Anaerobic Digestion in Scotland Opportunities and Challenges. Jenny Grant 23 rd May 2013

Size: px
Start display at page:

Download "Anaerobic Digestion in Scotland Opportunities and Challenges. Jenny Grant 23 rd May 2013"

Transcription

1 Anaerobic Digestion in Scotland Opportunities and Challenges Jenny Grant 23 rd May

2 About REA Largest UK trade association for renewables: Over 900 corporate members All sizes one man bands to multinationals All sectors (power, heat, green gas to grid and transport & waste) Members activities span all technologies Unparalleled track record of policy wins Work with other associations Members of all sizes with democratic, 1 member, 1 vote structure FITS & RHI campaign with FOE 2

3 REA FITs Seminar 3

4 Scale of AD industry in UK 104 plants in UK (plus 146 plants in water industry) Wide range of capacities Electric production capacity of 88MW Plants are community (waste fed), agricultural or industrial 4

5 Plants in Scotland 4 Industrial (distillery) plants 6 community (food waste) plants 6 agricultural plants 5

6 Biogas Installations in Scotland Year KWe Feedstock Tuquoy - Westray Farm residues Gask Farm, Turriff Abattoir, farm 7 On Farm SW Scotland 2006 Heat Slurries Comhairle nan Eilean Siar I of Lewis MSW Food Girvan, Ayrshire Malting wastes North British, Edinburgh Malting wastes Roseisle, Elgin, Speyside 2010 Malting wastes Bruichladdich, 2010 Malting wastes Scottish Water Deerdykes, Cumbernauld Food Energen / Shanks, Cumbernauld Food Scottish & Southern, Barkip, Ayrshire Food Binn Farm (TEG), Glenfarg, Perthshire Food REA FITs Seminar 6

7 Rennie & Sons, Gask Farm AD plant Turriff REA FITs Seminar 7

8 Why AD? Waste (Scotland) Regulations > Requirement for separate food waste collections > Ban on macerators > Landfill ban for biodegradable waste Incentives Benefits of Digestate 8

9 Incentives Feed-in Tariffs (FiTs) > Facilities with less than 5MW capacity > 3 bands - tarriff dependent on size > Degression from 2014, issue for plants <500 kwe Renewables Obligation Scotland > All scales of plants > Currently 2 ROCs/MWh > From 2017, closed to new generators 9

10 Incentives Renewable Heat Incentive > Biogas combustion up to 200kW scale receives 7.3p/kWh > Larger scale (phase 2) announced summer 2013 > Biomethane injection to grid receives 7.3p/kWh Levy Exemption Certificates Renewable Transport Fuel Obligation 10

11 Biofertiliser Certification Scheme Provides assurance to consumers, farmers, food producers and retailers that biofertiliser is safe and of good quality. The BCS uses the PAS110 and additional scheme rules as instruments recognised by SEPA as end of waste criteria where the material becomes a product. Material can be used in markets specified where waste regulations do not apply. 11

12 PAS110: 2010 Specification for digestate including: > the requirements for a QMS and HACCP > control of input materials > Process management and monitoring > Pasteurisation > Testing parameters and upper limits > Actions in the event of a test failure 12

13 Consultancy Support WRAP funded consultancy support to assist plant operators become certified Maximum of 3 days support available for 10 plants up to end March 2014 Assist with QMS, HACCP and identify any other compliance issues Consultant allocation administered by BCS - contact us to request an application form 13

14 Benefits of Digestate Excellent alternative to bagged fertiliser > Readily available nitrogen > Useful amounts of phosphate and potash Financial value of nutrients in digestate 6.55 per tonne Lots of WRAP trials demonstrating benefits 14

15 Challenges Funding Uncertainty of tarriffs and incentives long term Difficult for small scale plants Planning community engagement very important Quality Assurance Schemes acceptance of digestate 15

16 Biogas Scotland Sector Group Advice on regulations specific to Scotland Scotland specific policy development and support Events and training courses Information and newsletters Technical advice and PAS110 advice specific to Scotland 16

17 Jenny Grant AD Portal -