Project Management Manual Prepared by: Project Support Office, Major Projects Department

Size: px
Start display at page:

Download "Project Management Manual Prepared by: Project Support Office, Major Projects Department"

Transcription

1 Project Management Manual Prepared by: Project Support Office, Major Projects Department Version: 2015

2 Project Support Office Project Management Manual Version: November 2015 This manual is a living document and will be updated to meet the evolving project management needs of the organization. DOCUMENT REVISIONS Date of Revision Description of Revision Approved by: November 20, 2014 First version GH, KS April 1, 2015 Updates to client support contact information GH April 30, 2015 Updates to client support; updates and clarifications GH, RS, CE within the Initiation Phase section November 30, 2015 Updates to client support GH, RS, MM All tools referenced in this manual can be found at: G:\Corporate PSO Other reference documents that project participants may find helpful: - Administration Bylaw, Schedule D (Purchasing Policy) (authorities and procedures for procurement) available at Regina.ca or contact Purchasing Capital Project Process Manual (useful for construction projects) contact Development Engineering Intended Audience: This manual will be useful to sponsors, steering committee members, project managers, and project teams. Questions or comments? Contact the Project Support Office, Major Projects Department, 7 th Floor, City Hall Manager: Jill Hyndman, Client Support: City Manager s Office City Manager Executive Director, Chief Legislative Officer & City Clerk City Clerk s Office Chief Financial Officer Deputy City Manager & Chief Operations Officer Jill Hyndman ghyndman@regina.ca Corporate Services Group Strategy Management Branch Strategy & Operations Branch PSO Project Management Manual November

3 Operations Group Executive Director, City Services Executive Director, Planning & Development Executive Director, Transportation & Utilities Major Projects Department Strategy & Operations Branch Service Regina Branch Asset Management Branch Policy Support Branch Corporate Services Group Finance Facilities Management Legal Services Meghan McEachern Operations Group Assessment, Tax & Real Estate Planning Development Services Water Works Solid Waste City Manager s Office Communications Legal Services Ryley Slywka rslywka@regina.ca Corporate Services Group Fleet Services Human Resources Information Technology Operations Group Parks & Open Space Community Services Transit Services Fire & Protective Services Roadways & Transportation PSO Project Management Manual November

4 PSO Project Management Manual November

5 Table of Contents SECTION DEFINITIONS... 7 What is a project?... 7 What is Project Management?... 8 RATIONALE... 8 Why is the City of Regina promoting and supporting a culture of project management?... 8 PROJECT GOVERNANCE... 8 ROLES AND RESPONSIBILITIES Sponsor Project Manager Project Team Executive Lead Steering Committee Change Manager What governance does my project require? Role of the Project Support Office SECTION PROJECT MANAGEMENT PROCESS PROJECT PHASES AND TOOLS Phase 1: Initiation INITIATION WORKBOOK... Error! Bookmark not defined. SCOPE WORKSHOP ROLES AND RESPONSIBILITIES WORKSHEET RISK ASSESSMENT... Error! Bookmark not defined. STAKEHOLDER ASSESSMENT SECURITY/PRIVACY RISK QUICK ASSESSMENT PROJECT PROPSOSAL... Error! Bookmark not defined. INITIATION CHECKLIST... Error! Bookmark not defined. Phase 2: Planning PROJECT PLAN WORKBOOK PROJECT PLAN SCHEDULE/WORK BREAKDOWN STRUCTURE (WBS) PROJECT PLAN FINANCIAL PLAN PROJECT PLAN RESOURCE (PEOPLE) PLAN PROJECT PLAN RISK LOG/PLAN PROJECT PLAN STAKEHOLDER/COMMUNICATION MANAGEMENT PLAN(S) CHARTER PHASE REVIEW FORM... Error! Bookmark not defined. Phase 3: Execution PROJECT PLAN ISSUE LOG CHANGE ORDER AND LOG MEETING AGENDAS AND MINUTES PSO Project Management Manual November

6 STATUS REPORT PHASE REVIEW FORM... Error! Bookmark not defined. Phase 4: Close LESSONS LEARNED WORKSHOP CLOSE OUT REPORT PHASE REVIEW FORM... Error! Bookmark not defined. PSO Project Management Manual November

7 SECTION 1 DEFINITIONS What is a project? A project is a temporary piece of work that produces a unique or new product, service or result, within a specified budget, with clearly defined authorities. Characteristics that differentiate a project from day to day operations/business include: Projects are unique in nature. They may involve repetitive processes, but the outcome of the process is new. Every project is different from the last, whereas operational activities often entail undertaking repetitive processes with the same results each cycle. Projects have a defined time frame, with a clearly specified start and end date within which the deliverables must be produced to meet particular requirements. Projects have an approved (limited) budget of resources. At the start of a project an agreed amount of labour and money is allocated to carry out the deliverables of the project. Projects may involve an element of risk or uncertainty they often involve doing something the organization has never done before and therefore carry business risk. Projects achieve change, whether that is a new asset in the community such as a road or park; a new policy to guide decisions; or a new business process to streamline operations. Examples of types of work that are considered projects: Construction: build an asset, i.e., Stadium, WWTP, new park Policy/bylaw review or study: develop and implement a new policy/bylaw or conduct a study; i.e., OCP, Downtown Serviceability Study, Zoning Bylaw update Culture change: i.e., taking action on the Employee Survey results for a branch or department Process improvement: rolling out new technology to a branch, i.e., GPS for solid waste collection Program or service development: creating a new line of business for the community and launching it, i.e., Waste Plan Regina Projects Temporary Unique product or output No pre-assigned jobs The process must be created or modified Different inputs each time Not part of the permanent organizational structure (team members and governance)* Business Processes/Day to Day Work Permanent Repetitive product or output Jobs assigned The process is the same each time the business process is run Same inputs or supplies each time Part of permanent structure of organization PSO Project Management Manual November

8 *Although a project may use the existing organizational structure for governance see Project Governance, below. What is Project Management? Project management is the application of knowledge, skills, tools and processes to project activities to successfully deliver the project outcomes. to reduce the level of risk within a project, and improve its probability of success to monitor and control the schedule, budget, scope, resources, risk and outcomes of a project Project management methodologies offer various specialized tools and processes (and lingo!) for various industries and flavours of work. The organization is adopting a basic standard open source methodology that can be adapted to fit the business needs of various lines of business across the Group. RATIONALE Why is the City of Regina promoting and supporting a culture of project management? To build more effective project teams to deliver a range of project outcomes in our city To create consistency in terms of project management efforts across the organization To provide measures of project success and address opportunities to improve To allow divisions, departments and branches to make good choices around project management based on their needs To build project management capacity throughout the organization To reinforce the idea that leadership, ownership and accountability reside at all levels in the organization PROJECT GOVERNANCE Project governance simply means everyone is clear about who has the authority to make decisions about a project. Effective project governance requires clear roles and responsibilities for all parties involved in the project, clear decision and approval points, and clear processes to make decisions or get approvals. The City will use organizational structure-based governance for projects as much as possible. For example, a Director may be the project sponsor, a direct-report Manager may be the project manager, and the project team may all be direct reports of that Director or Manager. PSO Project Management Manual November

9 Sponsor (Director, Department A) Project Manager (Staff, Department A) Project Team (Staff from Department A) For more complex projects (i.e., those that involve resources from across several departments or divisions, or involve external stakeholders or partners), a governance structure may be established that is outside the organizational structure, such as a steering committee comprising Directors from several divisions and some external stakeholders, for example. Or, a project manager may report directly to a sponsor who is not part of their organizational structure hierarchy. Sponsor (Director, Department A) Sponsor (ED, Division A) Project Manager (Staff, Depart. B) Steering Committee (EDs and Directors, Divisions A, B, C) Project Team (Staff from Department A, B, C) Project Manager (Staff, Department C) Project Team (Staff from Departments A, B, C) In the Initiation and Planning phases of a project, the specific roles will be defined in the charter and project plan. In general, the following roles will be defined for most projects, but adapted PSO Project Management Manual November

10 to suit the needs of each project where necessary. These adaptations should be captured in the Resource (People) Plan in the Planning phase. ROLES AND RESPONSIBILITIES Sponsor The primary responsibility of the sponsor is to direct and champion the project to completion. The sponsor is the decision maker on behalf of the organization and ensures that the project aligns with Council, community and organizational goals. The sponsor has overall accountability for the project (i.e., their butt is on the line when things go not so well, and they take the credit when things go well). A sponsor can be at any level within the organization, however, they must have enough authority and influence to fulfill this role. Key functions of a sponsor: Leads the development of the project proposal, and directs and provides the content for the charter Approves the project proposal, charter, change orders, and project deliverables Approves resources (people and budget) required for the project and ensures they are committed for the duration of the project, either directly, or by securing resources from their colleagues across the organization Oversees and directs the work of the project manager and project team Actively and visibly promotes the project: is the face of the project and manages communication with all stakeholders Resolves issues that arise throughout the project Eliminates roadblocks that get in the way of project success Monitors and reviews progress by regularly reviewing status reports and deliverables with the project manager Holds the project team accountable for their work on the project Conducts Phase Reviews during each phase of the project Chairs the steering committee (if applicable) Project Manager The project manager, or PM, is responsible to deliver the project successfully. The PM manages the process to enable the project team to deliver the outcomes defined in the charter, while adhering to the scope, schedule and budget. Key functions of a PM: Coordinates the charter development with the sponsor Coordinates the project plan by working with the team to identify and schedule all the work required to fulfill the scope Tracks and manages the project plan, including schedule, scope, budget, and resources (people) assigned to the project, and manages the risk log, issue log and stakeholder/communication plan PSO Project Management Manual November

11 Creates and manages the project records and documentation Facilitates project team meetings Monitors and reports on the progress of the project using status reports Coordinates change orders when required Directs and manages external vendors for project deliverables Escalates issues and risks to the sponsor as required Project Team The project team includes business and technical staff (subject matter experts, or SMEs) with the required skills and knowledge to complete the work required to deliver the project. Key functions of a project team: Assist the PM to create the project plan by identifying tasks and effort required to complete deliverables Complete assigned projects tasks within agreed timelines and to agreed upon quality Identify risks, issues and roadblocks and communicate them to the project manager Actively participate in project meetings, and communicate relevant information to and from their home branch/department Executive Lead (when necessary) An executive lead is an optional role on a project. This role is usually fulfilled by a member of ELT (an Executive Director or Chief Officer) when the project will need to be presented to ELT and/or Council or any other Committee during its life. If a project doesn t need to be presented to ELT/Council, then an executive lead is not necessary. Key functions of an executive lead: Present the project to ELT and/or Council or other Committee, as required Support the sponsor and/or steering committee in their roles, and step in to remove barriers or make decisions when the sponsor requires an objective but informed third party Be the face of the project in public, if the project has high reputational or political risk Steering Committee (when necessary) The steering committee is responsible for the business issues associated with the project and for providing guidance and support to the sponsor, project manager and project team. The steering committee should consist of individuals who are representative of the business area(s) and have a direct, vested interest in realizing the project s deliverables and objectives. Participation is determined by the project sponsor. Key functions of a steering committee: Provides direction to the project in coordination with the sponsor, often representing the business needs/expertise of their home branch or department Commits the necessary resources to the project from their respective home branches/departments PSO Project Management Manual November

12 Approves decisions and deliverables of the project, as defined in the charter (requires clarity between sponsor s authority and steering committee s authority, i.e., does the sponsor have veto or tie-breaking power?) Resolves issues that arise throughout the project Eliminates roadblocks that get in the way of project success Monitors and reviews progress by regularly reviewing status reports and deliverables with the project manager and sponsor Change Manager (where necessary) For projects that will result in a change to employee s jobs, pay or duties, or create major changes or new ways of doing things with stakeholders, you may consider engaging a change manager. This function considers and plans for the impact of the project on people affected by the project outcomes. Key functions of a change manager: Conducts an organizational change readiness assessment Determines the scope and impact of change within and because of the project Advises on/recommends appropriate strategies to manage the change created through and by the project Supports the sponsor and PM in managing the change What governance does my project require? Some questions to consider when determining an appropriate project structure/governance include: Sponsor: Who is the appropriate sponsor for this project? What level of authority is required? Executive Lead: Does the project need to be presented to ELT and/or Council? Does this project carry a high level of reputational or political risk that may need to be spoken to in public? Steering Committee: Does this project require a steering committee? What value/benefit will they add? Is this a cross-divisional/departmental project? Does this project have high reputational or political risk? Project Manager: Who is an appropriate PM for this project? Do they require subject matter expertise, or would they be better suited with process expertise? Project Team: Who has a role to play in creating the deliverables of this project? What skills and functions are required to create the deliverables? Do these functions and skills exist within the organization? Are they available to work on the project? Do we need to hire external expertise? Change Manager: Does this project require a change manager or change management support? Will anyone s job change because of this project? Will anyone s pay or benefits change because PSO Project Management Manual November

13 of this project? Do we need to consider managing resistance, training people how to do their job differently, etc.? Other supports: What other support does this project require (i.e., financial reporting, legal review, etc.)? Are these functions within these staff s day to day work, or will these roles need to do something new/different on the project? Role of the Project Support Office The Project Support Office was created to support the implementation of project management processes across the organization. The PSO does these things We develop/define and document the project management process for OG We coach, advise, train, troubleshoot and support project teams We evaluate best practices, internally and externally We check in regularly with ELT and project participants We analyze and report on the City s evolving project management culture, including participation in training, use of tools and techniques, and emerging needs Why? To ensure role clarity for all participants To ensure understanding of basic expectations and tools for all projects To ensure the appropriate tools and techniques are applied to the appropriate projects (simple vs. complex) To help ensure your projects succeed To give the organization contemporary and evolving project management support To understand your changing needs and ensure we add value to your projects To identify successes and areas for more or different support The PSO does NOT: Manage projects we are not a project delivery office; we do not have project managers to run your projects for you! Approve projects to proceed (or decide they should not proceed) those decisions lie with management teams Police work units to ensure you are using project management tools the expectations for the use of project management processes and tools is established and managed by management teams, not the PSO PSO Project Management Manual November

14 SECTION 2 PROJECT MANAGEMENT PROCESS PSO Project Management Manual November

15 PROJECT PHASES AND TOOLS Phase 1: Initiation This phase is about the idea, problem or opportunity that is creating the potential project. In this phase, you should be thinking about: What problem are you trying to solve? What is the business need? What are the options? What is the urgency? How can you get this project supported/advanced? Who else needs to be involved in figuring this out? How does this align strategically to the OCP/Corporate Strategic Plan/my business plan? What are the high-level needs to do this work: money, time, people/governance, stakeholders, and risks? Summary: Use the initiation tools to develop the content for the Initiation Document, which is the approval document to move from Initiation to Planning Phase. PROJECT START-UP WORKSHOP (optional) To define the project in order to complete the Initiation Document: o What problem will the project solve/opportunity will the project take advantage of? o What is the rationale for this project? o Who might need to be involved? Who might be impacted? o What risks exist if the City doesn t pursue this project? What risks emerge by pursuing this project? o Is the organization ready to pursue this project? Initiated/Completed/Led by: Sponsor or project initiator/pso A workshop can be facilitated by the PSO or the business owner to determine the initial definition of the proposed project. A facilitation guide is available from the PSO. This type of workshop can be tailored to cover any or all components of the Initiation Document. PSO Project Management Manual November

16 INITIATION CHECKLIST (recommended) To both plan for at the beginning and review at the end of the Initiation Phase to ensure all aspects of the project have been considered Completed/Facilitated by: Sponsor, with input from PM and others. SPONSOR INITIATION CHECKLIST (recommended) A list of key questions for a potential sponsor to consider at the front-end of establishing a potential project Completed by: Sponsor (or potential sponsor) ROLES AND RESPONSIBILITIES WORKSHEET (recommended) To determine the appropriate governance for the project, and begin to identify the resources (people) needed to deliver the project (functions, skills, expertise) What authority is needed to advance the project? Is there a sponsor who can get the project done and does that sponsor have the capacity to sponsor the project? Is the expertise available to get the project done? Completed by: Sponsor, PM or project initiator The information captured in the document will inform the Project Initiation Document and the future Charter. STAKEHOLDER IDENTIFICATION WORKSHEET (recommended) To identify individuals and groups impacted by the project Asks: Who needs to have input to the design of the project? Asks: Who is impacted during project execution? Asks: Who is impacted by the outcome and/or outputs? Ask: How should they be involved? Initiated/Completed by: Sponsor, PM or project initiator The information captured in the document will inform the Project Initiation Document, the Charter, the Change Management Plan, the Stakeholder Management Plan, and the Communications Plan. PSO Project Management Manual November

17 PROJECT INITIATION DOCUMENT (required) To gain approval to proceed with project planning Should have enough information/detail for the sponsor to make a business decision Identify business problem or opportunity Recommend a preferred solution that aligns to organizational direction Identify any risks, issues and business impacts To identify risks associated with the project: o Risks that exist by doing the project o Risks that exist by not doing the project Provides information to make a call on whether the benefits of the project outweigh the risks can we live with the risks if we proceed? Assesses the readiness of the organization to move forward with this project. Initiated/Completed by: Sponsor, PM (if assigned), project initiator or staff (as assigned) Approval: Sponsor (and/or) Executive Lead The information captured in the document will inform the Charter, Risk Management Plan and Risk Management Log. PSO Project Management Manual November

18 Phase 2: Planning This phase is about: Defining what the project is, will be, and what s involved to deliver it Defining the triple constraints and prioritizing them (time, cost, scope) Planning the work Elaborating on the Initiation Document to ensure appropriate consideration of constraints and agreement on the path forward PROJECT PLAN WORKBOOK (recommended) The Project Plan provides the PM with a roadmap; it becomes the how-to document to guide and manage the project. Developing a Project Plans helps to define the details behind various project components including scope, schedule, budget, risks, stakeholders and communications requirements. There are a number of tools that can help generate the content of both the Project Plan, and ultimately the Charter. PROJECT PLAN SCHEDULE/WORK BREAKDOWN STRUCTURE (WBS) (recommended) To develop a schedule and task plan for the project Identify major milestones and key dates Identify major categories of tasks, and sub-tasks Identify dependencies between tasks and associated timing Informs or validates the Schedule estimate made in Initiation Phase Informs or validates Budget estimates Informs or validates Resource estimates. Clarify roles and responsibilities in terms of task and deliverables Completed/Managed by: PM with input from Project Team PROJECT PLAN FINANCIAL PLAN (recommended) To develop the budget to deliver the project Align budget with tasks, milestones and deliverables To identify funding sources Completed/Managed by: PM, with input from team members and subject matter experts PSO Project Management Manual November

19 PROJECT PLAN RESOURCE (PEOPLE) PLAN (recommended) To identify the specific functions/skills/expertise required to deliver the project, and determine the amount of time and effort those resources will need to contribute Determine candidates that could fill the roles Identify the capacity required of the individuals Completed/Managed by: PM, with resource commitment coordinated by Sponsor PROJECT PLAN RISK LOG/PLAN (recommended) To identify risks and strategies to deal with those risks throughout the project development and execution Categorize and prioritize each potential risk Determine the likelihood of the risks Determine the impact on the risk Identify preventive actions or contingency to reduce risk Set controls to monitor the status of each risk throughout the project Completed/Managed by: PM, with input from Sponsor, Project Team PROJECT PLAN STAKEHOLDER/COMMUNICATION MANAGEMENT PLAN(S) (recommended) To identify a plan to manage stakeholder expectations and communicate with project stakeholders throughout the life of the project Depending on the project, could be a single plan, or split into two separate plans (communications and stakeholder) Identify each stakeholder and audience Determine appropriate communications events and tactics Determine the method and frequency of each communication channel Determine resources to be allocated to the communication process Determine measures of successful stakeholder management and communications strategies Completed/Managed by: PM, Sponsor, Change Manager, Communications Lead/Support CHARTER (required) Creates the baseline against which the project is measured (scope, schedule, budget, resources and deliverables) PSO Project Management Manual November

20 o Anything that changes must use a Change Order; the Charter is NOT updated with changes; change order or the change log is attached for reference of any changes to scope, schedule, budget, resources. Captures the project outcome and objectives Defines the complete scope and schedule of the project Lists all of the critical project deliverables Lists the key roles and their responsibilities in governance/project delivery Outlines the overall implementation plan Identifies costs, contingencies and human resource requirements Identifies high-level risks and management plan Lists the assumptions and constraints of the project Can be thought of as the executive summary of the project plan Assigns authority to the Project Manager, Steering Committee (if applicable), Project Team Once signed, is the official approval for the project to be executed Completed by: PM Approved by: Sponsor; (Executive Lead, Steering Committee if applicable) Key Terms in the Charter: Assumptions are statements which are assumed to be true for the sake of project planning. Constraints are statements which are assumed to be certain, and which influences the manner in which the project can be conducted. Constraint Prioritization is used to prioritize between the three sides of the project triangle (scope, schedule, and cost) and establish limits where appropriate. It is important to understand and document the least flexible to the most flexible. For example: Project If budget is finite and cannot be changed, regardless of what happens on Scope the project, it is least flexible. If the project doesn t have any external dependencies on the schedule, and therefore the schedule could be expanded or contracted as needed throughout the project, then the schedule is most flexible. Schedule Cost PSO Project Management Manual November

21 Phase 3: Execution (Monitoring and Control) This phase is about: Doing the work to build/create/produce the deliverables Managing scope, budget, schedule and people Managing stakeholders and communicating with impacted and interested parties Addressing issues and managing risk Implementing change management preparing and guiding people impacted by the project through a process to mitigate resistance and improve acceptance at the end of the project This phase involves the execution of each activity and task listed in the Project Plan, and tracking decisions, issues, risks and other milestones to form the official project history. PROJECT PLAN (recommended) To ensure the project is delivered according to plan and adjustments are made as appropriate and documented properly A project plan details how the project will be delivered. The documents that comprise the project plan are to be used to both plan the project prior to receiving approval to begin the work (i.e., build the deliverables), and to manage the project throughout the execution of the project. The project plan can be treated as the overall work plan for the project. All the tabs in the Project Plan Workbook should be used during Execution to run the project, including: Schedule/Work Breakdown Structure Resource (People) Plan Financial Plan Stakeholder Management Plan Communication Plan Risk Log/Plan As well as two new tabs, Issue Log and Change Order Log, as identified below. Managed by: PM, and Project Team members as assigned ISSUE LOG (recommended) To identify issues that arise during the project and create and manage plans to address them Risks that actually happen are issues. PSO Project Management Manual November

22 Managed by: PM, with input from Project Team and Sponsor CHANGE ORDER AND LOG (required) To document the need for a change to scope, schedule, budget or people required to deliver the project, and gain approval to make that change Uses the Charter as baseline; the Change Log and Orders become records of approvals to change original scope, schedule, budget or people allocated to the project Completed/Managed by: PM, with input from Project Team and approval by Sponsor MEETING AGENDAS AND MINUTES (recommended) To plan and document meetings that occur throughout the project, including decisions and actions that inform the schedule/wbs, risk log, issue log, and change orders Completed by: PM or other project support as assigned STATUS REPORTING AND AUTOMATED DASHBOARD (required) Enables PM to relay the need for intervention by the sponsor Tracks progress on the project May feed into a branch, department, division, group or corporate dashboard Completed by: PM Reviewed by: Sponsor; (and Steering Committee, Executive Lead if applicable) PSO Project Management Manual November

23 Phase 4: Close This phase is about: Ensuring the deliverables meet the requirements/objectives/outcomes of the project Evaluating the delivery of the project within the constraints Identifying any additional actions that need to be taken Transferring ownership: project outputs become integrated as BAU Closing out contracts with suppliers and contractors Discussing and documenting lessons learned to be applied to future projects Celebrating successes Once all of the deliverables have been accepted the project is ready for closure. This phase involves discharging the final deliverables, handing over project documentation, terminating supplier contracts, releasing project resources and communicating the closure of the project to all stakeholders. A project is officially finished, or closed, one the Close Out Report is signed by the Sponsor (and Steering Committee, if appropriate). LESSONS LEARNED WORKSHOP (recommended) A group exercise to review what worked well on the project and what could have gone better, and to identify any lessons that can be applied to future projects to avoid similar challenges Outputs are captured in the Close Out Report FUTURE: PSO will develop a process for sharing lessons learned across and between projects Facilitated by: Sponsor, PM or PSO CLOSE OUT REPORT (required) Sign-off signals the official close of a project Completed by: PM, with input from Project Team Approved by: Sponsor PSO Project Management Manual November

Who Should be on Your Project Team: The Importance of Project Roles and Responsibilities

Who Should be on Your Project Team: The Importance of Project Roles and Responsibilities Who Should be on Your Project Team: The Importance of Project s and One significant factor contributing to the success of projects is having the right people engaged in the process. Who are the right stakeholders

More information

Introduction to PM². Laurent Kummer COEPM² Team

Introduction to PM². Laurent Kummer COEPM² Team Introduction to PM² laurent.kummer@ext.ec.europa.eu Laurent Kummer COEPM² Team Course Agenda Introduction & context Governance model Project lifecycle Processes & Artefacts Mindsets 2 Laurent Kummer PM²

More information

Enterprise Data Strategy and Governance

Enterprise Data Strategy and Governance Project Charter DATE: 9/20/2017 VERSION 1.0 Prepared By: Melany Leavitt and Paul Given Page 1 Document Revision History Version Number Date Description.01 5/25/2017 Draft Charter.02 9/1/2017 Draft for

More information

Guidance on project management

Guidance on project management BSI Standards Publication NO COPYING WITHOUT BSI PERMISSION EXCEPT AS PERMITTED BY COPYRIGHT LAW raising standards worldwide Guidance on project management BRITISH STANDARD National foreword This British

More information

Project Charter. A. General Information

Project Charter. A. General Information A. General Information Project Title: Brief Project Description: Prepared By: Date: Version: B. Project Objective: Explain the specific objectives of the project. For example: What value does this project

More information

OE PROJECT CHARTER PROJECT NAME: PREPARED BY: PROJECT CHARTER VERSION HISTORY VERSION DATE

OE PROJECT CHARTER PROJECT NAME: PREPARED BY: PROJECT CHARTER VERSION HISTORY VERSION DATE PROJECT : PREPARED BY: Josh Blatt DATE (MM/DD/YYYY): 1/9/2012 Institutional Data Council Project Manager PROJECT CHARTER VERSION HISTORY VERSION DATE COMMENTS (DRAFT, SIGNED, REVISED CURRENT STATUS) (MM/DD/YYYY)

More information

Chapter One PROJECT MANAGEMENT OVERVIEW

Chapter One PROJECT MANAGEMENT OVERVIEW Chapter One PROJECT MANAGEMENT OVERVIEW Project management itself is not a new concept. It has been practiced for hundreds, even thousands of years. Any large undertaking requires a set of objectives,

More information

Project Management Basics: Patsy Writesman,

Project Management Basics: Patsy Writesman, Project Management Basics: Patsy Writesman, 615.310.7003 Understanding the Context.. What is a Project? A Project is. A temporary endeavor undertaken to create a unique product or service. This term temporary

More information

Information Technology Services Project Management Office Operations Guide

Information Technology Services Project Management Office Operations Guide Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...

More information

Project Management Proposal

Project Management Proposal Project Management Proposal INTRODUCTION Managing Government Projects can often be challenging. You typically need to manage internal staff, external suppliers, contractors, equipment and materials - while

More information

PROJECT MANAGEMENT OVERVIEW

PROJECT MANAGEMENT OVERVIEW Chapter One PROJECT MANAGEMENT OVERVIEW Project management itself is not a new concept. It has been practiced for hundreds, even thousands of years. Any large undertaking requires a set of objectives,

More information

RESCUING A TROUBLED PROJECT

RESCUING A TROUBLED PROJECT RESCUING A TROUBLED PROJECT INTRODUCTION Most endeavors, business or personal, are bound to face challenges at one point or another. The introduction of a new product may encounter problems while manufacturing

More information

FLORIDA DEPARTMENT OF JUVENILE JUSTICE PROCEDURE. Title: Information Technology (IT) Project Management and Governance Procedures

FLORIDA DEPARTMENT OF JUVENILE JUSTICE PROCEDURE. Title: Information Technology (IT) Project Management and Governance Procedures PROCEDURE Title: Information Technology (IT) Project Management and Governance Procedures Related Policy: FDJJ 1270 I. DEFINITIONS Agency for State Technology (AST) Rule Rules 74-1.001 through 74-1.009,

More information

Project Management Overview 4/17/2013 1

Project Management Overview 4/17/2013 1 Project Management Overview 4/17/2013 1 Without Project Management 4/17/2013 2 Without Project Management 4/17/2013 3 What is a Project? A temporary and one-time endeavor undertaken to create a unique

More information

STRATEGIC PLANNING: IMPLEMENTATION ROADMAP

STRATEGIC PLANNING: IMPLEMENTATION ROADMAP STRATEGIC PLANNING: IMPLEMENTATION ROADMAP MOVING FROM THE STRATEGIC PLAN TO AN OPERATIONAL PLAN Strategic plans provide broad guidance and direction for a higher education institution s immediate future.

More information

Manitoba Health, Seniors and Active Living Transformation Program Charter. February 16, 2018 Version 1.0

Manitoba Health, Seniors and Active Living Transformation Program Charter. February 16, 2018 Version 1.0 Manitoba Health, Seniors and Active Living Transformation Program Charter February 16, 2018 Version 1.0 Table of Contents 1 Purpose... 3 2 Background... 3 3 Scope of the Transformation Program... 5 3.1

More information

AGENCY FOR STATE TECHNOLOGY

AGENCY FOR STATE TECHNOLOGY AGENCY FOR STATE TECHNOLOGY PROJECT RISK & COMPLEXITY ASSESSMENT TOOL Risk & Complexity Assessment Model for State Information Technology Projects Purpose: In order to determine the level of risk associated

More information

Value of Failure! Students Course! Module 4: Preventing Failure!

Value of Failure! Students Course! Module 4: Preventing Failure! Value of Failure Students Course Content 1. Project Management 2. Basics of risk management Project: The black box of project management Project Idea Project Management Completion / Operation Project management

More information

ITS PROJECT MANAGEMENT FRAMEWORK

ITS PROJECT MANAGEMENT FRAMEWORK ITS PROJECT MANAGEMENT FRAMEWORK This document provides an overview of the Project Management Framework for University of Maine System (UMS) Information Technology projects. The framework provides a standardized

More information

THE STANDARD FOR PROGRAM MANAGEMENT

THE STANDARD FOR PROGRAM MANAGEMENT THE STANDARD FOR PROGRAM MANAGEMENT COURSE STRUCTURE INTRODUCTION Module 1 PROGRAM MANAGEMENT PERFORMANCE DOMAINS Module 2 PROGRAM STRATEGY ALIGNMENT Module 3 PROGRAM BENEFITS MANAGEMENT Module 4 COURSE

More information

Project Management Handbook

Project Management Handbook Project Management Handbook Version 0.1 September 2011 1 CONTENTS Introduction 3 The Project Lifecycle 3 Aspyre 4 Project or Programme 5 Project Management 6 Phase 1 Prepare 7 Project Brief 7 Business

More information

Define and Initiate SubPhase

Define and Initiate SubPhase Project Management Methodology Project Management Methodology Training Define and Initiate SubPhase Course Purpose Familiarize team members with the Start Project Sub-Phase processes. Understand process

More information

Software Project & Risk Management Courses Offered by The Westfall Team

Software Project & Risk Management Courses Offered by The Westfall Team Software Project & Risk Management is a 5-day course designed to provide a knowledge base and practical skills for anyone interested in implementing or improving Software Project and Risk Management techniques

More information

the council initiative on public engagement

the council initiative on public engagement public engagement at the city of edmonton share your voice shape our city the council initiative on public engagement new public engagement practice and implementation roadmap final report CITY OF EDMONTON

More information

Establishing a Program Management Office

Establishing a Program Management Office Establishing a Program Management Office Agenda Why companies need Program Management 3 Objectives of Program Management 4 Program and Project Management definitions 5 Program Management infrastructure

More information

How To Manage a Troubled Project GTC Center for Project Management, All Rights Reserved

How To Manage a Troubled Project GTC Center for Project Management, All Rights Reserved How To Manage a Troubled Project GTC 2007 1 How To Manage a Troubled Project 2 Logistics Start and finish Breaks and lunch Morning: one 15-minute break Lunch: 60 minutes Afternoon: one 15-minute break

More information

CHP 1: AN OVERVIEW OF IT PROJECT MANAGEMENT

CHP 1: AN OVERVIEW OF IT PROJECT MANAGEMENT 1 CHP 1: AN OVERVIEW OF IT PROJECT MANAGEMENT Slides by: Ms. Shree Jaswal TOPICS TO BE COVERED Introduction The state of IT project management Context of project management Need of project management Project

More information

Project Management for Non-Profits What s in it for you? Benefits of Improved Project Management (PM) Skills, Techniques and Processes.

Project Management for Non-Profits What s in it for you? Benefits of Improved Project Management (PM) Skills, Techniques and Processes. Project Management for Non-Profits What s in it for you? Benefits of Improved Project Management (PM) Skills, Techniques and Processes Nov 2014 1 Overview What is a project? Impact on organizational results

More information

Guidance Note: Corporate Governance - Audit Committee. January Ce document est aussi disponible en français.

Guidance Note: Corporate Governance - Audit Committee. January Ce document est aussi disponible en français. Guidance Note: Corporate Governance - Audit Committee January 2018 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance Audit Committee (the Guidance Note

More information

Five Guiding Principles of a Successful Center of Excellence

Five Guiding Principles of a Successful Center of Excellence Five Guiding Principles of a Successful Center of Excellence What is a Center of Excellence? At some point in their life cycle, most companies find it beneficial to develop a Center of Excellence (CoE).

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Management 1 Project Management Develop Project Charter Develop Project Management Plan Monitor and Control Perform Integrated Change Control Close Project or Phase

More information

Supply Chain Specialist

Supply Chain Specialist Role Title Job Family Supply Chain Specialist Supply Chain Competency Level Pay Range / Scale Principal Officer/Manager PO6 Purpose To support the council s category management approach to procurement

More information

Guidance on portfolio, programme and project management

Guidance on portfolio, programme and project management Guidance on portfolio, programme and project management The Standard for Infrastructure Procurement and Delivery Management (SIPDM) defines the following two generic terms: Portfolio: collection of projects

More information

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan M3 Playbook Guidance Phase 1: Readiness This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration

More information

Project Portfolio Management Assessment

Project Portfolio Management Assessment Management Assessment PREPARED FOR: Ross Little, IAG DIAGNOSTIC PROGRAM POWERED BY INFO-TECH RESEARCH GROUP January 13th, 2017 Powered by: Data is comprised of feedback from 2 respondents, including: James

More information

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Introduction Context Agenda Introduction to Methodologies What is a Methodology? Benefits of an Effective Methodology Methodology

More information

PPM Assessment. Analyze Your PPM Practices In-Depth for Systematic Improvement

PPM Assessment. Analyze Your PPM Practices In-Depth for Systematic Improvement Assessment Analyze Your Practices In-Depth for Systematic Improvement Your Journey Starts Here. Understand Your Strengths & Weaknesses Evaluate Performance and Required Next Steps by Area Build a Improvement

More information

RTI Release. Project Management Plan. Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning

RTI Release. Project Management Plan. Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning 1 Project Management Plan Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning SOUTH WEST CORRIDOR STUDY (OXLEY ROAD) PROJECT OWNER: GRAEME READ 2 Document Change History

More information

Darryl Vleeming June 13, 2012

Darryl Vleeming June 13, 2012 Darryl Vleeming June 13, 2012 darryl@chasmconsulting.ca Projects are: Temporary in nature (have a start and finish) Create a unique product, service or result Operations are: On-going and repetitive No

More information

THE PMO AND PROJECT MANAGEMENT CHRIS DOWHOWER, PROJECT MANAGEMENT DIRECTOR, PMP, VIZO FINANCIAL

THE PMO AND PROJECT MANAGEMENT CHRIS DOWHOWER, PROJECT MANAGEMENT DIRECTOR, PMP, VIZO FINANCIAL THE PMO AND PROJECT MANAGEMENT WHY, WHAT & HOW? CHRIS DOWHOWER, PROJECT MANAGEMENT DIRECTOR, PMP, VIZO FINANCIAL CONNECT WITH US Objectives What is a project? What does it look like today? Project Management

More information

S O Seminar Objective

S O Seminar Objective Introduction to Project Management Welcome! Presenter: Bob Hull CalACT Conference September 202 S O Seminar Objective To provide an overview of project management processes and provide some skills, tools

More information

Overview: Status Reports/Dashboards provide program leadership and governance with updates on program progress, and strategic program risks/issues.

Overview: Status Reports/Dashboards provide program leadership and governance with updates on program progress, and strategic program risks/issues. M3 Playbook Guidance Phase 4: Migration This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration

More information

CORROSION MANAGEMENT MATURITY MODEL

CORROSION MANAGEMENT MATURITY MODEL CORROSION MANAGEMENT MATURITY MODEL CMMM Model Definition AUTHOR Jeff Varney Executive Director APQC Page 1 of 35 TABLE OF CONTENTS OVERVIEW... 5 I. INTRODUCTION... 6 1.1 The Need... 6 1.2 The Corrosion

More information

Programme Manager - Strategic Initiatives

Programme Manager - Strategic Initiatives Programme Manager - Strategic Initiatives Location: [Global] Category: Project Management *Position location to be determined by home country of successful candidate in a jurisdiction (country of US state)

More information

Meltem Özturan

Meltem Özturan Meltem Özturan www.mis.boun.edu.tr/ozturan/samd 1 1 Introduction Project Initiation Project Planning, Execution & Control - SDLC Project Closing What is Project?... a temporary endeavour undertaken to

More information

Project Planning & Scheduling

Project Planning & Scheduling Project Planning & Scheduling 2 Objectives To introduce and discuss key concepts and techniques for planning and scheduling major projects To provide ideas for development of a practice session to apply

More information

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room. APM Project Fundamentals Qualification Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use

More information

The Agile PMP Teaching an Old Dog New Tricks

The Agile PMP Teaching an Old Dog New Tricks The Agile PMP Teaching an Old Dog New Tricks Why are we here today? What is Project Management? When will the project be done? How much will it cost? Do we all agree on what done looks like? What are the

More information

Project Management Session 6.2. Project Initiation Phase Integration Management

Project Management Session 6.2. Project Initiation Phase Integration Management Project Management Session 6.2 Project Initiation Phase Integration Management 1 Project Phases & Knowledge Areas 1. Integration 2. Scope Management 3. Time Management 4. Cost Management 5. Quality Management

More information

RESEARCH SUPPORT SERVICES FRAMEWORK. Streamlining the management and governance of R&D studies in the NHS

RESEARCH SUPPORT SERVICES FRAMEWORK. Streamlining the management and governance of R&D studies in the NHS RESEARCH SUPPORT SERVICES FRAMEWORK Streamlining the management and governance of R&D studies in the NHS Page 1 of 22 Contents 1. INTRODUCTION... 3 How to use this document... 3 Background... 4 Purpose

More information

5 DIMENSIONS OF CHANGE MANAGEMENT AND PROJECT MANAGEMENT INTEGRATION

5 DIMENSIONS OF CHANGE MANAGEMENT AND PROJECT MANAGEMENT INTEGRATION THOUGHT LEADERSHIP ARTICLE 5 DIMENSIONS OF CHANGE MANAGEMENT AND PROJECT MANAGEMENT INTEGRATION The disciplines of change management and project management understandably cross paths throughout the execution

More information

Foundation Sample Paper 1

Foundation Sample Paper 1 MSP Foundation and Practitioner training ACADEMY Foundation Sample Paper 1 Copyright exists in all of this material. Copying of any kind is not permitted. D a r e t o C h a l l e n g e Page 259 Quint Wellington

More information

An Example Portfolio Management Process

An Example Portfolio Management Process BEST PRACTICES WHITE PAPER An Example Portfolio Management Process Jenny Stuart, Vice President of Consulting, Construx Software Version 1, June 2009 Contributors Jerry Deville, Professional Software Engineer

More information

Identification Selection Definition Execution. Schedule.

Identification Selection Definition Execution. Schedule. SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification

More information

Strategy Analysis. Chapter Study Group Learning Materials

Strategy Analysis. Chapter Study Group Learning Materials Chapter Study Group Learning Materials 2015, International Institute of Business Analysis (IIBA ). Permission is granted to IIBA Chapters to use and modify this content to support chapter activities. All

More information

PROJECT MANAGEMENT METHODOLOGY

PROJECT MANAGEMENT METHODOLOGY Put your logo here Put your organization name here Project Management Methodology Rev. 3.0, 4/15/2008 PROJECT MANAGEMENT METHODOLOGY Your organization logo here Your organization name

More information

Topic for today: From tactical to strategic the journey of a PMO

Topic for today: From tactical to strategic the journey of a PMO Topic for today: From tactical to strategic the journey of a PMO The Start-up PMO Structure Chief Executive Officer Director: Strategy Group Executive: Strategic Projects Project Administrator Portfolio

More information

Project Management Casey Lucius, Ph.D. Oct 16, 2017 AGENDA. Introductions 8/31/2017

Project Management Casey Lucius, Ph.D. Oct 16, 2017 AGENDA. Introductions 8/31/2017 Project Management Casey Lucius, Ph.D. Oct 16, 2017 AGENDA 8:00 8:50 Goals, key concepts, five process groups, nine knowledge areas 8:50 9:00 Break/questions 9:00 9:50 Initiating & Planning the project

More information

DOWNLOAD PDF STAGES OF PROJECT MANAGEMENT LIFE CYCLE

DOWNLOAD PDF STAGES OF PROJECT MANAGEMENT LIFE CYCLE Chapter 1 : The Project Life Cycle - Understanding the 5 Stages of Project Management in Construction The Five Steps in the PM Life Cycle No matter what project it is that you're preparing for, the project

More information

Programme & Project Planning and Execution

Programme & Project Planning and Execution Portfolio, LEADING THE WAY IN PROJECTS Programme & Project Planning and Execution Caravel Group - Project Management with a total focus on value THE SPECIALIST FOR LARGE COMPLEX MULTI-DISCIPLINED PROJECTS

More information

Managing Troubled Projects. Mr. Anthony Eve, MAPM, PMP, PRINCE2 Practitioner

Managing Troubled Projects. Mr. Anthony Eve, MAPM, PMP, PRINCE2 Practitioner Managing Troubled Projects Mr. Anthony Eve, MAPM, PMP, PRINCE2 Practitioner Anthony Eve, PMP, MAPM, PRINCE2 PRACTITIONER Senior Partner and VP BMC Consulting ENGINEERING Agenda The Issues Structure and

More information

Information Technology Audit & Cyber Security

Information Technology Audit & Cyber Security Information Technology Audit & Cyber Security Managing Information System Projects Systems & Infrastructure Lifecycle Management Introduction Definitions INTRODUCTION Governance Roles and Responsibilities

More information

Continuous Improvement Toolkit. Risk Analysis. Continuous Improvement Toolkit.

Continuous Improvement Toolkit. Risk Analysis. Continuous Improvement Toolkit. Continuous Improvement Toolkit Risk Analysis The Continuous Improvement Map Managing Risk FMEA Understanding Performance Check Sheets Data Collection PDPC RAID Log* Risk Analysis* Fault Tree Analysis Traffic

More information

OE Project Charter Template

OE Project Charter Template Project Charter EMI Outreach April 12, 2011 OE Project Charter Template Project Name: Energy Management Office Prepared by: Sara Shirazi Date (MM/DD/YYYY): August 1, 2011 Project Charter Version History:

More information

Requirements Analysis and Design Definition. Chapter Study Group Learning Materials

Requirements Analysis and Design Definition. Chapter Study Group Learning Materials Requirements Analysis and Design Definition Chapter Study Group Learning Materials 2015, International Institute of Business Analysis (IIBA ). Permission is granted to IIBA Chapters to use and modify this

More information

Project Manager s Roadmap We re all smarter together

Project Manager s Roadmap We re all smarter together Version 7.0a Project Manager s Roadmap We re all smarter together Think Top Down! Methodology Checklists Define Plan Execute Close Conflict Resolution Modes Contract Outsource Management Mentoring References

More information

DIRECTOR OF FINANCE/CFO

DIRECTOR OF FINANCE/CFO With a west coast climate, spectacular scenery and year-round recreational offerings at our doorstep, the City of Campbell River is an ideal location to live, work, and play. DIRECTOR OF FINANCE/CFO We

More information

University of St Andrews Financial Operating Procedure Management of Business Transformation Initiatives

University of St Andrews Financial Operating Procedure Management of Business Transformation Initiatives University of St Andrews Financial Operating Procedure Management of Business Transformation Initiatives Updated: October 2017 1. Introduction This procedure exists to ensure operational adherence with

More information

Table of Contents. INTRODUCTION... 5 Overview... 5 Purpose... 5 Project Sizing Guidelines... 6 Document Organization... 6

Table of Contents. INTRODUCTION... 5 Overview... 5 Purpose... 5 Project Sizing Guidelines... 6 Document Organization... 6 Table of Contents INTRODUCTION... 5 Overview... 5 Purpose... 5 Project Sizing Guidelines... 6 Document Organization... 6 PROJECT INITIATING... 8 Project Initiating Considerations... 9 IT Governance at

More information

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Integration Management: processes & activities needed to properly coordinate all aspects of the project to meet stakeholder

More information

CMMI Project Management Refresher Training

CMMI Project Management Refresher Training CMMI Project Management Refresher Training Classifica(on 2: Foxhole Technology Employees Only RMD 032 Project Management Refresher Training Course September 21, 2017 Version 1.0 The Process Approach The

More information

Guidance Note: Corporate Governance - Audit Committee. March Ce document est aussi disponible en français.

Guidance Note: Corporate Governance - Audit Committee. March Ce document est aussi disponible en français. Guidance Note: Corporate Governance - Audit Committee March 2015 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance Audit Committee (the Guidance Note )

More information

The Sector Skills Council for the Financial Services Industry. National Occupational Standards. Risk Management for the Financial Sector

The Sector Skills Council for the Financial Services Industry. National Occupational Standards. Risk Management for the Financial Sector The Sector Skills Council for the Financial Services Industry National Occupational Standards Risk Management for the Financial Sector Final version approved April 2009 IMPORTANT NOTES These National Occupational

More information

Cascading change throughout an organisation

Cascading change throughout an organisation Cascading change throughout an organisation Author Melanie Franklin Director Agile Change Management Limited Introduction Organisations all over the world are experiencing high volumes of change as a result

More information

ERP IMPLEMENTAITONS: DOING IT RIGHT THE 2 ND TIME

ERP IMPLEMENTAITONS: DOING IT RIGHT THE 2 ND TIME ERP IMPLEMENTAITONS: DOING IT RIGHT THE 2 ND TIME INTRODUCTION ERP implementations are hard. They are complex systems with many moving parts, that require an organization s focus in order to be completed

More information

COMM 391. Learning Objective 1. Learning Objectives. Introduction to Management Information Systems

COMM 391. Learning Objective 1. Learning Objectives. Introduction to Management Information Systems COMM 391 Introduction to Management Information Systems INFORMATION SYSTEMS SOURCING AND PROJECT MANAGEMENT Winter 2014 Term 1 Learning Objectives 1. Explain the basic concepts of IS projects. 2. Describe

More information

Internal Policy. Policy Title: Applies to: Reference #

Internal Policy. Policy Title: Applies to: Reference # Page 1 of 5 Internal Policy Policy Title: Applies to: Reference # All City employees ###-XXX-## Approved by: Dates: Total # of Pages Effective: 01-JUL-2017 Executive Director, Transportation & Last Review:

More information

Appendix Project Management Templates

Appendix Project Management Templates Appendix Project Management Templates This book contains a bonus CD-ROM with 25 project management templates, described in the following table, that cover various project management steps from the TenStep

More information

Child Welfare Services New System Project. Requirements Management Plan

Child Welfare Services New System Project. Requirements Management Plan Child Welfare Services New System Project Requirements Management Plan September 2017 Revision History REVISION HISTORY REVISION/VERSION # DATE OF RELEASE AUTHOR SUMMARY OF CHANGES Version 1.0 October

More information

Leading Practice: Approaches to Organizational Change Management

Leading Practice: Approaches to Organizational Change Management Leading Practice: Approaches to Organizational Change Management Abstract This document provides recommended approaches to organizational change management (OCM) when implementing CA Project and Portfolio

More information

Achieving Organisational Goals. Accomplishing Strategic Initiatives. Implementation of Organisational Objectives. Stakeholder Management

Achieving Organisational Goals. Accomplishing Strategic Initiatives. Implementation of Organisational Objectives. Stakeholder Management Achieving Organisational Goals Accomplishing Strategic Initiatives Implementation of Organisational Objectives High Quality Training Courses presented by Internationally Recognised Expert Speakers Stakeholder

More information

TOOL 8.1. HR Transformation Milestones Checklist. The RBL Group 3521 N. University Ave, Ste. 100 Provo, UT

TOOL 8.1. HR Transformation Milestones Checklist. The RBL Group 3521 N. University Ave, Ste. 100 Provo, UT HR TOOL 8.1 HR Transformation Milestones Checklist The RBL Group 3521 N. University Ave, Ste. 100 Provo, UT 84604 801.373.4238 www.hrtransformation.com TOOL 8.1 HR Transformation Milestones Checklist In

More information

CITIBANK N.A JORDAN. Governance and Management of Information and Related Technologies Guide

CITIBANK N.A JORDAN. Governance and Management of Information and Related Technologies Guide CITIBANK N.A JORDAN Governance and Management of Information and Related Technologies Guide 2018 Table of Contents 1. OVERVIEW... 2 2. Governance of Enterprise IT... 3 3. Principles of Governance of Enterprise

More information

Project Management Concepts, Tools & Techniques

Project Management Concepts, Tools & Techniques Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid

More information

PROJECT EXECUTION PLANNING FOR COST AND SCHEDULE MANAGERS

PROJECT EXECUTION PLANNING FOR COST AND SCHEDULE MANAGERS PROJECT EXECUTION PLANNING FOR COST AND SCHEDULE MANAGERS ALLEN C. HAMILTON PMP CCE Project Management Associates LLC 3 Totten Way, Suite 110 Morris Plains, New Jersey 07950 USA Telephone: +1 973 984-1853

More information

Finance Division Strategic Plan

Finance Division Strategic Plan Finance Division Strategic Plan 2018 2022 Introduction Finance Division The Finance Division of Carnegie Mellon University (CMU) provides financial management, enterprise planning and stewardship in support

More information

Key Roles in Successful Teams

Key Roles in Successful Teams Key Roles in Successful Teams General Manager Coach Assistant Coach Trainer Team Captain KEY ROLES IN A PROFESSIONAL SPORTS TEAM Executive Sponsor Primary Executive Stakeholder Program Owner Domo Master

More information

GUIDE TO THE CHANGES IN PMP simpl learn i

GUIDE TO THE CHANGES IN PMP simpl learn i GUIDE TO THE CHANGES IN PMP- 2015 simpl learn i Table of contents Introduction the purpose of this manual 1 New Tasks: Initiating 3 New Tasks: Planning 4 New Tasks: Executing 6 New Tasks: Monitoring and

More information

Trial Master File Reference Model. Project Charter. Review, Testing, and Ratification of the etmf Exchange Mechanism Standard, Version 1

Trial Master File Reference Model. Project Charter. Review, Testing, and Ratification of the etmf Exchange Mechanism Standard, Version 1 Trial Master File Reference Model Project Charter Review, Testing, and Ratification of the etmf Exchange Mechanism Standard, Version 1 Prepared by The Exchange Mechanism Standard Subgroup of the TMF Reference

More information

Management Consulting and Project Management: Hand in Glove

Management Consulting and Project Management: Hand in Glove Service. Accountability. Better Government. Consulting and Project : Hand in Glove J. Kendall Lott President, M Squared Strategies The Task: Rock the PMBOK The Charge Why is PM important for you? It is

More information

Functionality First: A Prescriptive Approach to Simpler, Faster and More Cost-effective Project and Portfolio Management (PPM)

Functionality First: A Prescriptive Approach to Simpler, Faster and More Cost-effective Project and Portfolio Management (PPM) Functionality First: A Prescriptive Approach to Simpler, Faster and More Cost-effective Project and Portfolio Management (PPM) Copyright 2014 CA. All rights reserved. Why the Need for Smarter PPM? The

More information

EAST SUSSEX FIRE AUTHORITY Job Description

EAST SUSSEX FIRE AUTHORITY Job Description EAST SUSSEX FIRE AUTHORITY Job Description Job Title: Supplier Service Manager Job Family: JF6 Specialist/Technical Manager Reporting to: ITG Manager Responsible for: 1 direct report (Support Officer,

More information

Job Family Matrix. Core Duties Core Duties Core Duties

Job Family Matrix. Core Duties Core Duties Core Duties Job Function: Information Technology Job Family Matrix Job Family: IT Project Management - Professional Job Family Summary: Perform or manage a range of activities related to the design, planning, execution,

More information

Project Origination: Item Description (Origination) Comments (or reasons for NOT completing)

Project Origination: Item Description (Origination) Comments (or reasons for NOT completing) Project Origination: (Origination) Develop Project Proposal: 24 Formulate business need/problem and 24 anticipated benefits to all parties Review project s fit with organization s mission 24 Identify project

More information

Capturing synergies to deliver deal value

Capturing synergies to deliver deal value November 2012 Capturing synergies to deliver deal value A publication from PwC's Deals M&A Integration practice At a glance Value realized from an acquisition depends on how well the newly combined company

More information

Project Plan. Executive Summary. Project Name: Prepared By: Date: Business Need/Problem Identify business need/problem that needs to be solved.

Project Plan. Executive Summary. Project Name: Prepared By: Date: Business Need/Problem Identify business need/problem that needs to be solved. Project Plan Project Name: Prepared By: Date: A Executive Summary Information in the project summary areas was started during the project concept phase and should be included here. Information includes

More information

The Scheduling Maturity Model. ched

The Scheduling Maturity Model. ched at The Scheduling Maturity Model ched Table of contents Preface 4 Foreword 5 Acknowledgements 6 Applicability 7 Introduction 8 Fundamental Concepts 9 How is the Maturity Model used for Assessment? 10 What

More information

Project+ Examination Blueprint Version June 1, 2003

Project+ Examination Blueprint Version June 1, 2003 Introduction The Project + examination is designed for business professionals involved with projects with a technology component. The examination is designed for candidates possessing at least 12 months

More information

PMO In A Box. Prepared for UBS

PMO In A Box. Prepared for UBS PMO In A Box Prepared for UBS Roadmap Why PMO In A Box? Establish PMO Governance Standardize Methodology Create a Stakeholder Partnership Plan 2 PMOs Are In Transition 3 CEB PMO Executive Council pmo in

More information

CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS

CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS Objectives Introduction The objectives are: Describe the purpose of the phase planning activity, preconditions, and deliverables in the implementation methodology.

More information