QUALITY ASSURANCE FOR SHRP2 R06C TECHNOLOGIES

Size: px
Start display at page:

Download "QUALITY ASSURANCE FOR SHRP2 R06C TECHNOLOGIES"

Transcription

1 QUALITY ASSURANCE FOR SHRP2 R06C TECHNOLOGIES JULY 31, 2018 DENNIS DVORAK FHWA RESOURCE CENTER

2 Material Process Sampling Testing Composite Variability

3 States Using PWL for Asphalt Pavement Pavement AK HI WA OR NV CA ID UT AZ MT WY CO NM ND SD NE KS OK MN WI IA MO AR IL MS MI OH IN KY TN AL GA PA WV VA NC SC VT NY ME CT NJ DE MD DC NH MA RI Key: TX LA Use PWL for Asphalt Pavement FL Do not use PWL Source: 2014 Update FHWA QA Assessment PR 3

4 PERCENT WITHIN LIMITS EFFICIENTLY CAPTURES MEAN AND STANDARD DEVIATION IN ONE QUALITY MEASURE X - mean s - standard deviation -3s -2s -1s X 1s 2s 3s

5 PERCENT WITHIN LIMITS 90 PWL 90 PWL

6 STEPS FOR ESTIMATING PWL 1. OBTAIN RANDOM SAMPLES 2. COMPUTE MEAN ( X ) STANDARD DEVIATION (S) 3. COMPUTE QUALITY INDEX (Q) 4. CONVERT Q TO ESTIMATED PWL

7 3. COMPUTE QUALITY INDEX Q U = USL - X s Q L = X LSL s LSL USL -3s -2s -s X s 2s 3s

8 OPTIMAL SAMPLE SIZE 18 n=3 Variability of Est. PWLs n=4 n=15 PWL = Number of Samples

9 PERCENT CONFORMING FOR ATTRIBUTES ACCEPTANCE PLANS, THE PERCENTAGE OF UNITS HAVING NO DEPARTURE OF AN ATTRIBUTE FROM ITS INTENDED LEVEL. *E-C173 TRB Glossary of Quality Assurance Terms 90 PWL 90 PC

10 AASHTO PAY EQUATION PF = * PWL PF = * PC *AASHTO R9-05 (2018) Standard Practice for Acceptance Sampling Plans for Highway Construction

11 1 23 CFR 637 APPROPRIATE PAYMENT CONTRACTOR FRAUD AA IA PQ/C DR QC LA/Q

12 32 States use Contractor test results in the Acceptance Decision AK HI WA OR NV CA ID UT AZ MT WY CO NM ND SD NE KS OK MN WI IA MO AR IL MS MI OH IN KY TN AL GA PA WV VA NC SC VT NY ME CT NJ DE MD DC NH MA RI TX LA Key: FL Use Contractor test results Use State Tests for Acceptance Source: 2014 Update FHWA QA Assessment PR 12

13 Code of Federal Regulations: 23 CFR 637 Subpart B - Quality Assurance Procedures for Construction Policy: Quality Assurance (Non-Regulatory Supplement to 23 CFR 637) July

14 23 CFR INDEPENDENT VERIFICATION QUALITY CONTROL SAMPLING AND TESTING RESULTS MAY BE USED AS PART OF THE ACCEPTANCE DECISION PROVIDED THAT THE QUALITY OF THE MATERIAL HAS BEEN VALIDATED BY THE VERIFICATION SAMPLING AND TESTING. THE VERIFICATION TESTING SHALL BE PERFORMED ON SAMPLES THAT ARE TAKEN INDEPENDENTLY OF THE QUALITY CONTROL SAMPLES. *TITLE 23 CODE OF FEDERAL REGULATIONS PART 637 SUBPART B QUALITY ASSURANCE PROCEDURES FOR CONSTRUCTION (23 CFR (A)(1)(II)(B)).

15 APPLICATION SURFACE DIELECTRIC PROFILING SYSTEM USING GROUND PENETRATING RADAR INTELLIGENT COMPACTION (IC) PAVER MOUNTED THERMAL PROFILING FEDERAL-AID FUNDS SHOULD NOT BE USED FOR PAY ADJUSTMENTS SINCE PAYMENT IS BASED ON CONTACTOR EQUIPMENT

16 QUALITY ASSURANCE PROGRAM Independent Assurance Dispute Resolution Agency Acceptance QA Program Contractor Quality Control Personnel Qualification Lab Qualification 16

17 QUALITY ASSURANCE PROGRAM CONTRACTOR QUALITY CONTROL (QC) MATERIALS SAMPLING & TESTING IF PART OF ACCEPTANCE DECISION INDEPENDENT OF AGENCY VERIFICATION QUALIFIED TECHNICIANS QUALIFIED LABORATORIES INDEPENDENT ASSURANCE EVALUATION Note: Contractor QC may be included if sampling & testing meets certain requirements [23 CFR (a)(1)(ii)].

18 QUALITY ASSURANCE PROGRAM AGENCY ACCEPTANCE VERIFICATION SAMPLING & TESTING QUALITY EVALUATION ACCEPTANCE & PAYMENT MAY INCLUDE CONTRACTOR TEST RESULTS IF VALIDATED Note: See 23 CFR (d) and (a)(1)(ii)(B) for specific requirements.

19 QUALITY ASSURANCE PROGRAM TECHNICIAN QUALIFICATION REQUIRED FOR ALL SAMPLING & TESTING IN ACCEPTANCE DECISION QUALIFICATION PROGRAMS STATE PROGRAMS REGIONAL PARTNERSHIPS NATIONAL PROGRAMS Note: Technician qualification requirement can be found at 23 CFR (b).

20 QUALITY ASSURANCE PROGRAM LABORATORY ACCREDITATION/QUALIFICATION [23 CFR (A)] 20 ACCREDITATION REQUIRED AGENCY CENTRAL LAB CONSULTANT DISPUTE RESOLUTION LABS CONSULTANT INDEPENDENT ASSURANCE LABS QUALIFICATION REQUIRED TESTING LABS USED IN ACCEPTANCE DECISION AGENCY VERIFICATION TESTING CONTRACTOR QC TESTING

21 QUALITY ASSURANCE PROGRAM INDEPENDENT ASSURANCE (IA) EVALUATE ALL ACCEPTANCE SAMPLING & TESTING SEPARATE FROM ACCEPTANCE TESTING TECHNICIAN PROCEDURE EVALUATION TESTING EQUIPMENT EVALUATION Note: See 23 CFR (a)(2) and (b) for specific requirements.

22 QUALITY ASSURANCE PROGRAM MATERIALS TESTING DISPUTE RESOLUTION REQUIRED WHEN CONTRACTOR DATA USED IN ACCEPTANCE DECISION DOCUMENTED PROCESS ADDRESS DISCREPANCIES AGENCY VERIFICATION TESTING CONTRACTOR QC Note: See 23 CFR (a)(1)(iii) and 23 CFR (a) for more information.

23 QUESTIONS