INTRODUCTION SITE LOCATION AND SURROUNDINGS CONNECTIVITY CONCEPTUAL PLAN. M/s Aura Buildwell Pvt. Ltd. 46. Conceptual Plan

Size: px
Start display at page:

Download "INTRODUCTION SITE LOCATION AND SURROUNDINGS CONNECTIVITY CONCEPTUAL PLAN. M/s Aura Buildwell Pvt. Ltd. 46. Conceptual Plan"

Transcription

1 CONCEPTUAL PLAN INTRODUCTION Sports City- Proposed Group Housing & Villas project to be developed by M/s Aura Buildwell Pvt. Ltd. The Project is located at SC-02-B, on a land measuring 96, Sq.m. The name of the developer is M/s Aura Buildwell Pvt. They have been successful in providing specifically designed housing solutions to the elite professional keeping in mind their daily needs and their exquisite taste in lifestyle. SITE LOCATION AND SURROUNDINGS Sports City- Proposed Group Housing & Villas project is located at SC-02-B, Sector 27, Greater Noida, U.P. The Co-ordinates of the project site are N and E. Google earth image & Toposheet map showing project site & surroundings within 500 m and 2 km are attached at Annexure 1(a & b). CONNECTIVITY The project site is well connected to transport facilities. The site has excellent connectivity to Noida Greater Noida expressway about 0.69 km away from project site in South direction and Dadri main Road about 3.19 km away from project site in North direction. The nearest railway station is Dadri Railway Station, about km away from the project site in NE direction. The nearest airport is Indira Gandhi International Airport, New Delhi, which is about km from the project site in West direction. M/s Aura Buildwell Pvt. Ltd. 46

2 AREA STATEMENT The total area of the project is estimated at 96, m2 (or acres). The detailed Area Statement is provided below in Table 1. Table 1: Area Statement S. No PARTICULARS F.A.R. % SQ.MTR./NOS. 1 Total Plot Area 96, A Permissible F.A.R For Housing = X 1.5 = ,44, Additional F.A.R For Green Building B 5% Of Permissible F.A.R 7, = 5% OF Total Permissible F.A.R = A + B 1,51, Permissible 15% F.A.R. For Facility Of Total Main F.A.R Area, 15% Of % 21, = Sq.Mt. 3 Permissible Ground Coverage % = Sq.Mt. 30% 28, Proposed Total Ground Coverage (@ 17.54% ) 16, Permissible F.A.R For Commercial = X 1.5 = Sq.Mt 2, Proposed Commercial F.A.R Area Details 2, Total F.A.R. Achieved 1,48, A F.A.R Achieved For Residential 1,45, B F.A.R Achieved For Commercial 2, C F.A.R For Swimming Centre Total Achieved Area For Basement Achieved For Facility A Proposed Area In 15% Facility Area Housing = Fire Staircase Area + Lift Lobby Area + Mumty Area + Machine Room Area + Lift Shaft Area + Service Shaft Area + Cupboard + Gaurd Room + Over Head Tank + S.T.P + L.T. Panel Room 9, M/s Aura Buildwell Pvt. Ltd. 47

3 9 Required Landscape Area Required Landscape Area = 50% Of Open Area Open Area = Plot Area - 30% Ground Coverage ) 33, = 50% Of ( ) 10 Proposed Landscape Area. 35, Total Built-Up Area 1,97, A Total F.A.R. Area 1,48, B Total Basement Area C Total Facility Area In 15% D Total Stilt Area Total ( A + B + C + D ) 35, , , ,97, *(Source: Site Plan) Table 2: Per cent wise plot area breakup S. No Particulars Area (in sq.m.) Percentage (%) 1 Plot area Ground Coverage Landscape Area Open Parking Area Paved Area/Road Area for vehicular movement POPULATION DENSITY The total population of the project is 6439 persons. The detailed population breakup is given below in the Table 2. Table 3: Population Break up S. No. Category No. of Persons 1. Dwelling Units (Villas + Apartments) (1152 units) 5189 M/s Aura Buildwell Pvt. Ltd. 48

4 3. Club & Floating Population Staff Commercial/ Shopping 150 WATER REQUIREMENT During operation phase, water will be supplied by Greater Noida Industrial Development Authority. The total water requirement is approx KLD, out of which fresh water requirement is KLD. This works out to % of the total water requirement. The remaining water requirement will be met through treated water. The daily water requirement calculation is given below in Table 3: S. No. Particulars 1. Dwelling Units Residents 2. Club & Floating Population 3. Commercial + Staff Table 4: Calculations for Daily Water Demand Expected Population 5,189 (@ 4.5 persons/dwelling unit) Base of Calculation (lpcd) 135 (90 lpcd for fresh water and 45 lpcd for flushing) (10 lpcd for fresh water and 5 lpcd for flushing) (30 lpcd for fresh water and 15 lpcd for flushing) Treated Water Fresh Water Total Water Flushing Other Domestic Other Consumption (KLD) (KLD) (KLD) (KLD) (KLD) Filter M/s Aura Buildwell Pvt. Ltd. 49

5 Backwash 5. Make- up for swimming pool 6. Green Belt ( sq. m) Lit / sq. m Total WASTE WATER GENERATION Table 5: Water Requirement &Waste Water Generation S. No. Description Quantity of water (KLD) 1. Total water requirement Fresh water availability Waste water generation (80% of fresh water + 100% of flush water) 4. Water requirement for green area STP Capacity Treated water from STP (80% of waste water) 526 Wastewater Generation & Treatment It is expected that the project will generate approx KLD of wastewater. The wastewater will be treated in a STP provided within the Group Housing Complex. It will generate KLD of treated water. After reusing in flushing and green area development KLD of treated water will become surplus, which will be used for nearby construction site/maintenance of greenbelt. M/s Aura Buildwell Pvt. Ltd. 50

6 Figure 1: Water Balance Diagram Water Conservation Plan: To reduce the consumption of water and conserve the same the following measures will be taken during construction & operation phase of the project. (A) Construction Phase: 1. Usage of Ready mix concrete at the site. 2. Usage of water sprinklers for curing. 3. The concrete will be covered with gunny bags before spraying of water so as to retain maximum moisture for a longer period. 4. Creation of ponds at the construction site to collect the surface runoff. This will be reused in curing and washing of wheels of vehicles. 5. A Supervisor will be posted at the site to look after proper usage of water resources at the site to prevent its wastage. M/s Aura Buildwell Pvt. Ltd. 51

7 (B) Operation Phase: 1. Installation of water meter at inlet & outlet point to monitor water consumption and detect leakages. 2. Usage of water conservation fixtures in toilets and bathrooms like dual flushing cistern, sensor operated low faucet water taps 3. Low water/waterless urinals will be provided in commercial & institutional area 4. Installation of low flow shower in bathrooms. 5. Tap aerators or flow regulators will be installed to increase water delivery pressure even at low flow rate 6. Dual pipe plumbing system will be installed for use of STP treated water for flushing, horticulture & DG cooling. 7. Installation of rain water Harvesting System to recharge ground water. Extent of water saving Extent of water saving is provided in the table below: Table 6: Extent of water savings FIXTURE OPERATIONS WATER SAVING CISTERNS 2/4 Dual Flush Pressing one button discharges 2 Savings 6-8 litres/flush. cistern fittings litres/flush and pressing both the (standard flush uses buttons discharges 4 liters/flush litres/flush) URINALS Sensor Operated Water is applied automatically on asset frequency through drip feeding system Saves litres (standard flush uses Litres litres/flush) FAUCETS M/s Aura Buildwell Pvt. Ltd. 52

8 Electronic Meters IRRIGATION Drip Irrigation Open or Close taps by the proximity detection Land is irrigated through tiny holes on pipe reducing evaporative losses of water Saves 40-50% water Saves 40-50% water SEWAGE TREATMENT TECHNOLOGY FAB TECHNOLOGY Sewerage System An external sewage network will collect the sewage from all the units and flow by gravity to the proposed sewage treatment plant. Following are the benefits of installing a Sewage Treatment Plant in the proposed Expansion of Group Housing project. Reduced net daily water requirements. Availability of treated water for Horticultural uses. Less dependence on public utilities for water supply and sewerage systems. Sludge generated from the Sewage Treatment Plant is rich in organic content which works as excellent fertilizer for horticultural purposes. Wastewater Details (a) Daily load (KLD) : (b) Duration of flow to STP (hours) : 24 M/s Aura Buildwell Pvt. Ltd. 53

9 (c) Maximum Temperature (Celcius) : 32 0 (d) ph : 7 to 9.5 (e) Colour : Mild (f) T.S.S. (mg/l) : (g) BOD 5 (mg/l) : (h) COD (mg/l) : b. Final discharge characteristics (a) ph : 6.5 to 7.5 (b) Oil & Grease mg/l : <10 (c) B.O.D. mg/l : <10 (d) C.O.D. mg/l : <20 (e) Total Suspended Solids mg/l : <10 Treatment Technology The technology is based on attached growth aerobic treatment followed by clarification by a tube settler. Lime will be dosed in for suppression of foaming tendencies. The clarified water will be filtered in a pressure sand filter after dosing of coagulant (alum) for removal of unsettled suspended impurities. This water will be passed through an activated carbon filter for removal of organics. The filtered water from ACF is then chlorinated & stored in the flushing tank. The attached growth fluidized aerobic bed reactor (FAB) process combines the biological processes of attached & suspended growth. It combines submerged fixed film with extended aeration for treatment of the waste water. The waste water after screening is collected in an equalization tank. The equalization tank is required for preventing surges in flow & facilitating equalization of characteristics over the M/s Aura Buildwell Pvt. Ltd. 54

10 entire quantity of effluent in a given time. A provision for pre-aeration is made in the equalization tank in order to ensure mixing & to prevent the sewage from going septic. The equalized sewage is then pumped into the FAB reactor for biological processing. The water enters the bottom of the reactor & flows up through the fixed film media which grossly enhances the hydraulic retention time & provides a large surface area for growth of biological micro organisms. The FAB reactor is aerated by fine pore sub surface diffusers which provide the oxygen for organic removal. The synthetic media floats on the water & the air agitation ensures good water to micro-organism contact. The FAB treatment is an attached growth type biological treatment process wherein the majority of biological activity takes place on the surface of the PVC media. Continuous aeration ensures aerobic activity on the surface of the media. Micro organisms attach themselves on the media & grow into dense films of a viscous jelly like nature. Waste water passes over this film with dissolved organics passing into the bio-film due to concentration gradients within the film. Suspended particles & colloid may get retained on this sticky surface where they are decomposed into soluble products. Oxygen from the aeration process in the waste water provides oxygen for the aerobic reactions at the bio-film surface. Waste products from the metabolic processes diffuse outward & get carried away by the waste water or air currents through the voids of the media. The aerated effluent passes into a tube deck settler for clarification. The theory of gravity tube settler system is that the carrier fluid maintains laminar flow in the settling media at specified maximum viscosity. These two parameters of a carrier fluid, flowing through a hydraulic configuration, will determine the velocity gradients of the flow, the height of boundary layer at the inclined surface and the residence time within the media. The carrier fluid must be viscous Newtonian, exhibiting a Reynolds number of less than 1000 and preferably, a number under 400. The laminar flow, through the inclined tubes, will produce velocity gradients sufficiently large to form an adequate boundary layer, where the velocity of M/s Aura Buildwell Pvt. Ltd. 55

11 fluid approaches zero. Boundary layers are necessary in functioning tube settlers, to allow suspended solids to separate from the viscous carrier fluid. Under gravitational forces, they will settle to the hydraulic surface of the tube and subsequently from the clarifier media. Since the tubes are inclined at 60 degrees, solids settled on the tubes are continually discharged down. This downward rolling action increases particle contact and hence further agglomeration, which increases the sludge settle ability. Studies show that these agglomerated sludge particles can have a settling rate in excess of ten times the settling rate of the individual flock particles in the influent. These heavy agglomerated masses quickly slide down the 60 degree inclined tube and settle at the bottom of the tank. At the bottom of the Tube deck, where the sludge leaves the Tube surface, the larger agglomerated captures smaller particles in the upcoming stream. This solid contact phenomenon greatly enhances the capture efficiency. Stages of Treatment: The treatment process consists of the following stages: Equalization Bio- Degradation Clarification & Settling Filtration Figure 2: Schematic Diagram of STP M/s Aura Buildwell Pvt. Ltd. 56

12 Sewer System The alignment and slope of the sewer line will follow the road network, drains or natural ground surface and will be connected to the trunk sewers. The discharge point will be a treatment plant, a pumping station, a water course or an intercepting sewer. Pumping stations will be provided at places where the natural slope of the terrain is insufficient to permit gravity flow or the cost of excavation is uneconomical to do the same. PROPOSED RAIN WATER HARVESTING SYSTEM The storm water disposal system for the premises will be self-sufficient to avoid any collection/stagnation and flooding of water. The amount of storm water run-off depends upon many factors such as intensity and duration of precipitation, characteristics of the tributary area and the time required for such flow to reach the drains. The drains will be located near the carriage way along either side of the roads. Taking the advantage of road camber, the rainfall run off from roads will flow towards the drains. Storm water from various plots will be connected to adjacent drain by a pipe through catch basins. Total 7 rainwater harvesting pits at selected locations, are provided which will catch the maximum run-off from the area. 1) Since the existing topography is congenial to surface disposal, a network of storm water pipe drains has been planned adjacent to roads. All building roof water will be brought down through rain water pipes. 2) Proposed storm water system consists of pipe drain, catch basins and seepage pits at regular intervals for rain water harvesting and ground water recharging. 3) For basement parking, the rainwater from ramps will be collected in the basement storm water storage tank. This water will be pumped out to the nearest external storm water drain. 4) The peak hourly rainfall of 35 mm/hr will be considered for designing the storm water drainage system. M/s Aura Buildwell Pvt. Ltd. 57

13 Rain water harvesting will be catered to and designed as per the guideline of CGWB. Peak hourly rainfall has been considered as 35 mm/hr. The recharge pit of 4 m diameter and 3 m depth will be constructed for recharging the water. Inside the recharge pit, a recharge bore will be constructed having adequate diameter and depth. The ground water level in the area is meters bgl. At the bottom of the recharge well, a filter media will be provided to avoid choking of the recharge bore. Design specifications of the rain water harvesting plan are as follows: Catchments/roofs would be accessible for regular cleaning. The roof will have smooth, hard and dense surface which is less likely to be damaged allowing release of material into the water. Roof painting will be avoided since most paints contain toxic substances and may peel off. All gutter ends will be fitted with a wire mesh screen and a first flush device will be installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags and paper pieces will get arrested by the mesh at the terrace outlet and to prevent contamination by ensuring that the runoff from the first minutes of rainfall is flushed off. No sewage or wastewater will be admitted into the system. No wastewater from areas likely to have oil, grease, or other pollutants will be connected to the system. The table below presents Rain Water runoff on various types of surfaces. Table 7: Rain Water runoff on various types of surfaces S. No. Type of Surface Catchment's Area sq. m Ha. Run off Coeff. [C] Intensit y of Rainfall (mm/hr) Discharge (Run Off) [Q=10CIA] m 3 /hr Total (m 3 /hr ) [Q] M/s Aura Buildwell Pvt. Ltd. 58

14 1. Building (Terrace) /Roof Top Area 15, X0.90X35X Paved Surface/ Road Surface Area 42, X0.7X35X , Natural Ground/Green s Area 37, X0.7X35X Grand Total ( 1+2+3) 2,463.3 KLD Calculations for storm water load Roof-top area = Ground Coverage = 15, m 2 Green Area = 37, m 2 Paved Area = Total Plot Area (Roof-top Area + Green Area) = 42, m 2 VOLUME OF STORM WATER DRAINAGE Considering 15 min (0.250 Hr) Retention Period Volume Required = 2,463.3 X Volume = VOLUME OF 1RAINWATER HARVESTING PIT Taking the effective dia and depth of a Recharge pit 4 m and 3 m respectively, Volume of a single Recharge pit = π r2h = = m3 TOTAL NO. OF RAINWATER HARVESTING PIT M/s Aura Buildwell Pvt. Ltd. 59

15 = /37.68 = Number = or 16 Number Total Number of Rainwater Harvesting Pit Required will be 16. Figure 3: Typical Rain Water Harvesting Pit Design M/s Aura Buildwell Pvt. Ltd. 60

16 VEHICLE PARKING FACILITIES Adequate provision will be made for car/vehicle parking at the project site. There shall also be adequate parking provisions for visitors so as not to disturb the traffic and allow smooth movement at the site. Table 7: Parking Details REQUIRED 1 E.C.S. / 80 SQM. F.A.R AREA = / 80 = SAY 1850 E.C.S PROPOSED PARKING UPPER BASEMENT PARKING AREA A = 30 SQ.M PER E.C.S LOWER BASEMENT PARKING AREA 30 SQ.M PER E.C.S) B 1850 E.C.S E.C.S. = / 30 = E.C.S SAY 562 E.C.S = / 30 = E.C.S SAY 562 E.C.S C D MECHANICAL CAR PARKS FOR 180 NOS. i.e TOTAL PARKING AT LOWER BASEMENT LEVEL STILT PARKING AREA = 30 SQ.M PER E.C.S OPEN PARKING AREA = 20 SQ.M PER E.C.S TOTAL PARKING ( A + B + C + D ) = 742 E.C.S = / 30 = E.C.S SAY 138 E.C.S = X 20 = E.C.S SAY 412 E.C.S 1854 ECS IN ORDER TO ACHIEVE THE REQUIRED NO. OF CAR PARKS, MECHANICAL CAR PARKING HAS BEEN PROPOSED AT THE LOWER BASEMENT LEVEL. M/s Aura Buildwell Pvt. Ltd. 61

17 POWER REQUIREMENT The power supply shall be supplied by State Electricity Board. The connected load will be 4090 KVA. Details of D.G Sets: There is provision of 4 no. of DG sets of (2 x x 600 KVA) capacity for power back up in the Group Housing Project. The DG sets will be equipped with acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion. SOLID WASTE GENERATION Solid waste would be generated both during the construction as well as during the operation phase. The solid waste expected to be generated during the construction phase will comprise of excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following steps are proposed to be followed for the management solid waste: Construction yards are proposed for storage of construction materials. The excavated material such as topsoil and stones will be stacked for reuse during later stages of construction Excavated top soil will be stored in temporary constructed soil bank and will be reused for landscaping of the group housing project. Remaining soil shall be utilized for refilling / road work / rising of site level at locations/ selling to outside agency for construction of roads etc. During the operation phase, waste will comprise domestic as well as e-waste and agricultural waste. The solid waste generated from the project shall be mainly domestic waste and estimated quantity of the waste shall be approx kg/day, containing 1613 Municipal solid waste. M/s Aura Buildwell Pvt. Ltd. 62

18 Arrangements will be made at the site in accordance to Municipal Solid Wastes (Management and Handling) Rules, 2000 and amended Rules, Table 8: Calculation of Solid Waste Generation S. No. Description of Population Municipal Solid waste 1. Dwelling Units Residents Occupancy Waste Generated (Kg per capita / day) Waste Generated (kg/day) 5,189 (@ 4.5 persons/dwell ing Club & Floating Population 3. Commercial Staff Total Area Waste Generated 4 Landscape Waste 0.2 kg/acre/day 1.87 sq.m /9.36 acres Total Waste Generation = kg/day Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, Central Public Health & Environment Engineering Organization, Ministry of Urban Development, (Government of India, May 2000)) Collection and Segregation of waste M/s Aura Buildwell Pvt. Ltd. 63

19 1. A door to door collection system will be provided for collection of domestic waste in colored bins from household units. 2. The local vendors will be hired to provide separate colored bins for dry recyclables and Bio-Degradable waste. 3. For commercial waste collection, adequate number of colored bins (Green and Blue & dark grey bins separate for Bio-degradable and Non Bio-degradable) are proposed to be provided at the strategic locations of the commercial area. 4. Litter bin will also be provided in open areas like parks etc. Treatment of waste Bio-Degradable wastes Bio-degradable waste will be subjected to composting by organic waste converter and the compost will be used as manure. STP sludge is proposed to be used for horticultural purposes as manure. Horticultural Waste is proposed to be composted and will be used for gardening purposes. Recyclable wastes Grass Recycling The cropped grass will be spread on the green area. It will act as manure after decomposition. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclables. Disposal Recyclable and non-recyclable wastes will be disposed through Govt. approved agency. Hence, the Municipal Solid Waste Management will be conducted as per the guidelines of Municipal Solid Wastes (Management and Handling) Rules, 2000 and amended Rules, A Solid waste management Scheme is depicted in the following figure for the residential project. M/s Aura Buildwell Pvt. Ltd. 64

20 Figure 4: Solid Waste Management Scheme (Construction Phase) Organic Waste Converter A waste converter is a machine used for the treatment and recycling of solid and liquid refuse material. A converter is a self-contained system capable of performing the following functions: pasteurization of organic waste; sterilization of pathogenic or biohazard waste; grinding and pulverization of refuse into unrecognizable output; trash compaction; dehydration M/s Aura Buildwell Pvt. Ltd. 65

21 Figure 5: Organic Waste Convertor Benefits of organic waste converter: 1. Large quantity of solid waste is converted to fertilizer in a very short period 2. This fertilizer can be sold as compost to farmers, or used for gardening 3. Machine requires less space and the efficiency is high 4. Manpower and maintenance is very less 5. This is one of the latest techniques of managing solid waste. GREEN AREA M/s Aura Buildwell Pvt. Ltd. 66

22 Total green area measures m 2 i.e % of the open area which will be area under tree plantation along the roads. Evergreen tall and ornamental trees like Saraca asoca, Delonix regia have been proposed to be planted inside the premises. Table 10: Landscape area details S.No Particulars Area in sq.m 1 Landscape area required (@50% of open area) 2 Landscape area proposed (@52.22% of open area) 3 Number of trees required (@ tree/100 sq.m of open area) 4 Number of trees required 1202 (MoEFCC norms) (@ 1 tree/80 sq.m of plot area) 5 Number of trees proposed 1210 Green Belt development Plan All the developments are associated with the pollution of one or more environmental component. Plants are the natural sink of that pollution. Plants help in abatement of the pollution and restore the degraded environment. Green belt lowers down the air pollution by providing a surface to settle down or by absorbing the pollutants, attenuate noise level and uses the waste water. For this project area of m 2 is proposed to be put under green cover. Green cover will comprise of: A peripheral green belt Avenue plantation Lawns/parks & grass cretes M/s Aura Buildwell Pvt. Ltd. 67

23 Planters Vertical plantation Plantation Plan Healthy and established sapling having 1m height shall be selected for planting in greenbelt to avoid mortality. Pit measurements of 1 m x 1 m x 1 m for big trees and 0.6 m x 0.6 m x 0.6 m for small trees and shrubs are proposed to be dug up at desired point in triangular pattern. The pit should be filled with earth, sand, silt and manure in pre-determined proportions. Saplings planted in these pits will be watered liberally. Trees in peripheral green belt will be grown at the distance of 5 m and plants along the road will be grown at distance of 1-3 m as per requirement. Three tier peripheral plantations will be developed composed of front and rear row of medium and dwarf trees and middle row of tall trees so as to form a curtain of foliage around project site. Avenue plantation will composed of trees and shrubs in ratio of 1:3, whereas lawns and parks will contain trees, shrubs, herbs, grass and climbers. Close plantation also result in tall trees with deeper roots and ultimately yield more bio-mass per unit area and more efficient absorption of pollutants. Plantation of trees in staging arrangement in multiple rows across the direction of the wind is recommended for better trapping and absorption of the pollutants. Selection of Plant Species for Green Belt Development Selection of plant species for the development depends on various factors such as climate, elevation and soil. The plants would exhibit the following desirable characteristics in order to be selected for plantation 1. Species should be fast growing and providing optimum penetrability with minimal maintenance. Perennial, evergreen & fast growing trees M/s Aura Buildwell Pvt. Ltd. 68

24 2. Species should be wind-firm and deep rooted 3. Indigenous and locally available species will be planted 4. Trees with high foliage density, leaves with larger leaf area and hairy on both the surfaces. Round, thick & spreading canopy is preferred for peripheral green belt and oblong canopy for road side plantation 5. Ability to withstand conditions like inundation and drought 6. Soil improving plants (Nitrogen fixing rapidly decomposable leaf litter) 7. Bird and insect attracting tree species 8. Tolerant to climatic conditions of the area and with less water requirement & after care will preferable be planted. Species tolerance to air pollutants like SO 2 and NO 2 should be preferred 9. Plantation trees with ornamental foliage & shrubs with fragrant flowers will enhance scenic beauty of the area. Attractive appearance with good flowering and fruit bearing 10. Plantation should be such that it maintains ecological & hydrological balance of the region. DETAILS OF CONSTRUCTION MATERIALS List of building materials being used at site: Coarse sand Fine sand Stone aggregate Stone for masonry work Cement Reinforcement steel Pipe scaffolding (cup lock system) Bricks M/s Aura Buildwell Pvt. Ltd. 69

25 CLC fly ash blocks P.V.C. conduit MDS, MCBs PVC overhead water tanks 2 1/2' thick red colour paver tiles PPR (ISI marked) PVC wastewater lines S.W. sewer line up to main sewer PVC rain water down take Stainless steel sink in kitchen Joinery hardware- ISI marked LIST OF MACHINERIES (i) Dumper (ii) Concrete mixer with hopper (iii) Excavator (iv) Concrete Batching Plant (v) Cranes (vi) Road roller (vii) Bulldozer (viii) RMC Plant (ix) Tower Cranes (x) Hoist (xi) Labor Lifts M/s Aura Buildwell Pvt. Ltd. 70

26 (xii) Pile Boring Machines (xiii) Concrete pressure pumps (xiv) Mobile transit mixer MATERIALS USED FOR CONSTRUCTION & THEIR U-VALUES Table 9: List of Construction Materials U-Values in W/m 2 o C R Value W -1 m 2 o C Type of Construction Walls: Brick: Plastered both side mm Solid, Unclastered mm Plastered both sides -228 mm Concrete block cavity, 250 mm ( ), outside rendered, inside plastered: Aerated Concrete blocks Hollow Concrete block 228 mm, single skin, outside rendered, inside plastered: Aerated Concrete blocks Roofs pitched: Tiles or slates on Boarding and felt with plaster ceiling Roofs Flat: Reinforced Concrete slab, 100 mm, screed mm, 3 layers bituminous felt Floors: Concrete on ground or hardcore fill Grano Terrazzo or the tile finish Wood block finish Windows: Exposure South, Sheltered: Single glazing Double glazing 6mm space M/s Aura Buildwell Pvt. Ltd. 71