CASE STUDY: TGF PROJECT 2016 / 2017 TURKMENISTAN

Size: px
Start display at page:

Download "CASE STUDY: TGF PROJECT 2016 / 2017 TURKMENISTAN"

Transcription

1 CASE STUDY: TGF PROJECT 2016 / 2017 TURKMENISTAN Collection from FOB European origins Direct FTL, LTL, rail and Airfreight shipments Transhipment operations River transportation up to Caspian port Discharging to Caspian port & Storage Re-loading on trailers & barges Shuttle barge operations : Turkmenbashi - Garabogaz Road permits, obstacle removals, civil works Name : Garabogaz Fertilizer Plant Project Site location : Garabogaz, Turkmenistan Volume : 168,582 CBM River vessels utilized : 37 Heaviest unit 478 mt along with 19 units over 100 mt 9 Shuttle barge transportation between Turkmenbashi - Garabogaz 10

2 CASE STUDY: GTG PROJECT 2016 / 2017 TURKMENISTAN Collection from FAS worldwide origins Direct FTL, LTL, rail and Airfreight shipments Ocean carriage up to TS ports Transhipment operations River transportation up to Caspian port Discharging to Caspian port & Storage Re-loading on trailers & transit clearance Road permits, obstacle removals, civil works Lifting & Erection works Import customs clearance at final destination Name : Gas to Gasoline Project Site location : Ovadandepe, Turkmenistan Volume : 154,110 CBM Axles utilized : 210 hydraulic Axle movements : 1,280 movements River vessels utilized : 36 Overland distance: 645 km s Heaviest unit 317 mt along with 23 units over 100 mt 77 OOG/HL units Ocean, river, air, truck transportation from 27 different origins Project is the largest gas to gasoline plant ever built in the world! 11

3 CASE STUDY: KARBALA PROJECT 2016 / 2017 IRAQ Transportation from Umm Qasr port up to final destination Storage Civil works & by-pass constructions Bridge and flyover constructions Various engineering works Name : Karbala Refinery Site location : Karbala, Iraq Volume : 200,000 CBM Axles utilized : 180 hydraulic & 52 SPMT axles 6 x 665 mt, 3 x 720 mt bullets Total 540 km s overland distance Heaviest ever cargo to be transported in Iraq! Extensive road improvement works: Samawah Tubular Bridge Construction (150 m ) Kofa Cement Factory Ramp (400 m L) & flyover bridge (12m) construction. 350 km of road width extension (4 m extension) done 16 x bypass road construction avoiding the culverts. 12

4 CASE STUDY: KIRIKKALE CCPP PROJECT 2016 TURKEY Discharging to Samsun Port Storage Re-loading on trailers Equipment installation with gantry crane Name : Samsung Kirikkale CCPP Site location : Kirikkale, Yahsiyan, Turkey Volume : 300,000 CBM Axles utilized : 200 SPMT Axle movements : 820 movements Overland distance : 360 km s Heaviest Unit Width

5 CASE STUDY: ZEYNELBEY PROJECT 2016 TURKEY - Historical Structure Relocation - The ancient town of Hasankeyf is located in southeastern Turkey The Zeynel Bey Tomb which is located in Hasankeyf, commemorates the warrior son of a Turkish ruler, who died in a battle against the Ottomans six centuries ago. The burial chamber has long disappeared but the tomb, made from cut stones, is architecturally unique in Turkey and an example of central Asian influences The discussions of possibility to relocate the structure began three-and-a-half years ago after scientists warned that the structure was at risk of being submerged with the construction of the Ilısu Dam In the conclusion of long studies and discussions, CJ-ICM Engineers and Crew have rolled up their sleeves to take important part of saving the historic Zeynel Bey Tomb The 1,100 Zeynel Bey Monument was transported for 2km by using 48 Axles SPMT in May,

6 CASE STUDY: FORMULA1 GRAND PRIX 2016 AZERBAIJAN Ocean freight Discharging at Poti Port On-carriage to Baku by rail Customs clearance Re-loading on trailers Transportation to site & offloading Post race logistics (sea, road & air freight) Name : Formula-1 Grand Prix of Europe Site location : Baku, Azerbaijan Volume : 2,400 MT 14 Charter flights (B747) Over 1,550 mt of airfreight Over 550 mt of containerized cargo incl. block train from Poti to Baku 160 TEU Over 200 FTL local deliveries Over 300 of int l road freight shipments about 42 FTL 15

7 CASE STUDY: UGCC PROJECT 2014 UZBEKISTAN Origin Transhipment Unloading Storing Reloading Civil Works Onshore Haulage Loading at origins & transshipment to river vessels River vessel transportation & various HL engineering works Discharging to Caspian port & Storage Re-loading on trailers & transit clearance Road permits, obstacle removals, civil works Name : UGCC Ethylene Plant Project Site location : Akchalak, Uzbekistan Volume : 98,240 CBM Axles utilized : 258 hydraulic Axle movements : 1,082 movements River vessels utilized : 13 Overland distance : 827 km s 126 OOG/HL units 16 major bypass constructions Heaviest Unit Widest Unit width width

8 CASE STUDY: TORE PROJECT 2013 TURMENISTAN Transshipment to river vessels River vessel transportation Various HL engineering works Name : Turkmenbashi Oil Refineries Site location : Turkmenbashi, Turkmenistan Volume : 98,240 CBM CHALLENGE Passing the gas-line pipes on ground and railway with hl unit SOLUTION CJ-ICM designed & built a fly-over bridge to eliminate the challenge. Discharging to Caspian port Re-loading on trailers & transit clearance Road permits, obstacle removals, civil works Heaviest Unit Highest Unit width 9, width

9 CASE STUDY: YOLOTEN PROJECT 2010/2013 TURKMENISTAN Collection from FOB & EX-works worldwide origins Pre-carriage up to FOB load ports, airports Direct FTL, LTL, rail and Airfreight shipments Ocean carriage up to TS ports Transhipment operations River transportation up to Caspian port Discharging to Caspian port & Storage Re-loading on trailers & transit clearance Road permits, obstacle removals, civil works Import customs clearance at final destination Name : South Yoloten Gas Development Project Site location : Mary, Yoloten, Turkmenistan Volume : ~700,000 CBM 37 Heaviest Unit 5.6 Width Axles utilized : 270 hydraulic Axle movements : 2,068 movements River vessels utilized : OOG/HL units Transported 100 KM (8,614 pieces) of 56 coated pipes from FOB Italy to site with 24 ocean & 44 river vessels in 143 days 18

10 CASE STUDY: VARIOUS HL TRANSPORTATION PROJECTS 19