ESB Generation & Wholesale Markets Response to:
|
|
- Marshall Dean
- 5 years ago
- Views:
Transcription
1 ESB Generation & Wholesale Markets Response to: DS3: System Services Consultation Finance Arrangements February 13 th 2013
2 Part One: Introduction ESB Generation and Wholesale Markets (ESB GWM) welcome the opportunity to respond to this consultation. The ESB GWM generation portfolio comprises of both conventional and renewable generators. The successful delivery of the DS3 programme is therefore important to the ESB GWM business. We welcome the work being carried out by Eirgrid and SONI in relation to this. The main points of ESB GWM s response to this consultation are summarised below. Part Two of the consultation response gives more detailed comments. Responses to the specific consultation questions raised are outlined in the Appendix. 1.1 Summary of Main Comments ESB GWM support the introduction of the new system services in order to facilitate higher levels of renewable generation required to meet both Governments 2020 targets ESB GWM are now of the view, that given the level of system services that are required on the system in order to facilitate increased amounts of renewable generation, that these system services are kept separate to capacity payments. Capacity payments are for incentivising generation adequacy whereas system service payments are required to incentivise generation flexibility and as such the two should not be linked. ESB GWM agrees in principle with the value based approach for determining the system services pot subject to total cost recovery for provision of the services at a very minimum. This approach should also be extended to include existing Ancillary Services. The consultation assumes that synchronous generators can all comply with the proposed ROCOF Grid Code modification, and so neither the cost nor the value of the provision of inertia to the system has been captured. ESB GWM considers this to be a serious flaw in the consultation. ESB GWM strongly recommend that in order to incentivise investment in provision of these services that: o remuneration for provision of the services should reflect the fact that new additional costs (both capital and O&M) are being incurred by generators and new revenue streams are required to cover this. It is inappropriate to simply move monies out of one pot into another 2
3 o system services payments should be paid on the basis of capability to provide the service o tariffs should be fixed for at least five years o the performance scalar concept as outlined in the consultation should be radically changed Part Two: Detailed Comments 2.1 The System Services Pot and Linkage with Capacity Payments Change in how generators earn revenues As levels of intermittent generation in the SEM increase the revenue streams for generators are changing. Whilst historically energy and capacity payments have been the most important revenue streams, with Ancillary Service (AS) income small in comparison, this is likely to change substantially. The system now requires generators to provide different services. Operational flexibility is increasing in value and at the same time energy payments will be decreasing in value due to the low marginal cost of wind generation. The system services pot should reflect this shift. New costs require new revenue streams The pot available for system services should also reflect the fact that new additional costs will be incurred by generators for the provision of the new system services required on the system. New revenue streams will therefore be required in order for generators to be incentivised to provide these services. It is not appropriate to simply move monies from the capacity pot into system services. Capacity and system service payments should be separate since they are addressing separate requirements. Linkage between capacity and system services pots System services payments are required in order to incentivise the enhanced operational flexibility of generators that is needed in order to achieve Government 2020 renewable targets. Capacity payments under the current Capacity Payment Mechanism (CPM) are designed to incentivise sufficient levels of available generation capacity in order to ensure generation adequacy and that the security of supply standard is met. It is clear that both schemes have different objectives and therefore should not be linked. Methodology, fixing and distribution of system services pot The consultation proposes a methodology for valuing the system services. ESB GWM is in broad agreement with this approach, and also agree that the consumer 3
4 should share in any net benefit that arises. This value based approach should also be extended to determining the pot for existing AS. ESB GWM believes that consideration should be given to how the pot for system services could be fixed and fully distributed to providers of the services. For example, any monies not paid to providers due to poor performance, could be redistributed to providers with good performance. 2.2 ROCOF The consultation assumes that the ROCOF issue has been resolved and all generators can meet the proposed new standard. The valuation of the Synchronous Inertial Response (SIR) product therefore assumes that this service is no longer scarce and so has little value. The costs of compliance with the proposed new ROCOF standard have not been included in the consultation. Achievement of the new ROCOF standard is crucial if the System Non-Synchronous Penetration Level (SNSP) is to be increased and the reduction in system production costs, as outlined in the consultation, are to be obtained. Yet the substantial cost implications associated with achievement of the new proposed ROCOF standard have not been addressed at all. This issue is of fundamental importance to the successful implementation of DS3 and needs to be addressed by the TSOs and the Regulatory Authorities (RA). Separate to this consultation response ESB GWM have submitted proposals to the CER on how this issue should be dealt with and are happy to discuss these proposals further with both the TSOs and RAs in order that an efficient and swift solution is achieved. 2.3 Investment Decisions In order to be able to provide the new system services generators will have to consider the investment required to do so. However many of the proposals in the consultation will lead to revenues being uncertain and difficult to forecast and therefore investment will not be incentivised. The consultation proposes that tariff rates should be reviewed on a three to five year basis which clearly leads to uncertainty around future revenue streams. ESB GWM considers that product rates should be fixed for five years in order to give confidence. Also proposed in the consultation is a dispatch payment basis. Generator dispatch is getting more and more difficult to predict as the level of 4
5 intermittent renewable generation on the system increases. Linking payment to dispatch therefore creates another layer of uncertainty. ESB GWM considers that investment would be better incentivised if payments were based on capability to provide the service. The performance scalar concept is also introduced in the consultation, where performance below 50% is not remunerated. This measure also creates massive uncertainty as to the level of future revenues. (Further comments on the performance scalar are given in 2.4 below) Investors will require higher returns in order to be incentivised in the face of such uncertainty and unpredictability. Ultimately then the end-user will end up paying a higher rate for provision of the same service. 2.4 Performance Scalar Currently AS are remunerated based on capability to provide the service, with penalties for non-performance. The proposals in this consultation are significantly different, both in terms of payment basis and also performance. Comments on payment basis are given in 2.3 above. It is proposed that there would be a sliding scale of reduced payment rates between 50-90% performance with no payments to be made for performance below 50%. ESB GWM considers that this approach is draconian. All generators that provide services required for the system should be compensated. However, we recognise the importance of reliability and so would be supportive of a reduced scalar for performance in the range of 0-49%. It is unclear how the performance scalar will be applied for services that are event driven and infrequent in nature. Clarification is required on whether rolling averages of performance will be used. It is important that the process does not lead to situations whereby generators are no longer incentivised to provide services as they may already have fallen below the payment threshold and know that within the timeframe they will be unable to reverse this. A time limit could be introduced on how long reduced performance payments would apply if the generator has not been given the chance to prove itself. Services providers should have the ability to declare themselves unavailable for services when they know in advance that they will be unable to provide that service. Non-provision of services when declared unavailable should not be penalised or impact of performance. 5
6 It is essential that service providers are given the opportunity to input into the development of the Performance Monitoring Process for System Services. 2.5 Products Synchronous Inertial Response (SIR) As currently designed the product includes an arbitrary minimum load threshold below which providers of inertia will not receive payment. ESB GWM are of the strong view that all providers of inertia should be compensated. Payments could be scaled so that lower minimum loads receive higher payments, however all providers should receive payment. It is unclear how the performance of this product would be measured. The product volume appears to be a desktop calculation. However the consultation stipulates that disturbance recorders would be required in the performance monitoring of fast acting products such as SIR. Actual inertial response of synchronous generators will be dependent on the make up of the system at the time of the frequency event. It would therefore be inappropriate to have a contracted value to which performance would be measured. More detail is required on how this would work in practice. Steady State Reactive Power The product as designed currently does not take into account the ability of many conventional generators to provide higher levels of reactive power capability at lower active power loads. Currently only a single declaration of reactive power is allowed, and therefore the lowest capability level across the active power range must be declared. Remuneration of this service should reflect the full range of reactive power capability of a generator for its entire active power range. If the TSO requires increased reactive power, it can obtain this by allowing units to declare reactive power capability in accordance with their capability chart instead of one single value across the MW range. Fast Acting Products & Performance Measurement It is proposed to introduce disturbance recorders for use in the performance measurement of the fast acting products (SIR, Fast Frequency Response, Fast Post Fault Active Power Recovery and Dynamic Reactive Response). Performance of generators in such short time frames as these products cover will be difficult to measure against a contracted value, as there will be considerable transient effects in the waveforms which will differ from event to event depending on the magnitude of the system disturbance event and also the system conditions and configuration at the 6
7 time of the event. In such circumstances it is unclear how performance could then fairly be ascertained. More details on how this would work are required. 2.6 KEMA Costs & Generation Investment Scenario ESB GWM does not consider that the portfolio assumed in the Generation Investment Scenario is fully reflective of the generators that will be providing the system services. For example no costs to coal plant have been assumed. With regard to KEMA report, unfortunately there has been insufficient time in order to be able to verify the costs contained in the report. OEMs would have to be consulted in order to do this and the consultation time line did not allow for this. There is also insufficient information in the report around the detail and breakdown of these costs. For example the enhanced cost for existing CCGT investment is not broken down to show how much of the cost is attributable to having a reduced min load and start up times or faster frequency response. For more specific examples, there is crucial detail missing i.e. how much MW reduction in minimum load was obtained for the cost of the capability was it 5% or 25% of nominal capacity. If more information can be provided, ESB GWM is willing to investigate the costs further and meet bilaterally with the TSOs if required. If you have any questions or would like to discuss any of the matters raised further please contact: Jag Basi (jag.basi@esb.ie) Regulation Manager, ESB Generation & Wholesale Markets 7
8 Appendix: Response to Consultation Questions Question Value of System Services to the Electricity System Do you agree that the proposed value based approach to informing the amount of funding available for System Services is necessary and appropriate to deliver the required services to achieve the renewable targets? Financial Modelling and Analysis Approach To what extent, if any, should the capital costs inform the decision regarding future system services? Do you agree with the proposed methodology for determining the aggregate available pot for System Services? Allocation of System Services Revenue Which of the four methods outlined to allocate the funds between the System Services products would you prefer or is there another approach which should Response Yes, in principle agree with the value based approach. However the level of revenues available should be sufficient to ensure that service providers can at a minimum recover the costs incurred for the provision of these services. The capital costs, combined with any associated operational costs, associated with the provision of the services should be used to set the minimum revenue requirement. As stated above, ESB GWM agree in principle with the value based approach for calculating the pot available for provision of system services. Also agree that in principle the consumer should share in any benefits that are incurred as a result of the increased renewables on the system. However it must be recognised that provision of these new services will incur new incremental costs (both capital and operational costs) to generators and the revenue for the provision of these services should at a minimum allow generators to recover these costs. Without this generators will not be incentivised to provide these services. Agree with the TSO preference for the third option whereby the allocation between products is calculated based on their relative value to the system. However, independent of its value, the allocation per service should be sufficient to 8
9 be considered? Remuneration Approach Is the rationale for proposing dispatch-dependent payments clear? Is there further justification, not included in earlier consultation responses, for adopting a more capability-based approach? Proposed Contractual Arrangements and Payments Are the proposed general contractual and payment arrangements clear? incentivise the required level of that service. The TSOs have explained their arguments for their preference for dispatch-dependent payments. However, ESB GWM does not agree that this is the best compromise in terms of incentivising service providers and minimising costs to consumers. Dispatchdependent payments are by their nature less predictable. This unpredictability will increase in the future as the running regime of generators changes to accommodate increasing levels of intermittent renewables. Investment decisions will therefore need to take into account the increasing uncertainty of revenue streams and will require higher levels of return in order to be justified. Ultimately the consumer will end up paying more. Compliance with the European Target Model for Electricity and the changes that will mean for the SEM mean that there is currently a lot of uncertainty for generators in the SEM. A capability-based payment structure for system services would ensure that at least some part of revenues into the future will be more predictable. No Product Volume: How product volumes would differ depending on whether payment is dispatch or capability based is not fully clear for all products Performance Scalar: How this would work in operation is not fully clear. How many events is performance measured over? Performance Monitoring: It is not clear how some of the performance of products can be accurately measured. The timeframes associated with many of the products are in the immediate aftermath of a system event. It is not clear how a contracted value could be compared fairly to the actual response given that responses will vary depending on 9
10 system conditions. Contract award: It is unclear on what basis contracts will be awarded. It is important that the process is fair and transparent. More clarity is also required with regard to the timing of the contract award. Investors would need certainty on contracts and tariff levels for system services in advance of financial commitments being made. 10
DS3: System Services Review TSO Recommendations
DS3: System Services Review TSO Recommendations A Synopsis for the SEM Committee EirGrid and SONI, 2012 Page 1 1. Executive Summary 1.1 Introduction The power system of Ireland and Northern Ireland is
More informationTSO Recommendation System Services. 26 th June 2013
TSO Recommendation System Services 26 th June 2013 Agenda 1. Context and background 2. Consultation Process 3. Main consultation elements 4. Key Responses to Third Consultation 5. Recommendations 6. Economic
More informationConsultation on DS3 System Services Scalar Design
Consultation on DS3 System Services Scalar Design DS3 System Services Implementation Project 11 March 2015 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland, and SONI as the TSO
More informationDS3 and Qualifier Trials Update. Ian Connaughton 29 September 2017
DS3 and Qualifier Trials Update Ian Connaughton 29 September 2017 EirGrid An All-Island Energy Company European Targets Ireland has ambitious targets for renewables, particularly wind Targets for non-synchronous
More informationConsultation on DS3 System Services Market Ruleset. DS3 System Services Implementation Project
Consultation on DS3 System Services Market Ruleset DS3 System Services Implementation Project 15 March 2018 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland, and SONI as the TSO
More informationResponse to I-SEM DS3 System Services Auction Design Consultation Paper SEM
Response to I-SEM DS3 System Services Auction Design Consultation Paper SEM-15-105 22 nd December 2015 On behalf of AES Kilroot Power Ltd and AES Ballylumford Ltd 12 th February 2016 DS3 Auction Design
More informationDS3: Rate of Change of Frequency (ROCOF) Workstream
DS3: Rate of Change of Frequency (ROCOF) Workstream EirGrid and SONI, 2011 Page 1 BACKGROUND Rate of Change of Frequency and the investigation of same is one workstream within the DS3 programme. This,
More informationOperating High Variable, Renewable Generation Power Systems Lessons Learned from Ireland and Northern Ireland
Operating High Variable, Renewable Generation Power Systems Lessons Learned from Ireland and Northern Ireland 16 th September 2015 Overview 2 EirGrid s Role EirGrid is the Transmission System Operator
More informationConsultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project
Consultation on DS3 System Services Contracts for Interim Arrangements DS3 System Services Implementation Project 21 April 2016 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland,
More informationConsultation on DS3 System Services Enduring Tariffs. DS3 System Services Implementation Project
Consultation on DS3 System Services Enduring Tariffs DS3 System Services Implementation Project 4 July 2017 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland, and SONI as the TSO
More informationDS3 Rate of Change of Frequency Modification Recommendation to the CER
DS3 Rate of Change of Frequency Modification Recommendation to the CER Dated: 20/12/2012 1 P a g e Introduction The TSOs EirGrid and SONI are jointly recommending that the proposed RoCoF modification be
More informationConsultation on DS3 System Services Volume Capped Competitive Procurement. DS3 System Services Implementation Project
Consultation on DS3 System Services Volume Capped Competitive Procurement DS3 System Services Implementation Project 29 March 2018 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland,
More informationBlack Start Procurement Methodology
Issue 1 Revision Black Start Procurement Methodology Produced in accordance with Standard Condition C16 of the National Grid Transmission Licence Effective from 1 st April 2017 to 31 st March 2018 DOCUMENT
More informationDelivering a Secure, Sustainable Electricity System (DS3) Programme Overview E i r G r i d a n d S O N I, Page 1
Delivering a Secure, Sustainable Electricity System (DS3) Programme Overview - 2015 E i r G r i d a n d S O N I, 2 0 1 5 Page 1 1 Context 1.1 Background In order to facilitate the successful transition
More informationHarmonised Other System Charges 2014/2015. Recommendations Paper
Harmonised Other System Charges 2014/2015 Recommendations Paper 9 th July 2014 Other System Charges 2014/2015 Recommendations 1. EXECUTIVE SUMMARY For the upcoming tariff period running from the 1st October
More informationNational Energy Guarantee Draft Detailed Design Consultation Paper. Engineers Australia Submission
National Energy Guarantee Draft Detailed Design Consultation Paper Engineers Australia Submission 13 July 2018 Contact Details: Mark Stewart, Senior Policy Advisor Engineers Australia 11 National Circuit,
More informationDS3 System Services auction design report
DS3 System Services auction design report December 2015 DotEcon Ltd 17 Welbeck Street London W1G 9XJ www.dotecon.com Content Content 1 Introduction... 13 2 Payment basis... 22 2.1 Defining availability...
More informationChapter 2: Inputs. Chapter 3: Inputs
Chapter 2: Inputs Chapter 3: Inputs 1 Foreword (1/2) This section describes the data inputs to the scheduling and dispatch process including the source of the data and how it is used. There are thousands
More informationESB GWM Response DS3 System Services Auction Design SEM
ESB GWM Response DS3 System Services Auction Design SEM-15-105 12 th February 2015 1 Contents Contents... 2 1 Introduction... 3 2 Summary... 3 2.1 Emerging concerns with DS3 design... 3 2.1.1 Suitability
More informationRate of Change of Frequency (RoCoF) project Six Monthly Report for May 2015
Rate of Change of Frequency (RoCoF) project Six Monthly Report for May 2015 Document identifier: Authored by: Tom McCartan (tom.mccartan@soni.ltd.uk) Document version: 1 Checked by: B Woods Date of current
More informationResponse to: CER/15/284 - Review of Connection and Grid Access Policy: Initial Thinking & Proposed Transitional Arrangements
Response to: CER/15/284 - Review of Connection and Grid Access Policy: Initial Thinking & Proposed Transitional Arrangements ESB Generation and Wholesale Markets (GWM) welcome the opportunity to respond
More information1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:
1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: encourage generators and suppliers to balance their own positions before gate closure, thus reducing the call
More informationEuropean Commission DG Energy Unit B2: Wholesale markets, electricity & gas Office: DM24, 6th floor Rue De Mot 24 B 1049 Brussels/Belgium
European Commission DG Energy Unit B2: Wholesale markets, electricity & gas Office: DM24, 6th floor Rue De Mot 24 B 1049 Brussels/Belgium 6th February 2013 European Commission public consultation on generation
More informationRate of Change of Frequency (RoCoF) project Six Monthly Report for November 2016
Rate of Change of Frequency (RoCoF) project Six Monthly Report for November 2016 Document identifier: Authored by: Tom McCartan (Tom.Mccartan@soni.ltd.uk) Document version: 1 Checked by: N Watson Date
More informationIWEA Conference DS3 System Services - Volume Capped. 11 October 2018 John Young
IWEA Conference DS3 System Services - Volume Capped 11 October 2018 John Young Agenda What is DS3 & what are System Services? What are the two different types of System Services arrangements? What were
More informationRate of Change of Frequency Distribution Code Modifications. Response to the Consultation
Rate of Change of Frequency Distribution Code Modifications Response to the Consultation 1. INTRODUCTION 1.1 1.2 1.3 1.4 Following discussions held with the Transmission System Operators (TSOs) in Ireland
More informationSummary of Studies on Rate of Change of Frequency events on the All-Island System
Summary of Studies on Rate of Change of Frequency events on the All-Island System August 212 Authored by: Salim Temtem & Karen Creighton Checked by: David Cashman & Raymond Skillen Approved by: Jonathan
More informationALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008
ALL ISLAND GRID STUDY STUDY OVERVIEW January 2008 1 Study Overview The All Island Grid Study is the first comprehensive assessment of the ability of the electrical power system and, as part of that, the
More informationBy 22 nd June 2018
By Email 22 nd June 2018 Joint Office of Gas Transporters Radcliffe House Blenheim Court Warwick Road Solihull B91 2AA Sent by email to: enquires@gasgovernance.co.uk Representation - UNC Modification 0621,
More informationDate of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017
Market Participant Comments and AESO Replies Matrix Proposed Amended Section 304.3, Wind and Solar Power Ramp Up Management ( amended Section 304.3 ) Date of Request for Comment: April 7, 2017 Period of
More informationSystem Services Industry Forum. 12 October 2017
System Services Industry Forum 12 October 2017 Agenda Topic Time Speaker Registration (Tea & Coffee) 09.30 Introduction 10.00 Ian Connaughton Regulatory Authority Update 10.15 CRU/URegNI Regulated Tariffs
More informationPerformance Monitoring Workshop. 6 th June Belfast 11 th June Dublin
Performance Monitoring Workshop 6 th June 2013 - Belfast 11 th June 2013 - Dublin Opening Remarks Anne Trotter # Topic Time Presenter Registeration 10:00-1 Opening Remarks 10:15 Anne Trotter (Chair) 2
More informationIWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015
IWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015 By e-mail to: ress@dcenr.gov.ie Introduction IWEA welcomes the opportunity to respond to the
More informationIntermittent power generation: Market implications. IEEE Workshop. Bern, April 28 th 2011
Intermittent power generation: Market implications IEEE Workshop Bern, April 28 th 2011 Agenda 1. Introduction 2. Some issues on the power system level 3. Other issues on the power plant level 4. Conclusion
More informationBalancing Market Principles Statement
Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Version 1.0 8 September 2017 Version Control Version No. Date Notes 1.0
More informationSection 3 Firm Access Quantities and Associated Transmission Reinforcements
GATE 3 FREQUENTLY ASKED QUESTIONS Latest Update May 2013 Section 3 Firm Access Quantities and Associated Transmission Reinforcements 1. What does the term Firm Access Quantity or FAQ mean? 2. I own or
More informationAlternative Connection Application and Offer Process Proposal
Alternative Connection Application and Offer Process Proposal Consultation Paper 4 March 2016 Table of Contents 1. Executive Summary... 5 2. Introduction... 7 2.1 Purpose of this Paper... 7 2.2 Structure
More informationMarket Stabilisation Analysis: Enabling Investment in Established Low Carbon Electricity Generation
Click here to enter text. 21 April 2017 Market Stabilisation Analysis: Enabling Investment in Established Low Carbon Electricity Generation An Arup report for ScottishPower Renewables July 2017 21 April
More informationCUSC Amendment Proposal Form CAP: 162
CUSC Amendment Proposal Form CAP: 162 Title of Amendment Proposal: Transmission Access - Entry Overrun Description of the Proposed Amendment (mandatory by proposer): Creation of a commercial mechanism
More information28/09/16 1. Challenges for wind energy projects in. World Wind Energy Association. Legal Working Group. Eoin Cassidy. Ireland. Mason Hayes & Curran
Challenges for wind energy projects in Ireland World Wind Energy Association Legal Working Group Eoin Cassidy Partner Mason Hayes & Curran 28/09/16 1 Wind Energy Positives Ireland In July 2016 there are
More informationInitial Modification Report No.39. Transfer of Exit Capacity between Northern Ireland Exit Points to permit Secondary Trading of Exit Capacity
Initial Modification Report No.39 Transfer of Exit Capacity between Northern Ireland Exit Points to permit Secondary Trading of Exit Capacity 30 th September 2016 Please find below Initial Modification
More informationRegulatory Approach to Maintaining Local Security of Supply in Electricity
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Regulatory Approach to Maintaining Local Security of Supply in Electricity Information Paper Reference: CRU17346 Date Published: 18/12/2017
More informationDS3 System Services Project Plan Detailed Design and Implementation Phase
DS3 System Services Project Plan Detailed Design and Implementation Phase Dated: 20/5/2015 Executive Summary The System Services work stream within the DS3 Programme relates to the procurement of services
More informationQuick Guide to the I-SEM
Quick Guide to the I-SEM 1 Contents 1 BACKGROUND... 3 2 THE NEW MARKET THE I-SEM... 6 3 HOW I-SEM WORKS... 7 4 IMPACT ON CONSUMERS... 9 5 I-SEM KEY BENEFITS... 10 Glossary of Key Terms... 11 2 1 BACKGROUND
More informationFuture of Gas Entry Tariff Regime Draft Decision (CER/15/057)
19 th May 2015 Mr Colm Ó Gormáin Commission for Energy Regulation The Exchange Belgard Square North Tallaght Dublin 24 Dear Colm Re: Future of Gas Entry Tariff Regime Draft Decision (CER/15/057) I am writing
More informationTémoignage de Mme Judy W. Chang de The Brattle Group sur la politique d'ajouts au réseau de transport
Demande R--0 Témoignage de Mme Judy W. Chang de The Brattle Group sur la politique d'ajouts au réseau de transport Original : 0-0-0 HQT-, Document En liasse Policy on Network Upgrades Direct Testimony
More informationJLL Energy & Infrastructure Advisory. Corporate PPAs: The Devil s In The Detail
JLL Energy & Infrastructure Advisory Corporate PPAs: The Devil s In The Detail Description A volatile energy market and fluctuating wholesale power prices make the planning of future energy expenditure
More informationConsultation Paper Contents Introduction Network Capacity and Operational Capability... 6
CONSULTATION ON CONNECTING FURTHER GENERATION I N NORTHERN IRELAND CONSULTATION PAPER 31 st January 2018 1. CONTENTS Consultation Paper... 1 1. Contents... 2 2. Introduction... 4 3. Network Capacity and
More informationPass Through Costs for Business Electricity Customers from 1st October 2017
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Pass Through Costs for Business Electricity Customers from 1st October 2017 Information Paper Reference: CRU 18083 Date Published:
More informationRe: Proposed Decision on Electricity Network Connection Policy CER 09/072
John Orme Electricity Distribution Commission for Energy Regulation The Exchange Belgard Square North Tallaght Dublin 24 Friday, 15 May 2009 Re: Proposed Decision on Electricity Network Connection Policy
More informationI-SEM Testing Tariff High Level Options Consultation
I-SEM Testing Tariff High Level Options Consultation 02 June 2017 Version 1.0 EXECUTIVE SUMMARY Testing Tariffs are currently applied to Units Under Test (UUT) in the Single Electricity Market (SEM) on
More informationReporting and Incentives under Price Review 4
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Reporting and Incentives under Price Review 4 Decision PR4 Reporting & Incentives Decision Reference: CER/18/087 Date Published: 10/05/2018
More informationRegional Impact of Renewables: ERCOT
Regional Impact of Renewables: ERCOT Kenan Ögelman VP, Commercial Operations, ERCOT February 1, 2018 The ERCOT Region The interconnected electrical system serving most of Texas, with limited external connections
More informationDS3: RoCoF Workstream Plan 2015
DS3: RoCoF Workstream Plan 2015 EirGrid and SONI, 2015 Page 1 CONTEXT The Facilitation of Renewables report published in 2010 indicated that one of the key limitations to increasing the real time penetration
More informationDay Ahead Market Enhancements. Issue Paper/Straw Proposal
Day Ahead Market Enhancements February 28, 2018 Intentionally left blank CAISO/MDP/D.Tretheway & M.Poage Page 2 February 28, 2018 Day Ahead Market Enhancements Issue Paper & Straw Proposal Table of Contents
More informationREPORT ON CONSULTATION ON DRAFT TRANSMISSION DEVELOPMENT PLAN
REPORT ON CONSULTATION ON DRAFT TRANSMISSION DEVELOPMENT PLAN 2016-2026 Table of Contents Abbreviations... 3 Glossary... 4 Introduction... 5 Description of Consultation Process... 5 Purpose of the Transmission
More informationEnsuring a Secure, Reliable and Efficient Power System in a Changing Environment
Ensuring a Secure, Reliable and Efficient Power System in a Changing Environment June 2011 KEY MESSAGES The power system of Ireland and Northern Ireland is changing. The combined system will have more
More informationRepresentation - Draft Modification Report 0541A/B
Representation - Draft Modification Report 0541A/B Removal of uncontrollable UNC charges at ASEPs which include subterminals operating on a 06:00-06:00 Gas Day Responses invited by: 5pm 11 April 2016 Representative:
More informationAbout Energy UK. Introduction
REC 34-15 Energy UK response to DG Comp investigation of Investment Contract (early Contract for Difference) for Lynemouth power station biomass conversion 10 May 2015 About Energy UK Energy UK is the
More informationConsultation on Connecting Further Generation in Northern Ireland. Call for Evidence
Consultation on Connecting Further Generation in Northern Ireland Call for Evidence 12 Table of Contents 1 Executive Summary... 3 2 Introduction... 6 2.1 Purpose of this Paper... 6 3 Alternative Connection
More informationMaintaining Baseload Generation Capacity
Maintaining Baseload Generation Capacity Frank A. Wolak Director, Program on Energy Sustainable Development Professor, Department of Economics Stanford University wolak@stanford.edu http://www.stanford.edu/~wolak
More informationJoint TSO/DSO Group Processing Approach Pricing Principles Guidelines
Joint TSO/DSO Group Processing Approach Pricing Principles Guidelines Published: 27/02/2007 Table of Contents 1 Introduction...3 2 Connection Method Principles...5 3 Connection Charging Principles...8
More informationBalancing Market Principles Statement
Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Version 2.0 11 th April 2018 Version Control Version No. Date Notes 1.0
More informationDS3: Voltage Control Workstream
DS3: Voltage Control Workstream EirGrid and SONI, 2011 Page 1 BACKGROUND The system voltage is determined by the balance of reactive power production and absorption. Generators have traditionally been
More informationAlternative Connection Application and Offer Process Proposal
Alternative Connection Application and Offer Process Proposal Decision Paper 31 May 2016 Table of Contents 1. Executive Summary... 4 2. Introduction... 7 2.1 Purpose of the Paper... 7 2.2 Structure of
More informationtowards2030-dialogue Electricity markets and renewable energy
towards2030-dialogue Electricity markets and renewable energy Based on work by Arthur Henriot and Jean-Michel Glachant Hugo Gil Research Fellow Renewable Energy towards2030-dialogue Stakeholder dialogue
More informationBT s response to Ofcom consultation document. Price Rises in Fixed Term Contracts
BT s response to Ofcom consultation document Price Rises in Fixed Term Contracts 14 March 2013 1 Executive Summary We welcome the opportunity to comment on this consultation on Price Rises in Fixed Term
More informationAnnual Renewable Energy Constraint and Curtailment Report 2017
Annual Renewable Energy Constraint and Curtailment Report 2017 01/06/2018 Contents Executive Summary... 4 1 Introduction... 7 1.1 Context... 7 1.2 Reasons for Dispatch-Down... 7 1.3 Reporting Methodology...
More informationAnnual Renewable Energy Constraint and Curtailment Report 2016
Annual Renewable Energy Constraint and Curtailment Report 2016 07/04/2017 Contents Executive Summary... 3 1 Introduction... 5 1.1 Context... 5 1.2 Reasons for Dispatch-Down... 5 1.3 Reporting Methodology...
More informationRate of Change of Frequency (RoCoF) Project Quarterly Report for Q3 2015
Rate of Change of Frequency (RoCoF) Project Quarterly Report for Q3 2015 DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Information Note CER/15/257 30 th October 2015 mvencius@cer.ie The Commission
More informationDay Ahead Market Enhancements. Revised Straw Proposal
Day Ahead Market Enhancements April 11, 2018 Intentionally left blank CAISO/MDP/D.Tretheway & M.Poage Page 2 April 11, 2018 Day Ahead Market Enhancements 1. Purpose... 4 1.1. Changes from Issue Paper/Straw
More informationConsultation on Competitive CfD Allocation Response from the Renewable Energy Association
Consultation on Competitive CfD Allocation Response from the Renewable Energy Association The REA represents a wide variety of organisations involved in renewable energy in the UK, including generators,
More informationDispatching Variable Generation Resources
Dispatching Variable Generation Resources A Discussion Paper for Stakeholder Engagement 91 (Renewable Integration) Table of Contents Introduction... 3 IESO Dispatch Processes... 5 Registration... 5 Dispatch
More informationEngineering, Economics and Regulation of the Electric Power Sector TERM PAPERS
Engineering, Economics and Regulation of the Electric Power Sector Spring term 2010 Instructor: Ignacio J. Pérez-Arriaga Course number: ESD.934, 6.974 TERM PAPERS Logistics Papers can be prepared individually
More informationSystem Operational Costs Reduction with Non-Conventional Reactive Power Sources.
2014 3rd International Conference on Informatics, Environment, Energy and Applications IPCBEE vol.66 (2014) (2014) IACSIT Press, Singapore DOI: 10.7763/IPCBEE. 2014. V66. 24 System Operational Costs Reduction
More informationCapacity Performance FAQ Response
PJM Interconnection September 15, 2014 This page is intentionally left blank. PJM 2014 www.pjm.com 2 P age Contents FAQ Response Introduction... 4 Capacity Products... 4 Methodology for Establishing Maximum
More informationModelling Transitions to Robust High-VRE Systems
Modelling Transitions to Robust High-VRE Systems Colin Silvester, Christopher Bates and Arjun Chohan Digital Engineering Solutions Uniper Nottingham, UK Colin.Silvester@uniper.energy Abstract Uniper is
More informationCalculation of Demand Curve Parameters
Calculation of Demand Curve Parameters Rationale 4.1 Resource adequacy standard 4.1.1 The resource adequacy standard announced by the Government of Alberta prescribes a minimum level of reliability as
More informationSmart Grids, New Downstream & the New Deal for EU Electricity Consumers
Smart Grids, New Downstream & the New Deal for EU Electricity Consumers Pavla Mandátová, Advisor Retail Markets, EURELECTRIC European Power Generation Summit Prague, 27 th November 2015 EURELECTRIC represents
More informationUNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF NATIONAL HYDROPOWER ASSOCIATION
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Electric Storage Participation in Regions ) with Wholesale Electric Markets ) Docket No. AD16-20-000 COMMENTS OF NATIONAL HYDROPOWER ASSOCIATION
More informationCONTRACTUAL AND REGULATORY REFORM WORKSTREAM. RDG vision for the charges and incentives regime in the long run
CONTRACTUAL AND REGULATORY REFORM WORKSTREAM RDG vision for the charges and incentives regime in the long run Published December 2014 What is the Rail Delivery Group? The Rail Delivery Group (RDG) seeks
More informationIMPROVING THE OUTCOME AND DELIVERY INCENTIVE REGIME. A Water 2020 paper by Northumbrian Water
IMPROVING THE OUTCOME AND DELIVERY INCENTIVE REGIME A Water 2020 paper by Northumbrian Water 1 Introduction The concept of Outcomes, Performance Commitments (PCs) and Outcome Delivery Incentives (ODIs)
More informationPrimary control - description of main technical and design characteristics
Primary control - description of main technical and design characteristics Summary The purpose of this note is to give enough clarification on the needed requirements a market player has to respect to
More informationRate of Change of Frequency (RoCoF) Project Quarterly Report for Q4 2015
Rate of Change of Frequency (RoCoF) Project Quarterly Report for Q4 2015 DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Information Note CER/16/006 19 th January 2016 mvencius@cer.ie The Commission
More informationAnalysing the Value of Pumped Storage in the 2020 Irish Power System. Aidan Cummins, Luke Dillon
Analysing the Value of Pumped Storage in the 2020 Irish Power System Aidan Cummins, Luke Dillon Department of Civil & Environmental Engineering BE (Energy Engineering) Module NE4020 Final Report Analysing
More informationRate of Change of Frequency (ROCOF) Review of TSO and Generator Submissions Final Report
Rate of Change of Frequency (ROCOF) Review of TSO and Generator Submissions Final Report PPA Energy 1 Frederick Sanger Road Surrey Research Park Guildford, Surrey GU2 7YD, UK www.ppaenergy.co.uk Tel: +44
More informationCAN YOU RELY ON A RELIABILITY OPTION?
CAN YOU RELY ON A RELIABILITY OPTION? Andy Kelly National Power Summit, February 2017 OVERVIEW OF PRESENTATION TOPICS New capacity mechanism is complex but aim today to focus on some key topics RO price
More informationBrexit: implications for the energy market
Agenda Advancing economics in business Brexit: implications for the energy market The outcome of the UK s EU referendum on 23 June 2016 had an immediate effect on the financial markets in the EU and beyond.
More informationELEXON response to National Grid s consultation of its System Needs and Product Strategy 18 July 2017
ELEXON response to National Grid s consultation of its System Needs and Product Strategy 18 July 2017 ELEXON sent the following responses to National Grid in relation to its System Needs and Product Strategy
More informationNon-BM Balancing Services Volumes and Expenditure
Non-BM Balancing Services Volumes and Expenditure Table of Contents Background... 1 Summary of Total Non-BM Service Provision... 2 Total Ancillary Services Expenditure... 2 Frequency Response... 3 Dynamic
More informationExploring how the ESO could be funded in RIIO-2
Exploring how the ESO could be funded in RIIO-2 15 th October 2018 Exploring how the ESO could be funded in RIIO-2 0 Executive Summary From April 2019 the Electricity System Operator (ESO) will be a legally
More informationBoard Staff Discussion Paper
Ontario Energy Board Board Staff Discussion Paper on Issues Related to the Connection of Micro-Embedded Generation Facilities EB-2012-0246 December 20, 2012 - 2 - INTRODUCTION Prior to the introduction
More informationAncillary Service. the WEM System Management. June 2018
Ancillary Service Report for the WEM 2018-19 June 2018 System Management Important notice PURPOSE AEMO publishes the Wholesale Electricity Market Ancillary Services report under clause 3.11.13 of the Wholesale
More informationIntegration of Renewable Energy Sources in the Electricity System - Grid Issues -
Integration of Renewable Energy Sources in the Electricity System - Grid Issues - Brussels, 30 March 2005 Background At European and national level mid-term plans exist to increase the share of electricity
More informationORR consultation on on-rail competition: Options for change in open access Network Rail s response
Peter Swattridge Head of Regulatory Economics Network Rail Kings Place, 90 York Way London, N1 9AG To: Philip Wilcox Office of Rail Regulation One Kemble Street London, WC2B 4AN 13 August 2013 Dear Philip,
More informationBalancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements
Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements CONSULTATION VERSION 7 April 2017 IMPORTANT INFORMATION This Balancing
More informationElectricity Market Design Principles
Electricity Market Design Principles Identifying long-term market design principles to support a sustainable energy future for Australia Executive Summary 19 April 2018 KPMG.com.au Important Notice If
More informationSummary of Impacts of Environmental Regulations in the ERCOT Region. Warren Lasher Director, System Planning
Summary of Impacts of Environmental Regulations in the ERCOT Region Warren Lasher Director, System Planning April 8, 2015 Study Purpose and Background Several new regulations have been proposed or finalized
More informationRenewable Technologies in the Future NEM
Renewable Technologies in the Future NEM 100% Renewables for Australia? Dr Jenny Riesz Australian Power Institute (API) Summer School Wednesday 24 th February 2016 Who am I? Overview 100% Renewables: Worth
More informationDS3: Grid Code Work Stream 2015
DS3: Grid Code Work Stream 2015 CONTEXT The purpose of the Grid Codes in Ireland and Northern Ireland is to set the (minimum) standards relating to the operation and use of the Transmission System and
More information