JOB SAFETY ENVIRONMENT ANALYSIS (JSEA) CS-OHS-11

Size: px
Start display at page:

Download "JOB SAFETY ENVIRONMENT ANALYSIS (JSEA) CS-OHS-11"

Transcription

1 CS ENERGY PROCEDURE FOR JOB SAFETY ENVIRONMENT ANALYSIS (JSEA) CS-OHS-11 Responsible Officer: HSSE Management Systems Specialist Responsible Executive: Group Manager Health Safety Security and Environment DOCUMENT HISTORY Key Changes Prepared By Checked By Approved By Date Issued for implementation F Welch 15/04/2003 Modified F Welch 21/10/2005 Updated to include new JSEA form and consistent with training package Updated to include latest risk management framework Review of content to reflect Risk Management Framework by Risk and Assurance Inclusion of the additional requirements of Safe Work Method Statements for Overhauls and High Risk Construction Work. Update format. F Welch 19/11/2008 F Welch 14/03/2011 B Johnson 29/09/2011 D Clarke K Ussher K Ussher 22/08/2013 Page 1

2 CONTENTS DOCUMENT HISTORY PURPOSE CONTEXT SCOPE RESPONSIBILITIES AND ACCOUNTABILITIES Group Manager Health Safety, Security and Environment Site Manager Superintendents and Supervisors Principal s Site Representative Health and Safety Specialists/Advisors Officers in Charge / Person in Charge of Work APPLICATION When to Use a JSEA When to Modify a JSEA Completing a JSEA Identifying the Tasks for the Work Being Assessed Identifying Hazards and Environmental Impacts Assess the Risk Initial Determine the Control Measures Assess the Risk with the Control Measures Residual Checking, authorisation and sign-off SAFE WORK METHOD STATEMENTS FOR CONSTRUCTION WORK Purpose of a safe work method statement (SWMS) Using a JSEA as a SWMS for Construction Work RECORDING MONITORING AND REVIEW TRAINING DEFINITIONS REFERENCES APPENDIX 1 JSEA FLOW CHART APPENDIX 2 S1878 JSEA FORM APPENDIX 3 S2136 SAFE WORK METHOD STATEMENT DECLARATION APPENDIX 4 JSEA QUALITY CHECKLIST AND SCORE Page 2

3 1 PURPOSE The purpose of this procedure is to provide the minimum requirements for personnel to conduct a Job Safety and Environmental Analysis (JSEA) effectively across CS Energy sites. The aim of a Job Safety and Environmental Analysis is to evaluate, select, record and specify safe systems of work to eliminate or minimise the risk of injury, illness, hazard exposure, near miss, property damage, environmental impact and process loss in the performance of work and enable the work to be completed with the risk level as low as is reasonably practicable. 2 CONTEXT The JSEA is a formalized and structured process within the CS Energy risk management system following the standards set out in the CS Energy Risk Management Framework. It is an essential part of a safe system of work as it provides a process for hazard identification, risk assessment and implementing suitable control measures based on the hierarchy of control. It is a mandatory component of the Permit to Work (PTW) system. The JSEA is a higher level risk management tool to the Task Risk Analysis (TRA). While the TRA is the initial risk assessment tool for any work, its resulting outcome determines whether a JSEA is required, such as if the risk is significant or high and/or a PTW is required. The aim of the JSEA is to eliminate a hazard or where this is not possible; the risks associated with the hazard are reduced to as low as is reasonably practicable. 3 SCOPE This procedure applies to all CS Energy company employees, and any other persons working for, or on behalf of CS Energy and its associated operations. This procedure is not intended to consider specialist plant control, reliability, efficiency and risk analysis methods that may be used via specific and specialised risk management tools e.g. fault tree analysis, outcome analysis and hazard and operability studies. All personnel shall be informed of this procedure at induction. Additional competency based training shall be undertaken as part of the company health and safety training program. Contractors may use the risk analysis tool specific to their organisation, only if it does not compromise the integrity of the requirements of CS Energy s procedures and format, i.e. must include a breakdown of the task or activity, task steps, hazards identified, control measures proposed and an assessment of the risk outcome. These are to be approved by site management. 4 RESPONSIBILITIES AND ACCOUNTABILITIES 4.1 Group Manager Health Safety, Security and Environment Group Manager for Health Safety, Security and Environment is responsible for authorisation of any JSEA completed where the residual risk assessed is high. 4.2 Site Manager Managers are responsible for: implementation of this procedure; ensuring sufficient resources are provided to effectively conduct JSEAs; Page 3

4 provision of appropriate training; authorisation of a completed JSEA where the residual risk is significant; and ensuring quality and effective JSEAs are carried out. 4.3 Superintendents and Supervisors Superintendents and Supervisors are responsible for: monitoring compliance with this procedure and the risk control measures being implemented by the work party/team members; conducting periodic review of process, completed JSEA s for quality and adherence to the PTW scope of work and report on effectiveness and application; provision of appropriate training and other support to all personnel in application of this procedure; conducting and/or assisting personnel with JSEAs; and authorisation of a completed JSEA where the residual risk is moderate. 4.4 Principal s Site Representative The CS Energy principal s site representative is responsible for: ensuring contractors are aware of the requirement to provide JSEAs for the work they perform on site; reviewing contractors completed JSEAs for compliance with CS Energy s health and safety site rules and conditions; and obtaining assistance from the relevant site specialist, where necessary, to review and comment on contractor developed JSEAs. 4.5 Health and Safety Specialists/Advisors The Health and Safety Specialists/Advisors are responsible for: providing support and advice to personnel regarding a JSEA; periodic monitoring and review of completed JSEA s to the CS Energy standard; and ensure the procedure and form is relevant and current. 4.6 Officers in Charge / Person in Charge of Work Officers in Charge (OIC) and Persons in Control of Work (PCW) are responsible for: preparing the JSEA prior to the work being performed and modifying the JSEA if conditions or the scope of work change; involving team members or work party members in the development of the JSEA; seeking assistance from the technical/experienced persons on site in identifying hazards and implementing appropriate control measures; monitoring the work tasks to verify the control measures are implemented, effective and appropriate for the work; Page 4

5 identifying any new hazards in the work activity that have been previously overlooked, have appeared due to a change in work conditions or if the controls put in place have not been effective in controlling the risk; and Communicating the JSEAs to work party team members via training and or site instruction. 5 APPLICATION The application and process steps outlined in this section are illustrated in Appendix 1, JSEA Flow Chart. 5.1 When to Use a JSEA A JSEA must be completed: i. for any work that is assessed with a residual risk rating as moderate, significant or high (following the outcomes from a TRA; refer to CS-OHS-46, Procedure for Conducting a 2X2 Task Risk Analysis); ii. for any work requiring a PTW and prior to the issue of the PTW; iii. before introducing any new plant, machinery, equipment, hazardous substances or work practices; iv. prior to making design changes or modifications to plant or equipment that will affect the way the plant is used, the procedures associated with the plant or the location of the plant; v. when work activities or modifications to any plant or equipment has the potential to release a contaminant to the environment or storm water or to exceed site license conditions; vi. prior to removing or installing safety features (guardrails, machinery guards, interlocks, covers, flooring); vii. prior to conducting live electrical work; viii. prior to performing work in proximity to or with bonded asbestos containing materials and friable asbestos; or ix. prior to working with or adjacent to areas or plant with explosive atmospheres, excessive temperatures, vibration and flammable substances. 5.2 When to Modify a JSEA A JSEA shall be modified in consultation with personnel involved in the work: i. when changes to work are identified and additional hazards are introduced needing further control measures to be implemented; ii. after an incident or near miss to review/modify control measures to satisfy a safe system of work; iii. when information becomes known about a hazardous workplace environmental condition, hazardous work activity, process or behaviour; or iv. where a control measure is changed to improve its effectiveness. 5.3 Completing a JSEA To effectively conduct a JSEA, the following key steps and criteria are to be applied and documented on Form S1878, Job Safety and Environment Analysis. This process adheres to the CS Energy Risk Management Procedure. A form is detailed in Appendix 2, Sample JSEA Form. Page 5

6 5.3.1 Identifying the Tasks for the Work Being Assessed The work to be undertaken must be analysed and broken down into the individual tasks. Each of these tasks is recorded on the form in sequence of doing the work. Sufficient detail should be provided so that other people can understand and follow the work. Where possible, discuss the job tasks and activities with another person (i.e. work party member) who is familiar with the job to validate the tasks and sequence to efficiently and safely perform the work. Also, the JSEA must include: specific people and skills required for each step e.g. licensed person, rigger, crane driver etc; tools and equipment e.g. scaffolding, slings and crane etc; personal protective equipment required e.g. fall restraint harness etc; drawings e.g. P&ID, etc; and MSDS, e.g. chemicals Identifying Hazards and Environmental Impacts Potential hazards and environmental impacts are to be identified for each task and recorded on the JSEA form. The first page of the JSEA form provides a list of typical hazards and the relevant hazards can be documented against the relevant task Assess the Risk Initial Use the CS Energy 6x5 Risk Matrix (detailed in Appendix 2) to assess the risk for each task by determining the likelihood and consequence. This is the initial risk score to initiate what control measures are to be implemented. The risk matrix is detailed on Form S1878, Job Safety and Environment Analysis Determine the Control Measures Where a hazard has been identified, the preferred method to control the hazard is by eliminating the hazard. However, this is not always possible and risks associated with the hazard must be reduced so far as reasonably practicable. While there is no definite level of what represents reasonably practicable, it is essentially where the organisation has applied reasonable controls to reduce the risk to a safe level given the conditions present. CS Energy follows the hierarchy of controls 1 in determining the most appropriate manner in reducing risk. 1 Workplace Heath and Safety Act 27A Managing exposure to risks (2) To properly manage exposure to risks, a person should consider the appropriateness of control measures in the following order - (a) eliminating the hazard or preventing the risk; (b) if eliminating the hazard or preventing the risk is not possible, minimising the risk by measures that must be considered in the following order - (i) substituting the hazard giving rise to the risk with a hazard giving rise to a lesser risk (ii) isolating the hazard giving rise to the risk from anyone who may be at risk; (iii) minimising the risk by engineering means; (iv) applying administrative measures; (v) using personal protective equipment. Page 6

7 5.3.5 Assess the Risk with the Control Measures Residual Apply the CS Energy 6x5 Risk Matrix (detailed in Appendix 2) to assess the risk for each task with the identified control measures implemented. This new risk score is the residual risk for the work. This determines the level of authorisation required for work to proceed ensuring a safe system of work is followed Checking, authorisation and sign-off After the JSEA has been completed, and all details are recorded on the form, the JSEA must be checked by a second person. This may be a peer, supervisor or site specialist (e.g., Health and Safety / Environmental Coordinator, Chemist, Engineer etc.) dependant on the complexity and risk level of the work. The following authorisations are required: i. if the residual risk is moderate; authorisation by the Supervisor; ii. if the residual risk is significant; authorisation by the Site Manager; and iii. if the residual risk is high; authorisation by the Executive Production Manager. Once authorisations are complete, all personnel working on the job specific to the JSEA are to sign on to the JSEA form before they commence work, i.e. before the initial commencement of the job. Note: The hazards and risk shall be monitored/reviewed periodically throughout the job typically at the start of each shift using either the TRA or by updating the JSEA as determined by the conditions/risks. 6 SAFE WORK METHOD STATEMENTS FOR CONSTRUCTION WORK The Work Health and Safety Act 2011 requires safe work method statements for all high risk construction work in connection with a construction project. CS Energy overhauls, some outages and special projects are classified as construction work under the construction work definition. High risk construction work undertaken in connection with the project is to be outlined in the relevant Construction/Project Safety Plan. Safe Work Method Statements underpin the broader Safety Plan for the project. 6.1 Purpose of a safe work method statement (SWMS) The primary purpose of a SWMS is similar to that of JSEA. It enables supervisors, workers and any other persons at the workplace to understand the requirements that have been established to carry out the high risk construction work in a safe and healthy manner using the risk management method and hierarchy of control. The aim of a SWMS is to: describe the activity or task to be undertaken identify the resources, manpower and skills associated with the task assess and select control measures (as appropriate) systematically plan the activity so it can be completed efficiently and effectively. Page 7

8 6.2 Using a JSEA as a SWMS for Construction Work It is permissible to modify an existing JSEA (generic) developed for work that is carried out on regular basis and convert it to Safe Work Method Statement using the following guidelines: 1. A construction/project specific safe work method statement declaration [see Appendix 3] is attached that details: The person conducting a business or undertaking's name, address and ABN Details of the person(s) responsible for ensuring implementation, monitoring and compliance with the SWMS; The work is being carried out on the construction project: o o o o the name of the principal contractor; the address where the high risk construction work will be carried out; the date the SWMS was prepared; and the review date (if any). 2. The work and JSEA/SWMS is reviewed to ensure it applies to each new activity and actual workplace/work environment. 3. The JSEA/SWMS is submitted with the Construction/Project Safety Plan to enable CS Energy (PCBU) to be aware, review and approve the work scheduled to be carried out. Note: The content of a SWMS should provide clear direction on the control measures to be implemented. There should be no statements that require a decision to be made by supervisors or workers. For example, the statement 'use appropriate PPE' does not detail the control measures. The control measures should be clearly specified. 7 RECORDING Completed JSEA forms shall be maintained by the PTW Officer for all JSEAs associated to a PTW. All other JSEAs are maintained by the relevant supervisor. These are to be available for review and monitoring purposes. Records shall be kept and maintained for at least 5 years 8 MONITORING AND REVIEW Periodic monitoring and review of JSEAs shall be conducted to determine and maintain the quality and effectiveness of JSEAs. Monitoring and review shall be conducted at each site: at a frequency nominated by the site manager; and by senior staff nominated by the site manager. This will also be supplemented with periodic monitoring and review by CS Energy health and safety. A checklist to qualify monitoring and review performed on JSEAs is detailed in Appendix 3. Additionally, CS Energy Health & Safety will conduct a formal review of this procedure every two years. The review will evaluate the effectiveness of the Job Safety Analysis Procedure, to prioritise, identify, assess and control risks. Page 8

9 9 TRAINING All personnel, both employees and contractors, are to be appropriately trained in the risk management process including hazard identification and risk assessment, i.e. JSEA process. All personnel shall be given basis risk management training during their induction. The level of training required for personnel with the functions within the roles of the PTW process is to follow the requirements outlined in: CS Energy PTW Manual, CS-PTW-01; and Training and Authorisation of Roles in the PTW System, CS-PTW-SOP-02; refer to Section 5, Training and Competency Matrix The CS Energy preferred training is the Hazard Identification Risk Assessment (HIRA). Refresher training for those people trained to the HIRA or equivalent level is required at least every 2 years. Refresher training shall cover any changes/improvements to the JSEA and/or TRA process and be a forum for discussion about the process. Page 9

10 10 DEFINITIONS Hazard Term Definition A source of potential harm to personnel, plant or the environment Office in Charge (OIC) Permit to Work Officer (PTWO) Person in Charge of Work (PICW) Principal s Site Representative Risk Risk Assessment Risk Matrix Work Party An authorised person who has successfully completed all appropriate OIC training and is deemed competent. They coordinate the work and where applicable, a workgroup which is operating within a specific PTW. The OIC carries the responsibility for the PTW once issued. An authorised person who has successfully completed all appropriate PTW training and is deemed competent to isolate the plant and issue a PTW allowing work to safely proceed, then on return close the PTW and restore the plant An authorised person who has successfully completed the required training and is authorised as competent to coordinate and manage work under a PTW. This role is responsible for managing the work party signed onto the PTW to complete work within the isolation boundary. A site based person representing the Principal for the overall management of technical / commercial aspect of the contract for the Principal. Effect of uncertainty on objectives Overall process of risk identification, risk analysis and risk evaluation. A table to analyse risk resulting in the magnitude of risk expressed in terms of the combination of consequences and their likelihood. All persons who perform specific work activities as coordinated by an Officer In Charge under a Permit To Work. 11 REFERENCES Reference No Reference Title Author Work Health and Safety Act 2011 Aust Govt Work Health and Safety Regulations 2011 Aust Govt Electrical Safety Act 2002 Qld Govt Electrical Safety Regulation 2002 Qld Govt Electrical Safety Code of Practice 2010 Risk Management Qld Govt AS/NZS 4360 Risk Management Aust Standard "B/D/11/30977" Procedure - CS-OHS-M-01 - Health and Safety Manual CS Energy "B/D/11/19582" Procedure - CS-PTW-01 - Permit to Work (PTW) Manual CS Energy "B/D/11/30968" Procedure - CS-OHS-46 - Conducting 2x2 Task Risk Analysis CS Energy "B/D/10/21585" Form - S JSEA - Job Safety and Environmental Analysis Template CS Energy "B/D/13/25987" Form - S Safe Work Method Statement Declaration CS Energy Page 10

11 12 APPENDIX 1 JSEA FLOW CHART Job to be performed Risk Assessment Process - JSEA Is a JSEA required for work? Yes Identify individual Tasks If conditions change or control measures are ineffective No Conduct a Task Risk Analysis Identify Hazards Assess the RISK (Initial) Determine Control Measures Assess the Risk (Residual) Acknowledgement and Authorisation Process JSEA Check (by another person) Authorisation Perform Task Sign off by work party Monitor Conditions (use TRA) Records (PTW Office or supervisor) Page 11

12 13 APPENDIX 2 S1878 JSEA FORM TRIM Reference: "B/D/10/21585" Page 12

13 Page 13

14 Page 14

15 Page 15

16 14 APPENDIX 3 S2136 SAFE WORK METHOD STATEMENT DECLARATION TRIM Reference: "B/D/13/25987" Page 16

17 15 APPENDIX 4 JSEA QUALITY CHECKLIST AND SCORE Checklist against CS Energy Procedure for a Job Safety and Environmental Analysis, CS-OHS-11 Effectiveness Measure: 1 = Not established, not effective 5 = fully established, fully effective JSEA Quality Elements 1. Supervisor conducted JSEA review and provided for feedback/input from all workers. 2. All workers participated in the JSEA review before starting work. 3. JSEA is readily visible and appropriately maintained at job location. 4. JSEA includes all job steps for specific task. 5. JSEA identifies and records all actual or potential safety/health hazards. 6. JSEA identifies that all associated hazards are eliminated or mitigated. 7. Required PPE is listed on JSEA and all PPE properly used by workers. 8. JSEA signed by OIC/Supervisor 9 JSEA has been authorised by appropriate person. 10. All nominated personnel have signed onto the JSEA. 11. Field observations at job location indicate all workers are following JSEA. 12. JSEA records all modifications when the work scope or job conditions change. 13. Steps and work instructions for job task are provided to all workers. 14. JSEA training has been completed by all work party members on task. Score : Effectiveness (1 to 5) Comments % Effectiveness : (100 x Score / 70) Page 17

CS ENERGY PROCEDURE FOR A JOB SAFETY AND ENVIRONMENTAL ANALYSIS CS-OHS-11

CS ENERGY PROCEDURE FOR A JOB SAFETY AND ENVIRONMENTAL ANALYSIS CS-OHS-11 CS-OHS-11 (Amd 09/11) CS ENERGY PROCEDURE FOR A JOB SAFETY AND ENVIRONMENTAL ANALYSIS CS-OHS-11 Responsible Officer: Group Manager Health and Safety Approved: EGM Corporate CONTENTS 1 Purpose... 3 2 Context...

More information

CONDUCTING 2X2 TASK RISK ANALYSIS CS-OHS-46

CONDUCTING 2X2 TASK RISK ANALYSIS CS-OHS-46 CS-OHS-46 (Amd 01/11) CS ENERGY PROCEDURE FOR A CONDUCTING 2X2 TASK RISK ANALYSIS CS-OHS-46 Responsible Officer: Group Manager Health and Safety Approved: GM Corporate CONTENTS 1 Purpose... 2 2 Context...

More information

CONDUCTING SAFETY INTERACTIONS CS-OHS-19

CONDUCTING SAFETY INTERACTIONS CS-OHS-19 CS ENERGY PROCEDURE FOR CONDUCTING SAFETY INTERACTIONS CS-OHS-19 Responsible Officer: Health, Safety and Security Coordinator Responsible Executive: Group Manager Health Safety Security and Environment

More information

CONDUCTING CRITICAL CONTROL AUDITS CS-OHS-60

CONDUCTING CRITICAL CONTROL AUDITS CS-OHS-60 CS ENERGY PROCEDURE FOR CONDUCTING CRITICAL CONTROL AUDITS CS-OHS-60 Responsible Officer: Health and Safety Specialist Responsible Executive: Group Manager Safety Environment and Quality DOCUMENT HISTORY

More information

Safe Operating Procedures 1 SECTION 1 INTRODUCTION 2 PURPOSE 2 SCOPE 2 DEFINITIONS 2 LEGISLATIVE CONTEXT 4

Safe Operating Procedures 1 SECTION 1 INTRODUCTION 2 PURPOSE 2 SCOPE 2 DEFINITIONS 2 LEGISLATIVE CONTEXT 4 OH&S Guideline Name: Approved by: Safe Operating Procedures Director Human Resources Last reviewed: December 2013 Safe Operating Procedures 1 SECTION 1 INTRODUCTION 2 PURPOSE 2 SCOPE 2 DEFINITIONS 2 LEGISLATIVE

More information

WHS Management Plans

WHS Management Plans WHS Management Plans Disclaimer This Guide provides general information about the obligations of persons conducting a business or undertaking and/or persons in control of premises and workers under the

More information

Permit to Work Manual

Permit to Work Manual Permit to Work Manual Release Date March 2016 CS-PTW-01 Version 3.1 Originator PTW Committee For further information, contact your supervisor or the site safety department. THIS DOCUMENT IS UNCONTROLLED

More information

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Manager Environment Approved: Executive General Manager Asset Strategy DOCUMENT HISTORY Date

More information

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Environmental Specialist Responsible Manager: Head of Environment Responsible Executive:

More information

HAZARD / IMPROVEMENT REPORTING CS-OHS-51

HAZARD / IMPROVEMENT REPORTING CS-OHS-51 CS ENERGY PROCEDURE FOR HAZARD / IMPROVEMENT REPORTING CS-OHS-51 Responsible Officer: Group Manager Health Safety Security and Environment Responsible Executive: Chief Executive Officer (CEO) DOCUMENT

More information

Health and Safety Manual

Health and Safety Manual Health and Safety Manual CS-OHS-M-01 Version 2 Effective date: 30 November 2012 Next review date: 01 November 2014 Health and Safety Manual CS-OHS-M-01 FOREWORD The foundation of CS Energy s success as

More information

Construction Safety Audit Scoring System (ConSASS) Audit Checklist

Construction Safety Audit Scoring System (ConSASS) Audit Checklist I 1.1 1 OSH Policy The occupier's management with executive or site responsibility shall define and document its policy for safety including objectives for its commitment to safety. (CP79 - Section 1.2)

More information

Asbestos Management Policy

Asbestos Management Policy ECM Document Set ID Number: 3428289 Revision Date: August 2016 July 2016 20 th July 2016 Risk Principal Approval Date: 20 th July 2016 Manager Works 20 th July 2016 Manager Building and Property Review

More information

Health & Safety Policy & Management Systems. Guidance Note 13

Health & Safety Policy & Management Systems. Guidance Note 13 Health & Safety Policy & Management Systems Guidance Note 13 1 Health & Safety Policy & Management Systems Introduction This Guidance Note gives practical information regarding basic health and safety

More information

Procedure. Work Health and Safety Pre-approved work. Document number: PRO Rev no.

Procedure. Work Health and Safety Pre-approved work. Document number: PRO Rev no. Procedure Work Health and Safety Pre-approved work Document number: PRO-01488 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

UNCONTROLLED IF PRINTED. Issued with the authority of the Chief Commissioner and General Manager of Scouts Australia NSW

UNCONTROLLED IF PRINTED. Issued with the authority of the Chief Commissioner and General Manager of Scouts Australia NSW PROCEDURE Contractor Safety Issued with the authority of the Chief Commissioner and General Manager of Chief Commissioner signature Chief Executive Officer signature Sponsor Head of Risk Document type

More information

Phoenix Energy Holdings Gas Ltd Health & Safety Policy

Phoenix Energy Holdings Gas Ltd Health & Safety Policy Phoenix Energy Holdings Gas Ltd Health & Safety Policy July 2017 Phoenix Energy Holdings Ltd Health & Safety Policy July 2017 Contents 1.0 Introduction 2.0 Purpose 3.0 Scope 4.0 References 5.0 Definitions

More information

PETROLEUM AND GAS SAFETY MANAGEMENT CS-OHS-02

PETROLEUM AND GAS SAFETY MANAGEMENT CS-OHS-02 CS ENERGY PROCEDURE FOR PETROLEUM AND GAS SAFETY MANAGEMENT CS-OHS-02 Responsible Manager: Group Manager Health Safety Security and Environment Responsible Executive: Chief Executive Officer (CEO) DOCUMENT

More information

Appendix 4A - SWMS Description

Appendix 4A - SWMS Description SAFE WORK METHOD STATEMENT (SWMS) Duty holders A person conducting a business or undertaking (PCBU) carrying out any high risk work in connection with a construction project is required to have a detailed

More information

Apply for Confined Space Permit

Apply for Confined Space Permit Apply for Confined Space Permit Details of revisions Level Details Date Initial 1 Creation of initial document for use MW Title: Apply for Confined space Permit (Guide) Date Published: ID: 000275 Version:

More information

Apply for Confined Space Permit

Apply for Confined Space Permit Apply for Confined Space Permit Details of revisions Level Details Date Initial 1 Creation of initial document for use MW 2 Amendment 16/01/2019 MW Title: Apply for Confined space Permit (Guide) Date Published:

More information

Health and Safety Management Standards

Health and Safety Management Standards Management Standards Curtin University Sept 2011 PAGE LEFT INTENTIONALLY BLANK Management Standards Page 2 of 15 CONTENTS 1. Introduction... 4 1.1 Hierarchy of Documents... 4 2. Management System Model...

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

CONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY

CONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY CONTRACTOR WHS SYSTEM STANDARD RISK MANAGEMENT EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

Health & Safety Policy

Health & Safety Policy Health & Safety Policy Policy Statement What is Comms-care s commitment to H&S Comms-care Group Ltd places the highest priority on protecting the health, safety and wellbeing of its employees and others,

More information

S25 Risk Assessment & Safe Systems of Work - 1 / 5

S25 Risk Assessment & Safe Systems of Work - 1 / 5 S25 Opening Statement Risk Assessment & Safe Systems of Work Risk assessment is the fundamental process for health and safety management. When investigating accidents and incidents it is nearly always

More information

TECHNICAL SUPPORT ASSOCIATES HEALTH AND SAFETY POLICY STATEMENT

TECHNICAL SUPPORT ASSOCIATES HEALTH AND SAFETY POLICY STATEMENT TECHNICAL SUPPORT ASSOCIATES HEALTH AND SAFETY POLICY STATEMENT Technical Support Associates 57-59 High Street Bagshot Surrey GU19 5AH Tel: 01276 476237 Email: enquiries@tsaservices.co.uk Website: www.tsaservices.co.uk

More information

MANUAL HANDLING PROCEDURE

MANUAL HANDLING PROCEDURE Document uncontrolled when printed Procedure ID no 0480/05 MANUAL HANDLING PROCEDURE This procedure is applicable to: All Department of Education and Children's Services employees. DOCUMENT CONTROL Managed

More information

OH&S MANAGEMENT SYSTEM CHECKLIST - AS 4801:2001 (STATUS A = Acceptable; N = Not Acceptable; N/A = Not Applicable)

OH&S MANAGEMENT SYSTEM CHECKLIST - AS 4801:2001 (STATUS A = Acceptable; N = Not Acceptable; N/A = Not Applicable) OH&S MANAGEMENT SYSTEM CHECKLIST - AS 4801:2001 (STATUS A = Acceptable; N = Not Acceptable; N/A = Not Applicable) 4.1 General Requirements 4.2 OHS policy Has the organisation an established and maintained

More information

National Health and Safety Function, Workplace Health and Wellbeing Unit, National HR Division. Guideline Document

National Health and Safety Function, Workplace Health and Wellbeing Unit, National HR Division. Guideline Document National Health and Safety Function, Workplace Health and Wellbeing Unit, National HR Division Guideline Document Ref: GD:004:00 RE: Completion of Occupational Safety and Health Risk Assessments Issue

More information

SECTION 1 - INTRODUCTION 2 PURPOSE 2 SCOPE 2 DEFINITIONS 2 LEGISLATIVE CONTEXT 4 RESPONSIBILITIES 4

SECTION 1 - INTRODUCTION 2 PURPOSE 2 SCOPE 2 DEFINITIONS 2 LEGISLATIVE CONTEXT 4 RESPONSIBILITIES 4 OH&S Procedure Name: Manual Handling Procedure Approved by: Director Human Resources Last reviewed: December 2013 SECTION 1 - INTRODUCTION 2 PURPOSE 2 SCOPE 2 DEFINITIONS 2 LEGISLATIVE CONTEXT 4 RESPONSIBILITIES

More information

SHE Training Procedure

SHE Training Procedure APAC SHE Procedure S3[APAC]-003-PR1 1. Purpose and Scope AECOM will ensure that all employees and persons under their control receive appropriate SH&E training to allow them to carry out their work in

More information

HAZARDOUS CHEMICALS AND REGULATED WASTE CS-OHS-08

HAZARDOUS CHEMICALS AND REGULATED WASTE CS-OHS-08 CS ENERGY PROCEDURE HAZARDOUS CHEMICALS AND REGULATED WASTE CS-OHS-08 Responsible Officer: Health and Safety Brisbane Responsible Manager: Head of Health and Safety Responsible Executive: Executive General

More information

The Health & Safety Policy

The Health & Safety Policy The Health & Safety Policy April 2014 Issue: 3 Page 1 of 16 Review Date: April 2015 Introduction This document sets out the Health & Safety arrangements for Astra Signs Ltd and represents our commitment

More information

Work Health and Safety Management Systems and Auditing Guidelines

Work Health and Safety Management Systems and Auditing Guidelines Work Health and Safety Management Systems and Auditing Guidelines 5th edition, September 2013 (Updated May 2014) Work Health and Safety Management Systems and Auditing Guidelines These Guidelines are a

More information

National self-insurer OHS management system audit tool. Version 3

National self-insurer OHS management system audit tool. Version 3 National self-insurer OHS management system audit tool Version 3 Release Date: 4 August 2014 Next Review Date: 2016 Approval Status: Prepared by: Approved by Heads of Workers Compensation Authorities WorkCover

More information

Management of Risk Assessment

Management of Risk Assessment Health and Safety Services WELLBEING, SAFETY AND HEALTH Management of Risk Assessment Guidance for Heads of School/ Service This is a controlled document whilst viewed at www.leeds.ac.uk/safety. Once downloaded

More information

Apply for Crane Permit

Apply for Crane Permit Apply for Crane Permit Details of revisions Level Details Date Initial 1 Creation of initial document for use 20/08/2016 J.O S 2 Implementation of time frames 23/03/2018 MW Title: Apply for Crane Permit

More information

The following is a description of the type of work that our Company undertakes:

The following is a description of the type of work that our Company undertakes: Health & Safety Introduction K9 Patrol is committed to providing a workplace that is healthy and safe for our employees and anyone who interacts with us e.g. customers and members of the public. Conformance

More information

Evaluation of Occupational Health & Safety Management System

Evaluation of Occupational Health & Safety Management System Section 1 Legal Obligation Employers have a duty of care to provide a safe workplace and systems of work, to consult with workers, to identify and manage workplace hazards and to keep them informed about

More information

Occupational Health and Safety. Improvement Standard

Occupational Health and Safety. Improvement Standard Premier s Department New South Wales Occupational Health and Safety Improvement Standard A tool for measuring OHS performance within NSW Government Agencies OHS IMPROVEMENT STANDARD NSW GOVERNMENT - REVIEW

More information

WORK METHOD STATEMENT CABINETRY/JOINERY

WORK METHOD STATEMENT CABINETRY/JOINERY ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 73 Contact Position: Director Address: PO Box 3, Townsville QLD 0 Contact Phone Number: 0 96 97 PROJECT

More information

Workplace Safety and Health Guidelines Contractor Management

Workplace Safety and Health Guidelines Contractor Management Published in September 2011 by the Workplace Safety and Health Council in collaboration with the Ministry of Manpower. All rights reserved. This publication may not be reproduced or transmitted in any

More information

HEALTH AND SAFETY POLICY AND PROCEDURES

HEALTH AND SAFETY POLICY AND PROCEDURES HEALTH AND SAFETY POLICY AND PROCEDURES Relevant Legislation The Health and Safety At Work Act 1974 The Management of Health and Safety At Work Regulations 1999(as amended) All associated Health and Safety

More information

Release: 1. CPCCBC4002A Manage occupational health and safety in the building and construction workplace

Release: 1. CPCCBC4002A Manage occupational health and safety in the building and construction workplace Release: 1 CPCCBC4002A Manage occupational health and safety in the building and construction workplace CPCCBC4002A Manage occupational health and safety in the building and construction workplace Modification

More information

WHSE POL 1 WORK HEALTH, SAFETY & ENVIRONMENT MANAGEMENT POLICY

WHSE POL 1 WORK HEALTH, SAFETY & ENVIRONMENT MANAGEMENT POLICY Issue Number: 5 Prepared by (author): Greg McDonald, Group Manager WHSE Authorised by: Chen Wei Ng, Managing Director Date of release: 01 January 2014 Date of review 01 December 2015 WHSE POL 1 WORK HEALTH,

More information

Supervisor Course. Conduct safety and health investigations

Supervisor Course. Conduct safety and health investigations Supervisor Course RIICOM301D RIIWHS301D RIIRIS301D Communicate information Conduct safety and health investigations Apply risk management processes 1 A workplace assessment completes the assessment in

More information

WORK HEALTH AND SAFETY AUDIT STANDARD

WORK HEALTH AND SAFETY AUDIT STANDARD WORK HEALTH AND SAFETY AUDIT STANDARD FORESTRY INDUSTRY South Australia, Victoria and Tasmania Safety Standards 2017 2017 Content I. Introduction... 2 II. Audit Criteria and Indicators... 3 1 PLANNING...

More information

Organisation Details:

Organisation Details: Organisation Details: Business Name Address Applicable Standard (s) ISO 45001: 2018 Audit Type Transition to ISO 45001:2018 GRS Reference Management contact: Total no of employee Risk Category High Medium

More information

Apply for Working at Heights Permit

Apply for Working at Heights Permit Apply for Working at Heights Permit Details of revisions Level Details Date Initial 1 Creation of initial document for use 05/09/2017 MW 2 Amendment to implement time frames 23/03/2018 MW Title: Apply

More information

Document: HSE NET NAT SWMS APAND00002 Version: 0.01 Date: 20/11/2012 Review by: 15/01/2014 Page 1 of 9 pages

Document: HSE NET NAT SWMS APAND00002 Version: 0.01 Date: 20/11/2012 Review by: 15/01/2014 Page 1 of 9 pages Principal Contractor (PC) Approving Authority APT AM Holdings Pty. Ltd. [ABN] 95124754383 APA Group Level, HSBC Building 580 George Street Sydney NSW 2000 State Representative John Ferguson Group Executive

More information

Contractor Selection & Management Guideline Rev01. Revision 00. April 2011

Contractor Selection & Management Guideline Rev01. Revision 00. April 2011 Contractor Selection and Management Guideline Revision 00 April 2011 Document Details and Issue Record Rev No. Details Date Author 00 Draft 10/04/2011 CJMD Checked Text Calcs Approved Document Reference:

More information

Work Health & Safety Procedure

Work Health & Safety Procedure 1 PURPOSE This procedure explains the process for qualification of Contractors at Port of Newcastle (PON). It outlines the responsibilities for PON Representatives and Contractors. It also provides a system

More information

Health and Safety Manual

Health and Safety Manual Health and Safety Manual Contents Revisions... 4 Distribution List... 4 Tower Cranes NZ Health & Safety Policy... 5 1. Introduction... 6 2. Purpose... 6 3. Scope... 6 4. Objectives... 7 5. Planning...

More information

Hazard Identification & Risk Assessment

Hazard Identification & Risk Assessment Purpose/ Objective: Berland River Safety Inc. has established this written safety policy and implemented procedures to ensure that hazard identification and risk assessment will be part of routine safety

More information

Safe Work Method Statement. 14/4/16 Approved by (Snr Management Rep):

Safe Work Method Statement. 14/4/16 Approved by (Snr Management Rep): ABN 39 137 318 873 Unit 2, 36 Lidco St Arndell Park NSW 2148 QAC swms2 Phone: 1300 121 544 Fax 1300 078 877 Safe Work Method Statement SWMS No: 1 Revision Date: 14/4/16 Approved by (Snr Management Rep):

More information

HEALTH & SAFETY POLICY

HEALTH & SAFETY POLICY 1. Policy Statement CONTENTS 1. Policy Statement 2. Responsibilities 3. In Practice 3.1 Risk Assessments 3.2 COSHH 3.3 PPE 3.4 Safety Training 3.5 Accident Procedure 3.6 Emergency Procedure 3.7 Site Audits

More information

HEALTH & SAFETY POLICY AND ORGANISATIONAL ARRANGEMENTS

HEALTH & SAFETY POLICY AND ORGANISATIONAL ARRANGEMENTS HEALTH & SAFETY POLICY AND ORGANISATIONAL ARRANGEMENTS Enquin Environmental Limited 1 Ringside Business Centre Heol Y Rhosog Wentloog Cardiff CF3 2EW Enquin Environmental Ltd Page 1 of 10 March 2016 Introduction

More information

Health and Safety Management System Manual

Health and Safety Management System Manual Message from the Managing Director Health and Safety Management System Manual The Blackley Group of Companies are committed to ensuring our workers and contractors have a safe place to work and strive

More information

Procedure Plant Management Procedure

Procedure Plant Management Procedure Procedure Plant Management Procedure 1. Purpose Give guidance on the OHS management of plant and equipment items used by Greater Shepparton City Council workers. 2. Actions Required Hazard assess plant

More information

WHS Manual Insert Business Name & Logo

WHS Manual Insert Business Name & Logo WHS Manual Insert Business Name & Logo Version5 Work Health & Safety Manual INDEX OVERVIEW 4 1. WORK HEALTH AND SAFETY POLICY 5 2. PLANNING, REVIEW AND EVALUATION 9 3. HAZARD IDENTIFICATIO, ASSESSMENT

More information

WHS Change Management

WHS Change Management Page 1 of 6 Issue: 2 1. Intent The Salvation Army Australia Eastern Territory (TSA-AUE) is committed to the provision of a safe, healthy and injury free environment for all persons in the mission / ministry

More information

Critical Elements from the Arrium Codes of Practice (Including Arrium Mining Codes of Practice)

Critical Elements from the Arrium Codes of Practice (Including Arrium Mining Codes of Practice) Critical Elements from the Arrium Codes of Practice (Including Arrium Mining Codes of Practice) Version 3 June 2014 Authorised by Arrium Safety Council TOOL75.WHS.COP.001 Critical Elements from the Code

More information

Safe Work Method Statement

Safe Work Method Statement Safe Work Method Statement 01 WHAT IS A SWMS? A SWMS is a document that sets out the high risk construction work activities to be carried out at a workplace, the hazards arising from these activities and

More information

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY 1. Introduction 1.1 SCOPE & PURPOSE This policy (which includes this document and the work health and safety standards, policies, procedures and safety control

More information

Health, Safety and Environment Pre-Qualification Questionnaire Health, Safety & Environmental Long Form Questionnaire Version 1, August FINAL

Health, Safety and Environment Pre-Qualification Questionnaire Health, Safety & Environmental Long Form Questionnaire Version 1, August FINAL Health, Safety and Environment Pre-Qualification Questionnaire Health, Safety & Environmental Long Form Questionnaire Version 1, August 2016 - FIAL Contract ame: [insert name here] Company ame: [insert

More information

MECHANICAL JOINT INTEGRITY ROUTE TO COMPETENCE GUIDANCE. Working together to prevent hydrocarbon releases through safety critical competence

MECHANICAL JOINT INTEGRITY ROUTE TO COMPETENCE GUIDANCE. Working together to prevent hydrocarbon releases through safety critical competence MECHANICAL JOINT INTEGRITY ROUTE TO COMPETENCE GUIDANCE Working together to prevent hydrocarbon releases through safety critical competence Revision 2, June 2 2013 AN OVERVIEW Mechanical joints have the

More information

CHAS Assessment Standards

CHAS Assessment Standards CHAS Assessment Standards Section 1 - All Prosecutions or Enforcement Notices The Supplier has provided details of any enforcement notices or prosecutions served on them in the last three years by the

More information

Health, Safety and Environmental Management Systems Audit Report

Health, Safety and Environmental Management Systems Audit Report Health, Safety and Environmental Management Systems Audit Report SMART Group of Companies Jaunuary 2016 Page 1 of 18 1.0 Executive Summary A review of SMART Technical Services workplace health and safety

More information

CONTENTS MANAGEMENT STANDARDS ANGLO OCCUPATIONAL HEALTH WAY MANAGEMENT SYSTEM STANDARDS INTRODUCTION 1 3 LEGAL AND OTHER REQUIREMENTS 10

CONTENTS MANAGEMENT STANDARDS ANGLO OCCUPATIONAL HEALTH WAY MANAGEMENT SYSTEM STANDARDS INTRODUCTION 1 3 LEGAL AND OTHER REQUIREMENTS 10 Version 1 July 2007 CONTENTS INTRODUCTION 1 3 LEGAL AND OTHER REQUIREMENTS 10 OCCUPATIONAL HEALTH IN ANGLO AMERICAN OUR VISION OUR PRINCIPLES OUR POLICY 2 THE ANGLO OCCUPATIONAL HEALTH FRAMEWORK 3 CORPORATE

More information

JOB SAFETY ANALYSIS (JSA) FOR. <Insert Organization Name> Adopted <Insert Date Policy Is Adopted> LC-442 Rev. 3/11

JOB SAFETY ANALYSIS (JSA) FOR. <Insert Organization Name> Adopted <Insert Date Policy Is Adopted> LC-442 Rev. 3/11 JOB SAFETY ANALYSIS (JSA) FOR Adopted LC-442 I. Introduction In an effort to identify workplace hazards, the Organization will conduct a Job Safety

More information

Working for business. Workplace Safety Discount Application For those with employees

Working for business. Workplace Safety Discount Application For those with employees Working for business Workplace Safety Discount Application For those with employees What is the Workplace Safety Discount programme? The Workplace Safety Discount programme provides a framework for building

More information

Safe Work Method Statement

Safe Work Method Statement Safe Work Method Statement Disclaimer: Use of Master Builders Generic Safe Work Method Statements The Master Builders Association of Victoria expressly disclaim all and any liability to any person in respect

More information

9001:2015, ISO 14001:2015 & ISO

9001:2015, ISO 14001:2015 & ISO Quality management input comprises the standard requirements from ISO 9001:2015 which are deployed by our organization to achieve customer satisfaction through process control. Environmental input comprises

More information

MVDC F041 Safety Inspection Checklist

MVDC F041 Safety Inspection Checklist MVDC F041 Safety Inspection Checklist JOB TITLE: DEPARTMENT: JOB NO.: DATE: LEGEND 1 Satisfactory 2 Requires Improvement 3 Non Existent 4 Not Applicable EMERGENCY PREPAREDNESS Emergency procedure is posted

More information

NORTHERN EDUCATION TRUST HEALTH AND SAFETY DOCUMENT OF POLICIES

NORTHERN EDUCATION TRUST HEALTH AND SAFETY DOCUMENT OF POLICIES NORTHERN EDUCATION TRUST HEALTH AND SAFETY DOCUMENT OF POLICIES Contents Policy on Health and Safety COSHH Policy Working with VDU's Policy Management of Health and Safety at Work Policy The Workplace

More information

CITY OF DARWIN CRUISES Environmental Management System

CITY OF DARWIN CRUISES Environmental Management System CITY OF DARWIN CRUISES Environmental Management System 1. Introduction Environmental Management Systems (EMS) are designed to enable organisations to address both environmental concerns and economic imperatives

More information

PROGRAM OVERVIEW JOB HAZARD ANALYSIS (JHA) SAFETY PROGRAM REGULATORY STANDARD: 29 CFR

PROGRAM OVERVIEW JOB HAZARD ANALYSIS (JHA) SAFETY PROGRAM REGULATORY STANDARD: 29 CFR PROGRAM OVERVIEW JOB HAZARD ANALYSIS (JHA) SAFETY PROGRAM REGULATORY STANDARD: 29 CFR 1910.132-138. INTRODUCTION: Injuries in the workplace often occur because employees are not adequately trained in the

More information

PROPERTY SERVICES OPERATING PROCEDURE

PROPERTY SERVICES OPERATING PROCEDURE This is a internal document and is only applicable to the internal operations of the RMIT. OPERATING PROCEDURE INTENT The Permit to Work (PTW) procedure is a formal written system used to control certain

More information

LEICESTERSHIRE COUNTY COUNCIL HEALTH, SAFETY & WELLBEING POLICY. July 2011 To be reviewed: July 2014

LEICESTERSHIRE COUNTY COUNCIL HEALTH, SAFETY & WELLBEING POLICY. July 2011 To be reviewed: July 2014 LEICESTERSHIRE COUNTY COUNCIL HEALTH, SAFETY & WELLBEING POLICY July 2011 To be reviewed: July 2014 Policy Prepared By: Colin Jones CMIOSH Corporate Health, Safety and Wellbeing Manager 1 CONTENTS 1. INTRODUCTION

More information

Quality, Health Safety & Environment Code: 2013

Quality, Health Safety & Environment Code: 2013 Price: AUD 35 Quality, Health Safety & Environment Code Quality, Health Safety & Environment Code: 2013 Published by: TQCS International Pty Ltd Head Office: 117A Tapleys Hill Road HENDON SA 5014 AUSTRALIA

More information

PROCESS SAFETY MANAGEMENT FRAMEWORK GUIDANCE DOCUMENT

PROCESS SAFETY MANAGEMENT FRAMEWORK GUIDANCE DOCUMENT PROCESS SAFETY MANAGEMENT FRAMEWORK GUIDANCE DOCUMENT AIGA 099/17 Asia Industrial Gases Association 52 Jurong Gateway Road,JEM, #15-02, Singapore 608550 Tel : +65 6276 0160 Fax : +65 6274 9379 Internet

More information

CPCCCM2010A Work safely at heights

CPCCCM2010A Work safely at heights CPCCCM2010A Work safely at heights Release: 1 CPCCCM2010A Work safely at heights Modification History Not Applicable Unit Descriptor Unit descriptor This unit of competency specifies the outcomes required

More information

BEHAVIOUR ON SAFE SITES

BEHAVIOUR ON SAFE SITES Page: 1 of 8 P932 (a) Introduction: Black & Veatch has set a target of achieving ZERO incidents and injuries across all of its business operations. At B&V, we believe that zero incidents and injuries are

More information

Roy Hill Inductions and Orientation Procedure Health & Safety

Roy Hill Inductions and Orientation Procedure Health & Safety 1 Purpose and scope The purpose of this procedure is to ensure all employees, contractors and visitors requiring access to Roy Hill sites are informed of relevant health, safety and environmental risks

More information

OHS Management of Contractors in Capital Works and Maintenance

OHS Management of Contractors in Capital Works and Maintenance OHS Management of Contractors in Capital Works and Maintenance Physical Resources/Risk, Health and Safety Prepared by: Physical Resources/Risk, Health and Safety Version: 08/04/2008 Contents Page 1. INTRODUCTION...

More information

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2 Purpose This procedure provides guidance to the Diocese of Maitland Newcastle (DoMN), principal contractors and other persons conducting a business or undertaking (PCBU) who commission or carry out construction,

More information

PGR Innovations Limited. Company Policy For Health & Safety

PGR Innovations Limited. Company Policy For Health & Safety PGR Innovations Limited Company Policy For Health & Safety January 2012 CONTENTS Company Policy Statement 1.0 Organisation Duties And Responsibilities 2.0 Managing Director 2.1 Projects Managers and Site

More information

CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015

CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015 POLICY NUMBER P15/2 VERSION 1.0 CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015 AUTHORISED BY Trust ISSUED DATE 10/08/2015 DISTRIBUTION External REVIEW DATE

More information

Permit Manager Training Guide Apply for Permit to Isolate High Voltage

Permit Manager Training Guide Apply for Permit to Isolate High Voltage Permit Manager Training Guide Apply for Permit to Isolate High Voltage Details of revisions Level Details Date Initial 01 Creation of initial document for use 06-01-17 J.O S 02 Revisions from Permit Workshops

More information

REFURBISHMENT DEMOLITION

REFURBISHMENT DEMOLITION CONTRACTOR WHS HAZARD STANDARD REFURBISHMENT DEMOLITION EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

at work Health and safety p o l i c y d o c u m e n t

at work Health and safety p o l i c y d o c u m e n t Employees & visitors Safety Champion Supporting teams Roles & responsibilities Health and safety at work p o l i c y d o c u m e n t The Health and Safety at Work Policy provides a framework to ensure

More information

Safe Practices Safety Management System III (Steps 6-10)

Safe Practices Safety Management System III (Steps 6-10) SUBJECT 6 Safe Practices Safety Management System III (Steps 6-10) studymassage.com.au HLT50307 Diploma of Remedial Massage HLT40312 Certificate IV in Massage Therapy Practice Evolve College Pty Ltd, 2015

More information

JOB SAFETY ANALYSIS PROGRAM. Owner: Risk Management Revision No: 01. Document number: Q-001 Date last revised:

JOB SAFETY ANALYSIS PROGRAM. Owner: Risk Management Revision No: 01. Document number: Q-001 Date last revised: Table of Contents 1.0 Applicability...2 2.0 Scope...2 3.0 Definitions...2 4.0 Core Information and Requirements...2 5.0 Roles and Responsibilities...6 6.0 Goals, Objectives and Performance Measures...7

More information

External Supplier Control Obligations

External Supplier Control Obligations External Supplier Control Obligations Health and Safety Barclays recognises that we have clear Health and Safety (H&S) responsibilities towards everyone impacted by our business operations including,

More information

Abu Dhabi Occupational Safety and Health System Framework (OSHAD-SF) OSHAD-SF Guidance Document

Abu Dhabi Occupational Safety and Health System Framework (OSHAD-SF) OSHAD-SF Guidance Document Abu Dhabi Occupational Safety and Health System Framework (OSHAD-SF) OSHAD-SF Guidance Document OSH Roles and Responsibilities Version 3.0 July 2016 Table of Contents 1. Introduction... 3 2. OSH Leadership

More information

Health and Safety Management Systems Interfacing. Guidance

Health and Safety Management Systems Interfacing. Guidance Health and Safety Management Systems Interfacing Guidance Re-issue 2003 INTRODUCTION 2 Background to the Guidance 2 The Need for SMS Interfacing Arrangements 2 APPLYING THE GUIDANCE 3 GUIDING PRINCIPLES

More information

POLICY. Occupational Health and Safety Policy. (from Complispace) Approved: 18 April 2018

POLICY. Occupational Health and Safety Policy. (from Complispace) Approved: 18 April 2018 POLICY Occupational Health and Safety Policy (from Complispace) Approved: 18 April 2018 Version: 2.1 Page 0 18 April 2018 This is a controlled document. Hardcopies of this document are considered uncontrolled.

More information

Assessor Assessment Pack

Assessor Assessment Pack Contribute to Health and Safety of Self and Others BSBWHS201 Precision Group (Australia) Pty Ltd 44 Bergin Rd, Ferny Grove, QLD, 4055 Email: info@precisiongroup.com.au Website: www.precisiongroup.com.au

More information