ABC Ramps Transportation Options Program Plan Scope of Work Kick off meeting 10/5/2016

Size: px
Start display at page:

Download "ABC Ramps Transportation Options Program Plan Scope of Work Kick off meeting 10/5/2016"

Transcription

1 ABC Ramps Transportation Options Program Plan Scope of Work Kick off meeting 10/5/2016 Proposal Summary The ABC Ramps were completed in 1992 as part of the I-394 construction using Federal Aid Interstate funds. The purpose of the ramps is to have programs that support reducing congestion and improving air quality by reducing SOV trips from the I-394 corridor. At the time of inception the main program was to provide discount carpool parking. At time the ramps were built, the ramp goals were aligned with the city of Minneapolis parking system goals and the I- 394 Corridor Management Plan. Since that time, however, the transportation modes, technologies and plans surrounding the ramps have changed, as well as the travel behaviors of the users. As the ramps reach the midpoint of the 50-year design life, this study will examine the programs, policies and goals developed for the ramps to ensure they continue to address current transportation challenges and align with regional stakeholder s goals and emerging trends, behaviors and technology. Updating the multi-modal programs: Participation in the discount carpool parking program has declined substantially in the last 10 years. The current program is over 25 years old. Multi-modal programs should be updated and expanded to align with today s travel behaviors, multi-modal transportation options and technology. Serving other corridors: Other corridors coming in to downtown and regional goals may have changed, leading to opportunities for the ABC ramp programs to benefit areas beyond the I-394 corridor. Furthermore, new modes and travel options (including LRT, BRT and advances in telecommuting options) have come on-line since the ramps were constructed, leading some of the existing multi-modal programs to no longer be as effective as they were 25 years ago. Improving parking space utilization: Parking lots are being developed and parking ramps are being torn down near the ABC Ramps. For the first time in 25 years, both Ramps B and C are filling almost daily. If drive-alone trips are reduced there is a chance to accommodate the demand for parking spaces without having to build more parking facilities. Using emerging technology: Technology is changing rapidly and finally allowing for easy management of more flexible transportation options with sustainable incentives to reduce drive-alone trips. Capitalizing on new travel behaviors: Travel behavior is embracing the shared economy - people are sharing cars, bikes and sourcing rides with technology facilitating these connections. People no longer want to be tied to one mode. They want the flexibility to use a variety of modes.

2 Task 1: Project Management Description: Provide administration and project management resources. Arrange technical advisory committee meetings, take and distribute meeting minutes. Coordinate TAP approval of detailed workplans before start of each task, track status of tasks, and facilitate regular communication between Technical Liaison, interested TAP members and task leaders. This task will be carried out by State and Local Policy Program (Douma) Anticipated Start Date: September 1, 2016 Scheduled date to submit draft deliverable: April 30, 2018 Scheduled date for final task approval: June 30, 2018 Duration: 22 months including the TAP review and comment period Deliverable: Quarterly progress reports, meeting minutes, agendas, meeting schedules, project plan and timeline, TAP member list Task 2: History of ABC ramps Description: Assemble documents and hold interviews and focus groups with local stakeholders that were involved with the planning of the ABC ramps and implementation of their related programs. Key areas to review and include in the report include (where available): Policy context that lead to construction of the ramps, including planning and funding of I-394 and other structures (such as skyways) constructed with ramps; Travel trends before and after construction, including mode split, with particular attention to carpooling; Stakeholder review, including organizational relationships (role of City of Minneapolis, Downtown Minneapolis Transportation Management Organization, MetroTransit (and predecessor organizations); the Metropolitan Council, MnDOT, Federal Highway Administration, and private organizations, including Minnesota Timberwolves and Minnesota Twins); Annual revenues and occupancy of each ramp; Operational highlights, including safety and security issues, technology changes, etc. This task will be led by Adeel Lari of the State and Local Policy Program Anticipated Start Date: September 1, 2016 Scheduled date to submit draft deliverable: March 31, 2017 Scheduled date for final task approval: May 31, 2017 Duration: 9 months including the TAP review and comment period Deliverable: summary report reviewing key moments in the history of the ABC ramps Task 3: Corridor Evaluation, current, programed and planned Description: Review and evaluate all corridors leading to the ABC ramps, including, but not limited to the I-394 corridor. Draw on existing plans, studies, reports, research and stakeholders to identify dominant modes (focus on those dominated by single occupancy vehicles, noting MnPASS vehicle occupancy counts in particular), challenges to increasing alternative mode shares, as well as other options for reducing congestion, and construction projects that may positively or negatively affect access to the ramps. MnDOT s INRIX data set, which uses GPS and Smart Phone data, and is maintained by SRF Consulting, may be utilized to identify travel patterns. This task will be led by Adeel Lari of the State and Local Policy Program. Anticipated Start Date: September 1, 2016 Scheduled date to submit draft deliverable: December 31, 2016 Scheduled date for final task approval: February 28, 2017 Duration: 6 months including the TAP review and comment period Deliverable: Report on corridors leading into downtown, discussing and rating (minor, major, etc.) potential impacts they may have on ABC ramps.

3 Task 4: Customer and Commuter Demographics Description: Analyze demographics, transportation habits and motivators of current and potential ABC Ramps customers: Age, income, household size and ages, location of residence, distance to work, employer, transportation behavior, desired transportation behavior and other factors. Draw on existing research, including Metropolitan Council Travel Behavior Inventory (TBI), Flexible Parking Pricing study, and other data, such as the Transit Onboard study, zip code data from credit card transactions at ABC ramps, and demographic and travel behavior data from the INRIX data set, where feasible.. Conduct additional research and public engagement activities to fill in gaps. If feasible, include an evaluation of the customer experience and customer satisfaction. This task will be led by Humphrey School Professor Yingling Fan Anticipated Start Date: September 1, 2016 Scheduled date to submit draft deliverable: January 31, 2017 Scheduled date for final task approval: March 31, 2017 Duration: 7 months including the TAP review and comment period Deliverable: report summarizing transportation needs of ABC ramp customers and the general public Task 5: Employer and business evaluation Description: Using documents on file with the Downtown Minneapolis Transportation Management Organization and similar documents, as well as targeted employer interviews, assess currency and commitment to implementing and maintaining Transportation Demand Management programs of employers with the potential of using the ABC Ramps (about a halfmile radius). This task will be led by Frank Douma of the State and Local Policy Program, possibly with assistance from Humphrey School Professor Jason Cao. Anticipated Start Date: September 1, 2016 Scheduled date to submit draft deliverable: March 31, 2017 Scheduled date for final task approval: May 31, 2017 Duration: 9 months including the TAP review and comment period Deliverable: Summary report on local employer commitment to TDM efforts. Report will include review of demographic data (and quality of it) discussion of TDM measures employed (transit passes, parking programs, biking facilities, etc.), and relationship of these measures to ABC ramp opportunities. Task 6: Regional stakeholder goals Description: Investigate key stakeholder s goals and regional goals to determine how they align with ABC Ramps transportation options goals. Key stakeholders may include neighborhood, Downtown Council, city of Minneapolis, Metropolitan Council, Move Minneapolis, Hennepin County, and MnDOT MinnesotaGO. This task will be led by Frank Douma of the State and Local Policy Program Anticipated Start Date: January 1, 2017 Scheduled date to submit draft deliverable: March 31, 2017 Scheduled date for final task approval: May 31, 2017 Duration: 5 months including the TAP review and comment period Deliverable: summary report reviewing goals of key stakeholders, assessing the extent they align with those of the ABC ramps and recommending steps that could help bring goals of the ABC ramps into better alignment.

4 Task 7: ABC Ramp Management, Oversight and Resources Description: Provide administrative support to outside consultant to review the governing documents and practices of the ABC Ramps, including those related to management, maintenance and operations, service areas and transit operations, to assess alignment with current circumstances and future goals of the ABC ramps and most efficient and effective best practices.. Administrative support (including meeting coordination, minute taking, etc.) to be led by State and Local Policy Program. Consultant to contract directly with MnDOT. Anticipated Start Date: September 1, 2016 Scheduled date to submit draft deliverable: January 31, 2017 Scheduled date for final task approval: March 31, 2017 Duration: 7 months including the TAP review and comment period Deliverable: University deliverable to be limited to meeting schedules, agendas, minutes and related administrative support. Task 8A: Policy, ordinance, statute and guidance review Description: Concurrent with Task 7, review the federal, state and local policies, ordinances, statues, obligations and guidance, including CMAQ, that affect ABC Ramps transportation options. Recommend changes to support the programs. This task will be led by Frank Douma of the State and Local Policy Program. Anticipated Start Date: September 1, 2016 Scheduled date to submit draft deliverable: January 31, 2017 Scheduled date for final task approval: March 31, 2017 Duration: 7 months including the TAP review and comment period Deliverable: Summary report of current legal environment in which ABC ramps must operate, and recommending changes as necessary to allow Ramps to best achieve new goals. Task 8B: Updated Policy, ordinance, statute and guidance review Description: Pursuant to strategies identified in task 11, add any additional analysis, as needed of federal, state and local policies, ordinances, statues and guidance, that may affect the new strategies. This task will be led by Frank Douma of the State and Local Policy Program Anticipated Start Date: May 1, 2017 Scheduled date to submit draft deliverable: June 30, 2017 Scheduled date for final task approval: August 31, 2017 Duration: 4 months including the TAP review and comment period Deliverable: Updated summary report of current legal environment in which ABC ramps must operate, and recommending changes as necessary to allow Ramps to best achieve new goals. Task 9: Literature Review / Program Scan Description: Conduct a domestic and international literature review and program scan of transportation options programs and services and transit oriented development practices that could be integrated with parking programs and facilities. This review will have 3 sections: (1) Best practices from around the country and world, as applicable; (2) a local section that covers current and planned transit routes, including park and ride facilities, that serve the ABC Ramps area, as well as selected studies and best practices from other Transportation Management Organizations; and (3) comparison of these programs with current ABC Ramps products and programs including SOV daily and contract parking, carpool programs, transit service, bicycle programs, EV charging stations, parking and transportation for large events and others. This task will also include an analysis of various parking pricing strategies and parking availability and how they affect travel behavior. For example, what impact does free or low cost

5 first hour parking pricing have on on-street meter availability and people circulating looking for an on-street spot. What affect does high cost of monthly contract or all-day parking rates have on shifting modes to transit. What does limiting the availability of monthly contracts have on mode shift to transit. This task will be led by Humphrey School Professor Jason Cao Anticipated Start Date: September 1, 2016 Scheduled date to submit draft deliverable: February 28, 2017 Scheduled date for final task approval: April 30, 2017 Duration: 8 months including the TAP review and comment period Deliverable: Summary report documenting current ABC Ramp programs, and comparing to other best practices. Task 10: Long Range Transportation Trends Description: This task will identify the potential long range transportation scenarios over the next 25 years, and the nature of their impact on the ABC Ramps goals. This task will develop scenarios that anticipate the potential impact of transportation innovations including autonomous vehicles; car sharing, ride-sharing and other shared economy initiatives, teleworking, electrification of vehicles, changes to transportation finance mechanisms, and other trends as identified by the researchers and TAP. This task will draw from existing data including the background information gathered for the Minnesota State Highway Transportation Plan, Minnesota Go!, and the Transportation Futures Study. Specific downtown Minneapolis / ABC Ramps information will also be included. (e.g. This task to be led by Frank Douma, Adeel Lari and Barbara Rohde of the State and Local Policy Program. Anticipated Start Date: September 1, 2016 Scheduled date to submit draft deliverable: April 30, 2017 Scheduled date for final task approval: June 30, 2017 Duration: 10 months including the TAP review and comment period Deliverable: Summary report discussing the potential long range transportation scenarios over the next 25 years, and the nature of their impact on the ABC Ramps parking and TDM goals Task 11: Program Evaluation Description: Provide support for a task that will build upon the previous tasks and evaluate and recommend new programs for ABC Ramps to reduce congestion and improve air quality. This task will be led by an outside consultant directly contracted with MnDOT, but supported by the State and Local Policy Program. Anticipated Start Date: January 1, 2017 Scheduled date to submit draft deliverable: June 30, 2017 Scheduled date for final task approval: August 31, 2017 Duration: 8 months including the TAP review and comment period Deliverable: University deliverable to be limited to administrative efforts including meeting schedules, agendas, and minutes, as well as providing supporting reports and other materials to outside consultant who will prepare a recommended strategy and specific initiatives in support of that strategy, for continued use of the ABC Ramps to reduce congestion and improve air quality.

6 Task 12: Outreach evaluation Description: Provide administrative support for a task that will evaluate marketing, communications and outreach best practices that is currently being done to educate and encourage the public to use various transportation options, and compare these efforts to best practices being done in other communities.. This task will be led by an outside consultant directly contracted with MnDOT, but supported by the State and Local Policy Program. Anticipated Start Date: January 1, 2017 Scheduled date to submit draft deliverable: June 30, 2017 Scheduled date for final task approval: August 31, 2017 Duration: 8 months including the TAP review and comment period Deliverable: University deliverable to be limited to meeting schedules, agendas, minutes and related administrative support. Task 13: Implementation Strategies and Recommendations Description: Based upon the findings from the previous tasks, make recommendations for updated programs and outreach for the next and a process for implementing these changes. This task will be led by an outside consultant directly contracted with MnDOT, but supported by the State and Local Policy Program. Anticipated Start Date: April 1, 2017 Scheduled date to submit draft deliverable: July 31, 2017 Scheduled date for final task approval: September 30, 2017 Duration: 6 months including the TAP review and comment period Deliverable: Recommendations for how to implement new programs. although University deliverable will be limited to meeting schedules, agendas, minutes and related administrative support. Task 14: Summary Report Description: This task will result in the creation of a short report summarizing the key findings, recommended changes and implementation strategies in a summary document that can be widely distributed to a range of audiences. This document will be distributed at a one-day symposium where findings and best practices will be presented to a wide audience of stakeholders from the Twin Cities. This task will be led by the State and Local Policy Program, possibly with the aid of an outside writer. Anticipated Start Date: August 1, 2017 Scheduled date to submit draft deliverable: October 31, 2017 Scheduled date for final task approval: December 31, 2017 Duration: 5 months including the TAP review and comment period Deliverable: Summary report document Task 15: Compile Report, Technical Advisory Panel Review and Revisions Description: A draft report will be prepared, following MnDOT publication guidelines, to document project activities, findings and recommendations. This report will need to be reviewed by the Technical Advisory Panel (TAP), updated by the Principal Investigator to incorporate technical comments, and then approved by Technical Liaison before this task is considered complete. TAP members may be consulted for clarification or discussion of comments. This task will be led by the State and Local Policy Program Anticipated Start Date: September 1, 2017 Scheduled Date to Submit Draft Report: February 28, 2018 Schedule Date for Final Report Approval: April 30, 2018 Duration: 8 months including TAP review, discussion, and PI revisions Deliverables: A Draft Report and Final Report Approved for Publication

7 Task 16: Editorial Review and Publication of Final Report Description: During this task the Approved Report will be processed by MnDOT s Contract Editors. The editors will review the document to ensure it meets the publication standard. This task must be completed within the Contract time because the editors will provide editorial comments and request information from the Principal Investigator. Scheduled Start Date: April 30, 2018 Scheduled End Date: June 30, 2018 Duration: 2 months Deliverables: Final Published Report

8 Task 2: History of ABC Ramps Task Lead: Adeel Lari and GRA Vanessa Voller Start Date: 10/31/16 Draft Date: 04/15/16 Final Task Approval Date: 05/15/16 Deliverable: Summary report reviewing key moments in the history of the ABC ramps including a one page executive summary and perhaps a visual timeline. Major Assignments 1. Review of policy context that lead to the construction of the ramps, including the planning and funding of and other structures (i.e. skyways) constructed with the ramps. a. Locate historical documents of I-394 construction b. Research what other structures were conducted in tandem with the ramps through literature review and interviews c. Identify the key planning members of the ABC ramp construction and hold interviews d. Research any other interesting social, political, or demographic trends pertaining to transportation at the time, both at a local state and national level e. Cross reference this information with data from Task 8A 2. Summary of travel trends before and after construction, including mode split, with particular attention to carpooling a. Locate documents outlining travel trends in Minneapolis before and after construction of ramps (1992) b. Create visual representation of travel trends 3. Pending any gaps from the preliminary literature review, schedule interviews for historical stakeholder r a. With the consultation of Adeel Lari, assemble a final draft of the stakeholders to be interviewed b. Create individual interview guide for historical stakeholders review. Some preliminary questions may include: c. Schedule individual interview times, facilitate and record interviews, transcribe and code interviews. 4. Report of annual revenues and occupancy of each ramp a. Gather data of the ramp s annual revenue and occupancy since 1992 b. Create visual representation of revenue and occupancy trends highlighting any major fluctuations 5. Report of operational highlights including safety and security issues, technology changes, etc. a. While looking through historical documents make note of any operational highlights b. If needed, consult key informants about operational highlights 6. Assemble final narrative

9 a. Write outline for final narrative b. Write first and second drafts and review with Adeel Lari and Lisa Austin c. Edit and revise working drafts d. Submit final narrative

10 Task 3: Corridor Evaluation Task Lead: Adeel Lari and GRA Kevin Karner Start Date: 10/31/16 Draft Date: 1/31/16 Final Task Approval Date: 02/28/17 Context: Review and evaluate all corridors leading to the ABC ramps, including but not limited to the I-394 corridor. Draw on existing plans, studies, reports, research and stakeholders to identify dominant modes (focus on those dominated by single occupancy vehicles, noting MnPASS vehicle occupancy counts in particular), challenges to increasing alternative mode shares, as well as other options for reducing congestion and construction projects that may positively or negatively affect access to the ramps. MnDOT s INRIX dataset, which uses GPS and phone data, is maintained by SRF and may be utilized. Deliverable: Report on corridors leading into downtown, discussing and rating (minor/major) potential impacts on the ABC Ramps. Major Assignments: 1. Use MnDOT AADT data to identify major corridors leading to ABC ramps/downtown a. Identify corridors leading from western suburbs (AADT) 2. Identify trip characteristics a. Number of trips total by route (INRIX) b. Temporal distribution of trips (INRIX) c. Origin and destination of trips by route (LEHD/INRIX/TBI) d. Number of trips made in single occupancy vehicles (MnPASS) 3. Interview transportation managers to determine future congestion mitigation activities and how ABC ramps could fit into those plans a. Interview MnDOT corridor managers on major routes to determine future congestion mitigation goals and the potential role of ABC ramps in those goals i. I-94 ii. I-394 iii. I-35 b. Interview relevant Metro Transit officials on impact of transit on corridor traffic i. Green Line (historical and projected impact) ii. Blue Line (historical and projected impact) iii. BRT projects 4. Determine present and estimated modal split of overall trips into downtown a. Infer from TBI and existing Met Council/CTS studies and reports b. Infer from interviews with corridor and transit managers c. Identify future construction projects that may impact traffic patterns 5. Synthesize findings into a series of maps and descriptive paragraphs Busiest Corridors Origin/Destination # Trips Purpose Time SOV Modal Split

11 INRIX (pending) x x x x x AADT (public) x TBI (public) x x x x LEHD (public) x x x MnPASS (pending) x

12 Task 4: Customer Demographics Task Lead: Yingling Fan Start Date: 09/1/16 Draft Date: 1/31/2017 Final Task Approval Date: 03/31/17 Deliverable: Report that summarizes transportation trends of ramp users and general public. Major Assignments 1. Identify travel shed geography for downtown Minneapolis a. Identify regional travel shed into ABC ramps = LEHD on the map b. Identify ABC eligible boundary = Move Minneapolis protocol 2. Identify geography of potential users = LEHD/Zip Code/TBI/INRIX a. Locate contract holders = Mark Read contract maps b. Locate non-contract users of ramps (survey?) c. Locate travelers to downtown = TBI inventory trip destinations i. Drivers ii. Transit users 3. Collect demographic data on households within respective geographies a. Demographics = TBI i. Age group ii. Income iii. Type of household b. Origin-Destination = TBI i. Trip purpose ii. Trip start/end time c. Mode split = TBI i. SOV ii. HOV users iii. Ridesharing iv. Transit v. Bike/Walk 4. Create driver profiles = informed by step 3 and an original intercept survey a. Current users of ABC users (drivers/transit users) i. Why do they choose the mode they do? ii. What mode would they prefer? iii. If different that current mode, why don t they use that mode? iv. What barriers do they have in doing something different? v. What would help them do something different? vi. Motivation/barriers to carpooling vii. Maybe get them to react to some ideas for different programs if we have any ideas to get feedback. b. Potential users within buffer zone = extrapolation from TBI i. Why do they choose the mode they do?

13 ii. What mode would they prefer? iii. If different that current mode, why don t they use that mode? iv. What barriers do they have in doing something different? v. What would help them do something different? vi. Maybe get them to react to some ideas for different programs if we have any ideas to get feedback. 5. Cross reference profiles with results from other sources a. Flexible Parking Pricing study b. Transit onboard study c. LEHD 6. Create narrative document pulling from all sources. a. Include map series

14 Task 5: Employer and business evaluation Task Lead: Frank Douma and Jason Cao Start Date: 09/1/16 Draft Date: 3/31/2017 Final Task Approval Date: 05/31/17 Deliverable: Summary report on local employer commitment to TDM efforts. Report will include a review of demographic data (and quality of it), discussion of TDM measures employed (transit passes, parking programs, biking facilities, etc.) and relationship of those measures to ABC ramp opportunities. Major Assignments 1. Determine workforce transportation trends in half mile buffer area of ABC ramps a. Identify workforce demographic statistics for the buffer zone b. Establish a list of employers/developers in buffer zone = assessor data c. Compile list of relevant TDMs on file with the City of Minneapolis = done d. Determine TDMs within buffer zone = done 2. Create matrix that identifies specific program efforts of employers around transportation a. Create a matrix that details type and degree of traffic mitigation effort b. Scan employer/developer TDM plans and enter into matrix 3. Engage employers about current and future commitment to TDM plans. a. Draft surveys geared towards employers and developers b. Send surveys to employer/developer contacts with instructions for completion c. When necessary, arrange for in-person follow up meetings 4. Compile deliverable report detailing overlap between TDM practices and ABC ramps a. Engage city and regional TAP members for input on drafts b. Maintain communication with survey respondents

15 Task 6: Regional Stakeholder Goals Task Lead: Frank Douma and GRA Vanessa Voller Start Date: 01/01/2017 Draft Date: 03/31/2017 Final Task Approval Date: 05/15/17 Deliverable: Summary report reviewing goals of key stakeholders, assessing the extent they align with those of the ABC ramps and recommending steps that could help bring goals of the ABC ramps into better alignment. Major Assignments 1. Conduct a text analysis of each stakeholder s website and other various publicity materials to identify each stakeholder s mission and vision statements and organizational goals and values. 2. When appropriate, consult with the TAP membership and other stakeholders specifically about their organization s mission and vision statements and organizational goals and values to ensure that information gathered online was correct. 3. Identify ABC Ramp s mission and vision statements and a list of its organizational goals and values. 4. Create a visual representation of each stakeholder s mission and vision statements and organizational goals and values highlighting the overlap between the stakeholders and those of ABC Ramps. 5. With the aid and consultation of Frank Douma and Lisa Austin create an individualized action plan as to how ABC ramps can better shift their organizational mission and vision to meet the goals and values of their clientele.

16 Task 8A: Policy, Ordinance, Statute, and Guidance Review Task Lead: Frank Douma Start Date: 12/01/16 Draft Date: 03/31/17 Final Task Approval Date: 05/31/17 Deliverable: Summary report of current legal environment in which ABC ramps must operate, and recommending changes as necessary to allow Ramps to best achieve new goals Major Assignments 1. Review of the federal, state, and local policies, ordinances, statutes, obligations and guidance, including CMAQ, that affect the ABC Ramps transportation and carpooling program options. a. Locate the local political documents outlining the local-level politics policies, ordinances, statutes, obligations and guidance, including CMAQ, that affect the ABC Ramps transportation options b. Locate the state political documents outlining the local-level politics policies, ordinances, statutes, obligations and guidance, including CMAQ, that affect the ABC Ramps transportation options c. Locate the federal political documents outlining the local-level politics policies, ordinances, statutes, obligations and guidance, including CMAQ, that affect the ABC Ramps transportation and carpooling program options d. Cross reference this information with data from Tasks 2 and 7 2. Create a brief list of recommended changes to support carpooling programs a. Research other local, national, and international policies, ordinances, statutes, obligations and guidance that are positively impacting carpooling programs b. After compiling the above-mentioned list, examine ways in which said l policies, ordinances, statutes, obligations could be implemented into local policy 3. Assemble final narrative a. Write outline for final narrative b. Write first and second drafts and review with Lisa Austin and Frank Douma c. Edit and revise working drafts d. Submit final narrative

17 Task 9: Literature Review and Program Scan Task Lead: Jason Cao Start Date: 09/1/16 Draft Date: Final Task Approval Date: 04/24/17 Deliverable: Report that (1) generates a list of innovative programs and outreach strategies that could be used by the ABC Ramps to reduce the number of drive alone commute trips to a central business district and (2) provides a summary and analysis of products and programs that are currently offered at ABC ramps. Major Assignments 1. Identify transit and multimodal infrastructure and programs near or that serve ABC ramps and I-394 Corridor and the ABC Ramps programs. Analyze what travel behavior each program encourages, promotes and rewards; and what behavior is discouraged or made more difficult in with program; and how equitable each program is. a. Bike i. Bike share ii. Monthly bike locker rental iii. Bike routes iv. Bike Centers b. Car i. ABC Ramps Carpool discount parking contract. $20 rate and $99 rate. ii. ABC Ramps SOV parkings contracts iii. ABC Ramps Early Bird Rate transient parking iv. ABC Ramps Event and entertainment parking v. ABC Ramps Airport parking vi. Onstreet parking vii. Car share viii. Ride hailing/ ride sourcing ix. EV charging c. Transit i. Transit Hubs and Stations with amenities ii. Bus routes, LRT and NorthStar iii. SW transit and other carriers iv. Megabus, Jefferson, Greyhound v. Park and rides d. Other i. Guaranteed Ride Home 2. Have students research innovative, effective and equitable Transportation Demand Management and Transportation Options programs worldwide. Identify programs in similar contexts to the Twin Cities that are successful in reducing drive alone trips a. Local TMOs (4 students total)

18 i. Move Minneapolis (1 student), St. Paul Smart trips (1 student), UMN (1 student), I-494 Commuting Service (1 student) b. TDM programs and/or TMOs in comparable cities domestic and international (7 students total) i. Portland, Seattle, Arlington VA, Buffalo NY, Columbus OH, LA County, San Francisco, Chicago (divided into two groups and 4 students total), Canada (1 student), Australia (1 student), North Europe (1 student) c. Programs of private sector such as Microsoft Foundation (3 students) d. Different car sharing/bike sharing schemes such as car2go, hour car, mobike (2 students) e. Parking policies, like early-bird rates, dynamic parking contract, SF park, 30-min reduced rate, etc. (3 students) f. Innovative payment for multimodal systems such as ramp-ride, ramp-sharing (2 students) Potential Student Resources: ACT Mobility Lab Shared Use Mobility Center TRB TDM News IPI City Lab Universities (ie ASU)

19 Task 10: Long Range Transportation Trends Task Lead: Frank Douma, Adeel Lari, and Barbara Rohde and GRA Vanessa Voller Start Date: 12/01/16 Draft Date: 04/31/16 Final Task Approval Date: 07/31/16 Deliverable: Summary report discussing the potential long range transportation scenarios over the next 25 years, and the nature of their impact on ABC Ramps parking and TDM goals Major Assignments 1. Identify the long range transportation scenarios over the next 25 years and the nature of their impact on the ABC Ramps a. Develop a series of scenarios that anticipate the potential impact of transportation innovations of the following: i. autonomous vehicles ii. car sharing iii. ride-sharing iv. any other shared economy initiatives v. teleworking vi. electrification of vehicles vii. changes to transportation finance mechanisms viii. other trends identified by researchers and TAP members. b. Each scenario should will include: 2. Review and create abstract-like summary of pertitent background information from the following. Specifically for downtown/abc Ramp area: a. Minnesota State Highway Transportation Plan b. Minnesota Go! c. Transportation Futures Study 3. Assemble final narrative a. Write outline for final narrative b. Write first and second drafts and review with Lisa and Frank c. Edit and revise working drafts d. Submit final narrative

ABC Ramps Research Overview

ABC Ramps Research Overview ABC Ramps Research Overview Frank Douma, Barbara Rohde, Adeel Lari, Yingling Fan, Jason Cao, Kevin Karner, Rachel Dame, Frank Alarcon UofM Research Scope of Work Task 1: Project Management Task 2: History

More information

TRANSPORTATION OPTIONS PROGRAM PLAN TAP MEETING #1 1/23/17

TRANSPORTATION OPTIONS PROGRAM PLAN TAP MEETING #1 1/23/17 TRANSPORTATION OPTIONS PROGRAM PLAN TAP MEETING #1 1/23/17 Agenda Introductions ABC Ramps Info and History Multi-modal programs Partners and Stakeholders Research Problem Statement Research Scope of Work

More information

2030 Transportation Policy Plan SUMMARY PRESENTATION. Land Use Advisory Committee November 15, 2012

2030 Transportation Policy Plan SUMMARY PRESENTATION. Land Use Advisory Committee November 15, 2012 2030 Transportation Policy Plan SUMMARY PRESENTATION Land Use Advisory Committee November 15, 2012 Today s Topics Transportation Policy Plan (TPP) Requirements and Background Current TPP Policies, Issues

More information

2040 Transportation Policy Plan Conversion to Performance Based Planning Basis. 25 th Annual CTS Transportation Research Conference May 21, 2014

2040 Transportation Policy Plan Conversion to Performance Based Planning Basis. 25 th Annual CTS Transportation Research Conference May 21, 2014 2040 Transportation Policy Plan Conversion to Performance Based Planning Basis 25 th Annual CTS Transportation Research Conference May 21, 2014 1 About the plan Long-range transportation plan for the Twin

More information

Congestion Management Process (CMP)

Congestion Management Process (CMP) Congestion Management Process (CMP) Introduction The Congestion Management Process (CMP) is a systematic, data-driven, and regionally accepted approach that aims to improve the performance of the transportation

More information

Chapter 14 Work Program

Chapter 14 Work Program Chapter 14 Work Program The Metropolitan Council will carry out or participate in many studies and plans over the next three years. This is not an exhaustive list of all work to be completed by the Metropolitan

More information

City of Fairfax, Virginia City Council Regular Meeting

City of Fairfax, Virginia City Council Regular Meeting City Council Regular Meeting Agenda Item # 7b City Council Meeting 5/10/2016 TO: FROM: SUBJECT: ISSUE(S): SUMMARY: Honorable Mayor and Members of City Council Robert Sisson, City Manager Consideration

More information

EXAMPLES OF COMPREHENSIVE PLAN POLICIES HOW TO ESTIMATE THE BENEFITS OF THE CTR PROGRAM

EXAMPLES OF COMPREHENSIVE PLAN POLICIES HOW TO ESTIMATE THE BENEFITS OF THE CTR PROGRAM TABLE OF CONTENTS INTRODUCTION... I BACKGROUND OF THE COMMUTE TRIP REDUCTION EFFICIENCY ACT... II MAKING THE CONNECTION BETWEEN COMMUTE TRIP REDUCTION AND THE GROWTH MANAGEMENT ACT... IV CTR PLANNING AND

More information

Executive Summary T Transportation Committee Item:

Executive Summary T Transportation Committee Item: Executive Summary T Transportation Committee Item: 2012-12 Meeting date: January 9, 2012 Council Meeting: N/A ADVISORY INFORMATION Date: January 5, 2012 Subject: Adopt Transportation Committee 2012 Work

More information

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015 ACTIVE TRANSPORTATION ADVISORY COMMITTEE Memphis MPO March 30, 2015 Agenda Welcome & Introductions Announcements and Briefings Livability 2040: Regional Transportation Plan Congestion Management Process

More information

Regional Transit System Plan

Regional Transit System Plan Policy, Program Development & Intergovernmental Relations Committee Item III-A October 14, 2010 Regional Transit System Plan Washington Metropolitan Area Transit Authority Board Action/Information Summary

More information

BACKGROUND. The FasTracks Plan includes three core goals:

BACKGROUND. The FasTracks Plan includes three core goals: BACKGROUND The Regional Transportation District (RTD) was created in 1969 by the Colorado General Assembly to develop, operate, and maintain a mass transportation system for the benefit of 2.87 million

More information

Administration and Projects Committee STAFF REPORT

Administration and Projects Committee STAFF REPORT Meeting Date: Subject Summary of Issues Recommendation Financial Implications Options Attachments Changes from Committee Innovate 680 (Project 8009) Authorization to Issue Request for Proposals (RFP) No.

More information

SONG - Homework #2. Transportation Network Development System Analysis. The main objectives of this assignment are to help student

SONG - Homework #2. Transportation Network Development System Analysis. The main objectives of this assignment are to help student SONG - Homework #2 Transportation Network Development System Analysis The main objectives of this assignment are to help student learn to draw implications of alternative policies on transportation network

More information

EXECUTIVE SUMMARY REGIONAL TRANSPORTATION PLAN 2050

EXECUTIVE SUMMARY REGIONAL TRANSPORTATION PLAN 2050 EXECUTIVE SUMMARY REGIONAL TRANSPORTATION PLAN 2050 Introduction Goals Policies, and Performance Measures Growth Forecast and Planned Land Use Development Key Recommendations i Executive Summary April

More information

Travel Demand Forecasting User Guide

Travel Demand Forecasting User Guide Travel Demand Forecasting User Guide A Supplement to the Regional Transitway Guidelines Metropolitan Council February 2012 This document supplements the Project Development, Leadership, and Oversight discussion

More information

Chapter #9 TRAVEL DEMAND MODEL

Chapter #9 TRAVEL DEMAND MODEL Chapter #9 TRAVEL DEMAND MODEL TABLE OF CONTENTS 9.0 Travel Demand Model...9-1 9.1 Introduction...9-1 9.2 Overview...9-1 9.2.1 Study Area...9-1 9.2.2 Travel Demand Modeling Process...9-3 9.3 The Memphis

More information

Highest Priority Performance Measures for the TPP

Highest Priority Performance Measures for the TPP Highest Priority Performance Measures for the TPP The following list of measures are the highest priority performance measures as identified by modal working groups. These groups consist of staff from

More information

Comprehensive Transportation Study for Glencoe, MN

Comprehensive Transportation Study for Glencoe, MN Comprehensive Transportation Study for Glencoe, MN Introduction and Project Information Introduction There have been a number of planning and preliminary engineering studies completed in the Glencoe area

More information

What is the Transportation Policy Plan (TPP)?

What is the Transportation Policy Plan (TPP)? Summary What is the Transportation Policy Plan (TPP)? The region s long range transportation plan Includes all modes of transportation: highways, transit, airports, freight, biking, pedestrians Meets the

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL No. 2016-54 DATE: November 3, 2016 TO: FROM: Transportation Advisory Board Technical Advisory Committee PREPARED

More information

2018 Comprehensive Guide Plan Steering Committee. Wednesday, October 11, Minnehaha Room, Minnetonka City Hall. 6:00 8:00 p.m.

2018 Comprehensive Guide Plan Steering Committee. Wednesday, October 11, Minnehaha Room, Minnetonka City Hall. 6:00 8:00 p.m. 2018 Comprehensive Guide Plan Steering Committee Wednesday, October 11, 2017 Minnehaha Room, Minnetonka City Hall 6:00 8:00 p.m. Agenda: 6:00 6:15 Dinner 6:15 6:45 Transportation planning overview 6:45

More information

Demand Reduction Assumptions Used For Travel Demand Analysis of EIS Alternatives

Demand Reduction Assumptions Used For Travel Demand Analysis of EIS Alternatives M E M O R A N D U M Demand Reduction Assumptions Used For Travel Demand Analysis of EIS Alternatives TO: FROM: Project Management Team Steve Perone/PTV America DATE: Revised: February 6, 2009 Background

More information

From Policy to Reality

From Policy to Reality From Policy to Reality Updated ^ Model Ordinances for Sustainable Development 2000 Environmental Quality Board 2008 Minnesota Pollution Control Agency Funded by a Minnesota Pollution Control Agency Sustainable

More information

General Population Survey Summary

General Population Survey Summary General Population Survey Summary A short online survey was used to get input from general population users of the Highway 169 corridor. The survey was promoted through a press release, email blast, social

More information

Chapter 6 Transit Investment Direction and Plan

Chapter 6 Transit Investment Direction and Plan Chapter 6 Transit Investment Direction and Plan Residents and businesses view a strong public transit system as an essential part of a transportation system that will serve a prosperous, livable, equitable

More information

Current Trends in Traffic Congestion Mitigation

Current Trends in Traffic Congestion Mitigation Current Trends in Traffic Congestion Mitigation April 24, 2009 NCSL Spring Forum Washington, DC Jeff Lindley Associate Administrator, Office of Operations Federal Highway Administration U.S. Department

More information

Midtown Corridor Alternatives Analysis. Technical Advisory Committee Meeting November 15, 2012

Midtown Corridor Alternatives Analysis. Technical Advisory Committee Meeting November 15, 2012 Midtown Corridor Alternatives Analysis Technical Advisory Committee Meeting November 15, 2012 Today s Agenda Introductions Roles and Responsibilities Alternatives Analysis Process Overview Outreach Overview

More information

APPENDIX B - GLOSSARY FEBRUARY 2017

APPENDIX B - GLOSSARY FEBRUARY 2017 APPENDIX B - GLOSSARY FEBRUARY 2017 DENVERMOVES Transit Denver Moves: Transit - ii - APPENDIX B TRANSIT AND MOBILITY GLOSSARY Amenities, stop or station: Objects or facilities (such as a shelter, bench,

More information

Los Angeles County Congestion Reduction Demonstration Project

Los Angeles County Congestion Reduction Demonstration Project Los Angeles County Congestion Reduction Demonstration Project frequently asked questions update #1 /august 2008 Los Angeles County Metropolitan Transportation Authority (Metro), California Department of

More information

CHAPTER 1 COMMUTE TRIP REDUCTION BASIC INFORMATION

CHAPTER 1 COMMUTE TRIP REDUCTION BASIC INFORMATION CHAPTER 1 COMMUTE TRIP REDUCTION BASIC INFORMATION COMMUTE TRIP REDUCTION (CTR) OVERVIEW In 1991, the Washington State Legislature passed the Commute Trip Reduction (CTR) Law requiring employers to work

More information

I-66 Corridor Improvements Outside the Capital Beltway in Northern Virginia, USA

I-66 Corridor Improvements Outside the Capital Beltway in Northern Virginia, USA 15th International Conference on Managed Lanes I-66 Corridor Improvements Outside the Capital Beltway in Northern Virginia, USA Case Study for Funding of Transit Service and Transportation Demand Management

More information

LONG-RANGE TDM PLAN-APPENDIX C

LONG-RANGE TDM PLAN-APPENDIX C LONG-RANGE TDM PLAN-APPENDIX C RIDEFINDERS PROGRAM MONITORING AND EVALUATION prepared by Cambridge Systematics, Inc. with Center for Urban Transportation Research LDA Consulting Southeastern Institute

More information

Chapter 1: Overview. page 1. Figure 2-1: Road congestion is expected to continue to grow

Chapter 1: Overview. page 1. Figure 2-1: Road congestion is expected to continue to grow Chapter 1: Overview Figure 2-1: Road congestion is expected to continue to grow The region s mobility so fundamental to its economic vitality and quality of life is challenged by mounting congestion, rising

More information

12 Evaluation of Alternatives

12 Evaluation of Alternatives 12 Evaluation of Alternatives This chapter evaluates the effectiveness of the No-Build Alternative and the proposed METRO Blue Line Light Rail Transit (BLRT) Extension project based on the information

More information

The Role of Transportation Systems Management & Operations in Supporting Livability and Sustainability

The Role of Transportation Systems Management & Operations in Supporting Livability and Sustainability The Role of Transportation Systems Management & Operations in Supporting Livability and Sustainability Michael Grant, ICF International February 7, 2012 NTOC Webinar Highlights of FHWA/FTA Primer Background:

More information

STRATEGIC MOBILITY PLAN ADVISORY COMMITTEE MEETING 2 MAY 16, 2017

STRATEGIC MOBILITY PLAN ADVISORY COMMITTEE MEETING 2 MAY 16, 2017 STRATEGIC MOBILITY PLAN ADVISORY COMMITTEE MEETING 2 MAY 16, 2017 1 AGENDA 1. Summary of public & stakeholder input 2. Review of market findings and forecast, trends and opportunities and threats 3. Work

More information

THE REGION S PLAN POLICY FRAMEWORK. August 2015

THE REGION S PLAN POLICY FRAMEWORK. August 2015 THE REGION S PLAN POLICY FRAMEWORK August 2015 2 What is The Policy Framework? Cover photo credit: Sinan Sinharoy for Atlanta BeltLine, Inc. Atlanta is one of the world s most dynamic metropolitan areas,

More information

APPENDIX A - PLANS AND POLICY REVIEW FEBRUARY 2017

APPENDIX A - PLANS AND POLICY REVIEW FEBRUARY 2017 APPENDIX A - PLANS AND POLICY REVIEW FEBRUARY 2017 DENVERMOVES Transit Denver Moves: Transit APPENDIX A PLANS AND POLICY REVIEW 2035 Metro Vision Regional Transportation Plan (MVRTP) (2011) 2040 Fiscally

More information

Chapter 2 Transportation Policy Plan Strategies

Chapter 2 Transportation Policy Plan Strategies Chapter 2 Transportation Policy Plan Strategies As discussed in Chapter 1, the current federal transportation law, Fixing America s Surface Transportation Act (FAST Act), mandates a streamlined and performance-based

More information

and Unmet Need: Methodology and Results

and Unmet Need: Methodology and Results 2 Demand and Unmet Need: Methodology and Results Projecting unmet park-and-ride need is the key indicator for park-and-ride expansion. There is gross demand and net new demand (also known as unmet need)

More information

Moffett Towers. Final Transportation Demand Management (TDM) Plan. Jay Paul Company. Prepared for: Prepared by:

Moffett Towers. Final Transportation Demand Management (TDM) Plan. Jay Paul Company. Prepared for: Prepared by: Moffett Towers Final Transportation Demand Management (TDM) Plan Prepared for: Jay Paul Company Prepared by: January 10, 2008 TABLE OF CONTENTS I. Project Description 1 II. Site Facilities and Amenities

More information

Los Angeles County Sustainability Summit Your Community: Smart Growth and Community Development

Los Angeles County Sustainability Summit Your Community: Smart Growth and Community Development Los Angeles County Sustainability Summit Your Community: Smart Growth and Community Development Barbara Dye The South Bay Cities Council Of Governments (SBCCOG) is a joint powers authority of 16 cities

More information

SUBURBAN EDGE COMMUNITY ROLE COUNCIL ROLE ALL COMMUNITIES SUBURBAN EDGE

SUBURBAN EDGE COMMUNITY ROLE COUNCIL ROLE ALL COMMUNITIES SUBURBAN EDGE Orderly and Efficient Land Use Align land use, development patterns, and infrastructure to make the best use of public and private investment. Plan and stage development for forecasted growth through 2040

More information

Overview of Changes Made to CMAQ & System Performance Measures. Presented by: Jason Pavluchuk Association for Commuter Transportation

Overview of Changes Made to CMAQ & System Performance Measures. Presented by: Jason Pavluchuk Association for Commuter Transportation Overview of Changes Made to CMAQ & System Performance Measures Presented by: Jason Pavluchuk Association for Commuter Transportation Agenda CMAQ Overview Changes Made by FAST ACT 2013 Guidance Performance

More information

Service Development. Committee of the Whole April 3, 2019 Adam Harrington, Director of Service Development 1

Service Development. Committee of the Whole April 3, 2019 Adam Harrington, Director of Service Development 1 Service Development Committee of the Whole April 3, 2019 Adam Harrington, Director of Service Development 1 Transit Service 130 bus routes A Line 2 LRT lines 1 commuter rail 2.4 million annual bus service

More information

41 st & Fox Station Area Property Owner Meeting August 16, 2018

41 st & Fox Station Area Property Owner Meeting August 16, 2018 Parking Maximum Overlay 41 st & Fox Station Area Property Owner Meeting August 16, 2018 1 Agenda What is this all about? Background 41 st & Fox Station Area Plan Vision Major Implementation Steps What

More information

San Francisco Freeway Corridor Management Study (SF FCMS)

San Francisco Freeway Corridor Management Study (SF FCMS) Item 6 Enclosure B Plans and Programs Committee March 17, 2015 San Francisco Freeway Corridor Management Study (SF FCMS) Phase 1 Findings and Recommendations Agenda Item 6 SAN FRANCISCO COUNTY TRANSPORTATION

More information

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11

Contents i Contents Page 1 A New Transportation Plan Community Involvement Goals and Objectives... 11 Contents i Contents 1 A New Transportation Plan... 1 Why develop a new plan?... 1 What area does the LRTP focus on?... 2 Why is this LRTP important?... 3 Meeting Requirements for Transportation Planning...

More information

EXHIBIT A. TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No

EXHIBIT A. TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No EXHIBIT A TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No. 429768-4-12-01 This Exhibit forms an integral part of the Agreement between the DEPARTMENT and, the CONSULTANT,

More information

Webinar Series for Comprehensive Plan Updates. Transportation Overview

Webinar Series for Comprehensive Plan Updates. Transportation Overview Webinar Series for Comprehensive Plan Updates Transportation Overview Presented by Michael Larson and Mark Filipi August 18, 2016 2040 Transportation Policy Plan Adopted January 14 th, 2015 Multimodal

More information

Appendix C: Scenarios and Future Drivers Impacting Transportation

Appendix C: Scenarios and Future Drivers Impacting Transportation Prepared for Washington County Prepared by David Evans and Associates, Inc. 2100 SW River Parkway Portland, Oregon 97201 TABLE OF CONTENTS 1. INTRODUCTION... 2 2. SCENARIOS PLANNING OVERVIEW... 2 3. SCENARIOS

More information

Transform 66 Multimodal Project: Prioritization Process and Evaluation Criteria Approved March 3, 2016

Transform 66 Multimodal Project: Prioritization Process and Evaluation Criteria Approved March 3, 2016 Transform 66 Multimodal Project: Prioritization Process and Evaluation Criteria Approved March 3, 2016 The Memorandum of Agreement (MOA) for the Transform 66: Inside the Beltway Project directs NVTC to

More information

Transportation Demand Management

Transportation Demand Management Transportation Demand Management Performance Measures December 2013 Transportation Reform Demonstration Project: Creating jobs and economic development in Michigan by removing barriers to coordinated federal,

More information

Appendix. Appendix C. Metropolitan Council 2030 Park-and-Ride Plan

Appendix. Appendix C. Metropolitan Council 2030 Park-and-Ride Plan Appendix C Appendix C Stakeholder Comments on the January 2010 Draft Metropolitan Council Park-and-Ride and Metropolitan Council Responses Metropolitan Council 2030 Park-and-Ride Revision/Metropolitan

More information

Effective Transportation Demand Management (TDM) in Congested Corridors US 422 TDM Best Practices Policy Brief and Recommendations

Effective Transportation Demand Management (TDM) in Congested Corridors US 422 TDM Best Practices Policy Brief and Recommendations Effective Transportation Demand Management (TDM) in Congested Corridors US 422 TDM Best Practices Policy Brief and Recommendations Pennsylvania Chapter of the American Planning Association Annual Conference

More information

Congestion Management Process in the US A Federal Requirement

Congestion Management Process in the US A Federal Requirement Congestion Management Process in the US A Federal Requirement ITS Argentina November 6, 2013 U.S. Department of Transportation Federal Highway Administration Outline of Seminar Discussion of Congestion

More information

DES MOINES AREA MPO. Environment Roundtable. October 13, 2015

DES MOINES AREA MPO. Environment Roundtable. October 13, 2015 DES MOINES AREA MPO Environment Roundtable October 13, 2015 October 13, 2015 Agenda 1. Call to Order 2. VOTE: Approval of Agenda 3. VOTE: Approval of Meeting Minutes 4. UPDATE: Water Trails 5. DISCUSSION:

More information

Policy Research CENTER

Policy Research CENTER Connecting Demand Management and Economic Development Activities TRANSPORTATION Policy Research CENTER Recent research into employer-based demand management strategies highlighted the fact that most business

More information

SCS Scenario Planning

SCS Scenario Planning E SCS Scenario Planning Introduction As part of the 2035 MTP/SCS process, AMBAG developed a series of land use and transportation alternative scenarios for evaluation and testing to demonstrate how the

More information

Transit Investment Direction and Plan Introduction. Transportation Advisory Board TPP Workshop August 16, 2017

Transit Investment Direction and Plan Introduction. Transportation Advisory Board TPP Workshop August 16, 2017 Transit Investment Direction and Plan Introduction Transportation Advisory Board TPP Workshop August 16, 2017 Today s Topics - Transit Where are we now, what are the current issues? Where do we want to

More information

A Plan for Sustainable Transportation at Yale. June 2012 [Updated September 1, 2013] INTRODUCTION

A Plan for Sustainable Transportation at Yale. June 2012 [Updated September 1, 2013] INTRODUCTION A Plan for Sustainable Transportation at Yale June 2012 [Updated September 1, 2013] INTRODUCTION Yale Transportation Options has been providing support for members of the Yale community interested in more

More information

ATTACHMENT A. Detailed Study Scope. I-66 (Inside) Multi-modal Study Scope

ATTACHMENT A. Detailed Study Scope. I-66 (Inside) Multi-modal Study Scope ATTACHMENT A Detailed Study Scope I-66 (Inside) Multi-modal Study Scope EXECUTIVE SUMMARY The Virginia Department of Transportation (VDOT) seeks consultant assistance in identifying and evaluating a range

More information

Locally Preferred Alternative. Work In Progress; Subject To Change Without Notice 1

Locally Preferred Alternative. Work In Progress; Subject To Change Without Notice 1 Locally Preferred Alternative 1 Riverview Corridor Study Area 12 mile study area between Saint Paul and Bloomington. Connects major destinations, neighborhoods and job concentrations. Serves growing and

More information

PINELLAS COUNTY MOBILITY PLAN SUMMARY REPORT

PINELLAS COUNTY MOBILITY PLAN SUMMARY REPORT PINELLAS COUNTY MOBILITY PLAN SUMMARY REPORT In September, 2013, the Pinellas County Mobility Plan Report was approved by the Metropolitan Planning Organization (MPO). This action endorsed a countywide

More information

Highway and Freight Current Investment Direction and Plan. TAB September 20, 2017

Highway and Freight Current Investment Direction and Plan. TAB September 20, 2017 Highway and Freight Current Investment Direction and Plan TAB September 20, 2017 Today s Topics Where are we now, what are the current issues? Where do we want to go? How will we get there? What are the

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 11 DIVISION: Director of Transportation BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Adopt the new San Francisco Municipal Transportation Agency

More information

COMMUTE TRIP REDUCTION (CTR) OVERVIEW

COMMUTE TRIP REDUCTION (CTR) OVERVIEW COMMUTE TRIP REDUCTION (CTR) OVERVIEW In 1991, the Washington State Legislature passed the Commute Trip Reduction (CTR) Law requiring employers to work with employees to reduce the number and length of

More information

Parking is the sacred cow of land uses. It claims privileged status in zoning codes

Parking is the sacred cow of land uses. It claims privileged status in zoning codes Parking Management for Smart Growth R I C H A R D W I L L S O N Parking is the sacred cow of land uses. It claims privileged status in zoning codes and there is simply too much of it in cities. Previous

More information

I-880 ICM Systems Engineering Management Plan TAC Meeting

I-880 ICM Systems Engineering Management Plan TAC Meeting I-880 ICM Systems Engineering Management Plan TAC Meeting Presented by Metropolitan Transportation Commission (MTC) November 16, 2011 1 Agenda Introductions, Agenda Project Status I-880 ICM Strategies

More information

Direction 1: Promote active and green transportation biking, walking and transit

Direction 1: Promote active and green transportation biking, walking and transit Why is this important? We need transportation sidewalks, bikes, buses, trains and cars to get to work, to school and do every day things. We also need efficient transportation and access to keep the economy

More information

Southwest LRT Management Committee. September 7, 2011

Southwest LRT Management Committee. September 7, 2011 Southwest LRT Management Committee September 7, 2011 Today s Topics Project Status Updates Follow-Up Requests Funding Partner Commitments Communications and Public Involvement Process 2 Project Status

More information

RE: Alternatives for SANDAG s Environmental Analysis for San Diego Forward: The Regional Plan

RE: Alternatives for SANDAG s Environmental Analysis for San Diego Forward: The Regional Plan February 10, 2015 SANDAG Rob Rundle 401 B St. Ste. 800 San Diego, CA 92101 RE: Alternatives for SANDAG s Environmental Analysis for San Diego Forward: The Regional Plan Dear Rob: On behalf of Circulate

More information

Chapter 5 Transportation Draft

Chapter 5 Transportation Draft Chapter 5 Transportation Draft Discussion Similar to the other elements in the Comprehensive Plan, the transportation element impacts the quality of life, economic development and public safety of the

More information

Summary of transportation-related goals and objectives from existing regional plans

Summary of transportation-related goals and objectives from existing regional plans SMTC 2050 Long Range Transportation Plan Appendix A: Summary of transportation-related goals and objectives from existing regional plans SMTC 2050 Long Range Transportation Plan Summary of transportation-related

More information

Transit Investment Direction and Plan Introduction. Transportation Advisory Board October 18, 2017

Transit Investment Direction and Plan Introduction. Transportation Advisory Board October 18, 2017 Transit Investment Direction and Plan Introduction Transportation Advisory Board October 18, 2017 Today s Topics - Transit Where are we now, what are the current issues? Where do we want to go? How will

More information

CAPITAL- ALAMO CONNECTION STUDY

CAPITAL- ALAMO CONNECTION STUDY CAPITAL- ALAMO CONNECTION STUDY TECHNICAL ADVISORY COMMITTEE BRIEFING November 27, 2017 What is the Capital-Alamo Connection Study? A JOINT EFFORT BY: OBJECTIVE: To develop a regional strategy to enhance

More information

CAPITAL- ALAMO CONNECTION STUDY

CAPITAL- ALAMO CONNECTION STUDY CAPITAL- ALAMO CONNECTION STUDY TECHNICAL ADVISORY COMMITTEE BRIEFING December 1, 2017 What is the Capital-Alamo Connection Study? A JOINT EFFORT BY: OBJECTIVE: To develop a regional strategy to enhance

More information

Commonwealth Transportation Board I-66 Corridor Briefing Outside the Beltway Route 15 to I-495

Commonwealth Transportation Board I-66 Corridor Briefing Outside the Beltway Route 15 to I-495 Commonwealth Transportation Board I-66 Corridor Briefing Outside the Beltway Route 15 to I-495 January 13, 2015 1 Project Status Update Transit P3 Procurement I-66 Corridor Briefing Overview Major Project

More information

Proposed Comprehensive Update to the State of Rhode Island s Congestion Management Process

Proposed Comprehensive Update to the State of Rhode Island s Congestion Management Process Proposed Comprehensive Update to the State of Rhode Island s Statewide Planning Program January 2018 Summary Outline of of Action Steps 1. Develop Objectives for Congestion Management What is the desired

More information

3. STATION SPACING AND SITING GUIDELINES

3. STATION SPACING AND SITING GUIDELINES 3. STATION SPACING AND SITING GUIDELINES The station spacing and siting guidelines are summarized in Table 3-1. Table 3-1 also includes benchmark information for local transit service and express bus as

More information

Chapter 12: Federal Requirements

Chapter 12: Federal Requirements 12.1 Chapter 12: Federal Requirements 2040 2040 TRANSPORTATION POLICY PLAN version 1.0 12.2 CONTENTS Chapter 12: Federal Requirements Transportation System Performance Evaluation 12.4 Congestion Management

More information

Alternatives Evaluation Report. Appendix C. Alternatives Evaluation Report

Alternatives Evaluation Report. Appendix C. Alternatives Evaluation Report s Evaluation Report Appendix C s Evaluation Report I-35W North Corridor Project EA Minnesota Department of Transportation Final Project s Report I-35W North Corridor Preliminary Design Project Report Version

More information

Chapter 3 Transportation System Management & Operations and Travel Demand Management

Chapter 3 Transportation System Management & Operations and Travel Demand Management Chapter 3: Transportation System Management & Operations and Travel Demand Management As roadways in Washington County grow more congested, it becomes increasingly important to focus on costeffective strategies

More information

Transportation Demand Management (TDM) Plan 2075 Broadway, Redwood City, CA

Transportation Demand Management (TDM) Plan 2075 Broadway, Redwood City, CA Transportation Demand Management (TDM) Plan 2075 Broadway, Redwood City, CA Prepared For: Lane Partners, LLC Prepared By: SANDIS 644 Menlo Avenue, Second Floor 636 9 th Street Menlo Park, CA 94025 Oakland,

More information

Congestion Management Process 2013 Update

Congestion Management Process 2013 Update OVERVIEW OF THE DALLAS-FORT WORTH CONGESTION MANAGEMENT PROCESS Traffic Congestion In The Dallas-Fort Worth Region With the Dallas-Fort Worth (DFW) urban area as its center, the North Central Texas region

More information

Eco-Logical Pilot Project - Free Bridge Congestion Relief Stakeholder Information Handout

Eco-Logical Pilot Project - Free Bridge Congestion Relief Stakeholder Information Handout Eco-Logical Pilot Project - Free Bridge Congestion Relief Stakeholder Information Handout Problem: The US 250 link across the Rivanna River known locally as Free Bridge. This bridge is a key connection

More information

10. PROJECT DEVELOPMENT, LEADERSHIP, AND OVERSIGHT GUIDELINES

10. PROJECT DEVELOPMENT, LEADERSHIP, AND OVERSIGHT GUIDELINES 10. PROJECT DEVELOPMENT, LEADERSHIP, AND OVERSIGHT GUIDELINES It is important to note that the Transitway Guidelines are not intended to be prescriptive, but rather to provide a consistent basis for planning,

More information

Strategic Plan PROPOSED STRATEGIC PLAN METRICS. Progress Report

Strategic Plan PROPOSED STRATEGIC PLAN METRICS. Progress Report Strategic Plan PROPOSED STRATEGIC PLAN METRICS Progress Report Policy and Governance Committee September 15, 2017 1 Agenda Review of metrics development process Review of currently proposed KPIs Discussion

More information

2004 FEASIBILITY STUDY UPDATE

2004 FEASIBILITY STUDY UPDATE Austin-San Antonio Intermunicipal Commuter Rail District 2004 FEASIBILITY STUDY UPDATE December 2004 EXECUTIVE SUMMARY INTRODUCTION Almost 3 million people in Central Texas, living and working between

More information

Strategic Plan. SFMTA Board of Directors Workshop

Strategic Plan. SFMTA Board of Directors Workshop Strategic Plan SFMTA Progress Strategic ReportPlan SFMTA Board of Directors Workshop January 23, 2018 Agenda Review of strategic planning and metrics development to date Overview of proposed plan elements

More information

South Bay Corridor Study and Evaluation for Dynamic Corridor Congestion Management (DCCM) Metro Streets and Freeways Subcommittee Meeting

South Bay Corridor Study and Evaluation for Dynamic Corridor Congestion Management (DCCM) Metro Streets and Freeways Subcommittee Meeting South Bay Corridor Study and Evaluation for Dynamic Corridor Congestion Management (DCCM) Metro Streets and Freeways Subcommittee Meeting October 17, 2013 Agenda 1. DCCM Background 2. Project Overview

More information

A428 / Western Corridor brief. Background

A428 / Western Corridor brief. Background A428 / Western Corridor brief Background The Transport Strategy that has been developed to support the current Local Plan review outlines major investment in public transport as a pre-requisite to support

More information

Alameda Countywide Transportation Plan Update Evaluation Outcomes

Alameda Countywide Transportation Plan Update Evaluation Outcomes TAWG Meeting 07/14/11 Attachment 06 Handout Alameda Countywide Transportation Plan Update Evaluation Outcomes presented to Technical Advisory Working Group presented by Cambridge Systematics, Inc. July

More information

Appendix O Congestion Management Program REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY

Appendix O Congestion Management Program REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY Appendix O Congestion Management Program REGIONAL TRANSPORTATION PLAN/SUSTAINABLE COMMUNITIES STRATEGY 2014 REGIONAL CONGESTION MANAGEMENT PROGRAM 2014 RTP/SCS APPENDIX O SAN JOAQUIN COUNCIL OF GOVERNMENTS

More information

Priorities are for AG comment at today's meeting. Four time frames proposed for implementation

Priorities are for AG comment at today's meeting. Four time frames proposed for implementation Prioritization Overview Priorities are for AG comment at today's meeting Four time frames proposed for implementation Prioritization Overview Some editing of Principles to read as implementation versus

More information

Champion Report. REPORTING PERIOD: April 15, 2014 through July 15, Theme Area: Transportation Jarrett Leas, Tim Houle, Tad Erickson

Champion Report. REPORTING PERIOD: April 15, 2014 through July 15, Theme Area: Transportation Jarrett Leas, Tim Houle, Tad Erickson Champion Report Theme Area: Transportation Jarrett Leas, Tim Houle, Tad Erickson REPORTING PERIOD: April 15, 2014 through July 15, 2014 Goals/Strategies or Action Steps: What NEW success have you had in

More information

Overview of Draft Metro Strategic Plan April 12, 2018

Overview of Draft Metro Strategic Plan April 12, 2018 Overview of Draft Metro Strategic Plan April 12, 2018 OUR STORY Population and economic growth are increasing travel demand on a congested system. GHG and environmental impacts of transportation grow with

More information

Executive Summary i Regional Transportation Plan March 2018

Executive Summary i Regional Transportation Plan March 2018 Executive Summary i Regional Transportation Plan March 2018 Executive Summary ii iii 2041 Regional Transportation Plan The Greater Toronto and Hamilton Area (GTHA) is one of the fastest growing regions

More information

Attachment 1. Task Order Services, Schedule and Deliverables

Attachment 1. Task Order Services, Schedule and Deliverables AECOM Project Number: AECOM Project Name: MCSA Task Order No.: Attachment 1 Task Order Services, Schedule and Deliverables SCOPE OF SERVICES TASK 1: PROJECT COORDINATION The AECOM approach includes an

More information