Ltd. Yeo Substation Project Facility Application February 18, 2015

2 Alberta Utilities Commission Decision 3476-D : Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document Application ATCO Electric Ltd. Yeo Substation Project Applications to Proceeding 3476 February 18, 2015 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:

3 Alberta Utilities Commission Calgary, Alberta Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document ATCO Electric Ltd. Decision 3476-D Yeo Substation Project Applications and to Facility Application Proceeding Introduction and background 1. The Alberta Electric System Operator (AESO) filed Application (the needs identification document application) with the Alberta Utilities Commission on October 21, 2014, pursuant to Section 34 of the Electric Utilities Act, for approval of the need for the new Yeo 2015S substation and a new 240-kilovolt (kv) transmission line between the proposed Yeo 2015S substation and the approved Birchwood Creek 960S substation. 2. Pursuant to Section 35 of the Electric Utilities Act, the AESO directed ATCO Electric Ltd. (ATCO) to submit a facility application to the AUC for the construction of the new Yeo 2015S substation and transmission line to meet the need identified in the needs identification document application. 3. ATCO filed Applications to (the facility application) with the AUC on October 21, 2014, pursuant to sections 14, 15, 19 and 21 of the Hydro and Electric Energy Act, for approval to construct and operate the Yeo 2015S substation and the 240-kV transmission line 9L144, and to alter and operate the approved Birchwood Creek 960S substation. 4. The AESO and ATCO requested that the Commission consider the needs identification document application and the facility application jointly, pursuant to Section 15.4 of the Hydro and Electric Energy Act. The Commission advised the AESO and ATCO that the applications had been combined and were being considered jointly as Proceeding After reviewing the applications, the Commission issued two rounds of information request to ATCO on November 19, 2014, and January 23, ATCO responded to the information requests on December 9, 2014, and January 27, 2015, respectively. 6. The Commission issued a notice of applications for Proceeding 3476 on December 16, The notice provided information about how to express objections to, concerns about or support for one or more of the applications with a deadline to file any submissions to the AUC by January 14, The notice was sent directly to all landowners, occupants, agencies and other interested parties within 800 metres of the project. The notice was distributed electronically to market participants and published on the AUC website. Decision 3476-D (February 18, 2015) 1

4 Yeo 2015S Substation Project 7. On January 8, 2015, Alberta Parks submitted correspondence to the Commission indicating that it had received the notice of applications and did not have any concerns with the project because the project would not occur within or near any park boundaries. 8. No objections or concerns were received by the submission deadline of January 14, Discussion 2.1 Needs identification document application 9. ATCO, as the owner of electric distribution facilities in the Fort McMurray area, requested transmission system access service to serve a new industrial load associated with the Grand Rapids Mackay pump station. 10. The AESO s proposed transmission development to address the requested transmission system access included the following major components: one new 240/25- kv substation, to be designated as Yeo 2015S, with two 240/25-kV transformers; and one new 240-kV transmission line between the proposed Yeo 2015S substation and the approved Birchwood Creek 960S substation. 11. The AESO stated that three options were considered to address the need to supply the industrial load growth associated with the Grand Rapids Mackay pump station. The proposed transmission development was selected as the preferred option because it would be located closer to the new industrial load than one of the options and would provide greater reliability than the other option. 12. The AESO directed ATCO to assist it in conducting a participant involvement program. 2.2 Facility application 13. To meet the need identified by the AESO in the needs identification document application, ATCO proposed to: construct a new 240/25-kV substation to be designated as Yeo 2015S; construct approximately 1.5 kilometres of new single-circuit 240-kV transmission line, to be designated as 9L144, from the proposed Yeo 2015S substation to the approved Birchwood Creek 960S substation; alter the existing 240-kV transmission line 9L57 between Birchwood Creek 960S substation and Livock 939S substation by decommissioning and salvaging an approximately 750-metre line segment near Birchwood Creek 960S substation and rebuilding an approximately 750-metre line segment directly southeast to accommodate the new transmission line 9L144; and alter the approved Birchwood Creek 960S substation. 2 Decision 3476-D (February 18, 2015)

5 Yeo Substation Project 14. The proposed Yeo 2015S substation would contain the following major equipment: two 240-kV/25-kV, 30/40/50-megavolt-ampere transformers; two 240-kV circuit breakers; and five 25-kV circuit breakers. 15. ATCO included only one proposed location for the proposed Yeo 2015S substation and one proposed route for transmission line 9L144 and altered portion of transmission line 9L The proposed Yeo 2015S substation would be located in the Regional Municipality of Wood Buffalo, approximately 40 kilometres west of the urban services area of Fort McMurray. The proposed substation site is located in the southwest quarter of Section 34, Township 89, Range 14, west of the Fourth Meridian on Crown land. The substation site would be approximately 200 metres by 200 metres with a fenced area of approximately 82 metres by 57 metres. 17. ATCO stated that the site for the proposed Yeo 2015S substation was selected because: it is compatible and integrated with current and planned developments in the surrounding area; it reduces the overall impact on stakeholders and surrounding environment; ATCO will not have to construct a new access to the substation; the amount of new clearing for temporary construction laydown area is less than other areas; it avoids environmentally sensitive areas; it allows for future expansion; and it reduces the length and footprint of connections to the customer s facility. 18. ATCO stated that the proposed route for transmission line 9L144 would incorporate the existing land use development because it utilizes the right-of-way of the existing transmission line 9L57. A portion of transmission line 9L57 would be re-routed directly adjacent and parallel to the transmission line 9L144 right-of-way, which would reduce the total amount of land disturbed by integrating tree-free zones. ATCO also stated that this arrangement would avoid two unnecessary and higher risk line crossings. 19. ATCO stated that, while the proposed alignment for transmission lines 9L144 and 9L57 routes is through caribou habitat and environmentally significant areas, it would allow for minimal tree clearing, integration with the existing disturbances, reduction in safety hazards and increased electrical reliability. 20. The selected site for the proposed Yeo 2015S substation and the proposed routes for transmission line 9L144 and a portion of transmission line 9L57 were presented to stakeholders, including oil and gas developers, agencies, First Nations, interested parties, and the public. Decision 3476-D (February 18, 2015) 3

6 Yeo 2015S Substation Project 21. ATCO stated that the proposed route for transmission line 9L144 was chosen because it: minimizes disturbances to natural systems in the study area; requires no new access; has low environmental impacts overall; has no transmission line crossings; has no objections from stakeholders and agencies; and minimizes transmission line length and cost. 22. The proposed transmission line 9L144 is located within the Boreal Forest Natural Region and the Central Mixedwood and Lower Boreal Highlands sub-regions. ATCO stated that the project is located within the Lower Athabasca Regional Plan (LARP) and that the project is consistent with the LARP in the following ways: ATCO consulted with the government agencies, industrial landholders and trappers in the routing process. The project follows existing linear disturbances, where possible, while avoiding other constraints including wetlands, water crossings and industrial facilities. ATCO worked closely with the large-scale industrial operators in the area to integrate transmission line route planning with other current and planned industrial activities. ATCO engaged the aboriginal communities in the planning process in developing the routing and siting options for the project. The air emissions from the project will not cause the ambient air quality conditions to exceed the triggers or limits detailed in the air quality management framework of the LARP. Depending on weather and ground conditions, ATCO may withdraw water to help stabilize work areas by freezing them. If this is required, ATCO will obtain the necessary regulatory approvals in that regard. The project does not require the use of groundwater, except for the stabilization work noted above. 23. ATCO stated that the Comprehensive Regional Infrastructure Sustainability Plan for the Athabasca Oil Sands Area (CRISP) describes Alberta s mandate of integrating multi-use corridor planning and incorporating extensive consultation in the Athabasca oilsands area for the proposed projects. ATCO also stated that the project is consistent with the CRISP. 24. ATCO indicated that it completed extensive consultation with Alberta Environment and Sustainable Resource Development (ESRD) to mitigate the environmental effects of the project and worked closely with ESRD on the siting of the project. 25. Further, ATCO submitted that the project would comply with the relevant sections of the Alberta Environmental Protection and Enhancement Act, the Environmental Protection Guidelines for Transmission Lines, and other relevant statutes, regulations, rules and guidelines. 4 Decision 3476-D (February 18, 2015)

7 Yeo Substation Project 26. ATCO stated that Historical Resources Act clearance was issued by Alberta Culture in October ATCO submitted an environmental evaluation report 1 and an environmental protection plan 2 to provide an assessment of the potential environmental effects of the proposed project. The environmental evaluation report for the project described the environmental and land use conditions in the project area including historical resources, land use and designated areas, watercourse crossings and wetlands, soils, vegetation, and wildlife and discussed the potential adverse effects of the project on these environmental components. The environmental evaluation report was based on both desktop data and the results of field surveys. The report included recommended mitigation measures that would limit these potential effects. 28. The environmental evaluation report acknowledged that the project has the potential to impact rare plants, wetland vegetation communities and wildlife species of conservation concern including species at risk such as woodland caribou. However, with the implementation of the recommended mitigation measures, the impacts of the project on vegetation and wildlife were predicted to be low to moderate in magnitude. 29. ATCO conducted a noise impact assessment for the project and submitted a noise impact assessment summary form as part of the application. The results indicated that the project would be in compliance with the noise levels established by Rule 012: Noise Control. ATCO also submitted that the nearest noise receptor (a work camp) from the proposed Yeo 2015S substation is approximately 2,500 metres away. 30. ATCO and the AESO conducted a joint participant involvement program. ATCO and the AESO submitted that project stakeholders, including oil and gas developers, agencies, and other interested parties potentially affected by the project were part of the consultation program. ATCO and the AESO also notified stakeholders, landowners, agencies, and other potentially interested parties within 800 metres of the transmission line route and substation site. ATCO also conducted personal consultation with all the landholders, occupants, agencies and interested parties with 800 metres of the proposed transmission line right-of-way and the proposed Yeo 2015S substation site. 31. The project would be located in a traditional area identified by three First Nation communities. ATCO stated that a consultation plan was implemented to ensure a thorough and meaningful consultation with the affected communities. 32. ATCO estimated the cost of the proposed project to be approximately $21,802,485 (within +20 per cent/-10 per cent accuracy). 3 Findings 33. The Commission has reviewed the needs identification document application and the facility application filed by the AESO and ATCO, respectively. The Commission finds that both applications meet the information requirements stipulated in Rule 007: Applications for 1 2 Exhibit AE Exhibit AE Decision 3476-D (February 18, 2015) 5

8 Yeo 2015S Substation Project Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments. 34. No interested party demonstrated that the AESO s assessment of the need for the proposed facilities is technically deficient or that approval of the needs identification document application is not in the public interest. Therefore, the Commission considers the AESO s assessment of the need to be correct, in accordance with Section 38(e) of the Transmission Regulation, and approves the AESO s needs identification document application. 35. The Commission finds that the facility application for the substation and transmission line as proposed by ATCO, satisfies the need identified by the AESO. 36. The Commission recognizes that a participant involvement program was completed, and finds that there are no outstanding objections or concerns with the applications. The Commission finds that the respective consultation efforts made by the AESO and ATCO fulfill the requirements of Rule 007. In addition, the Commission notes that there were no objections or concerns received in response to the AUC notice of applications. 37. The Commission is satisfied that the submitted noise impact assessment is in compliance with the requirements of Rule The Commission acknowledges that the project is within the LARP area and is satisfied that the project is in accordance with the requirements of the LARP, and that ATCO has committed to comply with the relevant sections of the Alberta Environmental Protection and Enhancement Act, the Environmental Protection Guidelines for Transmission Lines and other relevant regulations and guidelines. 39. The Commission acknowledges ATCO s commitment to continue to consult and work with the Fish and Wildlife Operations Division of ESRD regarding the adverse effects of the project on birds, to complete post-construction bird mortality monitoring activities, and to implement any mitigation measures recommended by ESRD. 40. The Commission acknowledges ATCO s commitment to develop a caribou protection plan for the project, to submit the caribou protection plan to ESRD for approval upon completion, and to conform to the mitigation measures identified in the Alberta Woodland Caribou Policy and the caribou protection plan for the project. 41. The Commission expects ATCO to comply with all restricted activity periods, implement sufficient mitigation measures to ensure the protection of wildlife and rare plants prescribed under the Wildlife Act, and to maintain the ESRD recommended setback distances for the specified wildlife, plants, and their associated habitat during project construction. 42. The Commission is satisfied that any environmental issues can be addressed adequately through the mitigation measures proposed by ATCO in its environmental evaluation and environmental protection plan. 43. In order to confirm compliance, ATCO has made commitments in response to the environmentally related information requests. In this regard, the Commission finds that approval of the Yeo 2015S substation project would also require the following conditions: 6 Decision 3476-D (February 18, 2015)

9 Yeo Substation Project ATCO shall protect the bog adder s mouth rare plant by: avoiding the immediate area where occurrences of the rare plant are located; flagging a 0.6-hectare buffer area around the rare plant occurrences that will not be cleared of vegetation; amending the boundary of the proposed Yeo 2015S substation Crown land lease and submitting the amended lease to ESRD Public Lands for approval; and conducting a post-construction survey of the rare plant occurrences within the appropriate survey timing window and advising ESRD of the results of this survey. If bird mortality occurs during operation of the project, ATCO shall consult with a local wildlife biologist at the Wildlife Management Unit of ESRD on appropriate mitigation measures. ATCO shall not conduct any brushing activity along the transmission line right-of-way or within the substation boundaries during breeding bird season. An ATCO environmental advisor has been assigned to this project and shall maintain a presence throughout the project. If the nighthawks are observed during construction, ESRD shall be consulted. A pre-construction nest sweep shall be conducted prior to the start of brushing operations to assess the presence of nests. One year following completion of construction, a post-construction raptor survey shall be conducted in the recommended timing window as per the Sensitive Species Inventory Guidelines. A post-construction auditory amphibian survey shall be conducted in the recommended timing window as per Sensitive Species Inventory Guidelines. An owl survey shall be conducted in early March 2015 as per Sensitive Species Inventory Guidelines or as directed by ESRD. 44. The Commission considers that the technical, siting and environmental aspects of the facilities, as specified in Rule 007, have been met. 45. Based on the foregoing, and having considered the social, economic, and environmental impacts of the proposed project, the Commission finds that the project is in the public interest pursuant to Section 17 of the Alberta Utilities Commission Act. 4 Decision 46. Pursuant to Section 34 of the Electric Utilities Act, the Commission approves the AESO s needs identification document application and grants the AESO the approval set out in Appendix 1 Approval 3476-D Pursuant to sections 14, 15, 19 and 21 of the Hydro and Electric Energy Act, the Commission approves the facility application and grants ATCO the following approvals: Decision 3476-D (February 18, 2015) 7

10 Yeo 2015S Substation Project Permit and Licence 3476-D to construct and operate Yeo 2015S substation as set out in Appendix 2. Permit and Licence 3476-D to alter and operate Birchwood Creek 960S substation as set out in Appendix 3. Permit and Licence 3476-D to construct and operate transmission line 9L144 as set out in Appendix 4. Permit and Licence 3476-D to alter and operate transmission line 9L57 as set out in Appendix 5. Permit and Licence 3476-D to decommission and salvage a portion of transmission line 9L57 as set out in Appendix The appendices will be distributed separately. Dated on February 18, Alberta Utilities Commission (original signed by) Neil Jamieson Commission Member 8 Decision 3476-D (February 18, 2015)

Alberta Electric System Operator Needs Identification Document Application

Alberta Electric System Operator Needs Identification Document Application Decision 22618-D01-2017 Alberta Electric System Operator Needs Identification Document Application Facility Applications June 22, 2017 Alberta Utilities Commission Decision 22618-D01-2017: Alberta Electric

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22562-D01-2017 ENMAX No. 31 Substation Alteration May 25, 2017 Alberta Utilities Commission Decision 22562-D01-2017 ENMAX No. 31 Substation Alteration Proceeding 22562 Application 22562-A001 May

More information

NOVA Chemicals Corporation

NOVA Chemicals Corporation Decision 2013-426 NOVA Chemicals Corporation Industrial System Designation Amendment November 29, 2013 The Alberta Utilities Commission Decision 2013-426: NOVA Chemicals Corporation Industrial System Designation

More information

Suncor Energy Inc. Errata to Decision Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment

Suncor Energy Inc. Errata to Decision Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment Decision 2011-523 (Errata) Errata to Decision 2011-523 Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment January 10, 2012 The Alberta Utilities Commission Decision

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions December 19, 2016 Alberta Utilities Commission Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions Proceeding 22229 Application

More information

Seven Generations Energy Ltd.

Seven Generations Energy Ltd. Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant January 17, 2018 Alberta Utilities Commission Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant Proceeding 22976

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017

More information

Decision Cenovus FCCL Ltd.

Decision Cenovus FCCL Ltd. Decision 2012-196 Construct and Operate a 95-MW Cogeneration Power Plant, Construct and Operate Sunday Creek 539S Substation, Industrial System Designation and Interconnection of the Christina Lake Industrial

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 23468-D01-2018 Margie 1034S Substation May 28, 2018 Alberta Utilities Commission Decision 23468-D01-2018 Margie 1034S Substation Proceeding 23468 Application 23468-A001 May 28, 2018 Published

More information

Nexen Inc. and CNOOC Canada Inc.

Nexen Inc. and CNOOC Canada Inc. Decision 2012-330 Long Lake Project December 6, 2012 The Alberta Utilities Commission Decision 2012-330: Long Lake Project Application No. 1608729 Proceeding ID No. 2074 December 6, 2012 Published by The

More information

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018 Decision 23890-D01-2018 Swan Hills F.P.L. 744S Substation Decommission and Salvage November 8, 2018 Alberta Utilities Commission Decision 23890-D01-2018 Swan Hills F.P.L. 744S Substation Decommission and

More information

SunEEarth Alberta Solar Development Inc.

SunEEarth Alberta Solar Development Inc. Decision 22422-D01-2017 Yellow Lake Solar Project September 26, 2017 Alberta Utilities Commission Decision 22422-D01-2017 Yellow Lake Solar Project Proceeding 22422 Application 22422-A001 September 26,

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22499-D01-2017 June 7, 2017 Decision 22499-D01-2017 Proceeding 22499 Application 22499-A001 June 7, 2017 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta

More information

Harvest Operations Corp.

Harvest Operations Corp. Decision 2014-214 Six-MW Power Plant Exemption July 21, 2014 The Alberta Utilities Commission Decision 2014-214: Six-MW Power Plant Exemption Application No. 1610444 Proceeding No. 3153 July 21, 2014 Published

More information

Grande Prairie Generation, Inc.

Grande Prairie Generation, Inc. Decision 20292-D01-2015 Northern Prairie Power Plant November 27, 2015 Alberta Utilities Commission Decision 20292-D01-2015 Northern Prairie Power Plant Proceeding 20292 Application 20292-A001 November

More information

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011 Decision 2011-496 December 15, 2011 The Alberta Utilities Commission Decision 2011-496: Application No. 1607774 Proceeding ID No. 1505 December 15, 2011 Published by The Alberta Utilities Commission Fifth

More information

NaturEner Wild Rose 1 Energy Inc.

NaturEner Wild Rose 1 Energy Inc. Decision 2013-348 Amendment to Wild Rose 1 Wind Power Plant September 13, 2013 The Alberta Utilities Commission Decision 2013-348: Amendment to Wild Rose 1 Wind Power Plant Application No. 1609685 Proceeding

More information

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013 Decision 2013-027 Brooks Solar Power Plant January 31, 2013 The Alberta Utilities Commission Decision 2013-027: Brooks Solar Power Plant Application No. 1608532 Proceeding ID No. 1938 January 31, 2013

More information

Aquatera Utilities Inc.

Aquatera Utilities Inc. Decision 2014-194 Aquatera Utilities Inc. 2.85-MW Power Plant June 26, 2014 The Alberta Utilities Commission Decision 2014-194: Aquatera Utilities Inc. 2.85-MW Power Plant Application No. 1610366 Proceeding

More information

Connacher Oil and Gas Limited

Connacher Oil and Gas Limited Decision 2010-094 Cogeneration Plant and Industrial System Designation March 2, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-094: Cogeneration Plant and Industrial System Designation Application No.

More information

Pteragen Canada Inc.

Pteragen Canada Inc. Decision 2013-171 May 7, 2013 The Alberta Utilities Commission Decision 2013-171: Application No. 1608907 Proceeding ID No. 2181 May 7, 2013 Published by The Alberta Utilities Commission Fifth Avenue Place,

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22296-D01-2017 Hays Solar Power Plant June 7, 2017 Alberta Utilities Commission Decision 22296-D01-2017 Hays Solar Power Plant Proceeding 22296 Application 22296-A001 June 7, 2017 Published by

More information

TransAlta Corporation

TransAlta Corporation Decision 23808-D01-2018 Coal-to-Gas Conversion of Keephills Power Plant Units 1 and 2 December 21, 2018 Alberta Utilities Commission Decision 23808-D01-2018 Coal-to-Gas Conversion of Keephills Power Plant

More information

Solar Krafte Utilities Inc.

Solar Krafte Utilities Inc. Decision 23323-D01-2018 August 21, 2018 Alberta Utilities Commission Decision 23323-D01-2018 Proceeding 23323 Application 23323-A001 August 21, 2018 Published by the: Alberta Utilities Commission Eau Claire

More information

Pembina NGL Corporation

Pembina NGL Corporation Decision 22928-D01-2018 45-Megawatt Cogeneration Power Plant, Alteration to Scoria 318S Substation and Amendment to the Redwater Industrial System Designation January 9, 2018 Alberta Utilities Commission

More information

Greengate Power Corporation

Greengate Power Corporation Decision 2011-085 Blackspring Ridge Wind Project March 9, 2011 The Alberta Utilities Commission Decision 2011-085: Blackspring Ridge Wind Project Application No. 1604777 Proceeding ID No. 190 March 9,

More information

Signalta Resources Limited

Signalta Resources Limited Decision 22388-D01-2017 Coaldale 6.4-Megawatt Cogeneration Station June 1, 2017 Alberta Utilities Commission Decision 22388-D01-2017 Coaldale 6.4-Megawatt Cogeneration Station Proceeding 22388 Application

More information

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018 Decision 22711-D01-2018 Bonnybrook Cogeneration Expansion Project May 17, 2018 Alberta Utilities Commission Decision 22711-D01-2018 Bonnybrook Cogeneration Expansion Project Proceeding 22711 Application

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23713-D01-2018 August 28, 2018 Alberta Utilities Commission Decision 23713-D01-2018 Proceeding 23713 Application 23713-A001 August 28, 2018 Published by the: Alberta Utilities Commission Eau Claire

More information

Decision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013

Decision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013 Decision 2013-180 13.05-kW Photovoltaic Micro-Generation System May 15, 2013 The Alberta Utilities Commission Decision 2013-180: 13.05-kW Photovoltaic Micro-Generation System Application No. 1609500 Proceeding

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 2010-461 Oldman 2 Wind Farm Project September 24, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-461: Oldman 2 Wind Farm Project Application No. 1605398 Proceeding ID. 293 September 24, 2010

More information

Pengrowth Energy Corporation

Pengrowth Energy Corporation Decision 2013-308 Lindberg SAGD Industrial System Designation August 20, 2013 The Alberta Utilities Commission Decision 2013-308: Lindberg SAGD Industrial System Designation Application No. 1609200 Proceeding

More information

Nexen Inc. OPTI Canada Inc.

Nexen Inc. OPTI Canada Inc. Decision 2010-006 Nexen Inc. OPTI Canada Inc. Long Lake South Phase 1 Cogeneration Power Plant January 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-006: Nexen Inc. and OPTI Canada Inc. Long Lake

More information

Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014

Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014 Decision 2014-212 Syncrude Canada Ltd. Mildred Lake Power Plant July 17, 2014 Decision 2014-212: Syncrude Canada Ltd. Mildred Lake Power Plant Application No. 1610311 Proceeding No. 3068 July 17, 2014

More information

Grizzly Oil Sands ULC

Grizzly Oil Sands ULC Decision 2013-124 Algar Lake Project Distribution System Exemption March 28, 2013 The Alberta Utilities Commission Decision 2013-124: Algar Lake Project Distribution System Exemption Application No. 1609370

More information

Burdett Solar GP Corp.

Burdett Solar GP Corp. Decision 23364-D01-2018 Burdett Solar Project Time Extension October 3, 2018 Alberta Utilities Commission Decision 23364-D01-2018 Burdett Solar Project Time Extension Proceeding 23364 Application 23364-A001

More information

Yeo Substation Project

Yeo Substation Project Yeo Substation Project Application to the Alberta Utilities Commission October 2014 10035 105 Street, Edmonton AB, Canada T5J 2V6 Tel: 1-866-600-0022 Fax: 780-420-5030 www.atcoelectric.com Application

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22447-D01-2017 Vauxhall Solar Power Plant July 4, 2017 Alberta Utilities Commission Decision 22447-D01-2017 Vauxhall Solar Power Plant Proceeding 22447 Application 22447-A001 July 4, 2017 Published

More information

The City of Red Deer

The City of Red Deer Decision 2010-148 The City of Red Deer 15-kW Solar Power Plant for City of Red Deer Civic Yards Building April 5, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-148: The City of Red Deer 15-kW Solar Power

More information

Alberta Power (2000) Ltd.

Alberta Power (2000) Ltd. Decision 23558-D01-2018 Battle River Power Plant Alterations August 27, 2018 Alberta Utilities Commission Decision 23558-D01-2018 Battle River Power Plant Alterations Proceeding 23558 Application 23558-A001

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on March

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23918-D01-2018 Paddle Prairie Compressor Station Installation Mackenzie County October 11, 2018 Alberta Utilities Commission Decision 23918-D01-2018 Paddle Prairie Compressor Station Installation

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on December

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on June

More information

Renewable Energy Services Ltd.

Renewable Energy Services Ltd. Decision 1976-D01-2018 McLaughlin Wind Power Plant and Substation February 23, 2018 Alberta Utilities Commission Decision 1976-D01-2018 McLaughlin Wind Power Plant and Substation Proceeding 1976 Applications

More information

Welcome to our Open House!

Welcome to our Open House! Welcome to our Open House! Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If

More information

May 8, 2017 EASB File #: Transaction #:

May 8, 2017 EASB File #: Transaction #: Ministry of Environment Environmental Assessment and Stewardship Branch 4 th floor, 3211 Albert Street Regina, Saskatchewan S4S 5W6 Phone: (306) 787-6132 Fax: (306) 787-0930 May 8, 2017 EASB File #: 2016-022

More information

APPLICATION TO THE ALBERTA UTILITIES COMMISSION SWEETHEART LAKE TRANSMISSION PROJECT. February 2014

APPLICATION TO THE ALBERTA UTILITIES COMMISSION SWEETHEART LAKE TRANSMISSION PROJECT. February 2014 APPLICATION TO THE ALBERTA UTILITIES COMMISSION SWEETHEART LAKE TRANSMISSION PROJECT February 2014 10035-105 Street P.O. Box 2426 Station Main Edmonton, Alberta T5J 2V6 ATCO Electric Ltd. Sweetheart Lake

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 22706-D01-2017 Spring 2017 Comprehensive Sound Survey at Receptors R and S August 25, 2017 Alberta Utilities Commission Decision 22706-D01-2017 Proceeding 22706 Application 22706-A001 August 25,

More information

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017 FALL 2017 PROJECT OVERVIEW EDF EN Canada is proposing to develop, construct, and operate the Cypress Wind Power Project with 243.6 megawatts (MW) of generating capacity. The Project is south of Dunmore,

More information

October 30, 2012 Our File:

October 30, 2012 Our File: October 30, 2012 Our File: 5000-510-5120 Minister of Environment and Sustainable Resource Development 204 Legislature Building 10800 97 Avenue Edmonton, AB T5K 2B6 Attention: Honourable Diana McQueen at

More information

Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc.

Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc. Decision 2010-612 Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc. Needs Identification Document, Transmission Line, Substation and Power Plant Al-Pac Pulp

More information

Meadow Creek West. Project overview:

Meadow Creek West. Project overview: Project overview: Meadow Creek West will be a steam assisted gravity drainage (SAGD) oil sands development in northeast Alberta. Meadow Creek West is an additional phase to our Meadow Creek project and

More information

SemCAMS Area Project Description

SemCAMS Area Project Description REGULATORY The Redwillow Pipeline Project involves crossing a provincial boundary, and therefore, approval for it will require the preparation of an application to the NEB. plans to proceed with the regulatory

More information

Ellerslie Substation Expansion

Ellerslie Substation Expansion Ellerslie Substation Expansion Volume 2 UV 2 North Saskatchewan River EDMONTON UV 216 UV 14 ") ELLERSLIE 89S Bretona!! Trevithick March 2010 Why are you receiving this newsletter? You are receiving this

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest What s Inside? Answers to On: NextBridge Infrastructure and the East-West Tie Project Electricity in Northern Ontario Land issues Routing Project approval process Health

More information

ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc.

ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc. Regulatory Audit Report #2008-001 ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc. Inter-Affiliate Code

More information

Section 1 - Introduction

Section 1 - Introduction Section 1 - Introduction Algar Lake SAGD Project Section 1 Project Introduction TABLE OF CONTENTS 1. PROJECT INTRODUCTION... 1 1.1 PROJECT BACKGROUND... 1 1.2 PROJECT PROPONENT... 1 1.3 PROJECT OVERVIEW...

More information

REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT

REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT SASKATCHEWAN WATER CORPORATION BUFFALO POUND NON-POTABLE WATER SUPPLY SYSTEM EXPANSION PROJECT Introduction

More information

Lloydminster to Spruce Lake 138kV Transmission Line Projects

Lloydminster to Spruce Lake 138kV Transmission Line Projects Lloydminster to Spruce Lake 138kV Transmission Line Projects Preferred Corridor Presentation June 2017 SaskPower continues to invest in the province s electricity system to ensure we have the infrastructure

More information

Substation Developments Environmental Guidelines Checklist for Applicants

Substation Developments Environmental Guidelines Checklist for Applicants Substation Developments Environmental Guidelines Checklist for Applicants Effective date: February 1, 2016 These guidelines are intended to be used in conjunction with the flowchart in Figure 1 which conceptually

More information

Highway 11 Realignment

Highway 11 Realignment Highway 11 Realignment Preferred Alternative Option 1D (optimized) Key Advantages (+) / Disadvantages (-) + Comparatively lowest cost to construct. Comparatively lowest construction complexity. + Optimal

More information

EDF EN Canada Development Inc.

EDF EN Canada Development Inc. Decision 21203-D01-2016 Blackspring Ridge Wind Power Plant March 2, 2016 Alberta Utilities Commission Decision 21203-D01-2016 Blackspring Ridge Wind Power Plant Proceeding 21203 Application 21203-A001

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 22274-D01-2018 Provost to Edgerton and Nilrem to Vermilion Transmission System Reinforcement January 12, 2018 Alberta Utilities Commission Decision 22274-D01-2018 Provost to Edgerton and Nilrem

More information

Project siting. Lanfine. Wind resource assessment. Wind Power Project

Project siting. Lanfine. Wind resource assessment. Wind Power Project Project siting Wind resource assessment This assessment determines how much electrical energy can be extracted from the wind Meteorological towers are installed on site to measure wind speed and direction

More information

3.0 Natural Resource Management Policies. 3.4 Resource Extraction Policies

3.0 Natural Resource Management Policies. 3.4 Resource Extraction Policies 3.0 Natural Resource Management Policies 3.4.1 Mineral Aggregates INTRODUCTION Oxford County is characterized by significant reserves of mineral aggregates, including bedrock-derived crushed stone and

More information

October 2, 2015 EAB File #: Transaction #:

October 2, 2015 EAB File #: Transaction #: Ministry of Environment Environmental Assessment Branch 4 th floor, 3211 Albert Street Regina, Saskatchewan S4S 5W6 Phone: 306.787 5971 Fax: 306 787 0930 October 2, 2015 EAB File #: 2015-013 Transaction

More information

Notice of Technical Meeting

Notice of Technical Meeting Notice of Technical Meeting Amendments to three wind energy projects in the Pincher Creek area proposed by Welsch Wind Power Inc., Windy Point Wind Park Ltd. and NextEra Canada Development & Acquisitions,

More information

ALBERTA TRANSPORTATION TERMS OF REFERENCE

ALBERTA TRANSPORTATION TERMS OF REFERENCE ALBERTA TRANSPORTATION TERMS OF REFERENCE FOR ENVIRONMENTAL EVALUATION June 2011 Page 1 SCOPE OF ASSESSMENT The TERMS OF REFERENCE FOR ENVIRONMENTAL EVALUATION are to be utilized for those projects that

More information

LNG Canada Development Inc.

LNG Canada Development Inc. LNG Canada Development Inc. Shell Centre 32 nd Floor 400 4 th Avenue SW PO Box 100, Station M Calgary AB T2P 2H5 Canada Submitted electronically to: compliance.conformite@ceaa-acee.gc.ca April 20, 2016

More information

Environmental Guidelines Checklist

Environmental Guidelines Checklist Environmental Guidelines Checklist Stakeholder: Alberta Environment & Parks (Brian Lambert), AltaLink, ATCO Electric, EPCOR Distribution & Transmission (EDTI) Section Subsection Existing Proposed changes

More information

LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012

LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012 LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012 01 STONY MOUNTAIN PIPELINE Laricina will develop and follow an environmental protection plan that meets or exceeds

More information

ENVIRONMENTAL SCREENING REPORT

ENVIRONMENTAL SCREENING REPORT ENVIRONMENTAL SCREENING REPORT Pursuant to the Canadian Environmental Assessment Act (CEA Act) SCREENING SUMMARY TransCanada PipeLines Limited (TransCanada) is proposing to conduct a contaminant sampling

More information

To: Steve Lines From: Fiona Christiansen. File: Date: September 15, 2015

To: Steve Lines From: Fiona Christiansen. File: Date: September 15, 2015 Memo To: From: Fiona Christiansen Greenstone Gold Mines (GGM) Guelph ON Office File: 160960946 Date: CONTEXT As part of the provincial individual environmental assessment (EA) process for the Hardrock

More information

KEEYASK TRANSMISSION PROJECT EA REPORT APPENDIX C VALUED ENVIRONMENTAL COMPONENTS

KEEYASK TRANSMISSION PROJECT EA REPORT APPENDIX C VALUED ENVIRONMENTAL COMPONENTS APPENDIX C VALUED ENVIRONMENTAL COMPONENTS C.1. VALUED ENVIRONMENTAL COMPONENTS Valued environmental components (VECs) are defined as fundamental elements of the physical, biological or socio-economic

More information

Environmental Impact Statement for the Slave Falls Tramway Conversion Project

Environmental Impact Statement for the Slave Falls Tramway Conversion Project Environmental Impact Statement for the Slave Falls Tramway Conversion Project Prepared for Submitted by 41844.101 March 2008 ENVIRONMENTAL IMPACT STATEMENT FOR THE SLAVE FALLS TRAMWAY CONVERSION PROJECT

More information

Alberta Wetland Assessment and Impact Report Directive

Alberta Wetland Assessment and Impact Report Directive Alberta Wetland Assessment and Impact Report Directive June 2017 Title: Number: Program Name: Water Policy Branch Effective Date: June 1, 2015 This document was updated on: Disclaimer: June 1, 2017 This

More information

HYDRO AND ELECTRIC ENERGY REGULATION

HYDRO AND ELECTRIC ENERGY REGULATION Province of Alberta HYDRO AND ELECTRIC ENERGY ACT HYDRO AND ELECTRIC ENERGY REGULATION Alberta Regulation 409/1983 With amendments up to and including Alberta Regulation 136/2015 Office Consolidation Published

More information

Under Section 113 of the Environmental Protection and Enhancement Act

Under Section 113 of the Environmental Protection and Enhancement Act Order Made at Slave lake, in the Province of Alberta, on July 13, 2018 ALBERTA ENERGY REGULATOR Under Section 113 of the Environmental Protection and Enhancement Act Under Section 29 of the Pipeline Act

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest THANK YOU for attending this Open House We want to hear from you www.nextbridge.ca Purpose of the Open House We are here to provide you

More information

Municipal Class EA Process

Municipal Class EA Process Purpose of Tonight s Meeting INTRODUCTION This is the first Public Information Centre (PIC) to present information on the Class Environmental Assessment (EA) Study for a new operations centre. The following

More information

Order. -AI1ta. Energy Regulator. MADE at the City of Fort McMurray, in the Province of Alberta, on

Order. -AI1ta. Energy Regulator. MADE at the City of Fort McMurray, in the Province of Alberta, on -AI1ta Order Energy Regulator MADE at the City of Fort McMurray, in the Province of Alberta, on August 11 2015 ALBERTA ENERGY REGULATOR Under Sections 113 and 156 of the Environmental Protection and Enhancement

More information

SITE C FIELD WORK FOR 2019

SITE C FIELD WORK FOR 2019 January 2019 SITE C FIELD WORK FOR 2019 During the construction of Site C, BC Hydro will conduct environmental and engineering field work along the Peace River between the Williston Reservoir and the Alberta

More information

Canadian Natural Upgrading Limited

Canadian Natural Upgrading Limited 20180523B Canadian Natural Upgrading Limited Application for Jackpine Mine Tailings Management Plan May 23, 2018 Alberta Energy Regulator Decision 20180523B: Canadian Natural Upgrading Limited; Application

More information

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement Your guide to the SOUTHERN ALBERTA Transmission Reinforcement OUR TRANSMISSION LINES TRANSPORT THE POWER YOU USE EVERY DAY. Edmonton Red Deer Calgary Lethbridge 85% AltaLink s transmission system efficiently

More information

The ELC s comments are separated into general comments about the RAC Recommendations approach and specific comments about specific recommendations.

The ELC s comments are separated into general comments about the RAC Recommendations approach and specific comments about specific recommendations. October 6, 2010 Our File: 5320 LARP Phase 2Workbook c/o Stantec Consulting, PC 1165 200-325 25th Street SE Calgary, Alberta T2A 7H8 RE: Lower Athabasca Regional Plan To Whom It May Concern, Introduction

More information

Santoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement.

Santoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement. Environmental Impact Assessment Technical Review Comments on the Environmental Impact Statement as submitted by Claude Resources Inc. Saskatchewan Ministry of Environment December, 2009 1. INTRODUCTION

More information

(2) The permission to occupy and use Crown land does not entitle the permit holder to exclusive possession of the operating area.

(2) The permission to occupy and use Crown land does not entitle the permit holder to exclusive possession of the operating area. n COMMISSION June 16, 2016 Pipeline Ltd. 450-1st Street SW Calgary, AB T2P 5H1 Attention: Katherine Sheriff RE: Storage Permit located within Unit 74. Block A, Group 93-P-12 Date of Issuance: June 16,

More information

TABLE OF CONTENTS TABLE OF FIGURES TABLE OF TABLES 2. REGULATORY PROCESS Impact Assessment Process Permits and Licences...2.

TABLE OF CONTENTS TABLE OF FIGURES TABLE OF TABLES 2. REGULATORY PROCESS Impact Assessment Process Permits and Licences...2. TABLE OF CONTENTS PAGE 2. REGULATORY PROCESS...2.1 2.1 Impact Assessment Process...2.1 2.1.1 Mackenzie Valley Resource Management Act... 2.1 2.1.2 Taltson Expansion Project and Impact Assessment Process...

More information

Decision FortisAlberta Inc. Micro-Generation Determination. December 16, 2008

Decision FortisAlberta Inc. Micro-Generation Determination. December 16, 2008 Decision 2008-132 FortisAlberta Inc. Micro-Generation Determination December 16, 2008 ALBERTA UTILITIES COMMISSION Decision 2008-132: FortisAlberta Inc. Micro-Generation Determination Application No. 1594619

More information

LNG Canada submitted a formal update as per Condition 11.2 of the CEAA Decision Statement on June 30, 2017:

LNG Canada submitted a formal update as per Condition 11.2 of the CEAA Decision Statement on June 30, 2017: LNG Canada Development Inc. Shell Centre 32 nd Floor 400 4 th Avenue SW PO Box 100, Station M Calgary AB T2P 2H5 Canada Submitted electronically to: compliance.conformite@ceaa-acee.gc.ca July 4, 2018 Canadian

More information

Alberta Transportation The City of Edmonton The City of Calgary

Alberta Transportation The City of Edmonton The City of Calgary Alberta Transportation The City of Edmonton The City of Calgary PUBLISHING INFORMATION TITLE: PREPARED BY: DOCUMENT HOLDER: Environmental Construction Operations (ECO) Plan Framework Instructions for

More information

Peace Region Electricity Supply Project open house

Peace Region Electricity Supply Project open house Peace Region Electricity Supply Project open house Welcome! Please take a look at our materials to learn more about the project and what to expect during construction. Project team members are here to

More information

2006, Queen s Printer for Ontario Printed in Ontario, Canada

2006, Queen s Printer for Ontario Printed in Ontario, Canada 2006, Queen s Printer for Ontario Printed in Ontario, Canada Single copies of this publication are available at no charge from the address noted below. Bulk orders may involve charges. Natural Resources

More information

HORIZON NORTH PIT EXTENSION PROJECT

HORIZON NORTH PIT EXTENSION PROJECT HORIZON NORTH PIT EXTENSION PROJECT Plain Language Project Package File Number for Consultation: FNC201706486 Page 0 WHO IS CANADIAN NATURAL? Canadian Natural Resources Limited (Canadian Natural) is a

More information

AMHERST ISLAND WIND ENERGY PROJECT PROPERTY LINE SETBACK ASSESSMENT REPORT. File No April Prepared for:

AMHERST ISLAND WIND ENERGY PROJECT PROPERTY LINE SETBACK ASSESSMENT REPORT. File No April Prepared for: PROPERTY LINE SETBACK ASSESSMENT REPORT File No. 160960595 April 2013 Prepared for: Windlectric Inc. 2845 Bristol Circle Oakville ON L6H 7H7 Prepared by: Stantec Consulting Ltd. Suite 1 70 Southgate Drive

More information

SUNDANCE 7 January 2014

SUNDANCE 7 January 2014 Artist rendering of a combined-cycle natural gas power plant. SUNDANCE 7 January 2014 Project Information Booklet Table of Contents Introduction to Sundance 7 1 TransAlta and MidAmerican 1 Project location

More information

City of Mississauga Environmental Impact Studies Terms of Reference 2002

City of Mississauga Environmental Impact Studies Terms of Reference 2002 City of Mississauga Environmental Impact Studies Terms of Reference 2002 1.0 INTRODUCTION To ensure in so far as possible, both private and public developments are consistent with Natural Heritage and

More information

Information Document Service Proposals and Cost Estimating ID # R

Information Document Service Proposals and Cost Estimating ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

Re: Teck Frontier Oils Sands Mine Project: Responses to Supplemental Information Requests (SIRs)

Re: Teck Frontier Oils Sands Mine Project: Responses to Supplemental Information Requests (SIRs) Fort Chipewyan Métis Local 125 Métis Nation of Alberta February 27, 2013 Carolyn Dunn Crown Consultation Coordinator Canadian Environmental Assessment Agency Email: Carolyn.Dunn@ceaa-acee.gc.ca Re: Teck

More information