An overall framework for understanding changes in megaprojects a Norwegian approach
|
|
- Evelyn Richards
- 6 years ago
- Views:
Transcription
1 Available online at Procedia - Social and Behavioral Sciences 00 (2012) Procedia Social and Behavioral Sciences 26th IPMA World Congress, Crete, Greece, 2012 An overall framework for understanding changes in megaprojects a Norwegian approach Youcef J-T. Zidane a, Anandasivakumar Ekambaram b *, Agnar Johansen c a NTNU, Trondheim, Norway b SINTEF, S.P. Andersens vei 5, NO-7465 Trondheim, Norway c SINTEF, S.P. Andersens vei 5, NO-7465 Trondheim, Norway Abstract Projects are also one of the means to make a change in this world; however, they themselves cannot escape from undergoing changes. During the last decades there has been intensive research about managing change in projects. Several researchers indicate that change should always be avoided and project team should be proactive in dealing with it. However, change is not always deleterious; some changes are beneficial and can also lead to new opportunities. The focus of this paper is on changes in megaprojects. These have a very significant impact on the society as a whole. These projects are known for their characteristics, such as large scope, high cost capital, long duration, with high complexity and uncertainty. Furthermore, they are open to dynamic environment. These characteristics are some of the major reasons why these projects are exposed to continuous change in their scope, cost, plan, etc. Many of these projects are famous for their inefficiency (cost overrun, time delays, and quality defect) in producing the intended output. They even fail occasionally to meet the desired outcome measured in terms of their effectiveness. Scholars suggest several reasons for the failure. Their suggestions point out the importance of looking at factors such as flexibility, complexity, uncertainty and stakeholder management. This paper considers all these factors and presents a project change model that illustrates the dynamic of changes with respect to effectiveness and efficiency. This paper provides a comprehensive literature study accompanied with empirical results obtained from Norwegian companies. The study related to this paper is based on interviews, case study, and surveys, and it presents a Norwegian approach to managing changes in megaprojects Published by Elsevier Ltd. Selection and/or peer-review under responsibility of IPMA "Keywords: Megaprojects; Project Change; Complexity; Uncertainty; Flexibility." * Corresponding author. Tel.: ; address: siva@sintef.no
2 2 Zidane,Ekambaram, Johansen/ 26 th IPMA World Congress, Greece (2012) 1. Introduction Generally speaking, what really happens with megaprojects is highly unsatisfactory. Several megaprojects end up as failed and abandoned and not meeting the anticipated outcomes / objectives (effectiveness). This is true despite the tremendous investments that are made (Bar-Yam, 2002). Likewise, failure to meet the desired efficiency (that is translated in terms of cost overrun and time delays) is also a common practice in the world of megaprojects (Flyvbjerg et al., 2003; Morris and Hough, 1987). Many scholars have attributed this kind of failures to changes at various stages of a project (Sun & Meng, 2009), which are originated from either external or internal pressures (Love et al, 2003). Changes in projects may be deleterious or beneficial, affecting the cost, the schedule and the project duration, either directly or indirectly. In this paper, we adopt the term project change to include all the changes that may occur during the whole life cycle of the projects. This paper contains five parts. They are: 1. Introduction 2. Research methods 3. Description of theory 4. Discussion and solutions 5. Reflections and Concluding remarks 2. Research Methods The paper is based primarily on literature study. Given the large volume of published work, there was a need to set a limit to the scope of the study. Hence, we chose to focus on the topic of causes and effects of changes at the project level and its relationship with other project management concepts. The work related to this paper is also influenced by a number of case studies and personal experience from consulting and research engagements. When it comes to the case studies, a research methodology based on the works of Yin (2009) regarding case studies as a qualitative paradigm has been used. One of the characteristics of case studies is that multiple sources of information are used, including archives, interviews and observations. In addition, qualitative surveys had been made. 3. Description of theory: Project Change and the Anatomy of Megaprojects There is no exact definition of a megaproject. Moreover, there is no definite understanding of what differentiates it from any other large or complex project. The only common agreement among practitioners and researchers is the concept of a large scale project with a price tag in excess of one billion dollar (Fiori et al. 2005), that frequently leads to cost overruns (Flyvbjerg et al. 2003). Megaprojects are invariably described by using superlatives (the prefix mega is already one of them). They are called the giants among the projects (Grün, 2004) or the new animal (Flyvbjerg et al., 2003). While such projects are large, they are not unparalleled in history. Megaprojects are only new as subjects of research. Grün (2004) puts the emphasis on the aspect of multi-organizational enterprises and characterizes these by (1) singularity (uniqueness), (2) complexity, (3) goal-orientation (technical, financial, time) and (4) the nature and number of project owners. The label megaproject is not used by all authors. Some refer to them as large-scale engineering projects (Hassan et al., 1999), and describe them by five attributes: (1) high capital cost, (2) long duration but program urgency (high pace), (3) technologically and logistically demanding, (4) requiring multidisciplinary inputs from many organizations, and (5) leading to a virtual enterprise for the execution of the project.
3 Zidane,Ekambaram, Johansen/ 26 th IPMA World Congress, Greece (2012) 3 Project Change: In this paper, project change is considered in broad sense than the change in scope or scope management. In engineering and construction projects, a change refers to an alteration to design, building work, project program or other project aspects caused by modifications to pre-existing conditions, assumptions or requirements. Construction, as a project-based practice, is particularly prone to a high degree of change for a variety of reasons (Sun M. & Meng X., 2009). Ibbs et al. (2001) indicated that any additions or deletions to project goals or scope are considered to be changes, whether they increase or decrease the project cost, schedule or quality. Arain and Pheng (2005) defined that project change is any modification to the contractual agreement provided by the contractors or owners. When changes occur in projects, then there will be certain consequences. The impact of project changes can either be significant or trivial as it may affect the operation and progress of the project. The Construction Industry Institute (CII, 1994) established a concept for project change management where change is considered as a modification to an agreement between project participants. The CII s report defined the project elements that are subject to change and that will affect the change process as project scope, project organization, work execution methods, control methods, contracts and risk allocation. Lazarus and Clifton (2001) define the change in a construction project as anything that affects: 1) The scope, requirements or brief for the project; 2) The capital cost, whole-life cost or value of the project; 3) The time required to design or construct the project; 4) The project team relationships and appointments; 5) Project-associated risk allocation or scope; 6) The form of procurement. Our description of change will be presented later in this paper. However, we could say that our description touches upon issues such as efficiency, effectiveness, complexity and flexibility. Efficiency: efficiency is a question of doing things right and producing project outputs in terms of the agreed scope, cost, time and quality. An important point should be clarified here; quality is not a constraint per se, but often a by-product of the other three factors (scope, time and cost), and one that generally suffers when the others are not properly managed. Changes have direct and indirect effects on efficiency; change effects lead to time extension, to indirect and direct cost increase and to a scope creep in some cases. Effectiveness: Effectiveness is more about ensuring / adding value for owners and users; owners and users are giving more concerns to the project effectiveness; in our case, let us say the planned and desired goals (long term effects) and objectives (short term effects) as outcomes from the project, which will affect the concerned stakeholders by those outcomes. So the measure of effectiveness is more related to the project stakeholders. Williams (2002) emphasizes the importance of managing both internal and external stakeholders. As we see it, stakeholders are one of the characteristics of the project. Stakeholders focus more on the project outcomes; they will try to influence the outcomes, modify them or shape them based on their needs. Stakeholders' influence tends to generate modifications within the project, and thus leads to deviation from the original plan. The effectiveness is one of the most important, potential sources of changes in projects. Project complexity Project complexity can be seen as high density of the varied elements of the project and the interdependencies of these elements (structural complexity) as defined by Baccarini (1996). Complex project is a project in which the project behaviors and outcomes are difficult to predict and difficult to explain. Complex projects, by their nature, comprise multiple interdependencies, and involving nonlinear relationships which themselves are dynamic (Howick et al, 2011). Project future behavior is determined by its initial conditions; a consequence of sensitivity to initial conditions is that if we start with only a finite amount of information about the project where it is always the case, then beyond a certain time the project will be no longer predictable. Large scale engineering projects are
4 4 Zidane,Ekambaram, Johansen/ 26 th IPMA World Congress, Greece (2012) complex systems. Changes in one part may have effects on other parts of the system, which can in turn trigger further changes in other parts and so on. Lorenz (1963) argued that minute changes can have major and unpredictable consequences in non-linear systems, which is known as the butterfly effect. A small change in initial conditions of a project can cause a chain of events leading to higher level of complexity. It should be noted that uncertainty is considered as a part of the project complexity in this paper. Project Flexibility In project management, project flexibility is an enigma. Projects need constancy and control to be executed efficiently (cost, time, and scope). However, lack of information in the planning phase to make present or future decisions create a need for flexibility options (Olsson 2006). Project flexibility includes preparations to manage both internal and contextual uncertainty, such as scope change management, iterative decision process, and adjustments related to uncertain funding in general. In product development, Verganti (1999) mentioned that the purpose of flexibility is to handle uncertainty during implementation and meeting project efficiency. Proposed Project Change Model The project change in this paper is the deviation from the intended change to the realized on (Figure 1). By intended change, we mean the conception of a project itself; a project is carried out in order to make a change, and we call this change as the intended change. Once we know what change we want, we implement that change. This is represented in the Figure 1 as deliberate change (Planning and execution). During this period, which is supposed to be the longest in the sequence, some emergent change will appear and interfere. These changes can be gradual or radical; anticipated or arises spontaneously; elective or required. The sources of these emergent changes are the context or the content of the project itself. Once the deliberated change ends, we will get the realized change, which is the final deliverables of the project. By comparing the realized change and intended change, we could find whether there is a difference between them. This difference can be seen as a result of emergent changes and the unrealized changes. Emergent Change Conception (Plan for a Change by Project) Intended Change Implementation (Planning - Execution) Deliberate Change Operation Realized Change Fig. 1. Project Change Formation Unrealized
5 Zidane,Ekambaram, Johansen/ 26 th IPMA World Congress, Greece (2012) 5 In order to understand the relationships between project change and all relevant aspects, a model is developed based on the works of Motawa (2005) and Sun & Meng (2009). The model is presented in Figure 2. Motawa (2005) defined project characteristics are factors or aspects that have an influence on the project and may initiate the causes of change. Causes of change are the direct causes of a specific change event when it occurs. And effects of change are the consequences of the changes on project parameters (e.g. cost, etc.). The model in Figure 2 indicates that causes and effects of changes in projects stem mostly from the project complexity including uncertainty (risk/ opportunity) along with project characteristics (highlighting stakeholders as a major source), that has been deduced by comparing the causes of changes to the elements of complexity and uncertainty. The effects of change have direct or indirect consequences on efficiency, and also they will have impact on project characteristics and increase project complexity. Fig. 2. Project change model Effectiveness is also to be taken into consideration. The P represents the percentage of effectiveness in the start of the project and P the percentage of the missing effectiveness (P+P = 100%). Let us assume that effectiveness of the project is (dealt with) 100% in the start. This means that the input to the project complexity and the causes of change will be 0. This further means that at the start of the project, effectiveness is perfectly dealt with so that it will have no impact on project change. The opposite of it will be a poor focus on effectiveness at the start (0% as a score) and the input to project complexity will be 100%. This means huge negative impact on the efficiency even the project may have to be cancelled. The sign plus minus (+/-) from the effects of change can, for example, mean the following: During the implementation of the project, some stakeholders come up with new requirements that affect the effectiveness of the project. The stakeholders did not consider the requirements in the early phase. It
6 6 Zidane,Ekambaram, Johansen/ 26 th IPMA World Congress, Greece (2012) means that the requirements will give a positive score for the effectiveness. But, it can probably give negative score (minus) to efficiency, since the new requirements can, for instance, lead to increase the cost and delay the project. Hence, lack of focus on effectiveness in the early project phases (conception and front-end phases) will likely to increase the complexity and uncertainty of the project. On the other hand, changes, for example in technology and politics can affect the intended outcome and thus effectiveness of the project. In this situation, it is less or no relevance to increase the efficiency. In other words, a positive score to efficiency in the execution phase may not ensure or improve effectiveness. Case Studies The two cases presented here are Norwegian megaprojects; the first case is from energy industry with around US$ 4 Billion as investment cost and five years from conception to delivery; this megaproject is in its end execution phase and it is supposed to end the first quarter of The second case is from construction project with less than a billion US dollar as investment cost and the duration of three years. This project was delivered by the fourth quarter of 2009 but still running in parallel with operation phase. During the data collection, we were making our research based on the defined change in this paper this means any deviation from the project aspects, comparing the intended change with the realized change during all the project phases. 3. Discussion The green line in figure 3 represents the level of change for the first case; the first project knew about a lot of changes already in the conception and early planning phases. Huge work has been done to score high effectiveness before even the start of the planning phase. During late planning and execution the project went very smoothly with fewer negative changes. The only noticed changes came from the weather (delay of 3 weeks) and bad cooperation between some subcontractors (a risk to delay the project some weeks). However, the project recorded positive changes which made the project to save one fourth US billion dollars from the original budget. These positive changes came from some changes in the raw materials and product used (cheaper and with a short product lifecycle and same quality). This project has a robust project organization and full control of the whole situation during the execution phase. Furthermore, this project had high flexibility in the start helped in scoring high level effectiveness. On the other hand, there was high control during late planning phase and still in the execution phases; this maintained the level of efficiency to more than the expected one. Opposite to the first case (red line in figure 3), the construction project did not meet the desired efficiency by a cost overrun of 20% comparing to the initial investment cost. In addition, there was delay in the delivery and there were quality defects. This project is still running even after its delivery. This case was having fewer changes in the conception and early planning phases. This is explained by the late involvement of the users in the project by the project owner. The users were asked about their requirements in the late planning phases. This caused a sequence of changes and scope modification by increasing the product quality. In other words, the effectiveness score of the project was very law in the start of the project, using the model in figure 3; the effectiveness input (output from effectiveness) to the causes of change and project complexity will be high, since the effectiveness score is low. This would lead to reduce the efficiency because attempts were made to increase the effectiveness to the desired level. The two cases can be compared with the project change model. From the discussed case studies, we come up with the management approach illustrated in figure 3. The green transparent colour represents zone 1 (including to unknown unknowns, most elements are known
7 Zidane,Ekambaram, Johansen/ 26 th IPMA World Congress, Greece (2012) 7 unknowns). It is the degree of flexibility the project should have during its lifecycle. At start, project management team should focus more about the effectiveness and make it 100% before the late planning phase. Being flexible in the conception and early planning phases can absorb all possible changes and increase the effectiveness. Fig. 3. Project Change and Project management approach The blue transparent colour which is zone 2 (most elements are known knowns) represents the level of control. The level of control grows up with the increase of collected information. There are several methods to control the project better. The late conception incorporates "locking" the effectiveness after making sure that all the intended objectives and goals are realistic. Involving the main concerned stakeholders during early planning, will increase the changes in the start and then decrease gradually. Having a robust project organization is of very high importance during execution, but still it is not enough; using all control management methods is also of high importance, for example, project control related to cost, time, quality, risk management and change management. This kind control is helpful during the execution phase. Zone 3 represents the unknown unknowns; the things happening in this zone are beyond the capacity of the project management team. The only way to deal with them is by improvisation or just accepting them. 4. Conclusion Changes can be seen as the only certainty in projects. The success of the megaprojects is determined by the ability of the project team to be proactive with managing the project change. Change refers here to all deviations from the plan, and the deviation could arise during the project life cycle. The project change model described in this paper aims to provide a comprehensive understanding of project change and its
8 8 Zidane,Ekambaram, Johansen/ 26 th IPMA World Congress, Greece (2012) relationship with other project management aspects. It presents a framework for academic researchers and practitioners to reflect upon the topic of managing changes in megaprojects, especially with respect to relationship between flexibility and control. References Arain FM, Pheng LS., (2005), The potential effects of variation orders on institutional building projects. Facilities 2005;23(11): Bar-Yam Y., (2002), Large Scale Engineering and Evolutionary Change: Useful Concepts for Implementation of FORCEnet, Newport Center for Information Age Warfares Studies. Construction Industry Institute (CII) (1994) Project Change Management, Special Pub Concise Oxford Dictionary (1990) 8ed., ed R.E., Alien Fiori, C. and Kovaka, M., (2005), Defining Megaprojects: Learning from Construction at the Edge of Experience 2005 American Society of Civil Engineers Construction Research Congress, April 5-7, San Diego, California. Flyvbjerg, B., Bruzelius, N., & Rothengatter, W., (2003). Megaprojects and risk: an anatomy of Ambition. Cambridge: Cambridge University Press. Grün O., (2004), Taming giant projects: Management of multi-organization enterprises. Berlin: Springer. Hassan S., McCaffer, R. and Thorpe, T., (1999), Emerging Clients Needs for Large Scale Engineering Projects. Engineering Construction and Architectural Management, 6, Howick S., Ackermann F., Eden C. Williams T., (2011), Delay and Disruption in Complex Project, Spring Science+Business Media, LLC. 2011, Complex systems in finance and economics p ISBN Ibbs, C.W., Wong, C.K., and Kwak, Y.H. (2001), Project change management system, Journal of Management in Engineering, ASCE, vo. 17, no.3, pp Lazarus, D, Clifton, R (2001) Managing project change: A best practice guide, CIRIA C556, Lond, UK Love PED, Smith J. (2003), Benchmarking, benchaction, and benchlearning:rework mitigation in projects. J Manage Eng 2003;19(4): Lorenz Edward N., (1963), "Deterministic Nonperiodic Flow". Journal of the Atmospheric Sciences 20 (2): ISSN Motawa I.A, Anumba C.J., EI-Hamalawi A., (2005), A systematic approach to modelling change processes in construction projects, Australian Jof Construction Economics and Building, 5(1), 23-31
9 Zidane,Ekambaram, Johansen/ 26 th IPMA World Congress, Greece (2012) 9 Morris, P. W. G. and Hough, G. H. (1987) The Anatomy of Major Projects: A Study of the Reality of Project Management. New York: Wiley. Olsson N.O.E., Magnussen O.M., (2006), Projects trapped in their freedom: Flexibility aspects of frontend quality assurance of major projects, Project Management Journal. Sun M., Meng X., (2009), Taxonomy for change causes and effects in construction projects, International Journal of Project Management 27 (2009) Verganti, R Planned flexibility: Linking anticipation and reaction in product development projects. Journal of Product Innovation Management 16:4, Williams T., (2002), Modelling Complex Projects. John Wiley & Sons Inc ISBN-10: ISBN-13: Yin R.K., (2009), Case Study Research: Design and Methods, Sage Publications Inc., Fourth Edition. ISBN-10: ISBN-13:
Available online at ScienceDirect. Procedia Computer Science 64 (2015 )
Available online at www.sciencedirect.com ScienceDirect Procedia Computer Science 64 (2015 ) 844 851 Conference on ENTERprise Information Systems / International Conference on Project MANagement / Conference
More informationReliance on and Reliability of the Engineer s Estimate in Heavy Civil Projects
Construction Economics and Building Vol. 17, No. 2 June 2017 VIEWPOINT Reliance on and Reliability of the Engineer s Estimate in Heavy Civil Projects George Okere School of Design and Construction, Washington
More informationMANAGING PROJECT CHANGE IN CONSTRUCTION: THE DEPENDENCY FRAMEWORK
MANAGING PROJECT CHANGE IN CONSTRUCTION: THE DEPENDENCY FRAMEWORK A. Fleming, S. Senaratne, M. Sexton, M. Sun*, G. Aouad Research Institute for the Built and Human Environment, School of Construction &
More informationScienceDirect. Uncertainty analysis 5 challenges with today's practice. Agnar Johansen a, Bettina Sandvin b, Olav Torp c, Andreas Økland d *,
Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Scienc es 119 ( 2014 ) 591 600 27 th IPMA World Congress Uncertainty analysis 5 challenges with today's practice
More informationImpacts of Engineering Work Quality on Project Success
Available online at www.sciencedirect.com Procedia - Social and Behavioral Sciences 74 ( 2013 ) 429 437 26 th IPMA World Congress, Crete, Greece, 2012 Impacts of Engineering Work Quality on Project Success
More informationKeywords: project change management, modelling processes, evaluation.
4 A Systematic Approach to Modelling Change Processes in Construction Projects Ibrahim A. Motawa (Department of Structural Engineering, Faculty of Engineering, Mansoura University, Egypt) Abstract Modelling
More informationWorking Paper Proceedings
Working Paper Proceedings 15 th Engineering Project Organization Conference with 5 th International Megaprojects Workshop Stanford Sierra Camp, California June 5-7, 2017 Robust Methodology to Learn Across
More informationAvailable online at ScienceDirect. Procedia Engineering 145 (2016 ) Identifying and measuring project complexity
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 145 (2016 ) 476 482 International Conference on Sustainable Design, Engineering and Construction Identifying and measuring project
More informationCRITICAL SUCCESS FACTORS FOR PROJECT PERFORMANCE: A STUDY FROM FRONT-END ASSESSMENTS OF LARGE PUBLIC PROJECTS IN NORWAY
CRITICAL SUCCESS FACTORS FOR PROJECT PERFORMANCE: A STUDY FROM FRONT-END ASSESSMENTS OF LARGE PUBLIC PROJECTS IN NORWAY OLAV TORP, KJELL AUSTENG AND WUBISHET JEKALE MENGESHA (NORWEGIAN UNIVERSITY OF SCIENCE
More informationGoverning Complex Infrastructure Developments: Learning From Successful Megaprojects
Governing Complex Infrastructure Developments: Learning From Successful Megaprojects Tim Brady a Andrew Davies b Abstract: Past literature suggests increasing complexity in projects may be a significant
More informationPROCEDURES FOR CHANGE MANAGEMENT IN THE REALIZATION PHASE OF CONSTRUCTION PROJECTS
PROCEDURES FOR CHANGE MANAGEMENT IN THE REALIZATION PHASE OF CONSTRUCTION PROJECTS Maja-Marija Nahod 1 and Mladen Radujković Construction Management Department, Faculty of Civil Engineering, University
More informationThe Impact of Variation Orders on Public Building Projects
International Journal of Construction Engineering and Management 016, 5(3): 86-91 DOI: 10.593/j.ijcem.0160503.03 The Impact of Variation Orders on Public Building Projects Andualem Endris Yadeta School
More informationAvailable online at ScienceDirect. Procedia Technology 16 (2014 )
Available online at www.sciencedirect.com ScienceDirect Procedia Technology 16 (2014 ) 1065 1071 CENTERIS 2014 - Conference on ENTERprise Information Systems / ProjMAN 2014 - International Conference on
More informationManaging Project Risks
The Project Reality As per The Standish Group report released in 1994 only 16% of all IT projects attempted successfully occur within the "triple constraint" of cost, time, and user requirements. While
More informationHighlights of CCPM - Critical Chain Project Management The TOC way of managing projects By Oded Cohen International Director Goldratt Schools
Highlights of CCPM - Critical Chain Project Management The TOC way of managing projects By Oded Cohen International Director Goldratt Schools ABSTRACT For many years the systemic approach to improve systems
More informationMethodologies to Implement ERP Systems: Are they PMBOK Compliant? Andres E. Diaz, P.Eng., MBA, PMP Hunter Business Group Inc.
Methodologies to Implement ERP Systems: Are they PMBOK Compliant? Andres E. Diaz, P.Eng., MBA, PMP Hunter Business Group Inc. www.hunter-inc.com Abstract Enterprise Resources Planning (ERP) systems are
More informationAvailable online at ScienceDirect. Procedia CIRP 28 (2015 ) rd CIRP Global Web Conference
Available online at www.sciencedirect.com ScienceDirect Procedia CIRP 28 (2015 ) 179 184 3rd CIRP Global Web Conference Quantifying risk mitigation strategies for manufacturing and service delivery J.
More informationProject Risk Management: Challenges and Good Practices in Active Project Ownership
Project Risk Management: Challenges and Good Practices in Active Project Ownership Hans Petter Krane 1 (PhD Candidate, Norwegian University of Science and Technology, Trondheim, Norway) Jan Alexander Langlo
More informationProject Management Maturity Model (PMMM) in educational organizations
Available online at www.sciencedirect.com Procedia Social and Behavioral Sciences 9 (2010) 1641 1645 WCLTA 2010 Project Management Maturity Model (PMMM) in educational organizations C. Demir a *, brahim
More informationA Project Management Approach to Improve on Time Delivery Performance in Manufacturing Industry
A Project Management Approach to Improve on Time Delivery Performance in Manufacturing Industry B. Shyam Sundar 1, Dr. D. Sivakumaran 2 1 Research scholar, Bharathiyar University, Coimbatore, India 2 Research
More informationAPPLICATION OF SUPPLY CHAIN PERFORMANCE MEASUREMENT IN SCOR MODEL AT BUILDING PROJECT
Contribution of Civil Engineering toward Building Sustainable City 60 APPLICATION OF SUPPLY CHAIN PERFORMANCE MEASUREMENT IN SCOR MODEL AT BUILDING PROJECT Mochamad Agung Wibowo, Moh Nur Sholeh Department
More informationHOW TO DEAL WITH PROJECT RISK MANAGEMENT EFFECTIVELY IN YOUR ORGANIZATION? Maxime LE BRAS ESC RENNES SCHOOL OF BUSINESS
HOW TO DEAL WITH PROJECT RISK MANAGEMENT EFFECTIVELY IN YOUR ORGANIZATION? Maxime LE BRAS ESC RENNES SCHOOL OF BUSINESS Abstract The management of risk inside a project should follow different steps to
More informationInternational Journal of Engineering Research and General Science Volume 4, Issue 4, July-August, 2016 ISSN
Causes of Variation Orders on Public Building Projects in Addis Ababa Andualem Endris Yadeta 1 1 School of Civil and Environmental Engineering, Addis Ababa Institute of Technology, Addis Ababa University,
More informationMANAGEMENT AUDITS OF PROJECTS AND PROGRAMMES HOW TO IMPROVE PROJECT MANAGEMENT AND PROGRAMME MANAGEMENT QUALITY
MANAGEMENT AUDITS OF PROJECTS AND PROGRAMMES HOW TO IMPROVE PROJECT MANAGEMENT AND PROGRAMME MANAGEMENT QUALITY Dr. Martina Huemann PROJEKTMANAGEMENT GROUP, Vienna University for Economics and Business
More informationHOW TO PRODUCE RELIABLE TIMETABLES FOR A MEGAPROJECT? Veikko Välilä Senior Advisor, Legal Lounge Ltd
HOW TO PRODUCE RELIABLE TIMETABLES FOR A MEGAPROJECT? Veikko Välilä Senior Advisor, Legal Lounge Ltd The 12th International Project Management Conference 12 & 13 February 2017 Tehran, Islamic Republic
More informationJames A. Rispoli, P.E., BCEE, NAC Professor of Practice, NCSU Center for Nuclear Energy Facilities & Structures Department of Civil, Construction and
1 James A. Rispoli, P.E., BCEE, NAC Professor of Practice, NCSU Center for Nuclear Energy Facilities & Structures Department of Civil, Construction and Environmental Engineering ***************************
More informationProcedia - Social and Behavioral Sciences 230 ( 2016 ) Ganna Lytvynchenko*
Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Sciences 230 ( 2016 ) 198 203 3rd International Conference on New Challenges in Management and Organization: Organization
More informationPROJECT MANAGEMENT AND INFORMATION TECHNOLOGY-A PARADIGM SHIFT
PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY-A PARADIGM SHIFT J.VENUGOPAL REDDY Assistant Professor K.B.R Engineering College Telangana ABSTRACT: This paper studies the business process known as project
More informationResearch Collection. Complexity of Megaprojects. Conference Paper. ETH Library. Author(s): Brockmann, Christian; Girmscheid, Gerhard
Research Collection Conference Paper Complexity of Megaprojects Author(s): Brockmann, Christian; Girmscheid, Gerhard Publication Date: 2007 Permanent Link: https://doi.org/10.3929/ethz-a-005997850 Rights
More informationAbstract. Introduction
Strategic Management of Variation Orders for Institutional Buildings: Leveraging on information technology * Faisal Manzoor Arain Research Scholar, Department of Building, School of Design and Environment,
More informationRELIABILITY AND STABILITY BUFFERING APPROACH IN CONCURRENT DESIGN AND CONSTRUCTION PROJECTS
RELIABILITY AND STABILITY BUFFERING APPROACH IN CONCURRENT DESIGN AND CONSTRUCTION PROJECTS SangHyun Lee, Feniosky Peña-Mora, and Moonseo Park ABSTRACT Current construction projects often need to reduce
More informationAvailable online at ScienceDirect. Procedia Engineering 145 (2016 )
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 145 (2016 ) 491 496 International Conference on Sustainable Design, Engineering and Construction Project complexity assessment
More informationScope Control Through Managing Changes in Construction Projects
Scope Control Through Managing Changes in Construction s Maja-Marija Nahod, M.Sc., M.Eng., Civ. Eng. University of Zagreb, Faculty of Civil Engineering e-mail: majan@grad.hr, DOI 10.5592/otmcj.2012.1.9
More informationThe Agile PMP Teaching an Old Dog New Tricks
The Agile PMP Teaching an Old Dog New Tricks Why are we here today? What is Project Management? When will the project be done? How much will it cost? Do we all agree on what done looks like? What are the
More informationLecture- 10. Project Scheduling. Dronacharya College of Engineering
Lecture- 10 Project Scheduling Dronacharya College of Engineering Scheduling and Planning The majority of projects are 'completed' late, if at all. A project schedule is required to ensure that required
More informationProject Management Auditing Guide
Project Management Auditing Guide Index Page 1.0 Objective 4 2.0 Risks 4 3.0 Safeguards and Controls 3.1.Project Characteristics 4 3.2.Quality in Project Management Process 4 3.3.Strategic Processes 5
More informationControlling Of Variation Orders in Highway Projects in Jordan
Journal of Engineering and Architecture December 15, Vol.,., pp. 95-1 ISSN: -98 (Print), -99 (Online) Copyright The Author(s). All Rights Reserved. Published by American Research Institute for Policy Development
More informationThe Successive Principle
Executive Briefing on The Successive Principle Russell D. Archibald August 15, 2016 What is the Successive Principle? A Proven Process to Reduce Uncertainty, Minimize Risk, Capitalize on Opportunities,
More informationEST Accuracy of FEL 2 Estimates in Process Plants
EST.2215 Accuracy of FEL 2 Estimates in Process Plants Melissa C. Matthews Abstract Estimators use a variety of practices to determine the cost of capital projects at the end of the select stage when only
More informationNCOVER. ROI Analysis for. Using NCover. NCover P.O. Box 9298 Greenville, SC T F
NCOVER ROI Analysis for Test Coverage Using NCover NCover P.O. Box 9298 Greenville, SC 29601 T 864.990.3717 F 864.341.8312 conversation@ncover.com www.ncover.com Table of Contents Executive Summary 2 Cost
More informationPMP Exam Preparation Course Project Time Management
Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,
More informationPROJECT EXECUTION PLANNING FOR COST AND SCHEDULE MANAGERS
PROJECT EXECUTION PLANNING FOR COST AND SCHEDULE MANAGERS ALLEN C. HAMILTON PMP CCE Project Management Associates LLC 3 Totten Way, Suite 110 Morris Plains, New Jersey 07950 USA Telephone: +1 973 984-1853
More informationWEAPONS OF A PERFECT PROJECT MANAGER
WEAPONS OF A PERFECT PROJECT MANAGER Prof. P. Maheswari, Ph.D Kasturba Gandhi Degree and PG College for Women West Marredpally, Secunderabad, Telangana State, India. Introduction As every child is special
More informationDEFINITIONS AND KEY MEASURES
PRODUCT AND SERVICE DEVELOPMENT DEFINITIONS AND KEY MEASURES The Framework for Process Improvement Experience shows that benchmarking s potential to drive dramatic improvement lies squarely in making out-of-the-box
More informationProject Management CSC 310 Spring 2018 Howard Rosenthal
Project Management CSC 310 Spring 2018 Howard Rosenthal 1 Notice This course is based on and includes material from the text: A User s Manual To the PMBOK Guide Authors: Cynthia Stackpole Snyder Publisher:
More informationLean beyond Software Development
Lean beyond Software Development Alina Hsu alina.hsu@alum.mit.edu 2 Why should we care about COTS software projects? Every organization uses COTS software High risk of very substantial cost/effort overruns
More informationAnalysis of Spiral Model in Software Projects for the Software Houses of Pakistan
International Journal of Scientific & Engineering Research, Volume 7, Issue 12, December-2016 Analysis of Spiral Model in Software Projects for the Software Houses of Pakistan 1486 Muhammad Saleem 1 saleemstriker@hotmail.com
More information// How Traditional Risk Reporting Has Let Us Down
// How Traditional Risk Reporting Has Let Us Down Dr. Dan Patterson, PMP CEO & President, Acumen November 2012 www.projectacumen.com Table of Contents Introduction... 3 What is Project Risk Analysis?...
More informationDarshan Institute of Engineering & Technology for Diploma Studies Rajkot Unit-1
Failure Rate Darshan Institute of Engineering & Technology for Diploma Studies Rajkot Unit-1 SOFTWARE (What is Software? Explain characteristics of Software. OR How the software product is differing than
More informationProject Cost Contingency Estimation in Ghana: An Integrated Approach
Science Journal of Civil Engineering and Architecture ISSN: 2276-6332 http://www.sjpub.org Author(s) 2012. CC Attribution 3.0 License. Research Article Published By Science Journal Publication International
More informationNOWIcob A tool for reducing the maintenance costs of offshore wind farms
Available online at www.sciencedirect.com ScienceDirect Energy Procedia 35 (2013 ) 177 186 DeepWind'2013, 24-25 January, Trondheim, Norway NOWIcob A tool for reducing the maintenance costs of offshore
More informationOverview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition
Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Topics for Discussion PMI Foundational Standards Harmonization of PMI s Foundational Standards Top 10 changes
More informationRisk Mitigation: Some Good News after the Cost / Schedule Risk Analysis Results
Risk Mitigation: Some Good News after the Cost / Schedule Risk Analysis Results David T. Hulett, Ph.D. Hulett & Associates, LLC ICEAA Professional Development and Training Workshop San Diego, CA June 9-12,
More informationBetter Cost Estimation Through Radically Improved Risk Identification. Laurie Wiggins CEO
Better Cost Estimation Through Radically Improved Risk Identification Laurie Wiggins CEO 1 Relationship between risk and cost Unknown or underestimated risks add an unknown amount of uncertainty to the
More informationISACA CRISC. Certified in Risk and Information Systems Control. Download Full Version :
ISACA CRISC Certified in Risk and Information Systems Control Download Full Version : http://killexams.com/pass4sure/exam-detail/crisc QUESTION: 391 Jane, the Director of Sales, contacts you and demands
More informationEvolutionary Differences Between CMM for Software and the CMMI
Evolutionary Differences Between CMM for Software and the CMMI Welcome WelKom Huan Yín Bienvenue Bienvenido Wilkommen????S???S??? Bienvenuto Tervetuloa Välkommen Witamy - 2 Adapting an An Integrated Approach
More informationPLANNING BEST PRACTICES
PLANNING BEST PRACTICES Planning Basics + Planning Best Practices John H. Cable, R.A., PMP Copyright 2017, All rights reserved Isn t this a great day to study Project Management! Webster Plan A method
More informationAgile Projects 7. Agile Project Management 21
Contents Contents 1 2 3 4 Agile Projects 7 Introduction 8 About the Book 9 The Problems 10 The Agile Manifesto 12 Agile Approach 14 The Benefits 16 Project Components 18 Summary 20 Agile Project Management
More informationProject Management CTC-ITC 310 Fall 2018 Howard Rosenthal
Project Management CTC-ITC 310 Fall 2018 Howard Rosenthal Notice This course is based on and includes material from the text: A User s Manual To the PMBOK Guide Authors: Cynthia Stackpole Snyder Publisher:
More informationStakeholder Management Plan <Project Name>
The following template is provided for use with the Stakeholder Management Plan deliverable. The blue text provides guidance to the author, and it should be deleted before publishing the document. This
More information1 The system of final modification on order refers to postponed manufacturing (Van Hoek, 1998). In a
Action Research using Case Study Methodology for Implementation of Process Improvement Initiatives in Food SMEs Anita Kumar, Seamus O Reilly (S.OReilly@ucc.ie) & Fred Adam, University College Cork, Ireland
More informationInternational Journal of Advanced Research in Engineering Vol 2(3) Jul-Sep 2016
An Overview of Procurement Methods and Techniques for Effective Delivery of Construction Projects Abstract-Procurement processes in the construction industry are many and the choice of a suitable one depends
More informationSoftware Engineering II - Exercise
Software Engineering II - Exercise April 29 th 2009 Software Project Management Plan Bernd Bruegge Helmut Naughton Applied Software Engineering Technische Universitaet Muenchen http://wwwbrugge.in.tum.de
More informationIn this Part 6 we will cover:
August 2007 Ten Steps to Comprehensive Project Portfolio Management Part 6 Tips on Steps 8 & 9 By R. Max Wideman This series of papers has been developed from our work in upgrading TenStep's PortfolioStep.
More informationT Software Testing and Quality Assurance Test Planning
T-76.5613 Software Testing and Quality Assurance 10.10.2007 Test Planning Juha Itkonen Outline Test planning, purpose and usage of a test plan Topics of test planning Exercise References: IEEE Std 829-1998,
More informationIdentification Selection Definition Execution. Schedule.
SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification
More informationPROJECT SCHEDULING & CONTROL
PROJECT SCHEDULING & CONTROL Project Project Management PM Knowledge Areas Time Management 1 Project What is a PROJECT? Definition used by PMI: A temporary endeavor undertaken to create a unique product,
More informationCritical Factors Affecting the Implementation of Total Quality Management in the Construction Industry in U.A.E
Critical Factors Affecting the Implementation of Total Quality Management in the Construction Industry in U.A.E Firas Mohamad Al-Sabek Abstract The purpose of the paper is to examine the most critical
More informationScenario analysis on China s alternative fuel vehicle industry risk identification
Available online www.jocpr.com Journal of Chemical and Pharmaceutical Research, 2014, 6(5):2019-2023 Research Article ISSN : 0975-7384 CODEN(USA) : JCPRC5 Scenario analysis on China s alternative fuel
More informationDevelopment of an experimental waste framework based on BIM/lean concept in construction design
Development of an experimental waste framework based on BIM/lean concept in construction design Mollasalehi, S, Fleming, AJ, Talebi, A and Underwood, J Title Authors Type URL Development of an experimental
More informationin the Product Development Process
3D interface with PLM Solutions is transforming methods in the Product Development Process Contents Market Scenario - 3 Trade Dynamics - 4 PLM driving faster product innovation - 6 PLM interfacing with
More informationCO 2 capture processes: Novel approach to benchmarking and evaluation of improvement potentials
Available online at www.sciencedirect.com Energy Procedia 37 (2013 ) 2536 2543 GHGT-11 CO 2 capture processes: Novel approach to benchmarking and evaluation of improvement potentials Rahul Anantharaman
More informationb u i l d i n g a b r o a d
b u i l d i n g a b r o a d procurement of construction and reconstruction projects in the international context FACTORS CAUSING CONSTRUCTION COMPANY FAILURE Serkan Kivrak, Anadolu University email: serkankivrak@anadolu.edu.tr
More informationPROJECT EFFECTIVENESS IMPROVEMENT: A CASE STUDY IN PT.X
JOURNAL OF BUSINESS AND MANAGEMENT Vol. 4, No.5, 2015: 587-593 PROJECT EFFECTIVENESS IMPROVEMENT: A CASE STUDY IN PT.X Zulia Manalu and Yuliani Dwi Lestari School of Business and Management Institute Technology
More informationHIA Report Guide December 2010 Prepared by Human Impact Partners for Health Impact Project HIA grantees
HIA Report Guide December 2010 Prepared by Human Impact Partners for Health Impact Project HIA grantees The following information is meant to provide a basic structure for your HIA report including the
More informationProject vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,
Project vs Operation PROJECTS OPERATIONS Temporary Ongoing Unique Repetitive Closes after attaining the objectives Objective is to sustain business Prototyping the new car model Assembly line production
More informationThe Rational and Behavioral View in Project Management Yao YAO
2016 3 rd International Conference on Social Science (ICSS 2016) ISBN: 978-1-60595-410-3 The Rational and Behavioral View in Project Management Yao YAO 1 School of Project Management, Faculty of Engineering
More informationINTEGRATION of PROJECT MANAGEMENT and SYSTEMS ENGINEERING
Copyright 2018 by Yves Theriault. Permission granted to INCOSE to publish and use. INTEGRATION of PROJECT MANAGEMENT and SYSTEMS ENGINEERING San Diego INCOSE Mini-Conference December 1, 2018 John Wood,
More informationAssessment of Extension of Time Claims in Hydropower Projects of Pakistan
International Journal of Engineering and Advanced Technology (IJEAT) Assessment of Extension of Time Claims in Hydropower Projects of Pakistan Hashim Hanif, Yasar Saleem, Zuhaib Aslam Shahid, Abdullah
More informationNonlinear Dynamic Analysis a Step Advance
Nonlinear Dynamic Analysis a Step Advance in Assessing the Vulnerability of Buildings Editor s note: The strength of an earthquake catastrophe model in producing to Earthquake reliable loss estimates lies
More informationENGLISH SUMMARY. Introduction. Development process
ENGLISH SUMMARY This summary is similar to the Dutch summary which describes the translates of the research Integrated construction sector; comparative studies on the use of integrated contracts in the
More informationAdopting iterative development: the perceived business value
Adopting iterative development: the perceived business value Caryna Pinheiro, Frank Maurer, Jonathan Sillito University of Calgary Calgary, Alberta, Canada {capinhei, frank.maurer, sillito}@ucalgary.ca
More informationValidation of NORM (Needs Oriented Framework for Producing Requirements Decision Material) Framework in Industry
Master Thesis Software Engineering Thesis no: MSE-2012:102 09 2012 Validation of NORM (Needs Oriented Framework for Producing Requirements Decision Material) Framework in Industry Salman Nazir Rizwan Yousaf
More informationIndustrial Engineering Prof. Inderdeep Singh Department of Mechanical and Industrial Engineering Indian Institute of Technology, Roorkee
Industrial Engineering Prof. Inderdeep Singh Department of Mechanical and Industrial Engineering Indian Institute of Technology, Roorkee Module - 04 Lecture - 04 Sales Forecasting I A very warm welcome
More informationPROGRAM RISK ID. Radical Risk Identification for Meeting Program Objectives. Laurie Wiggins CEO Sysenex Inc.
PROGRAM RISK ID Radical Risk Identification for Meeting Program Objectives Laurie Wiggins CEO Sysenex Inc. 1 What is the Problem? Program Overruns (and performance problems too) In March 2014, the GAO
More informationTHE EFFECT OF DESIGN KNOWLEDGE TOWARDS THE PERFORMANCE OF REFURBISHMENT PROJECTS IN MALAYSIA
034 THE EFFECT OF DESIGN KNOWLEDGE TOWARDS THE PERFORMANCE OF REFURBISHMENT PROJECTS IN MALAYSIA Azlan Shah Ali CEBUS, Faculty of Built Environment, University of Malaya 50603 Kuala Lumpur Email: asafab@um.edu.my
More informationTHE TRUE VALUE OF PROJECT RISK ANALYSIS
THE TRUE VALUE OF PROJECT RISK ANALYSIS Dr. Dan Patterson, PMP Chief Design Officer, PLANNING & SCHEDULING Introduction Much has been written in recent years about the benefits of conducting a project
More informationA Parametric Approach to Project Cost Risk Analysis
A Parametric Approach to Project Cost Risk Analysis By Evin Stump Senior Systems Engineer Galorath Incorporated Preface Risk arises when the assignment of the probability of an event is statistically possible
More informationChapter 2: Project Methodologies and Processes
Chapter 2: Project Methodologies and Processes True/False 1. A methodology provides a systematic way to plan, manage, and execute projects. Ref: INTRODUCTION 2. The Project Management Body of Knowledge
More informationAdvantages and Disadvantages of. Independent Tests. Advantages. Disadvantages
8.0 Test Management Outline 8.1 Test organisation 8.2 Test planning and estimation 8.3 Test program monitoring and control 8.4 Configuration management 8.5 Risk and testing 8.6 Summary Independent Testing
More informationPreliminary Model Development of Client Orientation in Civil Engineering Businesses
Vol. 2, Issue. 5, Sept.-Oct. 2012 pp-2981-2985 ISSN: 2249-6645 Preliminary Model Development of Client Orientation in Civil Engineering Businesses Christopher Nigel Preece, Hooman Abadi Department of Civil
More informationScienceDirect. Web-based project management influence on project portfolio managers technical competencies
Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Scienc es 119 ( 2014 ) 387 396 27 th IPMA World Congress Web-based project management influence on project portfolio
More informationProject Execution Plan For
Project Execution Plan For [Insert Name Here] Project Document Revision History Revision Date Project Manager Project Sponsor Page 1 of 24 About This Project Execution Plan Template: This template is intended
More informationDefining Program Types
Defining Program Types Typologies are based on the inherent characteristics of the project or program (not the industry they are based in). Significant work has been done defining the different types of
More informationProcedia - Social and Behavioral Sciences 147 ( 2014 ) ICININFO
Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Sciences 147 ( 2014 ) 64 69 ICININFO The Benefit and Cost Factors of CMDB Implementations: An Investigation of three
More informationThe Impact of Design Rework on Construction Project Performance
The Impact of Design Rework on Construction Project Performance Ying Li Graduate Student University of Kentucky, College of Engineering Department of Civil Engineering, 116 Raymond Building, Lexington,
More informationDisciplined Agility for the Development of Softwareintensive. Dr. Peter Hantos, I.S.T.J. Consultant
Disciplined Agility for the Development of Softwareintensive Systems Dr. Peter Hantos, I.S.T.J. Consultant 2003 Peter Hantos SLIDE 1 Yet Another Manifesto (1) I believe in Planning (2) I believe in Architecture
More informationAchieving Excellence in Capital Projects Delivery Focusing on Four Pillars. Introdution
Page1 Achieving Excellence in Capital Projects Delivery Focusing on Four Pillars Introdution October 1, 2015 Prepared by: George E. Baram P.Eng., M.Sc., PMP, CCE, Fellow AACE International Baram and Associates
More informationProgramme & Project Planning and Execution
Portfolio, LEADING THE WAY IN PROJECTS Programme & Project Planning and Execution Caravel Group - Project Management with a total focus on value THE SPECIALIST FOR LARGE COMPLEX MULTI-DISCIPLINED PROJECTS
More informationSPECIFICATION RISK ANALYSIS: INTRODUCING A RISK MANAGEMENT METHOD FOR PRODUCT ARCHITECTURES
INTERNATIONAL DESIGN CONFERENCE - DESIGN 2008 Dubrovnik - Croatia, May 19-22, 2008. SPECIFICATION RISK ANALYSIS: INTRODUCING A RISK MANAGEMENT METHOD FOR PRODUCT ARCHITECTURES C. Wagner, M. Graebsch, W.
More information