1 PPP experiences from the Danish Building & Property Agency s perspective Chief advisor and project manager Njal Olsen August 24,
2 Agenda 1. The Danish Building and Property Agency 2. What PPP is in the DBPA 3. Lessons learned 4. The PPP perspective 2
3 The Danish Building and Property Agency (DBPA) We are a Property agency we build or let others build for us (for example PPP). The state's property manager and developer. We focus on clients, whilst ensuring the proper maintenance of buildings. A competent provider of advice on office space planning. Build effectively and fast to market price with a focus on quality, both in PPP and with the agency as the owner/provider. 3
4 What PPP is in the DBPA 4
5 PPP in Denmark Analysis consistently demonstrates that the Danish building sector could be more efficient and innovative. Successive governments have designated PPP as one of a number of means to improve efficiency. Guidelines followed by experience leads to improved guidelines. Subject to state building regulations (in competition with government construction works or leased contracts). 5
6 Why we are interested in PPP Our focus is both our client s needs and the proper maintenance of buildings. In Denmark PPP is not chosen as a means to raise funds, but rather for its inherent life cycle costing and risk allocation attributes. With rising constraints on public spending bundling or outsourcing of non core businesses can be attractive - e.g. construction works, running and maintenance. 6
7 Main drivers for the procurer Risk assessment and allocation. Focus on life cycle costing inherent to PPP, which is particularly relevant in relation to the emerging climate agenda (incentives in the payment mechanism ensures that the PPP supplier does not get to gain all the upside). 7
8 Our take on PPP No standard PPP-model since the model is adapted to the individual project, however : Contracts lengths years. Typically 100 pct. private ownership due to residual risk and tax issues Risks allocated to the party best equipped to handle or nullify them. Lease perspective with en bloc transfer of risks. Keep it simple (not just for the sake of the Public sector). Careful transition from traditional specifications to output specifications as output specifications do not secure outcome. 8
9 Implementing PPP Describe the features The PPP supplier provides the solution. Must be possible for the PPP supplier to optimize ie few demands with limited possible solutions. As regards the procurement rules, a PPP project does not differ from other forms of construction projects. So far 12 PPP-projects commissioned and one (large project) under construction. 9
10 Lessons learned 10
11 The construction phase All in all successful construction phase until commission and the first years of running/maintenance. Important that all parties are responsible and play their intended role To be the builder differs from just being the contractor. So far no delays or significant defects in the commissioned projects. We need to assert arms length in process more difficult than it sounds. 11
12 The operational phase Limited use of resources from client side. The day-to-day dialogue between tenants and the PPP supplier s operator is all-in-all working well as regards handling minor issues as they occur. The long-term contract benefits the relationship. Still a learning process in regard to the handling of more or less substantial building changes after commissioning. 12
13 The PPP perspective 13
14 We have come a long way Still a learning process. We have shown that PPP can be combined with good incentives for energy conservation. We still need to learn from the operational phases. PPP is just one way to provide the state with cost-effective office premises. 14
15 The next steps In order to further reduce transaction costs, increased knowledge of the PPP model is required. When the project is otherwise suitable, PPPs can provide very good results. Who will finance? Who will build, operate and maintain? 15
16 Challenges Requires competence at an advanced level for the contracting entity. Continued learning with regard to the handling of the inevitable need for structural changes after commissioning. The process of reducing payments to the PPP supplier due to defects in a building's functionality and/or facility management needs to be more operational. 16
The Leeds Trolley Vehicle System Order
Documents Reference: APP-4-1 Transport and Works Act 1992 The Leeds Trolley Vehicle System Order John Henkel: Metro NGT and Bus Operations APP-4-1: Summary Proof of Evidence on behalf of the Applicants
More informationPublic Private Partnership PPP & The Egyptian Experience
Public Private Partnership PPP & The Egyptian Experience Bassel Shoirah Project Manager / Utilities Sector - Egypt Good Governance for Development In Arab Countries initiatives of the OECD July 8, 2009
More informationPrivate Public Partnerships: Sample Standard Bidding Documents for Design-Build-Operate (DBO) for Solid Waste Management
Partnerships: Sample Standard Bidding Documents for Design-Build-Operate (DBO) for Solid Waste Management Presented by Allan Rotman Sr. Environmental Specialist Context for DBO for SWM in MNA Initiated
More informationInternational Airport Expansion Project. Terms of Reference for Legal Advisor
A. Background International Airport Expansion Project Terms of Reference for Legal Advisor 1. [ ] International Airport (IA) is a medium size airport with a total passenger per year volume of [ ]. IA has
More informationSR&ED How to respond to CRA Requirements Tax and R&D Teams Working Together. Paul G Leroux 23 October 2014
SR&ED How to respond to CRA Requirements Tax and R&D Teams Working Together Paul G Leroux 23 October 2014 Agenda Introduction Recent financial changes to the Program Program requirements that impact claim
More informationPublic Private Partnerships in Ports:
Port Financing and Investment Sopot, 10-11 May 2012 Public Private Partnerships in Ports: Pitfalls and Challenges maritime & transport business solutions Content introduction pitfalls-challenges lessons
More informationPolicy, legal and regulatory frameworks for successful PPPs
Policy, legal and regulatory frameworks for successful PPPs Anthony Smith Member UN PPP Team of Specialists Former Head of United Nations PPP Readiness Task Force Associate Expert, UNDP Farne Project Consultancy
More informationBranch guide to options appraisals
Supporting members Defending services Branch guide to options appraisals Branch guide to options appraisals Introduction Options appraisals offer a critical intervention point for branches seeking to fight
More informationProcurement s new operating model
Procurement s new operating model Contacts Chicago Eduardo Alvarez Principal, PwC US +1-312-578-4774 eduardo.alvarez @strategyand.us.pwc.com Eric Dustman Principal, PwC US +1-847-269-4758 eric.dustman
More informationMOTION NO. M Contract Amendment for a Risk Management Information System PROPOSED ACTION
MOTION NO. M2017-150 Contract Amendment for a Risk Management Information System MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION 12/07/2017 Final Action
More informationImplementing Category Management for Common Goods and Services
Implementing Category Management for Common Goods and Services Darbi Dillon Office of Federal Procurement Policy 1800 G Street NW, Washington DC 20006 Audit Tax Advisory Grant Thornton LLP 333 John Carlyle
More informationINSEAD PPPs as Policy Instruments. Abraham Akkawi November 29, 2010
INSEAD PPPs as Policy Instruments Abraham Akkawi November 29, 2010 Content PPP Defined PPP Advantages PPP Types Public Sectors Readiness Sample PPP example in the MENA region Case Study: Mafraq-Gweifat
More informationOffshore Wind Seminar Legal and commercial features of Transport and Installation Contracts
Offshore Wind Seminar Legal and commercial features of Transport and Installation Contracts When: 8 November 2017 Where: Copenhagen, Denmark This inter-active session is for professionals working within
More informationManaging Schedule Change
Managing Schedule Change Ted Douglas, CCP, PSP, FAACE CPM Construction Conference Orlando, Florida January 11, 2017 Managing Schedule Change Outline Change Drivers Contract Changes Clause Schedule Change
More informationEnergy Trading Risk Management (ETRM) System Selection and Implementation Top Challenges
Energy Trading Risk Management (ETRM) System Selection and Implementation Top Challenges May 27, 2014 Energy Trading Risk Management Challenges Agenda Agenda Speaker Introduction Overview of Energy Trading
More informationFinancial Controller
Controller Grade: Department: Responsible To: Accountable To: Band 8c Finance Associate Director of Finance Director of Finance Job Summary To deputise for the Associate Director of Finance ( Services)
More informationPlanning Construction Procurement. A guide to developing your procurement strategy
Planning Construction Procurement A guide to developing your procurement strategy First published October 2015 Revised October 2016 ISBN: 978-1-98-851707-0 (Online) New Zealand Government Procurement PO
More informationW. Cass Street Ste. B Tampa, FL (877)
2107 W. Cass Street Ste. B Tampa, FL 33606 AGENDA Introduction What is a PEO or Co-Employment? Client Advantages Common Objections Ideal Client Profile Frequently Asked Questions Getting Started Introducing
More informationready for change? REVENUE RECOGNITION Private Equity and their Portfolio Companies
ready for change? REVENUE RECOGNITION Private Equity and their Portfolio Companies Are you ready for principles-based revenue recognition? THE NEW GUIDANCE PROVIDES A PRINCIPLES-BASED, FIVE-STEP PROCESS
More informationA PRACTICAL GUIDE TO REVENUE RECOGNITION. How will the new requirements under ASC 606 Revenue from Contracts with Customers affect your business?
A PRACTICAL GUIDE TO REVENUE RECOGNITION How will the new requirements under ASC 606 Revenue from Contracts with Customers affect your business? FEBRUARY 2017 BACKGROUND In May of 2014, the Financial Accounting
More informationContracting for Goods and Services
Contracting for Goods and Services Northwest Territories Office of the Auditor General of Canada Bureau du vérificateur général du Canada Ce document est également publié en français. This document is
More informationBox Clever Consulting. Executive Summary Project Report. June Strand Plaza. Liverpool. for. Primesite Developments
Box Clever Consulting Executive Summary Project Report June 2017 Strand Plaza Liverpool for Primesite Developments Author - Graham Flynn Issued - 06/07/17 Strand Plaza - Liverpool Status Report @ End of
More informationNORDEFCO strategy Public-Private Partnerships 2010
Coordination Group PPP Page 1 of 12 NORDEFCO strategy Public-Private Partnerships 2010 Ways of raising efficiency in the military through cooperation with or benchmarking against the private sector Coordination
More informationTHE ITERATIVE ENGAGEMENT MODEL A CALCULATED RISK AND A WHOLE LOT OF REWARD. By Mikhail Papovsky CEO, Abraic, Inc.
THE ITERATIVE ENGAGEMENT MODEL A CALCULATED RISK AND A WHOLE LOT OF REWARD By Mikhail Papovsky CEO, Abraic, Inc. Fall 2016 1 The traditional vendor engagement model is flawed. Technology initiatives are
More informationClient: Model File Limited Prepared by: MK Date: 30/03/17
5.02 A. Audit Strategy: Refer to Section 6.2.3 of the Manual for further guidance on completion of the Audit Strategy. See Appendix I - Section 6 on the matters that may be considered in developing an
More informationDefinition of a lease: Applying the new lease standards
Definition of a lease: Applying the new lease standards May 12, 2016 kpmg.com/ca/leases Today s presenters Jeff King Partner Accounting Advisory 416.777.8458 jgking@kpmg.ca Mag Stewart Partner Professional
More informationFM 3.09 Understanding Support Services Operations in an Organisation FM.4.04 Understanding facilities management support services operations
FM 3.09 Understanding Support Services Operations in an Organisation FM.4.04 Understanding facilities management support services operations Mal Ashall CBIFM MRICS Agenda FM 3.09/FM4.04 Understanding Support
More informationINTERNAL AUDIT OF PROCUREMENT AND CONTRACTING
OFFICE OF THE COMMISSIONNER OF LOBBYING OF CANADA INTERNAL AUDIT OF PROCUREMENT AND CONTRACTING AUDIT REPORT Presented by: Samson & Associates February 20, 2015 TABLE OF CONTENT EXECUTIVE SUMMARY... I
More informationWhy Businesses Love Payables Lockbox
Why Businesses Love Payables Lockbox (And Yours Should, Too!) A whitepaper examining how businesses can streamline accounts payable processing, reduce payment processing time, and lower accounts payable
More informationMicrosoft Requirements Guide. Yes. Yes. Y e s. Contact Shared Services. Contact Dawn Darby at Microsoft
Microsoft Requirements Guide Yes Contact Shared Services Contact Dawn Darby at Microsoft 613-232-4684 Does the requirement fall under Shared Services Mandate? SSC Provisioning Email NO No And Premier Support
More informationManagement Information Systems. B14. Acquiring IT Applications and Infrastructure
Management Information Systems Management Information Systems B14. Acquiring IT Applications and Infrastructure Code: 166137-01+02 Course: Management Information Systems Period: Spring 2013 Professor:
More informationFramework Information Day
Framework Information Day 11 th July 2017 http://www.southernconstructionframework.org.uk Agenda Welcome What will we cover today Who and what we are Duties, performance and the mini competition process
More informationACTIONS FOR RECOVERY. An Essential Industry creating immediate solutions
ACTIONS FOR RECOVERY An Essential Industry creating immediate solutions INVESTMENT IN CONSTRUCTION ACTIVITIES CREATES UNIQUE AND IMMEDIATE ECONOMIC, SOCIAL AND ENVIRONMENTAL BENEFITS ACROSS THE COMMUNITY.
More informationMANSFIELD DISTRICT COUNCIL Creating a District where People can Succeed SINGLE STATUS AND JOB EVALUATION - INFORMATION FOR JOB APPLICANTS
MANSFIELD DISTRICT COUNCIL Creating a District where People can Succeed SINGLE STATUS AND JOB EVALUATION - INFORMATION FOR JOB APPLICANTS This information is designed to inform you about two key issues
More information10 STEPS. Τhe. in selling your business BUSINESS SELLING YOUR
SELLING YOUR BUSINESS Τhe 10 STEPS in selling your business A chieving the right price at the right time in regard to the sale of your business requires a huge amount of listening, learning and preparation;
More informationStrategic procurement in capital expenditure the use of program management & delivery
Strategic procurement in capital expenditure the use of program management & delivery Project Scope Changes Changing Client Needs Environment of Uncertainty Diverse Stakeholder Interests Community Involvement
More informationNSW DEPARTMENT OF EDUCATION AND COMMUNITIES
NSW DEPARTMENT OF EDUCATION AND COMMUNITIES Position Description POSITION DETAILS Position Title: Reports to: Manager, Asset Management Unit (Various locations) Manager, Delivery Date: April 2010 PRIMARY
More informationperspective Googlization and Amazonization of Procurement Essential building blocks for increasing user and spend adoption
perspective Googlization and Amazonization of Procurement Essential building blocks for increasing user and spend adoption Introduction Making an informed choice on sourcing and procuring best quality
More informationKseniia Jones Senior Manager Global Risk Advisory Deloitte UK
Inside magazine - Edition 2018 You and I were The rise of managed services Hugo Morris Partner Managed Risk Services Deloitte UK Mark Whitehead Director UK Risk Advisory Deloitte UK Kseniia Jones Senior
More informationMILITARY OUTSOURCING: UK EXPERIENCE. Professor Keith Hartley Director Centre for Defence Economics University of York
MILITARY OUTSOURCING: UK EXPERIENCE Professor Keith Hartley Director Centre for Defence Economics University of York Introduction The UK Ministry of Defence (MoD) and the Armed Forces have considerable
More informationBuilding and operating the UK s infrastructure. Establishing your roadmap to success
Building and operating the UK s infrastructure Establishing your roadmap to success Building for the future The UK government has issued a challenge to the sector to remedy a 50 year backlog in investment
More informationinform practice note Issued by the Construction Industry Development Board
construction industry development inform practice note Issued by the Construction Industry Development Board Development through partnership construction procurement and delivery CONSTRUCTION PROCUREMENT
More informationExtended Enterprise Risk Management
Extended Enterprise Risk Management Driving performance through the extended enterprise October 2015 A network within a network The Extended Enterprise is the concept that an organization does not operate
More informationInternal Audit Challenges & Opportunities Speaker: Laurie Shen, Director, Grant Thornton LLP
Internal Audit Challenges & Opportunities Speaker: Laurie Shen, Director, Grant Thornton LLP March 28, 2012-1 - Speaker Introduction Laurie Shen is a Director at Grant Thornton's Northeast Internal Audit
More informationDirector Procurement & Value Delivery
Position Reports to Direct Reports Band Director Procurement & Value Delivery Chief Executive Heads of Procurement (3), Sustainability Officer (1), Head Procurement Operations (1), Head Clinical Engagement
More informationInternal Oversight Division. Internal Audit Strategy
Internal Oversight Division Internal Audit Strategy 2018-2020 Date: January 24, 2018 page 2 TABLE OF CONTENTS LIST OF ACRONYMS 3 1. BACKGROUND 4 2. PURPOSE 4 3. WIPO STRATEGIC REALIGNMENT PROGRAM 5 (A)
More informationTrends in Public Management: a Road Authority Perspective
Trends in Public Management: a Road Authority Perspective Ass. Professor Peter Smidt Deloitte-Nyenrode Public Governance Research Institute Warsaw, Piarc, October 20 2005 Associate Professor Peter Smidt
More informationSlide 1. The market for Public-Private Partnerships in Germany
Slide 1 The market for Public-Private Partnerships in Germany Slide 2 What is PPP? Agreement on Planning + Building + Financing + Operation (+ Post-contract life) between public and private partners PPP
More informationAn Analysis of the UK MoD s Through-Life Approach to Weapon Systems Sustainment
An Analysis of the UK MoD s Through-Life Approach to Weapon Systems Sustainment William Lucyshyn Director of Research and Senior Research Scholar Center for Public Policy and Private Enterprise School
More informationGovernance and decision rights. HR Business Partner and Centers of Expertise. The HR Chief Operating Officer. HR Organization
5 HR Business Partner and Centers of Expertise 6 Governance and decision rights HR Organization 4 The HR Chief Operating Officer 5 HR Business Partners and Centers of Expertise HR is at a turning point.
More informationWider Adoption of PPP Models in Hong Kong
Public Private Partnerships Opportunities and Challenges Wider Adoption of PPP Models in Hong Kong Malcolm PEARSON Executive Director Maunsell Consultants Asia Ltd Hong Kong Convention and Exhibition Centre
More informationfuture The of lean government Authors Shared Service Centres in the public sector 1 Dinu Bumbăcea Partner Management Consulting
The future of lean government Authors Dinu Bumbăcea Partner Management Consulting Radu Andrei Principal Management Consulting Shared Service Centres in the public sector 1 Shared Service Centres in the
More informationpwc.com.au PwC Infrastructure Advisory (Brisbane) Darren Black November 2013
pwc.com.au Infrastructure Advisory (Brisbane) Darren Black November 2013 Discussion Points Commercial Feasibility Objectives o What is the Point of the Business Case? o Risk Development o Updated Business
More informationPolicy,Legal and Regulatory Frameworks
Policy,Legal and Regulatory Frameworks Anthony Smith Chairman PPP Experts Head of Legal Dept. Altra Capital Member United Nations PPP Team of Specialists Former Head of United Nations PPP Readiness Task
More informationTake a bold, new path
Take a bold, new path Deal Advisory / South Africa We can help guide you through a successful Buy Side transaction. Supporting your growth agenda by helping you buy the right assets at the right price.
More informationMaking capital work Unlocking cash through cross-collaboration
Attack the Flat : strategies to succeed in the challenging construction market Article 2 Making capital work Unlocking cash through cross-collaboration In today s challenging construction market, leading
More informationLexis PSL Commercial. Transition in outsourcing
Transition in outsourcing 1 Please note that while this Practice Note is a comprehensive document, it does refer to some supplemental resources which are only available with a paid subscription to LexisPSL.
More informationCorporate Governance Statement
Corporate Governance Statement Statutory Corporate Governance Statement pursuant to section 107b of the Danish Financial Statements Act for the financial year 2017 NNIT A/S INTERNAL USE 2015-02-17 Table
More informationAGEC 429: AGRICULTURAL POLICY LECTURE 3: THE AGRICULTURAL POLICY PROCESS
AGEC 429: AGRICULTURAL POLICY LECTURE 3: THE AGRICULTURAL POLICY PROCESS AGEC 429 Lecture #3 THE AGRICULTURAL POLICY PROCESS The policy process begins with groups and individuals with policy goals pressuring
More informationReady or Not, Here Come the New Lease Accounting Standards
Ready or Not, Here Come the New Lease Accounting Standards JLL Michael Billing Managing Director Global Lease Accounting Lead sig.org/summit Ready or not Here come the new lease accounting standards Michael
More informationNgäi Tahu Property Position Description. Project Manager
Ngäi Tahu Property Position Description Project Manager Position Title: Reporting to: Project Manager Auckland Senior Project Manager Date created: 1/04/2017 Date last updated: 10/05/2017 # Direct reports:
More informationAdvanced Agriculture and Advisory Systems in Denmark Danish advisory service. Chief crop advisor Hans Henrik Fredsted Agrovi, Denmark
Advanced Agriculture and Advisory Systems in Denmark Danish advisory service Chief crop advisor Hans Henrik Fredsted Agrovi, Denmark CV Education and working experience Msc. Agronomy 2001 Agronomist crop
More informationRISK MANAGEMENT. Harald Wagner PhD, PE
WATER RESOURCES & HYDROPOWER DEVELOPMENT IN ASIA TRAINING COURSE ON CONTRACT MANAGEMENT VIENTIANE, LAO PDR February 28-29, 2016 GUEST LECTURE RISK MANAGEMENT Principles in Hydropower Tunnelling Harald
More informationFiduciary Duty of Board of Directors to Oversee Financial Affairs
Fiduciary Duty of Board of Directors to Oversee Financial Affairs 1. Need for Financial Oversight Corporate governance has been an important issue on the national agenda since the Enron scandal, which
More informationKrakow Center IBM Corporation
Krakow Center 2011 IBM Corporation 1 ABOUT US Business Transformation Outsourcing (BTO) combines process, people and technology transformation in an outsourced delivery model. Rather than just taking over
More informationPRODUCT INFORMATION MANAGEMENT
RSM TECHNOLOGY ACADEMY Syllabus and Agenda PRODUCT INFORMATION MANAGEMENT FOR MICROSOFT DYNAMICS AX Course Details 3 Audience 3 At Course Completion 3 Course Cancellation Policy 5 Guaranteed to Run 5 Travel
More informationIMPROVING THE DELIVERY OF SOCIAL HOUSING IN UK- USING THE AMPHION INITIATIVE AS A CASE STUDY
IMPROVING THE DELIVERY OF SOCIAL HOUSING IN UK- USING THE AMPHION INITIATIVE AS A CASE STUDY Yamuna Kaluarachchi and Keith Jones School of Architecture and Construction, The University of Greenwich Avery
More informationASEAN CHARTER AND ASEAN LAWYERS FOR THE RULE OF LAW, ACCESS TO JUSTICE AND HUMAN RIGHTS
ASEAN CHARTER AND ASEAN LAWYERS FOR THE RULE OF LAW, ACCESS TO JUSTICE AND HUMAN RIGHTS Dr. Luu Tien Dzung Partner, YKVN Lawyers Chairman, International Cooperation, Vietnam Bar Federation. 1 Introduction
More informationGCC VAT implementation roadmap are you ready?
GCC VAT implementation roadmap are you ready? www.kpmg.com/qa A brief introduction to VAT in the GCC The GCC states have worked together to develop a broad framework to introduce Value-Added Tax (VAT).
More informationAuthors: Majella Clarke, Petra Mikkolainen, Marisa Camargo, Nagmeldin Elhassan
The World Bank Second Evaluation of the Forest Carbon Partnership Facility Final Report Authors: Majella Clarke, Petra Mikkolainen, Marisa Camargo, Nagmeldin Elhassan Helsinki, Finland 7580 September 19,
More informationPROCURE-TO-PAY INVENTORY MANAGEMENT
RSM TECHNOLOGY ACADEMY Syllabus and Agenda PROCURE-TO-PAY INVENTORY MANAGEMENT FOR MICROSOFT DYNAMICS AX Course Details 3 Audience 3 At Course Completion 3 Course Cancellation Policy 5 Guaranteed to Run
More informationTransforming the HR function for high performance. kpmg.com
Transforming the HR function for high performance kpmg.com Contents 01 Driving the people agenda 5 02 Measuring value 8 03 Succeeding in a changing world 10 04 Taking HR to the next level 12 05 Getting
More informationMARKET REVIEW INTO THE OWNERSHIP AND COMPETITIVENESS OF INFRASTRUCTURE PROVISION PSR MR15/2.1
8 September 2015 infrastructurereview@psr.org.uk Direct Line 020 3217 8276 Stuart.Cole@chequeandcredit.co.uk Infrastructure Review Team Payment Systems Regulator (15th floor) 25 The North Colonnade Canary
More information2017 Four Year Plan Guide
2017 Four Year Plan Guide June 2016 ISBN: 978-0-478-43458-3 Crown copyright ISBN 978-0-478-43458-3 (Online) This copyright work is licensed under the Creative Commons Attribution 4.0 International licence.
More informationHead of Finance, Governance and Risk Management in the Residential Tenancies Board (RTB) Assistant Director (Professional Accountant Grade I)
Head of Finance, Governance and Risk Management in the Residential Tenancies Board (RTB) Assistant Director (Professional Accountant Grade I) Applications are now sought to fill the post of Head of Finance,
More informationSynoptek Managed AWS: Cloud Optimization & Risk Mitigation
Synoptek Managed AWS: Cloud Optimization & Risk Mitigation Snap your fingers. If you re among those who think that cloud computing works like that, you ve been watching too many commercials. Like the many
More informationLooking beyond simple savings
Looking beyond simple savings PwC Singapore s Sourcing and Procurement Practice www.pwc.com/sg 2 Looking beyond simple savings l PwC Singapore s Sourcing and Procurement Practice Procurement for the 21
More informationPROGRESS TOWARD SUSTAINABLE ENERGY
PROGRESS TOWARD SUSTAINABLE ENERGY Global Tracking Framework 2015 What is the Global Tracking Framework? Global Tracking Framework preparing its third edition Title of Presentation 3 Global Tracking Framework
More informationCisco Unified Workspace Licensing
Solution Overview Workspace Licensing The Challenge Today s organizations must contend with increasingly complex communications environments featuring a wide array of communications methods. Globally dispersed
More informationMaximizing $avings Through Innovative Procurement Methods
Maximizing $avings Through Innovative Procurement Methods 1301 East 2nd Street, Sanford, FL 32771 (407) 665-7112 Office bcohen@seminolecountyfl.gov Betsy J. Cohen C.P.M., CPPO, CPPB January 4, 2016 BACKGROUND:
More informationOwn your business? Own your numbers.
Own your business? Own your numbers. Find out how the right bilingual software can make accounting simple for you, so you can manage costs, cash, invoicing, and taxes with confidence all in the language
More informationTECHNICAL SUMMARY. The Use of Warehouse Receipt Finance in Agriculture in Transition Countries
TECHNICAL SUMMARY The Use of Warehouse Receipt Finance in Agriculture in Transition Countries by Frank Höllinger, Lamon Rutten, and Krassimir Kiriakov, Working paper, FAO Investment Centre, St. Petersburg:
More informationISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE HANDOVER TO UNIVERSITY
THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 5 LAST MODIFIED 2 December 2010 DATE PRINTED RIBA stages JK JK 5 ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE
More informationThird Party Risk Management ( TPRM ) Transformation
Third Party Risk Management ( TPRM ) Transformation September 20, 2017 Internal use only An introduction to TPRM What is a Third Party relationship? A Third Party relationship is any business arrangement
More informationTOWN ADMINISTRATOR. Position Purpose:
TOWN ADMINISTRATOR Position Purpose: Performs professional management work overseeing activities of town departments under the jurisdiction of the Board of Selectmen and in accordance with federal, state,
More informationrepresents a likely source of cost savings, improved business performance and stronger customer-facing capabilities.
Achieving operational excellence with EY and Guidewire EY Insurance Nexus EY Insurance Nexus The complete strategic offering for cloud-based modernization of core insurance technology for P&C carriers
More informationSuccessfully Implementing T&E Globally
Sven Ringling Hannah Smith Successfully Implementing T&E Globally 1 iprocon: Better HR www.iprocon.com Agenda Rollout Strategies Lessons Learnt from Customer Projects Implementation Top Tips 2 Rollout
More informationES. EXECUTIVE SUMMARY FOR RESIDENTIAL MULTI-FAMILY PROGRAM AREA (R5)
ES. EXECUTIVE SUMMARY FOR RESIDENTIAL MULTI-FAMILY PROGRAM AREA (R5) ES.1 INTRODUCTION This volume presents results of a comparative analysis of residential multi-family comprehensive programs included
More informationGlobal Infrastructure Facility
Global Infrastructure Facility ------------------------------------------------------------------------------------------------------------------- Partnership Framework As Adopted by the Governing Council
More informationPPPS IN THE SOCIAL SECTORS: EDUCATION AND HEALTH
PPPS IN THE SOCIAL SECTORS: EDUCATION AND HEALTH JACQUES COOK PUBLIC-PRIVATE PARTNERSHIP WHITE PAPER SERIES Introduction Public-Private Partnerships (PPPs) have been successfully applied in many countries
More informationSustainability in Facilities Management Report 2013
Sustainability in Facilities Management Report 2013 E X E C U T I V E S U M M A R Y Sponsored by Acknowledgements: AUTHORS This report has been produced with the support of the following individuals: Sunil
More informationA Strategic Approach to Bank Fraud
Fraud Case Study A Strategic Approach to Bank Fraud How Banks Can Move From Reactive to Proactive Fraud Prevention and Detection Fraud prevention and detection remains one of the biggest and most pressing
More informationAcquiring e-sourcing and e-procurement Technology
Acquiring e-sourcing and e-procurement Technology What Questions Should You Really Ask? by Michael Lamoureux, Ph.D. Editor-in-Chief, Sourcing Innovation http://blog.sourcinginnovation.com/ Webinar Overview
More informationContinuous Monitoring - Definition
Agenda Continuous Monitoring ADB Treasury Operation Road Map for Introducing Continuous Monitoring in Treasury Investment Activities using ACL Lessons Learnt References Q&A 2 Continuous Monitoring - Definition
More informationTop 5 reasons to upgrade Infor Lawson
Top 5 reasons to upgrade Infor Lawson In today s fast-paced, changing world, it s critical to keep your systems current. Which is why Infor has made significant investments in evolving the Infor Lawson
More informationChecklist for Higher Education
Checklist for Higher Education The following section contains a checklist addressing issues of particular relevance to higher education. The guidance is considered best practice for higher education. The
More informationA GUIDE TO BEST PRACTICES SMALL BUSINESS BASICS:
SMALL BUSINESS BASICS: A GUIDE TO BEST PRACTICES Starting Your Business Controlling Cash Flow Increasing Profitability Growing Your Business Protecting Your Assets Planning for Business Transition Similar
More informationRemuneration Committee : Time to Raise the Bar? kpmg.com.my/aci
Audit committee institute Remuneration Committee : Time to Raise the Bar? kpmg.com.my/aci Foreword Remuneration invariably factors in the attraction and retention of top talent, particularly against the
More informationThe US PPP Market: Is a Common Institutional Framework Possible?
The US PPP Market: Is a Common Institutional Framework Possible? Michael J. Garvin, PhD, PE Associate Professor & Associate Director Virginia Tech Open Day, 22 March 2012 PPP in Transport: Trends & Theory
More information1 C. The Chief Executive Officer Affiliate Class of Services are 2 Provided at a Reasonable Cost
1 C. The Chief Executive Officer Affiliate Class of Services are 2 Provided at a Reasonable Cost 3 Q. Are the costs of the Chief Executive Officer affiliate class of services 4 reasonable? 5 A. Yes. The
More information