2015 BASELINE ASSESSMENT A REPORT CARD FOR ROADS, WATER, SEWER, AND STORMWATER APPENDIX

Size: px
Start display at page:

Download "2015 BASELINE ASSESSMENT A REPORT CARD FOR ROADS, WATER, SEWER, AND STORMWATER APPENDIX"

Transcription

1 2015 BASELINE ASSESSMENT A REPORT CARD FOR ROADS, WATER, SEWER, AND STORMWATER APPENDIX FEBRUARY, 2015

2 GRADING SCALE Classification Description Value A Exceptional: Fit for the future The infrastructure in the system or network is generally in excellent condition, typically new or recently rehabilitated, and meets capacity needs for the future. A few elements show signs of general deterioration that require attention. Facilities meet modern standards for functionnality and resilient to windstand most disasters and severe weather events B C Good: Adequate for Now Mediocre: Requires Attention The infrastructure in the system or network is in good to excellent condition; some elements show signs of general deterioration that require attention. A few elements exhibit significant deficiencies. Safe an reliable with minimal capacity issues and minimal risk The infrastructure in the system or network is in fair to good condition; it shows general signs of deterioration and requires attention. Some elements exhibit significant deficiencies in conditions and functionality, with increasing vulnerability to risk D Poor: At Risk The infrastructure is in poor to fair condition and mostly below standard, with many elements approaching the end of their service life. A large portion of the system exhibits significant deterioration. Condition and capacity are of significant concern with strong risk of failure F Failing/Critical: Unfit for Purpose The infrastructure in the system is in unacceptable condition with widespread advanced signs of deterioration. Many of the components of the system exhibit signs of imminent failure. 19 0

3 GRADING CRITERIA CAPACITY CONDITION FUNDING FUTURE NEED OPERATION AND MAINTENANCE PUBLIC SAFETY RESILIENCE INNOVATION Evaluate the infrastructure's capacity to meet current and future demands Evaluate the infrastructure's existing or near future physical condition Evaluate the current level of funding (from all levels of government) for the infrastructure category and compare it to the estimated funding need Evaluate the cost to improve the infrastructure and determine if future funding prospects will be able to meet the need Evaluate the owner's ability to operate and maintain the infrastructure properly and determine that the infrastructure is in compliance with government regulations. Evaluate to what extent the public's safety is jeopardized by the condition of the infrastructure and what the consequences of failure may be. Evaluate the infrastructure system's capability to prevent or protect against significant multihazard threats and incidents and the ability to expeditiously recover and reconstitute critical services with minimum damage to public safety and health, the economy, and national security. Evaluate the implementation and strategic use of innovative techniques and delivery methods.

4 THIS PAGE INTENTIONALLY LEFT BLANK

5 INFRASTRUCTURE BASELINE ASSESSMENT ROADS SUPPORTING INFORMATION FEBRUARY, 2015

6 ROADS Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Weighted Value Weighted Value Arterial Collector Local Alley Weighted Average Overall D+ The City maintains over 72 miles of local roadways. Roadways are classified as Arterial, Collector and Local. The Arterial and Collector roads within the City limits total 16.8 miles and are maintained by the State and County. The Public Works Department focuses on pavement management while the Engineering Division focuses on replacing streets that are beyond rehabilitation. The City tracks the condition of all its roads and alleys via a pavement maintenance management software known as MicroPAVER. A Pavement Condition Index (PCI) is utilitized to determine an appropriate maintenance budget and activities to prevent roads from falling into disrepair.

7 Road Asset Value & Replacement Cost Pavement Condition Index PCI PCI Range Pavement System Description Road Miles as % of Roads 100 To 86 Good A 18 58% 85 To 71 Satisfactory B To 56 Fair C 21 29% 55 To 41 Poor 7 D 40 To 26 Very Poor 1 12% 25 To 11 Serious 1 F 10 To 0 Failed 0 COSA Roads Rehabilitation Costs $4,463,900 $4,391,500 Replacement Costs $52,886,000 COSA Roads Surface Breakdown Surface Material Quantity (Miles) % of Total Average PCI Asphalt % 69 Brick 1.9 3% 73 Concrete 0.4 1% 89 Unpaved 4.1 5% 97 Total 72.8

8 THIS PAGE INTENTIONALLY LEFT BLANK

9 INFRASTRUCTURE BASELINE ASSESSMENT WATER DISTRIBUTION SUPPORTING INFORMATION FEBRUARY, 2015

10 WATER DISTRIBUTION SYSTEM Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Component Weighting Weighted Value Distribution % Water Meters % 2.07 Weighted Average 100% 50.6 Overall C The City's water distribution system is comprised of over 200 miles of distribution mains ranging in size from 2 to 20 inches, 3,941 valves, 973 fire hydrants and over 13,000 service connections. The current efforts of the water main replacement program has resulted in over 30,000 linear feet of distribution mains replaced in the past 3 years. In house crews conduct preventative maintenance measures on each fire hydrant annually to ensure fire protection for the citizens and business owners. The City's water distribution system has over 13,000 potable water service connections ranging in size from 5/8" to 6". The meters are read by in house meter readers. Approximately 56% of the system meters are greater than 10 years old and approximately 23% are more than 20 years old. As meters age they tend to deteriorate due to sand and particulates in the water which results in inaccurate and typically low recordings of water consumption. This makes it difficult for a utility to understand water consumption behaviors, institute water conservation measures, detect water losses and leaks, and appropriately charge customers for water usage. Currently meters in areas of water main construction projects are being evaluated and replaced as necessary.

11 WATER DISTRIBUTION SYSTEM COMPONENTS Distribution Component Capacity Condition Funding Future Need O&M Public Average Component Resilience Innovation Safety Weighting Distribution System % Hydrants % Weighted % Overall C Water Meters Component Capacity Condition Funding Future Need O&M Public Average Resilience Innovation Safety Water Meters Overall C

12 Water Distribution System Asset Value & Replacement Cost Estimated Construction Costs to Bring Deficient Water Distribution System Assets up to Acceptable Standard Approx Total Asset Value/Replacement Cost = $ 182,583,400 Approx Cost to Rehabilitate = $ 59,855,410 Distribution Distribution Pipe Total Unit Total Pipe Total Unit Total Size Length Cost Value Size Length Cost Value (inches) (feet) ($/ft) ($) (inches) (feet) ($/ft) ($) 1 2,734 $ $ 82, ,734 $ $ 410, ,887 $ $ 10,294, ,887 $ $ 30,883, ,003 $ $ 50, ,003 $ $ 150, ,187 $ $ 2,782, ,187 $ $ 3,478, ,560 $ $ 54,534, ,360 $ $ 19,554, ,855 $ $ 30,213,900 Approximate cost to eliminate all cast iron pipes equal $ 54,475, ,401 $ $ 28,280,200 to or less than 6 inches and upsize pipes less than ,724 $ $ 23,933,760 inches to a min ,301 $ $ 20,524,280 of 6 inches $ $ 52,160 Total $ 170,747,260 Hydrant Unit Cost Total Location No. ($/FH) Value City 569 $ 3,500 $ 1,991,500 County 404 $ 4,000 $ 1,616,000 Total $ 3,607,500

13 Water Distribution System Asset Value & Replacement Cost Estimated Construction Costs to Bring Deficient Water Distribution System Assets up to Acceptable Standard Water Meters Water Meters Meter Size No. of Meters Unit Total Type of Rehabilitation Age (Yrs) No. of Unit Total (inches) Cost Value Meters Cost Cost ($/Ea) ($) ($/Ea) ($) 5/8" 778 $ $ 447,350 Convert Water Meters Less 5 yrs 902 $ $ 207,460 3/4" 11,121 $ $ 6,394,575 Replace Meters More than 5 yrs 12,315 $ $ 5,172,300 1" 867 $ $ 650,250 Assume contractor conducts replacement program Total $ 5,379, " 33 $ 1, $ 42,075 2" 367 $ 1, $ 576,190 3" 39 $ 1, $ 70,200 6" 12 $ 4, $ 48,000 Total $ 8,228,640 Cost includes meter assembly and box

14 Water Distribution System: Pipe Material Length Total Weighted Size (feet) Length Point (inches) CI DI GS HDPE PVC (feet) Point , , ,178 37, , , ,003 1, ,419 19,768 23, , , , , , , ,467 2, , , ,848 1,439 3,886 71,551 99, ,929 1,652 2,724 53,996 73, Total 261,220 4,111 39,334 9, ,996 1,078, Weighted Hydrant Capacity Location No. Pipe Percent (%) Weighted City 569 Size of Point County 404 (inches) System Point Total 973 Dia. < Dia. < Dia Total * Diameters less than 6 inches do not provide adequate capacity for fire flow protection. Pipe Size Weighted Average = 56.1 C Material Weighted Average = 55.5 C Capacity Weighted Average = 60.0 B

15 Water Distribution System: Pipe by Material Percentage Valves Size CI DI GS HDPE PVC Size No Unknown Total Total

16 Materials 2012 Inventory (miles) Water Main Inventory & Replacement (Catch Up) Analysis 2012 Material Breakdown of Inventory (%) Inventory (miles) 12/16/2013 Material Breakdown of Inventory (%) 12/16/2013 Inventory (miles) 12/19/2014 Material Breakdown of Inventory (%) 12/19/2014 PVC % % % Cast Iron (CI) 55 28% % % CI < 6" 10 18% % % CI = 6" 28 51% % % Galvanized Steel (GS) 9 4% % % Ductile Iron (DI) 1 1% 1 0.5% 1 0.5%

17 Water Meters Size (inches) 5 yrs or less 6 to 10 yrs 11 to 15 yrs Age (Years) 16 to 20 yrs 21 to 25 yrs More than 25 yrs Total Meters by Size Capacity Weighted Capacity 5/8" ,780 3/4" 2,184 2,816 2,558 1,343 1, , ,470 1" , " ,310 2" ,690 3" ,730 6" Total Meters by Age 2,628 3,144 2,844 1,567 1,741 1,293 13, ,510 Condition Weighted Condition ,465 Capacity Overall = 66.5 B Condition Overall = 40.7 C

18 THIS PAGE INTENTIONALLY LEFT BLANK

19 INFRASTRUCTURE BASELINE ASSESSMENT WATER TREATMENT SUPPORTING INFORMATION FEBRUARY, 2015

20 WATER TREATMENT Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Component Weighting Weighted Value Wellfield % Water Treatment Plant % Weighted Average 100% 55.5 Overall C+

21 WELLFIELD Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Replacement Cost Weight Deep Wells $ 1,435, % Turbine Pumps and Motors $ 612, % Pump Well Houses $ 262, % Piping $ 5,500, % Electrical and Controls $ 1,190, % $ 9,000, % Weighted Overall C+ DEEP WELLS Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Well B Casing B Screen B Average Average 70.8 B TURBINE PUMPS AND MOTORS Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Pumps B Motors B Average Average 68.8 B

22 PUMP WELL HOUSES Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Structure B Average 68.6 B PIPING Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Pump Discharge B Main Pipe C Average Average 54.4 C+ ELECTRICAL AND CONTROLS Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Underground Elec B Electrical Panels B Control Panels B Average Average 60.8 B

23 WATER TREATMENT PLANT Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Replacement Weight Cost Lime Softening Plant $ 11,750, % Low Pressure Reverse Osmosis Plant (2.0 MGD) $ 11,750, % North Tank $ 1,750, % South Tank $ 1,750, % $ 27,000, % Weighted Overall C+ LIME SOFTENING PLANT Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Structure D Equipment D Piping D Elec and Controls C Average Average 38.8 D+ LOW PRESSURE REVERSE OSMOSIS (LPRO) PLANT Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Structure B Equipment B Piping B Elec and Controls B Average Average 67.0 B

24 NORTH TANK Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Structure B Equipment B Piping B Elec and Controls B Average Average 72.2 B SOUTH TANK Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Structure C Equipment C Piping C Elec and Controls C Average Average 54.0 C+

25 Water Treatment Systems Asset Value & Replacement Cost: Estimated Construction Costs to Bring Deficient Water Treatment System Assets up to Acceptable Standard Approx Total Asset Value/Replacement Cost = $ 36,000,000 Approx Cost to Rehabilitate = $ 15,350,000 Wellfield Wellfield Component Total Cost Component Total Cost Deep Wells ( gpm) Upper Florida Wells $ 3,500,000 Deep Wells $ 200,000 Transmission Pipe Line (12" and 20") $ 5,500,000 Turbine Pumps and Motors $ Total $ 9,000,000 Pump Well Houses Piping Electrical and Controls $ 200,000 $ $ 150,000 Total $ 550,000 Water Treatment Plant Water Treatment Plant Component Total Cost Component Total Cost Raw Water Blend (2.5 MGD) Low Pressure Reverse Osmosis Plant (4.0 MGD) North Tank and South Tank Lime Softening Plant Low Pressure Reverse Osmosis Plant (2.0 MGD) North Tank $ 400,000 $ 13,000,000 $ 200,000 Total $ 27,000,000 South Tank $ 1,200,000 Total $ 14,800,000

26 WELLFIELD BASELINE EVALUATION SUMMARY Component Avg Cost Deep Wells 70.8 B $ 200,000 Turbine Pumps and Motors 68.8 B $ Pump Well Houses 68.6 B $ 200,000 Piping 54.4 C+ $ Electrical and Controls 60.8 B $ 150,000 Overall 64.7 B Total Cost $ 550,000

27 DEEP WELLS Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Well B Casing B Screen B Average 70.8 B The City phased out nine (9) surficial wells as required by SJRWMD in 2008 when the new CUP Permit was issued. Installation of four (4) new Upper Floridan Aquifer with each well having a 1500 gpm capacity were installed between 2009 and These new wells in combinationwith three (3)) existing deep wells and one (1) surficial well form the wellfield system for the City. Also, as required by SJRWMD five (5) monitoring wells were installed in order to monitor the water quality of the groundwater. So, the wells are new and they are in good condition. A budgetary amount of $200,000 is established in this Report Card in order to provide acidification to each well within the next five (5) years.

28 TURBINE PUMPS AND MOTORS Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Pumps B Motors B Average 68.8 B New pumps and motors were installed when the new wells were drilled in These pumps and motor are presently in good condition and they will provide the projected flow to the WTP for treatment within the next twenty (20) years.

29 PUMP WELL HOUSES Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure B Average 68.6 B Pump Motor, Electrical and Control Panels for each new well are housed in a new Pump House made of concrete block and concrete roof. Each Pump Hose was designed and constructed to withstand winds of 150 mph. The pump houses are in good condition. The old pump houses that served to house the old motors and electrical equipment, must be demolished and all the debrie from the demolition must be disposed of in accordance with present regulations. An amount of $200,000 is assigned for demolition and material disposal of the old well houses.

30 PIPING Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Pump Discharge B Main Pipe C Average 54.4 C+ The discharge piping, fittings and valves from each well pump are in good condition. The transmission main that transports the raw water from the well field to the WTP is composed of 9,200 LF of 12 inch Ductile Iron pipe and approximately 39,300 LF of 20 inch Ductile Iron pipe. This transmission line was installed in 1981 and its in fair condition.

31 ELECTRICAL AND CONTROLS Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Underground Electric B Electrical Panels B Control Panels B Average 60.8 B New electrical and control systems were installed for each new well in The electrical and control systems are generally in good condition.. It is advisable that a new emergency generator be installed in one of the well sites in orderr to improve realibily service in case of power failure caused during major weather storms. A budgetary amount of $150,000 is estimated for for the purchasing and installation of the new emergency generator and transfer switch.

32 WATER TREATMENT PLANT BASELINE EVALUATION SUMMARY Component Avg Cost Lime Softening Plant 38.8 D+ $ 400,000 Low Pressure Reverse Osmosis Plant 67.3 B $ 13,000,000 North Tank 71.9 B $ 200,000 South Tank 55.0 C+ $ 1,200,000 Overall 58.2 C+ Total Cost $ 14,800,000

33 LIME SOFTENING PLANT Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Structure D Equipment D Piping D Electrical and Controls C Average 38.8 D+ The Lime Softening Water Treatment Plant was originally placed in service in the 1920s. Modifications to the original plant were constructed in Studies conducted in 2006 and 2007 determined that the City must build a new plant to replace the original plant. The Lime Softening Plant is scheduled for demolition when the new Low Pressure Reverse Osmosis (LPRO) is expanded to meet future demands. A budgetary amount of $400,000 is made for the demolition and disposal of the plant structures and piping

34 LOW PRESSURE REVERSE OSMOSIS (LPRO) PLANT Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Structure B Equipment B Piping B Electrical and Controls B Average 67.3 B The existing 2.0 MGD Low Pressure Reverse Osmosis WTP was built in This plant is scheduled to be expanded to 4.0 MGD within the next three or four years. The permeate from the expanded LPRO plant will be blended with pretreated raw water from the wellfield. The ultimate treatment capacity will be 6.5 MGD. The estimated cost for the treatment plant expansion has been estimated at $ 13 million dollars.

35 NORTH TANK Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure B Equipment B Piping B Electrical and Controls B Average 71.9 B The existing facilities of the North Tank are presently being rehabilitated. New pumps, piping, valves, metering, chemical feed systems and electrical controls are being replaced. Therefore, the mechanical, piping and electrical systems will be in good conditions. However, the 1.0 prestressed concrete tank needs to be cleaned, recoated and disinfected. A budget of $200,000 is estimated to perform the required work for the tank.

36 SOUTH TANK Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure C Equipment C Piping C Electrical and Controls C Average 55.0 C+ The South Tank facilities are in mediocre conditions and therefore a replacement of mechanical, piping and electrical systems are recommended to bring this facility to a good conditions and to provide a reliable service to the customers. Also the prestressed concrete tank must be cleaned, recoated and disinfected. A total budgetary amount of $1.2 million dollars is allocated for the complete rehabilitation of this facility.

37 INFRASTRUCTURE BASELINE ASSESSMENT SEWER COLLECTION SUPPORTING INFORMATION FEBRUARY, 2015

38 SEWER COLLECTION SYSTEM Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Component Weighting Weighted Value Gravity Conveyance System % 29.4 Forcemains % 17.3 Pump Stations % 4.5 Weighted Average 51.2 Overall C The City's sewer system is composed of the gravity conveyance system, lift stations, and forcemains. The gravity conveyance system incorporates 79.5 miles of gravity sewer piping ranging in size from 6 inch to 24 inch and approximately 1,950 manholes. There are 75 lift stations and approximatley 61 miles of associated forcemain rangining in size from 2 inch to 36 inch.

39 Sewer Collection System Asset Value & Replacement Cost Estimated Construction Costs to Bring Deficient Sewer Collection System Assets up to Acceptable Standard Approx Total Asset Value/Replacement Cost = $ 176,902,912 Approx Cost to Rehabilitate = $ 32,354,347 Gravity Sewer Gravity Sewer Pipe Total Unit Cost Total Pipe Total Unit Cost Total ($/ft)* Cost Size Length ($/ft) Value Size Length (inches) (feet) (inches) (feet) 6 13,634 $ $ 2,317, ,634 $ $ 2,045, ,239 $ $ 38,447, ,822 $ $ 5,403, ,576 $ $ 36,646, ,552 $ $ 380, ,510 $ $ 9,752, ,141 $ $ 760, ,999 $ $ 2,359, ,321 $ $ 76, $ $ 68, $ $ 44, $ $ 245, $ $ 12, $ $ 38,283 Approximate Cost to Upgrade to 6" diameter $ 8,723,036 Total $ 89,877,622 pipe to 8" and slip line non plastic materials = Manholes Unit Cost Total Manholes Unit Cost Total Material No. ($/MH) Value Material No. Brick 1145 $ 4,500 $ 5,152,500 Brick Rehab 573 $ 3,000 $ 1,719,000 Precast 793 $ 4,500 $ 3,568,500 Brick Replace 572 $ 4,500 $ 2,574,000 Unknown 161 $ 4,500 $ 724,500 Precast Rehab 199 $ 3,000 $ 597,000 Total $ 9,445,500 Unknown Rehab 161 $ 3,000 $ 483,000 Cost to replace or rehabilitate Total $ 5,373,000

40 Sewer Collection System Asset Value & Replacement Cost Estimated Construction Costs to Bring Deficient Sewer Collection System Assets up to Acceptable Standard Forcemains Forcemains Total Length (feet) Unit Cost ($/ft) Pipe Total Unit Cost Total Pipe Size (inches) Size Length ($/ft) Value (inches) (feet) Unknown 3,134 $ $ 391,700 Uknown 3,134 $ $ 391, ,920 $ $ 2,592, $ $ 6, ,416 $ $ 148, ,137 $ $ 392, ,159 $ $ 5,769, ,829 $ $ 574, ,536 $ $ 10,130, ,957 $ $ 1,432, ,548 $ $ 6,398, ,301 $ $ 6,460, ,937 $ $ 5,587, ,412 $ $ 4,178, ,439 $ $ 17,145, $ $ 9, ,955 $ $ 7,827, $ $ 193, $ $ 204, ,662 $ $ 1,678, ,400 $ $ 3,023, ,700 $ $ 1,572, ,564 $ $ 1,939,795 Approximate cost to replace Total $ 16,889,469 Total $ 61,159,790 *Assume Unknown is 4" piping unsuitable forcemain materials and add or increase size of existing forcemains for capacity Total Cost

41 Sewer Collection System Asset Value & Replacement Cost Costs to Bring Deficient Sewer Collection System Assets up to Acceptable Standard Pump Stations Wet Well Depth (feet) Discharge FM Size (inches) Total Value Pump Stations Discharge No. of Pump FM Size Stations Need (inches) Rehabilitation Total Cost D $/Pump Station $ 60,000 $ 145,000 $ 160,000 $ 225,000 $ 320,000 $ 375,000 $ 2,455, $ 108,456 >10 D $ 516,765 $/Pump Station $ 75,000 $ 160,000 $ 180,000 $ 250,000 $ 350,000 $ 400,000 $ 4,300, $ 275,871 >15 D $ 119,602 $/Pump Station $ 90,000 $ 180,000 $ 200,000 $ 275,000 $ 380,000 $ 460,000 $ 7,700, $ 86,332 >20 D $ 261,817 $/Pump Station $ 115,000 $ 205,000 $ 250,000 $ 325,000 $ 430,000 $ 515,000 $ 1,965,000 Total $ 1,368,842 Total $ 16,420,000

42 Sewer Conveyance System: Pipe Material Length Total Weighted Size (feet) Length Slip Lined Slip Lined Slip Lined Point (inches) Cast Iron Clay Ductile Iron Concrete/RCP PVC (feet) Point Cast Iron Clay Ductile Iron , , , , ,119 3, , ,731 8, , , ,681 16, ,449 37, , ,678 7, Total 1,288 1,155 41, , , , , Weighted 90,129 5,774 3,121, ,267 21,838 3,666 7,440 14,464, Manhole Capacity Pipe Size Weighted Average = 77.6 B+ Material No. Pipe Percent Weighted Material Weighted Average = 44.6 C Brick 1145 Size (%) of Point Capacity Weighted Average = 77.6 B+ Precast 793 (inches) System Point Unknown 161 Dia. < Condition (Pipe and Mtl Avg) = 61.1 B Total Dia. < Total * Diameters less than 8 inches do not meet minimum engineering standards and are assumed unfit for purpose resulting in a failing grade.

43 Forcemain System Pipe Material Length Total Weighted Size (feet) Length Point (inches) Uknown Cast Iron Ductile Iron HDPE PVC (feet) Point Uknown 3,134 3, ,699 24,160 25, ,416 1, ,869 1,268 43,022 46, , ,443 67, ,675 3,650 5,267 24,324 35, ,565 6,036 4,336 27, ,867 3, ,395 60,531 71, ,521 24,401 27, , , ,564 4, Total 9,695 36,796 11,781 12, , , Weighted Capacity Needed Length Importance Weighted Pipe Size Weighted Average = 79.3 B+ Pipe Size (feet) to Entire Material Weighted Average = 66.8 B (inches) System Point Capacity Weighted Average = 42.7 C () 6 1, Condition (Pipe and Mtl Avg) 73.0 B 8 3, , , , Total 26, *Based on an evaluation of forcemains needing an increase in size and the importance of that forcemain to the functionality and capacity of the entire sewer collection system.

44 Pump Stations Pump Station ID Discharge FM (inches) Upstream FM (inches) PS Type Wet Well Size (ft) HP Wet Well Depth (ft) Total Estimated Rehabilitation Cost Condition Weighted Condition Capacity Weighted Capacity PS 1 4 dry 5' 3 12 $30, PS 2 8 Sub 8' $34, PS 3 6 dry 5' $38, PS 4 4 dry 4' $37, PS 5 4 dry 4' 5 11 $35, PS 6 12 Sub Triplex 10' $121, PS 7 10 Sub Triplex 12' $47, PS 8 6 dry 6' 5 13 $32, PS 9 8 Sub 8' PS Sub Triplex 11.5' $47, PS 11 6 Sub 8' PS 12 6 Sub 8' $22, PS 14 6 Dry 5' $36, PS 15 4 Dry 6' 5 15 $30, PS 16 4 Sub 5' 1 7 $49, PS 17 6 Sub 4'.2'' 3 9 $4, PS 18 4 dry 5' 2 10 $30, PS Dry 8' 20 $25, PS Sub 6' PS 22 4 Sub 6' PS 23 6 Sub 8' $9, PS Sub 8' $13, PS 25 6 Dry 4' 3 9 $4, PS 26 6 Sub 4' 7 $21, PS 28 6 Sub 6' 3 12 $12, PS 29 6 Sub 6' 3 14 $7, PS 30 4 Sub 6' $4,

45 Pump Station ID Discharge FM (inches) Upstream FM (inches) PS Type Wet Well Size (ft) HP Wet Well Depth (ft) Total Estimated Rehabilitation Cost Condition Weighted Condition Capacity Weighted Capacity PS 34 6 Sub 8' $10, PS 35 6 Sub 6' 13 $6, PS 36 Dry Single 4' 1 7 $41, PS 38 6 Dry 5' 10" PS 39 6 Dry 5' PS 40 4 Dry 5' $6, PS 41 4 Dry 4' $50, PS 42 4 Sub 4' 3 9 $59, PS 43 2 Sub 4' 3 10 $3, PS 44 8 Sub 6' $20, PS 45 8 Sub 8' $10, PS 46 4 Sub 6' 2 11 $4, PS 47 4 Sub 4' 3 10 $4, PS 49 6 Sub 8' $11, PS 50 6 Dry 6' 5 $17, PS 51 8 dry 6' PS dry 8' PS 53 2 Sub 6.5" 2 12 $49, PS 54 6 Sub 6' 5 20 $36, PS 55 4 Sub 6' 20 9 $68, PS 56 4 Sub 6' $7, PS 57 4 Sub 6' 3 18 $6, PS 58 4 Sub 6' $39, PS 59 4 Sub 3' 5 $15, PS Sub 6' $36, PS 61 2 Sub 10' 3 20 $13, PS ' 10 $3, PS 63 4 Sub 8' 2 16 $35, PS Sub Triplex 127''x88'' 47 8 $56, PS 65 8 Sub 12' $55,

46 Pump Station ID Discharge FM (inches) Upstream FM (inches) PS Type Wet Well Size (ft) HP Wet Well Depth (ft) Total Estimated Rehabilitation Cost Condition Weighted Condition Capacity Weighted Capacity PS 66 6 Sub 8' PS 67 4 Sub 8' PS 68 6 sub 6' PS 69 4 Sub 8' PS 70 4 Sub 8' PS 71 6 Sub 6' PS 72 4 Sub 8' PS 73 4 Sub 8' PS Sub 6' PS 75 6 Sub 8' PS Sub 8' PS Sub 11.5' PS Sub 11.5' PS 80 4 Sub 11.5' PS 81 4 Sub 5.5' PS 82 6 Sub 7.5' PS PS Total 456 Condition Overall 51.1 C Capacity Overall 66.5 B Capacity grade based on overall assessment that the master (triplex) pump stations are approximately a "C" grade and the others are "B" grade. A pump station with a single Condition grade based on noted recommended upgrades, size of wet well (too small or non standard) and need for wet well liner; pump stations with no info or Resilience grade based on overall condition of pump stations and the fact that 28 of the 75 pump stations don't have pump outs

47 INFRASTRUCTURE BASELINE ASSESSMENT WASTEWATER TREATMENT SUPPORTING INFORMATION FEBRUARY, 2015

48 WASTEWATER TREATMENT Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Component Weighting Weighted Value WWTP % 49.5 Weighted Average 49.5 Overall C The WWTP has a permitted capacity of 4.95 MGD and utilizes a complete mix activated sludge treatment process which utilizes a headworks system for removal of grit and debris, aeration basins, clarifiers, disinfection chambers and post aeration. Effluent is disinfected utilizing paracetic acid, an innovative process which eliminates the creation of environmentally damaging chlorinated disinfection byproducts and reduced chemical costs. Effluent from the WWTP is discharged to the Matanzas River. Residuals are aerobically digested and dewatered and land applied.

49 WWTP Compilation of Weighted Using Cost Data HEADWORKS Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure D+ Equipment C Piping B Average Average 51.5 C BIOLOGICAL TREATMENT UNITS (BTUs) Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure D+ Equipment C Piping C Average Average 47.0 C CLARIFIERS Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure C Equipment C Piping C+ Average Average 52.0 C

50 Disinfection and Post Aeration Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure B Equipment B Piping B Average Average 62.5 B Return and Waste Sludge Pumping Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure C Equipment C Piping C Average Average 50.2 C Sludge Treatment and Handling Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure C Equipment C Piping C Average Average 47.9 C

51 Plant Pumping Station Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure C Equipment C Piping C Average Average 48.1 C Yard Piping Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Piping C Average 46.3 C Electrical Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Overall Electrical B Average 60.5 B

52 WWTP Compilation of Weighted Using Cost Data Overall WWTP Assessment Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Weight Headworks % BTUs % Clarifiers % Dis & Post Aer % RAS/WAS Pump % Sludge % Plant Pump % Piping % Overall Electrical % 100.0% Overall WWTP C

53 Wastewater Treatment System Asset Value & Replacement Cost Estimated Construction Costs to Bring Deficient Wastewater Treatment System Assets up to Acceptable Standard Approx Total Asset Value/Replacement Cost = $ 26,500,000 Approx Cost to Rehabilitate = $ 11,600,000 Wastewater Treatment Plant WWTP Capacity (MGD) Unit Cost ($/WWTP) Total Value Wastewater Treatment Plant Component Headworks $ Total Cost 3,000,000 5 $ 26,500,000 $ 26,500,000 Biological Treatment Units Clarifiers Disinfection and Post Aeration Return and Waste Sludge Pumping Sludge Treatment and Handling Plant Pumping Station Piping Electrical $ 5,000,000 $ 1,400,000 $ 200,000 $ 950,000 $ 320,000 $ 80,000 $ 500,000 $ 150,000 Total $ 11,600,000

54 WASTEWATER TREATMENT PLANT BASELINE EVALUATION SUMMARY Component Avg Cost Headworks 51.5 C $ 3,000,000 Biological Treatment Units (BTUs) 47.0 C $ 5,000,000 Clarifiers 52.0 C $ 1,400,000 Disinfection and Post Aeration 62.5 B $ 200,000 Return and Waste Sludge Pumping 50.2 C $ 950,000 Sludge Treatment and Handling 47.9 C $ 320,000 Plant Pumping Station 48.1 C $ 80,000 Piping 46.3 C $ 500,000 Electrical 60.5 B $ 150,000 Overall 51.8 C Total Cost $ 11,600,000

55 HEADWORKS Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Structure D Equipment C Piping B Average 51.5 C The headworks structurally is adequate for current conditions but does not have reserve strength for modifications to provide additional hydraulic capacity. The structure does not have the hydraulic capacity to handle Maximum Daily Flows. The equipment needs to be replaced to improve the removal of grit and rags that are present in the incoming flow. The construction of a new Headworks structure with a more efficient equipment is estimated at $3,000,000

56 BIOLOGICAL TREATMENT UNITS (BTUs) Component Capacity Condition Funding Future Need O&M Public Safety Resilience Innovation Average Structure D Equipment C Piping C Average 47.0 C The biological treatment units presently meet treatment requirements, although the concrete structures are in a need of repair due to vertical cracking in the structure walls. A new aeration system was installed in 2010 which provides the required air for treatment and mixing. It is estimated that EPA and FDEP will require Advance Wastewater Treatment to this facility in the next permit period (2019). Furthermore, it is also estimated the WWTP needs to be expanded to accommodate additional flow. Therefore these structures need to be modified to accommodate more flow and removal of nitrogen and phosphorous. The estimated cost for the BTUs modifications and structural repairs is approximately $5,000,000 for both structures

57 CLARIFIERS Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure C Equipment C Piping C Average 52.0 C The clarifier structures need to be repair to bring them to a good condition. The equipment has reached the life expectancy and need to be replaced in their totallity. The estimated cost to make the structural repairs and replace the equipment on both clarifiers is approximately $1,400,000

58 Disinfection and Post Aeration Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure B Equipment B Piping B Average 62.5 B The disinfection and post aeration structure is in a good condition. Presently, no modifications or additions to this structure are contemplated. It appears that this structure has enough capacity to meet the required detention time for the expansion of the WWTP in the future. A budget figure of $200,000 is included in this evaluation to recoat the inside walls of the structure in the future.

59 Return and Waste Sludge Pumping Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure C Equipment C Piping C Average 50.2 C The pumping equipment and piping of the return sludge and waste sludge systems are in mediocre condition and need to be replaced, The primary issue with these systems is that the pumps, piping and valves are near the end of their service life and therefore need replacement. The key engineering goal for this task will be equipment selection to meet hydraulic and functional requirements within the constrains of the existing infrastructure. The estimated cost to replace the return sludge and waste sludge pumping and piping systems is approximately $950,000.

60 Sludge Treatment and Handling Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure C Equipment C Piping C Average 47.9 C The aerobic Digesters are near the end of their life expectancy. However these structures can be rehabilitated to bring them to a good condition. As mentioned before the present regulations can change, so at this time is very difficult to predict any upgrades that need to be implemented to the entire sludge treatment and handling facilities. The supernatant lift station for the digesters needs to be rehabilitated in its entirely There are some booster pumps within the system that need to be replaced. Also, it is advisable to improve the inside conditions of the aerobic digesters by blasting and lining the interior walls. A cost estimate for the improvements of this WWTP component is as follows: Replace Booster pumps $70,000. Supernatant Pumping Station $100,000 and Rehab the digesters by blasting and lining the interior walls $ 150,000. Therefore the total cost is approximately, $320,000

61 Plant Pumping Station Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Structure C Equipment C Piping C Average 48.1 C The Plant Pumping Station needs to be refurbished to bring it to a good and operable condition. It is required that the wetwell be lined to discontinue the deterioration of the concrete walls. Piping must be replaced and the electrical cabinet and pump controls must be replaced. The estimate cost to bring the Plant Pumping Station to a good condition is approximately $80,000

62 Yard Piping Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Piping C Average 46.3 C The existing piping that transport the wastewater troughout the entire plant lacks of valves which makes the system difficult to operate and control the flows between different WWTP tanks. Also the existing structures lack of drain pipes and valves. Therefore, pumps must be utilized to empty tanks for maintenance or repairs. An estimated budget of $500,0000 is assigned for the installation of the valves. Not budget is assigned to retrofit the existing structures with drain pipes. This retrit is costly and the City can continue utilizing pumps to drain the tanks.

63 Electrical Component Capacity Condition Funding Future Public Average O&M Resilience Innovation Need Safety Overall Electrical B Average 60.5 B The electrical system at the WWTP was refurbished in The electrical system was brought to meet the Electrical Code Standards. New conduits, wire and new electrical contol panels were installed to replace the old electrical system. There is an existing Motor Control Center (MCC) that need to be replaced. The cost of the replacement of this MCC is estimated at $150,000

64 THIS PAGE INTENTIONALLY LEFT BLANK

65 INFRASTRUCTURE BASELINE ASSESSMENT STORMWATER SYSTEM SUPPORTING INFORMATION FEBRUARY, 2015

66 STORMWATER Future Public Average Weighted Weighted Component Capacity Condition Funding O&M Resilience Innovation Need Safety Value Value Conveyance System Channels Treatment Structures Weighted Average Overall D+ The City's stormwater conveyance system spans 13 watersheds consisting of pipes, inlets, manholes, water quality treatment structures and swales within the road system and drainage channels. St. Augustine has approximately 3 miles of channels, 20 miles of storm sewer pipes and culverts including 103 outfalls to surrounding waterbodies, 949 inlets, 298 manholes and 14 treatment structures. Since 1995, extensive improvements have been made in areas that suffered from frequent flooding while new stormwater conveyance systems are constructed with road projects. Maintenance is performed on a routine basis and repairs are made on an as needed.

67 Stormwater System Asset Value & Replacement Cost Estimated Construction Costs to Bring Deficient Stormwater System Assets up to Acceptable Standard Approx Total Asset Value/Replacement Cost = $ 29,966,430 Approx Cost to Rehabilitate = $ 11,792,000 Pipe Total Pipe Total Unit Cost Total Unit Cost Total Size Length Size Length ($/ft) Value ($/ft) Value (inches) (feet) (inches) (feet) $ $ 19, $ $ 32, $ $ 218, $ $ 364, $ $ 2,029, $ $ 3,383, $ $ 1,777, $ $ 2,962, $ $ 3,029, $ $ 5,049, $ $ 3,073,000 Approximate Cost to Upgrade to 15" diameter $ 11,792, $ $ 157,250 pipe = $ $ 3,021, $ $ 430, $ $ 43, $ $ 2,836, $ $ 439, $ $ 1,738, $ $ 852, $ $ 774, $ $ 458, $ $ 335, $ $ 214,200 Total $ 21,450,430

68 Stormwater System Asset Value & Replacement Cost Manhole Unit Cost Total Material No. ($/MH) Value Brick 211 $ 4,500 $ 949,500 Precast 87 $ 4,500 $ 391,500 Total $ 1,341,000 Inlets No. Unit Cost ($/Inlet) Total Value 949 $ 5,000 $ 4,745,000 Outfall No. 103 $ 10,000 $ 1,030,000 Treatment Str. No. Unit Cost ($/OF) Unit Cost ($/TS) Total Value Total Value 14 $ 100,000 $ 1,400,000

69 Conveyance System: Pipe Material Length Total Weighted Size (feet) Length Point (inches) ADS Cast Iron Clay CMP Concrete HDPE PVC RCP (feet) Point Total Weighted