RESOURCE MANAGEMENT. Dr. Ahmed Elyamany
|
|
- Rolf Atkinson
- 6 years ago
- Views:
Transcription
1 1 RESOURCE MANAGEMENT Dr. Ahmed Elyamany
2 Outline Definition of Resources Resource Aggregation/Loading Problems Associated with Resource Resource Leveling Resource Scheduling
3 What a resource? 3 Any thing that is used by an activity to get the work done, such as: Material, Equipment, Labor, Money,..
4 Resources Classification 4 Resources can be: Consumable (Money, Material, ) Non Consumable (Labor, Equipment, ) Resources can be: Key or constrained resources (Skilled labor, Equipment, ) Secondary or non-constrained resources (Labor, ) General resources, used by all activities
5 Five M Resources 5 Main/Sub contractor Money Manpower Material Machine
6 Planning and Resources 6 How it will be implemented What are the needed resources When it will be implemented What is needed to implemented Planning How much it will cost
7 Activity Analysis 7 What Work quantities How Construction methods Activity Resources -material -manpower -machine Cost Duration
8 Example 8 Work includes pouring of PC for isolated footing, each is 4m length x 4m width x.5m depth. Construction method: use one mixer + labor crew Production rate: 8 m3/day Rental cost of mixer: 4 LE/day Labor crew cost rate: 35 LE/day Material cost: 5 LE/m3
9 Example 9 Quantity = 4x4x.5x = 16 m3 Duration = 16/8 = days Material cost = 16 x 5 = 4, LE Labor cost = 35 x = 7 LE Equipment cost = 4 x = 8 LE Activity total cost = 4,+7+8=41,5 LE Activity unit cost = 41,5/16 = 59.4 LE/m3
10 Example 1 Resource cost distribution Labor; 1.7% Equipment; 1.9% Material; 96.4%
11 Duration-Driven Schedule 11 All CPM scheduling techniques are duration driven schedules Basic units: activities, durations, relationships Assumes resources are available whenever needed Difference between: Working dates Calendar dates
12 Optimum Resource Usage 1 Need of resource is fixed along the project construction time Impossible to achieve because of activities overlap Work volume = Area = resource units x time Resource demand Resource available
13 Resource Time relationship 13 If the time decreased, Resources need to be increased Resource Resource Time
14 Resource Histogram 14 Graphically represents resource needs Relation between resource units and time Procedure: Draw the network Draw the bar chart Determine the points where activities start and/or finish.
15 15 Preferred Resource Usage
16 Resource Aggregation/Loading 16 The summation, on a period-by-period basis, of the resources required to complete all activities based on the schedule carried out in the previous stage The results are usually shown graphically as a histogram A separate graph will be required for each resource
17 Resource Aggregation/Loading 17 Consider the following activities Resource limit = 1 units /week Activity Duration (week) Resources (units/week) A B C D E 3 5 Shown in the histogram
18 Resource Aggregation/Loading 18 WEEK A 1 1 B C 6 D E 6 6 Total required resource Resource unit aggregation chart Resource Limit
19 Resource Availability 19 Resource Requirement Resource Available? Unlimited resource (leveling) Limited resource (Scheduling)
20 Problems Associated with Resource Resource Fluctuation (Resource leveling) Resource Over allocation (Resource Scheduling) High hiring and firing Less hiring and firing
21 Resource Leveling (Smoothing) 1 Unconstrained resource scheduling (Constrained time) Resource Leveling Resource unconstrained (No limits on resources) Time (Project completion) constrained; project duration not be delayed Reduce the difference between the peaks and the valleys Average resource usage The objective is to smooth the use of the resources to avoid the resource fluctuation
22 Resource Leveling (Smoothing)
23 Resource Leveling (Smoothing) 3 Minimum Moment Algorithm
24 Resource Leveling (Smoothing) 4 Heuristic Method Procedure Prepare a complete activity schedule Draw a bar chart based on ES timings Draw the FF as dashed line beside the upper side of the bar and the TF beside the lower side Put the resource usage in each bar of the related activity Critical activities to be drawn first (do not move them) Aggregate the resources in each time period
25 Resource Leveling (Smoothing) 5 Heuristic Method Procedure Calculate the total usage of resources = Σ unit period usage Calculate the average resource usage = Σ usage / utilization period Shift non-critical activities within their FF first, then their TF to decrease the peaks and raise the valleys Revise the activities float Aggregate the resources in each time period
26 Resource Leveling (Example) 6 Activity Activity Duration (Weeks) Predecessors Resource (units/week) A B C D E F G H I J K L M N , 6 6, 7, 8, 8, 9 1, 11, 1,
27 7 Resource Leveling (Example)
28 Resource Leveling (Example) Activity ES EF FF TF A B C D E F G H I J K L M N
29 9 Resource Leveling (Example)
30 3 Resource Leveling (Example)
31 31 Resource Leveling (Example)
32 3 Resource Leveling (Example)
33 33 Resource Leveling (Example)
34 Resource Scheduling 34 Constrained resource scheduling (Unconstrained time) Resource Scheduling Constrained Resources Unconstrained project completion; project time may be delayed Reduce the resource usage to be less than the resource availability The objective is to meet the resources limits
35 35 Resource Scheduling
36 Resource Scheduling 36 Is there is a way to prioritize activities That compete for the limited resources so that the net project delay is minimized?
37 Resource Scheduling 37 Resource Scheduling Rules of Thumb Many rules have been experimented with Least TF were found to be most effective Least LS has the same effect as the least TF and doesn t require network recalculations In case of a tie use least TF
38 Resource Scheduling 38 Procedure Prepare a complete activity schedule Aggregate the daily resource demand If demand greater than available then determine activities compete for resources Prioritize these activities based on their LS Allocate resources to some activities and delay the others Put your solution in table format
39 Resource Scheduling (Example) Activity Duration (Weeks) Predecessors Resource (units/week) R1 8 R 1 A B C D E F G H I J K A D B B F E, H C G, J
40 4 Resource Scheduling (Example)
41 41 Resource Scheduling (Example)
42 4 Resource Scheduling (Example)
43 43 Questions Contact: Dr. Ahmed Elyamany
Planning & Scheduling
Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,
More informationFor the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.
For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com
More informationArtificial Intelligence
Artificial Intelligence Combinatorial Optimization G. Guérard Department of Nouvelles Energies Ecole Supérieur d Ingénieurs Léonard de Vinci Lecture 4 Outline 1 2 Decisions about Resource Allocation Which
More informationGLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155
GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms
More informationSPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
More informationViews and Layouts for Program Management
MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted
More informationResource-Constrained Multi-Project Scheduling with Resource Moving Time for Construction Projects in Vietnam
First International Conference on Construction In Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi,, Pakistan Resource-Constrained
More informationAvailable online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 123 (2015 ) 308 315 Creative Construction Conference 2015 (CCC2015) Application of Relationship Diagramming Method (RDM) for
More information12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish
International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,
More informationProject Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:
Project Management Dr. Richard Jerz 1 Learning Objectives Describe or Explain: What are projects The role of the project manager Work breakdown structure Project management tools (Gantt, PERT, & CPM) The
More informationCambridge International AS & A Level Computer Science
Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
More informationResource-constrained project scheduling using Relationship Diagramming Method (RDM)
Creative Construction Conference 2015 Resource-constrained proect scheduling using Relationship Diagramming Method (RDM) J. Uma Maheswari 1, Purva Muumdar 2, Anshul Goyal 3 & V. Paul C. Charlesra 4 * 1,2,3
More informationPS.08. Let s Scrap the Precedence Diagramming Method
2004 AACE International Transactions PS.08 Let s Scrap the Precedence Diagramming Method Earl T. Glenwright Jr. THE STATE OF CONSTRUCTION SCHEDULING PRACTICES AND SCHEDULES WHY PRECEDENCE DIAGRAMMING WAS
More informationDocument No: SB002-P3 Revision No: Last Updated: April
BRIEF People often are confused with the term - Out-of-Sequence, and use them in inappropriate ways. While we talk about Out-of-Sequence, we also need to discuss the difference between Retained Logic and
More informationIST 302 : Project Time Management
IST 302 : Project Time Management Developing quality schedules is important. 1 Schedule issues are the main reason for conflicts on projects There are five core project time management process groups.
More informationPlanning & Scheduling CSTM 102
Planning & Scheduling CSTM 102 Items Big A Project on Website Thursday Discuss Big A Project next Tuesday April 18, 2011 CPM Scheduling You were the successful bidder! What s next? Procurement/Buy
More informationCHAPTER 1. Basic Concepts on Planning and Scheduling
CHAPTER 1 Basic Concepts on Planning and Scheduling Eugénio Oliveira Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the and ordering of activities as well
More informationDeveloping a Project Plan
Chapter 6 Developing a Project Plan I had six honest serving men who taught men all I know : their names were what and how and why, and when and where and who. Rudyard Kipling Project Management 105 Figure
More informationCalculating and Using Float
Core Scheduling Papers: #5 Calculating and Using Float Origin of Float The concept of schedule float is the creation of the Critical Path Method (CPM) of scheduling. Before 1957 float only had one meaning
More informationGuten Tag. (good day)
Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources
More informationCOST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL
SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,
More informationMicro Planner X-Pert
Micro Planner X-Pert V3.5.1 Overview Presenter: Patrick Weaver PMI-SP Micro Planning International Asia Pacific Cell:+61 418 53 1111 raf@microplanning.com.au. Arrow Diagram Precedence Diagram Working
More informationScott M. Francis, P.E., PSP
Scott M. Francis, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Scott M. Francis,
More informationTopic # 12. CIS Project Management: an overview
Topic # 12 CIS Project Management: an overview Project Planning Major Activities during Project Planning: 1) describing project scope, alternatives, and feasibility; 2) dividing the project into manageable
More informationAdministration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.
Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones
More informationPDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05
PDM Precedence Diagramming Method (PDM) Part 1 Con E 441 P05 A. Four (4) possible relationships 1. Finish to Start (FS). Start to Start (SS) 3. 4. Start to Finish (SF) B. Plus combined relationships SS
More informationitaskx 3 Project Management User Manual
itaskx 3 Project Management User Manual GET STARTED Basics Recommended workflow Views in itaskx Adjust project options Set working time for the project-calendar 2 Unit 1 Project management basics Learn
More informationMICROSOFT PROJECT 2010 Level 1
MICROSOFT PROJECT 2010 Level 1 Microsoft Project 2010 Level 1 Contents CONTENTS PREFACE - PROJECT MANAGEMENT BASICS... 5 Project Management Overview... 6 Project Definition Techniques... 7 Project Planning
More informationEstimating Project Schedule-Time and Cost
Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities
More informationEffective Resources Management in Construction Industries for Success
Modern Applied Science November, 2008 Effective Resources Management in Construction Industries for Success Jayakumar Muthuramalingam School of Engineering and Science, Curtin University Technology Sarawak
More informationCommon Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards
Common Tool for Intelligent Scheduling / Critical Chain Project Management for US Navy & Contractor Shipyards Rob Richards, Ph.D. April 20, 2016 Planning, Production Processes & Facilities Panel (PPP&F)
More informationPMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?
PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document
More informationISE480 Sequencing and Scheduling
ISE480 Sequencing and Scheduling INTRODUCTION ISE480 Sequencing and Scheduling 2012 2013 Spring term What is Scheduling About? Planning (deciding what to do) and scheduling (setting an order and time for
More informationLine of balance programming
Line of balance programming 1. INTRODUCTION Most contractors are familiar with programming a single project where a critical path analysis or, more likely, a bar chart is drawn up indicating what activities
More informationDecember 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE
December 25, 17 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and
More informationMS Project Professional 2007 Schedule Leveling: Tips & Tricks. By Lloyd C. Miller III, PMP
MS Project Professional 2007 Schedule Leveling: Tips & Tricks By Lloyd C. Miller III, PMP Agenda What, Where, When & Why Understanding the Options Considering Different Views / Reports Tips & Tricks 2
More informationProject Time Management
Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use
More informationWelcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course PMI REP No 3001 Course Number PP6 Administration Evacuation Timings and meals Facilities Mobile
More informationResource Optimization of Construction Project Using Primavera P6
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 14, Issue 1 Ver. V (Jan. - Feb. 2017), PP 01-08 www.iosrjournals.org Resource Optimization of Construction
More informationCLB 029 Wrap Rate Projections
CLB 029 Wrap Rate Projections Lesson Defense Acquisition University Table of Contents Wrap Rate Projections... 3 Introduction... 3 Wrap Rate Projection Methods... 4 Wrap Rate Projections Applied... 6 Summary...
More informationPrimavera Training - P6 Basic Course (102)
Primavera Training - P6 Basic Course (102) This training session provides hands-on training for Primavera s client/server-based solution, leading participants through the entire project life cycle, from
More informationThe Performance of Heuristic Rules in Resource Constrained Project Scheduling
The Performance of Heuristic Rules in Resource Constrained Project Scheduling OSMAN HÜROL TÜRKAKIN Department of Civil Engineering Istanbul University 34320 Avcılar, Faculty of Engineering, Istanbul, Turkey
More informationP6 Instructors Sample Presentation
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation
More informationProject Planning, Scheduling and Preparation of Quality Assurance Control Documents
Project Planning, Scheduling and Preparation of Quality Assurance Control Documents J.SHARANYASREENIVAS 1, G.GAJALAKSHMI 2, K.RAVI THEJA 3 1P.G Student M.Tech (Structural Engg. and construction managment),
More informationRESOURCE OPTIMIZATION IN CONSTRUCTION OF A RESIDENTIAL APARTMENT USING PRIMAVERA P-6 SOFTWARE
RESOURCE OPTIMIZATION IN CONSTRUCTION OF A RESIDENTIAL APARTMENT USING PRIMAVERA P-6 SOFTWARE BHAJANTHRI THIRUMALESHA 1, RAJANI V.AKKI 2,BASAVARAJ BAVI 3 1 P.G. Student, Civil Engineering Department, Shree
More informationJustifying Simulation. Why use simulation? Accurate Depiction of Reality. Insightful system evaluations
Why use simulation? Accurate Depiction of Reality Anyone can perform a simple analysis manually. However, as the complexity of the analysis increases, so does the need to employ computer-based tools. While
More informationAn Oracle White Paper October Four Ways Enterprise Project Portfolio Management Can Increase ROI in Asset- Intensive Process Industries
An Oracle White Paper October 2009 Four Ways Enterprise Project Portfolio Management Can Increase ROI in Asset- Intensive Process Industries Executive Overview Asset-intensive companies like those in the
More informationVrije Universiteit Amsterdam Faculty of Exact Sciences. Exam: Software Project Management Version A. Dr. Nelly Condori-Fernandez. Date: May 27, 2015
Vrije Universiteit Amsterdam Faculty of Exact Sciences Exam: Software Project Management Version A Code: Coordinator: X_401093 Dr. Nelly Condori-Fernandez Date: May 27, 2015 Duration: Calculator allowed:
More informationPrinciples of Schedule Contingency Management
Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation
More informationThe Differences Between CPM and Resource-Loaded Scheduling and How They Applied to The Martinez Tesoro Refinery Flare Header Replacement Project
The Differences Between CPM and Resource-Loaded Scheduling and How They Applied to The Martinez Tesoro Refinery Flare Header Replacement Project Conor Carone California Polytechnic State University San
More informationWhat's New - Task Planning
What's New - Task Planning by Dale Howard and Gary Chefetz With this chapter, teach yourself how to use Microsoft Project 2010 s new manual scheduling feature. This self-paced study guide includes hands-on
More informationResource Allocation Optimization in Critical Chain Method
Annales UMCS Informatica AI XII, 1 (2012) 17 29 DOI: 10.2478/v10065-012-0006-2 Resource Allocation Optimization in Critical Chain Method Grzegorz Pawiński 1, Krzysztof Sapiecha 1 1 Department of Computer
More informationOperations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management
Instant download and all chapters Test Bank Operations Management 11th Edition Jay Heizer, Barry Render https://testbankdata.com/download/test-bank-operations-management-11thedition-jay-heizer-barry-render/
More informationProject Controls Expo 13 th Nov 2013
Project Controls Expo 13 th Nov 2013 Twickenham Stadium, London From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle Copyright @ 2011. All rights reserved
More informationDeswik.Sched Gantt Chart Scheduling
Deswik.Sched Gantt Chart Scheduling SCHEDULING SOLUTIONS THAT SET US APART A dynamic, modern approach to scheduling From interactive Gantt charts to PERT network diagrams, Deswik.Sched is tailored for
More informationSCHEDULING FOR HIGH-RISE BUILDING CONSTRUCTION USING SIMULATION TECHNIQUES
SCHEDULING FOR HIGH-RISE BUILDING CONSTRUCTION USING SIMULATION TECHNIQUES Arthur W T Leung Division of Building Science and Technology, City University of Hong Kong bsawtl@cityu.edu.hk Dr C M Tam Department
More informationTOPIC 2 : WORK METHODS 2.1 Elemental breakdowns 2.2 Performance rating 2.3 Personal, fatigue, unavoidable delay allowances 2.4 Workload and line balan
TOPIC 2 WORK METHODS TOPIC 2 : WORK METHODS 2.1 Elemental breakdowns 2.2 Performance rating 2.3 Personal, fatigue, unavoidable delay allowances 2.4 Workload and line balancing 2.5 Machine and process studies
More informationDeliverable Factors of Manpower Requirement Plan: An Evidence from Indian EPC Company
Deliverable Factors of Manpower Requirement Plan: An Evidence from Indian EPC Company Amruth Gurudev S #1, Srinivasa Rao Potti *2, Shiva Prasad H.C #3 # 1 PG Research Scholar, Humanities and Management,
More informationImproving Productivity of Yard Trucks in Port Container Terminal Using Computer Simulation
The 31st International Symposium on Automation and Robotics in Construction and Mining (ISARC 2014) Improving Productivity of Yard Trucks in Port Container Terminal Using Computer Simulation Essmeil Ahmed
More information3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -
3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline - PREPARED BY: Jessica Summers Virtual Training Coordinator PPM Global Services, Inc. P: 1-800-746-4029 x 310 F: 1-800-746-4029 E:
More informationControl Solutions. ES - The latest in control technology
Control Solutions ES - The latest in control technology Limit costs for the best return on investment A properly managed compressed air network will save energy, reduce maintenance, decrease downtime,
More informationIntelligent Production Cost Allocation System
Session 2259 Intelligent Production Cost Allocation System Michael L. Rioux, Dr. Bruce E. Segee University of Maine Department of Electrical and Computer Engineering Instrumentation Research Laboratory
More informationAtlas Copco Control Solutions. ES Cutting-edge central control capability
Atlas Copco Control Solutions ES Cutting-edge central control capability Total capability, total responsibility Right at the heart of your business, Atlas Copco delivers quality compressed air for superior
More informationLOADING AND SEQUENCING JOBS WITH A FASTEST MACHINE AMONG OTHERS
Advances in Production Engineering & Management 4 (2009) 3, 127-138 ISSN 1854-6250 Scientific paper LOADING AND SEQUENCING JOBS WITH A FASTEST MACHINE AMONG OTHERS Ahmad, I. * & Al-aney, K.I.M. ** *Department
More informationLessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International
Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Hill International Construction CPM Conference
More informationA Sequencing Heuristic to Minimize Weighted Flowtime in the Open Shop
A Sequencing Heuristic to Minimize Weighted Flowtime in the Open Shop Eric A. Siy Department of Industrial Engineering email : eric.siy@dlsu.edu.ph Abstract: The open shop is a job shop with no precedence
More informationAggregate Planning and S&OP
Aggregate Planning and S&OP 13 OUTLINE Global Company Profile: Frito-Lay The Planning Process Sales and Operations Planning The Nature of Aggregate Planning Aggregate Planning Strategies 1 OUTLINE - CONTINUED
More informationApplying PSM to Process Measurement
Applying PSM to Process Measurement Name: Bill Golaz Title: LM Fellow & LM Aero Measurement and Analysis Lead PSM All rights reserved. Copyright 2010 1 Topics Why Measure Why Process Measurement Using
More informationProject Scheduling and Tracking. CIS 375 Bruce R. Maxim UM-Dearborn
Project Scheduling and Tracking CIS 375 Bruce R. Maxim UM-Dearborn 1 What does the customer want to know? Do you understand my needs? Can you design a system to help me? How long will it take? How much
More informationProject Management Techniques
Project Management Techniques CHAPTER C Learning Objectives After reading this chapter, you should be able to: Calculate net present value, payback period, and return on investment Chapter Outline Calculating
More informationProject Scheduling with GanttProject. EGR 386w
Project Scheduling with GanttProject EGR 386w 1 GanttProject http://www.ganttproject.biz/ Download version 2.6.x Has numbered tasks option The video (access from ganttproject.biz) http://www.youtube.com/watch?v=5rhcsa5ad34&feature=youtu.be
More informationProject Planning and Control Using Oracle Primavera P6 : P8.3, 8.4, 15.2
Primavera Essential Course Contents: 1. Overview Describe the Primavera modules Explain the difference between global and project-specific data Project Portfolio Management Defining the Enterprise Project
More informationAGGREGATE PLANNING (SCM) Bijay Lal Pradhan, Ph.D.
AGGREGATE PLANNING (SCM) Bijay Lal Pradhan, Ph.D. What is Aggregate Planning? DEFINITION WHAT IS AGGREGATE PLAN The aggregate production plan (APP) is a long-range materials plan. Since capacity expansion
More informationAndrew Avalon, P.E., PSP
Andrew Avalon, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Andrew Avalon,
More informationLesson 15-Planning and Costing
Lesson 15-Planning and Costing Overview The process of making multimedia. Scheduling. Estimating. RFPs and bid proposals. The Process of Making Multimedia Idea analysis. Pre-testing. Task planning. Development.
More informationWelcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management
Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR
More informationProject Management Concepts, Tools & Techniques
Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid
More informationCreate and Dispatch a Job to a Job Lead
to a Job Lead The JOBS & QUOTES tab provides end-to-end control of every job or quote at every location. Jobs and Quotes are core to the delivery of service and business operations. They can be scheduled
More informationProject Planning and Estimating DJ
Project Planning and Estimating DJ201 0807 Copyright ESI International August 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any
More informationExam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.
Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Examsoon QUESTION
More informationSales and Operations Planning
Sales and Operations Planning Alessandro Anzalone, Ph.D. Hillsborough Community College, Brandon Campus 1. Purpose of Sales and Operation Planning 2. General Design of Sales and Operations Planning 3.
More informationToday s Lecture. Fall 2004 SE 101 Introduction to Software Engineering 2
Project Planning Today s Lecture 1. Intro to Software Engineering 2. Inexact quantities 3. Error propagation 4. Floating-point numbers 5. Design process 6. Teamwork - no web review 7. Project planning
More informationProject Management using MS PROJECT Middle East College Training Unit
1 Project Management using MS PROJECT 2013 About the course 1 Microsoft Project training course trains you to plan and manage projects more effectively. Microsoft Project is a project management tool
More informationCustom Home Building Proposal
Custom Home Building Proposal Scroll down to read the first part of this sample. When purchased, the complete sample is 20 pages long and is written using these Proposal Pack chapters: Cover Letter, Title
More informationExam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.
Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Testinside
More informationRisk Management User Guide
Risk Management User Guide Version 17 December 2017 Contents About This Guide... 5 Risk Overview... 5 Creating Projects for Risk Management... 5 Project Templates Overview... 5 Add a Project Template...
More informationUnderstanding Import & Export with NetPoint 4.2
Understanding Import & Export with NetPoint 4.2 Eric Lowther PMA Consultants 1 Primary Differences Regarding Import/ Export CPM Tools F9 and Early/Late Dates Float & Total Float Gantt Charts (Waterfall
More informationITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)
ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED) 275.1. Description. This Item shall govern for treating subgrade, new and/or existing base [with or without asphaltic concrete pavement (ACP)], or
More informationMicrosoft Project study guide
Microsoft Project study guide Chap 1 An estimated duration appears with a(n) after the duration. a. pound sign c. question mark b. exclamation point d. red bullet Which of the following tasks in a LAN
More informationMS Project 2007 Overview Table of Contents
Table of Contents Microsoft Project Overview... 1 Terminology... 1 Starting Microsoft Project... 2 Projects on the Web... 2 Toolbars... 2 View Bar... 2 Views... 3 Setting Up the Project... 3 Identifying
More informationPERSPECTIVE. Oracle Planning Central Cloud centralizes planning for better supply chains. Abstract
PERSPECTIVE Oracle Planning Central Cloud centralizes planning for better supply chains Abstract A special system for optimization, which provides higher flexibility to the local system while having a
More informationProject Management for Facility Constructions
Project Management for Facility Constructions A Guide for Engineers and Architects Bearbeitet von Alberto De Marco 1. Auflage 2011. Buch. viii, 189 S. Hardcover ISBN 978 3 642 17091 1 Format (B x L): 15,5
More informationIntegral Risk Management for DBFM Tenders and Contracts in the Netherlands
770 Geotechnical Safety and Risk V T. Schweckendiek et al. (Eds.) 2015 The authors and IOS Press. This article is published online with Open Access by IOS Press and distributed under the terms of the Creative
More informationMicrosoft Office Project 2010 Basic Course 01: Getting Started
Microsoft Office Project 2010 Basic Course 01: Getting Started Slide 1 Topic A Project Management Concepts Slide 2 Project Constraints Slide 3 Phases of Project Management The initial Phase Initiating
More informationTotal Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2
Fundamentals 1 & 2 1. Answer: B Process Group. Each project management knowledge area is subdivided into specific process group, each of which is characterized by their inputs, tools and techniques, and
More informationLATRINE CONSTRUCTION SHELTER. Pour flush latrine 2. Pour flush micro septic tank 3. Initial investment, location, human resources 4.
LATRINE CONSTRUCTION Pour flush latrine 2 Pour flush micro septic tank 3 Initial investment, location, human resources 4 Concrete rings 5 Box 6 Cover 7 Slab and ceramic pan 8 Ring mold 9 Structure and
More informationBACCARAT REVENUE MANAGEMENT
By the team at Tangam Systems www.tangamsystems.com BACCARAT REVENUE MANAGEMENT Yield-management strategies to drive Baccarat performance By the team at Tangam Systems www.tangamsystems.com CONTENTS Executive
More informationA VIRTUAL CONSTRUCTION MODEL OF 4D PLANNING IN ROAD PROJECT
A VIRTUAL CONSTRUCTION MODEL OF 4D PLANNING IN ROAD PROJECT R. K. Shah 1, N. Dawood 2, J. Dean 3 and S. Castro 4 1 Ph. D. Candidate, School of Science and Technology, University of Teesside, Middlesbrough,
More informationIntegrated Volt/VAR Control
Yukon energy automation software platform Integrated Volt/VAR Control For more efficient, higher quality and less costly power Integrated Volt/VAR Control enables smart grid power quality strategies 2
More informationJosh Raphael CM Dr. Riley. Technical Report 3. Holiday Inn Express Absecon, NJ
Josh Raphael CM Dr. Riley Technical Report 3 Holiday Inn Express Absecon, NJ Table of Contents Executive Summary....... 2 Constructability Challenges....... 3-4 New Entry.... 3 Existing Facility..... 3-4
More information