Tools for Building Monitoring and Evaluation Systems in Public Works Projects

Size: px
Start display at page:

Download "Tools for Building Monitoring and Evaluation Systems in Public Works Projects"

Transcription

1 Tools for Building Monitoring and Evaluation Systems in Public Works Projects Laura B. Rawlings Lead Social Protection Specialist Human Development Network World Bank 1 Making Public Works Work South South Learning Forum Arusha June 2010

2 Objectives of this session 1. Functions of Monitoring and Evaluation (M&E) Systems 2. Structuring M&E Systems for Programs 3. Monitoring and Evaluation Tools 4. Operationalizing M&E Systems 5. Quick Tips! 2

3 Objectives of Monitoring and Evaluation Systems Why do we need good M&E systems? Managing for results Information to improve decision making and steer development interventions towards clearly defined goals. Accountability and transparency Information to track performance and report on progress to stakeholders, civil society Knowledge generation on development effectiveness. Evidence on the outcomes of development programs There is no blueprint for an M&E system systems should be designed to reflect the needs of program managers, policymakers Simple approaches are often the best! 3

4 Principles of Management for Development Results* 5. Using results 1. Focusing the information for dialogue on results at learning and all phases of the decision making development process 4. Managing for, not by, results 2. Aligning programming, M&E with results 3. Keeping measurement t& reporting simple & cost-effective Tools for performance measurement to increase the effectiveness of development interventions Results-based M&E * Roundtable on Managing for Results in 2004

5 Objectives of this session 1. Functions of Monitoring and Evaluation (M&E) Systems 2. Structuring M&E Systems for Public Works Programs 3. Monitoring and Evaluation Tools 4. Operationalizing M&E Systems 5. Quick Tips! 5

6 The Cycle of Project Level M&E Engage stakeholders 2-Selecting Indicators Be Selective 1-Formulating Objectives 3-Setting Baselines and Targets 6 Promote Transparency 5-Reviewing and Reporting on Performance 4-Monitoring and Evaluation Communicate

7 1. Formulating Objectives: Using a Results Chain Results chains are a simple approach to mapping the causal logic/theory of change underpinning a program best used as a participatory i t tool, during project design basis for constructing a M&E approach which will test the validity of the theory of change A results chain answers 3 questions What are the intended results of the program? How will we achieve the intended results? How will we know we have achieved the intended results? 7

8 The Results Chain Inputs Activities t Outputs Outcomes Final Outcomes Financial, human, and other resources mobilized to support activities Budgets, staffing, other available resources Actions taken or work performed to convert inputs into specific outputs Series of activities undertaken to produce goods and services Products resulting from converting inputs into tangible outputs Goods and services produced and delivered, under the control of the implementing agency Changes resulting from use of outputs by targeted population Not fully under the control of implementing agency The final objective of the program Long-term goals Changes in outcomes with multiple drivers SUPPLY SIDE DEMAND + SUPPLY 8

9 Critical factors for defining results to be achieved Socio- economic context: Results sought by the program should reflect current needs and priorities Local Capacity: Existing skills, leadership, and management capacity will impact on what can be implemented to achieve expected results Resources: Level of resources will impact on what can realistically be achieved Timetable: Results framework should identify the results (changes) to be achieved in the life of the program

10 2- Selecting Key Performance Indicators 3- Setting Baselines, Targets Use Results Chain/Logframe as a guide Select indicators along the results chain (activities, outputs, outcomes) Be clear on use of indicators Be selective and work with stakeholders to ID best indicators Indicators should be SMART Specific: measure as closely as possible what you want to know Measurable: be clear about how it will be measured ttributable: logically and closely linked to a program s efforts ealistic: data obtainable at reasonable cost, frequency, and accuracy argeted: Specific to the program s target group Attributable Realistic Targeted Collect baselines, set targets 10

11 4 - Monitoring and Evaluation Monitoring A continuous process of collecting and analyzing information -- To compare how well a project, program or policy is performing against expected results -- To inform implementation and program management Often based on administrative data Navigation system tailored to different users Evaluation A selective, systematic, objective assessment of an on-going or 11 completed project, program, or policy, its design, implementation and/or results --To determine the relevance and fulfillment of objectives, development efficiency, effectiveness, impact and sustainability. --To generate lessons learned to inform the decisionmaking process. --Tailored to key questions Often based on specialized data, surveys

12 Indicator Planning Matrix Expected Results (Outcomes & Outputs) Indicators (with Baselines & Indicative Targets) Data Source Time or Schedule and Frequency Responsibilities Analysis and Reporting Resources End Use Risks Obtained From results How are Frequency Who is Frequency of Estimate of Who will What are the from development plan and results framework 12 framework data to be obtained? Source and Indicators location should also capture key priorities Example: such as through a capacity survey, a development review or and gender stakeholder meeting, etc. of data responsible for analysis, analysis resources availability organizing the method, and required and data collection responsibility of committed and verifying data reporting for carrying quality and out planned source? m&e activities receive and risks and review this assumptions information? for carrying out the What planned m&e purpose does activities? it serve? How may these affect the planned m&e events and quality of data? Source: Adapted from Handbook on Planning, Monitoring

13 Monitoring and Evaluation Tools Examples from Public Works Projects Monitoring Management Information Systems (MIS) Costs Coverage Service delivery Compliance Beneficiary profiles Financial data Spot check system Complaints and appeals systems Evaluation Financial, Operational audits Process evaluations Participatory evaluations Social audits Beneficiary assessments Community scorecards Targeting assessments Impact evaluations Cost- benefit analysis Expenditure tracking studies 13

14 Sources of Monitoring Data Tips! 14 Administrative Databases (MIS) Essential, but difficult to assure that they cover all relevant units (clients, customers, households, etc.) and that all the fields you need are filled in, and filled in accurately. Require a good deal of quality control; most likely to be accurate if the line workers and other agency personnel depend d on their accuracy for their daily work. Funding data Needed for efficiency and productivity measures, but difficult to know that they include all real costs for an intervention and do not include some funds actually going to other activities. Don t take at face value; probe knowledgeable people about what they contain. Spot Check Systems Good approach for verifying accuracy of Administrative/MIS data Can involve review of records, surveys of providers, beneficiaries and other stakeholders Can involved trained observation - works best on easily observed and quantified measures Complaints and Appeals Systems Good source of information for troubleshooting Not representative of projects or beneficiaries as a whole, so careful drawing conclusions Source: adapted from Burt. Greiner

15 Sources of Monitoring Data Tips! Don t always need complex computer systems! Dt Data can be generated td from hand-processed d forms at a local l or point-of-service level and aggregated and computerized at a provincial or higher level. The more frequently data are collected or processed, the more computerization and networking is desirable. Take advantage of routine tasks Use routine steps in the project and subproject cycle to gather and use key data, such as entering data on beneficiaries in MIS system to review targeting and program eligibility.

16 Sources of evaluation data Rigor/Difficulty (Cost/Time/skills)( ) Community Focus Interviews Group Interviews Key Informant Interviews Choice depends Direct Observation Review of official records 1. Issue to be examined One-Time Survey Census Panel Surveys 2. Quality of the information needed Impact Evaluation Validity Reliability Credibility Statistical i Emphasis 3. Time frame in which information is needed 4. Cost Source: Kusek, Karthouri

17 5. Reviewing and Reporting on Performance The Feedback Process: Program managers together with evaluation, planning and budget units can Review M&E results on a periodic basis Hold How are we doing? sessions Develop action plans/responses to results Are program changes needed? How will we continue to track progress? Report results to others Use information to inform program management, policy 17

18 Getting it done! Champions Inside the program managers and key stakeholders Outside the program policymakers; Ministries of Finance, Congress, budget offices; citizens, media Changing culture from threats to tools 18

Monitoring and Evaluation: the Foundations for Results

Monitoring and Evaluation: the Foundations for Results Monitoring and Evaluation: the Foundations for Results Laura B. Rawlings Lead Social Protection Specialist Human Development Network World Bank Beijing, China Impact Evaluation Workshop July 2009 1 Objectives

More information

Building Monitoring and Evaluation Systems. Maddalena Honorati Economist Human Development Network The World Bank

Building Monitoring and Evaluation Systems. Maddalena Honorati Economist Human Development Network The World Bank Building Monitoring and Evaluation Systems Maddalena Honorati Economist Human Development Network The World Bank Outline Why M&E? What is a good M&E system? Monitoring vs. Evaluation Using Results Chain

More information

How to write a logframe

How to write a logframe How to write a logframe Why do we need logframes? Results frameworks and logframes are essential throughout the project cycle, informing decisionmaking at each stage from identifying options, designing

More information

Monitoring and Evaluation in the GEF: How Country Stakeholders Get Involved. GEF Expanded Constituency Workshops Group Work

Monitoring and Evaluation in the GEF: How Country Stakeholders Get Involved. GEF Expanded Constituency Workshops Group Work Monitoring and Evaluation in the GEF: How Country Stakeholders Get Involved GEF Expanded Constituency Workshops Group Work Group Exercise Work with the group at your table as a team to provide input to

More information

Monitoring and Evaluation in the GEF: How Country Stakeholders Get Involved. GEF Expanded Constituency Workshops Group Work

Monitoring and Evaluation in the GEF: How Country Stakeholders Get Involved. GEF Expanded Constituency Workshops Group Work Monitoring and Evaluation in the GEF: How Country Stakeholders Get Involved GEF Expanded Constituency Workshops Group Work Group Exercise Work with the group at your table as a team to provide input to

More information

9. Project Cycle Management and Logical Framework: The case of the EC. By Claudio Foliti

9. Project Cycle Management and Logical Framework: The case of the EC. By Claudio Foliti 9. Project Cycle Management and Logical Framework: The case of the EC By Claudio Foliti What is a project? (EC, Aid Delivery Methods, 2004) Definition: A project is a series of activities aimed at bringing

More information

Monitoring and Evaluation Policy

Monitoring and Evaluation Policy Monitoring and Evaluation Policy 1 M&E Policy Last Updated October 2017 1. Introduction The Monitoring and Evaluation (M&E) policy will apply to the global C&A Foundation including Fundación C&A in Mexico

More information

Logical Framework for the project

Logical Framework for the project Annex 6 Logframe Annex C Improved Water Supply and Sanitation Information and Monitoring System for the Settlements of the urban Poor in Kenya Overall objectives Intervention Objectively verifiable Sources

More information

PDP s Third Call for Proposals

PDP s Third Call for Proposals Training on How to write a Full Application for PDP s Third Call for Proposals Development of the Logical Framework - May/June 2016 - Ministry of Housing Utilities and Urban Communities Page 1 Recommendations

More information

TERMS OF REFERENCE. Independent Evaluation of the ILO Action Plan for Gender Equality

TERMS OF REFERENCE. Independent Evaluation of the ILO Action Plan for Gender Equality TERMS OF REFERENCE Independent Evaluation of the ILO Action Plan for Gender Equality 2010-15 1 Introduction The results-based ILO Action Plan for Gender Equality 2010-15 (the Action Plan) aims to operationalize

More information

PROCEDURE AND TOOLS FOR EVALUABILITY REVIEW OF ILO PROJECTS OVER US$5 MILLION

PROCEDURE AND TOOLS FOR EVALUABILITY REVIEW OF ILO PROJECTS OVER US$5 MILLION PROCEDURE AND TOOLS FOR EVALUABILITY REVIEW OF ILO PROJECTS OVER US$5 MILLION August 2014 (containing forms to fill in at end of document) BACKGROUND Over two-thirds of independent evaluations flag poor

More information

ISPA tools South Asia and East Asia Pacific Regional ISPA Face-2-Face Training Yogyakarta, Indonesia, March 2018

ISPA tools South Asia and East Asia Pacific Regional ISPA Face-2-Face Training Yogyakarta, Indonesia, March 2018 ISPA tools South Asia and East Asia Pacific Regional ISPA Face-2-Face Training Yogyakarta, Indonesia, 12-16 March 2018 Team and Work Plan Team Veronika Wodsak, Social Security Specilalist, ILO Ruslan Yemtsov,

More information

Monitoring and Evaluation: A Logical Frame. Evaluating the Impact of Projects and Programs Beijing, China, April 10-14, 2006 Shahid Khandker, WBI

Monitoring and Evaluation: A Logical Frame. Evaluating the Impact of Projects and Programs Beijing, China, April 10-14, 2006 Shahid Khandker, WBI Monitoring and Evaluation: A Logical Frame Evaluating the Impact of Projects and Programs Beijing, China, April 10-14, 2006 Shahid Khandker, WBI 1 What is M&E? Monitoring and evaluation are tools that

More information

MERIT SYSTEM SERVICES Date Established: 10/30/80 Date Revised: 05/04 STAFF SERVICES ANALYST I/II (Madera County Title: Staff Services Analyst I)

MERIT SYSTEM SERVICES Date Established: 10/30/80 Date Revised: 05/04 STAFF SERVICES ANALYST I/II (Madera County Title: Staff Services Analyst I) MERIT SYSTEM SERVICES Date Established: 10/30/80 Date Revised: 05/04 STAFF SERVICES ANALYST I/II (Madera County Title: Staff Services Analyst I) CLASSIFICATION DEFINITION The Staff Services Analyst I/II

More information

Training on Project Cycle Management for Researchers Ethiopian Academy of Sciences May 2016, Ghion Hotel, Addis Ababa

Training on Project Cycle Management for Researchers Ethiopian Academy of Sciences May 2016, Ghion Hotel, Addis Ababa Training on Project Cycle Management for Researchers Ethiopian Academy of Sciences 25-27 May 2016, Ghion Hotel, Addis Ababa To increase participants understanding of the concepts used in designing M&E

More information

Servacius B. Likwelile EXECUTIVE DIRECTOR Tanzania Social Action Fund (TASAF) Dar es Salaam, TANZANIA October 1-5, 2007

Servacius B. Likwelile EXECUTIVE DIRECTOR Tanzania Social Action Fund (TASAF) Dar es Salaam, TANZANIA October 1-5, 2007 INFORMATION FLOW, TRANSPARENCY AND ACCOUNTABILITY AT THE DISTRICT AND COMMUNITY LEVEL IN TANZANIA FOR EFFECTIVE DELIVERY OF HIV/AIDS SUPPORT: THE TASAF EXPERIENCE Servacius B. Likwelile EXECUTIVE DIRECTOR

More information

DevNet Conference Kate Averill Director, Evaluation Consult PhD research, November 2010

DevNet Conference Kate Averill Director, Evaluation Consult PhD research, November 2010 Using Results Frameworks to Connect Development Outcomes, Management, Aid, Monitoring and Evaluation: Emerging Research on the Principles Underpinning Country and Sector Results and Outcomes Frameworks

More information

Workshop II Project Management

Workshop II Project Management Workshop II Project Management UNITAR-HIROSHIMA FELLOWSHIP FOR AFGHANISTAN 2007 Introduction to Project Management 15 17 August 2007, Dehradun, India Presented by: Jobaid Kabir, Ph.D. Fellowship Program

More information

i FACILITATOR S GUIDE

i FACILITATOR S GUIDE i FACILITATOR S GUIDE ii FACILITATOR S GUIDE CONTENTS MODULE 6: MONITORING AND EVALUATING THE PROJECT Objectives 1 Session 9 2 The monitoring and evaluation process 2 Monitoring 2 Elements of monitoring

More information

Monitoring and Evaluation Guidance Note

Monitoring and Evaluation Guidance Note Monitoring and Evaluation Guidance Note May 2009 Content List Section One Introduction...1 Section Two Monitoring and Evaluation Defined...1 Section Three SPARC Approach to Monitoring and Evaluation...2

More information

NATIONAL EXPORT STRATEGY

NATIONAL EXPORT STRATEGY NATIONAL EXPORT STRATEGY BUILDING AN EXPORT CULTURE This document is for discussion purposes only and does not imply any engagement or liability on the part of the International Trade Centre (ITC). Copyright

More information

Organizational capacity Assessment tool 1

Organizational capacity Assessment tool 1 Organizational capacity Assessment tool 1 Purpose This assessment tool is intended to guide HI staff and members of local structures to assess organisational capacity. The questions highlight three key

More information

Indicators, Targets and Data Sources

Indicators, Targets and Data Sources Indicators, Targets and Data Sources At the end of the session, participants will be able to: Construct Establish Describe Agree SMART Indicators Targets Good quality Data Sources on next steps 2 Results

More information

Senior Monitoring and Evaluation Specialist, Niger

Senior Monitoring and Evaluation Specialist, Niger Senior Monitoring and Evaluation Specialist, Niger Location: [Africa] [Niger] Town/City: Maradi Category: Field Operations Job Type: Fixed term, Full-time PURPOSE OF POSITION: World Vision seeks a Senior

More information

Glossary of Performance Measurement Terms Ontario Public Service Reference Document for Provincial Ministries

Glossary of Performance Measurement Terms Ontario Public Service Reference Document for Provincial Ministries Glossary of Performance Measurement Terms Ontario Public Service Reference Document for Provincial Ministries Introduction The following definitions are based on a number of sources and have been tailored

More information

TIPS PREPARING AN EVALUATION STATEMENT OF WORK ABOUT TIPS

TIPS PREPARING AN EVALUATION STATEMENT OF WORK ABOUT TIPS NUMBER 3 2 ND EDITION, 2010 PERFORMANCE MONITORING & EVALUATION TIPS PREPARING AN EVALUATION STATEMENT OF WORK ABOUT TIPS These TIPS provide practical advice and suggestions to USAID managers on issues

More information

GLOSSARY OF SELECT M&E TERMS

GLOSSARY OF SELECT M&E TERMS GLOSSARY OF SELECT M&E TERMS NOTE: This glossary contains only select M&E terms used throughout this guide. Other important terms exist in the field of M&E, but are not dealt with in this guide. For a

More information

Introduction Concept of the National Policy Project Objective Guiding principles

Introduction Concept of the National Policy Project Objective Guiding principles 1 Introduction With the aim of creating an appropriate developmental environment that achieves the Palestinian people s aspirations and purposes, it is important for national policies and plans to adopt

More information

Terms of Reference for a Gender Analysis

Terms of Reference for a Gender Analysis Terms of Reference for a Gender Analysis 1. BACKGROUND The European Commission defines a gender analysis as the study of differences in the conditions, needs, participation rates, access to resources and

More information

AFRICA FOR RESULTS INITIATIVE GUIDANCE ON ASSESSING THE PERFORMANCE OF MFDR PROJECTS. Introduction. Massoud Moussavi Tool N 2 SYNOPSIS

AFRICA FOR RESULTS INITIATIVE GUIDANCE ON ASSESSING THE PERFORMANCE OF MFDR PROJECTS. Introduction. Massoud Moussavi Tool N 2 SYNOPSIS AFRICA FOR RESULTS INITIATIVE GUIDANCE ON ASSESSING THE PERFORMANCE OF MFDR PROJECTS Massoud Moussavi Tool N 2 SYNOPSIS A comprehensive assessment of an MfDR initiative will include continuous monitoring

More information

Management response to the annual report for 2017 on the evaluation function in UNICEF

Management response to the annual report for 2017 on the evaluation function in UNICEF UNICEF/2018/EB/5 Distr.: General 25 April 2018 English only For information United Nations Children s Fund Executive Board Annual session 2018 11 14 Item 8 of the provisional agenda* Management response

More information

PLANNING AND CONDUCT OF EVALUATIONS

PLANNING AND CONDUCT OF EVALUATIONS PLANNING AND CONDUCT OF EVALUATIONS 6. Planning for Scope and Methodology Principles and Norms ENSURING QUALITY OF EVALUATION 6.1 Each evaluation should employ processes that are quality oriented, and

More information

Module 6 Introduction to Measurement

Module 6 Introduction to Measurement Module 6 Introduction to Measurement 1 Module Objectives By the end of this module participants will be able to: 1 2 Make initial decisions regarding when you need to collect data and on whom or what you

More information

White Paper Realising benefits: How to plan for success

White Paper Realising benefits: How to plan for success Realising benefits: How to plan for success UK Government departments are currently facing significant challenges prioritising their initiatives effectively under increased resource constraints. Robust

More information

CRITERIA FOR EQUASS ASSURANCE (SSGI)

CRITERIA FOR EQUASS ASSURANCE (SSGI) CRITERIA FOR EQUASS ASSURANCE (SSGI) 2008 by European Quality for Social Services (EQUASS) All rights reserved. No part of this document may be reproduced in any form or by any means, electronic, mechanical,

More information

Beaver Works: Business Excellence Adding Value & Service. Business Operations Project Plan Information Sessions August-October 2018

Beaver Works: Business Excellence Adding Value & Service. Business Operations Project Plan Information Sessions August-October 2018 Beaver Works: Business Excellence Adding Value & Service Business Operations Project Plan Information Sessions August-October 2018 Information Session Agenda Where We ve Been Background, Challenges, and

More information

POVERTY REDUCTION ACTION PLAN (PRAP) DEVELOPMENT GUIDANCE 1

POVERTY REDUCTION ACTION PLAN (PRAP) DEVELOPMENT GUIDANCE 1 Introduction POVERTY REDUCTION ACTION PLAN (PRAP) DEVELOPMENT GUIDANCE 1 BNTF Participating Countries (PCs) are required to develop their PRAPs as a condition for the allocation of BNTF funding. It is

More information

Terms of Reference Final external evaluation of the African Children s Charter Project (ACCP) Bridge period (April 2015-December 2016)

Terms of Reference Final external evaluation of the African Children s Charter Project (ACCP) Bridge period (April 2015-December 2016) Terms of Reference Final external evaluation of the African Children s Charter Project (ACCP) Bridge period (April 2015-December 2016) 1. Background The African Children s Charter Project (ACCP) bridge

More information

Provincial framework for. public participation in Gauteng

Provincial framework for. public participation in Gauteng Provincial framework for plan act public participation in Gauteng by Hermine Engel, Planact 4 March 2010 Prepared for Provincial Public Participation Dialogue Making towns & cities work for people 1 Structure

More information

WORLD INTELLECTUAL PROPERTY ORGANIZATION GENEVA INTERNAL AUDIT AND OVERSIGHT DIVISION INTERNAL REVIEW ON PROGRAM PERFORMANCE REPORTING PROCESS

WORLD INTELLECTUAL PROPERTY ORGANIZATION GENEVA INTERNAL AUDIT AND OVERSIGHT DIVISION INTERNAL REVIEW ON PROGRAM PERFORMANCE REPORTING PROCESS WIPO WORLD INTELLECTUAL PROPERTY ORGANIZATION GENEVA Reference: EV/01/2008 INTERNAL AUDIT AND OVERSIGHT DIVISION INTERNAL REVIEW ON PROGRAM PERFORMANCE REPORTING PROCESS Evaluation Section October 10,

More information

The Role of Monitoring & Evaluation for Good Governance King Mongkut s University of Technology North Bangkok

The Role of Monitoring & Evaluation for Good Governance King Mongkut s University of Technology North Bangkok The Role of Evaluation for Good Governance King Mongkut s University of Technology North Bangkok Director of the Center for Evaluation, Saarland University, Germany Content rational 1. 2. Outcomeoriented

More information

USAID PROGRAM CYCLE OVERVIEW

USAID PROGRAM CYCLE OVERVIEW USAID PROGRAM CYCLE OVERVIEW USAID AUGUST 2012 CONTENTS Background...3 Overview Summary...3 Program Cycle Components:...3 Agency Policies and Strategies:...4 Country Development Cooperation Strategies:...5

More information

Joint Assessment of National Health Strategies and Plans

Joint Assessment of National Health Strategies and Plans Joint Assessment of National Health Strategies and Plans Version 2: September 2011 Joint Assessment of National Health Strategies and Plans Joint Assessment Tool: the attributes of a sound national strategy

More information

The Seven Areas of Responsibility of Health Educators Area of Responsibility I: ASSESS NEEDS, ASSETS AND CAPACITY FOR HEALTH EDUCATION COMPETENCY

The Seven Areas of Responsibility of Health Educators Area of Responsibility I: ASSESS NEEDS, ASSETS AND CAPACITY FOR HEALTH EDUCATION COMPETENCY The Seven Areas of Responsibility of Health Educators Area of Responsibility I: ASSESS NEEDS, ASSETS AND CAPACITY FOR HEALTH EDUCATION COMPETENCY 1.1. Plan Assessment Process 1.1.1 Identify existing and

More information

Significant Service Contracts Framework

Significant Service Contracts Framework 1 Significant Service Contracts Framework The Significant Service Contracts Framework is delivered by New Zealand Government Procurement (NZGP). NZGP delivers on the Ministry of Business Innovation and

More information

Terms of Reference (TOR)

Terms of Reference (TOR) CONFÉRENCE DES NATIONS UNIES SUR LE COMMERCE ET LE DÉVELOPPEMENT UNITED NATIONS CONFERENCE ON TRADE AND DEVELOPMENT Terms of Reference (TOR) External Evaluation of Development Account Project 1213 I Strengthening

More information

PROJECT IDENTIFICATION

PROJECT IDENTIFICATION Project Identification steps Step 1 Strategic Alignment Align Overall and Programme (s)strategies Project Identification - Align projects to programmes Annual Budget for Programmes (not part of toolkit)

More information

Guide on the elaboration of local plans for increasing transparency and ensuring access to information in the activity of the local public authorities

Guide on the elaboration of local plans for increasing transparency and ensuring access to information in the activity of the local public authorities Guide on the elaboration of local plans for increasing transparency and ensuring access to information in the activity of the local public authorities This publication has become possible due to the financial

More information

Organizing Framework for a Functional National HIV Monitoring & Evaluation System

Organizing Framework for a Functional National HIV Monitoring & Evaluation System Regional Training on Strategic and Operational Planning in HIV & AIDS Organizing Framework for a Functional National HIV Monitoring & Evaluation System Final Draft for submission to the HIV Monitoring

More information

Executive Board of the United Nations Development Programme and of the United Nations Population Fund

Executive Board of the United Nations Development Programme and of the United Nations Population Fund United Nations DP/2011/3 Executive Board of the United Nations Development Programme and of the United Nations Population Fund Distr.: General 15 November 2010 Original: English First regular session 2011

More information

ENGAGING WITH CITIZENS FOR IMPROVED DEVELOPMENT RESULTS

ENGAGING WITH CITIZENS FOR IMPROVED DEVELOPMENT RESULTS ENGAGING WITH CITIZENS FOR IMPROVED DEVELOPMENT RESULTS Towards a Strategic Framework for Mainstreaming Citizen Engagement in WBG Operations April 10, 2014 Motivation External Factors Renewed focus on

More information

KATSINA STATE GOVERNMENT CORPORATE PLANNING POLICY PAPER

KATSINA STATE GOVERNMENT CORPORATE PLANNING POLICY PAPER KATSINA STATE GOVERNMENT CORPORATE PLANNING POLICY PAPER September, 2013 1. Introduction A pilot corporate plan has been completed for the Ministry of Finance, Budget and Economic Planning (MoFB&EP) and

More information

Organizing framework for functional national WASH monitoring and evaluation systems

Organizing framework for functional national WASH monitoring and evaluation systems Organizing framework for functional national WASH monitoring and evaluation systems Accelerating national and subnational WASH monitoring for improved asset management and service delivery (UNICEF, IRC,

More information

GEROS Evaluation Quality Assurance Tool Version

GEROS Evaluation Quality Assurance Tool Version GEROS Evaluation Quality Assurance Tool Version 2016.4 Title of the Evaluation Report Report sequence number Reviewers: complete all cells highlighted in Yellow Support to community sanitation in eastern

More information

TERMS OF REFERENCE FOR CONSULTANTS

TERMS OF REFERENCE FOR CONSULTANTS Preparing the Inclusive Health Project TajikistanTA 51010 Individual Consultants TERMS OF REFERENCE FOR CONSULTANTS 1. International facility masterplan and rationalization specialist (3 person-months,

More information

Call for Expression of Interest

Call for Expression of Interest Call for Expression of Interest Mid term Evaluation Project: Empowerment of Vulnerable Women in Sri Lanka Deadline for submission of Expression of Interest: October 17 th 2014 1. Introduction Empowerment

More information

GUIDANCE NOTE: DEVELOPING A RESULTS

GUIDANCE NOTE: DEVELOPING A RESULTS GUIDANCE NOTE: DEVELOPING A RESULTS TITTLE ORIENTED EITI WORKPLAN EITI International Secretariat Oslo, 1 May 2013 Implemented by GUIDANCE NOTE: DEVELOPING AN EITI WORKPLAN 1 Requirement 1.4 of the Standard

More information

Linkages between the Africa Governance Inventory (AGI) and the African Peer Review Mechanism (APRM)

Linkages between the Africa Governance Inventory (AGI) and the African Peer Review Mechanism (APRM) UNITED NATIONS NATIONS UNIES DEPARTMENT OF ECONOMIC AND SOCIAL AFFAIRS/ DEPARTEMENT DES AFFAIRES ECONOMIQUES ET SOCIALES Linkages between the Africa Governance Inventory (AGI) and the African Peer Review

More information

TERMS OF REFERENCE. 1. Background on the project

TERMS OF REFERENCE. 1. Background on the project TERMS OF REFERENCE DEVELOPMENT OF A MONITORING & EVALUATION FRAMEWORK AND BASELINE STUDY FOR THE PROJECT PROMOTING BROADER AND EFFECTIVE PARTICIPATION OF SOUTH AFRICAN CIVIL SOCIETY IN ENVIRONMENTAL GOVERNANCE

More information

Indigenous and Northern Affairs Canada. Internal Audit Report. Audit of Performance Measurement. Prepared by: Audit and Assurance Services Branch

Indigenous and Northern Affairs Canada. Internal Audit Report. Audit of Performance Measurement. Prepared by: Audit and Assurance Services Branch Internal Audit Report Audit of Performance Measurement Prepared by: Audit and Assurance Services Branch January 2017 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 1. BACKGROUND... 4 2. AUDIT OBJECTIVE AND SCOPE...

More information

Western Balkans Recommendation on Public Participation

Western Balkans Recommendation on Public Participation Western Balkans Recommendation on Public Participation Preamble The Ministers in charge of Public Administration Reform from Western Balkan economies, Acknowledging the Public Administration Reform as

More information

Personal and Public Involvement (PPI) Trust Board Update Paper

Personal and Public Involvement (PPI) Trust Board Update Paper Personal and Public Involvement (PPI) Trust Board Update Paper Dr G. Rankin June 2009 Introduction and Background In line with the Regional Strategy and Departmental Guidelines there has been a growing

More information

Service Evaluation. An introductory guide

Service Evaluation. An introductory guide Service Evaluation An introductory guide Contents ------------------------------------------------------------------------------------------------------- Key Points... 2 Introduction... 3 Types of Evaluation...

More information

Working Party on Aid Evaluation

Working Party on Aid Evaluation For Official Use DCD/DAC/EV(2001)3 DCD/DAC/EV(2001)3 For Official Use Organisation de Coopération et de Développement Economiques Organisation for Economic Co-operation and Development 24-Apr-2001 English

More information

Performance Auditing: What It Is, and Why It Is Important Presented by: Harriet Richardson, CPA, CIA, CGAP Audit Manager, City of Berkeley

Performance Auditing: What It Is, and Why It Is Important Presented by: Harriet Richardson, CPA, CIA, CGAP Audit Manager, City of Berkeley Performance Auditing: What It Is, and Why It Is Important Presented by: Harriet Richardson, CPA, CIA, CGAP Audit Manager, City of Berkeley ASMC Sacramento Mini PDI 24 January 2012 Session Objectives Provide

More information

What will we do?

What will we do? What will we do? Methodology of the transversal analysis Lotte Staelens systematic analysis of a specific topic within Lithuania, particularly key development problems, and of the options for addressing

More information

SMS Elements Veriforce, LLC. All rights reserved.

SMS Elements Veriforce, LLC. All rights reserved. 1. Leadership and Management Commitment 2. Stakeholder Engagement 3. Risk Management 4. Operational Controls 5. Incident Investigation, Evaluation, and Lessons Learned 6. Safety Assurance 7. Management

More information

Social and Environmental Assessments, Indicators, Information, Monitoring, Reporting and Verification

Social and Environmental Assessments, Indicators, Information, Monitoring, Reporting and Verification Social and Environmental Assessments, Indicators, Information, Monitoring, Reporting and Verification Session 10 Diane Russell, USAID Forestry and Biodiversity Office Evan Notman, USAID Global Climate

More information

DIAKONIA TERMS OF REFERENCE FOR BASELINE SURVEY CONSULTANCY PROCUREMENT REFERENCE NUMBER: DK/CONS/09/001/2015

DIAKONIA TERMS OF REFERENCE FOR BASELINE SURVEY CONSULTANCY PROCUREMENT REFERENCE NUMBER: DK/CONS/09/001/2015 1. Over View of Diakonia Work in Uganda Diakonia is a Christian development organization working together with local partners for sustainable change for the most vulnerable people of the world. Diakonia

More information

Monitoring and Evaluating Social Protection Programs Efforts to Respond to Natural Disasters and Climate Change-Related Shocks

Monitoring and Evaluating Social Protection Programs Efforts to Respond to Natural Disasters and Climate Change-Related Shocks Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Why Is It Important to Monitor and Evaluate Disaster- and Climate Shock-sensitive Components

More information

CODI CORE DIAGNOSTIC INSTRUMENT ASSESSMENT MATRIX SYSTEM

CODI CORE DIAGNOSTIC INSTRUMENT ASSESSMENT MATRIX SYSTEM CODI CORE DIAGNOSTIC INSTRUMENT ASSESSMENT MATRIX SYSTEM 1. Inclusiveness Refers to the system s capacity to protect all members of society along the life cycle with special consideration for the most

More information

Fairtrade International Monitoring Evaluation and Learning Programme ISEAL Impacts Code Public System Report January Executive Summary 2

Fairtrade International Monitoring Evaluation and Learning Programme ISEAL Impacts Code Public System Report January Executive Summary 2 Fairtrade International Monitoring Evaluation and Learning Programme ISEAL Impacts Code Public System Report January 2017 Contents 1. Executive Summary 2 2. Scope and Boundaries of the Fairtrade MEL System

More information

MONITORING AND EVALUATION UNDAF CAMPANION GUIDANCE UNDAF COMPANION GUIDANCE: MONITORING AND EVALUATION

MONITORING AND EVALUATION UNDAF CAMPANION GUIDANCE UNDAF COMPANION GUIDANCE: MONITORING AND EVALUATION MONITORING AND EVALUATION UNDAF CAMPANION GUIDANCE 1! TABLE OF CONTENTS 1. INTRODUCTION... 3 2. THE CONCEPT... 4 3. MOVING FROM THEORY TO PRACTICE... 6 3.1 Establish an M&E Technical Working Group... 6

More information

Terms of Reference End of Programme Evaluation of CAFOD s UK Aid Match Round 2 Programme: Climate Resilient Agriculture: transforming the livelihoods of 450,000 poor women, men and children in marginalised,

More information

Participatory planning and monitoring

Participatory planning and monitoring Participatory planning and monitoring Session 1 Participatory approaches to corporate-community relations in the extractive industries: Concepts, tools, benefits and risks 1 Overview This presentation

More information

Theory of Change. Aparna Krishnan JPAL South Asia at IFMR. 3 July, 2017

Theory of Change. Aparna Krishnan JPAL South Asia at IFMR. 3 July, 2017 Theory of Change Aparna Krishnan JPAL South Asia at IFMR 3 July, 2017 Course Overview 1. What is Evaluation? 2. Theory of Change 3. Outcome, Impact, & Indicators 4. Why Randomize? 5. How to Randomize?

More information

Developing a Monitoring and Evaluation Plan for Food Security and Agriculture Programmes

Developing a Monitoring and Evaluation Plan for Food Security and Agriculture Programmes Developing a Monitoring and Evaluation Plan for Food Security and Agriculture Programmes Basic monitoring and evaluation concepts Text-only version In this lesson LEARNING OBJECTIVES... 2 INTRODUCTION...

More information

ToR for Individual Consultant Evaluation of GOPP-UNDP Projects

ToR for Individual Consultant Evaluation of GOPP-UNDP Projects ToR for Individual Consultant Evaluation of GOPP-UNDP Projects II. Post Title: GOPP-UNDP Projects Evaluation Consultant III. Contract Duration: 5 months 30 working days VI. Deadline for Application: 12

More information

Executive Board of the United Nations Entity for Gender Equality and the Empowerment of Women

Executive Board of the United Nations Entity for Gender Equality and the Empowerment of Women United Nations UNW/2012/12 Executive Board of the United Nations Entity for Gender Equality and the Empowerment of Women Distr.: General 2 October 2012 Original: English Second regular session of 2012

More information

NETWORK OF ECONOMIC REGULATORS. The First Five Years: Taking Stock

NETWORK OF ECONOMIC REGULATORS. The First Five Years: Taking Stock NETWORK OF ECONOMIC REGULATORS The First Five Years: Taking Stock Contents The First Five Years: Taking Stock...2 What makes a regulator world class?...4 Participation across different sectors in the NER...

More information

COMMUNITY LIVING BRITISH COLUMBIA 2015/ /18 SERVICE PLAN

COMMUNITY LIVING BRITISH COLUMBIA 2015/ /18 SERVICE PLAN COMMUNITY LIVING BRITISH COLUMBIA 2015/16 2017/18 SERVICE PLAN For more information on CLBC contact: Community Living British Columbia 7 th Floor - Airport Square 1200 West 73 rd Avenue Vancouver, British

More information

Terms of reference Evaluator for mid-term review of 4.5-year EuropeAid Grant Agreement

Terms of reference Evaluator for mid-term review of 4.5-year EuropeAid Grant Agreement Terms of reference Evaluator for mid-term review of 4.5-year EuropeAid Grant Agreement Forus (previously known as International Forum of National NGO Platforms or IFP) is seeking an external evaluator

More information

WHO reform. WHO evaluation policy

WHO reform. WHO evaluation policy EXECUTIVE BOARD EB130/5 Add.8 130th session 22 December 2011 Provisional agenda item 5 WHO reform WHO evaluation policy BACKGROUND 1. In 2002, WHO developed a framework on Programme Management, focusing

More information

New Zealand Aid Programme Results-Based Management Toolkit

New Zealand Aid Programme Results-Based Management Toolkit New Zealand Aid Programme Results-Based Management Toolkit Purpose The purpose of this toolkit is support staff and partners in their understanding and application of Results-Based Management (RBM) for

More information

Summative Evaluation Guidelines for Jobs Fund Partners

Summative Evaluation Guidelines for Jobs Fund Partners s for Jobs Fund Partners May 2017 Contents Introduction... 3 Purpose of the Summative Evaluation... 3 Evaluation Criteria... 4 Responsibilities of the Jobs Fund Partners... 5 Planning for the Evaluation...

More information

TERMS OF REFERENCE FOR THE REVIEW OF WIPO S TECHNICAL ASSISTANCE ACTIVITIES IN THE AREA OF COOPERATION FOR DEVELOPMENT prepared by the Secretariat

TERMS OF REFERENCE FOR THE REVIEW OF WIPO S TECHNICAL ASSISTANCE ACTIVITIES IN THE AREA OF COOPERATION FOR DEVELOPMENT prepared by the Secretariat E CDIP/4/8/REV/TOR ORIGINAL: ENGLISH DATE: OCTOBER 20, 2010 TERMS OF REFERENCE FOR THE REVIEW OF WIPO S TECHNICAL ASSISTANCE ACTIVITIES IN THE AREA OF COOPERATION FOR DEVELOPMENT prepared by the Secretariat

More information

Quality Improvement Framework

Quality Improvement Framework Quality Improvement Framework Individual and Family Empowerment Reducing Barriers Affecting Service Equity OUTCOMES Youth will: Increase safety, security and positive engagement with the community Youth

More information

CSR / Sustainability Governance and Management Assessment By Coro Strandberg President, Strandberg Consulting

CSR / Sustainability Governance and Management Assessment By Coro Strandberg President, Strandberg Consulting Introduction CSR / Sustainability Governance and Management Assessment By Coro Strandberg President, Strandberg Consulting www.corostrandberg.com November 2015 Companies which adopt CSR or sustainability

More information

Mid-term Evaluation for the Gender and Generational Empowerment project in Tanzania.

Mid-term Evaluation for the Gender and Generational Empowerment project in Tanzania. Mid-term Evaluation for the Gender and Generational Empowerment project in Tanzania. Twin is a non-profit organization which owns a trading company. This structure allows us to combine trade, marketing,

More information

INTERNATIONAL LABOUR OFFICE JOB DESCRIPTION. One year (with the possibility to renew)

INTERNATIONAL LABOUR OFFICE JOB DESCRIPTION. One year (with the possibility to renew) Vacancy Notice No.: Organisational Unit/Department: Centralised or Decentralised Project Position (Title) Proposed grade Duty Station: Type of contract: Duration: TC/EIIP/113/Dec.14 Employment Injury Insurance

More information

Building Back Better. focus on resilience and participation

Building Back Better. focus on resilience and participation Building Back Better focus on resilience and participation Prof. Vinod K. Sharma Executive Vice-Chairman Sikkim State Disaster Management Authority, India Aiming for a reconstruction process that builds

More information

Provision of Support Services: Office space: Yes x No Equipment (laptop etc): Yes x No Secretarial Services Yes x No. Signature of the Budget Owner:.

Provision of Support Services: Office space: Yes x No Equipment (laptop etc): Yes x No Secretarial Services Yes x No. Signature of the Budget Owner:. I. Position Information Title: International Evaluator Final Evaluation of the Advancing Climate Change Agenda in Kosovo (SLED II) Project Department/Unit: Environment, Climate and Disaster Resilience

More information

EXTERNAL EVALUATION OF THE EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS DRAFT TECHNICAL SPECIFICATIONS

EXTERNAL EVALUATION OF THE EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS DRAFT TECHNICAL SPECIFICATIONS EXTERNAL EVALUATION OF THE EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS DRAFT TECHNICAL SPECIFICATIONS / / / 1) Motivation for this evaluation According to the founding Regulation (168/2007) of the Fundamental

More information

DISCRETIONARY GRANT MONITORING AND EVALUATION POLICY AND GUIDELINES

DISCRETIONARY GRANT MONITORING AND EVALUATION POLICY AND GUIDELINES DISCRETIONARY GRANT MONITORING AND EVALUATION POLICY AND GUIDELINES Status Approved Custodian IPO Manager Board Approval number 060/15 Decision date 12 November 2015 Review date 12 November 2016 Version

More information

Harnessing the potential for SAIs to contribute to the success of the Sustainable Development Goals

Harnessing the potential for SAIs to contribute to the success of the Sustainable Development Goals 1 (6) EUROSAI regional paper for INCOSAI, theme I: Sustainable Development Goals Coordinator: National Audit Office of Finland Contributors: Estonia, European Court of Auditors, Finland, Netherlands and

More information

GCF Templates and Guidance: Window A

GCF Templates and Guidance: Window A GCF Templates and Guidance: Window A [COVER PAGE] General Information Applicant: Jurisdiction: Project title: Proposed start date: Proposed duration (must not exceed 18 months): Total request in USD (must

More information

Designing IAEA Technical Cooperation Projects using the Logical Framework Approach

Designing IAEA Technical Cooperation Projects using the Logical Framework Approach Designing IAEA Technical Cooperation Projects using the Logical Framework Approach A Quick Reference Guide www.iaea.org/technicalcooperation Contents 1. INTRODUCTION... 1 2. THE IAEA s TECHNICAL COOPERATION

More information

Certified Training Professional for Workplace Performance. Accredited by Institute of Training & Occupational Learning, UK

Certified Training Professional for Workplace Performance. Accredited by Institute of Training & Occupational Learning, UK Certified Training Professional for Workplace Performance Accredited by Institute of Training & Occupational Learning, UK About The Program The Certified Training Professional (CTP) designation recognizes

More information

National Health Workforce Observatories. Concept and Implementation strategy. In the context of Africa Health Workforce Observatory DRAFT

National Health Workforce Observatories. Concept and Implementation strategy. In the context of Africa Health Workforce Observatory DRAFT National Health Workforce Observatories In the context of Africa Health Workforce Observatory Concept and Implementation strategy DRAFT Division of Health Systems and Services Development Regional Office

More information

CSO Evaluability Assessment Checklist: Working Draft

CSO Evaluability Assessment Checklist: Working Draft CSO Evaluability Assessment Checklist: Working Draft What Is an Evaluability Assessment? An Evaluability Assessment (EA) is a review, generally conducted prior to an evaluation, to determine an evaluation