An Approach of Contractor Selection By Analytical Heirarchy Process

Size: px
Start display at page:

Download "An Approach of Contractor Selection By Analytical Heirarchy Process"

Transcription

1 An Approach of Contractor Selection By Analytical Heirarchy Process Multi Criteria Decision Making System Meghalkumar I Zala (PG Student) Master of Engineering in Construction Eng. & Management Birla Vishvakarma Mahavidyalaya Vallabh Vidhyanagar,Gujarat, India meghalzala@yahoo.in Prof. Rajiv B Bhatt (Ph.D. Cont.) Department of Civil Engineering A.D.Patel Institute Of Technology New Vallabh Vidhyanagar,Gujarat, India rajivbhatt123@yahoo.co.in Abstract--Contractor selection is one of the most important aspects in construction contract. This paper suggest AHP technique for contractor selection problem in Indian context. Literature survey is carried out in this area and shown. Concerning to these problems, the contractor pre- qualification, evaluation and selection process needs to be reviewed to achieve the project goals based on multi criteria decision making process. The data collected are used to create a hierarchical model for contractor selection that represented by the Analytic Hierarchy Process(AHP). By using this model & with the help of AHP technique one can develop contractor selection approach which can be most useful for the stakeholders. Key words:-- Contractor selection criteria, Pre-qualification, Bid evaluation, Multi criteria dicision making(mcdm) system, Analytical Hierarchy Process (AHP). The paper is organized as follows: It provides a review of some relevant literature on contractor selection. This literature is utilized to review contractor evaluation methodology and criteria, appropriate investigation issues. Introduces a qualitative study that was conducted to address the research issues. It is composed of the investigation objectives and tasks. It provides conclusions. II. LITERATURE REVIEW Table:1- Contractor Selection Model Suggested by Researchers 17 I. INTRODUCTION Various stakeholders(clients, contractors, technical supervisors of construction, etc) are involved in the construction process. A construction project is developed considering the goals and requirements of a client and the potential of a contractor and suppliers. In a construction project, the selection of an appropriate contractor is the most critical for project success. Quite often construction projects behind schedule, price changes and inappropriate quality are a direct outcome of the selection of an inadequate contractor. When selecting a contractor, a client evaluates its qualification (checks whether it meets specified legal, financial, economic and technical requirements) and compares qualification of different contractors. There are three prime causes of inadequate contractor selection. Firstly, inappropriate criteria are selected when evaluating qualification of a contractor. Secondly, inappropriate significance is attributed to the criteria (e.g. to bid price). Thirdly, inappropriate methodology is applied for the contractor evaluation and selection task. This paper is focused on the contractor evaluation/selection criteria. It describes an investigation of companies on the criteria for evaluation of contractors qualification and the importance of criteria weight. Selecting a construction contractor is one of major decisions which may influence the progress and success of any construction project. Contractor prequalification is a commonly used process for identifying a qualified, sound and reliable Page 1 of 6

2 construction contractor. A general prequalification exercise is performed to identify an appropriate i e the best, contractor from the applicants and to evaluate and score them according to their economic and technical aspects, quality standards, past performance and other characteristics. Various procedures, such as open tendering, restricted tendering or negotiation, are practiced for contractor selection. A contractor is selected either from all the bidders or the contractor selection process can be divided into two phases: prequalification and final selection. Contractor prequalification involves a screening procedure based on a set of criteria set forth by each individual owner [1]. As pointed out by Palaneeaswaran [2] contractor prequalification is generally preferred by clients to minimize risks and failures and to enhance the performance levels of selected contractors by means of established minimal capacities below which contractors will not be considered. F. Ling [3] examined bidding practices in Australia, Canada, Saudi Arabia, Singapore, the UK and the USA. In the case of a governmental project, contractor selection by means of a bidding mechanism is required by law. However, G. Ang et al [4] state that traditional forms of procurement and tendering, supported by prescriptive, solution-based specifications, and the lowest price only, are suitable for routine projects but will hamper innovation in other types of projects. The contractor s qualification (i e financial strength, past experience, business plan, work capacity, quality and experience of the technical personnel, etc), and project characteristics (i e work schedule, type, value, duration, complexity, location of a project, contract type and variation between the contractor s bid price and the next lowest bidder s price etc) are the fundamental factors that affect contractor default [5]. Time-delays and cost-increases of construction projects are closely related to specifications on the qualifications of contractors (financial, technical, experience, etc) [6]. In construction projects, quality performance of constructors is considered as vital for client satisfaction [7]. The selection of a construction contractor is a decision characterized by multiple objectives [8]. Based on these main aspects, a list of criteria can be generated. Numerous researchers, such as J. Russell et al [1], S. Ng and R. Skitmore [9], C. Wong et al [10, 11], K. Molenaar and D. Johnson [12], Y. Topcu [10], and E. Zavadskas et al have identified common criteria for prequalification and bid evaluation. G. Holt and D. Edwards [12] provide qualitative analysis that identifies criteria to be considered when evaluating and selecting a domestic builder. By Literature review, we can conclude the hierarchical model of contractor selection in Indian context which is shown in Appendix-1 and contractor selection criteria & its importance in Indian context which is shown in Appendix-2. A. Objective of The Research The research is set-up to examine the criteria of contractor selection and to support the procurers on the appropriate contractor selection using the decision support system. a) To understand the nature of contractor selection approaches practiced by various contractor. b) To explore and define the potential criteria which affect the selection of contractor. c) To develop theoretical model that represents the appropriate contractor selection based on AHP process. B. Scope and Limitation of The Research The scope of the research is to identify the criteria for contractor selection using knowledge acquisition phases and to assess the information which involves multi criteria decision making ability using Analytic Hierarchy Process. Hence, the research is limited to the following scope: a) Knowledge acquisition phase involve contractor working methodology in INDIA. b) Assessment of the information is used to develop the theoretical model based on Analytic Hierarchy Process. c) The study is consider for contractor selection and it will focus on the application of AHP as one of tool for decision support system. III. 1.- ANALYTIC HIERARCHY PROCESS (AHP) Analytic Hierarchy Process is an effective decision making technique based on multi-criteria decision making methodology (MCDM). It consider the human judgment, experience, perception and feelings in the decision making process. This research focus on developing a theoretical selection model based on the AHP approach. It help decision maker to select the most appropriate contractor against a number of contractors with various alternatives. The Analytic Hierarchy Process was chosen for this study based on following reason: a) The ability of AHP to incorporate tangible and intangible factors in a systematic way. b) It able to solve constructed problems in a variety of decision making situation, ranging from the simple personal decisions to the complex capital intensive decision. c) The problem is broken down in a logical fashion from the large elements to smaller elements. d) It works by examining judgments made by decision makers and measure the consistently of those judgments. e) It does not required numerical judgment from the decision maker. III. 2.- BACKGROUND OF AHP The Analytic Hierarchy Process (AHP) was develop by Thomas Saaty in 1970 s[1], to provide a simple but the theoretically sound multiple criteria methodology for evaluating alternatives. It aims at quantifying relative priorities for a given set of alternative on a ratio scale, based on the judgment of the decision maker and stresses the importance of the intuitive judgment of a decision maker as well as the consistently of the comparison of the alternative in the decision making process (Saaty. T.L. 1980)[4]. The application of Analytic Hierarchy Process can be found in such diverse fields as portfolio selection model solve by using AHP methodology Page 2 of 6

3 include project procurement system (Mohammed I.A, Khalil 2000), project management (Kamal 2001) and Engineering problems (Saaty 2001).[5] According to Partovi (1992),the AHP is a decision aiding tool for dealing with complex, unstructured and multi attribute decision. Ny Dick and Hill (1992) described the AHP as a methodology to rank alternative courses of action based on the decision makers judgment concerning the important of the criteria and the extend to which they are met by each alternative.golden (1989), described AHP as analytical by using members, hierarchy by structuring the decision problem into levels and process-oriented because its step- by-step approach. Murahdar (1990) support the belief that the AHP caters specifically for decision making with multi criteria. III. 3.- AHP STEPS: Saaty [2,4,7] developed the following steps for applying the AHP: a) Define the problem and determine its goal. b) The hierarchy from the top (the objectives from a decision-maker's viewpoint) through the intermediate levels (criteria on which sub sequent levels depend) to the lowest level which usually contains the list of alternatives. c) Construct a set of pairwise comparison matrices(size n x n) for each of the lower levels with one matrix for each element in the level immediately above by using the relative scale measurement shown in Table 2. The pair-wise comparisons are done in terms of which element dominates the other. d) There are n(n-1) / judgments required to develop the set of matrices in step 3. Reciprocals are automatically assigned in each pair-wise comparison. e) Hierarchical synthesis is now used to weight the eigenvectors by the weights of the criteria and the sum is taken over all weighted eigenvector entries corresponding to those in the next lower level of the hierarchy. f) Having made all the pair-wise comparisons, the consistency is determined by using the eigenvalue, Imax, to calculate the consistency index, CI as follows: C.I.=(Imax-n) / (n-1) where n is the matrix size. Judgment consistency can be checked by taking the consistency ratio (CR) of CI with the appropriate value. The CR is acceptable, if it does not exceed If it is more, the judgment matrix is inconsistent. To obtain a consistent matrix, judgments should be reviewed and improved. g) Steps(d-f) are performed for all levels in the hierarchy. Table:-2 Pairwise Comparison Scale for AHP Preferences, Saaty[1,3] Numerical Verbal judgment of preferences Scale 9 Extremely preferred 8 Very Strongly to Extremely 7 Very Strongly Preferred 6 Strongly to Very Strongly 5 Strongly Preferred 4 Moderately to Strongly 3 Moderately Preferred 2 Equally to Moderately 1 Equally Preferred IV. CONCLUSION Contractor selection involves complex decision making situations that discerning abilities and methods to make sound decisions. This paper has discussed in details on knowledge acquisition process and transforming the information to a manageable form for developing a theoretical model represents the AHP methodology. The AHP is a decision aiding tools based on multi- criteria decision making for dealing with complex and multi attribute decision. The AHP process is simplifies using a decision support system. V. REFERENCES 1. Saaty, T.L. (1980) The Analytical Hierarchy Process, McGraw-Hill, New York. 2. Saaty,T.L.(1994) How To Make adecision:the Analytical Hierarcchy Process,24(6), Palaneeaswaran Saaty,T.L.(1996) Decision Making with Dependence and Feedback: The Analytica Network Process, RWS Publications, Pittsburgh, P.A., F. Ling 4. Saaty, T.L., Decision making in complex environments: the analytic network process for decision making with dependence and feedback. RWS Publications, USA., G. Ang et al 5. Saaty T.L. (1983), Axiomatic Foundations of the Analytic Hierarchy Process,Management Science, Vol Saaty T.L. (1987), Decision Making, New Information, Ranking and Structure Mathematical Modeling, Vol Saaty T.L.(1987), The Analytic Hierarchy Process : Planning, Priority Setting, Resources Allocation, Rws Publication, Pittsburg, PA. 8. Saaty, T.L. (1994a), Fundamentals of Decision Making and Priority Theory with the Analytic Hierarchy Process, Rws Publications, Pittsburgh, PA. 9. Hatush, Z. & Skitmore, M. (1998), Contractor selection using multicriteria utility theory: an additive model, Building and Environment, 33(2~3): S.Ngand R. Skitmore 105~ Hatush, Z. & Skitmore, M. (1997a), Criteria for contractor selection, Construction Management and Economics, 15:19~38, C. Wong et al 11. Hatush, Z. & Skitmore, M. (1997b), Assessment and evaluation of contractor data against client goals using PERT approach, Construction Management and Economics,15:327~340, K. Molenaar and D. Johnson 12. Holt, G. D., Olomolaiye, P. O., and Harris, F. C. (1994). Factors influencing U.K. construction clients choice of Page 3 of 6

4 contractor. Build. Environ.,29, "Evaluate the conntractor performance:dubai construction industry" 13. Hatush, Zedan and Skitmore, Martin R. (1997) Criteria for contractor selection. Construction Management and Economics 15(1):pp , Y. Topcu 14. Journal of construction engineering and management / march/april 2002 / 155 -"Concessionaire selection for BOT tunnel project in Hong Kong", E. Zavadskas et al 15. The hong kong institute of value management-vol. 13, No. 3 / 4, 2007 HKIVM-"Value managementin the architectural service department in Hongkong" 16. International Journal of Project Management 19 (2s001) 19±27-"Application of AHP in Project Management" 17. Operational Research an International journal vol.6-no.3 september-december Appendix-1 Contractor Selection Hierarchical Model in Indian Context Page 4 of 6

5 Appendix-2 Contractor Selection Criteria & its Importance Page 5 of 6

6 Page 6 of 6

ESTABLISHING RELATIVE WEIGHTS FOR CONTRACTOR PREQUALIFICATION CRITERIA IN A PRE-QUALIFICATION EVALUATION MODEL

ESTABLISHING RELATIVE WEIGHTS FOR CONTRACTOR PREQUALIFICATION CRITERIA IN A PRE-QUALIFICATION EVALUATION MODEL ESTABLISHING RELATIVE WEIGHTS FOR CONTRACTOR PREQUALIFICATION CRITERIA IN A PRE-QUALIFICATION EVALUATION MODEL N. El-Sawalhi 1*, D. Eaton 2, and R. Rustom 3 1, 2 Research Institute for the Built and Human

More information

A Decision Support Model for Contractor Selection in a Government Procurement Supply Chain: Evidence from an Emerging Market

A Decision Support Model for Contractor Selection in a Government Procurement Supply Chain: Evidence from an Emerging Market A Decision Support Model for Selection in a Government Procurement Supply Chain: Evidence from an Emerging Market Chris I. Enyinda Alabama A & M University Alphonso O. Ogbuehi Clayton State University

More information

VENDOR RATING AND SELECTION IN MANUFACTURING INDUSTRY

VENDOR RATING AND SELECTION IN MANUFACTURING INDUSTRY International Journal of Decision Making in Supply Chain and Logistics (IJDMSCL) Volume 2, No. 1, January-June 2011, pp. 15-23, International Science Press (India), ISSN: 2229-7332 VENDOR RATING AND SELECTION

More information

Multi Criteria Decision Analysis for Optimal Selection of Supplier Selection in Construction Industry A Case Study

Multi Criteria Decision Analysis for Optimal Selection of Supplier Selection in Construction Industry A Case Study Multi Criteria Decision Analysis for Optimal Selection of Supplier Selection in Construction Industry A Case Study Ms. S.V.S.N.D.L.Prasanna 1 and Mr. Praveen Kumar 2 1. Assistant Professor, Civil Engineering

More information

Introduction. Analytical Hierarchy Process. Why AHP? 10/31/2011. The AHP is based on three principles: Decomposition of the decision problem

Introduction. Analytical Hierarchy Process. Why AHP? 10/31/2011. The AHP is based on three principles: Decomposition of the decision problem Introduction A multi-criteria decision making process. Analytical Hierarchy Process The analytical hierarchy process (AHP) is a comprehensive, logical and structured framework. 56:134 Process Engineering

More information

MULTIPLE-OBJECTIVE DECISION MAKING TECHNIQUE Analytical Hierarchy Process

MULTIPLE-OBJECTIVE DECISION MAKING TECHNIQUE Analytical Hierarchy Process MULTIPLE-OBJECTIVE DECISION MAKING TECHNIQUE Analytical Hierarchy Process Business Intelligence and Decision Making Professor Jason Chen The analytical hierarchy process (AHP) is a systematic procedure

More information

Use of AHP Method in Efficiency Analysis of Existing Water Treatment Plants

Use of AHP Method in Efficiency Analysis of Existing Water Treatment Plants International Journal of Engineering Research and Development ISSN: 78-067X, Volume 1, Issue 7 (June 01), PP.4-51 Use of AHP Method in Efficiency Analysis of Existing Treatment Plants Madhu M. Tomar 1,

More information

Product Evaluation of Rijal Tashi Industry Pvt. Ltd. using Analytic Hierarchy Process

Product Evaluation of Rijal Tashi Industry Pvt. Ltd. using Analytic Hierarchy Process Proceedings of IOE Graduate Conference, 2016 pp. 239 244 Product Evaluation of Rijal Tashi Industry Pvt. Ltd. using Analytic Hierarchy Process Rojan Shrestha 1, Shree Raj Sakya 2 1,2 Department of Mechanical

More information

A Stochastic AHP Method for Bid Evaluation Plans of Military Systems In-Service Support Contracts

A Stochastic AHP Method for Bid Evaluation Plans of Military Systems In-Service Support Contracts A Stochastic AHP Method for Bid Evaluation Plans of Military Systems In-Service Support Contracts Ahmed Ghanmi Defence Research and Development Canada Centre for Operational Research and Analysis Ottawa,

More information

The Potential Utilization of the Analytical Hierarchy Process (AHP) for the Selection of a Tenure Track Faculty Position

The Potential Utilization of the Analytical Hierarchy Process (AHP) for the Selection of a Tenure Track Faculty Position The Potential Utilization of the Analytical Hierarchy Process (AHP) for the Selection of a Tenure Track Faculty Position Raida Abuizam Purdue University Calumet John J. Lucas Purdue University Calumet

More information

Construction management activity scheduling using proposed Analytical Node Activity Hierarchy Process (ANAHP)

Construction management activity scheduling using proposed Analytical Node Activity Hierarchy Process (ANAHP) 2017; 3(6): 1163-1169 ISSN Print: 2394-7500 ISSN Online: 2394-5869 Impact Factor: 5.2 IJAR 2017; 3(6): 1163-1169 www.allresearchjournal.com Received: 11-04-2017 Accepted: 13-05-2017 Kunal Dhadse Post Graduate,

More information

Keywords- AHP, Operating System, MCDM, Linux, Mac, Windows.

Keywords- AHP, Operating System, MCDM, Linux, Mac, Windows. Volume 4, Issue 5, May 2014 ISSN: 2277 128X International Journal of Advanced Research in Computer Science and Software Engineering Research Paper Available online at: www.ijarcsse.com Operating System

More information

An AHP Model for Construction Contractor Prequalification

An AHP Model for Construction Contractor Prequalification Ent2etpqotak-~ "Ep~ova / Operational Research. An International Journal. Vol.6, No 3 (2006), pp.333-346 An AHP Model for Construction Contractor Prequalification K. P. Anagnostopoulos, A. P. Vavatsikos

More information

Analytical hierarchy process (AHP) approach to the selection of heritage building element

Analytical hierarchy process (AHP) approach to the selection of heritage building element Analytical hierarchy process (AHP) approach to the selection of heritage building element Siti Nor Fatimah Zuraidi 1, Mohammad Ashraf Abdul Rahman 2, Zainal Abidin Akasah 3 1,2 Facutly of Engineering Technology,

More information

USING AHP TO ANALYZE THE PRIORITY OF PERFORMANCE CRITERIA IN NATIONAL ENERGY PROJECTS

USING AHP TO ANALYZE THE PRIORITY OF PERFORMANCE CRITERIA IN NATIONAL ENERGY PROJECTS USING AHP TO ANALYZE THE PRIORITY OF PERFORMANCE CRITERIA IN NATIONAL ENERGY PROJECTS Hsin-Pin Fu, Department of Marketing and Distribution Management, National Kaohsiung First University of Science and

More information

Determining and ranking essential criteria of Construction Project Selection in Telecommunication of North Khorasan-Iran

Determining and ranking essential criteria of Construction Project Selection in Telecommunication of North Khorasan-Iran Determining and ranking essential criteria of Construction Project Selection in Telecommunication of North Khorasan-Iran Majid Mojahed, Rosnah bt Mohd Yusuff, Mohammad Reyhani Abstract Economy project

More information

The Analytic Hierarchy Process Based Supplier Selection Approach for Collaborative Planning Forecasting and Replenishment Systems

The Analytic Hierarchy Process Based Supplier Selection Approach for Collaborative Planning Forecasting and Replenishment Systems The Analytic Hierarchy Process Based Selection Approach for Collaborative Planning Forecasting and Replenishment Systems Rajesh A. Kubde Associate Professor, Mechanical Engineering Department. Prof. Ram

More information

Chapter 4 Fuzzy Analytic Hierarchy Process of Green Supply Chain Management in the Pharmaceutical Industry

Chapter 4 Fuzzy Analytic Hierarchy Process of Green Supply Chain Management in the Pharmaceutical Industry Chapter 4 Fuzzy Analytic Hierarchy Process of Green Supply Chain Management in the Pharmaceutical Industry 4.1 Introduction During the past decade with increasing environmental concerns, a consensus, the

More information

AN STUDY OF APPLICATIONS OF ANP IN THE CONTEXT OF LOGISTICS AND SUPPLY CHAIN MANAGEMENT

AN STUDY OF APPLICATIONS OF ANP IN THE CONTEXT OF LOGISTICS AND SUPPLY CHAIN MANAGEMENT AN STUDY OF APPLICATIONS OF ANP IN THE CONTEXT OF LOGISTICS AND SUPPLY CHAIN MANAGEMENT [Abstract Code: 004-0527] Sanjay Jharkharia Department of Mechanical Engineering Bundelkhand Institute of Engineering

More information

SELECTION OF PLANT MAINTENANCE STRATEGY AND PERFORMANCE ENHANCEMENT OF A WIRE MANUFACTURING INDUSTRY USING AHP

SELECTION OF PLANT MAINTENANCE STRATEGY AND PERFORMANCE ENHANCEMENT OF A WIRE MANUFACTURING INDUSTRY USING AHP SELECTION OF PLANT MAINTENANCE STRATEGY AND PERFORMANCE ENHANCEMENT OF A WIRE MANUFACTURING INDUSTRY USING AHP Manoj Parmar 1, Manish Soni 2, Santosh Patidar 3 1 Research Scholar, Mechanical Engineering

More information

The Use of AHP (Analytical Hierarchy Process) as Multi Criteria Decision Tool for the Selection of Best Water Supply Source for Benin City

The Use of AHP (Analytical Hierarchy Process) as Multi Criteria Decision Tool for the Selection of Best Water Supply Source for Benin City Nigerian Journal of Environmental Sciences and Technology (NIJEST) www.nijest.com Vol 1, No. 1 March 2017, pp 169-176 The Use of AHP (Analytical Hierarchy Process) as Multi Criteria Decision Tool for the

More information

Using the Analytic Hierarchy Process in Long-Term Load Growth Forecast

Using the Analytic Hierarchy Process in Long-Term Load Growth Forecast Journal of Electrical Engineering 5 (2017) 151-156 doi: 10.17265/2328-2223/2017.03.005 D DAVID PUBLISHING Using the Analytic Hierarchy Process in Long-Term Load Growth Forecast Blagoja Stevanoski and Natasa

More information

Submitted to the Grand Rapids Community College Provost and AGC Executive Committee.

Submitted to the Grand Rapids Community College Provost and AGC Executive Committee. Oscar Neal Fall 2012 Sabbatical Report Submitted to the Grand Rapids Community College Provost and AGC Executive Committee. The main objective of my sabbatical was to complete my dissertation proposal

More information

A MODIFIED AHP ALGORITHM FOR NETWORK SELECTION

A MODIFIED AHP ALGORITHM FOR NETWORK SELECTION Proceedings of the 11th International Conference on Manufacturing Research (ICMR2013), Cranfield University, UK, 19th 20th September 2013, pp 501-506 A MODIFIED AHP ALGORITHM FOR NETWORK SELECTION Xin

More information

Use of Fuzzy Analytic Hierarchy Process in Pavement Maintenance Planning

Use of Fuzzy Analytic Hierarchy Process in Pavement Maintenance Planning Use of Fuzzy Analytic Hierarchy Process in Pavement Maintenance Planning J. Farhan & T. F. Fwa Department of Civil Engineering, National University of Singapore, Singapore ABSTRACT: In pavement management,

More information

Presentation Program Outline

Presentation Program Outline Presentation Program Outline MASTERPLAN PROCESS EFFECTIVE PLANNING ELEMENTS DECISION MAKING PROCESS ANALYTICAL HIERARCHY PROCESS (AHP) HOW TO APPLY AHP SIMPLE EXAMPLE CASE STUDY APPLICATION WHDS MDP Decision

More information

Product quality evaluation system based on AHP fuzzy comprehensive evaluation

Product quality evaluation system based on AHP fuzzy comprehensive evaluation Journal of Industrial Engineering and Management JIEM, 2013 6(1):356-366 Online ISSN: 2013-0953 Print ISSN: 2013-8423 http://dx.doi.org/10.3926/jiem.685 Product quality evaluation system based on AHP fuzzy

More information

DECISION SUPPORT FOR SOFTWARE PACKAGE SELECTION: A MULTICRITERIA METHODOLOGY

DECISION SUPPORT FOR SOFTWARE PACKAGE SELECTION: A MULTICRITERIA METHODOLOGY 5-03-30 INFORMATION MANAGEMENT: STRATEGY, SYSTEMS, AND TECHNOLOGIES DECISION SUPPORT FOR SOFTWARE PACKAGE SELECTION: A MULTICRITERIA METHODOLOGY Farrokh Mamaghani INTRODUCTION Software selection is a critical

More information

Multi-criteria decision making for supplier selection using AHP and TOPSIS method

Multi-criteria decision making for supplier selection using AHP and TOPSIS method International Journal of Engineering Inventions e-issn: 2278-7461, p-issn: 2319-6491 Volume 6, Issue 2 [Feb. 2016] PP: 13-17 Multi-criteria decision making for supplier selection using AHP and TOPSIS method

More information

ENHANCING THE PLACEMENT VALUE OF PROFESSIONALLY QUALIFIED STUDENTS IN MARKETING: AN APPLICATION OF THE ANALYTIC HIERARCHY PROCESS

ENHANCING THE PLACEMENT VALUE OF PROFESSIONALLY QUALIFIED STUDENTS IN MARKETING: AN APPLICATION OF THE ANALYTIC HIERARCHY PROCESS ENHANCING THE PLACEMENT VALUE OF PROFESSIONALLY QUALIFIED STUDENTS IN MARKETING: AN APPLICATION OF THE ANALYTIC HIERARCHY PROCESS Sanjay Gupta, Shree Atam Vallabh Jain College Vinay Dawar, Shree Atam Vallabh

More information

INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING RESEARCH AND DEVELOPMENT (IJIERD)

INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING RESEARCH AND DEVELOPMENT (IJIERD) INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING RESEARCH AND DEVELOPMENT (IJIERD) International Journal of Industrial Engineering Research and Development (IJIERD), ISSN 0976 ISSN 0976 6979 (Print) ISSN

More information

Introduction. Key Words: Analytic Hierarchy Process (AHP), Fuzzy AHP, Criteria weightings, Decisionmaking

Introduction. Key Words: Analytic Hierarchy Process (AHP), Fuzzy AHP, Criteria weightings, Decisionmaking Application of AHP and Fuzzy AHP to Decision-Making Problems in Construction Sangwook Lee, Ph.D. University of Wisconsin-Platteville Platteville, Wisconsin The approach to selecting key factors has been

More information

Evaluation and Selection of Construction Contractors Based on Analytic Hierarchy Process (AHP)

Evaluation and Selection of Construction Contractors Based on Analytic Hierarchy Process (AHP) Evaluation and Selection of Construction Contractors Based on Analytic Hierarchy Process (AHP) Samiaah M. Hassen M. Al-Tmeemy Prof. Dr. Hamzah Abdul- Rahman Associate Prof. Dr. Zakaria Harun Abstract Contractor

More information

A Strategic Model for Cleaner Production Implementation In a Paper Making Mill

A Strategic Model for Cleaner Production Implementation In a Paper Making Mill A Strategic Model for Cleaner Production Implementation In a Paper Making Mill P. Ghorbannezhad, M. Azizi, M. Layeghi* Department of Wood & Paper Science & Technology University of Tehran E-mail: Payam.gs2008@gmail.com

More information

An Integrated Multi-Attribute-Decision Making Approach for Selecting Structural System: A Case Study

An Integrated Multi-Attribute-Decision Making Approach for Selecting Structural System: A Case Study CCC 2018 Proceedings of the Creative Construction Conference (2018) Edited by: Miroslaw J. Skibniewski & Miklos Hajdu Creative Construction Conference 2018, CCC 2018, 30 June - 3 July 2018, Ljubljana,

More information

Group Decision Support System for Multicriterion Analysis A Case Study in India

Group Decision Support System for Multicriterion Analysis A Case Study in India Group Decision Support System for Multicriterion Analysis A Case Study in India K. Srinivasa Raju Department of Civil Engineering, S.E.S.College of Engineering, Kopargaon 423 603, Maharashtra, India D.Nagesh

More information

Mostafa Khanzadi Assistant Professor of Structural Engineering Iran University of Science and Technology Tehran, Iran

Mostafa Khanzadi Assistant Professor of Structural Engineering Iran University of Science and Technology Tehran, Iran APPLICATION OF ANALYTIC HIERARCHY PROCESS (AHP) TO PRIORITIZE CAUSES OF CLAIMS BASED ON THE EFFECT ON THE TIME AND COSTS OF INFRASTRUCTURAL PROJECTS IN THE FIELD OF IRAN OIL AND GAS Mostafa Khanzadi Assistant

More information

Supplier Selection of Technical Goods Using AHP Methods

Supplier Selection of Technical Goods Using AHP Methods Supplier Selection of Technical Goods Using AHP Methods Fatkhor Rozi Industrial Engineering, Engineering Faculty University of Surabaya Surabaya, Indonesia fatkhorrozi@gmail.com Evy Herowati Industrial

More information

Sustainable development through desert tourism planning: a SWOT approach

Sustainable development through desert tourism planning: a SWOT approach Sustainable Tourism IV 59 Sustainable development through desert tourism planning: a SWOT approach M. Sabokkhiz & S. Sabokkhiz University of Isfahan, College of Engineering, Department of Surveying and

More information

Establishment of Legal Metrology Conformity Assessment Model Based on Risk Management

Establishment of Legal Metrology Conformity Assessment Model Based on Risk Management Establishment of Legal Metrology Conformity Assessment Model Based on Risk Management Chun-Min Su, Cheng-Tsair Yang and Jiunn-Haur Shaw Center for Measurement Standards/ITRI, Taiwan NCSLI 2011, National

More information

The Multi criterion Decision-Making (MCDM) are gaining importance as potential tools

The Multi criterion Decision-Making (MCDM) are gaining importance as potential tools 5 MCDM Methods 5.1 INTRODUCTION The Multi criterion Decision-Making (MCDM) are gaining importance as potential tools for analyzing complex real problems due to their inherent ability to judge different

More information

A Fuzzy MCDM for Evaluating Risk of Construction Projects

A Fuzzy MCDM for Evaluating Risk of Construction Projects Australian Journal of Basic and Applied Sciences 5(12): 162-171 2011 ISSN 1991-8178 A Fuzzy MCDM for Evaluating Risk of Construction Projects 1 A. Sotoudeh Gohar 1 M. Khanzadi and 2 M. Parchami Jalal 1

More information

Proposal for using AHP method to evaluate the quality of services provided by outsourced companies

Proposal for using AHP method to evaluate the quality of services provided by outsourced companies Available online at www.sciencedirect.com ScienceDirect Procedia Computer Science 55 (2015 ) 715 724 Information Technology and Quantitative Management (ITQM 2015) Proposal for using AHP method to evaluate

More information

Supplier Selection Using Analytic Hierarchy Process: An Application From Turkey

Supplier Selection Using Analytic Hierarchy Process: An Application From Turkey , July 6-8, 2011, London, U.K. Supplier Selection Using Analytic Hierarchy Process: An Application From Turkey Betül Özkan, Hüseyin Başlıgil, Nergis Şahin Abstract Decision making is one of the most activities

More information

Plant Location Selection in Natural Stone Industry

Plant Location Selection in Natural Stone Industry Key Engineering Materials Online: 2013-04-10 ISSN: 1662-9795, Vol. 548, pp 371-378 doi:10.4028/www.scientific.net/kem.548.371 2013 Trans Tech Publications, Switzerland Plant Location Selection in Natural

More information

A Literature Review on Ahp (Analytic Hierarchy Process)

A Literature Review on Ahp (Analytic Hierarchy Process) A Literature Review on Ahp (Analytic Hierarchy Process) Virendra Rajput 1, Dinesh Kumar 2, Arun Sharma 3, Shubham Singh 4, Rambhagat 5 1. Asst. Prof. Dept. of Mechanical Engineering, Mittal Institute of

More information

RESEARCH ON DECISION MAKING REGARDING HIGH-BUSINESS-STRATEGY CAFÉ MENU SELECTION

RESEARCH ON DECISION MAKING REGARDING HIGH-BUSINESS-STRATEGY CAFÉ MENU SELECTION RESEARCH ON DECISION MAKING REGARDING HIGH-BUSINESS-STRATEGY CAFÉ MENU SELECTION Cheng-I Hou 1, Han-Chen Huang 2*, Yao-Hsu Tsai 3, Chih-Yao Lo 4 1 Department of Leisure Management, Yu Da University of

More information

A feasibility evaluation on the outsourcing of quality testing and inspection

A feasibility evaluation on the outsourcing of quality testing and inspection Available online at www.sciencedirect.com International Journal of Project Management 27 (2009) 89 95 www.elsevier.com/locate/ijproman A feasibility evaluation on the outsourcing of quality testing and

More information

ScienceDirect. Analytic Hierarchy Process of Academic Scholars for Promoting Energy Saving and Carbon Reduction in Taiwan

ScienceDirect. Analytic Hierarchy Process of Academic Scholars for Promoting Energy Saving and Carbon Reduction in Taiwan Available online at www.sciencedirect.com ScienceDirect Procedia Environmental Sciences 20 ( 2014 ) 526 532 The 4 th International Conference on Sustainable Future for Human Security, SustaiN 2013 Analytic

More information

Final contractor selection using the analytical hierarchy process

Final contractor selection using the analytical hierarchy process Construction Management and Economics (2000) 18, 547 557 Final contractor selection using the analytical hierarchy process PATRICK SIK-WAH FONG 1 and SONIA KIT-YUNG CHOI 2 1 Department of Building & Real

More information

Multi-Criteria Analysis of Advanced Planning System Implementation

Multi-Criteria Analysis of Advanced Planning System Implementation Multi-Criteria Analysis of Advanced Planning System Implementation Claudemir L. Tramarico, Valério A. P. Salomon and Fernando A. S. Marins São Paulo State University (UNESP) Engineering School, Campus

More information

PRIORITISATION OF ROAD CORRIDORS BY DEVELOPING COMPOSITE INDEX

PRIORITISATION OF ROAD CORRIDORS BY DEVELOPING COMPOSITE INDEX ISSN (Online) : 2319-8753 ISSN (Print) : 2347-6710 International Journal of Innovative Research in Science, Engineering and Technology An ISO 3297: 2007 Certified Organization, Volume 2, Special Issue

More information

Optimal polymer matrix coating for composite railway sleeper Analytic Hierarchy Process

Optimal polymer matrix coating for composite railway sleeper Analytic Hierarchy Process University of Southern Queensland From the SelectedWorks of Wahid Ferdous Summer December 14, 15 Optimal polymer matrix coating for composite railway sleeper Analytic Hierarchy Process Wahid Ferdous Allan

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION 1.1 Background of Study Tender means make a formal written offer to carry out work, supply goods, etc. for a stated fixed price (Oxford Dictionary, 2002). The greater part of the

More information

AN IMPROVEMENT ON SAATY'S AHP

AN IMPROVEMENT ON SAATY'S AHP AN IMPROVEMENT ON SAATY'S AHP Feng Kong, Hongyan Liu Department of Economics and management, North China Electric Power University, Baoding, P.R. China, 7 Abstract: Key words: AHP is a commonly used method

More information

Analysis and evaluation of criteria for pre-selecting contractors in the Saudi Arabian construction sector

Analysis and evaluation of criteria for pre-selecting contractors in the Saudi Arabian construction sector Loughborough University Institutional Repository Analysis and evaluation of criteria for pre-selecting contractors in the Saudi Arabian construction sector This item was submitted to Loughborough University's

More information

Application of AHP Model for Evaluation of Solid Waste Treatment Technology

Application of AHP Model for Evaluation of Solid Waste Treatment Technology Mohd Armi Abu Smah et al Int J Engg Techsci Vol 1(1) 2010,35-40 Application of AHP Model for Evaluation of Solid Waste Treatment Technology Mohd Armi Abu Samah, Latifah Abd Manaf and Nur llyana Mohd Zukki

More information

Knowledge-Based Systems

Knowledge-Based Systems -Based Systems 22 (2009) 363 367 Contents lists available at ScienceDirect -Based Systems journal homepage: www.elsevier.com/locate/knosys An measurement model for knowledge management Yuan-Feng Wen *

More information

The Application of the Analytic Hierarchy Process for Multicriterion Evaluation of the Enterprise s Investment Attractiveness

The Application of the Analytic Hierarchy Process for Multicriterion Evaluation of the Enterprise s Investment Attractiveness The Application of the Analytic Hierarchy Process for Multicriterion Evaluation of the Enterprise s Investment Attractiveness Khakimdzhon Aminov, Maria Kossukhina Saint-Petersburg State University of Engineering

More information

Cloud adoption decision support for SMEs Using Analytical Hierarchy Process (AHP)

Cloud adoption decision support for SMEs Using Analytical Hierarchy Process (AHP) Cloud adoption decision support for SMEs Using Analytical Hierarchy Process (AHP) ROBERT WILSON, Berlin Mano, KHAZAEI, Babak and HIRSCH, Laurence Available from Sheffield

More information

Application of AHP for Lean Implementation Analysis in 6 MSMEs

Application of AHP for Lean Implementation Analysis in 6 MSMEs Application of AHP for Lean Implementation Analysis in 6 MSMEs 1 Ravikumar M.M*,1, Marimuthu K 2, H. Abdul Zubar 3 Research Scholar, Faculty of Mechanical Engineering, Anna University, India (Email ID:

More information

Supplier Selection for Construction Projects Through TOPSIS and VIKOR Multi-Criteria Decision Making Methods

Supplier Selection for Construction Projects Through TOPSIS and VIKOR Multi-Criteria Decision Making Methods Supplier Selection for Construction Projects Through TOPSIS and VIKOR Multi-Criteria Decision Making Methods Dr. Bhatt Rajiv & Dr. Bhatt Darshana Associate Professor, Civil Engineering Department, A.D.

More information

Abstract Number: Abstract Title: Supplier Selection with Component Commonality

Abstract Number: Abstract Title: Supplier Selection with Component Commonality Abstract Number: 007-0144 Abstract Title: Supplier Selection with Component Commonality R Samuel Sale Louisiana Tech University 407 Kennon Lane Apt 39 Ruston LA, 71270 rssale@hotmail.com POMS 18 th Annual

More information

SELECTING A PROFOUND TECHNICAL SERVICE PROVIDER TO PERFORM A TECHNICAL FIELD DEVELOPMENT STUDY FROM GIVEN MULTIPLE CRITERIA

SELECTING A PROFOUND TECHNICAL SERVICE PROVIDER TO PERFORM A TECHNICAL FIELD DEVELOPMENT STUDY FROM GIVEN MULTIPLE CRITERIA SELECTING A PROFOUND TECHNICAL SERVICE PROVIDER TO PERFORM A TECHNICAL FIELD DEVELOPMENT STUDY FROM GIVEN MULTIPLE CRITERIA Slamet Riyadi, Lokman Effendi and Rafikul Islam Department of Business Administration,

More information

SELECTION OF RAIL IMPROVEMENT PROJECTS USING THE ANALYTIC NETWORK PROCESS (ANP)

SELECTION OF RAIL IMPROVEMENT PROJECTS USING THE ANALYTIC NETWORK PROCESS (ANP) SELECTION OF RAIL IMPROVEMENT PROJECTS USING THE ANALYTIC NETWORK PROCESS (ANP) J. Montesinos-Valera. P. Aragonés-Beltrán. J.P. Pastor-Ferrando. Department of Engineering Projects Universidad Politécnica

More information

APPLY THE ANALYTIC HIERARCHY PROCESS METHOD FOR SELECTING SUPPLIER IN AUTOMOTIVE BUSINESS

APPLY THE ANALYTIC HIERARCHY PROCESS METHOD FOR SELECTING SUPPLIER IN AUTOMOTIVE BUSINESS APPLY THE ANALYTIC HIERARCHY PROCESS METHOD FOR SELECTING SUPPLIER IN AUTOMOTIVE BUSINESS Supakit Laksanasiri Department of Industrial Engineering, Kasetsart University, Thailand Naprud Paisansin International

More information

ISSN: ISO 9001:2008 Certified International Journal of Engineering and Innovative Technology (IJEIT) Volume 3, Issue 9, March 2014

ISSN: ISO 9001:2008 Certified International Journal of Engineering and Innovative Technology (IJEIT) Volume 3, Issue 9, March 2014 A Comprehensive Model for Evaluation of Sport Coaches Performance Qiang ZHANG 1* Bo HOU 1 Yue WANG 1 Yarong XIAO 1 1. College of Optoelectronic Engineering Chongqing University Chongqing P.R. China 400044

More information

Multi-Attribute Utility Theory for Contractor Pre-Qualification

Multi-Attribute Utility Theory for Contractor Pre-Qualification Multi-Attribute Utility Theory for Contractor Pre-Qualification Shivraj Sarjerao Patil #1, Prof.Dr.D.N.Mudgal #2, Prof.S.B.Patil #3 #1. P.G.Student,Department of CivilEngineering, Ashokrao Mane Group Of

More information

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES T.M.S. Elhag and A.H. Boussabaine School of Architecture and Building Engineering, The University of Liverpool, Liverpool L69 3BX, UK Understanding the

More information

main target of the AHP is to decide and help decision makers in making resolutions for the complex problems by

main target of the AHP is to decide and help decision makers in making resolutions for the complex problems by Application of Analytical Hierarchy Process in Evaluation of Best Sewage Treatment Plant Kshitij Upadhyay Civil Engineering Department Rajkiya Engineering College, Bijnor Abstract: This paper presents

More information

Thomas Michael Lintner, Steven D. Smith, Scott Smurthwaite / Paper for the 2009 ISAHP

Thomas Michael Lintner, Steven D. Smith, Scott Smurthwaite / Paper for the 2009 ISAHP THE AEROSPACE PERFORMANCE FACTOR: UTILIZATION OF THE ANALYTICAL HIERARCHY PROCESS TO DEVELOP A BALANCED PERFORMANCE AND SAFETY INDICATOR OF THE NATIONAL AIRSPACE SYSTEM FOR THE FEDERAL AVIATION ADMINISTRATION

More information

Selecting an appropriate forestry extension model for the Zagros area in Iran through the AnalyticHierarchy Process (AHP)

Selecting an appropriate forestry extension model for the Zagros area in Iran through the AnalyticHierarchy Process (AHP) Selecting an appropriate forestry extension model for the Zagros area in Iran through the AnalyticHierarchy Process (AHP) Davood Samari 1, Ali R. Estelaji 2, Majid Azizi 3 Gholam H. Salehnasab 4 1. Faculty

More information

Decision making for Raw material Procurement in Paper making factory. Majid Azizi Natural Resources Faculty, University of Tehran ut.ac.

Decision making for Raw material Procurement in Paper making factory. Majid Azizi Natural Resources Faculty, University of Tehran ut.ac. ISAHP 2005, Honolulu, Hawaii, July 8-10,2005 Decision making for Raw material Procurement in Paper making factory Majid Azizi Natural Resources Faculty, University of Tehran mazizi@ ut.ac.ir Keywords:

More information

A Fuzzy Analytic Hierarchy Process Approach for Optimal Selection of Manufacturing Layout

A Fuzzy Analytic Hierarchy Process Approach for Optimal Selection of Manufacturing Layout A Fuzzy Analytic Hierarchy Process Approach for Optimal Selection of Manufacturing Layout Lindley Bacudio 1, Giselle Joy Esmeria 1 and Michael Angelo Promentilla 2 1 Industrial Engineering Department,

More information

A RANKING AND PRIORITIZING METHOD FOR BRIDGE MANAGEMENT

A RANKING AND PRIORITIZING METHOD FOR BRIDGE MANAGEMENT A RANKING AND PRIORITIZING METHOD FOR BRIDGE MANAGEMENT Saleh Abu Dabous and Sabah Alkass Department of Building, Civil and Environmental Engineering, Concordia University, Rm: EV-6139 1455 de Maisonneuve,

More information

TESTING THE VALUE OF BEST VALUE: EVIDENCE FROM EDUCATIONAL FACILITIES PROJECTS

TESTING THE VALUE OF BEST VALUE: EVIDENCE FROM EDUCATIONAL FACILITIES PROJECTS Eke, G., and Elgy, J. (2017). Testing the value of Best Value. In: LC3 2017 Volume II Proceedings of the 25th Annual Conference of the International Group for Lean Construction (IGLC), Walsh, K., Sacks,

More information

Combining AHP and TOPSIS Approaches to Support Site Selection for a Lead Pollution Study

Combining AHP and TOPSIS Approaches to Support Site Selection for a Lead Pollution Study 2012 2nd International Conference on Environmental and Agriculture Engineering IPCBEE vol.37 (2012) (2012) IACSIT Press, Singapore Combining AHP and TOPSIS Approaches to Support Site Selection for a Lead

More information

Research on the Evaluation of the New Energy Auto Industry Innovation System

Research on the Evaluation of the New Energy Auto Industry Innovation System Management Science and Engineering Vol. 5, No. 4, 2011, pp. 1-6 DOI:10.3968/j.mse.1913035X20110504.171 ISSN 1913-0341[Print] ISSN 1913-035X[Online] www.cscanada.net www.cscanada.org Research on the Evaluation

More information

Using Analytical Hierarchy Process for Selecting Intercrop in Rubber Field A Case Study in Phitsanulok, THAILAND

Using Analytical Hierarchy Process for Selecting Intercrop in Rubber Field A Case Study in Phitsanulok, THAILAND Using Analytical Hierarchy Process for Selecting Intercrop in Rubber Field A Case Study in Phitsanulok, THAILAND Chutiphon Srisawat 1, Janjira Payakpate 2 1,2 CSIT, Faculty of Science, Naresuan University,

More information

Optimization Model in Subcontractors Assignment in Jordan

Optimization Model in Subcontractors Assignment in Jordan Optimization Model in Subcontractors Assignment in Jordan 1 Shereen Yahya Abunada and 2 Ibrahim Abed Mohammed 1,2 Isra University- Jordan. 1 ORCID 0000-0003-2785-4914 Abstract Contracting companies carry

More information

Application of Fuzzy AHP for Evaluation of Green Supply Chain Management Strategies

Application of Fuzzy AHP for Evaluation of Green Supply Chain Management Strategies Application of Fuzzy AHP for Evaluation of Green Supply Chain Management Strategies P Muralidhar 1, Dr K Ravindranath 2, Dr V Srihari 3 1, 3 (NICMAR s -CISC, NAC Campus, Kondapur post Hyderabad-500084)

More information

ANALYSIS OF THE EFFICIENCY OF BANKS IN MONTENEGRO USING THE AHP

ANALYSIS OF THE EFFICIENCY OF BANKS IN MONTENEGRO USING THE AHP ANALYSIS OF THE EFFICIENCY OF BANKS IN MONTENEGRO USING THE AHP Svetlana Rakocevic Faculty of Economics University of Montenegro Podgorica, Montenegro E-mail: svetr@cg.ac.yu Zdenka Dragasevic! Faculty

More information

Fuzzy AHP approach for the Selection of Groundwater Recharge Alternative: Sensitivity Analysis

Fuzzy AHP approach for the Selection of Groundwater Recharge Alternative: Sensitivity Analysis Fuzzy AHP approach for the Selection of Groundwater Recharge Alternative: Sensitivity Analysis Masengo Ilunga, Department of Civil Engineering and Chemical Engineering, University of South Africa, Pretoria,

More information

International Journal of Advance Engineering and Research Development STUDY OF SOME PERFORMANCE MEASUREMENT INDICES OF SUPPLY CHAIN MANAGEMENT

International Journal of Advance Engineering and Research Development STUDY OF SOME PERFORMANCE MEASUREMENT INDICES OF SUPPLY CHAIN MANAGEMENT Scientific Journal of Impact Factor (SJIF): 4.14 International Journal of Advance Engineering and Research Development Volume 3, Issue 3, March -2016 e-issn (O): 2348-4470 p-issn (P): 2348-6406 STUDY OF

More information

ERP Reference models and module implementation

ERP Reference models and module implementation ERP Reference models and module implementation Based on Supporting the module sequencing decision in the ERP implementation process An application of the ANP method, Petri Hallikainen, Hannu Kivijärvi

More information

SUPPLIER EVALUATION OF LOGISTICS FACTORS AND THEIR CONTRIBUTION TO IMPROVED CUSTOMER SERVICE

SUPPLIER EVALUATION OF LOGISTICS FACTORS AND THEIR CONTRIBUTION TO IMPROVED CUSTOMER SERVICE SUPPLIER EVALUATION OF LOGISTICS FACTORS AND THEIR CONTRIBUTION TO IMPROVED CUSTOMER SERVICE M. Muya 1, A. D. F. Price 2 and A. Thorpe 3 Department of Civil and Building Engineering, Loughborough University,

More information

A Dynamic Model for Vendor Selection

A Dynamic Model for Vendor Selection Feb. 2007, Volume 6, No.2 (Serial No.35) China-USA Business Review, ISSN1537-1514, USA A Dynamic Model for Vendor Selection ZHU Xue-zhen (School of Business, Soochow University, Suzhou 215021, China) Abstract:

More information

The Importance-Weights Determination of the Safety Factors of Fishing Ports in Zhuhai via the AHP Method

The Importance-Weights Determination of the Safety Factors of Fishing Ports in Zhuhai via the AHP Method Advances in Computer Science Research, volume nd International Conference on Computer Engineering, Information Science & Application Technology (ICCIA 0) The Importance- Determination of the Safety Factors

More information

An Innovative B2C E-commerce Websites Selection using the ME-OWA and Fuzzy AHP

An Innovative B2C E-commerce Websites Selection using the ME-OWA and Fuzzy AHP Proceedings of the First International Conference on Information DOI: 10.15439/2018KM37 Technology and Knowledge Management pp. 13 19 ISSN 2300-5963 ACSIS, Vol. 14 An Innovative B2C E-commerce Websites

More information

ANALYTIC HIERARCHY PROCESS IN SELECTING BEST GROUNDWATER POND

ANALYTIC HIERARCHY PROCESS IN SELECTING BEST GROUNDWATER POND 31 st International Geological Congress, Rio de Janeiro, Brazil, 6-17 August 2000 ANALYTIC HIERARCHY PROCESS IN SELECTING BEST GROUNDWATER POND JANDRIC, Z., SRDJEVIC, B. Institute for Water Management,

More information

KING FAHD UNIVERSITY OF PETROLEUM & MINERALS

KING FAHD UNIVERSITY OF PETROLEUM & MINERALS KING FAHD UNIVERSITY OF PETROLEUM & MINERALS DEPARTMENT OF CONSTRUCTION ENGINEERING AND MANAGEMENT CEM 610 THESIS PROPOSAL: EFFICACY OF CONTRACTOR PREQUALIFICATION MODELS Submitted by: MIR FAROOQ ALI Student

More information

Design-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka

Design-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka Design-Bid-Build Vs Design Build Projects: Performance Assessment of Commercial Projects In Sri Lanka S. Ratnasabapathy and R. Rameezdeen Department of Building Economics, University of Moratuwa, Sri Lanka.

More information

UK CONSTRUCTION CLIENTS OPINIONS OF THE CONTRACTOR SELECTION PROCESS

UK CONSTRUCTION CLIENTS OPINIONS OF THE CONTRACTOR SELECTION PROCESS UK CONSTRUCTION CLIENTS OPINIONS OF THE CONTRACTOR SELECTION PROCESS Chee H Wong 1, Gary D. Holt 2 and Phil Harris 3 School of Engineering and the Built Environment, University of Wolverhampton, Wulfruna

More information

A study on Supply Chain issues of Indian Railway in Samastipur division using AHP technique

A study on Supply Chain issues of Indian Railway in Samastipur division using AHP technique A study on Supply Chain issues of Indian Railway in Samastipur division using AHP technique Saurabh Bhardwaj 1, C.S. Jawalkar 2 1,2 Department of Production and Industrial Eng., PEC University of Technology,

More information

Zulpan Hadi and Suryawan Murtiadi Master of Civil Engineering, Postgraduate Study Program, University of Mataram, Indonesia

Zulpan Hadi and Suryawan Murtiadi Master of Civil Engineering, Postgraduate Study Program, University of Mataram, Indonesia International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 7, July 2018, pp. 1538 1545, Article ID: IJCIET_09_07_164 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=7

More information

Selection of the most optimal contractor in Indian Construction Industry using Topsis and Extended Topsis model

Selection of the most optimal contractor in Indian Construction Industry using Topsis and Extended Topsis model Selection of the most optimal contractor in Indian Construction Industry using Topsis and Extended Topsis model Patcy Paul 1, Salini P S 2, Sreepriya Mohan 3 1 (Assistant Professor, Civil Engineering,

More information

Employee Performance Appraisal to Determine Best Engineer Candidates with Analytical Hierarchy Process Approach

Employee Performance Appraisal to Determine Best Engineer Candidates with Analytical Hierarchy Process Approach IOP Conference Series: Materials Science and Engineering PAPER OPEN ACCESS Employee Performance Appraisal to Determine Best Engineer Candidates with Analytical Hierarchy Process Approach To cite this article:

More information

Identification of Target Issues in Turkey s ADR Integration

Identification of Target Issues in Turkey s ADR Integration Identification of Target Issues in Turkey s ADR Integration Matthias Klumpp 1, Dilay Çelebi 2 1 Institute for Logistics and Service Management (ild), FOM University of Applied Sciences, Leimkugelstraße

More information

A MODEL OF CONTRACTOR SELECTION USING ANP AND RISK ASSESSEMENT ON A PROCUREMENT SERVICE

A MODEL OF CONTRACTOR SELECTION USING ANP AND RISK ASSESSEMENT ON A PROCUREMENT SERVICE A MODEL OF CONTRACTOR SELECTION USING ANP AND RISK ASSESSEMENT ON A PROCUREMENT SERVICE Endi 1) and Bambang Syairudin Master s Program in Management of Technology, Institut Teknologi Sepuluh Nopember Jl.

More information

CHOOSING THE BEST TRAINING AIRCRAFT FOR A FLIGHT TRAINING ORGANIZATION BY MULTI CRITERIA DECISION MAKING METHODS

CHOOSING THE BEST TRAINING AIRCRAFT FOR A FLIGHT TRAINING ORGANIZATION BY MULTI CRITERIA DECISION MAKING METHODS CHOOSING THE BEST TRAINING AIRCRAFT FOR A FLIGHT TRAINING ORGANIZATION BY MULTI CRITERIA DECISION MAKING METHODS Ece YURDUSEVİMLİ, Asuman ÖZGER Anadolu University, Department of Aircraft Electric & Electronics,

More information