Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Size: px
Start display at page:

Download "Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M."

Transcription

1 Project Scheduling ARCH 738: REAL ESTATE PROJECT MANAGEMENT Morgan State University Jason E. Charalambides, PhD, M.ASCE, AIA, ENV_SP (This material has been prepared for educational purposes) Introduction 2

2 Introduction! There is a timing factor that relates the series of activities to the cost and to the execution of a Construction Project.! Scheduling can be considered as the process of designing the interrelationships of activities and timing from the beginning to the conclusion of a Project.! For the generation of a Construction Schedule the following need to be organized: " Fragmentation of project into activities " Designing relationships between activities " Construction of diagrams indicating activities and durations " Determining a Critical Path 3 Introduction! Some Fundamental Definitions: " Activity: Work with estimated timing that will yield a defined outcome. An activity would have an estimated cost and an expected amount of man-hours " Man-hour: An hour of work for a worker (depends on type of activity and skill level) " Float/Slack: The number of days within which an activity can start and finish. An activity may be possible to start early and finish early, or start late and finish late without impacting the total project time. " Critical Path: The set of activities that have no float and determine the total duration of the project. Any modification to the Critical Path will impact the duration of the project 4

3 Introduction! There are three basic methods of representation of a project schedule that we shall address in this course: " Bar/Gantt Charts " Network Analysis / CPM & " PERT 5 Introduction! Steps to be Taken " Define the activities " Sequence them " Estimate time for each activity " Develop the schedule! Techniques " Gantt Chart " CPM " PERT " Computer software hybrid methods 6

4 !!!! Activity Duration 7 Activity Duration! An Activity has to be defined! The quantity of work per activity is calculated " Measure from plans and specifications! Available resources should be identified and quantified! Labor and Equipment productivity should be determined! Activity durations are calculated by division of Quantity of work by Work Labor and/or Equipment Productivity Quantity of Work T = Productivity! Productivity Rates can be obtained from: " RS Means " Other published records (if available) " Company's historical records " Or through Project Manager's and site Foremen's experience and expertise. 8

5 Activity Duration! Example: " Measure the time it takes for a 4,000 cubic yards of loose soil to be removed. " Production per hour:! If the excavator can operate about 0.75 yd 3 per minute on that type of soil Productivity= 0.75yd = 45yd 1 min 1 hour " Therefore, it can be estimated that the total amount of time necessary for one operator with an excavator will take... 3 Time= 4000yd 45 yd 3 hour 89 hour " Note that the above estimation does not account for contingencies such as meal breaks etc. 9 Bar/Gantt Charts 10

6 ! Example of a Bar Chart generated on MS. Project 11 Bar Charts! What are they? " Gantt charts are set on two axes. The Abscissa is dedicated to time reference, and the Ordinates indicate a series of activities. " It is visually simple method that allows users to illustrate the start and finish dates of the activities. " Gantt charts generated by contemporary software such as MS Project, or the more advanced Primavera) also show the dependencies and the relationships between activities, as well as current schedule status using percent-complete shadings and a vertical "TODAY" line. 12

7 Bar Charts! Example " A very simple Bar Chart 13! Example Bar Charts " Gannt Chart with dependencies,! Note the numbers that refer to the week of beginning of an activity and the week of ending of an activity.! Arrows indicate the dependency of an activity upon the completion of another activity " Source: Woodgate,

8 Bar Charts Vs Networks! Transition " As seen here, the qualities and characteristics of one method can be infused in another. " On top we see a typical Gannt chart that includes the critical path of the project, and on the bottom a network with Activity on Axis that also indicates the critical path 15! Use Gantt / Bar Charts " There is a lot of software that is available at this time that can perform a vey sophisticated set of tasks that will lay out a schedule in Bar Charts. " Primavera happens to be a very advanced program but it is also a very complicated software where professionals with many years of experience end up not knowing many of the hidden treasures it carries. " Microsoft project is a much more affordable type of software that can be learnt within a few hours of simple experimentation, and would be more than adequate for smaller to medium size projects. " The method indicates milestones/events/activities in a time order. 16

9 CPM / PERT 17! Example of Network with Critical Path Method 18

10 Critical Path Method! Main Points " Created by DuPont & Remington Rand (1956). " Deterministic task times " Activity on Node Construction " Also known as the Cost/Time Trade-off analysis method 19! Example of Activity on Arrow PERT network 20

11 Project Evaluation and Review Technique! Main Points " Developed by the US Navy, Booz & Hamilton, and Lockheed Co " Multiple task time estimates " Was specifically designed for the Polaris Missile " Activity on Arrow network construction " Probabilistic method - Uses probability theory and applies three time estimates 21 CPM / PERT Networks! Activity on Node " Nodes represent activities, and arrows show precedence relationships! Activity on Arrow " Arrows represent activities and nodes are events for points of time! Event " Completion or beginning of an activity in a project 22

12 CPM / PERT Networks! Some Standard Procedures: 23 CPM / PERT Networks! Some Standard Procedures: 24

13 CPM / PERT Networks! Activity on Axis " The activity is indicated on the axis together with the duration (e.g. days) allowing the user to calculate the total time for the project, " But this is not as flexible as the AON. 25 CPM / PERT Networks! What if we have concurrent activities in AOΑ? Incorrect Precedence Relationship Correct Precedence Relationship " Two nodes can never be connected through two activities. For concurrent activities, a third node and a dummy activity may be used instead 26

14 CPM / PERT Networks! Determining the Critical Path in a schedule " Consider that on each node the upper number is the activity, and the lower number is the duration (e.g days) and try all scenarios:! yields 10 days! yields 9 days! yields 8 days! yields 9 days 27 CPM / PERT Networks! Determining the Critical Path in a schedule " The longest of the paths is the critical path, in this case the path ! Critical is the longest! That path determines the minimum amount of time (average) that the project will take 28

15 CPM / PERT Networks! Slack or Float " Slack or Float refers to the amount of time can be delayed without disturbing the finish time of the project! That means that the Critical Path is undisturbed.! No activity on the Critical Path has Slack " There are two types of Slack: " Total Slack TS! That is the difference between ES and LS times, or equivalently, LF and LS times. " Free Slack FS! That is the difference between the EF time and the earliest of the ES times of all its immediate predecessors. 29 CPM / PERT Networks! Forward Pass " Having a number of days within which an activity can take place is what we call a slack or float. " Given this "float" time, the manager can determine the early start and early finish dates for all of the uncompleted segments of work for all network activities. " Calculation of the early start date and early finish date accommodates the manager in deciding the earliest possible allocation of the resources that may be needed for completion of the project and the activities contained within, such as the expenditure of the resources and expenditures of man hours. 30

16 CPM / PERT Networks! Backward Pass " Similar in concept (and opposite in direction) is the backward pass in the area of project management. " It is the calculation of late finish dates and late start dates for the portions of schedule activities that have not been completed and it is determined by starting at the project s scheduled end date and working backwards through the schedule network logic. " The end date may be set by the assigning party, or it may be determined through use of a forward pass. " To accommodate an easier visual aid to forward and backward pass, another method of graphing the AON is indicated in the next slide 31 CPM / PERT Networks! Mode Configuration for Activity on Node 32

17 CPM / PERT Networks! Conducting a Forward and a Backward Pass " Using the node design that accommodates the information for early start & finish, and late start & finish, applied on the diagrammed schedule below, a Forward Pass and a Backward Pass will be conducted: 33 CPM / PERT Networks! Conducting a Forward Pass " Using the following diagrammed schedule, a Forward Pass will be executed:! Start at the beginning of the CPM/PERT network to determine the earliest activity times! Earliest Start Time (ES) " Earliest time an activity can start " ES=Maximum EF of immediate predecessors! Earliest Finish Time (EF) " Earliest time an activity can finish " Earliest start time plus activity time EF =ES +t 34

18 CPM / PERT Networks! Conducting a Forward Pass " By following this process, a network indicating the Earliest Activity Start and Finish Times can be constructed: 35 CPM / PERT Networks! Conducting a Forward Pass " One more view with arrows explaining the way time is added: " " " " " " " " " " " So here we see how activity 1 ends on the 3 rd month and activity 7 ends on the 10 th month. 36

19 CPM / PERT Networks! Conducting a Backward Pass " Using the same diagrammed schedule, a Backward Pass will be executed to determine the latest activity times :! Start at the end of the CPM/PERT network to determine the earliest activity times! Latest Start Time (LS) " Latest time an activity can start without extending the critical path.! Latest Finish Time (LF) LS= LF t " Latest time an activity can be completed without delaying the project (extending the critical path) " LF=minimum LS of immediate predecessors 37 CPM / PERT Networks! Conducting a Backward Pass " Similarly, the process can be applied to indicate the Latest Activity Start and Finish Times. 38

20 Crashing/Expediting 39 Crashing/Expediting! The ultimate goals when it comes to timing are Quality and Profit. " Finishing a project on time is a goal that is based on the schedule of operations. " Alteration of the project schedule's delivery date may have an impact on the operations which can entitle the owner to impose penalty if that goal is not met. " Early delivery may be profitable and an owner may provide an incentive to the PM to finish earlier, but not always:! A tollway can produce more revenue earlier,! A summer resort beach hotel delivered in Winter will have maintenance costs for very little gain if any! " Sacrificing quality for time will likely lead to several problems both in short and long run, and it can become a very complicated matter. 40

21 Crashing/Expediting! Crashing an activity or the schedule may require more human resources, more equipment, or likely both. " It can be anticipated that minimizing the time necessary for an activity to be completed, will come at a cost. " That cost may be higher or even much higher than simple addition of resources, because of several factors such as risk, sense of urgency that allows operators to use cost leverage, limitations in resources, etc. " Therefore, crashing a project schedule or an activity, should take place after considering the cost/benefit ratio.! Incentives need to be clearly set! Risks of any failure should be measured! Monetary benefits should be compared to the costs 41 Crashing/Expediting! A simple method to apply Crashing for a Project: " Draw an AOA, show the Critical Path along with normal ES, EF, LS and LF for each activity " Using the most economical method crash the project one day at a time until the targeted or closest to targeted project duration is met. List the added costs for the project on a daily basis. " Graph the project time vs direct costs.! If there are indirect costs identify and add them. " List the total project cost for each day of the project duration between normal and crash times. " Plot the total and the indirect cost curves on the graph. " Determine the most economically feasible duration for the project (when you should not crash any further). 42

22 Probabilistic Time Estimation 43 Probabilistic Time Estimation! Quoting: That path determines the minimum amount of time (average) that the project will take " The term average is key in this situation. " Average means that on an average basis each activity takes a certain amount of time. " So each activity can take more or it can take less time,... " Average means that it the activity, or the schedule altogether, has a 50% possibility to be completed at that estimated amount of time, and that is based on data that give the average time that each activity is anticipated to take! " So this is not a guarantee that the activity will be completed by that average estimated time! 44

23 Probabilistic Time Estimation! How do we calculate a duration that would be more likely than average? " It is optional for each and every activity that is on the critical path to be given an average duration, together with an optimistic and a pessimistic duration " That will allow a cumulative calculation of project durations that will give a fairly precise number that will correspond to possibilities of project completion. " Complicated methods of calculating probabilities through the use of probability tree or Monte-Carlo simulation may yield results with relatively high precision " In PERT, use of Z-Score (a statistical measurement of a score's relationship to the mean in a group of scores) can be just as effective and much more efficient. 45 Probabilistic Time Estimation! PERT makes provisions for Uncertainties: " TM Most probable activity duration! Most likely Best Guess. " TP Pessimistic activity duration! If everything goes wrong excluding highly unusual catastrophes as force majeur. " TO Optimistic activity duration! If everything goes right! " For standard straight activities with well known historic data the above should not vary much. " The greater the risk or uncertainty, the greater the variance. 46

24 Probabilistic Time Estimation! PERT Calculation of Expected time of an activity duration as the weighted average of three time estimates: " T O & T P likely to occur: " T M is 4 times more likely to occur: T E = T O+4T M +T P 6 " Activity time durations have been traditionally following a beta distribution (unimodal with single peak value) " The distribution has finite and positive end points, i.e. no negative durations can occur! " It is not necessarily symmetrical Note: A normal distribution does not satisfy the last two criteria 47 Probabilistic Time Estimation! PERT Figure: Determination of activity durations: 48

25 Probabilistic Time Estimation! Example determining the Estimated Time: " Given that TO=5, TM=9, and TP=20, determine the value of TE: T E = T O+4T M +T P 6 = = Probabilistic Time Estimation! Variability of Activity durations: " It is necessary to examine the reliability of the expected time. If the time is highly variable, i.e. the range of the estimates is very large, that generates less managerial confidence.! e.g. a situation of {5,9,19} vs {8,9,10} " A means of measuring the variability of an activity's duration is needed. " This measure is given by the Standard Deviation Δσ of the activity's probability distribution. " PERT simplifies the calculation of the Δσ because the distribution consists of only three values. 50

26 Probabilistic Time Estimation! Variance and Standard Deviation: " Δσ is the square root of Variance Δσ=[ T P T O 6 ] V =[ T P T O 6 " A high Δσ represents high level of uncertainty in this case. " In case more than one critical path exists (rare but possible to have two paths with same length), the one with the highest variance is chosen to determine the variance and the standard deviation. " Paths that are close to the critical path's duration, but with higher variances should be carefully addressed as becoming the critical path. ]2 51! Variance : Probabilistic Time Estimation " Consider the two following scenarios! A : " T O =4 " T M =6 " T P =8! B : " T O =4 " T M =5.5 " T P =10 T E (A) = =6 T E (B) = =6 6 52

27 ! Variance : Probabilistic Time Estimation " Although the expected durations are identical, the variances differ substantially. That causes great difference in the risk profile of each scenario: V A = (8 4)2 6 2 =0.44 V B = (10 4)2 6 2 =1 V B V A =2.27 " A factor of risk difference of the scale of 2.27 occurs between the two projects. Project B is substantially more risky. 53 Probabilistic Time Estimation! Using Z scores: " A table of values of Z scores can be used to determine the risk factor or the probability of something. " In this case it can be applied to the schedule to determine the chances of a schedule being completed in any time other than the average anticipated: Z = D T E Δ σ " Where D is the goal duration 54

28 Probabilistic Time Estimation! Using Z scores: " e.g. What is the likelihood that a project with an expected time T E of 20 days will be completed within 23 days, given that the standard deviation of the critical path is 3 days? Z = =1 3 " From Z Tables: Source for table: 55 Probabilistic Time Estimation! Using Z scores with formula: " Tables are convenient if they are available at any given time. " Sometimes a formula (especially if registered in a calculator) may be much quicker to use. " The probability of a Z score can be returned by the following formula: 1 Prob= 1+e ( Z Z )! Where e is Euler's constant 56

29 Probabilistic Time Estimation! Example using Z values: " Using an estimated value for optimistic duration, pessimistic duration, and most probable duration for each of the activities, determine the probability of finishing the following project at 95% of the average time (Critical Path is shown on continuous lines): " Note: The shown schedule is simplified for the purposes of this exercise. 57 Probabilistic Time Estimation! Example using Z values: " Setting values in a table (highlighted variance is on Critical Path): 58

30 Probabilistic Time Estimation! Example using Z values: Z = = Prob= 1+(2.7183) = ( ( 2.708) ( 2.708)) " Δσ = 15.51, TE = 849 days. " D = 95% of TE = 807 days. " Therefore, the chances of finishing this 849 days work in 807 days are 0.3%, which can be considered an impossibility! " Let's try 870 days: Z = = Prob= 1+(2.7183) ( (1.354) (1.354)) " At 91.2% it can be considered close to certainty! 59 Probabilistic Time Estimation! How can this be used? " A PM can determine what would potentially be a timing for guaranteed completion of a project and use that information accordingly before bidding the project. " Risk of bidding a project on shorter schedule may be a gamble that a PM would have to take provided the incentive is worth the risk. " At any rate, there is no guarantee on scheduling, but a well structured schedule with sound estimations for activities and relations of each activity is the best a PM can do. 60

31 Summary & Conclusion 61 Summary & Conclusion! Timing and duration of a project is dependent upon a series of sequential activities that need to take place for the completion of the project.! The series of activities that are sequential, each one being dependent on preceding activities and upon which subsequent activities are dependent, is the Critical Path.! The Critical Path determines the total duration of a project.! Activities on the CP have no float (slack)! Schedules can be represented through the use of Bar Charts, or Networks with Activities on Arrow, or Activities on Node " Contemporary software performs most custom functions and usually represent schedules on Bar Charts! Forward Pass and Backward Pass are methods to determine the Earliest Start/Finish and Latest Start/Finish.! Probabilistic Time Estimation with PERT allows managers to determine optimum project duration for bidding or Risk Management 62

Cambridge International AS & A Level Computer Science

Cambridge International AS & A Level Computer Science Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Planning & Scheduling

Planning & Scheduling Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,

More information

Topic # 12. CIS Project Management: an overview

Topic # 12. CIS Project Management: an overview Topic # 12 CIS Project Management: an overview Project Planning Major Activities during Project Planning: 1) describing project scope, alternatives, and feasibility; 2) dividing the project into manageable

More information

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain: Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE December 25, 17 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and

More information

IST 302 : Project Time Management

IST 302 : Project Time Management IST 302 : Project Time Management Developing quality schedules is important. 1 Schedule issues are the main reason for conflicts on projects There are five core project time management process groups.

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context PM Network diagrams in context SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

Artificial Intelligence

Artificial Intelligence Artificial Intelligence Combinatorial Optimization G. Guérard Department of Nouvelles Energies Ecole Supérieur d Ingénieurs Léonard de Vinci Lecture 4 Outline 1 2 Decisions about Resource Allocation Which

More information

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155 GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms

More information

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM)

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) Content Writer/Author: Email id: Mrs. RENU ARORA renu214@gmail.com Structure of Module/Syllabus of module(define

More information

Developing a Project Plan

Developing a Project Plan Chapter 6 Developing a Project Plan I had six honest serving men who taught men all I know : their names were what and how and why, and when and where and who. Rudyard Kipling Project Management 105 Figure

More information

CHAPTER 1. Basic Concepts on Planning and Scheduling

CHAPTER 1. Basic Concepts on Planning and Scheduling CHAPTER 1 Basic Concepts on Planning and Scheduling Eugénio Oliveira Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the and ordering of activities as well

More information

7. Gaining Insight. 1. Deterministic evaluation Sensitivity analysis Tornado diagrams

7. Gaining Insight. 1. Deterministic evaluation Sensitivity analysis Tornado diagrams R.E.Marks 2001 Lecture 5-1 7. Gaining Insight The product of any analysis should be new insights which clarify a course of action. There are several tools to generate these new insights into the problem.

More information

Project Planning and Estimating DJ

Project Planning and Estimating DJ Project Planning and Estimating DJ201 0807 Copyright ESI International August 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any

More information

Application of a PERT-Type System and "Crashing" in a Food Service Operation

Application of a PERT-Type System and Crashing in a Food Service Operation Hospitality Review Volume 7 Issue 2 Hospitality Review Volume 7/Issue 2 Article 8 1-1-1989 Application of a PERT-Type System and "Crashing" in a Food Service Operation Glenn A. Leitch Michigan State University,

More information

Activity on Arrow (AOA) network model to enable mold productivity optimization

Activity on Arrow (AOA) network model to enable mold productivity optimization Activity on Arrow (AOA) network model to enable mold productivity optimization Lim Ming Siong Infineon Technologies (Malaysia) Sdn. Bhd. Free Trade Zone, Batu Berendam, 7535 Melaka MingSiong.Lim@infineon.com

More information

Chapter 3 Managing the Information Systems Project

Chapter 3 Managing the Information Systems Project Princess Noura University Computer Science and Information Faculty Information Systems Department IS321 Chapter 3 Managing the Information Systems Project Learning Objectives Discuss skills required to

More information

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents Project Planning, Scheduling and Preparation of Quality Assurance Control Documents J.SHARANYASREENIVAS 1, G.GAJALAKSHMI 2, K.RAVI THEJA 3 1P.G Student M.Tech (Structural Engg. and construction managment),

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05 PDM Precedence Diagramming Method (PDM) Part 1 Con E 441 P05 A. Four (4) possible relationships 1. Finish to Start (FS). Start to Start (SS) 3. 4. Start to Finish (SF) B. Plus combined relationships SS

More information

A Practical Approach using CPM/PERT: for Certain Activity Times in Construction Parking Project

A Practical Approach using CPM/PERT: for Certain Activity Times in Construction Parking Project World Applied Sciences Journal 35 (7): 1180-1184, 2017 ISSN 1818-4952 IDOSI Publications, 2017 DOI: 10.5829/idosi.wasj.2017.1180.1184 A Practical Approach using CPM/PERT: for Certain Activity Times in

More information

Review: Simple schedule risk modelling with Safran Risk

Review: Simple schedule risk modelling with Safran Risk Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Review: Simple schedule risk modelling with Safran Risk With a view to exploring alternative

More information

Chapter 7: Project Planning: Task Determination and Resource Assignment

Chapter 7: Project Planning: Task Determination and Resource Assignment Project and Process Management Chapter 7: Project Planning: Task Determination and Resource Assignment The Why, What and How of Project Planning Defining Project Boundaries and Scope Breaking Your Project

More information

DEPARTMENT OF MCA CLASS / YEAR : III MCA SUB. CODE & NAME: MC9252, SOFTWARE PROJECT MANAGEMENT. UNIT I 2 MARKS QUESTIONS & ANSWERS 1. What is software project management? Software project management is

More information

Project Management THE MANAGERIAL PROCESS

Project Management THE MANAGERIAL PROCESS Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Lecture 4 Developing a Project Plan Activity on Node (AON) Copyright 2006 The McGraw-Hill Companies. All rights reserved.

More information

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A Deltek Acumen Planning, Risk, Acceleration Tom Polen Director, Solution Architecture Learning Objectives The 5 steps 1. Capturing uncertainty: calibrating the schedule 2. Identifying risk events: accounting

More information

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management Instant download and all chapters Test Bank Operations Management 11th Edition Jay Heizer, Barry Render https://testbankdata.com/download/test-bank-operations-management-11thedition-jay-heizer-barry-render/

More information

Lesson 15-Planning and Costing

Lesson 15-Planning and Costing Lesson 15-Planning and Costing Overview The process of making multimedia. Scheduling. Estimating. RFPs and bid proposals. The Process of Making Multimedia Idea analysis. Pre-testing. Task planning. Development.

More information

SCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS

SCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS SCHEDULE RISK ANALYSIS ESSENTIALS FOR PROJECT SUCCESS CSVA 2011 Conference Toronto, Ontario Nov 14-16, 2011 Laszlo A. Retfalvi P.Eng PMP PMI-RMP Retfalvi and Associates 1 Agenda of Session Key Take Aways

More information

Risk Management User Guide

Risk Management User Guide Risk Management User Guide Version 17 December 2017 Contents About This Guide... 5 Risk Overview... 5 Creating Projects for Risk Management... 5 Project Templates Overview... 5 Add a Project Template...

More information

13 Project Graphics Introduction

13 Project Graphics Introduction Page 725 13 Project Graphics 13.0 Introduction In Chapter 11, we defined the steps involved in establishing a formal program plan with detailed schedules such that the total program can be effectively

More information

MICROSOFT PROJECT 2010 Level 1

MICROSOFT PROJECT 2010 Level 1 MICROSOFT PROJECT 2010 Level 1 Microsoft Project 2010 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project Management Overview... 6 Project Definition Techniques... 7 Project Planning

More information

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT Course Outline TEC D 205 Engineering Tech Project Planning Week 1 Chapter 4: DEFINING THE PROJECT 1. Step one: Defining the Project Scope A. Employing a Project Scope Checklist 1. Project objective 2.

More information

1.Which of the items listed below is not one of the software engineering layers?

1.Which of the items listed below is not one of the software engineering layers? 1.Which of the items listed below is not one of the software engineering layers? Process Manufacturing Methods Tools 2.The software quality assurance activity which is performed to check errors in logic,

More information

Common Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards

Common Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards Common Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards Rob Richards, Ph.D. April 20, 2016 Planning, Production Processes & Facilities Panel (PPP&F)

More information

Project Risk Analysis (with Pertmaster)

Project Risk Analysis (with Pertmaster) Project Risk Analysis (with Pertmaster) AACE Toronto Section October 2, 2008 Brought to you by: Presenter Ian Nicholson, P.Eng. VP Solutions, Emerald Associates Mechanical Engineer Primavera Systems Authorized

More information

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

PMP Sample Questions  Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope? PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document

More information

Sawtooth Software. Sample Size Issues for Conjoint Analysis Studies RESEARCH PAPER SERIES. Bryan Orme, Sawtooth Software, Inc.

Sawtooth Software. Sample Size Issues for Conjoint Analysis Studies RESEARCH PAPER SERIES. Bryan Orme, Sawtooth Software, Inc. Sawtooth Software RESEARCH PAPER SERIES Sample Size Issues for Conjoint Analysis Studies Bryan Orme, Sawtooth Software, Inc. 1998 Copyright 1998-2001, Sawtooth Software, Inc. 530 W. Fir St. Sequim, WA

More information

Continuous Improvement Toolkit. Risk Analysis. Continuous Improvement Toolkit.

Continuous Improvement Toolkit. Risk Analysis. Continuous Improvement Toolkit. Continuous Improvement Toolkit Risk Analysis The Continuous Improvement Map Managing Risk FMEA Understanding Performance Check Sheets Data Collection PDPC RAID Log* Risk Analysis* Fault Tree Analysis Traffic

More information

Richard J. Long, P.E.

Richard J. Long, P.E. Richard J. Long, P.E. LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Construction Contract

More information

Available online at ScienceDirect. Procedia CIRP 28 (2015 ) rd CIRP Global Web Conference

Available online at  ScienceDirect. Procedia CIRP 28 (2015 ) rd CIRP Global Web Conference Available online at www.sciencedirect.com ScienceDirect Procedia CIRP 28 (2015 ) 179 184 3rd CIRP Global Web Conference Quantifying risk mitigation strategies for manufacturing and service delivery J.

More information

CS 307: Software Engineering. Lecture 14: Project Management

CS 307: Software Engineering. Lecture 14: Project Management CS 307: Software Engineering Lecture 14: Project Management Prof. Jeff Turkstra 2017 Dr. Jeffrey A. Turkstra 1 Announcements Sprint 1 planning document due Monday, February 13 Also when Sprint 1 begins

More information

Project Management for Facility Constructions

Project Management for Facility Constructions Project Management for Facility Constructions A Guide for Engineers and Architects Bearbeitet von Alberto De Marco 1. Auflage 2011. Buch. viii, 189 S. Hardcover ISBN 978 3 642 17091 1 Format (B x L): 15,5

More information

Resource Allocation Optimization in Critical Chain Method

Resource Allocation Optimization in Critical Chain Method Annales UMCS Informatica AI XII, 1 (2012) 17 29 DOI: 10.2478/v10065-012-0006-2 Resource Allocation Optimization in Critical Chain Method Grzegorz Pawiński 1, Krzysztof Sapiecha 1 1 Department of Computer

More information

USING A LARGE RESERVOIR MODEL IN THE PROBABILISTIC ASSESSMENT OF FIELD MANAGEMENT STRATEGIES

USING A LARGE RESERVOIR MODEL IN THE PROBABILISTIC ASSESSMENT OF FIELD MANAGEMENT STRATEGIES PROCEEDINGS, Twenty-Seventh Workshop on Geothermal Reservoir Engineering Stanford University, Stanford, California, January 28-30, 2002 SGP-TR-171 USING A LARGE RESERVOIR MODEL IN THE PROBABILISTIC ASSESSMENT

More information

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text.

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text. Construction Planning ISBN 978-0-7277-6057-9 ICE Publishing: All rights reserved http://dx.doi.org/10.1680/cp2e.60579.191 Index Page locators in italics and bold respectively refer to figures and tables

More information

Management of Projects

Management of Projects of Projects Giuseppe Lami Page 1 Course Outline! Part 1: The Project (PM) Framework! Part 2: The PM as a Process! Part 3: Techniques, Methods and Tools Supporting the PM! Part 4: Requirements Engineering

More information

PS.08. Let s Scrap the Precedence Diagramming Method

PS.08. Let s Scrap the Precedence Diagramming Method 2004 AACE International Transactions PS.08 Let s Scrap the Precedence Diagramming Method Earl T. Glenwright Jr. THE STATE OF CONSTRUCTION SCHEDULING PRACTICES AND SCHEDULES WHY PRECEDENCE DIAGRAMMING WAS

More information

SOFTWARE ENGINEERING Staffing Level Estimation and Scheduling

SOFTWARE ENGINEERING Staffing Level Estimation and Scheduling SOFTWARE ENGINEERING Staffing Level Estimation an Scheuling Staffing level estimation Once the effort require to evelop a software has been etermine, it is necessary to etermine the staffing requirement

More information

Project Management Techniques

Project Management Techniques Project Management Techniques CHAPTER C Learning Objectives After reading this chapter, you should be able to: Calculate net present value, payback period, and return on investment Chapter Outline Calculating

More information

S O Seminar Objective

S O Seminar Objective Introduction to Project Management Welcome! Presenter: Bob Hull CalACT Conference September 202 S O Seminar Objective To provide an overview of project management processes and provide some skills, tools

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course PMI REP No 3001 Course Number PP6 Administration Evacuation Timings and meals Facilities Mobile

More information

Vrije Universiteit Amsterdam Faculty of Exact Sciences. Exam: Software Project Management Version A. Dr. Nelly Condori-Fernandez. Date: May 27, 2015

Vrije Universiteit Amsterdam Faculty of Exact Sciences. Exam: Software Project Management Version A. Dr. Nelly Condori-Fernandez. Date: May 27, 2015 Vrije Universiteit Amsterdam Faculty of Exact Sciences Exam: Software Project Management Version A Code: Coordinator: X_401093 Dr. Nelly Condori-Fernandez Date: May 27, 2015 Duration: Calculator allowed:

More information

Ir. Herwin Rubijono Hotel Ambhara 19 September Manajemen Proyek. Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim

Ir. Herwin Rubijono Hotel Ambhara 19 September Manajemen Proyek. Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim Ir. Herwin Rubijono Hotel Ambhara 19 September 2016 Manajemen Proyek Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

Calculating and Using Float

Calculating and Using Float Core Scheduling Papers: #5 Calculating and Using Float Origin of Float The concept of schedule float is the creation of the Critical Path Method (CPM) of scheduling. Before 1957 float only had one meaning

More information

INDUSTRIAL ENGINEERING

INDUSTRIAL ENGINEERING 1 P a g e AND OPERATION RESEARCH 1 BREAK EVEN ANALYSIS Introduction 5 Costs involved in production 5 Assumptions 5 Break- Even Point 6 Plotting Break even chart 7 Margin of safety 9 Effect of parameters

More information

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2 Fundamentals 1 & 2 1. Answer: B Process Group. Each project management knowledge area is subdivided into specific process group, each of which is characterized by their inputs, tools and techniques, and

More information

The Dummy s Guide to Data Analysis Using SPSS

The Dummy s Guide to Data Analysis Using SPSS The Dummy s Guide to Data Analysis Using SPSS Univariate Statistics Scripps College Amy Gamble April, 2001 Amy Gamble 4/30/01 All Rights Rerserved Table of Contents PAGE Creating a Data File...3 1. Creating

More information

Project Planning & Management. Lecture 11 Project Risk Management

Project Planning & Management. Lecture 11 Project Risk Management Lecture 11 Project Risk Management The Importance of Project Risk Management PMBOK definition of Project Risk An uncertain event or condition that, if it occurs, has a positive or negative effect on the

More information

Line of balance programming

Line of balance programming Line of balance programming 1. INTRODUCTION Most contractors are familiar with programming a single project where a critical path analysis or, more likely, a bar chart is drawn up indicating what activities

More information

Online Student Guide Types of Control Charts

Online Student Guide Types of Control Charts Online Student Guide Types of Control Charts OpusWorks 2016, All Rights Reserved 1 Table of Contents LEARNING OBJECTIVES... 4 INTRODUCTION... 4 DETECTION VS. PREVENTION... 5 CONTROL CHART UTILIZATION...

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources

More information

Management Terminology

Management Terminology Management Terminology Acceptance Acceptance Criteria Accounting Period Acquisition Active Listening Activity Activity Definition Activity Description (AD) Activity Duration Estimating Activity-On- Arrow

More information

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline - 3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline - PREPARED BY: Jessica Summers Virtual Training Coordinator PPM Global Services, Inc. P: 1-800-746-4029 x 310 F: 1-800-746-4029 E:

More information

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

PMI-001 Questions & Answers

PMI-001 Questions & Answers PMI-001 Questions & Answers Number: PMI-001 Passing Score: 700 Time Limit: 137 min File Version: 21.2 http://www.gratisexam.com/ PMI-001 Questions & Answers Exam Name: Project Management Professional v5

More information

Managing Strategic Initiatives for Effective Strategy Execution

Managing Strategic Initiatives for Effective Strategy Execution Managing Strategic Initiatives for Effective Strategy Execution Process 1: Initiative Rationalization A Balanced Scorecard Collaborative White Paper September 2005 Introduction The proper management of

More information

Andrew Avalon, P.E., PSP

Andrew Avalon, P.E., PSP Andrew Avalon, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Andrew Avalon,

More information

Getting Started with Risk in ISO 9001:2015

Getting Started with Risk in ISO 9001:2015 Getting Started with Risk in ISO 9001:2015 Executive Summary The ISO 9001:2015 standard places a great deal of emphasis on using risk to drive processes and make decisions. The old mindset of using corrective

More information

Project Management Concepts, Tools & Techniques

Project Management Concepts, Tools & Techniques Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid

More information

Understanding Import & Export with NetPoint 4.2

Understanding Import & Export with NetPoint 4.2 Understanding Import & Export with NetPoint 4.2 Eric Lowther PMA Consultants 1 Primary Differences Regarding Import/ Export CPM Tools F9 and Early/Late Dates Float & Total Float Gantt Charts (Waterfall

More information

Project Planning. COSC345 Software Engineering 2016 Slides by Andrew Trotman given by O K

Project Planning. COSC345 Software Engineering 2016 Slides by Andrew Trotman given by O K Project Planning COSC345 Software Engineering 2016 Slides by Andrew Trotman given by O K Overview Assignment: The assignment sheet specifies a minimum Think about what else you should include (the cool

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR

More information

Integral Risk Management for DBFM Tenders and Contracts in the Netherlands

Integral Risk Management for DBFM Tenders and Contracts in the Netherlands 770 Geotechnical Safety and Risk V T. Schweckendiek et al. (Eds.) 2015 The authors and IOS Press. This article is published online with Open Access by IOS Press and distributed under the terms of the Creative

More information

How Much Should You Invest In Software Security?

How Much Should You Invest In Software Security? How Much Should You Invest In Software Security? Kelce S. Wilson, PhD, MBA, J.D. Research In Motion 122 West John Carpenter Freeway, Suite 430 Irving, TX 75039 USA Abstract - A Protection Valuation Tool

More information

Micro Planner X-Pert

Micro Planner X-Pert Micro Planner X-Pert V3.5.1 Overview Presenter: Patrick Weaver PMI-SP Micro Planning International Asia Pacific Cell:+61 418 53 1111 raf@microplanning.com.au. Arrow Diagram Precedence Diagram Working

More information

Principles of Schedule Contingency Management

Principles of Schedule Contingency Management Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation

More information

Ronald J. Rider, MBA

Ronald J. Rider, MBA Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Ronald J. Rider,

More information

Construction Project Scheduling of MK Apartment Using MS Project 2013

Construction Project Scheduling of MK Apartment Using MS Project 2013 Construction Project Scheduling of MK Apartment Using MS Project 2013 Monish Kumar K 1, Maheshwar S Maregoudru 2, Sparsha B.P 3 1,2 PG Student, Dept. of Civil Engineering, KVGCE, Sullia, Karnataka, India

More information

STATISTICAL TECHNIQUES. Data Analysis and Modelling

STATISTICAL TECHNIQUES. Data Analysis and Modelling STATISTICAL TECHNIQUES Data Analysis and Modelling DATA ANALYSIS & MODELLING Data collection and presentation Many of us probably some of the methods involved in collecting raw data. Once the data has

More information

1) Operating costs, such as fuel and labour. 2) Maintenance costs, such as overhaul of engines and spraying.

1) Operating costs, such as fuel and labour. 2) Maintenance costs, such as overhaul of engines and spraying. NUMBER ONE QUESTIONS Boni Wahome, a financial analyst at Green City Bus Company Ltd. is examining the behavior of the company s monthly transportation costs for budgeting purposes. The transportation costs

More information

PMI Scheduling Professional (PMI-SP)

PMI Scheduling Professional (PMI-SP) PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management

More information

White Paper Using S-Curves to improve Project Performance

White Paper Using S-Curves to improve Project Performance White Paper Using S-Curves to improve Project Performance Ever increasing pressure on businesses to deliver projects on time and to budget means that accurate monitoring of progress, resources and costs

More information

Glossary bglos.indd 10/28/2015 Page 1

Glossary bglos.indd 10/28/2015 Page 1 Glossary 2 Glossary Numbers 360 degree review A form of project performance appraisal (a tool and technique of the Manage Project Team process) that solicits feedback from everyone with whom the team member

More information

Risk Analysis Overview

Risk Analysis Overview Risk Analysis Overview What Is Risk? Uncertainty about a situation can often indicate risk, which is the possibility of loss, damage, or any other undesirable event. Most people desire low risk, which

More information

Project Scheduling and Tracking. CIS 375 Bruce R. Maxim UM-Dearborn

Project Scheduling and Tracking. CIS 375 Bruce R. Maxim UM-Dearborn Project Scheduling and Tracking CIS 375 Bruce R. Maxim UM-Dearborn 1 What does the customer want to know? Do you understand my needs? Can you design a system to help me? How long will it take? How much

More information

2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline -

2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline - 2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline - PREPARED BY: Jake Lilley, PMP President PPM Global Services, Inc. P: 1-800-746-4029 F: 1-800-746-4029 E: jlilley@ppmglobalservices.com

More information

9. Verification, Validation, Testing

9. Verification, Validation, Testing 9. Verification, Validation, Testing (a) Basic Notions (b) Dynamic testing. (c) Static analysis. (d) Modelling. (e) Environmental Simulation. (f) Test Strategies. (g) Tool support. (h) Independent Verification

More information

Implement. Control. Integrate. Knowledge Leverage. Course Overview

Implement. Control. Integrate. Knowledge Leverage. Course Overview Conceptualize Plan Plan & Deliver Organize Implement Control Change if Required Integrate Deliver & Closeout Knowledge Leverage Course Overview The Certificate In Project Management (CIPM) exam is administered

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration

More information

System Cost Modeling Using Proxy Estimation and COSYSMO

System Cost Modeling Using Proxy Estimation and COSYSMO System Cost Modeling Using Proxy Estimation and COSYSMO October 21, 2014 Reggie Cole Lockheed Martin Senior Fellow reggie.cole@lmco.com Kevin Woodward Lockheed Martin Fellow kevin.woodward@lmco.com 1 We

More information

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Hill International Construction CPM Conference

More information

Test your Understanding-The Answers

Test your Understanding-The Answers Table of Contents Module 1 Project management methodology... 2 A. Introduction to Project Management... 2 B. The Phases of Project Management... 2 C. Project Management Methodology questions... 2 Module

More information

Chapter 9 Balancing Demand and Productive Capacity

Chapter 9 Balancing Demand and Productive Capacity GENERAL CONTENT Multiple Choice Questions Chapter 9 Balancing Demand and Productive Capacity 1. Which of the following is NOT one of the productive capacity forms in a service context? a. Physical facilities

More information