LHC Point 5: UJ56, RR53/57, UPS54/56 and Adjacent Areas

Size: px
Start display at page:

Download "LHC Point 5: UJ56, RR53/57, UPS54/56 and Adjacent Areas"

Transcription

1 CERN CH-1211 Geneva 23 Switzerland the Large Hadron Collider project LHC-R2E-PR-P5-v0.1 Document Prepared By R2E TaskForce EDMS Document No. xxxxxx Date: asss R2E Point-Review Report LHC Point 5: UJ56, RR53/57, UPS54/56 and Adjacent Areas to be finilazed Abstract Prepared by : M. Brugger, D. Kramer, A. L. Perrot, S. Roesler, G. Spiezia, A. Vergara, S. Weisz, T. Wijnands to be added Checked by : R2E Taskforce to be added Approval group members: to be added

2 Page 2 of 11 History of Changes Rev. No. Date Pages Description of Changes 1.1-draft All Draft structure

3 Page 3 of 11 Table of Contents MISSING SCOPE AREA LAYOUT EQUIPMENT OVERVIEW, RACK AND MONITOR LOCATIONS EQUIPMENT CLASSES AND OWNERS RACK LOCATIONS MONITOR LOCATIONS RAMSES RADMONS EXPECTED RADIATION LEVELS OVERVIEW AND ASSUMPTIONS OF EXISING SIMULATIONS RESCALING TO 2009/10 OPERATION FUTURE SIMULATION REQUIREMENTS RISK OF EQUIPMENT FAILURE DETAILED EQUIPMENT ANALYSIS AND INTERDEPENDENCIES FAILURE CONSEQUENCES AND SAFETY ISSUES RADIATION TEST REQUIREMENTS INTEGRATION CONSTRAINTS SHIELDING RELOCATION IMPACT AND CONCERNS FOR 2009/10 OPERATION FOR LATER OPERATION RECOMENDATIONS REFERENCES... 11

4 Page 4 of 11

5 Page 5 of 11 MISSING [M. Brugger] - contributions as listed below 1. SCOPE [M. Brugger] Radiation levels expected around CMS adjacent areas and more precisely the integrated flux of high-energy hadrons (multi-mev range) pose a significant risk to all electronics not specifically designed or tested for such radiation levels. This document summarizes the respective point iteration as carried out through the R2E study group [1] for the LHC Point 5 and shall serve as basis for all present and future actions. After a general description of the areas and an overview of the equipment and radiation monitoring inventory, reviewed radiation levels are presented and projected to both early as well as later operational conditions. Based on a detailed equipment analysis as performed through the RadWG [2] equipment sensitivities and possible failure rates are deducted, as well as inter-dependencies identified. Possible safety issues, resulting operational constraints as well as the need of radiation test requirements are summarized. Furhtermore, general integration options and constraints are investigated with respect to shielding of areas, as well as possible relocation options. The impact on early (2009/10) and later operation is summarized and respective recommendations are given. For doumentation, the R2E document library [3] has been updated with all P5 related documents. Available simulation results and respective reports were added for all CMS adjacent areas (UJ56, RR53/57, UPS54/56). All provided informations as aquired during the preparation of the review (pictures, documents, comments, layout drawings, rack locations, ) are inclued and available in the above database. It shall be noted, that a careful cross-check of some of the included documents and respective onstraints is constantly required and the reader is encouraged to provide comments to the authors or the R2E study group. 2. AREA LAYOUT [A. L. Perrot] 3. EQUIPMENT OVERVIEW, RACK AND MONITOR LOCATIONS 3.1 EQUIPMENT CLASSES AND OWNERS Table X lists the equipment installed in the underground areas around Point 5, namely RR53, UJ56 and RR57. Table x_ List of equipment and owners for RR53, UJ56 and RR57. Equipment Class Owner Current Location Power converters (with FGCs) V. Montabonnet H. Thiesen RR53-Level 0 RR53-Level 1 UJ56-Level 1 RR57-Level 0 Energy extraction/quench protection system R. Denz RR53-Level 1 UJ56-Level 1

6 Page 6 of 11 Current leads heating system A. Ballarino RR53-Level 1 Power Interlock Controller M. Zerlauth RR53-Level 1 UJ56-Level 1 Cryogenics controls S. Claudet RR53-Level 1 UJ56-Level 1 Beam Instrumentation R. Jones RR53-Level 1 UJ56-Level 1 Fire detection R. Nunes UJ56-Level 0 GSM F. Chapron UJ56-Level 0 Ethernet E. Sallaz UJ56-Level 1 Optical Fibers D. Ricci UJ56-Level 1 Timing R.Chery UJ56-Level 1 Front End G. Surback UJ56-Level 1 Survey A. Marin UJ56-Level 1 Access C. Delamare UJ56-Level 1 Collimator electronics A. Masi UJ56-Level RACK LOCATIONS In figures x.1 and x.2, the location of racks in RR53 and UJ56 is illustrated. The installations in RR57 are identical to those of RR53. Summarizing, the racks in RR53 include: - Power converters and transformers on the ground floor; - On the first floor: o 13 ka switches o Power converters (PC) o Energy extraction racks (EE) o Racks for spare components o DFB Current Lead temperature controls (CL) o Power interlock controller (PIC) o Quench protection system (QPS) o Cryogenics controls (Cryo) o Beam instrumentation (BI)

7 Page 7 of 11 RR53 _ Ground level RR53 _ First floor Figure x.1 _ Electronics installations in RR53. Concerning the UJ56, only GSM and Fire detection racks are located in the ground floor safe room. For the first floor, the installed racks include: o Power converters (PC) o Beam Instrumentation (BI) o Survey electronics o Access control racks o Cryogenics controls (Cryo) o Optical fibers o Ethernet o Timing o Front end o Quench protection system (QPS) o Collimation controls

8 Page 8 of 11 UJ56 _ Ground level RR53 _ First floor Figure x.1 _ Electronics installations in UJ MONITOR LOCATIONS RAMSES [S. Roesler] RADMONS [D. Kramer]

9 Page 9 of EXPECTED RADIATION LEVELS [M. Brugger] 4.1 OVERVIEW AND ASSUMPTIONS OF EXISING SIMULATIONS 4.2 RESCALING TO 2009/10 OPERATION 4.3 FUTURE SIMULATION REQUIREMENTS 5. RISK OF EQUIPMENT FAILURE [T. WIjnands, D. Kramer, G. Spiezia] 5.1 DETAILED EQUIPMENT ANALYSIS AND INTERDEPENDENCIES 5.2 FAILURE CONSEQUENCES AND SAFETY ISSUES 5.3 RADIATION TEST REQUIREMENTS 6. INTEGRATION CONSTRAINTS [A. L. Perrot, S. Weisz] 6.1 SHIELDING 6.2 RELOCATION 7. IMPACT AND CONCERNS [SUMMARY draft by M. Brugger, iterations all] 7.1 FOR 2009/10 OPERATION

10 Page 10 of FOR LATER OPERATION 8. RECOMENDATIONS [SUMMARY draft by M. Brugger, iterations all]

11 Page 11 of REFERENCES [1] Radiation To Electronics (R2E) TaskForce [2] Radiation Working Group (RadWG) [3]