VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Odour Management Plan. November 2009

Size: px
Start display at page:

Download "VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Odour Management Plan. November 2009"

Transcription

1 VIRIDOR WASTE MANAGEMENT LIMITED Lostock Waste Treatment Plant

2 CONTENTS 1 Introduction Sources, releases and impacts Odour Control Measures Site Management Responsibility Physical Control Measures Management Control Measures Monitoring General Odour Contingency Measures Introduction Odour complaint investigation Elevated Odour Levels Reporting Measures Emergency Plans General Abnormal Meteorological Conditions Breakdown of Process Equipment and Plant Staffing Issues Management Responsibilities and Review Review of odour control measures...13 APPENDICES Appendix 1 Odour Report Form

3 1 Introduction This outlines the methods by which Viridor will systematically assess, reduce and prevent potentially odorous emissions from the Lostock Waste Treatment Plant (WTP). The odour management plan is a working document with the specific aim of ensuring that: odour impact is considered as part of routine inspections odour is primarily controlled at source by good operational practices, including physical and management control measures all appropriate measures are taken to prevent or, where that is not reasonably practicable, to reduce odorous emissions to air from the WTP at nearby receptors This addresses the impact of odour release and the control measures employed to mitigate the risk. These are supported through monitoring procedures to identify both elevated levels and review complaints should they arise. The complaints management procedure including the management responsibilities are also addressed The methodologies presented in this management plan take full account of Environment Agency guidance documentation as detailed below: Internal Guidance for the Regulation of Odour at Waste Management Facilities Technical Guidance Note IPPC H4, Horizontal Guidance for Odour 1

4 2 Sources, releases and impacts Odour may be released during the following activities: Unloading of waste at the site in the reception halls Storage of waste in reception halls Mechanical Separation Biodrying and refinement Storage of SRF and recyclable materials awaiting transport offsite Once released into the atmosphere, the pathway for odour will be air transport. Sensitive receptors will include humans living close to the site, in particular residential properties to the north and west of the site. The Odour and Ammonia modelling indicates that the proposed [27m] stack will give adequate dispersion to prevent odour nuisance from the site, with levels meeting 0.49ou E /m 3 (as 1 hour 98 th percentile concentrations) at the maximum modelled receptor concentration, which is well below the 1.5ou E /m 3 level that may cause a nuisance, giving an overall low risk Further detail on the risks and pathways of odour release are provided in 03 Risk Assessment. Odour and Ammonia modelling has also been undertaken and is provided as Appendix 4 to 03 Risk Assessment All potential odour sources are located within enclosed buildings. Further detail on the processes that may release odour is provided in 02 Operating Techniques. 2

5 3 Odour Control Measures Physical and management measures have been included to control odour at the WTP. These are discussed below. 3.2 Site Management Responsibility The Technically Competent Manager (TCM) (or designated responsible person) will have responsibility for ensuring that nuisances and hazards arising from the facility due to odour are minimised. Regular meetings will be instigated to discuss current and planned site operations that have the potential to generate odorous site emissions. 3.3 Physical Control Measures A comprehensive range of physical control measures will be implemented at the site. These control measures are as follows Enclosed building provided with high speed automatic roller shutter doors and air curtains on all doors will be employed All waste processing plant, including conveyors, will be enclosed units with point source air extraction technology applied at strategic locations Air extraction equipment will actively extract potentially odorous air from the waste reception hall, treatment building and enclosed waste processing plant (including conveyors). The air extraction system will induce a slight negative pressure within the relevant buildings. This negative pressure will promote the inflow of air into rather than out of the facility so that when the doors are open there is less potential for odour to leave the building Air Treatment Technology, incorporating dust filters and biofilters, will manage aerial emission prior to discharge to the atmosphere via a stack. The stack has been designed to be of sufficient height (27m) to aid dispersion to the point where emissions will not impact on any receptors Dust filters will remove particulates, including bioaerosols from collected air. Biofilters will then slow the air flow down so that any residual particles of suspended particulates are filtered out of the air. Biofilters will remove odour from the emissions through the use of an organic medium containing biological agents which aerobically digest complex molecules thus removing odour from the output air stream. 3

6 These conditions are promoted by keeping the medium moist with a humidifier/condenser. 3.4 Management Control Measures A comprehensive range of management control measures will be implemented at the site All waste unloading, loading, treatment and storage will be undertaken inside the WTP buildings All doors in the waste reception halls to be kept shut during unloading and loading operations and at all times when waste access is not required All odour control equipment as detailed in the physical control measures, including the biofilter and organic medium will be maintained to the manufacturers specifications to ensure that it operates effectively at all times. The biofilter and organic medium will be maintained to a specific maintenance programme to ensure that it is operating effectively at all times. Only one biofilter will be subjected to routine maintenance at any one time to ensure that adequate air treatment will be continuously available If at any time it is necessary to undertake temporary actions that are likely to cause elevated levels of odour, the TCM (or designated responsible person) will contact the Environment Agency and any other interested parties before such actions are taken to inform them of the operations being undertaken and that the elevated levels of odour will be of a temporary nature. Where practicable, such actions will only proceed when the prevailing wind direction is away from sensitive receptors. 4

7 4 Monitoring 4.1 General Weather conditions (including wind speed and direction) shall be visually assessed and recorded at regular intervals. This will enable potential odour issues to be predicted and necessary remedial actions implemented All operational staff will be responsible for reporting any odour problems immediately to the TCM (or designated responsible person) (or designated responsible person) Daily olfactory monitoring will be undertaken at the site boundary by operational staff The inspections shall be undertaken as follows: The operational member of staff will walk slowly along the site boundary and breathe normally. If an odour cannot be detected in this way, the inspector will periodically stand still and inhale deeply facing upwind. If odour is detected while walking and breathing normally, the intensity will be recorded as 3 (moderate odour). If odour can only be detected whilst standing still and inhaling whilst facing the wind then intensity will be recorded as 2 (faint odour). Following the identification of an odour at the site boundary, an on site inspection will be carried out to trace any odour back to source and enable any corrective or preventative action to take place Observations including time, date, weather conditions, temperature, wind strength, wind direction, intensity, odour type and sensitivity will be recorded in an Odour Report Form (Appendix 1). Site operating conditions at the time of survey will also be recorded, enabling the identification of any abnormal site operating conditions such as downtime for refurbishment or maintenance Should elevated levels of odour be identified, the TCM (or designated responsible person) will be informed immediately and will initiate the mitigation measures identified in section 5. 5

8 4.1.7 Wherever possible, odour inspectors will be chosen from office-based staff that are unlikely to suffer from adaptation to odour. Adaptation to odour process whereby a person gets used to (adapts to) an odour and so may be unable to detect an odour. All staff responsible for assessing odour will receive appropriate and adequate training from the site management on the odour inspection procedure. Each inspector carrying out odour assessments will be initially accompanied by a more experienced member of site management to ensure that the nature and offensiveness of any odours detected are being perceived similarly Staff will be instructed to avoid strong food or drinks for at least one hour beforehand and those members of staff who have a cold, sore throat or sinusitis will not be used to carry out odour assessments. 6

9 5 Odour Contingency Measures 5.1 Introduction Elevated levels of odour may be identified either by: receipt of an odour complaint from a third party suggesting that there is an odour from the WTP, detection of odour at the site boundary as a result of the monitoring procedures detailed in Section 4; or malfunction of the odour abatement system This section details the contingency measures in place to identify the source of elevated odour levels and bring odour levels back under control and minimise their impact. 5.2 Odour complaint investigation There will be a, site diary, plus forms to record complaints, which will be completed by the TCM (or designated responsible person) and input into the Issue Management System (IMS) As part of the Business Management System, a customer care and complaints procedure will be implemented. The customer care and complaints procedure applies to all complaints, feedback and requests made by third parties regarding Viridor's operational activities, environmental, health and safety performance or quality of service/product All complaints from third parties including external customers, potential customers, statutory authorities, statutory consultees, members of the general public and internal clients will be forwarded to the TCM (or designated responsible person) to action as below and recorded onto an online incident reports database within 72 hours The TCM (or designated responsible person) will ensure that: The complaint is investigated to identify the cause, if necessary this may involve direct communication with the complainant In the event of elevated levels of odour being detected, the presence of abnormal on-site activity is assessed and if necessary preventative action is taken that will prevent a reoccurrence of the same problem. These actions must be documented 7

10 The Complainant will be contacted and given information on the investigations conducted and actions taken as appropriate Where a complaint or query is likely to involve a statutory authority, the emergency services, an insurance company, or the media, the External Affairs Manager will be informed Complaints involving a location with Local Authority Contracts will be reported in line with specific Contract requirements and timescales. Local procedures may need to be in place to ensure these are adhered to All complaints are reported to Regional Directors and discussed at site meetings Details of other complaints are sent to the other Company personnel as appropriate. If the investigation indicates that the complaint has not been justified this will be clearly recorded on the Incident Report. All complaints will be logged. 5.3 Elevated Odour Levels Any elevated levels of odour identified by the monitoring programme detailed in Chapter 4 and the customer care and complaints procedure identified in section 5.1 will be mitigated as follows: The TCM (or designated responsible person) will carry out a range of checks at the identified source of the elevated levels to ensure the plant is being operated to the manufacturer s specification, to the requirements set out in Sections 3.2 and 3.3 of this management plan, and to ensure that any improvements required to minimise the odour levels are made. This may include the cleaning of all stockpiled waste either through processing or transportation directly to landfill and ensuring that waste is not stored for more than three days in the reception halls To further mitigate the elevated odour levels, the following actions shall also be considered. The site could temporarily restrict the waste types accepted at site (i.e. those with highest potential to cause odour) to see if the odour issues continue. 8

11 Alternatively the site could reduce the waste throughput or temporarily halt waste processing. As identified in 02 Operating Techniques, there are several of each piece of processing equipment, allowing the partial shutdown of the plant with continued processing. In addition to this, the feed rate can be reduced. Both of these measures will allow for a reduction in waste processing. The site has three days storage capacity in the waste reception hall which will allow a complete stop in operations If necessary the TCM (or designated responsible person) will temporarily divert waste to other delivery points that form part of the Cheshire PFI waste treatment contract or to contingent treatment points In the event of a serious incident requiring the complete shutdown of the plant for an extended period, contingent treatment points will be used to divert waste that would otherwise have been delivered to the site The TCM (or designated responsible person) will ensure a close liaison with the Environment Agency throughout all stages of the process following the emissions limit being exceeded Once the improvements identified by the TCM (or designated responsible person) have been completed, the manager will commission a further odour assessment to ensure that the improvements have addressed the source of the elevated levels. If the elevated levels are still present then the manager will repeat the request for improvements and subsequent assessments until the limits are met If operational failings are identified, the retraining of employees will take place to ensure that all employees operate to the required standards. If the failings are identified as part of the operating techniques then the problem will be raised as part of the review of control measures detailed in section Reporting Measures In the event of elevated levels of odour being identified, the event will be reported into an Issue Management System immediately by a member of operational staff. This Issue Management System is 9

12 accessed via internal company intranet, known as the portal. Upon notification of an Environmental Incident, the TCM (or designated responsible person) will complete an incident reporting form. The completed form is then distributed throughout the company All performance failures will be categorised for input into the IMS as follows; Minor event: quick fix possible, locally resolved; Medium event: brief disruption to service, Management intervention required; Major event: significant disruption to service significant disruption to service Each non-conformance category has a given deadline for rectification The IMS will record any actions taken to rectify the issue any necessary actions or review are recorded onto the Issue Management system and the person reporting the incident is notified. These reports are reviewed at national, regional and local levels, via operational, management and health and safety meetings The Compliance Manager will investigate the performance failure event within [2] hours and, if necessary, will report the event to the Environment Agency. Once the issue has been resolved, the corrective action taken will be entered onto the system and the issue will be closed. 10

13 6 Emergency Plans 6.1 General This section considers the potential for accidents (or incidents) which would result in the loss of control of odorous substances and could have an unacceptable short term impact on the local community Should an emergency occur outside of normal operating hours, a nominated representative will be on site within two hours of notification Should an emergency occur out of hours, the nominated representative will contact his operatives and managers, as appropriate, via mobile telephone. The nominated representative will identify whether the emergency services are required to attend a site emergency and will contact them directly if necessary. 6.2 Abnormal Meteorological Conditions Abnormal meteorological conditions such as low wind strength, low pressure, high temperatures may promote elevated levels of odour either on the site or at nearby sensitive receptors. A wind direction towards sensitive receptors may increase odour levels. Conversely very low wind strength and temperature inversions may minimise dispersion and potentially create a build up of odour. High temperatures may also increase emissions The mitigation measures to be undertaken in the event of abnormal meteorological conditions are the same as the contingency mitigation measures detailed in section 5.3. The Unit Emergency Plan for flood will also provide further detail on the procedures to be undertaken in the case of flooding at the site. 6.3 Breakdown of Process Equipment and Plant The breakdown of the waste treatment process or abatement equipment may cause elevated levels of odour to be created due to the build up of waste or the failure of control equipment The mitigation measures to be undertaken in the event of process breakdown are the same as the contingency mitigation measures detailed in Section

14 6.4 Staffing Issues Human error and accidents may cause elevated levels of odour to be created either through the stopping or breakdown of the process or the failure of control equipment The mitigation measures to be undertaken in the event of staffing issues are the same as the contingency mitigation measures detailed in Section 5.3. The Unit Emergency Plan for accident/injury will also provide further detail on the procedures to be undertaken in the case of an accident at the site. 12

15 7 Management Responsibilities and Review The control of odour will be managed according the Business Management System which includes Environmental Management at the site accredited to ISO It will be the responsibility of the TCM (or designated responsible person) to ensure that the Business Management System is adhered to at the site. This includes ensuring that the odour control measures detailed in Chapter 3 are adhered to The TCM (or designated responsible person) will be supported by the Compliance Manager. The Compliance Manager is responsible for monitoring, auditing and evaluation of site performance, which will include ensuring continued compliance with the ISO standard. 7.2 Review of odour control measures Odour control measures will be reviewed through internal audits as part of the monitoring and reporting of the Business Management System With reference to odour the internal audits will include but will not be limited to the following; Monthly spot check inspections of the paper trail of forms and the IMS to ensure that all data is being entered correctly. Checks to ensure that any issues entered into the IMS have been resolved correctly. Visual inspections to ensure that there is no non compliant waste getting on to site. Checks to ensure that the EWC codes are being used to ensure the identification and separation of contract and non contract waste. External Audits External Audits of the Business Management System (BMS) will be carried out in order to achieve and maintain ISO14001 accreditation. 13

VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Airborne Pollutant Management Plan. November 2009

VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Airborne Pollutant Management Plan. November 2009 VIRIDOR WASTE MANAGEMENT LIMITED Lostock Waste Treatment Plant CONTENTS 1 Introduction... 1 2 Sources, releases and impacts... 2 3 Airborne Pollutant Control Measures... 3 3.1 General... 3 3.2 Site Management

More information

VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Appendix 3 Bioaerosol Risk Assessment. November 2009

VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Appendix 3 Bioaerosol Risk Assessment. November 2009 VIRIDOR WASTE MANAGEMENT LIMITED Lostock Waste Treatment Plant Appendix 3 Lostock Waste Treatment Plan Contents 1 Introduction...1 1.2 Bioaerosols...1 2 Potential Sources of Bioaerosols...1 3 Pathways

More information

Global Waste Technical Services Ltd. Street Fuel Ltd, Beth 6 Basin 3 Chatham Dockyard Chatham ME4 4SR. NOISE and VIBRATION MANAGEMENT PLAN

Global Waste Technical Services Ltd. Street Fuel Ltd, Beth 6 Basin 3 Chatham Dockyard Chatham ME4 4SR. NOISE and VIBRATION MANAGEMENT PLAN Street Fuel Ltd, Beth 6 Basin 3 Chatham Dockyard Chatham ME4 4SR NOISE and VIBRATION MANAGEMENT PLAN Permit No. EPR/XP3598XP Global solutions any waste, anywhere Revision 1.0 May 2013 Global Solutions

More information

Street Fuel Ltd Beth 6, Basin 3 Chatham dockyard Chatham ME4 4SR. DUST MANAGEMENT PLAN Permit No. EPR/XP3598XP. Global Waste Technical Services Ltd

Street Fuel Ltd Beth 6, Basin 3 Chatham dockyard Chatham ME4 4SR. DUST MANAGEMENT PLAN Permit No. EPR/XP3598XP. Global Waste Technical Services Ltd Street Fuel Ltd Beth 6, Basin 3 Chatham dockyard Chatham ME4 4SR DUST MANAGEMENT PLAN Permit No. EPR/XP3598XP Global solutions any waste, anywhere Revision 1.1 May 2013 (15th May 2013) 1.0 Background 1.1

More information

VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Accident Management Plan. November 2009

VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Accident Management Plan. November 2009 VIRIDOR WASTE MANAGEMENT LIMITED Lostock Waste Treatment Plant CONTENTS 1 Introduction... 1 2 Mitigation... 8 2.1 Inadequate waste acceptance procedures... 8 2.2 Waste storage... 9 2.3 Transfer of substances...

More information

Crushing and Screening Management Procedure Environment

Crushing and Screening Management Procedure Environment 1 Purpose and Scope This procedure specifies the operational environmental requirements relating to crushing and screening management at the Roy Hill Project. This procedure applies to all personnel involved

More information

Environmental Roles and Responsibilities

Environmental Roles and Responsibilities Environmental Roles and Responsibilities All members of staff have a responsibility for their actions and the following impact on the companies identified environmental risks. All staff have responsibilities

More information

Document B Specification

Document B Specification Tender for The Provision of a Communal Cleaning & Window Cleaning Service Reference: PDT 18-035 Document B Specification Dated: February 2019 General Scope This specification defines the quality and standards

More information

AEL and dust emission reporting requirements required by the licensing authorities to be submitted in compliance with the Act

AEL and dust emission reporting requirements required by the licensing authorities to be submitted in compliance with the Act AEL and dust emission reporting requirements required by the licensing authorities to be submitted in compliance with the Act CITY HEALTH-AIR QUALITY MANGEMENT NACA Western Cape 1 Day seminar Presented

More information

Fugitive Dust Management Plan

Fugitive Dust Management Plan Lansing Board of Water & Light July 2014 1.0 INTRODUCTION The Renewable Operating Permit B4001-2010 requires continuously implementing a written Fugitive Dust Control Program for the purpose of minimizing

More information

Loy Yang B Environment Improvement Plan

Loy Yang B Environment Improvement Plan Loy Yang B Environment Improvement Plan 2017 Table of Contents 1 Endorsement 1 2 Environment Policy 2 3 Operating Arrangements 3 4 Site Management and Business Systems 4 5 Environmental Impacts and Risks

More information

Environment Act Licence of sur l'environnement Licence

Environment Act Licence of sur l'environnement Licence Environment Act Licence of sur l'environnement Licence Manitoba Conservation Conservation Manitoba Licence No./Licence n 964 R Issue Date/Date de delivrance October 29, 1982 Revised: December 1, 2000 IN

More information

Procedure 14 Internal Audits

Procedure 14 Internal Audits Procedure 14 Internal Audits Table of Contents 1 Introduction... 2 2 Audit Planning... 2 2.1 Head Office... 2 2.2 Critical Locations... 3 3 Conducting the Audit... 3 4 Non-conformances... 3 5 Client file

More information

PROPOSED PROTEIN RECOVERY PLANT (PRP) 24 SCOTT STREET, WARRNAMBOOL. WORKS APPROVAL APPLICATION RESPONSE TO s.20(b) CONFERENCE REPORT

PROPOSED PROTEIN RECOVERY PLANT (PRP) 24 SCOTT STREET, WARRNAMBOOL. WORKS APPROVAL APPLICATION RESPONSE TO s.20(b) CONFERENCE REPORT PROPOSED PROTEIN RECOVERY PLANT (PRP) 24 SCOTT STREET, WARRNAMBOOL WORKS APPROVAL APPLICATION RESPONSE TO s.20(b) CONFERENCE REPORT 3 December 2018 1 INTRODUCTION Midfield has prepared this response to

More information

About this Exhibition

About this Exhibition About this Exhibition Proposals for a new waste facility for Cheshire This exhibition provides you with important information about Viridor s revised proposals for a new waste treatment facility at Lostock

More information

Dust Management Procedure Environment

Dust Management Procedure Environment 1 Purpose and Scope This procedure specifies the operational environmental requirements relating to dust management at the Roy Hill Project. This procedure applies to all personnel involved in activities

More information

Measurement Assurance and Certification Scotland

Measurement Assurance and Certification Scotland Measurement Assurance and Certification Scotland Performance Standard MACS-WAT-02 Sample and data management Version 2 August 2017 Record of amendments Version Date Amendment(s) 1 October 2016 First issue.

More information

Gunlake Quarry. Air Quality Management Plan

Gunlake Quarry. Air Quality Management Plan Gunlake Quarry Air Quality Management Plan August 2015 Table of Contents 1. Introduction 3 1.1 Overview 3 1.2 Aims and Objectives 3 2. Air Quality Criteria 3 2.1 Impact Assessment Criteria 4 2.2 Sources

More information

Non-notified resource consent application report and decision

Non-notified resource consent application report and decision Non-notified resource consent application report and decision Summary of decision Activity: File Reference: To discharge contaminants into air arising from the operation of a spray painting booth. WGN090275

More information

Amersham Waste Transfer Station, Amersham, Buckinghamshire. Environmental Permit (EP) Application Operating Techniques SLR Ref:

Amersham Waste Transfer Station, Amersham, Buckinghamshire. Environmental Permit (EP) Application Operating Techniques SLR Ref: , Amersham, Buckinghamshire Environmental Permit (EP) Application Operating Techniques Ref: 416.00197.00815/OT September 2011 Waste Recycling Limited i Ref:.416.00197.00815/OT CONTENTS 1.0 INTRODUCTION...

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Air Quality Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site

More information

HAUC England Advice Note No. 2014/02. Code of Practice for Inspections: Defects Not Causing Danger Inspections ENGLAND

HAUC England Advice Note No. 2014/02. Code of Practice for Inspections: Defects Not Causing Danger Inspections ENGLAND HAUC England Advice Note No. 2014/02 Code of Practice for Inspections: Defects Not Causing Danger Inspections ENGLAND Version: VI Control Document No.: 1 Document Owner: Roger Culpin and Mark Ostheimer

More information

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY S1014-0340-0008MPW NTS Rev1.doc Print Date 19 February 2009 ISSUE NUMBER 1 DATE 19/02/09 AUTHOR CHECKED MPW SMO Title Page

More information

INTEGRATED MANAGEMENT SYSTEM MANUAL

INTEGRATED MANAGEMENT SYSTEM MANUAL Integrated Management System Documentation 1 of 8 INTEGRATED MANAGEMENT SYSTEM MANUAL Ashtree Vision & Safety Ltd Ashtree Works Brownroyd Street Bradford BD8 9AF 01274 546732 www.avsuk.co.uk Integrated

More information

Central Greenwaste and Firewood Monitoring Programme Biennial Report Technical Report

Central Greenwaste and Firewood Monitoring Programme Biennial Report Technical Report Central Greenwaste and Firewood Monitoring Programme Biennial Report 2016-2018 Technical Report 2018-29 Taranaki Regional Council ISSN: 1178-1467 (Online) Private Bag 713 Document: 2089250 (Word) STRATFORD

More information

QP 02 Audit and Certification Procedure

QP 02 Audit and Certification Procedure 1. AUDIT PROGRAMME [9.1.1] The audit programme shall be conducted in stages within a 3-year certification cycle as follows; Initial audit: Two stage process Surveillance audit: Conducted in the first and

More information

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Manager Environment Approved: Executive General Manager Asset Strategy DOCUMENT HISTORY Date

More information

INJURY AND ILLNESS PREVENTION PROGRAM. Adopted June 25, 1991 by Board Resolution 91-95

INJURY AND ILLNESS PREVENTION PROGRAM. Adopted June 25, 1991 by Board Resolution 91-95 INJURY AND ILLNESS PREVENTION PROGRAM Adopted June 25, 1991 by Board Resolution 91-95 Latest Annual Review/Revision December, 2012 TABLE OF CONTENTS 1.0 Introduction... 1 2.0 Definitions... 1 3.0 Policy...

More information

YOUR CERTIFICATION PROCESS EXPLAINED

YOUR CERTIFICATION PROCESS EXPLAINED ISO 22000 FOOD SAFETY MANAGEMENT SYSTEMS FSSC 22000 FOOD SAFETY SYSTEM CERTIFICATION This document outlines the audit process for the above referenced standard. It outlines the stages to audit and gives

More information

Air Monitoring Plan for Ground Intrusive Activities at the Various PPG Hexavalent Chromium Sites in New Jersey

Air Monitoring Plan for Ground Intrusive Activities at the Various PPG Hexavalent Chromium Sites in New Jersey Environment Submitted to: Submitted by: PPG Industries Inc. AECOM Jersey City, NJ Piscataway, NJ 60149955-4010A May 14, 2012 Air Monitoring Plan for Ground Intrusive Activities at the Various PPG Hexavalent

More information

CCR COMPLIANCE FUGITIVE DUST CONTROL PLAN

CCR COMPLIANCE FUGITIVE DUST CONTROL PLAN CCR COMPLIANCE FUGITIVE DUST CONTROL PLAN FOR INDIAN RIVER LANDFILL PREPARED BY: Aptim Environmental and Infrastructure, Inc. Revised Plan Date: November 2017 PREPARED FOR: Indian River Power, LLC; a subsidiary

More information

AEP GENERATION RESOURCES

AEP GENERATION RESOURCES AEP GENERATION RESOURCES CONESVILLE PLANT ANNUAL CCR FUGITIVE DUST CONTROL REPORT Prepared By: AEP Generation Resources, Inc. 47201 County Road 273 Conesville, Ohio 43811 and American Electric Power Service

More information

ECO2 LINCS LTD SLEAFORD RENEWABLE ENERGY PLANT IPPC APPLICATION - NON TECHNICAL SUMMARY

ECO2 LINCS LTD SLEAFORD RENEWABLE ENERGY PLANT IPPC APPLICATION - NON TECHNICAL SUMMARY SLEAFORD RENEWABLE ENERGY PLANT IPPC APPLICATION - NON TECHNICAL SUMMARY ISSUE NUMBER 1 DATE 16/11/07 AUTHOR CHECKED SMO TME Title Page ISSUE NUMBER 1 DATE 16/11/07 AUTHOR CHECKED SMO TME Title Page TABLE

More information

AEP GENERATION RESOURCES

AEP GENERATION RESOURCES AEP GENERATION RESOURCES CONESVILLE PLANT ANNUAL CCR FUGITIVE DUST CONTROL REPORT Prepared By: AEP Generation Resources, Inc. 47201 County Road 273 Conesville, Ohio 43811 and American Electric Power Service

More information

LENZ ENTERPRISES COMPOST FACILITY PROGRESSIVE ODOR MANAGEMENT PLAN

LENZ ENTERPRISES COMPOST FACILITY PROGRESSIVE ODOR MANAGEMENT PLAN Page 1 LENZ ENTERPRISES COMPOST FACILITY PROGRESSIVE ODOR MANAGEMENT PLAN Jeff Gage, 360-957-0900 jpgage@msn.com Lenz Enterprises. Inc. 5210 SR 532, Stanwood WA 98292, 360-629-2933 P.O. Box 868, Stanwood,

More information

9.0 Environmental Protection Program

9.0 Environmental Protection Program 9.0 Environmental Protection Program 9.1.1 Overview Manitoba Hydro s Environmental Protection Program (EPP) provides the framework for the delivery, management and monitoring of environmental and socio-economic

More information

Health, Safety & Wellbeing Policy

Health, Safety & Wellbeing Policy Clacton County High School Health, Safety & Wellbeing Policy This Document was originally approved: January 2013 This Document was Last Reviewed: September 2017 This Document is due for review: September

More information

20 January 2011 at Allington Quarry Integrated Waste Management Facility. Attending Brian White (Chair) Councillor Malcolm Robertson

20 January 2011 at Allington Quarry Integrated Waste Management Facility. Attending Brian White (Chair) Councillor Malcolm Robertson Allington Quarry Integrated Waste Management Facility Community Liaison Committee Notes Meeting 20 January 2011 at Allington Quarry Integrated Waste Management Facility Attending Brian White (Chair) Councillor

More information

Gunlake Quarry. Noise and Blast Management Plan

Gunlake Quarry. Noise and Blast Management Plan Gunlake Quarry Noise and Blast Management Plan August 2015 Table of Contents 1. Introduction 3 1.1 Overview 3 1.2 Aims and Objectives 3 2. Noise Criteria 3 2.1 Operational Noise Assessment Criteria 3 2.2

More information

London Borough of Hillingdon. Permit Ref: EPA/B2/17. Environmental Permitting (England and Wales) Regulations 2007 (as amended) SI 2007:3538

London Borough of Hillingdon. Permit Ref: EPA/B2/17. Environmental Permitting (England and Wales) Regulations 2007 (as amended) SI 2007:3538 London Borough of Hillingdon Permit Ref: EPA/B2/17 Environmental Permitting (England and Wales) Regulations 2007 (as amended) SI 2007:3538 Installation Address Thames Materials Ltd. Skip Lane Uxbridge,

More information

The licensee shall take the actions specified to close out the non-compliances and observations raised in this Site Visit Report.

The licensee shall take the actions specified to close out the non-compliances and observations raised in this Site Visit Report. Site Visit Report The site visit process is a sample on a particular day of an installation's compliance with some of its licence conditions. Where non-compliance against a particular condition has not

More information

Rules for Ship Recycling Management System Certification

Rules for Ship Recycling Management System Certification Rules for Ship Recycling Management System Certification Effective from July 1 st 2009 RINA Società per azioni Via Corsica, 12-16128 Genova - Italy Tel.: +39 01053851 - Fax: +39 0105351000 www.rina.org

More information

Construction Environment Management Plan

Construction Environment Management Plan Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated

More information

and the term landfill generically refers to all landfills, including the above types, unless specified otherwise.

and the term landfill generically refers to all landfills, including the above types, unless specified otherwise. 7 Landfills 7.1 Introduction Facilities for disposing of wastes to the ground have been variously described as landfills, tips, or dumps, without reference to the degree of environmental safeguards employed

More information

Air Quality Monitoring Plan

Air Quality Monitoring Plan Air Quality Monitoring Plan 1 OBJECTIVE The monitoring and management of air quality within the Port of Townsville is critical to address a potential risk that has generated considerable public interest

More information

The effluent treatment plant had numerous sources of high strength odours.

The effluent treatment plant had numerous sources of high strength odours. 8. ODOUR IMPACT ASSESSMENT. 8.1 INTRODUCTION 8.1.1. This section should be read in conjunction with the following drawings in the Appendices the Existing Site (Plan 02) and the Proposed 2015 Masterplan

More information

Form PPC1 Part B : Application for a permit. B1 About the installation

Form PPC1 Part B : Application for a permit. B1 About the installation Form PPC1 Part B : Application for a permit FOR SEPA USE ONLY Name Assigned to Installation Application Reference Use this part of the form if you are applying for a new permit. When completing the form

More information

Environmental Odour Philip Branchflower SLR Consulting

Environmental Odour Philip Branchflower SLR Consulting Environmental Odour Philip Branchflower SLR Consulting Litigating Public, Private and Statutory Nuisances for Noise and Smell (including Group Actions). UKELASouth West Regional Group Thursday 17th September

More information

Asbestos Management Policy

Asbestos Management Policy Asbestos Management Policy December 2017 1. Purpose Manningham Housing Association has a legal duty to ensure the health and safety of its employees, tenants, leaseholders and other stakeholders in relation

More information

The assessment is based upon the design ore production of 95 million tonnes / annum.

The assessment is based upon the design ore production of 95 million tonnes / annum. 9A Air Quality Assessment Supporting Information This annex sets out the detailed methodology, input data and criteria for the assessment. The overarching assessment approach is detailed in Chapter 9:

More information

POSITION DESCRIPTION Property Operations Manager

POSITION DESCRIPTION Property Operations Manager POSITION DESCRIPTION Property Operations Manager The BlueCross Vision A dynamic organisation, BlueCross is supported by a team of great staff, who are willing to challenge traditions. With a long history

More information

ENVIRONMENTAL GUIDELINES FOR PREVENTION AND CONTROL OF FUGITIVE EMISSIONS FROM CEMENT PLANTS

ENVIRONMENTAL GUIDELINES FOR PREVENTION AND CONTROL OF FUGITIVE EMISSIONS FROM CEMENT PLANTS ENVIRONMENTAL GUIDELINES FOR PREVENTION AND CONTROL OF FUGITIVE EMISSIONS FROM CEMENT PLANTS For achieving effective prevention and control of potential fugitive emission sources in cement manufacturing

More information

July 22, Robert Cyr Cyr Construction 1998 Ltd. Box 24, Group 525, RR 5 Winnipeg MB R2C 2Z2. Dear Mr. Cyr:

July 22, Robert Cyr Cyr Construction 1998 Ltd. Box 24, Group 525, RR 5 Winnipeg MB R2C 2Z2. Dear Mr. Cyr: Conservation Climate Change and Environmental Protection Division Environmental Assessment and Licensing Branch 123 Main Street, Suite 160, Winnipeg, Manitoba R3C 1A5 T 204 945-7100 F 204 945-5229 www.gov.mb.ca/conservation/eal

More information

HEALTH, SAFETY AND ENVIRONMENT MANAGEMENT SYSTEM

HEALTH, SAFETY AND ENVIRONMENT MANAGEMENT SYSTEM HEALTH, SAFETY AND ENVIRONMENT MANAGEMENT SYSTEM CHAPTER 1 of 5.0 SCOPE The Company has established an internal and external audits and internal inspections program to ascertain both the general condition

More information

Wastewater Management Procedure Environment

Wastewater Management Procedure Environment 1 Purpose and Scope This procedure specifies the operational environmental requirements relating to the management of wastewater and the operation and maintenance of Roy Hill wastewater treatment plants

More information

DRINKING WATER SYSTEM. Summary Report toronto.ca/water

DRINKING WATER SYSTEM. Summary Report toronto.ca/water DRINKING WATER SYSTEM Summary Report 2017 toronto.ca/water R.C. Harris WTP 2017 Summary Report 2017 Summary Report Toronto (R.C. Harris) Water Treatment Plant Contents: 1.0 General Overview 2.0 System

More information

The purpose of this report is to seek the views of the NSS Board on membership of the Occupational Health and Safety Advisory Committee.

The purpose of this report is to seek the views of the NSS Board on membership of the Occupational Health and Safety Advisory Committee. B/17/38 NSS Board Meeting Friday, 7 April 2017 Occupational Health, Safety, Wellbeing Policy Occupational Health and Safety Advisory Committee Board Membership Purpose The purpose of this report is to

More information

Environmental Bill of Rights Draft Version DRAFT - For Consultation Purposes Only Ministry of the Environment

Environmental Bill of Rights Draft Version DRAFT - For Consultation Purposes Only Ministry of the Environment Ministry of the Environment Soil Management A Guide for Best Management Practices The Ministry of the Environment (ministry) encourages the beneficial reuse of excess soils in a manner promoting sustainability

More information

Drayton Management System Standard. Air Quality Management and Monitoring Plan

Drayton Management System Standard. Air Quality Management and Monitoring Plan Anglo Coal (Drayton Management) Pty Ltd Policies and Procedures Air Quality Management and Monitoring Plan Drayton Management System Standard Air Quality Management and Monitoring Plan Author: Name Pam

More information

PROCEDURE (Essex) / Linked SOP (Kent) Asbestos Management. Number: U 1005 Date Published: 22 July 2015

PROCEDURE (Essex) / Linked SOP (Kent) Asbestos Management. Number: U 1005 Date Published: 22 July 2015 1.0 Summary of Changes 1.1 This is a new joint procedure/sop for Essex Police and Kent Police. 2.0 What this Procedure is about 2.1 This document identifies how Essex Police and Kent Police shall manage

More information

Licence No. / Licence n. Pursuant to Sections 10(1) and 14(2) / Conformement au Paragraphes 10(1) et 14(2)

Licence No. / Licence n. Pursuant to Sections 10(1) and 14(2) / Conformement au Paragraphes 10(1) et 14(2) THE ENVIRONMENT ACT LOI SUR LENVIRONNEMENT Licence No. / Licence n 2375 R Issue Date / Date de delivrance August 3,2011 In accordance with The Environment Act (C.C.S.M. c. E125) / Conformement I la Loi

More information

Government Gazette Staatskoerant

Government Gazette Staatskoerant Government Gazette Staatskoerant REPUBLIC OF SOUTH AFRICA REPUBLIEK VAN SUID AFRIKA Regulation Gazette No. 10177 Regulasiekoerant Vol. 621 17 March Maart 2017 No. 40698 N.B. The Government Printing Works

More information

The NOSE Platform : A Real-Time Solution to Forecast & Monitor Nuisance Odours

The NOSE Platform : A Real-Time Solution to Forecast & Monitor Nuisance Odours A publication of CHEMICAL ENGINEERING TRANSACTIONS VOL. 30, 2012 Guest Editor: Renato Del Rosso Copyright 2012, AIDIC Servizi S.r.l., ISBN 978-88-95608-21-1; ISSN 1974-9791 The Italian Association of Chemical

More information

Table OCO 8.1 Air Quality Management. Audit Check. Ref Subject Reference Control Activity Responsibility Timing Performance Measure

Table OCO 8.1 Air Quality Management. Audit Check. Ref Subject Reference Control Activity Responsibility Timing Performance Measure These tables set out the operational controls required to achieve the objectives and targets set out in Program 08 Air Quality Management. BBA will, as a minimum, implement the control activities and performance

More information

(2) Check List Pre-treatment Facility

(2) Check List Pre-treatment Facility 3.1.2. Pre-treatment facilities I. Activity What is the general condition of the facility? (visible spillages, strong odour, intensive dust layer, rusted vessels and pipes) Is a pre-acceptance procedure

More information

IN ACCORDANCE WITH THE MANITOBA ENVIRONMENT ACT (C.C.S.M. c. E12S) THIS LICENCE IS ISSUED PURSUANT TO SECTIONS 10(1) TO:

IN ACCORDANCE WITH THE MANITOBA ENVIRONMENT ACT (C.C.S.M. c. E12S) THIS LICENCE IS ISSUED PURSUANT TO SECTIONS 10(1) TO: - - - - - - - -.- Licence No./Licence n 2111 Issue Date/Date de d6livrance March J. 2006 IN ACCORDANCE WITH THE MANITOBA ENVIRONMENT ACT (C.C.S.M. c. E12S) THIS LICENCE IS ISSUED PURSUANT TO SECTIONS 10(1)

More information

PORT OF PORT HEDLAND - BULK PRODUCT MANAGEMENT PROCEDURE

PORT OF PORT HEDLAND - BULK PRODUCT MANAGEMENT PROCEDURE TABLE OF CONTENTS 1. PURPOSE... 2 2. SCOPE... 2 3. RESPONSIBILITIES... 2 4. SPECIFICATION OF BULK MINERAL PRODUCTS... 3 4.1 PROVISION OF ONGOING INFORMATION...4 4.2 SAMPLING...5 4.3 PRODUCT DEM AND MOISTURE

More information

Waterview Operational Air Quality Monitoring Report November 2017

Waterview Operational Air Quality Monitoring Report November 2017 Waterview Operational Air Quality Monitoring Report November 2017 Document No: [Subject] Waterview Tunnel Joint Operation nzta.govt.nz/waterviewconnection 1399 Great North Road, Waterview, Auckland 1026

More information

Quality Assurance Policy

Quality Assurance Policy Quality Assurance Policy Quality Assurance Policy And Project Organisation Plan This document defines the general policy for Quality Assurance to be used for the whole project. It gives the project organisation,

More information

Wylfa Newydd Project Site Preparation and Clearance Application

Wylfa Newydd Project Site Preparation and Clearance Application ENERGY WORKING FOR BRITAIN Wylfa Newydd Project Site Preparation and Clearance Application Environmental Management Plan Management of Dust and Air Quality Procedure Table of Contents 1 Introduction 1

More information

Annual Performance Report 2007

Annual Performance Report 2007 SELCHP Energy Recovery Facility PPC Permit: NP3738SY 1. Introduction. Annual Performance Report 2007 This report fulfils the requirements of Article 12(2) of the Waste Incineration Directive regarding

More information

EIGHT POINT WIND, LLC

EIGHT POINT WIND, LLC EIGHT POINT WIND, LLC, Including Noise Complaint and Resolution Plan and Post Construction Noise Evaluation Steuben County, New York COMPLAINT RESOLUTION PLAN (the Applicant), a subsidiary of NextEra Energy

More information

Stage 1 BSI Assessment for ISO10002:2014 certification

Stage 1 BSI Assessment for ISO10002:2014 certification Audit Committee, 16 March 2016 Stage 1 BSI Assessment for ISO10002:2014 certification Executive summary and recommendations Introduction HCPC underwent the Stage 1 audit in the ISO10002:2014 certification

More information

2017 Environment Management System & Community Engagement Report

2017 Environment Management System & Community Engagement Report 2017 Environment Management System & Community Engagement Report March 30, 2018 Table of Contents Summary 1. Background 2. Communications and Community Engagement 3. Community Air Quality Monitoring 4.

More information

Level 6 NVQ Diploma in Construction Site Management (Construction)

Level 6 NVQ Diploma in Construction Site Management (Construction) Level 6 NVQ Diploma in Construction Site Management (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

HEALTH AND SAFETY POLICY AND PROCEDURES

HEALTH AND SAFETY POLICY AND PROCEDURES HEALTH AND SAFETY POLICY AND PROCEDURES Relevant Legislation The Health and Safety At Work Act 1974 The Management of Health and Safety At Work Regulations 1999(as amended) All associated Health and Safety

More information

WasteMINZ Webinar 22 February 2018

WasteMINZ Webinar 22 February 2018 WasteMINZ Webinar 22 February 2018 Dr Doug Boddy Senior Air Quality Scientist Pattle Delamore Partners Ltd Auckland doug.boddy@pdp.co.nz Ph +64 9 529 5858 Mob +64 21 977 810 https://www.linkedin.com/in/doug-boddy-b279615/

More information

Permit SW-06/04 Page 2 of 12 Table of Contents

Permit SW-06/04 Page 2 of 12 Table of Contents Page 2 of 12 Table of Contents I. GENERAL CONDITIONS:... 3 A. Permit Replaced... 3 B. Applicability... 3 C. Application Documents... 3 D. General Conditions... 3 II. OPERATIONS:... 4 A. General Operations:...

More information

Waterview Operational Air Quality Monitoring Report January 2018

Waterview Operational Air Quality Monitoring Report January 2018 Waterview Operational Air Quality Monitoring Report January 2018 Document No: [Subject] Waterview Tunnel Joint Operation nzta.govt.nz/waterviewconnection 1399 Great North Road, Waterview, Auckland 1026

More information

Water NSW Reporting Manual

Water NSW Reporting Manual Water NSW Reporting Manual Operating Licence 2017-2022 Reporting Manual Water July 2017 Independent Pricing and Regulatory Tribunal of New South Wales 2017 This work is copyright. The Copyright Act 1968

More information

Alternative Resource Account Governance Process

Alternative Resource Account Governance Process Alternative Resource Account Governance Process Document Author: Alternative Resource Account Manager Date Approved: 26 th September 2018 Document Reference PO Alternative Resource Account Governance Process

More information

WHSE POL 1 WORK HEALTH, SAFETY & ENVIRONMENT MANAGEMENT POLICY

WHSE POL 1 WORK HEALTH, SAFETY & ENVIRONMENT MANAGEMENT POLICY Issue Number: 5 Prepared by (author): Greg McDonald, Group Manager WHSE Authorised by: Chen Wei Ng, Managing Director Date of release: 01 January 2014 Date of review 01 December 2015 WHSE POL 1 WORK HEALTH,

More information

The Water Connections Code for Scotland

The Water Connections Code for Scotland The Water Connections Code for Scotland Prepared by Authors: Issued Date: 21 st July 2014 Version: 1.3 1 Contents 1 Glossary of Terms...4 2 Foreword...6 2.1 Background...6 3 The Accreditation Scheme...8

More information

WORK HEALTH AND SAFETY AUDIT STANDARD

WORK HEALTH AND SAFETY AUDIT STANDARD WORK HEALTH AND SAFETY AUDIT STANDARD FORESTRY INDUSTRY South Australia, Victoria and Tasmania Safety Standards 2017 2017 Content I. Introduction... 2 II. Audit Criteria and Indicators... 3 1 PLANNING...

More information

Level 2 NVQ Diploma in Building Maintenance Multi-trade Repair and Refurbishment Operations (Construction)

Level 2 NVQ Diploma in Building Maintenance Multi-trade Repair and Refurbishment Operations (Construction) Level 2 NVQ Diploma in Building Maintenance Multi-trade Repair and Refurbishment Operations (Construction) Qualification Specification ProQual 2018 Contents Page Introduction 3 Qualification profile 3

More information

Sickness and Absence Policy

Sickness and Absence Policy Sickness and Absence Policy Page 1 of 9 1.0 Purpose 1.1 This procedure is intended to support staff whilst enabling managers to manage sickness absence in a way, which is fair, consistent, that adheres

More information

VIRIDOR WASTE MANAGEMENT LTD

VIRIDOR WASTE MANAGEMENT LTD VIRIDOR WASTE MANAGEMENT LTD Proposed re-phasing of landfilling operations; amended restoration levels and aftercare scheme; and provision of a new waste reception building with associated site infrastructure

More information

Procedure for Conducting Audits and Management Reviews

Procedure for Conducting Audits and Management Reviews Procedure for Conducting Audits and Management Reviews 1.0 Purpose This procedure establishes the method by which Quality System audits and management reviews are performed within the State Crime Laboratory

More information

Date Ratified 02/12/2010 Business Service Development Committee Review Date 01/12/2012 Director of Operations Expiry Date 01/12/2013 Withdrawn Date

Date Ratified 02/12/2010 Business Service Development Committee Review Date 01/12/2012 Director of Operations Expiry Date 01/12/2013 Withdrawn Date Policy No: RM66 Version: 2.0 Name of Policy: Business Continuity Planning Policy Effective From: 24/02/2011 Date Ratified 02/12/2010 Ratified Business Service Development Committee Review Date 01/12/2012

More information

Modification Number: M1

Modification Number: M1 1 General considerations...1 2 Site engineering for pollution prevention and control...10 3 Site infrastructure...13 4 Site operations...14 5 Amenity management and reporting...21 6 Site records...24 7

More information

P&O FERRYMASTERS HOLDINGS LIMITED POLICY STATEMENT

P&O FERRYMASTERS HOLDINGS LIMITED POLICY STATEMENT P&O FERRYMASTERS HOLDINGS LIMITED POLICY STATEMENT P&O Ferrymasters Holdings Limited and its subsidiary undertakings (referred to as P&O Ferrymasters ) means P&O Ferrymasters Limited and any other company

More information

MSP 50 CONTROL OF CONTRACTORS

MSP 50 CONTROL OF CONTRACTORS CONTROL OF CONTRACTORS AUTHORISED BY: PURCHASING MANAGER DATE: 14/03/2011 THIS DOCUMENT WILL FORM PART OF THE PRE-TENDER, TENDER AND CONTRACT PROCESSES FOR EACH CONTRACT AND AS SUCH SHALL BE REQUIRED TO

More information

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol 1/11 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP EM EPA ERAP OEH PAH OOHWP EIS MCoA Distribution

More information

CONDUCTING CRITICAL CONTROL AUDITS CS-OHS-60

CONDUCTING CRITICAL CONTROL AUDITS CS-OHS-60 CS ENERGY PROCEDURE FOR CONDUCTING CRITICAL CONTROL AUDITS CS-OHS-60 Responsible Officer: Health and Safety Specialist Responsible Executive: Group Manager Safety Environment and Quality DOCUMENT HISTORY

More information

WASTE MANAGEMENT PROGRAM

WASTE MANAGEMENT PROGRAM Waste Management Program Page 1 of 23 WASTE MANAGEMENT PROGRAM 1.0 Objective The objective of this performance assessment is to evaluate the effectiveness of the laboratory's waste management program as

More information

INJURY & ILLNESS PREVENTION PROGRAM

INJURY & ILLNESS PREVENTION PROGRAM INJURY & ILLNESS PREVENTION PROGRAM For Compliance with: California code of Regulations, Title 8 General Industry Safety Orders Section 3203 CHARLES D. KISSEL CSUF Auxiliary Services Corporation Injury

More information

Section 11: Water treatment and related matters

Section 11: Water treatment and related matters SEC TION 11: WATER TREATMENT AND RELATED MATTERS 11 Section 11 Section 11: Water treatment and related matters Summary of Section 11 Describes the importance of quality assurance systems including written

More information

Practical Odour assessment. Nigel Gibson

Practical Odour assessment. Nigel Gibson Practical Odour assessment Nigel Gibson Odour - the problem The process of concern Local residents 1 Topics covered Complaints Off-site survey Odour/odorant sampling Odour/odorant measurement Odour assessment

More information

Whiting Metals, LLC 2230 Indianapolis Boulevard Hammond, Indiana 46394

Whiting Metals, LLC 2230 Indianapolis Boulevard Hammond, Indiana 46394 Permit # 03687 OPERATION PERMIT Hammond Department of Environmental Management Air Pollution Control Division 5925 Calumet Avenue Hammond, Indiana 46320-2598 (219) 853-6306 Whiting Metals, LLC 2230 Indianapolis

More information