Developing a Project Plan

Size: px
Start display at page:

Download "Developing a Project Plan"

Transcription

1 Chapter 6 Developing a Project Plan I had six honest serving men who taught men all I know : their names were what and how and why, and when and where and who. Rudyard Kipling Project Management 105 Figure 6.1 WBS/ Work Packages to Network Project Management 106 1

2 Constructing a Project Network; terminology Activity, is element of the project that requires time, it may or may not require resources. Examples of the latter are time waiting for contracts to be signed, materials to arrive, etc. Merge activity; This is an activity that has more than one activity immediately preceding it Parallel activities; these are activities that can take place at the same time, if the manager wishes. However, the manager may choose to have parallel activities not occur simultaneously. Path; A sequence of connected, dependent activities. Critical path; when this term is used, it means the longest path(s) through the network; if an activity on the path is delayed, the project is delayed the same amount of time Event; This term is used to represent a point in time when an activity is started or completed. It does not consume time Burst activity; this activity has more than one activity immediately following it Project Management 107 Basic Rules to Follow in Developing Project Networks Networks flow typically from left to right An activity cannot begin until all preceding connected activities have been completed Arrows on networks indicate precedence and flow. Arrows can cross over each other Each activity should have a unique identification number An activity identification number must be larger than that of any activities that precede it. Looping is not allowed Conditional statements are not allowed (if than,an if.. Than ) Experience suggest that when there are multiple starts, a common start node can be used indicate a clear beginning on the network. Similarly, a single project end node can be used to indicate a clear ending. Project Management 108 2

3 Figure 6.2 Activity-on- Node (AON) Fundamentals Project Management 109 Table 6.1 Network Information Project Management 110 3

4 Figure 6.3 Koll Business Center-Complete Network Project Management 111 Network Computation Process Forward Pass-Earliest Times How soon can the activity start? (early start ES) How soon can the activity finish? (early finish-ef) How soon can the project be finished? (expected time-te) Backward Pass-Latest Times How late can the activity start? (late start-ls) How late can the activity finish? (late finish-lf) Which activities represent the critical path (CP)? This is the longest path in the network which, when delayed, will delay the project How long can the activity be delayed? (slack or float SL) Project Management 112 4

5 Table 6.2 Forward Pass-Earliest Times Network Information Project Management 113 The forward pass requires that remember just three things when computing early activity times : You add activity times along each path in the network (ES+Dur=EF) You carry the early finish (EF) to next activity where it becomes its early start (ES), unless. The next succeeding activity is a merge activity. In this case you select the largest early finish number (EF) of all its immediate predecessor activities. Project Management 114 5

6 Backward Pass Latest Times, you need to remember three things You subtract activity times along each path starting with the project end activity (LF- Dur=LS) You carry the LS to the next preceding activity to establish its LF, unless The next preceding activity is a burst activity; in this case you select the smallest LS of all is immediate successor activities to establish its LF Project Management 115 Determining Slack (or Float) LS-ES=SL or LF-EF=SL; from figure 6.7, slack activity C=5, D=10, G=0. Free Slack (float); An activity with free slack is unique because the activity Can be delayed without delaying the ES of activity following it. Free slack is defined as difference between the EF of an activity an the ES of the activity that follows it. Free slack can never be negative. Activity E has free slack 165 workdays ( = 165) Activity C = 5 and D = 10 days Project Management 116 6

7 Using the Forward and Backward Pass Information What does a slack of workdays for activity D mean for the project manager? It means activity D can be delayed 10 days Activity E must be completed within the time interval 20 and 200 workdays; the activity can start as early as day 20 or finish as late as day 200. Conversely, Activity F, must start on day 20, or the project will be delayed. Project Management 117 Practical Considerations Net work logic rules, for example: if test successful build proto, if failure redesign are not permitted. Activity Numbering, Each activity needs a unique identification code-usually a number. Use of Computers to Develop Networks Calendar Dates; Ultimately you will want to assign calendar dates to your project activities. Multiple Start and Multiple Projects; when several projects are tied together in an organization, using a common start and end node help ti identify the total t planning period of all projects. Use of pseudo or dummy wait activities from the common start node allows different start dates for each project. Project Management 118 7

8 Figure 6.8 Air Control Project Project Management 119 Figure 6.9 Air Control Project Project Management 120 8

9 Extended Network Techniques to Come Closer to Reality Laddering; if that all immediate preceding activities must be 100% complete is too restrictive for some situations found in practice; the activity can be broken into segments and the drawn using a laddering approach, see figure 6.12 Use Lags; is the minimum amount of time a dependent activity must be delayed to begin or end. Finish to Start Relationship, there are situations in which the next activity in a sequence must be delayed even when the preceding activity is complete. Example : removing concrete forms cannot begin until the poured cement has cured for two time unit. Start to Start Relationship, use of lags to reduce detail. Figure 6.14A shows the start to start relationship with zero lag, while figure 6.14B shows the same relationship with a lag of five time units. Figure 6.15 shows the project using an AON network. The start to start relationship reduce network detail and project delays by using lag relationships. Project Management 121 Figure 6.12 Example of Laddering Using Finishto-Start Relationship Project Management 122 9

10 Figure 6.14 Start-to-Start Relationship Project Management 123 Figure 6.15 Use of Lag to Reduce Detail Project Management

11 Extended Network Techniques to Come Closer to Reality Finish to finish Relationship; the finish of one activity depends on the finish of another activity. For example, testing cannot be completed any early than four days after the prototype is complete. See figure 6.17 Start to Finish Relationship, represents situations in which the finish of an activity depends on the start another activity. See figure 6.18 Combinations of lag Relationships; these relationships are usually start to start and finish to finish combinations tied to two activities. For example : debug cannot begin until two time units after coding has started. Coding must be finished four days before debug can be finished. See figure 6.19 Project Management 125 Figure 6.17 Finish to Finish Relationship Project Management

12 Figure 6.18 Start to Finish Relationships Project Management 127 Figure 6.19 Combination Relationships Project Management

13 Figure 6.20 Network Using Lags Project Management 129 Hammock Activities Are frequently used to identify the use of fixed resources or costs over a segment of the project. Typical examples of H A are inspection service, consultants, or Construction management services. See figure 6.21 Project Management

14 Figure 6.21 Hammock Activity Project Management

Constructing Networks

Constructing Networks Constructing Networks 1 Network Terms Project: Obtain a college degree (B.S.) Register 1 Attend class, study etc. 4 Years Receive diploma Event (Node) Activity (Arrow) Event (Node) Activity Relationships

More information

Project Management THE MANAGERIAL PROCESS

Project Management THE MANAGERIAL PROCESS Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Lecture 4 Developing a Project Plan Activity on Node (AON) Copyright 2006 The McGraw-Hill Companies. All rights reserved.

More information

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS) /11/16 Network Diagram 11//16 1 WORK BREAKDOWN STRUCTURE (WBS) A work breakdown structure is a key project deliverable that organizes the team's work into manageable sections. The Project Management Body

More information

Time has the least. amount of flexibility; Schedule issues are the main reason for

Time has the least. amount of flexibility; Schedule issues are the main reason for PMBOK 5 Ed. DEI- Time has the least amount of flexibility; Schedule issues are the main reason for conflicts on projects, especially during the second half of projects The process required to manage timely

More information

Planning & Scheduling

Planning & Scheduling Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,

More information

6 PROJECT TIME MANAGEMENT

6 PROJECT TIME MANAGEMENT CHAPTER 6 PROJECT TIME MANAGEMENT LEARNING OBJECTIVES After reading this chapter, you will be able to: Understand the importance of project schedules and good project time management Define activities

More information

Scheduling. Adapted from John Musser

Scheduling. Adapted from John Musser Scheduling Adapted from John Musser Today Network Fundamentals Gantt Charts PERT/CPM Techniques WBS Review Types: Process, product, hybrid Formats: Outline or graphical organization chart High-level WBS

More information

PMP Exam Preparation Course Project Time Management

PMP Exam Preparation Course Project Time Management Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,

More information

Artificial Intelligence

Artificial Intelligence Artificial Intelligence Combinatorial Optimization G. Guérard Department of Nouvelles Energies Ecole Supérieur d Ingénieurs Léonard de Vinci Lecture 4 Outline 1 2 Decisions about Resource Allocation Which

More information

Project Time Management

Project Time Management Project Time Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Adapted from Managing Information Technology Projects, Schwalbe Learning Objectives Define activities as the basis

More information

Time Management PLANNING

Time Management PLANNING Time Management 6.1 Plan Schedule Management: The process of establishing policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule # Schedule

More information

Project Scope Management

Project Scope Management Project Scope Management Work Breakdown Structure (WBS) Created in Planning Process -> Scope Area Benefits of Work Breakdown Structure Organizes and defines the total scope of the project Helps prevent

More information

Information Technology Project Management, Seventh Edition

Information Technology Project Management, Seventh Edition Information Technology Project Management, Note: See the text itself for full citations. Understand the importance of project schedules and good project time management Discuss the process of planning

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

IST 302 : Project Time Management

IST 302 : Project Time Management IST 302 : Project Time Management Developing quality schedules is important. 1 Schedule issues are the main reason for conflicts on projects There are five core project time management process groups.

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

Cambridge International AS & A Level Computer Science

Cambridge International AS & A Level Computer Science Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05 PDM Precedence Diagramming Method (PDM) Part 1 Con E 441 P05 A. Four (4) possible relationships 1. Finish to Start (FS). Start to Start (SS) 3. 4. Start to Finish (SF) B. Plus combined relationships SS

More information

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8 CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8 Project Scope -Definition A documented description of the project in terms of

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 2 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falconppm.com Agenda 9:00 10:15 Practice the PMP Questions 10:15 10:30 Break 10:30

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Project Scheduling: Lagging, Crashing and Activity Networks

Project Scheduling: Lagging, Crashing and Activity Networks Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-1 Lags in Precedence Relationships The logical relationship

More information

Global Project Management, LLC

Global Project Management, LLC Global Project Management, LLC 2250 Gause Boulevard, Suite 310 Slidell, Louisiana 70461 Tel: 985-781-9190 A Projectis a temporary endeavor undertaken to create a unique product, service, or result. Initiation

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.307 Construction Planning and Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304 호 Project

More information

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Impact Schedules Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Project Management in Practice Fifth Edition

Project Management in Practice Fifth Edition Project Management in Practice Fifth Edition Chapter 5 Scheduling the Project Copyright 2014 John Wiley & Sons, Inc. Introduction Project schedule is the project plan in an altered format It is a convenient

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT PROJECT TIME MANAGEMENT 2020 Powered by POeT Solvers Limited SEQUENCE ACTIVITIES PLANNING MONITORING & CONTROLLING 6.1 Plan Schedule Mgt 6.7 Control Schedule 6.2 Define Activities 6.3 Sequence Activities

More information

Software Project Management

Software Project Management Software Project Management Dr. M.E. Fayad, Professor Computer Engineering Department College of Engineering, San José State University One Washington Square, San José, CA 95192-0180 E-mail: m.fayad@sjsu.edu

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

Estimating and Scheduling

Estimating and Scheduling Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management Project Management Professional (PMP) Exam Prep Course 6 - Project Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Risk Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

Team Member Application

Team Member Application MnDOT Project Management Office Presents: Team Member Application Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

East Central College

East Central College SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

The Project Planning Process Group

The Project Planning Process Group 3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity

More information

Scheduling Resources and Costs

Scheduling Resources and Costs Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used

More information

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT PMP Exam Prep PROJECT SCHEDULE MANAGEMENT Page 223 Schedule Management Process : Contains 6 of the 49 total processes Plan Schedule Management Define

More information

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference Project Planning & CPM Scheduling using MS Project APWA NorCal 2018 Annual Conference What is Planning? Planning: A determination of the what, how, where and by whom ; the tasks that need to be completed

More information

Operations Management

Operations Management 17-1 Project Management Operations Management William J. Stevenson 8 th edition 17-2 Project Management CHAPTER 17 Project Management McGraw-Hill/Irwin Operations Management, Eighth Edition, by William

More information

Calculating and Using Float

Calculating and Using Float Core Scheduling Papers: #5 Calculating and Using Float Origin of Float The concept of schedule float is the creation of the Critical Path Method (CPM) of scheduling. Before 1957 float only had one meaning

More information

Calculating and Using Float

Calculating and Using Float Core Scheduling Papers: #5 Calculating and Using Float Origin of Float The concept of schedule float is the creation of the Critical Path Method (CPM) of scheduling. Before 1957 float only had one meaning

More information

Principles of Planning for IT Projects

Principles of Planning for IT Projects Principles of Planning for IT Projects Introduction Building Timings Exercises Meals & refreshments Mobile Phones Part 1 Setting the Scene 1. Course Objectives 2. Where projects come from 3. What is a

More information

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation NEW PICKIE REQUIRED Course Objectives This course objectives are to teach participants: Introduction to the user interface, How to plan projects without resources, Filters, layouts and printing, Baselines,

More information

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT Course Outline TEC D 205 Engineering Tech Project Planning Week 1 Chapter 4: DEFINING THE PROJECT 1. Step one: Defining the Project Scope A. Employing a Project Scope Checklist 1. Project objective 2.

More information

Imagine this: If you create a hundred tasks and leave their default constraints

Imagine this: If you create a hundred tasks and leave their default constraints Chapter 6 Timing Is Everything In This Chapter Discovering how dependency links affect timing Reviewing the different kinds of dependency relationships Allowing for lag and lead time Creating dependency

More information

Project Time Management

Project Time Management Project Time Management Project Time Management Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management The process of establishing

More information

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1 MGT/437 Project Management Session #2 University of Phoenix 02/12/2004 Brian Smithson 02/12/2004 MGT/437 #2 -- Brian Smithson 1 Agenda Review/Questions Session content PMI project framework Project Knowledge

More information

Luis R. Garcilaso March 13, Lecture #22. Service Processes & Systems Dept. of Mechanical Engineering - Engineering Mechanics

Luis R. Garcilaso March 13, Lecture #22. Service Processes & Systems Dept. of Mechanical Engineering - Engineering Mechanics Lecture #22 Luis R. Garcilaso March 13, 2006 Graphs & Networks Subgraphs Graph coloring Activity networks Route problems Network flow Visibility graph problems Covering problems Project Management Service

More information

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M. Project Scheduling ARCH 738: REAL ESTATE PROJECT MANAGEMENT Morgan State University Jason E. Charalambides, PhD, M.ASCE, AIA, ENV_SP (This material has been prepared for educational purposes) Introduction

More information

Scheduling Concepts and MS. Project AZURITE PROJECT TRAINING AND CONSULTING PVT LTD (OPC) 2014

Scheduling Concepts and MS. Project AZURITE PROJECT TRAINING AND CONSULTING PVT LTD (OPC) 2014 Scheduling Concepts and MS Project 1 About the Faculty- Venkat Annapragada Chem Engg from IIT KGP in 1993 Graduation Process Engineer Cement Industry from 1993 to 1997 IT Industry from 1997 to 2010 Corporate

More information

Examinations for Semester I / 2014 Semester II

Examinations for Semester I / 2014 Semester II Programme BSc (Hons) Management BSc (Hons) Economics and Management Cohort BMANM/09/PT BMANM/L/12B/FT BMANG/12A/12B/FT BMANG/F/12B/FT BMANG/L/12A/FT BEM/12B/FT Examinations for 2014 2015 Semester I / 2014

More information

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155 GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms

More information

Project Planning and Estimating DJ

Project Planning and Estimating DJ Project Planning and Estimating DJ201 0807 Copyright ESI International August 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any

More information

CHAPTER 1. Basic Concepts on Planning and Scheduling

CHAPTER 1. Basic Concepts on Planning and Scheduling CHAPTER 1 Basic Concepts on Planning and Scheduling Eugénio Oliveira Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the and ordering of activities as well

More information

The recommended guided learning hours for this unit are 30 hours.

The recommended guided learning hours for this unit are 30 hours. Unit 281 Project Management 2 Credit 4 Level 2 QCA accreditation number Rationale The aim of this unit is to enable candidates to understand the business environment within which new Projects are initiated.

More information

Retained Logic and Progress Override in Primavera P6

Retained Logic and Progress Override in Primavera P6 By Pat Hendricks TEPCO, LLC www.tepco.us Retained Logic and Progress Override The retained logic and progress override setting can drastically affect a schedule depending on which is used, so understanding

More information

A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim

A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim 2018 International Conference on Mechanical, Electronic and Information Technology (ICMEIT 2018) ISBN: 978-1-60595-548-3 A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim Department

More information

Embarking new Project

Embarking new Project Embarking new Project Go to file, select new. This will open a screen for blank project click ok. You can now enter your project information viz. start date, finish date and also how would you like to

More information

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM)

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) Content Writer/Author: Email id: Mrs. RENU ARORA renu214@gmail.com Structure of Module/Syllabus of module(define

More information

MICROSOFT PROJECT 2007 Level 1

MICROSOFT PROJECT 2007 Level 1 Microsoft Project 2007 Level 1 Contents MICROSOFT PROJECT 2007 Level 1 WWP Learning and Development Page 1 Microsoft Project 2007 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project

More information

Construction Scheduling and Estimating

Construction Scheduling and Estimating P.E. Civil Exam Review: Construction Scheduling and Estimating J.P. Mohsen Email: jpm@louisville.edu 2 Project Management What is a Project? Project unique, one-time operational activity or effort Examples

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context PM Network diagrams in context SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

Links, Lags and Ladders - the subtleties of overlapping tasks -

Links, Lags and Ladders - the subtleties of overlapping tasks - Core Scheduling Papers: #4 Links, Lags and Ladders Logic in a Precedence Network Precedence diagrams use boxes to represent the basic network elements - the task (or activity). Tasks have durations giving

More information

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard Your easy, colorful, SEE-HOW guide! Plain&Simple Microsoft Project 03 Ben Howard Published with the authorization of Microsoft Corporation by O Reilly Media, Inc. 005 Gravenstein Highway North Sebastopol,

More information

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar MBP1133 Project Management Framework Prepared by Dr Khairul Anuar L4 Project Time Management www.notes638.wordpress.com Content 1. Scheduling 2. Common Scheduling Techniques 3. PERT 4. Network Fundamentals

More information

UNCLASSIFIED AH R&pAaduced. by Ute ARMED SERVICES TECHNICAL INFORMATION AGENCY ARLINGTON HALL STATION ARLINGTON 12, VIRGINIA UNCLASSIFIED

UNCLASSIFIED AH R&pAaduced. by Ute ARMED SERVICES TECHNICAL INFORMATION AGENCY ARLINGTON HALL STATION ARLINGTON 12, VIRGINIA UNCLASSIFIED UNCLASSIFIED AH 282 450 R&pAaduced by Ute ARMED SERVICES TECHNICAL INFORMATION AGENCY ARLINGTON HALL STATION ARLINGTON 12, VIRGINIA UNCLASSIFIED i NOTICE: When government or other drawings, sped - fications

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course PMI REP No 3001 Course Number PP6 Administration Evacuation Timings and meals Facilities Mobile

More information

CE2353-CONSTRUCTION PLANNING & SCHEDULING

CE2353-CONSTRUCTION PLANNING & SCHEDULING CE2353-CONSTRUCTION PLANNING & SCHEDULING UNIT-1 CONSTRUCTION PLANNING 1. What is planning? 2. What is construction planning? 3. What are the objectives of planning? 4. What are the types of project plans?

More information

Project Forecast Survey Results Good Scheduling Practices June 2016

Project Forecast Survey Results Good Scheduling Practices June 2016 Good Scheduling Practices 5 June 6 Good Scheduling Practices 5 June 6 Executive Summary There is a saying failing to plan is planning to fail, but what if the plan itself is a failure? The scheduling of

More information

Modern Systems Analysis and Design Seventh Edition

Modern Systems Analysis and Design Seventh Edition Modern Systems Analysis and Design Seventh Edition Jeffrey A. Hoffer Joey F. George Joseph S. Valacich Managing the Information Systems Project Learning Objectives ü Explain the process of managing an

More information

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents Project Planning, Scheduling and Preparation of Quality Assurance Control Documents J.SHARANYASREENIVAS 1, G.GAJALAKSHMI 2, K.RAVI THEJA 3 1P.G Student M.Tech (Structural Engg. and construction managment),

More information

SCHEDULING AND CONTROLLING PRODUCTION ACTIVITIES

SCHEDULING AND CONTROLLING PRODUCTION ACTIVITIES SCHEDULING AND CONTROLLING PRODUCTION ACTIVITIES Al-Naimi Assistant Professor Industrial Engineering Branch Department of Production Engineering and Metallurgy University of Technology Baghdad - Iraq dr.mahmoudalnaimi@uotechnology.edu.iq

More information

Software Process and Management

Software Process and Management Software Process and Management Gu Qing Nanjing University 2006-2-28 1 Chapter 4. Project Scheduling Work Breakdown Structure Considering Dependencies Scheduling the Work Staff Planning Critical Chain

More information

MICROSOFT PROJECT 2007 Level 1

MICROSOFT PROJECT 2007 Level 1 Microsoft Project 2007 Level 1 Contents MICROSOFT PROJECT 2007 Level 1 WWP Training Limited Page 1 Microsoft Project 2007 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project Management

More information

Project Management Techniques

Project Management Techniques Project Management Techniques CHAPTER C Learning Objectives After reading this chapter, you should be able to: Calculate net present value, payback period, and return on investment Chapter Outline Calculating

More information

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Plan Your Work, Work Your Plan Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Agenda Understand what a project is Understand the basics of

More information

SCSD2613 System Analysis and Design. PART II: Project Planning Process

SCSD2613 System Analysis and Design. PART II: Project Planning Process SCSD2613 System Analysis and Design PART II: Project Planning Process 1 Learning Objectives Understand how projects are initiated and selected. Define a business problem and determine the feasibility of

More information

Project Management Glossary of Terms

Project Management Glossary of Terms Project Management Glossary of Terms activity An element of project work that has an expected duration, and usually consumes cost and resources. Activities generally cover one or more tasks from a work

More information

SECTION CONSTRUCTION PROGRESS DOCUMENTATION

SECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

Lecture- 10. Project Scheduling. Dronacharya College of Engineering Lecture- 10 Project Scheduling Dronacharya College of Engineering Scheduling and Planning The majority of projects are 'completed' late, if at all. A project schedule is required to ensure that required

More information

Topic # 12. CIS Project Management: an overview

Topic # 12. CIS Project Management: an overview Topic # 12 CIS Project Management: an overview Project Planning Major Activities during Project Planning: 1) describing project scope, alternatives, and feasibility; 2) dividing the project into manageable

More information

Project Management PSGLE 122. Time and Resources

Project Management PSGLE 122. Time and Resources Project Management PSGLE 122 Time and Resources Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation

More information

MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar

MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar L7 Project Time Management - II www.notes638.wordpress.com Content 1. Slack Time 2. Network Replanning 3. Estimating Activity

More information

MICROSOFT PROJECT 2010 Level 1

MICROSOFT PROJECT 2010 Level 1 MICROSOFT PROJECT 2010 Level 1 Microsoft Project 2010 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project Management Overview... 6 Project Definition Techniques... 7 Project Planning

More information

Information Technology Audit & Cyber Security

Information Technology Audit & Cyber Security Information Technology Audit & Cyber Security Managing Information System Projects Systems & Infrastructure Lifecycle Management Introduction Definitions INTRODUCTION Governance Roles and Responsibilities

More information

EXHIBIT 2-2-C SCHEDULES

EXHIBIT 2-2-C SCHEDULES EXHIBIT 2-2-C SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The Work specified in this section consists of furnishing transportation, labor, materials, equipment, and incidentals necessary for preparation,

More information

Managing Project Time

Managing Project Time Chapter 6 Managing Project Time THE CHALLENGES OF PROJECT TIME MANAGEMENT IN THE PUBLIC SECTOR Private-sector projects often have time constraints. A company may want to introduce a new product as quickly

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2017

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2017 All Rights Reserved No. of Pages - 09 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2017 MGT 30725 Project

More information

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick CPM in Construction Management transition from 7 th to 8 th Edition James J. O Brien Fredric L. Plotnick Introduction to CPM is Still Required Chapter 1. Introduction to CPM Planning and Scheduling 3 1.1

More information

MICROSOFT PROJECT 2002(XP) AND 2003 LEVEL 1

MICROSOFT PROJECT 2002(XP) AND 2003 LEVEL 1 MICROSOFT PROJECT 2002(XP) AND 2003 LEVEL 1 Welcome! Thank you for choosing WWP as your learning and development provider. We hope that your programme today will be a stimulating, informative and rewarding

More information

Work Analysis and Design

Work Analysis and Design END 202 Work Analysis and Design Problem Solving Tools 1 Sibel ALUMUR ALEV January 2011 Methods engineering A technique for increasing the production per unit time or decreasing the cost per unit output

More information

Resource-constrained project scheduling using Relationship Diagramming Method (RDM)

Resource-constrained project scheduling using Relationship Diagramming Method (RDM) Creative Construction Conference 2015 Resource-constrained proect scheduling using Relationship Diagramming Method (RDM) J. Uma Maheswari 1, Purva Muumdar 2, Anshul Goyal 3 & V. Paul C. Charlesra 4 * 1,2,3

More information

Index. Backup plans for presentations, Backward pass, 55 59, 72 73, 102. Saleh Mubarak

Index. Backup plans for presentations, Backward pass, 55 59, 72 73, 102. Saleh Mubarak Index A Accelerated schedule, 211, 329 Accelerating projects See Schedule compression Activities adding or deleting from schedule, 151 152 in arrow networks, 22, 23 in bar charts, 14, 17 contiguous, in

More information

Available online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)

Available online at  ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 123 (2015 ) 308 315 Creative Construction Conference 2015 (CCC2015) Application of Relationship Diagramming Method (RDM) for

More information

Research Article Scheduling Methods for Food Resource Management under the Environment of Cloud

Research Article Scheduling Methods for Food Resource Management under the Environment of Cloud Advance Journal of Food Science and Technology 11(4): 281-285, 2016 DOI:10.19026/ajfst.11.2411 ISSN: 2042-4868; e-issn: 2042-4876 2016 Maxwell Scientific Publication Corp. Submitted: May 5, 2015 Accepted:

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information