1 Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1

2 Planning Successful Project Management depends on continues planning. The activities of Designers, Manufacturer, Suppliers & Contractors and all their resources have to be organized & integrated to meet the project objectives. Purpose of Planning: To persuade people to perform before delaying other people involved in the project activities. To provide a framework for decision making in the event of change. 2

3 Activity/Tasks Activities consume resources (materials, labor, Time, Equipment) which are the productive aspects of the project. Sequence of activities will be linked on a time scale to ensure that priorities are identified. It should be expected that a plan will change. Plans must be updated quickly and regularly. The plan should be simple and flexible to be understood & updated quickly 3

4 Six Methods of Scheduling Activity On Arrow (AOA) Activity On Node (AON) GANTT Chart (Bar Chart) Line of Balance Program Evaluation & Review Technique (PERT) Simulation (Mont-Carlo) 4

5 Networks AON Network Activity On Node AOA Network Activity On Arrow 5

6 Critical path method (CPM) CPM critical path method identifies those chains of activities in the project that control how long the project will take. the critical path can be defined as the longest possible path through the "network" of project activities There are two variations of CPM The traditional technique is called activity-on-arrow (Aon-A), or an arrow diagram, because the activities are represented in the network as arrows or lines. The alternative approach is activity-on-node (A-on-N); it s also called the precedence diagram. 6

7 Activity-on-arrow (A-on-A)/activityon- Node (A-on-N) Diagrams Activity-on- Node (A-on-N) Diagram have the following advantages on Arrow diagram: Flexibility since logic is defined in two stages. Dummy activities are eliminated. Revision and introduction of new activities is simple. Overlapping and delaying of activities is easily defined. Use of pre-printed sheets is possible. 7

8 Example 1. Set of Project Activities and Precedence use AON Task Predecessor a -- b -- c d e f g a b b c, d e 8

9 Stage 1 of AON Network 9

10 Stage 2 of AON Network 10

11 A Completed AON Network 11

12 Stage 1 of AOA Network 12

13 Stage 2 of AOA Network 13

14 A Completed AOA Network 14

15 A Completed AOA Network Using a Dummy Task 15

16 Example 2. Find the Critical Path and Critical Time Activity Predecessor Duration a -- 5 days b -- 4 c a 3 d a 4 e a 6 f b, c 4 g d 5 h d, e 6 i f 6 j g, h 4 16

17 Stage 1 of AON Network 17

18 Complete Network 18

19 Float Float is a period of time that will be used to adjust the timing of activity to obtain best possible use of resources. Total Float: is the difference between activities earliest and latest starts or finishes. Free Float: is the min difference between the earliest finish time of that activity and the earliest start time of the succeeding activity. 19

20 Start and finish Early Start (ES): the earliest time that an activity can start as determined by the latest of the early finish of all immediately preceding activities. Early finish (EF): The earliest time that an activity can finish. It is determined by adding the duration of the activity to the early start of the activity. Late Finish(LF): the latest time that an activity can be finished without dealying the project. Late Start (LS): the latest time that an activity can start without delaying the project completion. It is determined by subtracting the duration from the late finish of the activity. 20

21 Precedent notation Early Start(ES) Late Start (LS) Total Float (TF) Activity Name Duration(D) Early Finish (EF) Late Finish(LF) 21

22 Logical relationships between activities Four logical relationship do exist: Finish to start (FS):the successor task can t start until the predecessor task finishes. Start-to-Finish (SF): the successor task cannot finish until the predecessor task starts. Start-to-Start (SS): the successor can t start until the predecessor starts. Finish-to-Finish (FF) : the successor task can t finish until the predecessor task finishes. 22

23 Activities that have different early and late start times (i.e., ES(i,j) < LS(i,j)) can be scheduled to start anytime between ES(i,j) and LS(i,j) The concept of float is to use part or all of this allowable range to schedule an activity without delaying the completion of the project if E(i) + D ij < L(j), then some float is available in which to schedule this activity. 23

24 if one activity is allowed to float or change in the schedule, then the amount of float available for other activities may decrease 24

25 Example 25

26 Example Construct a precedence diagram assuming no research restrictions and calculate the minimum duration of project. Schedule the earliest and latest start and finish for each activity and show the critical path method. If activity F is extended to a duration of 15 days, what is the effect on critical path 26

27 27

28 Precedence diagram 28

29 Traditional Statistics Versus Simulation Similarities must enumerate alternate paths Differences simulation does not require assumption of path independence 29

PMP Exam Preparation Course Project Time Management

PMP Exam Preparation Course Project Time Management Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,

More information

Cambridge International AS & A Level Computer Science

Cambridge International AS & A Level Computer Science Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

Developing a Project Plan

Developing a Project Plan Chapter 6 Developing a Project Plan I had six honest serving men who taught men all I know : their names were what and how and why, and when and where and who. Rudyard Kipling Project Management 105 Figure

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Artificial Intelligence

Artificial Intelligence Artificial Intelligence Combinatorial Optimization G. Guérard Department of Nouvelles Energies Ecole Supérieur d Ingénieurs Léonard de Vinci Lecture 4 Outline 1 2 Decisions about Resource Allocation Which

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

IST 302 : Project Time Management

IST 302 : Project Time Management IST 302 : Project Time Management Developing quality schedules is important. 1 Schedule issues are the main reason for conflicts on projects There are five core project time management process groups.

More information

Software Project Management

Software Project Management Software Project Management Dr. M.E. Fayad, Professor Computer Engineering Department College of Engineering, San José State University One Washington Square, San José, CA 95192-0180 E-mail: m.fayad@sjsu.edu

More information

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M. Project Scheduling ARCH 738: REAL ESTATE PROJECT MANAGEMENT Morgan State University Jason E. Charalambides, PhD, M.ASCE, AIA, ENV_SP (This material has been prepared for educational purposes) Introduction

More information

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155 GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms

More information

Operations Management

Operations Management 17-1 Project Management Operations Management William J. Stevenson 8 th edition 17-2 Project Management CHAPTER 17 Project Management McGraw-Hill/Irwin Operations Management, Eighth Edition, by William

More information

Project Management THE MANAGERIAL PROCESS

Project Management THE MANAGERIAL PROCESS Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Lecture 4 Developing a Project Plan Activity on Node (AON) Copyright 2006 The McGraw-Hill Companies. All rights reserved.

More information

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05 PDM Precedence Diagramming Method (PDM) Part 1 Con E 441 P05 A. Four (4) possible relationships 1. Finish to Start (FS). Start to Start (SS) 3. 4. Start to Finish (SF) B. Plus combined relationships SS

More information

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

RESOURCE MANAGEMENT. Dr. Ahmed Elyamany

RESOURCE MANAGEMENT. Dr. Ahmed Elyamany 1 RESOURCE MANAGEMENT Dr. Ahmed Elyamany Outline Definition of Resources Resource Aggregation/Loading Problems Associated with Resource Resource Leveling Resource Scheduling What a resource? 3 Any thing

More information

Topic # 12. CIS Project Management: an overview

Topic # 12. CIS Project Management: an overview Topic # 12 CIS Project Management: an overview Project Planning Major Activities during Project Planning: 1) describing project scope, alternatives, and feasibility; 2) dividing the project into manageable

More information

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management Instant download and all chapters Test Bank Operations Management 11th Edition Jay Heizer, Barry Render https://testbankdata.com/download/test-bank-operations-management-11thedition-jay-heizer-barry-render/

More information

Estimating and Scheduling

Estimating and Scheduling Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques

More information

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain: Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context PM Network diagrams in context SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

CHAPTER 1. Basic Concepts on Planning and Scheduling

CHAPTER 1. Basic Concepts on Planning and Scheduling CHAPTER 1 Basic Concepts on Planning and Scheduling Eugénio Oliveira Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the and ordering of activities as well

More information

Calculating and Using Float

Calculating and Using Float Core Scheduling Papers: #5 Calculating and Using Float Origin of Float The concept of schedule float is the creation of the Critical Path Method (CPM) of scheduling. Before 1957 float only had one meaning

More information

Project Forecast Survey Results Good Scheduling Practices June 2016

Project Forecast Survey Results Good Scheduling Practices June 2016 Good Scheduling Practices 5 June 6 Good Scheduling Practices 5 June 6 Executive Summary There is a saying failing to plan is planning to fail, but what if the plan itself is a failure? The scheduling of

More information

Chapter 3 Managing the Information Systems Project

Chapter 3 Managing the Information Systems Project Princess Noura University Computer Science and Information Faculty Information Systems Department IS321 Chapter 3 Managing the Information Systems Project Learning Objectives Discuss skills required to

More information

Project management tools and techniques assist project managers and their teams in various aspects of project management Some specific ones include

Project management tools and techniques assist project managers and their teams in various aspects of project management Some specific ones include Abeer Bin Humaid Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements Triple constraints of project management Every

More information

Program Evaluation and Review Technique (PERT)

Program Evaluation and Review Technique (PERT) Program Evaluation and Review Technique (PERT) PERT Bar charts and CPM networks assume all activity durations are constant or deterministic. The assumption of constant durations may not be realistic because

More information

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick

CPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick CPM in Construction Management transition from 7 th to 8 th Edition James J. O Brien Fredric L. Plotnick Introduction to CPM is Still Required Chapter 1. Introduction to CPM Planning and Scheduling 3 1.1

More information

1.Which of the items listed below is not one of the software engineering layers?

1.Which of the items listed below is not one of the software engineering layers? 1.Which of the items listed below is not one of the software engineering layers? Process Manufacturing Methods Tools 2.The software quality assurance activity which is performed to check errors in logic,

More information

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents Project Planning, Scheduling and Preparation of Quality Assurance Control Documents J.SHARANYASREENIVAS 1, G.GAJALAKSHMI 2, K.RAVI THEJA 3 1P.G Student M.Tech (Structural Engg. and construction managment),

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources

More information

INDIAN INSTITUTE OF MATERIALS MANAGEMENT Post Graduate Diploma in Materials Management PAPER 18 C OPERATIONS RESEARCH.

INDIAN INSTITUTE OF MATERIALS MANAGEMENT Post Graduate Diploma in Materials Management PAPER 18 C OPERATIONS RESEARCH. INDIAN INSTITUTE OF MATERIALS MANAGEMENT Post Graduate Diploma in Materials Management PAPER 18 C OPERATIONS RESEARCH. Dec 2014 DATE: 20.12.2014 Max. Marks: 100 TIME: 2.00 p.m to 5.00 p.m. Duration: 03

More information

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM)

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) Content Writer/Author: Email id: Mrs. RENU ARORA renu214@gmail.com Structure of Module/Syllabus of module(define

More information

Today s Lecture. Fall 2004 SE 101 Introduction to Software Engineering 2

Today s Lecture. Fall 2004 SE 101 Introduction to Software Engineering 2 Project Planning Today s Lecture 1. Intro to Software Engineering 2. Inexact quantities 3. Error propagation 4. Floating-point numbers 5. Design process 6. Teamwork - no web review 7. Project planning

More information

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Plan Your Work, Work Your Plan Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Agenda Understand what a project is Understand the basics of

More information

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard Your easy, colorful, SEE-HOW guide! Plain&Simple Microsoft Project 03 Ben Howard Published with the authorization of Microsoft Corporation by O Reilly Media, Inc. 005 Gravenstein Highway North Sebastopol,

More information

Project Planning and Estimating DJ

Project Planning and Estimating DJ Project Planning and Estimating DJ201 0807 Copyright ESI International August 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any

More information

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Hill International Construction CPM Conference

More information

Planning & Scheduling CSTM 102

Planning & Scheduling CSTM 102 Planning & Scheduling CSTM 102 Items Big A Project on Website Thursday Discuss Big A Project next Tuesday April 18, 2011 CPM Scheduling You were the successful bidder! What s next? Procurement/Buy

More information

Project Management Techniques

Project Management Techniques Project Management Techniques CHAPTER C Learning Objectives After reading this chapter, you should be able to: Calculate net present value, payback period, and return on investment Chapter Outline Calculating

More information

Project Scheduling with GanttProject. EGR 386w

Project Scheduling with GanttProject. EGR 386w Project Scheduling with GanttProject EGR 386w 1 GanttProject http://www.ganttproject.biz/ Download version 2.6.x Has numbered tasks option The video (access from ganttproject.biz) http://www.youtube.com/watch?v=5rhcsa5ad34&feature=youtu.be

More information

Retained Logic and Progress Override in Primavera P6

Retained Logic and Progress Override in Primavera P6 By Pat Hendricks TEPCO, LLC www.tepco.us Retained Logic and Progress Override The retained logic and progress override setting can drastically affect a schedule depending on which is used, so understanding

More information

MICROSOFT PROJECT 2007 Level 1

MICROSOFT PROJECT 2007 Level 1 Microsoft Project 2007 Level 1 Contents MICROSOFT PROJECT 2007 Level 1 WWP Learning and Development Page 1 Microsoft Project 2007 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project

More information

Project Management for Facility Constructions

Project Management for Facility Constructions Project Management for Facility Constructions A Guide for Engineers and Architects Bearbeitet von Alberto De Marco 1. Auflage 2011. Buch. viii, 189 S. Hardcover ISBN 978 3 642 17091 1 Format (B x L): 15,5

More information

DEPARTMENT OF MCA CLASS / YEAR : III MCA SUB. CODE & NAME: MC9252, SOFTWARE PROJECT MANAGEMENT. UNIT I 2 MARKS QUESTIONS & ANSWERS 1. What is software project management? Software project management is

More information

PRINCESS NOURA UNIVESRSITY. Project Management BUS 302. Reem Al-Qahtani

PRINCESS NOURA UNIVESRSITY. Project Management BUS 302. Reem Al-Qahtani PRINCESS NOURA UNIVESRSITY Project BUS 302 Reem Al-Qahtani This is only for helping reading the PMBOK it has our notes for focusing on the book Project Framework What is PMBOK? o PMBOK= Project Body of

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

Andrew Avalon, P.E., PSP

Andrew Avalon, P.E., PSP Andrew Avalon, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Andrew Avalon,

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

Application of a PERT-Type System and "Crashing" in a Food Service Operation

Application of a PERT-Type System and Crashing in a Food Service Operation Hospitality Review Volume 7 Issue 2 Hospitality Review Volume 7/Issue 2 Article 8 1-1-1989 Application of a PERT-Type System and "Crashing" in a Food Service Operation Glenn A. Leitch Michigan State University,

More information

Project Management Concepts, Tools & Techniques

Project Management Concepts, Tools & Techniques Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid

More information

Project Management CSC 310 Spring 2017 Howard Rosenthal

Project Management CSC 310 Spring 2017 Howard Rosenthal Project Management CSC 310 Spring 2017 Howard Rosenthal 1 No?ce This course is based on and includes material from the text: Effective Project Management - Traditional, Agile, Extreme 7TH Edition Authors:

More information

Sensitivity and Risk Path Analysis John Owen, Vice President Barbecana, Inc.

Sensitivity and Risk Path Analysis John Owen, Vice President Barbecana, Inc. Sensitivity and Risk Path Analysis John Owen, Vice President Barbecana, Inc. Sensitivity Analysis Sensitivity Analysis shows us which tasks are creating uncertainty in a selected outcome. The outcome might

More information

FALL MGMT 405/ FINAL EXAM/REVISION

FALL MGMT 405/ FINAL EXAM/REVISION Business Department FALL 2017-18 MGMT 405/ FINAL EXAM/REVISION MGMT 405, Production Man. Section A/Multiple Choice-30% Revision 1) Which of the following part does not indicate the concept of project?

More information

Scheduling. Why Schedule? Scheduling will: Delivering On Your Promises

Scheduling. Why Schedule? Scheduling will: Delivering On Your Promises Scheduling Delivering On Your Promises Why Schedule? Don t need to, I ve done this before. I have the schedule in my head. Nobody will pay attention to it. Why bother, it just changes. I m on the line

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

ACTIVITY SCHEDULING IN THE DYNAMIC, MULTI-PROJECT SETTING: CHOOSING HEURISTICS THROUGH DETERMINISTIC SIMULATION. Robert C. Ash

ACTIVITY SCHEDULING IN THE DYNAMIC, MULTI-PROJECT SETTING: CHOOSING HEURISTICS THROUGH DETERMINISTIC SIMULATION. Robert C. Ash Proceedings of the 999 Winter Simulation Conference P. A. Farrington, H. B. Nembhard, D. T. Sturrock, and G. W. Evans, eds. ACTIVITY SCHEDULING IN THE DYNAMIC, MULTI-PROJECT SETTING: CHOOSING HEURISTICS

More information

A Framework for Project Management. The Project Management Institute Education Department

A Framework for Project Management. The Project Management Institute Education Department A Framework for Project Management The Project Management Institute Education Department Your Expectations What would you like to learn from this experience? Solution to a specific problem? Project management

More information

MICROSOFT PROJECT 2002(XP) AND 2003 LEVEL 1

MICROSOFT PROJECT 2002(XP) AND 2003 LEVEL 1 MICROSOFT PROJECT 2002(XP) AND 2003 LEVEL 1 Welcome! Thank you for choosing WWP as your learning and development provider. We hope that your programme today will be a stimulating, informative and rewarding

More information

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT Course Outline TEC D 205 Engineering Tech Project Planning Week 1 Chapter 4: DEFINING THE PROJECT 1. Step one: Defining the Project Scope A. Employing a Project Scope Checklist 1. Project objective 2.

More information

PS.08. Let s Scrap the Precedence Diagramming Method

PS.08. Let s Scrap the Precedence Diagramming Method 2004 AACE International Transactions PS.08 Let s Scrap the Precedence Diagramming Method Earl T. Glenwright Jr. THE STATE OF CONSTRUCTION SCHEDULING PRACTICES AND SCHEDULES WHY PRECEDENCE DIAGRAMMING WAS

More information

Project Scheduling and Tracking. CIS 375 Bruce R. Maxim UM-Dearborn

Project Scheduling and Tracking. CIS 375 Bruce R. Maxim UM-Dearborn Project Scheduling and Tracking CIS 375 Bruce R. Maxim UM-Dearborn 1 What does the customer want to know? Do you understand my needs? Can you design a system to help me? How long will it take? How much

More information

MICROSOFT PROJECT 2010 Level 1

MICROSOFT PROJECT 2010 Level 1 MICROSOFT PROJECT 2010 Level 1 Microsoft Project 2010 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project Management Overview... 6 Project Definition Techniques... 7 Project Planning

More information

Chapter 7: Project Planning: Task Determination and Resource Assignment

Chapter 7: Project Planning: Task Determination and Resource Assignment Project and Process Management Chapter 7: Project Planning: Task Determination and Resource Assignment The Why, What and How of Project Planning Defining Project Boundaries and Scope Breaking Your Project

More information

Resource-constrained project scheduling using Relationship Diagramming Method (RDM)

Resource-constrained project scheduling using Relationship Diagramming Method (RDM) Creative Construction Conference 2015 Resource-constrained proect scheduling using Relationship Diagramming Method (RDM) J. Uma Maheswari 1, Purva Muumdar 2, Anshul Goyal 3 & V. Paul C. Charlesra 4 * 1,2,3

More information

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A Deltek Acumen Planning, Risk, Acceleration Tom Polen Director, Solution Architecture Learning Objectives The 5 steps 1. Capturing uncertainty: calibrating the schedule 2. Identifying risk events: accounting

More information

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

PMP Sample Questions  Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope? PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document

More information

Vrije Universiteit Amsterdam Faculty of Exact Sciences. Exam: Software Project Management Version A. Dr. Nelly Condori-Fernandez. Date: May 27, 2015

Vrije Universiteit Amsterdam Faculty of Exact Sciences. Exam: Software Project Management Version A. Dr. Nelly Condori-Fernandez. Date: May 27, 2015 Vrije Universiteit Amsterdam Faculty of Exact Sciences Exam: Software Project Management Version A Code: Coordinator: X_401093 Dr. Nelly Condori-Fernandez Date: May 27, 2015 Duration: Calculator allowed:

More information

Resource-Constrained Multi-Project Scheduling with Resource Moving Time for Construction Projects in Vietnam

Resource-Constrained Multi-Project Scheduling with Resource Moving Time for Construction Projects in Vietnam First International Conference on Construction In Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi,, Pakistan Resource-Constrained

More information

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202 Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 June 28, 2017 ADDENDUM NUMBER: TWO (2) TITLE: Riverview Water Main Extension Phase

More information

PART SEVEN. Project Management. The chapter in this section covers various topics related to managing projects.

PART SEVEN. Project Management. The chapter in this section covers various topics related to managing projects. r C PART SEVEN Project Management The chapter in this section covers various topics related to managing projects. H Hfl7 1. I d t.] [Ii IT[4 Ui4 Iii LEARNING OBJECTIVES After completing this chapter; you

More information

Micro Planner X-Pert

Micro Planner X-Pert Micro Planner X-Pert V3.5.1 Overview Presenter: Patrick Weaver PMI-SP Micro Planning International Asia Pacific Cell:+61 418 53 1111 raf@microplanning.com.au. Arrow Diagram Precedence Diagram Working

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course PMI REP No 3001 Course Number PP6 Administration Evacuation Timings and meals Facilities Mobile

More information

The Performance of Heuristic Rules in Resource Constrained Project Scheduling

The Performance of Heuristic Rules in Resource Constrained Project Scheduling The Performance of Heuristic Rules in Resource Constrained Project Scheduling OSMAN HÜROL TÜRKAKIN Department of Civil Engineering Istanbul University 34320 Avcılar, Faculty of Engineering, Istanbul, Turkey

More information

MICROSOFT PROJECT. Global Information Systems

MICROSOFT PROJECT. Global Information Systems Global Information Systems MICROSOFT PROJECT This manual is not a complete discussion of project management, but you need to be familiar with some of the basic terms and concepts that are used in most

More information

Management Terminology

Management Terminology Management Terminology Acceptance Acceptance Criteria Accounting Period Acquisition Active Listening Activity Activity Definition Activity Description (AD) Activity Duration Estimating Activity-On- Arrow

More information

Glossary bglos.indd 10/28/2015 Page 1

Glossary bglos.indd 10/28/2015 Page 1 Glossary 2 Glossary Numbers 360 degree review A form of project performance appraisal (a tool and technique of the Manage Project Team process) that solicits feedback from everyone with whom the team member

More information

Project, People, Processes and Products

Project, People, Processes and Products Project, People, Processes and Products Project management skills schedule, monitoring, risk management, People management skills delegation, mentoring, staffing, promoting, evaluating, training, Process

More information

ACTIVITY SCHEDULE AND AFFECTIVE CONTROL OF COMPONENT BASED PROJECT

ACTIVITY SCHEDULE AND AFFECTIVE CONTROL OF COMPONENT BASED PROJECT ACTIVITY SCHEDULE AND AFFECTIVE CONTROL OF COMPONENT BASED PROJECT P. K. Suri 1, Karambir 2 1 Dean (Academic and Research & Development) and Chairman,(CSE/DCSA) Deptt, HCTM, Kaithal, Haryana, India 2 Assistant

More information

Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek

Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek Schedule Margin Contingency for Schedulers John Owen, Product Manager Schedule and Risk, Deltek Contingency / Management Reserve Let s start with a question Have you ever seen a project without any Contingency

More information

SOFTWARE ENGINEERING Staffing Level Estimation and Scheduling

SOFTWARE ENGINEERING Staffing Level Estimation and Scheduling SOFTWARE ENGINEERING Staffing Level Estimation an Scheuling Staffing level estimation Once the effort require to evelop a software has been etermine, it is necessary to etermine the staffing requirement

More information

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation

More information

Scheduling for Success with Critical Chain. Abstract

Scheduling for Success with Critical Chain. Abstract by Rob Newbold, September 2010 Abstract The Critical Chain scheduling approach described in this paper can be used to create good schedules that have provided substantial benefits in speed, predictability,

More information

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management PMP Training Training Topics Chapter 1 Introduction to PMP Objectives of PMP Requirements for PMP Exam About PMP Exam PMP Exam Syllabus Chapter 2 Objectives of Project Management Framework What is Project

More information

Management of Projects

Management of Projects of Projects Giuseppe Lami Page 1 Course Outline! Part 1: The Project (PM) Framework! Part 2: The PM as a Process! Part 3: Techniques, Methods and Tools Supporting the PM! Part 4: Requirements Engineering

More information

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE December 25, 17 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and

More information

Principles of Schedule Contingency Management

Principles of Schedule Contingency Management Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation

More information

Understanding Import & Export with NetPoint 4.2

Understanding Import & Export with NetPoint 4.2 Understanding Import & Export with NetPoint 4.2 Eric Lowther PMA Consultants 1 Primary Differences Regarding Import/ Export CPM Tools F9 and Early/Late Dates Float & Total Float Gantt Charts (Waterfall

More information

Available online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)

Available online at  ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 123 (2015 ) 308 315 Creative Construction Conference 2015 (CCC2015) Application of Relationship Diagramming Method (RDM) for

More information

Implement. Control. Integrate. Knowledge Leverage. Course Overview

Implement. Control. Integrate. Knowledge Leverage. Course Overview Conceptualize Plan Plan & Deliver Organize Implement Control Change if Required Integrate Deliver & Closeout Knowledge Leverage Course Overview The Certificate In Project Management (CIPM) exam is administered

More information

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text.

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text. Construction Planning ISBN 978-0-7277-6057-9 ICE Publishing: All rights reserved http://dx.doi.org/10.1680/cp2e.60579.191 Index Page locators in italics and bold respectively refer to figures and tables

More information

2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline -

2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline - 2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline - PREPARED BY: Jake Lilley, PMP President PPM Global Services, Inc. P: 1-800-746-4029 F: 1-800-746-4029 E: jlilley@ppmglobalservices.com

More information

A Practical Approach using CPM/PERT: for Certain Activity Times in Construction Parking Project

A Practical Approach using CPM/PERT: for Certain Activity Times in Construction Parking Project World Applied Sciences Journal 35 (7): 1180-1184, 2017 ISSN 1818-4952 IDOSI Publications, 2017 DOI: 10.5829/idosi.wasj.2017.1180.1184 A Practical Approach using CPM/PERT: for Certain Activity Times in

More information

Deliverable Factors of Manpower Requirement Plan: An Evidence from Indian EPC Company

Deliverable Factors of Manpower Requirement Plan: An Evidence from Indian EPC Company Deliverable Factors of Manpower Requirement Plan: An Evidence from Indian EPC Company Amruth Gurudev S #1, Srinivasa Rao Potti *2, Shiva Prasad H.C #3 # 1 PG Research Scholar, Humanities and Management,

More information

MINGGU Ke 2 Analisa dan Perancangan Sistem Informasi

MINGGU Ke 2 Analisa dan Perancangan Sistem Informasi MINGGU Ke 2 Analisa dan Perancangan Sistem Informasi Pokok Bahasan: Project Management Tujuan Instruksional Khusus: Learing to Choose and Manage System Information Project Referensi: (1) Hoffer, J.A.,

More information

Module #4 Time Impact Analysis

Module #4 Time Impact Analysis Reviewing & Analyzing CPM Construction Schedules Module #4 Forward looking schedule analysis technique that adds a modeled delay to an accepted contract schedule to determine the possible impact of that

More information

Critical path analysis and queuing

Critical path analysis and queuing ritical path analysis and queuing syllabusref eferenceence Elective topic Operations research networks and queuing In this cha chapter ritical path analysis ritical path analysis with backward scanning

More information

Project management practice by the public sector in a developing country

Project management practice by the public sector in a developing country PERGAMON International Journal of Project Management 18 (2000) 105±109 www.elsevier.com/locate/ijproman Project management practice by the public sector in a developing country Ghaleb Y. Abbasi *, Hisham

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR

More information