Planning & Scheduling

Size: px
Start display at page:

Download "Planning & Scheduling"

Transcription

1 Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1

2 Planning Successful Project Management depends on continues planning. The activities of Designers, Manufacturer, Suppliers & Contractors and all their resources have to be organized & integrated to meet the project objectives. Purpose of Planning: To persuade people to perform before delaying other people involved in the project activities. To provide a framework for decision making in the event of change. 2

3 Activity/Tasks Activities consume resources (materials, labor, Time, Equipment) which are the productive aspects of the project. Sequence of activities will be linked on a time scale to ensure that priorities are identified. It should be expected that a plan will change. Plans must be updated quickly and regularly. The plan should be simple and flexible to be understood & updated quickly 3

4 Six Methods of Scheduling Activity On Arrow (AOA) Activity On Node (AON) GANTT Chart (Bar Chart) Line of Balance Program Evaluation & Review Technique (PERT) Simulation (Mont-Carlo) 4

5 Networks AON Network Activity On Node AOA Network Activity On Arrow 5

6 Critical path method (CPM) CPM critical path method identifies those chains of activities in the project that control how long the project will take. the critical path can be defined as the longest possible path through the "network" of project activities There are two variations of CPM The traditional technique is called activity-on-arrow (Aon-A), or an arrow diagram, because the activities are represented in the network as arrows or lines. The alternative approach is activity-on-node (A-on-N); it s also called the precedence diagram. 6

7 Activity-on-arrow (A-on-A)/activityon- Node (A-on-N) Diagrams Activity-on- Node (A-on-N) Diagram have the following advantages on Arrow diagram: Flexibility since logic is defined in two stages. Dummy activities are eliminated. Revision and introduction of new activities is simple. Overlapping and delaying of activities is easily defined. Use of pre-printed sheets is possible. 7

8 Example 1. Set of Project Activities and Precedence use AON Task Predecessor a -- b -- c d e f g a b b c, d e 8

9 Stage 1 of AON Network 9

10 Stage 2 of AON Network 10

11 A Completed AON Network 11

12 Stage 1 of AOA Network 12

13 Stage 2 of AOA Network 13

14 A Completed AOA Network 14

15 A Completed AOA Network Using a Dummy Task 15

16 Example 2. Find the Critical Path and Critical Time Activity Predecessor Duration a -- 5 days b -- 4 c a 3 d a 4 e a 6 f b, c 4 g d 5 h d, e 6 i f 6 j g, h 4 16

17 Stage 1 of AON Network 17

18 Complete Network 18

19 Float Float is a period of time that will be used to adjust the timing of activity to obtain best possible use of resources. Total Float: is the difference between activities earliest and latest starts or finishes. Free Float: is the min difference between the earliest finish time of that activity and the earliest start time of the succeeding activity. 19

20 Start and finish Early Start (ES): the earliest time that an activity can start as determined by the latest of the early finish of all immediately preceding activities. Early finish (EF): The earliest time that an activity can finish. It is determined by adding the duration of the activity to the early start of the activity. Late Finish(LF): the latest time that an activity can be finished without dealying the project. Late Start (LS): the latest time that an activity can start without delaying the project completion. It is determined by subtracting the duration from the late finish of the activity. 20

21 Precedent notation Early Start(ES) Late Start (LS) Total Float (TF) Activity Name Duration(D) Early Finish (EF) Late Finish(LF) 21

22 Logical relationships between activities Four logical relationship do exist: Finish to start (FS):the successor task can t start until the predecessor task finishes. Start-to-Finish (SF): the successor task cannot finish until the predecessor task starts. Start-to-Start (SS): the successor can t start until the predecessor starts. Finish-to-Finish (FF) : the successor task can t finish until the predecessor task finishes. 22

23 Activities that have different early and late start times (i.e., ES(i,j) < LS(i,j)) can be scheduled to start anytime between ES(i,j) and LS(i,j) The concept of float is to use part or all of this allowable range to schedule an activity without delaying the completion of the project if E(i) + D ij < L(j), then some float is available in which to schedule this activity. 23

24 if one activity is allowed to float or change in the schedule, then the amount of float available for other activities may decrease 24

25 Example 25

26 Example Construct a precedence diagram assuming no research restrictions and calculate the minimum duration of project. Schedule the earliest and latest start and finish for each activity and show the critical path method. If activity F is extended to a duration of 15 days, what is the effect on critical path 26

27 27

28 Precedence diagram 28

29 Traditional Statistics Versus Simulation Similarities must enumerate alternate paths Differences simulation does not require assumption of path independence 29

6 PROJECT TIME MANAGEMENT

6 PROJECT TIME MANAGEMENT CHAPTER 6 PROJECT TIME MANAGEMENT LEARNING OBJECTIVES After reading this chapter, you will be able to: Understand the importance of project schedules and good project time management Define activities

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS) /11/16 Network Diagram 11//16 1 WORK BREAKDOWN STRUCTURE (WBS) A work breakdown structure is a key project deliverable that organizes the team's work into manageable sections. The Project Management Body

More information

Project Time Management

Project Time Management Project Time Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Adapted from Managing Information Technology Projects, Schwalbe Learning Objectives Define activities as the basis

More information

Project Management in Practice Fifth Edition

Project Management in Practice Fifth Edition Project Management in Practice Fifth Edition Chapter 5 Scheduling the Project Copyright 2014 John Wiley & Sons, Inc. Introduction Project schedule is the project plan in an altered format It is a convenient

More information

Scheduling. Adapted from John Musser

Scheduling. Adapted from John Musser Scheduling Adapted from John Musser Today Network Fundamentals Gantt Charts PERT/CPM Techniques WBS Review Types: Process, product, hybrid Formats: Outline or graphical organization chart High-level WBS

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

Developing a Project Plan

Developing a Project Plan Chapter 6 Developing a Project Plan I had six honest serving men who taught men all I know : their names were what and how and why, and when and where and who. Rudyard Kipling Project Management 105 Figure

More information

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8 CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8 Project Scope -Definition A documented description of the project in terms of

More information

PMP Exam Preparation Course Project Time Management

PMP Exam Preparation Course Project Time Management Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,

More information

Constructing Networks

Constructing Networks Constructing Networks 1 Network Terms Project: Obtain a college degree (B.S.) Register 1 Attend class, study etc. 4 Years Receive diploma Event (Node) Activity (Arrow) Event (Node) Activity Relationships

More information

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT PMP Exam Prep PROJECT SCHEDULE MANAGEMENT Page 223 Schedule Management Process : Contains 6 of the 49 total processes Plan Schedule Management Define

More information

Time has the least. amount of flexibility; Schedule issues are the main reason for

Time has the least. amount of flexibility; Schedule issues are the main reason for PMBOK 5 Ed. DEI- Time has the least amount of flexibility; Schedule issues are the main reason for conflicts on projects, especially during the second half of projects The process required to manage timely

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Project Scheduling: Lagging, Crashing and Activity Networks

Project Scheduling: Lagging, Crashing and Activity Networks Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-1 Lags in Precedence Relationships The logical relationship

More information

Artificial Intelligence

Artificial Intelligence Artificial Intelligence Combinatorial Optimization G. Guérard Department of Nouvelles Energies Ecole Supérieur d Ingénieurs Léonard de Vinci Lecture 4 Outline 1 2 Decisions about Resource Allocation Which

More information

Project Scope Management

Project Scope Management Project Scope Management Work Breakdown Structure (WBS) Created in Planning Process -> Scope Area Benefits of Work Breakdown Structure Organizes and defines the total scope of the project Helps prevent

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.307 Construction Planning and Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304 호 Project

More information

Cambridge International AS & A Level Computer Science

Cambridge International AS & A Level Computer Science Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

Project Time Management

Project Time Management Project Time Management Project Time Management Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management The process of establishing

More information

IST 302 : Project Time Management

IST 302 : Project Time Management IST 302 : Project Time Management Developing quality schedules is important. 1 Schedule issues are the main reason for conflicts on projects There are five core project time management process groups.

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

Information Technology Project Management, Seventh Edition

Information Technology Project Management, Seventh Edition Information Technology Project Management, Note: See the text itself for full citations. Understand the importance of project schedules and good project time management Discuss the process of planning

More information

Work Analysis and Design

Work Analysis and Design END 202 Work Analysis and Design Problem Solving Tools 1 Sibel ALUMUR ALEV January 2011 Methods engineering A technique for increasing the production per unit time or decreasing the cost per unit output

More information

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference

Project Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference Project Planning & CPM Scheduling using MS Project APWA NorCal 2018 Annual Conference What is Planning? Planning: A determination of the what, how, where and by whom ; the tasks that need to be completed

More information

Operations Management

Operations Management 17-1 Project Management Operations Management William J. Stevenson 8 th edition 17-2 Project Management CHAPTER 17 Project Management McGraw-Hill/Irwin Operations Management, Eighth Edition, by William

More information

Software Project Management

Software Project Management Software Project Management Dr. M.E. Fayad, Professor Computer Engineering Department College of Engineering, San José State University One Washington Square, San José, CA 95192-0180 E-mail: m.fayad@sjsu.edu

More information

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1 MGT/437 Project Management Session #2 University of Phoenix 02/12/2004 Brian Smithson 02/12/2004 MGT/437 #2 -- Brian Smithson 1 Agenda Review/Questions Session content PMI project framework Project Knowledge

More information

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Risk Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

Lecture 7 PROJECT SCHEDULING. Ferdinand Fassa

Lecture 7 PROJECT SCHEDULING. Ferdinand Fassa Lecture 7 PROJECT SCHEDULING Ferdinand Fassa Outline 1. Review Lecture 6 2. What is Scheduling 3. Planning vs. Scheduling 4. Scheduling methods 5. Scheduling What is Scheduling? There are multiple ways

More information

ENGINEERING MANAGEMENT (GE

ENGINEERING MANAGEMENT (GE بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 4 Scheduling and Bar Chart Contents Objectives of the present lecture Planning and Scheduling Activity and Event Scheduling Techniques

More information

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M. Project Scheduling ARCH 738: REAL ESTATE PROJECT MANAGEMENT Morgan State University Jason E. Charalambides, PhD, M.ASCE, AIA, ENV_SP (This material has been prepared for educational purposes) Introduction

More information

Luis R. Garcilaso March 13, Lecture #22. Service Processes & Systems Dept. of Mechanical Engineering - Engineering Mechanics

Luis R. Garcilaso March 13, Lecture #22. Service Processes & Systems Dept. of Mechanical Engineering - Engineering Mechanics Lecture #22 Luis R. Garcilaso March 13, 2006 Graphs & Networks Subgraphs Graph coloring Activity networks Route problems Network flow Visibility graph problems Covering problems Project Management Service

More information

Time Management PLANNING

Time Management PLANNING Time Management 6.1 Plan Schedule Management: The process of establishing policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule # Schedule

More information

Global Project Management, LLC

Global Project Management, LLC Global Project Management, LLC 2250 Gause Boulevard, Suite 310 Slidell, Louisiana 70461 Tel: 985-781-9190 A Projectis a temporary endeavor undertaken to create a unique product, service, or result. Initiation

More information

Modern Systems Analysis and Design Seventh Edition

Modern Systems Analysis and Design Seventh Edition Modern Systems Analysis and Design Seventh Edition Jeffrey A. Hoffer Joey F. George Joseph S. Valacich Managing the Information Systems Project Learning Objectives ü Explain the process of managing an

More information

PROJECT TIME PLANNING. Process and Bar Chart Technique

PROJECT TIME PLANNING. Process and Bar Chart Technique PROJECT TIME PLANNING Process and Bar Chart Technique Definition of Planning Planning is the process of thinking systematically about the future in order to decide what our goals are, and how we are going

More information

Index. Backup plans for presentations, Backward pass, 55 59, 72 73, 102. Saleh Mubarak

Index. Backup plans for presentations, Backward pass, 55 59, 72 73, 102. Saleh Mubarak Index A Accelerated schedule, 211, 329 Accelerating projects See Schedule compression Activities adding or deleting from schedule, 151 152 in arrow networks, 22, 23 in bar charts, 14, 17 contiguous, in

More information

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155 GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms

More information

PLANNING & SCHEDULING

PLANNING & SCHEDULING PLANNING & SCHEDULING 1 Planning & Scheduling Planning: Process of choosing the method and order of work Scheduling: Process of determining the interrelationship of associated timings of operations. 2

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT PROJECT TIME MANAGEMENT 2020 Powered by POeT Solvers Limited SEQUENCE ACTIVITIES PLANNING MONITORING & CONTROLLING 6.1 Plan Schedule Mgt 6.7 Control Schedule 6.2 Define Activities 6.3 Sequence Activities

More information

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Impact Schedules Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05 PDM Precedence Diagramming Method (PDM) Part 1 Con E 441 P05 A. Four (4) possible relationships 1. Finish to Start (FS). Start to Start (SS) 3. 4. Start to Finish (SF) B. Plus combined relationships SS

More information

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management Instant download and all chapters Test Bank Operations Management 11th Edition Jay Heizer, Barry Render https://testbankdata.com/download/test-bank-operations-management-11thedition-jay-heizer-barry-render/

More information

CE2353-CONSTRUCTION PLANNING & SCHEDULING

CE2353-CONSTRUCTION PLANNING & SCHEDULING CE2353-CONSTRUCTION PLANNING & SCHEDULING UNIT-1 CONSTRUCTION PLANNING 1. What is planning? 2. What is construction planning? 3. What are the objectives of planning? 4. What are the types of project plans?

More information

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar MBP1133 Project Management Framework Prepared by Dr Khairul Anuar L4 Project Time Management www.notes638.wordpress.com Content 1. Scheduling 2. Common Scheduling Techniques 3. PERT 4. Network Fundamentals

More information

A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim

A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim 2018 International Conference on Mechanical, Electronic and Information Technology (ICMEIT 2018) ISBN: 978-1-60595-548-3 A New Networking Technique The Beeline Diagramming Method Seon-Gyoo Kim Department

More information

The recommended guided learning hours for this unit are 30 hours.

The recommended guided learning hours for this unit are 30 hours. Unit 281 Project Management 2 Credit 4 Level 2 QCA accreditation number Rationale The aim of this unit is to enable candidates to understand the business environment within which new Projects are initiated.

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

Project Management THE MANAGERIAL PROCESS

Project Management THE MANAGERIAL PROCESS Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Lecture 4 Developing a Project Plan Activity on Node (AON) Copyright 2006 The McGraw-Hill Companies. All rights reserved.

More information

Information Technology Audit & Cyber Security

Information Technology Audit & Cyber Security Information Technology Audit & Cyber Security Managing Information System Projects Systems & Infrastructure Lifecycle Management Introduction Definitions INTRODUCTION Governance Roles and Responsibilities

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 2 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falconppm.com Agenda 9:00 10:15 Practice the PMP Questions 10:15 10:30 Break 10:30

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context PM Network diagrams in context SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc.

What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc. What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc. Schedule? A PLAN Schedule? Schedule? A PLAN With Respect to Time Schedule? A

More information

Construction Scheduling and Estimating

Construction Scheduling and Estimating P.E. Civil Exam Review: Construction Scheduling and Estimating J.P. Mohsen Email: jpm@louisville.edu 2 Project Management What is a Project? Project unique, one-time operational activity or effort Examples

More information

Planning & scheduling

Planning & scheduling Hashemite University Department of Civil Engineering Construction Planning & scheduling Introduction Dr. Maha alkasasbeh Planning & scheduling Owners want their projects completed within specified time

More information

Lecture- 11. Project Scheduling. Dronacharya College of Engineering

Lecture- 11. Project Scheduling. Dronacharya College of Engineering Lecture- 11 Project Scheduling Dronacharya College of Engineering Project Scheduling Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) Project Scheduling Both techniques (PERT and

More information

Topic # 12. CIS Project Management: an overview

Topic # 12. CIS Project Management: an overview Topic # 12 CIS Project Management: an overview Project Planning Major Activities during Project Planning: 1) describing project scope, alternatives, and feasibility; 2) dividing the project into manageable

More information

Chapter-7# Project Controlling and Scheduling

Chapter-7# Project Controlling and Scheduling Chapter-7# Project Controlling and Scheduling 7.1 Meaning of Project Controlling (PC) PC is concerned with the optimum use of the total resources of an organization to meet the technical, cost and time

More information

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management Project Management Professional (PMP) Exam Prep Course 6 - Project Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Scheduling Resources and Costs

Scheduling Resources and Costs Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used

More information

Team Member Application

Team Member Application MnDOT Project Management Office Presents: Team Member Application Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

SECTION CONSTRUCTION PROGRESS DOCUMENTATION

SECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

CHAPTER 1. Basic Concepts on Planning and Scheduling

CHAPTER 1. Basic Concepts on Planning and Scheduling CHAPTER 1 Basic Concepts on Planning and Scheduling Eugénio Oliveira Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the and ordering of activities as well

More information

RESOURCE MANAGEMENT. Dr. Ahmed Elyamany

RESOURCE MANAGEMENT. Dr. Ahmed Elyamany 1 RESOURCE MANAGEMENT Dr. Ahmed Elyamany Outline Definition of Resources Resource Aggregation/Loading Problems Associated with Resource Resource Leveling Resource Scheduling What a resource? 3 Any thing

More information

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain: Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The

More information

Project Management. Dr. Richard Jerz rjerz.com

Project Management. Dr. Richard Jerz rjerz.com Project Management Dr. Richard Jerz 1 2010 rjerz.com Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt,

More information

Chapter 3 Managing the Information Systems Project

Chapter 3 Managing the Information Systems Project Princess Noura University Computer Science and Information Faculty Information Systems Department IS321 Chapter 3 Managing the Information Systems Project Learning Objectives Discuss skills required to

More information

Estimating and Scheduling

Estimating and Scheduling Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques

More information

Project Management PSGLE 122. Time and Resources

Project Management PSGLE 122. Time and Resources Project Management PSGLE 122 Time and Resources Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation

More information

East Central College

East Central College SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar Lecture 6b Project Time Management - II MBP1123 Scope, Time & Cost Management Prepared by Dr. Zohreh Content 1. Introduction

More information

Examinations for Semester I / 2014 Semester II

Examinations for Semester I / 2014 Semester II Programme BSc (Hons) Management BSc (Hons) Economics and Management Cohort BMANM/09/PT BMANM/L/12B/FT BMANG/12A/12B/FT BMANG/F/12B/FT BMANG/L/12A/FT BEM/12B/FT Examinations for 2014 2015 Semester I / 2014

More information

BA /14/2010. PSU Problem Solving Process. The Last Step 5. The Last Step 8. Project Management Questions PLAN IMPLEMENT EVALUATE

BA /14/2010. PSU Problem Solving Process. The Last Step 5. The Last Step 8. Project Management Questions PLAN IMPLEMENT EVALUATE 1 3 BA 301 Fall 2010 Chapter 6 Achieve BA 301 Research & Analysis of Business Problems 4 The Last Step 5 PLAN IMPLEMENT EVALUATE 6 The Last Step 8 Project Management Questions PLAN IMPLEMENT EVALUATE Project

More information

Project Forecast Survey Results Good Scheduling Practices June 2016

Project Forecast Survey Results Good Scheduling Practices June 2016 Good Scheduling Practices 5 June 6 Good Scheduling Practices 5 June 6 Executive Summary There is a saying failing to plan is planning to fail, but what if the plan itself is a failure? The scheduling of

More information

A D-A1I CRITICAL PATH METHOD NETNORKS AND THEIR USE IN CLAIMS 1/2 ANALYSIS(U) FLORIDA UNIV GAINESVILLE M J PATTERSON usi FE 1984

A D-A1I CRITICAL PATH METHOD NETNORKS AND THEIR USE IN CLAIMS 1/2 ANALYSIS(U) FLORIDA UNIV GAINESVILLE M J PATTERSON usi FE 1984 A D-A1I59 234 CRITICAL PATH METHOD NETNORKS AND THEIR USE IN CLAIMS 1/2 ANALYSIS(U) FLORIDA UNIV GAINESVILLE M J PATTERSON usi FE 1984 N663i4-72-A-3029 FO51 N 134. J 11111120.4 12 11_L ICRCP ESLTO TS HR

More information

Software Process and Management

Software Process and Management Software Process and Management Gu Qing Nanjing University 2006-2-28 1 Chapter 4. Project Scheduling Work Breakdown Structure Considering Dependencies Scheduling the Work Staff Planning Critical Chain

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 22.11.2011 Why? To forecast the events/activities in the building project To lay down deadlines To forecast the requirements of money and other

More information

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

Lecture- 10. Project Scheduling. Dronacharya College of Engineering Lecture- 10 Project Scheduling Dronacharya College of Engineering Scheduling and Planning The majority of projects are 'completed' late, if at all. A project schedule is required to ensure that required

More information

The Project Planning Process Group

The Project Planning Process Group 3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity

More information

Program Evaluation and Review Technique (PERT)

Program Evaluation and Review Technique (PERT) Program Evaluation and Review Technique (PERT) PERT Bar charts and CPM networks assume all activity durations are constant or deterministic. The assumption of constant durations may not be realistic because

More information

Geog 469 GIS Workshop. Project Management

Geog 469 GIS Workshop. Project Management Geog 469 GIS Workshop Project Management Outline Basic principles of project management 6.1 What is a project versus an application? 6.2 What is a scoping statement for your project? 6.3 Why are critical

More information

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill,

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill, Chapter 5 Project Scheduling (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill, Project Scheduling Project Scheduling Project Scheduling important task to completed in

More information

EFFICIENCY OF CRITICAL PATH METHOD (CPM) AND PERT TECHNIQUE FOR YACHT CONSTRUCTION

EFFICIENCY OF CRITICAL PATH METHOD (CPM) AND PERT TECHNIQUE FOR YACHT CONSTRUCTION International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 11, November 2018, pp. 48 54, Article ID: IJMET_09_11_006 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=9&itype=11

More information

PERT and CPM S K Mondal Chapter 5. Time (4) To Calculate ES. To Calculate LS 34, 32 = 34. ES = max ES + t ; ES + t = max 15, 21 = 21

PERT and CPM S K Mondal Chapter 5. Time (4) To Calculate ES. To Calculate LS 34, 32 = 34. ES = max ES + t ; ES + t = max 15, 21 = 21 PERT and CPM S K Mondal Chapter 5 A B C 2 3 4 D E 5 G 7 F 6 H Fulkerson's Rule Time (4) ES = The earliest start time for an activity. The assumption is that all predecessor activities are started at their

More information

Calculating and Using Float

Calculating and Using Float Core Scheduling Papers: #5 Calculating and Using Float Origin of Float The concept of schedule float is the creation of the Critical Path Method (CPM) of scheduling. Before 1957 float only had one meaning

More information

Prepared by: Mr.M.SYED SHAHUL HAMEED CHAPTER 3 SYSTEMS PLANNING - MANAGING SYSTEMS PROJECTS

Prepared by: Mr.M.SYED SHAHUL HAMEED CHAPTER 3 SYSTEMS PLANNING - MANAGING SYSTEMS PROJECTS CHAPTER 3 SYSTEMS PLANNING - MANAGING SYSTEMS PROJECTS 1 Project Management: - Is the process of planning, scheduling, monitoring and controlling and reporting upon the development of an information system.

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 7-1 Project Resources

More information

PROJECT PLANNING AND SCHEDULING

PROJECT PLANNING AND SCHEDULING PROJECT PLANNING AND SCHEDULING AFTAB HAMEED MEMON Office: E6-003A, Makmal Kej. Bangunan Jab. Kej. Bangunan & Peminaan, FKAAS Contact No. 014-2527620 E-mail: ah78memon@hotmail.com Introduction to Project

More information

Seminar 6: Project Management Part 1 Semester 1, 2005

Seminar 6: Project Management Part 1 Semester 1, 2005 IMS 1501 Studio 1: Information Systems Foundations 1 Seminar 6: Project Management Part 1 Semester 1, 2005 Seminar 6.1 - Sem 1, 2005 IMS1501: Unit framework Ethics Documentation Efficiency Tools System

More information

Calculating and Using Float

Calculating and Using Float Core Scheduling Papers: #5 Calculating and Using Float Origin of Float The concept of schedule float is the creation of the Critical Path Method (CPM) of scheduling. Before 1957 float only had one meaning

More information

Seminar 6: Project Management Part 1 Semester 1, 2005

Seminar 6: Project Management Part 1 Semester 1, 2005 IMS1501: Unit framework IMS 1501 Studio 1: Information Systems Foundations 1 Ethics Documentation Developing Information Systems Efficiency Tools Seminar 6: Project Management Part 1 Semester 1, 2005 System

More information

SCSD2613 System Analysis and Design. PART II: Project Planning Process

SCSD2613 System Analysis and Design. PART II: Project Planning Process SCSD2613 System Analysis and Design PART II: Project Planning Process 1 Learning Objectives Understand how projects are initiated and selected. Define a business problem and determine the feasibility of

More information

Project Management Glossary of Terms

Project Management Glossary of Terms Project Management Glossary of Terms activity An element of project work that has an expected duration, and usually consumes cost and resources. Activities generally cover one or more tasks from a work

More information

Design Process & Project Management AN ITERATIVE DESIGN PROCESS. Prof Picone, Mississippi State University. Test Verification

Design Process & Project Management AN ITERATIVE DESIGN PROCESS. Prof Picone, Mississippi State University. Test Verification JEE4980 Sr Design Project Lecture Wilcox Chapter 1 discussion Assignment Team Progress Report due BL Team Meeting Agenda due BL Team Charter 1 ST draft due EL Product Brainstorm due EL Baseline design

More information

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick CPM in Construction Management transition from 7 th to 8 th Edition James J. O Brien Fredric L. Plotnick Introduction to CPM is Still Required Chapter 1. Introduction to CPM Planning and Scheduling 3 1.1

More information

1.Which of the items listed below is not one of the software engineering layers?

1.Which of the items listed below is not one of the software engineering layers? 1.Which of the items listed below is not one of the software engineering layers? Process Manufacturing Methods Tools 2.The software quality assurance activity which is performed to check errors in logic,

More information