COMMENTS ON CAISO PROPOSAL FOR RESOLVING DEFICIENCIES IN REPRESENTATION OF GENERATOR START-UP AND MINIMUM LOAD COSTS

Size: px
Start display at page:

Download "COMMENTS ON CAISO PROPOSAL FOR RESOLVING DEFICIENCIES IN REPRESENTATION OF GENERATOR START-UP AND MINIMUM LOAD COSTS"

Transcription

1 COMMENTS ON CAISO PROPOSAL FOR RESOLVING DEFICIENCIES IN REPRESENTATION OF GENERATOR START-UP AND MINIMUM LOAD COSTS On June 12, 2009, the CAISO published a paper entitled Changes to Restrictions on Bidding Start-Up and Minimum Load, ( Issue Paper ) 1 which was presented and discussed at the Market Surveillance Committee Meeting on June 17, Comments on that paper were requested by June 26, These comments are jointly submitted by the following market participants: Brian Theaker (530) Steve Greenleaf (916) Sean Beatty (925) Kerry Hattevik (510) Eric Leuze (916) Dynegy (Dynegy Morro Bay, LLC, Dynegy Moss Landing, LLC, Dynegy Oakland LLC and Dynegy South Bay, LLC) J.P. Morgan Ventures Energy Corporation and BE CA, LLC (J.P. Morgan) Mirant Delta, LLC, Mirant Potrero, LLC, Mirant California, LLC NRG Power Marketing LLC, Cabrillo Power I LLC, Cabrillo Power II LLC, El Segundo Power, LLC, and Long Beach Generation LLC (collectively, NRG or the NRG Companies ) RRI Energy, Inc. We appreciate the CAISO s responsiveness to this issue, and believe that the CAISO s paper offers an excellent starting point for developing a proposal that market participants can broadly support. URGENT ACTION IS REQUIRED Generating Units do not have the ability to accurately represent their opportunity costs and actual Start-Up Costs and Minimum Load Costs through the Proxy Cost and Registered Cost options specified in Section 30.4 of the CAISO Tariff. This leads to the frequent and uneconomic market commitment of short-start units, and other units with limited run times or environmental constraints; and risks for longer start units that cannot be fully mitigated. Of particular concern are frequent unit starts that are both inefficient and sub-optimal from a unit operations perspective. The inefficient commitment of these resources is exacerbated by the lack of opportunity to fully reflect fixed maintenance costs, such as wear and tear. Furthermore, the limitation on the ability to reflect During the discussion of this topic at the Market Surveillance Committee meeting, the CAISO announced that the original deadline of June 24, 2009 would be extended to June 26. June 26, 2009 Page 1 of 5

2 opportunity costs for start up and minimum load undermines the CAISO ability to make economic commitment decisions and allow for the economic optimization of limited run time and environmentally constrained resources. Heading in to the new market, resource owners had the expectation that they may be able to recover such costs through their market bids. However, because resources are being started and shut down and often not dispatched into their economic bid range (i.e., only committed and dispatched to their PMin), they often do not have an opportunity to recover these legitimate costs through their economic bids. As a result of these circumstances, resource owners are reevaluating the nature and level of their participation in the CAISO s markets. The current methodologies for determining Start-Up and Minimum Load Costs also likely influences non-market resource commitment that occur pursuant to the CAISO s Exceptional Dispatch authority. The Proxy Cost option, which is largely based on gas commodity costs, omits start-based wear and tear costs and as such understates the cost of committing resources outside the market (both pre and post market). The inability to reflect opportunity costs compounded by a noncomprehensive proxy cost calculation therefore results in uneconomic decisions to commit units to minimum load. With bid caps in place, the Registered Cost option unnecessarily binds the generator to a six-month commitment.. For this reason many generators have opted for a Proxy cost alternative since it at least allows for a more current reflection of gas prices. Resource owners are concerned that, under the existing Start-Up and Minimum Load Cost methodologies, the commitment of resources at PMin under Exceptional Dispatch: 1) does not appropriately compensate resources for the Energy provided; and 2) understates Exceptional Dispatch costs and thus may exacerbate the CAISO s reliance on out of market commitment. The ability of a generator to bid start up and minimum load costs, particularly quick start units, is a critical element in providing the ISO an economic basis for commitment and must be implemented as soon as possible. As further explained below, we recommend that the CAISO file tariff amendments for the short-term proposal outlined in the CAISO s Issue Paper 3 and seek an effective date of no later than August 1, SHORT TERM PROPOSAL We support the Issue Paper s proposal to reduce the duration of the commitment of the Registered Cost option to one-month, and also support the CAISO s plan to take the short-term proposal to the Board of Governors for approval in July While reducing the registered cost commitment to 1 month is an improvement, it still embodies substantial gas price risk compared with the Proxy 3 CAISO June 12, 2009 Issue Paper Changes to Restrictions on Bidding Start-up and Minimum Load Pages 3-4. June 26, 2009 Page 2 of 5

3 cost option. For this reason, we suggest short-term improvements to the proxy cost calculation that more accurately encompass true start up costs. We have three recommendations regarding the short-term proposal: A. Include Additional Cost Components in the Proxy Cost Option to Allow Generating Units to Recover Fixed Start-Up Maintenance and Labor Costs. The CAISO s market software commits units based on start-up and minimumload costs Generation resources that have declined to bear the risk associated with the six-month commitment required under the Registered Cost option have chosen the Proxy Cost option for calculating start-up costs. The comparatively lower resulting values for start-up and minimum-load have led to frequent commitment of generating units to minimum operating levels. A generator should be able to include certain fixed start-up costs, including wear and tear costs in the Proxy Cost calculations that the ISO uses to commit units. Each start contributes to additional maintenance costs that are not recognized in the current Proxy Cost calculation, which includes only the following cost components: 4 1) Cost of fuel based on the average volume required to start, priced at the prior day s index. 2) Auxiliary power priced at a resource-specific rate. Starting a generating unit increases maintenance costs from wear and tear and adds labor expenses. These costs are not adequately compensated for in the CAISO s Proxy Cost calculation or the CAISO O&M adder. While all other ISOs allow for bidding of start up and minimum load costs, when a unit is mitigated to cost in PJM it is permitted to recover maintenance costs and additional labor expenses. 5 PJM specifies the following categories of start-up costs for hot, intermediate, and cold starting conditions for cost-based units. Under cold-start conditions, for example, the following costs are considered: 1. Total fuel-related cost from first fire (initial reactor criticality for nuclear units) to breaker closing (including auxiliary boiler fuel) priced at the cost of fuel currently in effect, plus (+) shutdown fuel cost defined as the cost of 4 There is also an O&M adder for commitment to minimum load, but this is a variable cost factor not directly related to the cost of start-up. See CAISO BPM for Market Instruments at page 27, available at: 5 PJM Manual 15, (Cost Development Guidelines), pages ( PJM Cost Development Guidelines Manual ), available at: June 26, 2009 Page 3 of 5

4 fuel expended from breaker opening of the previous shutdown to shutdown of equipment needed for normal cool down of plant components, excluding normal plant heating/auxiliary equipment fuel requirements. 2. Plus (+) station service from initiation of start sequence to breaker closing (total station use minus normal base station use) priced at the Station Service rate. 3. Plus (+) station service after breaker opening during shutdown (station service during shutdown should be that associated with the normal unit auxiliary equipment operated during shutdown in excess of base unit use, this station service is not to include maintenance use or non-normal uses) priced at the Station Service rate. 4. Plus (+) additional labor costs in excess of normal station manning requirements that are incurred when starting the unit. 5. Plus (+) Start Maintenance Adder The CAISO s Proxy Cost option reasonably considers the fuel cost and station service components (items 1 through 3), but does not provide an opportunity to recover either the additional start-up labor costs or start-up maintenance costs that PJM allows generating units to recover when mitigated. The PJM Start Maintenance Adder, for example, compensates a resource for the start-up portion of the cost of labor and materials not otherwise recovered. 6 In the interest of quickly accommodating these additional Start-up Labor and Maintenance cost components, and avoiding the delay associated with changing the Master File and related software, the CAISO should explore how these costs could be accommodated within the existing Master File parameters. One approach could be to use the existing auxiliary power component of the start-up cost calculation, and allow adjustments, within some reasonable limits, to accommodate these additional costs We recognize that some additional process may be necessary to implement these changes. However, we stand ready to assist the CAISO as required in implementing this change. B. The CAISO Should Consider Using a Resource s First Bid Segment One option that several participants have discussed by with CAISO staff is to modify the Minimum Load Energy cost used for commitment decisions to be the greater of a) the Minimum Load Energy Cost as calculated under the Proxy Cost or Registered Cost options, and b) the value of the energy generated at PMin if 6 Id. at pages 24 and 60. June 26, 2009 Page 4 of 5

5 that energy were valued based on the first bid segment. While not a substitute for dynamic bidding, this approach would help protect the generating unit from being required to start and run at minimum load at a compensation level that fails to meet costs. The CAISO should explore whether this option can be implemented quickly as part of the short-term proposal. C. The CAISO Should Request an Effective Date Coincident with its Tariff Filing Recognizing the need for urgent action, and that the CAISO Board meeting is not until late July, we recommend that the CAISO make its tariff filing no later than August 1, 2009, and request that FERC accept the CAISO s tariff changes and establish the filing date as the effective date, subject to refund. LONGER TERM PROPOSAL The most efficient means for committing units is to allow resource owners flexibility to bid start-up and minimum load costs, thereby providing the ISO with an economic basis for commitment. Therefore, we believe that in the longer term, the CAISO should allow dynamic bidding of start-up and minimum load costs. This flexibility should be implemented as soon as possible. While hourly bidding provides maximum flexibility, daily bidding will be a vast improvement that allows for resource optimization. Therefore, if the flexibility to allow hourly bidding would delay implementation, then the initial roll-out should allow daily bidding. Hourly bidding could then be accommodated as soon as possible thereafter. In the interest of expeditiously implementing an efficient, market-based approach to economic unit commitment, we support providing for hourly bidding of Start-Up and Minimum Load costs while retaining the Registered Cost bid cap until such time as dynamic mitigation can be implemented. The rationale for deferring any feature of the longer term proposal (i.e., dynamic mitigation or hourly bidding) should be explained when the longer term proposal is taken to the Board in September. CONCLUSION We appreciate the opportunity to submit these comments and again thank the CAISO for its prompt attention to this issue. We look forward to working through the issues with the CAISO staff, and to completing changes to the Start-Up and Minimum Load functionality as soon as possible to allow suppliers the ability to fully mitigate the risk of uneconomic starts. June 26, 2009 Page 5 of 5

PJM Manual 15: Cost Development Guidelines Revision: 30 Effective Date: December 4, Prepared by Cost Development Subcommittee

PJM Manual 15: Cost Development Guidelines Revision: 30 Effective Date: December 4, Prepared by Cost Development Subcommittee PJM Manual 15: Cost Development Guidelines Revision: 30 Effective Date: December 4, 2018 Prepared by Cost Development Subcommittee PJM 2018 Table of Contents Table of Contents Table of Exhibits...8 Approval...10

More information

PJM Manual 15: Cost Development Guidelines Revision: 2930 Effective Date: May 15, 2017April 9, Prepared by Cost Development Subcommittee

PJM Manual 15: Cost Development Guidelines Revision: 2930 Effective Date: May 15, 2017April 9, Prepared by Cost Development Subcommittee PJM Manual 15: Cost Development Guidelines Revision: 2930 Effective Date: May 15, 2017April 9, 2018 Prepared by Cost Development Subcommittee PJM 20172018 Table of Contents Table of Contents Table of Exhibits...8

More information

PJM Manual 15: Cost Development Guidelines Revision: 2930 Effective Date: May 15, 2017July 31, Prepared by Cost Development Subcommittee

PJM Manual 15: Cost Development Guidelines Revision: 2930 Effective Date: May 15, 2017July 31, Prepared by Cost Development Subcommittee PJM Manual 15: Cost Development Guidelines Revision: 2930 Effective Date: May 15, 2017July 31, 2018 Prepared by Cost Development Subcommittee PJM 20172018 Table of Contents Table of Contents Table of Exhibits...8

More information

Cost Development Guidelines

Cost Development Guidelines DRAFT Manual 15 Language Clean Version Approved by CDS on October 25, 2012 PJM Manual 15: Cost Development Guidelines Revision: 20 Effective Date: November 1, 2012 Prepared by Cost Development Subcommittee

More information

Revision: 16 Effective Date: Prepared by Cost Development Task Force

Revision: 16 Effective Date: Prepared by Cost Development Task Force PJM Manual 15: Cost Development Guidelines Revision: 16 Effective Date: Prepared by Cost Development Task Force PJM 2010 i Table of Exhibits PJM 2010 PJM 2003 Approval and Current Revision PJM Manual 15:

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 30. Bid and Self-Schedule Submission for all CAISO Markets... 2 30.1 Bids, Including Self-Schedules... 2 30.1.1 Day-Ahead Market... 2 30.1.2 Real-Time Market... 2 30.2 Bid Types... 3

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 30. Bid And Self-Schedule Submission For All CAISO Markets... 2 30.1 Bids, Including Self-Schedules... 2 30.1.1 Day-Ahead Market... 2 30.1.2 Real-Time Market... 2 30.2 Bid Types... 3

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 30. Bid and Self-Schedule Submission for all CAISO Markets... 2 30.1 Bids, Including Self-Schedules... 2 30.1.1 Day-Ahead Market... 2 30.1.2 Real-Time Market... 2 30.2 Bid Types... 3

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 30. Bid and Self-Schedule Submission for all CAISO Markets... 2 30.1 Bids, Including Self-Schedules... 2 30.1.1 Day-Ahead Market... 2 30.1.2 Real-Time Market... 2 30.2 Bid Types... 3

More information

Cost Development Guidelines

Cost Development Guidelines PJM Manual 15: Cost Development Guidelines Revision: 18 Effective Date: Deleted: June 1, 2011 Prepared by Cost Development Subcommittee PJM 2011 PJM 2011 i Table of Exhibits PJM Manual 15: Cost Development

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 30. Bid And Self-Schedule Submission For All CAISO Markets... 2 30.1 Bids, Including Self-Schedules... 2 30.1.1 Day-Ahead Market... 2 30.1.2 Real-Time Market... 2 30.2 Bid Types... 3

More information

Cost Development Guidelines

Cost Development Guidelines PJM Manual 15: Cost Development Guidelines Revision: 15 Effective Date: Prepared by Cost Development Task Force PJM 2010 PJM 2010 i Table of Exhibits PJM Manual 15: Cost Development Guidelines Table of

More information

Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets

Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets Scott Harvey Member: California Market Surveillance Committee Folsom, California May 19, 2014 TOPICS ISO New England PJM MISO New York ISO

More information

BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, L.L.C. ) Docket Nos. ER

BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, L.L.C. ) Docket Nos. ER BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket Nos. ER16-372-000 MOTION FOR LEAVE TO ANSWER AND ANSWER OF THE PENNSYLVANIA PUBLIC UTILITY COMMISSION IN SUPPORT OF

More information

Cost Development Guidelines

Cost Development Guidelines PJM Manual 15: Cost Development Guidelines Revision: 18 Effective Date: February 8, 2012 Prepared by Cost Development Subcommittee PJM 2012 PJM 2012 i Table of Contents PJM Manual 15: Cost Development

More information

Updated Operating Parameter Definitions

Updated Operating Parameter Definitions Updated Operating Parameter Definitions Tom Hauske Senior Lead Engineer, Performance Compliance Market Implementation Committee February 10, 2016 Why are we discussing? A number of operating parameters

More information

126 FERC 61,150 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

126 FERC 61,150 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 126 FERC 61,150 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Acting Chairman; Suedeen G. Kelly, Marc Spitzer, and Philip D. Moeller. California Independent

More information

Cost Development Guidelines

Cost Development Guidelines PJM Manual 15: Cost Development Guidelines Revision: 28 Effective Date: October 18, 2016 Prepared by: Cost Development Subcommittee PJM 2016 Table of Contents PJM Manual 15: Cost Development Guidelines

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent Operator ) Corporation ) Docket No. ER10-500-000 MOTION FOR CLARIFICATION OR IN THE ALTERNATIVE REHEARING

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: December 6, 2017 Re: Decision on contingency

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) California Independent System ) Docket No. ER08-760-001 Operator Corporation ) ) MOTION FOR LEAVE TO FILE ANSWER OUT OF TIME AND

More information

Price Formation Education Session Day 1 Economic Dispatch

Price Formation Education Session Day 1 Economic Dispatch Slide 1 Price Formation Education Session Day 1 Economic Dispatch Anthony Giacomoni Melissa Maxwell Laura Walter December 4, 2017 Slide 2 Disclaimer Slide This is not a committee meeting. This session

More information

California ISO Draft Final Proposal Ancillary Services Procurement in HASP and Dispatch Logic

California ISO Draft Final Proposal Ancillary Services Procurement in HASP and Dispatch Logic California ISO Draft Final Proposal Ancillary Services Procurement in HASP and Dispatch Logic Redline Version August 25, 2009 Ancillary Services Procurement in HASP and Dispatch Logic Prepared for Discussion

More information

Energy Storage and Distributed Energy Resources Phase 4 (ESDER 4) Issue Paper and Stakeholder Working Group Meeting

Energy Storage and Distributed Energy Resources Phase 4 (ESDER 4) Issue Paper and Stakeholder Working Group Meeting Energy Storage and Distributed Energy Resources Phase 4 (ESDER 4) Issue Paper and Stakeholder Working Group Meeting Comments by Department of Market Monitoring April 2, 2019 Summary DMM appreciates the

More information

PJM Interconnection L.L.C., Docket No. ER Amended Compliance Filing Concerning the Offer Cap Rule

PJM Interconnection L.L.C., Docket No. ER Amended Compliance Filing Concerning the Offer Cap Rule PJM Interconnection, L.L.C. 2750 Monroe Blvd Audubon, PA 19403 Chenchao Lu Counsel 610.666.2255 fax 610.666.8211 Chenchao.Lu@pjm.com February 8, 2018 The Honorable Kimberly D. Bose Secretary Federal Energy

More information

Energy Imbalance Market Year 1 Enhancements. Issue Paper and Straw Proposal

Energy Imbalance Market Year 1 Enhancements. Issue Paper and Straw Proposal Energy Imbalance Market Year 1 Enhancements Issue Paper and Straw Proposal November 10, 2014 Energy Imbalance Market Year 1 Enhancements Issue Paper and Straw Proposal Table of Contents 1 Introduction...

More information

Commitment Cost Enhancements Phase 3 Action Plan

Commitment Cost Enhancements Phase 3 Action Plan Commitment Cost Enhancements Phase 3 Action Plan November 10, 2017 Table of Contents 1. Executive Summary... 3 2. Background... 3 3. Stakeholder Engagement... 6 4. Summary of Stakeholder Comments... 6

More information

Issue Paper. Modifying the DEC Bidding Activity Rule on Day-Ahead Schedules

Issue Paper. Modifying the DEC Bidding Activity Rule on Day-Ahead Schedules Issue Paper Modifying the DEC Bidding Activity Rule on Day-Ahead Schedules February 1, 2008 Modifying the DEC Bidding Activity Rule on Day Ahead Schedules Table of Contents 1 Introduction...3 2 Background:

More information

Day-Ahead Energy Market

Day-Ahead Energy Market Day-Ahead Energy Market PJM State & Member Training Dept. PJM 2017 Objectives Students will be able to: Identify the process and procedures for participating in the Day-Ahead Market PJM 2017 2 Markets

More information

163 FERC 61,211 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

163 FERC 61,211 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 163 FERC 61,211 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Kevin J. McIntyre, Chairman; Cheryl A. LaFleur, Neil Chatterjee, Robert F. Powelson, and Richard Glick.

More information

Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal

Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal Transmission Constraint Relaxation Parameter Revision ISO Straw Proposal October 18, 2012 Prepared by: Market and Infrastructure Development Version: 1.0 California Independent System Operator Contents

More information

RDRP Stakeholder Initiative

RDRP Stakeholder Initiative Reliability Demand Response Product RDRP Stakeholder Initiative Draft Final Proposal Review Stakeholder Conference Call September 13, 2010 Reliability Demand Response Product (RDRP) 1 2 3 We are here Project

More information

Commitment Cost Enhancements Phase 2 Straw Proposal

Commitment Cost Enhancements Phase 2 Straw Proposal Commitment Cost Enhancements Phase 2 Straw Proposal October 29, 2014 Table of Contents 1. Background... 3 2. Schedule for policy stakeholder engagement... 4 3. Initiative scope... 5 4. Summary of proposals...

More information

ISO-NE FCM Capacity Market Design Scott M. Harvey. October 9, 2007

ISO-NE FCM Capacity Market Design Scott M. Harvey. October 9, 2007 ISO-NE FCM Capacity Market Design Scott M. Harvey October 9, 2007 Summary The ISO-NE FCM capacity market design embodies many improvements over the prior ISO-NE capacity market. Five of these improvements

More information

Stakeholder Process: Commitment Cost Bidding Improvements. Summary of Submitted Comments

Stakeholder Process: Commitment Cost Bidding Improvements. Summary of Submitted Comments Stakeholder Process: Commitment Cost Bidding Improvements Attachment A Summary of Submitted Comments Two stakeholder initiatives are consolidated into one memo as both propose market improvements to ISO

More information

Commitment Cost and Default Energy Bid Enhancements

Commitment Cost and Default Energy Bid Enhancements Commitment Cost and Default Energy Bid Enhancements (CCDEBE) Second Revised Draft Final Proposal March 2, 2018 Table of Contents 1. Executive Summary... 5 2. Summary of changes... 5 3. Stakeholder comments...

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

Local Market Power Mitigation Enhancements

Local Market Power Mitigation Enhancements Local Market Power Mitigation Enhancements Draft Final Proposal May 6, 2011 CAISO/M&ID/CRH May 6, 2011 page 1 Draft Final Proposal Local Market Power Mitigation Enhancements Table of Contents 1. Introduction...

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 31. Day-Ahead Market... 2 31.1 Bid Submission and Validation in the Day-Ahead Market... 2 31.2 Day-Ahead MPM Process... 2 31.2.1 The Market Power Mitigation Process... 3 31.2.2 Bid Mitigation

More information

Market Disruption Report October 16, 2018 to November 15, 2018

Market Disruption Report October 16, 2018 to November 15, 2018 Market Disruption Report October 16, 2018 to November 15, 2018 December 17, 2018 CAISO Market Quality and Renewable Integration California CAISO 250 Outcropping Way Folsom, California 95630 (916) 351-4400

More information

Parameter Tuning for Uneconomic Adjustments. Lorenzo Kristov, Principal Market Architect

Parameter Tuning for Uneconomic Adjustments. Lorenzo Kristov, Principal Market Architect Parameter Tuning for Uneconomic Adjustments Lorenzo Kristov, Principal Market Architect Stakeholder Meeting May 13, 2008 Topics for Discussion Objectives of Current Parameter Tuning Effort Parameter Tuning

More information

Commitment Cost Enhancements Phase 3 Pre-Market Sim Training

Commitment Cost Enhancements Phase 3 Pre-Market Sim Training Commitment Cost Enhancements Phase 3 Pre-Market Sim Training Cynthia Hinman California ISO September 10, 2018 The information contained in these materials is provided for general information only and does

More information

Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area

Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area Regional Resource Adequacy Meeting December 16, 2015 Salt Lake City, Utah Keith Johnson Manager, Infrastructure Policy

More information

Commitment Costs and Default Energy Bid Enhancements Revised Draft Final Proposal

Commitment Costs and Default Energy Bid Enhancements Revised Draft Final Proposal Commitment Costs and Default Energy Bid Enhancements Revised Draft Final Proposal Cathleen Colbert, Sr. Policy Developer Brittany Dean, Policy Developer Bradford Cooper, Manager Market and Infrastructure

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: August 29, 2018 Re: Decision on the

More information

Market Disruption Report September 16, 2018 to October 15, 2018

Market Disruption Report September 16, 2018 to October 15, 2018 Market Disruption Report September 16, 2018 to October 15, 2018 November 15, 2018 CAISO Market Quality and Renewable Integration California ISO 250 Outcropping Way Folsom, California 95630 (916) 351-4400

More information

Pricing Logic Under Flexible Modeling of Constrained Output Generating Units

Pricing Logic Under Flexible Modeling of Constrained Output Generating Units Draft Final Proposal Pricing Logic Under Flexible Modeling of Constrained Output Generating Units April 14, 2008 This is the third CAISO paper on this issue. An Issue Paper was posted on February 1, 2008

More information

Pricing Behavior in the Balancing Market. Alan Isemonger Manager, Market Information

Pricing Behavior in the Balancing Market. Alan Isemonger Manager, Market Information Pricing Behavior in the Balancing Market Alan Isemonger Manager, Market Information Board of Governors General Session September 6th - 7th, 2007 Report History Technical root cause type of report Focuses

More information

Potential Effectiveness of the Demand Curve Approach for Mitigation of Local Market Power in Capacity Markets

Potential Effectiveness of the Demand Curve Approach for Mitigation of Local Market Power in Capacity Markets I. Background Potential Effectiveness of the Demand Curve Approach for Mitigation of Local Market Power in Capacity Markets Department of Market Monitoring October 11, 2007 If California moves forward

More information

Reliability Coordinator Services Rate Design, Terms and Conditions Straw Proposal Comments of the Salt River Project

Reliability Coordinator Services Rate Design, Terms and Conditions Straw Proposal Comments of the Salt River Project Reliability Coordinator Services Rate Design, Terms and Conditions Straw Proposal Comments of the Salt River Project Company Contact Person Date Submitted Salt River Project (SRP) Steven Cobb, Director

More information

The DAM consists of the following functions performed in sequence: the MPM-RRD, IFM, and RUC.

The DAM consists of the following functions performed in sequence: the MPM-RRD, IFM, and RUC. FERC ELECTRIC TARIFF First Revised Sheet No. 589 FOURTH REPLACEMENT VOLUME NO. I Superseding Original Sheet No. 589 31 Day-Ahead Market. The DAM consists of the following functions performed in sequence:

More information

2.1.1 Market Power Mitigation & Reliability Requirements Determination Market Power Mitigation & Reliability Requirements Determination

2.1.1 Market Power Mitigation & Reliability Requirements Determination Market Power Mitigation & Reliability Requirements Determination 2.1.1 Market Power Mitigation & Reliability Requirements Determination The Market Power Mitigation and Reliability Requirements Determination (MPM-RRD) function consists of two processes. The MPM is to

More information

Business Practice Manual for Compliance Monitoring

Business Practice Manual for Compliance Monitoring Style Definition: TOC 3: Left Business Practice Manual for Compliance Monitoring Version 45 Last Revised: August 4, 2010April 19, 2013 Approval Date: August 10, 2010 Effective Date: August 10, 2010July

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Offer Caps in Markets Operated by ) Docket No. RM16-5-000 Regional Transmission Organizations ) and Independent System Operators

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Udi Helman, Principal Market Economist Anjali Sheffrin, Chief Economist / Director, Market and Product Development

More information

Business Practice Manual for Distributed Generation Deliverability. Version

Business Practice Manual for Distributed Generation Deliverability. Version Business Practice Manual for Distributed Generation Deliverability Version 0.12.0 Revision Date: June 6, 20141, 2015 Approval History Approval Date: June 6, 2014 Effective Date: June 6, 2014 BPM Owner:

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Submitted by Company Date Submitted. Pacific Gas and Electric Company

Submitted by Company Date Submitted. Pacific Gas and Electric Company Comments of Pacific Gas and Electric Company on Commitment Costs and Default Energy Bid Enhancements Revised Straw Proposal and 8/11 Stakeholder Meeting Submitted by Company Date Submitted Cristy Sanada

More information

Black Start and System Restoration Phase 2. Draft Straw Proposal

Black Start and System Restoration Phase 2. Draft Straw Proposal Black Start and System Restoration Phase 2 Draft Straw Proposal February 14, 2017 Table of Contents 1 Introduction and Background... 3 2 Stakeholder process... 3 3 FERC Cost Allocation Principles... 4

More information

Commitment Cost Default Energy Bids Enhancements (CCDEBE) Business Rules

Commitment Cost Default Energy Bids Enhancements (CCDEBE) Business Rules CAISO proposes to allow market-based offers for each component of the supply offer subject to mitigation and to allow greater flexibility to negotiate or adjust each component. The purpose of this section

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Duke Energy Trading and Marketing Co. ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Duke Energy Trading and Marketing Co. ) Docket No. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Duke Energy Trading and Marketing Co. ) Docket No. EL03-152-000 PETITION FOR REHEARING OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

DEVELOPMENTS IN WESTERN MARKETS: RENEWABLES AND EXPANSION OF ORGANIZED MARKETS IN THE WEST

DEVELOPMENTS IN WESTERN MARKETS: RENEWABLES AND EXPANSION OF ORGANIZED MARKETS IN THE WEST DEVELOPMENTS IN WESTERN MARKETS: RENEWABLES AND EXPANSION OF ORGANIZED MARKETS IN THE WEST Power Regulatory Webinar Series Deanna E. King Stephen J. Hug September 28, 2016 CURRENT DEVELOPMENTS IN WESTERN

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 34. Real-Time Market... 3 34.1 Inputs To The Real-Time Market... 3 34.1.1 Day-Ahead Market Results as Inputs to the Real-Time Market... 3 34.1.2 Market Model and System Information...

More information

Reliability Demand Response Product

Reliability Demand Response Product Reliability Demand Response Product CAISO Response to Stakeholder Comments on the RDRP Straw Proposal Prepared for The Reliability Demand Response Product Stakeholder Initiative September 1, 2010 Comments

More information

SUMMARY OF MRTU STAKEHOLDER PROCESS

SUMMARY OF MRTU STAKEHOLDER PROCESS SUMMARY OF MRTU STAKEHOLDER PROCESS Since January 2002, the CAISO has conducted an extensive stakeholder process to guide the Market Redesign & Technology Upgrade ( MRTU ) effort. 1 In fact, from January

More information

161 FERC 61,088 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

161 FERC 61,088 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 161 FERC 61,088 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur, and Robert F. Powelson. California Independent System Operator

More information

Stepped Constraint Parameters. Issue Paper

Stepped Constraint Parameters. Issue Paper Stepped Constraint Parameters May 5, 2016 Table of Contents 1. Introduction... 3 2. Plan for Stakeholder Engagement... 4 3. Transmission constraint relaxation parameter... 5 4. Shift factor effectiveness

More information

UCA Position on the 12 Coincident Peak Transmission Cost Allocation Issues

UCA Position on the 12 Coincident Peak Transmission Cost Allocation Issues March 29, 2018 Introduction UCA Position on the 12 Coincident Peak Transmission Cost Allocation Issues 1. The UCA was an active participant in the facilitated stakeholder consultation session hosted by

More information

August 18, Energy Imbalance Market (EIM) Entity Readiness Criteria

August 18, Energy Imbalance Market (EIM) Entity Readiness Criteria Energy Imbalance Market (EIM) Entity Criteria August 18, 2015 Energy Imbalance Market (EIM) Entity Criteria Table of Contents 1 Introduction... 3 2 Criteria Categories... 4 2.1 Metrics, Criteria, and Thresholds...

More information

STATE OF NEW YORK PUBLIC SERVICE COMMISSION. In the Matter of Offshore Wind Energy. In the Matter of the Value of Distributed Energy Resources

STATE OF NEW YORK PUBLIC SERVICE COMMISSION. In the Matter of Offshore Wind Energy. In the Matter of the Value of Distributed Energy Resources STATE OF NEW YORK PUBLIC SERVICE COMMISSION In the Matter of Offshore Wind Energy In the Matter of the Value of Distributed Energy Resources Proceeding on Motion of the Commission to Implement a Large-Scale

More information

Commitment Costs and Default Energy Bid Enhancements. Issue Paper

Commitment Costs and Default Energy Bid Enhancements. Issue Paper Commitment Costs and Default Energy Bid Enhancements November 18, 2016 Table of Contents 1 Executive Summary... 4 2 Introduction... 6 3 Background... 8 3.1 Gas-Electric Markets... 8 3.1.1 Next Day Gas

More information

Local Market Power Mitigation Options Under Convergence Bidding

Local Market Power Mitigation Options Under Convergence Bidding California Independent System Operator Corporation I. Background Local Market Power Mitigation Options Under Convergence Bidding Department of Market Monitoring October 2, 2009 The introduction of convergence

More information

Beacon Power, LLC PJM RMISTF Package Proposal. December 5, 2016

Beacon Power, LLC PJM RMISTF Package Proposal. December 5, 2016 Beacon Power, LLC PJM RMISTF Package Proposal December 5, 2016 Beacon Power, LLC www.beaconpower.com Main Points PJM s Regulation Market Design was developed in response to FERC Order 755 Fair compensation

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Metcalf Energy Center LLC ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Metcalf Energy Center LLC ) Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Metcalf Energy Center LLC ) Docket No. ER18-240-000 MOTION FOR LEAVE TO ANSWER AND ANSWER OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

December 17, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

December 17, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation December 17, 2018 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

Business Practice Manual for Reliability Requirements. Version 34

Business Practice Manual for Reliability Requirements. Version 34 Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM

More information

Attachment H. Transition Costs for Multi-Stage Generator Resources

Attachment H. Transition Costs for Multi-Stage Generator Resources Attachment H Transition Costs for Multi-Stage Generator Resources H Transition Costs for Multi-Stage Generator Resources Transition Ccosts are a type of Sstart-Uup Ccost specific to multi-stage generators.

More information

3.2 Market Buyers Spot Market Energy Charges.

3.2 Market Buyers Spot Market Energy Charges. 3.2 Market Buyers. 3.2.1 Spot Market Energy Charges. (a) The Office of the Interconnection shall calculate System Energy Prices in the form of Day-ahead System Energy Prices and Real-time System Energy

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Electric Storage Participation in ) Markets Operated by Regional ) Docket Nos. RM16-23; AD16-20 Transmission Organizations and )

More information

3.2 Market Settlements.

3.2 Market Settlements. 3.2 Market Settlements. If a dollar-per-mw-hour value is applied in a calculation under this section 3.2 where the interval of the value produced in that calculation is less than an hour, then for purposes

More information

6.1.9 IFM Initial Conditions

6.1.9 IFM Initial Conditions 6.1.9 IFM Initial Conditions A Generating Unit that was committed in the previous day s Day-Ahead Market (IFM or RUC) run (TD-2 for TD-1) but was de-committed before HE24 would normally be considered initially

More information

Black Start and System Restoration Phase 2. Issue Paper

Black Start and System Restoration Phase 2. Issue Paper Black Start and System Restoration Phase 2 Issue Paper January 17, 2016 California ISO Straw Proposal Table of Contents 1 Introduction and Background... 3 2 Additional Procurement and Cost Allocation...

More information

Comments of Pacific Gas & Electric Company

Comments of Pacific Gas & Electric Company Comments of Pacific Gas & Electric Company Temporary Suspension of Resource Operations Straw Proposal Submitted by Company Date Submitted Jomo Thorne (415) 973-3144 Pacific Gas & Electric July 13, 2017

More information

NEW YORK INDEPENDENT SYSTEM OPERATOR

NEW YORK INDEPENDENT SYSTEM OPERATOR Rate Schedule 1 Study Status Update Review of Other ISO/RTO s March 2011 TABLE OF CONTENTS 1.0 RATE STRUCTURES AT OTHER ISO S/RTO S...1 1.1 PJM...1 1.2 ISO-New England...3 1.3 California ISO...6 1.4 Midwest

More information

2. Market Operations Overview

2. Market Operations Overview 2. Market Operations Overview 2.5 Market Information This section summarizes and describes the common information that is used by the Day-Ahead and Real-Time processes. 2.5.1 Resource Static Data Static

More information

The Role Of The Independent Market Monitor

The Role Of The Independent Market Monitor The Role Of The Independent Market Monitor Presented to: Wisconsin Public Utility Institute Energy Utility Basics Michael W. Chiasson, P.E. MISO IMM April 13, 2018 Objectives The Role of the Market Monitor

More information

Reliability Demand Response Product Draft Final Proposal Version 1.0

Reliability Demand Response Product Draft Final Proposal Version 1.0 Reliability Demand Response Product Draft Final Proposal Version 1.0 Prepared for The Reliability Demand Response Product Stakeholder Initiative September 1, 2010 Version 1.0 Date 08/02/10 to 09/01/10

More information

The Proposed Energy Storage Procurement Provides Ratepayer Benefits

The Proposed Energy Storage Procurement Provides Ratepayer Benefits procurement that will displace the need for costly contracts with fossil-fueled resources. More broadly, in using the RMR contracts as an opportunity to pivot from continued reliance on fossil fuels, Resolution

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket Nos. ER12-1630 Operator Corporation ) ER14-971 Informational Report of the California Independent System

More information

Reliability Coordinator Services. Rate Design, Terms and Conditions Straw Proposal COMMENTS TEMPLATE

Reliability Coordinator Services. Rate Design, Terms and Conditions Straw Proposal COMMENTS TEMPLATE Reliability Coordinator Services Rate Design, Terms and Conditions Straw Proposal COMMENTS TEMPLATE Company Contact Person Date Submitted Balancing Authority of Northern California and the Sacramento Municipal

More information

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Stakeholder Comments Template Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Submitted by Company Date Submitted Kevin T. Fox Keyes & Fox, LLP 436 14 th

More information

SCHEDULE 6A Black Start Service

SCHEDULE 6A Black Start Service SCHEDULE 6A Black Start Service References to section numbers in this Schedule 6A refer to sections of this Schedule 6A, unless otherwise specified. To ensure the reliable restoration following a shut

More information

Variable Operations and Maintenance (VOM) Costs: Educational Document

Variable Operations and Maintenance (VOM) Costs: Educational Document Variable Operation & Maintenance Costs - Where we are today Manual 15 does not specifically define Variable Operation & Maintenance (VOM) Costs, nor do any other PJM manuals. In a Review of Generator Compensation

More information

PG&E s General Comments on Demand Response Vision Update. January 11, 2008

PG&E s General Comments on Demand Response Vision Update. January 11, 2008 PG&E s General Comments on Demand Response Vision Update January 11, 2008 This document provides PG&E s comments on the draft California Demand Response: A Vision of the Future. The comments are divided

More information

EIM Resource Sufficiency Evaluation

EIM Resource Sufficiency Evaluation EIM Resource Sufficiency Evaluation Megan Poage & Don Tretheway Market Design Policy Stakeholder Call September 26, 2018 ISO proposes resource sufficiency evaluation improvements in response to stakeholder

More information

Stakeholder Comments Template. Day-Ahead Market Enhancements Phase 1 Initiative

Stakeholder Comments Template. Day-Ahead Market Enhancements Phase 1 Initiative Stakeholder Comments Template Day-Ahead Market Enhancements Phase 1 Initiative This template has been created for submission of stakeholder comments on the third revised straw proposal that was published

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 34. Real-Time Market... 2 34.1 Inputs To The Real-Time Market... 3 34.2 Real-Time Unit Commitment... 3 34.2.1 Commitment Of Fast Start And Short Start Units... 4 34.2.2 Real-Time Ancillary

More information

TESTIMONY OF BRAD BOUILLON ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

TESTIMONY OF BRAD BOUILLON ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Application No.: -0-00 Exhibit No.: Witness: Brad Bouillon Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) for Authority to Revise their Curtailment

More information

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1 No. 4120 Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1 Background... 3 2.2 Scope/ Applicability... 4 3. PROCEDURE DETAIL... 4 3.1 General Information... 4 3.2

More information

BPM Change Management Meeting

BPM Change Management Meeting BPM Change Management Meeting September 26, 2017 Julia Payton BPM Change Management Process BPM_CM@caiso.com Agenda BPM Change Management Meeting, September 26, 2017 Topic Introduction/meeting overview

More information