THE ROLE OF GAS IN BUILDING A SUSTAINABLE FUTURE FOR TANZANIA S POWER SECTOR ABOUT: Tanzania Spotlight. Richard Metcalf

Size: px
Start display at page:

Download "THE ROLE OF GAS IN BUILDING A SUSTAINABLE FUTURE FOR TANZANIA S POWER SECTOR ABOUT: Tanzania Spotlight. Richard Metcalf"

Transcription

1 THE ROLE OF GAS IN BUILDING A SUSTAINABLE FUTURE FOR TANZANIA S POWER SECTOR Richard Metcalf Partner Norton Rose Fulbright In Tanzania the future of its power sector is inextricably linked to the successful exploitation of its offshore gas reserves. The development of hydropower projects has been slowed by concern over the recent droughts; other forms of renewable energy generation will not achieve the scale of increase in electricity generation required by the country. Although the Government has reiterated its support for coal projects coalfired generation attracts ever stricter environmental controls. In this article we look at the unique opportunity now presented to Tanzania to harness its offshore resources to secure a step change in the provision of electricity to its citizens throughout the Republic. ABOUT: Richard Metcalf is a partner in the Norton Rose Fulbright energy team based in London. Richard focuses in particular on power generation and transmission and oil and gas exploration and development. He has worked in Africa for 20 years and is renowned for the work he does on behalf of African Governments and national energy companies as they negotiate for private investment and his current clients include Governments/ national utilities in Zimbabwe, Zambia and Botswana. His interest in Tanzania is reflected not only in his work for the Government and TANESCO but in the fact he has climbed to Uhuru Point on Mount Kilimanjaro, the highest point in Africa. he publication of Tanzania s first Natural Gas Policy in November 2013 was long awaited, a critical signal of the Government s strategic thinking about the role that gas can play in Tanzania s energy future. In the past three years Tanzania s profile has been transformed from that of a least developed country to one of the hottest for the global energy industry due to the discovery of offshore gas potential of 46 trillion cubic feet. Tanzania has joined the US, Australia, and Mozambique in the global LNG race. The steps that the Government of Tanzania takes in walking the tightrope towards realisation of this potential is being watched closely by stakeholders ranging from international oil majors and their shareholders to individual Tanzanian citizens, particularly those in Tanzania s underdeveloped southern regions closest to the gas fields. In terms of content, it is significant that the Natural Gas Policy was heavily amended from the draft version released in October 2012 to reflect developments subsequently encountered by the Government - particularly strong criticism from international oil companies and civil unrest in the Mtwara region and to appease stakeholders. Despite these amendments uncertainty remains. The Natural Gas Policy refers to an extensive list of legislation, further policies (such as a National Gas Utilisation Master Plan and upstream / petroleum policy) but none of this detail has yet appeared. 35

2 INSTITUTIONS From the information provided in the Policy, it is possible to map out a basic structure for the governance of the gas sector as follows: Tanzania Kwanza Tanzania first has been a constant message in the Government s gas announcements to date, as the Government recognises that electoral support is as key While enhancing the position of local stakeholders, the Government has relinquished its role in respect of gas infrastructure in order to induce greater investment. Whereas the 2012 Draft stated that the main gas infrastructure would initially be owned by the Government through the national oil company, the Natural Gas Policy refers to the Government now participating strategically in developing and operating such infrastructure through state-owned entities and public private partnerships (PPP) to develop and operate the infrastructure. This represents a concession to concerns raised by respondents on the 2012 Draft. as international support in the successful development of a natural gas industry by the ruling CCM party and seeks to ensure a sense of ownership for Tanzanian citizens. Given recent instances of civil unrest in Tanzania, this is also key for investors due to the effect of political risks such as riots, terrorism and sabotage on the feasibility and bankability of potential projects. This message is reflected in several aspects of the Natural Gas Policy, notably the domestic supply obligation. Precedence is to be given to supplying the domestic market over the export market. Given the energy situation in Tanzania, there is clear rationale for such prioritisation. Nonetheless, it will be a source of concern for investors until such time as details emerge of how this prioritisation will work. The Natural Gas Policy makes reference to problems that the Government has experienced in the past in relation to the implementation of PPPs and states that, in order to avoid such problems in future, a proper mechanism for risk sharing in natural gas PPP investments must be put in place. A statutory framework for PPPs was introduced in 2010 and followed with detailed regulations in 2011, but few (if any) projects have been implemented under the regime. Missing links Unlike the 2012 Draft, which applied to all streams and included provisions on exploration and development, the Natural Gas Policy specifies explicitly that its scope is 36

3 limited to the midstream and downstream segments. But although this might suggest that the Policy is more focused on a downstream activity such as the use of gas for power generation, this is not the case. The Policy indicated that more detail would be provided in other, imminent documents but at the time of writing these documents have still not emerged. Specifically: National Gas Utilisation Master Plan this was referred to in the Policy but no date has been given for when it will be published; Natural Gas Act as long ago as November 2013 the Government indicated that the new law was in the final stage of preparation but nothing has emerged. decided to remove this monopoly and encourage private sector participation. The main elements of the strategy consisted of: unbundling of NEPA s vertically integrated structure into 18 separate companies (6 generation, 1 transmission and 11 distribution business units; sale to the private sector of the 18 business units or in the case of the hydropower facilities, long-term concession as an additional option; allowing the private independent power producers to enter the power market; and establishment of an arms-length trading mechanism among these entities. From the perspective of those more interested in the use of gas for power generation, the biggest missing link is the absence of any policy which explicitly addresses the challenges of implementing a national gas transmission infrastructure necessary to provide gas to IPP investors and other bulk users of gas. Investors wait in anticipation as the Natural Gas Policy does contemplate the formation of a Gas Aggregator which is intended to develop and manage the requisite downstream infrastructure (from the pipeline network to processing facilities). The Gas Aggregator is envisioned to have exclusive rights to purchase, collect, transport and sell natural gas produced The Bureau of Public Enterprises (BPE) was entrusted with the reform process. While significant progress was made on most of the core elements of the strategy, it was noted that there was neither a clear and decisive approach to securing investors to provide the gas transmission infrastructure necessary to attract IPP investors into the power market, nor a focused effort to attract IPP investors. A project the G2P or gas to power project - was launched to remedy this deficiency. The project s objective was to undertake the preparatory work needed (i) to attract credible private sector investors Tanzania has joined the US, Australia, and Mozambique in the global LNG race in Tanzania. A useful point of comparison here is Nigeria and the challenges it faced a few years back when it found itself in a similar situation. It is instructive to look at the equivalent situation which first existed in Nigeria and how the Government there started the process which led to the vibrant Nigerian power sector of 2014 attracting substantial private sector investment. Some ten years ago the Federal Government of Nigeria (FGN), with the support of the World Bank, was pursuing a strategy of shifting the provision of electricity service in the country from the state-owned and run entity to the private sector. The FGN, through state-owned National Electric Power Authority (NEPA) had a monopoly over the generation, transmission and distribution of electric power in Nigeria. Due to its poor performance in accommodating the growing demand for electricity in Nigeria, the FGN to participate in the gas transmission infrastructure critical for IPPs to invest in power generation and also to provide access to gas throughout the major population centres of the country; (ii) to study and provide feasibility and basic design of pipeline infrastructure across the country that would permit independent power producers to site their facilities in or near the load centres of these areas to facilitate the reduction of power transmission losses while ensuring good voltage profiles; (iii) to identify and/or confirm the location and size of power station requirements for the next 20 years; (iv) to study, provide feasibility and design of more high voltage transmission lines to strengthen the existing lines in all parts of the country to ensure optimum power transmission, eliminate all bottlenecks and possible voltage collapses for anticipated generation and load demand; (v) to evaluate new technologies to mitigate under- and over-voltages at 37

4 certain fragile load centres; (vi) to examine and provide the design of new distribution lines and transformers to augment existing facilities especially for those feeding major load centres in the light of anticipated sitting of new power stations; and (vii) to provide access to gas to facilitate the emergence of gas-based/-using industries more broadly in the country. THE PROJECT WAS SCOPED TO COVER: Gas and Power Market Demand and Supply: An integrated study of the power supply requirements and forecasts (at least 20 years) to guide the likely locations of new power stations and the construction cost of new distribution and high voltage transmission lines; Gas Pipeline Engineering Study: this was to determine various routing options with related economic and engineering feasibility; Basic Engineering Designs: Preparation of basic engineering designs, implementation plans and preparation of tender documents in accordance with World Bank guidelines for large civil works contracts, with consideration to be given to breaking the tenders into manageable packages to assure early project completion; Pipeline Security Framework and Strategic Plan: development of a security plan to protect the operations of the existing and proposed network of pipelines. The security plan was also to include evaluation of options for adequate gas storage facilities at strategic locations along the pipeline route to ensure stability of gas supply in case of any disruption in the main gas pipeline supply; Integrated Impact Assessment: conduct of a baseline Environmental Impact Assessment (EIA) along the proposed pipeline routes; various tariff levels to assure economic rates of return ranging from 15% - 30%. As is always the case with such large, long-term projects this one evolved and changed shape. The challenges prompted the FGN to develop and implement the Nigerian Gas Master Plan (NGMP). Through the NGMP the FGN developed a deliberate interventionist policy aimed at leveraging the multiplier effect of natural gas in boosting the domestic economy. Given the rapid pace of growth of the Nigerian power sector, the short term focus of the NGMP was to address barriers that had hitherto stunted the growth of the domestic supply. These included: Gas Pricing Reform: hitherto, gas prices for the domestic market failed to reflect its true cost and were unsustainable for supply growth. The FGN introduced a new pricing arrangement for the domestic market, which provided for a more cost reflective tariff and stronger incentives for investment in the domestic sector. Contractual Frameworks: hitherto, gas was supplied to the power sector through Nigeria Gas Company (NGC) and there was no direct contractual relationship between the consumer and the gas supplier. NGC also served as the transporter, hence it offered a bundled service to the consumer. However, this service was not backed by a robust contractual framework, as gas was supplied on a best endeavour basis, as NGC had no control on supply. This arrangement was not bankable. A key element of the reform was the revision of the contractual framework to ensure bankability. The new arrangement involved the execution of a Gas Supply Agreement (GSAA) between Given the rapid pace of growth of the Nigerian power sector, the short term focus of the NGMP was to address barriers that had hitherto stunted the growth of the domestic supply Project Cost Estimate: prepare of a cost estimate (capital and operating) for the gas pipeline infrastructure from the gas inlet point(s), including the storage facility requirements from the supply points to the IPP locations; Economic and Financial Analysis: the determination of the gas supplier and the purchaser, accompanied by a Gas Transmission Agreement (GTA) with NGC. In order to streamline the operations of the sector a gas transmission network code was developed and issued. The network code complements the GTA and is aimed at managing 38

5 access and transmission through the gas pipeline network. The new arrangement is more bankable as the supplier is better placed to assure supply whilst NGC is best suited to assuring transmission. In order to support the efficient One of the goals of the GECSP is to support reform efforts aimed at improving Tanzania s business enabling environment and enhance private sector development. It specifically targets interventions geared towards improving the performance The GACN was setup to facilitate gas purchase and supply agreements, between the IOCs and successor generation companies and navigate the complicated logistics of gas delivery. The GACN acts as an intermediary between buyers and sellers of gas. execution of agreements, template agreements were developed and these allow for speedy customization for each transaction. Domestic Supply Obligations (DSO): another major interventionist aspect of the reform was the introduction of a regulatory framework through the DSO. This mandates all suppliers to set aside a certain amount of gas development for the domestic market in order to address the acute shortage of gas for the power sector. The DSO has played a major role in the increasing growth in domestic supply. Establishment of the Gas Aggregation Company of Nigeria (GACN): The GACN was setup to facilitate gas purchase and supply agreements, between the IOCs and successor generation companies and navigate the complicated logistics of gas delivery. The GACN acts as an intermediary between buyers and sellers of gas. Hitherto, potential consumers experienced difficulty in accessing gas. GACN now acts as that contact, thus facilitating rapid access to gas under the DSO scheme. It is self-evident that the particular challenges which face Tanzania will be different (whether in nature or scope) from those with which Nigeria has grappled as it has integrated gas into its energy mix. But equally it must be acknowledged that there is advantage in being able to look at the paths which other countries have followed as they have worked to optimise the use of gas. Furthermore, investors should be encouraged by the World Bank s and African Development Bank s (AfDB) support of reforms in Tanzania s energy sector, particularly by way of AfDB s recent assistance through the Governance and Economic Competitiveness Support Programme (GECSP). of the energy sector which is critical to attaining accessible, reliable and affordable power in Tanzania. The GECSP specifically aims to improve the power sector by financing much needed technical assistance (through loans and grants) in order to help the Government implement the following: adoption of an energy sector reform roadmap (by June 2014); studies to inform the new structure of TANESCO and TPDC (the current form of the proposed National Oil Company) and the energy sector reform roadmap (by June 2014); and performance / management audit of TANESCO (covering financial management, procurement systems and governance aspects - by June 2014). It is evident that that the next six months should, in theory, mark a turning point in the country s energy sector through (a) the country s affirmation of the proposed LNG project and (b) what it is hoped will be a robust legislative and institutional framework to ensure the bankability of downstream projects in order to dramatically expand capacity. What will be of further interest will be the extent to which AfDB and the World Bank are prepared to replicate their financial support of the Nigerian power sector; i.e. will partial risk guarantees be offered in order to encourage private investors to increase generation capacity? The reform of the energy sector along with the long-awaited National Gas Utilisation Master Plan and Natural Gas Act can hopefully ensure that Tanzania kwanza becomes a reality, incentivising investment through the creation of clear institutional roles, efficient contractual arrangements and secure and adequate gas infrastructure. 39

AN OVERVIEW OF THE NIGERIAN DOWNSTREAM GAS MARKET. Emeka Onyegbule Market Competition and Rates Division, NERC Abuja 27 th November 2012

AN OVERVIEW OF THE NIGERIAN DOWNSTREAM GAS MARKET. Emeka Onyegbule Market Competition and Rates Division, NERC Abuja 27 th November 2012 AN OVERVIEW OF THE NIGERIAN DOWNSTREAM GAS MARKET Emeka Onyegbule Market Competition and Rates Division, NERC Abuja 27 th November 2012 Presentation Outline Background Challenges and Obstacles to Gas development

More information

EFFECTIVE REGULATORY REGIMES AS A REQUIREMENT FOR RENEWABLE ENERGY DEVELOPMENT. Zambia Lusaka August 7 to

EFFECTIVE REGULATORY REGIMES AS A REQUIREMENT FOR RENEWABLE ENERGY DEVELOPMENT. Zambia Lusaka August 7 to EFFECTIVE REGULATORY REGIMES AS A REQUIREMENT FOR RENEWABLE ENERGY DEVELOPMENT Zambia Lusaka August 7 to 11 2017 1 Introduction Contents 2 Design Issues for Regulatory Support Mechanisms 3 Renewable Energy

More information

SYNOPSIS OF THE 2017 NATIONAL GAS POLICY

SYNOPSIS OF THE 2017 NATIONAL GAS POLICY SYNOPSIS OF THE 2017 NATIONAL GAS POLICY Introduction On Wednesday, June 28, 2017, the Federal Executive Council (FEC) at its monthly meeting approved the National Gas Policy, 2017 ( NGP ). The NGP, which

More information

The Nigerian Power Sector A case study of Power sector reform and the role of PPP

The Nigerian Power Sector A case study of Power sector reform and the role of PPP The Nigerian Power Sector A case study of Power sector reform and the role of PPP Erik Fernstrom World Bank November 14, 2011 1 Background: Nigeria Nigeria: Population is the seventh largest in the World,

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:PHI 30546 TECHNICAL ASSISTANCE (Financed by the Japan Special Fund) TO THE REPUBLIC OF THE PHILIPPINES FOR INSTITUTIONAL STRENGTHENING FOR THE DEVELOPMENT OF THE NATURAL GAS

More information

Rules on Initiation of Power Procurement and Review of Power Purchase Agreements. Eng. Anastas Mbawala, EWURA

Rules on Initiation of Power Procurement and Review of Power Purchase Agreements. Eng. Anastas Mbawala, EWURA Rules on Initiation of Power Procurement and Review of Power Purchase Agreements Eng. Anastas Mbawala, EWURA 1 Overview of this Presentation Background on statutory powers and purpose of the Rules Description

More information

REQUEST FOR EXPRESSIONS OF INTEREST

REQUEST FOR EXPRESSIONS OF INTEREST REQUEST FOR EXPRESSIONS OF INTEREST AFRICAN DEVELOPMENT BANK Immeuble CCIA, Abidjan, Côte d Ivoire African Natural Resources Center E-mail: M.HARRATHI@AFDB.ORG Telephone: +225 20 26 32 13 Department issuing

More information

PRESENTATION OUTLINE 1. GENERAL INFORMATION 1.1 COUNTRY PROFILE 1.2 ECONOMIC INDICATORS 2. ENERGY RESERVES 3. CURRENT ENERGY POLICY AND MEASURES 4. PA

PRESENTATION OUTLINE 1. GENERAL INFORMATION 1.1 COUNTRY PROFILE 1.2 ECONOMIC INDICATORS 2. ENERGY RESERVES 3. CURRENT ENERGY POLICY AND MEASURES 4. PA COUNTRY REPORT To be Presented at the Knowledge Co-creation Program in Japan on Energy Policy (B), Tokyo 28 th June 29 th July, 2017 By Eng. Salum Mandu Inegeja Ag. Assistant Commissioner for Electricity,

More information

Council conclusions on Energy 2020: A Strategy for competitive, sustainable and secure energy

Council conclusions on Energy 2020: A Strategy for competitive, sustainable and secure energy COUNCIL OF THE EUROPEAN UNION Council conclusions on Energy 2020: A Strategy for competitive, sustainable and secure energy 3072th TRANSPORT, TELECOMMUNICATIONS and ERGY Council meeting Brussels, 28 February

More information

Update energy and power sector strategies to reflect the growing cost advantages and other benefits of renewables

Update energy and power sector strategies to reflect the growing cost advantages and other benefits of renewables Recommended actions Renewable Energy Outlook: Egypt recommends seven key actions to accelerate the country s uptake of renewables: Update energy and power sector strategies to reflect the growing cost

More information

HOW AN INDUSTRIAL BASELINE SURVEY CAN INFORM LONG-TERM STRATEGIC PLANNING AND FACILITATE CREATION OF SUSTAINABLE ECONOMIC LINKAGES

HOW AN INDUSTRIAL BASELINE SURVEY CAN INFORM LONG-TERM STRATEGIC PLANNING AND FACILITATE CREATION OF SUSTAINABLE ECONOMIC LINKAGES HOW AN INDUSTRIAL BASELINE SURVEY CAN INFORM LONG-TERM STRATEGIC PLANNING AND FACILITATE CREATION OF SUSTAINABLE ECONOMIC LINKAGES Framework Step: STEP 2 - Build an empirical basis to inform decision-making

More information

that these standards can only be delivered effectively by devolution of responsibility to the frontline;

that these standards can only be delivered effectively by devolution of responsibility to the frontline; UK GOVERNMENT RESPONSE TO THE EUROPEAN COMMISSION S GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS, MAY 2004 The UK Government welcomes the debate on the

More information

In all our projects, we seek to provide fresh inspiration and practical solutions that have a positive impact.

In all our projects, we seek to provide fresh inspiration and practical solutions that have a positive impact. Lapis Elite Consulting Services Text for Profile on Website Overview Lapis Elite Consulting Services provides a broad range of consultancy and professional services, including management consulting, organisational

More information

11.0 Energy. Summary Energy snapshot

11.0 Energy. Summary Energy snapshot 11.0 Energy Summary Improving energy affordability and security will require significant reform of the energy sector. The NSW Government is delivering the sale of the generation businesses and has rationalised

More information

ZAMBIA REFIT POLICY 2015 GENERAL OVERVIEW

ZAMBIA REFIT POLICY 2015 GENERAL OVERVIEW ZAMBIA REFIT POLICY 2015 GENERAL OVERVIEW IES / SEE / Ea Pty Ltd 17 March 2014 Lusaka REFiT Status Work undertaken so far includes: Three Background Reports Interviews, meetings, data collection Workshops

More information

EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT. Programme for Supporting Renewable Energy in Ukraine

EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT. Programme for Supporting Renewable Energy in Ukraine EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT TERMS OF REFERENCE Programme for Supporting Renewable Energy in Ukraine Support to the Entity responsible for target setting The Programme for Supporting

More information

Response to Energy and Climate Change Committee Call for Evidence on Local Energy

Response to Energy and Climate Change Committee Call for Evidence on Local Energy Response to Energy and Climate Change Committee Call for Evidence on Local Energy Summary 1. The Energy Technologies Institute (ETI), a public-private partnership between global energy and engineering

More information

Renewable energy: Investing in Africa

Renewable energy: Investing in Africa 1. Who is responsible for energy policy? 2. To what extent have generation, transmission and distribution activities been unbundled? 3. Who owns and operates the (grid-connected) generation, transmission

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities West Kalimantan Power Grid Strengthening Project (RRP INO 41074) SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Road Map 1. Sector Performance, Problems and Opportunities 1. Development of Indonesia s energy

More information

TANZANIA PETROLEUM DEVELOPMENT CORPORATION TENDER NO. PA/031/ /C/10 FOR

TANZANIA PETROLEUM DEVELOPMENT CORPORATION TENDER NO. PA/031/ /C/10 FOR TANZANIA PETROLEUM DEVELOPMENT CORPORATION TENDER NO. PA/031/2018-2019/C/10 FOR CONSULTANCY SERVICES FOR FEASIBILITY STUDY FOR IMPLEMENTATION OF REGIONAL NATURAL GAS DISTRIBUTION PROJECT UNDER PPP MODEL

More information

Assessment of Wholesale Competition in the Nigerian Electricity Market

Assessment of Wholesale Competition in the Nigerian Electricity Market Assessment of Wholesale Competition in the Nigerian Electricity Market By U. D. Achinanya The Market Operator, PHCN, Nigeria 11/28/2007 WAPIC 2007, Abuja 1 Outline Wholesale Electricity Market:- Definition

More information

Infrastructure and Capital Projects

Infrastructure and Capital Projects Infrastructure and Capital Projects Contents Deloitte s Capabilities in Infrastructure and Capital Projects 1 Strategy and Planning 3 Financing and Procurement 4 Project Organisation, Execution and Construction

More information

INSTITUTIONAL CAPACITY ASSESSMENT

INSTITUTIONAL CAPACITY ASSESSMENT Demand-Side Energy Efficiency Sector Project (RRP IND 48224) INSTITUTIONAL CAPACITY ASSESSMENT A. Overview 1. Introduction. Energy Efficiency Services Limited (EESL) has been set up under the Indian Companies

More information

PIPED-GAS REGULATION FEBRUARY 2017

PIPED-GAS REGULATION FEBRUARY 2017 PIPED-GAS REGULATION FEBRUARY 2017 Disclaimer This frequently asked questions document (FAQ) is developed in the context of the liquefied natural gas (LNG) to Power IPP Procurement Programme currently

More information

Brief Overview of Renewable Energy Regulation in Tanzania

Brief Overview of Renewable Energy Regulation in Tanzania THE ENERGY AND WATER UTILITIES REGULATORY AUTHORITY (EWURA) Brief Overview of Renewable Energy Regulation in Tanzania Presentation by Anastas P. Mbawala Director of Electricity At the NARUC EWURA Mission

More information

Section 3 TERMS OF REFERENCE (TOR)

Section 3 TERMS OF REFERENCE (TOR) Section 3 TERMS OF REFERENCE (TOR) ENABLING FRAMEWORKS FOR INVESTMENT IN ECOWAS FOR THE IMPLEMENTATION OF THE WEST AFRICA CLEAN ENERGY CORRIDOR ACTION PLAN Capacity Building on Power Purchase Agreements

More information

Public Private Partnership PPP & The Egyptian Experience

Public Private Partnership PPP & The Egyptian Experience Public Private Partnership PPP & The Egyptian Experience Bassel Shoirah Project Manager / Utilities Sector - Egypt Good Governance for Development In Arab Countries initiatives of the OECD July 8, 2009

More information

COMMISSION STAFF WORKING DOCUMENT EXECUTIVE SUMMARY OF THE IMPACT ASSESSMENT. Accompanying the document

COMMISSION STAFF WORKING DOCUMENT EXECUTIVE SUMMARY OF THE IMPACT ASSESSMENT. Accompanying the document EUROPEAN COMMISSION Brussels, 4.6.2012 SWD(2012) 136 final COMMISSION STAFF WORKING DOCUMENT EXECUTIVE SUMMARY OF THE IMPACT ASSESSMENT Accompanying the document Proposal for a REGULATION OF THE EUROPEAN

More information

Challenges for Renewable Energy Finance

Challenges for Renewable Energy Finance Challenges for Renewable Energy Finance Seminar on Food Security, Climate Change and Energy Issues: South-South Opportunities Presentation by Mr. Peter Jones May 5th, 2010 World Exchange Plaza. P.O. Box

More information

UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES

UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES Jay Govender - National Practice Head - Projects and Infrastructure Cliffe Dekker Hofmeyr South Africa STRUCTURE OF PRESENTATION Regulatory Overview

More information

15 TH ANNUAL EAST AFRICAN POWER INDUSTRY CONVENTION

15 TH ANNUAL EAST AFRICAN POWER INDUSTRY CONVENTION 15 TH ANNUAL EAST AFRICAN POWER INDUSTRY CONVENTION Safari Park Hotel Nairobi, Kenya 10 th September, 2013 Development Plans and Goals for Energy Supply in East Africa: Making the Vision a Reality: The

More information

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Suite 2B, 08 Arnold Road, Rosebank, 2196, Johannesburg, South Africa Tel: +27 11 447 9852; Website: http://www.espcg.com Transaction advisory

More information

BOARD PAPER - NHS ENGLAND. Title: Developing commissioning support the future for commissioning support units

BOARD PAPER - NHS ENGLAND. Title: Developing commissioning support the future for commissioning support units Paper: 011404 BOARD PAPER - NHS ENGLAND Title: Developing commissioning support the future for commissioning support units Clearance: Rosamond Roughton, Interim National Director: Commissioning Development

More information

MEMORANDUM OF UNDERSTANDING BETWEEN THE STATE OF HAWAII AND THE U.S. DEPARTMENT OF ENERGY

MEMORANDUM OF UNDERSTANDING BETWEEN THE STATE OF HAWAII AND THE U.S. DEPARTMENT OF ENERGY MEMORANDUM OF UNDERSTANDING BETWEEN THE STATE OF HAWAII AND THE U.S. DEPARTMENT OF ENERGY I. Background The State of Hawaii depends on imported fossil fuels to meet over 90 percent of its energy needs.

More information

AFRICA RENEWABLE ENERGY INITIATIVE Criteria to be considered for attribution and eligibility/prioritization of funding

AFRICA RENEWABLE ENERGY INITIATIVE Criteria to be considered for attribution and eligibility/prioritization of funding AFRICA RENEWABLE ENERGY INITIATIVE Criteria to be considered for attribution and eligibility/prioritization of funding CONTEXT AND BACKGROUND! This document outlines the evaluation methodology (criteria

More information

THE ROLE OF THE EXTRACTIVE INDUSTRIES TRANSPARENCY INITIATIVE

THE ROLE OF THE EXTRACTIVE INDUSTRIES TRANSPARENCY INITIATIVE Jonas Moberg Victor Ponsford THE ROLE OF THE EXTRACTIVE INDUSTRIES TRANSPARENCY INITIATIVE IN DELIVERING SUSTAINABLE DEVELOPMENT IN THE EXTRACTIVE SECTOR 77 THE ROLE OF THE EXTRACTIVE INDUSTRIES TRANSPARENCY

More information

ACKNOWLEDGEMENTS. A number of RE100 member companies kindly contributed to this report. We would like to thank them for their ongoing support.

ACKNOWLEDGEMENTS. A number of RE100 member companies kindly contributed to this report. We would like to thank them for their ongoing support. ACKNOWLEDGEMENTS This report was prepared by E3G for RE100 initiative, to provide input to the current process for amending EU energy legislation. E3G 2016 A number of RE100 member companies kindly contributed

More information

Prospects of Solar Power Generation in Diversifying Nigeria's Energy Mix

Prospects of Solar Power Generation in Diversifying Nigeria's Energy Mix Prospects of Solar Power Generation in Diversifying Nigeria's Energy Mix As at July 2016, the total installed power generation capacity in Nigeria, a country of over 187 million people (www.worldometers.info),

More information

MAKING THE IMPACT STICK HOW TARGETED TECHNICAL ASSISTANCE CAN HELP TO 6CREATE A SUSTAINABLE PPP PROGRAMME

MAKING THE IMPACT STICK HOW TARGETED TECHNICAL ASSISTANCE CAN HELP TO 6CREATE A SUSTAINABLE PPP PROGRAMME LESSONS LEARNED FROM IMPLEMENTATION OF A SUCCESSFUL PPP PROGRAMME MAKING THE IMPACT STICK HOW TARGETED TECHNICAL ASSISTANCE CAN HELP TO 6CREATE A SUSTAINABLE PPP PROGRAMME MAKING THE IMPACT STICK How targeted

More information

Principal Barriers/ Constraints to Successful Public-Private Partnerships

Principal Barriers/ Constraints to Successful Public-Private Partnerships High-level Expert Group Meeting on Infrastructure Public-Private Partnerships for Sustainable Development 11-13 November 2012 Tehran, Islamic Republic of Iran Principal Barriers/ Constraints to Successful

More information

GABON, NATIONWIDE WATER & POWER. Case Study (Water and Power) Project Summary:

GABON, NATIONWIDE WATER & POWER. Case Study (Water and Power) Project Summary: GABON, NATIONWIDE WATER & POWER Case Study (Water and Power) Project Summary: In July 1997, the government of Gabon signed a twenty-year concession contract with a private French consortium to operate

More information

How freight transport can contribute to the achievement of sustainable economic development in Zimbabwe

How freight transport can contribute to the achievement of sustainable economic development in Zimbabwe UNCTAD Multiyear Expert Meeting on Transport, Trade Logistics and Trade Facilitation 21-23 November 2018, Geneva Sustainable freight transport in support of the 2030 Agenda for Sustainable Development

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY Java Bali 500-Kilovolt Power Transmission Crossing Project (RRP INO 42362) SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Development of Indonesia

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Country Partnership Strategy: Azerbaijan, 2014 2018 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map A. Sector Performance, Problems, and Opportunities 1. Azerbaijan is rich in energy resources. The

More information

Regulatory Impact Statement

Regulatory Impact Statement Regulatory Impact Statement Agency Disclosure Statement 1. This Regulatory Impact Statement (RIS) has been prepared by the Ministry of Business, Innovation and Employment (MBIE). 2. It provides an analysis

More information

Support for Competitive Procurement of Renewables in Mongolia

Support for Competitive Procurement of Renewables in Mongolia TERMS OF REFERENCE Support for Competitive Procurement of Renewables in Mongolia 1. Background The European Bank for Reconstruction and Development ( EBRD or the Bank ) and the Mongolian Ministry of Energy

More information

Blueprint Services Blueprint provides a unique range of services within the following fields.

Blueprint Services Blueprint provides a unique range of services within the following fields. Blueprint Services Blueprint provides a unique range of services within the following fields. 1. Economic Development Policies and Strategies Blueprint assists governments and their development partners

More information

Integrated Resource Planning. Monica Bansal E3 Energy Division March 6, 2017

Integrated Resource Planning. Monica Bansal E3 Energy Division March 6, 2017 Integrated Resource Planning Monica Bansal E3 Energy Division March 6, 2017 What is an IRP? Long-range planning process resulting in an investment plan. Period of 20 years usually, updated every 2 years

More information

Platts European Power Summit Emerging market drivers for conventional energy services and how utility companies can respond

Platts European Power Summit Emerging market drivers for conventional energy services and how utility companies can respond Platts European Power Summit Emerging market drivers for conventional energy services and how utility companies can respond Presenter: Dr Sopna Sury COO Third Party Services & Infrastructure, Uniper 26

More information

Concept Note Expert Working Group on PPPs in Africa s Electricity Sector

Concept Note Expert Working Group on PPPs in Africa s Electricity Sector UNITED NATIONS ECONOMIC COMMISSION FOR AFRICA Concept Note Expert Working Group on PPPs in Africa s Electricity Sector Introduction This initiative is intended to launch an effort by the United Nations

More information

Evaluation Brief. Comprehensive Evaluation of the Development Results of the African Development Bank Group Background and Context

Evaluation Brief. Comprehensive Evaluation of the Development Results of the African Development Bank Group Background and Context An IDEV Corporate Evaluation Independent Development Evaluation African Development Bank From experience to knowledge... From knowledge to action... From action to impact Comprehensive Evaluation of the

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Interim Country Partnership Strategy: Maldives, 2014 2015 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities A. Sector Performance 1. The Maldives

More information

Regional Perspective on Gas Sector Policy and Institutional Framework

Regional Perspective on Gas Sector Policy and Institutional Framework AFRICAN NATURAL RESOURCES CENTER (ANRC) Regional Perspective on Gas Sector Policy and Institutional Framework A presentation at the IGU Executive Committee Durban, South Africa, 6-7 April 2016 Presented

More information

TRIENNIAL ASSESSMENT OF THE COMPETITION IN THE ELECTRICITY MARKET IN KOSOVO

TRIENNIAL ASSESSMENT OF THE COMPETITION IN THE ELECTRICITY MARKET IN KOSOVO TRIENNIAL ASSESSMENT OF THE COMPETITION IN THE ELECTRICITY MARKET IN KOSOVO Address: Dërvish Rozhaja Str., No. 12, 10000 Prishtina, Kosovo Tel: 038 247 615 ext. 101, Fax: 038 247 620, E-mail: info@ero-ks.org,

More information

Overview of the Southern African Power Pool (SAPP) energy programme for the Southern African Development Community (SADC)

Overview of the Southern African Power Pool (SAPP) energy programme for the Southern African Development Community (SADC) Overview of the Southern African Power Pool (SAPP) energy programme for the Southern African Development Community (SADC) Fossil Fuel Foundation: IPP Conference 17 March 2016 Johannesburg Objectives Overview

More information

PROJECT FINANCE FOR RENEWABLE ENERGY SYSTEMS

PROJECT FINANCE FOR RENEWABLE ENERGY SYSTEMS Executive Summary PROJECT FINANCE FOR RENEWABLE ENERGY SYSTEMS Egypt case study Risk Analysis and mitigation measures in the existing policy and regulatory framework November 2018 About RES4MED & Africa

More information

SMALL SCALE LNG CATALYST FOR GROWING GAS MARKETS. April 24-25, 2018

SMALL SCALE LNG CATALYST FOR GROWING GAS MARKETS. April 24-25, 2018 SMALL SCALE LNG CATALYST FOR GROWING GAS MARKETS April 24-25, 2018 Access to Reliable Energy In the Emerging Market context, small-scale LNG demand could comprise of small (

More information

business, government and civil society. It is also providing energy at rapidly decreasing cost to the consumer.

business, government and civil society. It is also providing energy at rapidly decreasing cost to the consumer. Speech by the Minister of Energy, Hon Jeff Radebe, MP at the Renewable Energy Independent Power Producer Programme (REIPPPP) Bid Windows 3.5 and 4 Contractual Close signing ceremony 4 April 2018 I would

More information

Payment by Results: what are the key get rights prior to launching a successful programme?

Payment by Results: what are the key get rights prior to launching a successful programme? Payment by Results: what are the key get rights prior to launching a successful programme? Payment by Results: what are the key get rights prior to launching a successful programme? This paper will be

More information

Infrastructure investment in the transport sector - can PPPs deliver value?

Infrastructure investment in the transport sector - can PPPs deliver value? Infrastructure investment in the transport sector - can PPPs deliver value? DBSA Transport Integration Workshop 30 October 2012 Gideon van der Westhuizen, Transaction Adviser, Johnstaff, Southern Africa

More information

Standard Merger Notification Form Information Requirements Part 3: Markets

Standard Merger Notification Form Information Requirements Part 3: Markets Stard Merger Notification Form Information Requirements Part 3: Markets DISCLAIMER: This publication is a compilation of information received from national competition authorities of the European Union

More information

STRATEGIC BLUEPRINT: Keeping Pace With an Evolving Energy Sector

STRATEGIC BLUEPRINT: Keeping Pace With an Evolving Energy Sector STRATEGIC BLUEPRINT: Keeping Pace With an Evolving Energy Sector 2017-2022 Contents Message from the Chair... 1 Introduction & Our Strategic Challenges... 2 Background & Environmental Scan... 4 Our Vision,

More information

CSDP Supplier Guidelines

CSDP Supplier Guidelines CSDP Supplier Guidelines August 2010 ANNEXURE C Page 1 of 17 Contents What is CSDP?... 3 Definition... 3 Historical Context... 3 Transnet s commitment to CSDP... 3 What is expected of the Supplier?...

More information

ELECTRICITY DISTRIBUTION INDUSTRY RESTRUCTURING

ELECTRICITY DISTRIBUTION INDUSTRY RESTRUCTURING ELECTRICITY DISTRIBUTION INDUSTRY RESTRUCTURING 1. BACKGROUND On the 25 th of October 2006 Cabinet, having considered the results of the modelling exercise, approved the proposal to create six wall-to-wall

More information

ZSIC GROUP OF COMPANIES PROCUREMENT PLAN EXCEL VERSION

ZSIC GROUP OF COMPANIES PROCUREMENT PLAN EXCEL VERSION ZSIC GROUP OF COMPANIES PROCUREMENT PLAN 2015 EXCEL VERSION 1 P a g e 2 P a g e ZSIC Group Procurement Plan 2015 Contents Page 1. Background 3 2. Introduction 4 3. Executive Summary 5 4. Overall Expenditure

More information

About Energy UK. Introduction

About Energy UK. Introduction REC 34-15 Energy UK response to DG Comp investigation of Investment Contract (early Contract for Difference) for Lynemouth power station biomass conversion 10 May 2015 About Energy UK Energy UK is the

More information

ELECTRICITY SUPPLY INDUSTRY OF SOUTH AFRICA

ELECTRICITY SUPPLY INDUSTRY OF SOUTH AFRICA ELECTRICITY SUPPLY INDUSTRY OF SOUTH AFRICA General Information for Potential Investors May 2008 This publication was produced for review by the United States Agency for International Development. It was

More information

A PRACTICAL GUIDE TO: S.M.A.R.T.E.R. SUPPLIER MANAGEMENT. [ T y p e t h e c o m p a n y a d d r e s s ]

A PRACTICAL GUIDE TO: S.M.A.R.T.E.R. SUPPLIER MANAGEMENT. [ T y p e t h e c o m p a n y a d d r e s s ] A PRACTICAL GUIDE TO: S.M.A.R.T.E.R. SUPPLIER MANAGEMENT Entire contents 2009 Procurementtoolkit.com. All rights reserved. Page 1 EVALUATION REPORT HISTORY Document Location This document becomes uncontrollable

More information

Global Environment Facility

Global Environment Facility Global Environment Facility GEF/C.25/11 April 29, 2005 GEF Council Meeting June 6-8, 2005 Agenda Item 17 COST EFFECTIVENESS ANALYSIS IN GEF PROJECTS Recommended Council Decision The Council, having reviewed

More information

AZERBAIJAN ECONOMIC REFORMS REVIEW

AZERBAIJAN ECONOMIC REFORMS REVIEW April 2017 AZERBAIJAN ECONOMIC REFORMS REVIEW Editor-in-chief : Dr. Vusal Musayev PhD in Economics London University THE STRATEGIC ROADMAP FOR THE PRODUCTION OF CONSUMER GOODS IN AZERBAIJAN AT THE LEVEL

More information

Updates on Nigeria Energy Sector Development and Reforms

Updates on Nigeria Energy Sector Development and Reforms NARUC/Nigeria Electricity Regulatory Partnership Updates on Nigeria Energy Sector Development and Reforms DUBAI, MAY 5, 2015 1 Outline Status of ongoing Power Sector Reforms: Why Reforms Objectives of

More information

Africa is lagging behind in terms of energy use, with limited access to electricity and biomass often remaining the main energy source

Africa is lagging behind in terms of energy use, with limited access to electricity and biomass often remaining the main energy source Africa is lagging behind in terms of energy use, with limited access to electricity and biomass often remaining the main energy source Power consumption per capita in Africa remains very low, especially

More information

In responding to the consultation, we would like to draw your attention to the following points:

In responding to the consultation, we would like to draw your attention to the following points: Energy Networks Association 4 More London Riverside London SE1 2AU Dear Sir/Madam Open Networks Future Worlds consultation This response to the Open Networks Future Worlds consultation has been prepared

More information

KEYNOTE ADDRESS BY GNPC CEO, ALEXANDER K-M MOULD

KEYNOTE ADDRESS BY GNPC CEO, ALEXANDER K-M MOULD KEYNOTE ADDRESS BY GNPC CEO, ALEXANDER K-M MOULD TOPIC: GNPC, THE CRITICAL CATALYST FOR GHANA S DRIVE TOWARDS ENERGY SUSTAINABILITY GNPC APRIL 20, 2016 1 P a g e Theme: Driving Ghana s Oil, Gas, Power

More information

SCALING-UP RENEWABLE ENERGY PROGRAM (SREP) COUNTRY INVESTMENT PLAN KENYA

SCALING-UP RENEWABLE ENERGY PROGRAM (SREP) COUNTRY INVESTMENT PLAN KENYA SCALING-UP RENEWABLE ENERGY PROGRAM (SREP) COUNTRY INVESTMENT PLAN KENYA SREP Sub- Committee Meeting, Cape Town June 21, 2011 1 Introduction Kenya is one of the six Pilot Countries selected to benefit

More information

The Electricity System Operator Who we are and what we do September 2018 CONFICONFIDNEITA

The Electricity System Operator Who we are and what we do September 2018 CONFICONFIDNEITA The Electricity System Operator Who we are and what we do September 2018 CONFICONFIDNEITA Who we are As the Electricity System Operator (ESO), we operate the National Electricity Transmission System in

More information

CBI Response to BEIS Call for Evidence

CBI Response to BEIS Call for Evidence CBI Response to BEIS Call for Evidence Smart, Flexible Power System The CBI welcomes the opportunity to respond to the BEIS Call for Evidence on A Smart, Flexible Energy System. Across the UK, the CBI

More information

SECURITY OF POWER SUPPLY

SECURITY OF POWER SUPPLY SECURITY OF POWER SUPPLY What is the Situation and What is Namibia Doing? A Presentation to the Mining Conference 21 May 2015 Safari Conference Centre Windhoek, Namibia By Paulinus Shilamba Managing Director

More information

Carbon Rights in REDD+

Carbon Rights in REDD+ Policy Note The findings, interpretations, and conclusions expressed herein are those of the author(s), and do not necessarily reflect the views of the funders. Supporting research for this document was

More information

Progress since the 2004 White Paper on services of general interest

Progress since the 2004 White Paper on services of general interest COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 20.11.2007 SEC(2007) 1515 COMMISSION STAFF WORKING DOCUMENT Progress since the 2004 White Paper on services of general interest Accompanying document to

More information

Shared Services & Cost Saving Collaboration Deserve Respect

Shared Services & Cost Saving Collaboration Deserve Respect Page 1 of 7 ICMA Press / PM Magazine / Current Issue MAY 2011 VOLUME 93 NUMBER 4 COVER STORY Shared Services & Cost Saving Collaboration Deserve Respect by Monte Mercer Shared services, many of which are

More information

NATIONAL ENERGY BOARD

NATIONAL ENERGY BOARD NATIONAL ENERGY BOARD IN THE MATTER OF the National Energy Board Act, being Chapter N-7 of the Revised Statutes of Canada, as amended, and the Regulations made thereunder; AND IN THE MATTER of an Application

More information

2017 PARTNERSHIPS CONFERENCE Light Up and Power Africa. Astrid Manroth Director Transformative Energy Partnerships

2017 PARTNERSHIPS CONFERENCE Light Up and Power Africa. Astrid Manroth Director Transformative Energy Partnerships 2017 PARTNERSHIPS CONFERENCE Light Up and Power Africa Astrid Manroth Director Transformative Energy Partnerships 6 April 2017 Africa is rich in energy resources Gas OilGas Oil Hydro Oil Fossil fuels Oil

More information

For personal use only

For personal use only 21 June 2016 Market Update 100 MW CBM Power Supply Announced by Government of Botswana Tlou Energy Limited, the AIM and ASX listed company focused on delivering power in Botswana and Southern Africa through

More information

COUNTRY ENGAGEMENT STRATEGY A COUNTRY-DRIVEN APPROACH FOR COLLECTIVE IMPACT ON CLIMATE AND DEVELOPMENT ACTION

COUNTRY ENGAGEMENT STRATEGY A COUNTRY-DRIVEN APPROACH FOR COLLECTIVE IMPACT ON CLIMATE AND DEVELOPMENT ACTION COUNTRY ENGAGEMENT STRATEGY A COUNTRY-DRIVEN APPROACH FOR COLLECTIVE IMPACT ON CLIMATE AND DEVELOPMENT ACTION OCTOBER 2017 ABRIDGED VERSION INTRODUCTION 1. This Country Engagement Strategy orients current

More information

Regional Value Chains in East Africa. Ritwika Sen 14 th December, 2016 Trade, FDI & Regional Value Chains Workshop Kigali, Rwanda

Regional Value Chains in East Africa. Ritwika Sen 14 th December, 2016 Trade, FDI & Regional Value Chains Workshop Kigali, Rwanda Regional Value Chains in East Africa Ritwika Sen 14 th December, 2016 Trade, FDI & Regional Value Chains Workshop Kigali, Rwanda Regional Trade in the EAC From Commodities to Speciality Niches in RVCs?

More information

Vietnam takes further steps to encourage solar energy

Vietnam takes further steps to encourage solar energy Legal Update May 2017 Vietnam takes further steps to encourage solar energy On 11 April 2017, the Prime Minister issued long-awaited regulations on solar energy in Decision No. 11/2017/QD-TTg (Decision

More information

UNITED NATIONS ECONOMIC COMMISSION FOR AFRICA. Meeting of African Ministers responsible for Energy. Meeting of Experts. Statement

UNITED NATIONS ECONOMIC COMMISSION FOR AFRICA. Meeting of African Ministers responsible for Energy. Meeting of Experts. Statement UNITED NATIONS ECONOMIC COMMISSION FOR AFRICA Meeting of African Ministers responsible for Energy Meeting of Experts Statement By Joseph Atta-Mensah Director, Regional Integration, Infrastructure and Trade

More information

AFRICA INFRASTRUCTURE PROGRAM PROJECTS

AFRICA INFRASTRUCTURE PROGRAM PROJECTS BRIEFING ON AFRICAN ENERGY REFORM AFRICA INFRASTRUCTURE PROGRAM PROJECTS The Africa Infrastructure Program (AIP) provides capacity-building and late-stage transactional support services on clean and conventional

More information

African Development Bank

African Development Bank African Development Bank REQUEST FOR EXPRESSIONS OF INTEREST FOR AN INDIVIDUAL SHORT TERM CONSULTANT TO PREPARE AND FACILITATE A STRATEGY MEETING CCIA building, Avenue Joseph Anoma, Abidjan 01, Côte d

More information

A Paper Prepared for ABRACE by Ashley C. Brown, June 10, Advice on the Brazilian Natural Gas Market

A Paper Prepared for ABRACE by Ashley C. Brown, June 10, Advice on the Brazilian Natural Gas Market A Paper Prepared for ABRACE by Ashley C. Brown, June 10, 2014 Advice on the Brazilian Natural Gas Market The natural gas market in Brazil is largely dysfunctional and constitutes a major barrier to the

More information

Renewables in Vietnam OPPORTUNITIES FOR INVESTMENT

Renewables in Vietnam OPPORTUNITIES FOR INVESTMENT Renewables in Vietnam OPPORTUNITIES FOR INVESTMENT 1 Introduction The demand for electricity in Vietnam is rising rapidly to power the growing economy and forecasts predict an annual growth rate for electricity

More information

BABERGH DISTRICT COUNCIL and MID SUFFOLK DISTRICT COUNCIL

BABERGH DISTRICT COUNCIL and MID SUFFOLK DISTRICT COUNCIL BABERGH DISTRICT COUNCIL and MID SUFFOLK DISTRICT COUNCIL From: BDC Cabinet Member Communities MSDC Lead Member Health and Wellbeing To: Babergh and Mid Suffolk Cabinet Report Number: MCa/17/29 Date of

More information

SIAPS assistance is grouped into four technical areas

SIAPS assistance is grouped into four technical areas Our specific approaches to each of the five result areas follows Governance Under SIAPS, our approach to improving governance and accountability focuses on establishing transparent management systems grounded

More information

GET FiT Programme: Leveraging private investments in renewable energy. Bank aus Verantwortung

GET FiT Programme: Leveraging private investments in renewable energy. Bank aus Verantwortung GET FiT Programme: Leveraging private investments in renewable energy Bank aus Verantwortung Index 1 Background and Challenges for Private Investments in RE in Africa 2 GET FiT An Innovative Approach to

More information

Developing National Local Content Policy In Africa

Developing National Local Content Policy In Africa UNCTAD Regional Workshop and Project Launching on Ameliorating the Structural Effects of Mineral Resources in the Economic Community of Central African Countries Ndjamena, Chad, 25-30 November, 2015 Developing

More information

RWE Thames Water. GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COM(2004) 327 final

RWE Thames Water. GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COM(2004) 327 final GREEN PAPER ON PUBLIC-PRIVATE PARTNERSHIPS AND COMMUNITY LAW ON PUBLIC CONTRACTS AND CONCESSIONS COM(2004) 327 final Position RWE Thames Water Introduction: RWE Thames Water welcomes the Commission s Green

More information

World Bank s Role: Support Shift toward Sustainability

World Bank s Role: Support Shift toward Sustainability 6 World Bank s Role: Support Shift toward Sustainability Key messages: The World Bank Group is committed to scale up investment and analytical and advisory activities (AAA) in sustainable energy to support

More information

Powering Africa : PPP in the Energy Sector

Powering Africa : PPP in the Energy Sector Powering Africa : PPP in the Energy Sector The regulatory framework for PPP Projects Alex Sarac DLA Piper UK LLP Saidi Amiri Tanzania Investment Centre Presentation overview 1 Main applicable laws - Energy

More information

Aspects of regulatory design:

Aspects of regulatory design: Aspects of regulatory design: A submission to the Productivity Commission NZIER report to AECT October 2013 About NZIER NZIER is a specialist consulting firm that uses applied economic research and analysis

More information