SQUEEZING MARGINS: REDUCING COSTS WHILE BALANCING RISKS. G.A. Bloemhof, J. Knijp. KEMA T&D Power, the Netherlands

Size: px
Start display at page:

Download "SQUEEZING MARGINS: REDUCING COSTS WHILE BALANCING RISKS. G.A. Bloemhof, J. Knijp. KEMA T&D Power, the Netherlands"

Transcription

1 SQUEEZING MARGINS: REDUCING COSTS WHILE BALANCING RISKS G.A. Bloemhof, J. Knijp KEMA T&D Power, the Netherlands Liberalising the energy market increased the awareness of transmission and distribution companies for optimising network activities and reducing costs. Network operators have to balance between performance, risks and costs. The traditional approach leads to sub-optimisation. When planning, adapting or operating existing power supply systems one can save by using the system and its components closer to their limits. Increased use of margins means: taking more risks. By the end of the 2 th century - especially in the liberalising countries - an increase in optimising the activities of electricity transmission and distribution companies became apparent. Former practices could be characterised by maximising performance (reliability/safety), intuitive cost approach and avoiding risks. The new ambitions demand customer-oriented performance and thus cost effectiveness, requiring integral cost methods and controlled risks. Major concerns of network operators are about asset management: reducing costs and postponing investments, while keeping up reliability and power quality. New methods and techniques like life cycle costing, risk management and performance management are introduced, as in the left figure. Measures resulting in cost savings can be classified according to different aspects: planning or operations system oriented or component oriented time versus capacity limit Classification of measures alone is not enough. Each measure effects different dimensions like cost, risk and length of life. Dimensions concern technical constraints, economic goals, reliability and power quality and environment. Using practical cases, the paper demonstrates how investments, reliability and technical constraints can be handled jointly in one integral decision process. The examples prove that by doing so savings can be realised. The right figure shows how to compare margins for different aspects. The paper shows that margins and risks are inherent multidisciplinary problems. Decreasing costs, trying to maintain quality, or improving quality with minimal expenses, demands a balance between all aspects. Making decisions, when different scenarios are possible, brings risks. Risk is both in uncertainties about the future and in incomplete data. Comparing disciplines means using weighing factors, using break-even analysis or sensitivity analyses. A uniform system comparing all the disciplines involved, achieving optimal solutions and reaching a balance between all constraints is presented. Relieving a limit through working closer to another is delicate. Tools are available, however a systematic and consistent approach is required to use the system to its edges. An integrated analysis allows avoiding or postponing costs. The examples prove that significant savings can thus be achieved. Maximum Customer oriented supply (Cost/benefit analyses) SC 5 PERFORMANCE -5-1 Rational (Lifecycle costing) COST RISK Avoiding Intuitive (Risk management) Controlled Changing network management, balancing performance, risk and costs System performance related to 5 dimensions

2 SQUEEZING MARGINS: REDUCING COSTS WHILE BALANCING RISKS G.A. Bloemhof, J. Knijp KEMA T&D Power, the Netherlands ABSTRACT Liberalising the energy market increased the awareness of transmission and distribution companies for optimising network activities and reducing costs. Network operators have to balance between performance, risks and costs. The traditional approach leads to sub-optimisation. When planning, adapting or operating existing power supply systems one can save by using the system and its components closer to their limits. Increased use of margins means: taking more risks. This paper handles topics like types of risks, tools and methods and the decision-making process. Using practical cases, the paper demonstrates how investments, reliability and technical constraints can be handled jointly in one integral decision process. The examples prove that by doing so savings can be realised. CHANGE IS THE NAME OF THE GAME By the end of the 2 th century - especially in the liberalising countries - an increase in optimising the activities of electricity transmission and distribution companies became apparent. Former practices could be characterised by maximising performance (reliability/safety), intuitive cost approach and avoiding risks. The new ambitions demand customer-oriented performance and thus cost effectiveness. That requires rational and integral cost methods and controlled risks. Figure 1 shows the shift in network management. In the liberalised market different parties are concerned. Shareholders demand certain levels of operating profits. Governmental regulators impose Rational (Lifecycle costing) Intuitive Figure 1 Maximum Customer oriented supply (Cost/benefit analyses) COST PERFORMANCE RISK Avoiding (Risk management) Controlled Changing network management, balancing performance, risk and costs limits on transmission and distribution tariffs. Customers demand high reliability and are assertive, and threat with claims when disturbances occur. Knijp and Van Doorn (4) explain his further. That is why the major concerns of the contemporary network operators are about asset management: reducing costs and postponing investments, while keeping up reliability and power quality standards. Therefore new methods and techniques like life cycle costing, risk management and performance management are introduced, as shown in figure 1. Cliteur and Wetzer (3) and Hafkamp and Schutters (5) elaborate on this. SAVING COSTS MEANS TAKING MORE RISK In the liberalising energy market, cost reduction is the most important topic. The cost reduction process starts with a bottleneck, when the margin has become zero. Then there are opportunities to increase use and postpone investments. Traditional solutions have to be re-evaluated critically. Making decisions, avoiding additional costs, induces substituting margins. Going away from one limit and increasing the margin to above zero involves reducing the margin for a non-critical constraint. Increased use of margins means taking more risks. Classification of cost saving measures Measures that can result in cost savings can be classified according to different aspects: planning or operations system oriented or component oriented time versus capacity limit Planning or operation. The distinction between measures in operations or measures taken in the planning stage, lies in the remaining time to the actual bottleneck. The closer the deadline, the less the degrees of freedom. If there is sufficient time, we can change the transmission capacity by changing the network topology using planning criteria. During operation the topology is fixed and transmission capacity can only be changed within the operational limits. Figure 2 illustrates the difference. An example of such difference is the use of dispersed generation, distinguishing location and operation. During planning location, point of network coupling, rating and even time of installation

3 criteria for planning network topology Figure 2 Planning stage transmission capacity Operation stage criteria for operation network topology transmission capacity Differences between utilisation in planning and in operation are free to choose. For an already installed unit only the generated power is free for an operator. System or component. Crossing system thresholds can be solved on component level as well as a system level. Each component has its own limits mostly determined by physical characteristics. Exceeding the limits of components can often be solved locally. For the system level however other criteria are valid. These criteria are influenced by all components together. A simple example is the maximum load of bundled cables in one bedding. Although criteria can clearly be distinguished in limits per component and limits for the system, this is not so easy for the measures to be taken. For example overloading of a cable can be solved in several ways: (1) by replacing with a heavier component, (2) by changing the environment of the cable, (3) by applying newer standards (uprating), (4) by placing redundant elements in the systems, (5) by rerouting the load or (6) by changing the demands on the system (e.g. dropping a N-1 criterion or revising a load forecast or risk level). Time versus limit. Figure 3 shows the margins in limit (e.g. capacity) and in time and the interchangeability. Usually components can be overloaded at the cost of a reduction of the remaining lifetime. This is a long term balance. A short term effect is for instance planning using dynamic load profiles leading to a higher maximum load, which is only temporarily allowed. Grotenhuis et al (7) present a detailed application. Time is also related to risk, how long does it take for the next bottleneck to appear, either at the (same) component level or for the system elsewhere? Which scenarios are most critical? How to make decisions? Classification of measures alone is not enough. Different measures have to be compared mutually, in particular regarding the expected effect. After all, a decision made in a consequent and unambiguous manner is needed. Therefore quantification is essential. Each measure effects different dimensions like cost, risk and length of life. Table 1 shows different disciplines involved in the decision making process. These disciplines are external, related to the stakeholders, to laws and to physics, outside the control of the planner or operator. All the internal limits, usually based on isolated worst case scenarios, can be influenced and are thus part of the decision process. This also implies integration of activities like planning, operation and maintenance, throughout all departments, such as generation, transmission, distribution and protection. A uniform system, comparing all the disciplines involved, is necessary to achieve optimal solutions and to reach a balance between all constraints. It is important to avoid sub-optimisation. A systematic and consistent approach is needed to use the system to its utter limits. TABLE 1 Disciplines involved when squeezing margins and reducing cost 1. Technical constraints, considering margins for the (partial) system (e.g. voltage drop), and individual components (e.g. loading) 2. Economic targets (maximum profit) and budgetary constraints for the company put limits to decisions. Investments and life-cycle costs have to be combined. 3. Reliability, both the availability of components and the reliability of supply to customers. Deterministic criteria, as the N-1, and probabilistic parameters are involved. 4. Supply quality, from customers viewpoint 5. Environmental issues PRACTICAL EXAMPLES limit increased use (of margin) The following two cases will illustrate the decision making process in bottleneck situations. Both examples are from actual studies for Dutch utilities. For each we give the case, the bottleneck, the solutions, the approach, the results and conclusions. planned usage and horizon extended life Case 1: cost versus performance Figure 3 Margins in time or capacity limit time The case and the bottleneck. This case involves a 6 kv MV distribution network serving a medium sized village in the Netherlands, with about 3.

4 customers. An annual load growth of 2% is foreseen. During the last 1 years the network operator installed components suitable for 1 kv, still operated on 6 kv. When a fault occurs in the MVfeeders the restoration process requires switching customers off, due to capacity constraints and voltage limits. Possible solutions and approach. The solutions analysed are several changes in the configuration on the 6 kv level. Changing the nominal voltage to 1 kv would enhance the capacity, but would also require additional investments. The current bottleneck situation was analysed by comparing 4 different scenarios as in table 2. The main question was the future system voltage to be used: continuing with 6 kv or changing to 1 kv. TABLE 2 Four future alternatives for case 1 Variant nr. Description 1 6 kv with modification in 2 6 kv modifications in 2 en 3 1 kv variant 1, parallel 4 1 kv variant 2, looped All alternatives were evaluated regarding: investments (equipment, labour, maintenance) network losses, valued and capitalised over the lifetime (planning horizon) of the system reliability (non delivered energy), only the mutual differences are calculated Voltage quality and environmental issues are not accounted for in this case. The technical constraints are: the loadflow, checking component capacities and voltage levels short circuit, checking fault conditions and restoration schemes the N-1 criterion for the MV feeders All solutions were dimensioned such that all constraints are fulfilled. Results and conclusion case 1. In figure 4 relates the main results, both the total costs and the (Non-Delivered Energy) are presented. There is no single optimal solution, since the cheapest and the most reliable solution are not the same. The 1 kv variants appear to be cheaper than all 6 kv variants. The choice between the cheapest and the best depends on the value of, a subject widely under discussion. A break-even analysis shows that the break-even value in this case is very high, about 4 EUR/kWh. Since realistic values in the discussion range between.4 and 4., the decision is obvious. Total Cost (x 1 Euro) kv variant 1 6 kv variant Non Delivered Energy (kwh) Figure 4 Results Case 1: Performance vs. Cost This is not a general conclusion. The decision depends on the configuration, and on parameters like interest rate, planning horizon, value of energy losses, etc. It does show however how different aspects can be combined, and even if not all the parameters are exactly known, one still can reach an unambiguous decision. Case 2: multiple constraints 1 kv variant 1 1 kv variant 2 Linear break-even The case and the bottleneck. This study was performed for a Dutch 5/1kV substation with a double busbar configuration as shown in figure 5. Both busbars are connected through a bus coupler, which is normally closed. The station feeds a distribution network made up of 11 km underground cable with about 4 customers. Ajodhia and Bloemhof (1) describe this case in more detail. Here only the main results are given. In the underlying network there is a large number of greenhouses with lots of dispersed generation. The abundance of dispersed generation has lead to a situation where very high short circuit currents could exist in the station. This could lead to a situation (S2 in table 3) where the limits of safe operation would be exceeded. Transformer I Figure 5 Closed breaker Open breaker Bus coupler Transformer II Closed disconnector Open disconnector Case II: initial configuration (Bus coupler Closed ) Bus I Bus II

5 TABLE 3 S S1 S2 S3 S4 A1 A2 Description of Situations and Actions Case history, no bottlenecks Reaching short circuit limit of busbar Exceeding short circuit limit of busbar Open the coupling breaker Situation after opening breaker Add telecontrol system Final situation after adding telecontrol Possible solutions and approach. The first solution proposed was based on the N-1 principle and consisted of adding an additional (stand by) transformer. This would lead to a reduction of the short circuit currents. Installing such an extra transformer however would require high investments while its utilisation would be very low. The network operator looked for more cost-effective solutions. In the second solution it was proposed to just open the coupling breaker (table 3: A1) between the two busbars so short circuit currents would be limited. Each bus bar is then fed through a single transformer. The loads have been distributed between the busbars. In this case there would not be a N-1 situation anymore, since a fault in the supply of one of the busbars or one of the transformers would lead to an outage. Maintaining the reliability level, expressed in expected Non-Delivered Energy (), was defined as an extra constraint. During the study a third option arose: adding telecontrol using the SCADA system (table 3: A2), enabling a major reduction in restoration times. For the second proposed solution it was not clear what the effect on reliability would be when the N-1 criterion was abandoned. Therefore a reliability study was performed using a probabilistic computer programme. Results case 2. A graphical overview of the results is given in figure 6. On the X-axis the number of outages for the average customer is presented in outages/year. The Y-axis gives the average outage duration. The hyperbolic curves are iso-lines where the product of outage duration and outage frequency is a constant, apart from some constants they are iso- curves. In situation S1 there are no constraints. Increasing dispersed generation leads to too high short circuit currents in the station. These damage the station, requiring a considerable restoration time (S2). Opening the breaker (A1, S3) cancels this adverse effect. As figure 6 shows the situation S3 is still not as good as in situation S1. Comparing the values of shows an increase of 31%. A second action (A2, adding telecontrol) brings the average Outage Duration 2, 15, 1, 5,, constant =1% 131% 2% 88% S1 S2 S3 S Failure rate Figure 6 Reliability results for case 2 outage duration for S4 to 8% of the level in S1. Telecontrol appears to be a very cost-effective measure. Compared with the initial situation the Non-Delivered Energy has been lowered, the average duration is shorter, while the frequency of interruption rose with only 9%. Overall, the quality of supply (the reliability), has been improved. Note however that the N-1 criterion is still not fully met. Conclusion case 2: Case 2 handles the intended expansion of a substation, N-1 safe, for which modifications had to be made. Traditional and alternative options were compared. Reliability results showed that both the number of interruptions and the annual customer minutes lost increased. From the value of the extra Non Delivered Energy it was concluded that high investments were not justified from reliability point of view. Alternative measures were needed. This led to high savings in investments with only a minor decrease in reliability. GENERALISATION OF THE METH Figure 7 shows the main results of case 2 in an alternative way. Several constraints are given along relative axes in one diagram, as explained in the legend. The shaded area in the centre is not feasible or not allowed. Figure 7 shows situation S2 on top. For two criteria ( and ) the performance is not acceptable. The diagram in the middle shows S3, where the constraints are partially relieved. The bottom diagram shows the system in situation S4. The system performs within all limits, there is a margin for each constraint. This example shows how different margins could be used to keep the overall performance of the system within its target limits.

6 SC 5 CONCLUSION -5-1 It is shown that margins and risks are inherent multidisciplinary problems. Decreasing costs, trying to maintain quality, or improving quality with minimal expenses, demands a balance between all aspects. Making decisions, when different scenarios are posible, brings risks. Risk is both in uncertainties about the future and in incomplete data. Comparing disciplines means also using weighing factors, using break-even analysis or sensitivity analyses. SC 5-5 A uniform system comparing all the disciplines involved to achieve optimal solutions and to reach a balance between all the constraints is presented. Relieving a limit through working closer to another is a delicate matter. The tools needed are available, however a systematic and consistent approach is required to use the system to its edges. An integrated analysis allows avoiding or postponing costs. Practical examples prove that significant savings can thus be achieved. -1 ACKNOWLEDGEMENT The authors thank EnergieNed, who funded part of this work on behalf of the Dutch utilities. REFERENCES: 5 SC 1. Ajodhia V., Bloemhof G.A., Probabilistic criteria: Saving costs while maintaining high reliability, CEPSI Bloemhof G.A., Dijk H.E., Technico-Economic evaluation of protection systems taking reliability aspects into account, CIRED 1995, paper Cliteur G.J., Wetzer J.M, Condition assessment of power transmission and distribution components, CIRED 21, session Knijp J., Van Doorn J.C., Opportunity Or Responsibility? Developments in Marketing Power Quality, Distributech 2. Figure 7: Radar plot of system performance, top down: situations S2, S3, S4 Legend: SC Short circuit limit of busbar Non Delivered Energy Outage Duration Maximum System Voltage Maximum load current of critical cable 5. Hafkamp P.J.M., Schutters G., Designing and implementing a maintenance management system with an expert support system: Methodology, implementation, expert IT-system, achieved cost reductions after implementation, CIRED 21, session Bloemhof G.A., Wolters B.O, Protection of HVsystems: is simple and cheap good enough?, DPSP Grotenhuis B.J., Jaspers, J.E., Kerstens A., Van der Wey A.H., De Wild F.H., Increasing the Capacity of Cable Systems Using Cable Asset Management Based on Thermal and Mechanical Properties, CIRED 21, session 3.

DECISION SUPPORT FOR LIFE TIME MANAGEMENT OF HV INFRASTRUCTURES

DECISION SUPPORT FOR LIFE TIME MANAGEMENT OF HV INFRASTRUCTURES DECISION SUPPORT FOR LIFE TIME MANAGEMENT OF HV INFRASTRUCTURES E.Gulski (1), J.J.Smit (1), B. Quak (1), E.R.S.Groot (2) (1) Delft University of Technology, (2) KSANDR The Netherlands e.gulski@ewi.tudelft.nl

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

Transmission System Security and Planning Standards

Transmission System Security and Planning Standards ver. 1.4 page 1 from 13 Transmission System Security and Planning Standards April 2014 ver. 1.4 page 2 from 13 TABLE OF CONTENTS 1 Introduction... 4 2 Definitions... 4 2.1 Transmission System... 4 2.2

More information

WILEY A JOHN WILEY & SONS, INC., PUBLICATION

WILEY A JOHN WILEY & SONS, INC., PUBLICATION POWER DISTRIBUTION SYSTEM RELIABILITY Practical Methods and Applications Ali A. Chowdhury Don O. Koval IEEE PRESS SERIES ON POWER ENGINEERING IEEE Press WILEY A JOHN WILEY & SONS, INC., PUBLICATION Preface

More information

Study on the value of flexibility in the management and design basis of distribution networks in France

Study on the value of flexibility in the management and design basis of distribution networks in France Study on the value of flexibility in the management and design basis of distribution networks in France Summary - Version dated 7 December 2015 This document is a translation of E-CUBE Strategy Consultants

More information

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project PJM White Paper PJM Interconnection November 15, 2018 This page is intentionally left blank. PJM 2018 www.pjm.com i P a g e Contents Highlights... 1 Executive Summary... 1 I. Introduction... 2 Reliability

More information

Connection tariffs

Connection tariffs Connection tariffs 2012-2015 TARIFF CONDITIONS FOR CUSTOMERS DIRECTLY CONNECTED TO THE ELIA GRID AND FOR DISTRIBUTION GRID OPERATORS CONNECTED AT TRANSFORMER OUTPUT TO THE 70/36/30 KV NETWORK AND ON THE

More information

Draft Project Assessment Report. Dromana Supply Area. Project UE-DZA-S RIT-D Report

Draft Project Assessment Report. Dromana Supply Area. Project UE-DZA-S RIT-D Report Draft Project Assessment Report RIT-D Report This report presents the network limitations at Dromana zone substation and the distribution feeder network within the Dromana / Mornington supply areas, including

More information

Performance target setting and prioritising electrical power system-level investment

Performance target setting and prioritising electrical power system-level investment Performance target setting and prioritising electrical power system-level investment by Louis Pieterse, City Power City Power s engineering operations performance targets have traditionally been informed

More information

TRANSMISSION PLANNING IN EUROPE: FROM CURRENT METHODOLOGIES TO A NEW SYSTEMIC APPROACH Angelo L Abbate, Gianluigi Migliavacca, ERSE (former CESI RICERCA) Gianluca Fulli, JRC - European Commission Madeleine

More information

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board PJM Staff Whitepaper April 2018 EXECUTIVE SUMMARY On February 13, 2018, the PJM Board of Managers approved changes to the

More information

TRANSMISSION PLANNING IN EUROPE: FROM CURRENT METHODOLOGIES TO A NEW SYSTEMIC APPROACH

TRANSMISSION PLANNING IN EUROPE: FROM CURRENT METHODOLOGIES TO A NEW SYSTEMIC APPROACH TRANSMISSION PLANNING IN EUROPE: FROM CURRENT METHODOLOGIES TO A NEW SYSTEMIC APPROACH Angelo L Abbate, Gianluigi Migliavacca, ERSE (former CESI RICERCA) Gianluca Fulli, JRC - European Commission Madeleine

More information

THE IMPROVEMENTS TO PRESENT LOAD CURVE AND NETWORK CALCULATION

THE IMPROVEMENTS TO PRESENT LOAD CURVE AND NETWORK CALCULATION 1 THE IMPROVEMENTS TO PRESENT LOAD CURVE AND NETWORK CALCULATION Contents 1 Introduction... 2 2 Temperature effects on electricity consumption... 2 2.1 Data... 2 2.2 Preliminary estimation for delay of

More information

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA Transmission Planning Criteria Updated: March Compiled: September 2007 Compiled from: s Comprehensive Transmission Reliability Plan, July 2005 s Strategic

More information

Connection Study Requirements

Connection Study Requirements Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.

More information

Risk-based maintenance and replacement strategy for protection relays Morren, J.; Berende, M.J.C.

Risk-based maintenance and replacement strategy for protection relays Morren, J.; Berende, M.J.C. Risk-based maintenance and replacement strategy for protection relays Morren, J.; Berende, M.J.C. Published in: PAC World Published: 01/01/2014 Document Version Accepted manuscript including changes made

More information

SIMULATOR BASED OPERATOR TRAINING ENSURING QUALITY OF POWER SYSTEM OPERATION

SIMULATOR BASED OPERATOR TRAINING ENSURING QUALITY OF POWER SYSTEM OPERATION SIMULATOR BASED OPERATOR TRAINING ENSURING QUALITY OF POWER SYSTEM OPERATION U Spanel, M Kreutz, C Roggatz DUtrain GmbH, Germany ABSTRACT Liberalisation of the electricity supply industry causes new operation

More information

SUMMARY OF TRANSMISSION BUSINESS

SUMMARY OF TRANSMISSION BUSINESS Filed: September, 0 EB-0-00 Schedule Page of SUMMARY OF TRANSMISSION BUSINESS.0 INTRODUCTION 0 Hydro One Networks Inc. is licensed by the Ontario Energy Board (the OEB or the Board ) to own, operate and

More information

1 Workshop on Power System Testing

1 Workshop on Power System Testing 1 Workshop on Power System Testing DERlab/ SIRFN, 19 March 2015, 9:00 12:00 Moderators: Peter Vaessen (DNV GL), Wolfram Heckmann (Fraunhofer IWES) 1.1 Motivation Our society has become highly dependent

More information

INFORMATION SYSTEM SOLUTION FOR RELIABILITY BASED ANALYSIS AND DEVELOPMENT OF DISTRIBUTION NETWORKS

INFORMATION SYSTEM SOLUTION FOR RELIABILITY BASED ANALYSIS AND DEVELOPMENT OF DISTRIBUTION NETWORKS INFORMATION SYSTEM SOLUTION FOR RELIABILITY BASED ANALYSIS AND DEVELOPMENT OF DISTRIBUTION NETWORKS Pekka VERHO, Pertti JÄRVENTAUSTA, Antti MÄKINEN, Kirsi NOUSIAINEN Tampere University of Technology -

More information

March 3, Submitted to: CAISO

March 3, Submitted to: CAISO March 3, 2016 Submitted to: CAISO (regionaltransmission@caiso.com) COMMENTS OF NEXTERA ENERGY TRANSMISSION WEST, LLC ON THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION S 2015-2016 TRANSMISSION PLANNING

More information

REVIEW OF POWER SYSTEM EXPANSION PLANNING IN VIETNAM

REVIEW OF POWER SYSTEM EXPANSION PLANNING IN VIETNAM Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized REVIEW OF POWER SYSTEM EXPANSION PLANNING IN VIETNAM Tasks 1 and 2 Report Prepared for

More information

Mapping Document for FAC-010-3

Mapping Document for FAC-010-3 Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding

More information

Ergon Energy Corporation Limited 4 June 2010

Ergon Energy Corporation Limited 4 June 2010 Ergon Energy Corporation Limited 4 June 2010 Disclaimer While care was taken in preparation of the information in this discussion paper, and it is provided in good faith, Ergon Energy Corporation Limited

More information

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE GERHARD HACKL 1 HERWIG RENNER 2 MANFRED KRASNITZER 3 CHRISTIAN HOFBAUER 1 ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE Abstract The paper describes the process of

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

NERC Reliability Functional Model Technical Document Version 5

NERC Reliability Functional Model Technical Document Version 5 Reliability Functional Model Technical Document Version 5 Prepared by the Functional Model Working Group This document is a companion to Version 5 of the Functional Model. It provides context, explanations,

More information

Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany

Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Frank.Herbener@Piller.com, Germany 1 Contents 1 Scope 3 2 Power Demand and Distribution in today s Mission Critical Applications

More information

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY 1 1. Summary When one part of the grid is facing security of supply risk where local generation in one region of the grid is not enough for

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

Distribution Network Planning for Mumbai

Distribution Network Planning for Mumbai Newsletter Issue 98 January 2006 Distribution Network Planning for Mumbai Carsten Böse Project Manager Siemens AG, PTD SE PT carsten.boese@siemens.com Introduction The Indian utility Reliance Energy Ltd.

More information

Distribution System Operating Code

Distribution System Operating Code Distribution System Operating Code Draft Rev 5 Approved September 2007 Comments to this document can be forwarded to: RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission System

More information

Electrical utility distribution network capital planning

Electrical utility distribution network capital planning Electrical utility distribution network capital planning A network reliability informed approach to prioritising investment for economic sustainability Dr Clinton Carter-Brown Martin Cameron 63 rd AMEU

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments are needed periodically

More information

Analysing grid flow over time as a cornerstone of the Smart Grid strategy

Analysing grid flow over time as a cornerstone of the Smart Grid strategy Analysing grid flow over time as a cornerstone of the Smart Grid strategy European Utility Week 15-17 October 2013 - Amsterdam Einar Hoffmann, Managing IT Architect, DONG Energy, Denmark eihof@dongenergy.dk

More information

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission

More information

FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA The following information submitted for this Part 4 of FERC Form No. 715 consists of PJM's current Planning Criteria, and each member

More information

Maximum PV-penetration in low-voltage cable networks

Maximum PV-penetration in low-voltage cable networks Maximum PV-penetration in low-voltage cable networks R. Bernards Electrical Energy Systems Group Eindhoven University of Technology Eindhoven, the Netherlands Email: r.bernards@tue.nl J. Morren Enexis

More information

A PARTIAL RELATIONSHIP BETWEEN COSTS AND QUALITY AS A BASIS FOR SETTING REGULATION PARAMETERS OF SUPPLY CONTINUITY

A PARTIAL RELATIONSHIP BETWEEN COSTS AND QUALITY AS A BASIS FOR SETTING REGULATION PARAMETERS OF SUPPLY CONTINUITY A PARTIAL RELATIONSHIP BETWEEN COSTS AND QUALITY AS A BASIS FOR SETTING REGULATION PARAMETERS OF SUPPLY CONTINUITY Petr SKALA Václav DĚTŘICH Jan ŠEFRÁNEK EGÚ Brno, a.s. Czech Republic EGÚ Brno, a.s. Czech

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

TPL 001 AB 0 System Performance Under Normal Conditions

TPL 001 AB 0 System Performance Under Normal Conditions Alberta Reliability Standard System Performance Under rmal Conditions TPL-001-AB-0 TPL 001 AB 0 System Performance Under rmal Conditions 1. Purpose The purpose of this reliability standard is to ensure

More information

NERC PLANNING STANDARDS

NERC PLANNING STANDARDS NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements Page 220 of 257 A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments

More information

COPPER FOR BUSBARS CHAPTER 3: LIFE CYCLE COSTING

COPPER FOR BUSBARS CHAPTER 3: LIFE CYCLE COSTING European Copper Institute COPPER FOR BUSBARS CHAPTER 3: LIFE CYCLE COSTING David Chapman August 2011 ECI Available from www.leonardo-energy.org Document Issue Control Sheet Document Title: Publication

More information

Standard TPL System Performance Under Normal Conditions

Standard TPL System Performance Under Normal Conditions Standard TPL-001-0.1 System Performance Under rmal Conditions Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when

More information

THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks

THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Issued by: Review Cycle: Asset Management & Regulation, ESB Networks Three years Contents 1.0 Introduction....3 1.1 Definitions...3 1.2 Aim of Planning...5

More information

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5 Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods

More information

Standard TPL (i) System Performance Under Normal Conditions

Standard TPL (i) System Performance Under Normal Conditions Standard TPL-001-0.1(i) System Performance Under rmal Conditions A. Introduction 1. Title: System Performance Under rmal ( Contingency) Conditions (Category A) 2. Number: TPL-001-0.1(i) 3. Purpose: System

More information

A Probabilistic Security Criterion for Determination of Power Transfer Limits in a Deregulated Environment

A Probabilistic Security Criterion for Determination of Power Transfer Limits in a Deregulated Environment A Probabilistic Security riterion for Determination of Power Transfer Limits in a Deregulated Environment Kjetil Uhlen and Gerd H. Kjølle, SINTEF Energy Research Gunnar G. Løvås and Øyvind Breidablik,

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information

NETWORK ASSET CONDITION ASSESSMENT AND REFURBISHMENT PLANNING

NETWORK ASSET CONDITION ASSESSMENT AND REFURBISHMENT PLANNING NETWORK ASSET CONDITION ASSESSMENT AND REFURBISHMENT PLANNING D J Vrey (Senior Eng, M.Ing, Pr.Eng, NETGroup South Africa) M E N du Preez (Managing Dir, M.Ing, Pr.Eng, NETGroup South Africa) H H van der

More information

EDS GAS ZONE IDENTIFICATION AND ALARMS ON GAS INSULATED SWITCHGEAR

EDS GAS ZONE IDENTIFICATION AND ALARMS ON GAS INSULATED SWITCHGEAR ENGINEERING DESIGN STANDARD EDS 03-0026 GAS ZONE IDENTIFICATION AND ALARMS ON GAS INSULATED SWITCHGEAR Network(s): Summary: EPN, LPN, SPN This standard sets out the system of gas zone identification and

More information

effective date 1/8/01

effective date 1/8/01 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context clearly indicates otherwise, in this section and 25.212 of this title (relating to Technical

More information

FUNDAMENTAL ASPECTS OF INFORMATION PROCESSING TO SUPPORT ASSET MANAGEMENT

FUNDAMENTAL ASPECTS OF INFORMATION PROCESSING TO SUPPORT ASSET MANAGEMENT FUNDAMENTAL ASPECTS OF INFORMATION PROCESSING TO SUPPORT ASSET MANAGEMENT Ben QUAK (1), Edward GULSKI (2), Johan J. SMIT (2) & Philip WESTER (3) (1) Transportnet Zuid-Holland Netherlands (2) Delft University

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

TSOs, taking into account the following: Whereas

TSOs, taking into account the following: Whereas All TSOs proposal for a common grid model methodology in accordance with Articles 67(1) and 70(1) of Commission Regulation (EU) 2017/1485 of 02 August 2017 establishing a guideline on electricity transmission

More information

Optimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events

Optimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events IWAIS XIV, China, May 0 Optimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events Asim Haldar, Ph.D, P.Eng. ahaldar@nalcorenergy.com

More information

Methodology PLG-METH-0002-V1

Methodology PLG-METH-0002-V1 Methodology Department: Document No: System Planning and Strategic Projects PLG-METH-0002-V1 Title: Transmission Planning Assessment Practices Issue Date: September 27, 2012 Previous Date: Nov. 18, 2011

More information

C2-204 SC C2 PS2. Improved TSO coordination in the Central West European region

C2-204 SC C2 PS2. Improved TSO coordination in the Central West European region http : //www.cigre.org C2-204 SC C2 PS2 2012 Paris Session Improved TSO coordination in the Central West European region O. Arrivé (RTE), F. Boulet (Coreso), Cristina Moran-Pena and P. Johnson (National

More information

Optimal network topology and reliability indices to be used in the design of power distribution networks in oil and gas plants *

Optimal network topology and reliability indices to be used in the design of power distribution networks in oil and gas plants * Optimal network topology and reliability indices to be used in the design of power distribution networks in oil and gas plants * R Naidoo and EJ Manning University of Pretoria, Pretoria, South Africa ABSTRACT:

More information

AEP Guidelines for Transmission Owner Identified Needs

AEP Guidelines for Transmission Owner Identified Needs AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal

More information

Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal

Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal October 18, 2012 Prepared by: Market and Infrastructure Development Version: 1.0 California Independent System Operator Contents

More information

Standard TPL-002-0b System Performance Following Loss of a Single BES Element

Standard TPL-002-0b System Performance Following Loss of a Single BES Element A. Introduction 1. Title: System Performance Following Loss of a Single Bulk Electric System Element (Category B) 2. Number: TPL-002-0b 3. Purpose: System simulations and associated assessments are needed

More information

Effects of Renewable Distributed Generation on the Operational Characteristics of Meshed Power Distribution Systems

Effects of Renewable Distributed Generation on the Operational Characteristics of Meshed Power Distribution Systems Effects of Renewable Distributed Generation on the Operational Characteristics of Meshed Power Distribution Systems WEN-CHIH YANG Department of Electrical Engineering Technology and Science Institute of

More information

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway SUMMARY Cost efficient utilisation of the wind energy resource requires wind farms to be located

More information

Standard Development Timeline

Standard Development Timeline Standard TPL-001-4 Transmission System Planning Performance Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be

More information

International ejournals

International ejournals ISSN 2249 5460 Available online at www.internationalejournals.com International ejournals International Journal of Mathematical Sciences, Technology and Humanities 21 (2011) 205 212 ENERGY CONTROL CENTER

More information

Outcomes and recommendations GREDOR

Outcomes and recommendations GREDOR Outcomes and recommendations GREDOR The increase of the capacity of renewable generation, the evolution of consumption modes such as electrical vehicles, and the changes in the electricity markets sector

More information

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED PREPARED BY: Network Development VERSION: 2.0 RELEASE DATE: 30 May 2012 Version Release History Version Date By Changes 1.0 6 Oct 11 Transmission

More information

Postprint. This is the accepted version of a paper presented at 2017 CIGRÉ SC B3 (Substations) Colloquium.

Postprint.   This is the accepted version of a paper presented at 2017 CIGRÉ SC B3 (Substations) Colloquium. http://www.diva-portal.org Postprint This is the accepted version of a paper presented at 2017 CIGRÉ SC B3 (Substations) Colloquium. Citation for the original published paper: Babu, S., Hilber, P. (2017)

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

DOMESTIC COGENERATION OF HEAT AND ELECTRICITY

DOMESTIC COGENERATION OF HEAT AND ELECTRICITY DOMESTIC COGENERATION OF HEAT AND ELECTRICITY Henrik Weldingh DEFU - Denmark 1 hw@defu.dk INTRODUCTION CHP, Combined Heat and Power, or Cogeneration of Heat and Power, is the simultaneous production of

More information

Information Document Protection System Information ID# R

Information Document Protection System Information ID# R Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between the Information Document and the related authoritative document(s)

More information

Attachment G.7 SAPN_Reliability_Low reliability feeders 03 July, 2015

Attachment G.7 SAPN_Reliability_Low reliability feeders 03 July, 2015 Attachment G.7 SAPN_Reliability_Low reliability feeders 03 July, 2015 Rule requirement Table of Contents 1. Executive Summary... 3 2. Rule requirement... 5 3. Background... 6 3.1 Historical Performance...

More information

MANAGING SITUATION AWARENESS IN POWER DISTRIBUTION GRID DISTURBANCES

MANAGING SITUATION AWARENESS IN POWER DISTRIBUTION GRID DISTURBANCES MANAGING SITUATION AWARENESS IN POWER DISTRIBUTION GRID DISTURBANCES Kaisa PYLKKÄNEN Finland kaisa.pylkkanen@student.tut.fi Turo IHONEN Elenia Oy Finland turo.ihonen@elenia.fi ABSTRACT Power grid is one

More information

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS APPENDIX G AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS Transmission Planning Criteria - Basis and Assumptions Version 1.0 1. Introduction This document presents the reliability standards,

More information

Power Systems Fundamentals

Power Systems Fundamentals Power Systems Fundamentals This seminar will be valuable to participants in the power industry who need a fundamental understanding of the power system, and how system operation can impact power market

More information

List of training courses on electrical power system for Cambodia, Laos, Vietnam and Thailand (CLVT) countries

List of training courses on electrical power system for Cambodia, Laos, Vietnam and Thailand (CLVT) countries List of training courses on electrical power system for Cambodia, (Responsible and coordinator : Dr. Tuan Nguyen, t.nguyen@ied-sa.fr) 1. TRAINING COURSE 1 CUSTOMER SERVICE METERING AND BILLING 2. TRAINING

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

HARMONISATION OF FAULT AND INTERRUPTION DATA IN THE NORDIC COUNTRIES

HARMONISATION OF FAULT AND INTERRUPTION DATA IN THE NORDIC COUNTRIES HARMONISATION OF FAULT AND INTERRUPTION DATA IN THE NORDIC COUNTRIES Jørn Heggset, Olve Mogstad SINTEF Energy Research jorn.heggset@sintef.no olve.mogstad@sintef.no Morten Møller Jensen DEFU mmj@defu.dk

More information

Approaches to Generation Dispatch in Transmission Planning

Approaches to Generation Dispatch in Transmission Planning 21, rue d Artois, F-75008 PARIS Paper 135 GUILIN 2009 Approaches to Generation Dispatch in Transmission Planning P. J. PALERMO KEMA, Inc. USA SUMMARY A critical factor affecting transmission system development

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

Simplified reliability modelling as a basis for performance target setting and prioritising electrical power system-level investment

Simplified reliability modelling as a basis for performance target setting and prioritising electrical power system-level investment Simplified reliability modelling as a basis for performance target setting and prioritising electrical power system-level investment Author : Johanette van der Merwe, MSc Eng Senior Consultant, EON Consulting

More information

Dalrymple Substation Upgrade

Dalrymple Substation Upgrade Dalrymple Substation Upgrade RIT-T: Project Assessment Conclusions Report Version 1 ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office,

More information

DRAFT STUDY PLAN FOR 2018

DRAFT STUDY PLAN FOR 2018 DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure

More information

B Improvements on High Voltage Electrical Substations to face the new Brazilian Legislation. G. M. Bastos (*) R. C. Valente E.

B Improvements on High Voltage Electrical Substations to face the new Brazilian Legislation. G. M. Bastos (*) R. C. Valente E. 21, rue d'artois, F-75008 Paris http://www.cigre.org B3-214 Session 2004 CIGRÉ Improvements on High Voltage Electrical Substations to face the new Brazilian Legislation G. M. Bastos (*) R. C. Valente E.

More information

A computer-aided, reliability-centered maintenance strategy for power networks

A computer-aided, reliability-centered maintenance strategy for power networks A computer-aided, reliability-centered maintenance strategy for power networks The assessment of the technical condition of substation equipment and its influence on the network is basic to a reliability-centered

More information

TTC/ATC 1.0 DEFINITIONS

TTC/ATC 1.0 DEFINITIONS TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule

More information

Methodological Application to Integrate Renewable Energy Resource into Kuwait s Electrical Grid

Methodological Application to Integrate Renewable Energy Resource into Kuwait s Electrical Grid Methodological Application to Integrate Renewable Energy Resource into Kuwait s Electrical Grid Adel Qabazard Energy and Building Research Center Kuwait Institute for Scientific Research P. O. Box 24885,

More information

AN EXPERIENCE IN DETERMINING A COST VERSUS QUALITY OF SERVICE CHARACTERISTIC IN ORDER TO DEFINE OPTIMAL INVESTMENT LEVEL

AN EXPERIENCE IN DETERMINING A COST VERSUS QUALITY OF SERVICE CHARACTERISTIC IN ORDER TO DEFINE OPTIMAL INVESTMENT LEVEL AN EXPERIENCE IN DETERMINING A COST VERSUS QUALITY OF SERVICE CHARACTERISTIC IN ORDER TO DEFINE OPTIMAL INVESTMENT LEVEL Ivo Ordonha Cyrillo Marcelo Aparecido Pelegrini Gabriel Quiroga Sinapsis Inovação

More information

Kintyre Hunterston Link. The upgrade of grid access in Kintyre

Kintyre Hunterston Link. The upgrade of grid access in Kintyre The upgrade of grid access in Kintyre About us Scottish Hydro Electric Transmission plc (SHE Transmission), part of Scottish and Southern Energy Power Distribution (SSEPD), is the licensed electricity

More information

WPD Innovation. Paul Jewell Policy Manager

WPD Innovation. Paul Jewell Policy Manager WPD Innovation Paul Jewell Policy Manager Who are WPD? Distribution Network Operator Midlands, South West and Wales 7.8 million customers 55,500 square kilometres 220,000km of lines & cable 185,000 substations

More information

Study Committee A3. High Voltage Equipment. Action Plan

Study Committee A3. High Voltage Equipment. Action Plan Study Committee A3 High Voltage Equipment Action Plan October 2011 CIGRE Study Committee A3 - High Voltage Equipment Action Plan 1 Content 1 Content...2 2 Purpose of the Action Plan...3 3 Activities of

More information

GUARANTY OF SUPPLY AVAILABILITY IN A COMPETITIVE ENVIRONMENT - STRATEGY AND EXPERIENCE OF A GERMAN DISTRIBUTION COMPANY

GUARANTY OF SUPPLY AVAILABILITY IN A COMPETITIVE ENVIRONMENT - STRATEGY AND EXPERIENCE OF A GERMAN DISTRIBUTION COMPANY GUARANTY OF SUPPLY AVAILABILITY IN A COMPETITIVE ENVIRONMENT - STRATEGY AND EXPERIENCE OF A GERMAN DISTRIBUTION COMPANY Peter BIRKNER Lechwerke AG - Germany peter.birkner@lew.de Summary -- The most crucial

More information

Example of Information for EOL Projects. American Municipal Power October 19, 2017

Example of Information for EOL Projects. American Municipal Power October 19, 2017 Example of Information for EOL Projects American Municipal Power October 19, 2017 Baseline Project: Description of Project Add detailed map for all facilities mentioned for Problem Statement: PJM/NERC/TO

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

GUYANA POWER AND LIGHT INC

GUYANA POWER AND LIGHT INC GUYANA POWER AND LIGHT INC The Terms of Reference REQUEST FOR PROPOSALS: CONSULTANCY SERVICES COORDINATING GENERATOR PROTECTION WITH TRANSMISSION PROTECTION AND GENERATOR CONTROLS (GPL-PI-094-2016) November

More information

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004 Glossary of Terms Used in Standards Preliminary Draft Version 0 Standards September 1, 2004 Source References (Noted in draft only will not be part of final glossary) Functional Model () Glossary (GL)

More information