Peace Project Water Use Plan. Monitoring Program Terms of Reference. GMSMON-18 Williston Dust Control Monitoring
|
|
- Jennifer Harvey
- 5 years ago
- Views:
Transcription
1 Monitoring Program Terms of Reference GMSMON-18 Williston Dust Control Monitoring April 2, 2008
2 Terms of Reference for the Peace Project Water Use Plan Williston Dust Control Monitoring 1.0 MONITORING PROGRAM RATIONALE 1.1 Background This Terms of Reference (ToR) describes the GMSMON#18 Williston (WLL) Dust Control Monitoring project ( Dust Monitoring ). This project was proposed by the Committee for the Peace Project Water Use Plan (WUP) in the Committee Report dated December This monitoring program will assess the effectiveness of the dust control trials (conducted pursuant to ToR for GMSWORKS#21 WLL Dust Control Trials (the Dust Control Trials )) as well as other dust mitigation efforts carried out by BC Hydro and the First Nations (FNs) in the Finlay Reach drawdown zone of Williston Reservoir (Figure 1-1, Figure 1-2). Since creation of the Williston Reservoir following construction of the WAC Bennett Dam, winds have picked up fine particles of silts and clays ( dust ) from the exposed drawdown zone of the Finlay Reach of the reservoir. This aerial movement of particulates is of concern to residents and users of the area, particularly the Tsay Keh Dene (TKD) and Kwadacha First Nations (KFN). The village of Tsay Keh, a community of approximately 200 people, is located at the northern tip of Williston Reservoir; Kwadacha is located approximately 100 km north of the village (Figure 1-1). The large variation between full and low pool on Williston Reservoir, coupled with the reservoir topography, exposes up to 31,000 ha of drawdown zone (between elevations 672 m and 656 m) in the Finlay and upper Parsnip arms. Not all of this area is dust source beach; approximately 20,000 ha may contribute to aeolian dust erosion in extreme years, and an estimated 5,000 ha typically contributes the majority of the dust. The annual low elevation of the reservoir typically occurs in April and the majority of the beaches are flooded again by June. Some very high elevation beaches are flooded only in very high-pool years. The beaches are exposed to wind erosion for between two weeks and three months each year. This period of beach exposure to wind varies depending upon water levels, the reservoir recharge rate, and ice coverage of beaches. The beaches are composed of sand, silt, and clay in different proportions depending upon the beach. The beach soils are replenished each year as sediment carried into the reservoir settles out. The soils are very loose and have few nutrients, restricting plant growth. The short growing season (late May until flooded by the rising water) and cool temperatures typical of this northern high latitude also limits vegetation. Aeolian erosion of the beaches and consequent transport of suspended particulates was recognized as a WUP issue by the Peace WUP Committee (the Committee ) and two physical works projects, together with this monitoring program, were recommended by the Committee. Additional data about this issue have become available since the Committee Report was issued in BC Hydro Page 2
3 In 2007, BC Hydro, together with the TKD, contracted six outside experts in wind erosion and related issues to examine the emission of dust from Williston Reservoir and to propose a plan for mitigating those emissions. Those experts provided the Proposed Dust Mitigation Implementation Plan for Williston Reservoir, dated June 20, 2007 (the Experts Report ). That report recommended a strategy based upon tillage of dust source beaches, supplemented by irrigation and wetland/vegetation-use where appropriate. The Experts Report also recommended a regional air monitoring protocol to meet the WUP Committee s dust control audit proposal that formed the basis of this project. The experts have hypothesised that little dust comes directly from the reservoir banks but the results of the Dust Monitoring, the experts work in the field as part of the Williston Dust Mitigation Program, of which this project is a part (including the Dust Control Trials), and the subsequent long-term planning for the Williston Dust Mitigation Program, may suggest that specific work on dust emissions from those banks should be investigated. 1.2 First Nations Involvement This ToR was developed through a joint planning process between BC Hydro and TKD following consultation with the team of wind erosion experts. Once developed, the ToR underwent internal review by BC Hydro and Tsay Keh Dene First Nation. An external review process followed the internal review providing First Nations (FNs), stakeholders, and government agencies including Fisheries and Oceans Canada (DFO) and Ministry of Environment with an opportunity to comment on this document. Implementation of this project provides an opportunity for FNs to build capacity and knowledge related to dust monitoring methodologies. It is anticipated that the FNs will be actively involved by providing personnel and local knowledge, as well as learning about the project. To facilitate transfer of knowledge, effort will be made to include FNs personnel in all aspects of the project. At a minimum, it is expected that the FNs personnel will engage in all duties typical of a field assistant in projects of this nature. Costs associated with FNs labour are a component of the overall project costs. BC Hydro Page 3
4 Figure 1-1: Place Names in Peace Water Use Plan Finlay Reach BC Hydro Page 4
5 Figure 1-2: Finlay Reach Beaches BC Hydro Page 5
6 1.3 Management Questions The key management question is: What is the impact of dust mitigation treatments on aeolian dust emission from the Finlay Reach of Williston Reservoir? The Committee did not identify a specific management question to be addressed for this project. However, the Dust Control Monitoring Program has been designed to provide data to measure the effectiveness of the mitigation measures (including Dust Control Trials) in the Finlay Reach. As recommended by the Committee, trial and control sites will be used to assess the impact of dust mitigation treatments as baseline data is unavailable. 1.4 Management Study Hypothesis No specific hypothesis was recommended by the WUP Committee, however the primary hypothesis 1 being tested by this study is: H 1 : Dust mitigation measures carried out pursuant to the BC Hydro/FNs Williston Dust Mitigation Program (including measures carried out as part of the Dust Control Trials) significantly reduce the emission of wind-blown dust from the Williston Reservoir drawdown zone in the Finlay Reach. 1.5 Key Water Use Decision Affected The results of this project will provide input into both adaptive management of dust mitigation in Williston Reservoir and future water use decisions respecting dust control. 2.0 MONITORING PROGRAM PROPOSAL 2.1 Objective and Scope The objectives of the monitoring program is to address the management question identified in Section 1.2 by collecting the data necessary to draw inferences and to test the hypothesis outlined in Section 1.3. In addition, the monitoring program will: 1) Provide long-term data on airborne particulate matter concentrations in the upper Finlay Reach airshed; and 2) Evaluate the effectiveness of dust mitigation treatments in the Finlay Reach drawdown zone of Williston Reservoir. Six instrument packages consisting of air quality monitors and meteorological instruments will be installed in selected sites commencing in April Equipment will be provided by BC Hydro (purchased in advance of receiving Leave to Commence due to long lead times). Measurements will be taken between early 1 For clarity, the hypotheses are stated as the alternate hypotheses. Analyses will test the null hypotheses of no effect or difference. BC Hydro Page 6
7 spring and full pool each year commencing 2008 and terminating 2017 (10 years). Instrumentation will be installed and removed annually. 2.2 Approach Instrumentation will be installed at selected beach sites and one non-beach control site each year over the 10-year project (or for so long as dust mitigation measures are carried out in the Finlay Reach of Williston Reservoir, but for at least the three years of the Dust Control Trials). Data will be downloaded at regular intervals. An annual report will summarize daily air quality measurements and draw conclusions on the effectiveness of the mitigation measures. Equipment has been acquired in advance of this ToR due to long lead times for procurement and testing. For at least the first three years of this project, equipment maintenance and calibration will be provided by the University of Guelph. 2.3 Methods Task 1: Project Coordination Project coordination will involve the general administrative and technical oversight of the project. This task will include but not be limited to: 1) budget management, 2) study team management, 3) logistic coordination, 4) technical oversight of field and analysis components, 5) annual maintenance and calibration of the instruments, and 6) reporting. Data may also be useful to other projects so it will be made available to other investigators within the WUP projects if appropriate Task 2: Installation and Downloading of Data Instrumentation will be installed at sites selected as appropriate by Dr. Bill Nickling or his substitute. Currently proposed sites include Omineca Flats, Corless Bay, Tsay Keh, Van Somer Point, and Middle Creek South beaches, as well as one non-beach control site. Instruments will be downloaded at all sites on a weekly basis. Instrumentation at each site will include: single RM Young wind anemometer (speed and direction), data logger (CR 1000), partisol dictomus sampler (+2025 model) with 10 μm and 2.5 μm cuts. One 24-hour composite sample will be measured each day with filter retrieval done daily. These will be powered by a solar array, wind generator, and batteries. Rainfall, temperature, and relative humidity will also be measured hourly. Instrumentation will be installed as early as practicable each spring at relatively high locations on each beach and will be removed before the site is flooded by the rising reservoir (being the end of the dust season) Task 3: Maintenance of Equipment For at least the first three years of the project, equipment will be shipped to the University of Guelph at the end of each season for maintenance and calibration. Thereafter equipment will be subject to appropriate annual maintenance and calibration for the remainder of the life of this project. BC Hydro Page 7
8 Maintenance and calibration of all equipment will be performed according to manufacturer specifications. Records will be kept to track maintenance and calibration activities Task 4: Data Analysis All data will be entered into an appropriate database (Microsoft Excel or Access). Statistical analysis will entail assessing spatial and temporal variation in air quality along study sites within the Finlay Reach Task 5: Reporting Project reporting will consist of a series of annual data reports and a single final report at the conclusion of the monitoring program. Reporting will include: a) an executive summary of the project; b) description of field locations and map identifying sites; c) methods used to collect and analyze the data; d) data collected, presented in tabular and graphical form; e) results of analyses; f) an assessment of the findings as they relate to the management question and hypothesis; g) description of maintenance activities for equipment; and h) any recommendations towards future monitoring (if any) needed. A report will be provided in hard-copy and as Microsoft Word and Adobe Acrobat (*.pdf) format. The required maps and figures will included as embedded objects in the report. All maps and figures will also be provided in their native format as separate files. Raw data will be submitted in a Microsoft Excel or Access database. 2.4 Interpretation of Results The observations from the project will assist in the adaptive management of dust mitigation strategies in the Finlay Reach, both the related Dust Control Trials and other non-wup dust mitigation measures. 2.5 Schedule Instrumentation has been purchased in advance of Leave to Commence for this project because of the long lead times for procurement and equipment setup and calibration. Instruments will be installed at study sites annually beginning in 2008, during the 10-year monitoring program, in early spring with downloading and maintenance of equipment occurring every week. Instruments will be removed from study sites annually once the reservoir rises sufficiently to inundate the majority of the dust beaches. Monitoring is scheduled to occur annually over the life of the study. Equipment will be calibrated and maintained over the study period on an annual basis, initially by the University of Guelph. BC Hydro Page 8
9 2.6 Budget The estimated cost for the monitoring program in Year 1 is $642,192 (Table 3-1). The preliminary estimated total costs of the project for the remaining nine years is $2,702,929 (Table 3-2). Costs following Year 1 are uncertain and subject to change based on the results of this monitoring program and WLL Dust Control Trials. Assuming estimates are accurate, the total cost of the program over 10-year period is $3,345,121 (including 2% inflation). Table 3-1: Estimated Cost of the Dust Control Monitoring Program in Year 1 Total $642,192 Table 3-2: Preliminary Estimated Annual Cost of the Dust Control Monitoring Program following Year 1 Sub-total $2,444,929 Inflation 2% $258,000 Total $2,702,929 BC Hydro Page 9
Physical Works Terms of Reference
Physical Works Terms of Reference Williston Targeted Debris Management GMSWORKS #22 Order/Clause: Schedule A 3 (c ) and 5 (a) November 26, 2008 1.0 Introduction Terms of Reference for the Peace Water Use
More informationWilliston Dust Control Trials and Monitoring
Williston Dust Control Trials and Monitoring GMSMON-18 Williston Dust Control Monitoring Study GMSWORKS-20 Williston Dust Mapping Project GMSWORKS-21 Williston Dust Control Trial Project Williston Dust
More informationPeace Project Water Use Plan Physical Works Terms of Reference
Peace Project Water Use Plan Physical Works Terms of Reference GMSWORKS-16 Williston Reservoir Wetlands Inventory GMSWORKS-17 Williston Reservoir Trial Wetland April 21, 2008 Terms of Reference for the
More informationPeace Water Use Plan Spill Protocol and Archaeology Management Plan
Peace Water Use Plan Spill Protocol and Archaeology Management Plan Monitoring Programs and Physical Works Annual Report 2017 Implementation Period: June 2016 to August 2017 GMSMON-3 PCR Fish Stranding
More informationCollected Contractor Annual Reports for GMSMON#18 Williston Dust Control and GMSWORKS#21 WLL Dust Control Trials Implementation Year 2
Peace Project Water Use Plan Collected Contractor Annual Reports for GMSMON#18 Williston Dust Control and GMSWORKS#21 WLL Dust Control Trials Implementation Year 2 Reference: GMSWORKS#21 WLL Dust Control
More informationPhysical Works Terms of Reference
Peace Project Water Use Plan Physical Works Terms of Reference District of Mackenzie Effluent Discharge Feasibility and Design Study GMSWORKS #28a 23 November 2009 Terms of Reference for the Peace Water
More informationColumbia River Project Water Use Plan. Monitoring Program Terms of Reference KINBASKET RESERVOIR FISH AND WILDLIFE INFORMATION PLAN
Columbia River Project Water Use Plan Monitoring Program Terms of Reference KINBASKET RESERVOIR FISH AND WILDLIFE INFORMATION PLAN CLBMON-4 Kinbasket Reservoir Fish Stranding Assessment 24 October 2007
More informationTitle: A Feasibility Study for the Development of a RADARSAT-2 Dust Prediction System
Peace River Project Water Use Plan Title: A Feasibility Study for the Development of a RADARSAT-2 Dust Prediction System Reference GMSWORKS-20 Implementation Year 4 A Feasibility Study for the Development
More informationPeace Project Water Use Plan Peace River Spill Hydrology
Peace Project Water Use Plan Peace River Spill Hydrology Reference: GMSMON-9 Study Period: July 2009 July 2011 PRE-SPILL REPORT Northwest Hydraulic Consultants Ltd. 30 Gostick Place North Vancouver, BC
More informationTitle: A Feasibility Study for the Development of a RADARSAT-2 Dust Prediction System
Peace River Project Water Use Plan Title: A Feasibility Study for the Development of a RADARSAT-2 Dust Prediction System Reference GMSWORKS-20 Implementation Year 3 A Feasibility Study for the Development
More informationMonitoring Program Terms of Reference REVELSTOKE FLOW MANAGEMENT PLAN
Columbia River Project Water Use Plan Monitoring Program Terms of Reference REVELSTOKE FLOW MANAGEMENT PLAN CLBMON-18 Middle Columbia River Adult Fish Habitat Use Revisions May 12, 2010 Revised Terms of
More informationAlouette Project Water Use Plan Monitoring Program Terms of Reference
Monitoring Program Terms of Reference ALUMON#1 Smolt Enumeration ALUMON#2 Kokanee Out-migration ALUMON#3 Substrate Quality ALUMON#4 Sockeye Adult Enumeration ALUMON#5 Water Temperature ALUMON#6 Kokanee
More informationMonitoring Program Terms of Reference REVELSTOKE FLOW MANAGEMENT PLAN
Columbia River Project Water Use Plan Monitoring Program Terms of Reference REVELSTOKE FLOW MANAGEMENT PLAN CLBMON-17 Middle Columbia River Juvenile Fish Habitat Use Revisions May 12, 2010 Revised Terms
More informationMonitoring Program Terms of Reference
Columbia River Project Water Use Plan Monitoring Program Terms of Reference Revelstoke Flow Management Plan CLBMON-17 Middle Columbia River Juvenile Fish Habitat Use Addendum 2 January, 2017 Addendum 2
More informationCampbell River Project Water Use Plan Physical Works Terms of Reference
Campbell River Project Water Use Plan Physical Works Terms of Reference JHTWORKS-2 Upper Campbell Lake Reservoir and Campbell Lake Reservoir Recreation Facility Upgrade Feasibility January 2016 Campbell
More informationPHYSICAL ENVIRONMENT MONITORING P LAN DRAFT
Aquatic Effects Monitoring Plan PHYSICAL ENVIRONMENT MONITORING P LAN DRAFT October 2012 POINTE DU BOIS SPILLWAY REPLACEMENT PROJECT Physical Environment Monitoring Plan DRAFT Report Prepared for October
More informationBC Hydro Provincial Integrated Electricity Planning Committee Meeting 3 (March 15-16, 2005)
BC Hydro Provincial Integrated Electricity Planning Committee Meeting 3 (March 15-16, 2005) Information Sheet #3 Follow up Questions from Meeting 2 Willisn Reservoir Constraints. Willisn Reservoir was
More informationColumbia River Project Water Use Plan. Monitoring Program Terms of Reference COLUMBIA RIVER WHITE STURGEON MANAGEMENT PLAN
Columbia River Project Water Use Plan Monitoring Program Terms of Reference COLUMBIA RIVER WHITE STURGEON MANAGEMENT PLAN CLBMON-27: Mid Columbia River Sturgeon Incubation and Rearing Study January 7,
More informationJordan River Project Water Use Plan. Monitoring Program Terms of Reference. Addendum 1 to JORMON-01 Lower Jordan River Inflow Monitoring
Jordan River Project Water Use Plan Monitoring Program Terms of Reference Addendum 1 to JORMON-01 Lower Jordan River Inflow Monitoring May 2007 1 Monitoring Program Rationale 1.1 Background Lower Jordan
More informationModule 2 Measurement and Processing of Hydrologic Data
Module 2 Measurement and Processing of Hydrologic Data 2.1 Introduction 2.1.1 Methods of Collection of Hydrologic Data 2.2 Classification of Hydrologic Data 2.2.1 Time-Oriented Data 2.2.2 Space-Oriented
More informationTHE CLEAN WATER FACTORY:
THE CLEAN WATER FACTORY: Green infrastructure in Our Watersheds KEY CONCEPTS METHOD SUSTAINABILITY OF WATER RESOURCES REQUIRES CONSERVATION AND BEST MANAGEMENT PRACTICES. RESPONSIBILITY FOR WATER IS EVERYONE
More informationC-1. Received DC Office August 17/16. Hello,
Received DC Office August 17/16 From: Dayle Hopp [mailto:dayle.hopp@bchydro.com] Sent: Wednesday, August 17, 2016 10:55 AM To: Chris Cvik Subject: Information Update - 1 of 2 Hello,
More informationClowhom Project Water Use Plan Monitoring Programs Annual Report: For Water Licenses , and Conditional Water License
Monitor of Aquatic Wildlife in Wetlands Affected by Dam Operations Role of Littoral Zone in Governing Clowhom Reservoir Productive Capacity Validation of the Effective Littoral Zone Performance Measure
More informationMethylmercury Monitoring Plan. For Surface Water Quality. Muskrat Falls Reservoir, Churchill River and Lake Melville
DOC-2016-298 Methylmercury Monitoring Plan For Surface Water Quality Muskrat Falls Reservoir, Churchill River and Lake Melville Initial Plan Prepared: October 17, 2016 Revised: December 19, 2016 Introduction:
More informationBAEN 673 / February 18, 2016 Hydrologic Processes
BAEN 673 / February 18, 2016 Hydrologic Processes Assignment: HW#7 Next class lecture in AEPM 104 Today s topics SWAT exercise #2 The SWAT model review paper Hydrologic processes The Hydrologic Processes
More informationAir Monitoring Plan for Ground Intrusive Activities at the Various PPG Hexavalent Chromium Sites in New Jersey
Environment Submitted to: Submitted by: PPG Industries Inc. AECOM Jersey City, NJ Piscataway, NJ 60149955-4010A May 14, 2012 Air Monitoring Plan for Ground Intrusive Activities at the Various PPG Hexavalent
More informationDryland Degradation by Wind Erosion
GEO3-4304 Land Degradation Dryland Degradation by Wind Erosion Geert Sterk Department of Physical Geography Utrecht University Dryland degradation by wind erosion and its control Paper by G. Sterk, M.
More informationAmisk Hydroelectric Project Update
Amisk Hydroelectric Project Update AHP Development Corporation (AHP) is providing an update on the Amisk Hydroelectric Project ( Amisk /the Project ). Amisk is a proposed run-of-river hydroelectric project,
More informationEXECUTIVE SUMMARY. Executive Summary. Introduction to Water Use Planning
EXECUTIVE SUMMARY Executive Summary Introduction to Water Use Planning Water Use Planning was announced in 1996 to ensure that provincial water management decisions reflect changing public values and environmental
More informationThe Bridge River flows into the Fraser River near Lillooet. The Bridge River hydroelectric system is complex, comprised of:
EXECUTIVE SUMMARY A Water Use Plan (WUP) is a technical document that, once reviewed by provincial and federal agencies and accepted by the provincial Comptroller of Water Rights, defines how water control
More informationColumbia River Project Water Use Plan. Monitoring Program Terms of Reference
Columbia River Project Water Use Plan Monitoring Program Terms of Reference COLUMBIA RIVER WHITE STURGEON MANAGEMENT PLAN CLBMON-20 Mid Columbia River White Sturgeon Spawning Habitat Assessment 22 February
More informationDuncan Dam Project Water Use Plan Monitoring Program Terms of Reference. DDMMON-16 Lower Duncan River Fish Stranding Impact Monitoring
Duncan Dam Project Water Use Plan Monitoring Program Terms of Reference DDMMON-16 Lower Duncan River Fish Stranding Impact Monitoring April 24, 2008 Monitoring Program Terms of Reference 2008-04-24 1.0
More informationPeace Project Water Use Plan. Peace River Hydraulic Model. Reference: GMSWORKS Status Update. Study Period: August 2011 to December 2011
Peace Project Water Use Plan Peace River Hydraulic Model Reference: GMSWORKS-5 2011 Status Update Study Period: August 2011 to December 2011 Northwest Hydraulic Consultants Ltd. 30 Gostick Place, North
More informationAir Quality Near Railway Lines Used by Coal Trains
June 2016 Air Quality Near Railway Lines Used by Coal Trains Preliminary Summary of Data from White Rock and Delta This report was prepared by the Air Quality and Climate Change Division of Metro Vancouver.
More informationANNEXURE- II Proposed TOR
ANNEXURE- II Proposed TOR Annexure II Terms of Reference for EIA for Setting up of Ligno-Cellulosic Biomass based second generation (2G) Ethanol Bio-Refinery with capacity of 100 KLPD at village-sainjani,
More informationMonitoring Programs Annual Report: 2008
Ash River Project Water Use Plan Assessment of Adult Fish Passage at Dickson Falls During Pulse Flow Releases from Elsie Lake Dam Elsie Reservoir Archaeological Investigations For Water Licences FL119975
More informationAmbient Air and Sound. Monthly Report
Ambient Air and Sound Monthly Report July 2018 1 Table of Contents Introduction... 2 STAR Monitor Summary... 3 Particulate and Metrological Data... 3 Noise Data... 3 Appendix A Monitor Information... 5
More informationV: PROJECT SCOPING & METHODOLOGY
V: PROJECT SCOPING & METHODOLOGY 5.0 INTRODUCTION The scoping exercise is carried out to define the focus and scope of the EIA Study. The scoping exercise is required to understand the type of activities
More informationMonitoring Programs Annual Report: 2009
Ash River Project Water Use Plan Assessment of Adult Fish Passage at Dickson Falls during Pulse Flow Releases from Elsie Lake Dam Elsie Reservoir Archaeological Investigations For Water Licences FL119975
More informationEvaluating Environmental Monitoring Applications of Low-Cost Sensors for
Evaluating Environmental Monitoring Applications of Low-Cost Sensors for Electric Utilities A look at the potential applications for new low-cost sensors in industrial environmental monitoring. A variety
More informationBridge-Seton Water Use Plan. Monitoring Program Terms of Reference. BRGMON-12 Bridge-Seton Metals and Contaminant Monitoring Program
Monitoring Program Terms of Reference BRGMON-12 Bridge-Seton Metals and Contaminant Monitoring Program March 29, 2012 Bridge-Seton Water Use Plan Monitoring Program No. BRGMON-12 Bridge-Seton Metals and
More informationODEQ FINAL 401 WATER QUALITY CERTIFICATION QUESTIONS AND ANSWERS
ODEQ FINAL 401 WATER QUALITY CERTIFICATION QUESTIONS AND ANSWERS September 10, 2018 What does the ODEQ 401 Water Quality Certification mean for KRRC? The Oregon Department of Environmental Quality (ODEQ)
More informationManagement Modeling of Suspended Solids and Living Resource Interactions
Management Modeling of Suspended Solids and Living Resource Interactions Carl Cerco 1, Mark Noel 1, Sung-Chan Kim 2 1 Environmental Laboratory, US Army ERDC, Vicksburg MS, USA 2 Coastal and Hydraulics
More informationPeace Water Use Plan Dinosaur Reservoir Management Plan
Peace Water Use Plan Dinosaur Reservoir Management Plan Monitoring Programs and Physical Works Annual Report 2017 Implementation Period: June 2016 to May 2017 GMSMON-14 DNR Tributary Habitat Review GMSWORKS-8
More informationAmbient Air and Sound. Monthly Report
Ambient Air and Sound Monthly Report September 2018 1 Table of Contents Introduction... 2 STAR Monitor Summary... 3 Particulate and Metrological Data... 3 Noise Data... 3 Appendix A Monitor Information...
More informationCoquitlam-Buntzen Water Use Plan
Monitoring Program Terms of Reference COQMON#6 Lower Coquitlam River Temperature Monitoring Initial submission: October 24, 2005 Revision 1: December 14, 2006 December 14, 2006 Terms of Reference for the
More informationMONTHLY FIELD STUDIES SUMMARY
The Site C Clean Energy Project is continuing to conduct environmental and engineering field studies on and around the Peace River between the Williston Reservoir and the Alberta border to inform detailed
More informationPhysical Works Recommendation Report
Physical Works Recommendation Report JHTWORKS-2 Upper and Lower Campbell Lake Recreation Facility Redevelopment Recommendation Report from Identification/Feasibility Phase Addendum 1 October 11, 2017 JHTWORKS-2
More informationBridge-Seton Water Use Plan. Monitoring Program Terms of Reference. BRGMON-9 Seton River Habitat and Fish Monitoring
Bridge-Seton Water Use Plan Monitoring Program Terms of Reference BRGMON-9 Seton River Habitat and Fish Monitoring January 23, 2012 Bridge Seton Water Use Plan Monitoring Program No. BRGMON-9 Seton River
More informationDoig River First Nation ~56 Rose Prairie, B.C. VOC 2HO Ph: (250) 82'7-3'7'76 Fax: (250) 82'7-3'7'78
Doig River First Nation ~56 Rose Prairie, B.C. VOC 2HO Ph: (250) 82'7-3'7'76 Fax: (250) 82'7-3'7'78 November 16, 2015 Shauna Sigurdson, Regional Director, Prairie and Northern Region Canadian Environmental
More informationAir and Dust Monitoring Summary Report
Toronto Transit Commission Air and Dust Monitoring Summary Report Monitoring Period: 1 February 28 February 2014 Air quality monitoring is currently ongoing as part of the dust control program associated
More informationClowhom Lake Water Use Plan. Clowhom Lake Wildlife Census. CLOW-WUP-Wildlife. Year 4. Study Period: April 1, 2009 March 31, 2010
Clowhom Lake Water Use Plan Clowhom Lake Wildlife Census CLOW-WUP-Wildlife Year 4 Study Period: April 1, 2009 March 31, 2010 D.J. Bates and G. Ferguson Resource Management Department shíshálh Nation PO
More informationIndependent Expert Engineering Investigation and Review Panel. Report on Mount Polley Tailings Storage Facility Breach. Appendix G: Water Balance
Independent Expert Engineering Investigation and Review Panel Report on Mount Polley Tailings Storage Facility Breach Appendix G: Water Balance January 30, 2015 Report on Mount Polley Tailings Storage
More informationFACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods.
1 FACTSHEET INTRODUCTION World Water Day, on 22 March every year, is about focusing attention on the importance of water. This year s theme, Nature for Water, explores nature-based solutions (NBS) to the
More informationThe Construction General Permit and Erosion Prevention and Sedimentation Control
The Construction General Permit and Erosion Prevention and Sedimentation Control Presented at the Tennessee Gas Association Conference April 23, 2008 More than thirty years ago, two-third of the nation's
More informationSTORMWATER MONITORING GUIDELINES SOUTH OF DUNDAS STREET OPERATION, MAINTENENACE AND MONITORING OF STORMWATER MANAGEMENT PONDS
STORMWATER MONITORING GUIDELINES SOUTH OF DUNDAS STREET OPERATION, MAINTENENACE AND MONITORING OF STORMWATER MANAGEMENT PONDS STORMWATER MONITORING GUIDELINES: Operation, Maintenance and Monitoring Of
More informationColumbia River Project Water Use Plan. Monitoring Program Terms of Reference KINBASKET RESERVOIR FISH AND WILDLIFE INFORMATION PLAN
Columbia River Project Water Use Plan Monitoring Program Terms of Reference KINBASKET RESERVOIR FISH AND WILDLIFE INFORMATION PLAN CLBMON-44 Lower Columbia River Physical Habitat and Ecological Productivity
More informationEvent and Continuous Hydrological Modeling with HEC- HMS: A Review Study
Event and Continuous Hydrological Modeling with HEC- HMS: A Review Study Sonu Duhan *, Mohit Kumar # * M.E (Water Resources Engineering) Civil Engineering Student, PEC University Of Technology, Chandigarh,
More informationLGL Limited. February 15, Mr. Trevor Proverbs Site C Clean Energy Project PO Box 2218 Vancouver, BC V6B 3W2
LGL Limited Mr. Trevor Proverbs Site C Clean Energy Project PO Box 2218 Vancouver, BC V6B 3W2 9768 Second Street Sidney, BC CANADA V8L 3Y8 Tel: (250) 656-0127 Fax: (250) 655-4761 www.lgl.com February 15,
More informationWASA Quiz Review. Chapter 2
WASA Quiz Review Chapter 2 Question#1 What is surface runoff? part of the water cycle that flows over land as surface water instead of being absorbed into groundwater or evaporating Question #2 What are
More informationGREAT BASIN UNIFIED AIR POLLUTION CONTROL DISTRICT 157 Short Street, Bishop, California Fax:
Phillip L. Kiddoo Air Pollution Control Officer GREAT BASIN UNIFIED AIR POLLUTION CONTROL DISTRICT 157 Short Street, Bishop, California 93514-3537 760-872-8211 Fax: 760-872-6109 REASONABLE FURTHER PROGRESS
More informationRequest Number 9: Accidents & Malfunctions Dam Safety Cumulative Effects
Request Number 9: Accidents & Malfunctions Dam Safety Cumulative Effects References: EIS Guidelines Sec. 23.2; EIS Vol. 5, Section 37.2; EIS, Vol. 6, Technical Memo Dam Safety; Meeting Notes BC Hydro,
More informationSpecial Provision - Turbidity
1. DEFINITIONS Special Provision - Turbidity Instream Construction Activity Isolated Construction Activity Site Isolation Visually Conspicuous Plume Accidental Occurrence Any planned instream construction
More informationMETHODS PAPER: River Transect Sampling of Physical Attributes Downstream of the Mactaquac Generating Station
Mactaquac Aquatic Ecosystem Study Report Series 2015-014 METHODS PAPER: River Transect Sampling of Physical Attributes Downstream of the Mactaquac Generating Station Mark Gautreau, Ben Wallace, and Tommi
More informationRules of the South Florida Water Management District EVERGLADES PROGRAM Chapter 40E-63, F.A.C.
Rules of the South Florida Water Management District EVERGLADES PROGRAM Chapter 40E-63, F.A.C. Samira Daroub BMP Training April 11, 2013 Everglades Research and Education Center Outline The Everglades
More informationEnvironmental Monitoring of Village Contaminated by Radionuclides
Environmental Monitoring of Village Contaminated by Radionuclides Masaru Mizoguchi Graduate School of Agricultural and Life Sciences The University of Tokyo amizo@mail.ecc.u-tokyo.ac.jp Tetsu Ito Division
More informationProposed G3 Terminal Vancouver Project Update. Presented to North Shore Waterfront Liaison Committee January 14, 2016
Proposed G3 Terminal Vancouver Project Update Presented to North Shore Waterfront Liaison Committee January 14, 2016 G3 & G3 Terminal Vancouver G3 formed to invest in Canada s grain sector by establishing
More informationElko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights
Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights 7 April 2005 B Elko Project Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Elko Project
More informationAsh River Project Water Use Plan
Monitoring Program and Physical Works Annual Report: 2012 Implementation Period: October 2011 to September 2012 ASHMON-1 Assessment of Adult Fish Passage at Dickson Falls during Pulse Flow Releases from
More informationRequest for Proposal. Upper Arden Dam Dam Break Analysis
Request for Proposal For Upper Arden Dam Dam Break Analysis In Central Frontenac Township Requested by Quinte Conservation Authority October 14 th, 2016 Typographical Update: October 20 th, 2016 RfP Contact:
More informationATTACHMENT C RISK LEVEL 1 REQUIREMENTS
ATTACHMENT C RISK LEVEL 1 REQUIREMENTS A. Effluent Standards [These requirements are the same as those in the General Permit order.] 1. Narrative Risk Level 1 dischargers shall comply with the narrative
More informationFisheries and Aquatic Habitat Monitoring and Follow-up Program Annual Report: Dec 22, 2015 to Dec 31, 2016
Fisheries and Aquatic Habitat and Follow-up Annual Report: Dec 22, 2015 to Dec 31, 2016 Site C Clean Energy Project March 1, 2017 Table of Contents 1.0 Introduction... 3 1.1 Background... 3 1.2 Summary...
More informationGROUND WATER/SURFACE WATER INTERACTIONS 1-3 AWRA SUMMER SPECIALTY CONFERENCE 2002
JULY GROUND WATER/SURFACE WATER INTERACTIONS 1-3 AWRA SUMMER SPECIALTY CONFERENCE 2002 32bLg Pd6 IMPLEMENTING ADAPTIVE MANAGEMENT OF WATER RESOURCES IN THE ST. JOHNS RIVER WATER MANAGEMENT DISTRICT. William
More informationWATER AND THE HYDROLOGIC CYCLE
WATER AND THE HYDROLOGIC CYCLE Summary Water is essential for the support of life and can be considered as a fundamental environmental good. Water is needed to support human habitation, grow crops and
More informationJordan River Water Use Plan
Monitoring Programs and Physical Works Annual Report: 2010 Implementation Period: December 2009 to November 2010 JORMON-1 Lower Jordan River Inflow Monitoring JORMON-2 Fish Index: Lower Jordan River JORMON-3
More informationGunlake Quarry. Air Quality Management Plan
Gunlake Quarry Air Quality Management Plan August 2015 Table of Contents 1. Introduction 3 1.1 Overview 3 1.2 Aims and Objectives 3 2. Air Quality Criteria 3 2.1 Impact Assessment Criteria 4 2.2 Sources
More informationAPPENDIX 2. Nova Scotia Department of Environment and Labour Environmental Assessment Terms and Conditions for Environmental Assessment Approval
APPENDIX 2 Nova Scotia Department of Environment and Labour Terms and Conditions for Approval Approval Approval Date: March 14, 2007 Keltic Petrochemicals Inc. LNG and Petrochemical Plant Facilities Keltic
More informationSummary of Water Monitoring Data
Clay County Drainage Site Summary of Water Monitoring Data 2011 2015 Introduction The Red River Valley in northwestern Minnesota is experiencing an increase in the amount of agricultural subsurface drainage
More informationSubject: - Development of Fisheries Floating Nets for Resettlement Program of Hydropower Project Cirata Dam
IEA Hydropower Implementing Agreement Annex VIII - Hydropower Good Practices: Environmental Mitigation Measures and Benefits Case Study 14-05: Development of Regional Industries Cirata Hydro Electric Power
More informationBlack River Watershed Management Plan Plan
Black River Watershed Management Plan Plan Final Report Part II: Appendices May 2010 This watershed management plan was prepared for the New York State Department of State Division of Coastal Resources
More informationWhat we do. About our facility. About Weir. Why what we do is important
What we do About Weir About our facility Why what we do is important Weir Canada has been operating in Metro Vancouver since 2013 when we acquired the long established R. Wales Company. We are a leading
More informationGeographical & Hydrological Information System of the Sava River Basin. Sava GIS & Sava HIS. Overview
Geographical & Hydrological Information System of the Sava River Basin Sava GIS & Sava HIS Overview Mirza Sarač International Sava River Basin Commission - ISRBC Secretariat Protocol on flood protection
More informationCity of Daphne, Alabama Water Quality Monitoring Plan For Phase II MS4
City of Daphne, Alabama Water Quality Monitoring Plan For Phase II MS4 2016-2021 Permit # ALR 040039, Expiration Date: September 30, 2021 I. Introduction This document presents the City of Daphne s Stormwater
More informationCattle Temporal & Spatial Distribution in Midwestern Pastures Using Global Positioning (A Three-Year Progress Report)
Cattle Temporal & Spatial Distribution in Midwestern Pastures Using Global Positioning (A Three-Year Progress Report) A.S. Leaflet R258 Douglas A. Bear, research assistant; Jim Russell, professor of animal
More informationbeneficial management practices
beneficial management practices introduction Phosphorus is an essential nutrient for crop growth. Alberta soils are generally deficient or low in phosphorus for optimum crop production (
More informationPomeroy Hotel, Fort St. John (11308 Alaska Road) Attending open houses Providing feedback online: Hudson s Hope.
WELCOME Project Definition Consultation APRIL 10 MAY 31, 2012 We Want to Hear From You Project Definition Consultation, Spring 2012 takes place April 10 through May 31, 2012. Consultation materials are
More information(b) Water Engineering Basics
NRRI Training for the Oklahoma Corporation Commission March 14-16, 2017 Topic 3 (b) Water Engineering Basics Kathryn J. Kline Research Associate National Regulatory Research Institute kkline@nrri.org Industry
More informationApplication of AnnAGNPS to model an agricultural watershed in East-Central Mississippi for the evaluation of an on-farm water storage (OFWS) system
Application of AnnAGNPS to model an agricultural watershed in East-Central Mississippi for the evaluation of an on-farm water storage (OFWS) system Ritesh Karki a, Mary Love M. Tagert a, Joel O. Paz a,
More informationInformation Requirements Table for Liquid Waste
Applicant Summary Tracking # Authorization # Applicant / Facility Name Ministry of Environment Prepared by: Title Date The Information Requirements Table (IRT) for Liquid Waste is a tool used by Ministry
More informationFebruary/March 2015 Air Quality Report Burma Road Site
February/March 2015 Air Quality Report Burma Road Site Attached is a technical summary of air quality data for February/March 2015 at the Burma Road cleanup site submitted by PPG Industries air monitoring
More informationFEEDBACK FORM INSIDE. Peace River Site C Hydro Project. B.C. s growing electricity gap. and Feedback Form
FEEDBACK FORM INSIDE Peace River Site C Hydro Project An option to help close B.C. s growing electricity gap Pre-Consultation Discussion Guide and Feedback Form DECEMBER 2007 SITE C Pre-Consultation Discussion
More informationCS229 Project: Identifying Regions of High Turbidity in San Francisco Bay
CS229 Project: Identifying Regions of High Turbidity in San Francisco Bay Joe Adelson December 11, 2014 Introduction Suspended sediments in oceans, seas, and estuaries shape coastal geography, provide
More informationYes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e)
Checklist: 3. Hydropower Stations, Dams and Reservoirs (1) 1 Permits and Explanation 2 Pollution Control (1) EIA and Permits (2) Explanation to the Local Stakeholders Main Check s Have EIA reports been
More informationColumbia River Project Water Use Plan Kinbasket Fish and Wildlife Information Plan
Kinbasket Fish and Wildlife Information Plan Monitoring Programs Annual Report: 2014 Implementation Period: January 2013 to December 2013 CLBMON-1 Mica Dam Total Gas Pressure Monitoring and Abatement Program
More informationEIS TABLE OF CONTENTS
EIS TABLE OF CONTENTS GLOSSARY OF TERMS... GL-1 Glossary and Abbreviations... GL-1 Units... GL-14 EXECUTIVE SUMMARY... ES-1 INTRODUCTION... ES-1 PROJECT PROPONENTS... ES-1 LOCATION... ES-1 PROJECT DESCRIPTION...
More informationAnalysis of GPS Position Data of Beef Cattle
Analysis of GPS Position Data of Beef Cattle Benjamin K. Koostra, Carmen T. Agouridis, and Stephen R. Workman Biosystems and Agricultural Engineering University of Kentucky Lexington, Kentucky Abstract
More information6.5 Extended Detention Basin
6.5 Extended Detention Basin Figure 6-22: Extended Detention Basin. Photograph courtesy of Bill Southard (DES Architects and Engineers) Best uses Detain low flows Can be expanded to detain peak flows Sedimentation
More informationHYDROPOWER DEVELOPMENT IN THE MEKONG BASIN
HYDROPOWER DEVELOPMENT IN THE MEKONG BASIN Perspective of a Canadian Private Environmental Consulting Company Grant Bruce, M.Sc., PChem 3rd Annual Symposium of NSERC HydroNet Montréal, Quebec April 9th
More informationChemical Treatment. Batch treatment required, flow through continuous treatment not allowed
Chemical Treatment SE-11 Objectives EC SE TR WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control
More information